KR101388253B1 - Base structure of road facility - Google Patents
Base structure of road facility Download PDFInfo
- Publication number
- KR101388253B1 KR101388253B1 KR1020130041798A KR20130041798A KR101388253B1 KR 101388253 B1 KR101388253 B1 KR 101388253B1 KR 1020130041798 A KR1020130041798 A KR 1020130041798A KR 20130041798 A KR20130041798 A KR 20130041798A KR 101388253 B1 KR101388253 B1 KR 101388253B1
- Authority
- KR
- South Korea
- Prior art keywords
- bolt
- coupling
- anchor plate
- anchor
- foundation
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H17/00—Fencing, e.g. fences, enclosures, corrals
- E04H17/14—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
- E04H17/20—Posts therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
Description
본 발명은 도로 시설물의 기초 시공 방법에 관한 것으로, 더욱 상세하게는 난간, 펜스, 울타리, 방음벽, 가로등, 신호등, 표지판 등의 도로 시설물을 지반에 고정하기 위한 앵커볼트가 돌출되지 않도록 하여 미관을 개선할 수 있는 도로 시설물의 기초 시공 방법에 관한 것이다.
The present invention relates to a method for basic construction of road facilities, and more particularly, to improve aesthetics by preventing the anchor bolts for fixing road facilities such as railings, fences, fences, soundproof walls, street lights, traffic lights, signs, etc. to the ground. It is about basic construction method of possible road facilities.
일반적으로 도로 시설물을 설치하는 경우 기초구조물(콘크리트의 현장 타설 또는 프리캐스트 콘크리트 블록)을 구성하고, 도로 시설물의 기둥으로 사용되는 지주를 상기 기초구조물 위에 얹은 다음 앵커볼트와 너트로서 고정하여 설치하게 된다.In general, in the case of installing the road facility, the foundation structure (concrete cast or precast concrete block) is constituted, and the pillar used as the pillar of the road facility is placed on the foundation and then fixed by anchor bolts and nuts. .
한편, 도 1에서 보이는 바와 같이, 상기와 같은 기초구조물(1)을 제작할 때 도로 시설물의 지주(2)가 얹혀져 고정될 수 있도록 다수 개의 앵커볼트(3)가 일정한 길이만큼 수직상향으로 돌출되게 매립된다.On the other hand, as shown in Figure 1, when manufacturing the basic structure (1) as described above, a plurality of anchor bolts (3) are embedded to protrude vertically by a certain length so that the support (2) of the road facility is mounted and fixed do.
상기와 같이 제작된 기초구조물(1)의 상면에는 지주(2)의 저부에 결합된 앵커플레이트(4)가 얹혀져 결합되는데, 이때 앵커플레이트(4)에는 앵커볼트(3)가 관통되는 체결공이 형성되고, 앵커플레이트(4) 위에서 앵커플레이트(4)를 관통한 앵커볼트(3)에 너트(5)가 체결됨으로써 앵커플레이트(4)가 기초구조물(1) 위에 고정된다.An
이와 같이 제작된 도로시설물의 기초부는 앵커볼트(3)와 너트(5)[지주(2)의 둘레부에 형성된 보강리브 등도 포함]가 지면 또는 기초구조물(1)의 표면으로부터 돌출되어 미관이 좋지 못하고, 보행자가 앵커볼트(3)와 너트(5)(보강리브 등)에 걸리게 되어 넘어지는 등의 문제점이 있다.The foundation of the road facility thus constructed is such that the
이러한 문제점을 해결하기 위한 것으로 예를 들면 대한민국 실용신안등록 제112850호가 있다.As an example to solve this problem, there is a Republic of Korea Utility Model Registration No. 112850.
상기 실용신안등록 제112850호에 의하면, 도로시설물의 기초부분에 착탈이 가능한 보호커버를 설치하여 보행자의 안전을 도모하는 기술로서, 이를 살펴보면, 상단에 결합돌부를 가지고 시설물보다 외경이 크면서 상협 하광체로 되는 보호통체를 구성하되 보호통체를 반분으로 분할하여 일측 반분통체는 하단에 기초볼트 삽입홈을 가진 한 쌍의 고정돌편을 내측으로 형성하고 상기 고정돌편이 형성된 상부 양측 연부에 연결편을 돌출되게 형성하여 그 연결편에 입구가 개방된 연결홈을 구비시키고 이와 결합되는 타측의 상기 반분통체는 상기 고정돌편과 마주닿는 곳에 연결부를 만들어 입구에 연결돌기를 형성시키며 상기 두 반분통체의 상단부에 결합돌부를 형성하여 결합테로 결합케 하고, 상기 두 반분통체의 표면에는 요입홈부를 만들어 그 속에 야광 도로나 야광 테이프로 만든 야광표시구 및 야광 반사판을 부착하여 이것을 기존 시설물의 기초부분 외면에 착탈케 한 도로시설물용 기둥보호커버를 제공하고 있다.According to Utility Model Registration No. 112850, a technology that promotes the safety of pedestrians by installing a protective cover that can be attached to or detached from the base of a road facility. The protective cylinder is composed of a body, but the protective cylinder is divided into half, so that one half of the barrel forms a pair of fixing protrusions having a foundation bolt insertion groove at the bottom thereof, and protrudes the connecting pieces at both upper edges of the fixing protrusions. Forming a connection groove having an inlet opening in the connecting piece, and the half-cylindrical body on the other side coupled thereto forms a connection part facing the fixing protrusion piece to form a connection protrusion at the inlet, and a coupling protrusion at the upper ends of the two half-molecular bodies. To form a bond frame, and to make the recess groove in the surface of the two semi-tubular body It provides a pillar protection cover for road facilities that attaches luminous indicators and luminous reflectors made of light roads or luminous tapes and attaches and detaches them to the outer surface of the foundation part of existing facilities.
그러나, 상기한 도로시설물용 기둥 보호커버는, 기 시설된 도로시설물에 보호통체를 설치하기 위해서는 먼저 기초구조물에 기둥(즉 지주)의 하측(즉 원판형의 베이스)을 고정하고 있는 기초볼트(즉 앵커볼트)의 너트를 풀어서 일측의 반분통체를 고정하고 이후 상기 기초볼트에 고정된 일측의 반분통체에 또 다른 반분통체를 일일이 끼워 맞춤하여 접하게 한 다음 상기 두 반분통체의 결합돌부에 결합테를 감아서 고정시켜 주어야 하므로, 하나의 도로시설물에 보호통체를 설치하는데 많은 작업공정과 작업시간이 소요되는 문제점이 있었다.However, the above-described pillar protection cover for the road facility, in order to install the protective cylinder on the existing road facility, the foundation bolt (that is, the base of the disk) fixed to the lower side of the pillar (that is, the pillar) to the foundation structure (ie Anchor bolt) to loosen the nut of one side and then fix the half-cylinder on one side and then fit the other half-cylinder to the half-cylinder fixed on the foundation bolts to make contact with each other. Since it must be fixed in the road, there was a problem that a lot of work process and work time is required to install a protective cylinder in one road facility.
또한, 상기 기 시설된 도로시설물 하나에만 보호통체를 설치할 경우에는 그 작업에 따르는 시간이 그리 길다 할 수는 없으나 여러 개의 도로시설물에 보호통체를 설치할 경우나 여러 개의 도로시설물을 새로 시설할 경우에는 도로시설물 하나하나에 보호통체를 상기와 같은 방법으로 설치해야 하므로 그 작업시간이 상당히 많이 소요되고, 또 현장에서 도로시설물을 먼저 시설한 후에 보호통체를 설치해야 하는 2중의 작업을 수행해야 하므로 작업의 번거로움이 있고, 이것에 의해서 작업효율이 떨어진다.In addition, when the protective cylinder is installed in only one of the above-mentioned road facilities, the time required for the work may not be very long. However, when the protective cylinder is installed in several road facilities or when a plurality of road facilities are newly installed, Since the protective cylinder must be installed in each facility in the same way as above, it takes a lot of work time, and it is troublesome to perform the double work of installing the protective cylinder after installing the road facilities at the site first. There is a problem, and work efficiency falls by this.
따라서, 일정구간에 여러 개의 도로시설물을 새로 시설하거나 기 시설되어진 <도로시설물에 보호통체를 설치할 때에는 보호통체 하나를 설치하는 시간이 많이 소요되므로, 그 모든 작업을 완료하는데 따르는 공사기간이 많이 소요되어 작업구간을 지나는 보행자나 차량들에 많은 불편을 초래할 뿐 아니라 공사기간의 장기화에 따른 작업 비용의 상승을 가져오게 되는 문제점이 있다.Therefore, when installing a plurality of road facilities in a certain section or installing a protective cylinder on an existing <road facility, it takes a lot of time to install one protective cylinder, so it takes a lot of construction time to complete all the work. Not only does it cause a lot of inconvenience to pedestrians or vehicles passing the work zone, but also the work cost increases due to prolonged construction period.
또한, 두 개의 반분통체를 서로 결합하기 위한 구조가 복잡할 뿐 아니라 기둥의 하단에 삼각지지대와 함께 용접되어 기초구조물의 기초볼트(앵커볼트)에 고정되는 기둥하측(원판형의 베이스)과 이들을 은폐하는 목적으로만 사용되는 보호통체가 서로 분리 제작되어 설치되므로 기초구조물에 대하여 기둥을 지지하여 주는 힘이 약하고, 또 보호통체가 외부의 충격을 흡수할 수 있는 구조로 되어 있지 않아 외력에 의해서 쉽게 찌그러지거나 파손될 염려가 있으며, 특히 보호통체의 일부가 파손될 경우에 부분 교체가 용이치 않다는 문제점이 있다.
In addition, the structure for joining the two half-cylinders together is not only complicated, but also the lower side of the column (a disc-shaped base) that is welded together with a triangular support at the bottom of the column and fixed to the foundation bolt (anchor bolt) of the foundation structure, and concealing them. Since the protective cylinders, which are used only for the purpose of installation, are separately manufactured and installed, the force supporting the column against the basic structure is weak, and the protective cylinder is not structured to absorb external shocks, so it is easily crushed by external force. There is a risk of being damaged or broken, especially when a part of the protective cylinder is damaged there is a problem that the partial replacement is not easy.
본 발명은 전술한 바와 같은 문제점을 해결하기 위한 것으로, 난간, 펜스, 울타리, 방음벽, 가로등, 신호등, 표지판 등 도로 시설물의 지주를 지반(기초 구조물)에 고정하기 위한 자재(앵커볼트 등)가 돌출되지 않도록 한 도로 시설물의 기초 시공 방법을 제공하려는데 그 목적이 있다.The present invention is to solve the problems described above, the material (anchor bolt, etc.) for fixing the props of the road facilities such as railings, fences, fences, soundproof walls, street lights, traffic lights, signs, etc. to the ground (base structure) protrudes Its purpose is to provide a method of basic construction of road facilities that is not intended.
본 발명에 의한 도로 시설물의 기초 시공 방법은, 지중 또는 지상에 블록 형태의 기초 구조물을 시공하되, 상기 기초 구조물 안에 도로 시설물의 지주를 고정하기 위한 앵커볼트를 설치하고, 상기 앵커볼트의 지상측 단부에 암나사부가 구비된 커플링을 결속하는 제1단계와; 상기 제1단계를 통해 시공된 기초 구조물의 상면에 도로 시설물의 지주를 세우기 위한 앵커플레이트를 안착하되, 상기 앵커플레이트에 형성된 체결공을 상기 커플링과 일치되도록 안착하는 제2단계와; 상기 제2단계를 통해 안착된 앵커플레이트의 체결공을 통하여 기초볼트를 상기 커플링에 체결하여 상기 앵커플레이트를 상기 앵커볼트에 고정하는 제3단계를 포함하되, 상기 기초볼트의 두부가 상기 앵커플레이트의 체결공 둘레부에 형성된 안착턱에 삽입되어 앵커플레이트의 상부로 돌출되지 않도록 하는 것을 특징으로 한다.
In the basic construction method of the road facility according to the present invention, while constructing a block-shaped foundation structure in the ground or ground, install an anchor bolt for fixing the strut of the road facility in the foundation structure, the ground end of the anchor bolt A first step of engaging the coupling provided with the female screw portion in the; A second step of seating an anchor plate for erecting the support of the road facility on the upper surface of the foundation structure constructed through the first step, and seating a fastening hole formed in the anchor plate to match the coupling; And a third step of fixing the anchor plate to the anchor bolt by fastening the foundation bolt to the coupling through the fastening hole of the anchor plate seated through the second step, wherein the head of the foundation bolt is anchored to the anchor plate. Is inserted into the seating jaw formed in the periphery of the fastening hole is characterized in that it does not protrude to the top of the anchor plate.
본 발명에 의한 도로 시설물의 기초 시공 방법에 의하면, 난간, 펜스, 울타리, 방음벽, 가로등, 신호등, 표지판 등 도로 시설물의 지주를 지반(기초 구조물)에 고정하기 위한 앵커볼트와 기초볼트가 앵커플레이트의 상부로 돌출되지 않아 튀어나온 부분에 의한 시각적인 불쾌감을 없애 도시경관을 수려하게 유지할 수 있고, 보행자가 기초에 부딪치거나 간섭을 받지 않게 되어 보행의 불편함을 해소하고 보행자의 안전사고를 미연에 방지할 수 있다.According to the basic construction method of the road facility according to the present invention, the anchor bolt and the foundation bolt for fixing the pillar of the road facility, such as railings, fences, fences, soundproof walls, street lights, traffic lights, signs, etc. to the ground (base structure) The urban landscape can be kept beautiful by eliminating the visual discomfort caused by the protruding part because it does not protrude to the upper part, and the pedestrians do not hit the foundation or receive interference, eliminating the inconvenience of walking and preventing pedestrian safety accidents. It can prevent.
그리고, 앵커플레이트를 고정하는 기초볼트가 외력에 의해 풀리지 않으므로 앵커플레이트의 이탈, 지주의 넘어짐 등을 방지할 수 있다.And, since the base bolt for fixing the anchor plate is not released by the external force, it is possible to prevent the separation of the anchor plate, the fall of the support.
또한, 앵커플레이트를 고정하는 기초볼트의 손상시 앵커볼트의 교체없이 기초볼트만의 교체를 통해 유지보수가 가능하므로 유지보수 비용을 절감할 수 있다.
In addition, when the foundation bolt fixing the anchor plate is damaged by the replacement of the foundation bolt only without replacement of the anchor bolt can be maintained, thereby reducing the maintenance cost.
도 1은 종래 기술에 의한 도로 시설물의 기초 시공 방법을 보인 도면.
도 2는 본 발명에 의한 도로 시설물의 기초 시공 방법의 공정도.1 is a view showing the basic construction method of the road facility according to the prior art.
2 is a process chart of the basic construction method of the road facility according to the present invention.
도 1에서 보이는 바와 같이, 본 발명에 따른 도로 시설물의 기초 시공 방법은 기초 시공 - 앵커플레이트 설치의 공정으로 이루어지며, 이하 구체적인 공정을 설명한다.As shown in Figure 1, the basic construction method of the road facility according to the present invention consists of a process of basic construction-anchor plate installation, a detailed process will be described below.
1. 기초 시공.1. Foundation construction.
도로 시설물의 설치를 위해서는 철근 콘크리트의 기초 구조물(1)을 시공한다.For the installation of road facilities, the foundation structure (1) of reinforced concrete is constructed.
기초 구조물(1)은 현장 타설과 프리캐스트 콘크리트 블록 모두가 가능하고, 예를 들어 현장 타설의 경우 설계에 맞도록 철근을 배근 및 거푸집을 설치한 후 상기 거푸집 안에 콘크리트를 타설하여 기초 구조물(1)을 시공하며, 이 때, 앵커볼트(10)를 상기 철근에 묶어 고정하는 등의 방법으로 고정한다.The foundation structure (1) can be both on-site casting and precast concrete block, for example, in the case of on-site casting, reinforcement and formwork for reinforcing bars to fit the design, and then cast concrete in the formwork to form the foundation structure (1) Construction, and at this time,
앵커볼트(10)는 L형의 앵커볼트가 바람직하고, 지상측을 향하는 단부에 커플링(20)이 고정된다.The
커플링(20)은 앵커볼트(10)와 후술하는 기초볼트(30)를 결속하기 위한 매개물이며, 앵커볼트(10)와 기초볼트(30)의 나사 체결이 가능하도록 암나사부가 구비된다.
즉, 커플링(20)이 나사 체결된 앵커볼트(10)를 기초 구조물(1)의 시공을 위한 철근 등에 고정하여 설치하며, 이때, 커플링(20)이 기초 구조물(1) 상부로 돌출되지 않도록 설치한다. 물론, 커플링(20)이 기초 구조물(1)의 상부로 돌출되는 것도 무방하고, 이 경우 커플링(20)이 후술하는 앵커플레이트(40)의 체결공(41)에 삽입되도록 함으로써 앵커플레이트(40)의 초기 설치가 용이하고 앵커플레이트(40)의 흔들림을 막을 수 있을 것이다.That is, the
한편, 콘크리트의 타설 과정에서 콘크리트가 커플링(20)의 암나사부에 침투하지 않도록 커플링(20)의 암나사부에는 추후에 제거할 수 있지만 콘크리트의 침투를 막을 수 있는 충진재(고무 등)가 삽입된다.Meanwhile, in order to prevent concrete from penetrating into the female threaded portion of the
프리캐스트 콘크리트 블록 타입의 기초 구조물도 전술한 것과 동일한 방법으로 시공되고, 앵커볼트(10)와 커플링(20)이 설치된다.
The base structure of the precast concrete block type is also constructed in the same manner as described above, and the
2. 앵커플레이트 설치.2. Anchor plate installation.
도로 시설물의 지주(2)를 기초 구조물(1)에 설치하기 위하여 앵커플레이트(40)가 적용된다.An
앵커플레이트(40)는 지주(2)와 앵커볼트(10)가 안정적으로 설치될 수 있는 단면적과 두께로 이루어진 예컨대 철판이며, 기초볼트(30)를 체결하기 위한 체결공(41)이 구비된다. 체결공(41)은 상하부가 관통되는 구멍이며, 기초볼트(30)의 두부가 안착되는 안착턱(43)이 함께 구성된다. 체결공(41)은 시공 오차 등이 발생하여도 기초볼트(30)를 기초 구조물(1)에 고정된 커플링(20)에 체결할 수 있도록 기초볼트(30)의 볼트부(31)보다 큰 직경으로 형성되고, 또한, 기초볼트(30)의 두부가 앵커플레이트(40)의 상면으로 돌출되지 않는 깊이로 형성된다.
The
앵커플레이트(40)는 지주(2)의 하단부에 일체로 형성된 것도 가능하고, 도로 시설물의 다양한 지주에 적용 가능하도록 지주 고정부(42)가 구비되는 것도 가능하다. 지주 고정부(42)는 다양한 종류의 지주(2)의 고정이 가능하도록 다양한 구조로 변경 가능하며, 예를 들어, 앵커플레이트(40)의 상면에서 상부로 돌출되며 지주(2)에 내접 또는 외접되도록 끼움 및 고정수단[지주(2)와 지주 고정부(42)를 관통하는 볼트와 너트의 조합 등]을 통해 지주(2)가 고정될 수 있다.The
커플링(20)이 기초 구조물(1)에 돌출되지 않는 경우 앵커플레이트(40)의 체결공(41)을 커플링(20)에 맞도록 안착하고, 커플링(20)이 기초 구조물(1)에 돌출된 경우 앵커플레이트(40)의 체결공(41)에 커플링(20)의 돌출부가 삽입되도록 한다.If the
도면에서는 앵커플레이트(40)가 기초 구조물(1)의 상부로 돌출된 것으로 도시되었으나, 기초 구조물(1)에 홈을 형성하여 앵커플레이트(40)가 돌출되지 않을 수도 있다.
Although the
3. 기초볼트 체결.3. Foundation bolt tightening.
앵커플레이트(40)를 안착한 후, 기초볼트(30)의 볼트부(31)를 체결공(41)에 삽입 및 커플링(20)에 나사 체결함으로써 기초볼트(30)를 앵커플레이트(40)에 체결하여 앵커플레이트(40)를 기초 구조물(1)에 고정한다. After mounting the
기초볼트(30)의 체결시 기초볼트(30)와 앵커플레이트(40)간의 결속력을 증대하기 위하여 기초볼트(30)의 두부와 앵커플레이트(40)의 안착턱(43) 사이에 스프링와셔(32)가 개재되는 것이 바람직하다.Spring washer 32 between the head of the
또한, 도로 시설물이나 기초 구조물(1)에 전가되는 힘에 의해 기초볼트(30)가 커플링(20)에서 풀릴 수 있고, 나사 체결만으로는 기초볼트(30)의 풀림을 방지할 수 없으므로 기초볼트(30)의 풀림방지를 위하여 앵커볼트(40)의 체결공(41) 안에 채움재(예를 들어 몰탈)(50)를 채운다. 채움재(50)는 자연 경화, 강제 경화 등을 통해 체결공(41)안에 경화되어 기초볼트(30)를 체결공(41)에 고착시킴으로써 기초볼트(30)가 풀리지 않도록 한다.
In addition, the
1 : 기초 구조물, 2 : 지주
10 : 앵커볼트, 20 : 커플링
30 : 기초볼트, 40 : 앵커플레이트
41 : 체결공, 42 : 지주 고정부
43 : 안착턱, 50 : 채움재1: foundation structure, 2: prop
10: anchor bolt, 20: coupling
30: foundation bolt, 40: anchor plate
41: fastening hole, 42: holding fixture
43: seating jaw, 50: filling material
Claims (4)
상기 제1단계를 통해 시공된 기초 구조물의 상면에 도로 시설물의 지주를 세우기 위한 앵커플레이트(40)를 안착하되, 상기 앵커플레이트는 상기 커플링의 암나사부와 일치하는 체결공(41), 상면에 상기 지주에 내접 또는 외접하면서 끼워지고 고정수단을 통해 고정되는 지주 고정부(42)가 포함되어 상기 체결공(41)을 상기 커플링의 암나사부와 일치되도록 안착하는 제2단계와;
상기 제2단계를 통해 안착된 앵커플레이트의 체결공을 통하여 기초볼트(30)를 상기 커플링의 암나사부에 체결하여 상기 앵커플레이트를 상기 앵커볼트에 고정하되, 상기 기초볼트의 두부가 상기 앵커플레이트의 체결공 둘레부에 형성된 안착턱(43)에 삽입되어 앵커플레이트의 상부로 돌출되지 않도록 하는 제3단계를 포함하고;
상기 제3단계에서는, 상기 기초볼트의 두부 아래쪽에 스프링와셔를 개재한 후 상기 기초볼트를 체결하고, 상기 기초볼트를 체결 후 상기 체결공의 내부에 채움재를 충진하여 상기 기초볼트의 풀림을 방지하며,
상기 제1단계에서는 상기 커플링을 상기 기초 구조물의 상부로 돌출시키고, 상기 제2단계에서는 상기 앵커플레이트의 체결공에 상기 기초 구조물에서 돌출된 커플링이 삽입되도록 상기 앵커플레이트를 설치하여 상기 앵커플레이트가 상기 앵커볼트에 체결된 커플링에 끼움 결합되도록 하는 것을 특징으로 하는 도로 구조물의 기초 시공 방법.Construct a block-type foundation structure (1) in the ground or ground, install an L-shaped anchor bolt (10) for fixing the pillar of the road facility in the foundation structure, the female screw portion at the ground end of the anchor bolt A first step of screwing the provided coupling 20;
The anchor plate 40 for mounting the prop of the road facility on the upper surface of the foundation structure constructed through the first step, the anchor plate is fastened to the fastening hole 41, the upper surface corresponding to the female screw portion of the coupling A second step of mounting the fastening hole 41 to be coincident with the female screw portion of the coupling by including a support fixing portion 42 which is fitted while being internally or externally fitted to the support and is fixed through the fixing means;
Fastening the anchor plate to the anchor bolt by fastening the foundation bolt 30 to the female screw portion of the coupling through the fastening hole of the anchor plate seated through the second step, the head of the foundation bolt to the anchor plate And a third step inserted into the seating jaw 43 formed at the periphery of the fastening hole so as not to protrude to the top of the anchor plate;
In the third step, the spring bolt is interposed below the head of the foundation bolt, and then the foundation bolt is fastened, and after the fastening of the foundation bolt, the filler is filled in the fastening hole to prevent loosening of the foundation bolt. ,
In the first step, the coupling is projected to the upper portion of the base structure, and in the second step, the anchor plate is installed so that the coupling plate protruding from the base structure is inserted into the fastening hole of the anchor plate. The base construction method of the road structure, characterized in that the fitting is coupled to the coupling fastened to the anchor bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020130041798A KR101388253B1 (en) | 2013-04-16 | 2013-04-16 | Base structure of road facility |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020130041798A KR101388253B1 (en) | 2013-04-16 | 2013-04-16 | Base structure of road facility |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101388253B1 true KR101388253B1 (en) | 2014-04-24 |
Family
ID=50658471
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020130041798A KR101388253B1 (en) | 2013-04-16 | 2013-04-16 | Base structure of road facility |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101388253B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101888151B1 (en) * | 2018-04-19 | 2018-08-13 | (주)금비타워크레인 | Wall bracing apparatus for tower crane |
CN109235485A (en) * | 2018-10-24 | 2019-01-18 | 国网江苏省电力有限公司无锡供电分公司 | A kind of assembled power supply unit bracket basis |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200427360Y1 (en) * | 2006-06-28 | 2006-09-25 | 주식회사 신동아정공 | The Coupling Anchor Bolt for Concrete Pavement |
KR20080108705A (en) * | 2007-06-11 | 2008-12-16 | (주) 케이 이엔씨 | Bolt washer structure for bridge expansion joint |
KR101036237B1 (en) * | 2010-07-27 | 2011-05-20 | 주식회사 케이씨전자 | Pillar device for street furniture with street environment improvement structure |
-
2013
- 2013-04-16 KR KR1020130041798A patent/KR101388253B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR200427360Y1 (en) * | 2006-06-28 | 2006-09-25 | 주식회사 신동아정공 | The Coupling Anchor Bolt for Concrete Pavement |
KR20080108705A (en) * | 2007-06-11 | 2008-12-16 | (주) 케이 이엔씨 | Bolt washer structure for bridge expansion joint |
KR101036237B1 (en) * | 2010-07-27 | 2011-05-20 | 주식회사 케이씨전자 | Pillar device for street furniture with street environment improvement structure |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101888151B1 (en) * | 2018-04-19 | 2018-08-13 | (주)금비타워크레인 | Wall bracing apparatus for tower crane |
CN109235485A (en) * | 2018-10-24 | 2019-01-18 | 国网江苏省电力有限公司无锡供电分公司 | A kind of assembled power supply unit bracket basis |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101077238B1 (en) | Post foundation and constructing method using the same | |
KR200435077Y1 (en) | Hock Strut Assembly Structure and Foundation Lid | |
KR100885131B1 (en) | A fixing structure of pillar and construction method thereof | |
KR101229250B1 (en) | Pile type fence support device of fence | |
KR20200046412A (en) | Landfill facility for bridge inspection structure and construction method | |
KR100947852B1 (en) | Joint Structure Betweeen Street Lighting Pole and Base | |
KR100991886B1 (en) | A fixing structure of pillar | |
KR101114840B1 (en) | Assembly for support which is reinforced | |
KR101388253B1 (en) | Base structure of road facility | |
KR101066388B1 (en) | Embed type installation jig and its installation method for street lamp post fabricated easily and installed accurately | |
KR101358754B1 (en) | Pole for road facilities | |
KR200433150Y1 (en) | upholder for street lamppost | |
KR200453088Y1 (en) | Improved traffic-control sign tool | |
KR101011372B1 (en) | The foundation a streetlight for nstallation | |
KR200418034Y1 (en) | Soundproof wall support | |
KR100859660B1 (en) | Base for fixing support of road facilities | |
KR101338390B1 (en) | Support fixed apparatus | |
KR101148172B1 (en) | Street Lighting Pole Laying Footing Structure and Electing Method of Street Lighting Pole using the same | |
KR20100000441U (en) | post of the underground insertion type for the street | |
KR101354455B1 (en) | In-ground supporting structure of a post | |
KR20100104104A (en) | Supporting structure | |
KR101037594B1 (en) | A block of a wing type | |
KR20100042446A (en) | A fixing structure of pillar and construction method thereof | |
KR100920127B1 (en) | A support structure object for a road traffic equipment and construction method | |
JP2007297897A (en) | Pole structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E902 | Notification of reason for refusal | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20170213 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20180516 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20190507 Year of fee payment: 6 |