KR20180049533A - Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment - Google Patents

Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment Download PDF

Info

Publication number
KR20180049533A
KR20180049533A KR1020160145558A KR20160145558A KR20180049533A KR 20180049533 A KR20180049533 A KR 20180049533A KR 1020160145558 A KR1020160145558 A KR 1020160145558A KR 20160145558 A KR20160145558 A KR 20160145558A KR 20180049533 A KR20180049533 A KR 20180049533A
Authority
KR
South Korea
Prior art keywords
steel
girder
vertical
precast
composite girder
Prior art date
Application number
KR1020160145558A
Other languages
Korean (ko)
Inventor
구민세
박영희
구호원
Original Assignee
구민세
구호원
박영희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 구민세, 구호원, 박영희 filed Critical 구민세
Priority to KR1020160145558A priority Critical patent/KR20180049533A/en
Publication of KR20180049533A publication Critical patent/KR20180049533A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The present invention relates to manufacture of a support manufacturing device which is capable of adjusting a height in accordance with a height of a steel girder changing in accordance with a span length of a precast prestressed (P.S.) composite girder and is easily assembled or disassembled to manufacture the precast P.S. composite girder. Since a precast P.S. composite girder is manufactured in a form of being placed on a steel bottom plate on a floor plate support, the manufacturing device has a simple structure and facilitates disassembly, thereby improving safety and economic efficiency. Also, since the disassembled manufacturing device is quickly moved to a manufacturing position of a next step to be used, construction is performed quickly and materials are reduced. Also, the precast P.S. composite girder is completed by fixing and settling the composite girder by tensioning a tension member on the manufactured position without a movement by heavy equipment.

Description

높이조절이 가능한 지점부 제작대를 이용하여 받치는 형태로 프리캐스트 P.S(Prestressed)강합성거더를 제작하는 방법{Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment}[0001] The present invention relates to a method of manufacturing a precasted P.S prestressed steel composite girder in the form of a support which is supported by means of a height-

본 발명은 프리캐스트 P.S거더의 일종인 프리캐스트 P.S강합성거더에 관한 것으로 프리캐스트 P.S강합성거더의 제작을 위한 지점부 제작대의 조립 및 해체가 용이하고 강재거더의 높이(크기)를 조절할 수 있도록 설계된 지점부 제작대의 제작 방법에 관한 것이다The present invention relates to a pre-cast PS steel composite girder which is a kind of precast PS girder and which can easily be assembled and disassembled for the production of precast PS steel composite girders and the height (size) of the steel girders can be adjusted And a manufacturing method of a designed branch part production base

지금까지의 프리캐스트 P.S강합성거더의 제작방법은 P.S강합성거더를 지점부 제작대의 상부에서 매다는 형식이었다. 상기 방법은 거더 및 거푸집의 하중이 제작대 상부에서 중력 반대 방향으로 지지되고 다시 지면으로 하중이 전달되는 형식이다. 본 발명에 의한 제작방법은 제작대의 바닥판받침에 제작된 프리캐스트 P.S강합성거더가 받혀지는 형식으로 거더 및 거푸집에 의한 하중이 중력 방향으로 직접 지면으로 전달되도록 설계되어 있다. 따라서 제작대의 구조가 간단해지고 거더의 받침을 위한 바닥판받침을 제외하고 제작대의 해체가 용이한 설계가 가능해진다. 따라서 해체된 제작대의 재활용이 신속히 이루어질 수 있다The precast P.S steel composite girders so far have been of the type in which the P.S steel composite girders are hung from the upper part of the fulcrum. This method is a type in which the loads of the girders and the formwork are supported in the opposite direction of gravity at the upper portion of the production stand and the loads are transmitted to the ground again. The manufacturing method according to the present invention is designed such that the load caused by the girder and the form is transmitted directly to the ground in the gravity direction in a form in which the precast P.S steel composite girder manufactured in the bottom plate support of the production stand is supported. Therefore, the structure of the fabrication stand becomes simple, and it is possible to design the fabrication stand to be easily disassembled except for the bottom plate support for the girder support. Thus, the recycling of disassembled fabrics can be done quickly

등록특허공보 제 10-0541965호Patent Registration No. 10-0541965 등록특허공보 제 10-0547619호Patent Registration No. 10-0547619

지금까지의 프리캐스트 P.S강합성거더의 제작방법은 지점부 제작대 상부에 거더가 매달리는 형식이다. 따라서 제작된 거더가 크레인에 의해 이동되기 전에는 지점부 제작대의 해체가 불가능하다. 또한 지점부 제작대는 견고히 지면에 기초되었고 같은 장소에서 계속적으로 거더를 제작하도록 설계되었다. 따라서 크레인을 이용하여 제작된 거더의 이동이 불가피하다. 이 방법은 제작 중 작용되는 강합성거더 케이싱 콘크리트의 자중이 중력 반대방향으로 되어 다시 지면으로 하중이 전달되는 매다는 형식인 만큼 구조적으로 복잡할 수밖에 없다. 여기서 프리캐스트 P.S강합성거더는 지면상에서 제작된 거더를 의미하며 강합성거더는 인장재에 인장응력을 도입하기 전의 상태를 말한다. 본 발명에서는 거더 및 거푸집에 의한 하중을 바닥판받침에 받치는 형태의 제작대를 이용하여 하중이 중력 방향으로 작용되도록 하므로 제작대 구조의 조립 및 해체를 단순화할 수 있다. 또한 강재거더의 높이에 따라 높이를 조절할 수 있는 제작대의 기능을 갖도록 설계할 수 있다. 그리고 거더를 받치는 바닥판받침을 제외한 제작대를 해체할 수 있도록 설계되어 있다. 또한 제작된 거더를 제작된 위치에 그대로 야적시키므로 크레인을 이용한 제작된 거더의 이동이 불필요하다. 그리고 제작된 장소에서 거더의 이동 없이 인장작업을 수행하여 프리캐스트 P.S강합성거더를 완성시킬 수 있다. 따라서 안전 및 경제성을 제고시킬 수 있고 급속시공이 가능하다So far, precast P.S steel composite girders are manufactured in such a way that the girders hang on the upper part of the fuselage. Therefore, before the manufactured girder is moved by the crane, it is impossible to dismantle the fascia part. In addition, the fuselage section is rigidly ground-based and is designed to continuously produce girders in the same location. Therefore, it is inevitable to move the girder manufactured using the crane. This method is structurally complicated because the weight of concrete composite girder casing concrete acting during construction is in the form of a hanging form in which the weight is transferred to the ground again in the direction opposite to gravity. Here, the precast P.S steel composite girder refers to the girder manufactured on the ground, and the steel composite girder refers to the state before tensile stress is introduced into the tensile material. In the present invention, since the load is applied in the direction of gravity by using a work platform in which the load by the girder and the form is supported on the bottom plate support, the assembly and disassembly of the work structure can be simplified. In addition, it can be designed to have the function of a height that can be adjusted according to the height of the steel girder. It is designed to dismantle the workbench except for the bottom plate supporting the girder. Also, since the fabricated girder is left in the fabricated position, the movement of the fabricated girder using the crane is unnecessary. The pre-cast P.S steel composite girder can be completed by tensioning without moving the girder at the place where it is manufactured. Therefore, safety and economical efficiency can be improved and rapid construction is possible

본 발명에서는 기존의 매다는 형식의 프리캐스트 P.S강합성거더의 지점부 제작대의 문제점을 개선하기 위하여 강합성거더와 거푸집의 하중이 바닥판받침에 직접 전달되는 형태로 설계하므로 제작대 구조를 간소화할 수 있다. 본 발명에 의한 프리캐스트 P.S강합성거더의 제작을 위한 그 첫 번째 단계로는 강재거더를 제작대 상부에서 지지될 수 있도록 하고 강재거더의 높이에 맞춰 강재거더 하부플랜지를 둘러싸는 형태의 거푸집을 거더 전 구간에 설치하고 케이싱 콘크리트를 타설·양생시킨다. 이렇게 제작된 거더를 강합성거더라 칭한다. 두 번째 단계로는 제작대 내부에 설치된 강재바닥판을 제외한 거더 전 구간의 거푸집을 탈형한다. 세 번째 단계로는 지점부 제작대 좌우에 유압잭 설치를 위한 또 다른 받침을 설치하고 받침 상에 설치된 유압잭의 머리부가 케이싱 콘크리트 하부에 직접 접촉됨에 따른 응력집중을 분산시키기 위해 보강재로 보강된 강판을 케이싱 콘크리트 하부와 유압잭의 접촉부 사이에 설치한다. 여기서 지점부 제작대 좌우에 설치되는 모든 유압잭의 상승력은 강재거더 및 케이싱 콘크리트의 자중에 꼭 맞도록 하여야 한다. 유압잭을 설치하는 이유는 지점부 제작대가 조립된 후 강재거더가 매달린 상태로 설치되므로 수직재들에 설치된 볼트에 강재거더 및 케이싱 콘크리트에 의한 하향력을 상쇄시킬 수 있는 상향력을 주기 위함이다. 따라서 강재거더 및 케이싱 콘크리트의 자중만큼의 상향력을 유압잭을 이용하여 작용시키므로 볼트의 해체가 용이해진다. 만일 유압잭의 상승력이 강재거더 및 케이싱 콘크리트의 자중보다 크게 되면 커진 힘만큼의 힘이 연결볼트에 작용되므로 볼트해체가 어려워질 수 있다. 강재거더와 케이싱 콘크리트의 자중은 지점부 제작대의 수직보강재(203)를 갖는 수직재와 수평지지판과 결합된 높이조절이 가능한 수직재와의 연결볼트에 작용된다. 하부케이싱 콘크리트의 타설을 위한 거푸집은 설치 후 3일 정도 후에 탈형하게 된다. 거푸집의 자중은 설치되고 다시 탈형되므로 유압잭에 대한 상승력 계산에서는 무시할 수 있다. 거푸집 탈형 후 지점부 제작대 해체를 위한 유압잭에 의한 케이싱 콘크리트에 작용되는 지압응력은 거푸집 제거에 의한 허용응력에 비해 미미한 값이고 상승력에 의한 강합성거더 중앙부에 발생되는 압축응력도 허용응력에 못 미친다. 따라서 거푸집 철거와 동시에 안전하게 제작대의 해체가 가능하다. 네 번째 단계로는 유압잭을 이용해 강재거더 하중에 상당되는 상향력을 가한 상태에서 제작대의 수평변위를 제어하는 제어봉과 바닥판받침 상에 설치된 강재바닥판과 수직보강재를 갖는 수직재의 연결볼트 및 수평지지판과 결합된 높이를 조절할 수 있는 수직재와 수직보강재를 갖는 수직재를 연결하는 볼트를 해체한다. 다섯 번째 단계로는 유압잭의 상승력을 유지시킨 상태에서 바닥판을 제외한 지점부 제작대를 해체한다. 그리고 그 위치에서 인장재를 인장시켜 압축력을 도입하므로 프리캐스트 P.S강합성거더가 완성된다. 이렇게 제작된 프리캐스트 P.S강합성거더는 제작된 위치에 그대로 야적시키고 해체된 제작대 및 거푸집과 유압잭은 다음의 제작 위치로 이동시켜 조립함으로써 시공의 신속성 및 경제성이 제고된다In the present invention, in order to solve the problems of the prefabricated PS steel composite girder of the existing hanging type, the load of the composite girder and the form is directly transferred to the bottom plate support, have. The first step for manufacturing the precast PS steel composite girder according to the present invention is to form a form in which the steel girder is supported at the upper portion of the worktable and the steel girder lower flange is surrounded by the height of the steel girder Installed in all sections and cast casing concrete. The girder thus produced is called a steel composite girder. The second step is to demold the formwork of the entire girder except the steel deck installed inside the building. In the third step, another support for installing the hydraulic jacks is provided on the left and right of the fuselage section, and a steel plate reinforced with a reinforcing material is disposed on the casing in order to disperse stress concentration due to direct contact of the head of the hydraulic jack installed on the fuselage with the lower portion of the casing concrete. It is installed between the lower part of concrete and the contact part of the hydraulic jack. Here, the lifting force of all hydraulic jacks installed on the left and right sides of the spigot part should be matched to the weight of the steel girder and casing concrete. The reason for installing the hydraulic jack is to provide an upward force that can offset the downward force caused by the steel girder and the casing concrete to the bolts installed on the vertical members since the steel girder is suspended after the branch part manufacturing assembly is assembled. Therefore, the upward force as much as the weight of the steel girder and the casing concrete is operated by using the hydraulic jack, so that the disassembly of the bolt becomes easy. If the lifting force of the hydraulic jack is larger than the self weight of the steel girder and the casing concrete, a force as large as the force acts on the connecting bolt, so that it may become difficult to disassemble the bolt. The weight of the steel girder and the casing concrete acts on the connecting bolt between the vertical member having the vertical stiffener 203 and the height adjustable vertical member combined with the horizontal supporting plate. The mold for casting the lower casing concrete is to be demolded about 3 days after installation. Since the weight of the form is installed and demolded again, it can be neglected in the calculation of lift force for the hydraulic jack. The compressive stress applied to the casing concrete by the hydraulic jack for the manufacture of the fuselage after demolishing the form is insignificant compared with the allowable stress due to form removal and the compressive stress generated at the center of the composite girder due to the upward force is less than the allowable stress. Therefore, it is possible to safely dismantle the production line at the same time as demolishing the formwork. In the fourth stage, a control rod is used to control the horizontal displacement of the workbench with an upward force corresponding to the load of the steel girder using a hydraulic jack, a connection bolt and a horizontal support plate of a vertical member having a steel bottom plate and a vertical stiffener installed on the bottom plate base And the bolts connecting vertical members with adjustable height and vertical members with vertical stiffeners are disassembled. In the fifth stage, with the elevation force of the hydraulic jack maintained, dismantle the production base of the branch excluding the bottom plate. Then, the tensile material is tensioned at that position to introduce the compressive force, so that the precast P.S steel composite girder is completed. The precast P.S steel composite girder manufactured in this way is stuck at the position where it is manufactured, and the disassembled workbench, formwork, and hydraulic jack are moved to the next production site and assembled to improve the speed and economy of construction

본 발명은 프리캐스트 P.S강합성거더를 바닥판받침에 받치는 형태로 설계하므로 제작대 구조를 간소화시킬 수 있다. 또한 제작대의 상부구조인 수평지지판과 결합된 수직재는 높이조절을 가능케하므로 프리캐스트 P.S강합성거더의 경간에 따라 달라지는 여러 형태의 강재거더에 적용시킬 수 있고 제작대의 조립 및 해체가 용이해지는 효과를 얻을 수 있다. 제작된 프리캐스트 P.S강합성거더는 이동 없이 제작된 위치에 야적시키므로 기존 방법에서의 거더 이동을 위한 중장비가 불필요하다. 바닥판받침을 제외하고 해체된 지점부 제작대는 다음 제작 위치로 곧바로 투입되므로 제작의 신속성 및 경제성이 확보된다. 만약 3개 조의 지점부 제작대 및 거푸집으로 시공하는 경우 매일 1개의 프리캐스트 강합성거더의 생산이 가능해진다. 단, 거푸집의 탈형이 콘크리트 타설 3일후에 시행되는 경우이다The present invention is designed to support the precast P.S steel composite girder on the bottom plate support, thus simplifying the construction of the structure. In addition, since the vertical member combined with the horizontal support plate, which is the upper structure of the production stand, can be adjusted in height, it can be applied to various types of steel girders that vary according to the span of the precast PS steel composite girder, and the assembly can be easily assembled and disassembled . Manufactured precast P.S Steel composite girder is located at the position where it is made without moving, so heavy equipment for girder movement in the existing method is unnecessary. Since the dismantled spigot part stand is directly put into the next production position except for the bottom plate stand, the production speed and economy are secured. If the construction is done with three sets of spigot parts and formwork, it is possible to produce one precast steel composite girder every day. However, the demolding of the form is carried out 3 days after the casting of concrete

도 1은 특허문헌에 의한 프리캐스트 P.S강합성거더가 지점부 제작대(100) 상부에 매달려있는 상태의 개념도가 나타나 있다.
도 2는 본 발명에 의한 프리캐스트 P.S강합성거더의 제작 순서도이다. 프리캐스트 P.S강합성거더는 2지점 상에서 지지되고 대칭이므로 도 2의 설명에서는 한쪽 지점부 제작대에 대해 다루기로 한다. 도 2a는 한 쪽의 지점부 제작대로서 수직보강재(203)를 갖는 수직재(202)와 수평지지판(207) 상에 강재거더가 얹혀진 상태가 도시되어 있다. 여기서 수평지지판(207)은 높이 조절을 위한 수직재(210)와 결합되어 있고 수직보강재(203)를 갖는 수직재(202)와의 연결을 위한 연결볼트(213)가 나타나 있다. 도 2b는 강재거더의 높이가 도 2a보다 Δ(209)만큼 높은 경우 지점부 제작대의 상부구조 즉, 수평지지판(207)과 결합된 수직재(210)가 Δ만큼 상향으로 변위되어 수직보강재를 갖는 수직재(203)와 연결된 상태를 나타내고 있다. 도 2c는 도 2a의 상태에서 케이싱 콘크리트(208)가 타설되고 케이싱 콘크리트를 인장하여 압축력의 도입을 위한 인장재 또는 쉬스관(214)이 도시되어 있다. 도 2d는 지점부 제작대의 용이한 해체를 위해 하향으로 작용되는 강재거더 및 케이싱 콘크리트 자중에 상응되는 상향력을 작용시키기 위해 지점부 제작대의 바닥판받침(206) 좌우에 설치된 또 다른 받침(216)과 케이싱 콘크리트(208)에 작용되는 응력의 분산을 위한 강판(218) 사이에 설치된 유압잭(217)과 유압잭에 의한 상승력을 가한 상태에서 모든 연결볼트가 해체된 상태가 나타나 있다. 도 2e는 수직보강재(203)와 결합된 수직재(202)의 수평변위를 제어하는 제어봉(201) 설치를 위한 수직재 상부가 열려있는 형태의 흠(211)과 수직보강재를 갖는 수직재(202) 측면에 수평지지판과 결합된 수직재와의 볼트연결을 위한 볼트구멍(211)이 나타나있는 지점부 제작대의 측면도이다. 도 2f는 거푸집 제거 후 바닥판받침(206)을 제외한 지점부 제작대가 해체되고 강합성거더가 바닥판받침(206)에 얹혀진 상태를 나타내고 있다. 또한 이 때 바닥판받침 좌우에 설치되었던 받침(216)과 유압잭(217) 및 강판(218)은 철거된다. 이 상태에서 강재를 인장하여 고정·정착시키면 프리캐스트 P.S강합성거더가 완성된다.
도 3은 강합성거더가 바닥판받침(206)에 얹혀진 상태를 나타내고 있다
1 is a conceptual diagram of a state in which a precast PS steel composite girder according to the patent document is suspended on an upper part of the fascia producing stand 100.
Fig. 2 is a flowchart showing the production process of a precast PS steel composite girder according to the present invention. Since the precast PS steel composite girder is supported on two points and is symmetrical, the description of Fig. 2A shows a state in which a steel girder is placed on a vertical member 202 having a vertical stiffener 203 and a horizontal support plate 207 as one fulcrum member production stand. The horizontal support plate 207 is connected to the vertical member 210 for height adjustment and a connection bolt 213 for connection with the vertical member 202 having the vertical stiffener 203 is shown. FIG. 2B shows a vertical structure 210, which is coupled with the horizontal support plate 207, when the height of the steel girder is higher than that of FIG. 2A by Δ (209) (203). FIG. 2C shows a tensile material or sheath tube 214 for the introduction of compressive force by placing the casing concrete 208 in the state of FIG. 2A and pulling the casing concrete. FIG. 2d shows another support 216 installed on the left and right of the bottom plate support 206 of the fulcrum part manufacturing stand to apply an upward force corresponding to the self weight of the casing concrete and the downwardly acting steel girder for easy disassembly of the fulcrum part, And a hydraulic jack 217 provided between the steel plate 218 for dispersing the stress acting on the casing concrete 208 and a state in which all of the connection bolts are disassembled in a state where a lift force is applied by the hydraulic jack. 2E is a side view of a vertical member 202 having vertical stiffeners 203 and a vertical stiffener 202 having a vertical stiffener 211 and a vertical stiffener 202. The horizontal stiffener 203 has a vertical stiffener 203, And a bolt hole 211 for bolt connection with a vertical member coupled with the horizontal support plate. FIG. 2F shows a state in which after removing the form, the fulcrum assembly base except for the bottom plate support 206 is disassembled and the composite steel girder is placed on the bottom plate support 206. FIG. At this time, the pedestal 216, the hydraulic jack 217, and the steel plate 218, which are installed on the left and right sides of the bottom plate support, are removed. In this state, when the steel material is pulled and fixed and fixed, a precast PS steel composite girder is completed.
3 shows a state in which the steel composite girder is placed on the bottom plate support 206

이하에서는 본 발명의 실시 예를 첨부 도면을 이용하여 상세히 설명한다. 이하에 소개되는 실시 예들은 본 발명이 속하는 기술분야에서 통상의 지식을 가진 기술자에게 본 발명의 내용이 충분히 전달될 수 있도록 하기 위해 실시 예로써 서술되는 것이다. 본 발명은 이하 설명되는 실시 예들에 한정되지 않고 다른 형식으로 구체화될 수도 있다. 본 발명을 명확하게 설명하기 위해 설명과 관계없는 부분은 도면에서 생략하였으며 도면들에 있어서 구성요소의 폭, 길이, 두께 등은 편의를 위해 과장되어 표현될 수 있다. 명세서 전체에 걸쳐 동일한 참조번호들은 동일한 구성요소를 나타냈다. 참고로 본 명세서에서의 프리캐스트 P.S강합성거더는 강재거더(200)와 거더 하부에 타설되는 하부케이싱 콘크리트(208)에 인장재를 이용하여 압축력을 도입(prestressing)시킨 거더를 의미하고 프리캐스트 강합성거더(212)는 압축력이 도입되기 전 상태이다. 상기 과정은 물론 지면상에서 이루어진다. 본 발명의 목적을 달성하기 위한 첫 번째 단계(도 2a)로는 제작될 프리캐스트 강합성거더(212)의 양 단부로부터 내측으로 소정의 거리의 위치에 수직보강재를 갖는 수직재에 연결된 수평지지판(207) 상부에 강재거더를 지지시키고 하부케이싱 콘크리트가 강재바닥판(204)에 타설될 수 있도록 조립한다. 여기서 조립이란 바닥판강재(204)와 수직보강재(203)를 갖는 수직재(202)의 볼트연결과 조절봉(201)의 조립 및 수직보강재(203)를 갖는 수직재(202)와 수평지지판과 결합된 거더의 높이를 조절할 수 있는 수직재(210)와의 볼트연결(213)을 의미한다. 두 번째로는 도 2c와 같이 조립된 제작대 내부에 설치된 향후 압축력 도입을 위한 인장재 또는 쉬스관(214)이 설치된 상태에서 케이싱 콘크리트 거푸집(215) 내부에 콘크리트를 타설한다. 물론 지점부 제작대 내부의 강재거더와 그 외 구간의 강재거더 하부플랜지의 케이싱 콘크리트(208)는 동시에 타설된다. 여기서 지점부 제작대 내부에 설치되는 거푸집을 제외한 나머지 구간의 거푸집은 강재거더 상부플랜지에 매달린 상태이다. 세 번째 단계로는 제작대 내부에 설치된 거푸집을 제외한 나머지 부분의 거푸집을 탈형한다. 네 번째 단계로는 바닥판받침(206) 좌우에 설치된 또 다른 받침(216)을 설치하고 케이싱 콘크리트 하부에 설치되는 보강된 강판(218) 사이에 유압잭(217)을 거치시킨 후 유압잭을 작동시켜 강재거더 및 케이싱 콘크리트의 자중에 의한 하향력을 상쇄시킬 수 있는 상향력을 가한다. 상향력을 유지시킨 상태에서 지점부 제작대의 모든 볼트를 해체한다. 이 상태의 그림이 도 2d에 나타나 있다. 다섯 번째로는 도 2f와 같이 바닥판받침을 제외한 지점부 제작대가 해체된 상태와 바닥판받침(206)상에 강합성거더(212)가 얹혀져 있는 상태의 정면도가 나타나 있다. 마지막 단계로는 인장재에 압축력을 도입하고 강합성거더 양 단에서 고정, 정착하므로 프리캐스트 P.S강합성거더가 완성된다Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. The embodiments to be described below are described by way of example so that those skilled in the art will be able to fully understand the contents of the present invention to those skilled in the art. The present invention is not limited to the embodiments described below and may be embodied in other forms. In order to clearly explain the present invention, parts not related to the description are omitted in the drawings, and the width, length, thickness, etc. of the components in the drawings may be exaggerated for convenience. Like numbers refer to like elements throughout the specification. For reference, the precast PS steel composite girder in this specification means a girder in which a compressive force is prestressed by using a tensile material to a steel girder 200 and a lower casing concrete 208 placed under the girder, The girder 212 is in a state before the compression force is introduced. This process is of course done on the ground. In the first step (FIG. 2A) for achieving the object of the present invention, a horizontal support plate 207 connected to a vertical member having a vertical stiffener at a predetermined distance inward from both ends of the precast steel composite girder 212 to be manufactured, And the lower casing concrete is assembled so as to be poured into the steel bottom plate 204. As shown in FIG. Wherein the assembly comprises a vertical member 202 having a bottom plate steel 204 and a vertical stiffener 203 and a bolt connection of the vertical member 202 with the vertical stiffener 203, And a bolt connection 213 with a vertical member 210 capable of adjusting the height of the girder. Secondly, concrete is poured into the casing concrete form 215 in a state where a tensile material or a sheath pipe 214 for introducing a compressive force to be installed is installed in the fabricated assembly as shown in FIG. 2C. Of course, the casing concrete 208 of the steel girder inside the fuselage manufacturing base and the lower flange of the steel girder of the other section are simultaneously poured. Here, the form of the section except for the formwork installed inside the façade part manufacturing stand is suspended from the upper flange of the steel girder. The third step is to demold the remaining part of the formwork except for the molds inside the building. In the fourth stage, another support 216 installed on the left and right of the bottom plate support 206 is installed, a hydraulic jack 217 is installed between the reinforced steel plates 218 installed under the casing concrete, The upward force which can cancel the downward force due to the self weight of the girder and the casing concrete is applied. Dismantle all the bolts in the fuselage section while maintaining the upward force. A picture of this state is shown in Figure 2D. Fifthly, there is shown a front view of the state in which the fascia workbench except for the bottom plate fuselage is disassembled and the steel composite girder 212 is placed on the bottom plate fuselage 206 as shown in Fig. 2f. As a final step, the pre-cast P.S steel composite girder is completed because the tension is applied to the tensile material and fixed and fixed at both ends of the steel composite girder

100 : 지점부 제작대
200 : 강재거더
201 : 제작대 수직재의 수평변위를 제어하는 제어봉
202 : 수직보강재를 갖는 수직재
203 : 수직보강재
204 : 지점부 제작대 내부의 케이싱 콘크리트 타설을 위한 거푸집의 바닥판으로 이용되는 강재바닥판
205 : 강재바닥판과 수직보강재(203)를 갖는 수직재(202)의 연결볼트
206 : 바닥판받침
207 : 높이조절이 가능한 수직재와 결합된 강재거더의 상부플랜지를 지지하는 수평지지판
208 : 케이싱 콘크리트
209 : 강재거더의 높이 증가량
210 : 수평지지판(207)과 결합된 수직재로서 강형의 높이를 조절할 수 있는 수직재
211 : 제작대의 수평변위를 제어하는 제어봉 설치를 위한, 수직재 상부가 열려있는 형태의 홈
212 : 케이싱 콘크리트가 타설되므로 강재거더가 하부케이싱 콘크리트와 결합되어 강합성거더로 변환된 상태도
213 : 수평지지판과 결합된 높이조절이 가능한 수직재(210)와 수직보강재를 갖는 수직재(202)를 연결하는 볼트
214 : 압축력의 도입(prestressing)을 위한 인장재 또는 쉬스관
215 : 케이싱 콘크리트의 거푸집
216 : 유압잭의 거치를 위해 바닥판받침 좌우에 별도로 설치된 받침
217 : 유압잭
218 : 유압잭에 의한 응력집중을 분산시키기 위한 강판
100: Branch office production stand
200: Steel girder
201: control rod for controlling the horizontal displacement of the fabric to the vertical member
202: vertical member with vertical stiffener
203: vertical stiffener
204: Steel floor plate used as a deck for molding concrete for casing casing inside the fuselage manufacturing base
205: connecting bolt of a vertical member 202 having a steel bottom plate and a vertical stiffener 203
206: Floor plate base
207: Horizontal support plate supporting upper flange of steel girder combined with height-adjustable vertical member
208: casing concrete
209: Increase in height of steel girder
210: vertical member combined with horizontal support plate 207, vertical member capable of adjusting the height of the rigid member
211: a groove for opening the upper part of the vertical member for installing the control rod for controlling the horizontal displacement of the fabrication stand
212: The state that the steel girder is combined with the lower casing concrete and converted into the steel composite girder because casing concrete is poured.
213: a bolt connecting the height-adjustable vertical member 210 coupled with the horizontal support plate and the vertical member 202 having a vertical stiffener
214: tensile material or sheath tube for prestressing
215: Formwork of casing concrete
216: Separately installed supports on the left and right sides of the floor plate support for hydraulic jack mounting
217: Hydraulic Jack
218: Steel plate for dispersing stress concentration by hydraulic jack

Claims (6)

프리캐스트 P.S강합성거더가 바닥판받침 상에 얹혀지는 형태로 제작하기 위해 수직보강재를 갖는 수직재와 강재거더의 높이에 따라 조절이 가능한 수평지지판과 결합되고 수직재와의 볼트 연결이 가능한 특징을 갖고 또한 수직보강재를 갖는 수직재와 프리캐스트 P.S강합성거더를 받혀줄 수 있는 바닥판받침 상에 설치된 강재바닥판과의 볼트연결에 의해 형성되는 특징을 갖는 지점부 제작대의 제작방법Precast PS steel The composite girder is combined with a vertical member with vertical stiffener and a horizontal support plate which can be adjusted according to the height of the steel girder to be mounted on the bottom plate support, A method of manufacturing a fulcrum having a feature formed by bolting of a vertical member having a vertical stiffener and a steel bottom plate provided on a bottom plate support capable of receiving a precast PS steel composite girder 1항에 있어 수평지지판과 결합된 수직재와 강재거더의 높이에 맞추어 설치할 수 있는 수직보강재를 갖는 수직재와 볼트연결할 수 있는 연결방법       In connection with vertical members in combination with horizontal support plates in Par 1 and vertical members with vertical stiffeners that can be fitted to the height of the steel girder, 지점부 제작대의 바닥판받침 좌우에 설치되는 또 다른 받침과 케이싱 콘크리트 하부에 설치되는 강판사이에 유압잭을 거치시키고 강재거더 및 케이싱 콘크리트 자중에 의해 제작대 수평지지판에 전달되는 하향력을 유압잭을 작용시켜 상쇄시킬 수 있는 상향력을 가한 상태에서 제어봉의 해체와 수직보강재를 갖는 수직재와 강재바닥판과의 볼트연결의 해체 및 높이 조절이 가능한 수직재간의 볼트연결의 해체에 의해 바닥판받침을 제외한 지점부 제작대를 해체하는 특징을 갖는 지점부 제작대의 해체방법Hydraulic jack is mounted between another support installed on the left and right side of the floor plate support of the branch part manufacturing base and the steel plate installed on the lower part of casing concrete, and the downward force transmitted to the horizontal support plate is applied to the hydraulic jack by the weight of the steel girder and casing concrete. Disassembly of the control rod with the upward force that can cancel it, disassembly of the bolt connection between the vertical member having the vertical stiffener and the steel deck, and disassembly of the bolt connection between the vertical member capable of adjusting the height, Dismantling method of fuselage fabrication unit with characteristics of disassembly 1항에 있어 수직보강재를 갖는 수직재 상단에 지점부 제작대의 수평변위를 제어하기 위해 해체가 용이한 제어봉을 갖는 특징을 갖는 지점부 제작대의 조립방법The assembly of the fascia part with the feature that the control rod is easy to disassemble to control the horizontal displacement of the fascia part at the upper part of the vertical part with vertical stiffener 1항에 있어 제작된 강합성거더는 이동 없이 제작된 위치에서 인장하여 고정·정착되므로 프리캐스트 P.S강합성거더가 완성되는 특징을 갖는 시공법The steel composite girder manufactured in Par 1 is tensioned and fixed at the position where it is manufactured without moving. Therefore, the precast P.S steel composite girder is completed. 높이조절이 가능한 수직재와 결합된 수평지지판에 얹혀지는 강재거더의 양단으로부터 소정의 길이만큼 내측으로 지점부 제작대를 위치시킴에 따라 제작대의 조립 및 해체가 용이해지는 특징을 갖는 제작방법
A manufacturing method having a feature of facilitating the assembly and disassembly of a workbench by positioning the workbench inward by a predetermined length from both ends of a steel girder resting on a horizontal support plate combined with a vertical member capable of height adjustment
KR1020160145558A 2016-11-03 2016-11-03 Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment KR20180049533A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160145558A KR20180049533A (en) 2016-11-03 2016-11-03 Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160145558A KR20180049533A (en) 2016-11-03 2016-11-03 Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment

Publications (1)

Publication Number Publication Date
KR20180049533A true KR20180049533A (en) 2018-05-11

Family

ID=62185378

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160145558A KR20180049533A (en) 2016-11-03 2016-11-03 Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment

Country Status (1)

Country Link
KR (1) KR20180049533A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113174855A (en) * 2021-04-20 2021-07-27 中交第三公路工程局有限公司 Nondestructive assembling device and method for road steel plate beam

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100541965B1 (en) * 2005-05-14 2006-01-10 (주)삼현피에프 Manufacturing apparatus for steel composite girder whose self weight is loaded on steel girder and manufacturing method thereof
KR100540625B1 (en) * 2003-05-27 2006-01-11 주식회사 노빌테크 Constructing Method of Composite Beam Stiffened with In-Situ Concrete Panel Having Embedded Lower Flange
KR100890455B1 (en) * 2008-07-01 2009-03-26 박성규 Loading apparatus using gravitational method and apparatus of manufacturing preflex composite girder using the loading apparatus
KR101665121B1 (en) * 2016-01-28 2016-10-12 주식회사 티엠이앤씨 Method of manufacturing composite girder for bridge

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100540625B1 (en) * 2003-05-27 2006-01-11 주식회사 노빌테크 Constructing Method of Composite Beam Stiffened with In-Situ Concrete Panel Having Embedded Lower Flange
KR100541965B1 (en) * 2005-05-14 2006-01-10 (주)삼현피에프 Manufacturing apparatus for steel composite girder whose self weight is loaded on steel girder and manufacturing method thereof
KR100890455B1 (en) * 2008-07-01 2009-03-26 박성규 Loading apparatus using gravitational method and apparatus of manufacturing preflex composite girder using the loading apparatus
KR101665121B1 (en) * 2016-01-28 2016-10-12 주식회사 티엠이앤씨 Method of manufacturing composite girder for bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113174855A (en) * 2021-04-20 2021-07-27 中交第三公路工程局有限公司 Nondestructive assembling device and method for road steel plate beam

Similar Documents

Publication Publication Date Title
KR101657994B1 (en) Form traveler, and bridge construction method for using the same
KR100820299B1 (en) Temporary structure and precast concrete beam of pylon setting method using the bracket
KR101237000B1 (en) Precast concrete panel construction technique
CN102239302A (en) A means of stripping concrete formwork from a concrete surface
KR101396434B1 (en) Movable mold device
KR100402436B1 (en) The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack
JP2020183678A (en) Box girder construction method and construction system
KR20180049533A (en) Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment
KR20170043222A (en) Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment
KR20150032499A (en) Construction method of prestressed composite girder bridge
CN105863261A (en) Universally-adjustable suspension formwork system
KR20120117363A (en) The installation and dismantlement method of main girder for bridge temporary
JPH07279417A (en) Beam form device and execution method of beam
KR20180049538A (en) Manufacturing method of precast P.S composite girder using support device
KR20190066754A (en) Formwork structure supported by column unit
CN112140290B (en) Pouring method for prefabricated bridge deck
KR101291517B1 (en) Composite girder construction method using t shape steel plate
CN211057623U (en) Precast bridge deck inboard cantilever pouring braced system
CN114414354A (en) Temporary support test device for large-span box girder erection
KR100791991B1 (en) Temporary bridge consruction method using composite slab girder
KR20040102272A (en) Prestressed concrete double-t beam bridge & formwork applying incremental launching method
KR20120004117A (en) Toggle link means steel-fram assembly jig system
KR101314170B1 (en) Method for constructing tower silo
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
KR20170039858A (en) Manufacturing method of precast P.S composite girder using support device

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application