KR20110130196A - Subway platform and construct method of subway platform - Google Patents

Subway platform and construct method of subway platform Download PDF

Info

Publication number
KR20110130196A
KR20110130196A KR1020100049720A KR20100049720A KR20110130196A KR 20110130196 A KR20110130196 A KR 20110130196A KR 1020100049720 A KR1020100049720 A KR 1020100049720A KR 20100049720 A KR20100049720 A KR 20100049720A KR 20110130196 A KR20110130196 A KR 20110130196A
Authority
KR
South Korea
Prior art keywords
construction
subway station
platform
wall
constructed
Prior art date
Application number
KR1020100049720A
Other languages
Korean (ko)
Other versions
KR101285372B1 (en
Inventor
구자갑
Original Assignee
주식회사 코아이엔씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 코아이엔씨 filed Critical 주식회사 코아이엔씨
Priority to KR1020100049720A priority Critical patent/KR101285372B1/en
Publication of KR20110130196A publication Critical patent/KR20110130196A/en
Application granted granted Critical
Publication of KR101285372B1 publication Critical patent/KR101285372B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/08Sinking shafts while moving the lining downwards

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sustainable Development (AREA)
  • Mechanical Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

PURPOSE: A subway station and construction method of a subway station is provided to reduce construction costs and period by connecting upper and lower structures to a path. CONSTITUTION: A subway station comprises an upper structure(100), left and right platforms, lower structure, and a passage structure. The upper structure is installed in the ground toward the underground using an open cut method in order to form a waiting room or a function room. Right and left platforms are temporary installed in left and right running tunnels, through which the supper structure passes, using a respective tunnel method. Lower structure interlinks the left and right platforms.

Description

지하철 정거장 및 지하철 정거장의 시공방법{SUBWAY PLATFORM AND CONSTRUCT METHOD OF SUBWAY PLATFORM}Construction method of subway station and subway station {SUBWAY PLATFORM AND CONSTRUCT METHOD OF SUBWAY PLATFORM}

본 발명은 지하철 정거장의 시공방법에 관한 것으로서, 더욱 상세하게는 지하에 가설되는 상부 구조물과 하부 구조물을 각각 분리 시공한 후, 상기 상부 구조물과 하부 구조물을 통로로 연결하여 시공성을 증대시킨 지하철 정거장의 시공방법에 관한 것이다.The present invention relates to a construction method of a subway station, and more specifically, after separating and constructing the upper structure and the lower structure, respectively, which is hypothesized underground, the connection of the upper structure and the lower structure by the passage of the subway station to increase the construction It is about a construction method.

즉, 본 발명의 지하철 정거장의 시공방법은 심도와 지반조건에 따라 상부 구조물과 하부 구조물을 각각 분리 시공함으로써 상부 구조물에서 하부 구조물로 순차적으로 이루어지는 시공보다 시공성을 증대시킬 수 있고, 공사기간을 단축할 수 있으며, 공사비를 절약할 수 있다. That is, the construction method of the subway station of the present invention can increase the workability than the construction sequentially consisting of the upper structure and the lower structure by separating the upper structure and the lower structure according to the depth and ground conditions, respectively, and shorten the construction period Can save construction cost.

더욱 상세하게 설명하면, 상기 지하철 정거장의 시공방법은 지면과 연결되는 상부구조물인 대합실 및 기능실과, 지하철 터널 상에 시공되는 하부구조물인 승강장 및 환기구를 각각 분리 시공한 후, 상기 상부 구조물과 하부 구조물을 통로로 연결 시공한다.In more detail, the construction method of the subway station is separated after the construction of the waiting room and the functional room, the upper structure connected to the ground, and the platform and the ventilation opening of the lower structure to be constructed on the subway tunnel, respectively, the upper structure and the lower structure Connect to the passage.

일반적으로 지하철 정거장은 지하철 또는 철도관련 시설의 승강장에 있어서 많은 승객을 안전하고, 정확한 시간에 목적지까지 수송할 수 있는 유용한 교통수단으로, 이용객 수가 날로 증가하고 있다.In general, the subway station is a useful means of transporting many passengers to the destination in a safe and accurate time in the platform of the subway or railway-related facilities, the number of passengers is increasing day by day.

최근 대도시에서 주거지와 도심기반 시설의 밀집에 따라 교통난을 해소하기 위해 지하철 정거장의 건설이 활발하게 진행되면서 심도가 큰 굴착공사가 늘어나고 있는 추세이다. In recent years, the construction of subway stations has been increasing to solve traffic shortages due to the concentration of residential and urban infrastructure in large cities.

도 1은 종래 기술인 2층으로 이루어진 지하철 정거장의 시공방법을 나타낸 도면으로, 도 1의 (a)는 섬식 지하철 정거장을 나타낸 도면이고, 도 1의 (b)는 상대식 지하철 정거장을 나타낸 도면이다.1 is a view showing a construction method of a conventional two-story subway station, Figure 1 (a) is a view showing an island-type subway station, Figure 1 (b) is a view showing a relative subway station.

또한, 도 2는 종래 기술인 3층으로 이루어진 지하철 정거장의 시공방법을 나타낸 도면으로, 도 2의 (a)는 섬식 지하철 정거장을 나타낸 도면이고, 도 2의 (b)는 상대식 지하철 정거장을 나타낸 도면이다.In addition, Figure 2 is a view showing a construction method of a three-layer subway station of the prior art, Figure 2 (a) is a view showing an island-type subway station, Figure 2 (b) is a view showing a relative subway station. to be.

여기서, 도 1 및 도 2는 설치 위치 및 층수의 차이일 뿐 구성과 시공방법은 동일하게 이루어지기에, 동일한 구성부호를 사용한다.1 and 2 are only the difference between the installation position and the number of floors, the configuration and construction method is the same, the same reference numerals are used.

한편, 지하철이 통과하는 본선 터널(2)(3)은 TBM 및 실드 등의 장비에 의해 기계식 굴착으로 이루어지거나 발파등에 의해 굴착하고 숏크리트로 라이닝을 하는 NATM 공법으로 이루어지며 특히 TBM 및 실드등 장비에 의한 터널(2)(3) 가설은 지하철 노선을 처음부터 끝까지 또는 일부분이라도 긴 연장을 한 번의 장비조립으로 굴진시키는 것이 공사기간 및 비용 면에서 유리하다.On the other hand, the main line tunnel (2) (3) through which the subway passes is made of mechanical excavation by equipment such as TBM and shield, or by NATM method of excavating by blasting and lining with shotcrete, and especially in equipment such as TBM and shield. The hypothesis of tunnel (2) (3) is that it is advantageous in terms of construction period and cost to excavate a long extension of the subway line from start to finish or even part of it with one piece of equipment.

그리고 상기 본선 터널(2)(3)과 도로면(1)이 연결되게 지하철 정거장(4)이 설치되며, 상기 지하철 정거장(4)은 도 1 및 도 2에 도시된 바와 같이, 개착 방법 또는 굴착 터널 방식으로 시공된다.And the main tunnel (2) (3) and the subway station (4) is installed so that the road surface (1) is connected, the subway station (4), as shown in Figures 1 and 2, the attachment method or excavation It is constructed in a tunnel manner.

즉, 종래기술인 지하철 정거장(4)은 대합실과 기능실이 형성되는 상부 구조물(5)과, 승강장이 형성되는 하부 구조물(6)로 이루어지며, 상기 하부 구조물(6)과 상부 구조물(5)은 순차적으로 이루어지는 것이 일반적이다.That is, the prior art subway station 4 is composed of an upper structure 5 in which a waiting room and a functional room are formed, and a lower structure 6 in which a platform is formed, and the lower structure 6 and the upper structure 5 are It is generally done sequentially.

이와 같은 종래기술인 지하철 정거장의 시공방법은 도 1 또는 도 2를 참조하면, 지면에 굴착 경계면에 따라 흙막이를 위해 엄지말뚝(주로 H-Pile)(11) 및 토류시설(12) 등으로 가시설인 토압에 저항하는 벽체(10)를 축조한다. 그리고 상기 벽체(10)를 기준으로 계획된 단면만큼 벽체 내부를 굴착한다. 한편, 상기 벽체(10) 내부를 굴착하기 전에 도로면(1)의 지하에 정거장이 설치되는 경우에는 차량 통행이 가능하도록 복공판(20)을 설치한다. 1 or 2, the construction method of such a prior art subway station, the earth pressure as a temporary equipment (such as H-Pile) 11 and earth equipment 12 for the earthquake block according to the excavation interface on the ground The wall 10 which resists is constructed. And the inside of the wall is excavated by the cross section planned based on the wall (10). On the other hand, when the stop is installed in the basement of the road surface (1) before excavating the inside of the wall (10) is installed a perforated plate 20 to enable the vehicle traffic.

다음으로, 상기 벽체(10)는 토압이나 수압 등에 안정되도록 띠장이나 앵커 등으로 이루어지는 버팀 구조물(13)을 설치하고, 상기 버팀 구조물(13)의 설치가 완료되면 바닥 슬래브(30), 벽체 및 기둥(40), 중간슬래브(50), 상부슬래브(60) 등을 순서에 맞게 설치하면, 도 1 또는 도 2에 도시된 지하철 정거장(4)을 시공할 수 있다.Next, the wall 10 is provided with a support structure 13 made of a band or anchor so as to stabilize the earth pressure or hydraulic pressure, and, when the installation of the support structure 13 is completed, the bottom slab 30, the wall and the pillar If the 40, the intermediate slab 50, the upper slab 60 is installed in order, it is possible to construct the subway station 4 shown in FIG.

그러나 종래 기술인 지하철 정거장(4)은 본선 터널(2)(3) 중간에 일정간격으로 정거장이 위치하므로, 개착식 공법으로 시공되는 정거장 공사와 굴착터널 공법으로 시공되는 본선 터널 공사가 서로 간섭이 발생하여 본선터널 공사가 정거장 부근에서 중단되거나 본선 터널 공사 때문에 정거장 공사가 중단될 수 있으며, 이에 따라 지하철 공사 기간이 길어지는 문제점 있었다.However, in the conventional subway station 4, since the stations are located at regular intervals in the middle of the main line tunnels 2 and 3, interference between the main line tunnel construction constructed by the open-end method and the main line tunnel construction constructed by the excavation tunnel method occurs. As a result, the construction of the main tunnel may be stopped near the station or the construction of the station may be stopped due to the main tunnel construction.

더욱이, 종래 기술인 지하철 정거장(4)은 기계식 굴착 공법에 의한 터널 공사가 개착 공법을 이용한 정거장 공사에 의해 간섭을 받지 않도록 하기 위해서는 정거장의 폭이 본선 터널(2)(3)의 양 외측 폭을 보다 넓어야 하고(도 2 참조), 본선 터널(2)(3)이 가설되는 동안 터널 굴착 장비가 이동할 수 있도록 충분한 공간을 확보하도록 정거장 단면을 필요 이상으로 크게 만들어야 하는 문제점이 있었다.In addition, the prior art subway station (4) has a width of the station more than the outer width of the main tunnel (2) (3) in order to prevent the tunnel construction by the mechanical excavation method is not interfered by the station construction using the opening method 2 had to be wide (see FIG. 2), and the section of the station had to be made larger than necessary to secure enough space for the tunnel drilling equipment to move while the main tunnel 2 and 3 were installed.

또한, 종래 기술인 지하철 정거장(4)은 주로 지상도로의 하부에 설치되는 정거장의 폭은 공유지인 도로 내에 설치하기 위해서는 그 폭을 최소화해야 하는 경우가 많아 정거장의 폭을 키우는 것이 현실적으로 매우 어렵다.In addition, the prior art subway station 4 is often difficult to increase the width of the station is mainly installed in the lower part of the ground road, the width of the station in order to be installed in the common road, it is practically very difficult to increase the width of the station.

따라서, 종래 기술인 지하철 정거장(4)은 본선 터널(2)(3)을 안전하게 형성하고 지중에 다른 지하철이나 다른 지장물 등을 피하여 형성하기 위해서는 본선 터널의 심도가 깊어지며, 이에 따라 지하철 정거장의 층수가 늘어나 정거장의 규모가 정거장 구성에 필요로 하는 규모보다 커지게 되는 문제점이 있었다.Accordingly, the prior art subway station 4 has a deeper depth of the main line tunnel in order to safely form the main line tunnels 2 and 3 and to avoid other subways or other obstacles in the underground, thereby increasing the number of floors of the subway station. There was a problem that the size of the station is larger than the scale required for the station configuration.

본 발명은 상기와 같은 문제점을 해결하기 위해 발명된 것으로, 본 발명의 목적은 도로면과 연결되는 상부 구조물과, 지하철의 본선 터널에 설치되는 하부 구조물을 각각 분리 시공한 후, 상기 상부 구조물과 하부 구조물을 통로로 연결하여 시공성을 증대시킨 지하철 정거장의 시공방법을 제공하는데 있다.The present invention has been invented to solve the above problems, the object of the present invention is to separate and install the upper structure and the lower structure installed in the main line tunnel of the subway, respectively, the upper structure and the lower It is to provide a construction method of the subway station to increase the constructability by connecting the structure to the passage.

상기와 같은 목적을 달성하기 위한 본 발명인 지하철 정거장의 시공방법은 개착식 방법을 이용하여 지상에서 지하로 시공되는 상부 구조물과, 터널식 방법을 이용하여 지하철이 통과하는 좌측 및 우측 본선 터널에 시공되는 하부 구조물을 각각 분리하여 시공한 다음, 상기 상부 구조물과 하부 구조물을 연결하는 통로 구조물을 시공한다.The construction method of the present invention subway station for achieving the above object is the upper structure to be constructed from the ground to the ground using the detachable method, and the lower part to be installed in the left and right main line tunnel through the tunnel using the tunnel method Separately construct the structures, and then construct a passage structure connecting the upper structure and the lower structure.

상기 상부 구조물과 하부 구조물은 동시에 각각 분리 시공된다.The upper structure and the lower structure are separately constructed at the same time.

상기 상부 구조물은 심도가 낮고 대부분 토사인 구간을 굴착하는 초기 굴착 단계, 굴착된 경계면을 따라 가시설인 벽체를 축조하는 벽체 축조 단계, 도로면 지하에 상부 구조물이 시공될 경우 굴착면 상부에 복공판을 설치하는 복공판 설치 단계, 상기 가시설인 벽체 사이의 토사를 굴착하는 토사 굴착 단계, 상기 가시설인 벽체에 콘크리트를 타설하여 강성벽체를 시공하는 강성 벽체 시공 단계, 상기 강성벽체의 상단에 거더등을 이용하여 상부 슬래브를 설치하는 상부 슬래브 설치 단계, 상기 강성 벽체 하단에 콘크리트를 타설하여 바닥 슬래브를 시공하는 바닥 슬래브 시공 단계를 포함한다.The upper structure has a low depth and the initial excavation step of excavating the most earthen period, the wall construction step of constructing the wall of the temporary facility along the excavated boundary surface, when the upper structure is installed in the basement of the road surface, the perforated plate is installed on the upper surface of the excavation To install a perforated plate, the earth excavation step of excavating the soil between the walls of the temporary facility, the construction of a rigid wall to construct a rigid wall by placing concrete on the wall of the temporary facility, the upper part using a girder on the top of the rigid wall An upper slab installation step of installing a slab, and a floor slab construction step of constructing a floor slab by placing concrete on the bottom of the rigid wall.

상기 하부 구조물은 지하철이 통과하는 좌측 및 우측 본선 터널에 승강장을 각각 시공하는 승강장 시공 단계, 상기 좌측 및 우측 본선 터널에 시공된 승강장을 연결되게 승강장 통로를 가설하는 승강장 통로 시공단계를 포함한다.The lower structure includes a platform construction step of constructing a platform in the left and right main line tunnels through which the subway passes, and a platform passage construction step of constructing a platform passage to connect the platform constructed in the left and right main line tunnels.

상기 하부 구조물은 승강장을 시공하기 위해 지하철이 통과하는 본선 터널을 확장할 때, 본선 터널이 손상되지 않도록 콘크리트 또는 강재 등의 기둥을 이용하여 지지한 상태로 굴착하며, 굴착 후 상기 기둥은 스크린 도어의 설치 지주등으로 이용한다.When the lower structure expands the main tunnel through which the subway passes to construct the platform, the main structure is excavated in a supported state using pillars such as concrete or steel so that the main tunnel is not damaged, and after the excavation, the pillar is connected to the screen door. We use in setting props.

상기 통로 구조물은 상부 구조물로부터 하부 구조물까지 또는 하부 구조물로부터 상부 구조물까지 개착식 방법 또는 터널식 방법으로 시공한다.The passage structure is constructed in a detachable or tunneled manner from the superstructure to the substructure or from the substructure to the superstructure.

이와 같이 본 발명은 대합실 또는 기능실 등이 설치되는 상부 구조물과, 복선 터널에 설치되는 하부 구조물을 동시에 각각 분리 시공한 후 상부 구조물과 하부 구조물을 통로 구조물을 이용하여 연결되게 시공함으로써 시공시간 및 비용을 현저하게 절감할 수 있는 효과가 있다.As described above, the present invention separates the upper structure in which the waiting room or the functional room is installed and the lower structure installed in the double track tunnel at the same time, and then constructs the upper structure and the lower structure to be connected by the passage structure. There is an effect that can be significantly reduced.

도 1a는 종래기술인 2층으로 이루어진 섬식 지하철 정거장을 나타낸 도면.
도 1b는 종래기술인 2층으로 이루어진 상대식 지하철 정거장을 나타낸 도면.
도 2a는 종래기술인 3층으로 이루어진 섬식 지하철 정거장을 나타낸 도면.
도 2b는 종래기술인 3층으로 이루어진 상대식 지하철 정거장을 나타낸 도면.
도 3은 본 발명인 지하철 정거장의 시공방법을 나타낸 도면.
도 4는 본 발명인 상부 구조물 시공방법을 나타낸 공정도.
도 5는 본 발명인 하부 구조물 시공방법을 나타낸 도면.
도 6은 본 발명인 통로 구조물의 시공상태를 나타낸 제1 실시예.
도 7은 본 발명인 통로 구조물의 시공상태를 나타낸 제2 실시예.
Figure 1a is a view showing an island subway station consisting of a two-layer prior art.
Figure 1b is a view showing a relative subway station consisting of a two-layer prior art.
Figure 2a is a view showing an island subway station consisting of a three-layer prior art.
Figure 2b is a view showing a relative subway station consisting of a three-layer prior art.
Figure 3 is a view showing the construction method of the present inventors subway station.
Figure 4 is a process chart showing the present invention the upper structure construction method.
Figure 5 is a view showing a lower structure construction method of the present invention.
Figure 6 is a first embodiment showing a construction state of the present invention passage structure.
Figure 7 is a second embodiment showing the construction state of the present invention passage structure.

이하, 본 발명인 지하철 정거장의 시공방법을 첨부된 도 3 내지 도 7을 참조하여 상세히 설명한다.Hereinafter, the construction method of the present invention subway station will be described in detail with reference to FIGS.

한편, 본 발명의 실시예를 설명함에 있어 종래기술에서 전술한 구성과 기능이 동일한 구성에 대해서는 동일한 구성부호를 사용하며, 중복되는 설명은 생략한다.On the other hand, in describing the embodiment of the present invention, the same reference numerals are used for the same configuration as the above-described configuration and functions in the prior art, and redundant description is omitted.

본 발명인 지하철 정거장의 시공방법은 도 3에 도시된 바와 같이, 개착식 방법을 이용하여 가설되는 상부 구조물(100)과, 승강장이 가설되도록 터널식 방법을 이용하여 가설되는 하부 구조물(200), 및 상기 상부 구조물(100)과 하부 구조물(200)을 연결하는 통로 구조물(300)을 시공하여 시공성을 증대시킨 기술이다.The construction method of the present inventors subway station, as shown in Figure 3, the upper structure 100 is hypothesized using the detachable method, and the lower structure 200 is hypothesized using the tunnel type method to install the platform, and the The construction of the passage structure 300 connecting the upper structure 100 and the lower structure 200 to increase the workability.

즉, 본 발명인 지하철 정거장의 시공방법은 도 3에 도시된 바와 같이, 개착식 방법을 이용하여 지면에서 지하로 가설되며 대합실 또는 기능실 등이 설치되는 상부 구조물(100)과, 상기 상부 구조물(100) 하부를 통과하는 좌측 및 우측 본선 터널(2)(3)에 각각 터널식 방법을 이용하여 가설되며 좌측 및 우측 승강장, 상기 좌측 및 우측 승강장을 연결하는 승강장 통로가 설치되는 하부 구조물(200), 및 상기 상부 구조물(100)과 하부 구조물(200)을 연결하는 통로를 가설하며, 계단, 에스컬레이터, 및 엘리베이터가 설치되는 통로 구조물(300)을 포함한다.That is, the construction method of the present inventors subway station, as shown in Figure 3, using an open-type method is installed on the basement underground from the ground and the waiting room or functional room is installed, and the upper structure 100 ) A lower structure 200 installed on the left and right main line tunnels (2) (3) passing through the lower part by using a tunneling method, and a left and right platform, and a platform passage connecting the left and right platforms, and It installs a passage connecting the upper structure 100 and the lower structure 200, and includes a passage structure 300, a staircase, an escalator, and an elevator are installed.

이하, 본 발명인 지하철 정거장의 시공방법을 첨부된 도 4를 참조하여 상세히 설명한다.Hereinafter, the construction method of the present invention subway station will be described in detail with reference to FIG.

상부 구조물(100)의 시공방법은 공공시설인 대합실, 환기구, 및 기능실이 설치되는 곳으로, 심도가 낮고 대부분 토사인 구간을 굴착하는 초기 굴착 단계, 굴착된 경계면을 따라 가시설인 벽체(110)를 축조하는 벽체 축조 단계, 도로면(1) 지하에 상부 구조물(100)이 시공될 경우 굴착면 상부에 복공판(120)을 설치하는 복공판 설치 단계, 상기 가시설인 벽체(110) 사이의 토사를 굴착하여 제거하는 토사 굴착 단계, 상기 가시설인 벽체(110)에 콘크리트를 타설하여 강성벽체(130)를 시공하는 강성 벽체 시공 단계, 상기 강성벽체(130)의 상단에 거더(140)를 이용하여 상부 슬래브(150)를 설치하는 상부 슬래브 설치 단계, 상기 강성 벽체(130) 하단에 콘크리트를 타설하여 바닥 슬래브(160)를 시공하는 바닥 슬래브 시공 단계를 포함한다.The construction method of the upper structure 100 is a place where the waiting room, the ventilation opening, and the functional room, which are public facilities, are installed at an initial stage of excavation, which excavates a tossain section with a low depth, and the wall 110 is a temporary facility along the excavated boundary surface. Wall construction step to build the construction, when the upper structure 100 in the basement of the road surface (1) is installed in the perforated plate to install the perforated plate 120 on the upper surface of the excavation surface, excavation of the soil between the wall 110, the temporary Soil excavation step to remove by, the concrete wall to the concrete 110 to the rigid wall construction step of constructing the rigid wall 130, the upper slab using the girder 140 on the top of the rigid wall 130. The upper slab installation step of installing the 150, the bottom slab construction step of constructing the floor slab 160 by placing concrete on the bottom of the rigid wall 130.

즉, 상기한 상부 구조물(100)의 시공방법은 도 4의 (a)와 같이, 심도가 낮고 대부분 토사인 구간을 굴착기를 이용하여 굴착한다(초기 굴착 단계).That is, in the construction method of the upper structure 100, as shown in Figure 4 (a), the depth of the deep earth excavation is excavated using an excavator (initial excavation step).

다음으로, 도 4의 (b)와 같이, 굴착된 경계면을 따라 엄지말뚝(111)과 토류시설(112)을 설치하여 가시설인 벽체(110)를 축조하고, 콘크리트를 이용한 강성벽체(130)를 설치한다. 이때, 가시설인 벽체(110)에는 토압이나 수압 등에 의한 안정성을 증대시키기 위하여 띠장이나 앵커 등으로 이루어진 버팀보 구조물(113)을 설치할 수도 있다.(벽체 축조 단계).Next, as shown in (b) of FIG. 4, the thumb pile 111 and the earthwork facility 112 are installed along the excavated boundary surface to construct a wall 110 which is a temporary facility, and the rigid wall 130 using concrete. Install. At this time, the wall 110, which is a temporary facility, may be provided with a support structure 113 made of a belt or an anchor in order to increase stability by earth pressure or water pressure. (Wall building step).

다음으로, 도4의 (b)와 같이 차량 통행을 일시적으로 중단시키기 어려울 때는 굴착면 상부에 다수의 중간파일(121)을 이용하여 복공판(120)과 복공거더(122)를 설치하며, 상기 복공판(120)은 도로면(1)과 수평하게 설치하고, 이를 통해 보행자의 보행시 불편함과 안정성을 증대시킨다(복공판 설치 단계).Next, when it is difficult to temporarily stop the traffic of the vehicle as shown in Figure 4 (b) using a plurality of intermediate piles 121 to the upper surface of the excavation surface 120 and the hole girder 122 is installed, 120 is installed horizontally with the road surface (1), thereby increasing the inconvenience and stability when walking pedestrians (restoration board installation step).

복공판(120)을 설치하기 위하여 다수의 중간파일(121)을 설치할 수도 있고 복공거더(122)의 휨강성이 큰것을 사용할 수도 있다.In order to install the perforated plate 120, a plurality of intermediate piles 121 may be installed or a large bending rigidity of the perforated girder 122 may be used.

다음으로, 도4의 (c)와 같이 콘크리트로 된 강성벽체(130) 가시설인 벽체(110) 사이의 토사를 굴착기를 이용하여 굴착하고 제거한다(토사 굴착 단계).Next, as shown in (c) of FIG. 4, the earth and sand between the wall 110, which is a temporary rigid wall 130 made of concrete, is excavated and removed using an excavator (soil excavation step).

다음으로, 가시설인 벽체(110)에 콘크리트를 타설하여 강성벽체(130)를 시공하고, 상기 강성벽체(130)는 토압이나 수압 등에 의한 안정성을 증대시키기 위하여 띠장이나 앵커 등으로 이루어진 버팀보 구조물(113)을 설치할 수도 있다.(강성 벽체 시공 단계). Next, construct a rigid wall 130 by placing concrete on the wall 110, which is a temporary facility, and the rigid wall 130 is a support structure consisting of a belt or an anchor to increase stability by earth pressure or water pressure. ) Can be installed (stiff wall construction stage).

다음으로, 도 4의 (d)와 같이, 상기 강성벽체(130)의 상단에 거더(140)를 이용하여 상부 슬래브(150)를 설치한다. 여기서 상기 상부 슬래브(150) 설치시 개구부 또는 환기구(151)를 동시에 설치할 수 있다(상부 슬래브 설치 단계).Next, as shown in (d) of FIG. 4, the upper slab 150 is installed on the upper end of the rigid wall 130 by using the girder 140. Here, when the upper slab 150 is installed, an opening or a vent 151 may be installed at the same time (upper slab installation step).

즉, 상기 거더(140)를 이용하여 상부 슬래브(150)를 축조하면, 상부 슬래브(150) 콘크리트의 체적이 줄어들게 되고, 강성벽체(130)로 전달되는 하중도 줄어들게 되어, 상부 구조물(100)의 축조 물량을 경감시킬 수 있다. 그리고 상기 거더(140)에 응력을 많이 받지 않는 부분에 환기닥트 등이 통과할 수 있도록 개구부(151)를 설치하며, 이때 거더(140)가 설치된 상부 슬래브(150)의 높이가 높아져도 정거장의 높이가 많이 커지지 않는 장점이 있다. That is, when the upper slab 150 is constructed using the girder 140, the volume of the concrete of the upper slab 150 is reduced, and the load transmitted to the rigid wall 130 is also reduced, so that the upper structure 100 of the upper structure 100 is reduced. We can reduce building quantity. In addition, an opening 151 is installed to allow the ventilation duct to pass through the girder 140 without receiving much stress, and the height of the station is increased even when the height of the upper slab 150 in which the girder 140 is installed is increased. There is an advantage that does not grow much.

특히 이 거더(140)은 그 형상이 T거더, 박스거더, U거더 등 사용목적에 맞게 구성할 수 있다.In particular, the shape of the girder 140 can be configured to suit the purpose of use, such as T girder, box girder, U girder.

다음으로, 도 4의 (e)와 같이, 상기 강성 벽체(130) 하단에 콘크리트를 타설하여 바닥 슬래브(160)를 시공한다(바닥 슬래브 시공 단계).Next, as shown in Figure 4 (e), the concrete is placed on the bottom of the rigid wall 130 to construct the floor slab 160 (floor slab construction step).

즉, 상기 강성 벽체(130)의 하단 내부를 굴착한 후, 강성 벽체(130)와 라이닝벽체(170)를 형성하고 콘크리트를 타설하여 바닥 슬래브(160)를 축조한다.That is, after excavating the inside of the lower end of the rigid wall 130, the rigid wall 130 and the lining wall 170 is formed and the concrete is poured to build the floor slab 160.

다시 말해, 토류 가시설을 강성벽체(130)인 다이아프램 월이나 겸침 주열식 말뚝벽체(시컨트파일 월)로 시공하고 상부 슬래브(150)를 축조한 후, 내부를 굴착하고, 라이닝벽체(170)를 완성한 후, 바닥 슬래브(160)를 완성하는 Top-Down 공법을 적용하면 정거장이 설치되는 지역의 공사 중 점거기간을 획기적으로 줄일 수 있고, 별도의 복공판(120) 설치가 일시적으로 설치되거나 필요가 없으며, 정거장이 공용도로 하부에 설치되는 경우에는 공사 중 교통처리 비용을 획기적으로 줄일 수도 있다. In other words, the earthwork is constructed with a diaphragm wall or a cum-heating pile wall (secant pile wall), which is a rigid wall 130, and after the upper slab 150 is constructed, the interior is excavated, and the lining wall 170 is After completion, by applying the Top-Down method to complete the floor slab 160 can significantly reduce the occupancy period during construction of the area where the station is installed, there is no need to temporarily install a separate perforated plate 120 In addition, the cost of handling traffic during construction can be significantly reduced if the station is installed under a public road.

다음으로, 상부 및 바닥 슬래브가 형성된 강성 벽체(130) 내부에 공공시설인 대합실, 환기구, 및 기능실를 설치하면 상부 구조물(100)의 시공이 완료된다.Next, the installation of the upper structure 100 is completed by installing a waiting room, a ventilation hole, and a functional room, which are public facilities, inside the rigid wall 130 on which the upper and the bottom slabs are formed.

이러한 상부구조물의 시공방법은 지하차도의 시공방법에 적용할 수도 있으며, 이때 강성벽체(130) 사이에는 차량이 통과하게 되며 상하행 차로를 분리하기 위해 중간에 벽체나 기둥을 설치할 수도 있다.The construction method of the upper structure may be applied to the construction method of the underground roadway, in which the vehicle passes between the rigid wall 130 and may be installed in the middle to separate the up and down lanes.

한편, 하부 구조물(200)은 상부 구조물(100)과 동시에 분리 시공되는 것으로, 하부 구조물(200)의 시공방법은 도 5에 도시된 바와 같이, 지하철이 통과하는 좌측 및 우측 본선 터널(2)(3)에 승강장(210)을 각각 시공하는 승강장 시공 단계, 상기 좌측 및 우측 본선 터널(2)(3)에 시공된 승강장(210)을 연결되게 승강장 통로(220)를 가설하는 승강장 통로 시공단계를 포함한다.On the other hand, the lower structure 200 is to be separated and constructed at the same time as the upper structure 100, the construction method of the lower structure 200, as shown in Figure 5, the left and right main line tunnel (2) ( 3) the platform construction step for constructing the platform 210, respectively, and the platform passage construction step for constructing the platform passage 220 to be connected to the platform 210 constructed in the left and right main line tunnels 2 and 3, respectively. Include.

즉, 도 5를 참조하면, 도로면(1) 지하에 상부 구조물(100)과 하부 구조물(200)이 각각 분리되어 시공되었음을 확인할 수 있다.That is, referring to FIG. 5, it can be seen that the upper structure 100 and the lower structure 200 are separated and constructed under the road surface 1.

이와 같은 하부 구조물(200)의 시공방법은 지하철이 통과하는 좌측 및 우측 본선 터널(2)(3)에서 승강장이 설치된 부분을 확폭 굴착하고, 콘크리트를 타설하여 승강장(210)을 시공한다(승강장 시공 단계).In the construction method of the lower structure 200 as described above, a wide excavation of the part where the platform is installed in the left and right main line tunnels 2 and 3 through which the subway passes, and constructs the platform 210 by pouring concrete (platform construction) step).

여기서 하부 구조물(200)은 승강장(210)을 시공하기 위해 지하철이 통과하는 본선 터널(2)(3)을 확장할 때, 본선 터널이 손상되지 않도록 콘크리트 또는 강재 등의 기둥(211)을 이용하여 지지한 상태로 굴착하며, 굴착 후 상기 기둥(211)은 스크린 도어의 설치 지주로 사용한다.Here, when the lower structure 200 expands the main line tunnel (2) (3) through which the subway passes in order to construct the platform 210, using a pillar 211 such as concrete or steel so as not to damage the main line tunnel Excavation in a supported state, and after excavation, the pillar 211 is used as an installation post of the screen door.

다음으로, 좌측 및 우측 본선 터널(2)(3)에 각각 시공된 승강장(210) 사이를 굴착하여 연결한 다음, 콘크리트를 타설하여 승강장 통로(220)를 시공한다(승강장 통로 시공 단계).Next, excavation and connection between the landings 210 respectively constructed in the left and right main line tunnels (2) and (3), and then the concrete is poured to build the landing hall passage 220 (building hall passage construction step).

여기서 본 발명에서는 도 5에 도시된 바와 같이, 섬식 하부 구조물(200)을 일예로써 설명하였으나, 상대식 하부 구조물 또한 형태의 차이가 있을 뿐 동일한 방법으로 시공된다. 즉, 상대식 하부 구조물은 도면에는 도시되지 않았지만 좌측 및 우측 본선 터널(2)(3)에 각각 승강장을 시공한 다음, 상기 승강장의 상부로 좌측과 우측에서 각각 상부구조와 연결하여 승강장 통로를 시공하는 것으로, 이와 같은 구조는 현재 상대식 지하철 정거장에 널리 사용되는 연결 구조이며, 그에 따라 자세한 설명은 생략한다.In the present invention, as shown in FIG. 5, the island substructure 200 has been described as an example, but the relative substructure also has a difference in shape and is constructed in the same manner. In other words, the relative substructures are not shown in the drawings, respectively, the landings in the left and right main line tunnels (2) and (3), respectively, and then connected to the upper structure on the left and right to the upper of the platform, respectively, to construct the platform passageway As such, such a structure is a connection structure widely used at the current relative subway station, and thus a detailed description thereof will be omitted.

상기와 같이 상부 구조물(100)과 하부 구조물(200)의 시공이 완료되면, 이들 상부 구조물(100)과 하부 구조물(200)을 연결하기 위한 통로 구조물(300)을 시공한다.When the construction of the upper structure 100 and the lower structure 200 is completed as described above, the passage structure 300 for connecting the upper structure 100 and the lower structure 200 is constructed.

상기 통로 구조물(300)의 시공방법은 도 3에 도시된 바와 같이, 상부 구조물(100)의 바닥 슬래브(160)와 하부 구조물(200)의 승강장 통로(220) 사이를 굴착하는 토사 굴착 단계, 굴착된 벽체를 따라 콘크리트를 타설하는 콘크리트 타설 단계 및 내부에 계단, 에스컬레이터, 및 엘리베이터를 설치하는 이동수단 설치 단계를 포함한다.The construction method of the passage structure 300 is, as shown in Figure 3, excavation step of excavation between the bottom slab 160 of the upper structure 100 and the landing passage 220 of the lower structure 200, excavation A concrete placing step of pouring concrete along the wall and the installation means for installing the moving means for installing a staircase, an escalator, and an elevator therein.

여기서 상기 상부 구조물(100) 및 하부 구조물(200) 사이의 지반이 암반일 경우 도 6에 도시된 바와 같이, 터널식 방법으로 통로 구조물(300, 300')을 시공하여 상부 구조물(100) 및 하부 구조물(200)을 연결한다.If the ground between the upper structure 100 and the lower structure 200 is a rock, as shown in Figure 6, by constructing the passage structure (300, 300 ') in a tunneling method, the upper structure 100 and the lower structure Connect 200.

그리고 상기 상부 구조물(100) 및 하부 구조물(200) 사이의 지반이 토사일 경우 도 7에 도시된 바와 같이, 개착식 방법으로 통로 구조물(300, 300')을 시공하여 상부 구조물(100) 및 하부 구조물(200)을 연결한다.And when the ground between the upper structure 100 and the lower structure 200 is earth and sand, as shown in Figure 7, by constructing the passage structure (300, 300 ') in a detachable method to the upper structure 100 and lower Connect the structure 200.

한편, 상기 터널 굴착 방식 또는 개착 방식은 지하철 정거장의 시공방법으로 공지된 기술로, 그에 따라 자세한 설명은 생략한다.On the other hand, the tunnel excavation method or the opening method is a technique known as a construction method of the subway station, and thus a detailed description thereof will be omitted.

따라서 본 발명은 상부 구조물(100) 및 하부 구조물(200)을 동시에 각각 시공한 후, 상기 상부 구조물(100)과 하부 구조물(200)을 통로 구조물(300, 300')을 이용하여 연결함으로써 시공시간 및 비용을 절감할 수 있다.Therefore, the present invention constructs the upper structure 100 and the lower structure 200 at the same time, respectively, the construction time by connecting the upper structure 100 and the lower structure 200 using the passage structure (300, 300 ') And cost can be reduced.

100: 상부 구조물 110: 가시설인 벽체
111: 엄지말뚝 112: 토류시설
113: 버팀보 구조물 120: 복공판
122: 복공거더 130: 강성벽체
140: 거더 150: 상부 슬래브
160: 바닥 슬래브 170: 라이닝벽체
200: 하부 구조물 210: 승강장
220: 승강장 통로 300: 통로 구조물
100: superstructure 110: a wall of a temporary
111: thumb pile 112: earthwork
113: brace structure 120: perforated plate
122: hollow girder 130: rigid wall
140: girder 150: upper slab
160: floor slab 170: lining wall
200: lower structure 210: platform
220: platform passage 300: passage structure

Claims (7)

개착식 방법을 이용하여 지상에서 지하로 시공되는 상부 구조물과, 터널식 방법을 이용하여 지하철이 통과하는 좌측 및 우측 본선 터널에 시공되는 하부 구조물을 각각 분리하여 시공한 다음, 상기 상부 구조물과 하부 구조물을 연결하는 통로 구조물을 시공하는 지하철 정거장의 시공방법.Using the detachable method, the upper structure constructed from the ground to the underground and the lower structure constructed in the left and right main tunnels through which the subway passes by using the tunnel method are separately constructed and then the upper structure and the lower structure are constructed. Construction method of subway station constructing passage structure to connect. 청구항 1에 있어서,
상기 상부 구조물과 하부 구조물은 동시에 각각 분리 시공되는 지하철 정거장의 시공방법.
The method according to claim 1,
The upper structure and the lower structure is a construction method of a subway station that is separately separated at the same time.
청구항 1에 있어서,
상기 상부 구조물은 심도가 낮고 대부분 토사인 구간을 굴착하는 초기 굴착 단계, 굴착된 경계면을 따라 가시설인 벽체를 축조하는 벽체 축조 단계, 도로면 지하에 상부 구조물이 시공될 경우 굴착면 상부에 복공판을 설치하는 복공판 설치 단계, 상기 가시설인 벽체 사이의 토사를 굴착하는 토사 굴착 단계, 상기 가시설인 벽체에 콘크리트를 타설하여 강성벽체를 시공하는 강성 벽체 시공 단계, 상기 강성벽체의 상단에 거더를 이용하여 상부 슬래브를 설치하는 상부 슬래브 설치 단계, 상기 강성 벽체 하단에 콘크리트를 타설하여 바닥 슬래브를 시공하는 바닥 슬래브 시공 단계를 포함하는 지하철 정거장의 시공방법.
The method according to claim 1,
The upper structure has a low depth and the initial excavation step of excavating the most earthen period, the wall construction step of constructing the wall of the temporary facility along the excavated boundary surface, when the upper structure is installed in the basement of the road surface, the perforated plate is installed on the upper surface of the excavation Steps to install the perforated plate, the excavation step of excavating the soil between the wall is a temporary facility, the rigid wall construction step of constructing a rigid wall by placing concrete on the wall is a temporary facility, the upper slab using a girder on the top of the rigid wall The upper slab installation step of installing, the construction method of the subway station comprising a floor slab construction step of constructing a floor slab by placing concrete on the bottom of the rigid wall.
청구항 1에 있어서,
상기 하부 구조물은 지하철이 통과하는 좌측 및 우측 본선 터널에 승강장을 각각 시공하는 승강장 시공 단계, 상기 좌측 및 우측 본선 터널에 시공된 승강장을 연결되게 승강장 통로를 가설하는 승강장 통로 시공단계를 포함하는 지하철 정거장의 시공방법.
The method according to claim 1,
The lower structure is a subway station including a platform construction step for constructing the platform in the left and right main line tunnel through which the subway passes, and a platform passage construction step for installing a platform passage to connect the platform constructed in the left and right main line tunnel Construction method.
청구항 4에 있어서,
상기 하부 구조물은 승강장을 시공하기 위해 지하철이 통과하는 본선 터널을 확장할 때, 본선 터널이 손상되지 않도록 콘크리트 또는 강재 등의 기둥을 이용하여 지지한 상태로 굴착하며, 굴착 후 상기 기둥은 스크린 도어의 설치 지주로 이용하는 지하철 정거장의 시공방법.
The method of claim 4,
When the lower structure expands the main tunnel through which the subway passes to construct the platform, the main structure is excavated in a supported state using pillars such as concrete or steel so that the main tunnel is not damaged, and after the excavation, the pillar is connected to the screen door. Construction method of subway station to use as setting prop.
청구항 1에 있어서,
상기 통로 구조물은 상부 구조물로부터 하부 구조물까지 또는 하부 구조물로부터 상부 구조물까지 개착식 방법 또는 터널식 방법으로 시공하는 지하철 정거장의 시공방법.
The method according to claim 1,
The passage structure is a construction method of the subway station to be constructed in a detachable method or a tunnel method from the upper structure to the lower structure or from the lower structure to the upper structure.
청구항 1 내지 청구항 6 중 어느 하나의 청구항을 이용하여 시공되는 지하철 정거장.A subway station constructed using any one of claims 1 to 6.
KR1020100049720A 2010-05-27 2010-05-27 Subway platform and construct method of subway platform KR101285372B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100049720A KR101285372B1 (en) 2010-05-27 2010-05-27 Subway platform and construct method of subway platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100049720A KR101285372B1 (en) 2010-05-27 2010-05-27 Subway platform and construct method of subway platform

Publications (2)

Publication Number Publication Date
KR20110130196A true KR20110130196A (en) 2011-12-05
KR101285372B1 KR101285372B1 (en) 2013-07-11

Family

ID=45499067

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100049720A KR101285372B1 (en) 2010-05-27 2010-05-27 Subway platform and construct method of subway platform

Country Status (1)

Country Link
KR (1) KR101285372B1 (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101293550B1 (en) * 2012-05-24 2013-08-06 유제남 Construction method of underground structure
CN104153389A (en) * 2014-08-11 2014-11-19 中铁建大桥工程局集团第六工程有限公司 Construction method for prefabricated assembly type subway station
CN106436759A (en) * 2016-10-18 2017-02-22 郑州新大方重工科技有限公司 Assembly trolley for open-cut subway station formed by assembling prefabricated parts
CN107938707A (en) * 2017-11-24 2018-04-20 中国铁路设计集团有限公司 Prefabricated assembled underground subway station top board structure
CN108589770A (en) * 2018-05-09 2018-09-28 中铁十二局集团有限公司 Construction method is moved in the retaining wall of subway station
CN108914966A (en) * 2018-08-15 2018-11-30 北京市政建设集团有限责任公司 A kind of open-cut station main structure and its construction method
CN109026080A (en) * 2018-08-03 2018-12-18 中铁隆工程集团有限公司 A kind of Underground Subway Station water sealing structure and its construction method
CN109208637A (en) * 2018-08-08 2019-01-15 北京建工土木工程有限公司 Increase the construction method of open-cut station newly on the basis of existing tunnel
CN109555130A (en) * 2018-12-29 2019-04-02 长江勘测规划设计研究有限责任公司 Plate doubles as temporary support structure and construction method in subway main body structure
CN109736354A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Tunnel open excavation section main structure construction method
CN109854253A (en) * 2019-03-20 2019-06-07 中国铁路设计集团有限公司 A kind of existing Metro folds the enlargement method of island transfer station
CN110258634A (en) * 2019-06-28 2019-09-20 中铁第四勘察设计院集团有限公司 A kind of subway station pipeline, which changes, moves device and method
CN110453687A (en) * 2019-07-31 2019-11-15 南京林业大学 A kind of Metro station excavation excavates the protection structure and construction method of pipeline
CN110820804A (en) * 2019-11-20 2020-02-21 西南交通大学 Half-covered-excavated building structure and method suitable for urban rail transit underground station
RU2735506C1 (en) * 2019-10-03 2020-11-03 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Double-vaulted pylon subway station, constructed by trenchless method
RU2746610C1 (en) * 2019-08-05 2021-04-16 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Three-span metro station constructed in accordance with the open building method with an island passenger platform and single-track running tunnels
CN113293766A (en) * 2021-03-30 2021-08-24 内蒙古科技大学 Comprehensive earthwork excavation method for large-scale cover excavation top-down T-shaped transfer subway station
CN114912167A (en) * 2022-04-13 2022-08-16 中铁第六勘察设计院集团有限公司 BIM-based design and construction method for assembly type subway station
CN116479931A (en) * 2023-06-21 2023-07-25 中国铁路设计集团有限公司 Co-building construction method for subway station and municipal tunnel

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926669B (en) * 2016-04-29 2018-04-20 广州地铁设计研究院有限公司 A kind of Construction Method of Metro Station

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0732634Y2 (en) * 1992-03-25 1995-07-26 大豊建設株式会社 Double tunnel segment
JP4104781B2 (en) * 1999-05-27 2008-06-18 株式会社間組 Construction method of underground joint structure
KR100626328B1 (en) * 2004-01-20 2006-09-20 주식회사유신코퍼레이션 method for extending and removing wall of subway structure in subway service line
KR20080006066U (en) * 2008-11-18 2008-12-09 송재청 The structure of a main track and platform in monorail

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101293550B1 (en) * 2012-05-24 2013-08-06 유제남 Construction method of underground structure
CN104153389A (en) * 2014-08-11 2014-11-19 中铁建大桥工程局集团第六工程有限公司 Construction method for prefabricated assembly type subway station
CN106436759A (en) * 2016-10-18 2017-02-22 郑州新大方重工科技有限公司 Assembly trolley for open-cut subway station formed by assembling prefabricated parts
CN106436759B (en) * 2016-10-18 2018-06-26 郑州新大方重工科技有限公司 The assembled trolley of prefabricated components assembly type subway station is used for open cut formula
CN107938707A (en) * 2017-11-24 2018-04-20 中国铁路设计集团有限公司 Prefabricated assembled underground subway station top board structure
CN108589770A (en) * 2018-05-09 2018-09-28 中铁十二局集团有限公司 Construction method is moved in the retaining wall of subway station
CN109026080A (en) * 2018-08-03 2018-12-18 中铁隆工程集团有限公司 A kind of Underground Subway Station water sealing structure and its construction method
CN109208637A (en) * 2018-08-08 2019-01-15 北京建工土木工程有限公司 Increase the construction method of open-cut station newly on the basis of existing tunnel
CN108914966A (en) * 2018-08-15 2018-11-30 北京市政建设集团有限责任公司 A kind of open-cut station main structure and its construction method
CN109555130A (en) * 2018-12-29 2019-04-02 长江勘测规划设计研究有限责任公司 Plate doubles as temporary support structure and construction method in subway main body structure
CN109555130B (en) * 2018-12-29 2024-01-05 长江勘测规划设计研究有限责任公司 Middle plate of subway main body structure and temporary supporting structure and construction method
CN109736354A (en) * 2018-12-30 2019-05-10 中铁十四局集团有限公司 Tunnel open excavation section main structure construction method
CN109854253A (en) * 2019-03-20 2019-06-07 中国铁路设计集团有限公司 A kind of existing Metro folds the enlargement method of island transfer station
CN110258634A (en) * 2019-06-28 2019-09-20 中铁第四勘察设计院集团有限公司 A kind of subway station pipeline, which changes, moves device and method
CN110258634B (en) * 2019-06-28 2024-04-19 中铁第四勘察设计院集团有限公司 Subway station pipeline relocation device and method
CN110453687A (en) * 2019-07-31 2019-11-15 南京林业大学 A kind of Metro station excavation excavates the protection structure and construction method of pipeline
CN110453687B (en) * 2019-07-31 2024-03-19 南京林业大学 Protection structure of subway station foundation pit excavation pipeline and construction method
RU2746610C1 (en) * 2019-08-05 2021-04-16 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Three-span metro station constructed in accordance with the open building method with an island passenger platform and single-track running tunnels
RU2735506C1 (en) * 2019-10-03 2020-11-03 Открытое акционерное общество "Научно-исследовательский, проектно-изыскательский институт "Ленметрогипротранс" Double-vaulted pylon subway station, constructed by trenchless method
CN110820804A (en) * 2019-11-20 2020-02-21 西南交通大学 Half-covered-excavated building structure and method suitable for urban rail transit underground station
CN113293766A (en) * 2021-03-30 2021-08-24 内蒙古科技大学 Comprehensive earthwork excavation method for large-scale cover excavation top-down T-shaped transfer subway station
CN113293766B (en) * 2021-03-30 2022-12-30 内蒙古科技大学 Comprehensive earth excavation method for large-scale cover-excavation top-down T-shaped transfer subway station
CN114912167A (en) * 2022-04-13 2022-08-16 中铁第六勘察设计院集团有限公司 BIM-based design and construction method for assembly type subway station
CN114912167B (en) * 2022-04-13 2024-04-26 中铁第六勘察设计院集团有限公司 BIM-based design construction method for assembled subway station
CN116479931A (en) * 2023-06-21 2023-07-25 中国铁路设计集团有限公司 Co-building construction method for subway station and municipal tunnel

Also Published As

Publication number Publication date
KR101285372B1 (en) 2013-07-11

Similar Documents

Publication Publication Date Title
KR101285372B1 (en) Subway platform and construct method of subway platform
CN105041349B (en) A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel
CN106703828B (en) The construction method of subway station is built using prefabricated assembled lining cutting combination PBA
CN106337686A (en) Rock stratum underground excavation three-story subway station umbrella cover structure and construction method thereof
CN106907159A (en) A kind of Shallow Covered Metro Station separates open type structure and its construction method
CN103806464B (en) Large-scale high ferro station and subway cross top-down construction method up and down
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
Paul et al. Comparative study of construction technologies for underground metro stations in India
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN104632227A (en) Subway station excavation technology of single-layer beam arch structure
RU2012140916A (en) THREE-WATER COLUMN TYPE METRO STATION AND METHODS OF ITS ESTABLISHMENT (DEVICE AND METHODS OF YURKEVICH P.B.)
CN107514262A (en) The construction method of shield piping lane
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN110397278A (en) Method for synchronous construction of overground building and underground structure
JP2017096063A (en) Earth retaining excavation method and skeleton construction method
CN206888990U (en) A kind of Shallow Covered Metro Station separates open type structure
JP7503730B1 (en) Separated subway station structure and its construction method in land-sea junction area
CN113027495B (en) Underground excavation large-span station construction method implemented by interval tunnel organization
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN108978673A (en) A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
CN105386779A (en) Arch column method for building large-scale underground structure in shallow buried rock stratums
CN110486062B (en) Method for mechanically underground excavating multi-layer multi-span underground engineering in soft soil
CN205036388U (en) Block of four encircles knot hunch construction structures that PBA secretly dug subway station
KR20090125896A (en) Construction method for basement extention
CN105986830A (en) Underground-excavation building method for roadside strip-shaped underground garage

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160706

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170704

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180705

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190730

Year of fee payment: 7