KR200413470Y1 - The prefabricated revetment base block - Google Patents

The prefabricated revetment base block Download PDF

Info

Publication number
KR200413470Y1
KR200413470Y1 KR2020050037193U KR20050037193U KR200413470Y1 KR 200413470 Y1 KR200413470 Y1 KR 200413470Y1 KR 2020050037193 U KR2020050037193 U KR 2020050037193U KR 20050037193 U KR20050037193 U KR 20050037193U KR 200413470 Y1 KR200413470 Y1 KR 200413470Y1
Authority
KR
South Korea
Prior art keywords
anchor
block
construction
base block
river
Prior art date
Application number
KR2020050037193U
Other languages
Korean (ko)
Inventor
박성수
Original Assignee
극동엔지니어링(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 극동엔지니어링(주) filed Critical 극동엔지니어링(주)
Priority to KR2020050037193U priority Critical patent/KR200413470Y1/en
Application granted granted Critical
Publication of KR200413470Y1 publication Critical patent/KR200413470Y1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/14Preformed blocks or slabs for forming essentially continuous surfaces; Arrangements thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

개시된 본 고안은 하천제방 법면에 호안 시공을 위해 하천바닥에 설치되는 조립식 호안기초블록에 관한 것이다.The present invention disclosed relates to a prefabricated revetment base block installed on the riverbed for revetment construction on the river bank.

본 고안에 따른 조립식 호안기초블록은, 상·하단부에 돌부(12,14)가 서로 다른 방향을 향하여 돌출형성되고 각각의 돌부(12,14) 중앙에는 이들의 연속된 조립을 위해 앵커홀(16)이 천공된 호안기초블록(1)과, 하나의 호안기초블록(1)의 하단돌부(14)와 다른 하나의 호안기초블록(1)의 상단돌부(12) 각각에 형성된 앵커홀(16)이 연통되도록 두 개의 호안기초블록이 배치된 상태에서 상기 앵커홀(16)을 동시에 관통하면서 서로 이웃하는 호안기초블록을 연결하는 앵커(2)를 포함하여 이루어져, 그 시공이 매우 간단하면서도 블록간 결속력이 매우 견고하여 장마철과 같은 우수기 때 하천의 유량 및 유속이 빨라지더라도 붕괴되거나 해체되지 않으며, 수중 시공시 물길 차단을 위한 별도의 가시설 없이도 용이하게 시공할 수 있어 공기 단축 및 인력의 소모를 줄일 수 있는 효과가 있다.Prefabricated revetment base block according to the present invention, the protrusions 12, 14 at the upper and lower ends protruded in different directions, and each of the protrusions 12, 14 in the center of the anchor hole 16 for their continuous assembly Anchor holes 16 formed in each of the raft foundation block (1), the bottom projection 14 of one raft foundation block (1) and the top projection 12 of the other raft foundation block (1) is perforated It consists of an anchor (2) for connecting the neighboring banks of the banks at the same time while passing through the anchor hole 16 at the same time the two banks of the base block is arranged to communicate with each other, the construction is very simple, but the interlocking force It is very solid and does not disintegrate or disintegrate even when the river flows and flows faster during rainy seasons, and it can be easily installed without additional facilities to block the water during construction.There are effective.

하천 제방, 호안, 호안기초블록, 앵커 River Dike, Shoan, Shoan Base Block, Anchor

Description

조립식 호안기초블록{The prefabricated revetment base block}Prefabricated Revetment Base Block

도 1은 종래 일반적으로 하천 제방에 설치되는 호안의 시공상태를 나타낸 예시도.Figure 1 is an exemplary view showing a construction state of the lake is generally installed on the river bank embankment.

도 2은 본 고안에 따른 조립식 호안기초블록의 조립과정을 보여주기 위한 분해 사시도.Figure 2 is an exploded perspective view showing the assembly process of the prefabricated revetment base block according to the present invention.

도 3은 본 고안에 따른 조립식 호안기초블록의 시공상태를 나타내는 예시도.3 is an exemplary view showing a construction state of the prefabricated revetment base block according to the present invention.

<도면의 주요 부위에 대한 부호설명><Description of the code for the main parts of the drawing>

1: 호안기초블록1: Shoan foundation block

2: 앵커2: anchor

12: 상단돌부12: top protrusion

14: 하단돌부14: lower protrusion

20: 앵커관20: anchor pipe

22: 앵커봉22: anchor rod

24: 너트24: nut

220: 외확장형 돌기220: external extension projection

본 고안은 하천 수중에 하천 가장자리를 따라 설치되는 하천 호안기초블록에 관한 것으로, 앵커를 통한 블록 조립식으로 그 시공이 매우 간단하면서도 블록간 결속력이 매우 견고하여 장마철과 같은 우수기 때 하천의 유량 및 유속이 빨라지더라도 붕괴되거나 해체되지 않으며, 수중 시공시 물길 차단을 위한 별도의 가시설 없이도 용이하게 시공할 수 있어 공기 단축 및 인력의 소모를 줄일 수 있는 조립식 호안기초블록에 관한 것이다.The present invention relates to a river shore foundation block that is installed along the edge of the river in the river water, the block assembly type through the anchor, the construction is very simple, but the solidity between the blocks is very solid, the flow rate and flow rate of the river during rainy season like rainy season Even if the speed is not collapsed or dismantled, and can be easily installed without additional provisions for blocking the water during construction, relates to a prefabricated revetment base block that can shorten the air and reduce the consumption of manpower.

일반적으로, 호안(護岸)은 하천의 법면을 보호해서 폭우나 홍수가 발생할 경우 유수(流水)에 의하여 하천의 범람이나 유실 및 붕괴되는 것을 방지하기 위하여 그 법면에 시설하는 공작물이다. 이러한 호안을 시공하기 위해서는 사방공사가 필수적으로 병행되는데, 이는 하천제방에 석조나 콘크리트 블록을 시공하는 것을 말한다.Generally, a shelter is a workpiece installed on the surface of the river to protect the river's surface and prevent flooding, loss, and collapse of the river by running water in case of heavy rain or flood. In order to construct such a revetment, building construction is indispensable, which means the construction of stone or concrete blocks on river banks.

도 1은 일반적인 호안에 콘크리트 블록이 시공된 상태를 나타내는 예시도가 도시된다.1 is an exemplary view showing a state in which a concrete block is constructed in a general arc.

하천(1)의 제방에 연접한 호안을 형성하기 위해 콘크리트블록(10)을 설치하는 경우 먼저 하천(1)의 바닥면에 유로를 따라 길이 방향으로 기초콘크리트(3)가 설치된다. 기초콘크리트(3) 상부에는 다수개가 엇갈려 적층되는 잡석부(4) 및 법면(2)에 직접 타설되는 콘크리트 블록(5)이 설치된다. 이때 콘크리트 블록부(5) 의 상단에는 상단 콘크리트부(6)가 타설된다. 이와 같이 호안과 접하는 법면에는 콘크리트 블록(10)이 수직 또는 사선방향으로 설치되어 하천(1)의 법면(2)이 유수의 흐름에 의해 붕괴나 토사의 유실이 최대한 방지된다.In the case of installing the concrete block 10 to form a shelter connected to the bank of the river (1), first, the foundation concrete (3) is installed in the longitudinal direction along the flow path on the bottom surface of the river (1). In the upper part of the foundation concrete 3, the rubble part 4 and the concrete block 5 which are directly poured on the surface 2 are laminated | stacked several are laminated | stacked. At this time, the upper concrete portion (6) is poured in the upper end of the concrete block portion (5). In this way, the concrete block 10 is installed in the vertical or oblique direction on the surface in contact with the lake, the surface (2) of the river (1) is prevented to collapse or the loss of the soil by the flow of the flow as much as possible.

그러나, 종래의 경우 상기 기초콘크리트(3)는 현장에서 콘크리트를 직접타설하여 시공하고 있는 실정이여서 타설할 때 하천의 유수의 영향으로 시공이 매우 난해하며 긴 공사기간이 소요된다는 단점이 있다. 다시 말해, 하천에 물이 지속적으로 흐르는 관계로 종래에는 기초콘크리트 시공전 물길을 차단하기 위한 별도의 가시설 예컨대, 물막이 보와 같은 시설을 통해 물막이 선시공을 한 후 기초콘크리트를 후시공하게 되는데, 그 과정에서 가시설 설치 및 해체하는데 따른 별도의 인력과 추가 공사비용이 지출되며 그 만큼 공사기간이 길어지게 된다는 것이다.However, in the conventional case, the foundation concrete 3 has a disadvantage in that construction is very difficult and long construction period is required due to the flow of rivers when placing concrete by placing concrete directly on site. In other words, since water flows continuously in the stream, conventionally, after preliminary construction of a water barrier through a separate temporary facility for blocking the waterway before construction of the foundation concrete, for example, a water barrier beam, the construction of the foundation concrete is performed. In addition, additional manpower and additional construction costs will be expended in installing and dismantling provisional facilities, which will increase the construction period.

본 고안은 상기한 종래의 문제점을 해결하기 위한 것으로, 앵커를 통한 블록 조립식으로 그 시공이 매우 간단하면서도 블록간 결속력이 매우 견고하여 장마철과 같은 우수기 때 하천의 유량 및 유속이 빨라지더라도 붕괴되거나 해체되지 않으며, 수중 시공시 물길 차단을 위한 별도의 가시설 없이도 용이하게 시공할 수 있어 공기 단축 및 인력의 소모를 줄일 수 있는 조립식 호안기초블록을 제공하는 데에 그 목적이 있다.The present invention is to solve the above-mentioned problems, the block assembly type through the anchor, the construction is very simple, but the binding force between the blocks is very strong, collapsed or dismantled even if the flow rate and flow rate of the river is fast during rainy seasons such as rainy season The purpose is to provide a prefabricated revetment base block that can be easily installed without additional temporary equipment for water blocking when construction underwater, reducing air consumption and manpower consumption.

상기와 같은 목적을 달성하기 위하여 본 고안은, 하천제방 법면에 호안 시공을 위해 하천바닥에 설치되는 호안기초구조물에 있어서, 상·하단부에 돌부가 서로 다른 방향을 향하여 돌출형성되고 각각의 돌부 중앙에는 이들의 연속된 조립을 위해 앵커홀이 천공된 호안기초블록과, 하나의 호안기초블록의 하단돌부와 다른 하나의 호안기초블록의 상단돌부 각각에 형성된 앵커홀이 연통되도록 두 개의 호안기초블록이 배치된 상태에서 상기 앵커홀을 동시에 관통하면서 서로 이웃하는 호안기초블록을 연결하는 앵커를 포함하는 것을 특징으로 하는 조립식 호안기초블록을 제공한다.In order to achieve the above object, the present invention, in the riverbank foundation structure that is installed on the river floor for the revetment construction on the river bank embankment, the protrusions formed in the upper and lower end toward the different direction and each of the protrusions in the center Two raft foundation blocks are arranged so that anchor holes formed in each of the raft foundation blocks in which the anchor holes are drilled and anchor holes formed in the top projections of the other raft foundation block are connected to each other for continuous assembly thereof. It provides a prefabricated revetment base block comprising a plurality of anchors connecting neighboring revetment base blocks while penetrating the anchor hole at the same time.

바람직하게는, 본 고안에 적용된 상기 앵커는 앵커관과 앵커봉으로 이루어져 상기 앵커봉의 죔력 조절에 따라 앵커관 끝단이 확장되면서 상기 앵커홀내에서 견고한 결속력을 형성하는 세트앵커를 적용함이 좋을 것이다.Preferably, the anchor applied to the present invention is made of an anchor tube and the anchor rod it will be good to apply a set anchor to form a solid binding force in the anchor hole as the end of the anchor tube is expanded in accordance with the adjustment of the clamping force of the anchor rod.

이하, 첨부된 도면을 참조하여 본 고안의 바람직한 실시예를 상세히 설명하기로 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2은 본 고안에 따른 조립식 호안기초블록의 조립과정을 보여주기 위한 분해 사시도로서, 본 고안은 종래 호안 시공을 위해 하천바닥면 가장자리에 유로를 따라 길이방향으로 기초콘크리트를 타설시공하는 것과는 달리 호안기초를 기성폼으로 미리 일정크기의 블록형태로 성형하여 단위체적을 줄여 시공이 간편하면서도 견고한 결속력이 유지될 수 있도록 한 것이다. 이를 위해 본 고안은, 블록형태로 제작되는 다수의 호안기초블록(1)과 호안기초블록들을 서로 연결하기 위한 앵커(2)를 포함한다.Figure 2 is an exploded perspective view for showing the assembly process of the prefabricated revetment base block according to the present invention, the present invention is unlike the conventional construction of laying foundation concrete in the longitudinal direction along the flow path at the bottom edge of the river for the construction of the revetment The foundation is made of a ready-made foam in the form of a block of a predetermined size to reduce the unit volume so that the construction is simple and solid binding force can be maintained. To this end, the present invention includes a plurality of shoreline basic blocks (1) and anchors for connecting the shoreline basic blocks to each other manufactured in the form of blocks.

도 2을 다시 참조하면, 상기 호안기초블록(1)은 상·하단부에 돌부(12,14)가 서로 다른 방향을 향하여 돌출형성된 구조로 각각의 돌부 중앙에는 이러한 호안기초블록(1)의 연속된 조립을 위해 앵커홀(16)이 천공된다. 이와 같은 호안기초블록(1)은 현장타설이 아닌 기성폼으로 제작되어져 대량 양산이 가능하며 거푸집과 같은 별도의 가시설 없이도 현장직접시공이 가능하다. 또한, 현장 시공시 물길을 막기위한 가시설 예컨대, 물막이 보가 필요 없게 된다.Referring to FIG. 2 again, the revetment basic block 1 has a structure in which protrusions 12 and 14 protrude toward different directions at upper and lower ends thereof, and the continuous retreat of such revetment basic blocks 1 is formed at the center of each protrusion. Anchor hole 16 is drilled for assembly. Such a base block (1) is manufactured in a ready-made foam, not on-site casting, mass production is possible, and it is possible to construct a site directly without additional temporary facilities such as formwork. In addition, a temporary facility, such as a water barrier, for blocking the waterway at the site construction is not required.

상기한 호안기초블록(1)은 하나의 호안기초블록(1) 앞뒤로 다른 바닥기초블록들을 이웃하는 형태로 하천바닥면 가장자리를 따라 시공되며 이들은 앵커(2)를 통해 상호 견고히 연결될 수 있다.The revetment foundation block 1 is constructed along the river bottom edge in the form of neighboring other bottom foundation blocks before and after one revetment foundation block 1 and they can be firmly connected to each other through the anchor (2).

바람직하게는, 본 고안에 적용된 상기 앵커(2)는 속이빈 중공관으로 상단부에는 플랜지가 형성되고 하단부는 그 길이방향으로 소정높이 절개된 앵커관(20)과, 상기 앵커관(20)을 하부로부터 상부로 관통하며 상단부에는 나사산이 형성됨과 동시에 나사산이 형성된 상단은 앵커관(20) 상단으로 돌출되어 너트(24)로서 고정되고 하단에는 외확장형 돌기(220)가 구비된 앵커봉(22)으로 이루어진 세트앵커가 적용된다. 이와 같은 세트앵커는 앵커봉(22)에 체결되는 너트(24) 죔력 조절에 따라 앵커관(20) 끝단이 확장되면서 상기 앵커홀(16)내에서 견고한 결속력을 형성하여 이웃하는 두 개의 호안기초블록(1)을 견고히 연결시킬 수 있다.Preferably, the anchor 2 applied to the present invention is a hollow hollow tube, the upper end of the flange is formed and the lower end of the anchor tube 20 is cut in a predetermined height in the longitudinal direction, and the anchor tube 20 lower The upper end is formed with a screw thread at the upper end and at the same time the threaded upper end is protruded to the upper end of the anchor pipe 20 is fixed as a nut 24 and the lower end is an anchor rod 22 provided with an external extension protrusion 220. The set anchor made is applied. Such a set anchor is formed by a solid binding force in the anchor hole 16 as the end of the anchor pipe 20 is expanded in accordance with the adjustment of the clamping force of the nut 24 fastened to the anchor rod 22, two neighboring shore rest blocks (1) can be connected firmly.

상기와 같은 구성으로 이루어진 본 고안은 도 3에서와 같이 하천바닥에 시공되어 제방보호를 위한 호안의 초석을 이룬다.The present invention consisting of the above configuration is constructed on the river floor as shown in Figure 3 to form the cornerstone of the revetment for embankment protection.

좀더 구체적으로 살펴보면, 하천바닥면의 가장자리를 따라 호안기초블록(1)을 길게 배치한다. 이때, 하나의 호안기초블록(1)의 하단돌부(14)와 다른 하나의 호안기초블록(1)의 상단돌부(12)가 중첩되어 각각에 형성된 앵커홀(16)이 연통되도록 배치하는 것이 중요하다. 이러한 상태 즉, 하나의 호안기초블록(1)과 이와 이웃하는 다른 하나의 호안기초블록(1)의 앵커홀(16)이 서로 연통되게 배치된 상태에서 상기 연통된 앵커홀(16)들을 동시에 관통하도록 앵커(2)를 끼운 후 너트(24)로서 그 죔력을 조절하여 주면 호안기초블록(1)간 견고한 결속력이 유지되면서 간단하게 그 시공이 완료된다.Looking more specifically, the long shore basic block (1) is arranged along the edge of the river bottom surface. At this time, it is important to arrange the anchor hole 16 formed in each of the lower protrusions 14 of one basic bank block 1 and the upper protrusions 12 of the other basic bank block 1 overlap each other. Do. In this state, that is, the anchor hole 16 of the one shore basic block 1 and the other shore basic block 1 adjacent thereto are arranged to communicate with each other, and simultaneously pass through the communicating anchor holes 16. After fitting the anchor (2) to adjust the clamping force as a nut (24), the construction is completed simply while maintaining a solid binding force between the base block (1).

상기와 같이 시공되는 본 고안에 따르면, 하천 제방에 호안을 형성하기 위한 호안기초를 시공함에 있어서 기성폼형태로 제작되어진 단위 블록형태의 기초블록들을 연속적으로 연결하여 시공함에 따라 기존 콘크리트타설에 비해 시공면적이 줄어들고 시공이 간편하며, 시공시 물길을 차단하지 않은 상태에서도 현장직접시공이 가능하다. 또한, 특정구간에 하자가 발생될 경우 그 구간에 있는 호안기초블록만을 따로 분리시켜 보수공사를 시행할 수 있어 보수가 매우 용이하다.According to the present invention to be constructed as described above, in the construction of the revetment foundation for forming the revetment on the river banks, the construction is compared to the existing concrete casting by connecting the basic blocks of the unit block form made in the form of ready-made form in succession The area is reduced and the construction is easy, and the construction can be done directly in the field without blocking the waterway. In addition, when a defect occurs in a certain section, it is very easy to repair by separating and repairing only the shoreline block in the section separately.

이상에서 살펴본 바와 같이 본 고안인 조립식 호안기초블록에 의하면, 앵커를 통한 블록 조립식으로 그 시공이 매우 간단하면서도 블록간 결속력이 매우 견고하여 장마철과 같은 우수기 때 하천의 유량 및 유속이 빨라지더라도 붕괴되거나 해체되지 않으며, 수중 시공시 물길 차단을 위한 별도의 가시설 없이도 용이하게 시 공할 수 있어 공기 단축 및 인력의 소모를 줄일 수 있는 효과가 있다.As described above, according to the prefabricated shoreline basic block of the present invention, the block assembly type through anchors is very simple in construction, but the solidity between blocks is very strong, so that even when the flow rate and flow rate of the river are increased during rainy season, such as rainy season, It is not dismantled, and can be easily installed without any additional facility for blocking the water when constructing underwater, which has the effect of shortening the air and reducing the consumption of manpower.

이상에서 본 고안은 특정한 실시예에 관련하여 도시하고 설명하였지만, 이하의 실용신안등록 청구범위에 의해 마련되는 본 고안의 정신이나 분야를 벗어나지 않는 한도내에서 본 고안이 다양하게 개조 및 변화될 수 있다는 것을 당업계에서 통상의 지식을 가진자는 용이하게 알 수 있음을 밝혀두고자 한다.Although the present invention has been illustrated and described with reference to specific embodiments, the present invention may be variously modified and changed without departing from the spirit or the field of the present invention provided by the following utility model registration claims. It will be appreciated that those skilled in the art can easily know.

Claims (2)

하천제방 법면에 호안 시공을 위해 하천바닥에 설치되는 호안기초구조물에 있어서,In the shoreline foundation structure installed on the riverbed for the construction of the shoreline on the river bank embankment, 상·하단부에 돌부(12,14)가 서로 다른 방향을 향하여 돌출형성되고 각각의 돌부(12,14) 중앙에는 이들의 연속된 조립을 위해 앵커홀(16)이 천공된 호안기초블록(1)과;In the upper and lower portions, the projections 12 and 14 protrude in different directions, and at the center of each of the projections 12 and 14, an anchor hole 16 having a hole drilled therein for continuous assembly thereof. and; 하나의 호안기초블록(1)의 하단돌부(14)와 다른 하나의 호안기초블록(1)의 상단돌부(12) 각각에 형성된 앵커홀(16)이 연통되도록 두 개의 호안기초블록(1)들이 근접배치된 상태에서 상기 앵커홀(16)을 동시에 관통하면서 서로 이웃하는 호안기초블록을 연결하는 앵커(2);를 포함하는 것을 특징으로 하는 조립식 호안기초블록.The two raft foundation blocks (1) are formed so that the anchor hole (16) formed in each of the lower projections (14) of the one raft foundation block (1) and the top projections (12) of the other raft foundation block (1) is in communication with each other. Prefabricated revetment base block, comprising: an anchor (2) for connecting the neighboring revetment base block while simultaneously passing through the anchor hole (16) in a close arrangement. 제 1 항에 있어서, The method of claim 1, 상기 앵커(2)는 앵커관(20)과 앵커봉(22)으로 이루어져 상기 앵커봉(22)에 결합되는 너트(24)의 죔력 조절에 따라 앵커관(20) 끝단이 확장되면서 상기 앵커홀(16)내에서 견고한 결속력을 형성하는 세트앵커(Set-Anchor)인 것을 특징으로 하는 조립식 호안기초블록. The anchor 2 is composed of an anchor tube 20 and the anchor rod 22 and the end of the anchor tube 20 is expanded in accordance with the adjustment of the clamping force of the nut 24 coupled to the anchor rod 22 while the anchor hole ( 16) Prefabricated raft foundation block, characterized in that the set anchor (Set-Anchor) to form a solid binding force within.
KR2020050037193U 2005-12-30 2005-12-30 The prefabricated revetment base block KR200413470Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020050037193U KR200413470Y1 (en) 2005-12-30 2005-12-30 The prefabricated revetment base block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020050037193U KR200413470Y1 (en) 2005-12-30 2005-12-30 The prefabricated revetment base block

Publications (1)

Publication Number Publication Date
KR200413470Y1 true KR200413470Y1 (en) 2006-04-07

Family

ID=41763757

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020050037193U KR200413470Y1 (en) 2005-12-30 2005-12-30 The prefabricated revetment base block

Country Status (1)

Country Link
KR (1) KR200413470Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101035133B1 (en) * 2010-06-29 2011-05-19 준이앤씨(주) Block assembly for revetment and constructing method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101035133B1 (en) * 2010-06-29 2011-05-19 준이앤씨(주) Block assembly for revetment and constructing method thereof

Similar Documents

Publication Publication Date Title
US5087150A (en) Method of constructing a seawall reinforcement or jetty structure
US9644334B2 (en) Methods of and systems for controlling water flow, breaking water waves and reducing surface erosion along rivers, streams, waterways and coastal regions
KR100560986B1 (en) Multifunctional erosion control dam and its construction method
JP2010024745A (en) Reinforcing structure of dike
CN210216298U (en) Combined type trench flood control wall
US8011855B2 (en) Roadway-levee
KR200401960Y1 (en) Beachcomber and billow prevention tool
WO1979000084A1 (en) Method and means for beach restoration
KR200413470Y1 (en) The prefabricated revetment base block
JP2013253461A (en) Tsunami embankment
WO2005035879A1 (en) Cable stayed dams
KR100714234B1 (en) Beachcomber and billow prevention tool
JP3864393B2 (en) Construction method of river crossing structure
KR200411833Y1 (en) A temporary equipment for small river
CN220284708U (en) Assembled river levee module
KR200338820Y1 (en) Embankment structure having environmental block
KR200410821Y1 (en) Seaweed block consulating construction
CN215518715U (en) Counter-current sinking and draining device
CN215105050U (en) Dyke reinforcing structure
CN216664037U (en) Suction type combined pile dam structure for emergency of river channel
CN211621486U (en) Assembled sluice
JP2004270369A (en) Bridge structure and its construction method
KR100733283B1 (en) Structure for preventing overflowing of sea
KR200410822Y1 (en) Eco block executive construction
CN117449252A (en) Ecological toughness shore protection structure of canal and river channel and construction method thereof

Legal Events

Date Code Title Description
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
FPAY Annual fee payment

Payment date: 20130404

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140403

Year of fee payment: 9

EXPY Expiration of term