KR20220053812A - Pillar construction method based on segment plug-in and pillar structure constructed by the same - Google Patents

Pillar construction method based on segment plug-in and pillar structure constructed by the same Download PDF

Info

Publication number
KR20220053812A
KR20220053812A KR1020200137990A KR20200137990A KR20220053812A KR 20220053812 A KR20220053812 A KR 20220053812A KR 1020200137990 A KR1020200137990 A KR 1020200137990A KR 20200137990 A KR20200137990 A KR 20200137990A KR 20220053812 A KR20220053812 A KR 20220053812A
Authority
KR
South Korea
Prior art keywords
column
segment
reinforcing bar
segments
block
Prior art date
Application number
KR1020200137990A
Other languages
Korean (ko)
Other versions
KR102418610B1 (en
Inventor
정길제
이장석
김종현
이성형
Original Assignee
현대건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대건설주식회사 filed Critical 현대건설주식회사
Priority to KR1020200137990A priority Critical patent/KR102418610B1/en
Publication of KR20220053812A publication Critical patent/KR20220053812A/en
Application granted granted Critical
Publication of KR102418610B1 publication Critical patent/KR102418610B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Disclosed are a segment plugin-type pillar construction method and a pillar structure constructed thereby. In accordance with one embodiment of the present invention, the segment plugin-type pillar construction method includes the following steps of: (a) manufacturing a match cast block; (b) manufacturing a plurality of pillar segments by using the match cast block as a lower mold; (c) constructing the foundation part of a pillar by using the match cast block as a foundation in a construction site; (d) placing one of the plurality of pillar segments on an upper side of the match cast block; and (e) sequentially stacking the rest of the pillar segments on an upper side of the one pillar segment. Therefore, the present invention is capable of improving constructability for connection between the pillar segments and the foundation part.

Description

세그먼트 플러그인 방식의 기둥 시공 방법 및 이에 의해 시공되는 기둥 구조물{PILLAR CONSTRUCTION METHOD BASED ON SEGMENT PLUG-IN AND PILLAR STRUCTURE CONSTRUCTED BY THE SAME}Column construction method of segment plug-in method and column structure constructed thereby

본원은 세그먼트 플러그인 방식의 기둥 시공 방법 및 이에 의해 시공되는 기둥 구조물에 관한 것이다. 예를 들면, 본원은 세그먼트 플러그인 방식의 복합 연속화 조립식 교각 시공 방법에 관한 것이다.The present application relates to a method for constructing a column of a segment plug-in method and a column structure constructed by the method. For example, the present application relates to a method for constructing a complex continuous prefabricated pier using a segment plug-in method.

일반적으로 교량공사에서 시공되고 있는 교각은 현장타설 콘크리트 구조로, 현장에서 기초 터파기 작업이후, 기초 철근 및 거푸집을 배치한 상태에서 콘크리트를 타설한 뒤 일정 기간 동안 양생기간을 갖도록 하여 기초부를 형성한다. 이 때문에 현장타설 공법은 인력에 의존한 단순 반복작업으로 인해 생산성이 낮은 문제가 있다. 또한 교각은 시공되는 위치에 따라서 시공이 이루어지는 주변에 교통 혼잡을 주며, 배수처리 능력을 요하는 수중공사 등과 같이 작업환경이 열악한 상황에서는 시공관리가 어렵고 부실시공의 우려가 상존한다.In general, the piers being constructed in bridge construction are cast-in-place concrete structures. After excavating the foundation at the site, concrete is poured with the foundation reinforcement and formwork placed, and then the curing period is allowed for a certain period to form the foundation. . For this reason, the cast-in-place method has a problem of low productivity due to simple repetitive work that relies on manpower. In addition, depending on the location where the piers are constructed, traffic congestion is provided around the construction site, and under poor working conditions such as underwater construction that requires drainage treatment capacity, construction management is difficult and there is a constant risk of poor construction.

이를 위해 현장에서 기초부 시공을 수행한 이후에 제작된 단위 구조물을 조립하는 방식으로 교각을 시공하는 조립식 교각 시공 기법이 도입되었고, 이러한 조립식 교각 시공 방식은 교각을 이루는 단위 구조물 별로 프리캐스트 타입으로 제작되는 구조물(유닛)이 현장이 아닌 공장 등에서 사전 제작될 수 있으므로 콘크리트의 품질관리가 유리하고, 프리캐스트 유닛을 연속적으로 제작하므로 인력관리 및 거푸집 전용에 유리하며, 프리캐스트 유닛의 제작을 기초부 공사와 병행해서 실시할 수 있으므로 현장타설 방식에 비해서 공기를 단축시킬 수 있다는 이점을 가진다. 또한, 이러한 조립식 교각 공법에 의할 때 품질 향상, 교통 영향 최소화 등의 효과 역시 기대할 수 있다.To this end, the prefabricated pier construction technique was introduced in which the piers were constructed by assembling the unit structures manufactured after performing the foundation construction on site. Concrete quality control is advantageous because the structure (unit) to be used can be pre-fabricated in a factory, not on site, and it is advantageous for manpower management and exclusive use of formwork because precast units are continuously produced. Since it can be carried out in parallel with the cast-in-place method, it has the advantage of shortening the construction period compared to the cast-in-place method. In addition, when using this prefabricated pier construction method, effects such as quality improvement and traffic impact minimization can also be expected.

한편, 조립식 교각의 교각 세그먼트 간 연결부의 시공은 철근, 강연선 등의 인장 부재의 연결 방법에 따라 시공성이 결정되며, 이와 관련한 다양한 시공 방법이 개발 및 제안되었으나, 시공성의 개선이 여전히 요구된다.On the other hand, the construction of the connection between the pier segments of the prefabricated pier is determined by the connection method of tension members such as reinforcing bars and strands.

본원의 배경이 되는 기술은 한국등록특허공보 제10-1980656호에 개시되어 있다.The technology that is the background of the present application is disclosed in Korean Patent Publication No. 10-1980656.

본원은 전술한 종래 기술의 문제점을 해결하기 위한 것으로서, 철근 연결 작업을 간소화하고, 강연선 등의 긴장재를 통한 포스트 텐션을 통해 구조 성능을 최대화할 수 있는 세그먼트 플러그인 방식의 기둥 시공 방법 및 이에 의해 시공되는 기둥 구조물을 제공하려는 것을 목적으로 한다.The present application is to solve the problems of the prior art described above, and a method for constructing a column of a segment plug-in method that simplifies the rebar connection work and maximizes the structural performance through post tension through tension materials such as stranded wires, and It aims to provide a column structure.

본원은 세그먼트 적층과 동시에 주철근을 연속화하여 시공성을 향상할 수 있는 세그먼트 플러그인 방식의 기둥 시공 방법 및 이에 의해 시공되는 기둥 구조물을 제공하려는 것을 목적으로 한다.An object of the present application is to provide a method for constructing a column of a segment plug-in method capable of improving workability by sequencing main reinforcing bars at the same time as segment lamination, and a column structure constructed thereby.

다만, 본원의 실시예가 이루고자 하는 기술적 과제는 상기된 바와 같은 기술적 과제들로 한정되지 않으며, 또 다른 기술적 과제들이 존재할 수 있다.However, the technical problems to be achieved by the embodiments of the present application are not limited to the technical problems described above, and other technical problems may exist.

상기한 기술적 과제를 달성하기 위한 기술적 수단으로서, 본원의 일 실시예에 따른 세그먼트 플러그인 방식의 기둥 시공 방법은, (a) 매치 캐스트 블록을 제작하는 단계, (b) 상기 매치 캐스트 블록을 하측 거푸집으로 하여 복수 개의 기둥 세그먼트를 제작하는 단계, (c) 시공 현장에서 상기 매치 캐스트 블록을 기초로 기둥의 기초부를 시공하는 단계, (d) 상기 매치 캐스트 블록의 상면에 상기 복수 개의 기둥 세그먼트 중 어느 하나의 기둥 세그먼트를 배치하는 단계 및 (e) 상기 어느 하나의 기둥 세그먼트의 상측에 나머지 기둥 세그먼트를 순차적으로 적층하는 단계를 포함할 수 있다.As a technical means for achieving the above technical problem, the segment plug-in type column construction method according to an embodiment of the present application includes the steps of (a) manufacturing a match cast block, (b) using the match cast block as a lower formwork to manufacture a plurality of column segments, (c) constructing a column base on the basis of the match cast block at a construction site, (d) on the upper surface of the match cast block, any one of the plurality of column segments Disposing the column segments and (e) may include sequentially stacking the remaining column segments on top of any one of the column segments.

또한, 상기 매치 캐스트 블록의 상면에는 상기 기둥 세그먼트의 철근 돌출부가 삽입되는 상부 연결부가 함몰 형성될 수 있다.In addition, an upper connection part into which the reinforcing bar protrusion of the column segment is inserted may be recessed in the upper surface of the match cast block.

또한, 상기 기둥 세그먼트에는 상면에 상측에 배치되는 기둥 세그먼트의 상기 철근 돌출부가 삽입되는 철근 연결부가 함몰 형성될 수 있다.In addition, a reinforcing bar connection portion into which the reinforcing bar protrusion of the column segment disposed on the upper side of the column segment is inserted may be recessed in the column segment.

또한, 상기 기둥 세그먼트에는 하단이 상기 기둥 세그먼트의 하면으로부터 일부 하향 돌출되어 상기 철근 돌출부를 형성하는 주철근이 매립될 수 있다.In addition, the lower end of the column segment protrudes downward from the lower surface of the column segment, the main reinforcing bar forming the reinforcing bar protrusion may be embedded.

또한, 상기 (d) 단계는, 하측에 위치한 상기 매치 캐스트 블록의 상기 상부 연결부에 대하여 상측에 위치한 상기 어느 하나의 기둥 세그먼트의 상기 철근 돌출부를 적어도 일부 삽입하는 형태로 상기 어느 하나의 기둥 세그먼트를 배치할 수 있다.In addition, in the step (d), the one column segment is arranged in a form of inserting at least a part of the reinforcing bar protrusion of the one column segment located on the upper side with respect to the upper connection part of the match cast block located on the lower side can do.

또한, 상기 (e) 단계는, 적층되는 기둥 세그먼트의 상기 철근 돌출부를 하측에 배치된 기둥 세그먼트의 상기 철근 연결부에 삽입하는 방식으로 상기 나머지 기둥 세그먼트를 순차적으로 적층할 수 있다.In addition, in the step (e), the remaining column segments may be sequentially stacked in such a way that the reinforcing bar protrusions of the column segments to be stacked are inserted into the reinforcing bar connection parts of the column segments disposed on the lower side.

또한, 상기 매치 캐스트 블록에는 상하 방향으로 관통 연장되는 블록 측 덕트가 매립될 수 있다.In addition, a block-side duct extending vertically through the match cast block may be embedded.

또한, 상기 기둥 세그먼트에는 상기 블록 측 덕트에 대응되게 상하 방향으로 관통 연장되는 세그먼트 측 덕트가 매립될 수 있다.In addition, a segment-side duct extending through the vertical direction to correspond to the block-side duct may be embedded in the pillar segment.

또한, 본원의 일 실시예에 따른 세그먼트 플러그인 방식의 기둥 시공 방법은, (f) 적층된 상기 복수 개의 기둥 세그먼트 각각의 상기 세그먼트 측 덕트 및 상기 블록 측 덕트를 관통하도록 긴장재를 삽입하고 포스트 텐션을 수행하는 단계를 포함할 수 있다.In addition, in the column construction method of the segment plug-in method according to an embodiment of the present application, (f) inserting a tension member so as to penetrate the segment-side duct and the block-side duct of each of the plurality of column segments stacked and performing post tension may include the step of

또한, 상기 (a) 단계에서, 상기 매치 캐스트 블록은 하부 연결부를 더 포함하도록 제작될 수 있다.In addition, in step (a), the match cast block may be manufactured to further include a lower connection part.

또한, 상기 (c) 단계는, 상기 기초부의 시공을 위한 기초 철근을 상기 하부 연결부에 삽입하여, 상기 기초부의 내부에 상기 매치 캐스트 블록이 매립되도록 할 수 있다.In addition, in the step (c), a foundation reinforcing bar for construction of the foundation may be inserted into the lower connection portion, so that the match cast block is embedded in the interior of the foundation.

또한, 상기 (c) 단계는, (c1) 시공되는 상기 기초부에 대응하여 앵커 프레임을 배치하는 단계, (c2) 상기 앵커 프레임 상에 상기 매치 캐스트 블록을 배치하는 단계, (c3) 상기 기초 철근을 상기 하부 연결부에 삽입하여 배근하는 단계 및 (c4) 상기 기초 철근 및 상기 매치 캐스트 블록을 포위하도록 배치되는 기초부 거푸집에 기초하여 콘크리트를 타설 및 양생하는 단계를 포함할 수 있다.In addition, the step (c) includes: (c1) disposing an anchor frame corresponding to the foundation to be constructed, (c2) disposing the match cast block on the anchor frame, (c3) the foundation reinforcement and (c4) pouring and curing concrete based on the foundation formwork disposed to surround the foundation reinforcement and the match cast block.

또한, 상기 (b) 단계는, 상기 기둥 세그먼트에 매립되는 주철근이 상하 방향에 대하여 어느 일측으로 기울어지는 것이 방지되도록 상기 주철근의 상측 또는 상기 철근 연결부를 감싸 수평 방향으로 이동되지 않도록 고정하는 홀이 형성된 지그 구조체를 배치하는 단계를 포함할 수 있다.In addition, in the step (b), the upper side of the main reinforcing bar or the reinforcing bar connection part is wrapped around the main reinforcing bar or the reinforcing bar connection portion so that the main reinforcing bar embedded in the column segment is prevented from inclining to either side in the vertical direction. It may include the step of disposing the jig structure.

또한, 상기 지그 구조체는, 상측 지그 및 상기 상측 지그로부터 하측으로 간격을 두고 배치되는 하측 지그를 포함할 수 있다.In addition, the jig structure may include an upper jig and a lower jig disposed at an interval downward from the upper jig.

또한, 상기 매치 캐스트 블록은, 상하 방향에 직교하는 면 방향을 기준으로 방사형으로 배치되는 복수 개의 상부 연결부 및 복수 개의 블록 측 덕트를 포함할 수 있다.In addition, the match cast block may include a plurality of upper connection parts and a plurality of block-side ducts that are radially disposed with respect to a plane direction perpendicular to the vertical direction.

또한, 상기 기둥 세그먼트에는, 상기 복수 개의 상부 연결부에 대응하는 복수 개의 주철근 및 상기 복수 개의 블록 측 덕트에 대응하는 복수 개의 세그먼트 측 덕트가 각각 매립될 수 있다.In addition, a plurality of main reinforcing bars corresponding to the plurality of upper connection parts and a plurality of segment-side ducts corresponding to the plurality of block-side ducts may be respectively embedded in the column segments.

한편, 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물은, 기둥 세그먼트의 철근 돌출부가 삽입되는 상부 연결부 및 상하 방향으로 관통 연장되는 블록 측 덕트를 포함하는 매치 캐스트 블록 및 하면으로부터 적어도 일부가 하향 돌출되어 상기 철근 돌출부를 형성하는 주철근 및 상기 블록 측 덕트에 대응되게 상하 방향으로 관통 연장되는 세그먼트 측 덕트가 매립되고, 상기 매치 캐스트 블록을 하측 거푸집으로 하여 제작되는 복수 개의 기둥 세그먼트를 포함할 수 있다.On the other hand, the column structure constructed based on the segment plug-in method according to an embodiment of the present application is a match cast block including an upper connection part into which the reinforcing bar protrusion of the column segment is inserted, and a block side duct extending through the vertical direction from the lower surface At least a portion of the main reinforcing bar protruding downward to form the reinforcing bar protrusion and a segment-side duct extending vertically corresponding to the block-side duct are embedded, and a plurality of column segments manufactured using the match cast block as the lower formwork may include

또한, 상기 기둥 구조물은, 시공 현장에서 상기 매치 캐스트 블록을 기초로 기둥의 기초부를 시공하고, 상기 복수 개의 기둥 세그먼트 중 어느 하나의 기둥 세그먼트의 상기 철근 돌출부가 상기 매치 캐스트 블록의 상기 상부 연결부에 삽입되어 상기 기초부의 상면에 배치되고, 상기 어느 하나의 기둥 세그먼트의 상면에 나머지 기둥 세그먼트를 순차적으로 적층하는 방식으로 시공될 수 있다.In addition, in the column structure, the base part of the column is constructed based on the match cast block at the construction site, and the reinforcing bar protrusion of any one column segment among the plurality of column segments is inserted into the upper connection portion of the match cast block to be disposed on the upper surface of the base, and may be constructed in such a way that the remaining column segments are sequentially stacked on the upper surface of any one of the column segments.

또한, 상기 기둥 세그먼트의 상면에는 상측에 배치되는 기둥 세그먼트의 상기 철근 돌출부가 삽입되는 철근 연결부가 함몰 형성될 수 있다.In addition, a reinforcing bar connection portion into which the reinforcing bar protrusion of the column segment disposed on the upper side is inserted may be recessed in the upper surface of the column segment.

또한, 상기 복수 개의 기둥 세그먼트는, 적층되는 기둥 세그먼트의 상기 철근 돌출부를 하측에 배치된 기둥 세그먼트의 상기 철근 연결부에 삽입하여 상기 나머지 기둥 세그먼트를 순차적으로 적층하는 방식으로 시공될 수 있다.In addition, the plurality of column segments may be constructed in such a way that the reinforcing bar protrusions of the column segments to be stacked are inserted into the reinforcing bar connection portions of the column segments disposed on the lower side, and the remaining column segments are sequentially stacked.

또한, 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물은, 적층된 상기 복수 개의 기둥 세그먼트 각각의 상기 세그먼트 측 덕트 및 상기 블록 측 덕트를 관통하도록 삽입된 후 포스트 텐션이 수행되는 긴장재를 포함할 수 있다.In addition, the column structure constructed based on the segment plug-in method according to an embodiment of the present application is inserted to penetrate the segment-side duct and the block-side duct of each of the plurality of stacked column segments, and then post tension is performed. Tension materials may be included.

상술한 과제 해결 수단은 단지 예시적인 것으로서, 본원을 제한하려는 의도로 해석되지 않아야 한다. 상술한 예시적인 실시예 외에도, 도면 및 발명의 상세한 설명에 추가적인 실시예가 존재할 수 있다.The above-described problem solving means are merely exemplary, and should not be construed as limiting the present application. In addition to the exemplary embodiments described above, additional embodiments may exist in the drawings and detailed description.

전술한 본원의 과제 해결 수단에 의하면, 철근 연결 작업을 간소화하고, 강연선 등의 긴장재를 통한 포스트 텐션을 통해 구조 성능을 최대화할 수 있는 세그먼트 플러그인 방식의 기둥 시공 방법 및 이에 의해 시공되는 기둥 구조물을 제공할 수 있다.According to the above-described problem solving means of the present application, it is possible to simplify the reinforcing bar connection work and maximize the structural performance through the post tension through the tension member such as a stranded wire. Provide a column construction method of a segment plug-in method and a column structure constructed thereby can do.

전술한 본원의 과제 해결 수단에 의하면, 세그먼트 적층과 동시에 주철근을 연속화하여 시공성을 향상할 수 있는 세그먼트 플러그인 방식의 기둥 시공 방법 및 이에 의해 시공되는 기둥 구조물을 제공할 수 있다.According to the above-described problem solving means of the present application, it is possible to provide a column construction method of a segment plug-in method capable of improving workability by sequencing the main reinforcing bars at the same time as segment lamination and a column structure constructed thereby.

전술한 본원의 과제 해결 수단에 의하면, 세그먼트 적층 시에 주철근과 덕트의 수평 및 수직 위치 정합성이 개선될 수 있다.According to the above-described problem solving means of the present application, the horizontal and vertical alignment of the main reinforcing bar and the duct can be improved when the segments are stacked.

전술한 본원의 과제 해결 수단에 의하면, 적층되는 기둥 세그먼트와 기초부 사이의 연결 시공성이 향상될 수 있다.According to the above-described problem solving means of the present application, the connection workability between the column segment and the base to be laminated can be improved.

다만, 본원에서 얻을 수 있는 효과는 상기된 바와 같은 효과들로 한정되지 않으며, 또 다른 효과들이 존재할 수 있다.However, the effects obtainable herein are not limited to the above-described effects, and other effects may exist.

도 1은 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물에 대한 정면도 및 측면도이다.
도 2는 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물의 매치 캐스트 블록의 세부 구성도이다.
도 3은 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물의 복수의 기둥 세그먼트 중 하측 세그먼트의 세부 구성도이다.
도 4는 복수의 기둥 세그먼트 중 하측 세그먼트의 단면도이다.
도 5는 기둥 세그먼트에 매립되는 주철근의 형상을 나타낸 도면이다.
도 6은 기둥 세그먼트의 제작 시 매치 캐스트 블록의 상부 연결부와 상부 연결부에 삽입되는 주철근의 철근 돌출부의 배치를 나타낸 도면이다.
도 7은 기둥 세그먼트의 제작 시 매치 캐스트 블록의 상부 연결부와 상부 연결부에 삽입되는 주철근의 철근 돌출부의 상호 간섭을 방지하기 위해 개재되는 관형 부재를 나타낸 도면이다.
도 8은 기둥 세그먼트의 제작 시 타설되는 콘크리트가 매치 캐스트 블록의 상부 연결부로 침입하지 않도록, 상부 연결부의 개구된 상측과 주철근 사이의 사이 공간을 실링하는 것을 설명하기 위한 도면이다.
도 9는 기둥 세그먼트의 제작 시 주철근이 기울어지는 것이 방지되도록 배치되는 지그 구조체를 설명하기 위한 도면이다.
도 10은 기둥 세그먼트의 제작 프로세스를 나타낸 개념도이다.
도 11은 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물의 복수의 기둥 세그먼트 중 상측 세그먼트의 세부 구성도이다.
도 12는 복수의 기둥 세그먼트 중 상측 세그먼트의 단면도이다.
도 13는 기초부에 배치되는 앵커 프레임을 나타낸 도면이다.
도 14는 본원의 일 실시예에 따른 세그먼트 플러그인 방식의 기둥 구조물 시공 방법에 대한 동작 흐름도이다.
1 is a front view and a side view of a column structure constructed based on a segment plug-in method according to an embodiment of the present application.
2 is a detailed configuration diagram of a match cast block of a column structure constructed based on a segment plug-in method according to an embodiment of the present application.
3 is a detailed configuration diagram of a lower segment of a plurality of column segments of a column structure constructed based on a segment plug-in method according to an embodiment of the present application.
4 is a cross-sectional view of a lower segment of a plurality of column segments.
5 is a view showing the shape of the main reinforcing bar embedded in the column segment.
6 is a view showing the arrangement of the upper connection part of the match cast block and the reinforcing bar protrusion of the main reinforcing bar inserted into the upper connection part when the column segment is manufactured.
7 is a view showing a tubular member interposed to prevent mutual interference between the upper connection part of the match cast block and the reinforcing bar protrusion of the main reinforcing bar inserted into the upper connection part when the column segment is manufactured.
8 is a view for explaining sealing the space between the open upper side of the upper connection part and the main reinforcing bar so that concrete poured during the production of the column segment does not penetrate into the upper connection part of the match cast block.
9 is a view for explaining a jig structure that is arranged to prevent the main reinforcing bar from inclining during the manufacture of the column segment.
10 is a conceptual diagram illustrating a manufacturing process of a column segment.
11 is a detailed configuration diagram of an upper segment of a plurality of column segments of a column structure constructed based on a segment plug-in method according to an embodiment of the present application.
12 is a cross-sectional view of an upper segment of a plurality of column segments.
13 is a view showing an anchor frame disposed on the base.
14 is an operation flowchart for a method for constructing a column structure of a segment plug-in method according to an embodiment of the present application.

아래에서는 첨부한 도면을 참조하여 본원이 속하는 기술 분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본원의 실시예를 상세히 설명한다. 그러나 본원은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본원을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.Hereinafter, embodiments of the present application will be described in detail with reference to the accompanying drawings so that those of ordinary skill in the art to which the present application pertains can easily carry out. However, the present application may be implemented in several different forms and is not limited to the embodiments described herein. And in order to clearly explain the present application in the drawings, parts irrelevant to the description are omitted, and similar reference numerals are attached to similar parts throughout the specification.

본원 명세서 전체에서, 어떤 부분이 다른 부분과 "연결"되어 있다고 할 때, 이는 "직접적으로 연결"되어 있는 경우뿐 아니라, 그 중간에 다른 소자를 사이에 두고 "전기적으로 연결" 또는 "간접적으로 연결"되어 있는 경우도 포함한다. Throughout this specification, when a part is "connected" with another part, it is not only "directly connected" but also "electrically connected" or "indirectly connected" with another element interposed therebetween. "Including cases where

본원 명세서 전체에서, 어떤 부재가 다른 부재 "상에", "상부에", "상단에", "하에", "하부에", "하단에" 위치하고 있다고 할 때, 이는 어떤 부재가 다른 부재에 접해 있는 경우뿐 아니라 두 부재 사이에 또 다른 부재가 존재하는 경우도 포함한다.Throughout this specification, when a member is positioned “on”, “on”, “on”, “on”, “under”, “under”, or “under” another member, this means that a member is positioned on the other member. It includes not only the case where they are in contact, but also the case where another member exists between two members.

본원 명세서 전체에서, 어떤 부분이 어떤 구성 요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성 요소를 제외하는 것이 아니라 다른 구성 요소를 더 포함할 수 있는 것을 의미한다.Throughout this specification, when a part "includes" a certain component, it means that other components may be further included, rather than excluding other components, unless otherwise stated.

참고로, 본원의 실시예에 관한 설명 중 방향이나 위치에 관련된 용어(상하 방향, 상면, 상측, 하향, 하방, 하단 등)는 도면에 나타나 있는 각 구성의 배치 상태를 기준으로 설명한 것이다. 예를 들면, 도1에서 보았을 때 상하 방향은 12시에서 6시방향일 수 있다. 또한, 도 4 및 도 12에서 보았을 때 상하 방향은 도면의 법선 방향일 수 있다.For reference, in the description of the embodiments of the present application, terms related to directions or positions (up and down direction, upper surface, upper, downward, lower, lower, etc.) are described based on the arrangement state of each component shown in the drawings. For example, when viewed in FIG. 1 , the vertical direction may be 12 o'clock to 6 o'clock. In addition, when viewed in FIGS. 4 and 12 , the vertical direction may be a normal line direction of the drawing.

다만, 이러한 방향 설정은 본원 구조물의 배치 상태에 따라 달라질 수 있다. 예를 들면, 필요에 따라서는 도 1 기준 상향이 수평 방향(좌우 방향)을 향하도록 본원 구조물이 배치될 수 있고, 다른 예로 도 1 기준 상향이 비스듬한 경사 방향을 향하도록 본원 구조물이 배치될 수 있다.However, this direction setting may vary depending on the arrangement state of the present structure. For example, if necessary, the structure of the present application may be arranged so that the upward direction in FIG. 1 faces a horizontal direction (left and right direction), and as another example, the present structure may be arranged so that the upward direction in FIG. 1 faces an oblique inclination direction. .

본원은 세그먼트 플러그인 방식의 기둥 시공 방법 및 이에 의해 시공되는 기둥 구조물에 관한 것이다. 예를 들면, 본원은 세그먼트 플러그인 방식의 복합 연속화 조립식 교각 시공 기법에 관한 것이다.The present application relates to a method for constructing a column of a segment plug-in method and a column structure constructed by the method. For example, the present application relates to a complex continuous prefabricated pier construction technique of a segment plug-in method.

도 1은 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물에 대한 정면도 및 측면도이다. 구체적으로, 도 1의 (a)는 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물(10)(이하, '기둥 구조물(10)'이라 한다.)의 정면도이고, 도 1의 (b)는 기둥 구조물(10)의 측면도를 나타낸 것이다.1 is a front view and a side view of a column structure constructed based on a segment plug-in method according to an embodiment of the present application. Specifically, Fig. 1 (a) is a front view of the pillar structure 10 (hereinafter referred to as 'pillar structure 10') constructed based on the segment plug-in method according to an embodiment of the present application, and Fig. 1 (b) shows a side view of the column structure 10 .

도 1을 참조하면, 기둥 구조물(10)은 매치 캐스트 블록(100), 복수 개의 기둥 세그먼트(200)를 포함할 수 있다. 또한, 도 1을 참조하면, 기둥 구조물(10)은 매치 캐스트 블록(100)을 기초로 하여 시공되는 기초부(150)의 상측에 복수 개의 기둥 세그먼트(200)를 적층하는 방식으로 시공되는 것일 수 있다.Referring to FIG. 1 , the pillar structure 10 may include a match cast block 100 and a plurality of pillar segments 200 . In addition, referring to FIG. 1 , the column structure 10 may be constructed in such a way that a plurality of column segments 200 are stacked on the upper side of the foundation 150 constructed based on the match cast block 100 . there is.

또한, 도 1을 참조하면, 복수 개의 기둥 세그먼트(200)는 하측 세그먼트(200a) 및 상측 세그먼트(200b)를 포함할 수 있다. 구체적으로, 상측 세그먼트(200b)는 기둥 구조물(10)에 포함된 복수 개의 기둥 세그먼트(200) 중 최상단에 적층되는 세그먼트를 의미하고, 하측 세그먼트(200a)는 기초부(150)와 상측 세그먼트(200b) 사이에 배치(적층)되는 적어도 하나의 기둥 세그먼트(200)를 의미할 수 있다. 달리 말해, 본원에서 개시하는 기둥 구조물(10)은 매치 캐스트 블록(100)을 포함하도록 시공된 기초부(150)의 상측에 적어도 하나의 하측 세그먼트(200a)를 순차적으로 적층하고, 최상단에 상측 세그먼트(200b)를 적층하는 방식으로 시공될 수 있다.Also, referring to FIG. 1 , the plurality of pillar segments 200 may include a lower segment 200a and an upper segment 200b. Specifically, the upper segment 200b refers to a segment stacked on the top of the plurality of column segments 200 included in the column structure 10 , and the lower segment 200a includes the base 150 and the upper segment 200b. ) may mean at least one column segment 200 disposed between (stacked). In other words, the column structure 10 disclosed herein sequentially stacks at least one lower segment 200a on the upper side of the foundation 150 constructed to include the match cast block 100 , and the upper segment on the uppermost end (200b) can be constructed in a stacking manner.

한편, 본원에서 개시하는 '기둥 구조물(10)'은 교량의 교각(pier) 기둥 등 토목 구조물의 기둥을 의미하는 것일 수 있으나, 이에만 한정되는 것은 아니고, 본원의 구현예에 따라 건축물에서의 공간 형성을 위한 기둥 구조물 등과 같이 기둥으로 정의될 수 있는 다양한 구조물들을 포괄하는 넓은 개념으로 이해될 수 있다.On the other hand, the 'pillar structure 10' disclosed herein may mean a column of a civil structure such as a pier of a bridge, but is not limited thereto, and a space in a building according to the embodiment of the present application It can be understood as a broad concept encompassing various structures that can be defined as columns, such as column structures for formation.

도 2는 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물의 매치 캐스트 블록의 세부 구성도이다.2 is a detailed configuration diagram of a match cast block of a column structure constructed based on a segment plug-in method according to an embodiment of the present application.

도 2를 참조하면, 기둥 구조물(10)에 포함되는 기둥 세그먼트(200)를 프리캐스트를 통해 제작하는데 사용되고, 시공 현장에서는 기둥 구조물(10)의 기초부(150) 시공을 위해 매립되는 매치 캐스트 블록(100)은 상부 연결부(110), 블록 측 덕트(120) 및 하측 연결부(130)를 포함하도록 제작될 수 있다.Referring to FIG. 2 , a match cast block that is used to manufacture the column segment 200 included in the column structure 10 through precast, and is buried for the construction of the base 150 of the column structure 10 at the construction site. 100 may be manufactured to include the upper connection part 110 , the block side duct 120 , and the lower connection part 130 .

구체적으로, 매치 캐스트 블록(100)은 기둥 세그먼트(200)의 철근 돌출부(212)가 삽입되는 상부 연결부(110) 및 상하 방향으로 관통 연장되는 블록 측 덕트(120)를 포함할 수 있다. 또한, 매치 캐스트 블록(100)은 기초부(150)의 시공을 위한 기초 철근이 삽입되는 하부 연결부(130)를 포함할 수 있다.Specifically, the match cast block 100 may include an upper connecting portion 110 into which the reinforcing bar protrusion 212 of the column segment 200 is inserted, and a block-side duct 120 extending through the vertical direction. In addition, the match cast block 100 may include a lower connecting portion 130 into which the foundation reinforcement for the construction of the foundation 150 is inserted.

즉, 매치 캐스트 블록(100)은 기둥 세그먼트(200)의 주철근의 철근 돌출부(212)가 삽입되는 상부 연결부(110) 및 후술하는 세그먼트 측 덕트(220)에 대응되는 상하 방향으로 관통 연장된 블록 측 덕트(120)를 포함함으로써 제작장에서 기둥 세그먼트(200)를 제작하기 위한 하측 거푸집으로 활용될 수 있을 뿐만 아니라, 기초 철근이 삽입되는 하부 연결부(130)를 포함함으로써 시공 현장에서는 복수 개의 기둥 세그먼트(200) 중 첫 번째로 적층되는 기둥 세그먼트가 상측에 배치되는 기초부(150)에 포함될 수 있다.That is, the match cast block 100 extends through the block side in the vertical direction corresponding to the upper connection part 110 into which the reinforcing bar protrusion 212 of the main reinforcing bar of the column segment 200 is inserted and the segment-side duct 220 to be described later. By including the duct 120, it can be utilized as a lower formwork for manufacturing the column segment 200 in the manufacturing plant, as well as a plurality of column segments ( 200), the first stacked column segment may be included in the base 150 disposed on the upper side.

한편, 본원의 실시예에 관한 이하의 설명에서는, 기둥 구조물(10)이 시공되는 '시공 현장'과 대비하여 프리캐스트 방식으로 매치 캐스트 블록(100)을 기초로 하여 복수 개의 기둥 세그먼트(200)가 제작되는 공간을 '제작장'으로 지칭하도록 하며, 제작장의 용어는 공장 등으로 달리 지칭될 수 있음은 물론이다.On the other hand, in the following description of the embodiment of the present application, a plurality of column segments 200 based on the match cast block 100 in a precast method in comparison with the 'construction site' where the column structure 10 is constructed. It goes without saying that the manufacturing space is referred to as a 'workshop', and the term of the manufacturing site may be referred to as a factory or the like.

또한, 도 2를 참조하면, 매치 캐스트 블록(100)은 매립되는 블록 측 덕트(120)를 접속 및 지지하기 위한 덕트 연결부(121)를 포함할 수 있다. 또한, 도 2를 참조하면, 매치 캐스트 블록(100)은 기초부(150)의 상면과 기초부(150)의 상측으로 배치되는 기둥 세그먼트(200)가 연속적으로 시공될 수 있도록 기초부(150)의 내부로 적어도 일부 매립되는 형태로 시공될 수 있다.Also, referring to FIG. 2 , the match cast block 100 may include a duct connection part 121 for connecting and supporting the buried block-side duct 120 . In addition, referring to FIG. 2 , the match cast block 100 includes the upper surface of the base part 150 and the base part 150 so that the column segments 200 disposed on the upper side of the base part 150 can be continuously constructed. It can be constructed in a form that is at least partially buried into the interior of the

도 3은 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물의 복수의 기둥 세그먼트 중 하측 세그먼트의 세부 구성도이다.3 is a detailed configuration diagram of a lower segment of a plurality of column segments of a column structure constructed based on a segment plug-in method according to an embodiment of the present application.

도 3을 참조하면, 복수의 기둥 세그먼트(200) 중 최상단에 적층(배치)되는 상측 세그먼트(200b)가 아닌 하측 세그먼트(200a)의 상면에는 상측에 배치되는 기둥 세그먼트(200)의 철근 돌출부(212)가 삽입되는 철근 연결부(211)가 함몰 형성될 수 있다.Referring to FIG. 3 , a reinforcing bar protrusion 212 of a column segment 200 disposed on the upper surface of the lower segment 200a rather than the upper segment 200b stacked (arranged) on the top of the plurality of column segments 200 . ), the reinforcing bar connection part 211 into which it is inserted may be recessed.

또한, 도 3을 참조하면, 기둥 세그먼트(200)에는 하단이 기둥 세그먼트(200)의 하면으로부터 일부 하향 돌출되어 철근 돌출부(212)를 형성하는 주철근(210)이 매립될 수 있다. 또한, 기둥 세그먼트(200)에는 매치 캐스트 블록(100)의 블록 측 덕트(120)에 대응되게 상하 방향으로 관통 연장되는 세그먼트 측 덕트(220)가 매립될 수 있다.In addition, referring to FIG. 3 , the main reinforcing bar 210 , the lower end of which partially protrudes downward from the lower surface of the column segment 200 to form the reinforcing bar protrusion 212 , may be embedded in the column segment 200 . In addition, the segment-side duct 220 extending vertically through the column segment 200 to correspond to the block-side duct 120 of the match cast block 100 may be embedded.

또한, 도 3을 참조하면, 기둥 세그먼트(200)의 상면에는 매립되는 세그먼트 측 덕트(220)를 접속 및 지지하기 위한 덕트 연결부(221)를 포함할 수 있다. 또한, 도 3을 참조하면, 기둥 세그먼트(200)는 주철근(210)을 감싸는 형태로 배치되는 복수 개의 수평철근(201)을 포함할 수 있다. 여기서, 수평철근(201)은 상하 방향으로 수직 배치되는 주철근(210)에 대하여 배치되는 고리(링)형, 띠형 등의 형상으로 구비될 수 있으며, 본원의 실시예에 따라 띠철근, 전단철근 등으로 달리 지칭될 수 있다.In addition, referring to FIG. 3 , the upper surface of the pillar segment 200 may include a duct connection part 221 for connecting and supporting the embedded segment-side duct 220 . In addition, referring to FIG. 3 , the column segment 200 may include a plurality of horizontal reinforcing bars 201 disposed in a shape surrounding the main reinforcing bars 210 . Here, the horizontal reinforcing bar 201 may be provided in the shape of a ring (ring) shape, a belt shape, etc. disposed with respect to the main reinforcing bar 210 disposed vertically in the vertical direction, and according to the embodiment of the present application, a band reinforcing bar, shear reinforcing bar, etc. may be referred to differently.

구체적으로, 매치 캐스트 블록(100)을 하측 거푸집으로 하여 제작되는 기둥 세그먼트(200) 각각은, 주철근(210)의 철근 돌출부(212)를 매치 캐스트 블록(100)의 상측 연결부(110)에 삽입하고, 주철근(210)을 감싸는 수평철근(201)을 배근하고, 주철근(210) 및 수평철근(201)을 포위하도록 배치되는 세그먼트 거푸집(여기서, 하측 거푸집은 매치 캐스트 블록(100)을 이용한다.)에 기초하여 콘크리트를 타설 및 양생하는 방식으로 제작되는 것일 수 있다.Specifically, each of the column segments 200 manufactured by using the match cast block 100 as the lower formwork, the reinforcing bar protrusion 212 of the main reinforcing bar 210 is inserted into the upper connecting portion 110 of the match cast block 100, and , the horizontal reinforcing bar 201 surrounding the main reinforcing bar 210 is reinforced, and the segment formwork arranged to surround the main reinforcing bar 210 and the horizontal reinforcing bar 201 (here, the lower formwork uses the match cast block 100). It may be manufactured by pouring and curing concrete based on it.

한편, 제작장에서는 복수 개의 기둥 세그먼트(200)가 하나의 매치 캐스트 블록(100)을 활용하여 반복하여 제작되므로, 기둥 세그먼트(200)의 반복 제작에 따라 매치 캐스트 블록(100)의 상부 연결부(110), 블록 측 덕트(120) 등이 손상되는 것을 방지하고, 매치 캐스트 블록(100)의 상부 연결부(110), 블록 측 덕트(120) 등에 타설되는 콘크리트가 인입되는 것을 방지할 수 있는 수단이 요구되며, 이와 관련하여서는 도 6 내지 도 8을 참조하여 상세히 후술하도록 한다.On the other hand, since a plurality of pillar segments 200 are repeatedly manufactured using one match cast block 100 in the manufacturing plant, the upper connection part 110 of the match cast block 100 is repeatedly manufactured according to the repeated manufacturing of the pillar segments 200 . ), block side duct 120, etc. from being damaged, and means to prevent the concrete poured into the upper connection part 110 of the match cast block 100, the block side duct 120, etc. from entering is required. In this regard, it will be described later in detail with reference to FIGS. 6 to 8 .

도 4는 복수의 기둥 세그먼트 중 하측 세그먼트의 단면도이다. 구체적으로, 도 4의 (a)는 도 3의 'A' 방향을 기준으로 한 단면을 나타내고, 도 4의 (b)는 도 3의 'B' 방향을 기준으로 한 단면을 나타낸 것이다.4 is a cross-sectional view of a lower segment of a plurality of column segments. Specifically, (a) of FIG. 4 shows a cross-section based on the 'A' direction of FIG. 3, and FIG. 4(b) shows a cross-section on the basis of the 'B' direction of FIG. 3 .

본원의 일 실시예에 따르면, 매치 캐스트 블록(100)은 상하 방향에 직교하는 면 방향을 기준으로 방사형으로 배치되는 복수 개의 상부 연결부(110) 및 복수 개의 블록 측 덕트(120)를 포함할 수 있다.According to an embodiment of the present application, the match cast block 100 may include a plurality of upper connection parts 110 and a plurality of block-side ducts 120 that are radially disposed with respect to a plane direction orthogonal to the vertical direction. .

또한, 도 4의 (a)를 참조하면, 복수 개의 기둥 세그먼트(200) 중 하측 세그먼트(200a)에는 매치 캐스트 블록(100)의 복수 개의 상부 연결부(110)에 대응하는 복수 개의 주철근(210) 및 매치 캐스트 블록(100)의 복수 개의 블록 측 덕트(120)에 대응하는 복수 개의 세그먼트 측 덕트(220)가 각각 매립될 수 있다.In addition, referring to FIG. 4 (a), the lower segment 200a of the plurality of column segments 200 includes a plurality of main reinforcing bars 210 corresponding to the plurality of upper connection parts 110 of the match cast block 100 and A plurality of segment-side ducts 220 corresponding to the plurality of block-side ducts 120 of the match cast block 100 may be embedded, respectively.

구체적으로, 도 4를 참조하면, 기둥 세그먼트(200) 각각은 상하 방향에 직교하는 면 방향을 기준으로 각각 45도의 각도 범위로 이격 배치되는 8개의 주철근(210) 및 각각 90도의 각도 범위로 이격 배치되는 4개의 세그먼트 측 덕트(220)를 포함할 수 있다. 다만, 이에만 한정되는 것은 아니며, 시공하려는 기둥 구조물(10)의 직경, 높이 등에 기초하여 주철근(210) 및 세그먼트 측 덕트(220)는 전술한 예시 대비 많은 수 또는 적은 수로 다양하게 구비될 수 있다.Specifically, referring to FIG. 4 , each of the column segments 200 is spaced apart from each other in an angular range of 45 degrees based on a plane direction perpendicular to the vertical direction, and eight main reinforcing bars 210 and each are spaced apart in an angular range of 90 degrees. It may include four segment side ducts 220 . However, it is not limited thereto, and based on the diameter, height, etc. of the column structure 10 to be constructed, the main reinforcing bar 210 and the segment-side duct 220 may be provided in a variety of numbers greater or less than the above-described example. .

한편, 도 4를 참조하여 이해될 수 있는 바와 같이, 본원에서 개시하는 기둥 구조물(10)은 적층되는 복수 개의 기둥 세그먼트(200)의 철근 돌출부(212) 및 철근 연결부(211)를 통한 철근 삽입 체결 및 세그먼트 측 덕트(220)를 관통하도록 삽입되는 긴장재(예를 들면, 강연선 등)를 통한 포스트 텐션이 조합되는 방식으로 복합 연속화 방식으로 시공됨으로써, 덕트를 통해 관통 삽입되는 긴장재(예를 들면, 강연선 등)에 기반한 포스트 텐션을 수행하지 않는 종래의 시공 방식과 대비하여 기둥 세그먼트(200) 내에 매립되는 철근의 개수가 대폭 감소(축소)될 수 있으며, 마찬가지로 포스트 텐션을 위하여 삽입되는 긴장재의 수 역시 주철근(210)을 통한 철근 삽입 체결을 기초로 한 결합력을 고려하여 감소될 수 있으므로, 기둥 세그먼트(200)의 제작을 위해 소요되는 비용을 저감할 수 있는 이점이 있다.On the other hand, as can be understood with reference to FIG. 4 , the column structure 10 disclosed herein is a reinforcing bar insertion and fastening through the reinforcing bar protrusion 212 and the reinforcing bar connection part 211 of the plurality of column segments 200 to be stacked. And by constructing in a complex continuation method in such a way that the post tension through the tension material (eg, stranded wire, etc.) inserted to penetrate the segment-side duct 220 is combined, the tension material inserted through the duct (eg, stranded wire) The number of reinforcing bars embedded in the column segment 200 can be significantly reduced (reduced) compared to the conventional construction method that does not perform post tension based on Since it can be reduced in consideration of the coupling force based on the reinforcing bar insertion and fastening through 210 , there is an advantage that can reduce the cost required for manufacturing the column segment 200 .

도 5는 기둥 세그먼트에 매립되는 주철근의 형상을 나타낸 도면이다.5 is a view showing the shape of the main reinforcing bar embedded in the column segment.

도 5를 참조하면, 주철근(210)은 상단에 형성되는 철근 연결부(211) 및 하단에 형성되는 철근 돌출부(212)를 포함할 수 있다. 즉, 주철근(210)이 매립되는 기둥 세그먼트(200)의 상면에는 해당 기둥 세그먼트(200)의 상측에 배치되는 기둥 세그먼트(200)의 철근 돌출부(212)가 삽입되는 철근 연결부(211)가 함몰 형성될 수 있고, 기둥 세그먼트(200)의 하면으로부터 주철근(210)의 하단이 일부 하향 돌출되어 철근 돌출부(212)를 형성할 수 있다.Referring to FIG. 5 , the main reinforcing bar 210 may include a reinforcing bar connection part 211 formed at the upper end and a reinforcing bar protrusion 212 formed at the lower end. That is, in the upper surface of the column segment 200 in which the main reinforcing bar 210 is embedded, the reinforcing bar connection part 211 into which the reinforcing bar protrusion 212 of the column segment 200 disposed on the upper side of the column segment 200 is inserted is recessed. The lower end of the main reinforcing bar 210 may be partially protruded downward from the lower surface of the column segment 200 to form the reinforcing bar protrusion 212 .

또한, 도 5의 철근 연결부(211)에 대한 확대된 도시를 참조하면, 철근 연결부(211)에는 기둥 세그먼트(200)의 적층시 철근 연결부(211)로 삽입된 상측의 기둥 세그먼트(200)의 철근 돌출부(212)와 철근 연결부(211) 사이의 부착력을 제공하기 위한 그라우트(Grout)가 충진될 수 있다. 또한, 철근 연결부(211)의 내주면에는 충진된 그라우트(Grout)에 의한 부착력을 향상시켜 철근 돌출부(212)가 철근 연결부(211)로부터 이탈하는 것을 방지하기 위한 돌기 부재(2111)가 형성될 수 있다. 한편, 본원의 실시예에 관한 설명에서 그라우트(Grout)는 모르타르(몰탈)와 같은 시멘트 재료를 포함하는 충전재를 통칭하는 포괄적인 용어로 이해함이 바람직하다.In addition, referring to the enlarged view of the reinforcing bar connection 211 of FIG. 5 , the reinforcing bar of the upper column segment 200 inserted into the reinforcing bar connecting portion 211 when the column segments 200 are stacked in the reinforcing bar connecting portion 211 . A grout for providing an adhesive force between the protrusion 212 and the reinforcing bar connection part 211 may be filled. In addition, a protrusion member 2111 may be formed on the inner circumferential surface of the reinforcing bar connection part 211 to improve the adhesion by the filled grout to prevent the reinforcing bar protrusion 212 from being separated from the reinforcing bar connection part 211. . On the other hand, in the description of the embodiment of the present application, the grout (Grout) is preferably understood as a generic term that collectively refers to a filler including a cement material such as mortar (mortar).

또한, 도 5를 참조하면, 주철근(210)의 철근 연결부(211)의 하측 일부 영역과 철근 돌출부(212)의 하단부인 헤드(Head)부의 상측 일부 영역은 부착력을 증대시키기 위하여 이형철근(2101) 형상으로 형성될 수 있다.In addition, referring to FIG. 5 , the lower part of the reinforcing bar connection 211 of the main reinforcing bar 210 and the upper part of the upper part of the head, which is the lower end of the reinforcing bar protrusion 212, are deformed reinforcing bars 2101 to increase the adhesion force. It may be formed in a shape.

한편, 도 5를 참조하여 전술한 철근 연결부(211)의 구조 및 형상은 적층되는 복수 개의 기둥 세그먼트(200) 중 기초부(150)에 대하여 배치되는 첫 번째 기둥 세그먼트(200)인 하측 세그먼트(200a)의 철근 돌출부(212)가 삽입되는 매치 캐스트 블록(100)의 상부 연결부(110)와 대응되는 것일 수 있으므로, 상부 연결부(110)의 구조 및 형상에 대한 자세한 설명은 생략하도록 한다.On the other hand, the structure and shape of the reinforcing bar connection part 211 described above with reference to FIG. 5 is the lower segment 200a which is the first column segment 200 disposed with respect to the base part 150 among the plurality of column segments 200 to be stacked. ) may correspond to the upper connection part 110 of the match cast block 100 into which the reinforcing bar protrusion 212 is inserted, so a detailed description of the structure and shape of the upper connection part 110 will be omitted.

본원의 일 실시예에 따르면, 복수 개의 기둥 세그먼트(200)는 제작장에서 매치 캐스트 블록(100)에 기초하여 각각 제작된 후 시공 현장으로 이송될 수 있다. 이후, 시공 현장에서는 매치 캐스트 블록(100)이 매립되도록 기초부(150)가 시공되며, 기초부(150)의 상측으로 배치되는 복수 개의 기둥 세그먼트(200) 중 어느 하나의 기둥 세그먼트(200)는 하측에 위치한 매치 캐스트 블록(100)의 상부 연결부(110)에 대하여 철근 돌출부(212)를 적어도 일부 삽입하는 형태로 배치될 수 있다.According to an embodiment of the present application, the plurality of pillar segments 200 may be respectively manufactured based on the match cast block 100 at the manufacturing site and then transported to the construction site. Thereafter, at the construction site, the foundation 150 is constructed so that the match cast block 100 is buried, and any one of the plurality of pillar segments 200 disposed above the foundation 150 is The reinforcing bar protrusion 212 may be at least partially inserted with respect to the upper connection part 110 of the match cast block 100 located on the lower side.

또한, 복수 개의 기둥 세그먼트(200) 중 나머지 기둥 세그먼트(200)는 기초부(150)의 상측으로 배치된 전술한 어느 하나의 기둥 세그먼트(200)의 상측에 순차적으로 적층되며, 이 때, 적층되는 기둥 세그먼트(200)의 철근 돌출부(212)를 하측에 배치된 기둥 세그먼트(200)의 철근 연결부(211)에 삽입하는 방식으로 나머지 기둥 세그먼트(200)가 순차적으로 적층되는 것일 수 있다. 한편, 시공 현장에서 순차적으로 적층되는 복수 개의 기둥 세그먼트(200) 중 최상단에 적층되는 기둥 세그먼트(200)는 전술한 상측 세그먼트(200b)일 수 있으며, 상측 세그먼트(200b)는 도 3 및 도 4를 참조하여 전술한 하측 세그먼트(200a)와 상이한 구조로 제작될 수 있으며, 이러한 상측 세그먼트(200b)에 관하여는 도 11 및 도 12를 참조하여 후술하도록 한다.In addition, the remaining pillar segments 200 of the plurality of pillar segments 200 are sequentially stacked on the upper side of any one of the above-described pillar segments 200 disposed above the base part 150 , and at this time, the stacked The remaining column segments 200 may be sequentially stacked by inserting the reinforcing bar protrusion 212 of the column segment 200 into the reinforcing bar connection 211 of the column segment 200 disposed on the lower side. On the other hand, the column segment 200 stacked on the top of the plurality of column segments 200 sequentially stacked at the construction site may be the above-described upper segment 200b, and the upper segment 200b is shown in FIGS. 3 and 4 . It may be manufactured to have a different structure from the aforementioned lower segment 200a with reference, and the upper segment 200b will be described later with reference to FIGS. 11 and 12 .

이하에서는, 도 6 내지 도 8을 참조하여 제작장에서 복수 개의 기둥 세그먼트(200) 각각이 매치 캐스트 블록(100)을 활용하여 반복 제작되는 과정에서, 매치 캐스트 블록(100)의 상부 연결부(110), 블록 측 덕트(120) 등의 손상을 방지하기 위하여 개재되는 관형 부재(1110) 및 매치 캐스트 블록(100)의 상부 연결부(110), 블록 측 덕트(120) 등에 기둥 세그먼트(200)의 제작을 위해 타설되는 콘크리트가 인입되는 것을 방지하기 위한 실링 기법을 설명하도록 한다.Hereinafter, with reference to FIGS. 6 to 8 , in the process where each of the plurality of column segments 200 is repeatedly manufactured using the match cast block 100 at the manufacturing site, the upper connection part 110 of the match cast block 100 , to prevent damage to the block side duct 120, etc., the tubular member 1110 and the upper connection part 110 of the match cast block 100, the block side duct 120, etc. The production of the column segment 200 The sealing technique to prevent the inflow of concrete to be poured for this purpose will be described.

도 6은 기둥 세그먼트의 제작 시 매치 캐스트 블록의 상부 연결부와 상부 연결부에 삽입되는 주철근의 철근 돌출부의 배치를 나타낸 도면이다.6 is a view showing the arrangement of the reinforcing bar protrusion of the main reinforcing bar inserted into the upper connection part and the upper connection part of the match cast block when the column segment is manufactured.

도 6을 참조하면, 매치 캐스트 블록(100)의 상부 연결부(110)는 삽입되는 철근 돌출부(212)의 직경 보다 큰 내부 직경을 갖도록 함몰 형성되며, 이에 따라 상부 연결부(110)에 삽입되는 철근 돌출부(212)와 상부 연결부(110)의 함몰 형성된 내주면 사이에는 소정의 간격 공간(도 6의 A)이 형성될 수 있다.Referring to FIG. 6 , the upper connecting portion 110 of the match cast block 100 is recessed to have an inner diameter greater than the diameter of the inserted reinforcing bar protrusion 212 , and accordingly, the reinforcing bar protrusion inserted into the upper connecting portion 110 . A predetermined spacing space (A of FIG. 6 ) may be formed between the 212 and the inner circumferential surface of the upper connection part 110 , which is recessed.

한편, 도 6을 참조하면, 철근 돌출부(212)는 실제 시공 현장에서 기둥 세그먼트(200)가 적층될 때 상부 연결부(110) 또는 철근 연결부(211)에 충진되는 그라우트(Grout)와의 부착력을 증대시키기 위하여 철근 돌출부(212)의 외주면 적어도 일부에 형성되는 이형철근(2101) 형상의 외면을 포함할 수 있다. 또한, 상측 연결부(110)에도 실제 시공 현장에서 주입되는 그라우트(Grout)와의 부착력을 증대시키기 위한 돌기 부재(111)가 형성될 수 있다.On the other hand, referring to FIG. 6 , the reinforcing bar protrusion 212 increases the adhesion with the grout filled in the upper connection part 110 or the reinforcing bar connection part 211 when the column segments 200 are stacked at the actual construction site. To this end, it may include an outer surface in the shape of a deformed reinforcing bar 2101 formed on at least a portion of the outer circumferential surface of the reinforcing bar protrusion 212 . In addition, the protrusion member 111 for increasing the adhesion to the grout injected at the actual construction site may be formed in the upper connection part 110 as well.

이와 관련하여, 기둥 세그먼트(200)의 제작 과정에서 상측 연결부(110) 측의 돌기 부재(111)와 제작되는 기둥 세그먼트(200)의 철근 돌출부(212)의 헤드부 또는 이형철근(2101) 형상의 외면이 상호 간섭하게 되어, 상측 연결부(110) 측의 돌기 부재(111), 제작되는 기둥 세그먼트(200)의 철근 돌출부(212)의 헤드부 및 이형철근(2101) 형상의 외면 중 적어도 하나에서 마모 등의 손상이 발생하면, 실제 시공현장에서 충진되는 그라우트(Grout)와의 부착력이 감소하는 문제가 발생할 수 있다.In this regard, in the manufacturing process of the column segment 200, the head of the protrusion member 111 on the side of the upper connection part 110 and the reinforcing bar protrusion 212 of the column segment 200 to be manufactured or the shape of the deformed reinforcing bar 2101 The outer surfaces interfere with each other, and at least one of the protrusion member 111 on the side of the upper connection part 110, the head of the reinforcing bar protrusion 212 of the column segment 200 to be manufactured, and the outer surface of the deformed reinforcing bar 2101 shape wears out If the back is damaged, there may be a problem in that the adhesive force with the grout is reduced at the actual construction site.

도 7은 기둥 세그먼트의 제작 시 매치 캐스트 블록의 상부 연결부와 상부 연결부에 삽입되는 주철근의 철근 돌출부의 상호 간섭을 방지하기 위해 개재되는 관형 부재를 나타낸 도면이다.7 is a view illustrating a tubular member interposed to prevent mutual interference between the upper connection part of the match cast block and the reinforcing bar protrusion of the main reinforcing bar inserted into the upper connection part when the column segment is manufactured.

도 7을 참조하면, 전술한 기둥 세그먼트(200)의 제작 시 발생 가능한 매치 캐스트 블록(100)의 상부 연결부(110)와 상부 연결부(110)에 삽입되는 주철근(210)의 철근 돌출부(212)의 상호 간섭을 방지하기 위하여, 전술한 간격 공간(A)에는 상부 연결부(110)의 내주면과 철근 돌출부(212)의 외주면 사이의 상호 간섭을 방지하기 위한 관형 부재(1110)가 삽입될 수 있다.Referring to FIG. 7 , the reinforcing bar protrusion 212 of the main reinforcing bar 210 inserted into the upper connecting portion 110 and the upper connecting portion 110 of the match cast block 100 that may occur during the production of the above-described column segment 200 . In order to prevent mutual interference, a tubular member 1110 for preventing mutual interference between the inner circumferential surface of the upper connecting portion 110 and the outer circumferential surface of the reinforcing bar protrusion 212 may be inserted into the aforementioned gap space A.

보다 구체적으로, 본원의 일 실시예에 따르면, 상부 연결부(110)의 상향 개구된 내부 공간은 관형 부재(1110)가 내측에 삽입될 수 있도록 철근 돌출부(212)와 상부 연결부(110)의 내주면 사이에 상호 간접 방지 목적으로 소정의 두께를 갖도록 구비된 관형 부재(1110)가 충분히 개재될 수 있는 크기로 형성됨이 바람직하다. 예시적으로, 상부 연결부(110)는 철근 돌출부(212)가 상부 연결부(110)에 삽입된 상태에서 철근 돌출부(212)와 상부 연결부(110)의 내주면 사이의 이격 거리(도 7의 d)는 관형 부재(1110) 부재의 두께 대비 미리 설정된 임계 여유치를 갖도록 설계되는 것일 수 있다.More specifically, according to an embodiment of the present application, the upwardly opened internal space of the upper connection part 110 is between the inner peripheral surface of the reinforcing bar protrusion 212 and the upper connection part 110 so that the tubular member 1110 can be inserted therein. It is preferable that the tubular member 1110 provided to have a predetermined thickness for mutual indirect prevention purpose is formed in a size that can be sufficiently interposed therebetween. Illustratively, in the upper connection part 110, the separation distance between the reinforcing bar protrusion 212 and the inner circumferential surface of the upper connection part 110 in a state in which the reinforcing bar protrusion 212 is inserted into the upper connection part 110 (d in FIG. 7) is The tubular member 1110 may be designed to have a preset critical margin compared to the thickness of the member.

도 8은 기둥 세그먼트의 제작 시 타설되는 콘크리트가 매치 캐스트 블록의 상부 연결부로 침입하지 않도록, 상부 연결부의 개구된 상측과 주철근 사이의 사이 공간을 실링하는 것을 설명하기 위한 도면이다.8 is a view for explaining sealing the space between the open upper side of the upper connection part and the main reinforcing bar so that concrete poured during the production of the column segment does not penetrate into the upper connection part of the match cast block.

도 8을 참조하면, 기둥 세그먼트(200)가 제작되는 과정에서 제작되는 기둥 세그먼트(200)에 매립될 주철근(210)이 상부 연결부(110)에 전술한 관형 부재(1110)가 개재된 상태로 삽입되고 나면, 매치 캐스트 블록(100)을 하측 거푸집으로 하여 매치 캐스트 블록(100)의 상측에 콘크리트가 타설될 수 있다.Referring to FIG. 8 , the main reinforcing bar 210 to be embedded in the column segment 200 manufactured in the process of manufacturing the column segment 200 is inserted into the upper connection part 110 with the aforementioned tubular member 1110 interposed therebetween. Once completed, concrete can be poured on the upper side of the match cast block 100 using the match cast block 100 as the lower formwork.

다만, 매치 캐스트 블록(100)은 복수 개의 세그먼트 블록(100)의 제작에 반복적으로 사용될 수 있으므로, 상부 연결부(110)의 상향 개구된 내부 공간에는 특정 기둥 세그먼트(200)의 제작 시에 타설되는 콘크리트의 인입(침입)이 방지되어야 한다.However, since the match cast block 100 can be repeatedly used to manufacture the plurality of segment blocks 100 , the concrete poured during the manufacture of the specific column segment 200 in the upwardly opened inner space of the upper connection part 110 . of intrusion (intrusion) should be prevented.

따라서, 철근 돌출부(212)가 상부 연결부(110)에 삽입된 후, 상부 연결부(110)의 상향 개구된 내부 공간을 실링할 수 있도록 와셔 부재(1120)가 주철근(210)의 외측에 배치될 수 있다. 다만, 와셔 부재(1120)의 배치 후에도 주철근(210)과 와셔 부재(1120) 사이에는 틈새 공간(1130)이 형성될 수 있으므로, 도 8을 참조하면, 틈새 공간(1130)이 실리콘 등의 실링 부재를 도포하는 방식 등을 통해 메워진 후 콘크리트의 타설이 수행될 수 있다. 또한, 철근 돌출부(212)는 콘크리트, 실리콘 등의 이물질이 부착되는 것이 방지되도록 비닐과 같은 임시적인 커버 부재로 감싸 가고정될 수 있다.Therefore, after the reinforcing bar protrusion 212 is inserted into the upper connecting portion 110, the washer member 1120 may be disposed on the outside of the main reinforcing bar 210 to seal the upwardly opened inner space of the upper connecting portion 110. there is. However, since a gap space 1130 may be formed between the main reinforcing bar 210 and the washer member 1120 even after the washer member 1120 is disposed, referring to FIG. 8 , the gap space 1130 is a sealing member such as silicone. Concrete pouring can be carried out after filling through the method of applying, etc. In addition, the reinforcing bar protrusion 212 may be wrapped and temporarily fixed with a temporary cover member such as vinyl to prevent foreign substances such as concrete and silicone from being attached.

이하에서는, 도 9를 참조하여, 기둥 세그먼트(200)의 제작 시, 매치 캐스트 블록(100)의 상부 연결부(110)에 철근 돌출부(212)가 삽입되는 형태로 수직으로 배치되는 주철근(210)의 기울어짐을 방지하기 위한 지그 구조체의 형상 및 기능을 설명하도록 한다.Hereinafter, with reference to FIG. 9 , when the column segment 200 is manufactured, the reinforcing bar protrusion 212 is inserted into the upper connection part 110 of the match cast block 100 , and the main reinforcing bar 210 is vertically disposed. The shape and function of the jig structure to prevent inclination will be described.

도 9는 기둥 세그먼트의 제작 시 주철근이 기울어지는 것이 방지되도록 배치되는 지그 구조체를 설명하기 위한 도면이다.9 is a view for explaining a jig structure that is arranged to prevent the main reinforcing bar from inclining during the manufacture of the column segment.

도 9를 참조하면, 기둥 세그먼트(200)의 제작 시, 기둥 세그먼트(200)에 매립되는 주철근(210)이 상하 방향에 대하여 어느 일측으로 기울어지는 것이 방지되도록 주철근(210)의 상측 또는 철근 연결부(211)를 감싸 수평 방향으로 이동되지 않도록 고정하는 홀이 형성된 지그 구조체(240)가 배치될 수 있다.9, when the column segment 200 is manufactured, the upper side of the main reinforcing bar 210 or the reinforcing bar connection part ( A jig structure 240 in which a hole is formed to surround the 211 and fix it so as not to move in the horizontal direction may be disposed.

또한, 도 9를 참조하면, 지그 구조체(240)는 상측 지그(241) 및 상측 지그(241)로부터 하측으로 간격을 두고 배치되는 하측 지그(242)를 포함할 수 있다. 이와 관련하여, 지그 구조체(240)는 복수 개의 기둥 세그먼트(200) 각각에 매립되는 주철근(210)과 세그먼트 측 덕트(220)가 전체 기둥 구조물(10)의 상하 방향을 따라 연속적으로 배치되는 수평 및 수직 위치 정합성을 확보하기 위한 것일 수 있다.Also, referring to FIG. 9 , the jig structure 240 may include an upper jig 241 and a lower jig 242 disposed at an interval downward from the upper jig 241 . In this regard, the jig structure 240 is a horizontal and vertical direction in which the main reinforcing bars 210 and the segment-side duct 220 embedded in each of the plurality of column segments 200 are continuously arranged along the vertical direction of the entire column structure 10 . It may be for securing vertical position consistency.

구체적으로, 상측 지그(241) 및 하측 지그(242) 각각에는 매치 캐스트 블록(100)에 형성된 상부 연결부(110)와 블록 측 덕트(120)와 대응되는 위치에 형성된 복수의 홀을 포함하며, 상하 방향을 따라 소정의 간격을 두고 이격 배치되어, 주철근(210) 및 세그먼트 측 덕트(220) 중 적어도 하나를 소정의 간격에 대응하는 서로 다른 두 위치에서 각각 지지함으로써 주철근(210) 및 세그먼트 측 덕트(220)의 수평 및 수직 위치 정합성이 보다 정확하게 확보되는 것일 수 있다. 다만, 이에만 한정되는 것은 아니고, 본원의 구현예에 따라 지그 구조체(240)는 상하 방향으로 서로 간격을 두고 배치되는 3 개 이상의 단위 지그를 포함하도록 설계되는 것일 수 있다.Specifically, each of the upper jig 241 and the lower jig 242 includes a plurality of holes formed at positions corresponding to the upper connection part 110 and the block side duct 120 formed in the match cast block 100, The main reinforcing bar 210 and the segment-side duct ( 210) and the segment-side duct ( 220), the horizontal and vertical positional consistency may be more accurately secured. However, the present invention is not limited thereto, and the jig structure 240 according to the embodiment of the present application may be designed to include three or more unit jigs disposed at a distance from each other in the vertical direction.

도 10은 기둥 세그먼트의 제작 프로세스를 나타낸 개념도이다.10 is a conceptual diagram illustrating a manufacturing process of a column segment.

도 10을 참조하여 전술한 기둥 세그먼트(200)의 제작 과정을 종합하면, 복수 개의 기둥 세그먼트(200) 각각은 도 10의 (a)와 같이 제작된 매치 캐스트 블록(100)의 상측의 상부 연결부(110)에 주철근(210)의 철근 돌출부(212)를 삽입하고, 배치된 주철근(210)을 감싸는 수평철근(201)을 배치하여 배근하고(도 10의 (b)), 주철근(210) 및 수평철근(201)을 포위하도록 형성되는 세그먼트 거푸집 및 하측 거푸집인 매치 캐스트 블록(100)에 기초하여 콘크리트를 타설 및 양생(도 10의 (c))하는 방식으로 제작장에서 각각 제작될 수 있다.Combining the manufacturing process of the above-described pillar segment 200 with reference to FIG. 10, each of the plurality of pillar segments 200 includes an upper connection part ( Insert the reinforcing bar protrusion 212 of the main reinforcing bar 210 in 110), and arrange and reinforce the horizontal reinforcing bar 201 surrounding the arranged main reinforcing bar 210 (FIG. 10 (b)), the main reinforcing bar 210 and the horizontal Based on the match cast block 100, which is the segment formwork and the lower formwork formed to surround the reinforcing bar 201, concrete is poured and cured (FIG. 10(c)).

이하에서는 도 11 및 도 12를 참조하여, 상측 세그먼트(200b)의 형상 및 구조에 관해 설명하도록 한다.Hereinafter, the shape and structure of the upper segment 200b will be described with reference to FIGS. 11 and 12 .

도 11은 본원의 일 실시예에 따른 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물의 복수의 기둥 세그먼트 중 상측 세그먼트의 세부 구성도이고, 도 12는 복수의 기둥 세그먼트 중 상측 세그먼트의 단면도이다. 구체적으로, 도 12는 도 11의 'A' 방향을 기준으로 한 단면을 나타낸 것이다.11 is a detailed configuration diagram of an upper segment of a plurality of column segments of a column structure constructed based on a segment plug-in method according to an embodiment of the present application, and FIG. 12 is a cross-sectional view of an upper segment of the plurality of column segments. Specifically, FIG. 12 is a cross-sectional view taken along the 'A' direction of FIG. 11 .

도 11 및 도 12를 참조하면, 상측 세그먼트(200b)는 전술한 하부 세그먼트(200a)와 달리 상측에 다른 기둥 세그먼트가 적층되지 않으므로, 하부 세그먼트(200a)의 상면에 형성되는 철근 연결부(211) 및 덕트 연결부(221)가 미형성될 수 있다. 또한, 도 11 및 도 12를 참조하면, 상측 세그먼트(200b)에는 가력기가 연결되는 연결부(슬리브, Sleeve)가 관통 형성될 수 있다.11 and 12, since the upper segment 200b is different from the above-described lower segment 200a, other column segments are not stacked on the upper side, so the reinforcing bar connection 211 formed on the upper surface of the lower segment 200a and The duct connection part 221 may not be formed. Also, referring to FIGS. 11 and 12 , a connection part (sleeve, Sleeve) to which the pressurizer is connected may be formed through the upper segment 200b.

이하에서는 도 13을 참조하여 시공 현장에서 매치 캐스트 블록(100)을 기초로 기둥의 기초부(150)가 시공되는 프로세스를 설명하도록 한다.Hereinafter, a process in which the base portion 150 of the column is constructed based on the match cast block 100 at the construction site will be described with reference to FIG. 13 .

도 13은 기초부에 배치되는 앵커 프레임을 나타낸 도면이다. 구체적으로, 도 13의 (a)는 앵커 프레임(151)을 정면에서 바라본 정면도이고, 도 13의 (b)는 앵커 프레임(151)을 상측에서 바라본 평면도이다.13 is a view showing an anchor frame disposed on the base. Specifically, (a) of FIG. 13 is a front view of the anchor frame 151 as viewed from the front, and (b) of FIG. 13 is a plan view of the anchor frame 151 as viewed from above.

도 13을 참조하면, 앵커 프레임(151)은 복수 개의 수직 프레임(1511) 및 적어도 하나의 수평 플레이트(1512)를 포함할 수 있다. 구체적으로, 앵커 프레임(151)은 기둥 구조물(10)의 기초부(150)를 미리 설정된 높이로 형성하기 위해 사용되는 높이 조절용 부재로 기능할 수 있으며, 기초부(150)의 시공 시 앵커 프레임(151)의 상면에 사전 제작된 매치 캐스트 블록(100)이 배치되는 것일 수 있다. 또한, 본원의 일 실시예에 따르면, 앵커 프레임(151)은 매치 캐스트 블록(100)이 시공 완료된 기초부(150)에 대하여 적어도 일부 매립될 수 있는 높이로 배치됨이 바람직할 수 있다.Referring to FIG. 13 , the anchor frame 151 may include a plurality of vertical frames 1511 and at least one horizontal plate 1512 . Specifically, the anchor frame 151 may function as a member for height adjustment used to form the base 150 of the column structure 10 to a preset height, and when the base 150 is constructed, the anchor frame ( The pre-fabricated match cast block 100 may be disposed on the upper surface of the 151 . In addition, according to an embodiment of the present application, the anchor frame 151 may be preferably disposed at a height at which the match cast block 100 can be embedded at least partially with respect to the construction-completed foundation 150 .

또한, 도면에는 도시되지 않았으나, 앵커 프레임(151)의 수평 플레이트(1512)에는 기초부(150)의 시공을 위한 기초 철근 및 관통 삽입되는 덕트가 각각 통과하기 위한 복수의 홀이 매치 캐스트 블록(100)에 형성된 하측 연결부(130) 및 블록 측 덕트(120)에 대응하는 위치 및 크기로 형성될 수 있다.In addition, although not shown in the drawings, the horizontal plate 1512 of the anchor frame 151 has a plurality of holes through which the foundation reinforcement for the construction of the foundation 150 and the duct to be inserted through each pass through the match cast block 100 ) may be formed in a position and size corresponding to the lower connection portion 130 and the block-side duct 120 formed in.

구체적으로, 앵커 프레임(151)은 시공되는 기둥 구조물(10)의 기초부(150)에 대응하여 시공 현장에서 배치될 수 있다. 또한, 앵커 프레임(151) 상에는 매치 캐스트 블록(100)이 배치될 수 있다. 또한, 매치 캐스트 블록(100)이 배치되고 나면, 기초부(150)의 시공을 위한 기초 철근이 매치 캐스트 블록(100)의 하부 연결부(130)에 삽입되는 배근이 수행될 수 있다. 이어서, 삽입된 기초 철근과 매치 캐스트 블록(100)을 포위하도록 배치되는 기초부 거푸집에 기초하여 콘크리트를 타설 및 양생함으로써 기초부(150)가 시공되는 것일 수 있다.Specifically, the anchor frame 151 may be disposed at the construction site to correspond to the base portion 150 of the column structure 10 to be constructed. Also, the match cast block 100 may be disposed on the anchor frame 151 . In addition, after the match cast block 100 is disposed, reinforcement in which a foundation reinforcing bar for construction of the base unit 150 is inserted into the lower connection unit 130 of the match cast block 100 may be performed. Subsequently, the foundation 150 may be constructed by pouring and curing concrete based on the foundation formwork disposed to surround the inserted foundation reinforcement and the match cast block 100 .

본원의 일 실시예에 따르면, 매치 캐스트 블록(100)의 하부 연결부(130)와 기초부(150)를 이루는 기초 철근은 하부 연결부(130)와 삽입되는 기초 철근 사이에 개재되는 중간 커플러(미도시)를 매개로 하여 배근되는 것일 수 있다.According to an embodiment of the present application, the base reinforcement forming the lower connection part 130 and the base part 150 of the match cast block 100 is an intermediate coupler (not shown) interposed between the lower connection part 130 and the inserted basic reinforcement. ) may be deployed as a medium.

구체적으로, 중간 커플러(미도시)는 내부가 상하 방향으로 관통 형성되어 기초 철근의 일단부(상단부)가 삽입될 수 있으며, 중간 커플러(미도시)의 외면은 하부 연결부(130)에 삽입될 수 있는 규격으로 구비되는 것일 수 있다. 또한, 본원의 일 실시예에 따르면, 중간 커플러(미도시)에는 매치 캐스트 블록(100)의 하부 연결부(130)와 접촉하는 외주면 및 기초 철근의 삽입된 외면과 접촉하는 내주면에 모두 나사산이 형성될 수 있다.Specifically, the middle coupler (not shown) has an inner penetrating through it in the vertical direction, so that one end (upper part) of the basic reinforcing bar can be inserted, and the outer surface of the intermediate coupler (not shown) can be inserted into the lower connection part 130 . It may be provided with a standard. In addition, according to an embodiment of the present application, in the intermediate coupler (not shown), threads are formed on both the outer peripheral surface in contact with the lower connection part 130 of the match cast block 100 and the inner peripheral surface in contact with the inserted outer surface of the base reinforcing bar. can

또한, 중간 커플러(미도시)가 하부 연결부(130)와 기초 철근 사이에 개재된 상태에서 중간 커플러(미도시)를 제1방향으로 회전시키면 중간 커플러(미도시)가 하부 연결부(130) 및 기초 철근에 대하여 모두 조여지고, 전술한 제1방향과 대향하는 제2방향으로 중간 커플러(미도시)를 회전시키면 중간 커플러(미도시)가 하부 연결부(130) 및 기초 철근에 대하여 모두 풀리는 방향으로 중간 커플러(미도시)의 외주면에 형성된 외주 나사산 및 중간 커플러(미도시)의 내주면에 형성된 내주 나사산이 형성되는 것일 수 있다. 여기서, 제1방향 및 제2방향은 예시적으로 시계 방향 또는 반시계 방향을 의미하는 것일 수 있다.In addition, when the intermediate coupler (not shown) rotates the intermediate coupler (not shown) in the first direction in a state interposed between the lower connection part 130 and the foundation reinforcement, the intermediate coupler (not shown) is the lower connection part 130 and the foundation All of the reinforcing bars are tightened, and when the intermediate coupler (not shown) is rotated in the second direction opposite to the first direction described above, the intermediate coupler (not shown) is loosened with respect to the lower connection part 130 and the basic reinforcing bars in the middle An outer circumferential thread formed on the outer circumferential surface of the coupler (not shown) and an inner circumferential screw thread formed on the inner circumferential surface of the intermediate coupler (not shown) may be formed. Here, the first direction and the second direction may refer to, for example, a clockwise direction or a counterclockwise direction.

보다 구체적으로, 중간 커플러(미도시)를 제1방향으로 회전시키는 경우, 외주 나사산은 하부 연결부(130)의 내면을 따라 회전하여 중간 커플러(미도시)가 하부 연결부(130)의 함몰 형성된 내측 공간을 따라 상향 이동됨으로써 중간 커플러(미도시)가 하부 연결부(130)에 대하여 조여지고, 내주 나사산은 기초 철근의 외면(기초 철근의 외주면에 형성된 나사산)을 따라 회전(예를 들면 제2 방향)하여 기초 철근이 중간 커플러(미도시)의 내주면을 따라 상향 이동됨으로써 기초 철근이 중간 커플러(미도시)에 대하여 조여지는 것일 수 있다.More specifically, when rotating the intermediate coupler (not shown) in the first direction, the outer circumferential thread rotates along the inner surface of the lower connection part 130 so that the intermediate coupler (not shown) is recessed in the lower connection part 130 . The intermediate coupler (not shown) is tightened with respect to the lower connection part 130 by moving upward along the By moving upward along the inner peripheral surface of the base reinforcing bar intermediate coupler (not shown), the base reinforcing bar may be tightened with respect to the intermediate coupler (not shown).

반대로, 중간 커플러(미도시)를 제2방향으로 회전시키는 경우, 외주 나사산은 하부 연결부(130)의 내면을 따라 전술한 방향과 반대 방향으로 회전하여 중간 커플러(미도시)가 하부 연결부(130)의 함몰 형성된 내측 공간을 따라 하향 이동됨으로써 중간 커플러(미도시)가 하부 연결부(130)에 대하여 조임이 해제되고, 내주 나사산은 기초 철근의 외면(기초 철근의 외주면에 형성된 나사산)을 따라 전술한 방향과 반대 방향(제1 방향)으로 회전하여 기초 철근이 중간 커플러(미도시)의 내주면을 따라 하향 이동됨으로써 기초 철근이 중간 커플러(미도시)에 대하여 조임이 해제되는 것일 수 있다.Conversely, when rotating the intermediate coupler (not shown) in the second direction, the outer circumferential thread rotates in the opposite direction to the above-described direction along the inner surface of the lower connection part 130 so that the intermediate coupler (not shown) is connected to the lower connection part 130 . By moving downward along the recessed inner space of the intermediate coupler (not shown), the tightening with respect to the lower connection part 130 is released, and the inner circumferential thread is the outer surface of the base reinforcing bar (thread formed on the outer circumferential surface of the base reinforcing bar) in the above-described direction By rotating in the opposite direction (first direction) and the base reinforcing bar moves downward along the inner circumferential surface of the intermediate coupler (not shown), the tightening of the base reinforcing bars with respect to the intermediate coupler (not shown) may be released.

이와 관련하여, 상술한 도 1의 (b)를 참조하여 이해될 수 있는 바와 같이, 기초부(150)의 시공을 위해 배근되는 기초 철근은 직선 형상의 기초 철근 뿐만 아니라, 적어도 일부가 절곡(만곡)된 형태의 기초 철근을 포함할 수 있으므로, 매치 캐스트 블록(100)의 하부 연결부(130)에 절곡(만곡)된 형태의 기초 철근의 단부를 삽입하여 기초 철근 자체를 회전시켜 하부 연결부(130)와 기초 철근이 조여지도록 하는 방식은 주변 간섭 등으로 인해 어려움이 있을 수 있고, 이러한 문제는 기초부(150)가 시공되는 영역의 공간적 제약에 따라 보다 극심할 수 있다.In this regard, as can be understood with reference to the above-described Fig. 1 (b), the foundation reinforcement reinforced for the construction of the foundation 150 is not only a straight-shaped basic reinforcement, but also at least some of the bending (curved) ), by inserting the end of the bent (curved) form of the base reinforcing bar into the lower connecting portion 130 of the match cast block 100 to rotate the base reinforcing bar itself, the lower connecting portion 130 and the method of tightening the foundation reinforcing bars may have difficulties due to peripheral interference, etc., and this problem may be more severe depending on the spatial constraint of the area where the foundation 150 is constructed.

이를 고려하여 본원에서는, 매치 캐스트 블록(100)의 하부 연결부(130)와 기초 철근 사이에 개재되며, 제1방향으로 회전시키면 하부 연결부(130)와 기초 철근에 대하여 모두 조여지게 구비(외주 나사산 및 내주 나사산이 형성)되고, 제1방향과 대향하는 제2방향으로 회전시키면 하부 연결부(130)와 기초 철근에 대하여 모두 풀리게 구비(외주 나사산 및 내주 나사산이 형성)되는 중간 커플러(미도시)를 매개로 하여 기초부(150)의 시공을 위한 기초 철근을 하부 연결부(130)에 접속함으로써, 절곡(만곡)된 형태의 기초 철근에 대한 시공 편의성을 향상시킬 수 있다.In consideration of this, in the present application, it is interposed between the lower connection part 130 of the match cast block 100 and the foundation reinforcement, and provided to be tightened with respect to both the lower connection part 130 and the foundation reinforcement when rotated in the first direction (outer circumferential thread and The inner circumferential thread is formed), and when rotated in the second direction opposite to the first direction, both the lower connection part 130 and the base reinforcing bar are provided to be loosened (the outer circumferential thread and the inner circumferential thread are formed) Intermediate coupler (not shown) By connecting the foundation reinforcement for the construction of the foundation 150 to the lower connection part 130, it is possible to improve the construction convenience for the bent (curved) type of the foundation reinforcement.

이하에서는 상기에 자세히 설명된 내용을 기반으로, 본원의 동작 흐름을 간단히 살펴보기로 한다.Hereinafter, an operation flow of the present application will be briefly reviewed based on the details described above.

도 14는 본원의 일 실시예에 따른 세그먼트 플러그인 방식의 기둥 구조물 시공 방법에 대한 동작 흐름도이다.14 is an operation flowchart for a method for constructing a column structure of a segment plug-in method according to an embodiment of the present application.

도 14를 참조하면, 단계 S11에서는 (a) 매치 캐스트 블록(100)을 제작할 수 있다. 또한, 단계 S11을 통해 제작되는 매치 캐스트 블록(100)의 상면에는 기둥 세그먼트의 철근 돌출부가 삽입되는 상부 연결부가 매치 캐스트 블록(100)의 내측으로 함몰 형성될 수 있다. 또한, 단계 S11을 통해 제작되는 매치 캐스트 블록(100)에는 상하 방향으로 관통 연장되는 블록 측 덕트가 매립될 수 있다. 또한, 단계 S11을 통해 제작되는 매치 캐스트 블록(100)의 하면에는 기초부(150)의 시공을 위한 기초 철근이 삽입되는 하부 연결부가 매치 캐스트 블록(100)의 내측으로 함몰 형성될 수 있다.Referring to FIG. 14 , in step S11 (a), a match cast block 100 may be produced. Also, on the upper surface of the match cast block 100 manufactured in step S11 , an upper connection portion into which the reinforcing bar protrusions of the column segments are inserted may be formed by recessing the match cast block 100 . In addition, the block-side duct extending vertically through the match cast block 100 manufactured in step S11 may be embedded. In addition, on the lower surface of the match cast block 100 manufactured through step S11 , a lower connection portion into which a foundation reinforcing bar for construction of the foundation 150 is inserted may be formed by recessing into the match cast block 100 .

다음으로, 단계 S12에서는 (b) 매치 캐스트 블록(100)을 하측 거푸집으로 하여 복수 개의 기둥 세그먼트(200)를 제작할 수 있다. 또한, 단계 S12를 통해 제작되는 기둥 세그먼트(200)의 상면에는 상측에 배치되는 기둥 세그먼트(200)의 철근 돌출부(212)가 삽입되는 철근 연결부(211)가 함몰 형성될 수 있다. 또한, 단계 S12를 통해 제작되는 기둥 세그먼트(200)에는 하단이 기둥 세그먼트(200)의 하면으로부터 일부 하향 돌출되어 철근 돌출부(212)를 형성하는 주철근(210)이 매립될 수 있다.Next, in step S12 (b), a plurality of column segments 200 may be manufactured using the match cast block 100 as the lower formwork. In addition, a reinforcing bar connection part 211 into which the reinforcing bar protrusion 212 of the column segment 200 disposed on the upper side is inserted may be formed in a depression on the upper surface of the column segment 200 manufactured through step S12 . In addition, the main reinforcing bar 210 having the lower end protruding downward from the lower surface of the column segment 200 to form the reinforcing bar protrusion 212 may be embedded in the column segment 200 manufactured through step S12 .

또한, 본원의 일 실시예에 따르면, 단계 S12에서는 기둥 세그먼트(200)에 매립되는 주철근(210)이 상하 방향에 대하여 어느 일측으로 기울어지는 것이 방지되도록 주철근(210)의 상측 또는 철근 연결부(211)를 감싸 수평 방향으로 이동되지 않도록 고정하는 홀이 형성된 지그 구조체(240)가 배치될 수 있다. 여기서, 지그 구조체(240)는 상측 지그(241) 및 상측 지그(241)로부터 하측으로 간격을 두고 배치되는 하측 지그(242)를 포함할 수 있다.In addition, according to one embodiment of the present application, in step S12, the upper side of the main reinforcing bar 210 or the reinforcing bar connection part 211 to prevent the main reinforcing bar 210 embedded in the column segment 200 from inclining to either side with respect to the vertical direction. A jig structure 240 in which a hole is formed to surround and fix so as not to move in the horizontal direction may be disposed. Here, the jig structure 240 may include an upper jig 241 and a lower jig 242 disposed at an interval downward from the upper jig 241 .

다음으로, 단계 S13에서는 (c) 시공 현장에서 매치 캐스트 블록(100)을 기초로 기둥의 기초부(150)를 시공할 수 있다.Next, in step S13 (c), the base portion 150 of the column may be constructed based on the match cast block 100 at the construction site.

구체적으로, 단계 S13에서는 (c1) 시공되는 기초부(150)에 대응하여 앵커 프레임(151)을 배치할 수 있다. 또한, 단계 S13에서는 (c2) 앵커 프레임(151) 상에 매치 캐스트 블록(100)을 배치할 수 있다. 또한, 단계 S13에서는 (c3) 기초 철근을 하부 연결부(130)에 삽입하여 배근할 수 있다. 또한, 단계 S13에서는 (c4) 기초 철근 및 매치 캐스트 블록(100)을 포위하도록 배치되는 기초부 거푸집에 기초하여 콘크리트를 타설 및 양생하여 기초부(150)가 시공될 수 있다.Specifically, in step S13 (c1), the anchor frame 151 may be disposed to correspond to the foundation 150 to be constructed. Also, in step S13 (c2), the match cast block 100 may be arranged on the anchor frame 151 . In addition, in step S13 (c3) it can be reinforced by inserting the base reinforcement into the lower connection part 130 . In addition, in step S13 (c4), the foundation 150 may be constructed by pouring and curing concrete based on the foundation formwork disposed to surround the foundation reinforcement and the match cast block 100 .

다음으로, 단계 S14에서는 (d) 매치 캐스트 블록의 상면에 상기 복수 개의 기둥 세그먼트 중 어느 하나의 기둥 세그먼트를 배치할 수 있다. 여기서, 어느 하나의 기둥 세그먼트(200)는 하측 세그먼트(200a)일 수 있다.Next, in step S14 (d), any one of the plurality of pillar segments may be disposed on the upper surface of the match cast block. Here, any one of the pillar segments 200 may be the lower segment 200a.

구체적으로, 단계 S14는 하측에 위치한 매치 캐스트 블록(100)의 상부 연결부(110)에 대하여 상측에 위치한 어느 하나의 기둥 세그먼트(200)의 철근 돌출부(212)를 적어도 일부 삽입하는 형태로 어느 하나의 기둥 세그먼트(200)를 배치하는 것일 수 있다.Specifically, step S14 is a form of inserting at least a part of the reinforcing bar protrusion 212 of any one column segment 200 located on the upper side with respect to the upper connection part 110 of the match cast block 100 located on the lower side. It may be to arrange the column segment 200 .

또한, 본원의 일 실시예에 따르면, 단계 S14는 상부 연결부(110)의 상향 개구된 내측 공간에 그라우트(Grout)를 주입하고, 매치 캐스트 블록(100)과 어느 하나의 기둥 세그먼트(200)의 접합면에 대하여 에폭시(Epoxy)를 도포한 후, 어느 하나의 기둥 세그먼트(200)의 철근 돌출부(212)를 상부 연결부(110)에 삽입하는 방식으로 수행될 수 있다.In addition, according to an embodiment of the present application, in step S14, grout is injected into the upwardly opened inner space of the upper connection part 110, and the match cast block 100 and any one column segment 200 are joined. After applying epoxy to the surface, it may be performed in a manner of inserting the reinforcing bar protrusion 212 of any one of the pillar segments 200 into the upper connection part 110 .

다음으로, 단계 S15에서는 (e) 배치된 어느 하나의 기둥 세그먼트(200)의 상측에 나머지 기둥 세그먼트(200)를 순차적으로 적층할 수 있다.Next, in step S15 (e), the remaining pillar segments 200 may be sequentially stacked on top of any one of the arranged pillar segments 200 .

구체적으로, 단계 S15는 적층되는 기둥 세그먼트(200)의 철근 돌출부(212)를 하측에 배치된 기둥 세그먼트(200)의 철근 연결부(211)에 삽입하는 방식으로 나머지 기둥 세그먼트(200)를 순차적으로 적층할 수 있다.Specifically, in step S15, the remaining column segments 200 are sequentially stacked in such a way that the reinforcing bar protrusion 212 of the column segment 200 to be stacked is inserted into the reinforcing bar connection 211 of the column segment 200 disposed on the lower side. can do.

또한, 본원의 일 실시예에 따르면, 단계 S15는 하측에 배치된 기둥 세그먼트(200)의 철근 연결부(211)의 상향 개구된 내측 공간에 그라우트(Grout)를 주입하고, 하측에 배치된 기둥 세그먼트(200)와 적층되는 기둥 세그먼트(200)의 접합면에 대하여 에폭시(Epoxy)를 도포한 후, 적층되는 기둥 세그먼트(200)의 철근 돌출부(212)를 하측에 배치된 기둥 세그먼트(200)의 철근 연결부(211)에 삽입하는 방식으로 수행될 수 있다.In addition, according to an embodiment of the present application, step S15 is to inject a grout into the upwardly opened inner space of the reinforcing bar connection 211 of the column segment 200 disposed on the lower side, and the column segment disposed on the lower side ( After applying epoxy to the joint surface of the column segment 200 to be laminated with 200), the reinforcing bar protrusion 212 of the column segment 200 to be laminated is connected to the reinforcement of the column segment 200 disposed on the lower side It can be performed by inserting into (211).

다음으로, 단계 S16에서는 (f) 적층된 복수 개의 기둥 세그먼트(200) 각각의 세그먼트 측 덕트(220) 및 매치 캐스트 블록(100)의 블록 측 덕트(120)를 관통하도록 긴장재를 삽입하고 포스트 텐션을 수행할 수 있다. 여기서, 긴장재는 강연선 등을 포함할 수 있으며, 포스트 텐션에 의해 기둥 구조물(10)의 기둥-기초 간 일체화가 수행되는 것일 수 있다.Next, in step S16 (f) a tension member is inserted so as to penetrate the segment-side duct 220 of each of the stacked plurality of column segments 200 and the block-side duct 120 of the match cast block 100, and post tension is applied. can be done Here, the tension material may include a stranded wire and the like, and the integration between the pillars of the pillar structure 10 by the post tension and the foundations may be performed.

이와 관련하여, 본원에서 개시하는 세그먼트 플러그인 방식의 기둥 구조물 시공 방법에 의할 때, 철근 연결부(211) 및 철근 돌출부(212)를 이용하여 기둥 세그먼트(200) 각각에 대하여 매립되는 철근을 순차적으로 연결하는 방식(플러그인 방식)으로 기둥 세그먼트가 적층되고, 이후 기둥 세그먼트(200) 및 매치 캐스트 블록(100) 각각을 관통하여 연장되도록 형성되는 세그먼트 측 덕트(220) 및 블록 측 덕트(120)를 모두 통과하도록 삽입되는 긴장재를 통한 포스트 텐션이 후속하여 수행됨으로써, 가설시 안정성을 확보하면서도 휨 강도 및 내진 성능을 증가시킬 수 있으며, 접합부 소요 압축 응력 역시 도입될 수 있는 이점이 있다.In this regard, according to the segment plug-in type column structure construction method disclosed herein, the reinforcing bars embedded in each of the column segments 200 are sequentially connected using the reinforcing bar connection 211 and the reinforcing bar protrusion 212 . Column segments are stacked in such a way (plug-in method), and then pass both the segment-side duct 220 and the block-side duct 120 that are formed to extend through each of the column segments 200 and the match cast block 100 . By performing post-tensioning through the tension member inserted to do so, it is possible to increase the flexural strength and seismic performance while securing stability during construction, and there is an advantage that the compressive stress required for the joint can also be introduced.

특히, 본원에서 개시하는 세그먼트 플러그인 방식의 기둥 구조물 시공 방법은 철근 삽입 체결과 포스트 텐션을 조합한 시공 방식으로서, 포스트 텐션이 수행되지 않는 종래 시공 방식 대비 기둥 세그먼트 각각에 매립되는 주철근의 개수를 감소시켜 제작 비용을 저감할 수 있는 효과가 있다.In particular, the segment plug-in type column structure construction method disclosed herein is a construction method that combines rebar insertion and fastening and post tension, and reduces the number of main reinforcing bars embedded in each column segment compared to the conventional construction method in which post tension is not performed. There is an effect that can reduce the manufacturing cost.

상술한 설명에서, 단계 S11 내지 S16은 본원의 구현예에 따라서, 추가적인 단계들로 더 분할되거나, 더 적은 단계들로 조합될 수 있다. 또한, 일부 단계는 필요에 따라 생략될 수도 있고, 단계 간의 순서가 변경될 수도 있다.In the above description, steps S11 to S16 may be further divided into additional steps or combined into fewer steps, according to an embodiment of the present application. In addition, some steps may be omitted if necessary, and the order between steps may be changed.

전술한 본원의 설명은 예시를 위한 것이며, 본원이 속하는 기술분야의 통상의 지식을 가진 자는 본원의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.The foregoing description of the present application is for illustration, and those of ordinary skill in the art to which the present application pertains will understand that it can be easily modified into other specific forms without changing the technical spirit or essential features of the present application. Therefore, it should be understood that the embodiments described above are illustrative in all respects and not restrictive. For example, each component described as a single type may be implemented in a dispersed form, and likewise components described as distributed may be implemented in a combined form.

본원의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본원의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present application is indicated by the following claims rather than the above detailed description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present application.

10: 세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물
100: 매치 캐스트 블록
110: 상부 연결부
120: 블록 측 덕트
130: 하측 연결부
200: 기둥 세그먼트
201: 수평철근
210: 주철근
211: 철근 연결부
212: 철근 돌출부
220: 세그먼트 측 덕트
240: 지그 구조체
150: 기초부
151: 앵커 프레임
10: Column structure constructed based on the segment plug-in method
100: match cast block
110: upper connection part
120: block side duct
130: lower connection part
200: column segment
201: horizontal reinforcing bar
210: cast rebar
211: rebar connection
212: reinforcing bar overhang
220: segment side duct
240: jig structure
150: the base
151: anchor frame

Claims (12)

세그먼트 플러그인 방식의 기둥 구조물 시공 방법으로서,
(a) 매치 캐스트 블록을 제작하는 단계;
(b) 상기 매치 캐스트 블록을 하측 거푸집으로 하여 복수 개의 기둥 세그먼트를 제작하는 단계;
(c) 시공 현장에서 상기 매치 캐스트 블록을 기초로 기둥의 기초부를 시공하는 단계;
(d) 상기 매치 캐스트 블록의 상면에 상기 복수 개의 기둥 세그먼트 중 어느 하나의 기둥 세그먼트를 배치하는 단계; 및
(e) 상기 어느 하나의 기둥 세그먼트의 상측에 나머지 기둥 세그먼트를 순차적으로 적층하는 단계,
를 포함하고,
상기 매치 캐스트 블록의 상면에는 상기 기둥 세그먼트의 철근 돌출부가 삽입되는 상부 연결부가 함몰 형성되고,
상기 기둥 세그먼트의 상면에는 상측에 배치되는 기둥 세그먼트의 상기 철근 돌출부가 삽입되는 철근 연결부가 함몰 형성되고, 상기 기둥 세그먼트에는 하단이 상기 기둥 세그먼트의 하면으로부터 일부 하향 돌출되어 상기 철근 돌출부를 형성하는 주철근이 매립되고,
상기 (d) 단계는,
하측에 위치한 상기 매치 캐스트 블록의 상기 상부 연결부에 대하여 상측에 위치한 상기 어느 하나의 기둥 세그먼트의 상기 철근 돌출부를 적어도 일부 삽입하는 형태로 상기 어느 하나의 기둥 세그먼트를 배치하는 것인, 기둥 시공방법.
A method for constructing a column structure of a segment plug-in method, comprising:
(a) producing a match cast block;
(b) manufacturing a plurality of column segments using the match cast block as a lower formwork;
(c) constructing the base of the column on the basis of the match cast block at the construction site;
(d) disposing any one of the plurality of pillar segments on the upper surface of the match cast block; and
(e) sequentially stacking the remaining column segments on the upper side of any one column segment;
including,
An upper connection part into which the reinforcing bar protrusion of the column segment is inserted is recessed in the upper surface of the match cast block,
A reinforcing bar connection portion into which the reinforcing bar protrusion of the column segment disposed on the upper side is inserted is recessed in the upper surface of the column segment, and the lower end of the column segment protrudes partially downward from the lower surface of the column segment to form the reinforcing bar protrusion. buried,
Step (d) is,
The method of arranging any one of the pillar segments in the form of inserting at least a part of the reinforcing bar protrusion of the one of the pillar segments located on the upper side with respect to the upper connection part of the match cast block located on the lower side.
제1항에 있어서,
상기 (e) 단계는,
적층되는 기둥 세그먼트의 상기 철근 돌출부를 하측에 배치된 기둥 세그먼트의 상기 철근 연결부에 삽입하는 방식으로 상기 나머지 기둥 세그먼트를 순차적으로 적층하는 것인, 기둥 시공 방법.
According to claim 1,
Step (e) is,
How to sequentially stack the remaining column segments in such a way that the reinforcing bar projections of the column segments to be stacked are inserted into the reinforcing bar connections of the column segments disposed on the lower side, the column construction method.
제2항에 있어서,
상기 매치 캐스트 블록에는 상하 방향으로 관통 연장되는 블록 측 덕트가 매립되고,
상기 기둥 세그먼트에는 상기 블록 측 덕트에 대응되게 상하 방향으로 관통 연장되는 세그먼트 측 덕트가 매립되는 것인, 기둥 시공 방법.
3. The method of claim 2,
A block-side duct extending through the match cast block in the vertical direction is embedded;
In the column segment, a segment-side duct extending vertically to correspond to the block-side duct is embedded in the column segment.
제3항에 있어서,
(f) 적층된 상기 복수 개의 기둥 세그먼트 각각의 상기 세그먼트 측 덕트 및 상기 블록 측 덕트를 관통하도록 긴장재를 삽입하고 포스트 텐션을 수행하는 단계,
를 더 포함하는 것인, 기둥 시공 방법.
4. The method of claim 3,
(f) inserting a tension member to penetrate the segment-side duct and the block-side duct of each of the plurality of column segments stacked and performing post-tension;
Which will further include, the pillar construction method.
제2항에 있어서,
상기 (a) 단계에서, 상기 매치 캐스트 블록은 하부 연결부를 더 포함하도록 제작되고,
상기 (c) 단계는,
상기 기초부의 시공을 위한 기초 철근을 상기 하부 연결부에 삽입하여, 상기 기초부의 내부에 상기 매치 캐스트 블록이 매립되도록 하는 것인, 기둥 시공 방법.
3. The method of claim 2,
In step (a), the match cast block is manufactured to further include a lower connection part,
Step (c) is,
By inserting a foundation reinforcing bar for the construction of the foundation into the lower connection portion, so that the match cast block is embedded in the interior of the foundation, the pillar construction method.
제5항에 있어서,
상기 (c) 단계는,
(c1) 시공되는 상기 기초부에 대응하여 앵커 프레임을 배치하는 단계;
(c2) 상기 앵커 프레임 상에 상기 매치 캐스트 블록을 배치하는 단계;
(c3) 상기 기초 철근을 상기 하부 연결부에 삽입하여 배근하는 단계; 및
(c4) 상기 기초 철근 및 상기 매치 캐스트 블록을 포위하도록 배치되는 기초부 거푸집에 기초하여 콘크리트를 타설 및 양생하는 단계,
를 포함하는 것인, 기둥 시공 방법.
6. The method of claim 5,
Step (c) is,
(c1) disposing an anchor frame corresponding to the foundation to be constructed;
(c2) placing the match cast block on the anchor frame;
(c3) inserting the base reinforcement into the lower connecting portion to reinforce; and
(c4) pouring and curing concrete based on the foundation formwork arranged to surround the foundation reinforcement and the match cast block;
That comprising a, pillar construction method.
제1항에 있어서,
상기 (b) 단계는,
상기 기둥 세그먼트에 매립되는 주철근이 상하 방향에 대하여 어느 일측으로 기울어지는 것이 방지되도록 상기 주철근의 상측 또는 상기 철근 연결부를 감싸 수평 방향으로 이동되지 않도록 고정하는 홀이 형성된 지그 구조체를 배치하는 단계,
를 포함하는 것인, 기둥 시공 방법.
According to claim 1,
The step (b) is,
Disposing a jig structure formed with a hole for fixing the upper side of the main reinforcing bar or the reinforcing bar connection portion to prevent the main reinforcing bar embedded in the column segment from being inclined to one side with respect to the vertical direction so as not to move in the horizontal direction;
That comprising a, pillar construction method.
제7항에 있어서,
상기 지그 구조체는, 상측 지그 및 상기 상측 지그로부터 하측으로 간격을 두고 배치되는 하측 지그를 포함하는 것인, 기둥 시공 방법.
8. The method of claim 7,
The jig structure, the upper jig and the column construction method comprising a lower jig disposed at an interval downward from the upper jig.
제1항에 있어서,
상기 매치 캐스트 블록은, 상하 방향에 직교하는 면 방향을 기준으로 방사형으로 배치되는 복수 개의 상부 연결부 및 복수 개의 블록 측 덕트를 포함하고,
상기 기둥 세그먼트에는, 상기 복수 개의 상부 연결부에 대응하는 복수 개의 주철근 및 상기 복수 개의 블록 측 덕트에 대응하는 복수 개의 세그먼트 측 덕트가 각각 매립되는 것인, 기둥 시공 방법.
According to claim 1,
The match cast block includes a plurality of upper connection parts and a plurality of block-side ducts that are radially disposed with respect to a plane direction orthogonal to an up-down direction,
In the column segment, a plurality of main reinforcing bars corresponding to the plurality of upper connection parts and a plurality of segment-side ducts corresponding to the plurality of block-side ducts are respectively embedded, the column construction method.
세그먼트 플러그인 방식에 기반하여 시공되는 기둥 구조물로서,
기둥 세그먼트의 철근 돌출부가 삽입되는 상부 연결부 및 상하 방향으로 관통 연장되는 블록 측 덕트를 포함하는 매치 캐스트 블록; 및
하면으로부터 적어도 일부가 하향 돌출되어 상기 철근 돌출부를 형성하는 주철근 및 상기 블록 측 덕트에 대응되게 상하 방향으로 관통 연장되는 세그먼트 측 덕트가 매립되고, 상기 매치 캐스트 블록을 하측 거푸집으로 하여 제작되는 복수 개의 기둥 세그먼트,
를 포함하고,
상기 기둥 구조물은,
시공 현장에서 상기 매치 캐스트 블록을 기초로 기둥의 기초부를 시공하고, 상기 복수 개의 기둥 세그먼트 중 어느 하나의 기둥 세그먼트의 상기 철근 돌출부가 상기 매치 캐스트 블록의 상기 상부 연결부에 삽입되어 상기 기초부의 상면에 배치되고, 상기 어느 하나의 기둥 세그먼트의 상면에 나머지 기둥 세그먼트를 순차적으로 적층하는 방식으로 시공되는 것인, 기둥 구조물.
As a column structure constructed based on the segment plug-in method,
a match cast block including an upper connecting portion into which a reinforcing bar protrusion of a column segment is inserted, and a block-side duct extending through the upper and lower portions; and
The main reinforcing bar at least partially protruding downward from the lower surface to form the reinforcing bar protrusion and the segment-side duct extending through the block-side duct corresponding to the block-side duct are buried, and a plurality of pillars manufactured using the match cast block as the lower formwork segment,
including,
The pillar structure is
At a construction site, a foundation of a column is constructed based on the match cast block, and the reinforcing bar protrusion of any one of the plurality of column segments is inserted into the upper connection portion of the match cast block and disposed on the upper surface of the foundation And, the column structure will be constructed in such a way as to sequentially stack the remaining column segments on the upper surface of any one of the column segments.
제10항에 있어서,
상기 기둥 세그먼트의 상면에는 상측에 배치되는 기둥 세그먼트의 상기 철근 돌출부가 삽입되는 철근 연결부가 함몰 형성되고,
상기 복수 개의 기둥 세그먼트는,
적층되는 기둥 세그먼트의 상기 철근 돌출부를 하측에 배치된 기둥 세그먼트의 상기 철근 연결부에 삽입하여 상기 나머지 기둥 세그먼트를 순차적으로 적층하는 방식으로 시공되는 것인, 기둥 구조물.
11. The method of claim 10,
A reinforcing bar connection portion into which the reinforcing bar protrusion of the column segment disposed on the upper side is inserted is recessed formed on the upper surface of the column segment,
The plurality of pillar segments,
By inserting the reinforcing bar projections of the column segments to be stacked into the reinforcing bar connection of the column segments disposed on the lower side, the column structure will be constructed in such a way that the remaining column segments are sequentially stacked.
제11항에 있어서,
적층된 상기 복수 개의 기둥 세그먼트 각각의 상기 세그먼트 측 덕트 및 상기 블록 측 덕트를 관통하도록 삽입된 후 포스트 텐션이 수행되는 긴장재,
를 더 포함하는 것인, 기둥 구조물.
12. The method of claim 11,
Tension material to which post tension is performed after being inserted so as to penetrate the segment-side duct and the block-side duct of each of the plurality of column segments stacked;
Which will further include, the column structure.
KR1020200137990A 2020-10-23 2020-10-23 Pillar construction method based on segment plug-in and pillar structure constructed by the same KR102418610B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200137990A KR102418610B1 (en) 2020-10-23 2020-10-23 Pillar construction method based on segment plug-in and pillar structure constructed by the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200137990A KR102418610B1 (en) 2020-10-23 2020-10-23 Pillar construction method based on segment plug-in and pillar structure constructed by the same

Publications (2)

Publication Number Publication Date
KR20220053812A true KR20220053812A (en) 2022-05-02
KR102418610B1 KR102418610B1 (en) 2022-07-06

Family

ID=81593445

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200137990A KR102418610B1 (en) 2020-10-23 2020-10-23 Pillar construction method based on segment plug-in and pillar structure constructed by the same

Country Status (1)

Country Link
KR (1) KR102418610B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116427269A (en) * 2023-05-22 2023-07-14 浙江中天恒筑钢构有限公司 Variable-section inclined tower column steel-concrete combined section double-layer anchoring structure and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH084031A (en) * 1994-06-17 1996-01-09 P S Co Ltd Building method of lower part structure
KR200392532Y1 (en) * 2005-05-06 2005-08-19 삼보지질 주식회사 Deep water column mesh of making and leaving for zig
KR20080073279A (en) * 2008-07-21 2008-08-08 (주)대우건설 Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe and reinforcing bar, and constructing method thereof
KR100895033B1 (en) * 2008-07-21 2009-05-04 지에스건설 주식회사 Precasr pier unit and pier construction method therewith
KR100920204B1 (en) * 2008-09-12 2009-10-06 (주)대우건설 Constructing method of precast pier footing for bridge
KR20150047917A (en) * 2013-10-25 2015-05-06 주식회사 대산시빌테크날러지 Precast pier construction method with enlarged base block
KR101980656B1 (en) * 2017-08-28 2019-05-22 중앙대학교 산학협력단 Construction method of precast concrete column
KR102151174B1 (en) * 2017-09-06 2020-09-02 지에스건설 주식회사 Joint for Precast Columns and Foundation

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH084031A (en) * 1994-06-17 1996-01-09 P S Co Ltd Building method of lower part structure
KR200392532Y1 (en) * 2005-05-06 2005-08-19 삼보지질 주식회사 Deep water column mesh of making and leaving for zig
KR20080073279A (en) * 2008-07-21 2008-08-08 (주)대우건설 Psc bridge pier assembled with precast concrete segments having steel duct and steel pipe and reinforcing bar, and constructing method thereof
KR100895033B1 (en) * 2008-07-21 2009-05-04 지에스건설 주식회사 Precasr pier unit and pier construction method therewith
KR100920204B1 (en) * 2008-09-12 2009-10-06 (주)대우건설 Constructing method of precast pier footing for bridge
KR20150047917A (en) * 2013-10-25 2015-05-06 주식회사 대산시빌테크날러지 Precast pier construction method with enlarged base block
KR101980656B1 (en) * 2017-08-28 2019-05-22 중앙대학교 산학협력단 Construction method of precast concrete column
KR102151174B1 (en) * 2017-09-06 2020-09-02 지에스건설 주식회사 Joint for Precast Columns and Foundation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116427269A (en) * 2023-05-22 2023-07-14 浙江中天恒筑钢构有限公司 Variable-section inclined tower column steel-concrete combined section double-layer anchoring structure and construction method thereof
CN116427269B (en) * 2023-05-22 2024-01-23 浙江中天恒筑钢构有限公司 Variable-section inclined tower column steel-concrete combined section double-layer anchoring structure and construction method thereof

Also Published As

Publication number Publication date
KR102418610B1 (en) 2022-07-06

Similar Documents

Publication Publication Date Title
JP6427045B2 (en) Reinforcement structure and reinforcement method of existing concrete structure
KR100932468B1 (en) Centrifugal precast concrete pile having hollow and construction method using the same, concrete and steel beam
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
KR101339946B1 (en) Precast bridge post
KR100862005B1 (en) Manufacturing method of segmental internally confined hollow concrete filled tube
KR101507924B1 (en) Structure and method of constructing concrete footing structure of top structure
KR102418610B1 (en) Pillar construction method based on segment plug-in and pillar structure constructed by the same
KR20140109587A (en) Precast Pier and Construction Method
KR102142633B1 (en) Accelerated construction method of integral abutment bridge and chambered precast segment wall applied to the same
CN210827834U (en) Assembled reinforced concrete beam column connection structure
JP7158231B2 (en) Composite column, bridge pier using same, construction method
KR102200400B1 (en) Precast segment, pillar structure including the same and construction method of pillar structure usinging the same
KR100555046B1 (en) A tunnel structure and method for constructing of it
KR102640952B1 (en) Pillar construction method based on segment plug-in and pillar structure constructed by the same
KR102235873B1 (en) Fabrication method of partial pier cap, partial pier cap, and construction method of pier using partial pier cap
KR102213216B1 (en) Construction method for precast column structure and precast column structure
JP2001059360A (en) Earthquake resisting wall, and earthquake resistant reinforcing construction method for existing building
JP2831934B2 (en) How to build substructure
KR101913782B1 (en) Construction method of bridge without temporary bridge
KR20060023915A (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
JP5979597B2 (en) PC breakwater, its construction method, and PCLNG tank construction method using the same
JPH1096210A (en) Method of executing enlargement of bridge pier
JP2000297480A (en) Reinforcing method for steel-pipe structure column base section
KR101278151B1 (en) Prestressed precast segment rahmen-bridge
KR101621657B1 (en) Rahmen system advanced efficiency by plastic hinge/additional prestressing strand and precast girder unit manufacturing thereof and method constructing Rahmen bridge thereof

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant