KR102398268B1 - Providing method for a distribution line monitoring system - Google Patents
Providing method for a distribution line monitoring system Download PDFInfo
- Publication number
- KR102398268B1 KR102398268B1 KR1020210176894A KR20210176894A KR102398268B1 KR 102398268 B1 KR102398268 B1 KR 102398268B1 KR 1020210176894 A KR1020210176894 A KR 1020210176894A KR 20210176894 A KR20210176894 A KR 20210176894A KR 102398268 B1 KR102398268 B1 KR 102398268B1
- Authority
- KR
- South Korea
- Prior art keywords
- buried
- photographing
- distribution line
- grounding
- monitoring system
- Prior art date
Links
- 238000009826 distribution Methods 0.000 title claims abstract description 114
- 238000012544 monitoring process Methods 0.000 title claims abstract description 73
- 238000000034 method Methods 0.000 title claims abstract description 46
- 230000005856 abnormality Effects 0.000 claims abstract description 50
- 238000002360 preparation method Methods 0.000 claims abstract description 11
- 238000010276 construction Methods 0.000 claims abstract description 8
- 238000004140 cleaning Methods 0.000 claims description 9
- 238000009434 installation Methods 0.000 claims description 7
- 238000005507 spraying Methods 0.000 claims description 5
- 238000005202 decontamination Methods 0.000 claims description 4
- 230000003588 decontaminative effect Effects 0.000 claims description 4
- 238000010257 thawing Methods 0.000 claims description 4
- 239000007788 liquid Substances 0.000 claims description 3
- 239000012530 fluid Substances 0.000 description 7
- 239000000306 component Substances 0.000 description 5
- 230000000903 blocking effect Effects 0.000 description 4
- 238000003780 insertion Methods 0.000 description 4
- 230000037431 insertion Effects 0.000 description 4
- 230000008569 process Effects 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000003384 imaging method Methods 0.000 description 3
- 239000000126 substance Substances 0.000 description 3
- 238000009423 ventilation Methods 0.000 description 3
- 238000011109 contamination Methods 0.000 description 2
- 239000008358 core component Substances 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 230000004044 response Effects 0.000 description 2
- 230000035939 shock Effects 0.000 description 2
- 230000002159 abnormal effect Effects 0.000 description 1
- 238000009933 burial Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005283 ground state Effects 0.000 description 1
- 238000007373 indentation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
- 210000001364 upper extremity Anatomy 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/08—Locating faults in cables, transmission lines, or networks
- G01R31/081—Locating faults in cables, transmission lines, or networks according to type of conductors
- G01R31/085—Locating faults in cables, transmission lines, or networks according to type of conductors in power transmission or distribution lines, e.g. overhead
-
- B08B1/04—
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B08—CLEANING
- B08B—CLEANING IN GENERAL; PREVENTION OF FOULING IN GENERAL
- B08B3/00—Cleaning by methods involving the use or presence of liquid or steam
- B08B3/02—Cleaning by the force of jets or sprays
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/08—Locating faults in cables, transmission lines, or networks
- G01R31/081—Locating faults in cables, transmission lines, or networks according to type of conductors
- G01R31/083—Locating faults in cables, transmission lines, or networks according to type of conductors in cables, e.g. underground
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/50—Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
- G01R31/52—Testing for short-circuits, leakage current or ground faults
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R31/00—Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
- G01R31/50—Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
- G01R31/56—Testing of electric apparatus
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04N—PICTORIAL COMMUNICATION, e.g. TELEVISION
- H04N7/00—Television systems
- H04N7/18—Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Multimedia (AREA)
- Signal Processing (AREA)
- Power Engineering (AREA)
- Geophysics And Detection Of Objects (AREA)
Abstract
Description
본 발명은 배전 기술 분야 중 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법에 관한 것으로서, 보다 상세하게는 공동주택의 각 단자의 배전선로에서의 접지 상태를 실시간으로 모니링함과 아울러, 배전 선로에서의 접지를 지중에서의 접촉 면적을 늘려접지 효율을 향상시킬 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템에 관한 것이다. The present invention relates to a method of providing a monitoring system for abnormality of a buried underground distribution line in the field of distribution technology, and more particularly, monitoring the grounding state in the distribution line of each terminal of an apartment house in real time, and in the distribution line It relates to an abnormality monitoring system for buried underground distribution lines that can improve the grounding efficiency by increasing the contact area in the underground of the grounding.
또한, 본 발명은 배전선로 각각의 작업 상황에 대하여 시스템 구성물의 취급, 조립, 설치, 준비 등의 과정을 실시간 관리하고 시정과 필요한 조치를 신속하게 취하여 안전하고 신뢰성이 있는 모니터링 시스템으로 운용하는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, the present invention manages the process of handling, assembly, installation, preparation, etc. of system components in real time for each work situation of distribution lines, and quickly takes corrective actions and necessary measures to operate as a safe and reliable monitoring system. An object of the present invention is to provide a method for providing an abnormality monitoring system for an underground distribution line.
일반적으로, 전력은 발전소로부터 변전소로 전송되어 여러 단계의 변압과정을 거친 후 콘크리트 전주와 같은 배전로를 따라 전주의 주상 변압기를 통해 가정으로 전달된다. In general, electric power is transmitted from a power plant to a substation, undergoes several stages of transformation, and then is delivered to a home through a pole transformer on an electric pole along a distribution path such as a concrete pole.
이때, 전주에 설치되는 배전선로에는 뇌(雷), 써지(surge) 등 이상전압에 의한 기기보호와 누전으로 인한 각종 전기 재해방지를 위하여 배전선에서의 물질확보 및 양호한 접지를 필요로 한다. At this time, in the distribution line installed on the electric pole, it is necessary to secure the material in the distribution line and to have good grounding in order to protect the equipment by abnormal voltage such as thunder and surge and to prevent various electric disasters due to short circuit.
상기한 접지는 전력이나 낙뢰로부터 인간 및 전력설비 보호 기능을 갖는다. The grounding has a function of protecting people and power equipment from electric power or lightning.
특히, 공동 주택의 각 단지에는 배전함과 같은 배전부가 설치되고, 배전 선로 또한 설치된다. In particular, a distribution unit such as a distribution box is installed in each complex of the apartment house, and a distribution line is also installed.
종래에는 각 단지의 배전부들 각각에서의 접지 상태를 실시간으로 감시할 수 없었기 때문에, 어느 하나의 단지의 배전부에서 접지 불량이 발생되는 경우, 작업자의 감전 사고가 발생되는 문제점이 있다. Conventionally, since it was not possible to monitor the grounding state in each of the power distribution units of each complex in real time, when a grounding defect occurs in the distribution unit of any one complex, there is a problem in that an electric shock accident of an operator occurs.
본 발명의 목적은, 공동주택의 각 단자의 배전선로에서의 접지 상태를 실시간으로 모니링함과 아울러, 배전 선로에서의 접지를 지중에서의 접촉 면적을 늘려 접지 효율을 향상시킬 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.An object of the present invention is to monitor the grounding state in the distribution line of each terminal of the apartment house in real time, and to increase the contact area of the grounding in the distribution line underground to improve the grounding efficiency. It is to provide a method for providing a monitoring system for abnormalities in the furnace.
또한, 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법을 구현함에 있어 각각의 상황에 대하여 작업과 시스템 구성물의 취급, 조립, 설치, 준비 등의 과정을 관리하고 실시간으로 시정 및 조치를 취하여 안전하고 신뢰성이 있는 모니터링 시스템을 적용할 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, in implementing the method of providing an abnormality monitoring system for buried underground distribution lines, it manages the processes such as handling, assembly, installation, and preparation of work and system components for each situation, and takes corrective actions and measures in real time to ensure safe and secure An object of the present invention is to provide a method for providing an abnormality monitoring system for a buried underground distribution line to which a reliable monitoring system can be applied.
또한, 매설형 지중 배전선로의 이상유무 모니터링 시스템의 운용을 실시간 관리하고 시정 및 조치를 취하며 후속적인 문제의 검증을 수행할 수 있는 데이터를 제공하는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, the method of providing an abnormality monitoring system for buried underground distribution lines provides data that manages the operation of an abnormality monitoring system for buried underground distribution lines in real time, takes corrective actions and takes corrective actions, and provides data to verify subsequent problems. will provide
또한, 모니터링 시스템의 구조적 특징상 촬영를 수행하는 수단이 다양한 조건과 환경에 대응하여 체계적이고 안정적으로 관리하여 모니터링과 관련된 동작수명을 늘리는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, it is to provide a method for monitoring the presence or absence of abnormality of a buried underground power distribution line in which the means for performing imaging is systematically and stably managed in response to various conditions and environments due to the structural characteristics of the monitoring system to increase the operational lifespan related to monitoring.
또한, 외부오염과 외부충격으로부터 모니터링 시스템의 핵심적인 구성부를 보호하여 모니터링이 제한되는 것을 억제할 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, it is to provide a method for providing a monitoring system for abnormality of a buried underground distribution line, which can prevent the monitoring from being restricted by protecting the core components of the monitoring system from external contamination and external shocks.
또한, 외부로의 환기와 온도적조건 조절 이물방출 등을 위한 외부노출과 외부로부터의 차단을 선택적으로 신속하고 용이하게 수행할 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, it is to provide a method for providing a monitoring system for abnormality of a buried underground distribution line that can selectively, quickly and easily perform external exposure and blocking from the outside for ventilation to the outside, temperature control, and release of foreign substances.
본 발명은 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법으로서, 매설형 지중 배전선로의 이상유무 모니터링 시스템이 준비현장에서 준비되는 단계; 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템이 시공현장에 설치되는 단계를 포함하며, 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법은 관리유닛에 의하여 관리되되, 상기 관리유닛은, 상기 준비현장에 설치되어 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템의 부품들이 준비되는 상황 또는 사전결합이 되는 상황을 관리하거나, 상기 시공현장에 설치되어 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법의 설치상황을 관리하며, 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법은, 공동 주택의 각 단지에 배치되며, 배전 선로를 갖는 다수의 배전부; 상기 다수의 배전부 각각의 상기 배전 선로에 탈착 가능하도록 설치되며, 상기 배전 선로를 지중에 접지시키는 다수의 접지부; 및 상기 다수의 접지부에서 상기 배전 선로와의 단선 유무를 감지하여, 접지 상태를 실시간으로 모니터링하는 접지모니터링 부를 포함하는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공한다.The present invention provides a method for monitoring the presence or absence of an abnormality of a buried underground distribution line, the method comprising the steps of: preparing an abnormality monitoring system of a buried underground distribution line at a preparation site; The method of providing an abnormality monitoring system of the buried underground distribution line includes the step of installing an abnormality monitoring system of the buried underground distribution line at a construction site, wherein the management unit is managed by a management unit, the preparation site It is installed in the underground distribution line to manage the condition in which parts of the monitoring system are prepared or pre-combined, or installed at the construction site to provide a monitoring system for abnormality of the buried underground distribution line. A method for managing an installation situation and providing a monitoring system for abnormality of the buried underground distribution line includes: a plurality of distribution units disposed in each complex of a common house and having distribution lines; a plurality of grounding units detachably installed on the distribution lines of each of the plurality of distribution units and grounding the distribution lines underground; and a grounding monitoring unit configured to detect whether the plurality of grounding units are disconnected from the distribution line and monitor the grounding state in real time.
상기와 같은 본 발명에 따르면 다음과 같은 효과가 하나 혹은 그 이상이 있다.According to the present invention as described above, there are one or more of the following effects.
본 발명은 공동주택의 각 단자의 배전선로에서의 접지 상태를 실시간으로 모니링함과 아울러, 배전 선로에서의 접지를 지중에서의 접촉 면적을 늘려 접지 효율을 향상시킬 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.The present invention monitors the grounding state in the distribution line of each terminal of the apartment house in real time, and increases the contact area of the grounding in the distribution line underground to improve the grounding efficiency. It is to provide a method for providing a presence monitoring system.
또한, 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법을 구현함에 있어 각각의 상황에 대하여 작업과 시스템 구성물의 취급, 조립, 설치, 준비 등의 과정을 관리하고 실시간으로 시정 및 조치를 취하여 안전하고 신뢰성이 있는 모니터링 시스템을 적용할 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, in implementing the method of providing an abnormality monitoring system for buried underground distribution lines, it manages the processes such as handling, assembly, installation, and preparation of work and system components for each situation, and takes corrective actions and measures in real time to ensure safe and secure An object of the present invention is to provide a method for providing an abnormality monitoring system for a buried underground distribution line to which a reliable monitoring system can be applied.
또한, 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법의 운용을 실시간 관리하고 시정 및 조치를 취하며 후속적인 문제의 검증을 수행할 수 있는 데이터를 제공하는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, an abnormality monitoring system for buried underground distribution lines that provides data for real-time management of the operation of the method of providing an abnormality monitoring system for buried underground distribution lines, taking corrective actions and taking measures, and verifying subsequent problems It is to provide a method.
또한, 모니터링 시스템의 구조적 특징상 촬영를 수행하는 수단이 다양한 조건과 환경에 대응하여 체계적이고 안정적으로 관리하여 모니터링과 관련된 동작수명을 늘리는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, it is to provide a method for monitoring the presence or absence of abnormality of a buried underground power distribution line in which the means for performing imaging is systematically and stably managed in response to various conditions and environments due to the structural characteristics of the monitoring system to increase the operational lifespan related to monitoring.
또한, 외부오염과 외부충격으로부터 모니터링 시스템의 핵심적인 구성부를 보호하여 모니터링이 제한되는 것을 억제할 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, it is to provide a method for providing a monitoring system for abnormality of a buried underground distribution line, which can prevent the monitoring from being restricted by protecting the core components of the monitoring system from external contamination and external shocks.
또한, 외부로의 환기와 온도적조건 조절 이물방출 등을 위한 외부노출과 외부로부터의 차단을 선택적으로 신속하고 용이하게 수행할 수 있는 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법를 제공하는 것이다.In addition, it is to provide a method for providing a monitoring system for abnormality of a buried underground distribution line that can selectively, quickly and easily perform external exposure and blocking from the outside for ventilation to the outside, temperature control, and release of foreign substances.
도 1은 다수의 배전부에 설치되는 본 발명의 매설형 지중 배전선로의 이상유무 모니터링 시스템을 보여주는 전체 개념도이다.
도 2는 본 발명에 따르는 매설형 지중 배전선로의 이상유무 모니터링 시스템을 보여주는 도면이다.
도 3은 접지 부재가 분리되는 상태를 보여주는 도면이다.
도 4 내지 도 5는 본 발명에 따르는 접지 부재의 구조를 보여주는 도면이다.
도 6 내지 도 12는 도 1에 따른 구성을 도시한 도면들이다.1 is an overall conceptual diagram showing an abnormality monitoring system of a buried underground power distribution line of the present invention installed in a plurality of power distribution units.
2 is a view showing an abnormality monitoring system of a buried underground distribution line according to the present invention.
3 is a view showing a state in which the grounding member is separated.
4 to 5 are views showing the structure of the grounding member according to the present invention.
6 to 12 are views illustrating a configuration according to FIG. 1 .
이하, 첨부된 도면을 참조하여 본 발명의 매설형 지중 배전선로의 이상유무 모니터링 시스템를 설명한다. Hereinafter, an abnormality monitoring system of a buried underground power distribution line of the present invention will be described with reference to the accompanying drawings.
도 1은 다수의 배전부에 설치되는 본 발명의 매설형 지중 배전선로의 이상유무 모니터링 시스템를 보여주는 전체 개념도이고, 도 2는 본 발명에 따르는 매설형 지중 배전선로의 이상유무 모니터링 시스템를 보여주는 도면이고, 도 3은 접지 부재가 분리되는 상태를 보여주는 도면이고, 도 4는 본 발명에 따르는 접지 부재의 구조를 보여주는 도면이다.1 is an overall conceptual diagram showing an abnormality monitoring system of a buried underground distribution line of the present invention installed in a plurality of distribution units, and FIG. 2 is a diagram showing an abnormality monitoring system of a buried underground distribution line according to the present invention, FIG. 3 is a view showing a state in which the grounding member is separated, and FIG. 4 is a view showing the structure of the grounding member according to the present invention.
도 1 내지 도 4를 참조 하면, 본 발명의 지중 배전선로 접지구조는 공동 주택의 각 단지에 배치되며, 배전 선로를 갖는 다수의 배전부(100)와; 상기 다수의 배전부(100) 각각의 상기 배전 선로(110)에 탈착 가능하도록 설치되며, 상기 배전 선로(110)를 지중(1)에 접지시키는 다수의 접지부(200); 및 상기 다수의 접지부(200)에서 상기배전 선로(110)와의 단선 유무를 감지하여, 접지 상태를 실시간으로 모니터링하는 접지 모니터링 부(300)로 구성된다. 상기 다수의 접지부(200) 각각은, 상기 배전 선로(110)에 전기적으로 연결되는 접지 부재(210)와, 상기 지중(1)에 고정 설치되며, 상기 접지 부재(210)가 탈착 가능하게 접속되며, 상기 접지 부재(210)를 통해 상기 배전선로를 접지시키는 접지 장치(220)와, 상기 접지 장치(220)와 상기 접지 부재(210)와의 접속 상태를 감지하는 접속 감지 수단(230)로 구성된다.1 to 4, the underground distribution line grounding structure of the present invention is disposed in each complex of the apartment house, and a plurality of
상기 접지 부재(210)는 한 쌍으로 형성된다. 한 쌍의 접지 부재(210)는 서로 맞닿아 결합된다. 결합은 볼트(미도시)를 통해 이루어진다. 상기 한 쌍의 접지 부재(210) 각각에는 연결터미널이 형성되고, 상기 연결터미널에는 배전 선로(110)의 단부가 연결된다. 따라서, 한 쌍의 접지 부재(210)가 서로 마주보도록 결합되면, 각 연결터미널은 접속된다. 상기 접지 장치(220)는, 원판 형상의 접지 몸체(221)와, 상기 접지 몸체(221)의 테두리의 하단으로부터 연장되어, 상기 지중(1)에 매립 고정되는 다수의 매립 부재(222)와, 상기 접지 몸체(221)의 상단에 형성되며, 상기 접지 부재(210)의 하단과 스크류 체결되는 접속단(223)과, 상기 접지 몸체(221)의 내부에 설치되고, 금속으로 형성되며, 일단이 스크류 체결되는 상기 접지 부재(210)의 하단과 물리적으로 접촉되고, 타단이 상기 다수의 매립부재(222)의 하단을 통해 돌출되어 상기 지중(1)에 매립되는 내부 접지 부재(224)로 구성될 수 있다. The grounding
상기 접속 감지 수단(230)은, 상기 접지 부재(210)의 하단과 상기 내부 접지 부재(224)의 상단 사이에 설치되며, 스크류 체결됨으로 인한 상기 접지 부재(210)의 하단과 상기 내부 접지 부재(224)의 상단 사이의 압력을 측정하는 압력 센서를 포함할 수 있다. 상기 내부 접지 부재(224)의 하단은, 하방으로 뾰족하게 형성되도록 콘 형상으로 형성되는 콘 몸체(224a)와, 상기 콘 몸체(224a)의 외측 둘레로부터 돌출되어, 상지 지중(1)에 매립되는 다수의 단위 접지단(224b)으로 형성된다. 또한, 도 5에 도시되는 바와 같이, 본 발명에 따르는 내부 접지 부재(224)의 하단은 모터(500)의 구동에 의해 회전되며, 상기 내부 접지 부재(224)의 하단에는 회전되는 콘 형상의 콘 몸체(224a)가 형성된다. The connection detection means 230 is installed between the lower end of the
상기 콘 몸체(224a)의 외주에는 스크류 돌기(224c)가 형성된다. 상기 내부 접지 부재(224)는, 상기 모터(500)에 의해 회전되면, 상기 지중(1)에 스크류 결합된다. A
따라서, 접지 장치(220) 자체를 지중에서의 고정력을 향상시킬 뿐만 아니라 콘 몸체가 지중에 스크류 결합됨으로써, 고정력 형성 면적 및, 접지 면적을 증가시킬 수 있다. 상기 모터(500)는 후술되는 제어기(320)의 제어 신호에 의해 구동된다. 상기 모터(500)는 내부 접지 부재(224)의 하단에 설치되고, 상기 모터(500)의 모터축(미도시)은 하방을 향하도록 배치되고, 상기 모터축에 상기 콘 몸체(224a)의 중심이 연결된다.Accordingly, the
상기 모터(500)가 구동되면, 모터축은 회전되고, 회전되는 모터축에 연결되는 콘 몸체(224a)는 회전된다. When the
상기 접지 모니터링 부(300)는, 상기 다수의 접지부(200) 각각의 상기 배전 선로(110)를 연결 및 차단하는 개폐스위치(310)와, 상기 다수의 접지부(200) 각각에서 측정되는 압력을 전송 받고, 기설정되는 기준 압력 이하를 이루는 경우, 접지 불량으로 판단하는 제어기(320)로 구성된다. The
상기 제어기(320)는, 접지 불량으로 판단되는 상기 다수의 접지부(200) 중 해당 접지부(200)에 설치되는 개폐스위치(310)를 사용하여 배전 선로를 차단한다. The
상기 접지 부재(210)는, 원봉 형상의 금속으로 형성되고, 상기 접지 부재(210)의 외면에는, 사방으로 돌출되며, 다른 배전 선로(110)와 연결되는 다수의 연결단(210a)이 형성된다. The
상기 구성을 통해, 본 발명은 공동주택의 각 단자의 배전선로에서의 접지 상태를 실시간으로 모니링함과 아울러, 배전 선로에서의 접지를 지중에서의 접촉 면적을 늘려 접지 효율을 향상시킬 수 있다.Through the above configuration, the present invention can improve the grounding efficiency by monitoring the grounding state in the distribution line of each terminal of the apartment house in real time, and by increasing the contact area of the grounding in the distribution line underground.
또한, 본 발명은, 본 발명은 접지 불량이 발생되는 해당 단지의 배전부에서의 배전 선로를 즉시 차단하여 접지불량 상태에서 관리자의 감전 사고를 미연에 효율적으로 방지할 수 있다. In addition, the present invention can effectively prevent an electric shock accident of a manager in a grounding condition in advance by immediately blocking the distribution line in the distribution section of the complex in which the grounding failure occurs.
또한, 본 발명은, 하나의 접지 부재에 별도의 연결단을 마련하여 하나의 배전 선로에서 다수의 가닥으로 분기하 여 연결단에 연결하여 접지 불량의 가능성을 낮출 수 있다. In addition, according to the present invention, by providing a separate connection end to one grounding member, branching from one distribution line into a plurality of strands and connecting to the connecting end, it is possible to reduce the possibility of grounding failure.
도 6 내지 도 12를 참조하면 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법으로서, 매설형 지중 배전선로의 이상유무 모니터링 시스템이 준비현장에서 준비되는 단계; 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템이 시공현장에 설치되는 단계를 포함하며, 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법은 관리유닛에 의하여 관리되되, 상기 관리유닛은, 상기 준비현장에 설치되어 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템의 부품들이 준비되는 상황 또는 사전결합이 되는 상황을 관리하거나, 상기 시공현장에 설치되어 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법의 설치상황을 관리한다. 6 to 12, there is provided a method for monitoring the presence or absence of an abnormality of a buried underground distribution line, the method comprising: preparing an abnormality monitoring system of a buried underground distribution line at a preparation site; The method of providing an abnormality monitoring system of the buried underground distribution line includes the step of installing an abnormality monitoring system of the buried underground distribution line at a construction site, wherein the management unit is managed by a management unit, the preparation site It is installed in the underground distribution line to manage the condition in which parts of the monitoring system are prepared or pre-combined, or installed at the construction site to provide a monitoring system for abnormality of the buried underground distribution line. Manage the installation status.
여기서 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법은, 공동 주택의 각 단지에 배치되며, 배전 선로를 갖는 다수의 배전부; 상기 다수의 배전부 각각의 상기 배전 선로에 탈착 가능하도록 설치되며, 상기 배전 선로를 지중에 접지시키는 다수의 접지부; 및 상기 다수의 접지부에서 상기 배전 선로와의 단선 유무를 감지하여, 접지 상태를 실시간으로 모니터링하는 접지모니터링 부를 포함한다.Here, the method of providing an abnormality monitoring system of the buried underground distribution line includes: a plurality of distribution units disposed in each complex of a multi-family house, and having a distribution line; a plurality of grounding units detachably installed on the distribution lines of each of the plurality of distribution units and grounding the distribution lines underground; and a ground monitoring unit configured to detect whether the plurality of ground units are disconnected from the distribution line and monitor the ground state in real time.
여기서 상기 관리유닛은, 지면(S')에 매설되는 제1매설몸체(111')와, 상기 제1매설몸체(111')와 이웃하며 지면(S')에 매설되는 제2매설몸체(112')와, 상기 제2매설몸체(112')와 이웃하며 지면(S')에 매설되는 제3매설몸체(113')와, 상기 제3매설몸체(113')와 이웃하며 지면(S')에 매설되는 제4매설몸체(114')와, 상기 제1매설몸체(111')와 상기 제2매설몸체(112')사이에 장착되는 제1장착몸체(161',162')와, 상기 제2매설몸체(112')와 상기 제3매설몸체(113')사이에 장착되는 제2장착몸체(171',172')와, 상기 제3매설몸체(113')와 상기 제4매설몸체(114')사이에 장착되는 제3장착몸체(181',182')와, 상기 제1장착몸체(161',162') 내지 상기 제3장착몸체(181',182')의 상부로 설치되는 지지패널부(121')와,, 상기 지지패널부(121')상에 설치되며 수평방향으로 회전되는 회전모듈(122')과, 상기 회전모듈(122') 둘레부 일측에 설치되는 제1상부촬영체(124')와, 상기 회전모듈(122') 둘레부 일측에 제1상부촬영체(124') 보다 낮게 설치되는 제1하부촬영체(123')를 포함하는 제1촬영모듈(123',124')을 포함한다.Here, the management unit includes a first
아울러 여기서 상기 관리유닛은, 상기 회전모듈(122') 둘레부 타측에 설치되는 제2상부촬영체(126')와, 상기 회전모듈(122') 둘레부 타측에 제2상부촬영체(126') 보다 낮게 설치되는 제2하부촬영체(125')를 포함하는 제2촬영모듈(125',126')을 포함한다. 여기서 상기 제1촬영모듈(123',124') 내지 상기 제2촬영모듈(125',126')은 상기 회전모듈(122')의 회전을 통해 둘레부를 촬영하되, 연속적인 둘레부 회전 혹은 설정 범위로의 한정된 둘레부 회전을 통해 촬영을 수행한다.In addition, the management unit includes a second upper photographing body 126' installed on the other side of the circumference of the rotation module 122', and a second upper photographing body 126' on the other side of the circumference of the
한편 상기 관리유닛은, 상기 회전모듈(122')을 매개로 상기 지지패널부(121')와 대향하도록 설치되는 상판모듈(141',142')을 더 포함하며, 상기 상판모듈(141',142')은, 내부로부터 상기 제1촬영모듈(123',124')과 마주하도록 상기 제1촬영모듈(123',124')이 위치되는 공간측을 향하여 출몰되는 제1출몰모듈(131',132')과, 내부로부터 상기 제2촬영모듈(125',126')과 마주하도록 상기 제2촬영모듈(125',126')이 위치되는 공간측을 향하여 출몰되는 제2출몰모듈(133',134')이 구비된다.Meanwhile, the management unit further includes
여기서 상기 제1출몰모듈(131',132')은 출몰을 통해 상기 제1촬영모듈(123',124')의 촬영측 대한 이물제거, 오염제거, 습기제거, 성에제거를 위한 촬영측을 클리닝하며 상기 제2출몰모듈(133',134')은 출몰을 통해 상기 제2촬영모듈(125',126')의 촬영측에 대한 이물제거, 오염제거, 습기제거, 성에제거를 위한 촬영측을 클리닝한다.Here, the first haunting modules 131' and 132' clean the shooting side for removing foreign substances, decontamination, moisture removal, and defrosting on the shooting side of the first shooting modules 123' and 124' through the haunting and subsidence. And the second appearance module (133', 134') is a photographing side for removing foreign matter, decontamination, moisture removal, and defrosting for the photographing side of the second photographing module (125', 126') through the appearance. Clean.
한편 상기 제1출몰모듈(131',132')은, 상기 상판모듈(141',142')에서 하부로 하강되는 제1하강몸체(131')와, 상기 제1하강몸체(131')와 함께 하강되며 상기 제1하강몸체(131')에서 상기 제1촬영모듈(123',124')에 접촉하여 회전방식 및 세정액 분사 중 적어도 어느 하나의 방식으로 클리닝을 수행하는 제1클리닝체(132')를 포함한다.On the other hand, the first descending module 131', 132' includes a first descending body 131' that descends downward from the
상기 제2출몰모듈(133',134')은, 상기 상판모듈(141',142')에서 하부로 하강되는 제2하강몸체(133')와, 상기 제2하강몸체(133')에서 상기 제2촬영모듈(125',126')에 접촉하여 회전방식 및 세정액 분사 중 적어도 어느 하나의 방식으로 클리닝을 수행하는 제2클리닝체(134')를 포함한다.The second protruding modules 133' and 134' include a second descending body 133' that descends downward from the
아울러 상기 상판모듈(141',142')은, 상기 회점모듈과 접하는 중앙패널부(141')와, 상기 중앙패널부(141')의 일측으로 구비되며 하부로 상기 제1출몰모듈(131',132')이 출몰되는 제1구동패널부(142')와, 상기 중앙패널부(141')의 타측으로 구비되며 하부로 상기 제2출몰모듈(133',134')이 출몰되는 제2구동패널부(143')를 포함한다.In addition, the
이러한 상기 제1구동패널부(142')는 상기 제1촬영모듈(123',124')이 위치되는 제1공간을 외부로부터 차단하여 보관되도록 하는 제1셔터패널(151')이 구비되며, 상기 제2구동패널부(143')는 상기 제2촬영모듈(125',126')이 위치되는 제2공간을 외부로부터 차단하여 보관되도록 하는 제2셔터패널(152')이 구비된다.The first
상기 제1구동패널부(142')와 상기 제2구동패널부(143')는 상기 중앙패널부(141')의 양측에서 각각 틸트모드로 동작이 가능하여 상기 제1촬영모듈(123',124')과 상기 제2촬영모듈(125',126')을 덮어 보호상태로 만들거나 또는 상기 제1촬영모듈(123',124')과 상기 제2촬영모듈(125',126')을 노출시켜 외부 환기와, 온도조절, 습도조절이 가능하도록 한다.The first
상기 제1장착몸체(161',162')는, 상기 제1매설몸체(111')와 상기 제2매설몸체(112')에 삽입되는 제1삽입상태로 구비되는 제1삽입체(162')와, 상기 제1삽입체(162')와 연동되며 상기 지지패널부(121')에 설치되는 제1지지구동체(161')를 포함한다. 상기 제2장착몸체(171',172')는, 상기 제2매설몸체(112')와 상기 제3매설몸체(113')에 삽입되는 제2삽입상태로 구비되는 제2삽입체(172')와, 상기 제2삽입체(172')와 연동되며 상기 지지패널부(121')에 설치되는 제2지지구동체(171')를 포함한다.The
이때 상기 제3장착몸체(181',182')는, 상기 제3매설몸체(113')와 상기 제4매설몸체(114')에 삽입되는 제3삽입상태로 구비되는 제3삽입체(182')와, 상기 제3삽입체(182')와 연동되며 상기 지지패널부(121')에 설치되는 제3지지구동체(181')를 포함한다. 상기 제1지지구동체(161')는 상기 제1삽입상태에서 상기 제1삽입체(162')를 모터회전방식으로 축회전시키며, 상기 제2지지구동체(171')는 상기 제2삽입상태에서 상기 제2삽입체(172')를 모터회전방식으로 축회전시키며, 상기 제3지지구동체(181')는 상기 제3삽입상태에서 상기 제3삽입체(182')를 모터회전방식으로 축회전시킨다.At this time, the third mounting body 181', 182' is a
아울러 상기 제1매설몸체(111')는 상기 제1삽입상태의 상기 제1삽입체(162')로 삽입장착되는 제1메인진입체(181')가 구비되며, 상기 제2매설몸체(112')는 상기 제1삽입상태의 상기 제1삽입체(162')로 삽입장착되는 제1서브진입체(191,192,193,194')가 구비된다. 상기 제2매설몸체(112')는 상기 제2삽입상태의 상기 제2삽입체(172')로 삽입장착되는 제2메인진입체(201')가 구비되며, 상기 제2매설몸체(112')는 상기 제2삽입상태의 상기 제2삽입체(172')로 삽입장착되는 제2서브진입체(211,212,213,214')가 구비된다.In addition, the first embedded
여기서 상기 제3매설몸체(113')는 상기 제3삽입상태의 상기 제3삽입체(182')로 삽입장착되는 제3메인진입체(221')가 구비되며, 상기 제3매설몸체(113')는 상기 제3삽입상태의 상기 제3삽입체(182')로 삽입장착되는 제3서브진입체(231,232,233')가 구비되며, 상기 제1메인진입체(181')는 상하간에 다수로 구비되며, 상기 제1서브진입체(191,192,193,194')는 상기 제1메인진입체(181')를 내부에 교호적으로 수용하도록 상하간에 다수로 구비된다.Here, the third
상기 제2메인진입체(201')는 상하간에 다수로 구비되며, 상기 제2서브진입체(211,212,213,214')는 상기 제2메인진입체(201')를 내부에 교호적으로 수용하도록 상하간에 다수로 구비되며, 상기 제3메인진입체(221')는 상하간에 다수로 구비되며, 상기 제3서브진입체(231,232,233')는 상기 제3메인진입체(221')를 내부에 교호적으로 수용하도록 상하간에 다수로 구비된다.The second main entry body 201' is provided in plurality between the upper and lower sides, and the second
상기 제1메인진입체(181')와 상기 제1서브진입체(191,192,193,194')는 상호간에 연동고정을 통해 상기 제1삽입체(162')에 대한 고정력을 가하는 제1동작모드로 동작되며, 상기 제2메인진입체(201')와 상기 제2서브진입체(211,212,213,214')는 상호간에 연동고정을 통해 상기 제2삽입체(172')에 대한 고정력을 가하는 제2동작모드로 동작되며, 상기 제3메인진입체(221')와 상기 제2서브진입체(211,212,213,214')는 상호간에 연동고정을 통해 상기 제3삽입체(182')에 대한 고정력을 가하는 제3동작모드로 동작된다.The first main entry body 181' and the first
아울러 상기 제1매설몸체(111'), 상기 제2매설몸체(112'), 상기 제3매설몸체(113') 및 상기 제4매설몸체(114')가 설치되는 하부의 하단몸체부(310')를 더 포함하며, 상기 하단몸쳄부상에서 상기 상기 제1동작모드 내지 상기 제4매설모드 상태인 상기 제1매설몸체(111') 내지 상기 제4매설몸체(114')를 각각 설정 범위로 내부로 하강시켜 상기 제1동작모드 내지 상기 제4동작모드에 의한 고정력을 강화시키는 강화모드로 동작된다.In addition, the lower
상기 제1서브진입체(191,192,193,194')는 상기 제2매설몸체(112')상에 위치되는 제1-1영역부(1911,1921,1931,1941')와, 상기 제2매설몸체(112')상에 위치되며 상기 제1메인진입체(181')가 진입하여 마주하게 되는 제1-2영역부(1912',1922',1932',1942')을 포함한다. 상기 제2서브진입체(211,212,213,214')는 상기 제3매설몸체(113')상에 위치되는 제2-1영역부(2111,2121,2131,2141')와, 상기 제3매설몸체(113')상에 위치되며 상기 제2메인진입체(201')가 진입하여 마주하게 되는 제2-2영역부(2112',2122',2132',2142')을 포함한다.The first
아울러 상기 제3서브진입체(231,232,233')는 상기 제4매설몸체(114')상에 위치되는 제3-1영역부(2311,2321,2331,2341')와, 상기 제4매설몸체(114')상에 위치되며 상기 제3메인진입체(221')가 진입하여 마주하게 되는 제3-2영역부(2312',2322',2332',2342')를 포함한다.In addition, the third sub-entry body (231,232,233') includes a 3-1 region part (2311,2321,2331,2341') positioned on the fourth embedded body 114', and the fourth embedded
상기 제1-2영역부(1912',1922',1932',1942'), 상기 제2-2영역부(2112',2122',2132',2142') 및 상기 제3-2영역부(2312',2322',2332',2342')는 기 설정된 수평길이의 규격으로 구비된다. 상기 제1-2영역부(1912',1922',1932',1942'), 상기 제2-2영역부(2112',2122',2132',2142') 및 상기 제3-2영역부(2312',2322',2332',2342')는 상기 제1메인진입체(181')가 상기 수평길이의 규격 내에 설정된 범위로 진입되는지 여부를 감지하여 외부로 상태정보를 송신하며, 상기 제1동작모드 내지 상기 제3동작모드, 상기 강화모드는, 상기 제1-2영역부(1912',1922',1932',1942'), 상기 제2-2영역부(2112',2122',2132',2142') 및 상기 제3-2영역부(2312',2322',2332',2342')는 상기 상태정보가 기설정된 기준을 만족하는 경우에 한하여 동작이 수행이 가능하다.The first-2
상기 하단몸체부(310') 일측에 구비되는 제1몸체패널(411')과, 상기 제1몸체패널(411')의 상부로 상하이동가능하게 구비되는 제1연장몸체패널(412')과, 상기 제1몸체패널(411')의 내측에 구비되오 온도조절을 위한 유체를 분사하는 제1온도가변부(413')와, 상기 하단몸체부(310') 일측에 구비되는 제2몸체패널(511')과, 상기 제2몸체패널(511')의 상부로 상하이동가능하게 구비되는 제2연장몸체패널(512')과, 상기 제2몸체패널(511')의 내측에 구비되오 온도조절을 위한 유체를 분사하는 제2온도가변부(513')를 더 포함한다.A
한편 상기 제1연장몸체패널(412')과 상기 제2연장몸체패널(512') 사이에는 덮개패널(611')이 구비되어 하부로 상기 상판모듈(141',142')을 수용하도록 구비되며, 상기 제1연장몸체패널(412')과 상기 제2연장몸체패널(512')은, 상기 제1온도가변부(413')와 상기 제2온도가변부(513')의 유체분사가 이루어지는 과정에서 상기 제1온도가변부(413')와 상기 제2온도가변부(513')의 유체분사가 되는 공간 체적을 조절하도록 상하 이동이 이루어지도록 한다.Meanwhile, a
상기 덮개패널(611')은, 하부에 출몰가능한 다수의 서브유체분사모듈(612,613')이 구비되어 상기 관리유닛의 온도를 2차적으로 조절하도록하며, 상기 제1연장몸체패널(412')과 상기 제2연장몸체패널(512') 사이에서 축회전하여 상기 서브유체분사모듈(612,613')이 축회전에 기반하여 주기적으로 상유체를 분사 가능하도록 한다.The
아울러 상기 제1연장몸체패널(412')에는 제1상부이동체(415')와, 상기 제1상부이동체(415')와 상기 상기 덮개패널(611')을 사이에두고 하부에 위치되는 제1하부이동체(414')가 구비되며, 상기 제1상부이동체(415')와 상기 제1하부이동체(414')는 상기 덮개패널(611')을 향하여 이동하여 가압고정하거나, 상기 제1상부이동체(415')와 상기 제1하부이동체(414')는 상기 덮개패널(611')로부터 멀어지도록 이동하여 가압고정을 해제한다.In addition, the first extended body panel 412' has a first upper movable body 415', and a first positioned lower with the first upper movable body 415' and the cover panel 611' interposed therebetween. A lower movable body 414' is provided, and the first upper movable body 415' and the first lower movable body 414' move toward the cover panel 611' to press and fix, or the first upper
여기서 상기 제2연장몸체패널(512')에는 제2상부이동체(515')와, 상기 제2상부이동체(515')와 상기 상기 덮개패널(611')을 사이에두고 하부에 위치되는 제2하부이동체(514')가 구비되며, 상기 제2상부이동체(515')와 상기 제2하부이동체(514')는 상기 덮개패널(611')을 향하여 이동하여 가압고정하거나, 상기 제2상부이동체(515')와 상기 제2하부이동체(514')는 상기 덮개패널(611')로부터 멀어지도록 이동하여 가압고정을 해제한다. 전술한 관리유닛은 지면 혹은 그에 준하는 기저부 상에서 용접 매설, 매립, 볼트나사, 삽입 등 다양한 공지 방식을 기반으로 촬영을 위한 대상부 주변에 설치되면 족하다.Here, the second extension body panel 512' includes a second upper movable body 515', and a second positioned lower with the second upper movable body 515' and the cover panel 611' interposed therebetween. A lower movable body 514' is provided, and the second upper movable body 515' and the second lower movable body 514' move toward the cover panel 611' and press and fix, or the second upper movable body 515' and the second lower movable body 514' are moved away from the cover panel 611' to release the pressure fixing. It is sufficient if the above-mentioned management unit is installed around the target part for shooting based on various known methods such as welding burial, embedding, bolt screw, insertion, etc. on the ground or an equivalent base.
이상에서 전술한 물리적 구성들의 구동방식은 모터, 엑츄에이터 등을 기반으로 전후유동, 회전이동이 이루어지며 각 구성부의 형상과 크기는 설치 현장과 구현하고자하는 자재들에 따라 다양하게 선택되어 구비될 수 있다. 본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 본 기술 분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 다른 실시예가 가능하다는 점을 이해할 것이다. 따라서, 본 발명의 진정한 기술적 보호 범위는 첨부된 특허청구범위의 기술적 사상에 의하여 정해져야 할 것이다.The driving method of the physical components described above is based on a motor, an actuator, etc., and the forward and backward movement and rotational movement are made, and the shape and size of each component can be variously selected and provided according to the installation site and materials to be implemented. . Although the present invention has been described with reference to the embodiment shown in the drawings, which is merely exemplary, it will be understood by those skilled in the art that various modifications and equivalent other embodiments are possible therefrom. Accordingly, the true technical protection scope of the present invention should be determined by the technical spirit of the appended claims.
100 : 배전부
200 : 접지부
300 : 접지 모니터링 부100: distribution unit
200: ground part
300: ground monitoring unit
Claims (2)
매설형 지중 배전선로의 이상유무 모니터링 시스템이 준비현장에서 준비되는 단계; 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템이 시공현장에 설치되는 단계를 포함하며,
매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법은 관리유닛에 의하여 관리되되,
상기 관리유닛은,
상기 준비현장에 설치되어 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템의 부품들이 준비되는 상황 또는 사전결합이 되는 상황을 관리하거나, 상기 시공현장에 설치되어 상기 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법의 설치상황을 관리하며,
상기 매설형 지중 배전선로의 이상유무 모니터링 시스템은,
공동 주택의 각 단지에 배치되며, 배전 선로를 갖는 다수의 배전부; 상기 다수의 배전부 각각의 상기 배전 선로에 탈착 가능하도록 설치되며, 상기 배전 선로를 지중에 접지시키는 다수의 접지부; 및 상기 다수의 접지부에서 상기 배전 선로와의 단선 유무를 감지하여, 접지 상태를 실시간으로 모니터링하는 접지모니터링 부를 포함하되,
상기 관리유닛은,
지면(S')에 매설되는 제1매설몸체(111')와, 상기 제1매설몸체(111')와 이웃하며 지면(S')에 매설되는 제2매설몸체(112')와, 상기 제2매설몸체(112')와 이웃하며 지면(S')에 매설되는 제3매설몸체(113')와, 상기 제3매설몸체(113')와 이웃하며 지면(S')에 매설되는 제4매설몸체(114')와, 상기 제1매설몸체(111')와 상기 제2매설몸체(112')사이에 장착되는 제1장착몸체(161',162')와, 상기 제2매설몸체(112')와 상기 제3매설몸체(113')사이에 장착되는 제2장착몸체(171',172')와, 상기 제3매설몸체(113')와 상기 제4매설몸체(114')사이에 장착되는 제3장착몸체(181',182')와, 상기 제1장착몸체(161',162') 내지 상기 제3장착몸체(181',182')의 상부로 설치되는 지지패널부(121')와, 상기 지지패널부(121')상에 설치되며 수평방향으로 회전되는 회전모듈(122')과, 상기 회전모듈(122') 둘레부 일측에 설치되는 제1상부촬영체(124')와, 상기 회전모듈(122') 둘레부 일측에 제1상부촬영체(124') 보다 낮게 설치되는 제1하부촬영체(123')를 포함하는 제1촬영모듈(123',124')을 포함하고,
상기 관리유닛은,
상기 회전모듈(122') 둘레부 타측에 설치되는 제2상부촬영체(126')와, 상기 회전모듈(122') 둘레부 타측에 제2상부촬영체(126') 보다 낮게 설치되는 제2하부촬영체(125')를 포함하는 제2촬영모듈(125',126')을 포함한다. 여기서 상기 제1촬영모듈(123',124') 내지 상기 제2촬영모듈(125',126')은 상기 회전모듈(122')의 회전을 통해 둘레부를 촬영하되, 연속적인 둘레부 회전 혹은 설정 범위로의 한정된 둘레부 회전을 통해 촬영을 수행하며,
상기 관리유닛은,
상기 회전모듈(122')을 매개로 상기 지지패널부(121')와 대향하도록 설치되는 상판모듈(141',142')을 더 포함하며, 상기 상판모듈(141',142')은, 내부로부터 상기 제1촬영모듈(123',124')과 마주하도록 상기 제1촬영모듈(123',124')이 위치되는 공간측을 향하여 출몰되는 제1출몰모듈(131',132')과, 내부로부터 상기 제2촬영모듈(125',126')과 마주하도록 상기 제2촬영모듈(125',126')이 위치되는 공간측을 향하여 출몰되는 제2출몰모듈(133',134')이 구비되고,
상기 제1출몰모듈(131',132')은 출몰을 통해 상기 제1촬영모듈(123',124')의 촬영측 대한 이물제거, 오염제거, 습기제거, 성에제거를 위한 촬영측을 클리닝하며
상기 제2출몰모듈(133',134')은 출몰을 통해 상기 제2촬영모듈(125',126')의 촬영측에 대한 이물제거, 오염제거, 습기제거, 성에제거를 위한 촬영측을 클리닝하고,
상기 제1출몰모듈(131',132')은, 상기 상판모듈(141',142')에서 하부로 하강되는 제1하강몸체(131')와, 상기 제1하강몸체(131')와 함께 하강되며 상기 제1하강몸체(131')에서 상기 제1촬영모듈(123',124')에 접촉하여 회전방식 및 세정액 분사 중 적어도 어느 하나의 방식으로 클리닝을 수행하는 제1클리닝체(132')를 포함하는, 매설형 지중 배전선로의 이상유무 모니터링 시스템 제공방법A method of providing a monitoring system for abnormality of a buried underground distribution line, the method comprising:
A step in which the abnormality monitoring system of the buried underground distribution line is prepared at the preparation site; Including the step of installing an abnormality monitoring system of the buried underground power distribution line at the construction site,
The method of providing an abnormality monitoring system for a buried underground distribution line is managed by the management unit,
The management unit is
Installed at the preparation site to manage the situation in which parts of the buried underground distribution line abnormality monitoring system are prepared or pre-combined, or installed at the construction site to monitor the abnormality of the buried underground distribution line Manage the installation status of the provision method,
The abnormality monitoring system of the buried underground distribution line,
a plurality of distribution units disposed in each complex of the common house and having distribution lines; a plurality of grounding units detachably installed on the distribution lines of each of the plurality of distribution units and grounding the distribution lines underground; and a grounding monitoring unit configured to detect the presence or absence of a disconnection with the distribution line in the plurality of grounding units and monitor the grounding state in real time,
The management unit is
A first buried body 111 ' to be embedded in the ground (S'), and a second buried body 112' which is adjacent to the first buried body 111' and is buried in the ground (S'), and the first 2, adjacent to the buried body 112' and a third buried body 113' buried in the ground (S'), and a fourth adjacent to the third buried body 113' and buried in the ground (S') The buried body 114 ′, the first mounting body 161 ′, 162 ′ mounted between the first buried body 111 ′ and the second buried body 112 ′, and the second buried body ( 112') and the second mounting body 171', 172' mounted between the third buried body 113', and the third buried body 113' and the fourth buried body 114'. A third mounting body (181', 182') mounted on the, and a support panel part ( 121'), a rotation module 122' installed on the support panel part 121' and rotated in the horizontal direction, and a first upper photographing body 124 installed on one side of the circumference of the rotation module 122'. ') and the first photographing module 123', 124' including a first lower photographing body 123' installed lower than the first upper photographing body 124' on one side of the circumference of the rotation module 122'. ), including
The management unit is
A second upper photographing body 126' installed on the other side of the circumference of the rotation module 122', and a second installed lower than the second upper photographing body 126' on the other side of the circumference of the rotation module 122' and second photographing modules 125' and 126' including a lower photographing body 125'. Here, the first photographing module (123', 124') to the second photographing module (125', 126') take pictures of the periphery through the rotation of the rotation module 122', but continuous rotation or setting of the periphery Filming is performed through a limited perimeter rotation into the range,
The management unit is
It further includes upper plate modules 141' and 142' installed to face the support panel part 121' via the rotation module 122', wherein the upper plate modules 141' and 142' are internal and first invading modules (131', 132') that protrude toward the space side in which the first photographing modules (123', 124') are located so as to face the first photographing modules (123', 124'); The second invading modules 133' and 134' that protrude toward the space where the second photographing modules 125', 126' are located so as to face the second photographing modules 125' and 126' from the inside provided,
The first appearance module (131', 132') cleans the photographing side for removing foreign matter, decontamination, moisture removal, and defrosting for the photographing side of the first photographing module (123', 124') through the appearance, and
The second appearance module (133', 134') cleans the photographing side for removing foreign matter, decontamination, moisture removal, and defrosting on the photographing side of the second photographing module (125', 126') through the appearance and removal. do,
The first protruding modules 131' and 132' include a first descending body 131' that descends downward from the upper plate modules 141' and 142', and the first descending body 131' together with A first cleaning body 132' that descends and contacts the first photographing modules 123' and 124' from the first descending body 131' to perform cleaning by at least one of a rotating method and a cleaning liquid spraying method. ), including a method of providing a monitoring system for abnormalities in buried underground distribution lines
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020210176894A KR102398268B1 (en) | 2021-12-10 | 2021-12-10 | Providing method for a distribution line monitoring system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020210176894A KR102398268B1 (en) | 2021-12-10 | 2021-12-10 | Providing method for a distribution line monitoring system |
Publications (1)
Publication Number | Publication Date |
---|---|
KR102398268B1 true KR102398268B1 (en) | 2022-05-17 |
Family
ID=81803401
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020210176894A KR102398268B1 (en) | 2021-12-10 | 2021-12-10 | Providing method for a distribution line monitoring system |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102398268B1 (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101584589B1 (en) * | 2015-09-16 | 2016-01-13 | (주)케이디엔지니어링건축사사무소 | Grounding monitoring apparatus of power line |
KR20200038210A (en) * | 2020-03-25 | 2020-04-10 | 인피니티에너지주식회사 | Solar module panel cleaning apparatus |
KR102300163B1 (en) * | 2021-03-03 | 2021-09-10 | 주식회사 엠피코씨엠 | System for monitoring electric equipment having distribution line between utility pole by using drone |
KR20210148666A (en) | 2020-06-01 | 2021-12-08 | 한국전력공사 | Control apparatus for interlocking on distribution lines and method thereof |
-
2021
- 2021-12-10 KR KR1020210176894A patent/KR102398268B1/en active IP Right Grant
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101584589B1 (en) * | 2015-09-16 | 2016-01-13 | (주)케이디엔지니어링건축사사무소 | Grounding monitoring apparatus of power line |
KR20200038210A (en) * | 2020-03-25 | 2020-04-10 | 인피니티에너지주식회사 | Solar module panel cleaning apparatus |
KR20210148666A (en) | 2020-06-01 | 2021-12-08 | 한국전력공사 | Control apparatus for interlocking on distribution lines and method thereof |
KR102300163B1 (en) * | 2021-03-03 | 2021-09-10 | 주식회사 엠피코씨엠 | System for monitoring electric equipment having distribution line between utility pole by using drone |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102408033B1 (en) | Distribution Line Monitoring System | |
JP5855772B2 (en) | Manual underground underground electrical equipment container system | |
KR102221709B1 (en) | Integrated management system of distribution line | |
KR101170680B1 (en) | A temperature and humidity control system adjusted automatic | |
US9608500B2 (en) | Portable generator system for providing temporary power to an electrical-distribution system | |
KR101943372B1 (en) | Circuit breaker for fault section of distribution line | |
KR101584589B1 (en) | Grounding monitoring apparatus of power line | |
KR102398268B1 (en) | Providing method for a distribution line monitoring system | |
KR102343548B1 (en) | Prevention of electric shock accident system and construction method thereof | |
KR102437261B1 (en) | Cable sag prevention system for underground distribution | |
KR102465128B1 (en) | Providing method for a distribution line fault recovery system | |
KR102484585B1 (en) | Distribution line leakage protection system | |
KR102459178B1 (en) | Providing method for a cable connection device for distribution lines | |
CN107958578A (en) | A kind of energy management system alarm linkage method | |
KR102459355B1 (en) | Track insulator system | |
KR101645226B1 (en) | Lightning counter system using earthing terminal box | |
KR100959896B1 (en) | Security unit for a ground wire | |
KR102484584B1 (en) | Distribution line monitoring system | |
KR102385883B1 (en) | Distribution cable short circuit prevention system | |
KR101796310B1 (en) | Remote monitoring apparatus of distribution line | |
KR102247225B1 (en) | System for realtime remote diagnosing underground power distribution line | |
KR102266534B1 (en) | Distribution cable connection system for underground power distribution | |
KR102400301B1 (en) | Distribution line abnormality monitoring system | |
KR102474570B1 (en) | providing method for a distribution box | |
KR102656856B1 (en) | Power distribution management system linked to artificial intelligence |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant |