KR101505579B1 - Prestressed precast concrete using pipe rack or beam column joint structure and construction method of the same - Google Patents

Prestressed precast concrete using pipe rack or beam column joint structure and construction method of the same Download PDF

Info

Publication number
KR101505579B1
KR101505579B1 KR1020120128144A KR20120128144A KR101505579B1 KR 101505579 B1 KR101505579 B1 KR 101505579B1 KR 1020120128144 A KR1020120128144 A KR 1020120128144A KR 20120128144 A KR20120128144 A KR 20120128144A KR 101505579 B1 KR101505579 B1 KR 101505579B1
Authority
KR
South Korea
Prior art keywords
column
stringers
fixing
precast concrete
concrete
Prior art date
Application number
KR1020120128144A
Other languages
Korean (ko)
Other versions
KR20140061031A (en
Inventor
이석
Original Assignee
이석
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이석 filed Critical 이석
Priority to KR1020120128144A priority Critical patent/KR101505579B1/en
Publication of KR20140061031A publication Critical patent/KR20140061031A/en
Application granted granted Critical
Publication of KR101505579B1 publication Critical patent/KR101505579B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/46Foundations for supply conduits or other canals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/10Ducts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Electromagnetism (AREA)
  • Physics & Mathematics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

본 발명은 기둥과 보를 프리캐스트 콘크리트로 구성하여 시공 비용을 대폭 절감하고, 보가 긴장력에 의해 기둥에 접합되어 접합력이 우수하며, 보의 휨 응력을 증대시킬 수 있도록 한 프리캐스트 콘크리트를 이용한 파이프 렉 및 그의 시공 방법을 제공한다. 본 발명의 적절한 일 실시 형태에 따른 프리캐스트 콘크리트를 이용한 파이프 렉의 시공 방법은, (a) 지반의 기초구조물에 각기 세로 방향으로 복수열로 배치되고 일정 높이마다 돌출된 복수 개의 브라켓을 포함하고 있는 PC 기둥을 수직으로 설치시켜 놓는 단계와; (b) 세로 방향과 가로 방향으로 이웃한 PC 기둥을 순차적으로 선택하여 서로 마주보게 된 대향된 브라켓에 PC 가로보 및 PC 세로보를 거치시켜 놓는 단계와; (c) 다수 개의 긴장재를 각기 PC 세로보에 설치된 어느 한 쪽의 정착판을 통해서 인입시켜 PC 기둥을 삽통한 후 긴장재 정착홈에 노출되도록 설치하는 단계; 및 (d) 상기 다수개의 긴장재를 각기 긴장시켜 양단을 정착장치를 통해 각기 정착판에 고정시켜 놓는 단계를 통하여 시공되는 것을 특징으로 하다.The present invention relates to a pre-cast concrete using pipe precast concrete, which is constructed by precast concrete, and which can reduce the construction cost greatly, And provides his method of construction. A method of constructing a pipelike using a precast concrete according to a preferred embodiment of the present invention includes: (a) a plurality of brackets arranged in a plurality of columns in a longitudinal direction on a foundation structure of a ground and projecting at a predetermined height Placing a PC column vertically; (b) sequentially arranging PC columns adjacent to each other in the longitudinal direction and the lateral direction and placing the PC side beam and the PC side beam on an opposing bracket facing each other; (c) inserting a plurality of tension members through one of the fixing plates installed on the PC stringers, inserting the PC columns and exposing them to the tension member fixing grooves; And (d) fixing each of the plurality of tension members to the fixing plate through a fixing device while tensing each of the plurality of tension members.

Description

프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조 및 그의 시공 방법{Prestressed precast concrete using pipe rack or beam column joint structure and construction method of the same}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a precast concrete precast concrete structure and a precast concrete precast concrete structure using the precast concrete precast concrete,

본 발명은 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 또는 보 기둥 접합구조 및 그 시공방법에 관한 것으로, 특히 기둥과 보를 프리캐스트 콘크리트로 구성하여 시공 비용을 대폭 절감할 수 있고, 보가 긴장력의 도입으로 기둥에 접합되어 접합력이 우수하고, 보의 휨 응력을 증대시킬 수 있도록 한 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조 및 그의 시공 방법에 관한 것이다.The present invention relates to a pipe lap or beam joining structure using a prestressed precast concrete and a construction method thereof. In particular, it is possible to drastically reduce the construction cost by constructing a column and a beam with precast concrete, The present invention relates to a pipe-lay structure or a beam-column joint structure using a prestressed precast concrete which is excellent in bonding strength and can increase bending stress of a beam and a construction method thereof.

일반적으로 석유 화학 공장과 같이 원료를 수송하기 위해 가스관, 송유관 등이 사용된다. 이러한 운송 관로의 정리 및 떠 받치기 위한 시설물로 파이프 렉이 건설되어 진다.Generally, gas pipes and pipelines are used to transport raw materials, such as petrochemical plants. Pipelets are constructed as facilities for arranging and supporting such transportation pipelines.

파이프 렉을 철골 구조로 시공할 경우 원자재의 고비용으로 시공비가 상승하는 문제가 있다. 따라서 시공비를 절감할 수 있는 대안으로 프리캐스트 콘크리트로 제작된 기둥과 보를 이용한 방안이 아래 본 발명의 배경 기술에 제시되어 있다.When pipelets are constructed with steel structure, there is a problem that the cost of construction increases due to high cost of raw materials. Therefore, a method using columns and beams made of precast concrete as an alternative to reduce the construction cost is presented in the Background of the Invention below.

본 발명의 배경이 되는 기술로는 한국 등록특허 등록번호 제10-1033693호(명칭: 프리캐스트 콘크리트부재로 조립된 파이프 렉)가 있다. 이는 프리캐스트 콘크리트 부재로 제작되며 횡방향과 종방향으로 각각 배열되며 기초부에 수직으로 설치되는 4개 이상의 칼럼, 상기 횡방향의 2개의 칼럼 사이에 수평으로 설치되는 것으로서 프리텐션이 적용된 프리캐스트 콘크리트 부재로 제작되며 내부에 중공부가 형성되어 있고 칼럼과의 사이에 포스트텐션이 적용되어 고정연결구조로 연결되고 각종 파이프들이 배설되는 다수의 횡방향 빔, 그리고 상기 종방향의 2개의 칼럼 사이에 수평으로 설치되는 것으로 프리텐션이 적용된 프리캐스트 콘크리트 부재로 제작되며 내부에 중공부가 형성되어 있고 칼럼과의 사이에 힌지 연결구조로 연결되는 다수의 종방향 빔을 포함한다.As a background of the present invention, there is Korean Registered Patent Registration No. 10-1033693 (name: Pipe-lak assembled with precast concrete member). It consists of four or more columns made of precast concrete members and respectively arranged in the lateral and longitudinal directions and perpendicular to the base, A plurality of transversal beams each having a hollow portion formed therein, a post tension applied between the column and the column, connected by a fixed connection structure, and various pipes disposed therein, and a plurality of horizontal beams horizontally And a plurality of longitudinal beams, which are made of pre-cast concrete members to which pre-tension is applied, and which have a hollow portion formed therein and are connected by a hinge connection structure with the column.

상기 배경기술은 종방향 빔이 힌지로 칼럼(기둥)에 연결되어 있는 힌지 연결구조를 갖는다. 그러나 이같이 힌지 연결구조의 경우 기둥과 보의 접합력을 증대시키기가 어렵다. 이는 힌지 연결을 위해 하나의 철근 또는 하나의 앵커볼트를 통해 종방향 빔이 칼럼에 연결될 수 밖에 없기 때문이다. 또한 종방향 빔에는 프리스트레스가 도입된 강선이 설치되어 종방향 빔 자체의 휨 응력을 증대시키나 종방향 빔의 단부측 접합부에는 긴장력에 의한 접합력을 생성시키지 못하는 문제가 있다.The background art has a hinge connection structure in which a longitudinal beam is connected to a column (column) by a hinge. However, in the case of the hinge connection structure, it is difficult to increase the joining force between the column and the beam. This is because the longitudinal beam must be connected to the column through one reinforcing bar or one anchor bolt for hinge connection. In addition, a steel wire with a prestress is installed in the longitudinal beam to increase the bending stress of the longitudinal beam itself, but there is a problem that the joint force due to the tension is not generated at the end side joint portion of the longitudinal beam.

미국 특허 제2311932호U.S. Patent No. 2311932 미국 특허 제5190337호U.S. Patent No. 5190337

본 발명은 기둥과 보를 프리캐스트 콘크리트로 구성하여 시공 비용을 대폭 절감하고, 보가 긴장력에 의해 기둥에 접합되어 접합력이 우수하며, 보의 휨 응력을 증대시킬 수 있도록 한 프리캐스트 콘크리트를 이용한 파이프 렉 및 그의 시공 방법을 제공함에 그 목적이 있다.The present invention relates to a pre-cast concrete using pipe precast concrete, which is constructed by precast concrete, and which can reduce the construction cost greatly, The purpose of his construction method is to provide.

본 발명의 적절한 일 실시 형태에 따른 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조의 시공 방법은,A method of constructing a pipelock structure or a beam-column joint structure using a prestressed precast concrete according to a preferred embodiment of the present invention,

(a) 지반의 기초구조물에 각기 세로 방향으로 복수열로 배치되고 일정 높이마다 돌출된 복수 개의 브라켓을 포함하고 있는 PC 기둥을 수직으로 설치시켜 놓는 단계와;(a) vertically installing a PC column including a plurality of brackets arranged in a plurality of rows in a longitudinal direction on a foundation structure of the ground and projecting at a predetermined height;

(b) 세로 방향과 가로 방향으로 이웃한 PC 기둥을 순차적으로 선택하여 서로 마주보게 된 대향된 브라켓에 PC 가로보 및 PC 세로보를 거치시켜 놓는 단계와;(b) sequentially arranging PC columns adjacent to each other in the longitudinal direction and the lateral direction and placing the PC side beam and the PC side beam on an opposing bracket facing each other;

(c) 다수 개의 긴장재를 각기 PC 세로보에 설치된 어느 한 쪽의 정착판을 통해서 인입시켜 PC 기둥을 삽통한 후 긴장재 정착홈에 노출되도록 설치하는 단계; 및(c) inserting a plurality of tension members through one of the fixing plates installed on the PC stringers, inserting the PC columns and exposing them to the tension member fixing grooves; And

(d) 상기 다수개의 긴장재를 각기 긴장시켜 양단을 정착장치를 통해 각기 정착판에 고정시켜 놓는 단계를 통하여 시공되는 것을 특징으로 하다.(d) tightening the plurality of tension members and fixing the both ends to the fixing plate through a fixing device.

이때, 상기 기초구조물은 기초 베이스와, 기초 베이스와 다수의 연결철근을 통해 기초 베이스 상면에 장착된 PC 푸팅과, PC 푸팅에 하단이 매설되어 상방으로 돌출되어 있는 다수 개의 텐션볼트를 갖고, 상기 PC 기둥의 하단부는 상기 텐션볼트에 삽입되어 텐션볼트에 나사 체결된 너트에 의해 고정되어 시공될 수 있다.The base structure includes a base foot, a PC footing mounted on an upper surface of the base through a base base and a plurality of connecting reinforcing bars, and a plurality of tension bolts whose lower ends are embedded in the PC footing and protruded upward, The lower end of the column may be fixed by a nut inserted into the tension bolt and screwed to the tension bolt.

또한, 상기 PC 기둥과 PC 세로보에는 다수의 긴장재를 인입시기키 위한 동수의 쉬스관이 미리 설치되어 시공될 수 있다.In addition, the PC column and the PC string can be installed in advance with the same number of sheath pipes for introducing a plurality of tension members.

또한, 상기 (c)단계와 (d)단계는 PC 세로보의 중앙 길이 방향으로 절단된 종단면을 기준으로 좌우 대칭적으로 2개소에서 실시될 수 있다.In addition, the steps (c) and (d) may be performed symmetrically at two locations with respect to the vertical longitudinal section of the PC stringer.

또한, 긴장재 정착홈은 PC 세로보의 좌우 측면에 형성되어 시공될 수 있다.In addition, the tension member fixing grooves can be formed on the left and right side surfaces of the PC string.

본 발명의 적절한 다른 실시 형태에 따른 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조의 시공 방법은,According to another preferred embodiment of the present invention, there is provided a method of constructing a pipelock structure or a beam-column joint structure using a prestressed precast concrete,

(a) 지반의 기초구조물에 각기 길이 방향으로 일정 높이마다 돌출된 복수 개의 브라켓을 포함하고 있는 PC 기둥을 입설시켜 놓는 단계와;(a) establishing a PC column including a plurality of brackets protruding at a predetermined height in the longitudinal direction on the foundation structure of the ground;

(b) 가로 방향과 세로 방향으로 이웃한 2개의 기둥을 순차적으로 선택하여 서로 마주보게 된 대향된 브라켓에 PC 가로보와 PC 세로보를 각기 거치시켜 놓은 후 PC 세로보에 각기 구비된 다수 개의 쉬스관을 상호 일치되도록 접속시키는 단계와;(b) Two columns adjacent to each other in the transverse direction and the longitudinal direction are sequentially selected, and the PC beam and the PC string are mounted on the opposed brackets facing each other, and then a plurality of sheath tubes provided in the PC string are connected to each other To be matched;

(c) PC 기둥과 수평 방향으로 교차되는 양쪽 2개의 PC 세로보를 선택하여 다수 개의 긴장재를 상기 쉬스관에 각기 삽입시켜 PC 세로보의 긴장재 정착홈에 설치된 정착판에 지지시켜 놓는 단계와;(c) selecting two PC stringers on both sides of the PC column in a horizontal direction, inserting a plurality of tension members into the sheath tube and supporting the same on a fixing plate installed in a tension member fixing groove of the PC stringer;

(d) 상기 PC 세로보에 형성된 쉬스관 매설홈에 콘크리트를 타설하는 단계; 및(d) casting concrete into a sheath tube buried groove formed in the PC stringer; And

(d) 콘크리트의 양생 후 긴장재를 긴장시켜 정착장치를 이용하여 정착판에 고정시켜 놓는 단계;를 통하여 시공되는 것을 특징으로 한다.(d) tightening the tension material after curing of the concrete and fixing it to the fixing plate by using a fixing device.

이때, 긴장재 정착홈은 상방으로 개구(開口)되어 있고, 쉬스관 매설홈은 양단에 상방과 말단으로 모두 개구(開口)된 구조를 가지고 시공될 수 있다.At this time, the tension member fixing grooves are opened upward, and the recesses of the sheath tube can be formed to have openings both at the upper and lower ends at both ends thereof.

또한, 상기 PC 기둥에는 PC 세로보와의 접합 부분에 쉬스관 매설홈과 연통되는 PC 기둥 개구부가 형성되어 시공될 수 있다.In addition, the PC column may be formed with a PC column opening portion communicating with a recess formed in the sheath pipe at a joint portion with a PC string.

또한, 본 발명은 제시된 실시 예들의 시공 방법으로 시공된 파이프 렉에 PC 세로보의 상면으로 현장 콘크리트를 타설하거나 PC 슬래브 또는 데크플레이트를 설치하여 슬라브가 더 시공되어 PC 기둥과 PC 보의 접합부에 긴장재가 도입된 건축 구조물이 시공될 수 있다.In addition, in the present invention, a concrete slab or a deck plate is installed on a top surface of a PC column in a pipeline constructed by the method of the present invention, and a slab is further installed so that a tensile material is applied to the joint between the PC column and the PC beam The introduced architectural structure can be constructed.

본 발명에 따른 프리캐스트 콘크리트를 이용한 파이프 렉 및 그의 시공 방법은, 기둥과 보를 프리캐스트 콘크리트로 구성하여 시공 비용을 대폭 절감할 수 있고, 용접이 불필요하여 공기를 단축시킬 수 있다.The pipelag and the construction method using the precast concrete according to the present invention can greatly reduce the construction cost by constructing the column and the beam with precast concrete and can shorten the air because the welding is unnecessary.

또한, 2개의 보가 긴장재의 긴장력에 의해 하나의 기둥에 동시 접합되는 시공 방법으로써 접합력이 우수하며, 접합부에서 발생된 긴장재의 긴장력에 의해 보의 휨 응력을 증대시킬 수 있어 파이프 렉의 구조적 안전성을 향상시킨다.Also, it is possible to increase the bending stress of the beam due to the tensile force of the tension material generated at the joint, thereby improving the structural safety of the pipe girder. .

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1 내지 도 7b는 본 발명에 관련된 도면으로,
도 1은 본 발명의 제1 실시 예에 따른 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조의 일부분 사시도이고,
도 2a는 기초구조물의 시공 상태도이고,
도 2b는 기초구조물의 확대도이고,
도 3은 PC 기둥의 시공 상태도이고,
도 4는 1층에 시공된 PC 가로보와 PC 세로보의 시공상태도이고,
도 5a는 1층에 시공된 PC 가로보의 시공상태도이고,
도 5b는 PC 세로보를 접합시키기 위한 긴장재의 배치 및 정착된 설치상태도이고,
도 6a는 본 발명의 제2 실시 예에 따른 PC 기둥과 PC 세로보의 거치 및 긴장재의 배치상태도이고,
도 6b는 도 6a의 일부확대도이고,
도 6c는 본 발명의 제2 실시 예에 따른 PC 세로보를 접합시키는 긴장재의 배치 및 정착상태도이고,
도 7a는 본 발명의 제3 실시 예에 따른 PC 기둥과 PC 세로보의 거치 및 긴장재의 배치상태도이고,
도 7b는 도 7a의 PC 세로보에 시공된 슬라브를 나타내는 건축 구조물의 시공 상태도이다.
BRIEF DESCRIPTION OF THE DRAWINGS The accompanying drawings, which are incorporated in and constitute a part of the specification, illustrate exemplary embodiments of the invention and, together with the description, serve to explain the principles of the invention, Shall not be construed as limiting.
1 to 7B are drawings related to the present invention,
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view of a part of a pipelike structure or a beam-column joint structure using a prestressed precast concrete according to a first embodiment of the present invention,
2A is a construction diagram of a foundation structure,
2B is an enlarged view of the base structure,
3 is a construction diagram of a PC column,
FIG. 4 is a construction diagram of the PC beam and the PC string installed on the first floor,
FIG. 5A is a construction diagram of the PC beam installed on the first floor,
FIG. 5B is a view showing an installation state of the tension members for fixing the PC string, and FIG.
FIG. 6A is a view showing the arrangement of a PC column and a PC string and a placement of a tension member according to a second embodiment of the present invention,
Figure 6b is a partial enlarged view of Figure 6a,
FIG. 6C is a view showing the placement and fixing of the tension member for connecting the PC string according to the second embodiment of the present invention,
FIG. 7A is a view showing the placement of a PC column and a PC string and a placement of a tension member according to a third embodiment of the present invention,
FIG. 7B is a construction diagram of a construction structure showing a slab constructed in the PC string of FIG. 7A. FIG.

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below with reference to the embodiments shown in the accompanying drawings, but the present invention is not limited thereto.

본 발명은 프리캐스팅 콘크리트(PC: Precast Concrete)로 제작된 PC 기둥과 PC 세로보가 제작된 후 이를 현장에서 긴장재로 긴장력을 도입하여 PC 세로보를 PC 기둥에 접합시키는 공법을 사용하여 파이프 렉 구조체를 시공하게 되어 있다.The present invention relates to a method for constructing a pipelec structure by using a method in which a PC column and a PC column made of precast concrete (PC: Precast Concrete) are manufactured, .

이때 PC 세로보에 도입되는 긴장재의 긴장 전에 콘크리트의 타설 여부에 따라 2가지 실시 예로 나눌 수 있다. 또한 이를 이용하여 건축 구조물을 시공하는 실시 예가 추가된다.In this case, there are two examples according to whether or not concrete is inserted before tension of a tension member introduced into a PC stringer. In addition, an embodiment of constructing an architectural structure is added.

본 명세서에서 PC는 프리캐스트 콘크리트(Precast Concrete)를 줄인 축약어로 사용한다. 따라서 후술할 PC 기둥(12), PC 세로보(14A,14B,14C,14D) 및 PC 가로보(13)는 몰드에 철근이 배근된 후 콘크리트를 타설 양생하여 제작된 것이다. 또한, 이들 각 부재에는 프리스트레스가 도입되어 제작될 수 있음은 물론이다. 보 프리스트레싱은 보측면은 물론 보 상단면에서도 가능하게 이루어진다.In this specification, PC is used as abbreviated abbreviation of precast concrete. Therefore, the PC columns 12, the PC stringers 14A, 14B, 14C and 14D and the PC beam 13 to be described later are manufactured by casting concrete after reinforcing bars are laid in the mold. Needless to say, these members can be manufactured by introducing a prestress. Beam prestressing is possible on the beam side as well as on the beam top side.

또한, 본 명세서에서 세로 방향이란 PC 파이프 렉의 길이 방향(운송관로의 길이 방향)을 의미하고, 가로 방향이란 세로 방향에 직각인 방향을 의미한다.In this specification, the vertical direction means the longitudinal direction (the longitudinal direction of the conveying duct) of the PC pipe rack, and the horizontal direction means the direction perpendicular to the longitudinal direction.

<제1 실시 예>&Lt; Embodiment 1 >

본 발명의 제1 실시 예에 따른 시공 방법으로 제작된 파이프 렉(1)이 도 1에 도시되어 있다. 제 1 실시 예에서 보 프리스트레싱은 보측면에 이루어진 것이다.A pipe rack 1 manufactured by the construction method according to the first embodiment of the present invention is shown in Fig. In the first embodiment, the beam pre-stressing is done on the beam side.

먼저, 도 2a 및 도 2b에 도시된 바와 같이 지반(2)에 격자 간격을 가지고 기초구조물(10)이 시공된다. 기초구조물(10)은 콘크리트로 현장 타설된 기초 베이스(101)와, 기초 베이스(102)와 다수의 연결철근(102)을 통해 기초 베이스 상면에 장착된 PC 푸팅(103)과, PC 푸팅(103)에 하단이 매설되어 상방으로 돌출되어 있는 다수 개의 텐션볼트(104)를 갖는다.First, as shown in FIGS. 2A and 2B, the foundation structure 10 is installed on the ground 2 with a lattice spacing. The foundation structure 10 includes a foundation base 101 placed on the concrete site, a PC footing 103 mounted on the upper surface of the foundation base through a foundation base 102 and a plurality of connection reinforcing bars 102, a PC footing 103 And a plurality of tension bolts 104 projecting upward.

다음, 도 3과 같이 지반의 기초구조물(10)에 PC 기둥(12)이 입설된다. PC 기둥(12)은 길이 방향으로 일정 높이마다 돌출된 복수 개의 브라켓(121,121)을 포함하고 있다. PC 기둥(12)의 하단은 도 2b의 텐션볼트(104)에 삽입되어 텐션볼트(104)에 나사 체결된 너트(105)에 의해 고정된다. 이때 PC 기둥(12)은 2열로 파이프 렉(1)의 길이 방향을 따라 일정 간격을 두고 설치된다. PC 기둥(12)은 본 실시 예에서 차량 운반을 고려하여 3층 1절 형태로 구성하였으나 이러한 형태에 본 발명이 한정되는 것은 아니다. 여기서 3층이란 후술할 PC 가로보 또는 PC 세로보가 하방에서 상방으로 3단 높이로 배치되는 것을 의미한다. 따라서 PC 기둥(12)에 각 층마다 복수 개의 브라켓(121,121)이 설치된다. Next, as shown in FIG. 3, the PC column 12 is installed in the foundation structure 10 of the ground. The PC column 12 includes a plurality of brackets 121 and 121 protruding at a predetermined height in the longitudinal direction. The lower end of the PC column 12 is inserted into the tension bolt 104 of Fig. 2B and fixed by a nut 105 screwed to the tension bolt 104. Fig. At this time, the PC columns 12 are installed at regular intervals along the longitudinal direction of the pipe rack 1 in two rows. In the present embodiment, the PC column 12 is configured as a three-layered one-section type in consideration of vehicle transportation, but the present invention is not limited to such a configuration. Here, the third layer means that a PC side beam or a PC side beam to be described later is arranged in three levels upwards from below. Therefore, a plurality of brackets 121 and 121 are provided for each layer on the PC column 12.

이때 PC 가로보(13)를 위해 PC 기둥(12)에는 도시안된 가로보용 브라켓이 구성됨은 물론이다.It is a matter of course that the PC column 12 for the PC beam 13 is formed with a bracket not shown.

그 다음, 도 4와 같이 PC 가로보(13)와 PC 세로보(14A 또는 14B)를 설치한다. PC 가로보(13)는 일반적으로 프리캐스트 콘크리트로 제작된 기둥과 보의 접합 구조를 가지므로 상세한 설명은 생략한다. 본 발명은 PC 세로보(14A 또는 14B)의 설치 구조에 특징이 있으므로 이에 대해 상세히 설명한다.Then, the PC side beam 13 and the PC side string 14A or 14B are installed as shown in Fig. The PC beam 13 has a joint structure of a column and a beam made of precast concrete, and thus a detailed description thereof will be omitted. Since the present invention is characterized by the installation structure of the PC stringer 14A or 14B, this will be described in detail.

PC 세로보(14A 또는 14B)는 세로 방향으로 배치되는 이웃한 2개의 기둥(12,12)을 선택하여 서로 마주보게 된 대향된 브라켓(121,121)의 상면에 거치된다.The PC stringer 14A or 14B is mounted on the upper surface of the opposed brackets 121 and 121 which are opposed to each other by selecting two adjacent columns 12 and 12 arranged in the longitudinal direction.

PC 세로보(14A 또는 14B)는 동일한 구조로서 어느 하나의 구성을 살펴본다.The PC stringer 14A or 14B has the same structure as any one of the configurations.

도 5a 및 도 5b와 같이 PC 세로보(14A)는 길이 방향으로 사각 단면을 갖는다. PC 세로보(14A)는 이웃한 기둥(12,12)간의 서로 마주하는 면과 면사이의 배치 간격과 동일한 길이를 갖는다. PC 세로보(14A)의 양단에는 콘크리트 타설 후 블럭이 제거되어 형성된 긴장재 정착홈(141a,141a)이 중앙의 길이 방향을 따르는 수직단면을 기준으로 좌우측 2개소에 형성되어 있다. 각기 긴장재 정착홈(141a)내에는 다수 개의 정착판(20a)이 상하 일렬로 설치되어 있다. 정착판(20a)은 곡선형으로 설치된 쉬스관(19a)을 고려하여 보의 단면에 대해 일측으로 틀어져 설치되어 있다. 각각의 정착판(20a)에는 콘크리트에 매설된 쉬스관(19a)의 일단이 연결되어 있고, 쉬스관(19a)의 타단은 PC 세로보(14A)의 일측 말단까지 연장되어 있다.As shown in Figs. 5A and 5B, the PC string 14A has a rectangular cross section in the longitudinal direction. The PC string 14A has the same length as the spacing between the facing surfaces and the surfaces of the adjacent pillars 12 and 12. [ Tension material fixing grooves 141a and 141a formed by removing the blocks after concrete pouring are formed at both ends of the PC stringer 14A at two positions on the left and right sides with respect to a vertical section along the longitudinal direction of the center. A plurality of fixing plates 20a are vertically arranged in a row in each tension member fixing groove 141a. The fixing plate 20a is provided on one side of the cross section of the beam in consideration of the sheath tube 19a provided in a curved shape. One end of a sheath pipe 19a embedded in concrete is connected to each fixing plate 20a and the other end of the sheath pipe 19a extends to one end of the PC stringer 14A.

본 실시 예에서 쉬스관(19a)은 PC 세로보(14A)의 좌우에 각기 4개가 설치되어 모두 8개로 구성되어 있으나 이러한 개수에 본 발명이 제한되는 것은 아니다.In the present embodiment, four sheath pipes 19a are provided on each of the right and left sides of the PC string 14A, and the number of the sheath pipes 19a is eight, but the present invention is not limited to this number.

그 다음, 도 5a 및 도 5b와 같이 PC 기둥(12)에 직각 방향으로 교차되는 양쪽 2개의 PC 세로보(14A,14B)를 선택하여 긴장재(18)를 배치시켜 놓는다. 즉, 긴장재(18)를 어느 한 쪽 PC 세로보(14A)의 긴장재 정착홈(141a)에서 시작하여 정착판(20a)을 통과시킨 후 다른 한 쪽 PC 세로보(14B)의 긴장재 정착홈(141b)측 정착판(20b)으로 돌출되도록 한다. 이때 긴장재(18)는 PC 기둥(12)내의 쉬스관(도시안됨)을 통하여 삽통한다. 긴장재(18)는 평면에서 보면 중앙 부분이 PC 기둥(12)의 중심단면측으로 휘어져 있도록 설치된다. 긴장재(18)는 강봉, 강연선, 프리스트레싱 와이어가 될 수 있다.Next, as shown in Figs. 5A and 5B, the two PC stringers 14A and 14B intersecting at right angles to the PC column 12 are selected to arrange the tension members 18. Fig. That is, after the tension member 18 is passed through the fixing plate 20a starting from the tension member fixing groove 141a of one PC column bar 14A and then passed through the tension member fixing groove 141b side of the other PC column bar 14B And is projected to the fixing plate 20b. At this time, the tension member 18 is inserted through the sheath tube (not shown) in the PC column 12. The tension member 18 is installed such that the central portion thereof is bent toward the central end surface of the PC column 12 in plan view. The tension member 18 may be a steel bar, a strand, or a prestressing wire.

그 다음, 다수개의 긴장재(18)를 각기 유압장치(도시안됨)를 이용하여 긴장시킨 후 긴장재(18)의 양단을 정착장치(20)를 구성하는 정착구(21)와 웨지(22)를 통해 각기 정착판(20a,20b)에 고정시켜 놓는 작업이 이루어진다. A plurality of tension members 18 are then tensioned using a hydraulic device (not shown), and both ends of the tension member 18 are fixed to the fixing device 20 through the fixing port 21 and the wedge 22, Fixing work to the fixing plates 20a and 20b is performed.

여기서 긴장재(18)는 PC 세로보(14A 또는 14B)의 중앙의 세로 방향을 따르는 수직 단면에 대하여 좌우 대칭적으로 시공되므로 긴장력의 균형을 유지하기 위해 양측의 긴장재를 교대적으로 긴장시켜 작업하는 것이 바람직하다.Here, since the tension members 18 are symmetrically installed with respect to the vertical section along the vertical direction of the center of the PC string 14A or 14B, it is preferable to alternately tense the tension members on both sides to balance the tension forces Do.

이와 같이 제1실시 예로 시공된 도 1의 프리캐스트 콘크리트 파이프 렉(1)은 기둥과 보가 프리캐스트 콘크리트로 제작되어져 있어 기존의 철골 구조로 제작되는 파이프 렉에 비해 시공 비용을 대폭 절감할 수 있다. The precast concrete pipe rack 1 of FIG. 1 constructed as the first embodiment is made of precast concrete with columns and beams, which can greatly reduce the construction cost as compared with the pipelike constructed using the conventional steel structure.

또한, 기초 작업, PC 기둥(12)의 설치 작업, PC 가로보(13) 및 PC 세로보(14A,14B)의 거치 작업 그리고 긴장재(18)의 긴장 작업만 가지고 시공이 완료되므로 용접 공정이 없어져 공기가 단축된다.In addition, since the construction is completed only by the foundation work, the installation work of the PC column 12, the installation of the PC beam 13 and the PC stringers 14A and 14B, and the tensioning of the tension member 18, .

또한, PC 세로보(14A,14B)가 긴장재(18)에 의해 PC 기둥(12)에 고정되어져 접합력이 증대되고, PC 보의 휨응력이 증가되어 처짐을 효과적으로 방지할 수 있는 이점을 갖게 된다.In addition, since the PC stringers 14A and 14B are fixed to the PC column 12 by the tension member 18, the joining force is increased, and the bending stress of the PC beam is increased, thereby effectively preventing deflection.

<제2 실시 예>&Lt; Embodiment 2 >

본 발명에 따른 제2 실시 예는 도 6a 내지 도 6c와 같이 PC 기둥(12a)의 브라켓(121a,121a)에 PC 세로보(14C,14D)를 거치시킨 상태에서 콘크리트를 타설 양생한 후 긴장재(18a)를 긴장시켜서 파이프 렉을 시공하는 공법이다. 제2 실시 예는 보 프리스트레싱이 보 상단면에서 이루어진 것이다.6A to 6C, concrete is placed and cured in a state in which the PC stringers 14C and 14D are mounted on the brackets 121a and 121a of the PC column 12a, and then the tension members 18a ) Is tense and it is construction method to construct pipe rak. In the second embodiment, the beam-prestressing is performed at the top end surface.

먼저, 도 2a와 같은 지반의 기초구조물(10)에 PC 기둥(12a)이 수직으로 설치된다. PC 기둥(12a)은 각기 길이 방향으로 일정 높이마다 돌출된 복수 개의 브라켓(121a,121a)을 포함하고 있다. PC 기둥(12a)의 설치구조는 제1 실시 예와 동일하게 이루어진다. PC 기둥(12a)에는 PC 세로보(14C,14D)와 접합되는 위치에 PC 기둥 개구부(122)가 형성되어 있다. PC 기둥 개구부(122)는 PC 세로보(14C,14D)에 형성되어 있는 쉬스관 매설홈(143a,143b)의 단면과 동일한 크기의 단면을 갖는다.First, a PC column 12a is vertically installed in a foundation structure 10 as shown in FIG. 2A. Each of the PC columns 12a includes a plurality of brackets 121a and 121a projecting at a predetermined height in the longitudinal direction. The installation structure of the PC column 12a is the same as that of the first embodiment. The PC column 12a is formed with a PC column opening 122 at a position to be joined to the PC column bulbs 14C and 14D. The PC column opening portion 122 has a cross section of the same size as the cross section of the sheath tube buried grooves 143a and 143b formed in the PC stringers 14C and 14D.

그 다음, 세로 방향으로 이웃한 2개의 기둥(12a,12a)을 선택하여 서로 마주보게 된 대향된 브라켓(121a,121a)에 PC 세로보(14C,14D)를 거치시켜 놓은 후 쉬스관(19c,19d)을 일치되게 정열시킨다. 쉬스관(19c,19d)의 정열은 접착테이프나 주지의 이음장치에 의해 이루어질 수 있다.Next, the PC stringers 14C and 14D are mounted on the opposed brackets 121a and 121a, which are opposed to each other by selecting two vertically adjacent columns 12a and 12a, and then the sheath tubes 19c and 19d ). The heat of the sheath pipes 19c and 19d can be made by an adhesive tape or a known jointing device.

여기서 PC 세로보(14C,14D)는 양측에 각기 상방과 말단으로 모두 개구(開口)되어 있는 긴 쉬스관 매설홈(143a,143b)을 갖는다. 또한 PC 세로보(14C,14D)는 쉬스관 매설홈(143a,143b)과 가까이 위치하여 일정 깊이에서 상방으로 개구되어 있는 정착홈(141'a,141'b)이 각기 형성되어 있고, 정착홈(141'a,141'b)에는 정착판(20'a,20'b)이 설치되어 있고, 정착판(20'a,20'b)에는 쉬스관 매설홈(143a,143b)내에 배치되어 있는 쉬스관(19c,19d)이 연결되어 있다.Here, the PC stringers 14C and 14D have long sheath tube buried grooves 143a and 143b, which are open on both sides of the PC stringers 14C and 14D, respectively. The PC stringers 14C and 14D are provided with fixing grooves 141'a and 141'b which are positioned close to the sheath tube buried grooves 143a and 143b and open upward at a predetermined depth, The fixing plates 20'a and 20'b are provided in the fixing plates 20'a and 20'b and the fixing plates 20'a and 20'b are disposed in the recessed grooves 143a and 143b And sheath pipes 19c and 19d are connected.

쉬스관(19c,19d)은 각기 본 실시 예에서 5열로 상하 2단으로 설치되어 있으나 이러한 배열에 본 발명이 한정되는 것은 아니다.The sheath pipes 19c and 19d are respectively provided in five rows in the upper and lower two stages in the present embodiment, but the present invention is not limited to this arrangement.

이 단계에서 PC 세로보(14C,14D)와 함께 도 4와 같이 PC 가로보(13)가 설치됨은 물론이다.At this stage, it is a matter of course that the PC side beam 13 is installed together with the PC stringers 14C and 14D as shown in FIG.

그 다음, 해당 PC 기둥(12a)과 직각 방향으로 교차되는 양쪽 2개의 PC 세로보(14A,14B)를 선택하여 긴장재(18a)를 각각의 쉬스관(19c,19d)에 삽입시켜 일측의 긴장재 정착홈(141'a)과 타측의 긴장재 정착홈(141'b)에 양단을 노출시켜 놓는다.Next, the two PC stringers 14A and 14B, which intersect at right angles with the PC column 12a, are selected to insert the tension members 18a into the respective sheath pipes 19c and 19d, And both ends are exposed to the tension member fixing groove 141'a on the other side and the tension member fixing groove 141'b on the other side.

그 다음, PC 세로보(14C,14D)의 쉬스관 매설홈(143a,143b)에 콘크리트를 타설한다. 콘크리트의 타설 후 양생이 완료되면, 콘크리트는 PC 기둥 개구부(122)에도 충전된다. 따라서 PC 세로보(14A,14B)는 콘크리트를 매개로 기둥(12a)과 합성되어 상호 직각 방향으로 일체화된다.Subsequently, concrete is cast into the sheath tube buried grooves 143a and 143b of the PC stringers 14C and 14D. When curing is completed after the concrete is poured, the concrete is also filled into the PC column opening portion 122. Therefore, the PC stringers 14A and 14B are combined with the column 12a via the concrete, and are integrated in a direction perpendicular to each other.

그 다음, 긴장재(18a)를 유압장치로 긴장시킨 후 제1 실시 예의 정착장치(20)를 이용하여 정착판(20'a,20'b)에 고정시켜 놓음으로써 긴장재(18a)에는 긴장력이 도입된다.Thereafter, the tension member 18a is tensioned by the hydraulic device and then fixed to the fixing plates 20'a and 20'b by using the fixing device 20 of the first embodiment, so that a tension force is introduced into the tension member 18a do.

따라서 PC 세로보(14C,14D)와 PC 기둥(12a)의 접합부에는 긴장재(18a)의 긴장에 따른 압축력이 발생되어 PC 세로보(14C,14D)의 휨 응력이 향상된다.Therefore, a compression force due to the tension of the tension member 18a is generated at the joining portion of the PC stringers 14C and 14D and the PC column 12a, and the bending stress of the PC stringers 14C and 14D is improved.

이와 같이 제2실시 예로 시공된 프리캐스트 콘크리트 파이프 렉은 제1 실시 예와 동일하게 기둥과 보가 프리캐스트 콘크리트로 제작되어져 있어 기존의 철골 구조로 제작되는 파이프 렉에 비해 시공 비용을 대폭 절감할 수 있다. As described above, the precast concrete pipe rack constructed according to the second embodiment is made of precast concrete such as pillars and beams as in the first embodiment, so that the construction cost can be drastically reduced as compared with the pipelack manufactured using the existing steel structure .

또한, 기초 작업, PC 기둥(12a)의 설치 작업, PC 세로보(14C,14D)의 거치 작업 , 콘크리트 타설 작업 및 긴장재(18)의 긴장 작업만 가지고 시공이 완료되므로 용접 공정이 없어져 제작 공기가 단축된다.In addition, since the construction is completed only by the foundation work, the installation of the PC column 12a, the installation of the PC stringers 14C and 14D, the concrete pouring work and the tensioning of the tension member 18, do.

또한, PC 세로보(14C,14D)가 긴장재(18a)에 의해 PC 기둥(12)에 고정되어져 접합력이 증대되고, PC 세로보(14C,14D)의 휨응력을 증가시킬 있다.In addition, the PC stringers 14C and 14D are fixed to the PC column 12 by the tension member 18a, thereby increasing the bonding force and increasing the bending stress of the PC stringers 14C and 14D.

<제3 실시 예>&Lt; Third Embodiment >

한편, 본 발명은 상술한 실시예1,2의 시공 방법을 이용하여 물류 창고, 냉동창고, 공장 등등의 건축 구조물을 시공할 수 있다.Meanwhile, the present invention can be applied to construction structures such as a logistics warehouse, a freezing warehouse, a factory, etc. by using the construction methods of the first and second embodiments.

즉, 도 4와 같이 PC 가로보(13)와 함께 PC 세로보(14A,14B) 또는 도 7a와 같이 PC 세로보(14C,14D)의 설치 완료 후 도 7b와 같이 슬래브(100)를 시공함으로써 건축 구조물이 제작된다. 슬래브(100)의 시공은 콘크리트 현장타설로 이루어지거나 PC 슬래브 또는 데크플레이트를 이용하여 이루어질 수 있다.That is, after the installation of the PC stringers 14A and 14B together with the PC beam 13 or the PC stringers 14C and 14D as shown in FIG. 7, the slab 100 is installed as shown in FIG. . The construction of the slab 100 may be done by concrete installation or by using a PC slab or deck plate.

제3 실시 예의 시공 방법으로 제작된 건축 구조물의 경우 용접 작업이 없어져 공기가 단축되며, PC 세로보가 긴장력에 의해 PC 기둥에 확고하게 접합되어지고 PC 세로보의 휨응력이 증가되어 슬라브의 구조적 안전성이 향상된다.In the case of the building structure manufactured by the construction method of the third embodiment, the welding operation is omitted and the air is shortened, and the PC string is firmly bonded to the PC column by the tensile force, and the bending stress of the PC string is increased to improve the structural safety of the slab .

한편, 본 발명은 파이프 렉 구조체의 구조뿐 아니라 기둥 보 형식의 구조 또는 바닥있는 구조체에도 동일하게 적용이 가능함은 물론이다.It goes without saying that the present invention is equally applicable to a column-beam type structure or a bottom-type structure as well as to a structure of a pipelike structure.

이때 기둥은 다수층으로 형성할 수 있는 다층 접합구조를 갖는 형식이면서, 분절형과 접합부 개방형 모두 적용이 가능하다.In this case, the column has a multi-layered structure that can be formed of a plurality of layers, and both the segmented type and the open-ended type are applicable.

지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is evident that many alternatives, modifications and variations will be apparent to those skilled in the art in light of the above teachings. will be. The invention is not limited by these variations and modifications, but is limited only by the claims appended hereto.

10: 기초구조물
101: 기초베이스
102: 연결철근
103: PC 푸팅
104: 텐션볼트
105: 너트
12,12a: PC 기둥
121,121a: 브라켓
122: PC 기둥 개구부
13: 가로보
14A,14B,14C,14D: PC 세로보
18: 긴장재
18a: 긴장재
19a,19b,19c,19d: 쉬스관
20a,20b: 정착판
143a,143b: 쉬스관 매설홈
100: 슬라브
10: foundation structure
101: Foundation base
102:
103: PC footing
104: tension bolt
105: Nuts
12,12a: PC column
121, 121a: Bracket
122: PC column opening
13: Rear view
14A, 14B, 14C, 14D: PC string
18: Tension material
18a: Tension material
19a, 19b, 19c, 19d: Sheath tube
20a, 20b: Fixing plate
143a, 143b: buried in the sheath tube
100: Slavic

Claims (10)

삭제delete 삭제delete 삭제delete 삭제delete 삭제delete (a) 지반의 기초구조물(10)에 각기 길이 방향으로 일정 높이마다 돌출된 복수 개의 브라켓(121a,121a)을 포함하고 있는 PC 기둥(12a)을 입설시켜 놓는 단계와;
(b) 가로 방향과 세로 방향으로 이웃한 2개의 기둥(12a,12a)을 순차적으로 선택하여 서로 마주보게 된 대향된 브라켓(121a,121a)에 PC 가로보(13)와 PC 세로보(14C,14D)를 각기 거치시켜 놓은 후 PC 세로보(14C,14D)에 각기 구비된 다수 개의 쉬스관(19c,19d)을 상호 일치되도록 접속시키는 단계와;
(c) PC 기둥(12)과 수평 방향으로 교차되는 양쪽 2개의 PC 세로보(14A,14B)를 선택하여 다수 개의 긴장재(18a)를 상기 쉬스관(19c,19d)에 각기 삽입시켜 PC 세로보(14A,14B)의 긴장재 정착홈(141'a,141'b)에 설치된 정착판(20'a,20'b)에 지지시켜 놓는 단계와;
(d) 상기 PC 세로보(14C,14D)에 형성된 쉬스관 매설홈(143a,143b)에 콘크리트를 타설하는 단계; 및
(d) 콘크리트의 양생 후 긴장재(18a)를 긴장시켜 정착장치(20)를 이용하여 정착판(20'a,20'b)에 고정시켜 놓는 단계;를 통하여 시공되는 것을 특징으로 하는 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조의 시공 방법.
(a) establishing a PC column 12a including a plurality of brackets 121a and 121a projecting at a predetermined height in the longitudinal direction on the foundation structure 10 of the ground;
(b) The PC beam 13 and the PC stringers 14C and 14D are sequentially placed on the opposed brackets 121a and 121a, which sequentially select the two columns 12a and 12a adjacent to each other in the horizontal direction and the vertical direction, And connecting the plurality of sheath pipes 19c and 19d provided to the PC stringers 14C and 14D so as to be mutually coincident with each other;
(c) Selecting two PC stringers 14A and 14B crossing the PC column 12 in the horizontal direction and inserting a plurality of tension members 18a into the sheath tubes 19c and 19d, respectively, (14'a, 141'b) of the tension member fixing grooves (141'a, 141'b) of the first and second fixing members (14A, 14B);
(d) placing concrete in the sheath tube buried grooves 143a and 143b formed in the PC stringers 14C and 14D; And
(d) fixing the tension member (18a) after curing of the concrete to the fixing plates (20'a, 20'b) using the fixing device (20) A method of constructing a pipe - lay structure or a beam - column joint structure using cast concrete.
제 6항에 있어서,
긴장재 정착홈(141'a,141'b)은 상방으로 개구(開口)되어 있고, 쉬스관 매설홈(143a,143b)은 양단에 상방과 말단으로 모두 개구(開口)된 구조를 가지고 시공되는 것을 특징으로 하는 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조의 시공 방법.
The method according to claim 6,
The tension member fixing grooves 141'a and 141'b are opened upward and the sheath tube embedded grooves 143a and 143b are formed so as to have a structure in which both the upper and the lower ends are opened at both ends A method of constructing a pipe-lay structure or a beam-column joint structure using a prestressed precast concrete.
제 6항에 있어서,
상기 PC 기둥(12a)에는 PC 세로보(14C,14D)와의 접합 부분에 쉬스관 매설홈(143a,143b)과 연통되는 PC 기둥 개구부(122)가 형성되어 시공되는 것을 특징으로 하는 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조의 시공 방법.
The method according to claim 6,
Wherein the PC column 12a is formed with a PC column opening 122 communicating with the sheath pipe grooves 143a and 143b at the joining portion with the PC stringers 14C and 14D. A method of constructing a pipe-lay structure or a beam-column joint structure using the method.
청구항 제6항 내지 제8항 중 어느 한 항의 시공 방법으로 시공된 것을 특징으로 하는 프리스트레스트 프리캐스트 콘크리트를 이용한 파이프 렉 구조체 또는 보 기둥 접합구조.9. A pipe-lay structure or a beam-column joint structure using a prestressed precast concrete, which is constructed by the method of any one of claims 6 to 8. 청구항 제6항 내지 제8항 중 어느 한 항의 시공 방법으로 시공된 파이프 렉에 PC 세로보(14A,14B 또는 14C,14D)의 상면으로 현장 콘크리트를 타설하거나 PC 슬래브 또는 데크플레이트를 설치하여 슬라브(100)가 더 시공되어 제작된 것을 특징으로 하는 PC 기둥과 PC 보의 접합부에 긴장재가 도입된 건축 구조물.A concrete slab or deck plate is laid on the upper surface of a PC stringer (14A, 14B or 14C, 14D) on a pipe rack constructed by the construction method of any one of claims 6 to 8, ) Is constructed by applying more tension to the joint between PC column and PC beam.
KR1020120128144A 2012-11-13 2012-11-13 Prestressed precast concrete using pipe rack or beam column joint structure and construction method of the same KR101505579B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120128144A KR101505579B1 (en) 2012-11-13 2012-11-13 Prestressed precast concrete using pipe rack or beam column joint structure and construction method of the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120128144A KR101505579B1 (en) 2012-11-13 2012-11-13 Prestressed precast concrete using pipe rack or beam column joint structure and construction method of the same

Publications (2)

Publication Number Publication Date
KR20140061031A KR20140061031A (en) 2014-05-21
KR101505579B1 true KR101505579B1 (en) 2015-03-26

Family

ID=50890189

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120128144A KR101505579B1 (en) 2012-11-13 2012-11-13 Prestressed precast concrete using pipe rack or beam column joint structure and construction method of the same

Country Status (1)

Country Link
KR (1) KR101505579B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102115706B1 (en) * 2019-09-20 2020-05-26 오종한 A Cooling tower inclding precast concret structure
KR102186738B1 (en) 2019-05-28 2020-12-04 (주)더시스템랩건축사사무소 the multipurpose residential rack system
KR102295506B1 (en) * 2020-11-29 2021-08-31 주식회사 아드보 Slim girder for a-type column and column system with the same
KR102351056B1 (en) 2021-10-26 2022-01-13 (주)정도 Self-driving transport lifting device and the Construction method using the device
KR102371456B1 (en) * 2021-06-02 2022-03-07 서울시립대학교 산학협력단 Repairable PC connection for plant pipe-rack structure and construction method thereof
KR102616121B1 (en) 2023-06-21 2023-12-20 (주)정도 Construction method using a AGV Smart Lift and AI Image analysis

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101459575B1 (en) * 2014-08-07 2014-11-07 에스케이하이닉스(주) Construction method for clean room with concurrent execution structure using joint basket
KR101713188B1 (en) * 2015-03-06 2017-03-08 경희대학교 산학협력단 the construction method of steel-concrete hybrid precast concrete pipe rack structure
KR102188106B1 (en) * 2019-04-26 2020-12-07 휴인 주식회사 Column and beam structures
CN110016856A (en) * 2019-05-14 2019-07-16 福州大学 Prestressing force assembled UHPC plank road column construction and its construction method
CN114134997B (en) * 2021-11-10 2023-03-10 河北工业大学 Assembled mortise-tenon joint's roof beam, post and post basis mosaic structure
CN114703965B (en) * 2022-06-06 2022-08-26 中国船舶重工集团国际工程有限公司 Steel structure quick-insertion connection node assembly and installation process thereof
CN115573597B (en) * 2022-11-02 2023-08-15 中铁建工集团有限公司 Fully-assembled concrete canopy and construction method thereof
CN116427543B (en) * 2023-04-14 2023-11-24 中建安装集团有限公司 Profile steel-concrete assembled petrochemical pipe gallery structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100089255A (en) * 2009-02-03 2010-08-12 구로사와 겐세츠 가부시키가이샤 Construction method of building with precast concrete member

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100089255A (en) * 2009-02-03 2010-08-12 구로사와 겐세츠 가부시키가이샤 Construction method of building with precast concrete member

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102186738B1 (en) 2019-05-28 2020-12-04 (주)더시스템랩건축사사무소 the multipurpose residential rack system
KR102115706B1 (en) * 2019-09-20 2020-05-26 오종한 A Cooling tower inclding precast concret structure
KR102295506B1 (en) * 2020-11-29 2021-08-31 주식회사 아드보 Slim girder for a-type column and column system with the same
KR102371456B1 (en) * 2021-06-02 2022-03-07 서울시립대학교 산학협력단 Repairable PC connection for plant pipe-rack structure and construction method thereof
KR102351056B1 (en) 2021-10-26 2022-01-13 (주)정도 Self-driving transport lifting device and the Construction method using the device
KR102616121B1 (en) 2023-06-21 2023-12-20 (주)정도 Construction method using a AGV Smart Lift and AI Image analysis

Also Published As

Publication number Publication date
KR20140061031A (en) 2014-05-21

Similar Documents

Publication Publication Date Title
KR101505579B1 (en) Prestressed precast concrete using pipe rack or beam column joint structure and construction method of the same
KR100797194B1 (en) Composite concrete column and construction method using the same
KR100926140B1 (en) Structure for using precast members and construction method thereof
KR101030419B1 (en) Joint structure of vertical member and horizontal member
KR101136926B1 (en) Composite beam by prestressed concrete filled tube
KR101663132B1 (en) Self-supporting type column structure
JP4844918B2 (en) Construction method of steel / concrete composite deck using precast concrete board
KR101339946B1 (en) Precast bridge post
KR101215060B1 (en) Steel reinforcement and concrete composite column having vertically coupling means and construction method using the same
KR100727114B1 (en) Precast segment for constructing through bridges and the constructing method using it
JP5386379B2 (en) Precast slab joints in bridges
KR101705002B1 (en) Prefabricated double composite plate girder bridge and its construction method
KR101329443B1 (en) Precast concrete frame and its construction method for buildings using precast concrete slab continued by post tensioning
KR100865133B1 (en) A fixing device, a pre-fabricating forms for concrete-structure and the construction method thereof
KR101181160B1 (en) Prestressed precast concrete beam having efficient prestressing anchorage structure
KR101036177B1 (en) Method for constructing building using PRC integrating method
KR101476411B1 (en) Precast concrete frame for buildings using precast concrete beam continued by post tensioning
KR101954387B1 (en) Grid precast concrete structure and constructing method thereof
KR101150369B1 (en) Complex girder for building
KR101436969B1 (en) Prefabricated wall frame using a timber
JP2006183286A (en) Connection structure of corrugated steel web for corrugated steel web u-shaped component bridge
KR101492066B1 (en) Construction method for foundation structure of column
KR102029001B1 (en) Wall structure and the construction method therefor
KR101004221B1 (en) One Way Waffle Slab System Continued by Post-tensioning and Post-tensioning method of the same
KR20160078150A (en) Segmental prestressed concrete girder and method for constructing same

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20181108

Year of fee payment: 4

R401 Registration of restoration
FPAY Annual fee payment

Payment date: 20190319

Year of fee payment: 5