KR200408091Y1 - Roof Frame of Keeping Warmth Cover - Google Patents

Roof Frame of Keeping Warmth Cover Download PDF

Info

Publication number
KR200408091Y1
KR200408091Y1 KR2020050032138U KR20050032138U KR200408091Y1 KR 200408091 Y1 KR200408091 Y1 KR 200408091Y1 KR 2020050032138 U KR2020050032138 U KR 2020050032138U KR 20050032138 U KR20050032138 U KR 20050032138U KR 200408091 Y1 KR200408091 Y1 KR 200408091Y1
Authority
KR
South Korea
Prior art keywords
truss
frame
frames
apartment
attached
Prior art date
Application number
KR2020050032138U
Other languages
Korean (ko)
Inventor
김관섭
Original Assignee
태원정공 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 태원정공 주식회사 filed Critical 태원정공 주식회사
Priority to KR2020050032138U priority Critical patent/KR200408091Y1/en
Application granted granted Critical
Publication of KR200408091Y1 publication Critical patent/KR200408091Y1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/242Safety or protective measures preventing damage to building parts or finishing work during construction for temporarily covering the whole worksite, e.g. building, trench
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/246Safety or protective measures preventing damage to building parts or finishing work during construction specially adapted for curing concrete in situ, e.g. by covering it with protective sheets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/28Safety or protective measures preventing damage to building parts or finishing work during construction against unfavourable weather influence
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/06Stiff scaffolding clamps for connecting scaffold members of common shape

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Tents Or Canopies (AREA)

Abstract

본 고안 조립식 덮개용 지붕틀은 동절기에 아파트를 시공할때 콘크리트 슬래브(slab)의 빠른 양생을 위해 비나 눈에 노출되어 동결되는 것을 방지하며 우천시에도 작업을 할 수 있도록 사용한다. The prefabricated cover truss is designed to prevent freezing by exposure to rain or snow for fast curing of concrete slab during winter construction.

따라서 보온 덮개 지붕 트러스를 공장에서 미리 규격화되게 제작하여 현장에서 바로 조립하여 설치할 수 있는 것은 물론 시공되는 아파트의 평형에 맞게 트러스의 길이를 조절하여 사용할 수 있도록 트러스를 연결몸체와 좌우측몸체로 분할하여 좌우측몸체는 평형에 상관없이 그대로 사용하고 연결몸체만 평형에 맞게 교체하여 사용할 수 있다.Therefore, the insulation cover roof truss is pre-standardized at the factory, and can be assembled and installed directly on site, and the truss is divided into a connecting body and a left and right body to adjust the length of the truss according to the equilibrium of the apartment to be constructed. The body can be used as it is regardless of equilibrium and only the connecting body can be replaced according to the equilibrium.

또한 동절기의 아파트 공사가 끝나면 부피가 큰 보온 덮개 지붕틀을 보관이 용이하도록 분해하고, 동절기에 공사가 새로 진행되면 조립하여 사용하는 것으로서 한번만 사용하는게 아니라 여러번 재사용할 수 있는 것을 특징으로 한다.In addition, when the construction of the winter apartment is finished, the bulky insulation cover truss is disassembled for easy storage, and when the construction is newly carried out in winter, it is assembled and used, and can be reused several times.

Description

조립식 덮개용 지붕틀{Roof Frame of Keeping Warmth Cover}Roof Frame of Keeping Warmth Cover

도 1은 본 고안을 도시해 보인 분리사시도.1 is an exploded perspective view showing the present invention.

도 2는 본 고안을 도시해 보인 결합사시도.Figure 2 is a perspective view showing a combination of the present invention.

도 3은 본 고안 지붕틀을 평형에 따라 교체하여 사용할 수 있는 것을 도시해 Figure 3 shows that the present invention can be used to replace the truss according to the equilibrium

보인 사시도.Viewed perspective view.

도 4는 본 고안 처마를 도시해 보인 사시도.Figure 4 is a perspective view showing the subject innovation eaves.

도 5는 본 고안 지붕틀을 구성하는 트러스에 처마가 부착된 것을 도시해 Figure 5 shows that the eaves are attached to the truss constituting the truss of the present invention

보인 사시도.Viewed perspective view.

도 6은 본 고안에 연결바가 결합된 것을 도시해 보인 사시도.Figure 6 is a perspective view showing that the connection bar is coupled to the subject innovation.

도 7는 본 고안에 천막을 덮은 것을 도시해 보인 사시도.Figure 7 is a perspective view showing the covering of the tent in the present invention.

도 8은 본 고안을 사용상태를 도시해 보인 예시도.8 is an exemplary view showing a state of use of the present invention.

* 도면의 주요 부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

1: 지붕틀 2: 연결몸체1: truss 2: connecting body

3: 좌측몸체 4: 우측몸체3: left body 4: right body

5: 상부프레임 6: 하부프레임5: upper frame 6: lower frame

7: 수직프레임 8: 체결공7: vertical frame 8: fastener

9: 볼트 10: 지지부재9: bolt 10: support member

12: 인양고리 13: 천막 12: Salvage 13: Tent

14: 가설구조물 15: 연결프레임 14: Temporary structure 15: Connecting frame

16: 콘크리트 슬래브 17: 클램프(clamp) 16: concrete slab 17: clamp

18: 체결프레임 19: 브라켓 18: Fastening frame 19: Bracket

20: 처마 22: 좌측프레임 20: eaves 22: left frame

23: 우측프레임 24; 보강판 23: right frame 24; Gusset

100: 트러스 100: truss

본 고안은 조립식 덮개용 지붕틀에 관한 것으로서, 더욱 상세히 설명하면 동절기에 아파트를 시공할때 콘크리트 슬래브(slab)의 빠른 양생을 위해 비나 눈에 노출되어 동결되는 것을 방지하며 우천시에도 작업을 할 수 있도록 사용하는 보온 덮개 지붕 트러스는 공장에서 미리 규격화되게 제작하여 현장에서 바로 조립하여 설치할 수 있다.The present invention relates to a prefabricated cover truss, and more specifically, to prevent freezing by exposure to rain or snow for fast curing of concrete slabs during construction in winter, it can be used to work even in rainy weather. Insulating cover roof trusses are pre-standardized at the factory, can be assembled and installed on site.

또한 시공되는 아파트의 평형에 맞게 트러스의 길이를 조절하기 위하여 좌우측몸체와 연결몸체로 분할되어 좌우측몸체는 아파트의 평형에 상관없이 그대로 사용하고 연결몸체만 교체 조립하여 사용한다. In addition, in order to adjust the length of the truss according to the balance of the construction of the apartment is divided into left and right body and the connecting body, the left and right body is used as it is, regardless of the flat balance of the apartment and replace and use only the replacement body.

또한 동절기의 아파트 공사가 끝나면 부피가 큰 보온 덮개 지붕틀을 보관이 용이하도록 분해하고 동절기에 공사가 발생하면 조립하여 사용하는 것으로 한번만 사용하는게 아니라 여러번 재사용할 수 있는 것을 특징으로 한다.In addition, when the construction of the winter apartment is finished, the bulky insulation cover truss is disassembled for easy storage, and when the construction occurs in winter, it can be reassembled and used several times instead of being used only once.

일반적으로 동절기에는 콘크리트의 동결 및 양생의 어려움등으로 인해 아파트 공사를 진행하지 않으나 최근에는 공기단축 등의 이유로 인해 동절기에도 공사를 강행하는 추세이다.In general, apartment construction is not carried out in winter due to freezing of concrete and difficulty in curing, but recently, construction is being forced in winter due to air shortening.

따라서 동절기에 공사를 진행할 때 양생전의 콘크리트 슬래브가 눈이나 비에 노출되지 않고 낮은 온도에 의해 동결되는 것을 방지하며, 또한 콘크리트의 빠른 양생을 위해 열을 가할때 열발산을 억제하기 위해 아파트 공사 현장에 보온 덮개를 설치한다.Therefore, during construction in winter, the concrete slab before curing is not exposed to snow or rain and is frozen by low temperature. Also, to prevent heat dissipation when applying heat for rapid curing of concrete, Install a thermal cover.

그러나 상기 아파트 공사현장에 설치되는 보온 덮개는 공사현장에서 직접 파이프 등의 부재를 서로 연결하여 골조를 형성하고 그 위에 천막을 덮어 덮개를 형성하였으나 아파트의 특성상 작업현장이 높은 곳에 위치하기 때문에 안전사고의 위험이 높고 해체시에는 천막이 쉽게 찢어지는 문제점이 있다.However, the insulation cover installed at the construction site of the apartment forms a frame by connecting members such as pipes directly at the construction site and covers the tent thereon, but due to the characteristics of the apartment, the work site is located at a high place. There is a high risk and there is a problem that the tent is torn easily during dismantling.

또한 아파트의 층수가 올라갈수록 현장에서 설치 및 해체를 반복하기 때문에 작업이 매우 어렵고 인력이 많이 소요되어 공사가 지연되는 문제점이 있다.In addition, since the number of floors of the apartment is increased, the installation and dismantling are repeated at the site, which makes the work very difficult and requires a lot of manpower.

따라서 최근에는 본 출원인에 발명된 특허등록번호 제509622호 건축물 공사용 보온 덮개 지붕틀을 제공하였다.Therefore, in recent years, the present inventors have provided a heat insulating cover truss for building construction patent registration No. 509622.

상기 선등록된 발명은 강체가 연결되어 구성된 강체구조물과 상기 강체구조물에 설치되고 크레인의 훅을 걸 수 있도록 하기 위한 훅걸이수단을 포함하여 구성되고, 필요에 따라 천막을 덮어 씌워, 건축하기 위한 구조물 주변으로 설치되는 가설구조물 상에 크레인을 이용하여 일체로 들어올려 설치할 수 있도록 된 건축물 공 사용 보온 덮개 지붕틀에 있어서, 상기 강체구조물은 강체들이 전, 후, 좌, 우로 연결되어 구성된 하층프레임, 상기 하층프레임 상에 강체들이 연결되어 상방으로 볼록하게 구성된 상층프레임으로 구성되었다.The pre-registered invention comprises a rigid structure consisting of a rigid body is connected to the rigid structure and hook hook means for allowing the hook of the crane to be mounted on the rigid structure, the structure for covering the tent, if necessary, building In the thermal insulation cover truss using the building ball to be installed by lifting the crane integrally on the temporary structure to be installed to the periphery, the rigid structure is a lower frame consisting of the rigid body connected to the front, rear, left, right, the lower layer The upper frame consists of rigid bodies connected to the frame and convex upward.

상기 보온 덮개용 지붕틀은 공장에서 설계도에 따라 상하층 프레임으로 구성된 강체구조물을 미리 제작하여 공사현장의 여건에 따라 다수개의 강체구조물을 배열하여 일체화되도록 상부에 다수개의 연결프레임이 평행하게 위치하여 교차되도록 용접하고 그 위에 천막을 덮어 덮개를 만든 후 지붕틀을 크레인으로 들어올려 설치하는 것이다.The thermal insulation cover truss is produced in advance in the factory according to the design of the rigid structure consisting of the upper and lower frame to arrange a plurality of rigid structures in accordance with the conditions of the construction site to be integrated so that a plurality of connecting frames are located in parallel to cross the top. It is welded, covered with a tent over it to make a cover, and the truss is lifted and installed by a crane.

그러나 상기 보온 덮개용 지붕틀은 공사현장에서 건축물의 평형에 맞게 직접 강체구조물과 연결바를 용접하여 고정하기 때문에 건축물이 아파트인 경우에는 건축되는 평형이 서로 달라 평형에 맞게 각각 제작해서 설치해야 하는 문제점이 있다.However, since the thermal insulation cover truss is fixed by welding the rigid structure and the connecting bar directly in accordance with the balance of the building at the construction site, there is a problem in that the building is different from the equilibrium to be built and installed separately according to the equilibrium .

또한 상기 보온 덮개용 지붕틀은 강체를 서로 용접하여 고정하였기 때문에 공사현장이 끝나거나 동절기가 지나 필요가 없는 경우에는 해체작업이 용이하지 않아 부피가 너무 커서 보관에 어려움으로 바로 폐기해야 하는 문제점이 있다.In addition, since the insulation cover truss is fixed by welding the rigid bodies to each other, when the construction site is finished or the winter season does not need to pass, the dismantling work is not easy, so the volume is too large to be disposed of immediately due to difficulty in storage.

따라서 상기 보온 덮개용 지붕틀은 한번 쓰고 폐기하기 때문에 건축비의 상승 및 자원재활용면에서 활용도가 떨어지는 문제점이 있다.Therefore, since the insulation cover truss is used once and discarded, there is a problem that the utilization rate is lowered in terms of construction cost and resource recycling.

따라서 상기와 같은 문제점을 해소하기 위한 본 고안의 목적은 아파트의 공사현장의 가설구조물에 설치하기가 매우 용이할 뿐만 아니라 아파트의 층수가 높아 짐에 따라 쉽게 이동시켜줌은 물론 강체구조물인 트러스와 연결프레임이 서로 분리결합이 가능한 것은 물론 트러스 자체도 분리 및 조립이 용이하도록 좌우측몸체와 연결몸체로 분할한다.Therefore, the purpose of the present invention for solving the above problems is not only very easy to install on the temporary structure of the construction site of the apartment, but also easily move as the number of floors of the apartment increases, as well as the trusses and connecting frames of rigid structures This can be separated from each other, as well as the truss itself is divided into the left and right body and the connecting body for easy separation and assembly.

따라서 보온 덮개용 지붕틀에서 좌우측몸체는 그대로 사용하고 연결몸체만 아파트의 평형에 따라 교체하여 조립하고, 한번 사용한 보온 덮개용 지붕틀은 해체하여 부피를 최소화함으로써 보관이 용이함으로 여러번 재사용이 가능한 조립식 덮개용 지붕틀을 제공하는 것이다.Therefore, the left and right body is used as it is in the insulation cover roof frame, and only the connecting body is replaced and assembled according to the equilibrium of the apartment. To provide.

상기와 같은 목적을 달성하기 위하여 본 고안은 강체가 서로 연결되어 구성된 트러스를 수평하게 각각 배열한 후 각각의 트러스를 연결하기 위하여 상부에 교차되어 용접된 다수개의 연결프레임과 그 위에 크레인의 훅을 걸 수 있도록 하기 위한 인양고리를 포함하여 구성되고, 필요에 따라 천막을 덮어 씌워, 건축하기 위한 구조물 주변으로 설치되는 가설구조물 상에 크레인을 이용하여 일체로 들어올려 설치할 수 있도록 된 보온 덮개 지붕틀에 있어서, 상기 아파트 공사용 보온 덮개 지붕틀은 소정의 간격으로 배열되는 트러스를 대칭형상인 한쌍의 좌우측몸체와, 상기 좌우측몸체 사이에서 분리결합되는 연결몸체를 구성하되, 하부프레임 양단에 좌우측프레임과 좌우측프레임 상단에 경사지게 상부프레임과 내부에는 지지부재가 내설되고, 상기 상부프레임 상단에는 각각의 트러스를 연결하는 연결바가 착탈되도록 클램프를 부착한 연결몸체와, 상기 연결몸체 양단에 위치하는 수직프레임과 밀착되도록 상부프레임과 하부프레임과 수직프레임이 직삼각형 형상을 갖으며 내부에는 지지부재가 내설되고, 연결몸체의 좌우측프레임과 체결이 가능하도록 볼트공이 각각 형성되어 볼트 체결되며, 상단에는 각각의 트러스를 연결하는 연결프레임이 착탈되도록 클램프가 부착된 것을 특징으로 한다.In order to achieve the above object, the present invention arranges the trusses horizontally configured with rigid bodies connected to each other, and then hooks the crane hooks on the plurality of connecting frames welded on the top to connect the respective trusses. Insulating cover roof frame is configured to include a lifting ring to be able to enable, and to cover the tent as needed, and to be lifted and installed integrally using a crane on the temporary structure installed around the structure for building, The thermal insulation cover truss for apartment construction constitutes a pair of left and right bodies having a symmetrical shape and trusses arranged at predetermined intervals, and a connecting body which is separated and coupled between the left and right bodies, but is inclined to the upper left and right sides of the frame and the left and right sides of the lower frame. The support member is built in the frame and the inside, The upper part of the subframe has a connecting body attached with a clamp to detach the connecting bar connecting each truss, and the upper frame, the lower frame and the vertical frame have a right triangle shape so as to be in close contact with the vertical frame located at both ends of the connecting body. The support member is internally installed, and bolt holes are formed to be fastened to each other so as to be fastened to the left and right frames of the connection body, and a clamp is attached to the upper and lower connection frames connecting the respective trusses.

이하 첨부된 도면에 본 고안을 상세히 설명하면 다음과 같다.Hereinafter, the present invention in detail with reference to the accompanying drawings.

도 1은 본 고안을 도시해 보인 분리사시도이고, 도 2는 본 고안을 도시해 보인 결합사시도이다.1 is an exploded perspective view showing the present invention, Figure 2 is a combined perspective view showing the present invention.

본 고안은 동절기에 아파트를 시공할때 콘크리트 슬래브(slab)의 빠른 양생을 위해 설치된 아파트 공사용 보온 덮개 지붕틀(1)을 여러번 재 사용할 수 있게 보관이 용이하도록 분리 조립하는 트러스(100)는 한쌍의 좌우측몸체(3, 4)와, 연결몸체(2)로 구성된다.The present design is a pair of left and right truss (100) for assembling separately for easy storage so that the thermal insulation cover truss (1) for the construction of the apartment installed for fast curing of the concrete slab (concrete slab) during the winter construction can be reused many times It consists of a body (3, 4), and the connecting body (2).

따라서 상기 트러스(100)는 좌우측몸체(3, 4)와 연결몸체(2)를 서로 조립할때 천막(13) 위에 고임현상이 없이 비나 눈이 흘러내릴 수 있도록 상부 중앙이 블록하고 하부는 수평을 유지한다.Therefore, when the truss 100 is assembled with the left and right body (3, 4) and the connecting body (2) with each other, the upper center blocks and the lower part is horizontal so that rain or snow can flow on the tent (13) without sticking phenomenon. do.

또한 한쌍의 좌우측몸체(3, 4)는 서로 대칭된 직삼각형 형상으로 하부프레임(6) 양단에 수직프레임(7)과 수직프레임(7) 상단에 경사지게 상부프레임(5)이 서로 용접되고, 내부에는 하중을 지지할 수 있도록 수직 또는 경사지게 지지부재(10)를 내설한다.In addition, the pair of left and right bodies 3 and 4 have a right triangular shape symmetrical with each other, and the upper frame 5 is welded to each other so as to be inclined to the upper end of the vertical frame 7 and the vertical frame 7 at both ends of the lower frame 6. The support member 10 is installed vertically or inclined to support the load.

또한 상기 경사진 상부프레임(5)에는 소정의 간격으로 배열된 트러스(100)를 일체화시킬 수 있도록 연결프레임(15)을 체결하는 클램프(17)를 상단에 부착한다.In addition, the inclined upper frame 5 is attached to the upper end of the clamp 17 to fasten the connecting frame 15 so as to integrate the truss 100 arranged at a predetermined interval.

상기 클램프(17)는 연결프레임(15)을 삽입하여 체결할 수 있도록 전면, 배 면, 상면이 개방되고 좌우측면 상단에는 삽입된 연결프레임(15)을 볼트의 회동에 의해 착탈하도록 볼트 일측은 힌지 체결되고 타측은 볼트를 체결할 수 있도록 체결홈이 형성된 구조이다. The clamp 17 is hinged to one side of the bolt so that the front, back, upper surface is open to insert the connecting frame 15 to be fastened, and the connecting frame 15 is detached by rotating the bolt at the upper left and right sides. It is fastened and the other side is a structure in which a fastening groove is formed to fasten the bolt.

따라서 연결프레임(15)이 클램프(17)에 삽입되면 볼트를 회동하여 체결홈에 삽입한 후 너트로 견고하게 조임 체결한다.Therefore, when the connecting frame 15 is inserted into the clamp 17, the bolt is rotated and inserted into the fastening groove, and then tightened and tightened with a nut.

또한 상기 좌우측몸체(3, 4)의 수직프레임(7)에는 연결몸체(2)의 좌우측프레임(22, 23)과 분리 조립할 수 있도록 동일위치에 체결공(8)이 각각 각각 형성된다.In addition, the fastening holes 8 are respectively formed at the same positions in the vertical frames 7 of the left and right bodies 3 and 4 so as to be separately assembled with the left and right frames 22 and 23 of the connecting body 2.

또한 상기 수직프레임(7) 인접부인 하부프레임(6)에는 연결몸체(2)와 체결시 견고함을 보강하기 위한 보강판(24)을 체결할 수 있도록 체결공(8)이 각각 형성된다.In addition, the lower frame 6 adjacent to the vertical frame 7 is formed with fastening holes 8 so as to fasten the reinforcing plate 24 for reinforcing the rigidity when the connection body 2 and the fastening.

또한 상기 좌우측몸체(3, 4) 사이에 위치하여 분리 조립되는 연결몸체(2)는 오각형형상으로 하부프레임(6) 양단에 좌우측프레임(22, 23)과 상기 좌우측프레임(22, 23) 상단에는 경사지게 상부프레임(5)이 서로 체결되고 내부에는 하중을 지지하도록 지지부재(10)가 내설된다.In addition, the connecting body 2 which is separated and assembled between the left and right bodies 3 and 4 has a pentagonal shape and has left and right frames 22 and 23 at both ends of the lower frame 6 and upper left and right frames 22 and 23. The support member 10 is inclined so that the upper frames 5 are inclined with each other and support the load therein.

또한 상기 상부프레임(5) 상단에는 좌우측몸체(3, 4)와 동일하게 각각의 트러스(100)를 연결하는 연결바(15)가 착탈되도록 클램프(17)를 부착한다.In addition, the upper side of the upper frame 5 is attached to the clamp 17 so that the connection bar 15 for connecting the respective truss 100 in the same way as the left and right body 3, 4 attached.

따라서 상기 좌우측몸체(3, 4) 사이에 연결몸체(2)를 밀착한 후 견고하게 조립되도록 수직프레임(7)과 좌우측프레임(22, 23)에 형성된 체결공(8)에 볼트(9)를 삽입 너트로 조임체결함으로써 일체화된 트러스(100)를 구성하는 것이다.Therefore, the bolts 9 are fastened to the fastening holes 8 formed in the vertical frame 7 and the left and right frames 22 and 23 so as to be firmly assembled after the connection body 2 is closely contacted between the left and right bodies 3 and 4. By tightening with an insertion nut, an integrated truss 100 is formed.

한편 좌우측몸체(3, 4)와 연결몸체(2)의 하부프레임(6)에는 견고함을 보강하 기위하여 보강판(24)을 밀착한 후 체결공(8)에 볼트를 체결한다.On the other hand, the left and right body (3, 4) and the lower frame (6) of the connecting body (2) in close contact with the reinforcing plate 24 to reinforce the firmness and then fasten the bolt to the fastening hole (8).

도 3은 본 고안 지붕틀을 평형에 따라 교체하여 사용할 수 있는 것을 도시해 보인 사시도이다.Figure 3 is a perspective view showing that the present invention can be used to replace the roof frame according to the equilibrium.

본 고안은 분리 결합이 가능한 트러스(100)를 공장에서 규격화시켜 제작함으로써 시공중인 아파트의 평형에 따라 좌우측몸체(3, 4)에서 연결몸체(2)만 교체하여 사용할 수 있도록 한다.The present invention is to make the truss (100) that can be separated and combined in the factory standardized to be used by replacing only the connecting body (2) in the left and right body (3, 4) according to the balance of the apartment under construction.

즉 상기 좌우측몸체(3, 4)의 크기는 동일하고 연결몸체(2)의 크기는 시공중인 아파트 평행에 알맞게 미리 제작한 것으로서, 예를 들면 시공중인 32평형인 아파트에 사용한 후 45평에 아파트에 사용할때는 좌우측몸체(3, 4)는 그대로 사용하고 45평형에 맞게 제작된 연결몸체(2)만을 교체하여 다시 사용할 수 있다.That is, the size of the left and right body (3, 4) is the same, and the size of the connecting body (2) is made in advance for the parallel to the apartment in construction, for example, used in the 32-flat apartment in construction, and then to the apartment in 45 pyeong When used, the left and right body (3, 4) can be used as it is and can be used again by replacing only the connecting body (2) made to fit the 45 balance.

도 4는 본 고안 처마를 도시해 보인 사시도이고, 도 5는 본 고안 지붕틀을 구성하는 트러스에 처마가 부착된 것을 도시해 보인 사시도이다.Figure 4 is a perspective view showing the present invention eaves, Figure 5 is a perspective view showing the eaves attached to the truss constituting the present invention truss.

본 고안은 아파트 공사용 보온 덮개 지붕틀(1)의 전면과 배면에 위치하는 트러스(100)에 직삼각형 형상의 처마(20)를 탈부착하여 빗물등의 고임현상이 없도록한다.The present invention is to prevent the high water phenomenon such as rain water by attaching and detaching the eaves (20) of the triangular shape to the truss (100) located on the front and rear of the thermal insulation cover truss (1) for apartment construction.

상기 처마(20)를 부착하기위해서는 좌우측몸체(3, 4)와 연결몸체(2) 내부에 수직으로 내설된 지지부재(10)에 처마(20)의 체결프레임(18)을 체결하기위한 클램프(17)가 각각 부착된다.In order to attach the eaves 20, clamps for fastening the fastening frame 18 of the eaves 20 to the support members 10 vertically embedded in the left and right bodies 3 and 4 and the connecting body 2 ( 17) are attached respectively.

한편 상기 클램프(17)는 좌우측몸체(3, 4)와 연결몸체(2)의 상부프레임(5)에 부착된 것과 동일한 구조이다.Meanwhile, the clamp 17 has the same structure as that attached to the left and right bodies 3 and 4 and the upper frame 5 of the connecting body 2.

또한 처마(20)는 수직형태인 체결프레임(18) 하부에는 지지부재(10)에 삽입되면서 하부프레임(6)에 안착되도록 상하좌우로 통공된 브라켓(19)이 부착된다.In addition, the cornice 20 is inserted into the support member 10 in the lower portion of the fastening frame 18 of the vertical shape is attached to the bracket 19 through the upper and lower left and right to be seated on the lower frame (6).

따라서 상기 트러스(100)를 구성하는 좌우측몸체(3, 4)와 연결몸체(2) 내부에 수직으로 내설된 지지부재(10)에 처마(20)를 부착하기위하여 체결프레임(18)에 부착된 브라켓(19)을 삽입하면 하부프레임(6)에 안착되고 클램프(17)에 의해 처마(20)의 체결프레임(18)을 체결하여 부착하는 것이다.Therefore, the left and right bodies 3 and 4 constituting the truss 100 and the connection body 2 are attached to the fastening frame 18 to attach the eaves 20 to the support members 10 vertically in the interior. Inserting the bracket 19 is seated on the lower frame (6) is to fasten and attach the fastening frame 18 of the eaves 20 by the clamp (17).

도 6은 본 고안에 연결바가 결합된 것을 도시해 보인 사시도이고, 도 7는 본 고안에 천막을 덮은 것을 도시해 보인 사시도이며, 도 8은 본 고안을 사용상태를 도시해 보인 예시도이다.Figure 6 is a perspective view showing that the connection bar is coupled to the subject innovation, Figure 7 is a perspective view showing a tent covering the subject innovation, Figure 8 is an exemplary view showing a state of use of the subject innovation.

본 고안은 동절기에 아파트를 시공할때 콘크리트 슬래브의 빠른 양생을 위해 설치하는 조립식 덮개 지붕틀(1)은 아파트의 평형에 맞게 공장에서 미리 규격화되게 제작된 트러스(100)를 연결몸체(2), 좌우측몸체(3, 4), 연결바(15), 처마(20)로 분리하여 운반한 후 공사현장에서 아파트의 평형에 맞게 연결몸체(2)를 선택한 후 좌우측몸체(3, 4)와 볼트(9) 체결하여 조립된 트러스(100)를 수평하게 배열한 후 상기 배열된 트러스(100)를 일체화시키기 위해 상부프레임(5)에 부착된 각각의 클램프(17)에 연결프레임(15)을 삽입 체결하여 지붕틀(1)을 형성한다.The present invention is a prefabricated cover truss (1) installed for fast curing of the concrete slab when construction of the apartment in winter, the truss (100) made in advance in the factory according to the equilibrium of the apartment connecting body (2), left and right After separating and transporting to the body (3, 4), connecting bar (15), eaves (20), select the connecting body (2) in accordance with the equilibrium of the apartment at the construction site and then left and right bodies (3, 4) and bolts (9) After fastening the assembled truss 100 horizontally by fastening and inserting and connecting the connection frame 15 to each clamp 17 attached to the upper frame 5 to integrate the arranged truss 100 The truss 1 is formed.

또한 상기 지붕틀(1)의 전면과 배면 가장자리에 위치하는 트러스(100)에는 처마(20)를 각각 부착하고 그 위에 천막(13)을 덮어 씌어 완성하는 것이다.In addition, the truss 100 located on the front and rear edges of the truss 1 is attached to the eaves 20 and covered with the tent 13 on it.

또한 상기 트러스(100)를 구성하는 좌우측몸체(3, 4)의 상부프레임(5) 상단 가장자리에는 완성된 보온 덮개 지붕틀(1)을 콘크리트 슬래브까지 크레인에 의해 견인할 수 있도록 인양고리(12)가 각각 형성되어 있다.In addition, the upper edge of the upper frame (5) of the left and right body (3, 4) constituting the truss 100, the lifting ring (12) is to be pulled by the crane to the finished thermal insulation cover truss (1) to the concrete slab Each is formed.

따라서 보온 덮개 지붕틀(1)에 형성된 인양고리(12)에 와이어를 서로 연결하여 크레인의 훅에 걸어서 크레인으로 들어올려 가설구조물(14)상에 설치한다. Therefore, the wires are connected to the lifting hooks 12 formed on the thermal insulation cover truss 1, hooked to the hooks of the cranes, lifted up by the cranes, and installed on the temporary structure 14.

이에 따라, 본 발명에 따른 건축물 공사용 덮개를 이용하는 경우, 높은 가설구조물(14)상에서 조립하지 않아도 되는 것을 물론 아파트의 평형에 따라 트러스(100)를 조립할때 좌우측몸체(3, 4)는 그대로 사용하고 연결몸체(2)만 평형에 맞게 교체 조립하여 사용할 수 있는 구조이다.Accordingly, in the case of using the cover for building construction according to the present invention, the assembly of the truss 100 according to the equilibrium of the apartment, as well as the need not to assemble on the high temporary structure 14 is used as it is Only the connecting body (2) is a structure that can be used to replace the assembly to balance.

또한 상기 보온 덮개 지붕틀(1)을 설치한 후 동절기가 지나거나 공사현장이 끝난 경우에는 비바람에 찢어진 천막(13)은 폐기하고 다음해의 동절기 공사현장에서 재사용할 수 있도록 트러스(100)를 보관이 용이하도록 분리 해체한다.In addition, if the winter cover after the installation of the insulation cover truss (1) or when the construction site is finished, the tent (13) torn in the wind is discarded and the truss (100) is stored so that it can be reused in the winter construction site next year. Separate and disassemble to facilitate.

이상에서 설명한 바와 같이 본 고안 아파트 공사용 보온 덮개 지붕틀은 동절기 또는 공사현장이 끝난후에는 바로 폐기하는게 아니라 다음해에 동절기 공사현장에서 여러번 재 사용할 수 있도록 보관이 용이하게 분해 조립하고, 또한 설치되는 아파트의 평형에 맞게 트러스를 규격화하여 연결몸체만 평형에 따라 교체하고 좌우측몸체는 그대로 사용함으로써 공사현장에 사용하는 부속물을 줄일 수 있어 재활용에 따른 건축비용 절감할 수 있는 효과가 있다.As described above, the thermal insulation cover truss for the construction of the present invention is not disposed of immediately after the end of the winter season or the construction site, but is easily disassembled and assembled so that it can be reused several times in the winter construction site in the following year. By standardizing the truss according to the equilibrium, only the connecting body can be replaced according to the equilibrium, and the left and right bodies can be used as it is, thereby reducing the accessories used at the construction site, thereby reducing the construction cost due to recycling.

Claims (4)

강체가 연결되어 구성된 트러스를 수평하게 각각 배열한 후 각각의 트러스를 연결하기 위하여 상부에 교차되어 용접된 다수개의 연결바와 그위에 크레인의 훅을 걸 수 있도록 하기 위한 인양고리를 포함하여 구성되고, 필요에 따라 천막을 덮어 씌워, 건축하기 위한 구조물 주변으로 설치되는 가설구조물 상에 크레인을 이용하여 일체로 들어올려 설치할 수 있도록 된 보온 덮개 지붕틀에 있어서,It is composed of a plurality of connecting bars welded on the upper part to connect each truss after arranging the trusses formed by the rigid body connected horizontally, and a lifting hook for hooking the crane on it. In the thermal insulation cover truss which covers the tent and can be lifted and installed integrally using a crane on the temporary structure installed around the structure for building, 상기 아파트 공사용 보온 덮개 지붕틀은 소정의 간격으로 배열되는 트러스를 대칭형상인 한쌍의 좌우측몸체와 상기 좌우측몸체 사이에서 분리결합되는 연결몸체를 구성하되, 하부프레임 양단에 좌우측프레임과 좌우측프레임 상단에 경사지게 상부프레임과 내부에는 지지부재가 내설되고, 상기 상부프레임 상단에는 각각의 트러스를 연결하는 연결프레임이 착탈되도록 클램프를 부착한 연결몸체와;The thermal insulation cover truss for the apartment construction constitutes a pair of left and right bodies having a symmetrical shape and a connecting body separated between the left and right bodies, the trusses arranged at predetermined intervals, the upper frame inclined to the left and right frames and the left and right upper frames at both ends of the lower frame. And a support body internally installed therein, and a connection body having a clamp attached to and detachable from a connection frame connecting the respective trusses to the upper end of the upper frame; 상기 연결몸체 양단에 위치하는 좌우측프레임과 밀착되도록 상부프레임과 하부프레임과 수직프레임이 직삼각형 형상에 내부에는 지지부재가 내설되고, 연결몸체 좌우측프레임과 체결이 가능하도록 볼트공이 각각 형성되어 볼트 체결되며, 상단에는 각각의 트러스를 연결하는 연결프레임이 착탈되도록 클램프가 부착된 것을 특징으로 하는 조립식 덮개용 지붕틀.The upper frame and the lower frame and the vertical frame are in a right triangle shape so as to be in close contact with the left and right frames positioned at both ends of the connecting body, and a supporting member is internally formed therein, and bolt holes are formed by bolts to be fastened to the left and right connecting frames, respectively. Prefabricated cover truss, characterized in that the clamp is attached to the top so that the connection frame for connecting each truss detachable. 제 1항에 있어서, 상기 분리 조립되는 트러스에 견고함을 보강할 수 있도록 좌우측몸체의 수직프레임과 연결몸체의 좌우측프레임 인접부의 하부프레임에 각각 형성된 체결공과 동일하게 체결공이 형성된 보강판이 하부프레임 하단에 볼트 체결된 것을 특징으로 하는 조립식 덮개용 지붕틀.The reinforcing plate having a fastening hole formed at the bottom of the lower frame according to claim 1, wherein the reinforcing plate is formed at the bottom of the lower frame in the same way as the fastening holes formed in the vertical frames of the left and right bodies and the lower frames adjacent to the left and right frames of the connecting body so as to reinforce the truss to be separated and assembled. Prefabricated cover truss characterized in that the bolt is fastened. 제 1항에 있어서, 상기 아파트 공사용 보온 덮개 지붕틀의 전면과 배면에 위치하는 트러스에 처마를 탈부착할 수 있도록 좌우측몸체와 연결몸체에 수직으로 내설된 지지부재에 처마의 체결프레임을 체결하기 위한 클램프와;According to claim 1, Clamps for fastening the eaves fastening frame to the support member vertically installed on the left and right body and the connecting body to attach the eaves to the trusses located on the front and back of the thermal insulation cover truss for the apartment construction ; 상기 지지부재에 부착된 클램프에 체결하도록 지지부재에 삽입되면서 하부프레임에 안착되도록 체결프레임 하부에 상하좌우로 통공된 브라켓이 부착된 처마가 조립되는 것을 특징으로 하는 조립식 덮개용 지붕틀.Prefabricated cover roof frame, characterized in that the eaves are attached to the lower portion of the fastening frame is attached to the support member to be fastened to the clamp attached to the support member attached to the lower frame to be mounted to the lower frame. 제 1항에 있어서, 공사용 보온 덮개 지붕틀을 아파트의 평형에 상관없이 사용할 수 있도록 좌우측몸체는 그대로 사용하고 평형에 맞게 미리 제작된 연결몸체만 교체하여 조립되는 것을 특징으로 하는 조립식 덮개용 지붕틀.The prefabricated cover roof frame according to claim 1, wherein the left and right bodies are used as they are so as to be used regardless of the equilibrium of the apartment, and only the connecting bodies pre-fabricated according to the balance are assembled.
KR2020050032138U 2005-11-14 2005-11-14 Roof Frame of Keeping Warmth Cover KR200408091Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020050032138U KR200408091Y1 (en) 2005-11-14 2005-11-14 Roof Frame of Keeping Warmth Cover

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020050032138U KR200408091Y1 (en) 2005-11-14 2005-11-14 Roof Frame of Keeping Warmth Cover

Publications (1)

Publication Number Publication Date
KR200408091Y1 true KR200408091Y1 (en) 2006-02-07

Family

ID=44481444

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020050032138U KR200408091Y1 (en) 2005-11-14 2005-11-14 Roof Frame of Keeping Warmth Cover

Country Status (1)

Country Link
KR (1) KR200408091Y1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100845461B1 (en) 2007-01-08 2008-07-10 진요임 Building construction keeping cover truss
KR101688773B1 (en) * 2016-06-03 2016-12-22 박용필 Reversible pretress introduction device and reinforcement and reconstruction method of structure using the same
KR101975513B1 (en) 2018-09-18 2019-08-28 조덕훈 Prefabricate temporarily roof for structure slab
KR20210114799A (en) * 2020-03-11 2021-09-24 삼목에스폼 주식회사 Apparatus for installing concrete curing membrane

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100845461B1 (en) 2007-01-08 2008-07-10 진요임 Building construction keeping cover truss
KR101688773B1 (en) * 2016-06-03 2016-12-22 박용필 Reversible pretress introduction device and reinforcement and reconstruction method of structure using the same
KR101975513B1 (en) 2018-09-18 2019-08-28 조덕훈 Prefabricate temporarily roof for structure slab
KR20210114799A (en) * 2020-03-11 2021-09-24 삼목에스폼 주식회사 Apparatus for installing concrete curing membrane
KR102330312B1 (en) * 2020-03-11 2021-11-24 삼목에스폼 주식회사 Apparatus for installing concrete curing membrane

Similar Documents

Publication Publication Date Title
KR200408091Y1 (en) Roof Frame of Keeping Warmth Cover
US20050081904A1 (en) Field tent against crosswind
JP4417371B2 (en) Snowfall prevention device
US20090071080A1 (en) Temporary construction and associated method of assembly
KR100845461B1 (en) Building construction keeping cover truss
JP2007270529A (en) Construction method for external facing structure
KR100509622B1 (en) Roof frame of warmth keeping cover for constructing a structure
KR101268221B1 (en) tent
KR100994412B1 (en) Membrane fixing structure of architectural structure and construction method thereof
KR200348011Y1 (en) Structure support for a vinyl house use a wire
KR200379642Y1 (en) Roof frame of warmth keeping cover for constructing a structure
KR100366715B1 (en) Plastic house
CN1137303A (en) Flexible formwork assembly
KR100950460B1 (en) Dome style lightweight iron frame infrastructure
US5899029A (en) Support structure for floor plates
KR200407047Y1 (en) Soundproof wall combined fall prevention
KR200272629Y1 (en) connecting construction of tent
KR100588983B1 (en) Framework system for a vinyl plastic hothouse
JP4110318B2 (en) Drainage structure of simple structure
JP2006124981A (en) Roof ventilator and its installation method
JP3047783B2 (en) Reinforcement method of existing wooden building
JP4774425B2 (en) Snowfall prevention structure
KR200465745Y1 (en) windbreak supporting tool for landscape of road
JP2003321913A (en) Method for repairing handrail and attachment device for new handrail
JP3022674U (en) Roof tiles for supporting columns

Legal Events

Date Code Title Description
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
FPAY Annual fee payment

Payment date: 20091116

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee