KR102436740B1 - Floor structure of tennis court with excellent vertical drainage and method of floor structure construction - Google Patents
Floor structure of tennis court with excellent vertical drainage and method of floor structure construction Download PDFInfo
- Publication number
- KR102436740B1 KR102436740B1 KR1020220051754A KR20220051754A KR102436740B1 KR 102436740 B1 KR102436740 B1 KR 102436740B1 KR 1020220051754 A KR1020220051754 A KR 1020220051754A KR 20220051754 A KR20220051754 A KR 20220051754A KR 102436740 B1 KR102436740 B1 KR 102436740B1
- Authority
- KR
- South Korea
- Prior art keywords
- water collecting
- collecting pipe
- concrete
- tennis court
- layer
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/08—Surfaces simulating grass ; Grass-grown sports grounds
- E01C13/083—Construction of grass-grown sports grounds; Drainage, irrigation or heating arrangements therefor
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C7/00—Coherent pavings made in situ
- E01C7/08—Coherent pavings made in situ made of road-metal and binders
- E01C7/32—Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C2201/00—Paving elements
- E01C2201/10—Paving elements having build-in shock absorbing devices
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C2201/00—Paving elements
- E01C2201/20—Drainage details
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
Description
본 발명은 수직 배수성이 우수한 테니스장의 바닥구조 및 그 바닥구조 시공방법에 관한 것으로, 더 상세하게는 코트 전체 면에 물 고임 및 규사 유실을 방지하도록 우수를 수직으로 배출하는 테니스장의 바닥구조 및 그 바닥구조를 시공하는 방법에 관한 것이다. The present invention relates to a floor structure of a tennis court with excellent vertical drainage and a method for constructing the floor structure, and more particularly, to a floor structure for a tennis court that vertically discharges rainwater to prevent water pooling and loss of silica sand on the entire surface of the court, and the floor It is about how to construct a structure.
일반적으로 인조잔디가 포설된 테니스장은 골재 층에 콘크리트를 포장하여 우천 시 표면 배수가 이루어지도록 시공된다. 상기 표면 배수를 위하여 코트 중앙의 네트를 기준으로 좌우 엔드라인까지 5%의 경사면을 형성하여 물 빠짐을 해소하는 공법이 적용되는데 이때, 코트표면의 미장은 수평 정밀성이 요구되고, 시공 후 물 고임 현상을 완벽하게 해소하기가 어려운 실정이다. 또한, 표면 배수에 따른 물 고임 및 규사 유실 현상은 운동장의 품격을 떨어뜨리는 원인이 된다. In general, tennis courts with artificial turf are constructed to drain the surface in case of rain by paving concrete on the aggregate layer. For the surface drainage, a 5% slope is formed from the net in the center of the court to the left and right end lines to solve the water dripping method is applied. It is difficult to completely solve the problem. In addition, stagnant water and loss of silica sand due to surface drainage cause deterioration of the quality of the playground.
본 출원인은 상술한 문제점을 해소하기 위하여 우수 및 눈 녹은 물이 콘크리트 바닥 면의 배수홀을 수직으로 통과하여 집수관으로 배출하는 배수 구조를 설계함으로써, 물 고임 및 규사 유실 현상을 방지하여 사용성이 우수한 테니스장을 건설할 수 있는 수직 배수성이 우수한 테니스장의 바닥구조 및 그 바닥구조 시공방법을 제공한다. In order to solve the above-mentioned problems, the present applicant designs a drainage structure in which rainwater and melted snow water passes vertically through the drainage hole of the concrete floor and is discharged to the water collecting pipe, thereby preventing water stagnant and silica sand loss and providing excellent usability. Provided are a floor structure for a tennis court with excellent vertical drainage for constructing a tennis court and a method for constructing the floor structure.
상술한 문제점을 해결하기 위한 본 발명의 목적은, 테니스장 전체 면의 우수 및 눈 녹은 물을 수직으로 배수하도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다. An object of the present invention for solving the above problems is to provide a floor structure of a tennis court having excellent vertical drainage, which is configured to vertically drain rainwater and melted snow from the entire surface of the tennis court.
본 발명의 다른 목적은, 지반 및 집수관 설치층, 골재 포설 및 콘크리트 타설층 및 인조잔디 포설층을 포함하여 구성되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다.Another object of the present invention is to provide a floor structure of a tennis court having excellent vertical drainage, which includes a ground and a water collecting pipe installation layer, an aggregate laying layer and a concrete laying layer, and an artificial turf laying layer.
본 발명의 또 다른 목적은, 상기 지반 및 집수관 설치층은 상기 테니스장 전체 면의 수평을 형성하는 지반과 상기 지반에 매설되어 배수 통로를 형성하는 집수관으로 구성되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다.Another object of the present invention is a floor structure of a tennis court with excellent vertical drainage, wherein the ground and the water collecting pipe installation layer are composed of a ground that forms a horizontal surface of the entire tennis court and a water collecting pipe buried in the ground to form a drain passage is to provide
본 발명의 또 다른 목적은, 상기 집수관은 상기 인조잔디 포설층으로부터 스며드는 수분이 배수 통로에 모이도록 콘크리트 표면에서 내부로 수직 관통되는 다수 개의 집수홀이 형성되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다.Another object of the present invention is to provide a floor structure of a tennis court with excellent vertical drainage in which the water collecting pipe has a plurality of water collecting holes vertically penetrating from the concrete surface to the inside so that the moisture permeating from the artificial turf laying layer collects in the drainage passage. is to provide
본 발명의 또 다른 목적은, 상기 집수관 표면에는 상기 집수홀을 통하여 이물질이 유입되는 것이 방지하도록 부직포를 감싸고 주변에는 골재로 뒷채움하여 구성되는 수직 배수성이 우수한 테니스장의 바닥구조을 제공하는 데 있다.Another object of the present invention is to provide a floor structure of a tennis court having excellent vertical drainage, which is configured by wrapping a nonwoven fabric on the surface of the water collecting pipe to prevent foreign substances from entering through the water collecting hole and backfilling the surrounding with aggregate.
본 발명의 또 다른 목적은, 상기 집수관은 상기 테니스장의 바닥면의 일 측 방향으로 일정한 간격으로 나란히 설치되는 지선 집수관과 상기 지선 집수관의 양단부에 연결되어 수분을 합류시켜 배출하는 본선 집수관으로 구성되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다.Another object of the present invention is that the water collecting pipe is connected to both ends of a branch water collecting pipe installed side by side at regular intervals in one direction of the floor surface of the tennis court, and the main line collecting pipe for converging and discharging water. It is to provide a floor structure of a tennis court with excellent vertical drainage consisting of
본 발명의 또 다른 목적은, 상기 골재 포설 및 콘크리트 타설층은 상기 지반 및 집수관 설치층의 상부에 고루 펼쳐서 포설되는 골재층과 상기 골재층 위에 타설되는 콘크리트층으로 구성되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다.Another object of the present invention is that the aggregate laying and concrete pouring layer is composed of an aggregate layer spread evenly on top of the ground and water collection pipe installation layer and a concrete layer poured on the aggregate layer. It is intended to provide a floor structure.
본 발명의 또 다른 목적은, 상기 콘크리트층에는 수직으로 골재층에 도달하도록 다수 개의 배수홀이 천공되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다.Another object of the present invention is to provide a floor structure of a tennis court having excellent vertical drainage in which a plurality of drainage holes are perforated to reach the aggregate layer vertically in the concrete layer.
본 발명의 또 다른 목적은, 상기 인조잔디 포설층은, 상기 타설된 콘크리트 위에 인조잔디매트를 포설하도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다.Another object of the present invention is to provide a floor structure of a tennis court with excellent vertical drainage, wherein the artificial turf laying layer is configured to install an artificial turf mat on the poured concrete.
본 발명의 또 다른 목적은, 상기 인조잔디 포설층의 상기 인조잔디매트는 기포지와 부직포를 열융착 방식으로 접합하여 기포층을 형성하여 규사는 유실되지 않고 우수만 수직으로 배수되도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조를 제공하는 데 있다.Another object of the present invention is that the artificial turf mat of the artificial turf laying layer forms a foam layer by bonding a foam paper and a non-woven fabric in a heat-sealing method, so that only the rainwater is vertically drained without loss of silica sand. It is to provide the floor structure of this excellent tennis court.
상술한 문제점을 해결하기 위한 본 발명의 목적은, (a) 지반 조성 단계, (b) 집수관 설치 단계, (c) 골재 포설 및 콘크리트 타설 단계 및 (d) 인조잔디매트 포설 단계를 포함하여 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다. It is an object of the present invention to solve the above problems, (a) ground composition step, (b) water collection pipe installation step, (c) aggregate and concrete pouring step and (d) artificial turf mat installation step An object of the present invention is to provide a floor structure construction method for a tennis court with excellent vertical drainage.
본 발명의 다른 목적은, 상기 (a) 지반 조성 단계는 상기 테니스장 전체 면의 수평을 형성하고 바닥면에 집수관을 매설하기 위한 홈을 형성하고 주변에 골재를 포설하도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다.Another object of the present invention is that, in the step (a), the ground composition step forms a horizontal surface of the tennis court, forms a groove for burying a water collecting pipe in the bottom surface, and installs aggregate around the tennis court with excellent vertical drainage. It is to provide a method of constructing a floor structure of
본 발명의 또 다른 목적은, 상기 (b) 집수관 설치 단계는 상기 조성된 지반의 홈에 집수관을 매설하도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다. Another object of the present invention is to provide a floor structure construction method of a tennis court having excellent vertical drainage, wherein the (b) water collecting pipe installation step is configured to bury the water collecting pipe in the groove of the created ground.
본 발명의 또 다른 목적은, 상기 (b) 집수관 설치 단계에는 본선 집수관과 지선 집수관을 연결하여 배수 구조를 형성하는 집수관 조립 단계를 더 포함하여 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다.Another object of the present invention is to provide a floor structure of a tennis court having excellent vertical drainage, comprising the step of assembling a water collecting pipe by connecting the main water collecting pipe and the branch collecting pipe to form a drainage structure in (b) installing the water collecting pipe. To provide a construction method.
본 발명의 또 다른 목적은, 상기 (b) 집수관 설치 단계에는 집수홀을 통한 이물질의 유입을 방지하도록 상기 집수관의 표면을 부직포로 감싸서 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다.Another object of the present invention is to provide a floor structure construction method for a tennis court having excellent vertical drainage, which is configured by wrapping the surface of the water collecting pipe with a non-woven fabric to prevent the inflow of foreign substances through the water collecting hole in the (b) water collecting pipe installation step is to do
본 발명의 또 다른 목적은, 상기 (c) 골재 포설 및 콘크리트 타설 단계는 상기 설치한 집수관 상부에 골재를 포설한 후 다시 상부에 콘크리트를 타설하도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다. Another object of the present invention is to provide a floor structure construction method for a tennis court with excellent vertical drainage, wherein the step (c) of installing aggregate and pouring concrete comprises installing aggregate on the upper part of the installed water collecting pipe and then pouring concrete on the upper part again. is to provide
본 발명의 또 다른 목적은, 상기 (c) 골재 포설 및 콘크리트 타설 단계에는 상기 콘크리트층을 수직으로 관통하여 골재층에 도달하도록 다수 개의 배수홀을 형성하는 배수홀 천공 단계를 더 포함하여 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다. Another object of the present invention is that (c) the step of laying the aggregate and pouring the concrete further comprises the step of drilling a drainage hole to form a plurality of drainage holes so as to vertically penetrate the concrete layer to reach the aggregate layer. An object of the present invention is to provide a floor structure construction method for a tennis court with excellent drainage.
본 발명의 또 다른 목적은, 상기 (d) 인조잔디매트 포설 단계는 상기 콘크리트가 양생한 후 위에 인조잔디매트를 포설하도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다. Another object of the present invention is to provide a floor structure construction method for a tennis court having excellent vertical drainage, wherein the (d) artificial turf mat installation step is configured to install an artificial turf mat on the concrete after curing.
본 발명의 또 다른 목적은, 상기 (d) 인조잔디매트 포설 단계에서 상기 인조잔디매트의 파일층과 기포층 사이에는 규사를 충진하도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다. Another object of the present invention is to provide a floor structure construction method for a tennis court having excellent vertical drainage, which is configured to fill silica sand between the pile layer and the bubble layer of the artificial turf mat in the step (d) installing the artificial turf mat. have.
본 발명의 또 다른 목적은, 상기 (d) 인조잔디매트 포설 단계에서 상기 인조잔디매트는 기포지와 부직포를 열융착 방식으로 기포층을 형성함으로써, 규사의 유실을 억제하고 수직 배수성이 우수하도록 구성되는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 제공하는 데 있다. Another object of the present invention is that in the (d) artificial turf mat installation step, the artificial turf mat is configured to suppress the loss of silica sand and to have excellent vertical drainage by forming a foam layer by heat-sealing the foam paper and the non-woven fabric. An object of the present invention is to provide a floor structure construction method for a tennis court with excellent vertical drainage.
이와 같은 목적을 달성하기 위한 본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 특징은, 테니스장 전체 면의 우수 및 눈 녹은 물을 수직으로 배수하도록 구성된다. The characteristic of the tennis court floor structure with excellent vertical drainage according to the present invention for achieving the above object is to vertically drain the rainwater and melted snow from the entire surface of the tennis court.
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 다른 특징은, 지반 및 집수관 설치층, 골재 포설 및 콘크리트 타설층 및 인조잔디 포설층을 포함하여 구성된다. Another characteristic of the tennis court floor structure having excellent vertical drainage according to the present invention is that it includes a ground and water collection pipe installation layer, an aggregate installation and concrete placement layer, and an artificial turf installation layer.
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 상기 지반 및 집수관 설치층은 상기 테니스장 전체 면의 수평을 형성하는 지반과 상기 지반에 매설되어 배수 통로를 형성하는 집수관으로 구성된다. Another feature of the tennis court floor structure having excellent vertical drainage according to the present invention is that the ground and the water collecting pipe installation layer are composed of a ground that forms a horizontal surface of the entire tennis court and a water collecting pipe buried in the ground to form a drainage passage do.
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 상기 집수관은 상기 인조잔디 포설층으로부터 스며드는 수분이 배수 통로에 모이도록 콘크리트 표면에서 내부로 수직 관통되는 다수 개의 집수홀이 형성된다. Another feature of the tennis court floor structure with excellent vertical drainage according to the present invention is that the water collecting pipe has a plurality of water collecting holes vertically penetrating from the concrete surface to the inside so that moisture permeating from the artificial turf layer is collected in the drainage passage. .
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 상기 집수관 표면에는 상기 집수홀을 통하여 이물질이 유입되는 것을 방지하도록 부직포를 감싸고 주변에는 골재로 뒷채움하여 구성된다. Another feature of the tennis court floor structure with excellent vertical drainage according to the present invention is that the surface of the water collecting pipe is wrapped around a nonwoven fabric to prevent foreign substances from entering through the water collecting hole and backfilled with aggregate.
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 상기 집수관은 상기 테니스장의 바닥면의 일 측 방향으로 일정한 간격으로 나란히 설치되는 지선 집수관과 상기 지선 집수관의 양단부에 연결되어 수분을 합류시켜 배출하는 본선 집수관으로 구성된다. Another feature of the tennis court floor structure excellent in vertical drainage according to the present invention is that the water collecting pipe is connected to both ends of a branch water collecting pipe installed side by side at regular intervals in one direction of the floor surface of the tennis court, and the branch line collecting pipe. It is composed of a main line collecting pipe that merges and discharges moisture.
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 상기 골재 포설 및 콘크리트 타설층은 상기 지반 및 집수관 설치층의 상부에 고루 펼쳐서 포설되는 골재층과 상기 골재층 위에 타설되는 콘크리트층으로 구성된다. Another feature of the tennis court floor structure having excellent vertical drainage according to the present invention is that the aggregate laying layer and the concrete pouring layer are spread evenly on top of the ground and water collecting pipe installation layer and the concrete layer poured on the aggregate layer. is composed of
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 상기 콘크리트층에는 수직으로 골재층에 도달하도록 다수 개의 배수홀이 천공된다. Another feature of the tennis court floor structure having excellent vertical drainage according to the present invention is that a plurality of drainage holes are perforated in the concrete layer to reach the aggregate layer vertically.
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 된다. Another feature of the tennis court floor structure with excellent vertical drainage according to the present invention is.
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 상기 인조잔디 포설층은, 상기 타설된 콘크리트 위에 인조잔디매트를 포설하도록 구성된다. Another feature of the tennis court floor structure having excellent vertical drainage according to the present invention is that the artificial turf installation layer is configured to install an artificial turf mat on the poured concrete.
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 또 다른 특징은, 상기 인조잔디 포설층의 상기 인조잔디매트는 기포지와 부직포를 열융착 방식으로 접합하여 기포층을 형성하여 규사는 유실되지 않고 우수만 수직으로 배수되도록 구성된다. Another feature of the tennis court floor structure with excellent vertical drainage according to the present invention is that the artificial turf mat of the artificial turf installation layer is excellent without loss of silica sand by bonding the foam paper and the non-woven fabric to form a foam layer by bonding the foam paper and the non-woven fabric to the thermal fusion method. It is only configured to drain vertically.
이와 같은 목적을 달성하기 위한 본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 특징은, (a) 지반 조성 단계, (b) 집수관 설치 단계, (c) 골재 포설 및 콘크리트 타설 단계 및 (d) 인조잔디매트 포설 단계를 포함하여 구성된다. The characteristics of the floor structure construction method of the tennis court with excellent vertical drainage according to the present invention for achieving the above object are: (a) ground composition step, (b) water collection pipe installation step, (c) aggregate laying and concrete pouring step and (d) It is constituted including the step of installing an artificial turf mat.
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 다른 특징은, 상기 (a) 지반 조성 단계는 상기 테니스장 전체 면의 수평을 형성하고 바닥면에 집수관을 매설하기 위한 홈을 형성하고 주변에 골재를 포설하도록 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is that in the step (a), the ground composition step forms a horizontal level of the entire surface of the tennis court and forms a groove for burying a water collecting pipe in the floor surface, and It is configured to lay aggregate on the
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 또 다른 특징은, 상기 (b) 집수관 설치 단계는 상기 조성된 지반의 홈에 집수관을 매설하도록 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is that the (b) water collecting pipe installation step is configured to bury the water collecting pipe in the groove of the created ground.
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 또 다른 특징은, 상기 (b) 집수관 설치 단계에는 본선 집수관과 지선 집수관을 연결하여 배수 구조를 형성하는 집수관 조립 단계를 더 포함하여 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is that in the (b) installation step of the water collection pipe, a water collecting pipe assembling step of connecting the main line water collecting pipe and the branch line collecting pipe to form a drainage structure is further performed. consists of including.
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 또 다른 특징은, 상기 (b) 집수관 설치 단계에는 집수홀을 통한 이물질의 유입을 방지하도록 상기 집수관의 표면을 부직포로 감싸서 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is that the surface of the water collecting pipe is wrapped with a nonwoven fabric to prevent the inflow of foreign substances through the water collecting hole in the (b) water collecting pipe installation step. .
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 또 다른 특징은, 상기 (c) 골재 포설 및 콘크리트 타설 단계는 상기 설치한 집수관 상부에 골재를 포설한 후 다시 상부에 콘크리트를 타설하여 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is that the step (c) of installing aggregate and pouring concrete includes laying the aggregate on the upper part of the installed water collection pipe and then pouring concrete on the upper part again. is composed
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 또 다른 특징은, 상기 (c) 골재 포설 및 콘크리트 타설 단계에는 상기 콘크리트층을 수직으로 관통하여 골재층에 도달하도록 다수 개의 배수홀을 형성하는 배수홀 천공 단계를 더 포함하여 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is that in the step (c) of laying the aggregate and pouring the concrete, a plurality of drainage holes are formed so as to penetrate the concrete layer vertically to reach the aggregate layer. It is configured to further include a drain hole drilling step.
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 또 다른 특징은, 상기 (d) 인조잔디매트 포설 단계는 상기 콘크리트가 양생한 후 위에 인조잔디매트를 포설하도록 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is that the (d) artificial turf mat installation step is configured to install the artificial turf mat on the artificial turf mat after the concrete has cured.
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 또 다른 특징은, 상기 (d) 인조잔디매트 포설 단계에서 상기 인조잔디매트의 파일층과 기포층 사이에는 규사를 충진하도록 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is to fill a space between the pile layer and the bubble layer of the artificial turf mat in the (d) artificial turf mat installation step.
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법의 또 다른 특징은, 상기 (d) 인조잔디매트 포설 단계에서 상기 인조잔디매트는 기포지와 부직포를 열융착 방식으로 기포층을 형성함으로써, 규사의 유실을 억제하고 수직 배수성이 우수하도록 구성된다. Another feature of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is that the artificial turf mat in the step (d) installing the artificial turf mat forms a foam layer by thermally bonding the foam paper and the non-woven fabric to form a foam layer, It is constructed to suppress the loss of silica sand and to have excellent vertical drainage.
이상에서와 같은 본 발명은 먼저, 테니스장 전체 면에 집수관을 매설하고 콘크리트 바닥을 천공하여 수직 배수가 이루어지도록 구성된다. 따라서 물 고임 현상이 나타나지 않는 운동 여건이 우수한 테니스장을 건설할 수 있다. The present invention as described above is configured such that vertical drainage is performed by first burying a water collecting pipe on the entire surface of the tennis court and perforating the concrete floor. Therefore, it is possible to construct a tennis court with excellent exercise conditions that does not cause stagnant water.
또한, 본 발명은 부직포를 열융착하여 제조되는 인조잔디매트 위에 규사를 포설하여 완성하도록 구성된다. 따라서 배수성이 좋은 부직포는 우수만 수직 배수하고 규사는 보존함으로써 테니스장의 기능을 완벽하게 유지하는 장점이 있다. In addition, the present invention is configured to complete by laying the silica sand on the artificial turf mat manufactured by heat-sealing the nonwoven fabric. Therefore, nonwoven fabric with good drainage has the advantage of perfectly maintaining the function of the tennis court by vertically draining only rainwater and preserving silica sand.
또한, 본 발명은 수직 배수가 가능하여 테니스장의 네트에서 엔드라인까지 경사각을 적용하지 않는 평면시공이 이루어진다. 따라서 일반적인 인조잔디 테니스장보다 코트 면의 수평 정밀도가 뛰어남으로써 경기력을 향상에 기여할 수 있는 코트를 시공할 수 있다. In addition, since the present invention is capable of vertical drainage, flat construction is made without applying an inclination angle from the net to the end line of the tennis court. Therefore, it is possible to construct a court that can contribute to improving the performance by having superior horizontal precision of the court surface than a general artificial turf tennis court.
도 1은 본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조를 개략적으로 나타내는 단면도이다.
도 2는 본 발명의 집수관 연결구조 및 우수 배출경로를 개략적으로 나타내는 평면도이다.
도 3은 본 발명의 집수관의 세부 구조를 나타내는 사진이다.
도 4는 본 발명의 콘크리트 바닥에 배수홀이 천공된 모습 및 부분 상세도이다.
도 5는 본 발명에 따른 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 단계별로 나타내는 공정도이다.1 is a cross-sectional view schematically showing a floor structure of a tennis court having excellent vertical drainage according to the present invention.
2 is a plan view schematically showing a water collecting pipe connection structure and rainwater discharge path of the present invention.
Figure 3 is a photograph showing the detailed structure of the water collecting pipe of the present invention.
Figure 4 is a state and partial details of the drainage hole perforated in the concrete floor of the present invention.
5 is a step-by-step process diagram illustrating a method of constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention.
본 발명은 다양한 변경을 가할 수 있고 여러 실시 예를 가질 수 있는바, 특정한 실시 예들을 도면에 예시하고 발명의 설명에 상세하게 설명하고자 한다. Since the present invention can have various changes and can have several embodiments, specific embodiments are illustrated in the drawings and described in detail in the description of the invention.
그러나 이는 본 발명을 특정한 실시 형태에 대해 한정하려는 것이 아니며, 본 발명의 사상 및 기술 범위에 포함되는 모든 변경, 균등물 및 대체물을 포함하는 것으로 이해하여야 한다. However, this is not intended to limit the present invention to a specific embodiment, it should be understood to include all modifications, equivalents and substitutes included in the spirit and scope of the present invention.
본 발명에 사용된 용어나 단어는 단지 특정한 실시 예를 설명하기 위해 사용된 것으로, 본 발명을 한정하려는 의도가 아니다. 자신의 발명을 최선으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙으로 본 발명의 기술적 사상에 부합되는 의미와 개념으로 해석되어야만 한다. The terms or words used in the present invention are only used to describe specific embodiments, and are not intended to limit the present invention. In order to best describe one's invention, it should be interpreted as a meaning and concept consistent with the technical idea of the present invention in principle that the concept of a term can be appropriately defined.
일반적으로 인조잔디가 포설된 테니스장은 골재 층에 콘크리트를 포장하여 우천 시 표면 배수가 이루어지도록 시공된다. 상기 표면 배수를 위하여 코트 중앙의 네트를 기준으로 좌우 엔드라인까지 5%의 경사면을 형성하여 물 빠짐을 해소하는 공법이 적용되는데 이때, 코트표면의 미장은 수평 정밀성이 요구되고, 시공 후 물 고임 현상을 완벽하게 해소하기가 어려운 실정이다. 또한, 표면 배수에 따른 물 고임 및 규사 유실 현상은 운동장의 품격을 떨어뜨리는 원인이 된다. In general, tennis courts with artificial turf are constructed to drain the surface in case of rain by paving concrete on the aggregate layer. For the surface drainage, a 5% slope is formed from the net in the center of the court to the left and right end lines to solve the water dripping method is applied. It is difficult to completely solve the problem. In addition, stagnant water and loss of silica sand due to surface drainage cause deterioration of the quality of the playground.
본 출원인은 다년간 인조잔디 테니스장을 건설하면서 상술한 문제점을 해소하기 위하여 연구를 거듭하였다. The present applicant has repeatedly studied to solve the above problems while constructing an artificial turf tennis court for many years.
본 발명은 우수 및 눈 녹은 물이 콘크리트 바닥 면의 배수홀을 수직으로 통과하여 집수관으로 배출하는 배수 구조를 설계함으로써, 물 고임 및 규사 유실 현상을 방지하여 사용성이 우수한 테니스장을 건설할 수 있는 수직 배수성이 우수한 테니스장의 바닥구조 및 그 바닥구조 시공방법을 개발하였다. The present invention is to design a drainage structure in which rainwater and melted snow water passes vertically through the drainage hole of the concrete floor and is discharged to the water collecting pipe, thereby preventing water stagnant and silica sand loss and constructing a tennis court with excellent usability. A floor structure of a tennis court with excellent drainage and a method for constructing the floor structure were developed.
본 발명의 구체적인 특징 및 이점은 첨부된 도면을 참조한 이하의 설명으로 더욱 명확해질 것이다.Specific features and advantages of the present invention will become more apparent from the following description with reference to the accompanying drawings.
도 1은 본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조를 개략적으로 나타내는 단면도이고, 도 2는 본 발명의 집수관 연결구조 및 우수 배출경로를 개략적으로 나타내는 평면도이고, 도 3은 본 발명의 집수관의 세부 구조를 나타내는 사진이고, 도 4는 본 발명의 콘크리트 바닥에 배수홀이 천공된 모습 및 부분 상세도이고, 도 5는 본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조 시공방법을 단계별로 나타내는 공정도이다.1 is a cross-sectional view schematically showing the floor structure of a tennis court having excellent vertical drainage according to the present invention, FIG. 2 is a plan view schematically showing a water collecting pipe connection structure and a rainwater discharge path of the present invention, and FIG. 3 is a house of the present invention It is a photograph showing the detailed structure of the water pipe, FIG. 4 is a state where the drainage hole is perforated in the concrete floor of the present invention and a partial detail view, and FIG. It is a process diagram showing.
<실시 예 1> 본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조<Example 1> Floor structure of a tennis court with excellent vertical drainage according to the present invention
본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조는, 테니스장 전체 면에 우수 및 눈 녹은 물을 수직으로 배수하는 구성에 관한 것이다. The floor structure of a tennis court having excellent vertical drainage according to the present invention relates to a configuration in which rainwater and melted snow water are vertically drained over the entire surface of the tennis court.
도 1을 참조하여 설명하면, 본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조는, 지반 및 집수관 설치층(100), 골재 포설 및 콘크리트 타설층(200) 및 인조잔디 포설층(300)을 포함하여 구성된다. 1, the floor structure of the tennis court with excellent vertical drainage according to the present invention includes a ground and water collection
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 상기 지반 및 집수관 설치층(100)은, 상기 테니스장 전체 면의 수평을 형성하는 지반(110) 및 상기 지반에 매설되어 배수 통로(132)를 형성하는 집수관(130)으로 구성된다. The ground and water collection
이러한 본 발명의 상기 지반 및 집수관 설치층(100)의 상기 집수관(130)은, 상기 인조잔디 포설층(300)으로부터 스며드는 수분이 배수 통로(132)에 모이도록 표면에서 내부로 관통되는 다수 개의 집수홀(131)이 형성된다. The
이때, 상기 집수관(130)은, PE 이중벽 관(일명 유공관)이 사용되며, 제품(길이 6m)을 테니스장의 규격에 맞추어 절단·연결하여 사용한다. At this time, as the
이러한 본 발명의 상기 집수관(130) 표면에는, 상기 집수홀(131)을 통하여 이물질이 유입되는 것을 방지하도록 부직포(120)를 감싸고 주변에는 골재로 뒷채움하도록 구성된다. The surface of the
이러한 본 발명의 상기 집수관(130)은, 상기 테니스장의 바닥면(110)의 일 측 방향으로 일정한 간격으로 나란히 설치되는 지선 집수관(11-2) 및 상기 지선 집수관의 양단부에 연결되어 수분을 합류시켜 배출하는 본선 집수관(11-1)으로 구성된다. The
이때, 상기 본선 집수관(11-1)은 지름의 300mm의 유공관이 적용되고, 지선 집수관(11-2)은 직경이 150mm이므로 T-소켓(133)을 이용하여 연결하며, 각 지선 집수관(11-2) 사이의 간격은 4,000mm로 배치한다. At this time, the main line collection pipe 11-1 is a perforated pipe having a diameter of 300 mm is applied, and since the branch line collection pipe 11-2 has a diameter of 150 mm, it is connected using a T-
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 상기 골재 포설 및 콘크리트 타설층(200)은, 상기 지반 및 집수관 설치층(100)의 상부에 고루 펼쳐서 포설되는 골재층(210) 및 상기 골재층 위에 타설되는 콘크리트층(220)으로 구성된다. The aggregate laying and concrete pouring
이러한 본 발명의 상기 콘크리트층(220)에는, 수직으로 골재층(210)에 도달하도록 다수 개의 배수홀(221)이 천공된다. In the
이때, 상기 배수홀(221)은 콘크리트 타공용 드릴(지름 20mm, 길이 200mm)을 이용하여 테니스장 전체 면에 가로·세로(500mm x 500mm) 간격을 격자 모양으로 타공한다. (도 4 참조) At this time, the
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 상기 인조잔디 포설층(300)은, 상기 타설된 콘크리트 위에 인조잔디매트(310)를 포설하도록 구성된다. The artificial
이러한 본 발명의 상기 인조잔디 포설층(300)의 상기 인조잔디매트(310)는, 기포지와 부직포를 열융착 방식으로 접합하여 기포층(312)을 형성하여 규사는 유실되지 않고 우수만 수직으로 배수되도록 구성된다. The
<실시 예 2> 본 발명에 따른 테니스장의 바닥구조 시공방법<Example 2> Method for constructing a floor structure of a tennis court according to the present invention
도 5를 참조하여 설명하면, 상술한 본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조의 시공방법은, (a) 지반 조성 단계(S100), (b) 집수관 설치 단계(S200), (c) 골재 포설 및 콘크리트 타설 단계(S300) 및 (d) 인조잔디매트 포설 단계(S400)를 포함하여 구성된다. Referring to FIG. 5, the construction method of a tennis court floor structure having excellent vertical drainage according to the present invention described above includes (a) ground composition steps (S100), (b) water collection pipe installation steps (S200), (c) It is configured including the steps of placing aggregates and placing concrete (S300) and (d) installing artificial turf mats (S400).
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조 시공방법의 상기 (a) 지반 조성 단계(S100)는, 상기 테니스장 전체 면의 수평을 형성하고 바닥면(110)에 집수관(130)을 매설하기 위한 홈을 형성하고 주변에 골재를 포설하도록 구성된다. The step (a) of the ground composition step (S100) of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is to form a horizontal level of the entire surface of the tennis court and to bury the
이때, 상기 집수관(130)의 표면에 형성된 집수홀(131)을 통해 이물질이 유입되는 것을 방지하도록 부직포(120)를 감싸고, 골재로 뒷채움하도록 구성된다. At this time, the
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조 시공방법의 상기 (b) 집수관 설치 단계(S200)는, 상기 조성된 바닥 면(지반)의 홈에 집수관(130)을 매설하도록 구성된다. The (b) water collecting pipe installation step (S200) of the method for constructing a floor structure with excellent vertical drainage according to the present invention is configured to bury the
이러한 본 발명의 상기 집수관(130)은, 상기 인조잔디 포설층(300)으로부터 스며드는 수분이 배수 통로(132)에 모이도록 표면에서 내부로 관통되는 다수 개의 집수홀(131)이 형성된다. In the
이러한 본 발명의 상기 (b) 집수관 설치 단계(S200)에는, 본선 집수관(11-1)과 지선 집수관(11-2)을 연결하여 배수 구조를 형성하는 집수관 조립 단계(S210)를 더 포함하여 구성된다. In the (b) water collecting pipe installation step (S200) of the present invention, a water collecting pipe assembling step (S210) of connecting the main line water collecting pipe 11-1 and the branch line collecting pipe 11-2 to form a drainage structure is performed. It includes more.
이때, 상기 본선 집수관(11-1)은 지름 300mm의 유공관이 적용되고, 지선 집수관(11-2)은 직경이 150mm이므로 T-소켓(133)을 이용하여 연결한다. At this time, the main line collecting pipe 11-1 is a perforated pipe having a diameter of 300 mm is applied, and since the branch collecting pipe 11-2 has a diameter of 150 mm, it is connected using a T-
이러한 본 발명의 상기 (b) 집수관 설치 단계(S200)에는, 집수홀(131)을 통한 이물질의 유입을 방지하기 위하여 매설되는 상기 집수관(130)의 표면을 부직포(120)로 감싸도록 구성된다. In the (b) water collecting pipe installation step (S200) of the present invention, the surface of the
이때, 표면을 부직포(120)로 감싸인 상기 집수관(130)의 주변은 골재로 뒷채움하여 수직·하강하는 우수의 집수 및 배출을 용이하게 한다. At this time, the periphery of the
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조 시공방법의 상기 (c) 골재 포설 및 콘크리트 타설 단계(S300)는, 상기 설치한 집수관 상부에 골재를 포설한 후 다시 상부에 콘크리트를 타설하도록 구성된다. The step (C) of the aggregate installation and concrete pouring step (S300) of the method for constructing a tennis court floor structure having excellent vertical drainage according to the present invention is configured to pour concrete on the upper part of the installed water collection pipe after laying the aggregate again. .
이때, 상기 콘크리트 타설 단계에서는 와이어 메쉬(직경 3mm, 바깥넓이 1,800mm x 1,800mm, 안넓이 150mm x 150mm)를 매립하여 콘크리트의 균열을 방지하도록 구성된다. At this time, in the concrete pouring step, the wire mesh (diameter 3mm, outer width 1,800mm x 1,800mm, inner width 150mm x 150mm) is embedded to prevent cracking of the concrete.
이러한 본 발명의 상기 (c) 골재 포설 및 콘크리트 타설 단계(S300)에는, 상기 콘크리트층(220)을 수직으로 관통하여 골재층(210)에 도달하도록 다수 개의 배수홀(221)을 형성하는 배수홀 천공 단계(S310)를 더 포함하여 구성된다. In the (c) aggregate and concrete pouring step (S300) of the present invention, a drain hole for forming a plurality of
이때, 상기 골재층(210) 및 콘크리트층(220)은 각각 200mm 두께로 형성되어, 콘크리트 타공용 드릴(지름 20mm, 길이 200mm)을 이용하여 테니스장 전체 면에 가로·세로(500mm x 500mm) 간격을 격자 모양으로 배수홀(221)을 타공한다. (도 4 참조) At this time, the
본 발명에 따른 수직 배수성이 우수한 테니스장 바닥구조 시공방법의 상기 (d) 인조잔디매트 포설 단계(S400)는, 상기 콘크리트가 양생한 후 위에 인조잔디매트(310)를 포설하도록 구성된다. The (d) artificial turf mat installation step (S400) of the method for constructing a floor structure of a tennis court having excellent vertical drainage according to the present invention is configured to install the
이때, 상기 인조잔디매트의 파일층(311)은, PE 성분으로 길이는 20mm로 구성된다. At this time, the pile layer 311 of the artificial turf mat is composed of a PE component and has a length of 20 mm.
이러한 본 발명의 상기 (d) 인조잔디매트 포설 단계(S400)에서 상기 인조잔디매트(310)의 파일층(311)과 기포층(312) 사이에는 규사(320)를 충진하도록 구성된다. It is configured to fill the
이러한 본 발명의 상기 (d) 인조잔디매트 포설 단계(S400)에서 상기 인조잔디매트(310)는, 기포지와 부직포를 열융착 방식으로 기포층(312)을 형성함으로써, 규사(320)의 유실을 억제하고 수직 배수성이 우수하도록 구성된다. In the (d) artificial turf mat installation step (S400) of the present invention, the
이러한 본 발명에 따른 수직 배수성이 우수한 테니스장의 바닥구조는 다음과 같은 특징이 있다. The floor structure of the tennis court having excellent vertical drainage according to the present invention has the following characteristics.
먼저, 본 발명은 테니스장 전체 면에 집수관을 매설하고, 콘크리트 바닥을 천공하여 수직 배수가 이루어지도록 구성된다. First, according to the present invention, a water collecting pipe is buried in the entire surface of a tennis court, and vertical drainage is performed by perforating a concrete floor.
따라서 물 고임 현상이 나타나지 않는 운동 여건이 우수한 테니스장을 건설할 수 있다. Therefore, it is possible to construct a tennis court with excellent exercise conditions that does not cause stagnant water.
또한, 본 발명은 부직포를 열융착하여 제조되는 인조잔디매트 위에 규사를 포설하여 완성하도록 구성된다. In addition, the present invention is configured to be completed by laying the silica sand on the artificial turf mat manufactured by heat-sealing the nonwoven fabric.
따라서 배수성이 좋은 부직포는 우수만 수직 배수하고 규사는 보존함으로써, 테니스장의 기능을 완벽하게 유지하는 장점이 있다. Therefore, the nonwoven fabric with good drainage has the advantage of perfectly maintaining the function of the tennis court by vertically draining only the rainwater and preserving the silica sand.
또한, 본 발명은 수직 배수가 가능하여 테니스장의 네트에서 엔드라인까지 경사각을 적용하지 않는 평면시공이 이루어진다. In addition, since the present invention is capable of vertical drainage, flat construction is made without applying an inclination angle from the net to the end line of the tennis court.
따라서 일반적인 인조잔디 테니스장보다 코트 면의 수평 정밀도가 뛰어남으로써 경기력을 향상에 기여할 수 있는 코트를 시공할 수 있다. Therefore, it is possible to construct a court that can contribute to improving the performance by having superior horizontal precision of the court surface than a general artificial turf tennis court.
10 : 수직 배수성이 우수한 테니스장의 바닥구조
100 : 지반 및 집수관 설치층
110 : 지반(바닥면)
120 : 부직포
130 : 집수관(유공관, PE 이중벽관)
130-1 : 본선 집수관
130-2 : 지선 집수관
131 : 집수홀
132 : 배수 통로
133 : T 소켓
200 : 골재 포설 및 콘크리트 타설층
210 : 골재층
220 : 콘크리트층
221 : 배수홀
300 : 인조잔디 포설층
310 : 인조잔디매트
311 : 파일층
312 : 기포층
320 : 규사10: Tennis court floor structure with excellent vertical drainage
100: ground and water collection pipe installation layer
110: ground (floor)
120: non-woven fabric
130: water collection pipe (perforated pipe, PE double wall pipe)
130-1 : Main line collection pipe
130-2: branch line collection pipe
131: catchment hole
132: drain passage
133: T socket
200: aggregate laying and concrete pouring layer
210: aggregate layer
220: concrete layer
221: drain hole
300: artificial turf layer
310: artificial turf mat
311: file layer
312: bubble layer
320: silica
Claims (8)
(a) 상기 테니스장 전체 면의 수평을 형성하고 바닥면(110)에 집수관(130)을 매설하기 위한 홈을 형성하고 주위에 골재를 포설하는, 지반 조성 단계(S100);
(b) 상기 조성된 바닥면의 홈에 집수관(130)을 매설하는, 집수관 설치 단계(S200);
(c) 상기 설치한 집수관 상부에 골재를 포설한 후 다시 상부에 콘크리트를 타설하는, 골재 포설 및 콘크리트 타설 단계(S300);
(d) 상기 콘크리트가 양생한 후 위에 인조잔디매트를 포설하는, 인조잔디매트 포설 단계(S400);를 포함하며,
상기 (b) 집수관 설치 단계(S200)에는 본선 집수관(11-1)과 지선 집수관(11-2)을 연결하여 배수 구조를 형성하는 집수관 조립 단계(S210)를 더 포함하며,
상기 (c) 골재 포설 및 콘크리트 타설 단계(S300)에는 상기 콘크리트층(220)을 수직으로 관통하여 골재층(210)에 도달하도록 다수 개의 배수홀(221)을 천공하는 배수홀 천공 단계(S310)를 더 포함하며,
상기 (b) 집수관 설치 단계(S200)에는, 집수홀(131)을 통한 이물질의 유입을 방지하기 위하여 매설되는 상기 집수관(130)의 표면을 부직포(120)로 감싸도록 구성되며,
상기 (c) 골재 포설 및 콘크리트 타설 단계(S300)의 상기 콘크리트 타설 단계에서는 직경 3mm, 바깥넓이 1800x1,800mm, 안넓이 150x150mm인 와이어 메쉬를 매립하여 콘크리트의 균열을 방지하도록 구성되며,
상기 배수홀(221)은 테니스장 전체 면에 가로·세로 500mm x 500mm 간격의 격자 모양으로 형성되는 것을 특징으로 하는 수직 배수성이 우수한 테니스장의 바닥구조 시공방법.The ground and water collecting pipe installation layer 100 comprising the ground 110 that forms the entire surface of the tennis court horizontally, the water collecting pipe 130 buried in the ground to form a drainage passage 132, and the ground and the water collecting pipe An aggregate layer 210 spread evenly over the installation layer 100 and a concrete layer 220 poured on the aggregate layer 200, and an artificial turf mat on the poured concrete. and an artificial turf installation layer 300 for installing It is composed of a water hole 131, and the surface of the water collecting pipe 130 is configured to wrap a nonwoven fabric 120 to prevent the inflow of foreign substances through the water collecting hole 131, and the water collecting pipe 130 is the tennis court. Branch line water collecting pipe 11-2 installed side by side at regular intervals in one direction of the bottom surface 110 of In the method of constructing a floor structure of a tennis court having excellent vertical drainage, which is composed of a T-socket 133 connecting the main line water collecting pipe 11-1 and the branch line collecting pipe 11-2,
(a) forming a level of the entire surface of the tennis court, forming a groove for burying the water collecting pipe 130 in the bottom surface 110, and laying aggregates around it, a ground composition step (S100);
(b) a water collecting pipe installation step (S200) of burying the water collecting pipe 130 in the formed groove of the bottom surface;
(c) an aggregate laying and concrete pouring step (S300) of laying the aggregate on the upper part of the installed water collecting pipe and then pouring the concrete on the upper part again;
(d) installing an artificial turf mat on top after the concrete is cured, an artificial turf mat installation step (S400); includes;
The (b) water collecting pipe installation step (S200) further includes a water collecting pipe assembling step (S210) of connecting the main line water collecting pipe 11-1 and the branch line collecting pipe 11-2 to form a drainage structure,
In the (c) aggregate laying and concrete pouring step (S300), a drain hole drilling step of drilling a plurality of drain holes 221 to vertically penetrate the concrete layer 220 to reach the aggregate layer 210 (S310) further comprising,
In the (b) water collecting pipe installation step (S200), the surface of the water collecting pipe 130, which is buried in order to prevent the inflow of foreign substances through the water collecting hole 131, is covered with a nonwoven fabric 120,
In the concrete pouring step of the (c) aggregate laying and concrete pouring step (S300), a wire mesh having a diameter of 3mm, an outer width of 1800x1,800mm, and an inner width of 150x150mm is embedded to prevent cracking of the concrete,
The drain hole 221 is a floor structure construction method with excellent vertical drainage, characterized in that formed in a lattice shape at intervals of 500 mm x 500 mm across the entire surface of the tennis court.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020220051754A KR102436740B1 (en) | 2022-04-27 | 2022-04-27 | Floor structure of tennis court with excellent vertical drainage and method of floor structure construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020220051754A KR102436740B1 (en) | 2022-04-27 | 2022-04-27 | Floor structure of tennis court with excellent vertical drainage and method of floor structure construction |
Publications (1)
Publication Number | Publication Date |
---|---|
KR102436740B1 true KR102436740B1 (en) | 2022-08-26 |
Family
ID=83113477
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020220051754A KR102436740B1 (en) | 2022-04-27 | 2022-04-27 | Floor structure of tennis court with excellent vertical drainage and method of floor structure construction |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102436740B1 (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100893363B1 (en) * | 2007-04-25 | 2009-04-17 | 주식회사 세주 | Draining structure of artificial turf and Draining method of the same |
KR20110080467A (en) * | 2010-01-06 | 2011-07-13 | 김동현 | Constructing method of nature-friendly artificial grass |
KR101086495B1 (en) | 2011-04-11 | 2011-11-25 | (주)신명건설기술공사 | A constructing method of red clay concrete flooring |
KR200460322Y1 (en) * | 2009-10-28 | 2012-05-21 | 주식회사 세주 | Draining Structure using Floor Drain |
KR102264245B1 (en) | 2018-09-18 | 2021-06-14 | 주식회사 조은에스피에스 | Concrete floor finishing structure and method |
-
2022
- 2022-04-27 KR KR1020220051754A patent/KR102436740B1/en active IP Right Grant
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100893363B1 (en) * | 2007-04-25 | 2009-04-17 | 주식회사 세주 | Draining structure of artificial turf and Draining method of the same |
KR200460322Y1 (en) * | 2009-10-28 | 2012-05-21 | 주식회사 세주 | Draining Structure using Floor Drain |
KR20110080467A (en) * | 2010-01-06 | 2011-07-13 | 김동현 | Constructing method of nature-friendly artificial grass |
KR101086495B1 (en) | 2011-04-11 | 2011-11-25 | (주)신명건설기술공사 | A constructing method of red clay concrete flooring |
KR102264245B1 (en) | 2018-09-18 | 2021-06-14 | 주식회사 조은에스피에스 | Concrete floor finishing structure and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10202737B2 (en) | Free-flowing waterproofing system | |
CN109137940A (en) | A kind of novel solid drainage system suitable for loose landfill side slope | |
US8186127B1 (en) | Basement water drainage method for use with a foundation having no footing | |
KR101460374B1 (en) | Liner assembly for a sand trap | |
KR101783950B1 (en) | Drain structure for planting grass and construction method thereof | |
JP2003193543A (en) | Construction method for draining ground and member used therefor | |
US10760223B2 (en) | Method for installation of system for paver support | |
CN108086333A (en) | The control method of filling roadbed stability of slope | |
KR100902308B1 (en) | Breast Wall Structure Possessing Drain and Method for Constructing The Same | |
KR102436740B1 (en) | Floor structure of tennis court with excellent vertical drainage and method of floor structure construction | |
CN106351310B (en) | A kind of installation method that greening structure soil is used as to rainwater accumulator | |
KR101098260B1 (en) | Constructing method of nature-friendly artificial grass | |
KR101840708B1 (en) | construction method eco water way including slop side and a irrigation pipe using the method | |
KR200460322Y1 (en) | Draining Structure using Floor Drain | |
JP2007211546A (en) | Bed soil draining improving structure for lawn grass ground surface | |
CN110805047A (en) | Soil slope protection landscape structure and construction method | |
KR101900728B1 (en) | afforestation method using a slanted holder one-piece mesh | |
JP3781631B2 (en) | Planting ground | |
CN211816324U (en) | Roadbed slope protection structure | |
CN111691251A (en) | Treatment method for subgrade settlement in tropical zone | |
JPS6059230A (en) | Laying work of water collection pipe | |
CN214005295U (en) | Asphalt permeable pavement and saltpetering alkali protection integrated structure in saline-alkali soil landscape | |
KR101841506B1 (en) | Stone wall infrastructure of using natural stone | |
KR101252583B1 (en) | Drainage system | |
KR200364453Y1 (en) | Knocked-down Double filter Stone-filled drainage, rainwater pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant |