KR100560986B1 - Multifunctional erosion control dam and its construction method - Google Patents

Multifunctional erosion control dam and its construction method Download PDF

Info

Publication number
KR100560986B1
KR100560986B1 KR1020050104077A KR20050104077A KR100560986B1 KR 100560986 B1 KR100560986 B1 KR 100560986B1 KR 1020050104077 A KR1020050104077 A KR 1020050104077A KR 20050104077 A KR20050104077 A KR 20050104077A KR 100560986 B1 KR100560986 B1 KR 100560986B1
Authority
KR
South Korea
Prior art keywords
blocking
blocking portion
block
concrete
dam
Prior art date
Application number
KR1020050104077A
Other languages
Korean (ko)
Inventor
허경태
원창남
Original Assignee
대한민국
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대한민국 filed Critical 대한민국
Priority to KR1020050104077A priority Critical patent/KR100560986B1/en
Application granted granted Critical
Publication of KR100560986B1 publication Critical patent/KR100560986B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/08Fish passes or other means providing for migration of fish; Passages for rafts or boats

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Revetment (AREA)

Abstract

본 발명은 다기능 사방댐 및 그 시공방법에 관한 것으로, 토석차단부(100)의 좌ㆍ우측에 소정높이의 땜어깨(110)가 형성되고, 상기 토석차단부(100) 전방에 워터쿠션부(300)가 형성되는 철근 콘크리트 구조물의 사방댐에서 상기 토석차단부(100)와 상기 토석차단부(100)의 좌ㆍ우측에 형성된 땜어깨(110) 사이에 금속재의 유목차단부(200)가 설치되어지는 사방댐에 있어서, 상기 토석차단부(100)의 하부에는 하나 이상의 어도가 형성되고, 상기 토석차단부(100)는 제1차단부(101), 제2차단부(102) 및 제3차단부(103)로 콘크리트가 순차적으로 타설되어 형성되어지되, 상기 제1차단부(101), 제2차단부(102) 및 제3차단부(103)의 수직 이음부에는 가로방향으로 지수판(120)의 상ㆍ하부가 서로 묻히도록 콘크리트가 타설되고 상기 제2차단부(102)에 앵커(130)가 설치되고 상기 앵커(130)에 유목차단부(200)가 설치되어 상기 앵커(130)와 유목차단부(200)의 하부가 묻히도록 제3차단부(103)의 콘크리트가 타설되고, 상기 토석차단부(100)의 중앙부의 수평 이음부에는 세로방향으로 필라(140)가 설치되고, 상기 필라(140) 중앙부에는 다수의 신축이음환봉(150)이 상기 필라(140)를 관통하여 상ㆍ하로 설치된 것이다.The present invention relates to a multi-functional four-way dam and its construction method, the solder shoulder 110 of a predetermined height is formed on the left and right sides of the earth blockage portion 100, the water cushion portion 300 in front of the earth blockage portion (100) The driftwood block 200 of the metal material is installed between the ground block 100 and the ground shoulder 110 formed on the left and right sides of the ground block 100 at the dams of the reinforced concrete structure in which is formed. In the four-sided dam, at least one fishery is formed at the lower portion of the soil blocking portion 100, and the soil blocking portion 100 includes a first blocking portion 101, a second blocking portion 102, and a third blocking portion ( Concrete is formed by sequentially pouring 103, but the vertical joints of the first blocking portion 101, the second blocking portion 102 and the third blocking portion 103 in the horizontal direction of the index plate 120 Concrete is poured so that the upper part and the lower part are buried together, and the anchor 130 is installed in the second blocking part 102 and the anchor 130 The driftwood block 200 is installed so that the bottom of the anchor 130 and the driftwood block 200 is buried, and the concrete of the third block 103 is poured, and the center portion of the earth block 100 is horizontal. Pillar 140 is provided in the joint portion in the longitudinal direction, and a plurality of expansion joint ring rods 150 are installed at the center of the pillar 140 through the pillar 140 and up and down.

사방댐, 토석차단부, 유목차단부, 배수구, 어도, 지수판, 필라 Four-sided dam, earth block, driftwood block, drain, fish, water plate, pillar

Description

다기능 사방댐 및 그 시공방법{Multifunctional Erosion Control Dam and its Construction Method}Multifunctional Erosion Control Dam and its Construction Method

도 1은 종래기술에 따른 이중벽댐의 일례를 도시한 도면,1 is a view showing an example of a double wall dam according to the prior art,

도 2는 종래기술에 따른 스크린댐의 일례를 도시한 도면,2 is a view showing an example of a screen dam according to the prior art,

도 3은 본 발명에 따른 다기능 사방댐의 사시도,3 is a perspective view of a multifunctional four-way dam in accordance with the present invention;

도 4는 본 발명에 따른 다기능 사방댐의 정면도,4 is a front view of the multifunctional four-way dam in accordance with the present invention;

도 5a는 본 발명에 따른 다기능 사방댐의 평면도,Figure 5a is a plan view of a multi-functional four-sided dam in accordance with the present invention,

도 5b는 본 발명의 다른 실시예에 따른 다기능 사방댐의 평면도,Figure 5b is a plan view of a multi-functional four-sided dam in accordance with another embodiment of the present invention,

도 6은 도 5a의 A-A선 단면의 확대도,6 is an enlarged view of a section A-A of FIG. 5A,

도 7은 본 발명에 따른 토목차단부의 세부 사시도,7 is a detailed perspective view of a civil engineering cutout unit according to the present invention;

도 8은 본 발명에 따른 다기능 사방댐의 시공 흐름도이다.8 is a construction flowchart of the multi-functional four-way dam in accordance with the present invention.

- 도면의 주요부분에 대한 부호의 설명 --Explanation of symbols for the main parts of the drawings-

100 : 토석차단부 101 : 제1차단부100: earth blockage portion 101: the first block

102 : 제2차단부 103 : 제3차단부102: second blocking portion 103: third blocking portion

110 : 땜어깨 120 : 지수판110: shoulder 120: index plate

130 : 앵커 140 : 필라130: anchor 140: pillar

150 : 신축이음환봉 151 : 환봉150: expansion joint round bar 151: round bar

152 : 캡 160a,160b : 어도152: Cap 160a, 160b: Fish

161 : 자연석 162 : 수초식재블럭161: natural stone 162: aquatic plant block

163 : 격벽 163a :꺽임부163: bulkhead 163a: bent portion

170 : 배수구 180 : 측벽부170: drain port 180: side wall portion

200 : 유목차단부 210 : 주부재 220 : 버트리스부재 230 : 스크린재 240 : 스트럿부재 300 : 워터쿠션부 301 : 끝돌림 310 : 소제구 320 : 이형철근200: driftwood cutout 210: main member 220: buttress member 230: screen member 240: strut member 300: water cushion portion 301: end 310: small section 320: deformed rebar

본 발명은 다기능 사방댐에 관한 것으로, 더욱 상세하게는 토석의 하류유출을 차단하는 기능과 유목의 흐름을 차단하는 기능을 동시에 수행할 수 있도록 된 다기능 사방댐 및 그 시공방법에 관한 것이다.The present invention relates to a multi-functional four-sided dam, and more particularly to a multi-functional four-sided dam and its construction method that can be performed at the same time to block the flow of drift and block the flow of driftwood.

일반적으로, 하상구배(河床勾配)가 큰 계곡에서는 급류가 강바닥을 파고 양쪽 산기슭을 깎아서 산사태를 유발하므로 이를 방지하고 급류를 따라 토석(土石)이 하류로 흘러 내려가는 것을 방지하기 위해서 사방(砂防)댐을 건설하게 된다.In general, in valleys with large river gradients, rapids digging riverbeds and shattering both sides of the mountains cause landslides, and to prevent this from happening. Will be built.

이렇게 산간계곡 등의 수해방지용으로 설치하는 사방댐은 크게 2가지 종류로 구분할 수 있는데, 하나는 중력식 댐인 콘크리트댐으로, 도 1에서 보는 바와 같이, 이 콘크리트댐(10)은 통상 댐의 상류에서 흘러 내려오는 물과 토석을 가두어 댐 하류의 피해를 예방하는 기능을 수행하게 된다.Thus, four-sided dams installed for preventing floods such as mountain valleys can be divided into two types. One is a concrete dam which is a gravity dam, and as shown in FIG. 1, the concrete dam 10 generally flows down the upstream of the dam. Water and soil will be trapped to prevent damage downstream of the dam.

다른 하나는 유목방지용 댐인 버트리스댐(Buttress Dam)으로, 도 2에서 보는 바와 같이, 이 버트리스댐(20)은 산간계곡 등의 상류에서 산사태가 발생하여 뿌리 채 뽑힌 유목(流木)이 떠 내려와 댐에 걸려서 댐 하류의 유로를 변경시키거나 교량에 걸려 유로를 변경시켜 인명과 주택 및 농경지에 피해를 주는 것을 방지하는 기능을 수행한다.The other is a driftwood prevention buttress (Buttress Dam), as shown in Figure 2, the buttress dam 20 is a driftwood rooted up by roots due to landslides occur upstream, such as mountain valleys It protects people, houses and farmland from being damaged by changing the flow path downstream of the dam by the dam or by changing the flow path by the bridge.

한편, 수해를 효과적으로 예방하기 위해서는 계통적으로 사방댐을 설치해야 하는데, 통상적으로 산간계류의 상류에는 유목방지에 효과가 뛰어난 버트리스댐(20)을 설치하고, 하류에는 토석의 하류유출을 방지하는 콘크리트댐(10)을 설치하게 된다.On the other hand, in order to effectively prevent flooding, it is necessary to systematically install four-sided dams. Typically, upstream mountain streams are provided with a buttressless dam 20 which is excellent for preventing driftwood, and a concrete dam that prevents the outflow of soils downstream. (10) will be installed.

하지만, 전술한 바와 같이 하나의 계류에 2개 이상의 사방댐을 설치하게 되면 산간계곡의 훼손이 불가피한 문제점과 아울러, 여러 개의 사방댐 설치로 인해 설치비용이 증가하는 문제점이 있었다.However, as described above, when two or more four-sided dams are installed in one mooring, damage to the mountain valleys is inevitable, and installation costs increase due to the installation of several four-sided dams.

이에 본 발명은 상기와 같은 문제점을 해결하기 위해 창출된 것으로, 토석의 하류유출을 차단하는 기능과 유목의 흐름을 차단하는 기능을 동시에 수행할 수 있는 다기능 사방댐을 제공하여, 집중호우 및 태풍 등으로 산사태가 발생하여 토석과 유목이 하천 하류의 인명, 가옥, 농경지 및 기타 산업기반시설에 피해를 주는 것을 방지함은 물론, 자연경관의 훼손을 최소화할 수 있도록 된 다기능 사방댐 및 그 시 공방법을 제공하는데 그 목적이 있다.Accordingly, the present invention was created to solve the above problems, by providing a multi-functional four-way dam that can simultaneously perform the function of blocking the flow of downstream and blocking the flow of driftwood, such as heavy rain and typhoon Provides a multifunctional all-round dam and its construction method that prevents landslides and drifts from damaging lives, houses, farmland and other industrial infrastructure downstream of the river, and minimizes damage to natural landscapes Its purpose is to.

상기와 같은 목적을 달성하기 위해 본 발명에 따른 다기능 사방댐은, 토석차단부의 좌ㆍ우측에 소정높이의 땜어깨가 형성되고, 상기 토석차단부 전방에 워터쿠션부가 형성되는 철근 콘크리트 구조물의 사방댐에서 상기 토석차단부와 상기 토석차단부의 좌ㆍ우측에 형성된 땜어깨 사이에 금속재의 유목차단부가 설치되어지는 사방댐에 있어서, 상기 토석차단부의 하부에는 하나 이상의 어도가 형성되고, 상기 토석차단부는 제1차단부, 제2차단부 및 제3차단부로 콘크리트가 순차적으로 타설되어 형성되어지되, 상기 제1차단부, 제2차단부 및 제3차단부의 수직 이음부에는 가로방향으로 지수판의 상ㆍ하부가 서로 묻히도록 콘크리트가 타설되고 상기 제2차단부에 앵커가 설치되고 상기 앵커에 유목차단부가 설치되어 상기 앵커와 유목차단부의 하부가 묻히도록 제3차단부의 콘크리트가 타설되고, 상기 토석차단부의 중앙부의 수평 이음부에는 세로방향으로 필라가 설치되고, 상기 필라 중앙부에는 다수의 신축이음환봉이 상기 필라를 관통하여 상ㆍ하로 설치되어지는 것을 특징으로 한다.In order to achieve the above object, the multifunctional four-way dam in accordance with the present invention, a solder shoulder having a predetermined height is formed on the left and right sides of the earth block, and the water cushion portion is formed in front of the earth block. In a four-way dam in which a driftwood block of metal is provided between a ground block and a shoulder formed on the left and right sides of the ground block, one or more fishes are formed under the ground block, and the ground block includes a first block. The concrete is formed by sequentially pouring the second blocking portion and the third blocking portion. The vertical joints of the first blocking portion, the second blocking portion, and the third blocking portion are buried with each other in the horizontal direction. The concrete is poured so that the anchor is installed in the second blocking portion and the driftwood blocking portion is installed in the anchor to bury the lower portion of the anchor and the driftwood blocking portion. Concrete is poured to the third blocking portion, the pillars are installed in the vertical direction in the horizontal joint portion of the central portion of the earth block, and a plurality of expansion joint rods are installed up and down through the pillar in the central portion of the pillar. It is characterized by.

본 발명의 일실시예에 따르면, 상기 어도는 양측벽을 자연석 찰쌓기로 하여 'S'자형의 어도를 형성하되, 상기 어도의 양측 바닥에는 수초식재블럭이 지그재그로 설치되는 것을 특징으로 한다.According to one embodiment of the present invention, the fish is to form a 'S' shaped fish by the natural stone piles on both sides of the wall, characterized in that the plants on both sides of the fish is installed in a zigzag block.

본 발명의 다른 실시예에 따르면, 상기 어도는 양측벽을 콘크리트로 하여'|'자형의 어도를 형성하되, 상기 어도 바닥의 양측벽에는 다수의 격벽이 지그재그로 설치되어지고 일측벽에 설치된 격벽의 단부는 상부로 꺽임부가 형성되는 것을 특징으로 한다.According to another embodiment of the present invention, the fishery forms a '|' shaped fishery with both side walls of concrete, and a plurality of bulkheads are zigzag on both sidewalls of the bottom of the fishery. The end is characterized in that the bent portion is formed in the upper portion.

본 발명에 따르면, 상기 유목차단부는 상기 앵커에 고정된 다수의 주부재와 버트리스부재 및 스크린재로 구성되어지되, 상기 버트리스부재의 일단은 상기 주부재의 후방에 연결되고 타단은 상기 앵커에 고정되며, 상기 주부재와 주부재 사이에는 다수의 스크린재가 결합되고, 상기 주부재와 상기 버트리스부재 사이에 스트럿부재가 연결되어지는 것이 바람직하다.According to the present invention, the driftwood block is composed of a plurality of main members, buttress member and the screen member fixed to the anchor, one end of the buttress member is connected to the rear of the main member and the other end is fixed to the anchor Preferably, a plurality of screen members are coupled between the main member and the main member, and a strut member is connected between the main member and the buttress member.

또한 본 발명에 따르면, 상기 토석차단부의 하부에는 가로방향으로 격자형의 이형철근이 배근되고, 상기 워터쿠션부의 중앙하부에는 세로방향으로 격자형의 이형철근이 배근되며 상기 땜어깨에는 격자형의 이형철근이 종방향으로 배근되어지되, 상기 토석차단부 또는 땜어깨의 하부에는 하나 이상의 배수구가 형성되며, 상기 워터쿠션부의 하부 끝돌림에는 소제구가 구비되고, 상기 토석차단부의 전면에는 자연석 찰쌓기 또는 자연석 문양 거푸집을 이용한 자연석 문양이 형성되는 것이 바람직하다.Further, according to the present invention, a lattice-shaped deformed reinforcing bar is disposed in the horizontal direction at the lower part of the earth block, and a lattice-shaped reinforcing bar is reinforced in the longitudinal direction at the center lower portion of the water cushion part, and lattice-shaped deforming is formed on the solder shoulder. Reinforcing bars are longitudinally reinforcement, one or more drain holes are formed in the lower portion of the earth block or solder shoulder, a lower end of the water cushion portion is provided with a jig, and the front of the earth block is a natural stone stacking or It is preferable that natural stone patterns are formed using natural stone pattern formwork.

한편 본 발명에 따른 다기능 사방댐의 시공방법은, 토석차단부의 좌ㆍ우측에 소정높이의 땜어깨가 형성되고, 상기 토석차단부 전방에 워터쿠션부가 형성되는 철근 콘크리트 구조물의 사방댐에서 상기 토석차단부와 상기 토석차단부의 좌ㆍ우측에 형성된 땜어깨 사이에 금속재의 유목차단부가 설치되어지는 사방댐의 시공방법에 있어서, 상기 사방댐의 대상지를 굴착하고 정지한 후 잡석다짐하는 단계; 상기 잡석다짐한 대상지에 토석차단부의 제1차단부와 워터쿠션부의 기초 콘크리트를 타설하는 단계; 상기 제1차단부에는 가로방향으로 격자형의 이형철근을 배근하고 상 기 워터쿠션부의 중앙부에는 세로 방향으로 격자형의 이형철근을 배근한 후 콘크리트를 타설하는 단계; 상기 토석차단부의 제1차단부의 가로방향으로 좌ㆍ우측에 땜어깨를 형성하는 단계; 상기 제1차단부 상부에 제2차단부의 콘크리트를 타설하는 단계; 상기 제2차단부 또는 땜어깨의 하부에 어도 또는 배수구를 설치하는 단계; 상기 제2차단부에 앵커를 설치하고, 상기 앵커에 유목차단부를 설치한 후 상기 앵커와 상기 유목차단부의 하부가 묻히도록 제3차단부의 콘크리트를 타설하는 단계; 상기 제1차단부, 제2차단부 및 제3차단부의 수직 이음부에는 가로방향으로 지수판을 설치하는 단계; 상기 토석차단부의 중앙부의 수평 이음부에는 세로방향으로 필라를 설치하고 상기 필라의 중앙부에는 다수의 신축이음환봉이 상기 필라를 관통하여 설치하는 단계; 및 상기 워터쿠션부의 하부에 소제구가 형성된 끝돌림을 형성하는 단계를 포함하는 것을 특징으로 한다.On the other hand, the construction method of the multi-functional four-sided dam in accordance with the present invention, the ground and shoulders of a predetermined height is formed on the left and right sides of the earth block, and the earth block in the four-way dam of reinforced concrete structure in which the water cushion is formed in front of the earth block Claims [1] A method of constructing a four-sided dam, wherein a driftwood-blocking portion of a metal is installed between solders formed on the left and right sides of the earth-blocking portion, the method comprising the steps of digging and stopping the target site of the four-sided dam; Placing foundation concrete of the first cut-off portion and the water-cushion portion of the soil cut-off portion on the rubble target site; Reinforcing the lattice-shaped deformed reinforcing bars in the horizontal direction to the first cut-off part and placing the lattice-shaped deformed reinforcing bars in the vertical direction in the center of the water cushion part; Forming a solder shoulder on the left and right sides in the horizontal direction of the first blocking portion of the earth block; Placing concrete on the first blocking portion on the second blocking portion; Installing an airway or a drain at a lower portion of the second blocking portion or solder shoulder; Installing an anchor on the second blocking part, installing a driftwood blocking part on the anchor, and placing concrete on the third blocking part so that the lower part of the anchor and the driftwood blocking part are buried; Installing a water stop plate in a horizontal direction on the vertical joint of the first blocking part, the second blocking part, and the third blocking part; Installing a pillar in the longitudinal direction in the horizontal joint portion of the center portion of the earth block, and a plurality of expansion joint ring rod is installed through the pillar in the central portion of the pillar; And characterized in that it comprises the step of forming the end of the water cushion is formed in the lower portion of the water cushion.

이하 본 발명을 첨부된 예시도면을 참조로 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도 3은 본 발명에 따른 다기능 사방댐의 사시도이고, 도 4는 본 발명에 따른 다기능 사방댐의 정면도이며, 도 5a 및 도 5b는 본 발명에 따른 다기능 사방댐의 평면도이고, 도 6은 도 5a의 A-A선 단면의 확대도이며, 도 7은 본 발명에 따른 토목차단부의 세부 사시도이고, 도 8은 본 발명에 따른 다기능 사방댐의 시공 흐름도이다.Figure 3 is a perspective view of a multi-functional four-way dam in accordance with the present invention, Figure 4 is a front view of the multi-functional four-way dam in accordance with the present invention, Figures 5a and 5b is a plan view of the multi-function four-way dam in accordance with the present invention, Figure 6 is a line AA of Figure 5a 7 is an enlarged cross-sectional view, and FIG. 7 is a detailed perspective view of the civil engineering cutout unit according to the present invention, and FIG. 8 is a construction flowchart of the multifunctional four-way dam according to the present invention.

본 발명에 따른 다기능 사방댐은, 도 3에서 보는 바와 같이, 토석차단부(100)의 좌ㆍ우측에 소정높이의 땜어깨(110)가 형성되고, 상기 토석차단부(100) 전방 및 좌ㆍ우측의 측벽부(180) 사이에 워터쿠션부(300)가 형성되는 철근 콘크리트 구조물의 사방댐으로서, 상기 토석차단부(100)와 상기 토석차단부(100)의 좌ㆍ우측에 형성된 땜어깨(110) 사이에 금속재의 유목차단부(200)가 설치된다.As shown in FIG. 3, the multifunctional four-sided dam according to the present invention has a solder shoulder 110 having a predetermined height formed on the left and right sides of the earth blockage portion 100, and the front and left and right sides of the earth blockage portion 100. Water cushion portion 300 is formed between the side wall portion 180 of the reinforced concrete structure of the four-sided dam, the earth shoulder block 100 and the solder shoulder 110 formed on the left and right sides of the soil block 100 The driftwood blocking portion 200 of the metal material is installed therebetween.

도 6 및 도 7에서 보는 바와 같이, 상기 토석차단부(100)는 제1차단부(101), 제2차단부(102) 및 제3차단부(103)로 콘크리트가 순차적으로 타설되어 형성되는데, 이것은 한 번의 콘크리트 타설을 통해 토석차단부(100)를 형성하는 것이 곤란하기 때문에 제1차단부(101), 제2차단부(102) 및 제3차단부(103)로 나누어서 콘크리트를 타설하게 되는 것이며, 이때 각 차단부(101,102,103)의 수직 이음부에는 가로방향으로 지수판(120)을 설치하여 수직 이음부의 누수를 방지하게 된다.As shown in FIG. 6 and FIG. 7, the earth blocking part 100 is formed by sequentially pouring concrete into the first blocking part 101, the second blocking part 102, and the third blocking part 103. This is because it is difficult to form the earth-blocking part 100 through one concrete pouring, so that the concrete is poured into the first blocking part 101, the second blocking part 102 and the third blocking part 103. In this case, the vertical joints of the blocking units 101, 102, and 103 are installed in the horizontal direction to prevent the leakage of the vertical joints.

즉, 상기 제1차단부(101), 제2차단부(102) 및 제3차단부(103)의 수직 이음부에는 가로방향으로 지수판(120)의 상ㆍ하부가 서로 묻히도록 콘크리트가 타설되며, 상기 제2차단부(102)에 앵커(130)가 설치되고, 상기 앵커(130)에 상기 유목차단부(200)가 설치되어 상기 앵커(130)와 유목차단부(200)의 하부가 묻히도록 제3차단부(103)의 콘크리트가 타설된다.That is, concrete is poured on the vertical joints of the first blocking part 101, the second blocking part 102, and the third blocking part 103 so that the upper and lower parts of the index plate 120 are buried in the horizontal direction. The anchor 130 is installed on the second blocking portion 102, and the driftwood blocking portion 200 is installed on the anchor 130 to bury the lower portion of the anchor 130 and the driftwood blocking portion 200. So that the concrete of the third blocking portion 103 is poured.

여기서, 상기 지수판(120)의 중앙부는 볼록하게 형성되어 작업자가 상기 지수판(120)의 설치위치를 시각적으로 용이하게 인지할 수 있다.Here, the central portion of the index plate 120 is convex, so that the operator can easily visually recognize the installation position of the index plate 120.

이러한 지수판(120)의 재질은 자연 생고무, 고밀도 합성고무, 폴리에틸렌 또는 E.V.A 등을 이용할 수 있으며, 상기 지수판(120)의 두께는 구조물의 크기에 따라 변경될 수 있으나, 본 발명의 사방댐에서는 10mm 내외가 바람직하다.The index plate 120 may be made of natural raw rubber, high-density synthetic rubber, polyethylene, or EVA, and the thickness of the index plate 120 may be changed depending on the size of the structure. desirable.

그리고, 상기 토석차단부(100)의 중앙부의 수평 이음부에는 세로방향으로 필라(140)가 설치되고, 상기 필라(140) 중앙부에는 다수의 신축이음환봉(150)이 상기 필라(140)를 관통하여 상ㆍ하로 설치된다.In addition, pillars 140 are vertically installed at horizontal joints of the central portion of the earth block 100, and a plurality of expansion joint rings 150 penetrate the pillars 140 at the pillars 140. Up and down.

여기서, 상기 필라(140)는 신축이음채움재(Expansion Joint Filler)라고도 불리우며, 콘크리트 타설시의 연속타설 불능, 지반의 부동침하, 지진 및 온도변화 등에 대응하기 위해 신축이음(Expansion Joint) 부분에 미리 채워져 콘크리트의 수축, 팽창 및 진동에 의한 구조물의 변위에 적응할 수 있도록 하기 위한 것이다.Here, the pillar 140 is also referred to as expansion joint filler (Expansion Joint Filler), and is pre-filled in the expansion joint (Expansion Joint) in order to cope with the inability to continuously cast during concrete pouring, ground subsidence, earthquake and temperature change It is to be able to adapt to the displacement of the structure due to the shrinkage, expansion and vibration of the concrete.

이러한 필라(140)의 재질은 전술한 지수판(120)의 재질과 동일하며, 상기 필라(140)의 두께는 구조물의 크기에 따라 변경될 수 있으나, 본 발명의 사방댐에서는 20mm 내외가 바람직하다.The material of the pillar 140 is the same as the material of the above-described index plate 120, the thickness of the pillar 140 may be changed according to the size of the structure, in the four-sided dam of the present invention is preferably around 20mm.

그리고, 상기 신축이음환봉(150)은 다웰바(Dowel Bar)라고도 불리우며, 환봉(151)과 캡(152)으로 이루어진다. 상기 환봉(151) 측은 콘크리트에 고정되며, 상기 캡(152) 측은 콘크리트에 직접 닿지 않게 위치된다. 상기 캡(152) 내부에는 그리스 등이 충진되어 방청작용 및 콘크리트 타설시 캡(152) 내부로 콘크리트가 들어가는 것을 방지하게 된다. 이러한 신축이음환봉(150)은 비연속적인 콘크리트 타설시 또는 연결부위에 시공하는 것으로, 콘크리트의 온도변화에 따른 수축 또는 팽창시 크랙 등을 방지하기 위하여 사용된다.The expansion joint ring 150 is also called a dowel bar, and includes a round bar 151 and a cap 152. The round bar 151 side is fixed to the concrete, the cap 152 side is positioned not to directly contact the concrete. The cap 152 is filled with grease to prevent the concrete from entering the cap 152 during the rust prevention and concrete pouring. The expansion joint ring 150 is to be installed at non-continuous concrete pouring or connecting portion, it is used to prevent cracks, such as shrinkage or expansion due to the temperature change of the concrete.

상기 신축이음환봉(150)은 필라(140)의 중앙부에 상기 필라(140)를 관통하여 상하로 소정의 간격을 두고 설치하되, 상기 신축이음환봉(150)의 캡(152)이 서로 교차되도록 설치하는 것이 바람직하며, 상기 신축이음환봉(150)은 열간압연처리된 원형봉강이 이용될 수 있다.The expansion joint ring 150 is installed at a predetermined interval up and down through the pillar 140 at the center of the pillar 140, the cap 152 of the expansion joint ring 150 is installed so as to cross each other. Preferably, the expansion joint ring 150 may be used hot rolled circular bar.

여기서, 상기 토석차단부(100)는 다수의 자연석을 포함하는 콘크리트 구조물 로 이루어질 수 있으며, 이를 통해 본 발명에 따른 다기능 사방댐을 주변 자연환경과 보다 더 잘 어우러지게 조성할 수 있다.Here, the earth blockage portion 100 may be made of a concrete structure including a plurality of natural stones, through which the multi-functional four-sided dam according to the present invention can be better combined with the surrounding natural environment.

본 발명에 따르면, 상기 토석차단부(100)의 하부에는 가로방향으로 격자형의 이형철근이 배근되고, 상기 워터쿠션부(300)의 중앙하부에는 세로방향으로 격자형의 이형철근(320)이 배근되며, 상기 땜어깨(110) 및 측벽부(180)에는 격자형의 이형철근이 종방향으로 배근될 수 있다.According to the present invention, a lattice-shaped deformed reinforcing bar is disposed in the horizontal direction at the lower portion of the earth blockage part 100, and a lattice-shaped deformed reinforcing bar 320 in the vertical direction is disposed at the center lower portion of the water cushion 300. The reinforcing bar 110 and the sidewall portion 180 may be a lattice-shaped deformed reinforcement in the longitudinal direction.

이렇게 상기 토석차단부(100) 또는 워터쿠션부(300)에 설치되는 격자형의 철근인 상기 이형철근(320)은 구조물의 부동침하나 균열 및 크랙이 예상될 경우에 사용되는 것으로, 일종의 신축이음(Expansion Joint)이라 할 수 있으며, 콘크리트를 끊어치기 할 때 사용되는 것이어서 시공이음(Construction Joint)이라고도 한다. Thus, the deformed reinforcing bar 320, which is a lattice-shaped reinforcement installed in the earth blockage part 100 or the water cushion part 300, is used when anticipating floating or cracking and cracking of a structure. It can be called (Expansion Joint), and it is also called Construction Joint because it is used to break concrete.

또한 본 발명에 따르면, 상기 토석차단부(100) 또는 땜어깨(110)의 하부에는 하나 이상의 배수구(170)가 형성되며, 상기 워터쿠션부(300)의 하부 끝돌림(301)에는 소제구(310)가 구비되고, 상기 토석차단부(100) 또는 땜어깨(110)의 전면에는 자연석(161) 찰쌓기 또는 자연석 문양 거푸집을 이용한 자연석 문양이 형성될 수 있다.In addition, according to the present invention, one or more drain holes 170 are formed at the lower portion of the earth blockage portion 100 or the solder shoulder 110, and at the lower end turn 301 of the water cushion portion 300, 310 is provided, the natural stone pattern using the natural stone 161 pile or natural stone pattern formwork may be formed on the front surface of the earth blockage portion 100 or the solder shoulder 110.

그리고 본 발명에 따르면, 상기 토석차단부(100)의 하부에는 하나 이상의 어도를 형성할 수 있는데, 이러한 어도는 다기능 사방댐의 설치에 따른 어류의 이동제한을 해결하여 보다 환경 친화적인 사방댐을 구축하기 위한 것이다.And according to the present invention, one or more fish can be formed in the lower portion of the earth blockage portion 100, such fishes to solve the restrictions on the movement of the fish according to the installation of the multi-function four-way dam to build a more environmentally friendly four-way dam will be.

본 발명의 일실시예에 따르면, 도 5a에서 보는 바와 같이, 상기 어도는 양측 벽을 자연석(161) 찰쌓기로 하여 'S'자형의 어도(160a)를 형성하되, 상기 어도(160a)의 양측 바닥에는 수초식재블럭(162)이 지그재그로 설치될 수 있다.According to one embodiment of the invention, as shown in Figure 5a, the fishery is to form a 'S' shaped fishery 160a by the natural stone 161 piles both sides walls, both sides of the fishery 160a The plant plant block 162 may be zigzag on the floor.

여기서, 상기 수초식재블럭(162) 내에는 흙이 그물망에 채워진 상태로 제공되어 다양한 수초가 쉽게 활착할 수 있다.Here, in the myelin planting block 162, the soil is provided in a state filled with the net can be easily a variety of plants.

한편, 본 발명의 다른 실시예에 따르면, 도 5b에서 보는 바와 같이, 어도는 양측벽을 콘크리트로 하여 '|'자형의 어도(160b)를 형성하되, 상기 어도(160b) 바닥의 양측벽에는 다수의 격벽(163)이 지그재그로 설치되어지고 일측벽에 설치된 격벽(163)의 단부는 상부로 꺽임부(163a)가 형성되도록 구성할 수 있는데, 상기 꺽임부(163a)는 물의 급격한 흐름을 방지하는 기능을 수행한다.On the other hand, according to another embodiment of the present invention, as shown in Figure 5b, the fishery to form a '|' shaped fishery 160b with both side walls as a concrete, a plurality of both sides of the bottom of the fishery 160b The partition wall 163 is installed in a zigzag and the end of the partition wall 163 installed on one side wall can be configured to be formed to be a bent portion (163a) to the top, the bent portion (163a) to prevent the rapid flow of water Perform the function.

본 발명에 따르면, 도 6에서 보는 바와 같이, 유목차단부(200)는 상기 앵커(130)에 고정된 다수의 주부재(210)와 버트리스부재(220) 및 스크린재(230)로 구성되며, 상기 버트리스부재(220)의 일단은 상기 주부재(210)의 후방에 연결되고 타단은 상기 앵커(130)에 고정된다.According to the present invention, as shown in Figure 6, the driftwood block 200 is composed of a plurality of main members 210, buttress member 220 and the screen member 230 fixed to the anchor 130, One end of the buttress member 220 is connected to the rear of the main member 210 and the other end is fixed to the anchor 130.

그리고, 상기 주부재(210)와 주부재(210) 사이에는 다수의 스크린재(230)가 결합되고, 상기 주부재(210)와 상기 버트리스부재(220) 사이에 스트럿부재(240)가 연결되어 이루어져 상류로부터 흘러내리는 유목 등을 안정적으로 차단할 수 있게 된다.Further, a plurality of screen members 230 are coupled between the main member 210 and the main member 210, and the strut member 240 is connected upstream between the main member 210 and the buttress member 220. It is possible to reliably block the driftwood and the like flowing down from.

그리고, 본 발명에 따른 다기능 사방댐의 시공방법을 살펴보면, 먼저 본 발명에 따른 다기능 사방댐의 최적 대상지를 선정하여 상기 사방댐의 대상지를 굴착하고 정지한 후 잡석다짐(S10)을 하고, 상기 잡석다짐한 대상지에 토석차단부(100) 의 제1차단부(101)와 워터쿠션부(300)의 기초 콘크리트를 타설하게 된다(S20).And, looking at the construction method of the multi-functional four-way dam according to the present invention, first select the optimal target site of the multi-function four-way dam in accordance with the present invention to excavate and stop the target site of the four-sided dam and then rubble (S10), the rubble on the target site The foundation concrete of the first blocking portion 101 and the water cushion portion 300 of the earth blockage portion 100 is poured (S20).

그리고, 상기 제1차단부(101)에는 가로방향으로 격자형의 이형철근을 배근하고, 상기 워터쿠션부(300)의 중앙부에는 세로 방향으로 격자형의 이형철근(320)을 배근한 후 콘크리트를 타설(S30)한 다음, 상기 토석차단부(100)의 제1차단부(101)의 가로방향으로 좌ㆍ우측에 땜어깨(110)를 형성한다(S40).In addition, the first reinforcement portion 101 is placed in the horizontal direction of the reinforcing bar reinforcing bar, and the center portion of the water cushion 300 is disposed in the longitudinal direction of the reinforcing bar 320 in the longitudinal direction to the concrete After pouring (S30), the solder shoulder 110 is formed on the left and right sides in the transverse direction of the first blocking portion (101) of the earth block (100) (S40).

또한, 상기 제1차단부(101) 상부에 제2차단부(102)의 콘크리트를 타설(S50)하고, 상기 제2차단부(102) 또는 땜어깨(110)의 하부에 어도 또는 배수구(170)를 설치(S60)하며, 상기 제2차단부(102)에 앵커(130)를 설치하고, 상기 앵커(130)에 유목차단부(200)를 설치한 후 상기 앵커(130)와 상기 유목차단부(200)의 하부가 묻히도록 제3차단부(103)의 콘크리트를 타설한다(S70).In addition, the concrete of the second blocking portion 102 is poured into the upper portion of the first blocking portion 101 (S50), and the air outlet or drain hole 170 below the second blocking portion 102 or the solder shoulder 110. ) Is installed (S60), and the anchor 130 is installed on the second blocking portion 102, and the driftwood blocking portion 200 is installed on the anchor 130, and then the anchor 130 and the driftwood blocking. The concrete of the third blocking portion 103 is poured so that the lower portion of the portion 200 is buried (S70).

그리고, 상기 제1차단부(101), 제2차단부(102) 및 제3차단부(103)의 수직 이음부에는 가로방향으로 지수판(120)을 설치하며(S80), 상기 토석차단부(100)의 중앙부의 수평 이음부에는 세로방향으로 필라(140)를 설치하고, 상기 필라(140)의 중앙부에는 다수의 신축이음환봉(150)이 상기 필라(140)를 관통하여 설치한다(S90).In addition, the vertical joint portion of the first blocking portion 101, the second blocking portion 102 and the third blocking portion 103 is installed with a water stop plate 120 in the horizontal direction (S80), the earth block ( The pillars 140 are vertically installed at the horizontal joints of the central portion of the center 100, and a plurality of expansion joint ring rods 150 are installed through the pillars 140 at the central portions of the pillars 140 (S90). .

이후, 상기 워터쿠션부(300)의 하부에 소제구(310)가 형성된 끝돌림(301)을 형성하는 과정(S100)을 거치게 되며, 필요에 따라 물받이 및 주변 경관을 조성하여 마무리하게 된다.Subsequently, a process (S100) of forming a tip 301 in which the cleaning tool 310 is formed at the lower portion of the water cushion part 300 is performed, and the drip tray and the surrounding landscape are formed as necessary.

전술한 바와 같이, 본 발명에 따른 다기능 사방댐은 산간계곡 등의 상류에서 물을 따라 함께 이동하는 토석과 유목을 동시에 차단할 수 있는데, 즉 상기 토석차단부(100)에서는 상류로부터 흘러내리는 물을 따라 함께 이동하는 토석을 차단하는 동시에, 소정량의 물을 저수하는 기능을 수행하게 되며, 상기 유목차단부(200)에서는 물을 따라 떠 내려오는 유목을 차단하는 한편, 유목차단부(200)의 틈새를 통해 물은 통과시킬 수 있게 된다.As described above, the multi-functional four-way dam in accordance with the present invention can simultaneously block the soil and driftwood moving along the water upstream, such as mountain valleys, that is, in the soil blocking unit 100 together along the water flowing from the upstream At the same time to block the moving soil, and to store a predetermined amount of water, the driftwood block 200 blocks the driftwood floating along the water, while the gap between the driftwood block 200 Through it, water can pass through.

이후, 상기 토석차단부(100)의 배수구(170) 및 유목차단부(200)를 통과한 물은 상기 워터쿠션부(300)를 거쳐 하류로 흐르게 되는데, 이 워터쿠션부(300)에 저장된 물은 필요에 따라 상기 소제구(310)를 개방하여 적절히 이용할 수 있다.Subsequently, the water passing through the drain 170 and the driftwood block 200 of the soil block 100 flows downstream through the water cushion 300, and the water stored in the water cushion 300 The opening may be appropriately used by opening the cleaning tool 310 as necessary.

이상 설명한 바와 같이 본 발명에 따르면, 상류에서 흘러 내려오는 토석과 유목을 동시에 차단할 수 있는 다기능 사방댐을 통해 우리나라의 급경사지 지형과 여름철 집중되는 폭우에 가장 적합한 사방댐을 제공할 수 있으며, 단일의 사방댐으로 토석과 유목을 동시에 차단할 수 있으므로 예산을 절감하고, 자연경관의 훼손을 최소화할 수 있다.As described above, according to the present invention, through the multi-functional four-way dam that can block the soil and driftwood flowing down from the upstream at the same time can provide the best four-sided dam for the steep terrain of the country and the heavy rains concentrated in summer, as a single four-sided dam It can cut both civil and driftwood at the same time, saving budget and minimizing the damage of natural landscape.

그리고, 본 발명에 따른 다기능 사방댐에는 어도가 구비되어 사방댐의 설치에 따른 어류 및 소생물의 이동제한을 해결하여 보다 환경 친화적인 사방댐을 구축할 수 있다.In addition, the multifunctional four-way dam in accordance with the present invention is provided with a fish can solve the restrictions on the movement of fish and microorganisms due to the installation of the four-way dam to build a more environmentally friendly four-way dam.

또한, 본 발명에 따른 다기능 사방댐의 토석차단부를 구성하는 각 차단부의 수직 이음부에는 지수판이 설치되므로 수직 이음부에서 발생하는 누수를 효과적으로 방지할 수 있음은 물론, 토석차단부의 중앙부에는 필라 및 신축이음환봉이 설치되어 콘크리트의 수축, 팽창 및 진동에 의한 구조물의 변위에 적절히 대응할 수 있어 콘크리트 구조물의 안정성을 크게 향상시킬 수 있는 효과가 있다.In addition, since the water discharge plate is installed in the vertical joints of each blocking portion constituting the soil blocking portion of the multi-functional four-way dam according to the present invention, it is possible to effectively prevent leakage occurring in the vertical joint portion, as well as pillars and expansion joints in the central portion of the soil blocking portion The round bar is installed to properly respond to the displacement of the structure due to the contraction, expansion and vibration of the concrete has the effect of greatly improving the stability of the concrete structure.

이상에서는 본 발명을 특정의 바람직한 실시예에 대해서 도시하고 설명하였지만, 본 발명은 상술한 실시예에만 한정되는 것은 아니며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 이하의 특허청구범위에 기재된 본 발명의 기술적 사상의 요지를 벗어나지 않고 얼마든지 다양하게 변경 실시할 수 있을 것이다.Although the present invention has been illustrated and described with respect to specific preferred embodiments, the present invention is not limited to the above-described embodiments, and those of ordinary skill in the art to which the present invention pertains should have the following claims. Various modifications can be made without departing from the spirit of the technical spirit of the invention described.

Claims (6)

토석차단부(100)의 좌ㆍ우측에 소정높이의 땜어깨(110)가 형성되고, 상기 토석차단부(100) 전방에 워터쿠션부(300)가 형성되는 철근 콘크리트 구조물의 사방댐에서 상기 토석차단부(100)와 상기 토석차단부(100)의 좌ㆍ우측에 형성된 땜어깨(110) 사이에 금속재의 유목차단부(200)가 설치되어지는 사방댐에 있어서,The soil shoulders 110 are formed on the left and right sides of the soil blocking part 100, and the soil blocks are blocked in all directions of the reinforced concrete structure in which the water cushion part 300 is formed in front of the soil blocking part 100. In the four-sided dam is provided with the driftwood block 200 of the metal material between the portion 100 and the solder shoulder 110 formed on the left and right sides of the earth blockage portion 100, 상기 토석차단부(100)의 하부에는 하나 이상의 어도가 형성되고, 상기 토석차단부(100)는 제1차단부(101), 제2차단부(102) 및 제3차단부(103)로 콘크리트가 순차적으로 타설되어 형성되어지되, 상기 제1차단부(101), 제2차단부(102) 및 제3차단부(103)의 수직 이음부에는 가로방향으로 지수판(120)의 상ㆍ하부가 서로 묻히도록 콘크리트가 타설되고 상기 제2차단부(102)에 앵커(130)가 설치되고 상기 앵커(130)에 유목차단부(200)가 설치되어 상기 앵커(130)와 유목차단부(200)의 하부가 묻히도록 제3차단부(103)의 콘크리트가 타설되고, 상기 토석차단부(100)의 중앙부의 수평 이음부에는 세로방향으로 필라(140)가 설치되고, 상기 필라(140) 중앙부에는 다수의 신축이음환봉(150)이 상기 필라(140)를 관통하여 상ㆍ하로 설치되어지는 것을 특징으로 하는 다기능 사방댐.One or more fishes are formed in the lower portion of the earth blockage part 100, and the earth blockage part 100 is formed of concrete as a first block part 101, a second block part 102, and a third block part 103. Is formed by pouring sequentially, the upper and lower portions of the index plate 120 in the horizontal direction on the vertical joint of the first blocking portion 101, the second blocking portion 102 and the third blocking portion 103 Concrete is embedded to be buried with each other, the anchor 130 is installed on the second blocking portion 102 and the driftwood blocking portion 200 is installed on the anchor 130 is the anchor 130 and the driftwood blocking portion 200 The concrete of the third blocking portion 103 is poured so that the lower portion of the buried portion, and the pillar 140 is installed in the vertical direction at the horizontal joint portion of the center portion of the earth blockage portion 100, and the pillar 140 is disposed at the center portion thereof. Multifunctional four-way dam, characterized in that a plurality of expansion joint ring rod 150 is installed up and down through the pillar 140. 제1항에 있어서,The method of claim 1, 상기 어도는 양측벽을 자연석(161) 찰쌓기로 하여 'S'자형의 어도(160a)를 형성하되, 상기 어도(160a)의 양측 바닥에는 수초식재블럭(162)이 지그재그로 설치되는 것을 특징으로 하는 다기능 사방댐.The fish is to form the 'S' shaped fish (160a) by the natural stone (161) piled on both sides of the wall, both sides of the bottom of the fish (160a) is characterized in that the plant plants block 162 is installed in a zigzag Multifunctional dams everywhere. 제1항에 있어서,The method of claim 1, 상기 어도는 양측벽을 콘크리트로 하여 '|'자형의 어도(160b)를 형성하되, 상기 어도(160b) 바닥의 양측벽에는 다수의 격벽(163)이 지그재그로 설치되어지고 일측벽에 설치된 격벽(163)의 단부는 상부로 꺽임부(163a)가 형성되는 것을 특징으로 하는 다기능 사방댐.The airway forms a '|' shaped fishery 160b having both side walls made of concrete, and a plurality of partition walls 163 are zigzag installed on both sidewalls of the bottom of the fishery 160b, and the barrier walls installed on one side wall ( End of the 163 is a multi-functional four-way dam, characterized in that the bent portion (163a) is formed in the upper portion. 제1항에 있어서,The method of claim 1, 상기 유목차단부(200)는 상기 앵커(130)에 고정된 다수의 주부재(210)와 버트리스부재(220) 및 스크린재(230)로 구성되어지되, 상기 버트리스부재(220)의 일단은 상기 주부재(210)의 후방에 연결되고 타단은 상기 앵커(130)에 고정되며, 상기 주부재(210)와 주부재(210) 사이에는 다수의 스크린재(230)가 결합되고, 상기 주부재(210)와 상기 버트리스부재(220) 사이에 스트럿부재(240)가 연결되어지는 것을 특징으로 하는 다기능 사방댐.The driftwood block 200 is composed of a plurality of main members 210 and the buttress member 220 and the screen member 230 fixed to the anchor 130, one end of the buttress member 220 It is connected to the rear of the main member 210 and the other end is fixed to the anchor 130, a plurality of screen member 230 is coupled between the main member 210 and the main member 210, the main member 210 and Multifunctional four-way dam, characterized in that the strut member 240 is connected between the buttress member 220. 제1항 내지 제4항 중 어느 한 항에 있어서,The method according to any one of claims 1 to 4, 상기 토석차단부(100)의 하부에는 가로방향으로 격자형의 이형철근이 배근되고, 상기 워터쿠션부(300)의 중앙하부에는 세로방향으로 격자형의 이형철근(320)이 배근되며 상기 땜어깨(110)에는 격자형의 이형철근이 종방향으로 배근되어지되, 상기 토석차단부(100) 또는 땜어깨(110)의 하부에는 하나 이상의 배수구(170)가 형성되며, 상기 워터쿠션부(300)의 하부 끝돌림(301)에는 소제구(310)가 구비되고, 상기 토석차단부(100) 또는 땜어깨(110)의 전면에는 자연석(161) 찰쌓기 또는 자연석 문양 거푸집을 이용한 자연석 문양이 형성되는 것을 특징으로 하는 다기능 사방댐.A lattice-shaped deformed reinforcing bar is disposed in the horizontal direction at the lower portion of the earth blockage part 100, and a lattice-shaped deformed reinforcing bar 320 is disposed in the vertical direction at the center lower portion of the water cushion part 300, and the solder shoulder. The lattice-shaped deformed reinforcement bars are disposed in the longitudinal direction at one or more, and at least one drain hole 170 is formed at the lower portion of the earth blockage portion 100 or the solder shoulder 110, and the water cushion portion 300 is formed. The lower end of the 301 is provided with a cleaning tool 310, the natural stone pattern using the natural stone 161 pile or natural stone pattern formwork is formed on the front surface of the earth blockage portion 100 or the solder shoulder 110 Multifunctional four sides dam, characterized in that. 토석차단부(100)의 좌ㆍ우측에 소정높이의 땜어깨(110)가 형성되고, 상기 토석차단부(100) 전방에 워터쿠션부(300)가 형성되는 철근 콘크리트 구조물의 사방댐에서 상기 토석차단부(100)와 상기 토석차단부(100)의 좌ㆍ우측에 형성된 땜어깨(110) 사이에 금속재의 유목차단부(200)가 설치되어지는 사방댐의 시공방법에 있어서,The soil shoulders 110 are formed on the left and right sides of the soil blocking part 100, and the soil blocks are blocked in all directions of the reinforced concrete structure in which the water cushion part 300 is formed in front of the soil blocking part 100. In the construction method of the four-sided dam is provided between the part 100 and the solder shoulder 110 formed on the left and right sides of the earth blockage portion 100, 상기 사방댐의 대상지를 굴착하고 정지한 후 잡석다짐하는 단계(S10);Excavating and stopping the target site of the four-sided dam and then settling rubble (S10); 상기 잡석다짐한 대상지에 토석차단부(100)의 제1차단부(101)와 워터쿠션부(300)의 기초 콘크리트를 타설하는 단계(S20);Pouring basic concrete of the first cut-off portion 101 and the water cushion portion 300 of the soil cut-off portion 100 to the rubble target site (S20); 상기 제1차단부(101)에는 가로방향으로 격자형의 이형철근을 배근하고 상기 워터쿠션부(300)의 중앙부에는 세로 방향으로 격자형의 이형철근(320)을 배근한 후 콘크리트를 타설하는 단계(S30);Placing the reinforcing bars of the lattice type in the horizontal direction to the first blocking portion 101 and placing the concrete after placing the reinforcing bars of the lattice type in the longitudinal direction to the central portion of the water cushion part 300. (S30); 상기 토석차단부(100)의 제1차단부(101)의 가로방향으로 좌ㆍ우측에 땜어깨(110)를 형성하는 단계(S40);Forming a solder shoulder (110) on the left and right sides in the horizontal direction of the first blocking portion (101) of the soil blocking portion (100) (S40); 상기 제1차단부(101) 상부에 제2차단부(102)의 콘크리트를 타설하는 단계(S50);Placing concrete of the second blocking portion 102 on the first blocking portion 101 (S50); 상기 제2차단부(102) 또는 땜어깨(110)의 하부에 어도 또는 배수구(170)를 설치하는 단계(S60);Installing an airway or a drain 170 at a lower portion of the second blocking portion 102 or the solder shoulder 110 (S60); 상기 제2차단부(102)에 앵커(130)를 설치하고, 상기 앵커(130)에 유목차단부(200)를 설치한 후 상기 앵커(130)와 상기 유목차단부(200)의 하부가 묻히도록 제3차단부(103)의 콘크리트를 타설하는 단계(S70);After the anchor 130 is installed on the second blocking portion 102 and the driftwood blocking portion 200 is installed on the anchor 130, the lower portion of the anchor 130 and the driftwood blocking portion 200 are buried. Placing the concrete of the third blocking part 103 so as to pour (S70); 상기 제1차단부(101), 제2차단부(102) 및 제3차단부(103)의 수직 이음부에는 가로방향으로 지수판(120)을 설치하는 단계(S80);Installing an index plate (120) in a horizontal direction on vertical joints of the first blocking portion (101), the second blocking portion (102) and the third blocking portion (103); 상기 토석차단부(100)의 중앙부의 수평 이음부에는 세로방향으로 필라(140)를 설치하고 상기 필라(140)의 중앙부에는 다수의 신축이음환봉(150)이 상기 필라(140)를 관통하여 설치하는 단계(S90); 및The pillars 140 are vertically installed at the horizontal joints of the central portion of the earth blocker 100, and a plurality of expansion joint ring rods 150 are installed at the central portions of the pillars 140 through the pillars 140. Step (S90); And 상기 워터쿠션부(300)의 하부에 소제구(310)가 형성된 끝돌림(301)을 형성하는 단계(S100)를 포함하는 것을 특징으로 하는 다기능 사방댐의 시공방법.Construction method of a multi-functional four-way dam, characterized in that it comprises the step (S100) of forming a tip 301 is formed in the lower section of the water cushion portion 300.
KR1020050104077A 2005-11-02 2005-11-02 Multifunctional erosion control dam and its construction method KR100560986B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050104077A KR100560986B1 (en) 2005-11-02 2005-11-02 Multifunctional erosion control dam and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050104077A KR100560986B1 (en) 2005-11-02 2005-11-02 Multifunctional erosion control dam and its construction method

Publications (1)

Publication Number Publication Date
KR100560986B1 true KR100560986B1 (en) 2006-03-17

Family

ID=37179686

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050104077A KR100560986B1 (en) 2005-11-02 2005-11-02 Multifunctional erosion control dam and its construction method

Country Status (1)

Country Link
KR (1) KR100560986B1 (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100704415B1 (en) 2006-09-13 2007-04-09 대한민국 Sliclean debris barrier in which screen and slit are combined
KR100741371B1 (en) * 2007-04-12 2007-07-27 대한민국 The rhombic dam having the crossing fishway
KR100750386B1 (en) 2006-09-30 2007-08-27 주식회사 삼안 Dam concrete injection method
KR100794922B1 (en) 2007-05-10 2008-01-21 대한민국 The beam creen rhombic dam which h-steel and screen are combined
KR100797779B1 (en) 2006-11-22 2008-01-24 주식회사 삼안 Fish way of turbine structure and gate structure for tidal power plant
KR100996518B1 (en) 2010-02-22 2010-11-24 최태수 A debris barrier and construction method thereof
KR101052295B1 (en) * 2008-09-24 2011-07-27 오점곤 Four-sided dam with double drips
KR101137942B1 (en) * 2009-09-21 2012-06-27 대한민국 Devris Barrier with fishway
KR101170789B1 (en) * 2010-01-15 2012-08-02 영남대학교 산학협력단 Complex debris barrier of eco-friendly
KR101171014B1 (en) * 2010-01-15 2012-08-08 영남대학교 산학협력단 Debris barrier having small hydropower generating apparatus
KR101581806B1 (en) * 2015-03-27 2015-12-31 주식회사 대흥미래기술 Multi-Function Complex Module Dam
KR102561322B1 (en) 2022-12-20 2023-07-31 (주)인텔리지오 Bypass type sanddam

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5859825U (en) 1981-10-15 1983-04-22 住金鋼材工業株式会社 metal dam

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5859825U (en) 1981-10-15 1983-04-22 住金鋼材工業株式会社 metal dam

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100704415B1 (en) 2006-09-13 2007-04-09 대한민국 Sliclean debris barrier in which screen and slit are combined
KR100750386B1 (en) 2006-09-30 2007-08-27 주식회사 삼안 Dam concrete injection method
KR100797779B1 (en) 2006-11-22 2008-01-24 주식회사 삼안 Fish way of turbine structure and gate structure for tidal power plant
KR100741371B1 (en) * 2007-04-12 2007-07-27 대한민국 The rhombic dam having the crossing fishway
KR100794922B1 (en) 2007-05-10 2008-01-21 대한민국 The beam creen rhombic dam which h-steel and screen are combined
KR101052295B1 (en) * 2008-09-24 2011-07-27 오점곤 Four-sided dam with double drips
KR101137942B1 (en) * 2009-09-21 2012-06-27 대한민국 Devris Barrier with fishway
KR101170789B1 (en) * 2010-01-15 2012-08-02 영남대학교 산학협력단 Complex debris barrier of eco-friendly
KR101171014B1 (en) * 2010-01-15 2012-08-08 영남대학교 산학협력단 Debris barrier having small hydropower generating apparatus
KR100996518B1 (en) 2010-02-22 2010-11-24 최태수 A debris barrier and construction method thereof
KR101581806B1 (en) * 2015-03-27 2015-12-31 주식회사 대흥미래기술 Multi-Function Complex Module Dam
KR102561322B1 (en) 2022-12-20 2023-07-31 (주)인텔리지오 Bypass type sanddam

Similar Documents

Publication Publication Date Title
KR100560986B1 (en) Multifunctional erosion control dam and its construction method
US9644334B2 (en) Methods of and systems for controlling water flow, breaking water waves and reducing surface erosion along rivers, streams, waterways and coastal regions
US20100054859A1 (en) Hydraulic Sliding Insertion Panel and Its Using Method
KR100965467B1 (en) Eco-pillar debris barrier
CN107816050B (en) Concrete cofferdam and earth-rock cofferdam combined cofferdam and construction method thereof
JP4979797B2 (en) Superstructure to raise the top of the dam
CN108018828B (en) Slope protection structure
RU2321701C2 (en) Weir construction method
KR100654936B1 (en) Method for constructing retaining wall
KR101170789B1 (en) Complex debris barrier of eco-friendly
CN114687321A (en) Construction method of energy dissipation type gabion retaining wall revetment structure
CN210134438U (en) Seasonal river soaks embankment side slope protective structure
CN112854131A (en) Ecological revetment for water source protection area and construction method thereof
CN106522163A (en) Ecological brick for riverway
CN108411851B (en) construction method of concrete slab facing structure for slope dike of river and sea reclamation area
KR100461664B1 (en) Structures and system of construction based on the use of plants growing block that protect a shore
CN109898403A (en) The underwater canal case steel suspension bridge of urban rives construction method nested with double steel sheet-pile cofferdam
KR101052295B1 (en) Four-sided dam with double drips
JPH06280239A (en) Fabricated fish way
CN210857100U (en) Landscape type dike reinforcing structure
KR102437778B1 (en) Gabion wall block
JP2020100988A (en) Construction method of water-permeable wall for reinforcing sloped face
CN219490834U (en) Riverway retaining wall restoration structure
CN213773318U (en) Row pile structure and river bank dam body
KR200357964Y1 (en) Block for retaining wall

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant