KR102017731B1 - Reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same - Google Patents

Reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same Download PDF

Info

Publication number
KR102017731B1
KR102017731B1 KR1020190062749A KR20190062749A KR102017731B1 KR 102017731 B1 KR102017731 B1 KR 102017731B1 KR 1020190062749 A KR1020190062749 A KR 1020190062749A KR 20190062749 A KR20190062749 A KR 20190062749A KR 102017731 B1 KR102017731 B1 KR 102017731B1
Authority
KR
South Korea
Prior art keywords
press
anchor bolts
reinforcement pile
pile
reinforcing pile
Prior art date
Application number
KR1020190062749A
Other languages
Korean (ko)
Inventor
김성수
김상우
김승은
Original Assignee
김성수
김상우
김승은
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김성수, 김상우, 김승은 filed Critical 김성수
Priority to KR1020190062749A priority Critical patent/KR102017731B1/en
Application granted granted Critical
Publication of KR102017731B1 publication Critical patent/KR102017731B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a reaction support for press fitting a reinforcing pile, which allows anchor bolts to be settled by using drilled holes drilled to press fit a conventional reinforcing pile for base reinforcement when the reinforcing pile is press fitted to eliminate the need for drilling of additional anchor holes and firmly settle the anchor bolts, thereby stably press fitting the reinforcing pile, and to a press fitting method for a reinforcing pile using the reaction support. According to the present invention, the reaction support for press fitting a reinforcing pile for press fitting a reinforcing pile into a lower portion of a base comprises: four anchor bolts inserted into drilled holes formed in a concrete base and settled by mortar filled in the drilled holes such that upper and lower ends thereof respectively protrude to upper and lower portions of the base; a guide sleeve provided between the anchor bolts to guide press fitting of the reinforcing pile; support steel bars coupled to upper portion of the anchor bolts; a pressure plate provided on upper portions the support steel bars to press the reinforcing pile; a hydraulic jack provided on an upper portion of the pressure plate to pressurize the pressure plate; an expansion link member consisting of a pair of link bars hinged to be foldable to each other and coupling two neighboring anchor bolts; and coupling plates interconnecting lower ends of opposing anchor bolts.

Description

보강파일 압입용 반력대 및 이를 이용한 보강파일 압입 방법{Reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same}Reaction bed for pressing reinforcement pile and reinforcing pile press method using same {reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same}

본 발명은 기존 기초 보강을 위한 보강파일의 압입 시공시, 보강파일 압입을 위해 천공되는 천공홀을 이용하여 앵커볼트를 정착함으로써, 추가적인 앵커홀 천공이 필요 없고 앵커볼트가 견고하게 정착되어 보강파일을 안정적으로 압입할 수 있는 보강파일 압입용 반력대 및 이를 이용한 보강파일 압입 방법에 대한 것이다. In the present invention, when anchoring the reinforcement pile for the existing foundation reinforcement, by fixing the anchor bolt using a drilled hole for the reinforcement pile indentation, no additional anchor hole drilling is required and the anchor bolt is firmly fixed to the reinforcement pile The present invention relates to a reaction table for press-fitting reinforcement pile which can be press-fitted stably and a method of press-fitting reinforcement pile using the same.

기시공된 건축물의 기초 지지력이 부족하거나 수직 증축 등의 리모델링시 중력 하중이 증가되는 경우 또는 지반 침하가 예상되는 경우 등에는 기존 기초를 보강하여야 한다. Existing foundations should be reinforced in case of lack of foundation support of the constructed structure, increase of gravity load during remodeling such as vertical extension, or when ground subsidence is expected.

이러한 기초 보강 공사는 대개 건축물 내부에서 이루어지므로 작업 공간이 협소하고 중대형 장비의 반입이 어렵다. Such foundation reinforcement work is usually done inside the building, so the working space is narrow and it is difficult to bring in medium and large equipment.

따라서 마이크로 파일이나 강관 파일 등의 보강파일을 지중에 압입하는 압입 파일 공법이 주로 사용된다. Therefore, the press-fitting file method for press-fitting reinforcement files such as micro piles and steel pipe piles into the ground is mainly used.

상기 압입 파일 공법은 구조물의 지지력 향상 또는 지반 침하 억제 등을 위해 사용되는 것으로, 기존 기초를 천공하여 천공홀을 형성한 후 천공홀을 통해 분절된 보강파일을 연속적으로 지반에 관입하여 이루어진다.The indentation pile method is used to improve the bearing capacity of the structure or to suppress ground subsidence, and is formed by continuously intruding a reinforcement pile segmented through the boring hole into the ground after forming the boring hole by drilling the existing foundation.

특히, 유압잭에 의해 보강파일을 압입하여 근입할 수 있으므로, 작업 공간이 협소하여 높이가 높은 장비의 반입이 어려운 경우 등에 효율적으로 활용 가능하다. In particular, the reinforcement pile can be pushed in by the hydraulic jack, so that it can be used efficiently.

그런데 이러한 압입 파일 공법은 유압잭에 의해 보강파일을 압입하기 위해 유압잭을 지지하여 보강파일을 가압할 수 있는 반력 구조물이 필요하다. However, the press-fitting pile method requires a reaction force structure capable of pressing the reinforcing pile by supporting the hydraulic jack to press-fit the reinforcing pile by the hydraulic jack.

이에 보강파일을 근입하기 위한 기초의 천공홀 주변에 별도의 앵커홀을 일정 깊이 천공하고, 천공홀에 앵커볼트를 정착하여 유압잭을 지지하는 기술이 개발되었다. To this end, a technology for supporting hydraulic jacks was developed by drilling a separate anchor hole at a predetermined depth around the foundation hole for entering the reinforcement pile, and anchoring the anchor bolt in the hole.

그러나 상기 종래 기술은 보강파일 근입을 위한 천공홀과 별개로 복수의 앵커홀을 천공해야 하므로 작업시간이 많이 소요되는 단점이 있다. However, the prior art has a disadvantage in that a lot of work time is required because a plurality of anchor holes must be drilled separately from the drilling holes for reinforcement pile intrusion.

아울러 공개특허 제10-2012-0130589호에는 기존 기둥 상부의 거더 하부에 반력틀을 설치하고, 반력틀 하부에 유압잭을 설치하여 보강파일을 압입하는 기술이 제안되었다. In addition, Patent Application Publication No. 10-2012-0130589 proposes a technique for installing a reaction frame in the lower part of the girder of the existing column, and installing a hydraulic jack in the lower reaction frame to press-fit the reinforcement pile.

그러나 상기 기술의 경우, 반력틀의 높이가 높아 반력틀 시공이 번거롭고, 잔여 보강파일의 높이가 높아 자재가 낭비되는 단점이 있다. However, in the above technology, the height of the reaction frame is high, the construction of the reaction frame is cumbersome, and the height of the residual reinforcement pile is high, there is a disadvantage that the material is wasted.

상기와 같은 문제점을 해결하기 위하여 본 발명은 기존 기초 보강을 위하여 보강파일을 압입 시공하는 경우, 반력대 설치를 위하여 추가로 앵커홀을 천공할 필요가 없는 보강파일 압입용 반력대 및 이를 이용한 보강파일 압입 방법을 제공하고자 한다. In order to solve the above problems, the present invention, when press-installing the reinforcement pile for the existing foundation reinforcement, reinforcement pile press-reinforcement reaction force and the reinforcement pile using the same do not need to additionally drill the anchor hole for installing the reaction table An indentation method is provided.

본 발명은 앵커볼트가 견고하게 정착되어 보강파일을 안정적으로 압입할 수 있는 보강파일 압입용 반력대 및 이를 이용한 보강파일 압입 방법을 제공하고자 한다.The present invention is to provide a reinforcement pile press reaction force and a reinforcement pile press-fitting method using the same that the anchor bolt is firmly settled to stably press the reinforcement pile.

바람직한 실시예에 따른 본 발명은 기초의 하부에 보강파일을 압입하기 위한 것으로, 상하단이 각각 기초의 상하부로 돌출되도록 콘크리트 기초에 형성된 천공홀에 삽입되어 천공홀 내부에 충전되는 모르타르에 의해 정착되는 4개의 앵커볼트; 상기 복수의 앵커볼트 사이에 구비되어 보강파일의 압입을 가이드하는 가이드 슬리브; 상기 앵커볼트의 상부에 결합되는 지지강봉; 상기 지지강봉의 상부에 구비되어 보강파일을 가압하는 가압플레이트; 상기 가압플레이트의 상부에 구비되어 가압플레이트를 가압하는 유압잭; 서로 접철 가능하게 힌지 결합된 한 쌍의 링크바로 구성되어 이웃하는 2개의 앵커볼트를 각각 결합하는 확장링크부재; 및 마주보는 앵커볼트의 하단을 각각 상호 연결하는 커플링플레이트; 로 구성되는 것을 특징으로 하는 보강파일 압입용 반력대를 제공한다.The present invention according to the preferred embodiment for press-fitting the reinforcement pile in the lower portion of the base, the upper and lower ends are respectively inserted into the drilling hole formed in the concrete foundation so as to protrude into the upper and lower portions of the foundation is settled by mortar filled in the drilling hole 4 Anchor bolts; A guide sleeve provided between the plurality of anchor bolts to guide the indentation of the reinforcement pile; A support steel rod coupled to the upper portion of the anchor bolt; A pressure plate provided on an upper portion of the supporting steel bar to pressurize the reinforcement pile; A hydraulic jack provided on the pressure plate to pressurize the pressure plate; Expansion link members consisting of a pair of link bars foldable hinged to each other to couple two adjacent anchor bolts; And coupling plates connecting the lower ends of the opposite anchor bolts to each other. It provides a reaction force for the reinforcement pile indentation, characterized in that consisting of.

다른 바람직한 실시예에 따른 본 발명은 상기 앵커볼트의 하단에는 너트가 결합되는 것을 특징으로 하는 보강파일 압입용 반력대를 제공한다.The present invention according to another preferred embodiment provides a reaction force for the reinforcement pile press-fitting, characterized in that the nut is coupled to the bottom of the anchor bolt.

삭제delete

삭제delete

다른 바람직한 실시예에 따른 본 발명은 상기 링크바의 타측 링크바 및 커플링플레이트와 힌지 결합되는 체결홀은 장공으로 형성되는 것을 특징으로 하는 보강파일 압입용 반력대를 제공한다.The present invention according to another preferred embodiment provides a reaction force for the reinforcement pile press-fitting, characterized in that the coupling hole hinged to the other side of the link bar and the coupling plate is formed in a long hole.

다른 바람직한 실시예에 따른 본 발명은 상기 커플링플레이트는 연결부의 양단에 결합부가 천공홀 내측 방향으로 돌출되도록 구성되고, 상기 확장링크부재의 링크바는 상기 결합부에 힌지 결합되는 것을 특징으로 하는 보강파일 압입용 반력대를 제공한다.In accordance with another aspect of the present invention, the coupling plate is configured such that the coupling portion protrudes in the inner direction of the drilling hole at both ends of the connection portion, and the link bar of the expansion link member is hinged to the coupling portion. Provides reaction force for pile indentation.

다른 바람직한 실시예에 따른 본 발명은 상기 연결부는 외측면이 천공홀의 내주면에 대응되도록 만곡된 원호 형상인 것을 특징으로 하는 보강파일 압입용 반력대를 제공한다.According to another preferred embodiment of the present invention, the connection part provides a reaction force for reinforcing pile indentation, characterized in that the outer surface has a curved arc shape to correspond to the inner circumferential surface of the drilling hole.

다른 바람직한 실시예에 따른 본 발명은 상기 보강파일 압입용 반력대를 이용한 보강파일 압입 방법에 관한 것으로, (a) 기초를 천공하여 천공홀을 형성하는 단계; (b) 상기 천공홀 내에 앵커볼트를 삽입하고, 앵커볼트 사이에 가이드 슬리브를 삽입하는 단계; (c) 상기 천공홀 내에 모르타르를 충전하여 앵커볼트를 정착하는 단계; (d) 상기 앵커볼트의 상부에 지지강봉, 가압플레이트 및 유압잭을 설치하는 단계; 및 (e) 상기 가압플레이트의 하부에 보강파일을 위치시키고 유압잭을 가동하여 보강파일을 가이드 슬리브를 통해 지반 내에 압입시키는 단계; 를 포함하여 구성되는 것을 특징으로 하는 보강파일 압입용 반력대를 이용한 보강파일 압입 방법을 제공한다.The present invention according to another preferred embodiment relates to a reinforcement pile indentation method using the reinforcement pile press reaction band, (a) forming a punching hole by drilling the foundation; (b) inserting an anchor bolt into the drilling hole and inserting a guide sleeve between the anchor bolts; (c) fixing the anchor bolt by filling mortar in the drilling hole; (d) installing a supporting steel bar, a pressure plate, and a hydraulic jack on an upper portion of the anchor bolt; And (e) placing the reinforcement pile in the lower portion of the pressing plate and operating the hydraulic jack to press the reinforcement pile into the ground through the guide sleeve. It provides a reinforcement pile press-fitting method using the reinforcing file press-fitting reaction table, characterized in that it comprises a.

본 발명에 따르면 다음과 같은 효과가 있다. According to the present invention has the following effects.

첫째, 기존 기초 보강을 위하여 보강파일을 압입 시공하는 경우, 보강파일 압입을 위해 천공되는 천공홀을 이용하여 앵커볼트를 정착할 수 있다. 따라서 반력대 설치를 위하여 천공홀 주변에 추가로 앵커홀을 천공할 필요가 없어 시공이 용이하고 공기 단축이 가능하다. First, in the case of press-fitting the reinforcement pile for the existing foundation reinforcement, it is possible to anchor the anchor bolt by using a drilled hole to be punched for the reinforcement pile. Therefore, it is not necessary to drill additional anchor holes around the drilling holes for the installation of the reaction table, so that the construction is easy and the air shortening is possible.

둘째, 복수의 앵커볼트가 보강파일 관통을 위해 천공홀 내에 구비되는 가이드 슬리브의 외측에서 천공홀에 채워지는 모르타르에 의해 견고하게 정착된다. 따라서 앵커볼트가 견고하게 정착되어 보강파일을 안정적으로 압입할 수 있다. Second, the plurality of anchor bolts are firmly fixed by mortar filled in the drilling holes on the outside of the guide sleeve provided in the drilling holes for the reinforcing pile penetration. Therefore, the anchor bolt is firmly settled and can reliably press-fit the reinforcement pile.

셋째, 앵커볼트의 하단에 결합되는 너트 또는 앵커볼트의 하단에 구비되는 확장링크부재와 커플링플레이트에 의하여 앵커볼트의 정착력을 증가시킬 수 있다. Third, it is possible to increase the anchoring force of the anchor bolt by the expansion link member and the coupling plate provided at the bottom of the nut or anchor bolt coupled to the bottom of the anchor bolt.

도 1은 본 발명 보강파일 압입용 반력대의 설치 상태를 도시하는 단면도.
도 2는 본 발명 보강파일 압입용 반력대를 도시하는 사시도.
도 3은 확장링크부재 및 커플링플레이트가 구비된 반력대를 도시하는 사시도.
도 4는 도 3의 반력대가 설치된 상태를 도시하는 단면도.
도 5는 확장링크부재와 커플링플레이트의 결합 관계를 도시하는 사시도.
도 6은 확장링크부재와 커플링플레이트의 결합 상태를 도시하는 사시도.
도 7은 확장링크부재와 커플링플레이트의 작동 관계를 도시하는 평면도.
도 8은 커플링플레이트의 다른 실시예를 도시하는 평면도.
도 9는 본 발명 보강파일 압입용 반력대를 이용한 보강파일 압입 방법의 단계별 공정을 도시하는 도면.
1 is a cross-sectional view showing an installation state of the reaction table for press-fitting reinforcement pile of the present invention.
2 is a perspective view showing a reaction table for press-fitting reinforcement pile of the present invention.
3 is a perspective view showing a reaction table provided with an expansion link member and a coupling plate.
4 is a cross-sectional view showing a state in which the reaction table of FIG. 3 is installed.
5 is a perspective view showing a coupling relationship between the expansion link member and the coupling plate.
Figure 6 is a perspective view showing a coupling state of the expansion link member and the coupling plate.
7 is a plan view showing an operating relationship between the expansion link member and the coupling plate;
8 is a plan view showing another embodiment of the coupling plate;
Figure 9 is a view showing a step-by-step process of the reinforcement pile indentation method using the reaction force for the reinforcement pile indentation of the present invention.

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다. Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

도 1은 본 발명 보강파일 압입용 반력대의 설치 상태를 도시하는 단면도이고, 도 2는 본 발명 보강파일 압입용 반력대를 도시하는 사시도이다.1 is a cross-sectional view showing an installation state of the present invention reinforcement pile press-fitting reaction table, and FIG.

도 1 및 도 2 등에 도시된 바와 같이, 본 발명 보강파일 압입용 반력대는 기초(2)의 하부에 보강파일(3)을 압입하기 위한 것으로, 상하단이 각각 기초(2)의 상하부로 돌출되도록 콘크리트 기초(2)에 형성된 천공홀(21)에 삽입되어 천공홀(21) 내부에 충전되는 모르타르(22)에 의해 정착되는 복수의 앵커볼트(41); 상기 복수의 앵커볼트(41) 사이에 구비되어 보강파일(3)의 압입을 가이드하는 가이드 슬리브(42); 상기 앵커볼트(41)의 상부에 결합되는 지지강봉(43); 상기 지지강봉(43)의 상부에 구비되어 보강파일(3)을 가압하는 가압플레이트(44); 및 상기 가압플레이트(44)의 상부에 구비되어 가압플레이트(44)를 가압하는 유압잭(45); 으로 구성되는 것을 특징으로 한다. As shown in Figure 1 and 2, etc., the reaction arm for the reinforcement pile press-fitting of the present invention is to press the reinforcement pile 3 in the lower portion of the foundation (2), the upper and lower ends of the concrete so as to project to the upper and lower portions of the foundation (2), respectively A plurality of anchor bolts 41 inserted into the boring holes 21 formed in the base 2 and fixed by mortar 22 filled in the boring holes 21; A guide sleeve 42 provided between the plurality of anchor bolts 41 to guide the indentation of the reinforcement pile 3; A support steel bar 43 coupled to an upper portion of the anchor bolt 41; A pressure plate 44 provided on the support steel bar 43 to pressurize the reinforcement pile 3; And a hydraulic jack 45 provided on the pressure plate 44 to pressurize the pressure plate 44. Characterized in that consists of.

본 발명은 기존 기초 보강을 위하여 보강파일을 압입 시공하는 경우, 반력대 설치를 위하여 추가로 앵커홀을 천공할 필요가 없고 앵커볼트(41)가 견고하게 정착되어 보강파일(3)을 안정적으로 압입할 수 있는 보강파일 압입용 반력대 및 이를 이용한 보강파일 압입 방법을 제공하기 위한 것이다. In the present invention, when the reinforcement piles are press-fitted for the existing foundation reinforcement, there is no need to drill additional anchor holes for installing the reaction table, and the anchor bolts 41 are firmly fixed to press-fit the reinforcement piles 3 stably. It is to provide a reinforcement pile press reaction unit and a reinforcement pile press-fit method using the same.

상기 보강파일 압입용 반력대(4)는 기초(2)의 하부에 보강파일(3)을 압입하기 위한 것이다. The reinforcing pile press-fitting reaction table 4 is for pressing the reinforcing pile 3 into the lower portion of the foundation 2.

상기 기초(2)는 확대기초(footing foundation), 매트기초(mat foundation) 등일 수 있다. The foundation 2 may be a footing foundation, a mat foundation, or the like.

상기 보강파일(3)은 마이크로 파일이나 강관 파일 등으로, 기존 기초(2)를 천공하여 형성된 천공홀(21)을 통해 복수 개가 상하 연속되도록 지반(1)에 관입되어 이루어진다. The reinforcement pile 3 is made of a micro pile or a steel pipe pile, and the like is inserted into the ground 1 so that a plurality of pieces are vertically continuous through the drilling holes 21 formed by drilling the existing foundation 2.

본 발명 보강파일 압입용 반력대(4)는 복수의 앵커볼트(41), 가이드 슬리브(42), 지지강봉(43), 가압플레이트(44) 및 유압잭(45)을 포함하여 구성된다. Reinforcing pile press-fitting reaction table 4 of the present invention comprises a plurality of anchor bolts 41, guide sleeves 42, support steel bar 43, pressure plate 44 and the hydraulic jack 45.

상기 앵커볼트(41)는 상하단이 각각 기초(2)의 상하부로 돌출되도록 콘크리트 기초(2)에 형성된 천공홀(21)에 삽입된다. The anchor bolts 41 are inserted into the drilling holes 21 formed in the concrete foundation 2 such that the upper and lower ends thereof protrude to the upper and lower portions of the foundation 2, respectively.

상기 앵커볼트(41)는 천공홀(21) 내부에 충전되는 모르타르(22)에 의해 정착된다. The anchor bolt 41 is fixed by the mortar 22 is filled in the drilling hole (21).

상기 앵커볼트(41)는 보강파일(3)의 주변으로 복수 개가 설치된다.A plurality of anchor bolts 41 are installed around the reinforcement pile 3.

상기 천공홀(21) 주변에 별도의 앵커홀을 천공하여 앵커볼트를 정착하는 종래 기술과 달리 본 발명은 보강파일(3) 압입을 위해 천공되는 천공홀(21)을 이용하여 앵커볼트(41)를 정착한다. Unlike the conventional technology of fixing the anchor bolt by drilling a separate anchor hole around the drilling hole 21, the present invention uses the anchor bolt 41 by using the punched hole 21 to be punched for the reinforcement pile 3 indentation. To settle down.

따라서 기존에 보강파일 압입을 위해 천공하는 천공홀의 지름보다 천공홀(21)의 지름을 약간 크게 형성한다. Therefore, the diameter of the drilled hole 21 is slightly larger than the diameter of the drilled hole drilled for the reinforcement pile.

상기 앵커볼트(41)는 후술할 보강파일(3) 관통을 위해 천공홀(21) 내에 구비되는 가이드 슬리브(42)의 외측에서 천공홀(21)에 채워지는 모르타르(22)에 의해 정착된다. The anchor bolt 41 is fixed by the mortar 22 filled in the drilling hole 21 on the outside of the guide sleeve 42 provided in the drilling hole 21 to penetrate the reinforcement pile 3 to be described later.

상기 앵커볼트(41)는 외주면에 나사산이 형성된 전산볼트나 나선철근 등을 사용하여 모르타르(22)와의 마찰력을 증가시키는 것이 바람직하다.The anchor bolt 41 is preferably used to increase the frictional force with the mortar (22) by using a threaded thread or a spiral reinforcing bar on the outer circumferential surface.

상기 가이드 슬리브(42)는 복수의 앵커볼트(41) 사이에 구비되어 보강파일(3)의 압입을 가이드한다. The guide sleeve 42 is provided between the plurality of anchor bolts 41 to guide the indentation of the reinforcement pile (3).

상기 가이드 슬리브(42)는 보강파일(3) 압입시 기초(2) 내에서 보강파일(3)이 관통되도록 함과 동시에 보강파일(3)의 압입을 가이드하는 것으로서, 천공홀(21) 하부의 지반(1) 상면에 거치될 수 있다.The guide sleeve 42 allows the reinforcement pile 3 to penetrate in the base 2 when the reinforcement pile 3 is press-fitted and guides the press-fit of the reinforcement pile 3. It can be mounted on the upper surface of the ground (1).

상기 지지강봉(43)은 앵커볼트(41)의 상부에 결합된다.The support steel bar 43 is coupled to the upper portion of the anchor bolt (41).

상기 지지강봉(43)은 보강파일(3) 압입시 반력을 앵커볼트(41)를 통해 기초(2)로 전달한다.The supporting steel bar 43 transmits the reaction force when the reinforcement pile 3 is press-fitted to the base 2 through the anchor bolt 41.

상기 지지강봉(43)은 앵커볼트(41)의 상단에 커플러(410)에 의해 고정 가능하다.The support steel bar 43 is fixed to the upper end of the anchor bolt 41 by the coupler 410.

상기 가압플레이트(44)는 지지강봉(43)의 상부에 구비되어 보강파일(3)을 가압한다. The pressure plate 44 is provided on the support steel bar 43 to press the reinforcement pile (3).

상기 가압플레이트(44)는 지지강봉(43)의 상부에 상하 이동 가능하게 구비되는 것으로, 가압플레이트(44)의 상부에는 가압플레이트(44)를 가압하는 유압잭(45)이 거치된다.The pressure plate 44 is provided to be able to move up and down on the support steel bar 43, the hydraulic jack 45 for pressing the pressure plate 44 is mounted on the pressure plate 44.

상기 가압플레이트(44)의 상부로 일정 간격 이격된 위치의 지지강봉(43)에는 유압잭(45)의 상단을 지지하는 상부플레이트(46)가 구비될 수 있다. An upper plate 46 supporting the upper end of the hydraulic jack 45 may be provided at the supporting steel bar 43 at a predetermined distance from the upper side of the pressing plate 44.

도 2 등에 도시된 바와 같이, 상기 앵커볼트(41)의 하단에는 너트(47)가 결합될 수 있다. As shown in FIG. 2, the nut 47 may be coupled to a lower end of the anchor bolt 41.

상기 앵커볼트(41)의 주면 마찰력만으로 보강파일(3)의 압입에 필요한 충분한 크기의 반력을 확보할 수 없는 경우 등을 위하여 앵커볼트(41)의 하단에 너트(47)를 결합하여 모르타르(22) 내에 견고하게 정착되도록 할 수 있다. In order to secure the reaction force of sufficient size necessary for the press-fit of the reinforcement pile 3 only by the frictional force of the main surface of the anchor bolt 41, the nut 47 is coupled to the lower end of the anchor bolt 41 to form a mortar 22. ) Can be firmly settled.

이 경우 지압 면적 확대를 위해 너트(47)의 상부에는 와셔플레이트를 구비할 수 있다. In this case, a washer plate may be provided on the upper portion of the nut 47 to enlarge the acupressure area.

상기 너트(47)는 앵커볼트(41)의 하단에 일체로 형성되는 볼트 헤드일 수도 있다.The nut 47 may be a bolt head integrally formed at the lower end of the anchor bolt 41.

도 3은 확장링크부재 및 커플링플레이트가 구비된 반력대를 도시하는 사시도이고, 도 4는 도 3의 반력대가 설치된 상태를 도시하는 단면도이다.FIG. 3 is a perspective view illustrating a reaction table provided with an expansion link member and a coupling plate, and FIG. 4 is a cross-sectional view showing a state where the reaction table of FIG. 3 is installed.

도 3 및 도 4 등에 도시된 바와 같이, 상기 앵커볼트(41)는 4개로 구비되고, 이웃하는 2개의 앵커볼트(41)의 하단은 각각 한 쌍의 링크바(480)가 서로 접철 가능하게 힌지 결합된 확장링크부재(48)에 의해 결합되도록 구성할 수 있다. As shown in Figure 3 and 4, the anchor bolt 41 is provided with four, the lower end of the two adjacent anchor bolts 41, each of the pair of link bar 480 is hinged to each other foldable It can be configured to be coupled by the expansion link member 48 coupled.

상기 천공홀(21) 내에 앵커볼트(41)가 삽입된 상태에서 콘크리트 기초(2) 하면에 물리적으로 걸려 정착력을 증가시킬 수 있도록 한 쌍의 앵커볼트(41) 하단에 확장링크부재(48)를 구비할 수 있다. Expansion link member 48 at the bottom of the pair of anchor bolts 41 so as to increase the fixing force physically caught on the bottom surface of the concrete foundation (2) in the state in which the anchor bolt 41 is inserted into the drilling hole 21 It may be provided.

상기 확장링크부재(48)는 한 쌍의 링크바(480)가 서로 접철 가능하게 힌지 결합되어 형성되는 것으로, 각 링크바(480)의 일단은 앵커볼트(41)의 하단에 회전 가능하게 결합된다. The expansion link member 48 is formed by a pair of link bars 480 are hinged to each other foldable, one end of each link bar 480 is rotatably coupled to the lower end of the anchor bolt (41). .

도 3, 도 5 등에 도시된 바와 같이, 상기 확장링크부재(48)는 한 쌍의 링크바(480)가 펼쳐진 상태에서의 길이가 천공홀(21)의 지름보다 크게 구성 가능하다. 이에 따라 한 쌍의 링크바(480)가 펼쳐진 상태에서 확장링크부재(48)는 천공홀(21)의 외측을 향해 돌출되게 구성된다. 그러므로 상기 확장링크부재(48)는 천공홀(21) 내에 삽입된 후 기초(2)의 하면에 걸리게 구성 가능하다. As shown in FIG. 3, FIG. 5, etc., the extension link member 48 may have a length greater than a diameter of the drilled hole 21 in the unfolded state of the pair of link bars 480. Accordingly, the expansion link member 48 is configured to protrude toward the outside of the drilling hole 21 in the unfolded state of the pair of link bars 480. Therefore, the expansion link member 48 may be configured to be caught by the lower surface of the foundation 2 after being inserted into the drilling hole 21.

상기 앵커볼트(41)를 천공홀(21) 내에 삽입할 때에는 하단이 확장링크부재(48)에 의해 서로 연결된 한 쌍의 앵커볼트(41)를 서로 근접시킨 상태, 즉 확장링크부재(48)의 링크바(480)가 접힌 상태에서 천공홀(21) 내부로 삽입한다(도 7의 (a)). When the anchor bolt 41 is inserted into the drilling hole 21, a pair of anchor bolts 41 connected to each other by the expansion link member 48 at the lower ends thereof are adjacent to each other, that is, the expansion link member 48 The link bar 480 is inserted into the drilled hole 21 in the folded state (FIG. 7A).

상기 확장링크부재(48)가 천공홀(21)의 하부까지 하강한 후에는 확장링크부재(48)가 천공홀(21) 외부의 기초(2) 하부 측에 위치하도록 앵커볼트(41)를 이동시킨다. After the expansion link member 48 descends to the lower portion of the drilling hole 21, the anchor bolt 41 is moved so that the expansion link member 48 is located on the lower side of the base 2 outside the drilling hole 21. Let's do it.

그리고 한 쌍의 앵커볼트(41)를 서로 벌려 확장링크부재(48)의 링크바(480)가 펼쳐진 상태에서 앵커볼트(41)를 천공홀(21)의 내벽에 밀착시킨다(도 7의 (b)).Then, a pair of anchor bolts 41 are opened to each other and the anchor bolts 41 are brought into close contact with the inner wall of the drilling hole 21 in a state where the link bar 480 of the expansion link member 48 is unfolded (FIG. 7B). )).

또 다른 한 쌍의 앵커볼트(41)도 위와 같은 방식으로 설치한다.Another pair of anchor bolts 41 are also installed in the same manner as above.

상기 앵커볼트(41)의 하단에 링크바(480)가 결합된 상태에서 링크바(480) 하부 위치의 앵커볼트(41)에 너트(47)를 결합하면, 링크바(480)의 이탈을 방지할 수 있다.When the nut 47 is coupled to the anchor bolt 41 at the lower position of the link bar 480 while the link bar 480 is coupled to the bottom of the anchor bolt 41, the separation of the link bar 480 is prevented. can do.

상기 한 쌍의 링크바(480)는 앵커볼트(41)가 결합되는 일측 단부에 앵커볼트(41)가 삽입되는 제1체결홀(481)이 각각 형성된다. 그리고 각 링크바(480)의 타측 단부에는 타측 링크바(480)와의 핀 결합을 위한 제2체결홀(482)이 형성된다(도 5 등). The pair of link bars 480 are formed with first fastening holes 481 into which the anchor bolts 41 are inserted at one end to which the anchor bolts 41 are coupled. A second fastening hole 482 for pin coupling with the other link bar 480 is formed at the other end of each link bar 480 (FIG. 5, etc.).

도 5는 확장링크부재와 커플링플레이트의 결합 관계를 도시하는 사시도이고, 도 6은 확장링크부재와 커플링플레이트의 결합 상태를 도시하는 사시도이다.5 is a perspective view illustrating a coupling relationship between the expansion link member and the coupling plate, and FIG. 6 is a perspective view illustrating a coupling state of the expansion link member and the coupling plate.

도 3, 도 5 및 도 6 등에 도시된 바와 같이, 마주보는 앵커볼트(41)의 하단은 각각 커플링플레이트(49)에 의해 상호 결합할 수 있다. As shown in FIGS. 3, 5 and 6, the lower ends of the facing anchor bolts 41 may be coupled to each other by the coupling plate 49.

여기에서 '마주보는' 앵커볼트(41)는 '이웃하는' 앵커볼트(41)와 직교하는 방향에 위치한 앵커볼트(41)를 의미한다.Here, the 'facing' anchor bolt 41 means the anchor bolt 41 located in a direction orthogonal to the 'neighbor' anchor bolt 41.

상기 커플링플레이트(49)는 마주보는 앵커볼트(41)의 하단을 서로 연결한다.The coupling plate 49 connects the lower ends of the opposite anchor bolts 41 to each other.

이에 따라 이웃하는 한 쌍의 앵커볼트(41)가 확장링크부재(48)로 연결된 한 조의 앵커볼트(41) 세트 2개를 서로 한 쌍의 커플링플레이트(49)로 연결하여 4개의 앵커볼트(41)를 한 번에 시공 가능하다. Accordingly, two sets of anchor bolts 41 connected to each other by the pair of anchor bolts 41 connected to the expansion link member 48 are connected to each other by a pair of coupling plates 49 to provide four anchor bolts ( 41) can be installed at one time.

상기 커플링플레이트(49)와 확장링크부재(48)의 링크바(480)는 서로 겹쳐지게 각 앵커볼트(41)의 하단에 결합된다. The coupling plate 49 and the link bar 480 of the expansion link member 48 are coupled to the bottom of each anchor bolt 41 to overlap each other.

상기 앵커볼트(41)의 최하단에는 너트(47)를 체결하여 커플링플레이트(49)와 링크바(480)의 이탈을 방지하도록 구성할 수 있다. The lower end of the anchor bolt 41 may be configured to prevent the separation of the coupling plate 49 and the link bar 480 by fastening the nut 47.

상기 커플링플레이트(49)는 양단에 앵커볼트(41)가 삽입되는 체결홀(493)이 형성된다. The coupling plate 49 has fastening holes 493 into which anchor bolts 41 are inserted at both ends.

도 7은 확장링크부재와 커플링플레이트의 작동 관계를 도시하는 평면도이다.7 is a plan view showing an operating relationship between the expansion link member and the coupling plate.

도 5 내지 도 7 등에 도시된 바와 같이, 상기 링크바(480)의 타측 링크바(480) 및 커플링플레이트(49)와 힌지 결합되는 체결홀(481, 482)은 장공으로 형성 가능하다. As shown in FIGS. 5 to 7, the coupling holes 481 and 482 hinged to the other link bar 480 and the coupling plate 49 of the link bar 480 may be formed as long holes.

4개의 앵커볼트(41)를 확장링크부재(48)와 커플링플레이트(49)로 연결하여 일체화하는 경우, 확장링크부재(48)가 외부로 돌출되도록 확장하여 펼치면 확장링크부재(48)와의 간섭으로 인해 앵커볼트(41)를 천공홀(21) 내에 삽입하기 어렵다. When the four anchor bolts 41 are integrated by connecting the expansion link member 48 and the coupling plate 49, the expansion link member 48 expands and extends to protrude to the outside, thereby interfering with the expansion link member 48. Due to this, it is difficult to insert the anchor bolt 41 into the drilling hole 21.

따라서 링크바(480)의 양단에 형성된 체결홀(481, 482)을 링크바(480)의 길이 방향으로 길이가 긴 장공으로 형성함으로써, 하나로 일체화된 4개의 앵커볼트(41) 한 세트를 천공홀(21)에 삽입할 때에는 도 7의 (a)와 같이 확장링크부재(48)의 링크바(480)가 접철되도록 내측으로 접는다. Accordingly, by forming the fastening holes 481 and 482 formed at both ends of the link bar 480 into long holes in the length direction of the link bar 480, one set of four anchor bolts 41 integrated into one is drilled. When inserting into 21, the link bar 480 of the expansion link member 48 is folded inwardly as shown in FIG.

그리고 천공홀(21) 내에 앵커볼트(41)를 삽입한 후에는 도 7의 (b)와 같이 확장링크부재(48)를 외측으로 확장하여 펼친 상태를 유지하도록 한다. After the anchor bolt 41 is inserted into the drilling hole 21, the expansion link member 48 is extended to the outside to maintain the expanded state as shown in FIG.

이 경우 상기 확장링크부재(48)가 콘크리트 기초(2) 하면에 물리적으로 걸려 정착력을 증가시킬 수 있다. In this case, the expansion link member 48 may be physically caught on the bottom surface of the concrete foundation 2 to increase the fixing force.

도 5 내지 도 7 등에 도시된 바와 같이, 상기 커플링플레이트(49)는 연결부(491)의 양단에 결합부(492)가 천공홀(21) 내측 방향으로 돌출되도록 구성되고, 상기 확장링크부재(48)의 링크바(480)는 상기 결합부(492)에 힌지 결합되도록 구성할 수 있다. As shown in FIGS. 5 to 7, the coupling plate 49 is configured such that the coupling portion 492 protrudes in the inner direction of the drilling hole 21 at both ends of the connection portion 491, and the expansion link member ( The link bar 480 of the 48 may be configured to be hinged to the coupling portion 492.

상기 확장링크부재(48)뿐 아니라 커플링플레이트(49)도 천공홀(21)의 외측으로 돌출되어 기초(2) 하부에 걸릴 수 있도록 커플링플레이트(49)를 연결부(491)와 결합부(492)로 형성하여 대략 ㄷ자 형을 이루도록 구성할 수 있다.Coupling plate 49 and the coupling portion (491) and the coupling portion (49) so that not only the expansion link member 48 but also the coupling plate (49) protrudes to the outside of the drilling hole (21) to be caught under the foundation (2). 492) can be configured to form an approximately C shape.

상기 확장링크부재(48)와 커플링플레이트(49)는 서로 직교하는 양방향으로 기초(2)의 하부에 걸려 지지되므로, 보다 안정적으로 반력을 지지할 수 있다.Since the expansion link member 48 and the coupling plate 49 are supported by the lower portion of the base 2 in both directions perpendicular to each other, it can support the reaction force more stably.

상기 앵커볼트(41) 삽입을 위하여 커플링플레이트(49)에 형성되는 체결홀(493)은 결합부(492)에 형성 가능하다. A fastening hole 493 formed in the coupling plate 49 for insertion of the anchor bolt 41 may be formed in the coupling portion 492.

도 8은 커플링플레이트의 다른 실시예를 도시하는 평면도이다.8 is a plan view showing another embodiment of the coupling plate.

도 8의 (a) 및 (b)에 도시된 바와 같이, 상기 연결부(491)는 외측면이 천공홀(21)의 내주면에 대응되도록 만곡된 원호 형상으로 구성할 수 있다. As shown in (a) and (b) of FIG. 8, the connection portion 491 may be configured in a circular arc shape so that the outer surface thereof corresponds to the inner circumferential surface of the drilling hole 21.

이 경우 일체화된 4개의 앵커볼트(41) 한 세트를 천공홀(21) 내에 삽입할 때 커플링플레이트(49)의 양 단부가 천공홀(21) 내벽면에 걸려 간섭되지 않는다(도 8의 (a)).In this case, when inserting a set of four integrated anchor bolts 41 into the drilling hole 21, both ends of the coupling plate 49 are caught by the inner wall surface of the drilling hole 21 so as not to interfere (see FIG. a)).

그리고 앵커볼트(41) 세트의 하강이 완료되어 커플링플레이트(49)의 연결부(491)가 기초(2) 하부로 이동한 상태에서는 만곡된 원호 형상인 연결부(491)가 전체 길이에 걸쳐 기초(2) 하부에 걸리므로 정착력을 강화시킬 수 있다(도 8의 (b)).Then, when the lowering of the set of anchor bolts 41 is completed and the connecting portion 491 of the coupling plate 49 is moved to the lower portion of the base 2, the curved circular arc-shaped connecting portion 491 is formed over the entire length ( 2) can be tightened because it is caught in the lower portion (Fig. 8 (b)).

도 9는 본 발명 보강파일 압입용 반력대를 이용한 보강파일 압입 방법의 단계별 공정을 도시하는 도면이다.9 is a view showing a step-by-step process of the reinforcement pile indentation method using a reaction table for press-fitting reinforcement pile of the present invention.

본 발명 보강파일 압입용 반력대를 이용한 보강파일 압입 방법은 도 1 내지 도 8을 참고하여 전술한 본 발명 보강파일 압입용 반력대를 이용하여 보강파일을 압입하는 방법에 관한 것이다. The reinforcement pile press-fitting method using the present invention reinforcing pile press-fitting reaction table relates to a method of press-fitting a reinforcement pile using the present invention reinforcing pile press-fitting reaction table described above with reference to FIGS. 1 to 8.

본 발명 보강파일 압입용 반력대를 이용한 보강파일 압입 방법에서는 먼저 (a) 기초(2)를 천공하여 천공홀(21)을 형성한다(도 9의 (a)). In the reinforcement pile press-fitting method using the reaction table for press-fitting reinforcement pile of the present invention, first, (a) the foundation 2 is drilled to form the drilling hole 21 (FIG. 9A).

상기 천공홀(21)은 앵커볼트(41)를 삽입하여 정착할 수 있도록 보강파일(3)의 압입에 필요한 직경보다 큰 직경으로 형성한다. The drilling hole 21 is formed to a diameter larger than the diameter necessary for the press-fit of the reinforcing pile (3) to be fixed by inserting the anchor bolt (41).

상기 천공홀(21)은 기초(2) 하부의 지반(1) 상부 일부까지 연장되도록 천공하여 앵커볼트(41)의 충분한 정착 길이를 확보할 수 있도록 구성함이 바람직하다.The drilling hole 21 is preferably configured to ensure a sufficient fixing length of the anchor bolt 41 by drilling to extend to the upper part of the ground (1) below the base (2).

또한, 지반(1) 상부 부분에는 기초(2)의 천공홀(21)보다 직경이 큰 천공홀을 형성함으로써, 하부에 지름이 확대된 정착 구근을 형성하여 반력을 보다 확실하게 지지하도록 구성할 수 있다. In addition, by forming a drill hole having a diameter larger than that of the drill hole 21 of the foundation 2 in the upper part of the ground 1, a fixing bulb having an enlarged diameter can be formed in the lower part to more reliably support the reaction force. have.

그리고 (b) 상기 천공홀(21) 내에 앵커볼트(41)를 삽입하고, 앵커볼트(41) 사이에 가이드 슬리브(42)를 삽입한다(도 9의 (b)).And (b) the anchor bolt 41 is inserted into the drilling hole 21, the guide sleeve 42 is inserted between the anchor bolt 41 (Fig. 9 (b)).

상기 천공홀(21) 내에 복수의 앵커볼트(41)를 삽입한 후에는 앵커볼트(41)를 천공홀(21) 내벽면 측으로 밀착하여 천공홀(21) 내부에 소정의 공간을 확보하도록 한다. 이후, 보강파일(3) 근입시 보강파일(3)이 관통될 수 있도록 보강파일(3)의 지름보다 내경이 큰 가이드 슬리브(42)를 천공홀(21) 내에 삽입한다.After the plurality of anchor bolts 41 are inserted into the drilling holes 21, the anchor bolts 41 are brought into close contact with the inner wall surface of the drilling holes 21 to secure a predetermined space inside the drilling holes 21. Thereafter, a guide sleeve 42 having a larger inner diameter than the diameter of the reinforcing pile 3 is inserted into the drilling hole 21 so that the reinforcing pile 3 can penetrate when the reinforcing pile 3 is moved in.

상기 가이드 슬리브(42)는 지반(1) 상부에 거치하여, 후술할 모르타르(22) 충전 단계에서 모르타르(22)가 가이드 슬리브(42) 내로 흘러들어가 가이드 슬리브(42)가 막히는 것을 방지하도록 한다.The guide sleeve 42 is mounted on the ground 1 to prevent the mortar 22 from flowing into the guide sleeve 42 to prevent the guide sleeve 42 from being blocked in the mortar 22 filling step to be described later.

상기 가이드 슬리브(42)가 천공홀(21) 내에서 수직도를 확보할 수 있도록 스페이서(미도시) 등을 설치할 수 있다. Spacers (not shown) may be installed to allow the guide sleeve 42 to secure a vertical degree in the drilling hole 21.

다음으로, (c) 상기 천공홀(21) 내에 모르타르(22)를 충전하여 앵커볼트(41)를 정착한다(도 9의 (c)).Next, (c) the anchor bolt 41 is fixed by filling the mortar 22 in the drilling hole 21 ((c) of FIG. 9).

상기 (c) 단계에서는 상기 천공홀(21) 내부, 즉 가이드 슬리브(42)의 외부에 모르타르(22)를 충전하고 양생하여 앵커볼트(41)들을 견고하게 정착 고정한다.In the step (c), the anchor bolts 41 are firmly fixed and fixed by filling and curing the mortar 22 inside the drilling hole 21, that is, the outside of the guide sleeve 42.

이후, (d) 상기 앵커볼트(41)의 상부에 지지강봉(43), 가압플레이트(44) 및 유압잭(45)을 설치한다(도 9의 (d)).Subsequently, (d) install the supporting steel bar 43, the pressure plate 44 and the hydraulic jack 45 on the upper portion of the anchor bolt 41 (Fig. 9 (d)).

상기 (c) 단계를 거쳐 앵커볼트(41)의 정착이 완료된 후에는 앵커볼트(41)의 상부에 보강파일(3) 압입을 위한 지지강봉(43), 가압플레이트(44), 유압잭(45) 등을 설치한다. After the fixing of the anchor bolt 41 through the step (c) is completed, the supporting steel bar 43, the pressure plate 44, the hydraulic jack 45 for press-fitting the reinforcement pile 3 on the upper part of the anchor bolt 41 Install the lamp.

마지막으로 (e) 상기 가압플레이트(44)의 하부에 보강파일(3)을 위치시키고 유압잭(45)을 가동하여 보강파일(3)을 가이드 슬리브(42)를 통해 지반(1) 내에 압입한다(도 9의 (e)).Finally, (e) the reinforcement pile 3 is placed under the pressing plate 44 and the hydraulic jack 45 is operated to press the reinforcement pile 3 into the ground 1 through the guide sleeve 42 ( (E)).

즉, 상기 가압플레이트(44)의 하부에 보강파일(3)을 위치시키고, 유압잭(45)을 신장하여 가압플레이트(44)로 보강파일(3)을 가압함으로써 지반(1) 내에 보강파일(3)을 압입한다.That is, the reinforcement pile 3 is placed in the ground 1 by placing the reinforcement pile 3 in the lower portion of the pressing plate 44, and extending the hydraulic jack 45 to press the reinforcement pile 3 with the pressure plate 44. )

상기 유압잭(45)은 1회 신장 길이가 한정되어 있다. 그러므로 유압잭(45)의 신축을 반복하면서 필요한 깊이만큼 보강파일(3)을 지반(1)에 압입한다.The hydraulic jack 45 is limited to one extension length. Therefore, the reinforcement pile 3 is press-fitted into the ground 1 to the required depth while repeating expansion and contraction of the hydraulic jack 45.

상기 보강파일(3)을 지반(1) 내에 압입한 후에는 가이드 슬리브(42) 내에 모르타르(22)를 충전하여 보강파일(3)의 두부를 기초(2)에 정착할 수 있다.After the reinforcement pile 3 is press-fitted into the ground 1, the mortar 22 may be filled in the guide sleeve 42 to fix the head of the reinforcement pile 3 to the foundation 2.

경우에 따라 가이드 슬리브(42)는 인발하여 제거 가능하다. In some cases, the guide sleeve 42 is pulled out and removable.

또한, 기초(2) 상부에 신설 기초가 추가 설치되는 경우, 보강파일(3)의 두부는 신설 기초 내부에 정착 가능하다. In addition, when a new foundation is additionally installed above the foundation 2, the head of the reinforcement pile 3 can be fixed inside the newly constructed foundation.

1: 지반 2: 기초
21: 천공홀 22: 모르타르
3: 보강파일 4: 반력대
41: 앵커볼트 410: 커플러
42: 가이드 슬리브 43: 지지강봉
44: 가압플레이트 45: 유압잭
46: 상부플레이트 47: 너트
48: 확장링크부재 480: 링크바
481: 제1체결홀 482: 제2체결홀
49: 커플링플레이트 491: 연결부
492: 결합부 493: 체결홀
1: ground 2: foundation
21: Punched Hole 22: Mortar
3: reinforcement pile 4: reaction table
41: anchor bolt 410: coupler
42: guide sleeve 43: support steel bar
44: pressure plate 45: hydraulic jack
46: upper plate 47: nut
48: extension link member 480: link bar
481: first fastening hole 482: second fastening hole
49: coupling plate 491: connection
492: coupling portion 493: fastening holes

Claims (8)

기초(2)의 하부에 보강파일(3)을 압입하기 위한 것으로,
상하단이 각각 기초(2)의 상하부로 돌출되도록 콘크리트 기초(2)에 형성된 천공홀(21)에 삽입되어 천공홀(21) 내부에 충전되는 모르타르(22)에 의해 정착되는 4개의 앵커볼트(41);
상기 복수의 앵커볼트(41) 사이에 구비되어 보강파일(3)의 압입을 가이드하는 가이드 슬리브(42);
상기 앵커볼트(41)의 상부에 결합되는 지지강봉(43);
상기 지지강봉(43)의 상부에 구비되어 보강파일(3)을 가압하는 가압플레이트(44);
상기 가압플레이트(44)의 상부에 구비되어 가압플레이트(44)를 가압하는 유압잭(45);
서로 접철 가능하게 힌지 결합된 한 쌍의 링크바(480)로 구성되어 이웃하는 2개의 앵커볼트(41)를 각각 결합하는 확장링크부재(48); 및
마주보는 앵커볼트(41)의 하단을 각각 상호 연결하는 커플링플레이트(49); 로 구성되는 것을 특징으로 하는 보강파일 압입용 반력대.
For pressing the reinforcement pile 3 in the lower part of the foundation 2,
Four anchor bolts 41 are inserted into the boring holes 21 formed in the concrete foundation 2 so that the upper and lower ends thereof protrude to the upper and lower portions of the foundation 2 and are fixed by the mortar 22 filled in the boring holes 21. );
A guide sleeve 42 provided between the plurality of anchor bolts 41 to guide the indentation of the reinforcement pile 3;
A support steel bar 43 coupled to an upper portion of the anchor bolt 41;
A pressure plate 44 provided on the support steel bar 43 to pressurize the reinforcement pile 3;
A hydraulic jack 45 provided on the pressure plate 44 to pressurize the pressure plate 44;
An expansion link member 48 composed of a pair of link bars 480 hingedly foldable to each other to couple two adjacent anchor bolts 41; And
Coupling plates 49 for connecting the lower ends of the opposite anchor bolts 41, respectively; Reinforcement pile press reaction unit characterized in that consisting of.
제1항에서,
상기 앵커볼트(41)의 하단에는 너트(47)가 결합되는 것을 특징으로 하는 보강파일 압입용 반력대.
In claim 1,
Reinforcement pile press reaction force, characterized in that the nut 47 is coupled to the lower end of the anchor bolt (41).
삭제delete 삭제delete 제1항에서,
상기 링크바(480)의 타측 링크바(480) 및 커플링플레이트(49)와 힌지 결합되는 체결홀(481, 482)은 장공으로 형성되는 것을 특징으로 하는 보강파일 압입용 반력대.
In claim 1,
Reinforcement pile for press-fitting reinforcement pile, characterized in that the coupling hole (481, 482) hinged to the other link bar 480 and the coupling plate 49 of the link bar 480 is formed in a long hole.
제5항에서,
상기 커플링플레이트(49)는 연결부(491)의 양단에 결합부(492)가 천공홀(21) 내측 방향으로 돌출되도록 구성되고, 상기 확장링크부재(48)의 링크바(480)는 상기 결합부(492)에 힌지 결합되는 것을 특징으로 하는 보강파일 압입용 반력대.
In claim 5,
The coupling plate 49 is configured such that the coupling portion 492 protrudes in the inward direction of the drilling hole 21 at both ends of the connection portion 491, and the link bar 480 of the expansion link member 48 is coupled to the coupling portion 491. Reinforcing pile press-fitting reaction table, characterized in that the hinge coupled to the portion (492).
제6항에서,
상기 연결부(491)는 외측면이 천공홀(21)의 내주면에 대응되도록 만곡된 원호 형상인 것을 특징으로 하는 보강파일 압입용 반력대.
In claim 6,
The connecting portion 491 has a circular arc shape that the outer surface is curved so as to correspond to the inner circumferential surface of the drilling hole (21).
제1항에 의한 보강파일 압입용 반력대를 이용한 보강파일 압입 방법에 관한 것으로,
(a) 기초(2)를 천공하여 천공홀(21)을 형성하는 단계;
(b) 상기 천공홀(21) 내에 앵커볼트(41)를 삽입하고, 앵커볼트(41) 사이에 가이드 슬리브(42)를 삽입하는 단계;
(c) 상기 천공홀(21) 내에 모르타르(22)를 충전하여 앵커볼트(41)를 정착하는 단계;
(d) 상기 앵커볼트(41)의 상부에 지지강봉(43), 가압플레이트(44) 및 유압잭(45)을 설치하는 단계; 및
(e) 상기 가압플레이트(44)의 하부에 보강파일(3)을 위치시키고 유압잭(45)을 가동하여 보강파일(3)을 가이드 슬리브(42)를 통해 지반(1) 내에 압입시키는 단계; 를 포함하여 구성되는 것을 특징으로 하는 보강파일 압입용 반력대를 이용한 보강파일 압입 방법.
Regarding the reinforcement pile indentation method using the reaction force for the reinforcement pile indentation according to claim 1,
(a) perforating the foundation 2 to form the perforation hole 21;
(b) inserting an anchor bolt 41 into the drilling hole 21 and inserting a guide sleeve 42 between the anchor bolts 41;
(c) fixing the anchor bolts 41 by filling the mortars 22 in the drilling holes 21;
(d) installing a supporting steel bar 43, a pressure plate 44, and a hydraulic jack 45 on an upper portion of the anchor bolt 41; And
(e) placing the reinforcement pile (3) in the lower portion of the pressing plate (44) and operating the hydraulic jack (45) to press the reinforcement pile (3) into the ground (1) through the guide sleeve (42); Reinforcement pile press-fitting method using the reinforcing pile press-fitting reaction table, characterized in that comprising a.
KR1020190062749A 2019-05-28 2019-05-28 Reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same KR102017731B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190062749A KR102017731B1 (en) 2019-05-28 2019-05-28 Reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190062749A KR102017731B1 (en) 2019-05-28 2019-05-28 Reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same

Publications (1)

Publication Number Publication Date
KR102017731B1 true KR102017731B1 (en) 2019-09-03

Family

ID=67951876

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190062749A KR102017731B1 (en) 2019-05-28 2019-05-28 Reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same

Country Status (1)

Country Link
KR (1) KR102017731B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102199641B1 (en) * 2019-09-19 2021-01-07 김성수 Construction method of driven pile for newly built structure
KR102329929B1 (en) * 2021-03-02 2021-11-23 김진기 Floating matter removal device for sewage treatment in sewage treatment plant

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101196459B1 (en) * 2012-06-04 2012-11-01 김인호 Anchor with enlarged connection member for nut and reinforcing construction method therewith

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101196459B1 (en) * 2012-06-04 2012-11-01 김인호 Anchor with enlarged connection member for nut and reinforcing construction method therewith

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102199641B1 (en) * 2019-09-19 2021-01-07 김성수 Construction method of driven pile for newly built structure
KR102329929B1 (en) * 2021-03-02 2021-11-23 김진기 Floating matter removal device for sewage treatment in sewage treatment plant

Similar Documents

Publication Publication Date Title
KR100654228B1 (en) Structure lifting method possible to be re-lifting using pile member
KR100938916B1 (en) Downward method by front reaming
KR101196459B1 (en) Anchor with enlarged connection member for nut and reinforcing construction method therewith
KR102017731B1 (en) Reaction bed for pressing in reinforcing pile and pressing in method of reinforcing pile using the same
KR101103530B1 (en) Apparatus for restoration of disparity sinking construction or introducing pre-stress of pipe pile
KR102159906B1 (en) Leading-edge extention tipe nail fixing device
KR101377019B1 (en) Reactive forcing device using guide rail and foundation reinforcing method therewith
KR20160015099A (en) Micropile reinforcement structure and Reinforcing method of foot concrete using it
KR101871118B1 (en) Pile head reinforcement structure using drilling bit capable of multistage expansion using unwelded coupler and pile construction method using it
KR100778137B1 (en) Bracket and Support for Prestressed Scaffolding System
KR102190480B1 (en) Implant pile pressing apparatus in architecture foundation system and a universal implant piling method
KR102092514B1 (en) Ground drilling method for foundation reinforcement
KR100714434B1 (en) A bracing for reinforcing support
JP3899094B2 (en) Foundation reinforcement method for existing structures by press-fitting steel pipe piles
KR101362173B1 (en) Fold type anchor reactive device and pile construction method therewith
KR20150085602A (en) Foundation structure and construction method thereof
KR20000064205A (en) Reinforcement structure for a foundation pile
KR102231707B1 (en) Method for fixing seismic reinforcing member to foundation and foundation reinforcement assembly therefor
KR102480876B1 (en) Structure for reinforcing foundation using steel piles and construction method thereof
KR101528846B1 (en) Reactive forcing device using jack lifting apparatus and foundation reinforcing method therewith
KR102124772B1 (en) Self-supporting retaining wall and construction method using it
KR101943185B1 (en) Foot Concrete Reinforcing Method Using Micropile And Dispersion Plate
KR102050170B1 (en) Foundation enlargement method for strengthening and lifting the foundation of a structure
CN109488341B (en) Supporting method and supporting structure of curtain frame type underground excavation system
KR101517169B1 (en) The the underground structure to equip the pressing dievice

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant