KR20170078311A - Freestanding temporary retaining of deep excavations and its construction method - Google Patents
Freestanding temporary retaining of deep excavations and its construction method Download PDFInfo
- Publication number
- KR20170078311A KR20170078311A KR1020150188682A KR20150188682A KR20170078311A KR 20170078311 A KR20170078311 A KR 20170078311A KR 1020150188682 A KR1020150188682 A KR 1020150188682A KR 20150188682 A KR20150188682 A KR 20150188682A KR 20170078311 A KR20170078311 A KR 20170078311A
- Authority
- KR
- South Korea
- Prior art keywords
- pile
- thumb
- fixing nut
- plate
- fixing
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2220/00—Temporary installations or constructions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
In the present invention, a thumb pile is installed on the ground, a support pile is installed on the back of the excavation of the thumb pile, and horizontal excavation is performed in the direction of the support pile from the thumb pile inserted into the ground in accordance with the depth required to support the thumb pile And then connecting the thumb pile and the support pile to a tie rod connecting member made of a high strength steel bar securing a predetermined tensile force to solve a structural problem and as a result, The present invention provides a self-supporting permanent earth retaining structure and a construction method thereof.
According to an aspect of the present invention, there is provided a self-supporting permanent pile of deep excavation, comprising: a thumb pile inserted into a perforation hole formed at a predetermined distance and a predetermined diameter and depth in a ground; A support pile inserted into a perforation hole spaced apart from the thumb pile by a predetermined distance; And a tie rod connecting member penetrating through the thumb pile and the support pile, wherein the thumb pile is composed of an H beam, the H beam having a flange disposed on both sides, a web fixedly installed between the flanges, And a cut-out portion formed at a predetermined position of the flange, wherein a rectangular front face plate is fixed to the outside of the thumb pile, a through hole is formed at the center of the front face plate, the support pile is formed of an H beam, The H beam is composed of a flange disposed on both sides, a web fixedly installed between the flanges, and a cut-out portion formed at a predetermined position of the flange, wherein a plate with a rectangular fixing nut is fixedly installed outside the support pile, Wherein a nut fixture is formed at the center of the nut attachment plate, and a fixture tool is connected to the fix nut attachment plate, And is tapered so as to become narrower from the end to the other end.
In accordance with another aspect of the present invention, there is provided a self-supporting type permanent earth retaining method for deep excavation, comprising: a thumb pile inserted into a perforation hole formed by drilling a predetermined diameter and depth at a predetermined interval in a ground; A support pile inserted into a perforation hole spaced apart from the thumb pile by a predetermined distance; And a tie rod connecting member penetrating through the thumb pile and the support pile, wherein the thumb pile is composed of an H beam, the H beam having a flange disposed on both sides, a web fixedly installed between the flanges, And a cut-out portion formed at a predetermined position of the flange, wherein a rectangular front face plate is fixed to the outside of the thumb pile, a through hole is formed at the center of the front face plate, the support pile is formed of an H beam, The H beam is composed of a flange disposed on both sides, a web fixedly installed between the flanges, and a cut-out portion formed at a predetermined position of the flange, wherein a plate with a rectangular fixing nut is fixedly installed outside the support pile, Wherein a nut fixture is formed at the center of the nut attachment plate, and a fixture tool is connected to the fix nut attachment plate, (S I) of forming a perforation hole with a predetermined diameter and a predetermined depth at a predetermined interval in the ground, the method comprising the steps of: ; Inserting the thumb pile and the supporting pile into the perforation hole so as to face each other (SII); A step (S Ⅲ) of excavating horizontally while performing a conventional wave measurement using a conventional wave measuring instrument from the thumb pile to the support pile; A step (SIV) of inserting and fixing the tie rod connecting member through the thumb pile and the supporting pile; And a step (S V) of tensioning the tie rod connecting member and fixing the tie rod connecting member with a fixing nut.
Description
The present invention relates to a self-supporting permanent pile of deep excavation and a method of constructing the same, and more particularly, to a pile of a ground pile spaced at a predetermined distance in the direction of the excavation back side of a thumb pile, And a method of constructing the same.
The earth anchor method is generally used to maintain the earth retaining wall during deep excavation for the underground structure construction.
Here, the above-described earth anchor method fixes the earth anchor by inserting the adjacent site more than 10M, but when the use of the adjacent site is restricted, strut or raker method is applied, which is disadvantageous in economy and construction conditions .
SUMMARY OF THE INVENTION Accordingly, the present invention has been made in order to solve the above-mentioned problems, and it is an object of the present invention to provide a pile of a pile- The tie rods are horizontally excavated in the direction of the support pile from the thumb pile inserted into the ground in accordance with the depth of the pile and then connected between the thumb pile and the support pile by a tie rod connection member made of a high strength steel bar securing a predetermined tensile force. And as a result, it is possible to improve the economical efficiency and the construction condition, and to provide a method of constructing the same.
According to an aspect of the present invention, there is provided a self-supporting permanent pile of deep excavation, comprising: a thumb pile inserted into a perforation hole formed at a predetermined distance and a predetermined diameter and depth in a ground; A support pile inserted into a perforation hole spaced apart from the thumb pile by a predetermined distance; And a tie rod connecting member penetrating through the thumb pile and the support pile, wherein the thumb pile is composed of an H beam, the H beam having a flange disposed on both sides, a web fixedly installed between the flanges, And a cut-out portion formed at a predetermined position of the flange, wherein a rectangular front face plate is fixed to the outside of the thumb pile, a through hole is formed in the center of the front face plate, and a fixing nut is installed outside the front face plate A small fixing nut having a size smaller than that of the fixing nut is provided on the rear surface of the fixing nut, and the supporting pile is composed of an H beam, the H beam having flanges disposed on both sides, And a cut-out portion formed at a predetermined position of the flange, wherein a plate with a rectangular fixing nut is fixed to the outside of the support pile A fixation nut tool is connected to the fixing nut attachment plate, and the fixation induction fixture is formed in a tapered shape that narrows from one end to the other end, .
In accordance with another aspect of the present invention, there is provided a self-supporting type permanent earth retaining method for deep excavation, comprising: a thumb pile inserted into a perforation hole formed by drilling a predetermined diameter and depth at a predetermined interval in a ground; A support pile inserted into a perforation hole spaced apart from the thumb pile by a predetermined distance; And a tie rod connecting member penetrating through the thumb pile and the support pile, wherein the thumb pile is composed of an H beam, the H beam having a flange disposed on both sides, a web fixedly installed between the flanges, And a cut-out portion formed at a predetermined position of the flange, wherein a rectangular front face plate is fixed to the outside of the thumb pile, a through hole is formed in the center of the front face plate, and a fixing nut is installed outside the front face plate A small fixing nut having a size smaller than that of the fixing nut is provided on the rear surface of the fixing nut, and the supporting pile is composed of an H beam, the H beam having flanges disposed on both sides, And a cut-out portion formed at a predetermined position of the flange, wherein a plate with a rectangular fixing nut is fixed to the outside of the support pile And a fixing nut tool is connected to the fixing nut mounting plate, wherein the fixing inducing tool has a tapered shape that tapers from one end to the other end, As a method for constructing a permanent pavement, a step (S I) of forming a perforation hole at a predetermined distance and a predetermined diameter and a predetermined depth in the ground; Inserting the thumb pile and the supporting pile into the perforation hole so as to face each other (SII); A step (S Ⅲ) of excavating horizontally while performing a conventional wave measurement using a conventional wave measuring instrument from the thumb pile to the support pile; A step (SIV) of inserting and fixing the tie rod connecting member through the thumb pile and the supporting pile; And a step (S V) of tensioning the tie rod connecting member and fixing the tie rod connecting member with a fixing nut.
As described above, according to the present invention, the self-supporting type permanent earth retaining pavement and its construction method of deep excavation can be achieved by simply connecting the thumb pile and the supporting pile with the tie rod connection material, And the construction period and construction conditions are also improved.
FIG. 1 is a perspective view showing a state in which a thumb pile and a supporting pile of a self-supporting permanent pile of a deep excavation according to the present invention are connected by a tie-
FIG. 2 is a side view showing a state in which a thumb pile and a support pile of a self-supporting permanent pile of deep excavation according to the present invention are connected by a tie-
FIG. 3 is a front view showing a state in which a thumb pile and a support pile of a self-supporting permanent pile of deep excavation according to the present invention are connected by a tie-
FIG. 4 is a plan view showing a state in which a thumb pile and a supporting pile of a self-supporting permanent pile of deep excavation according to the present invention are connected by a tie-
FIG. 5 is a perspective view, a front view, a side view, and a side view showing a fixture tool of a self-supporting permanent pile according to the present invention,
FIG. 6 is a perspective view, a front view, a side view, and a side view showing a fixing nut attachment plate of a self-supporting type permanent earth retaining mud according to the present invention,
FIG. 7 is a perspective view, a front view, a side view, and a side view showing a front plate attached to the entirety of a pile of a thumb pile of a self-
8 is a perspective view, a front view, and a side view showing a fixing nut and a small fixing nut for fixing a tie rod connection member of a self-supporting type permanent earth retaining tile according to the present invention.
Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.
FIG. 1 is a perspective view showing a state in which a thumb pile and a supporting pile of a self-supporting permanent pile of a deep excavation according to the present invention are connected by a tie rod connection material, and FIG. 2 is a perspective view of a self- FIG. 3 is a side view showing a state in which a thumb pile and a support pile are connected by a tie-rod connection material. FIG. 3 is a state in which a thumb pile and a support pile of a self- And FIG. 4 is a plan view showing a state in which a thumb pile and a support pile of a self-supporting permanent pile of a deep excavation according to the present invention are connected by a tie rod connection material.
As shown in these drawings, the self-supporting permanent pavement of the deep excavation according to the present invention comprises a
That is, in the self-supporting type permanent seal according to the present invention, the tie-
Here, the
A rectangular
7, the
The
A square fixing
6, the fixing
7, a
That is, in order to connect the
The tie-
The tie
Hereinafter, the construction of the self-sustaining permanent earth retaining structure of the deep excavation according to the present invention having the above-described construction will be described.
As shown in FIGS. 1 to 8, the self-supporting type permanent earth retaining method for deep excavation according to the present invention is a method for constructing a self-supporting type permanent earth retaining structure for a deep excavation according to the present invention, )and; A
That is, the self-supporting type permanent earth retaining method according to the present invention includes a perforation hole forming step (S I); A
Here, the perforation hole forming step S I is performed at a predetermined distance and a predetermined diameter and depth in the ground, or a plurality of perforation holes are formed by using a boring machine.
Next, the
Particularly, when the
The
In order to install the
At this time, the
In the horizontal excavation step S III, the
The tie
The
The preferred embodiments described in the specification of the present invention are intended to be illustrative, not limiting, and the scope of the present invention is indicated by the appended claims, and all modifications that come within the meaning of the claims are included in the present invention. .
100: Thumb pile 110: H beam
120: flange 130: web
140: cut portion 200: support pile
210: H beam 220: Flange
230: web 240: cut-
300: tie rod coupling member 400: coupler
500: Fixing oil tool 600: Fixing nut mounting plate
610: Nut fixture 700: Front plate
800: Fixing nut 900: Small fixing nut
Claims (3)
Forming a perforation hole (S Ⅰ) by drilling a predetermined diameter and depth at a predetermined interval on the ground;
Inserting the thumb pile 100 and the supporting pile 200 into the perforation hole so as to face each other (SII);
(S III) horizontally excavating from the thumb pile (100) in the direction of the support pile (200) while performing conventional wave measurement using a conventional wave meter;
The step (SIV) of inserting and fixing the tie rod coupling member 300 through the thumb pile 100 and the supporting pile 200;
And a step (S V) of tensioning the tie rod coupling member (300) and fixing the tie rod coupling member (300) with a fixing nut (800) and a small fixing nut (900).
The horizontal excavation step S III is a step in which the thumb plate 100 of the thumb pile 100 maintains the vertical position of the thumb pile 100 when the thumb pile 100 is closed, The depth coordinate Z which is an installation position of the front plate 700 positioned below the thumb pile 100 is corrected at the position coordinates X and Y of the thumb pile 100, (X, Y, Z: A point) of the support pile 200 is determined and the vertical position of the support pile 200 is maintained when the support pile 200 approaches The installation position of the fixing nut attachment plate 600 positioned below the support pile 200 at the positional coordinates (X ', Y') of the support pile 200 obtained from the ground at the position of the nut attachment plate 600 The depth coordinate Z 'is corrected to determine the position coordinates (X', Y ', Z': B 'point) of the fixing nut attachment plate 600 of the support pile 200, At the position coordinates (X, Y, Z: A) of the front plate 700 of the support plate (X ', Y', Z ': B point) direction of the fixed nut mounting plate (600) of the fixed nut (200) Construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150188682A KR20170078311A (en) | 2015-12-29 | 2015-12-29 | Freestanding temporary retaining of deep excavations and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150188682A KR20170078311A (en) | 2015-12-29 | 2015-12-29 | Freestanding temporary retaining of deep excavations and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20170078311A true KR20170078311A (en) | 2017-07-07 |
Family
ID=59353234
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150188682A KR20170078311A (en) | 2015-12-29 | 2015-12-29 | Freestanding temporary retaining of deep excavations and its construction method |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20170078311A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109457706A (en) * | 2018-12-28 | 2019-03-12 | 北京城建北方集团有限公司 | Foundation pit edge protection can be had enough to meet the need |
-
2015
- 2015-12-29 KR KR1020150188682A patent/KR20170078311A/en not_active Application Discontinuation
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109457706A (en) * | 2018-12-28 | 2019-03-12 | 北京城建北方集团有限公司 | Foundation pit edge protection can be had enough to meet the need |
CN109457706B (en) * | 2018-12-28 | 2024-04-02 | 北京城建北方集团有限公司 | Can have enough to meet need foundation ditch face limit protection |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9422687B2 (en) | Flat plate foundation supports | |
KR101242476B1 (en) | Base construct method of building and base construct member of building | |
KR101861805B1 (en) | H omitted | |
CN105464106B (en) | Stake connector | |
KR101888737B1 (en) | Prefabricated shoring structure | |
KR101618723B1 (en) | Reinforcing structure of the steel pipe for the retaining CIP wall | |
KR101667377B1 (en) | Freestanding temporary retaining of deep excavations and its construction method | |
JP5693778B1 (en) | Temporary mountain retaining structure and temporary mountain retaining method | |
JP2011080195A (en) | Anchor device and method of installing anchor | |
KR20170078311A (en) | Freestanding temporary retaining of deep excavations and its construction method | |
JP2015148099A (en) | Earth supporting material and end metal part used for the same | |
JP5427044B2 (en) | Construction method for deep foundation construction and construction structure for deep foundation construction | |
KR101557462B1 (en) | A freestanding temporary retaining and it's construction method | |
KR101386558B1 (en) | Construction method of earth retaining wall using phc pile | |
CN214061716U (en) | Testing arrangement of cement soil mud lateral pressure | |
JP5426424B2 (en) | Method for placing ground reinforcing pile and rod for preceding excavation and casting apparatus used therefor | |
JP2002047650A (en) | Set anchor body and executing method therefor | |
JP2007107233A (en) | Construction method for earth retaining structure | |
KR101705785B1 (en) | Apparatus for Supporting Anchor box for Tie-Back Anchor of H-Pipe Pile used in the Panel Retaining Wall Method without Wale and Method for Installing Tie-Back Anchor of H-Pipe Pile without Wale | |
JP2009162029A (en) | Retaining wall | |
KR101495318B1 (en) | Civil and building structures for mounting support | |
JP2017218844A (en) | Slide rail erection-type simple earth retaining method | |
JP2001207452A (en) | Method for burying pipe | |
JP6479554B2 (en) | Branch line anchor and construction method of branch line anchor | |
JP2992915B2 (en) | Supporting method for underground continuous wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application |