KR102171437B1 - Construction method of panel for pedestrian block - Google Patents

Construction method of panel for pedestrian block Download PDF

Info

Publication number
KR102171437B1
KR102171437B1 KR1020200053346A KR20200053346A KR102171437B1 KR 102171437 B1 KR102171437 B1 KR 102171437B1 KR 1020200053346 A KR1020200053346 A KR 1020200053346A KR 20200053346 A KR20200053346 A KR 20200053346A KR 102171437 B1 KR102171437 B1 KR 102171437B1
Authority
KR
South Korea
Prior art keywords
sidewalk block
tunnel structure
footwalk
blocks
segment
Prior art date
Application number
KR1020200053346A
Other languages
Korean (ko)
Inventor
김연환
안준규
Original Assignee
극동메이저 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 극동메이저 주식회사 filed Critical 극동메이저 주식회사
Priority to KR1020200053346A priority Critical patent/KR102171437B1/en
Application granted granted Critical
Publication of KR102171437B1 publication Critical patent/KR102171437B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to a construction method of footwalk blocks in a tunnel structure, and more specifically, to a construction method of footwalk blocks in a tunnel structure, which is able to easily install pre-fabricated footwalk blocks on a segment floor unit in the tunnel structure, and omit cumbersome conventional processes of installing formworks for constructing concrete for footwalks, installing an apparatus for transferring ready-mixed concrete, placing the ready-mixed concrete, etc. According to the present invention, the construction method of footwalk blocks in a tunnel structure, in a construction method of footwalk blocks in a tunnel structure for continuously constructing the footwalk blocks, which are made of concrete materials having a certain thickness in a plate shape to be used for the footwalks in a tunnel structure, and of which both cross-sections are formed to be curved surfaces corresponding to both sides of the segment (1) floor unit, on the floor unit in the tunnel structure, comprises: a step (S10) of installing an I-beam (20) of a certain length on a segment (1) ceiling unit, and installing footwalk block elevation/lowering members (30) which are movable forward and backward along the I-beam (20); a step of (S20) of removing slime at a position of construction of footwalk blocks (10); a step (S30) of installing a plurality of brackets (11) by distancing for a certain length on both sides of the segment floor unit of the position of construction of the footwalk blocks (10); and a step (S40) of settling the footwalk blocks (10) on an upper surface of the bracket (11) by using the footwalk blocks elevation/lowering members (30), and constructing the footwalk blocks (10).

Description

터널 구조물내 보도판블록의 시공공법{Construction method of panel for pedestrian block}Construction method of panel for pedestrian block

본 발명은 터널 구조물내 보도판블록의 시공공법에 관한 것으로, 더욱 상세히는 미리 제작된 보도판블록을 터널 구조물내부의 세그먼트 바닥부에 손쉽게 설치하여 종래의 보도용 콘크리트를 시공하기 위한 거푸집 설치, 레미콘 압송을 위한 장치 설치, 레미콘 타설 등의 번거로운 공정이 생략될 수 있는 터널 구조물내 보도판블록의 시공공법에 관한 것이다.The present invention relates to a construction method of a sidewalk block in a tunnel structure, and in more detail, a prefabricated sidewalk block is easily installed on the segment floor inside a tunnel structure to install a formwork for constructing conventional sidewalk concrete, ready-mixed concrete. It relates to a construction method of a sidewalk block in a tunnel structure in which cumbersome processes such as installation of a device for pressure feeding and placing of ready-mixed concrete can be omitted.

일반적으로, 터널은 도로, 철도, 수로 등을 통하게 하기 위해 땅속을 뚫은 통로를 말하며 용도에 따라 철도, 도로, 수로, 광산 터널로 나뉘고 터널 장소에 따라 산악, 시가, 수저 터널로 나뉘는데 현재는 장대한 터널이나 해저 터널도 건설되고 있다.In general, a tunnel refers to a passage through the ground in order to pass through roads, railroads, waterways, etc., and is divided into railroad, road, waterway, and mine tunnels according to the purpose, and is divided into mountain, street, and water tunnels depending on the tunnel location. Tunnels and submarine tunnels are also being built.

특히, 최근에는 복잡한 건물들과 노상구조물 등에 의해서 간섭을 받거나 미관을 저해하는 문제를 해소하기 위해서 전기케이블을 지하로 매설하기 위해서 터널, 즉 전력구가 이용되기도 한다.In particular, in recent years, tunnels, that is, electric power outlets, are sometimes used to bury electric cables underground in order to solve the problem of being interfered with or impeding aesthetics by complex buildings and road structures.

터널을 시공함에 있어 TBM 공법이 널리 사용되고 있는데, TBM(Tunnel Boring machine)이란 암반을 압쇄 굴착하는 터널 굴착기로서 다수의 디스크 커터를 전면에 장착한 커터헤드를 회전시켜 굴진 등의 작업을 연속으로 행하는 장치를 의미하고, TBM 공법이란 TBM을 이용하여 암반을 압쇄하거나 절삭하여 굴착하는 기계식 굴착공법을 의미한다.The TBM method is widely used in tunnel construction, and TBM (Tunnel Boring machine) is a tunnel excavator that crushes and excavates rock mass. It is a device that continuously performs excavation and other operations by rotating the cutter head equipped with a large number of disk cutters. Means, and the TBM method refers to a mechanical excavation method in which rock mass is crushed or cut and excavated using TBM.

최근에는 커터헤드가 전방으로 굴착해 나감과 동시에 커터헤드의 후방에서는 굴착면에 프리캐스트 콘크리트 세그먼트(precast concrete segment)를 기계적으로 즉시 설치함으로써 터널이 완성되는 공법이 사용되고 있다.Recently, a method of completing a tunnel by mechanically immediately installing a precast concrete segment on the excavation surface at the rear of the cutter head has been used while the cutter head excavates forward.

한편, 이러한 터널을 시공함에 있어서 작업자가 보행할 수 있고 누수되는 지하수 등이 배출될 수 있는 배수구 내지 배수로를 구비한 보도의 설치가 반드시 필요하다.On the other hand, in constructing such a tunnel, it is necessary to install a sidewalk provided with a drain or a drainage passage through which a worker can walk and discharge leaked groundwater.

이에, 기존에는 터널내 보도 설치를 위해서 현장타설공법이 널리 사용되었다. 그런데, 현장타설공법에 의할 경우 터널 내부의 하부에 유공관을 설치하고 그 위에 쇄석 및 콘크리트를 채운 후 일정한 양생기간을 거쳐 보도를 완성하였고, 콘크리트를 몰드를 성형하여 보도의 상부에 배수로를 확보하였다.Therefore, in the past, the cast-in-place method was widely used to install sidewalks in tunnels. However, according to the on-site casting method, a perforated pipe was installed in the lower part of the tunnel, crushed stone and concrete were filled on it, and the sidewalk was completed through a certain curing period, and a concrete mold was formed to secure a drainage passage at the top of the sidewalk. .

그러나 이러한 현장타설공법에 의할 경우 터널 내로 쇄석과 유공관을 운반하여 보도의 하부에 쇄석과 유공관을 설치하고 레미콘 운반, 콘크리트 타설과 일정시간 양생시간을 거친 후 보도의 상부에 별도의 배수로를 마련하여야 하므로 보도 단면의 두께가 두꺼워지며, 이에 의하여 자재비 내비 시공비가 증가되고 공기가 길어지는 등의 문제가 있다.However, according to this on-site casting method, crushed stone and perforated pipes must be transported into the tunnel to install crushed stone and perforated pipes at the bottom of the sidewalk, transport ready-mixed concrete, concrete pouring and curing for a certain period of time, and then a separate drainage channel must be provided at the top of the sidewalk. Therefore, the thickness of the cross section of the sidewalk becomes thick, thereby increasing the material cost, construction cost, and lengthening the construction period.

(특허문헌 0001) 국내등록특허 제10-0643124호(2006.10.31.등록) (Patent Document 0001) Domestic registration patent No. 10-0643124 (registered on October 31, 2006)

(특허문헌 0002) 국내등록특허 제10-1603642호(2016.03.09.등록)(Patent Document 0002) Domestic registered patent No. 10-1603642 (registered on March 9, 2016)

본 발명은 상기와 같은 문제점을 해결하기 위하여 세그먼트 바닥부에 시공하기 위한 보도판블록을 미리 제작하고 보도판블록을 지지할 수 있는 브라켓을 세그먼트 바닥부에 설치하며, 세그먼트 천장부에 설치되어 터널 구조물 내부의 전,후 방향으로 이동이 용이한 보도판블록 승하강장치를 이용해 보도판블록을 세그먼트 바닥부에 연속적으로 간편하게 시공하여 종래의 보도용 콘크리트를 시공하기 위한 거푸집 설치, 레미콘 압송을 위한 장치 설치, 레미콘 타설 등의 번거로운 공정이 생략될 수 있어 공사 원가를 절감하고 공사 기간을 크게 단축시킬 수 있는 터널 구조물내 보도판블록의 시공공법을 제공하는데 목적이 있다.In order to solve the above problems, the present invention prepares a sidewalk block for construction on the segment floor in advance and installs a bracket to support the sidewalk block on the segment floor, and is installed on the segment ceiling to inside the tunnel structure. By using a sidewalk block elevating and lowering device that is easy to move in the front and rear directions, the sidewalk block is continuously installed on the bottom of the segment to install a form for constructing the conventional concrete for sidewalks, and a device for pressing ready-mixed concrete. The purpose of this is to provide a method of constructing a sidewalk block in a tunnel structure that can reduce construction costs and greatly shorten the construction period because cumbersome processes such as placing ready-mixed concrete can be omitted.

본 발명의 터널 구조물내 보도판블록의 시공공법은 터널 구조물내에 보도용으로 이용되게 콘크리트 재질의 일정두께를 갖는 판형상이며 양단면이 세그먼트(1) 바닥부 양측과 대응되는 곡면부로 형성된 보도판블록을 터널 구조물내의 바닥부에 연속적으로 시공하기 위한 터널 구조물용 보도판블록 시공공법에 있어서,The construction method of the sidewalk block in the tunnel structure of the present invention is a plate shape having a certain thickness of concrete material to be used for sidewalks in the tunnel structure, and both ends are formed with curved parts corresponding to both sides of the bottom of the segment (1). In the method of constructing a sidewalk block for a tunnel structure for continuous construction on the bottom of a tunnel structure,

보도판블록(10)을 시공위치의 세그먼트(1) 천장부에 일정길이의 I빔(20)을 설치 후 I빔(20)을 타고 전,후로 이동가능한 보도판블록 승하강부재(30)를 설치하는 단계(S10);After installing the I-beam 20 of a certain length on the ceiling of the segment (1) at the construction location of the sidewalk block 10, the sidewalk block elevating member 30 that can move forward and backward by riding the I-beam 20 is installed. Step (S10);

보도판블록(10) 시공위치의 슬라임 청소단계(S20);Sidewalk block 10, slime cleaning step (S20) at the construction location;

보도판블록(10) 시공위치의 세그먼트 바닥부 양측에 일정길이로 이격시켜 복수의 브라켓(11)을 설치하는 단계(S30);Step of installing a plurality of brackets 11 spaced apart by a predetermined length on both sides of the floor of the segment at the construction location of the sidewalk block 10 (S30);

상기 보도판블록 승하강부재(30)를 이용하여 보도판블록(10)을 브라켓(11)의 상부면에 안착시켜 보도판블록(10)을 시공하는 단계(S40)로 이루어지는 것을 특징으로 한다.It characterized in that it consists of the step (S40) of constructing the sidewalk block 10 by mounting the sidewalk block 10 on the upper surface of the bracket 11 using the sidewalk block elevating member 30.

본 발명은 미리 제작된 보도판블록을 보도판블록 승하강장치를 이용해 세그먼트 바닥부에 연속 설치하여 보도판블록의 시공이 안전하고 손쉽게 이루어 지므로써 작업안정성이 확보되고 시공이 용이하며 브라켓에 의해 보도판블록이 지지되면서 안정적인 시공상태를 유지하고 보도판블록 승하강장치가 설치되는 I빔의 길이를 손쉽게 연장시켜 보도판블록 승하강장치의 분리 없이 연속사용이 가능하므로 작업속도가 빠르고 보도판블록의 연속시공이 용이한 효과가 있다.In the present invention, a pre-fabricated sidewalk block is continuously installed on the segment floor using a sidewalk block elevating device to ensure safe and easy construction of the sidewalk block, thereby ensuring work stability and easy construction, As the plate block is supported, it maintains a stable construction condition, and the length of the I-beam on which the sidewalk block elevating device is installed can be easily extended so that it can be used continuously without separating the sidewalk block lifting and lowering device. It has the effect of easy continuous construction.

또한 쇄석과 유공관을 별도로 설치할 필요가 없고 종래의 보도용 콘크리트를 시공하기 위한 거푸집 설치, 레미콘 타설 등의 작업과정이 생략되어 공사 원가를 절감하고 공사기간을 단축시킬 수 있는 효과가 있다.In addition, there is no need to separately install crushed stone and perforated pipes, and work processes such as installing a formwork for constructing concrete for sidewalks and placing ready-mixed concrete are omitted, thereby reducing construction cost and shortening the construction period.

도 1은 본 발명의 터널 구조물내 보도판블록의 시공공법으로 세그먼트 바닥부에 보도판블록과 브라켓이 설치된 상태도
도 2는 본 발명의 터널 구조물내 보도판블록의 시공공법으로 시공하기 위한 보도판블록 사시도
도 3은 본 발명의 터널 구조물내 보도판블록의 시공공법에 이용되는 보도판블록 승하강장치 상세도
도 4는 본 발명의 터널 구조물내 보도판블록의 시공공법에 이용되는 I빔 상세도
도 5은 본 발명의 터널 구조물내 보도판블록의 시공공법으로 보도판블록이 시공된 세그먼트 정면도
도 7은 도 6의 "A"부분 확대도
도 8은 본 발명의 터널 구조물내 보도판블록의 시공공법으로 세그먼트 바닥부에 보도판블록이 시공되는 상태도
1 is a state diagram of a sidewalk block and a bracket installed at the bottom of a segment by the construction method of a sidewalk block in a tunnel structure of the present invention
Figure 2 is a perspective view of the sidewalk block for construction by the construction method of the sidewalk block in the tunnel structure of the present invention
3 is a detailed view of a sidewalk block elevating device used in the construction method of a sidewalk block in a tunnel structure of the present invention
Figure 4 is a detailed view of the I-beam used in the construction method of the sidewalk block in the tunnel structure of the present invention
5 is a front view of a segment in which a sidewalk block is constructed by the construction method of a sidewalk block in a tunnel structure of the present invention
7 is an enlarged view of part "A" of FIG. 6
8 is a state diagram in which a sidewalk block is constructed on the segment floor by the construction method of the sidewalk block in the tunnel structure of the present invention

본 발명은 터널 구조물내 보도판블록의 시공공법에 관한 것으로, 더욱 상세히는 미리 제작된 보도판블록을 터널 구조물내부의 세그먼트 바닥부에 손쉽게 설치하여 종래의 보도용 콘크리트를 시공하기 위한 거푸집 설치, 레미콘 압송을 위한 장치 설치, 레미콘 타설 등의 번거로운 공정이 생략될 수 있는 터널 구조물내 보도판블록의 시공공법에 관한 것이다.The present invention relates to a construction method of a sidewalk block in a tunnel structure, and in more detail, a prefabricated sidewalk block is easily installed on the segment floor inside a tunnel structure to install a formwork for constructing conventional sidewalk concrete, ready-mixed concrete. It relates to a construction method of a sidewalk block in a tunnel structure in which cumbersome processes such as installation of a device for pressure feeding and placing of ready-mixed concrete can be omitted.

본 발명의 터널 구조물내 보도판블록의 시공공법은 터널 구조물내에 보도용으로 이용되게 콘크리트 재질의 일정두께를 갖는 판형상이며 양단면이 세그먼트(1) 바닥부 양측과 대응되는 곡면부로 형성된 보도판블록을 터널 구조물내의 바닥부에 연속적으로 시공하기 위한 터널 구조물용 보도판블록 시공공법에 있어서,The construction method of the sidewalk block in the tunnel structure of the present invention is a plate shape having a certain thickness of concrete material to be used for sidewalks in the tunnel structure, and both ends are formed with curved parts corresponding to both sides of the bottom of the segment (1). In the method of constructing a sidewalk block for a tunnel structure for continuous construction on the bottom of a tunnel structure,

보도판블록(10)을 시공위치의 세그먼트(1) 천장부에 일정길이의 I빔(20)을 설치 후 I빔(20)을 타고 전,후로 이동가능한 보도판블록 승하강부재(30)를 설치하는 단계(S10);After installing the I-beam 20 of a certain length on the ceiling of the segment (1) at the construction location of the sidewalk block 10, the sidewalk block elevating member 30 that can move forward and backward by riding the I-beam 20 is installed. Step (S10);

보도판블록(10) 시공위치의 슬라임 청소단계(S20);Sidewalk block 10, slime cleaning step (S20) at the construction location;

보도판블록(10) 시공위치의 세그먼트 바닥부 양측에 일정길이로 이격시켜 복수의 브라켓(11)을 설치하는 단계(S30);Step of installing a plurality of brackets 11 spaced apart by a predetermined length on both sides of the floor of the segment at the construction location of the sidewalk block 10 (S30);

상기 보도판블록 승하강부재(30)를 이용하여 보도판블록(10)을 브라켓(11)의 상부면에 안착시켜 보도판블록(10)을 시공하는 단계(S40)로 이루어지는 것을 특징으로 한다.It characterized in that it consists of the step (S40) of constructing the sidewalk block 10 by mounting the sidewalk block 10 on the upper surface of the bracket 11 using the sidewalk block elevating member 30.

상기 I빔(20)은 길이가 신축될 수 있게 내측에 다단형태의 연장빔(21)이 복수개 형성되며,The I-beam 20 has a plurality of multi-stage extension beams 21 formed inside so that the length can be extended and contracted,

후방으로 설치되는 다른 I빔(20)으로 전방의 연장빔(21)이 삽입되어 보도콘 승하강부재(30)의 연속이동이 가능하게 하는 것을 특징으로 한다.It is characterized in that the extension beam 21 in the front is inserted into another I-beam 20 installed in the rear, thereby enabling the continuous movement of the press cone elevating member 30.

상기 보도판블록(10)은 상부면에 양측으로 요입홈(100) 또는 상부면 중앙부에 돌출부(101)가 길이방향으로 형성되는 것을 특징으로 한다.The press plate block 10 is characterized in that the concave groove 100 on both sides of the upper surface or the protrusion 101 in the center of the upper surface are formed in the longitudinal direction.

상기 브라켓(11)의 상부면에는 탄성패드(12)가 설치된 것을 특징으로 한다.An elastic pad 12 is installed on the upper surface of the bracket 11.

상기 보도판블록 승하강부재(30)는 구동모터의 동력으로 I빔(20)의 양단을 타고 이동되는 한쌍의 롤러(31)와 하단에 체인(32)의 구동에 따라 승하강되는 후크(33)가 형성된 전동식 호이스트인 것을 특징으로 한다.The sidewalk block elevating member 30 includes a pair of rollers 31 that are moved along both ends of the I-beam 20 by the power of a driving motor and a hook 33 that is elevating and descending according to the driving of the chain 32 at the bottom. ) Is characterized in that it is formed electric hoist.

이하, 본 발명의 바람직한 실시예를 도면을 참조하여 상세히 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.

도 1 내지 도 3에 도시된 바와 같이, 보도판블록(10)은 프리캐스트 콘크리트이며 판형상으로 터널의 굴착면을 따라 설치된 터널 구조물내의 세그먼트(1) 바닥부에 길이방향으로 다수개가 설치되어 작업자들의 보도용으로 이용되게 한다.As shown in FIGS. 1 to 3, the sidewalk block 10 is precast concrete, and a plurality of sidewalk blocks 10 are installed in the longitudinal direction at the bottom of the segment 1 in the tunnel structure installed along the excavation surface of the tunnel in a plate shape. Let it be used for reporting.

한편, 프리캐스트 콘크리트란 공장에서 형틀에 의하여 성형 제조된 콘크리트 또는 콘크리트 제품을 의미하며, 현장에서 콘크리트 양생 등에 의하여 이루어지는 현장타설공법과 비교하여 공기의 단축, 공사비의 절감, 품질관리의 용이, 내구성 증대 등의 장점이 있다.On the other hand, precast concrete refers to concrete or concrete products molded and manufactured by a mold in a factory, and compared to the on-site casting method performed by curing concrete in the field, the construction time is shortened, construction cost is reduced, quality control is easy, and durability is increased. There are such advantages.

상기 보도판블록(10)은 상부면에 양측으로 요입홈(100) 또는 상부면 중앙에 소정높이 돌출된 돌출부(101)가 길이방향으로 형성되어 배수가 용이하도록 하며, 양단면은 세그먼트(1) 바닥부의 양측과 대응되게 라운드진 곡면부로 형성된다.The sidewalk block 10 is formed with concave grooves 100 on both sides of the upper surface or protrusions 101 protruding at a predetermined height in the center of the upper surface to facilitate drainage, and both ends are segments (1) It is formed with rounded curved portions corresponding to both sides of the bottom portion.

종래에는 터널 구조물내에서 작업자들이 이동할 수 있는 평평한 바닥을 형성하기 위해 터널 구조물의 바닥을 청소한 후 기초 구조물(접지선 및 접지봉, 유공관 등)을 포설하고 이후, 자갈 또는 잡석의 상단에 부직포를 도포하며 부직포의 상단에 거푸집을 설치한 후 거푸집에 레미콘을 타설하여 보도용 콘크리트가 시공되게 하였으나, 이러한 종래의 기술에 의한 경우 거푸집 설치과정, 레미콘 압송을 위한 장치를 설치하는 과정, 레미콘 타설 과정 등의 번거로운 공정을 거쳐야 해서 공정이 복잡하고 소요 자재가 많아 공사 원가 및 공사 기간이 증가하는 문제가 있었으며, 레미콘 압송을 위한 장치를 설치한 후 레미콘 타설하는 공정을 수행시 안전사고가 발생하는 문제점이 있었다.Conventionally, in order to form a flat floor for workers to move in the tunnel structure, the floor of the tunnel structure is cleaned, and then the foundation structure (ground line, ground rod, perforated pipe, etc.) is installed, and then, non-woven fabric is applied to the top of gravel or rubble. After installing the formwork on the top of the nonwoven fabric, concrete for sidewalks was constructed by pouring ready-mixed concrete on the formwork. There was a problem that the construction cost and construction period increased due to the complexity of the process and the large number of materials required, and there was a problem that a safety accident occurred when performing the process of placing ready-mixed concrete after installing a device for pressing ready-mixed concrete.

따라서, 본원발명의 터널 구조물내 보도판블록의 시공공법은 자갈 또는 잡석의 도포, 거푸집 설치, 레미콘 타설의 공정이 생략되어 공사원가 및 공사기간 단축, 작업의 안정성을 확보할 수 있는 상기 보도도판블록(10)을 손쉽게 시공할 수 있도록 보도판블록 승하강부재 설치단계(S10), 슬라임 청소단계(20), 브라켓 설치단계(S30), 보도판블록 시공단계(S40)로 이루어진다.Therefore, in the construction method of the sidewalk block in the tunnel structure of the present invention, the process of applying gravel or rubble, installing a formwork, and placing ready-mixed concrete is omitted, so that the construction cost and construction period can be shortened, and the sidewalk plate block that can secure work stability. (10) It consists of a sidewalk block elevating member installation step (S10), a slime cleaning step (20), a bracket installation step (S30), and a sidewalk block construction step (S40) for easy construction.

상기 보도판블록 승하강부재 설치단계(S10)는 터널 구조물 내에서 보도판블록(10)들을 시공위치에 손쉽게 운반하기 위한 수단인 보도판블록 승강부재(30)를 설치하기 위해 수행되는 것으로 보도판블록 승하강부재(30)를 고정시킬 수 있는 일정길이의 I빔(20)을 보도판블록(10)들이 시공될 위치의 상측 세그먼트(1) 천장부에 길이방향으로 설치한다.The sidewalk block elevating member installation step (S10) is performed to install the sidewalk block lifting member 30, which is a means for easily transporting the sidewalk block 10 to the construction location within the tunnel structure. An I-beam 20 of a predetermined length capable of fixing the block elevating member 30 is installed in the longitudinal direction on the ceiling of the upper segment 1 at the location where the sidewalk blocks 10 are to be constructed.

상기 I빔(20)을 세그먼트(1) 천장부에 설치 후에는 상기 I빔(20)을 타고 전,후로 이동가능하게 보도판블록 승하강부재(30)를 상기 I빔(20)에 설치한다.After the I-beam 20 is installed on the ceiling of the segment 1, a sidewalk block elevating member 30 is installed on the I-beam 20 so as to be movable forward and backward while riding the I-beam 20.

상기 보도판블록 승하강부재(30)는 도 3에 도시된 바와 같이, 구동모터에서 제공되는 구동력에 의해 I빔(20)의 양단을 타고 이동되는 좌,우 한쌍의 롤러(31)와 하단에 체인(32)의 구동에 따라 승하강되는 후크(33)가 설치된 전동식의 호이스트이다.As shown in FIG. 3, the sidewalk block elevating member 30 is at the bottom and a pair of left and right rollers 31 that are moved along both ends of the I-beam 20 by the driving force provided by the driving motor. It is an electric hoist equipped with a hook 33 that moves up and down according to the drive of the chain 32.

즉, 상기 한쌍의 롤러(31)는 외측으로 각각 수직플레이트(300)가 고정되며 상기 I빔(20)의 양 하단에 각각 안착되어 어느 하나의 수직플레이트(300)에 고정된 구동모터(310)의 동력에 의해 I빔(20)을 타고 전,후 방향으로 이동되고, 상기 후크(33)는 상기 수직플레이트(300)의 하단에 고정되며 체인박스(320)의 내부 공간에 수납된 체인(32)이 권상모터(321)의 동력에 의해 승하강되어 상기 체인(32)을 따라 후크(33)가 승하강하면서 상기 보도판블록(10)을 인양 및 운반하게 된다.That is, each of the pair of rollers 31 is fixed to each of the vertical plates 300 to the outside, and the driving motor 310 is mounted on each of the lower ends of the I-beam 20 and fixed to any one of the vertical plates 300 It is moved forward and backward by the power of the I-beam 20, and the hook 33 is fixed to the lower end of the vertical plate 300, and the chain 32 accommodated in the inner space of the chain box 320 ) Is lifted and lowered by the power of the hoisting motor 321 to lift and transport the press plate block 10 as the hook 33 rises and falls along the chain 32.

한편, 도 4에 도시된 바와 같이, 상기 I빔(20)은 길이가 용이하게 신축될 수 있는 길이 가변형으로 내측에 복수의 연장빔(21)이 다단형태로 내삽되어 설치된다.Meanwhile, as shown in FIG. 4, the I-beam 20 has a variable length that can be easily stretched and contracted, and a plurality of extension beams 21 are interpolated and installed in a multi-stage shape inside.

따라서, 상기 연장빔(21)은 복수개가 상기 I빔(20)의 내측에 다단형태로 내삽된 상태에서 I빔(20)의 길이만큼 상기 보도판블록 승하강부재(30)가 이동된 후에는 연장빔(21)들을 I빔(20)에서 순차적으로 빼내 I빔(20)의 길이가 늘어나게 하여 보도판블록 승하강부재(30)의 연속 이동이 가능하게 하고, 또한 후방으로 설치되는 다른 I빔(20)으로 상기 전방측 I빔(20)의 연장빔(21)을 삽입시켜 I빔(20)과 I빔(20)을 손쉽게 연결시킬 수 있어 보도판블록 승하강부재(30)를 분리할 필요없이 연속적으로 사용할 수 있게 하므로 작업속도가 빠르고 작업 안정성을 확보할 수 있게 한다.Therefore, after the sidewalk block elevating member 30 is moved by the length of the I-beam 20 in a state in which a plurality of the extension beams 21 are interpolated in a multi-stage form inside the I-beam 20, The extension beams 21 are sequentially removed from the I-beam 20 to increase the length of the I-beam 20, thereby enabling the continuous movement of the sidewalk block elevating member 30, and another I-beam installed rearward. (20) By inserting the extension beam 21 of the front side I-beam 20, it is possible to easily connect the I-beam 20 and the I-beam 20 to separate the sidewalk block elevating member 30. Since it can be used continuously without need, the work speed is fast and work stability can be secured.

상기 슬라임 청소단계(S20)는 터널 구조물 내에 설치된 세그먼트 바닥부에 쌓인 슬라임을 제거하기 위한 단계로 보도판블록(10)들이 시공될 위치에 쌓여있는 슬라임을 제거하기 위해서는 에어리프트 펌프방식, 워터제트 방식, 제트 석션(Suction)방식 등을 이용하여 슬라임을 제거하도록 하며, 상기 에어리프트 펌프방식, 워터제트 방식, 제트 석션 방식 등은 슬라임 제거시 통상적으로 사용되는 방식으로 자세한 설명은 생략하도록 한다.The slime cleaning step (S20) is a step for removing the slime accumulated on the bottom of the segment installed in the tunnel structure.In order to remove the slime accumulated at the location where the sidewalk blocks 10 will be installed, an air lift pump method or a water jet method , Jet suction method, etc. are used to remove slime, and the air lift pump method, water jet method, jet suction method, etc. are conventionally used when removing slime, and detailed descriptions thereof will be omitted.

상기 브라켓(11) 설치단계는 상기 보도판블록(10)이 시공될 위치의 세그먼트(1) 바닥부에 브라켓(11)을 설치하여 그 상부에 상기 보도판블록(10)이 브라켓(11)의 상부에 안착될 수 있게 수행되는 단계로 상기 브라켓(11)은 세그먼트 바닥부의 양측에서 길이방향으로 일정간격 이격되어 복수개가 설치된다.In the step of installing the bracket 11, the bracket 11 is installed at the bottom of the segment 1 at the location where the sidewalk block 10 will be installed, and the sidewalk block 10 This step is performed so as to be seated on the upper part, and a plurality of brackets 11 are installed at regular intervals in the longitudinal direction from both sides of the bottom of the segment.

도 5 및 도 6에 도시된 바와 같이, 상기 브라켓(11)은 "ㄱ"자로 절곡된 형태로 상기 보도판블록(10)의 하단이 안착되게 상부 안착면(110)이 형성되고, 하부에는 통공이 형성되어 앙카볼트가 끼움결합되므로 브라켓(11)이 세그먼트(1) 바닥부에 견고하게 설치되고 각 브라켓(11)의 상부에 보도판블록(10)이 손쉽게 시공될 수 있게 한다.5 and 6, the bracket 11 has an upper seating surface 110 formed so that the lower end of the press plate block 10 is seated in a form bent in a "b" shape, and a through hole in the lower part This is formed so that the anchor bolts are fitted so that the bracket 11 is firmly installed on the bottom of the segment 1 and the press plate block 10 can be easily installed on the upper part of each bracket 11.

즉, 세그먼트(1) 바닥부에 설치된 각 브라켓(11)의 상부면에는 상기 보도판블록(10)이 안착되고 보도판블록(10)은 브라켓(11)에 의해 지지되므로 보도판블록(100)이 세그먼트 바닥부의 곡면에 의해 좌,우 방향으로 이동되는 것이 방지되어 보도판블록(10)을 세그먼트(1)에 고정시키기 위한 별도의 고정장치나 고정작업이 생략되므로 보도판블록(10)의 시공이 간편해지게 된다.That is, the sidewalk block 10 is seated on the upper surface of each bracket 11 installed on the bottom of the segment 1 and the sidewalk block 10 is supported by the bracket 11, so the sidewalk block 100 Since it is prevented from moving in the left and right directions by the curved surface of the bottom of the segment, a separate fixing device or fixing work for fixing the sidewalk block 10 to the segment 1 is omitted, so the construction of the sidewalk block 10 This becomes simpler.

한편, 상기 브라켓(11)의 안착면(110)에는 상부에서 가해지는 충격을 흡수하여 브라켓(11)이 파손되는 것을 방지하고 안정적인 보도판블록(10)의 지지를 위해 고무 또는 실리콘재질의 탄성패드(12)가 설치되도록 한다.On the other hand, the mounting surface 110 of the bracket 11 absorbs the shock applied from the top to prevent the bracket 11 from being damaged, and an elastic pad made of rubber or silicone to support the stable sidewalk block 10 (12) should be installed.

상기 브라켓(11)의 설치단계 후에는 세그먼트 바닥부에 접지선 및 접지봉과 같은 기초 구조물을 설치하도록 한다.After the installation step of the bracket 11, a basic structure such as a ground wire and a ground rod is installed on the bottom of the segment.

도 7에 도시된 바와 같이, 상기 보도판블록(10)의 시공단계(S40)는 상기 I빔(20)에 설치된 보도판블록 승하강부재(30)를 이용하여 보도판블록(10)들을 시공위치 부근에 이동시킨 후 보도판블록(10)을 시공위치에 하나씩 인양시킨 후 상기 브라켓(11)의 상부에 안착시켜 세그먼트(1) 바닥부에 길이방향으로 다수의 보도판블록(10)을 연속적으로 시공하도록 한다.As shown in Figure 7, the construction step (S40) of the sidewalk block 10 constructs sidewalk blocks 10 using the sidewalk block elevating member 30 installed on the I-beam 20 After moving near the position, the sidewalk blocks 10 are lifted one by one at the construction site, and then mounted on the upper part of the bracket 11 to continuously attach a plurality of sidewalk blocks 10 in the longitudinal direction to the bottom of the segment (1). It should be constructed with.

상기 보도판블록(10)을 시공위치 부근에 이동시킬때에는 상기 보도판블록 승하강부재(30)를 이용하거나 또는 통상의 이동대차를 이용할 수도 있으며, 수직구를 통해 지상에서 터널구조물 내부로 공급되는 보도판블록(10)들이 세그먼트 바닥부에 설치된 바닥레일을 타고 이동되는 이동대차를 통해 보도판블록(10)의 시공위치 부근까지 이동될 수도 있다.When moving the sidewalk block 10 near the construction location, the sidewalk block elevating member 30 may be used, or a conventional mobile cart may be used, and supplied from the ground to the inside of the tunnel structure through a vertical hole. The sidewalk blocks 10 may be moved to the vicinity of the construction location of the sidewalk block 10 through a moving cart that moves along a floor rail installed on the segment floor.

상기 보도판블록(10)의 시공은 세그먼트(1) 바닥부에 대략 10M의 길이로 연속 시공된 후 길이가 신장되는 I빔(20)을 통해 보도판블록 승하강부재(30)를 연속 이동시키고, 상기 슬라임 청소단계, 브라켓 설치단계, 보도판블록 시공단계를 반복하면서 터널 구조물 내의 모든 구간에 상기 보도판블록(10)을 시공하도록 한다.The construction of the sidewalk block 10 continuously moves the sidewalk block elevating member 30 through an I-beam 20 extending in length after being continuously constructed to a length of approximately 10M on the bottom of the segment 1 , While repeating the slime cleaning step, the bracket installation step, and the sidewalk block construction step, the sidewalk block 10 is constructed in all sections within the tunnel structure.

이하, 본 발명의 터널 구조물내 보도판블록의 시공공법은 다음과 같은 순서에 의해 이루어진다.Hereinafter, the construction method of the sidewalk block in the tunnel structure of the present invention is performed by the following sequence.

먼저, 콘크리트 재질의 일정두께를 갖는 판형상이며 양단면이 곡면부로 형성된 보도판블록(10)들을 수직구를 통해 지상에서 터널 구조물 내부로 공급받아 준비하도록 한다.First, the sidewalk blocks 10 having a certain thickness of concrete and formed with curved portions at both ends are supplied from the ground through a vertical hole into the tunnel structure to be prepared.

그후, 상기 터널 구조물 내부의 발진구 방향에서부터 도달구 방향으로 보도판블록(10)이 시공되도록 발진구의 세그먼트 천장부에 일정길이의 I빔(20)을 설치하고, 세그먼트 천장부에 설치된 I빔(20)에 보도판블록 승하강부재(30)를 설치하여 보도판블록 승하강부재(30)가 I빔(20)을 타고 전,후 방향으로 이동이 가능하도록 한다.Thereafter, an I-beam 20 of a certain length is installed on the segment ceiling of the oscillation port so that the sidewalk block 10 is constructed from the oscillation port direction inside the tunnel structure to the arrival port direction, and the I-beam 20 installed on the segment ceiling. By installing the press plate block elevating member 30 to the press plate block elevating member 30 to be able to move in the front and rear directions by riding the I-beam 20.

다음으로, 보도판블록(10)의 시공위치의 세그먼트 바닥부에 쌓여있는 슬라임을 에어리프트 펌프방식, 워터제트 방식, 제트 석션(Suction)방식 등으로 깨끗이 제거한 후 세그먼트(1) 바닥부의 양측으로 브라켓(11)을 길이방향으로 복수개 설치한다.Next, after removing the slime accumulated on the bottom of the segment at the construction location of the sidewalk block 10 cleanly by using an air lift pump method, a water jet method, or a jet suction method, the brackets are placed on both sides of the bottom of the segment (1). Install a plurality of (11) in the longitudinal direction.

그 후, 보도판블록(10)들을 상기 보도판블록 승하강부재(30)를 이용하여 보도판블록(10)이 시공될 위치의 부근으로 이동시키거나 이동대차를 이용하여 보도판블록(10)들을 보도판블록의 시공위치 부근까지 이동시킨다.Thereafter, the sidewalk block 10 is moved to the vicinity of the position where the sidewalk block 10 is to be constructed using the sidewalk block elevating member 30 or the sidewalk block 10 using a moving cart. Move them to the vicinity of the construction location of the sidewalk block.

다음으로, 보도판블록 승하강부재(30)를 이용하여 보도판블록(10)을 하나씩 인양시킨 후 상기 브라켓(11)들의 상부에 안착시키는 작업을 반복하여 대략 10M의 길이씩 보도판블록(10)을 연속시공한다.Next, the sidewalk block 10 is lifted one by one by using the sidewalk block elevating member 30, and then the operation of seating on the upper part of the brackets 11 is repeated, and the length of the sidewalk block 10 is approximately 10M. ) Are continuously constructed.

그후, 상기 I빔(20)의 연장빔(21)들을 꺼내 I빔(20)의 길이를 신장시켜 보도판블록 승하강부재(30)의 연속이동이 이루어지게 한 후 상기 슬라임 청소단계, 브라켓 설치단계, 보도판블록 시공단계를 반복하여 세그먼트(1) 바닥부 전체에 보도판블록을 시공한다.Thereafter, the extension beams 21 of the I-beam 20 are taken out and the length of the I-beam 20 is elongated so that the sidewalk block elevating and descending member 30 is continuously moved, and the slime cleaning step, bracket installation Repeat the step, the sidewalk block construction step to construct the sidewalk block on the entire floor of the segment (1).

이때, 상기 I빔(20)들은 후방으로 설치되는 I빔(20)끼리 간격이 이격되어 설치되고, I빔(20)끼리는 연장빔(21)을 통해 연결되어 전방에서는 보도판블록의 시공이 이루어지고, 후방에서는 미리 I빔(20)의 설치작업이 이루어져 보도판블록 승하강부재(30)의 분리없이 연속적인 보도판블록 승하강부재(30)의 이동작업이 가능할 수 있다.At this time, the I-beams 20 are installed at a distance between the I-beams 20 installed in the rear, and the I-beams 20 are connected to each other through an extension beam 21, so that the construction of the sidewalk block is made in the front. In the upper and rear, the I-beam 20 is installed in advance so that it is possible to continuously move the press plate block elevating member 30 without separating the press plate block elevating member 30.

본 발명은 도면에 도시된 실시 예를 참고도 설명되었으나 이는 예시적인 것에 불과하며 당해 기술분야에서 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 실시 예가 가능하다는 점을 이해할 것이다.Although the present invention has been described with reference to the embodiments shown in the drawings, this is only exemplary, and those of ordinary skill in the art will appreciate that various modifications and equivalent embodiments are possible therefrom.

따라서 본 발명의 진정한 보호 범위는 첨부된 청구범위에 의해서만 정해져야 할 것이다.Therefore, the true scope of protection of the present invention should be determined only by the appended claims.

10-보도판블록
11-브라켓
20-I빔
21-연장빔
30-보도판블록 승하강부재
10-sidewalk block
11-bracket
20-I beam
21-extended beam
30-sidewalk block elevating member

Claims (5)

터널 구조물내에 보도용으로 이용되게 콘크리트 재질의 일정두께를 갖는 판형상이며 양단면이 세그먼트(1) 바닥부 양측과 대응되는 곡면부로 형성된 보도판블록을 터널 구조물내의 바닥부에 연속적으로 시공하기 위한 터널 구조물용 보도판블록 시공공법에 있어서,
보도판블록(10)을 시공위치의 세그먼트(1) 천장부에 일정길이의 I빔(20)을 설치 후 I빔(20)을 타고 전,후로 이동가능한 보도판블록 승하강부재(30)를 설치하는 단계(S10);
보도판블록(10) 시공위치의 슬라임 청소단계(S20);
보도판블록(10) 시공위치의 세그먼트 바닥부 양측에 일정길이로 이격시켜 복수의 브라켓(11)을 설치하는 단계(S30);
상기 보도판블록 승하강부재(30)를 이용하여 보도판블록(10)을 브라켓(11)의 상부면에 안착시켜 보도판블록(10)을 시공하는 단계(S40)로 이루어지며,
상기 I빔(20)은 길이가 신축될 수 있게 내측에 다단형태의 연장빔(21)이 복수개 형성되며,
후방으로 설치되는 다른 I빔(20)으로 전방의 연장빔(21)이 삽입되어 보도콘 승하강부재(30)의 연속이동이 가능하게 하고,
상기 보도판블록(10)은 상부면에 양측으로 요입홈(100) 또는 상부면 중앙부에 돌출부(101)가 길이방향으로 형성되며,
상기 브라켓(11)의 상부면에는 탄성패드(12)가 설치된 것을 특징으로 하는 터널 구조물내 보도판블록의 시공공법.
A tunnel for continuously constructing a sidewalk block formed with curved portions corresponding to both sides of the segment (1) bottom and in the shape of a plate with a certain thickness of concrete material to be used for sidewalks in the tunnel structure. In the structural sidewalk block construction method,
After installing the I-beam 20 of a certain length on the ceiling of the segment (1) at the construction location of the sidewalk block 10, the sidewalk block elevating member 30 that can move forward and backward by riding the I-beam 20 is installed. Step (S10);
Sidewalk block 10, slime cleaning step (S20) at the construction location;
Step of installing a plurality of brackets 11 spaced apart by a predetermined length on both sides of the floor of the segment at the construction location of the sidewalk block 10 (S30);
It consists of a step (S40) of constructing the sidewalk block 10 by mounting the sidewalk block 10 on the upper surface of the bracket 11 using the sidewalk block elevating member 30,
The I-beam 20 has a plurality of multi-stage extension beams 21 formed inside so that the length can be extended and contracted,
The extension beam 21 in the front is inserted into another I-beam 20 installed in the rear to enable the continuous movement of the press cone elevating member 30,
The press plate block 10 has concave grooves 100 on both sides of the upper surface or protrusions 101 in the center of the upper surface in the longitudinal direction,
Construction method of a sidewalk block in a tunnel structure, characterized in that an elastic pad (12) is installed on the upper surface of the bracket (11).
삭제delete 삭제delete 삭제delete 청구항 1에 있어서,
상기 보도판블록 승하강부재(30)는 구동모터의 동력으로 I빔(20)의 양단을 타고 이동되는 한쌍의 롤러(31)와 하단에 체인(32)의 구동에 따라 승하강되는 후크(33)가 형성된 전동식 호이스트인 것을 특징으로 하는 터널 구조물내 보도판블록의 시공공법.


The method according to claim 1,
The sidewalk block elevating member 30 includes a pair of rollers 31 that are moved along both ends of the I-beam 20 by the power of a driving motor and a hook 33 that is elevating and descending according to the driving of the chain 32 at the bottom. ) The construction method of the sidewalk block in the tunnel structure, characterized in that the electric hoist is formed.


KR1020200053346A 2020-05-04 2020-05-04 Construction method of panel for pedestrian block KR102171437B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200053346A KR102171437B1 (en) 2020-05-04 2020-05-04 Construction method of panel for pedestrian block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200053346A KR102171437B1 (en) 2020-05-04 2020-05-04 Construction method of panel for pedestrian block

Publications (1)

Publication Number Publication Date
KR102171437B1 true KR102171437B1 (en) 2020-10-29

Family

ID=73129371

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200053346A KR102171437B1 (en) 2020-05-04 2020-05-04 Construction method of panel for pedestrian block

Country Status (1)

Country Link
KR (1) KR102171437B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638750A (en) * 2021-07-13 2021-11-12 江苏思行达信息技术有限公司 Intelligent safety protection equipment for pit and tunnel operation and safety protection method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0532402U (en) * 1991-07-26 1993-04-27 日新電機株式会社 Rail pull-out device for track-type equipment
KR100643124B1 (en) 2005-01-10 2006-11-10 주식회사 지유디코퍼레이션 Earth structure of cable-turnnel
KR101519124B1 (en) * 2014-09-01 2015-05-11 (주) 대한이엔지 Monorail system for installing precast ventilation concrete slab in tunnel, method for controlling therefor, and method for tunneling using the same
KR101603642B1 (en) 2014-12-05 2016-03-15 주식회사 케이씨산업 PC panel for tunnel sidewalk and method for manufacturing a tunnel sidewalk using the same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0532402U (en) * 1991-07-26 1993-04-27 日新電機株式会社 Rail pull-out device for track-type equipment
KR100643124B1 (en) 2005-01-10 2006-11-10 주식회사 지유디코퍼레이션 Earth structure of cable-turnnel
KR101519124B1 (en) * 2014-09-01 2015-05-11 (주) 대한이엔지 Monorail system for installing precast ventilation concrete slab in tunnel, method for controlling therefor, and method for tunneling using the same
KR101603642B1 (en) 2014-12-05 2016-03-15 주식회사 케이씨산업 PC panel for tunnel sidewalk and method for manufacturing a tunnel sidewalk using the same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638750A (en) * 2021-07-13 2021-11-12 江苏思行达信息技术有限公司 Intelligent safety protection equipment for pit and tunnel operation and safety protection method
CN113638750B (en) * 2021-07-13 2023-12-05 江苏思行达信息技术有限公司 Pit tunnel operation safety protection intelligent equipment and safety protection method

Similar Documents

Publication Publication Date Title
US9322137B2 (en) Method for building structures, particularly passages under operating railways or the like
KR100713787B1 (en) The underground structure assembly and the underground structure building method which it uses
WO2018133740A1 (en) Underground building and construction method for same
KR101716573B1 (en) The Construction Method of linear curve-shaped non-excavation tunnel with using Forepoling Board and ground reinforcement
KR100991630B1 (en) A container sleeve push ahead type tunnel manufacture method
JP2009057680A (en) Structure and method for supporting covering plate
CN109454746B (en) Concrete pouring device for building construction and construction method thereof
KR101696845B1 (en) The Construction Method of Non-excavation tunnel what Steel pipe position can be substitute with PC-upper-slab by Extruding
KR102035995B1 (en) Frame support system using temporary strut for top-down method and construction method thereof
KR102171437B1 (en) Construction method of panel for pedestrian block
US20170268219A1 (en) Underground-structure construction method
CN106759486A (en) A kind of underground structure being made up of stake and wall and its construction method
JP6944882B2 (en) How to build an invert in an existing tunnel
JP6837394B2 (en) Invert pier and tunnel invert construction method
CN110438911B (en) Construction method for local ecological demolition structure of urban bridge
KR101427812B1 (en) Open cut method for constructing an underground structure
CN116378711A (en) Shallow-buried underground excavation tunnel separated trolley device and construction method
KR101249660B1 (en) Earth pressure supporting method of walls trench applying construction of none- excavation underground structure
JP2003278476A (en) Widening device of existing tunnel and its method
KR100362810B1 (en) Shield tunneling apparatus and method
KR101447381B1 (en) No-Dig construction method of step passage using gallery pipe pushed upward
KR102102593B1 (en) constructing level tunnel connecting part of vertical structure and apparatus thereof
JP4037004B2 (en) Construction method of underground structure
JP3996597B2 (en) Open shield machine and open shield method using it
CN110685719A (en) Quick construction method for double-span simply-supported inverted arch trestle

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant