KR200233607Y1 - Low Plate Structure of the Bridge Bearing - Google Patents

Low Plate Structure of the Bridge Bearing Download PDF

Info

Publication number
KR200233607Y1
KR200233607Y1 KR2020010004328U KR20010004328U KR200233607Y1 KR 200233607 Y1 KR200233607 Y1 KR 200233607Y1 KR 2020010004328 U KR2020010004328 U KR 2020010004328U KR 20010004328 U KR20010004328 U KR 20010004328U KR 200233607 Y1 KR200233607 Y1 KR 200233607Y1
Authority
KR
South Korea
Prior art keywords
steel plate
lower steel
mortar
bridge
shrink mortar
Prior art date
Application number
KR2020010004328U
Other languages
Korean (ko)
Inventor
오경환
고용춘
Original Assignee
(주)한석엔지니어링건축사사무소
김태한
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한석엔지니어링건축사사무소, 김태한 filed Critical (주)한석엔지니어링건축사사무소
Priority to KR2020010004328U priority Critical patent/KR200233607Y1/en
Application granted granted Critical
Publication of KR200233607Y1 publication Critical patent/KR200233607Y1/en

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

본 고안은 교좌장치용 하부강판 구조에 관한 것으로, 교량 상부구조물의 하부면에 정착되는 상부강판(10)과, 교대 또는 교각의 코핑부에 정착되는 하부강판 (20)과, 상기 상,하부강판(10)(20)들의 사이에 개재되어 교량의 압축력과 변형력을 지지하는 베어링패드(30)로 구성되어 교량의 상부구조에서 전달되는 자중과 교통하중을 하부구조물에 전달하는 교좌장치에 있어서, 상기 하부강판(40)의 중앙부에 소정의 크기를 가지면서 수직으로 관통하는 무수축몰탈 타설용 개공(21)을 형성하여서, 하부강판(20)을 교대 또는 교각 등의 코핑부에 견고히 정착시키기 위해 정위치에 셋팅시키고 주변에 거푸집을 설치한 후 강판하부에 실시하는 무수축몰탈 타설 공사시, 하부강판(20)의 측면과 거푸집 사이에 형성된 공간과 함께 상기 무수축몰탈 타설용 개공(21)을 이용하여 무수축몰탈을 주입토록 하고 개공(21) 부분에는 강판덮개(22)로 볼트체결하여 마무리함으로써, 하부강판의 하부에 타설되는 무수축몰탈을 간편하면서도 밀실하게 채울 수 있게 되어 시공이 용이할 뿐만 아니라, 무수축몰탈의 소요강도 및 품질이 확보되어서 교좌장치의 구조적인 안정성을 보장하고 사용수명을 대폭 연장할 수 있게 하여 주는 것이다.The present invention relates to a lower steel plate structure for a bridge device, the upper steel plate 10 is fixed to the lower surface of the bridge upper structure, the lower steel plate 20 is fixed to the coping portion of the alternating or piers, and the upper and lower steel plates (10) (20) interposed between the bearing pad (30) for supporting the compressive and deformation forces of the bridge to transfer the self-weight and traffic loads transmitted from the upper structure of the bridge to the lower structure, wherein The opening of the non-shrink mortar pouring hole 21 having a predetermined size in the center of the lower steel plate 40, and vertically penetrating, so that the lower steel plate 20 is firmly fixed to the coping portion such as alternating or pier After setting the position and installing the formwork around the non-shrink mortar casting work to be carried out on the bottom of the steel sheet, using the opening for the non-shrink mortar pouring with the space formed between the side and the formwork of the lower steel plate 20 By injecting non-shrink mortar and bolted to the opening 21 to the steel plate cover 22, the non-shrink mortar, which is placed on the lower part of the lower steel sheet, can be easily and tightly filled, thereby making construction easier. In addition, the required strength and quality of the non-shrink mortar is secured to ensure the structural stability of the teaching device and to significantly extend the service life.

Description

교좌장치용 하부강판 구조{Low Plate Structure of the Bridge Bearing}Low Plate Structure of Bridge Unit

본 고안은 교량의 상부구조에서 전달되는 자중과 교통하중을 하부구조물에 전달하기 위한 교좌장치에 관한 것으로, 특히 교량 상부구조의 압축력과 변형력을 지지하는 베어링패드를 설치하기 위해 교대 또는 교각의 코핑부에 정착되는 하부강판 구조를 개량하여 무수축몰탈의 타설이 용이하면서 밀실하게 채워질 수 있도록 한 교좌장치용 하부강판 구조에 관한 것이다.The present invention relates to a bridge device for transmitting the magnetic and traffic loads transmitted from the superstructure of the bridge to the substructure, in particular the coping portion of the alternating or piers to install bearing pads that support the compressive and deformation forces of the bridge superstructure The present invention relates to a lower steel plate structure for an apparatus for improving a lower steel plate structure to be fixed to the lower steel plate so that it can be easily and tightly filled.

교좌장치는 교량의 상부구조에서 작용하는 하중 및 변형을 흡수하거나 감소시켜서, 교량의 하부구조물에 무리한 힘이 전달되지 않도록 하며, 상부구조물의 국부적인 변형을 완화시킬 수 있도록 설치하는 완충장치로서 중·대형 교량에는 필수적으로 설치하고 있다.The bridge device is a shock absorber that absorbs or reduces loads and deformations acting on the superstructure of the bridge so that excessive force is not transmitted to the undercarriage of the bridge, and is installed to mitigate local deformation of the superstructure. It is essentially installed in large bridges.

이러한 교좌장치 중 하나로서 패드-슈 타입(pad-shoe type)이 있는데, 이 교좌장치는 도1의 도시와 같이, 교량 상부구조물(U)의 하부면에 정착되는 상부강판 (1)과, 교대 또는 교각(L)의 코핑(coping)부분에 정착되는 하부강판(2)과, 상기 상,하부강판(1)(2)들의 사이에 개재되어 교량의 압축력과 변형력을 지지하는 베어링패드(3)로 구성된다.One such a device is a pad-shoe type (pad-shoe type), which is shown in Figure 1, the upper steel plate (1) which is fixed to the lower surface of the bridge upper structure (U), alternately Or a bearing pad 3 interposed between the lower steel plate 2 fixed to the coping portion of the bridge L and the upper and lower steel plates 1 and 2 to support the compression and deformation forces of the bridge. It consists of.

그리고, 교량 상부구조 및 교통량에 따라 그 규격이 정해지며, 상,하부강판의 두께는 원칙적으로 22㎜이상으로 하고, 주요부의 두께는 주 강재 받침에 있어서는 25㎜이상이며, 주 철재 받침에서는 35㎜이상으로 교량상부 하중을 확실하게 하부 구조에 전달할 수 있도록 되어 있다.The standard is determined according to the upper structure of the bridge and the traffic volume. The thickness of the upper and lower steel plates is, in principle, not less than 22 mm, and the thickness of the main part is not less than 25 mm for the cast steel support, and 35 mm for the cast iron support. As mentioned above, it is possible to reliably transmit the upper load of the bridge to the lower structure.

상기와 같은 패드-슈 타입 교좌장치에서 상,하부강판(1)(2)은 그것들의 사이에 개재되는 베어링패드(3)의 미끄럼성을 확보하기 위한 것으로, 특히 하부강판(2)은 추후 시공되는 교량 상부구조의 수평도를 확보하기 위해 정밀 시공해야 하는 중요한 부분이다.The upper and lower steel plates (1) and (2) in the pad-shoe type stapling device as described above are to secure the sliding property of the bearing pads 3 interposed therebetween, and in particular, the lower steel plate 2 is constructed later. It is an important part that must be precisely constructed to secure the horizontality of the bridge superstructure.

종래 일반적으로 사용되는 하부강판(2)은 도2a의 도시와 같이 4각플레이트 형태로 되어 있으며, 그 하부에 고정된 앵커볼트(4)들을 통해 교대 또는 교각(L)의 코핑(coping)부분에 정착하도록 되어 있다.Conventionally commonly used lower steel plate (2) is in the form of a square plate, as shown in Figure 2a, through the anchor bolts (4) fixed to the lower portion of the coping (coping) of the alternating or piers (L) It is supposed to settle down.

이와 같은 하부강판(2)을 설치함에 있어서는, 도2b의 도시와 같이 교대 또는 교각(L)의 코핑부를 일정부분 절취해 내서 앵커볼트(4)가 매입될 자리를 확보한 다음, 받침보강을 위한 방석철근(5) 및 정위치 셋팅을 위한 체어철근(6)을 배치하고, 설치 위치에 대한 정확한 좌표 측량을 실시하면서 크레인을 이용해 하부강판(2)을 수평하게 셋팅한 후, 앵커볼트(4)를 체어철근(6)과 연결하여 하부강판(2)이 유동하지 않도록 고정시킨다.In installing such a lower steel plate 2, as shown in Figure 2b, by cutting a portion of the coping portion of the alternating or piercing (L) to secure a place where the anchor bolt (4) is to be embedded, and then for the reinforcement of the support After placing the reinforcing bar (5) and the chair reinforcing bar (6) for the exact position setting, and setting the lower steel plate (2) horizontally using a crane while performing accurate coordinate measurement for the installation position, anchor bolt (4) Is connected to the chair reinforcement (6) to fix the lower steel plate (2) does not flow.

이어서, 도2c의 도시와 같이 하부강판(2)의 주변에 무수축몰탈 구조체의 설계규격에 맞추어 거푸집(7)을 설치하고, 하부강판(2) 측면과 거푸집(7) 사이의 공간을 이용하여 측면에서 무수축몰탈(8)을 부은 후에 양생하고 탈형함으로써, 하부강판(2)의 설치작업을 완료하게 된다.Subsequently, as shown in FIG. 2C, the formwork 7 is installed around the lower steel plate 2 in accordance with the design specification of the non-shrink mortar structure, and the space between the side surface of the lower steel plate 2 and the formwork 7 is used. By curing and demoulding after pouring the non-contraction mortar 8 from the side, the installation work of the lower steel plate 2 is completed.

그런데, 상기와 같은 종래 하부강판(2)의 설치과정에서 하부강판(2)의 측면 부분은 무수축몰탈(8)의 다짐작업이 가능하고 육안으로 시공상태를 확인할 수 있어 무수축몰탈(8)의 적정강도 및 품질확보가 가능하나, 하부강판(2)의 중앙부 아래는 다짐작업도 불가능하고 측면에서 타설한 무수축몰탈(8)이 중심부까지 완전 충진되었는지 여부를 육안으로 확인할 수가 없기 때문에 무수축 몰탈의 적정강도를 확보하는데 곤란할 뿐만 아니라, 도2c의 도시와 같이 하부강판(2)의 중앙 저부에 공동 (C)이 발생되어 품질을 크게 저하시키는 문제점이 있었다.By the way, the side portion of the lower steel plate (2) in the installation process of the conventional lower steel plate 2 as described above can be compacted work of the non-condensation mortar (8) and the construction state can be confirmed with the naked eye no shrinkage mortar (8) Although it is possible to secure the proper strength and quality of the steel sheet, it is impossible to compact below the central part of the lower steel plate 2, and it is not possible to check whether the non-condensation mortar (8) poured from the side is completely filled to the center. Not only is it difficult to secure the appropriate strength of the mortar, there is a problem that the cavity (C) is generated in the center bottom of the lower steel plate 2, as shown in Figure 2c to significantly reduce the quality.

이를 해결하기 위해 현장에서는 무수축몰탈의 반죽질기 상태를 시방규정보다 질게 개어 시공함으로써 교좌장치 하부강판 측면에서 타설한 무수축몰탈이 강판의 중심부까지 완전히 흘러들어 가도록 기대하고 있으나, 이 방법 역시 미봉책에 불과한 것으로 무수축몰탈의 밀실한 채움이 곤란한 것은 물론, 무수축몰탈이 적정배합에서 벗어나기 때문에 양생이 완료된 무수축몰탈 구조체의 강도를 크게 저하시키게 되는 문제가 있다.In order to solve this problem, the site expects the non-shrink mortar to be completely flown to the center of the steel plate by installing the kneading state of the non-shrink mortar with the specification information. It is not only difficult to secure the filling of the non-condensation mortar, of course, there is a problem that greatly reduces the strength of the non-condensation mortar structure completed curing because the non-contraction mortar is out of the proper mixing.

이에 따라 본 고안은 교량의 상부 구조에서 전달되는 교량 상부구조 무게와 교통하중을 하부구조물에 전달하는 역할을 하는 교좌장치의 하부강판을 설치하는데 있어 종래 기술이 가지는 제 문제점을 해결하기 위해 안출한 것이다.Accordingly, the present invention has been devised to solve the problems of the prior art in installing the lower steel plate of the bridge device that serves to transfer the weight and traffic loads of the bridge superstructure transmitted from the superstructure of the bridge to the substructure. .

따라서 본 고안의 목적은 교대 또는 하부강판의 하부에 타설되는 무수축몰탈을 간편하면서도 밀실하게 채울 수 있게 함으로써, 시공이 용이할 뿐만 아니라, 무수축몰탈의 소요강도 및 품질이 확보되어서 구조적으로 보다 견실한 교좌장치를 얻을 수 있게 하여 주는 교좌장치용 하부강판 구조를 제공하는데 있다.Therefore, the object of the present invention is to enable easy and tight filling of the non-condensation mortar, which is placed on the lower part of the alternating or lower steel plate, and is easy to construct, and the required strength and quality of the non-condensation mortar are ensured, thereby making it more structurally robust. It is to provide a lower steel plate structure for the chair device to obtain a chair device.

상기 목적을 달성하기 위해 본 고안은 교각의 코핑부에 정착되는 하부강판 구조를 개량하여 교량 받침의 하부강판에 무수축 몰탈 타설시 하부강판 측면과 중앙부에서 동시에 타설할 수 있도록 한 기술구성을 제공한다.In order to achieve the above object, the present invention improves the structure of the lower steel plate fixed to the coping part of the pier to provide a technical configuration that can be poured simultaneously from the side of the lower steel plate and the center part when non-contraction mortar is placed on the lower steel plate of the bridge support. .

도1은 패드-슈 타입의 교좌장치를 개략적으로 나타낸 일측면도1 is a side view schematically showing a pad-shoe type staggering device;

도2a는 종래 교좌장치에 사용되는 하부강판의 사시도Figure 2a is a perspective view of the lower steel plate used in the conventional teaching device

도2b는 종래의 하부강판을 교각의 코핑부에 세팅된 상태를 나타낸 단면도Figure 2b is a cross-sectional view showing a state in which the conventional lower steel plate is set in the coping portion of the piers

도2c는 종래 하부강판을 이용해 무수축몰탈 타설을 완료한 상태의 단면도Figure 2c is a cross-sectional view of the completion of the non-shrink mortar casting using a conventional lower steel sheet

도3은 본 고안에 따른 교좌장치용 하부강판의 사시도Figure 3 is a perspective view of the lower steel plate for the chair apparatus according to the present invention

도4는 본 고안 하부강판을 교각의 코핑부에 셋팅된 상태를 나타낸 단면도Figure 4 is a cross-sectional view showing a state in which the lower steel sheet of the present invention is set to the coping portion of the piers

도5는 본 고안 하부강판을 이용해 무수축몰탈 타설을 완료한 상태의 단면도Figure 5 is a cross-sectional view of completing the non-shrink mortar casting using the present invention lower steel sheet

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10:상부강판 20:하부강판10: upper steel plate 20: lower steel plate

21:무수축몰탈 타설용 개공 22:강판덮개21: Opening for non-shrink mortar casting 22: Steel plate cover

30:베어링패드 40:앵커볼트30: bearing pad 40: anchor bolt

50:방석철근 60:체어철근50: cushion rebar 60: chair rebar

70:거푸집 80:무수축몰탈70: die 80: non-shrink mortar

U:상부구조물 L:교각U: Upper structure L: Pier

이하, 본 고안의 기술구성을 첨부도면을 참조하여 상세히 설명한다.Hereinafter, the technical configuration of the present invention will be described in detail with reference to the accompanying drawings.

도3은 본 고안에 따른 교좌장치용 하부강판을 나타낸 사시도이고, 도4는 무수축몰탈 타설전 본 고안의 하부강판을 교각의 코핑부에 세팅된 상태를 나타낸 단면도이며, 도5는 본 고안을 이용해 무수축몰탈의 타설을 완료한 상태의 단면도이다.Figure 3 is a perspective view showing a lower steel plate for the seating apparatus according to the present invention, Figure 4 is a cross-sectional view showing a state in which the lower steel plate of the present invention is set to the coping portion of the piers before non-contraction mortar casting, Figure 5 is the present invention It is sectional drawing of the state which completed the use of non-contraction mortar.

본 고안은 도1의 도시와 같이, 교량 상부구조물(U)의 하부면에 정착되는 상부강판(10)과, 교대 또는 교각(L)의 코핑부에 정착되는 하부강판(20)과, 상기 상,하부강판(10)(20)들의 사이에 개재되어 교량의 압축력과 변형력을 지지하는 베어링패드(30)로 구성되어 교량의 상부구조에서 전달되는 자중과 교통하중을 하부구조물에 전달하는 교좌장치에 있어서, 상기 하부강판(20)의 구조가 4각플레이트 형태로 되고, 그 하부에 고정된 앵커볼트(40)들을 통해 교대 또는 교각(L)의 코핑(coping)부분에 정착된다는 점에 있어서는 종래의 하부강판과 기술적 개념을 같이 한다.The present invention, as shown in Figure 1, the upper steel plate 10 is fixed to the lower surface of the bridge upper structure (U), the lower steel plate 20 is fixed to the coping portion of the alternating or bridge (L), and the upper The bearing pad 30 is interposed between the lower steel plates 10 and 20 to support the compressive force and the deformation force of the bridge, so that the self-weight and traffic load transmitted from the upper structure of the bridge are transferred to the lower structure. In the structure of the lower steel plate 20 is in the form of a quadrangular plate, and anchored to the coping portion of the alternating or piercing (L) through the anchor bolts 40 fixed to the bottom of the conventional Share the technical concept with the lower plate.

다만, 본 고안은 도3의 도시와 같이 상기 하부강판(20)의 중앙부에 소정의크기를 가지면서 수직으로 관통하는 무수축몰탈 타설용 개공(21)을 형성한 것을 기술구성상의 기본적인 특징으로 한다.However, the present invention is a basic feature of the technical configuration that is formed in the central portion of the lower steel plate 20 as shown in FIG. .

상기 무수축몰탈 타설용 개공(21)은 그 직경이 7∼9㎝의 범위를 갖는 원형구멍으로 형성함이 바람직하다.It is preferable that the above-mentioned non-contraction mortar pouring hole 21 is formed into a circular hole having a diameter in the range of 7-9 cm.

즉, 본 고안을 실시함에 있어서는 상기 개공(21)의 직경이 9㎝보다 큰 경우에는 단면 결손으로 인해 하부강판(20)의 구조적 문제점이 일어날 염려가 있으며, 직경이 7㎝보다 작을 경우 몰탈 타설 시공성이 떨어지므로 무수축 몰탈 투입 및 다짐작업, 하부 강판의 두께 등을 고려하여 7∼9㎝ 범위로 한정하여 형성함이 좋다.That is, in carrying out the present invention, if the diameter of the opening 21 is greater than 9 cm, there is a concern that structural problems of the lower steel plate 20 may occur due to cross-sectional defects, and when the diameter is smaller than 7 cm, mortar construction workability is achieved. Since it falls, it is good to limit the formation of the non-shrinkage mortar and compaction, the thickness of the lower steel sheet in the range of 7 ~ 9cm.

이때, 상기 하부강판(20)의 무수축몰탈 타설용 개공(21)은 공장에서 하부강판 제작 과정에서 이루어지므로 정밀성형이 가능하다.At this time, the opening for the non-shrink mortar pouring of the lower steel sheet 20 is made in the process of manufacturing the lower steel sheet in the factory, it is possible to precision molding.

그리고, 본 고안은 개공(21) 둘레의 단면이 반턱형상을 갖는 2단으로 형성되고, 그 반턱상에 얹혀져 볼트체결되는 강판덮개(22)가 구비되어서, 무수축몰탈의 시공이 완료된 후에 개공(21)을 차폐할 수 있도록 하고 있다.In addition, the present invention is provided with a steel plate cover 22 is formed in two stages with a cross-section around the opening 21 having a half jaw shape, and is mounted on the half jaw to be bolted, and then opened after completion of the construction of the non-shrink mortar. 21) to shield.

상기와 같이 구성되는 본 고안의 하부강판(20)을 교대 또는 교각(L)의 코핑부에 정착시킴에 있어서는 앞서 설명한 종래의 하부강판과 마찬가지로, 도4의 도시와 같이 교대 또는 교각(L)의 코핑부를 일정부분 절취해 내서 앵커볼트(40)가 매입될 자리를 확보한 다음, 받침보강을 위한 방석철근(50) 및 정위치 셋팅을 위한 체어철근(60)을 배치하고, 설치 위치에 대한 정확한 좌표 측량을 실시하면서 크레인을 이용해 하부강판(20)을 수평하게 셋팅한 후, 앵커볼트(20)를 체어철근(60)과 연결하여 하부강판(20)이 유동하지 않도록 고정시킨다.In fixing the lower steel plate 20 of the present invention, which is configured as described above, to the coping portion of the alternating or piercing L, as in the conventional lower steel plate described above, as shown in FIG. After cutting the coping part to secure a place where the anchor bolt 40 is to be inserted, the cushion reinforcing bar 50 for reinforcing the support and the chair reinforcing bar 60 for setting the exact position, and the exact position After setting the lower steel plate 20 horizontally using a crane while performing the coordinate measurement, the anchor bolt 20 is connected to the chair reinforcement 60 to fix the lower steel plate 20 does not flow.

이어서, 도5의 도시와 같이 하부강판(20)의 주변에 무수축몰탈 구조체의 설계규격에 맞추어 거푸집(70)을 설치하고, 무수축몰탈을 타설하게 되는데, 이때 본 고안에 의하면 무수축몰탈 타설 공사시, 하부강판(20)의 측면과 거푸집 사이에 형성된 공간과 함께 상기 무수축몰탈 타설용 개공(21)을 이용하여 무수축몰탈(80)을 주입함으로써, 무수축몰탈을 강판 하부에 밀실하게 채울 수 있다.Subsequently, as shown in FIG. 5, the formwork 70 is installed around the lower steel plate 20 in accordance with the design specifications of the non-shrink mortar structure, and the non-shrink mortar is poured according to the present invention. During construction, by injecting the non-condensation mortar 80 by using the opening of the non-contraction mortar pouring with the space formed between the side of the lower steel plate 20 and the formwork, the non-contraction mortar is tightly in the lower part of the steel sheet I can fill it.

즉, 본 고안에서는 교좌장치의 하부강판(20) 저부에 무수축몰탈 타설시 하부강판 측면 및 중심부분에서 동시에 작업이 이루어질 수 있게 함으로써, 시공이 용이할 뿐만 아니라, 무수축몰탈이 밀실하게 채워지는 견고한 구조체를 얻을 수 있다.In other words, in the present invention, when the non-shrink mortar is placed at the bottom of the lower steel plate 20 of the device, the work may be simultaneously performed at the side and the central portion of the lower steel plate, thereby facilitating the construction of the non-shrink mortar. A solid structure can be obtained.

무수축몰탈의 시공을 완료한 다음에는 개공(21)에 강판덮개(22)를 끼우고 볼트체결하여 마무리한다.After completing the construction of the non-shrink mortar, the steel plate cover 22 is inserted into the opening 21 and bolted to finish.

상기와 같이 이루어지는 본 고안은 다음과 같은 효과가 있다.The present invention made as described above has the following effects.

하부강판의 무수축몰탈 타설용 개공(開孔)의 설치가 교좌장치 제작 작업시 공장에서 이루어지므로 정밀제작이 가능하고, 교좌장치 설치를 위한 무수축몰탈 타설 작업시 교량받침 하부강판 중심부의 개공(開孔)을 이용할 수 있으므로 무수축몰탈 구조체의 시공이 대단히 간편하다.Since the installation of the non-condensation mortar casting hole of the lower steel plate is made in the factory during the manufacture of the bridge device, precise manufacturing is possible, and the opening of the center of the lower steel plate of the bridge support during the installation of the non-condensation mortar for the bridge device installation ( Iii) can be used, the construction of the non-contraction mortar structure is very easy.

뿐만 아니라, 하부강판의 중앙 저부에 무수축몰탈이 밀실하게 충진되는 현상을 육안으로 확인할 수 있으므로 무수축몰탈 구조체의 강도향상 및 강도증진을 통한 확실한 품질 확보가 가능하다.In addition, since the phenomenon that the non-condensation mortar is tightly filled in the central bottom of the lower steel sheet can be confirmed with the naked eye, it is possible to secure a certain quality by improving the strength and increasing the strength of the non-contraction mortar structure.

이상과 같이, 본 고안은 교좌장치의 하부강판 저부에 타설되는 무수축몰탈의 시공이 용이할 뿐만 아니라, 무수축몰탈 구조체의 강도 및 품질이 확실하게 확보됨으로써 교좌장치의 구조적인 안정성을 보장하고 사용수명을 대폭 연장할 수 있는 매우 유용한 고안이다.As described above, the present invention not only facilitates the construction of the non-shrink mortar that is placed on the bottom of the lower steel plate of the chair, but also ensures the strength and quality of the non-shrink mortar structure to ensure structural stability and use of the chair. It is a very useful design that can greatly extend the service life.

Claims (3)

교량 상부구조물의 하부면에 정착되는 상부강판(10)과, 교대 또는 교각의 코핑부에 정착되는 하부강판(20)과, 상기 상,하부강판(10)(20)들의 사이에 개재되어 교량의 압축력과 변형력을 지지하는 베어링패드(30)로 구성되어 교량의 상부구조에서 전달되는 자중과 교통하중을 하부구조물에 전달하는 교좌장치에 있어서,The upper steel plate 10 to be fixed to the lower surface of the bridge upper structure, the lower steel plate 20 to be fixed to the coping portion of the alternating or pier, and the upper and lower steel plates 10, 20 interposed between the In the ballast device consisting of a bearing pad (30) for supporting the compressive force and the deformation force to transfer the magnetic and traffic loads transmitted from the upper structure of the bridge to the lower structure, 상기 하부강판(40)의 중앙부에 소정의 크기를 가지면서 수직으로 관통하는 무수축몰탈 타설용 개공(21)을 형성하여서, 하부강판(20)을 교대 또는 교각 등의 코핑부에 견고히 정착시키기 위해 정위치에 셋팅시키고 주변에 거푸집을 설치한 후 강판하부에 실시하는 무수축몰탈 타설 공사시, 하부강판(20)의 측면과 거푸집 사이에 형성된 공간과 함께 상기 무수축몰탈 타설용 개공(21)을 이용하여 무수축몰탈을 주입토록 함으로써, 무수축몰탈을 강판 하부에 밀실하게 채울 수 있게 한 것을 특징으로 하는 교좌장치용 하부강판 구조.In order to firmly fix the lower steel plate 20 to a coping part such as an alternating or pier by forming the opening 21 for non-contraction mortar pouring having a predetermined size in the center portion of the lower steel plate 40 and penetrating vertically. After setting in place and installing the formwork around the non-shrink mortar casting work carried out on the bottom of the steel sheet, the opening for the non-shrink mortar pouring with the space formed between the side and the formwork of the lower steel plate 20 The lower steel sheet structure for a chair apparatus according to claim 1, wherein the non-condensed mortar is injected in such a manner that the non-condensed mortar can be filled in tightly under the steel sheet. 제1항에 있어서, 상기 무수축몰탈 타설용 개공(21)은 그 직경이 7∼9㎝의 범위를 갖는 원형구멍으로 형성된 것을 특징으로 하는 교좌장치용 하부강판 구조.2. The lower steel plate structure according to claim 1, characterized in that the openings for non-contraction mortar pouring are formed into circular holes whose diameter is in the range of 7 to 9 cm. 제1항에 있어서, 상기 무수축몰탈 타설용 개공(21)에는 볼트체결되는 강판덮개(22)가 구비되어서, 무수축몰탈의 시공이 완료된 후에 차폐할 수 있도록 한 것을 특징으로 하는 교좌장치용 하부강판 구조.The lower portion of the seating apparatus according to claim 1, wherein the hole 21 for pouring non-contraction mortar is provided with a steel plate cover 22 to be bolted to shield after completion of the construction of the non-contraction mortar. Steel plate structure.
KR2020010004328U 2001-02-20 2001-02-20 Low Plate Structure of the Bridge Bearing KR200233607Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020010004328U KR200233607Y1 (en) 2001-02-20 2001-02-20 Low Plate Structure of the Bridge Bearing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020010004328U KR200233607Y1 (en) 2001-02-20 2001-02-20 Low Plate Structure of the Bridge Bearing

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020010008368A Division KR20020068117A (en) 2001-02-20 2001-02-20 Low Plate Structure of the Bridge Bearing

Publications (1)

Publication Number Publication Date
KR200233607Y1 true KR200233607Y1 (en) 2001-09-29

Family

ID=73063366

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020010004328U KR200233607Y1 (en) 2001-02-20 2001-02-20 Low Plate Structure of the Bridge Bearing

Country Status (1)

Country Link
KR (1) KR200233607Y1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030060362A (en) * 2002-01-08 2003-07-16 이춘구 Bridge bearing and building method of bridge bearing
KR100419031B1 (en) * 2001-08-24 2004-02-19 대림산업 주식회사 Method for non-shrink grouting and members for the method
KR101471562B1 (en) * 2014-03-27 2014-12-11 씨에스글로벌 주식회사 Supporting apparatus with link type anchor and construction method thereof
KR101490896B1 (en) * 2014-03-28 2015-02-06 신영기술개발(주) Construction method of supporting apparatus for bridge and elastic supporting apparatus for bridge therefor
KR101765762B1 (en) * 2015-12-16 2017-08-07 주식회사 신원알피씨 Cantilever part for bridge and constructing method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100419031B1 (en) * 2001-08-24 2004-02-19 대림산업 주식회사 Method for non-shrink grouting and members for the method
KR20030060362A (en) * 2002-01-08 2003-07-16 이춘구 Bridge bearing and building method of bridge bearing
KR101471562B1 (en) * 2014-03-27 2014-12-11 씨에스글로벌 주식회사 Supporting apparatus with link type anchor and construction method thereof
KR101490896B1 (en) * 2014-03-28 2015-02-06 신영기술개발(주) Construction method of supporting apparatus for bridge and elastic supporting apparatus for bridge therefor
KR101765762B1 (en) * 2015-12-16 2017-08-07 주식회사 신원알피씨 Cantilever part for bridge and constructing method thereof

Similar Documents

Publication Publication Date Title
CN211036679U (en) Socket joint connection structure of prefabricated pier stud of assembled bridge and cushion cap
KR100802336B1 (en) The use of the bearing installation is involved the precast block and it for construction method of the bearing installation and the replacing methodof bearing installation
CN102817324B (en) Construction method for quickly installing pot rubber bearing by using epoxy resin mortar
CN110258333A (en) The jig structure and its application method of leveling connection are quickly positioned for Precast Pier Columns
CN112681117B (en) Connecting device and construction method for connecting position of bridge pier column and bearing platform
CN109162204B (en) Construction method for transverse block rapid assembling of bridge substructure
KR100788275B1 (en) Bridge deck with stay-in-place precast concrete panel
CN112695623A (en) Assembled pier and construction process thereof
KR200233607Y1 (en) Low Plate Structure of the Bridge Bearing
CN112779854A (en) Connecting structure of prefabricated assembled bridge pier and construction method
CN113832842B (en) Spherical support mounting and leveling method
CN215857171U (en) Connecting structure of prefabricated assembled bridge pier
KR100671944B1 (en) The understructure for seat device and in a day jack down working method for replace seat device
CN216076559U (en) Assembled self-adaptation vertical deformation&#39;s concrete structure system
KR20020068117A (en) Low Plate Structure of the Bridge Bearing
CN211850266U (en) Laminated floor slab structure
CN109898540B (en) Wet joint structure among bridge pier, bearing platform and pile foundation and construction process thereof
CN211735114U (en) A antidumping reinforced structure for rectangle single-column mound bridge
CN208586529U (en) A kind of gradient precast beam support leveling device
CN111706128A (en) Prefabricated inspection pit stand column and construction method thereof
CN106480793B (en) A kind of prefabricated floating plate ballast construction method
JP2003227109A (en) Mounting method of horizontal force buffer of structure and mounting structure
CN108824203A (en) A kind of gradient precast beam support leveling device
CN219343534U (en) Connection structure of prefabricated assembled frame post and basic cushion cap
CN216999270U (en) Wet seam connecting structure of prefabricated pier stud and bearing platform

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T601 Decision to invalidate utility model after technical evaluation
LAPS Lapse due to unpaid annual fee