KR20190061195A - Pillar reinforcement method of parking lot structure for residential use - Google Patents

Pillar reinforcement method of parking lot structure for residential use Download PDF

Info

Publication number
KR20190061195A
KR20190061195A KR1020170159306A KR20170159306A KR20190061195A KR 20190061195 A KR20190061195 A KR 20190061195A KR 1020170159306 A KR1020170159306 A KR 1020170159306A KR 20170159306 A KR20170159306 A KR 20170159306A KR 20190061195 A KR20190061195 A KR 20190061195A
Authority
KR
South Korea
Prior art keywords
pillar
reinforcing
column
reinforcement
forming step
Prior art date
Application number
KR1020170159306A
Other languages
Korean (ko)
Other versions
KR102157205B1 (en
Inventor
왕도현
탁영준
Original Assignee
왕도현
탁영준
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 왕도현, 탁영준 filed Critical 왕도현
Priority to KR1020170159306A priority Critical patent/KR102157205B1/en
Publication of KR20190061195A publication Critical patent/KR20190061195A/en
Application granted granted Critical
Publication of KR102157205B1 publication Critical patent/KR102157205B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0604Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention relates to a method for reinforcing a pillar of a parking lot having a residential piloti structure, capable of preventing breakage of a parking lot pillar even if the ground is shaken. According to the present invention, the method for reinforcing a pillar of a parking lot having a residential piloti structure comprises a base layer making step (S100), a base layer forming step (S200), a vertical pillar making step (S300), a metallic reinforcement body assembly step (S400), and a parking lot pillar forming step (S500).

Description

주택용 필로티구조의 주차장 기둥 보강공법 {Pillar reinforcement method of parking lot structure for residential use} BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a parking lot structure for residential use,

본 발명은 주택용 필로티구조의 주차장 기둥 보강공법에 관한 것으로, 보다 상세하게는 주택용 필로티구조를 갖는 건축물의 주차장 콘크리트기둥을 금속보강체 내부에 구성하는 방법을 제공하여 지반의 흔들림에도 주차장 기둥의 파손을 방지할 수 있도록 발명한 것이다.More particularly, the present invention provides a method of constructing a parking concrete column of a building having a residential pilotty structure inside a metal reinforcement, thereby preventing damage to the parking pillar due to the rocking of the ground. The present invention has been achieved.

일반적으로, 필로티구조의 건축물은 기초를 이루는 바닥면으로부터 일정 높이로 설치되는 복수개의 수직 기둥체로 상부 구조물을 지탱하면서, 상기 수직 기둥체의 높이에 따라 지상층 공간을 확보하여, 여기에 보행자나 차량의 통행공간과 주차공간으로 활용하고 있어 일반 다가구 주택이나 아파트와 같은 공동 건물에 많이 적용하고 있는 구조이다.Generally, a building having a pilotty structure supports an upper structure with a plurality of vertical columns installed at a predetermined height from a floor surface of a foundation, secures a ground floor space according to the height of the vertical column, It is used as a traffic space and a parking space, and it is applied to common buildings such as multi-family houses and apartments.

그러나, 아파트와 같은 공동 건물의 필로티구조는 건축물의 기초가 되는 수직 기둥체가 지중의 단단한 암반에 고정되면서 기본적으로 내진설계기준에 따라 건축되어 지진 등의 외력에도 내진성능을 갖추고 있는데 반해, 다세대, 다가구 주택의 필로티구조에는 내진설계기준이 없는 상태에서 수직 기둥체가 지중의 기초콘크리트를 통해 연결된 철골에 콘크리트를 타설 및 양생하여 형성함으로서, 수직기둥체가 지반의 수평 및 수직 흔들림에 쉽게 휘어지거나 부러지면서 주택이 무너지는 등의 문제점이 있었다.However, the pilotty structure of a common building such as an apartment is basically constructed according to the earthquake-proof design standard, while the vertical column which is the base of the building is fixed to the hard rock bed in the ground and has seismic performance against an external force such as an earthquake, The vertical structure of the house is constructed by pouring and curing the concrete in the steel frame connected with the foundation concrete through the vertical under the condition that there is no earthquake-proof design standard, so that the vertical column easily buckles or breaks in the horizontal and vertical shakes of the ground, There was a problem such as collapse.

또한, 주택에서 차량의 주차공간으로 활용하고 있어 차량과의 충돌이 빈번하여, 주차장 기둥에 충격이 전달되어 크랙이 발생되거나 콘크리트가 떨어져 내부 철근이 노출되는 등의 문제점이 있었다.In addition, since it is utilized as a parking space of a vehicle in a house, a collision with a vehicle is frequent, and a shock is transmitted to a parking pillar to cause a crack, or a concrete is dropped and an inner reinforcing bar is exposed.

[특허문헌 1]. 대한민국 등록특허공보 제10-1209363호 에이치형강 기둥의 내진보강용 콘크리트 블록 및 이를 이용한 내진보강방법 (등록일자 2012년12월06일)[Patent Document 1]. Korean Registered Patent No. 10-1209363 A concrete block and a seismic retrofit method using the steel of the present invention for an advanced steel column (Registration date: December 06, 2012)

상기와 같은 종래기술의 문제점을 해결하기 위한 것으로서, 본 발명은 주택용 필로티구조의 주차장을 구성하는 콘크리트 기둥을 금속보강체 내부에서 양생되게 하여, 주차장기둥의 변형이나 손상을 방지할 수 있도록 하는데 그 목적이 있다.In order to solve the problems of the conventional art as described above, the present invention is intended to prevent the concrete pillars constituting the parking lot structure for residential use from being cured inside the metal reinforcement member, .

본 발명의 다른 목적은, 주차장기둥의 뼈대인 철근을 금속보강체의 내부에 설치하여, 거푸집 설치 및 철거에 따른 공사기간 및 시간의 지연을 방지해 건축시공에 따른 비용을 절감할 수 있도록 하는데 있다.It is another object of the present invention to provide a metal reinforcing member, which is a skeleton of a parking pillar, in the interior of a metal reinforcement to prevent a construction period and a time delay due to installation and removal of a mold, .

이와 같은 기술적 과제를 해결하기 위해 본 발명은, According to an aspect of the present invention,

건축물의 크기에 맞게 종방향 및 횡방향의 기초철근을 배근하고, 둘레를 따라서 거푸집을 형성하는 기초층 제작단계(S100)와;A base layer forming step (S100) of arranging vertical reinforcing bars in the longitudinal and transverse directions according to the size of the building and forming a mold along the peripheries;

상기 기초층 제작단계(S100)를 통해 형성된 거푸집 내에 콘크리트를 타설 및 양생하는 기초층 형성단계(S200)와; A base layer forming step (S200) of placing and curing concrete in the mold formed through the base layer forming step (S100);

기초층(10)의 기초철근에서 연장된 복수개의 기둥철근(21)을 수직방향으로 배근하고, 상기 수직방향의 기둥철근(21) 내주면에 복수개의 늑근고정링(30)이 일정간격을 두고 일체 구비되는 수직기둥 제작단계(S300)와;A plurality of columnar reinforcing bars (21) extending from a foundation reinforcing bar of a foundation layer (10) are vertically arranged and a plurality of retaining rings (30) are integrally formed on the inner circumferential surface of the columnar reinforcing bars A vertical column manufacturing step (S300);

보강기둥(41)은 중공형 금속 파이프 형상을 갖고 하단에 받침플랜지(42)가 구비된 금속보강체(40)가, 상기 기둥철근(21)을 내부에 수용하면서 기초층(10)에 받침플랜지(42)를 안착되어 앵커볼트(43)를 이용해 상기 기초층(10)에 고정되는 금속보강체 조립단계(S400)와;The reinforcing column 41 has a hollow metallic pipe shape and a metal reinforcing member 40 provided with a receiving flange 42 at the lower end of the reinforcing column 41 supports the base flange 10, (S400) of mounting the metal reinforcement member (42) on the base layer (10) by using the anchor bolt (43);

상기 금속보강체(40)의 상부에서 기둥철근(21)의 늑근고정링(30)을 통해 콘크리트주입관(F)을 기둥철근(21)의 하단까지 삽입한 다음 상기 콘크리트주입관(F)을 승강 이동시키면서 콘크리트를 타설하여 금속보강체(40)의 보강기둥(41) 내에 콘크리트를 타설 및 양생하는 주차장 기둥 형성단계(S500)를 포함해 구성된다.The concrete injection pipe F is inserted into the lower end of the pillar reinforcement 21 through the retaining ring 30 of the pillar reinforcement 21 at the upper part of the metal reinforcement 40, And a parking pillar forming step (S500) in which the concrete is poured into the reinforcing pillar (41) of the metal reinforcement body (40) by pouring the concrete while moving up and down.

또, 금속보강체(40)의 보강기둥(41)은, 기둥철근(21)이 내부에 수용되는 중공부를 갖으면서 원형, 사각형, 육각형, 팔각형 중에서 어느 하나의 형상으로 제작되며, 주차장 기둥 형성단계(S500) 이후에 상기 보강기둥(41)의 형상에 대응하는 끼움홀(47a)을 갖는 상판플랜지(47)가 상기 보강기둥(41)에 더 끼워진 상태에서 1층 천장벽면에 고정하는 보강기둥 상단 고정단계(S700)가 더 포함된다.The reinforcing pillars 41 of the metal reinforcement member 40 are formed into any one of a circular shape, a square shape, a hexagonal shape, and an octagonal shape with a hollow portion in which the pillar reinforcing bars 21 are accommodated, The upper plate flange 47 having the fitting hole 47a corresponding to the shape of the reinforcing column 41 is inserted into the reinforcing column 41 and the reinforcing column upper end The fixing step S700 is further included.

또한, 주차장 기둥 형성단계(S500) 이후에 금속보강체(40)의 받침플랜지(42) 및 앵커볼트(43)의 선단이 매립되게 바닥층(50)을 형성하는 주차장 바닥 형성단계(S600)가 더 포함된다.The parking lot bottom forming step S600 in which the bottom layer 50 is formed so that the front ends of the receiving flange 42 and the anchor bolt 43 of the metal reinforcement 40 are embedded after the parking pillar forming step S500, .

그리고, 수직기둥 제작단계(S300)에서 수평방향의 수평늑근(22)이 수직방향의 기둥철근(21) 외주면을 감싸며 일정간격을 두고 연속 조립되게 하여 달성한다.In the vertical column manufacturing step S300, the horizontal horizontal shelf 22 is continuously assembled at regular intervals while surrounding the outer peripheral surface of the vertical pillar 21 in the vertical direction.

이러한 본 발명에 의하면, 주택용 필로티구조의 주차장 기둥을 금속보강체 내부에 양생되게 함으로서, 차량 주차 등에 따른 주차장 기둥의 손상을 방지할 수 있고 지진 등의 흔들림에도 주차장기둥이 휘어지거나 부러지는 등의 파손을 방지할 수 있어 안전성을 극대화시킬 수 있다.According to the present invention, it is possible to prevent damage to the parking pillar due to parking of the vehicle by curing the parking pillar of the residential pilotage structure inside the metal reinforcement, and to prevent damage such as bending or breaking of the parking pillar It is possible to maximize safety.

또한, 주차장 기둥을 형성하기 위한 거푸집을 설치하지 않고 금속보강체에 직접 콘크리트를 타설할 수 있어 공사기간을 단축시켜 건축시공 효율을 증대시킬 수 있는 효과 등도 있다.In addition, it is possible to place concrete directly on the metal reinforcement body without installing a mold for forming a parking pillar, thereby reducing the construction period and increasing the construction efficiency.

도 1은 본 발명이 적용된 필로티 구조의 주차장 기둥 단면도.
도 2a 내지 도 2f는 본 발명인 주택용 필로티구조의 주차장 기둥 보강공법을 설명하기 위한 단면도.
도 3은 본 발명인 주택용 필로티구조의 주차장 기둥 보강공법의 순서도.
1 is a sectional view of a parking lot of a pilotty structure to which the present invention is applied;
Figs. 2A to 2F are sectional views for explaining a parking pillar reinforcement method for a residential pilotty structure according to the present invention. Fig.
3 is a flow chart of a parking pillar reinforcement method for a residential pilotty structure according to the present invention.

본 발명은 주택용 필로티구조의 주차장 기둥 보강공법은, 주택용 필로티구조를 갖는 건축물의 주차장 콘크리트기둥을 금속보강체 내부에 구성하는 방법을 제공하여 지반의 흔들림에도 주차장 기둥의 파손을 방지할 수 있도록 발명한 것이다.The parking lot reinforcing method for a residential pilotty structure provides a method for constructing a parking concrete column of a building having a residential pilotty structure inside a metal reinforcement body so as to prevent breakage of a parking pillar will be.

이하, 본 발명에 따른 주택용 필로티구조의 주차장 기둥 보강공법에 대해 첨부된 도면을 참고로 하여 상세히 기술되는 실시 예들에 의해 그 특징들을 이해할 수 있을 것이다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the present invention will be described in detail with reference to the attached drawings, with reference to the parking pillar reinforcement method for residential pilots.

먼저, 본 발명은 도 1 내지 도 3에서와 같이 다세대, 다가구와 같은 주택용 필로티구조에서 1층 주차장 기둥의 보강을 위한 것으로서, 상기 주차장 기둥을 금속보강체 내에서 타설 및 양생되게 함으로서 주차장 기둥의 강성유지 및 이에 따른 지진발생 시에도 주택의 파손을 방지토록 한다.1 to 3, the present invention is for reinforcement of a first-floor parking pillar in a residential pilotty structure such as a multi-family building or a multi-family building, wherein the parking pillar is poured and cured in a metal reinforcement, And to prevent damage to the house even when an earthquake occurs.

이를 위해, 주차장 기둥을 보강하는 공법을 제시한 것으로, 먼저 도 2a와 같이 기초층 제작단계(S100)를 통해서 건축물의 크기에 맞게 종방향 및 횡방향의 기초철근을 배근하고, 둘레를 따라서 거푸집을 형성한다.As shown in FIG. 2A, the foundation reinforcement is longitudinally and transversely aligned with the size of the building through the foundation layer forming step (S100) .

기초층 형성단계(S200)는, 상기 제작된 거푸집 내에 콘크리트를 타설 및 양생하고 둘레를 따라 형성된 거푸집을 제거하는 것으로, 상기 기초층(10)을 형성하기 위한 공법은 일반적으로 다세대 및 다가구 주택을 건설하기 위한 공지의 단계이므로 더 이상의 자세한 설명은 생략하기로 한다.In the base layer forming step S200, the concrete is poured and cured in the manufactured mold, and the molds formed along the periphery are removed. The method for forming the base layer 10 generally includes the steps of constructing multi- And the detailed description thereof will be omitted.

이때, 기초층 제작단계(S100) 및 기초층 형성단계(S200)에서 후술되는 금속보강체(40)의 고정을 위해 기초층(10) 및 지반에 고정되는 앵커볼트(43)의 체결단부가 기초층(10)의 상부로 돌출되게 하며, 상기 앵커볼트(43)는 기초층(10)의 형성 이후에도 설치가 가능하다.At this time, in order to fix the metal reinforcement member 40 to be described later in the base layer forming step (S100) and the base layer forming step (S200), the fastening end portions of the base layer 10 and the anchor bolts So that the anchor bolts 43 can be installed even after the formation of the base layer 10.

또, 상기 기초층 제작단계(S100)에서 도 2b와 같이 주택설계도면에 따라 기초층(10)의 기초철근에 연장하여 복수개의 기둥철근(21)을 수직방향으로 배근하는 수직기둥 제작단계(S300)가 포함되는데, 본 발명은 상기 수직방향의 기둥철근(21) 내주면에 복수개의 늑근고정링(30)이 일정간격을 두고 일체 구비되게 한다.In the base layer forming step S100, as shown in FIG. 2B, a vertical column forming step S300 (see FIG. 2) for extending the base reinforcing bars of the foundation layer 10 and arranging the plurality of column reinforcing bars 21 in the vertical direction In the present invention, a plurality of telescoping rings 30 are integrally formed on the inner circumferential surface of the vertical pillar reinforcement 21 at regular intervals.

즉, 늑근고정링(30)의 외주면에 기둥철근(21)이 일체로 접하도록 용접 또는 철사로 고정하여 수직방향의 기둥철근(21)에 일정간격을 갖고 복수개가 구비되어 후술(後述)되는 콘크리트주입관(F)의 이동로가 형성되게 한다.That is, a plurality of pillar reinforcing bars (30) are provided at regular intervals in the vertical pillar reinforcement (21) by welding or wire fixing so that the pillar reinforcing bars (21) come into contact with the outer peripheral surface of the retaining ring (30) So that the path of the injection tube F is formed.

그리고, 수직기둥 제작단계(S300)에서, 수직방향의 기둥철근(21) 외주면을 수평방향으로 감싸는 수평늑근(22)이 일정간격을 두고 연속 조립되게 하여 기둥의 강성을 더욱 증대시키는 것도 바람직하다.In addition, in the vertical column manufacturing step (S300), it is preferable to further increase the rigidity of the column by horizontally assembling the horizontal supports (22) surrounding the outer peripheral surface of the columnar reinforcing bars (21) in the horizontal direction at regular intervals.

금속보강체 조립단계(S400)는, 도 2c와 같이 중공형(中孔形) 금속 파이프 형상을 갖는 보강기둥(41)이 상기 기둥철근(21)을 감싸도록 크레인장치를 이용해 기둥철근(21) 상부에서 하부방향으로 이동시켜, 상기 보강기둥(41) 하부에 더 구비된 받침플랜지(42)가 기초층(10)의 상면에 안정적으로 안착되도록 한다.In the metal reinforcing member assembling step S400, a reinforcing column 41 having a hollow metal pipe shape as shown in FIG. 2C is inserted into the column reinforcement 21 using a crane device so as to enclose the column reinforcement 21, So that the receiving flange 42 provided at the lower portion of the reinforcing column 41 stably stays on the upper surface of the base layer 10. [

이때, 기초층(10)의 상부에는 앵커볼트(43)의 체결단부가 돌출된 상태이므로 상기 받침플랜지(42)의 볼트구멍으로 상기 체결단부가 통과되게 한 다음 너트(미부호)로 고정함으로서 금속보강체(40)의 유동을 방지하고 안정적으로 고정할 수 있다.At this time, since the fastening end portion of the anchor bolt 43 is projected on the upper portion of the base layer 10, the fastening end portion is passed through the bolt hole of the receiving flange 42 and then fixed with a nut (not shown) It is possible to prevent the reinforcement member 40 from flowing and fix it stably.

따라서, 상기 보강기둥(41)의 내부에 기둥철근(21)이 수용되면서, 기초층(10)과는 받침플랜지(42) 및 앵커볼트(43)로 안정적으로 고정되는데, 여기에서 상기 기둥철근(21) 및 수평늑근(22)이 보강기둥(41)의 내면과 접촉되지 않고 그 사이에 콘크리트가 구비되게 설치하는 것이 바람직하다.Accordingly, the columnar reinforcing bar 41 is accommodated in the inside of the reinforcing column 41, and the base layer 10 is stably fixed to the supporting flange 42 and the anchor bolt 43, 21 and the horizontal shelter 22 are not in contact with the inner surface of the reinforcing column 41 but are provided with concrete therebetween.

그리고, 금속보강체(40)의 보강기둥(41)은, 기둥철근(21)이 내부에 수용되는 중공부를 갖으면서 원형, 사각형, 육각형, 팔각형 중에서 어느 하나의 형상으로 제작한데, 이를 통해 주차장기둥을 형성하기 위한 기둥철근(21)의 형상 및 늑근고정링(30)의 형상 변경에 용이하게 대응할 수 있다.The reinforcement column 41 of the metal reinforcement member 40 has a hollow portion in which the pillar reinforcement 21 is accommodated and is formed into any one of a circular shape, a square shape, a hexagonal shape, and an octagonal shape. It is possible to easily cope with the shape of the pillar reinforcement 21 and the shape of the retaining ring 30 to form the retaining ring 30.

주차장 기둥 형성단계(S500)는 도 2d 및 도 2e와 같이 금속보강체(40)의 상부에서 기둥철근(21)의 늑근고정링(30)을 통해 콘크리트주입관(F)을 기둥철근(21)의 하단까지 삽입한 다음 상기 콘크리트주입관(F)을 승강 이동시키면서 콘크리트를 타설하는 단계이다.The parking pillar forming step S500 is a step in which the concrete injection pipe F is inserted into the pillar reinforcement 21 through the retaining ring 30 of the pillar reinforcement 21 at the upper portion of the metal reinforcement 40 as shown in Figures 2d and 2e, And then the concrete is poured while the concrete injection pipe F is moved up and down.

즉, 콘크리트를 타설하기 위한 콘크리트주입관(F)이 늑근고정링(30)의 내경을 통해 안내되어 하단까지 용이하게 삽입될 수 있으면서, 상기 하단에서 상단으로 승강되면서 콘크리트주입관(F)을 통해 콘크리트가 타설 및 양생되어 콘크리트 내부의 중공층 형성을 방지할 수 있어 견고한 기둥의 형성이 가능하다.That is, the concrete injection pipe F for pouring concrete is guided through the inner diameter of the retaining ring 30 and can be easily inserted up to the lower end, while being lifted from the lower end to the upper end and being inserted through the concrete injection pipe F Concrete is poured and cured to prevent formation of a hollow layer in the concrete, so that a solid column can be formed.

그리고, 상기 주차장 기둥 형성단계(S500) 이후에는 상기 주차장 기둥과 배근되며 거푸집을 통해 2층을 구성하는 것은 이미 일반적으로 사용되고 있는 공지의 단계이므로 더 이상의 자세한 설명은 생략하기로 한다.In addition, after the parking pillar forming step S500, forming the two-layer structure through the molding pillar and the parking pillar is a well known step that is generally used, and thus a detailed description thereof will be omitted.

여기에서, 본 발명은 상기 주차장 기둥 형성단계(S500) 이후에 보강기둥 상단 고정단계(S700)를 더 추가하는 것도 가능하며, 이는 상기 보강기둥(41)의 형상에 대응하는 끼움홀(47a)을 갖는 상판플랜지(47)를 구비하여, 상기 보강기둥(41)에 상판플랜지(47)를 더 끼워조립한 상태에서, 2층 구조물의 바닥면 즉 1층 천장벽면에 상기 상판플랜지(47)를 앵커볼트 등으로 고정하여 보강기둥(41)의 상단을 더욱 보강하도록 한 단계이다.In the present invention, it is also possible to further add the reinforcing column top fixing step (S700) after the parking pillar forming step (S500), and the fitting hole (47a) corresponding to the shape of the reinforcing pillar (41) And the upper plate flange 47 is attached to the bottom surface of the two-layer structure, that is, the ceiling wall of the first layer, with the anchor plate 47 having the upper plate flange 47, Bolts or the like so as to further reinforce the upper end of the reinforcing column 41. As shown in Fig.

또한, 주차장 기둥 형성단계(S500) 이후에 도 2f와 같이 금속보강체(40)의 받침플랜지(42) 및 앵커볼트(43)의 선단이 매립되게 바닥층(50)을 형성하는 주차장 바닥 형성단계(S600)가 더 포함되는 것도 바람직하다.In the parking lot bottom forming step (S500), as shown in FIG. 2F, the bottom layer 50 is formed so that the ends of the receiving flange 42 and the anchor bolt 43 of the metal reinforcement 40 are buried S600) may be further included.

이상에서와 같이 상술한 실시 예는 본 발명의 가장 바람직한 예에 대하여 설명한 것이지만 상기 실시 예에만 한정되는 것은 아니며, 본 발명의 기술사상을 벗어나지 않는 범위 내에서 다양한 변형이 가능하다는 것은 당업자에게 있어서 명백한 것이다.Although the preferred embodiments of the present invention have been described for illustrative purposes, those skilled in the art will appreciate that various modifications, additions and substitutions are possible, without departing from the scope and spirit of the invention as disclosed in the accompanying claims. .

10. 기초층 21. 기둥철근
30. 늑근고정링 40. 금속보강체
41. 보강기둥 42. 받침플랜지
50. 바닥층
S100. 기초층 제작단계 S200. 기초층 형성단계
S300. 수직기둥 제작단계 S400. 금속보강체 조립단계
S500. 주차장기둥 형성단계 S600. 주차장 바닥 형성단계
S700. 보강기둥 상단 고정단계
10. Foundation layer 21. Pillar reinforcement
30. Retaining ring 40. Metal reinforcement
41. Reinforcing column 42. Support flange
50. Floor
S100. Base layer production step S200. Base layer forming step
S300. Vertical column making step S400. Metal reinforcement assembly phase
S500. Parking lot pillar formation step S600. Parking lot floor formation step
S700. Securing column top

Claims (4)

건축물의 크기에 맞게 종방향 및 횡방향의 기초철근을 배근하고, 둘레를 따라서 거푸집을 형성하는 기초층 제작단계(S100)와;
상기 기초층 제작단계(S100)를 통해 형성된 거푸집 내에 콘크리트를 타설 및 양생하는 기초층 형성단계(S200)와;
기초층(10)의 기초철근에서 연장된 복수개의 기둥철근(21)을 수직방향으로 배근하고, 상기 수직방향의 기둥철근(21) 내주면에 복수개의 늑근고정링(30)이 일정간격을 두고 일체 구비되는 수직기둥 제작단계(S300)와;
보강기둥(41)은 중공형 금속 파이프 형상을 갖고 하단에 받침플랜지(42)가 구비된 금속보강체(40)가, 상기 기둥철근(21)을 내부에 수용하면서 기초층(10)에 받침플랜지(42)를 안착되어 앵커볼트(43)를 이용해 상기 기초층(10)에 고정되는 금속보강체 조립단계(S400)와;
상기 금속보강체(40)의 상부에서 기둥철근(21)의 늑근고정링(30)을 통해 콘크리트주입관(F)을 기둥철근(21)의 하단까지 삽입한 다음 상기 콘크리트주입관(F)을 승강 이동시키면서 콘크리트를 타설하여 금속보강체(40)의 보강기둥(41) 내에 콘크리트를 타설 및 양생하는 주차장 기둥 형성단계(S500)를 포함해 구성되는 것을 특징으로 하는 주택용 필로티구조의 주차장 기둥 보강공법.
A base layer forming step (S100) of arranging vertical reinforcing bars in the longitudinal and transverse directions according to the size of the building and forming a mold along the peripheries;
A base layer forming step (S200) of placing and curing concrete in the mold formed through the base layer forming step (S100);
A plurality of columnar reinforcing bars (21) extending from a foundation reinforcing bar of a foundation layer (10) are vertically arranged and a plurality of retaining rings (30) are integrally formed on the inner circumferential surface of the columnar reinforcing bars A vertical column manufacturing step (S300);
The reinforcing column 41 has a hollow metallic pipe shape and a metal reinforcing member 40 provided with a receiving flange 42 at the lower end of the reinforcing column 41 supports the base flange 10, (S400) of mounting the metal reinforcement member (42) on the base layer (10) by using the anchor bolt (43);
The concrete injection pipe F is inserted into the lower end of the pillar reinforcement 21 through the retaining ring 30 of the pillar reinforcement 21 at the upper part of the metal reinforcement 40, And a parking pillar forming step (S500) of placing the concrete in the reinforcement column (41) of the metal reinforcement body (40) by placing the concrete while lifting and lowering the concrete .
청구항 1에 있어서, 금속보강체(40)의 보강기둥(41)은, 기둥철근(21)이 내부에 수용되는 중공부를 갖으면서 원형, 사각형, 육각형, 팔각형 중에서 어느 하나의 형상으로 제작되며, 주차장 기둥 형성단계(S500) 이후에 상기 보강기둥(41)의 형상에 대응하는 끼움홀(47a)을 갖는 상판플랜지(47)가 상기 보강기둥(41)에 더 끼워진 상태에서 1층 천장벽면에 고정하는 보강기둥 상단 고정단계(S700)가 더 포함됨을 특징으로 하는 주택용 필로티구조의 주차장 기둥 보강공법.The reinforcing column 41 of the metal reinforcement member 40 is formed in a shape of a circle, a quadrangle, a hexagon, or an octagon, having a hollow portion in which the columnar bar 21 is received, An upper plate flange 47 having a fitting hole 47a corresponding to the shape of the reinforcing column 41 is fixed to the ceiling wall of the first floor in a state of being further inserted into the reinforcing column 41 after the column forming step S500 And a step (S700) of fixing the upper end of the reinforced column is further included. 청구항 1에 있어서, 주차장 기둥 형성단계(S500) 이후에 금속보강체(40)의 받침플랜지(42) 및 앵커볼트(43)의 선단이 매립되게 바닥층(50)을 형성하는 주차장 바닥 형성단계(S600)가 더 포함됨을 특징으로 하는 주택용 필로티구조의 주차장 기둥 보강공법.The method as claimed in claim 1, further comprising: a parking lot floor forming step (S600) of forming a floor layer (50) so that the front ends of the receiving flange (42) and the anchor bolt (43) of the metal reinforcement (40) The parking lot reinforcing method for a residential pilotty structure is further provided. 청구항 1에 있어서, 수직기둥 제작단계(S300)에서 수평방향의 수평늑근(22)이 수직방향의 기둥철근(21) 외주면을 감싸며 일정간격을 두고 연속 조립되게 한 것을 특징으로 하는 주택용 필로티구조의 주차장 기둥 보강공법.
2. The method according to claim 1, wherein in the step of constructing the vertical pillar (S300), the horizontally-extending horizontal shelf (22) is continuously assembled at regular intervals while surrounding the outer peripheral surface of the vertical pillar Pillar Reinforcement Method.
KR1020170159306A 2017-11-27 2017-11-27 Pillar reinforcement method of parking lot structure for residential use KR102157205B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170159306A KR102157205B1 (en) 2017-11-27 2017-11-27 Pillar reinforcement method of parking lot structure for residential use

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170159306A KR102157205B1 (en) 2017-11-27 2017-11-27 Pillar reinforcement method of parking lot structure for residential use

Publications (2)

Publication Number Publication Date
KR20190061195A true KR20190061195A (en) 2019-06-05
KR102157205B1 KR102157205B1 (en) 2020-09-17

Family

ID=66845027

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170159306A KR102157205B1 (en) 2017-11-27 2017-11-27 Pillar reinforcement method of parking lot structure for residential use

Country Status (1)

Country Link
KR (1) KR102157205B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102218533B1 (en) 2019-09-16 2021-02-22 박정민 pillar structure
CN114809693A (en) * 2022-03-21 2022-07-29 重庆科技学院 High-load self-restraint reinforcing device for existing reinforced concrete column

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020085652A (en) * 2001-05-09 2002-11-16 주식회사 남영이엔씨 pier execution method of an light electric railway
KR101209363B1 (en) 2011-05-02 2012-12-06 서울시립대학교 산학협력단 Concrete block for seismic reinforcement of H-shaped column and seismic reinforcing method using the same
KR20130075995A (en) * 2011-12-28 2013-07-08 경희대학교 산학협력단 Lateral supporter, composite concrete column structure having the same, and constructing method thereeof
KR20130097385A (en) * 2012-02-24 2013-09-03 재단법인 포항산업과학연구원 Structure of reinforced columns by multi-layer steel plates
KR20150051290A (en) * 2013-11-01 2015-05-12 주식회사 포스코 Steel pipe system with fireproof coating and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020085652A (en) * 2001-05-09 2002-11-16 주식회사 남영이엔씨 pier execution method of an light electric railway
KR101209363B1 (en) 2011-05-02 2012-12-06 서울시립대학교 산학협력단 Concrete block for seismic reinforcement of H-shaped column and seismic reinforcing method using the same
KR20130075995A (en) * 2011-12-28 2013-07-08 경희대학교 산학협력단 Lateral supporter, composite concrete column structure having the same, and constructing method thereeof
KR20130097385A (en) * 2012-02-24 2013-09-03 재단법인 포항산업과학연구원 Structure of reinforced columns by multi-layer steel plates
KR20150051290A (en) * 2013-11-01 2015-05-12 주식회사 포스코 Steel pipe system with fireproof coating and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102218533B1 (en) 2019-09-16 2021-02-22 박정민 pillar structure
CN114809693A (en) * 2022-03-21 2022-07-29 重庆科技学院 High-load self-restraint reinforcing device for existing reinforced concrete column

Also Published As

Publication number Publication date
KR102157205B1 (en) 2020-09-17

Similar Documents

Publication Publication Date Title
KR101973701B1 (en) Assembling type pier
KR101355926B1 (en) Reusable waffle type slab form assembly
KR20190061195A (en) Pillar reinforcement method of parking lot structure for residential use
KR20230090300A (en) A twin wall structure using a PC panel and method for manufacturing of it
KR101401057B1 (en) Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed
JP5734168B2 (en) Building structure
KR101566528B1 (en) Basement extension construction method using underground structure
KR101750404B1 (en) Structure using same time pouring process for wall and foundation concrete and construction method therefor
JP5865567B2 (en) Connecting slab and its construction method
JP5131645B2 (en) Construction method of steel tower foundation
KR20170013009A (en) Method for constructing junction between the double wall Precast Concretes and the junction structure thereof, the construction method for underground parking using he double wall Precast Concrete, and construction method for the rainwater storage using he double wall Precast Concrete
JP4592497B2 (en) Prop base structure
KR101077971B1 (en) Elementary Block for Supporting of Steel Pipe
KR101730569B1 (en) Hybrid beam and constructing method for the same
KR102507299B1 (en) The construction method precast prestressed concrete parking buildings with precast concrete wall panels
KR101576215B1 (en) Prefabricated precast concrete girder for building construction
JP2018100488A (en) Base-isolation construction, base plate and method for construction of lower foundation member
JP2018096188A (en) Junction structure of seismic isolator to steel-pipe column, and base isolated building
KR101322581B1 (en) Spacer for fastening Reinforcement Bar and Hanger Bolt
JP5844579B2 (en) Tower structure
KR101692151B1 (en) A deck support frame
JP2008223242A (en) Manufacturing method for precast concrete panel
KR102634082B1 (en) Bracket reinforcement structure of hollow-core column and its construction method
KR102111883B1 (en) Construction Method of Transfer girder
JP6192286B2 (en) Evacuation building