KR20160085544A - The construction method of pile using soil and grouting - Google Patents
The construction method of pile using soil and grouting Download PDFInfo
- Publication number
- KR20160085544A KR20160085544A KR1020150002671A KR20150002671A KR20160085544A KR 20160085544 A KR20160085544 A KR 20160085544A KR 1020150002671 A KR1020150002671 A KR 1020150002671A KR 20150002671 A KR20150002671 A KR 20150002671A KR 20160085544 A KR20160085544 A KR 20160085544A
- Authority
- KR
- South Korea
- Prior art keywords
- pile
- grouting
- file
- soil
- excavating
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/62—Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Soil Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
The present invention relates to a method of constructing a file that forms the basis of a structure.
In general, when a high-rise building or a reinforced concrete structure is to be built, a basic construction is carried out by putting a PHC file or an H-type beam on the ground in order to strengthen the foundations, and the construction of the above- It is a very important construction for building structures.
As a method of constructing the above-mentioned file, a piling method and an excavation method have been introduced. The method of installing the electron is as follows: a method in which the hammer of the weight is elevated by using a hoisting rope installed on the upper part of a leader installed vertically in the crawler traveling device, So that the pile is poured into the ground while the hammer is raised and lowered. In the latter excavation method, a screw file mounted on a file connection part is rotated to excavate the ground to form a pile hole, and then the screw file is reversed to be pulled out from the excavated pile and inserted into the pile .
However, in the existing method using the screw file, there is an inconvenience that the slime occurring in the ground drilling is excessively generated, and the slime rising from the drilling hole must be removed by the excavator every time the drilling is performed. In addition, since the drilling apparatus and the injection apparatus for injecting are separately developed, there is a problem that the process for installing the pile is very troublesome, and the grouting material is excessively entered by removing all the soil from the perforation hole and performing the grouting, resulting in an economical problem.
In order to solve this problem, Patent No. 10-1441929 has been proposed. However, since the patent is merely punched and mixed with green slime and grouting material to form a file, stable design supportability can not be sufficiently exhibited. There is a problem that can not be used as a basis. In addition, in order to secure the design supporting force by using the above-mentioned patent, the number of files is excessively increased, which also causes economical problems.
SUMMARY OF THE INVENTION The present invention has been proposed in order to solve the above problems and it is an object of the present invention to provide a foundation for a high-rise building or an important structure by forming a foundation by using a steel pipe file or a PHC file, The present invention provides a method of constructing a pile using soil and grouting material that minimizes the occurrence of slime by using a slime so that grouting can be performed simultaneously with excavation, thereby minimizing a process for forming a foundation.
In order to achieve the above object, the present invention provides a method of installing a file on a ground, the method comprising the steps of: (a) measuring a position where a file is to be installed by design; and (b) (C) injecting the grouting solution while excavating the point measured in the step (a), and injecting the grouting solution into the grouting solution, (D) a step of loading and selecting a pile of the mixed material in the gel state by structural calculation, and (e) (d) curing and then curing. The present invention provides a pile construction method using soil and grouting materials.
The present invention has the following effects.
First, since slime is not generated during excavation, a slime removing process is not required and the grouting solution is mixed with the gravel to reduce the grouting material during excavation to save the construction period and the construction cost of the pile . In addition, the present invention can be used as a foundation of a high-rise building or an important structure by forming a foundation by inserting a steel pipe or a PHC file into a gel-like material mixed with a soil and a grouting solution.
Second, the present invention is an invention in which the grouting solution is injected at the same time while excavating the ground, the position where the file is to be constructed is in a gel state, and can be easily inserted by the weight of the file, It is an invention that can save construction cost.
1 is a flowchart of a file construction method of the present invention.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, a method of constructing a file using soil and grouting according to the present invention will be described in detail with reference to the accompanying drawings.
1 is a flowchart of a file construction method of the present invention.
The present invention relates to a file installation method using soil and grouting material, and more particularly, to a construction method for installing a file on a ground, comprising the steps of: (a) (C) injecting the grouting solution into an apparatus capable of injecting excavation and grouting solution after preparing a grouting solution which is mixed with the soil generated during excavation to form a gel state; and (c) A step of injecting a grouting solution while excavating the mixture to form a gel state by mixing the soil and the grouting liquid generated during excavation, and (d) And (e) curing after the step (d).
The present invention comprises steps (a) to (e), wherein a slime removal process is not necessary at the time of construction of a file, and a place where the excavation is performed is in a gel state so that it can be inserted by the weight of the file, The present invention relates to a file construction method using soil and grouting material that can save a construction period and a construction cost of a file.
In general, when a high-rise building or a reinforced concrete structure is to be built, a basic construction is carried out by putting a PHC file or an H-type beam on the ground in order to strengthen the foundations, and the construction of the above- It is a very important construction for building structures.
As a method of constructing the above-mentioned file, a piling method and an excavation method have been introduced. The method of installing the electron is as follows: a method in which the hammer of the weight is elevated by using a hoisting rope installed on the upper part of a leader installed vertically in the crawler traveling device, So that the pile is poured into the ground while the hammer is raised and lowered. In the latter excavation method, a screw file mounted on a file connection part is rotated to excavate the ground to form a pile hole, and then the screw file is reversed to be pulled out from the excavated pile and inserted into the pile .
However, in the existing method using the screw file, there is an inconvenience that the slime occurring in the ground drilling is excessively generated, and the slime rising from the drilling hole must be removed by the excavator every time the drilling is performed. In addition, since the drilling apparatus and the injection apparatus for injecting are separately developed, there is a problem that the process for installing the pile is very troublesome, and the grouting material is excessively entered by removing the soil from the perforation holes and performing the grouting.
In order to solve this problem, Patent No. 10-1441929 has been proposed. However, since the patent is merely punched and mixed with green slime and grouting material to form a file, stable design supportability can not be sufficiently exhibited. There is a problem that can not be used as a basis. In addition, in order to secure the design supporting force by using the above-mentioned patent, the number of files is excessively increased, which also causes economical problems.
SUMMARY OF THE INVENTION The present invention has been proposed in order to solve the above problems and it is an object of the present invention to provide a foundation for a high-rise building or an important structure by forming a foundation by using a steel pipe file or a PHC file, The present invention provides a method of constructing a pile using soil and grouting material that minimizes the occurrence of slime by using a slime so that grouting can be performed simultaneously with excavation, thereby minimizing a process for forming a foundation.
That is, the present invention does not require a slime removing process because there is almost no slime generated at the time of excavation, and the grouting solution is mixed with the gravel to reduce the material for grouting at the time of excavation so that the construction period and the construction cost of the pile can be saved . In addition, the present invention can be used as a foundation of a high-rise building or an important structure by forming a foundation by inserting a steel pipe or a PHC file into a gel-like material mixed with a soil and a grouting solution. In addition, the present invention is an invention in which the grouting solution is simultaneously injected while excavating the ground, the position where the file is to be constructed is in a gel state, and can be easily inserted by the weight of the file, thereby dramatically reducing the construction step of the file. It is an invention that can save construction cost.
Step (a) is a step of measuring a position where a file is to be constructed by design. That is, step (a) is a step of accurately measuring the location where the file is to be installed, so that the file can be accurately installed on the ground to be grounded to construct the file.
(b) is a step of injecting the grouting solution to be drilled into the hole to be drilled into the equipment capable of spraying the grouting solution. That is, step (b) is a step of mixing the grouting solution mixed with the slurry generated in the excavation to form a gel state, and injecting the grouting solution into the apparatus capable of spraying the perforation and grouting solution. The grouting solution is a material prepared by mixing the grouting material to be charged with water at a predetermined ratio. The equipment that can inject excavation and grouting liquid is the equipment commonly used in the construction site.
(c) is a step of spraying the grouting solution while excavating the ground to construct the pile according to the design. That is, in the step (c), the grouting solution is injected while excavating the point measured in the step (a), so that the soil and the grouting solution generated at the excavation are mixed to make a gel state. In addition, step (c) is a step of spraying the grouting solution by repeatedly excavating and rotating the excavation equipment to make the measured gel state in design. In the step (c), the gel state in which the soil and the grouting liquid are mixed is a state where the pile is easily inserted and seated when the pile is inserted.
(d) is a step in which a file selected by the structural calculation according to the site is inserted and settled. That is, step (d) is a step in which a file selected by the structural calculation is inserted into the gel-like mixed material constructed in step (c). For example, a gel state is a state in which a file can be easily inserted by the weight of the file when it is inserted. (d) is a step in which a file is inserted into a gel-like mixed material so as to be utilized as a basis of a high-rise structure or an important structure, in order to secure a stable endurance. That is, the pile is mixed with the mixed material in the gel state so that the pile is incorporated into the mixed material in the gel state to effectively support the load from the top. The file is a file selected by structural calculation according to the purpose of the foundation and the site, and a steel pipe, a PHC, or the like can be used.
In addition, the step (d) may further include the step of placing a file in the gel mixed material by applying a load to one end of the file. That is, in order to accelerate the penetration of the pile according to the air in which the foundation is constructed, a load may be applied to one end of the pile to allow the pile to be introduced into the gel-state mixed material sooner. Here, a method of applying a load to one end of a file may be performed by rotating the file while rotating the file, by vibrating the file using a vibration device, or by striking one end of the file, It is possible to apply a load by applying a load.
(e) is a step of curing after the step (d). That is, after the pile is inserted into the mixed material in the gel state, the pile is cured for a certain time so that the pile and the mixed material are integrated.
While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it should be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims. And the scope of the technical idea of the present invention is not limited by the description with reference to the drawings or the drawings. It will also be appreciated by those skilled in the art that the concepts and embodiments of the invention set forth herein may be used as a basis for modifying or designing other structures for carrying out the same purposes of the present invention It will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the present invention as defined by the appended claims and their equivalents. And various changes, substitutions, and alterations can be made without departing from the scope of the invention.
Claims (3)
(a) measuring a location at which a file is to be constructed by design;
(b) injecting the grouting solution mixed with the gravel generated during excavation into a device capable of jetting excavation and grouting solution after preparing a grouting solution having a gel state;
(c) spraying the grouting solution while excavating the point measured in the step (a) to mix the soil and the grouting solution to form a gel state;
(d) placing a selected file in the gel-state mixed material by the calculation of the structure; And
(e) curing after the step (d).
Wherein the step (c) is a step of repeatedly spraying the grouting solution while rotating the excavation equipment while rotating the surveyed point repeatedly to make the gel state required in design.
Wherein the step (d) further comprises the step of placing a file on the mixed substance in a gel state by applying a load to one end of the file, and seizing the file.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150002671A KR20160085544A (en) | 2015-01-08 | 2015-01-08 | The construction method of pile using soil and grouting |
PCT/KR2016/000199 WO2016111585A1 (en) | 2015-01-08 | 2016-01-08 | Pile construction method using soil and grouting material |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150002671A KR20160085544A (en) | 2015-01-08 | 2015-01-08 | The construction method of pile using soil and grouting |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20160085544A true KR20160085544A (en) | 2016-07-18 |
Family
ID=56356197
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150002671A KR20160085544A (en) | 2015-01-08 | 2015-01-08 | The construction method of pile using soil and grouting |
Country Status (2)
Country | Link |
---|---|
KR (1) | KR20160085544A (en) |
WO (1) | WO2016111585A1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107489143A (en) * | 2017-08-30 | 2017-12-19 | 中建四局第建筑工程有限公司 | A kind of concrete pouring of punched hole piles structure and its plain fill layer leakproof paste-making method |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101441929B1 (en) | 2014-02-03 | 2014-09-22 | 스키너스 주식회사 | Foundation method for complex pile |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3182586B2 (en) * | 1992-04-28 | 2001-07-03 | 株式会社テノックス | Construction method of soil cement composite pile |
JP2001248147A (en) * | 2000-03-07 | 2001-09-14 | Fumio Kosaka | Excavating/stirring blade for soil cement composite pile |
JP2002021072A (en) * | 2000-07-12 | 2002-01-23 | Tenox Corp | Method for constructing steel pipe reinforced soil cement pile |
KR100888166B1 (en) * | 2008-01-22 | 2009-03-10 | (주)진산이엔지 | Construction method of site direct forming soil concrete pile and the soil concrete pile |
JP5558314B2 (en) * | 2010-11-04 | 2014-07-23 | 株式会社テノックス九州 | Construction method of soil cement composite pile |
-
2015
- 2015-01-08 KR KR1020150002671A patent/KR20160085544A/en active Search and Examination
-
2016
- 2016-01-08 WO PCT/KR2016/000199 patent/WO2016111585A1/en active Application Filing
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101441929B1 (en) | 2014-02-03 | 2014-09-22 | 스키너스 주식회사 | Foundation method for complex pile |
Also Published As
Publication number | Publication date |
---|---|
WO2016111585A1 (en) | 2016-07-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100964796B1 (en) | Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction | |
US20220098817A1 (en) | Method for constructing structure | |
CN105464074B (en) | A kind of artificial digging pile high polymer grouting safeguard structure and its construction method | |
KR20120013820A (en) | Method for Constructing Cap Beam Combined Wale For Retaining Wall | |
KR102091646B1 (en) | Ground improvement type composite pile construction method | |
KR101021915B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
JP2015055088A (en) | Building construction method | |
KR20100058413A (en) | Soft soil improvement method | |
KR101095393B1 (en) | Method and apparatus for improving ground using cement grouting | |
KR101081343B1 (en) | Compaction grouting system | |
CN106917402A (en) | A kind of CFG pile precast piles head and CFG pile construction methods | |
KR20100095066A (en) | Method and apparatus for improving ground using cement grouting | |
KR20100095070A (en) | Method and apparatus for improving ground using cement grouting | |
JP5075090B2 (en) | Cast-in-place pile construction method and cast-in-place pile | |
KR20160085544A (en) | The construction method of pile using soil and grouting | |
KR101021913B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
JP5075093B2 (en) | Construction method and foundation structure of foundation structure in structure | |
KR20160150538A (en) | Ground Foundation Structure of Offshore Structures and Construction Method Thereof | |
KR101052363B1 (en) | Freestanding Digging Method for Deep Excavation | |
JP2010106546A (en) | Method of constructing foundation in structure, and foundation structure | |
KR20070068006A (en) | Concrete compaction pile grouting method | |
JP4074198B2 (en) | How to remove existing piles | |
KR20130073336A (en) | Pile structure and construction methods | |
KR102601336B1 (en) | PRD method proceeding from the upper part of the underground structure and casing guide device | |
KR20090128084A (en) | Jacket installing process of jacket facility structure using r.c.d. reamming bit for excavating enlarged hole in the earth |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
AMND | Amendment | ||
E601 | Decision to refuse application | ||
AMND | Amendment | ||
J201 | Request for trial against refusal decision | ||
J301 | Trial decision |
Free format text: TRIAL NUMBER: 2017101001318; TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20170320 Effective date: 20180802 |