KR200202345Y1 - Apparatus to reinforce the endurance force of structure using tensile beam - Google Patents

Apparatus to reinforce the endurance force of structure using tensile beam Download PDF

Info

Publication number
KR200202345Y1
KR200202345Y1 KR2020000011592U KR20000011592U KR200202345Y1 KR 200202345 Y1 KR200202345 Y1 KR 200202345Y1 KR 2020000011592 U KR2020000011592 U KR 2020000011592U KR 20000011592 U KR20000011592 U KR 20000011592U KR 200202345 Y1 KR200202345 Y1 KR 200202345Y1
Authority
KR
South Korea
Prior art keywords
elastic
reinforcement
preflex
reinforcing
bolt
Prior art date
Application number
KR2020000011592U
Other languages
Korean (ko)
Inventor
문지훈
Original Assignee
주식회사다인건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사다인건설 filed Critical 주식회사다인건설
Application granted granted Critical
Publication of KR200202345Y1 publication Critical patent/KR200202345Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 고안은 탄성빔을 이용한 구조물 내하력 증진 보강장치에 관하여, 구조체의 보강하고자 하는 영역에 따라 설정되는 캠버를 갖도록 벤딩되어 형성된 탄성 보강재와; 상기 구조체의 하부에 상기 탄성 보강재를 접촉시키고 상기 탄성 보강재의 양단부를 상부로 가압하여 상기 구조체에 결속하는 결속수단을 포함하여 상기 구조체의 내하력을 증가시키도록 구성된다. 이러한 본 고안은 사하중에 의한 휨 응력을 인장철근과 탄성 프리플렉스 보강보가 분담하게 하여 사하중에 대한 보강으로 활하중에 대한 저항능력을 증대시키는 이점이 있으며, 노후된 교량의 슬래브를 간편한 방법으로 시공하여 내하력을 증대시킴으로써 사용수명을 연장하여 장기간 안전하게 사용할 수 있도록 하는 효과가 있다.The present invention relates to a structural load-bearing reinforcement apparatus using an elastic beam, and an elastic reinforcement formed by bending to have a camber set according to the region to be reinforced; And a binding means for contacting the elastic reinforcement to the bottom of the structure and for pressing the both ends of the elastic reinforcement to the upper to bind the structure. The present invention has the advantage of increasing the resistance to live load by reinforcing the dead load and the tension reinforcement beam and the elastic preflex reinforcement beam to share the bending stress caused by the dead load, and constructing the slab of the aging bridge in a simple way to increase the load capacity Increasing the service life is effective to ensure long-term use safely.

Description

탄성빔을 이용한 구조물 내하력 증진 보강장치{APPARATUS TO REINFORCE THE ENDURANCE FORCE OF STRUCTURE USING TENSILE BEAM}Reinforcement device for structural load enhancement using elastic beams {APPARATUS TO REINFORCE THE ENDURANCE FORCE OF STRUCTURE USING TENSILE BEAM}

본 고안은 탄성빔을 이용한 구조물 내하력 증진 보강장치에 관한 것으로, 특히 구조물의 내하력을 증진시키기 위한 보강장치로 사하중에 의한 휨 응력을 인장철근과 탄성 프리플렉스 보강보가 분담하게 하여 사하중에 대한 보강으로 활하중에 대한 저항능력을 증대시키도록 한 탄성빔을 이용한 구조물 내하력 증진 보강장치에 관한 것이다.The present invention relates to a structural load-bearing reinforcement device using an elastic beam, and in particular, as a reinforcement device for enhancing the load-bearing capacity of a structure, the tensile reinforcement and the elastic preflex reinforcing beam are shared by the reinforcing load by the reinforcement of the dead load. It relates to a structural load-bearing reinforcement device using an elastic beam to increase the resistance to the.

일반적으로 각종 구조물은 파손 및 붕괴 등의 각종 사고가 발생하지 않도록 관리에 만전을 기하고 있으나, 노후화된 구조물들은 갑자기 현실에 맞는 상태로 개축하기에는 시간적 경제적 손실이 너무 많아 불가능한 실정이므로 노후된 구조물을 보다 정확한 방법과 저렴한 공사비로 보강 및 보수하는 방법이 절실히 요구되고 있다. 그러나 현실은 노후된 구조물을 정확히 보강하는 기술 부족으로 인해 외국에서 도입된 낙후된 방식을 그대로 모방하여 사용하고 있는 실정이다.In general, various structures are fully managed to prevent accidents such as breakage and collapse.However, aging structures cannot be renovated in a state that is suddenly suitable for reality. There is an urgent need for methods of reinforcement and repair at low cost. However, the reality is that the lack of technology for reinforcing old structures accurately mimics the outdated methods introduced from abroad.

본 출원인은 구조물의 여러 형태별 파손 원인을 분석하여 현실에 맞는 보강공사를 시행하고자 노력하던 중 만족하여야 할 요건을 충족하지 못하여 재가설하여야 할 상황까지 이르게 된 구조물을 효과적을 보강할 수 있는 본 공법을 개발하게 되었다.The Applicant has tried to analyze the causes of damage in various forms of the structure to implement the reinforcement work that is realistic, and to effectively reinforce the structure that leads to the situation to be re-established due to failure to meet the requirements to be satisfied. Developed.

따라서, 본 고안의 목적은 상기한 바와 같은 종래의 문제점 및 결함을 해소하기 위하여 창안한 것으로, 구조물의 내하력을 증진시키기 위한 보강공법으로 사하중에 의한 휨 응력을 인장철근과 탄성 프리플렉스 보강보가 분담하게 하여 사하중에 대한 보강으로 활하중에 대한 저항능력을 증대시킬 수 있게 되는 탄성빔을 이용한 구조물 내하력 증진 보강장치를 제공하기 위한 것이다.Therefore, the object of the present invention was devised to solve the above-mentioned problems and defects as described above. As a reinforcing method for enhancing the load-bearing capacity of a structure, the tensile reinforcement and the elastic preflex reinforcing beam are shared by the bending stress due to dead load. It is to provide a structural load-bearing reinforcement device using an elastic beam that can increase the resistance to live loads by reinforcing the dead load.

도 1 내지 도 11은 본 고안 탄성빔을 이용한 구조물 내하력 증진 보강장치에 관한 도면으로서,1 to 11 is a view regarding the structure load-bearing reinforcement device using the present invention elastic beam,

도 1a 내지 도 1e는 보강공정을 단계적으로 보인 설명도.1A to 1E are explanatory views showing the reinforcing step by step.

도 2는 도 1e의 'A'부 확대 측단면도.2 is an enlarged side cross-sectional view of portion 'A' of FIG. 1E;

도 3은 도 1e의 'B'부 확대 측단면도.3 is an enlarged side cross-sectional view of portion 'B' of FIG. 1E;

도 4는 도 3의 A-A선 단면도.4 is a cross-sectional view taken along the line A-A of FIG.

도 5는 인상장치의 구성도.5 is a configuration diagram of the pulling device.

도 6은 볼트의 부분 절결 사시도.6 is a partially cutaway perspective view of the bolt.

도 7은 본 고안이 적용되는 콘크리트 슬래브의 단면도.7 is a cross-sectional view of the concrete slab to which the present invention is applied.

도 8은 프리플렉스보강공법의 적용원리 설명도.8 is an explanatory view of the application principle of the preflex reinforcement method.

도 9는 보강후 단면력 변화 그래프.9 is a graph of cross-sectional force change after reinforcement.

도 10은 보강보의 설치위치 설명도.10 is an explanatory view of the installation position of the reinforcement beams.

도 11은 보강후 단면력 변화 설명도.11 is an explanatory view of the cross-sectional force change after reinforcement.

< 도면의 주요부분에 대한 부호의 설명><Description of the reference numerals for the main parts of the drawings>

1 : 구조체 1' : 슬래브1: Structure 1 ': Slab

1a : 관통공 1b : 고정공1a: through hole 1b: fixed hole

3a : 머리 3b : 몸통3a: head 3b: torso

3c : 수직 주입공 3d : 수평 주입공3c: vertical injection hole 3d: horizontal injection hole

4 : 너트 5 : 아스콘4: nut 5: ascon

5a : 작업면 6 : 좌굴방지재5a: working surface 6: buckling prevention material

10 : 에폭시 11 : 앵커볼트 정착지압판10: epoxy 11: anchor bolt anchorage plate

12 : 에폭시 콘크리트층 20 : 인상장치12: epoxy concrete layer 20: impression device

21 : 메인 펌프 22 : 실린더21: main pump 22: cylinder

23 : 유압잭 24 : 받침대23: hydraulic jack 24: pedestal

25 : 간격 지지강재 26 : 침하 방지강재25: gap support steel 26: sinking prevention steel

30 : 세트 앵커볼트 31 : 너트30: set anchor bolt 31: nut

이와 같은 목적을 달성하기 위하여 본 고안에 의한 탄성빔을 이용한 구조물 내하력 증진 보강장치는 구조체의 보강하고자 하는 영역에 따라 설정되는 캠버를 갖도록 벤딩되어 형성된 탄성 보강재와, 상기 구조체의 하부에 상기 탄성 보강재를 접촉시키고 상기 탄성 보강재의 양단부를 상부로 가압하여 상기 구조체에 결속하는 결속수단을 포함하여 상기 구조체의 내하력을 증가시키도록 구성된다.In order to achieve the above object, the structural load-bearing reinforcement apparatus using the elastic beam according to the present invention is an elastic reinforcement formed by bending to have a camber set according to a region to be reinforced, and the elastic reinforcement is formed under the structure. And binding means for contacting and forcing the ends of the elastic reinforcement to bind to the structure, thereby increasing the load capacity of the structure.

상기 탄성 보강재는 상기 구조체의 보강하고자 하는 영역에 따라 설정되는 캠버와 체결을 위한 볼트공을 갖도록 형성되는 탄성 프리플렉스 보강보이고, 상기 결속수단에는 상기 탄성 프리플렉스 보강보의 볼트공과 상기 구조체의 관통공에 삽입 체결되는 볼트와 너트가 이용된다.The elastic reinforcing material is an elastic preflex reinforcing beam formed to have a bolt hole for fastening with a camber set according to the area to be reinforced of the structure, the binding means is a bolt hole of the elastic preflex reinforcing beam and a through hole of the structure Bolts and nuts that are inserted into and fastened to are used.

상기 탄성 프리플렉스 보강보는 상기 구조체와 균일하게 밀착되도록 상기 구조체의 상부와 탄성 프리플렉스 보강보의 양단 하부 사이에 원형 강관 받침대, 유압잭, 메인 펌프, 간격 지지강재 및 침하 방지강재의 순서로 구조체의 높이에 따라 배치되어 각각 수평으로 설치되는 복수개의 인상장치에 의해 가압되고, 상기 탄성 프리플렉스 보강보의 양단부는 상기 각 인상장치의 메인 펌프에 부착된 유압 게이지에 의해 가압량을 측정하면서 인상되어진 것이다.The height of the structure in the order of the circular steel pipe support, the hydraulic jack, the main pump, the gap support steel and the anti-sedimentation steel between the upper portion of the structure and the lower end of both ends of the elastic preflex reinforcement beam so that the elastic preflex reinforcing beam is in close contact with the structure. It is pressurized by a plurality of lifting devices which are arranged in a horizontal manner and are horizontally installed, respectively, and both ends of the elastic preflex reinforcing beams are lifted while measuring the amount of pressure by a hydraulic gauge attached to the main pump of each of the pulling devices.

또, 본 고안의 장치는 상기 구조체의 상면에 적층된 아스콘을 깨내고 형성된 작업면에는 앵커볼트 정착지압판이 재치되고, 이 앵커볼트 정착지압판에 형성된 볼트공을 통하여 상기 탄성 프리플렉스 보강보를 체결하기 위한 볼트가 삽입되며, 상기 아스콘이 있던 작업면에는 에폭시 콘크리트층이 형성되어 방수처리되는 형태를 갖는다.In addition, the device of the present invention is to break the ascon laminated on the upper surface of the structure formed on the anchor bolt on the working surface The anchorage plate is mounted and this anchor bolt A bolt for fastening the elastic preflex reinforcing beam is inserted through a bolt hole formed in the anchorage plate, and an epoxy concrete layer is formed on the working surface of the asphalt concrete to form a waterproofing process.

그리고, 보다 견고하고 안정된 구조를 갖기위하여 상기 구조체의 관통공에 삽입된 상기 볼트의 수직 주입공과 수평 주입공으로 에폭시가 주입되어 상기 슬래브의 관통공의 내주면과 상기 볼트의 외주면 사이에 상기 에폭시가 충진되어 고정되며, 또한 상기 탄성 프리플렉스 보강보의 중간부에 고정된 세트 앵커볼트가 상기 구조체의 중간부에 형성된 고정공에 삽입 고정된다.In order to have a more stable and stable structure, epoxy is injected into the vertical injection hole and the horizontal injection hole of the bolt inserted into the through hole of the structure to fill the epoxy between the inner circumferential surface of the through hole of the slab and the outer circumferential surface of the bolt. It is fixed, and the set anchor bolt fixed to the middle portion of the elastic preflex reinforcing beam is inserted and fixed in the fixing hole formed in the middle portion of the structure.

또, 상기 탄성 프리플렉스 보강보의 양단부에는 좌굴방지재를 개재하고 상기 볼트를 체결하면 탄성 프리플렉스 보강보의 플랜지의 좌굴을 방지할 수 있다.In addition, when both ends of the elastic preflex reinforcing beam are interposed with a buckling preventing material, the bolt may be fastened to prevent buckling of the flange of the elastic preflex reinforcing beam.

상기 탄성 프리플렉스 보강보는 제작 및 시공 작업성, 그리고 보강력을 고려하여 원호형으로 벤딩되어 형성되는 것이 바람직하다.The elastic preflex reinforcing beam is preferably formed to be bent in an arc shape in consideration of manufacturing and construction workability, and reinforcement.

상기 탄성 프리플렉스 보강보로 이용되는 예를들어 SWS-520 이상의 구조용 강재는 고인장 강재로서 탄성한계 최대 인장력이 보통 강재 보다 50% 정도 크고, 응력 변형선도에서 높은 파괴점과 신장을 가지고 있다. 그래서 이 강재는 탄성 영역 범위 내에서 일정한 힘으로 구부린 후 가했던 힘을 제거하면 다시 원래의 상태대로 복원하려는 성질을 가지고 있다.For example, structural steels of SWS-520 or more, which are used as the elastic preflex reinforcing beams, are high tensile steels and have a maximum tensile strength of about 50% greater than that of ordinary steels, and have a high breaking point and elongation in the stress strain diagram. Therefore, this steel has the property of restoring it to its original state by removing the force applied after bending under constant force within the elastic range.

이 강재의 보강재를 일정한 굽힘을 주어 제작하여, 노후화된 구조물의 처짐이 심한 곳이나 균열이 많이 발생되어 붕괴 위험이 있는 곳의 상기 보강재를 하부에 밀착시키고, 일정한 힘으로 밀어올려 평편하게 한 상태에서 구조물과 일체화시키면 원래 형태로 되려는 복원력 때문에 구조물 하부를 계속 밀어 올려 내하력 증진에 탁월한 효과를 발휘하게 된다.The reinforcement of this steel is made with constant bending, and the reinforcement of the place where the aging structure is severely drooped or cracks are generated and the risk of collapse is closely adhered to the lower part, and it is pushed up with a constant force to make it flat. When integrated with the structure, because of the restoring force to be in its original form, the lower part of the structure is continuously pushed up to have an excellent effect on increasing the load capacity.

이러한 구조물 내하력 보강용 탄성빔 시공 순서는 빔이나, 플레이트 거더(plate girder)를 캠버(camber)가 주어진 상태로 공장에서 제작하고, 이 탄성 보강재를 현장으로 이동시켜 보강하고자 하는 교량의 슬래브(slab)와 같은 구조체의 하부에 거치하며, 상기 탄성 보강재의 하부에서 솟음량을 감소시키기 위하여 추상대를 설치한 후 인상장치로 정확한 힘을 가하여 탄성 보강재를 구조체의 하부에 밀착시킨다. 이후, 구조체와 탄성 보강재을 고정장치를 이용하여 고정시킨다. 이와 같이 하여 구조체에 탄성 보강재가 완전히 고정되면 탄성 보강재가 처음 상태로 복원하려는 성질 때문에 처짐 및 활하중 사하중 응력 감소 효과를 나타내는 구조체에 하부지지 없이 완벽하게 보강할 수 있게 된다.The construction order of the resilient beam for reinforcing load capacity of the structure is a slab of a bridge to be manufactured in a factory with a beam or plate girder given a camber, and to move the elastic reinforcement to the site for reinforcement. Mounted on the lower part of the structure, such as, to reduce the amount of rise in the lower portion of the elastic reinforcement, and then to install the abstract belt by applying an accurate force to the lifting device to closely adhere the elastic reinforcement to the lower portion of the structure. Thereafter, the structure and the elastic reinforcement are fixed using the fixing device. In this way, when the elastic reinforcing material is completely fixed to the structure, the elastic reinforcing material can be completely reinforced without supporting the structure showing the effect of reducing the deflection and live load dead weight stress due to the property of restoring to the initial state.

충진제는 콘크리트와 강재 사이의 간격이 일정하지 않으므로 완벽하게 일체화시키기 위하여 예를들어 에폭시를 사용한다. 주입방법은 콘크리트와 강재 사이를 에폭시 퍼티(epoxy putty)로 처리한 다음 주입구를 일정한 간격으로 배치하여 에폭시 퍼티가 완전히 경화된후 주입을 실시하며, 완벽한 주입확인을 위하여 중간중간에 에폭시 주입확인 배기구를 설치한다. 하부의 인상작업대와 인상기구는 주입된 에폭시가 완전히 경화된 후에 철수한다.Fillers use epoxy, for example, for perfect integration because the spacing between concrete and steel is not constant. The injection method is treated with epoxy putty between concrete and steel, and the injection holes are arranged at regular intervals and then injected after the epoxy putty is completely cured. Install. The lower lifting platform and the lifting mechanism are withdrawn after the injected epoxy has fully cured.

이하, 이와 같은 본 고안에 의한 탄성빔을 이용한 구조물 내하력 증진 보강장치를 첨부한 도면에 의하여 설명하면 다음과 같다.Hereinafter, described with reference to the accompanying drawings the structure load-bearing enhancement reinforcement using the elastic beam according to the present invention as follows.

도 1 내지 도 8은 본 고안 탄성빔을 이용한 구조물 내하력 증진 보강장치에 관한 도면으로서, 도 1a 내지 도 1d는 보강공정을 단계적으로 보인 설명도이고, 도 2는 도 1d의 'B'부 확대 측단면도, 도 3은 도 1e의 'A'부 확대 측단면도, 도 4는 도 3에 도시된 부분의 평면도를 각각 보인 것이며, 도 5는 인상장치의 구성도, 도 6은 볼트의 부분 절결 사시도를 각각 보인 것이다.1 to 8 is a view of a structure load-bearing reinforcement device using the present invention elastic beam, Figures 1a to 1d is an explanatory view showing a reinforcement step by step, Figure 2 is an enlarged 'B' portion of Figure 1d 3 is an enlarged side cross-sectional view of portion 'A' of FIG. 1E, FIG. 4 is a plan view of the portion shown in FIG. 3, FIG. 5 is a configuration diagram of the pulling device, and FIG. 6 is a partially cutaway perspective view of the bolt. Each one is seen.

그리고, 도 7은 본 고안이 적용되는 콘크리트 슬래브의 단면도를 보인 것이고, 도 8은 프리플렉스보강공법의 적용원리 설명도이며, 도 9는 보강후 단면력 변화 그래프이다.And, Figure 7 shows a cross-sectional view of the concrete slab to which the present invention is applied, Figure 8 is a diagram illustrating the application principle of the preflex reinforcement method, Figure 9 is a graph of the cross-sectional force change after reinforcement.

본 고안에 의한 탄성빔을 이용한 구조물 내하력 증진 보강장치는 구조체(1)의 보강하고자 하는 영역에 따라 설정되는 캠버를 갖도록 벤딩되어 형성된 탄성 보강재(2)와, 상기 구조체(1)의 하부에 상기 탄성 보강재(2)를 접촉시키고 상기 탄성 보강재(2)의 양단부를 상부로 가압하여 상기 구조체(1)에 결속하는 볼트(3), 너트(4)와 같은 결속수단을 포함하여 상기 구조체의 내하력을 증가시키도록 구성된다.Structure load-bearing reinforcement reinforcement using the elastic beam according to the present invention is an elastic reinforcement (2) formed to be bent to have a camber set according to the area to be reinforced of the structure (1), and the elastic under the structure (1) Including a binding means such as a bolt (3), a nut (4) for contacting the reinforcing material (2) and pressing both ends of the elastic reinforcing material (2) to the upper portion to increase the load capacity of the structure Is configured to.

상기 탄성 보강재(2)에는 상기 구조체(1)의 보강하고자 하는 영역에 따라 설정되는 캠버와 체결을 위한 볼트공(2a)을 갖도록 형성되는 탄성 프리플렉스 보강보(2')가 이용된다.As the elastic reinforcing material 2, an elastic preflex reinforcing beam 2 'formed to have a camber set in accordance with a region to be reinforced of the structure 1 and a bolt hole 2a for fastening is used.

이하, 본 고안에 의한 탄성빔을 이용한 구조물 내하력 증진 보강장치를 시공형태를 참조하여 상세히 설명하면, 먼저, 도 1a와 같이 보강하고자 하는 구조체(1), 예를들어 교량의 슬래브(slab)(1')의 형태를 조사하여, 도 1b와 같이, 보강하고자 하는 범위에 따라 플레이트 거더(plate girder)와 같은 탄성 보강재(2), 예를들어 탄성 프리플렉스 보강보(2')를 캠버(camber)가 주어진 상태로 원호형으로 공장에서 제작하고, 이 원호형으로 굽혀진 탄성 프리플렉스 보강보(2')를 현장의 슬래브(1') 하부로 이동시켜, 도 1c와 같이 보강하고자 하는 슬래브(1')의 하부에 거치하며, 이어서 도 1d와 같이, 상기 탄성 프리플렉스 보강보(2')의 하부에서 솟음량을 감소시키기 위하여 추상대를 설치한 후 인상장치로 정확한 힘을 가하여 탄성 프리플렉스 보강보(2')를 슬래브(1')의 하부에 밀착시킨다.Hereinafter, the structure load-bearing reinforcement reinforcing apparatus using the elastic beam according to the present invention will be described in detail with reference to the construction form. First, as shown in FIG. 1A, a structure 1 to be reinforced, for example, a slab of a bridge 1 '), And as shown in Figure 1b, according to the range to be reinforced, the elastic reinforcing material (2), such as a plate girder (for example, elastic preflex reinforcing beam 2') to the camber (camber) Is manufactured at the factory in an arc-shaped state, and the arc-shaped elastic preflex reinforcement beam 2 'is moved to the lower portion of the slab 1' on the site, and the slab 1 to be reinforced as shown in FIG. ') And then, as shown in Figure 1d, to install the abstract to reduce the amount of rise in the lower portion of the elastic preplex reinforcement beam (2') and then apply an accurate force to the lifting device to reinforce the elastic preflex The beam 2 'to the lower part of the slab 1' Close contact

이후, 도 1e와 같이, 슬래브(1')와 탄성 프리플렉스 보강보(2')를 고정장치를 이용하여 고정시키고, 이와 같이 하여 구조체에 탄성 보강재가 완전히 고정되면 탄성 보강재가 처음 상태로 복원하려는 성질 때문에 처짐 및 활하중 사하중 응력 감소 효과를 나타내는 구조체에 하부지지 없이 완벽하게 보강할 수 있게 된다.Then, as shown in Figure 1e, the slab (1 ') and the elastic preflex reinforcement beam (2') is fixed by using a fixing device, and thus the elastic reinforcement is to be restored to the initial state when the elastic reinforcement is completely fixed to the structure in this way Due to its properties, it is possible to perfectly reinforce the structure without sagging and underloading the structure, which shows the effect of reducing the deflection and live load stresses.

탄성영역내에 탄성 프리플렉스 보강보(2')의 단면의 복원성을 그대로 유지하면서 슬래브(1')의 하부에 밀착시키기 위해서는 일정한 힘으로 탄성 프리플렉스 보강보(2')의 굽힘을 상쇄하는 방법이 도입되어야 하며, 이를 위해서는 정확한 계측 및 일정한 힘을 줄 수 있는 인상장치가 필요하다.In order to closely adhere to the lower part of the slab 1 'while maintaining the restorability of the cross section of the elastic preflex reinforcing beam 2' in the elastic region, a method of canceling the bending of the elastic preflex reinforcing beam 2 'with a constant force is required. It needs to be introduced, which requires an impression device that can give accurate measurements and constant force.

도 5는 이와 같은 인상장치(20)를 예시한 것으로, 이 인상장치(20)는 유압측정 게이지가 부착된 메인 펌프(21)와, 이 메인 펌프(21)의 실린더(22)에 승강 가능하게 결합되는 유압잭(23)과, 원형 강관과 같은 받침대(25)로 이루어져 있다.FIG. 5 illustrates such an pulling device 20, which is capable of lifting up and down the main pump 21 with a hydraulic gauge and the cylinder 22 of the main pump 21. Composed of a hydraulic jack 23 and a pedestal 25, such as a circular steel pipe.

이하, 이러한 시공작업을 실제 행함에 있어서 상기 탄성 프리플렉스 보강보(2')를 슬래브(1')의 하부로 이동시킬 때에는 탄성 프리플렉스 보강보(2')의 손상 및 캠버 감쇄에 영향이 없도록 세심한 주의가 요구된다.Hereinafter, in moving the elastic preflex reinforcing beams 2 'to the lower part of the slab 1' in actual construction, the damage of the elastic preflex reinforcing beams 2 'and the camber attenuation are not affected. Careful attention is required.

또, 탄성 프리플렉스 보강보(2')를 보강하여야 할 슬래브(1')의 위치에 정확히 장착시켜야 하므로 슬래브(1')의 관통공(1a)은 탄성 프리플렉스 보강보(2')의 볼트공(2a)과의 거리를 측량기를 이용하여 측정하면서 오차가 발생하지 않도록 천공한다.In addition, the through hole 1a of the slab 1 'is the bolt of the elastic preflex reinforcing beam 2', since it must be correctly mounted at the position of the slab 1 'on which the elastic preflex reinforcing beam 2' is to be reinforced. While measuring the distance to the ball (2a) using an instrument, puncture so that no error occurs.

슬래브(1') 관통방법은 고속 코아드릴로 상부에서 관통하며, 이 때 슬래브(1') 상부에 있는 아스콘(5)을 일정한 면적 만큼 깨고, 콘크리트 상부에서 부터 코아 작업을 실시한다.The slab 1 'penetrating method penetrates the upper part with a high speed drill, and at this time breaks the ascon 5 in the upper part of the slab 1' by a predetermined area, and performs the core work from the upper part of the concrete.

상기 슬래브(1')에 관통공(1a)을 형성한 후에는 도 3 및 도 4와 같이 상기 아스콘(5)을 깨낸 작업면(5a)에 앵커볼트 정착지압판(11)을 재치시키고, 이 앵커볼트 정착지압판(11)에 형성된 볼트공을 통하여 볼트(3)를 삽입하여 탄성 프리플렉스 보강보(2')의 플랜지에 형성된 볼트공(2a)에 너트(4)로 체결하고, 일정한 높이까지 인상시키며, 이 때 탄성 프리플렉스 보강보(2')에 무리한 힘이 가하여지지 않도록 주의하여 작업한다. 상기 볼트(3)의 머리(3a) 하부에는 필요에 따라 앵커볼트 정착지압판(11)을 대신하여 머리(3a) 보다 약간 넓은 평와셔를 개재하고 볼트(3)를 체결할 수 있다.After the through hole 1a is formed in the slab 1 ', the anchor bolt fixing pressure plate 11 is placed on the working surface 5a from which the ascon 5 is broken, as shown in FIGS. 3 and 4. The bolt 3 is inserted through the bolt hole formed in the bolt anchorage plate 11 to be fastened to the bolt hole 2a formed on the flange of the elastic preflex reinforcing beam 2 'with the nut 4, and pulled up to a constant height. At this time, be careful not to apply excessive force to the elastic preflex reinforcing beam (2 '). The bolt 3 may be fastened to the lower part of the head 3a through a flat washer slightly wider than the head 3a in place of the anchor bolt fixing pressure plate 11 as necessary.

상기 볼트(3)를 삽입한 후에는 상기 슬래브(1')의 관통공(1a)과 볼트(3) 사이에는 에폭시(10)를 충진하는 데 일반적인 주입방법으로는 완전한 주입이 이루어지지 않으므로 특수 제작된 볼트(3)를 사용하여 주입하게 되며, 상기 아스콘(5)이 있던 작업면(5a)에는 무수축 에폭시 몰탈을 타설하여 에폭시 콘크리트층(12)을 형성함으로써 물이 스며들지 않도록 방수처리 한다.After inserting the bolt (3), the special injection method for filling the epoxy (10) between the through hole (1a) and the bolt (3) of the slab (1 ') is not made as a general injection method It is injected using the bolt (3), the working surface (5a) where the ascon (5) was placed by the non-condensation epoxy mortar to form an epoxy concrete layer (12) to prevent the water soaking.

상기 볼트(3)는 도 6과 같이 머리(3a)에서 몸통(3b)의 일정 깊이 까지 수직 주입공(3c)이 길이방향으로 형성되고, 이 수직 주입공(3c)의 하단부에서 수평 주입공(3d)이 폭방향으로 형성된 형태로 되어 있다.The bolt 3 is a vertical injection hole (3c) is formed in the longitudinal direction from the head (3a) to a predetermined depth of the body (3b) as shown in Figure 6, the horizontal injection hole (3) at the lower end of the vertical injection hole (3c) 3d) is formed in the width direction.

상기 볼트(3)의 머리(3a)에서 수직 주입공(3c)을 통하여 에폭시(10)를 주입하면 수직 주입공(3c)과 수평 주입공(3d)을 통하여 흘러들어가 슬래브(1')의 관통공(1a) 내주면과 볼트(3)의 외주면 사이에 충진되어 완벽한 충진 효과를 얻을 수 있다.When the epoxy 10 is injected through the vertical injection hole 3c from the head 3a of the bolt 3, it flows through the vertical injection hole 3c and the horizontal injection hole 3d to penetrate the slab 1 '. It is filled between the inner circumferential surface of the ball 1a and the outer circumferential surface of the bolt 3 to obtain a perfect filling effect.

이어서, 슬래브(1')와 탄성 프리플렉스 보강보(2')를 밀착시키기 위하여 보조장치인 인상장치(20)를 설치하며, 도 5와 같이, 원형 강관의 받침대(24), 유압잭(23), 메인 펌프(21), 간격 지지강재(25) 및 침하 방지강재(26)의 순서로 구조체(1)의 높이에 따라 배치한다. 이 때에는 유압잭(23)에 유압이 작용시 일정한 힘이 탄성 프리플렉스 보강보(2') 하부에 균일하게 전달되게 하기 위하여 정확한 수평 작업이 필요하다.Subsequently, in order to bring the slab 1 'and the elastic preflex reinforcing beam 2' into close contact with each other, a pulling device 20 serving as an auxiliary device is installed. As shown in FIG. 5, the base 24 of the circular steel pipe 24 and the hydraulic jack 23 are installed. And the main pump 21, the interval supporting steel 25 and the anti-settling steel 26 are arranged in accordance with the height of the structure 1. At this time, when the hydraulic pressure acts on the hydraulic jack 23, a precise horizontal work is required in order to uniformly transmit the lower portion of the elastic preflex reinforcing beam 2 '.

그리고, 메인 펌프(21)에 부착된 유압 게이지에 의해 탄성 프리플렉스 보강보(2')에 가해지는 톤(ton)량을 측정하여 과다 인상을 방지한다.Then, the amount of tons applied to the elastic preflex reinforcing beams 2 'by the hydraulic gauge attached to the main pump 21 is measured to prevent excessive pulling.

이 인상장치(20)는 탄성 프리플렉스 보강보(2')의 하부에 2대를 설치하여 동시에 인상하며, 이 때 작업자들은 슬래브(1')와 탄성 프리플렉스 보강보(2')가 밀착될 때에 볼트(3)에 너트(4)를 돌려 일체화 작업을 실시한다.The pulling device 20 is installed at the bottom of the elastic preflex reinforcing beam (2 ') by lifting two at the same time, at this time, the workers will be in close contact with the slab (1') and elastic preflex reinforcing beam (2 '). At this time, the nut 4 is turned to the bolt 3 to perform the integration work.

한편, 상기한 시공작업의 중간에는 슬래브(1')와 보강빔(2')을 보다 견고하고 쉽게 결속하기 위하여 중간부 고정단계를 행할 수 있으며, 이 중간부 고정단계는 보강빔(2')의 중간부에 도 2와 같이 세트 앵커볼트(30)를 양쪽에 용접하거나 너트(31)로 나사체결하여 고정하고, 슬래브(1')의 하면 중간부에는 고정공(1b)을 천공하여 슬래브(1')에 보강빔(2')을 밀착시키는 단계에서 보강빔(2')에 구비된 세트 앵커볼트(30)가 슬래브(1')의 고정공(1b)에 삽입 고정되도록 하다.On the other hand, in the middle of the construction work can be carried out in the middle part fixing step to more solidly and easily bind the slab (1 ') and the reinforcing beam (2'), this middle part fixing step is the reinforcing beam (2 ') As shown in FIG. 2, the set anchor bolts 30 are welded to both sides or screwed with nuts 31, and the fixing holes 1b are drilled in the middle of the lower surface of the slab 1 '. 1 ') in the step of closely contacting the reinforcing beam (2') is set so that the set anchor bolt 30 provided in the reinforcing beam (2 ') is inserted into the fixing hole (1b) of the slab (1').

도 2에서 10'는 앵커볼트(30)를 견고하게 고정하기 위한 에폭시 그라우트를 보인 것이다.In FIG. 2, 10 ′ shows an epoxy grout for firmly fixing the anchor bolt 30.

상기와 같은 작업을 행하여 슬래브(1')와 보강빔(2')의 관통볼트 체결작업이 완료되면 하부의 인상장치(20)를 철거하고 에폭시(10) 주입상태를 관찰하여 일체 여부를 재확인 한다. 마무리 작업은 도장작업 및 보호 캡 작업으로 슬래브(1') 하부에 손상 및 부식방지를 위해 녹발생 우려 부위에 그리스를 바르고 강재 보호 박스를 제작하여 마무리한다.When the above-described bolting work of the slab 1 'and the reinforcing beam 2' is completed by removing the lower pulling device 20 and observing the injection state of the epoxy 10, the unit is checked again. . Finishing work is to paint and protect cap work, and finish by applying grease to the rust area to prevent damage and corrosion on the lower part of slab (1 ') and manufacturing steel protection box.

[실시예1]Example 1

도 7은 본 고안이 적용되는 콘크리트 슬래브의 단면도를 보인 것이고, 도 8에서 (a)는 단순보의 슬래브(1')에 탄성 프리플렉스 보강재(2)를 결속한 형태를 나타낸다. 그리고 (b)는 슬래브(1')의 사하중 휨모멘트를 나타내고, (c)는 탄성 프리플렉스 보강빔(2')의 휨모멘트(상향력)을 나타내며, (d)는 프리플렉스보강공법에 의해 휨모멘트가 보강된 형태를 나타내고 있다.7 is a cross-sectional view of a concrete slab to which the present invention is applied, and FIG. 8 (a) shows a form in which an elastic preflex stiffener 2 is bound to a slab 1 'of a simple beam. And (b) shows the dead load bending moment of the slab 1 ', (c) shows the bending moment (upward force) of the elastic preflex reinforcing beam 2', and (d) shows the preflexive reinforcing method. The bending moment is reinforced.

이하, 도 7 내지 도11을 참조하여 본 고안을 지간이 L1인 단순보에 적용한 경우를 실시예로 들어 설명하면 다음과 같다.Hereinafter, a case in which the present invention is applied to a simple beam having an interval L1 will be described with reference to FIGS. 7 to 11 as follows.

1) 먼저, 도 8a와 같은 형태의 단순보에서 사하중에 의해 발생된 휨응력에 대한 탄성 프리플렉스 보강보(2')의 상향력 결정에 대하여 살펴보면, 사하중에 의한 최대 휨모멘트 (Md)(도 8조)는 다음식과 같고,1) First, looking at the determination of the upward force of the elastic preflex stiffening beam (2 ') with respect to the bending stress generated by dead weight in the simple beam of the form as shown in Figure 8a, the maximum bending moment (Md) due to dead load (Fig. 8 Jo) is the same as

탄성 프리플렉스 보강보(2')에 의한 상향력 모멘트(Mp)는 다음식과 같다.The upward force moment Mp by the elastic preflex reinforcing beam 2 'is as follows.

탄성 프리플렉스 보강보(2')의 상향력은 사하중에 의한 휨 모멘트를 탄성 프리플렉스 보강보(2')의 분담량에 따라서 결정되며, 사하중에 의한 휨모멘트와 보강강재에 의한 상향력의 차이만큼이 기존구조물의 사하중에 대한 보강량이 된다.The upward force of the elastic preplex reinforcement beam 2 'is determined by the amount of bending moment due to dead weight of the elastic preflex reinforcement beam 2', and the difference between the bending moment due to dead load and the upward force due to the reinforcing steel. This is the reinforcement amount for dead weight of existing structure.

2)탄성 프리플렉스 보강보(2')의 제작2) Fabrication of elastic preplex reinforcement beam (2 ')

탄성 프리플렉스 보강보(2')의 길이는 기존 구조물의 작업조건과 현장 여건에 따라서 결정되어야 하며, 탄성 프리플렉스 보강보(2')의 길이가 길어지면 솟음량은 증가를 한다.The length of the elastic preplex reinforcement beam 2 'should be determined according to the working conditions and site conditions of the existing structure, and the rise amount increases as the length of the elastic preflex reinforcement beam 2' is increased.

탄성 프리플렉스 보강보(2')는 솟음량에 대하여 보강재가 직선으로 변형하면서 상향력을 발휘하며, 솟음량은 사용강재의 단면성질과 길이 및 사하중에 대한 보강량이 결정이되면 다음과 같은 방법으로 결정한다.The elastic preflex reinforcing beam 2 'exerts an upward force as the reinforcement deforms in a straight line with respect to the amount of rise, and the amount of rise is determined by the following method when the reinforcement amount for the cross-sectional quality, length and dead weight of the used steel is determined. Decide

여기서, P = 보강보 지간중앙점에서 발생되는 상향력, L = 탄성 프리플렉스 보강보(2')의 길이, E = 사용강재의 탄성계수, I = 사용강재의 단면2차모멘트,Where P = upward force generated at the midpoint of the reinforcing beam, L = length of the elastic preflex reinforcing beam (2 '), E = elastic modulus of the steel used, I = cross-section secondary moment of the steel used,

다음으로 프리플렉스보강공법의 작업순서는 다음과 같다.Next, the work order of the preplex reinforcement method is as follows.

1) 노후교량에 대한 선행 작업1) Predecessor Work on Aging Bridges

탄성 프리플렉스 보강보(2')가 분담하게 될 휨모멘트가 결정이 되면 보강강재가 상향력을 발휘할 수 있는 강재의 단면과 길이 및 솟음량이 결정된다.When the bending moment to which the elastic preflex reinforcing beam 2 'is to be shared is determined, the cross section, length, and amount of the reinforcing steel to which the reinforcing steel can exert upward force are determined.

탄성 프리플렉스 보강보(2')의 정착위치에 정밀한 시공측량을 통하여 슬래브(1')의 양단에는 구조물을 관통하는 천공을 실시한다.Perforations penetrating the structure are performed at both ends of the slab 1 'through precise construction surveying at the anchoring position of the elastic preflex reinforcing beam 2'.

천공작업시에는 앵커볼트(3)와의 공차를 고려하여 천공을 실시하고, 천공작업은 수직도가 유지될 수 있도록 정밀하게 시공되어야 한다.In the drilling work, the drilling is carried out in consideration of the tolerance with the anchor bolt (3), and the drilling work should be precisely constructed so that the verticality can be maintained.

기존 구조물 앵커볼트(3) 체결위치의 상면 슬래브(1')에는 앵커볼트 정착지압판(11) 설치와 작업공간확보를 위한 작업을 선행한다.The upper surface slab (1 ') of the existing structure anchor bolt (3) fastening position is preceded by the anchor bolt anchoring plate (11) installation and work for securing the working space.

2) 탄성 프리플렉스 보강보(2') 제작 및 설치위치2) Fabrication and installation location of elastic preflexive reinforcement beam (2 ')

탄성 프리플렉스 보강보(2')가 분담하게 될 휨응력을 유발할 수 있는 강재보를 제작하는데 사용강재와 강재보의 상향력에의하여 솟음량을 결정하여 제작한다.The elastic preplex reinforcement beam (2 ') is used to produce the steel beams that can cause the bending stress that will be shared.

기존 구조물의 최대 휨모멘트 발생위치와 탄성 프리플렉스 보강보(2')의 상향력이 작용할 중앙점이 일치하도록 제작한다.The maximum bending moment location of the existing structure and the center point where the upward force of the elastic preflex reinforcing beam (2 ') is to be made to coincide.

3) 탄성 프리플렉스 보강보(2')의 설치3) Installation of the elastic preplex reinforcement beam (2 ')

탄성 프리플렉스 보강보(2')의 설치작업은 현장여건에 따라서 여러가지 방법이 적용될 수 있다.The installation work of the elastic preplex reinforcement beam 2 'may be applied in various ways depending on the site conditions.

탄성 프리플렉스 보강보(2')의 인상작업을 위한 인상 작업대를 설치하는 경우에는 지반이 부등침하가 발생하지 않도록 하여야 하며, 유압잭(23)에 의한 상향력이 탄성 프리플렉스 보강보(2')에 균일하게 전달되도록 하고, 유압에 의하여 슬래브(1')가 상향처짐이 발생하지 않도록 유의 시공하여야 한다.When installing the lifting work platform for the lifting work of the elastic preflex reinforcing beam (2 '), the ground should not prevent unequal settlement, and the upward force by the hydraulic jack (23) is the elastic preflex reinforcing beam (2'). It is to be uniformly delivered to and should be constructed so that the slab 1 'does not sag upward due to hydraulic pressure.

4) 탄성 프리플렉스 보강보(2')의 정착4) Fixation of elastic preflex reinforcing beams (2 ')

탄성 프리플렉스 보강보(2')의 양단과 기존구조물과의 정착은 특수제작된 앵커볼트(3)를 사용하여 정착시켜야 하며, 앵커볼트(3)와 콘크리트가 접하게 되는 부분은 앵커볼트 정착지압판(11)을 설치하도록 한다.The anchoring of both ends of the elastic preflexive reinforcing beam (2 ') and the existing structure should be fixed using a specially manufactured anchor bolt (3), and the part where the anchor bolt (3) is in contact with concrete is anchor bolt anchorage plate ( 11) to be installed.

탄성 프리플렉스 보강보(2') 양단과 중앙점의 정착위치에는 기존 구조물과 정착기구와의 완전한 밀착을 통하여 정착효과를 높이고 에폭시를 사용한 경우에는 완전히 경화한 후에 인상장치(20)를 철수한다.At the fixing position of both ends of the elastic preflex reinforcing beam (2 ') and the central point to increase the fixing effect through the complete close contact with the existing structure and the fixing mechanism, if the epoxy is used, the pulling device 20 is withdrawn after fully hardened.

5) 탄성 프리플렉스 보강보(2')의 설치상태5) Installation condition of elastic preflex reinforcing beam (2 ')

탄성 프리플렉스 보강보(2')의 양단 앵커정착위치에는 탄성 프리플렉스 보강보(2')의 국부적인 찌그러짐을 예방하기 위하여 수직보강재인 좌굴방지재(6)를 설치한다.At both ends of anchoring positions of the elastic preflex reinforcing beams 2 ', a buckling preventing material 6, which is a vertical reinforcement, is installed to prevent local crushing of the elastic preflex reinforcing beams 2'.

미리 제작된 탄성 프리플렉스 보강보(2')의 정확한 성능을 발휘하기 위하여서는 솟음량이 기존구조물과 수평으로 일체가 되어야 하므로 설치전 솟음량과 설치후 탄성 프리플렉스 보강보(2')의 수평정도를 비교하여 시공정도를 판단한다.In order to show the accurate performance of the prefabricated elastic preflex reinforcing beams (2 '), the rising amount should be horizontally integrated with the existing structure. Determine the process flow chart by comparing.

다음으로 프리플렉스보강공법의 적용검토를위한 구조계산 예를 살펴보면 다음과 같다.Next, an example of structural calculation for the application of the preflex reinforcement method is as follows.

본 공업의 적용가능성과 문제점을 구체적으로 파악하기 위해, 국내에서 70-80년대 많이 적용했던 건설교통부(당시:건설부) '도로교상부구조표준도'에 실려있는 단순 슬래브교 3연속 슬래브교를 모델로 설정하여, 본 공법을 적용하였을때의 단면력과 철근응력 등의 변화를 조사하였으며, 여기에는 단순 슬래브교에 대한 내용을 예시하였다.In order to grasp the applicability and problems of this industry in detail, we modeled the simple slab bridge three consecutive slab bridges listed in the Structural Standards of Road Bridges, which was frequently applied in the 70s and 80s in Korea. In this study, the variation of the cross sectional force and the reinforcement stress when the method was applied was investigated. Here, the contents of the simple slab bridge are exemplified.

1 보강전1 reinforcement

(1) 구조계산 대상 교량제원(1) Specifications of bridges for structural calculation

(2) 단면제원은 도 7에 도시된 콘크리트 슬래브의 단면참조(2) Sectional specifications refer to the section of the concrete slab shown in FIG.

(3) 재료상수(3) material constant

구조계산 대상 교량은 표준 도면의 단면제원과 재료의 물리적 성질을 사용하여 철근의 허용응력은를 적용하였고, 콘크리트설계 압축강도는를 구조계산시 적용하였다.Bridges subject to structural calculations use the section properties of the standard drawing and the physical properties of the material. The compressive strength of concrete design is applied Was applied in the structural calculation.

(4) 해석을 위한 제원(4) Specifications for interpretation

콘크리트 슬래브 교량의 차도폭이 약 9m(2차선)에 해당되므로 보강프리플렉스보 4본을 대략 등간격으로 배치하여 보강하는 것이 합리적이라고 하겠다. 그래서, 슬래브(1')를 횡방향으로 4등분하여 1/4개의 종방향 슬래브 대(strip)에 대하여 간략하게 해석해도 본 고안의 목적에 충분하다고 판단하였다. 해석에 사용한 단면제원 및 단면 성질은 다음 표와 같다.Since the roadway width of the concrete slab bridge is about 9m (two lanes), it is reasonable to arrange and reinforce four reinforced preflex beams at approximately equal intervals. Therefore, even if the slab 1 'is divided into four equally in the transverse direction and briefly analyzed for 1/4 longitudinal slab strips, it was judged to be sufficient for the purpose of the present invention. Sectional specifications and cross-sectional properties used in the analysis are shown in the following table.

(5) 작용하중(5) working load

사하중은 횡단면에 아스팔트 단위중량으로 2.3, 콘크리트 단위중량으로 2.4를 사용하였다.Dead weight is 2.3 by the unit weight of asphalt in the cross section. 2.4, concrete unit weight Was used.

(6) 최대 단면력(6) the maximum cross-sectional force

사하중에 의한 1/4슬래브대의 최대 휨모멘트와 최대 전단력을 계산하면 다음표와 같으며, 도시하면 도 9a,9b와 같다.The maximum bending moment and maximum shear force of the 1/4 slab band due to dead load are calculated as shown in the following table, and are shown in FIGS. 9a and 9b.

2. 프리플렉스 보강공법의 적용2. Application of preflex reinforcement method

1) 보강량의 결정1) Determination of reinforcement amount

위에서 정리한 해석결과를 주인장철근의 응력 관점에서 살펴보면, 총응력 732kg/㎠ 중에서 슬래브(1') 자중이 차지하는 응력이 485 kg/㎠으로 66%에 해당한다. 일반적으로 슬래브교에서 총설계하중에서 사하중이 차지하는 비율이 50-70%에 해당한다. 그래서, 여기서는 사하중에 의한 주철근 인장응력의 50%에 해당하는 양을 탄성 프리플렉스 보강보(2')가 분담하도록 가정하여 계산하였다.Looking at the analysis results summarized above from the stress point of the reinforcing bar, the stress of the slab 1 'own weight among the total stress 732kg / ㎠ accounted for 66%, 485 kg / ㎠. In general, dead weight accounts for 50-70% of the total design load in slab bridges. Thus, it was calculated here assuming that the elastic preplex reinforcement beam 2 'shared an amount corresponding to 50% of the tensile stress of the reinforcing bar due to dead weight.

이렇게 감소된 철근응력은 활하중을 저항하는데 사용할 수 있게 되기 때문에 결과적으로 그만큼 교량의 내하력이 증가된다.This reduced reinforcement can be used to withstand live loads, which in turn increases the load capacity of the bridge.

앞에서 계산한 지간중앙의 사하중 모멘트가 69.2 tm이므로, 이 양의 1/2에 해당하는 모멘트는 34.6tm의 보강이 필요하다.Since the dead center moment of the mid-center calculated earlier is 69.2 tm, a moment equal to half of this quantity requires a reinforcement of 34.6 tm.

2) 프리플렉스 강재의 제원결정2) Determination of specifications of preflex steels

보강용 프리플렉스 강재의 전 길이는 지점부근에서 작업공간 확보를 위하여 교량 지간의 약(3/4)L(L:교량 순지간)에 해당하는 8m로 하는것이 합리적이라 판단된다. 그러면, 탄성 프리플렉스 보강보(2')가 분담하게 될 모멘트는 다음식과 같이 34.6tm 이므로It is reasonable that the total length of the reinforcing preflex steel should be 8m, which is about (3/4) L (L: bridge) between bridges to secure a working space near the point. Then, the moment that the elastic preflex reinforcing beam 2 'will be shared is 34.6tm as

탄성 프리플렉스 보강보(2') 중앙에서 상향력()는 17.3 ton이 필요하게 된다.Lifting force at the center of the elastic preflex ) Requires 17.3 tons.

탄성 프리플렉스 보강보(2')의 위치는 도 10과 같이 고정하중에 대한 최대 휨 모멘트를 나타내는 지간중앙위치와 보강보의 중심을 일치하도록 설치한다.The position of the elastic preflex reinforcing beam 2 'is installed so as to coincide with the center of the reinforcing beam and the center position of the center showing the maximum bending moment with respect to the fixed load as shown in FIG.

탄성 프리플렉스 보강보(2')로 사용될 강재는 SWS570을 사용하고, 허용휨강도의 대략 1/2정도(나머지 1/2은 보강후의 활하중에 저항할 수 있는 여분의 강도) 수준으로 앞에서 계산한 8m길이의 34.6ton의 모멘트를 저항하기 위해서는 대략 H-300x300x10x15 단면의 구조형강이 필요하게된다.The steel to be used as the elastic preflex stiffener (2 ') uses SWS570 and the 8m calculated above at the level of approximately 1/2 of the allowable bending strength (the other half is the extra strength to withstand the live load after reinforcement). In order to withstand a moment of 34.6 tons in length, structural sections of approximately H-300x300x10x15 sections are required.

3)프리플렉스보의 솟음(camber)량 결정3) Determination of the amount of camber of the preflex beam

앞에서 본 공법의 기본 원리를 설명한 바와 같이, 보강용 강재에 미리 솟음을 갖는 솟음량은 보강정도를 결정하는 매우 중요한 값이다. 보강 강재의 프리플렉스가 양단 앵커볼트(3)에 의해 직선으로 변형되면서 슬래브(1') 하부에 상향력을 발생시키는 원리이기 때문에, 앞에서 계산한 상향력 17.3 ton과 보강 강재 보의 길이 8m를 적용하여 탄성처짐량 계산식에 의해 소요 솟음량을 계산하면 다음식과 같다.As described above, the basic principle of the present method, the amount of preliminary rise in the reinforcing steel is a very important value for determining the degree of reinforcement. Since the preflex of the reinforcing steel is deformed in a straight line by the anchor bolts 3 at both ends, the upward force is generated in the lower part of the slab 1 '. When the required amount of rise is calculated by the elastic deflection amount formula, it is as follows.

여기서, P = 17.3ton, L = 8m, E = 2.0 ×E6 kg/㎠, I = 20400을 적용하였다. 산정한 솟음량 4.52cm는 순수 탄성이론에 의해 계산된 값이고, 현실적으로 제작오차 국부적 변형, 기존 슬래브(1')의 프리플렉스 상향력에 의한 상향 처짐등에 의한 손실을 대략적으로 보완하고, 시공상의 편리를 고려하여 50mm로 결정하면 합리적이라 하겠다.Where P = 17.3ton, L = 8m, E = 2.0 × E6 kg / cm 2, I = 20400 Was applied. The calculated rise of 4.52cm is a value calculated by the pure elasticity theory, and practically compensates for the loss due to local error of manufacturing error, upward deflection due to the preflex upward force of the existing slab 1 ', and convenience in construction. In consideration of this, it is reasonable to determine 50mm.

4) 프리플렉스보의 설치4) Installation of Preflexo

보강용으로 사전 제작한 프리플렉스강재는 양단에 수직으로 배치하는 앵커볼트(3)에 의해 그림 9와 같이 설치한다. 본 실시예에서 소요 앵커볼트(3)는 길이가 긴 특성상 연강으로 된 강봉을 특수하게 제작하여 사용하여야 한다. 사용강봉의 허용인장을 1500kg/㎠이 된다. 따라서, 앵커볼트(3)의 소용 단면적은 다음식과 같다.Pre-fabricated steel material for reinforcement is installed as shown in Fig. 9 by anchor bolts (3) arranged vertically at both ends. In this embodiment, the required anchor bolt (3) has to be used to make a special steel bar made of mild steel due to its long length. Allowable tensile strength of the steel bar is 1500kg / ㎠. Therefore, the required cross-sectional area of the anchor bolt 3 is as follows.

As,b = 8650/750 = 11.5 ㎠As, b = 8650/750 = 11.5 cm 2

기존 슬래브(1') 구체의 손상을 최소화하면서 시공성을 고려하여 직경 22mm 앵커볼트(3)를 적용한다면, 탄성 프리플렉스 보강보(2')의 각 단에 4개의 앵커볼트(3)가 소요된다. 기존 슬래브(1')에 앵커볼트(3) 설치를 위한 천공작업시에는 정착을 위한 공차를 두고 천공을 해야하며, 수직이 유지될 수 있도록 주의하여 시공을 한다.If you apply 22mm diameter anchor bolts (3) in consideration of workability while minimizing damage to the existing slab (1 ') spheres, four anchor bolts (3) are required at each end of the elastic preflex reinforcing beam (2'). . In the drilling work for installing the anchor bolt (3) to the existing slab (1 ') should be drilled with a tolerance for fixing, and care should be taken to maintain the vertical.

앵커볼트(3)의 정착으로 인한 보강용 강재 하부플랜지의 국부적 찌그러짐을 방지하기 위해서는 도 3과 같이 강재 단부에 수직 보강재인 좌굴방지재(6)를 설치해야 한다.In order to prevent local distortion of the lower flange of the reinforcing steel due to the anchor bolt (3), as shown in Figure 3, the buckling preventing material (6) that is a vertical reinforcement to the steel end.

(5) 앵커볼트(3)의 앵커볼트 정착지압판(11)(5) Anchor bolt anchorage plate (11) of anchor bolt (3)

기존 슬래브(1')의 상면에 앵커볼트(3)와 너트의 정착을 위해 앵커볼트 정착지압판(11)을 설치해야 한다. 이 앵커볼트 정착지압판(11) 아래의 콘크리트 응력은 3축압축상태이므로, 1축압축상태의 허용압축응력보다 훨씬 큰 값이 되지만, 여기서는 1축 압축상태의 허용압축용력을 허용지압강도로 가정을 하였다. 앵커볼트(3)에 의한 총 지압력이 8.65 ton이고, 보강 후에 작용하는 활하중에 대한 여유분을 고려하여 최대 지압응력을 허용지압응력의 약 1/2로 보면, 소요 지압면적은 206㎠이 산출된다. 따라서, 탄성 프리플렉스 보강보(2')의 플랜지 폭이 30cm이므로 앵커볼트(3)를 정착하기 위한 앵커볼트 정착지압판(11)은 30x20 ㎠ 크기로 하고, 판 두께는 15mm 정도면 충분할 것이다.The anchor bolt anchoring plate 11 must be installed for fixing the anchor bolt (3) and the nut on the upper surface of the existing slab (1 '). Since the concrete stress under the anchor bolt anchoring plate 11 is triaxially compressed, the value is much larger than the allowable compressive stress in the monoaxial compression. Is assumed as the allowable acupressure. When the total bearing pressure by the anchor bolt (3) is 8.65 ton and the maximum bearing pressure is about 1/2 of the allowable bearing stress in consideration of the allowance for the live load acting after reinforcement, the required bearing area is 206cm2. . Therefore, since the flange width of the elastic preflex reinforcing beam 2 'is 30 cm, the anchor bolt fixing pressure plate 11 for fixing the anchor bolt 3 is 30x20 cm 2 in size, and the plate thickness may be about 15 mm.

(6) 프리플렉스 상향력의 손실(6) loss of preplex upward force

본 공법에서도 프리스트레스트 콘크리트와 같이 초기 프리스트레스 손실이 발생하며, 손실을 유발시키는 원인은 대략 다음과 같이 추정할 수 있다.In this method, the initial prestress loss occurs like prestressed concrete, and the cause of the loss can be estimated as follows.

가) 프리플렉스 상향력 의한 슬래브(1')의 상향 처짐A) Upward deflection of slab 1 'due to preflex upward force

도 10에 보인것과 같이 초기 프리플렉스 상향력 17.3ton에 의한 슬래브(1')의 상향처짐이 발생하여 그 만큼 손실이 발생한다. 구조계산에 의해 이 처짐량을 계산한 결과 약 1.6mm가 산출되었다. 이 값은 프리플렉스 상향력의 0.55ton 감소량에 해당하는 것으로서, 손실율은 3.2%에 해당한다.As shown in FIG. 10, the upward deflection of the slab 1 ′ due to the initial preflex upward force of 17.3 ton occurs, thereby causing a loss. The amount of deflection was calculated by structural calculation, yielding about 1.6mm. This value corresponds to a 0.55 ton reduction in preplex upward force, with a loss rate of 3.2%.

나) 앵커볼트 정착지압판(11)의 변형과 지압응력에 의한 콘크리트 변형에 의한 손실B) losses due to deformation of the anchor bolt anchor plate (11) and deformation of concrete due to acupressure stress

사용된 앵커볼트 정착지압판(11)의 변형은 판두께에 따라 달라진다. 본 실시예에서 실제 지압응력이 14.4kg/㎠ 정도이기 때문에 판의 변형은 무시할 수 있는 량이며, 또한, 이 지압응력에 의한 콘크리트 구체의 변형도 1/100mm단위로 충분히 무시할 수 있다고 하겠다.The deformation of the anchor bolt anchoring plate 11 used depends on the plate thickness. In this embodiment, since the actual acupressure stress is about 14.4kg / cm 2, the deformation of the plate is negligible, and the deformation of the concrete sphere by this acupressure stress can also be sufficiently ignored in units of 1/100 mm.

다)앵커볼트(3)에 의한 탄성 프리플렉스 보강보(2')의 하부 플랜지 변형에 의한 손실C) Loss due to deformation of the lower flange of the elastic preflex reinforcing beam 2 'by the anchor bolt 3

탄성 프리플렉스 보강보(2')의 양단이 수직 스티프너인 좌굴방지재(6)에 의해 충분히 보강되어 있다면, 플랜지의 변형은 무시할 수 있을 정도로 적을 것이다.If both ends of the elastic preflex reinforcing beams 2 'are sufficiently reinforced by the anti-buckling member 6, which is a vertical stiffener, the deformation of the flange will be negligibly small.

결과적으로, 프리플렉스 상향력의 손실율은 위에서 언급한 내용외에 다른요인을 포함한다고 할지라도, 총 5%를 초과하지 않으리라 판단된다.As a result, the loss rate of the preflex upwards will not exceed 5% in total, even if the factors mentioned above are included.

(7) 전단연결재 설계(7) Shear connector design

탄성 프리플렉스 보강보(2')로 보강후에 차량하중이 재하되면, 이 활하중은 기존 슬래브(1')와 보강 강재가 서로 분담하게 된다. 이때 슬래브(1')와 탄성 프리플렉스 보강보(2')가 전단연결재에 의해 충분히 합성되어 있다면, 합성작용에 의해 활하중을 효과적으로 저항한다. 반면에 전단열결제를 설치하지 않는다면, 슬래브(1')와 탄성 프리플렉스 보강보(2')가 비합성상태에서 활하중을 저항하게 된다.When the vehicle load is loaded after reinforcement with the elastic preflex reinforcing beam 2 ', the live slab is divided between the existing slab 1' and the reinforcing steel. At this time, if the slab (1 ') and the elastic preflex reinforcing beam (2') is sufficiently synthesized by the shear connector, it effectively resists the live load by the synthesis action. On the other hand, if the shear thermal binder is not installed, the slab 1 'and the elastic preflex reinforcing beam 2' will resist the live load in an unsynthesized state.

도로교표준시방서에 따라 전단연결재를 계산해보면, 8m 전장의 보강재 상부 플랜지에 직경 22mm의 스터드가 20cm 간격의 2열 배치된 총 40개가 필요하게 된다.If the shear connector is calculated according to the road bridge standard specification, a total of 40 studs of 22 mm diameter are arranged in two rows of 20 cm intervals on the upper flange of the 8-meter reinforcement.

현실적으로, 위와 같은 전단연결재를 설치한다는 것은 슬래브(1') 구체의 손상, 기존 인장철근의 손상등의 해로운 영향 뿐만아니라, 실제 설치하기도 상당히 어려우며, 설치한다 하더라도 완전한 기능을 발휘하리라고 기대하기는 어렵다고 생각된다. 그래서 전단연결재를 설치않은 비합성상태로 활하중에 저항하도록 하든지, 또는, 합성보와 비합성보의 차이만큼에 해당하는 보강량을 더 증가시켜서 동일한 보강효과를 기대하는 것이 더 합리적이라고 판단된다.In reality, the installation of the shear connector as well as the harmful effects such as damage of the slab (1 ') spheres, damage to existing tensile reinforcing bars, as well as the actual installation is quite difficult, and even if installed, it is difficult to expect full functionality do. Therefore, it is more reasonable to expect the same reinforcement effect by either resisting the live load in a non-synthetic state without installing the shear connector or by increasing the amount of reinforcement corresponding to the difference between the composite beam and the non-synthetic beam.

(8) 교량과 탄성 프리플렉스 보강보(2')의 연결방법(8) Connection method of bridge and elastic preplex reinforcement beam (2 ')

교량과 탄성 프리플렉스 보강보(2') 양단의 고정점은 고장력 앵커볼트(3)가 관통하여 체결될 수 있도록 천공기로 관통을 시킨 후에 탄성 프리플렉스 보강보(2')와 구조물을 고정시킨다. 교량 상부 아스콘이 있던 부위는 무수축 에폭시 몰탈을 타설하여 물이 스며들지 않도록 방수처리하며, 관통구멍과 관통 앵커볼트(3) 사이는 에폭시로 충진하는데 일반적인 주입법으로는 완전하게 주입되지 않으므로, 특수 제작된 도 6과 같은 앵커볼트(3)를 사용하여 주입공극을 메워야한다. 특수 앵커볼트(3)는 머리부분을 관통하여 앵커볼트(3) 중앙부위로 에폭시가 충진되도록 고안하여 제작한 것으로 이는 천공 콘크리트면 사이에 에폭시의 완벽한 충진효과를 기대할 수 있게 고안되었다.Fixing points at both ends of the bridge and the elastic preplex reinforcing beam (2 ') is fixed to the elastic preflex reinforcing beam (2') and the structure after the penetration through a perforator so that the high-tensile anchor bolt (3) can be fastened through. The part where the ascon on the bridge was located is waterproof to prevent water penetration by pouring non-condensation epoxy mortar, and the filling between the through hole and the through anchor bolt (3) is filled with epoxy. Anchor bolts 3 as shown in FIG. 6 should be used to fill the injection voids. The special anchor bolt (3) is designed to be filled with epoxy through the head portion of the anchor bolt (3) is designed to be able to expect the perfect filling effect of epoxy between the perforated concrete surface.

탄성 프리플렉스 보강보(2') 중간 위치에서 구조물과는 앵커볼트(3)를 사용하여 구조체와 일체화 시킨다. 구조물과 관통앵커볼트(3) 체결작업이 완료되면 하부 인상장치(20)를 철거하여 에폭시 주입상태를 확인하여 일체여부를 재확인한다. 마무리 작업은 도장작업 및 보호캡 작업으로 구조물 하부에 손상 및 부식방지를 위해 녹 발생우려 부위에 그리스를 바르고 강재보호 박스를 제작하여 마무리한다.The elastic preplex reinforcement beam 2 'is integrated with the structure using an anchor bolt 3 with the structure at an intermediate position. When the fastening operation of the structure and the through anchor bolt (3) is completed, the lower lifting device 20 is removed to check the state of epoxy injection and re-confirm the integrity. Finishing work is painting work and protective cap work. Finish the work by applying grease to the area where rust is generated to prevent damage and corrosion on the lower part of the structure.

3. 프리플렉스보강후 단면력의 변화는 다음표 및 도 11과 같다.3. The change in the cross-sectional force after preflex reinforcement is shown in the following table and FIG.

단순 슬래브(1') 1/4대에 대한 프리플렉스 보강을 한후 사하중에 대한 보강전후의 단면력의 변화를 비교하여 보면, 탄성 프리플렉스 보강보(2')가 지간중앙 사하중에 의하여 발생된 휨모멘트의 50%를 분담하도록 보강을 한 결과, 지간 중앙에서의 휨 모멘트에 대한 보강은 탄성 프리플렉스 보강보(2')가 50%를 분담하는것으로 나타났다. 기존 구조물에 프리플렉스의 작용은 지간중앙에서는 상향력을 나타내며, 보강 강재 양단에서는 하향력을 작용하게 된다. 보강재 양단의 위치에서는 기존 전단력으 50% 감소를 보이고, 기간중에서는 상향력에 의하여 전단력(8.6ton)이 발생을 하였으나, 그 발생정도는 콘크리트 슬래브(1')교에서는 큰 문제가 되지 않을 것으로 판단된다.After comparing the pre-reinforcement of 1/4 simple slab (1 ') and comparing the change of cross-sectional force before and after reinforcement with dead weight, the bending moment generated by the mid-center dead weight of elastic preflexive reinforcement beam (2') As a result of reinforcement to share 50% of the reinforcement, the reinforcement for the bending moment at the center of the span showed that 50% of the elastic preflex reinforcement beam (2 ') shared. The action of the preplex on the existing structure shows an upward force in the middle of the trunk and a downward force on both ends of the reinforcing steel. The shear force decreased by 50% at both ends of the reinforcement, and shear force (8.6ton) was generated due to the upward force during the period, but the degree of occurrence is not a big problem in the concrete slab (1 ') bridge. do.

[실시예2]Example 2

슬래브 교량의 연장 35.95m인 블록1과 연장 35.95m인 블록2의 현장조사 및 구조 안정 검토를 실시한 결과 당초 구조 계산서에 의하면 상부구조 슬래브의 정모멘트 구간에 주철근이 D32 ⓐ10cm 로 배근하도록 되어 있으나, 시공은 D29 ⓐ15 cm로 시공되어 있다.As a result of the field survey and structural stability review of the block 1 of 35.95m extension and the block 2 of 35.95m extension of the slab bridge, the original structural calculation shows that the main reinforcing bar is placed at D32 ⓐ10cm in the moment of the superstructure slab. Construction is done with D29 ⓐ 15 cm.

이 슬래브교량에 대하여 본 고안의 탄성 프리플렉스 보강공법에 따라 다음과 같은 구체적인 보강공법을 실시하였다.This slab bridge was subjected to the following concrete reinforcement method according to the elastic preflex reinforcement method of the present invention.

보강방법의 작업 난이도 및 보강효과 측면에서 다른 타공법보다 우수하고 사하중 철근의 하중 응력이 1401 kg/㎠로 시방서의 허용응력 1500 kg/㎠에 거의 육박하는 상태로서 활하중에 저항하는 여유분이 100kg/㎠ 밖에 되지않는 실정이어서 구조물의 안정성과 사용성을 만족 시키는 보강방법을 강구하던중 적극적인 방법 즉, 활하중에 의한 인장응력 감소 뿐만 아니라 사하중에 의해 현재 발생되어 잇는 사하중 응력을 감소시키는 방법이 포함되어있는 본 고안을 실행하게 된 것이다.It is superior to other drilling methods in terms of working difficulty and reinforcing effect of reinforcement method and the load stress of dead reinforcing bar is 1401 kg / ㎠, which is close to the allowable stress 1500 kg / ㎠ of the specification, and 100kg / ㎠ The present invention includes a method to reduce the stress caused by dead load as well as to reduce the tensile stress caused by the dead load, while seeking a reinforcement method that satisfies the stability and usability of the structure. Will be executed.

사용 탄성 프리플렉스 보강보(2')는 단면:300 ×300 ×10 ×15인 H형 빔이고, 전길이 8.7 M, 단면2차 모멘트 20,400, 탄성계수 2.0 E 06kg/㎠, 사용재질 SWS 520, 허용응력 2100 kg/㎠이다.The elastic preplex reinforcement beam (2 ') is an H-shaped beam having a cross section of 300 × 300 × 10 × 15, and has a total length of 8.7 M and a cross section secondary moment of 20,400. Elastic modulus 2.0 E 06kg / ㎠, material SWS 520, allowable stress 2100 kg / ㎠.

그리고, 탄성 프리플렉스 보강보(2')의 허용 모멘트는 다음식과 같이 계산되었다.And the allowable moment of the elastic preflex reinforcing beam 2 'was calculated as follows.

4) 캠버량 결정4) Camber amount determination

여기서, 처짐 5.62cm는 탄성 프리플렉스 보강보(2')의 초기 캠버량임.Here, the deflection of 5.62 cm is the initial camber amount of the elastic preflex reinforcing beam 2 '.

안전진단결과 탄성 프리플렉스 보강보(2')의 초기 솟음량 5.62 cm 를 주어 구조체 하부에 탄성영역 한계에서 부착시켜 보강할 경우 2P = 16.72 ton (지간 중앙에 작용해야 하는 하중크기) 탄성 프리플렉스 보강보(2') 에 의해 보강 받게 된다.Safety diagnosis resulted in the initial rise of 5.62 cm of the elastic preplex reinforcement beam (2 '), when it is attached to the lower part of the structure at the elastic area limit and reinforced, 2P = 16.72 ton (load size to be applied to the center of the area). It is reinforced by the beam 2 '.

프리플렉스에 의한 보강방법은 프리플렉스에 의한 사하중 응력의 감소와 활하중에 대한 단면강성의 증가가 가장 큰 효과라 할 수 있다. 즉 프리플렉스에 의한 상향력은 사하중 크기를 감소시키는 역할을 하며 지점앵커와 지간 중앙부에서 전단연결재 기능의 앵커를 이용하여 탄성 프리플렉스 보강보(2')을 슬래브(1')에 고정시킴으로서 슬래브(1')와 H빔의 합성작용에 의한 강성증가는 활하중에 의한 응력의 크기를 감소 시키는 것이다.In the reinforcement method using the preflex, the greatest effect is the reduction of the dead load stress and the increase of the cross stiffness due to the live load. In other words, the upward force by the preflex serves to reduce the dead weight, and by fixing the elastic preflex reinforcement beam 2 'to the slab 1' by using the anchor of the shear connector at the point anchor and the center part of the slab, The increase in stiffness due to the combined action of 1 ') and H-beams reduces the magnitude of stress due to live loads.

이상에서 설명한 바와 같은 본 고안은 사하중에 의한 휨 응력을 인장철근과 탄성 프리플렉스 보강보가 분담하게 하여 사하중에 대한 보강으로 활하중에 대한 저항능력을 증대시키는 이점이 있으며, 노후된 교량의 슬래브를 간편한 방법으로 시공하여 내하력을 증대시킴으로써 사용수명을 연장하여 장기간 안전하게 사용할 수 있도록 하는 효과가 있다.As described above, the present invention has the advantage of increasing the resistance to live load by reinforcing the dead load by dividing the flexural stress caused by the dead load between the reinforcing bar and the elastic preflex reinforcement beam, and by using the simple method of the slab of the aging bridge. By increasing the load-bearing construction, it has the effect of extending the service life so that it can be used safely for a long time.

Claims (8)

구조체의 보강하고자 하는 영역에 따라 설정되는 캠버를 갖도록 벤딩되어 형성된 탄성 보강재와; 상기 구조체의 하부에 상기 탄성 보강재를 접촉시키고 상기 탄성 보강재의 양단부를 상부로 가압하여 상기 구조체에 결속하는 결속수단을 포함하여 상기 구조체의 내하력을 증가시키도록 구성됨을 특징으로 하는 탄성빔을 이용한 구조물 내하력 증진 보강장치.An elastic reinforcing member bent to have a camber set according to a region to be reinforced of the structure; The load capacity of the structure using the elastic beam, characterized in that configured to increase the load capacity of the structure, including a binding means for contacting the elastic reinforcement to the lower portion of the structure and presses both ends of the elastic reinforcement to the upper to bind to the structure. Enhancement bracing. 제 1 항에 있어서, 상기 탄성 보강재는 상기 구조체의 보강하고자 하는 영역에 따라 설정되는 캠버와 체결을 위한 볼트공을 갖도록 형성되는 탄성 프리플렉스 보강보이고, 상기 결속수단은 상기 탄성 프리플렉스 보강보의 볼트공과 상기 구조체의 관통공에 삽입 체결되는 볼트와 너트인 것을 특징으로 하는 탄성빔을 이용한 구조물 내하력 증진 보강장치.According to claim 1, wherein the elastic reinforcing material is an elastic preflex reinforcing beam formed to have a bolt hole for fastening with a camber set according to the area to be reinforced of the structure, the binding means is a bolt of the elastic preflex reinforcing beam Structural load-bearing reinforcement device using an elastic beam, characterized in that the ball and the bolt and nut is inserted into the through-hole of the structure. 제 2 항에 있어서, 상기 탄성 프리플렉스 보강보는 상기 구조체와 균일하게 밀착되도록 상기 구조체의 상부와 탄성 프리플렉스 보강보의 양단 하부 사이에 원형 강관 받침대, 유압잭, 메인 펌프, 간격 지지강재 및 침하 방지강재의 순서로 구조체의 높이에 따라 배치되어 각각 수평으로 설치되는 복수개의 인상장치에 의해 가압되고, 상기 탄성 프리플렉스 보강보의 양단부는 상기 각 인상장치의 메인 펌프에 부착된 유압 게이지에 의해 가압량을 측정하면서 인상되어진 것임을 특징으로 하는 탄성빔을 이용한 구조물 내하력 증진 보강장치.According to claim 2, wherein the elastic preflex reinforcing beam is a circular steel pipe bracket, the hydraulic jack, the main pump, the gap support steel and anti-sedimentation steel between the upper portion of the structure and the lower end of both ends of the structure so as to be in close contact with the structure uniformly Pressurized by a plurality of lifting devices which are arranged in accordance with the height of the structure in the order of the horizontally installed, respectively, wherein both ends of the elastic preflex reinforcement beams are pressurized by a hydraulic gauge attached to the main pump of the respective lifting devices Structural load-bearing reinforcement device using an elastic beam, characterized in that the impression was taken while measuring. 제 2 항에 있어서, 상기 탄성 프리플렉스 보강보를 체결하기 위한 볼트가 삽입되는 볼트공이 형성되고 상기 구조체의 상면에 적층된 아스콘을 깨내고 형성된 작업면에 결합되는 앵커볼트 정착지압판과, 상기 작업면의 앵커볼트 정착지압판 상부에 형성되는 에폭시 콘크리트층을 더 포함하여 구성된 것을 특징으로 하는 탄성빔을 이용한 구조물 내하력 증진 보강장치.The anchor bolt of claim 2, wherein a bolt hole into which a bolt for fastening the elastic preflex reinforcing beam is inserted is formed, and the ascon laminated on the upper surface of the structure is broken and coupled to a work surface formed. Fixing acupressure plate and structural load capacity enhancement reinforcement using an elastic beam, characterized in that it further comprises an epoxy concrete layer formed on the anchor bolt anchorage plate of the working surface. 제 2 항에 있어서, 상기 구조체의 관통공에 삽입된 상기 볼트의 수직 주입공과 수평 주입공으로 에폭시가 주입되어 상기 슬래브의 관통공의 내주면과 상기 볼트의 외주면 사이에 상기 에폭시가 충진 고정되어 구성됨 을 특징으로 하는 탄성빔을 이용한 구조물 내하력 증진 보강장치.According to claim 2, wherein the epoxy is injected into the vertical injection hole and the horizontal injection hole of the bolt inserted into the through hole of the structure is characterized in that the epoxy is filled and fixed between the inner peripheral surface of the through hole of the slab and the outer peripheral surface of the bolt. Structure load-bearing reinforcement device using elastic beam. 제 2 항에 있어서, 상기 탄성 프리플렉스 보강보의 중간부에 고정된 세트 앵커볼트가 상기 구조체의 중간부에 형성된 고정공에 삽입 고정되어 구성된 것을 특징으로 하는 탄성빔을 이용한 구조물 내하력 증진 보강장치.The apparatus of claim 2, wherein the set anchor bolt fixed to the middle portion of the elastic preflex reinforcement beam is inserted and fixed to the fixing hole formed in the middle portion of the structure. 제 2 항에 있어서, 상기 탄성 프리플렉스 보강보는 원호형으로 벤딩된 것임을 특징으로 하는 탄성빔을 이용한 구조물 내하력 증진 보강장치.The structure load-bearing reinforcement device of claim 2, wherein the elastic preflex reinforcing beam is bent in an arc shape. 제 2 항에 있어서, 상기 탄성 프리플렉스 보강보의 양단부에 플랜지의 좌굴을 방지하기 위한 좌굴방지재를 개재하고 상기 볼트를 체결된 것을 특징으로 하는 탄성빔을 이용한 구조물 내하력 증진 보강장치.The structure load-bearing reinforcement apparatus of claim 2, wherein the bolt is fastened to a buckling member for preventing buckling of the flange at both ends of the elastic preflex reinforcing beam.
KR2020000011592U 1999-12-03 2000-04-24 Apparatus to reinforce the endurance force of structure using tensile beam KR200202345Y1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019990054749A KR100352646B1 (en) 1999-12-03 1999-12-03 Method to reinforce the endurance force of structure using tensile beam

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1019990054749A Division KR100352646B1 (en) 1999-12-03 1999-12-03 Method to reinforce the endurance force of structure using tensile beam

Publications (1)

Publication Number Publication Date
KR200202345Y1 true KR200202345Y1 (en) 2000-11-15

Family

ID=19623420

Family Applications (2)

Application Number Title Priority Date Filing Date
KR1019990054749A KR100352646B1 (en) 1999-12-03 1999-12-03 Method to reinforce the endurance force of structure using tensile beam
KR2020000011592U KR200202345Y1 (en) 1999-12-03 2000-04-24 Apparatus to reinforce the endurance force of structure using tensile beam

Family Applications Before (1)

Application Number Title Priority Date Filing Date
KR1019990054749A KR100352646B1 (en) 1999-12-03 1999-12-03 Method to reinforce the endurance force of structure using tensile beam

Country Status (1)

Country Link
KR (2) KR100352646B1 (en)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100393103B1 (en) * 2001-04-18 2003-07-31 (주)평화엔지니어링 Method for reinforcing resistance force of a bridge using repulsing force of elastic fulcrum
KR20020080913A (en) * 2001-04-18 2002-10-26 (주)평화엔지니어링 Method for reinforcing resistance force of a bridge using preflexion restoring force
KR100426342B1 (en) * 2001-06-27 2004-04-08 이승영 The reinforcement method of slab bridge
KR100453419B1 (en) * 2001-11-16 2004-10-20 김준성 Method for reinforcing concrete structure using a pre-flex panel
KR100467046B1 (en) * 2002-05-27 2005-01-24 동양종합건업 주식회사 Prestressed concrete bridge using thereof and method for connecting prestressed concrete beam using connecting plates
KR100530024B1 (en) * 2003-03-18 2005-11-22 노윤근 Apparatus for reinforcing slab installing the upper and lower cover plate and fixing device of tension materials in prelexed H-type beam, and method for reinforcing slab using the apparatus
KR100866208B1 (en) * 2005-11-21 2008-10-30 위영민 A prestressed girder with slab and method of making the structure with it
KR100733609B1 (en) * 2006-03-31 2007-06-28 주식회사 제일엔지니어링 Reinforcing method of concrete structures using camber of steel beam
KR101170463B1 (en) * 2012-02-10 2012-08-07 주식회사 다인건설 The structure for load-carrying capacity improvementmethod of construction having load measuring
KR101400448B1 (en) * 2012-12-05 2014-05-28 조선대학교산학협력단 Measurement device of reinfored beam member
KR101400449B1 (en) * 2012-12-05 2014-05-28 조선대학교산학협력단 Reinforcing device of beam member
CZ307101B6 (en) * 2016-05-13 2018-01-10 Václav Rojík A method of limiting a sag and increasing beam load
KR101897495B1 (en) 2018-01-29 2018-09-12 이경훈 Long span structure using bending beam
KR101974064B1 (en) 2018-09-14 2019-04-30 민경기술 주식회사 Method for reinforcing concrete structure using preflex panel
KR102169796B1 (en) * 2018-10-12 2020-10-26 유지훈 Apparatus for close type reinforcing concrete structure
KR102107666B1 (en) 2018-11-14 2020-05-07 이경훈 Long Span Composite Beam And Long Span Structure Construction Method Using The Same
KR102085794B1 (en) 2018-11-14 2020-03-06 이경훈 Long span steel beam bending construction method
KR102152299B1 (en) 2018-11-14 2020-09-04 이경훈 Long span structure and construction method using bending beam

Also Published As

Publication number Publication date
KR100352646B1 (en) 2002-09-28
KR20010054105A (en) 2001-07-02

Similar Documents

Publication Publication Date Title
KR200202345Y1 (en) Apparatus to reinforce the endurance force of structure using tensile beam
Alkhrdaji et al. Upgrading the transportation infrastructure: solid RC decks strengthened with FRP
CN109706846B (en) High and narrow bridge capping beam through steel bar construction method for slope foundation
CN110541354B (en) Single-section prefabricated anti-seismic pier and construction method thereof
KR100890455B1 (en) Loading apparatus using gravitational method and apparatus of manufacturing preflex composite girder using the loading apparatus
KR20120065218A (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
JP2005090115A (en) Reinforcing construction method for existing floor slab by beam
KR100467647B1 (en) The repair and reinforcement method for a bridge
CN111305066A (en) Hybrid combination beam steel-concrete combination section and mounting method thereof
JPH05340031A (en) Prestressed concrete girder and its manufacture
CN210482022U (en) Prefabricated pier stud structure of assembling of slot-in type connection
JP2007169950A (en) Expansion body for bridge, and bridge expansion structure using the same
Scribner et al. Investigation of the collapse of L'Ambiance Plaza
CN211735114U (en) A antidumping reinforced structure for rectangle single-column mound bridge
CN113789732A (en) Shear-resistant reinforcing method and shear-resistant reinforcing device for hollow plate beam
Patel Strengthening of noncomposite steel girder bridges with post-installed shear connectors: fatigue behavior of the adhesive anchor
CN110700122A (en) A antidumping reinforced structure for rectangle single-column mound bridge
KR200378428Y1 (en) Bridge bearing one body
KR20020059960A (en) Precasted Concrete using a Fiber Reinforced Concrete and method for construction
AT526252B1 (en) METHOD FOR PRODUCING A ROAD Slab FOR A BRIDGE
JP2003064621A (en) Hanging floor slab bridge and reinforcing method of hanging floor slab
Toutlemonde et al. Fatigue tests of cracked reinforced concrete slabs for estimating the service life of composite bridge decks
De Corte et al. Evaluation of an experimental CFRP pre-stressed beam and slab road bridge
Bailey et al. Seismic isolation retrofitting of the Salt Lake City and County building
JP3073159B2 (en) Reinforcing structure of hinge part of Gerber Bridge

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
T701 Written decision to grant on technology evaluation
FPAY Annual fee payment

Payment date: 20001120

Year of fee payment: 3

LAPS Lapse due to unpaid annual fee