KR20090108305A - Construction method of hollow slab bridge - Google Patents

Construction method of hollow slab bridge Download PDF

Info

Publication number
KR20090108305A
KR20090108305A KR1020080033663A KR20080033663A KR20090108305A KR 20090108305 A KR20090108305 A KR 20090108305A KR 1020080033663 A KR1020080033663 A KR 1020080033663A KR 20080033663 A KR20080033663 A KR 20080033663A KR 20090108305 A KR20090108305 A KR 20090108305A
Authority
KR
South Korea
Prior art keywords
slab
hollow
abdominal
members
construction method
Prior art date
Application number
KR1020080033663A
Other languages
Korean (ko)
Other versions
KR101024369B1 (en
Inventor
신현기
Original Assignee
주식회사 아이비엘이앤씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 아이비엘이앤씨 filed Critical 주식회사 아이비엘이앤씨
Priority to KR1020080033663A priority Critical patent/KR101024369B1/en
Publication of KR20090108305A publication Critical patent/KR20090108305A/en
Application granted granted Critical
Publication of KR101024369B1 publication Critical patent/KR101024369B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A construction method of a hollow slab bridge is provided to improve the construction quality and make a cross section structure simple by making an upper slab more detail and uniform. CONSTITUTION: A hollow member(24) is arranged and temporarily fixed in a space segmented with steel wire(21a, 22a) arranged before molding of a bottom slab(21). A fastening protrusion is located in a molding space of a middle slab(22) when the line of the bottom slab is molded. A top slab(23) and the meddle slab are molded to be extended from top of the fastening protrusion.

Description

중공 슬래브교의 시공방법{Construction method of hollow slab bridge}Construction method of hollow slab bridge

본 발명은 철근콘크리트 단면내에 중공부재가 매립된 중공의 슬래브를 구비하도록 시공되는 중공 슬래브교에 관한 것으로, 특히 중공의 슬래브를 시공하는 과정에서 하부슬래브로부터 중공부재들이 부분적으로 들떠서 배부름 현상이 발생됨을 최대한 억제하여, 중공의 슬래브 시공품질 및 시공능률을 향상시킬 수 있게 한 중공 슬래브교의 시공방법에 관한 것이다.The present invention relates to a hollow slab bridge that is constructed to have a hollow slab with a hollow member embedded in a reinforced concrete cross section. Particularly, in the process of constructing a hollow slab, the hollow members are partially lifted from the lower slab, resulting in a filling phenomenon. The present invention relates to a method of constructing a hollow slab bridge, which can be suppressed as much as possible to improve hollow slab construction quality and construction efficiency.

중공 슬래브교라 함은 철근콘크리트로서 단면내에 복수개의 중공부들을 형성시킨 중공의 슬래브를 구비하도록 시공되는 교량을 의미하는 바, 이와 같이 중공 슬래브교에 구비되는 중공의 슬래브는 단면내에 속이 빈 중공부들이 존재하기 때문에, 일반 슬래브교에 구비되는 슬래브에 비해 자중과 원재료가 대폭적으로 감축되어, 시공상 경제성이 우수한 특성을 갖는 것으로 알려져 있다.Hollow slab bridge refers to a bridge that is constructed to have a hollow slab formed of a plurality of hollow portions in the cross-section as a reinforced concrete bar. As such, the hollow slab provided in the hollow slab bridge has hollow hollow portions in the cross-section. Since it exists, compared with the slab provided in the general slab bridge, self-weight and raw materials are reduced significantly and it is known that it has the characteristic which is excellent in economical efficiency in construction.

한편, 상기한 중공 슬래브교와 관련하여 국내 특허공보 등록공고번호 제0279018호(2001.01.15)에는 중공슬래브교의 시공방법이 등록공고되어 있다.On the other hand, in relation to the above-mentioned hollow slab bridges, Korean Patent Publication No. 0279018 (2001.01.15) has been registered and registered the construction method of the hollow slab bridge.

이 중공슬래브교의 시공방법은 도 1에 도시되는 바와 같이, 교각(1)의 상단부에 설치된 거푸집(2) 위에 철근을 배근하고 콘크리트를 타설하여 하측부분(3a)을 선시공 하되, 그 하측부분의 상면에 고정앵커(5)들을 돌출되게 배치하고, 선시공 된 하측부분(3a)의 상면에 발포성 합성수지제로 제작된 중공부재(4)를 배치하며, 고정앵커(5)들에 양단부가 고정되는 고정수단(6)으로 중공부재(4)를 결박하여 고정시킨 후에, 하측부분(3a)과 연이어지도록 철근을 배근하고 콘크리트를 타설하여 상측부분(3b)을 후 시공하는 방식으로 중공슬래브(3)을 완성하게 되었다.As shown in Figure 1, the construction method of the hollow slab bridge is to reinforce the reinforcing bar on the formwork (2) installed on the upper end of the pier (1) and to cast the lower portion (3a) by placing concrete, the upper surface of the lower portion Fixing anchors (5) protruding in the arrangement, the hollow member (4) made of a foamed synthetic resin on the upper surface of the lower portion (3a) pre-installed, fixing means for fixing both ends to the fixed anchors (5) 6) After the hollow member 4 is fixed by the strap, the reinforcing bars are connected to connect with the lower portion 3a, and the concrete is poured to complete the hollow slab 3 in a post-construction manner. It became.

이러한 종래 중공슬래브교의 시공방법에 따르면, 선시공되어 고정앵커(5)들이 돌출되게 설치된 하측부분(3a)의 상면에 중공부재(4)를 배치하고, 이 중공부재(4)를 고정앵커(5)들에 양단부가 고정되는 고정수단(6)들로 결박하여 고정시킨 상태로 상측부분(3b)을 후시공하여, 상측부분(3b)의 시공시 타설되는 콘크리트에 의한 부력으로 중공부재(4)가 부상하게 됨을 방지하게 되므로, 상측부분(3b)을 설계두께로 정확히 형성할 수 있게 하여 원하는 설계강도를 유지할 수 있도록 하였다.According to the construction method of the conventional hollow slab bridge, the hollow member 4 is disposed on the upper surface of the lower portion 3a in which the fixed anchors 5 are protruded, and the hollow member 4 is fixed anchor 5. The hollow member 4 is buoyant by the concrete which is poured during the construction of the upper portion 3b by the post-construction of the upper portion 3b in a state in which it is fixed by fixing means 6 fixed at both ends to the field. Since it is to prevent the floating, it is possible to form the upper portion (3b) accurately to the design thickness to maintain the desired design strength.

그러나, 종래 중공슬래브의 시공방법은 하측부분(3a)의 상면에 중공부재(4)를 고정시킨 상태로 상측부분(3b)을 후시공하는 과정에서 타설되는 콘크리트에 의해 중공부재(4)가 부력을 받게 되면, 고정수단(6)이 결박 고정된 지점에서는 중공부재(4)가 들뜨지 않고 하측부분(3a)에 붙어있게 되지만, 고정수단(6)이 결박 고정되어 있지 않은 지점에서는 중공부재(4)가 부분적으로 들떠서 하측부분(3a)과 벌어진 간극으로 타설 중인 콘크리트가 채워짐에 따라, 중공부재(4)의 상면에 배부름 현상이 발생되면서 평탄성을 상실하게 되어, 실제로는 후시공되는 상측부분(3b)을 설계두께대로 정확히 형성할 수 없게 되므로, 상측부분(3b)을 원하는 설계강도로 유지하게 할 수 없을 뿐만 아니라, 그로 인한 취약부에서 균열이 쉽게 발생되는 등의 문제점을 수반하게 되었다.However, in the conventional hollow slab construction method, the hollow member 4 is buoyant by concrete poured in the process of post-installing the upper portion 3b while the hollow member 4 is fixed to the upper surface of the lower portion 3a. When the fixing means 6 is fixed to the strap, the hollow member 4 is attached to the lower portion 3a without lifting, but at the point where the fixing means 6 is not fixed, the hollow member 4 is fixed. ) Is partially excited, and as the concrete being poured is filled with the gap between the lower portion 3a and the gap, the upper surface of the hollow member 4 loses its flatness, and the flatness is lost. Since it is impossible to form 3b) precisely at the design thickness, not only can the upper portion 3b not be maintained at the desired design strength, but also it is accompanied with problems such that cracks are easily generated at the weak part.

본 발명은 하부슬래브 성형 전에 가고정시켜 둔 중공부재들의 둘레면 하단이 하부슬래브를 선 성형할 때에 형성한 구속용 돌부로 구속되게 하여, 복부 및 상부슬래브를 후 성형할 때에 타설되는 콘크리트에 의해 중공부재들이 부분적으로 들떠서 배부름 현상이 발생되는 일없이, 상부슬래브를 더욱 정밀하고 균일하게 성형할 수 있게 하여 줌으로써, 첫째, 중공의 슬래브가 전체적으로 안정적인 단면구조로서 우수한 구조적강도를 갖게 하여 시공품질을 대폭적으로 향상시킨 중공 슬래브교의 시공방법을 제공하는데 목적이 있으며, 둘째, 중공의 슬래브를 성형하는 과정에서 불필요한 작업공정을 줄여서 시공능률을 획기적으로 향상시킨 중공 슬래브교의 시공방법을 제공하는데 목적이 있다.The present invention allows the lower end of the circumferential surface of the hollow members temporarily fixed before forming the lower slab to be restrained by the restraining protrusion formed when the lower slab is pre-molded, so that the hollow is formed by the concrete that is poured during the post-molding of the abdomen and the upper slab. By making the upper slab more precisely and uniformly without causing the members to partially float, the first, the hollow slab has an excellent structural strength as a whole stable cross-sectional structure, greatly improving the construction quality. The purpose of the present invention is to provide a method of constructing a hollow slab bridge, and to provide a method of constructing a hollow slab bridge, which greatly improves construction efficiency by reducing unnecessary work processes in forming a hollow slab.

본 발명도 하부구조물(10)의 상부에 가설되는 거푸집(A) 위에서 철근콘크리트로서 하부슬래브(21)를 선 성형하고 복부 및 상부슬래브(22)(23)는 후 성형하는 중에 발포성수지로 된 복수개의 중공부재(24)들을 매립시켜서, 상기 하부구조물(10) 상부에 중공부재(24)들이 단면내에 매립된 중공의 슬래브(20)를 시공하는 점에서 종래의 것과 기술개념을 같이 한다.The present invention also preforms the lower slab 21 as reinforced concrete on the formwork A installed on the upper part of the lower structure 10, and the abdomen and the upper slab 22, 23 are a plurality of foamed resins during post-molding. By embedding the hollow members 24, the technical concept is the same as in the construction of the hollow slab 20, the hollow member 24 is embedded in the cross-section on top of the lower structure (10).

단, 본 발명 중공 슬래브교의 시공방법은 상기 하부슬래브(21)의 성형 전에 배근되는 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간마다 중공부재(24) 들을 각각 배치하여 가고정시키고, 상기 하부슬래브(21)를 선 성형할 때 그 상면에 복부슬래브(22)의 성형 위치마다 상기 중공부재(24)들의 둘레면 하단을 밀착 구속할 수 있도록 구속용 돌부(22b)를 일체로 형성한 후에, 상기 구속용 돌부(22b)의 상단으로부터 연이어지도록 복부 및 상부슬래브(22)(23)를 후 성형하여서 됨을 기술구성상의 특징으로 한다.However, in the construction method of the hollow slab bridge of the present invention, the hollow members 24 are temporarily disposed in each of the spaces partitioned by the lower and abdominal slab reinforcing bars 21a and 22a, which are reinforced before the lower slab 21 is formed. When forming the lower slab 21, the restraining protrusion 22b is integrally formed on the upper surface of the lower slab 21 so as to tightly restrain the lower end of the circumferential surface of the hollow members 24 at every forming position of the abdominal slab 22. After that, the abdomen and the upper slab 22, 23 are post-molded so as to be connected from the upper end of the restraining protrusion 22b.

본 발명 중공 슬래브의 시공방법에 따르면, 하부슬래브(21)의 성형을 위해 미리 배근되는 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간에 각각 배치하여 가고정시킨 중공부재(24)들의 둘레면 하단이, 하부슬래브(21)를 선 성형할 때 그 상면에 복부슬래브(22)가 성형될 위치마다 형성되는 구속용 돌부(22b)들로서 밀착 구속되게 하여, 복부 및 상부슬래브(22)(23)를 후 성형할 때에 타설되는 콘크리트가 하부슬래브(21)와 중공부재(24)들 사이로 침투하지 못하도록 차단하는 동시에, 하부슬래브(21)로부터 중공부재(24)들이 들뜨지 못하도록 붙잡아서, 중공부재(24)들의 상면이 배부르지 않고 항상 편평한 상태를 유지할 수 있게 하여 주므로, 이후에 복부슬래브(22)와 함께 성형되는 상부슬래브(23)가 더욱 균일하고 정밀한 단면두께를 가질 수 있게 하여 준다.According to the construction method of the hollow slab of the present invention, the hollow member 24 temporarily arranged and temporarily fixed in the space partitioned by the lower and abdominal slab reinforcing bar (21a) (22a) which is pre-arranged for forming the lower slab 21 When the lower end of the circumferential surface of the lower face slab 21 is closely constrained as restraining protrusions 22b which are formed at positions where the abdominal slab 22 is to be formed on the upper surface thereof, the abdomen and the upper slab 22 are formed. When the 23 is post-molded, the concrete to be poured is blocked from penetrating between the lower slab 21 and the hollow member 24, and at the same time, the hollow member 24 is caught from the lower slab 21 so as not to be lifted, thereby the hollow member. Since the upper surface of the (24) can be always kept flat without being full, the upper slab 23 which is subsequently formed together with the abdominal slab 22 can have a more uniform and precise cross-sectional thickness.

이와 같이 본 발명은 첫째, 하부구조물(10)의 상부에 중공의 슬래브(20)를 시공하는 과정에서, 하부슬래브(21)로부터 중공부재(24)들이 부분적으로 들떠서 배부름 현상이 발생되는 일없이 항상 편평한 상태를 유지시켜서, 상부슬래브(23)를 더욱 균일하고 정밀하게 성형하여 줄 수 있으므로, 시공이 완료된 중공의 슬래브(20)가 보다 안정적인 단면구조로 우수한 구조적 강도를 발휘하여 균열이 발생됨을 예방할 수 있는 장점이 있다.Thus, in the present invention, first, in the process of constructing the hollow slab 20 on the upper portion of the lower structure 10, the hollow member 24 is partially lifted from the lower slab 21 without the occurrence of a full stomach phenomenon. By maintaining a flat state at all times, the upper slab 23 can be molded more uniformly and precisely, and thus the hollow slab 20 having completed construction exhibits excellent structural strength with a more stable cross-sectional structure to prevent cracks from occurring. There are advantages to it.

둘째, 하부구조물(10)의 상부에 중공의 슬래브(20)를 시공하는 과정에서, 하부슬래브(21)와 일체로 돌출 형성되어 이후에 복부슬래브(22)의 일부가 되는 구속용 돌부(22b)로서 중공부재(24)들을 구속하여 주게 되므로, 중공부재(24)들을 고정시키기 위해서 별도로 고정앵커 등을 설치하게 되는 등의 불필요한 작업을 생략하게 하여서 작업부담을 경감시키고 작업시간을 단축시킬 수 있는 등의 장점이 있다.Second, in the process of constructing the hollow slab 20 on the upper portion of the lower structure 10, the convex protrusion 22b which is formed integrally with the lower slab 21 and becomes part of the abdominal slab 22 afterwards. Since the hollow member 24 is constrained, unnecessary work such as installing a separate anchor to fix the hollow member 24 can be omitted, thereby reducing the workload and reducing the work time. Has the advantage.

이하, 첨부도면에 도시되는 구체적인 실시예를 통하여 본 발명의 기술내용을 상세히 설명하면 다음과 같다.Hereinafter, the technical details of the present invention through the specific embodiments shown in the accompanying drawings in detail.

본 발명에서 중공 슬래브교는 도 2에서와 같이, 먼저 시공 위치에 기초받침과 교각을 세워서 하부구조물(10)을 시공하고, 하부구조물(10)의 상부에 지보재(B)로 지지되도록 거푸집(A)을 가설한 후에, 거푸집(A) 위에 철근콘크리트로서 하부슬래브(21)를 선 성형하고 복부 및 상부슬래브(22)(23)를 후 성형하면서 중공부재(24)가 단면내에 매립되도록 중공의 슬래브(20)를 시공하고, 시공된 중공의 슬래브(20) 위에 노면(30) 및 방호벽(40)을 시공하여 완성하게 되는 바, 본 발명에서 통상적인 기술내용이라 할 수 있는 하부구조물(10)의 시공, 거푸집(A) 및 지보재(B)의 가설 등에 대하여는 상세한 설명을 생략하고, 중공의 슬래브(20)를 시공하 는 작업과정을 단계별로 상세히 설명하기로 한다.Hollow slab bridge in the present invention, as shown in Figure 2, first to build the base structure and the piers in the construction position to form the lower structure 10, the formwork to be supported by the support material (B) on top of the lower structure (10) After the hypothesis, hollow slab is formed so that the hollow member 24 is embedded in the cross-section while preforming the lower slab 21 as the reinforced concrete on the formwork A and post-molding the abdomen and the upper slab 22, 23. (20) to the construction of the road surface 30 and the barrier wall 40 on the hollow slab (20) to be constructed, the bar structure of the lower structure (10) can be referred to in the present invention Construction, form (A) and the support material (B), such as the hypothesis of the detailed description will be omitted, and will be described in detail step by step the process of construction of the hollow slab (20).

도 3a는 중공부재들을 배치하여 가고정시키는 작업공정을 나타낸 것이다.Figure 3a shows a working process for placing and fixing the hollow members.

상기 중공부재(24)들은 발포성수지를 소재로 하여 만들어진 것으로, 하부 및 복부슬래브(21)(22)의 성형을 위해 거푸집(A) 위에 수평하게 배근되는 하부슬래브용 철근(21a)과 수직으로 세워져서 종,횡측으로 배근되는 복부슬래브용 철근(22a)으로 구획된 공간들마다 나누어서 배치하고, 그 공간들에 배치된 개개의 중공부재(24)는 가고정시켜서 상기 하부슬래브(21)를 성형하기 위해 콘크리트를 타설할 때 임의로 유동되거나 부상하게 됨을 방지하여 주도록 한다.The hollow members 24 are made of a foamed resin material, and stand vertically with the lower slab reinforcing bars 21a horizontally disposed on the formwork A for molding the lower and abdominal slabs 21 and 22. The lower slabs 21 are formed by dividing the spaces divided by the reinforcing bars 22a for abdominal slabs, which are laid in the longitudinal and lateral directions, and temporarily fixing the individual hollow members 24 disposed in the spaces. In order to prevent concrete from being floated or floated, it is necessary to prevent it.

그리고, 상기 중공부재(24)들을 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간에 배치할 때에, 상기 중공부재(24)들과 하부슬래브용 철근(21a) 사이에 별도의 간격유지부재(D)들을 배열 설치하여서, 상기 하부슬래브(21)를 성형을 위해 타설되는 콘크리트에 하부슬래브용 철근(21a)이 설계두께로 정확히 피복될 수 있게 함이 바람직하다.When the hollow members 24 are disposed in a space partitioned by lower and abdominal slabs 21a and 22a, a separate gap between the hollow members 24 and the lower slabs 21a is provided. By arranging the holding members D, it is preferable that the lower slab reinforcing bar 21a can be accurately coated with a design thickness on the concrete to which the lower slab 21 is cast for molding.

또, 상기 중공부재(24)들은 상기 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간들에 배치된 상태에서, 복부슬래브용 철근(22a)에 양단이 고정되는 별도의 고정부재(C)로 결박하여 간단히 가고정시킬 수 있도록 한다.In addition, the hollow member 24 is a separate fixing member that is fixed at both ends to the abdominal slab reinforcing bar (22a) in a state arranged in the space partitioned by the lower and abdominal slab reinforcing bar (21a) (22a) ( Strap it to C) so that it can be temporarily fixed.

이와 같이 상기 중공부재(24)들을 가고정시킨 고정부재(C)는, 상기 상부슬래브(21)의 상면에 중공부재(24)들의 둘레면 하단을 구속하는 구속용 돌부(22b)를 형성한 후에는 제거하여서, 이후에 성형되는 복부 및 상부 슬래브(22)(23)에 매립된 상태로 부식됨을 방지하여, 시공이 완료된 중공의 슬래브(30)에 균열을 일으키지 않도록 예방함이 바람직하다.As described above, the fixing member C temporarily fixing the hollow members 24 forms a restraining protrusion 22b on the upper surface of the upper slab 21 to constrain the lower end of the circumferential surface of the hollow members 24. It is desirable to prevent the corrosion by being embedded in the abdominal and upper slabs 22 and 23 to be molded later, so as not to cause cracks in the hollow slab 30 of which construction is completed.

본 발명의 실시예에서 상기 중공부재(24)들은 각각 둘레면의 하단에 보조 구속수단(24a)을 구비하여서, 상기 하부슬래브(21)의 상면에 형성되는 구속용 돌부(22b)로 구속되는 개개의 중공부재(24)의 둘레면 하단을 더욱 견실하고 긴밀하게 구속시킬 수도 있음을 밝혀 둔다.In the embodiment of the present invention, each of the hollow members 24 is provided with an auxiliary restraining means 24a at the lower end of the circumferential surface, each of which is constrained by a restraining protrusion 22b formed on the upper surface of the lower slab 21. It turns out that the bottom of the circumferential surface of the hollow member 24 may be more firmly and tightly constrained.

여기에서, 상기 보조 구속수단(24a)은 도 4 및 도 5a에서와 같이, 상기 중공부재(24)들의 둘레면 하단에 길이방향으로 적어도 1개이상 요입되는 요홈(241)으로 형성될 수 있다. 이 요홈(241)은 상기 구속용 돌부(22b)를 성형할 때 타설되는 측면 콘크리트의 일부가 채워져서 키결합된 형태로 개개의 중공부재(24) 둘레면 하단을 보다 견실하고 긴밀하게 구속하는데 도움이 된다.Here, the auxiliary restraining means 24a may be formed as a recess 241 recessed at least one or more in the longitudinal direction at the lower end of the circumferential surface of the hollow members 24, as shown in FIGS. 4 and 5A. This groove 241 is a part of the side concrete to be poured when forming the restraining protrusion (22b) is filled with key to help to restrain the bottom of the peripheral surface of the individual hollow member 24 more tightly and tightly Becomes

또, 상기 보조 구속수단(24a)은 도 5b에서와 같이, 상기 중공부재(24)들의 둘레면 하단에 길이방향으로 적어도 1개이상 돌출되는 돌기(242)로 형성될 수 있다. 이 돌기(242)는 상기 구속용 돌부(22b)를 성형할 때에 타설되는 콘크리트의 측면을 향하여 돌출되어 키결합된 형태로 개개의 중공부재(24)의 둘레면 하단을 보다 견실하고 긴밀하게 구속하는데 도움이 된다.In addition, the auxiliary restraining means 24a may be formed as protrusions 242 protruding at least one or more in the longitudinal direction at the lower end of the circumferential surface of the hollow members 24, as shown in FIG. 5B. The protrusion 242 protrudes toward the side of the concrete to be poured when forming the restraining protrusion 22b, and restrains the lower end of the circumferential surface of each hollow member 24 in a keyed form more tightly and tightly. It helps.

도 3b는 하부슬래브 및 구속용 돌부를 성형하는 작업공정을 나타낸 것이다.Figure 3b shows the working process of forming the lower slab and restraining protrusions.

상기 하부슬래브(21)는 미리 배근되는 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간들마다 중공부재(24)들을 배치하여 가고정시킨 상태에서, 상기 거 푸집(A)의 상면으로부터 중공부재(24)들의 하면에 이르기까지 하부슬래브용 철근(21a)이 피복되도록 콘크리트를 타설하고 양생시켜서 성형된다.The lower slab 21 is the upper surface of the form (A) in a state in which the hollow member 24 is temporarily fixed to the space partitioned by the lower and abdominal slab reinforcing bar (21a) (22a) to be reinforcement in advance The concrete is cast and cured so that the lower slab reinforcing bars 21a are covered from the bottom to the lower surfaces of the hollow members 24.

상기 구속용 돌부(22b)는 콘크리트를 타설하여 하부슬래브(21)를 성형할 때에, 그 하부슬래브의 상면에 복부슬래브(22)의 성형 위치마다 상향 돌출되도록 형성하여서 된다. 이때 구속용 돌부(22b)를 형성하도록 타설되는 콘크리트는 상기 복부슬래브용 철근(22a)의 하부를 피복하여 주게 된다.The restraining protrusion 22b is formed so as to protrude upward at each forming position of the abdominal slab 22 on the upper surface of the lower slab when the lower slab 21 is cast by pouring concrete. At this time, the concrete poured to form the restraining protrusion 22b covers the lower part of the abdominal slab reinforcing bar 22a.

이러한 구속용 돌부(22b)는 상기 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간에 배치되어 가고정되는 개개의 중공부재(24) 둘레면 하단을 밀착 구속하여서, 이후에 복부 및 상부슬래브(22)(23)를 성형하기 위해 타설되는 콘크리트가 하부슬래브(21)와 중공부재(24) 사이에 침투하지 못하도록 차단하고, 하부슬래브(21)로부터 중공부재(24)들이 들뜨지 못하도록 붙잡아서, 상기 중공부재(24)들이 콘크리트에 의한 배부름 현상이 발생되지 않고 평탄한 상태를 유지할 수 있게 하여 준다.The restraining protrusion 22b is tightly constrained to the lower end of the periphery of each hollow member 24 which is arranged and temporarily fixed in the space partitioned by the lower and abdominal slab reinforcing bars 21a and 22a, and then the abdomen and It blocks the concrete poured to form the upper slabs 22 and 23 from penetrating between the lower slab 21 and the hollow member 24, and holds the hollow members 24 from the lower slab 21 so that they cannot be lifted. In addition, the hollow members 24 may maintain a flat state without the phenomenon of full load caused by concrete.

그리고, 상기 구속용 돌부(22b)는 상기 하부 및 복부슬래브용 철근(21a)(22a) 중량의 합보다 상기 하부슬래브(21)와 구속용 돌부(22b)를 성형하기 위해 타설되는 콘크리트의 부력이 작게 작용되는 지점에 해당하는 높이(h)로서 하부슬래브(21)의 상면에 돌출 형성하여서 된다.The restraining protrusion 22b has a buoyancy force of concrete poured to form the lower slab 21 and the restraining protrusion 22b rather than the sum of the weights of the lower and abdominal slab reinforcing bars 21a and 22a. The height h corresponding to the small acting point may be formed to protrude on the upper surface of the lower slab 21.

이는 상기 중공부재(24)를 하부슬래브용 철근(21a)에 고정부재(C)로서 가고정시킨 상태에서, 상기 하부슬래브(21)와 구속용 돌부(22b)의 성형시 타설되는 콘크리트에 의한 부력으로 상기 중공부재(24)들이 하부 및 복부슬래브용 철 근(21a)(22a)과 함께 부상하게 됨을 방지하여, 상기 상부슬래브(23)를 균일하고 정밀하게 성형할 수 있도록 하는 동시에, 하부 및 복부슬래브용 철근(21a)(22a)이 정위치에 피복되도록 하는데 도움이 된다.This is because the hollow member 24 is temporarily fixed to the lower slab reinforcing bar (21a) as a fixing member (C), buoyancy due to concrete poured during the molding of the lower slab 21 and the restraining protrusion (22b) This prevents the hollow members 24 from floating together with the lower and abdominal slabs 21a and 22a, so that the upper slab 23 can be uniformly and precisely formed, and the lower and abdomen It is helpful for the slab reinforcing bars 21a and 22a to be coated in place.

여기에서, 상기 구속용 돌부(22b)의 높이(h)는 하부슬래브(21)의 상면으로부터 3~20㎝로 돌출되게 함이 중요하다. 그 이유는, 상기 구속용 돌부(22b)의 높이(h)가 하부슬래브(21)의 상면에서 3㎝이하로 돌출되면 상기 중공부재(24)들의 하부 양단을 확실히 구속하기 어렵고, 상기 구속용 돌부(22b)의 높이(h)가 하부슬래브(21)의 상면에서 20㎝이상이면 상기 하부 및 구속용 돌부(22b)를 형성할 때에 타설되는 콘크리트의 부력이 커져서 중공부재(24)들이 하부 및 복부슬래브용 철근(21a)(22a)과 함께 부상할 수 있기 때문이다.Here, it is important that the height h of the restricting protrusion 22b protrudes from 3 to 20 cm from the upper surface of the lower slab 21. The reason is that when the height h of the restricting protrusion 22b protrudes 3 cm or less from the upper surface of the lower slab 21, it is difficult to reliably restrain the lower ends of the hollow members 24, and the restricting protrusion If the height h of the lower portion 22b is 20 cm or more from the upper surface of the lower slab 21, the buoyancy of the concrete to be poured when forming the lower portion and the restraining protrusion 22b is increased, so that the hollow members 24 are lowered and the abdomen. This is because it can rise together with the reinforcing bar 21a (22a) for the slab.

본 발명의 실시예에서는 상기 중공의 슬래브(20)를 시공하기 위해 구속용 돌부(22b)와 함께 선 성형되는 하부슬래브(21)가 상기 하부구조물(10)의 상부에 미리 위치시켜 둔 교좌장치(E) 위에 안치되게 하여, 시공이 완료된 중공의 슬래브(20)를 교좌장치(E)로 떠받친 슬래브 구조형식으로 시공된 것으로 예시되어 있다.In the embodiment of the present invention, the lower slab 21 which is pre-formed with the restraining protrusion 22b to construct the hollow slab 20 is previously placed on the upper portion of the lower structure (10) E) It is illustrated that the hollow slab 20 is constructed in the form of a slab structure that holds the hollow slab 20 completed by the teaching device E.

도 3c는 복부 및 상부슬래브를 성형하는 작업공정을 나타낸 것이다.Figure 3c shows a working process for shaping the abdomen and the upper slab.

상기 복부 및 상부슬래브(22)(23)는 먼저 복부슬래브용 철근(22a)의 상부에 수평하게 상부슬래브용 철근(23a)을 배근한 후에, 상기 구속용 돌부(22b) 위에 연이어서 복부슬래브용 철근(22a)과 상부슬래브용 철근(23a)이 피복되도록 콘크리트를 타설하고 양생하여, 중공의 슬래브(20)를 이루도록 성형하게 된다.The abdomen and the upper slab 22, 23 is first placed horizontally to the upper slab reinforcing bar 23a horizontally on the upper part of the abdominal slab reinforcing bar (22a), and then connected to the restraining protrusion (22b) for the abdominal slab The concrete is poured and cured so that the reinforcing bar 22a and the upper slab reinforcing bar 23a are coated and molded to form a hollow slab 20.

그리고, 상기 상부슬래브용 철근(23a)과 중공부재(24) 사이에는 간격유지부재(D)들을 배열 설치하여서, 상기 상부슬래브(23)를 성형을 위해 타설되는 콘크리트에 상부슬래브용 철근(23a)이 설계두께로 피복될 수 있게 함이 바람직하다.In addition, by arranging the space maintaining members (D) between the upper slab reinforcing bar (23a) and the hollow member 24, the upper slab (23a) for the upper slab to the concrete to be cast for molding It is desirable to be able to coat with this design thickness.

이와 같이 복부 및 상부슬래브(22)(23)를 성형하여 중공의 슬래브(20)의 시공을 완료한 후에는, 도 3d에서와 같이 거푸집(A) 및 지보재(B)를 제거하고, 상부슬래브(23) 위에 방호벽(40)과 아스팔트로 포장된 노면(30)을 설치하는 등의 마무리 공정을 수행하여 중공 슬래브교를 완성하게 된다.After completing the construction of the hollow slab 20 by forming the abdomen and the upper slab 22, 23, as shown in Figure 3d, the form (A) and the support material (B) is removed, and the upper slab ( 23) to finish the hollow slab bridge by performing a finishing process, such as installing the protective wall 40 and the asphalt-paved road surface (30).

도 6 및 도 7은 본 발명의 일실시예를 나타낸 것이다.6 and 7 show an embodiment of the present invention.

본 발명의 일실시예도 본 발명도 하부구조물(10)의 상부에 가설되는 거푸집(A) 위에서 철근콘크리트로서 하부슬래브(21)를 선 성형하고 복부 및 상부슬래브(22)(23)는 후 성형하는 중에 발포성수지로 된 복수개의 중공부재(24)들을 매립시켜서, 상기 하부구조물(10) 상부에 중공부재(24)들이 단면내에 매립된 중공의 슬래브(20)를 시공하는 것에 있어서, 상기 하부슬래브(21)의 성형 전에 배근되는 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간마다 중공부재(24)들을 각각 배치하여 가고정시키고, 상기 하부슬래브(21)를 선 성형할 때 그 상면에 복부슬래브(22)의 성형 위치마다 상기 중공부재(24)들의 둘레면 하단을 밀착 구속할 수 있도록 구속용 돌부(22b)를 일체로 형성한 후에, 상기 구속용 돌부(22b)의 상단으로부터 연이어지도록 복부 및 상부슬래브(22)(23)를 후 성형하여서 된 점에서 본 발명의 실시예와 기술구성이 동일하다.One embodiment of the present invention also the present invention is preformed the lower slab 21 as reinforced concrete on the formwork (A) is installed on the upper portion of the lower structure 10 and the abdomen and the upper slab 22 (23) is post-molded In embedding the plurality of hollow members 24 made of a foamed resin in the middle, and in the construction of the hollow slab 20 in which the hollow members 24 are embedded in the cross section on the lower structure 10, the lower slab ( The hollow members 24 are temporarily arranged and temporarily fixed in the space partitioned by the lower and abdominal slab reinforcing bars 21a and 22a, which are arranged before the molding of 21, and an upper surface thereof when the lower slab 21 is preformed. After forming the constraining protrusion 22b integrally with each other at the molding position of the abdominal slab 22 so that the lower end of the circumferential surface of the hollow members 24 can be tightly constrained, the constraining protrusion 22b is continuously connected to the upper end of the constraining protrusion 22b. Abdomen and upper slab (22, 23) It is the same as the embodiment of the present invention and the technical configuration in that it was molded after.

단, 본 발명의 일실시예에서 상기 중공부재(24)의 전,후측 끝부분에는 그 좌,우면과 상면이 경사져서 단면적이 점차로 작게 형성되는 전,후측 모따기부(24b)(24c)를 더 포함하여서 된 것이다.However, in one embodiment of the present invention, the front and rear ends of the hollow member 24 are further inclined to the left and right surfaces and the upper surface, so that the front and rear chamfers 24b and 24c are gradually smaller in cross section. It was included.

이와 같은 본 발명의 일실시예에 따른 전,후측 모따기부(24b)(24c)는 상기 복부슬래브(22)의 전,후측 벽면과 상기 상부슬래브(23)의 전,후측 하면에 각각 경사지는 보강용 헌치부(22c)(23c)를 형성할 수 있게 하여 주어서, 국부적인 응력을 많이 받는 복부슬래브(22)의 전,후측 단부를 보강하여 주는 동시에, 복부슬래브(22)와 상부슬래브(23)가 만나는 전,후측 접선부위의 강도를 증대시켜서 균열이 발생됨을 방지할 수 있는 이점이 있다.The front and rear chamfers 24b and 24c according to the exemplary embodiment of the present invention are inclined to the front and rear wall surfaces of the abdominal slab 22 and the front and rear lower surfaces of the upper slab 23, respectively. It is possible to form the haunting portions 22c and 23c, thereby reinforcing the front and rear ends of the abdominal slab 22 subjected to a lot of local stress, and the abdominal slab 22 and the upper slab 23. There is an advantage that can prevent the occurrence of cracks by increasing the strength of the front and rear tangential region where the.

본 발명의 일실시예에서 상기 중공부재(24)들은 각각 둘레면의 하단 보조 구속수단(24a)을 구비하여서, 상기 하부슬래브(21)의 상면에 형성되는 구속용 돌부(22b)로 구속되는 개개의 중공부재(24)의 둘레면 하단을 더욱 견실하고 긴밀하게 구속시킬 수 있게 한 점은 위의 본 발명 실시예에서와 같다.In one embodiment of the present invention, each of the hollow members 24 is provided with a constraining protrusion 22b formed on the upper surface of the lower slab 21, each having a lower auxiliary auxiliary restraining means 24a on the circumferential surface. The point that makes it possible to more tightly and tightly constrain the bottom of the circumferential surface of the hollow member 24 is the same as in the embodiment of the present invention above.

도 8 및 도 9는 본 발명의 다른 실시예를 나타낸 것이다.8 and 9 show another embodiment of the present invention.

본 발명의 다른 실시예도 하부구조물(10)의 상부에 가설되는 거푸집(A) 위에서 철근콘크리트로서 하부슬래브(21)를 선 성형하고 복부 및 상부슬래브(22)(23)는 후 성형하는 중에 발포성수지로 된 복수개의 중공부재(24)들을 매립시켜서, 상기 하부구조물(10) 상부에 중공부재(24)들이 단면내에 매립된 중공의 슬래브(20)를 시공하는 것에 있어서, 상기 하부슬래브(21)의 성형 전에 배근되는 하부 및 복부슬래 브용 철근(21a)(22a)으로 구획된 공간마다 중공부재(24)들을 각각 배치하여 가고정시키고, 상기 하부슬래브(21)를 선 성형할 때 그 상면에 복부슬래브(22)의 성형 위치마다 상기 중공부재(24)들의 둘레면 하단을 밀착 구속할 수 있도록 구속용 돌부(22b)를 일체로 형성한 후에, 상기 구속용 돌부(22b)의 상단으로부터 연이어지도록 복부 및 상부슬래브(22)(23)를 후 성형하여서 된 점에서 본 발명의 실시예와 기술구성이 동일하다.Another embodiment of the present invention also preforms the lower slab 21 as reinforced concrete on the formwork A installed on top of the substructure 10 and the abdominal and upper slabs 22, 23 are foamed resins during post-molding. By embedding a plurality of hollow members 24, the hollow slab 20 in which the hollow members 24 are embedded in the cross-section on the upper portion of the lower structure 10, of the lower slab 21 The hollow members 24 are temporarily arranged and temporarily fixed in the space partitioned by the lower and abdominal slab reinforcing bars 21a and 22a, respectively, before forming, and the upper slab 21 is formed on the upper surface when the lower slab 21 is preformed. After forming the constraining protrusion 22b integrally so as to tightly constrain the lower end of the circumferential surface of each of the hollow members 24 at each molding position of the 22, the abdomen and After the upper slab (22) (23) This embodiment and the technical configuration of the present invention in hayeoseo the point is the same.

단, 본 발명의 다른 실시예에서 상기 하부 및 복부슬래브(21)(22)를 성형할 때에 복수개의 긴장재(25)들을 1개조로 하여 단면내에 매설되도록 하되, 1개조의 긴장재(25)들 중 일부는 일측단이 하부슬래브(21)의 일측 끝부분에서 인장정착단(25a)이 되고 타측단은 복부슬래브(22)의 타측 끝부분 근처에서 고정정착단(25b)이 되게 설치하며, 1개조의 긴장재(25)들 중 다른 일부는 일측단이 하부슬래브(21)의 타측 끝부분에서 인장정착단(25c)이 되고 타측단은 복부슬래브(22)의 일측 끝부분 근처에서 고정정착단(25d)이 되게 설치하여서 된 것이다.However, in another embodiment of the present invention, when the lower and abdominal slabs 21 and 22 are molded, a plurality of tension members 25 may be embedded in a cross section, but one of the tension members 25 may be included. Some of them are installed so that one end becomes the tension fixing end 25a at one end of the lower slab 21 and the other end is the fixed fixing end 25b near the other end of the abdominal slab 22, one set The other part of the tension member 25 of the one end is the tension fixing end (25c) at the other end of the lower slab 21 and the other end is fixed anchoring end (25d near the one end of the abdominal slab 22) This is because it is installed.

이와 같은 본 발명의 일실시예에 따르면, 기본적으로 상기 중공의 슬래브(20)에 긴장재(25)들로서 프리스트레스를 도입하여서 장경간으로 시공할 수 있게 함은 물론이고, 상기 중공의 슬래브(20)에 긴장재(25)들로서 프리스트레스를 도입할 때에, 일부 긴장재(25)들은 하부슬래브(21)의 일측 끝부분에 설정된 인장정착단(25a)을 통해 인장작업을 수행하고, 다른 일부 긴장재(25)들은 하부슬래브(21)의 타측 끝부분에 설정된 인장정착단(25c)을 통해 인장작업을 수행하게 되므로, 중공의 슬래브(20) 양단에 집중되는 지압응력을 분산 감소시켜서, 중공의 슬래브(20)가 쉽게 손상됨을 방지하여 줄 수 있는 이점을 갖는다.According to one embodiment of the present invention, by introducing the prestress as the tension material 25 to the hollow slab 20 basically to be constructed in a long span, of course, to the hollow slab 20 When introducing prestress as tension members 25, some tension members 25 perform tensioning through tension settling ends 25a set at one end of the lower slab 21, and some other tension members 25 are lowered. Since the tensioning operation is performed through the tension fixing end 25c set at the other end of the slab 21, by reducing the dispersion of acupressure stress concentrated at both ends of the hollow slab 20, the hollow slab 20 is easily It has the advantage of preventing damage.

그리고, 상기 긴장재(25)들은 상기 중공의 슬래브(20)의 시공이 완료된 후 거푸집(A)을 지지하는 지보재(B)를 제거하기 전에 인장시켜서 중공의 슬래브(20)에 프리스트레스를 도입한다. 이는 하부슬래브(21)의 하단에 인장응력이 초과되지 않고 압축응력 상태를 유지하게 하여서, 중공의 슬래브(20)가 인장파괴에 견실히 대응할 수 있게 하기 위함이다.In addition, the tension members 25 are tensioned before removing the support material B supporting the form A after the construction of the hollow slab 20 is completed to introduce prestress into the hollow slab 20. This is to maintain the compressive stress state without exceeding the tensile stress at the lower end of the lower slab 21, so that the hollow slab 20 can cope with the tensile failure.

도 1은 종래 발명을 종단면도로 나타낸 것임1 is a longitudinal cross-sectional view showing a conventional invention

도 2는 본 발명 중공 슬래브교의 시공방법에 따른 실시상태를 일부절결 정면도로 나타낸 것임Figure 2 is a partial cutaway front view showing an embodiment according to the construction method of the present invention hollow slab bridge

도 3a 내지 도 3d는 본 발명 중공 슬래브교의 시공방법에 따른 작업과정을 단계별로 나타낸 것임Figure 3a to 3d is a step-by-step showing the operation process according to the construction method of the present invention hollow slab bridge

도 4는 본 발명 중공 슬래브교의 시공방법에 채용된 중공부재를 사시도로 나타낸 것임Figure 4 is a perspective view of the hollow member employed in the construction method of the present invention hollow slab bridge

도 5a 및 도 5b는 본 발명 중공 슬래브교의 시공방법에 채용된 중공부재의 실시상태를 부분 단면도로 나타낸 것임5a and 5b is a partial cross-sectional view showing an embodiment of the hollow member employed in the construction method of the hollow slab bridge of the present invention

도 6은 본 발명 일실시예에 따른 중공부재를 사시도로 나타낸 것임Figure 6 is a perspective view of a hollow member according to an embodiment of the present invention

도 7은 본 발명 일실시예에 따른 중공부재가 매설된 중공의 슬래브를 일부절결 평면도로 나타낸 것임7 is a partial cutaway plan view of a hollow slab embedded with a hollow member according to an embodiment of the present invention.

도 8은 본 발명의 다른 실시예에 따른 긴장재가 설치된 중공의 슬래브를 일부절결 평면도로 나타낸 것임8 is a partially cutaway plan view of a hollow slab in which a tension member is installed according to another exemplary embodiment of the present invention.

도 9는 본 발명의 다른 실시예에 따른 긴장재로서 중공의 슬래브에 프리스트레스를 도입하는 상태를 정 단면도로 나타낸 것임9 is a front cross-sectional view showing a state in which the prestress is introduced into the hollow slab as a tension material according to another embodiment of the present invention.

< 도면의 주요 부분에 대한 부호의 설명 ><Description of Symbols for Main Parts of Drawings>

10: 하부구조물 20: 중공의 슬래브10: substructure 20: hollow slab

21: 하부슬래브 21a: 하부슬래브용 철근21: Lower slab 21a: Reinforcing bar for lower slab

22: 복부슬래브 22a: 복부슬래브용 철근22: Abdominal slab 22a: Reinforcing bar for abdominal slab

22b: 구속용 돌부 22c: 보강용 헌치부22b: restraining protrusion 22c: reinforcing haunt

23: 상부슬래브 23a: 상부슬래브용 철근23: upper slab 23a: rebar for upper slab

23c: 보강용 헌치부 24: 중공부재23c: reinforcing haunch 24: hollow member

24a: 보조 구속수단 24b, 24c: 전,후측 모따기부24a: auxiliary restraining means 24b, 24c: front and rear chamfers

25: 긴장재 25a, 25c: 인장정착단25: tension member 25a, 25c: tensile fixing end

25b, 25d: 고정정착단 A: 거푸집25b, 25d: Fixed fixing end A: Formwork

B: 지보재 C: 고정부재B: Supporting material C: Fixing member

D: 간격유지부재 h: 높이D: spacing member h: height

Claims (11)

하부구조물(10)의 상부에 가설되는 거푸집(A) 위에서 철근콘크리트로서 하부슬래브(21)를 선 성형하고 복부 및 상부슬래브(22)(23)는 후 성형하는 중에 발포성수지로 된 복수개의 중공부재(24)들을 매립시켜서, 상기 하부구조물(10) 상부에 중공부재(24)들이 단면내에 매립된 중공의 슬래브(20)를 시공하는 것에 있어서,A plurality of hollow members made of foamed resin during linear molding of the lower slab 21 as a reinforced concrete on the formwork A installed on the upper part of the lower structure 10, and the abdomen and the upper slab 22 and 23 are post-molded. In embedding the (24), in the construction of the hollow slab 20, the hollow member 24 is embedded in the cross-section on top of the lower structure 10, 상기 하부슬래브(21)의 성형 전에 배근되는 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간마다 중공부재(24)들을 각각 배치하여 가고정시키고, 상기 하부슬래브(21)를 선 성형할 때 그 상면에 복부슬래브(22)의 성형 위치마다 상기 중공부재(24)들의 둘레면 하단을 밀착 구속할 수 있도록 구속용 돌부(22b)를 일체로 형성한 후에, 상기 구속용 돌부(22b)의 상단으로부터 연이어지도록 복부 및 상부슬래브(22)(23)를 후 성형하여서 됨을 특징으로 하는 중공 슬래브교의 시공방법.The hollow members 24 are temporarily arranged and temporarily fixed in each of the spaces partitioned by the lower and abdominal slab reinforcing bars 21a and 22a, which are arranged before the lower slab 21 is formed, and the lower slab 21 is linearly formed. When the convex projection 22b is integrally formed on the upper surface of the abdominal slab 22 so as to be tightly constrained at the lower end of the circumferential surface of the hollow members 24, the confinement projection 22b is formed. A method of constructing a hollow slab bridge, characterized in that by forming the abdomen and the upper slab (22) and (23) so as to connect from the top of the. 제1항에 있어서, 상기 중공부재(24)들을 하부 및 복부슬래브용 철근(21a)(22a)으로 구획된 공간에 배치할 때에, 상기 중공부재(24)들과 하부슬래브용 철근(21a) 사이에 별도의 간격유지부재(D)들을 배열 설치하여서 됨을 특징으로 하는 중공 슬래브교의 시공방법.The method of claim 1, wherein the hollow members 24 are disposed between the hollow members 24 and the lower slab reinforcing bars 21a when the hollow members 24 are disposed in a space partitioned by the lower and abdominal slab reinforcing bars 21a and 22a. Construction method of the hollow slab bridge, characterized in that by installing a separate spacing maintaining members (D) in the arrangement. 제1항에 있어서, 상기 중공부재(24)들은 상기 하부 및 복부슬래브용 철 근(21a)(22a)으로 구획된 공간들에 배치된 상태에서, 복부슬래브용 철근(22a)에 양단이 고정되는 별도의 고정부재(C)로 결박하여 간단히 가고정시킬 수 있도록 함을 특징으로 하는 중공 슬래브교의 시공방법.The method of claim 1, wherein the hollow member 24 is fixed at both ends to the reinforcing bar 22a for the abdominal slab in a state in which the hollow member 24 is disposed in the spaces partitioned by the lower and abdominal slab reinforcing bars 21a, 22a. Construction method of a hollow slab bridge characterized in that to be temporarily fixed by binding to a separate fixing member (C). 제1항에 있어서, 상기 중공부재(24)들은 각각 둘레면의 하단에 보조 구속수단(24a)을 구비하여서 됨을 특징으로 하는 중공 슬래브교의 시공방법.The method of claim 1, wherein the hollow members (24) are each provided with an auxiliary restraining means (24a) at the lower end of the circumferential surface. 제4항에 있어서, 상기 보조 구속수단(24a)은 상기 중공부재(24)들의 둘레면 하단에 길이방향으로 적어도 1개이상 요입되는 요홈(241)으로 형성됨을 특징으로 하는 중공 슬래브교의 시공방법.The method of claim 4, wherein the auxiliary restraining means (24a) is a hollow slab bridge construction method characterized in that formed in the groove (241) recessed at least one or more in the longitudinal direction at the lower end of the peripheral surface of the hollow member (24). 제4항에 있어서, 상기 보조 구속수단(24a)은 상기 중공부재(24)들의 둘레면 하단에 길이방향으로 적어도 1개이상 돌출되는 돌기(242)로 형성됨을 특징으로 하는 중공 슬래브교의 시공방법.The method of claim 4, wherein the auxiliary restraining means (24a) is a hollow slab bridge construction method characterized in that it is formed with at least one protrusion (242) protruding in the longitudinal direction at the lower end of the peripheral surface of the hollow member (24). 제1항에 있어서, 상기 구속용 돌부(22b)는 상기 하부 및 복부슬래브용 철근(21a)(22a) 중량의 합보다 상기 하부슬래브(21)와 구속용 돌부(22b)를 성형하기 위해 타설되는 콘크리트의 부력이 작게 작용되는 지점에 해당하는 높이(h)로서 하부슬래브(21)의 상면에 돌출 형성하여서 됨을 특징으로 하는 중공 슬래브교의 시공방법.2. The restraining protrusion 22b is poured to form the lower slab 21 and the restraining protrusion 22b rather than the sum of the weights of the lower and abdominal slab reinforcing bars 21a and 22a. Hollow slab bridge construction method characterized in that the height (h) corresponding to the point where the buoyancy of the concrete acts small to protrude on the upper surface of the lower slab (21). 제7항에 있어서, 상기 구속용 돌부(22b)의 높이(h)는 하부슬래브(21)의 상면으로부터 3~20㎝로 돌출되게 함을 특징으로 하는 중공 슬래브교의 시공방법.8. The method of construction of a hollow slab bridge according to claim 7, wherein the height h of the restricting protrusion 22b protrudes from 3 to 20 cm from an upper surface of the lower slab 21. 제1항에 있어서, 상기 상부슬래브용 철근(23a)과 중공부재(24) 사이에는 간격유지부재(D)들을 배열 설치하여서 됨을 특징으로 하는 중공 슬래브교의 시공방법.The method of claim 1, wherein the space between the upper slab reinforcing bar (23a) and the hollow member (24) is provided by arranging the interval holding member (D). 제1항에 있어서, 상기 중공부재(24)의 전,후측 끝부분에는 그 좌,우면과 상면이 경사져서 단면적이 점차로 작게 형성되는 전,후측 모따기부(24b)(24c)를 더 포함하여서 됨을 특징으로 하는 중공 슬래브교의 시공방법.The front and rear ends of the hollow member 24 further include front and rear chamfers 24b and 24c in which the left and right surfaces and the top surface are inclined to form a cross-section. Hollow slab bridge construction method characterized in that. 제1항에 있어서, 상기 하부 및 복부슬래브(21)(22)를 성형할 때에 복수개의 긴장재(25)들을 1개조로 하여 단면내에 매설되도록 하되, 1개조의 긴장재(25)들 중 일부는 일측단이 하부슬래브(21)의 일측 끝부분에서 인장정착단(25a)이 되고 타측단은 복부슬래브(22)의 타측 끝부분 근처에서 고정정착단(25b)이 되게 설치하며, 1개조의 긴장재(25)들 중 다른 일부는 일측단이 하부슬래브(21)의 타측 끝부분에서 인장정착단(25c)이 되고 타측단은 복부슬래브(22)의 일측 끝부분 근처에서 고정정착단(25d)이 되게 설치하여서 됨을 특징으로 하는 중공 슬래브교의 시공방법.The method of claim 1, wherein when forming the lower and the abdominal slab 21, 22, a plurality of tension members (25) in one set to be embedded in the cross section, some of one set of tension members (25) One end of the lower slab 21 is a tension fixing end (25a) at one end and the other end of the abdominal slab 22 is installed to be a fixed fixing end (25b) near the other end, one set of tension material ( The other part of the 25 is one end is the tension fixing end (25c) at the other end of the lower slab 21 and the other end is a fixed fixation end (25d) near one end of the abdominal slab (22) Hollow slab bridge construction method characterized in that the installation.
KR1020080033663A 2008-04-11 2008-04-11 Construction method of hollow slab bridge KR101024369B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080033663A KR101024369B1 (en) 2008-04-11 2008-04-11 Construction method of hollow slab bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080033663A KR101024369B1 (en) 2008-04-11 2008-04-11 Construction method of hollow slab bridge

Publications (2)

Publication Number Publication Date
KR20090108305A true KR20090108305A (en) 2009-10-15
KR101024369B1 KR101024369B1 (en) 2011-03-23

Family

ID=41551720

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080033663A KR101024369B1 (en) 2008-04-11 2008-04-11 Construction method of hollow slab bridge

Country Status (1)

Country Link
KR (1) KR101024369B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101935983A (en) * 2010-08-27 2011-01-05 郑州大学 Construction method for assembling integral hollow slab bridge
CN103993750A (en) * 2014-05-16 2014-08-20 河南省交通工程加固有限责任公司 Reinforcement method of hollow component for engineering
CN105088932A (en) * 2014-05-06 2015-11-25 郑州大学 Novel prefabricated hollow slab and hollow slab bridge construction method using same
CN108547210A (en) * 2018-06-21 2018-09-18 烟台大学 A kind of highway hollow slab bridge and construction method using old plate

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862609A (en) * 2016-05-25 2016-08-17 郑州大学 Steel belt and bolt interlined hooping method for reinforcing hollow slab bridges and hooping system thereof
KR102275286B1 (en) 2021-03-08 2021-07-13 대한강관 주식회사 Hollow slab structure using corrugated steel pipe and corrugated steel plate

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07166556A (en) * 1993-12-17 1995-06-27 Kurimoto Ltd Construction method for hollow foundation slab
JP2001107499A (en) 1999-08-03 2001-04-17 Daiwa House Ind Co Ltd Hollow slab and its construction method
KR100508532B1 (en) 2002-10-23 2005-08-17 주식회사 용마엔지니어링 Structure of Bridge with Hollow Slab and Constructing Method Thereof
KR100681849B1 (en) 2005-01-11 2007-02-15 채성태 Fabricated Hollow Precast Concrete Slab

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101935983A (en) * 2010-08-27 2011-01-05 郑州大学 Construction method for assembling integral hollow slab bridge
CN105088932A (en) * 2014-05-06 2015-11-25 郑州大学 Novel prefabricated hollow slab and hollow slab bridge construction method using same
CN103993750A (en) * 2014-05-16 2014-08-20 河南省交通工程加固有限责任公司 Reinforcement method of hollow component for engineering
CN103993750B (en) * 2014-05-16 2016-04-27 河南省交通工程加固有限责任公司 A kind of reinforcement means of engineering hollow unit
CN108547210A (en) * 2018-06-21 2018-09-18 烟台大学 A kind of highway hollow slab bridge and construction method using old plate
CN108547210B (en) * 2018-06-21 2024-01-19 烟台大学 Expressway hollow slab bridge utilizing old slab and construction method

Also Published As

Publication number Publication date
KR101024369B1 (en) 2011-03-23

Similar Documents

Publication Publication Date Title
KR101024369B1 (en) Construction method of hollow slab bridge
KR101275754B1 (en) Psc girder with shear block, psc girder making method with shear block and bridge construction method using psc girder with shear block
KR100999660B1 (en) multi span precast parts which has a construction improvement function
KR20130102898A (en) Pier construction method using pile and precast capbeam
KR101860512B1 (en) Method for reinforcing cross section installation of ground and underwater structure using integral mold module
KR20090050520A (en) Libbed half pc slab and manufacturing method of the same
KR101308792B1 (en) Various Section Box Girder And Manufacturing Method thereof, And Bridge Construction Method Using The Same
KR100876388B1 (en) Stay in place deck precast panel
KR100984249B1 (en) Bridge construction method using strength connector detail and composite curing pannel
KR101344219B1 (en) Prestressed concrete girder strengthened by lateral compressive stresses due to bi-axial stress effect and fabrication method therefor
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR20090080666A (en) Hollow concrete girder making method and bridge construction method therewith
KR101007012B1 (en) Reinforcement structure for tunnel and reinforcement method using the same
KR100984247B1 (en) Bridge construction method using strength connector detail joined with rebar of upper flange concrete
KR100989153B1 (en) Psc girder connection structure with strength connector detail for substitution of rebar placement in deck and bridge construction method using the same
KR100669860B1 (en) Asymmetry Pretensioning Precast Beam Girder- APP Beam Girder
KR100279018B1 (en) Construction method of hollow slab bridge
KR100508532B1 (en) Structure of Bridge with Hollow Slab and Constructing Method Thereof
KR101389821B1 (en) Prestressed concrete girder with means to add additional stress and method of production and maintenance thereof
KR101064752B1 (en) Deck for concrete slab construction
KR20200004087A (en) Method constructing the reinforcing materials to the minus moment of continuous girder
KR200478204Y1 (en) Rise preventing device of hollow materials for hollow core slab
KR101340871B1 (en) Psc girder and psc girder making method using concrete saddle and psc girder thereof
KR20060056008A (en) Construction method for p.s.c. girder bridges and bridges production it
KR101389819B1 (en) Continuous prestressed concrete girder structure and construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140226

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150316

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160316

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170316

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20180316

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20190318

Year of fee payment: 9