KR101017117B1 - Method and device for waterproofing steel pipe loop structure by a water drainage process for constructing underground structure by non-excavation - Google Patents
Method and device for waterproofing steel pipe loop structure by a water drainage process for constructing underground structure by non-excavation Download PDFInfo
- Publication number
- KR101017117B1 KR101017117B1 KR1020100085497A KR20100085497A KR101017117B1 KR 101017117 B1 KR101017117 B1 KR 101017117B1 KR 1020100085497 A KR1020100085497 A KR 1020100085497A KR 20100085497 A KR20100085497 A KR 20100085497A KR 101017117 B1 KR101017117 B1 KR 101017117B1
- Authority
- KR
- South Korea
- Prior art keywords
- steel pipe
- loop structure
- drainage
- pipe loop
- lower joint
- Prior art date
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 188
- 239000010959 steel Substances 0.000 title claims abstract description 188
- 238000000034 method Methods 0.000 title claims abstract description 50
- 238000004078 waterproofing Methods 0.000 title claims abstract description 29
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title abstract description 6
- 238000009412 basement excavation Methods 0.000 title abstract description 3
- 239000002689 soil Substances 0.000 claims abstract description 5
- 230000006698 induction Effects 0.000 claims description 57
- 238000010276 construction Methods 0.000 claims description 32
- 238000003466 welding Methods 0.000 claims description 12
- 238000004140 cleaning Methods 0.000 claims description 7
- 230000001788 irregular Effects 0.000 claims description 7
- 238000007599 discharging Methods 0.000 abstract description 2
- 239000000463 material Substances 0.000 abstract 1
- 239000003673 groundwater Substances 0.000 description 7
- 239000004576 sand Substances 0.000 description 5
- 239000011248 coating agent Substances 0.000 description 4
- 238000000576 coating method Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 4
- 239000000853 adhesive Substances 0.000 description 3
- 230000001070 adhesive effect Effects 0.000 description 3
- 238000009415 formwork Methods 0.000 description 3
- 230000007547 defect Effects 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 208000001034 Frostbite Diseases 0.000 description 1
- 239000011230 binding agent Substances 0.000 description 1
- 238000001035 drying Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 239000004033 plastic Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 239000002990 reinforced plastic Substances 0.000 description 1
- 238000007665 sagging Methods 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/19—Three-dimensional framework structures
- E04B1/1903—Connecting nodes specially adapted therefor
- E04B1/1909—Connecting nodes specially adapted therefor with central cylindrical connecting element
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/04—Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Electromagnetism (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
본 발명은 비개착 지중구조물의 축조를 위한 강관루프구조체의 배수식 방수 방법 및 장치에 관한 것으로, 더욱 상세하게는 지중에 압입 추진되는 강관을 이용하여 구축되는 강관루프구조체와 그 강관루프구조체의 내측에 조성되는 콘크리트 구조물의 사이에 적용되는, 비개착 지중구조물의 축조를 위한 개방형 유도배수관을 이용한 강관루프구조체의 배수식 방수 방법 및 장치에 관한 것이다.The present invention relates to a drainage type waterproofing method and apparatus for constructing an unattached underground structure, and more particularly, to a steel pipe loop structure and an inner side of the steel pipe loop structure, which are constructed by using a steel pipe press-propelled in the ground. The present invention relates to a drainage waterproof method and apparatus for a steel pipe loop structure using an open induction drainage pipe for construction of an unattached underground structure applied between concrete structures.
도 1 내지 도 3에 도시한 바와 같이, 통상 비개착 지중구조물은 도 1의 지중에 강관(10)을 압입 추진하여 강관(10)의 외측 상하부에 형성된 상부 날개부의 상부 조인트부(23)와 하부 날개부의 하부 조인트부(27)가 마주하도록 강관루프구조체(100)를 설치하는 제1 공정과, 도 2의 축조된 강관루프구조체(100)를 지보재로 하여 내측의 토사를 굴착제거하고 강관(10)의 하부와 하부 조인트부(27)에 방수시트(30)를 부착하는 제2 공정과, 도 3의 지중구조물(200)을 설치하는 제3 공정을 포함하여 축조된다. As shown in Figures 1 to 3, the non-attached underground structure is usually the
비개착 지중구조물의 축조를 위하여 지중에 설치되는 강관루프구조체(100)는 지중에 루프상으로 압입 추진된 강관(10)을 이용한 가설용 구조체로서 강관 내측은 몰탈로 충진되는데 압입 추진 강관으로 조성되는 구조 특성상 추진 강관의 횡방향 연결부에서 종방향으로 하부 조인트부가 형성되고 이곳에 지하수가 모이면 방수시트(30)가 들뜨게 되어 누수가 발생된다. The steel
종래의 방수 방법은 강관루프구조체(100) 내측에 방수시트(30)를 일괄적으로 단순 부착하거나 방수도료를 스프레이방식으로 피복하여 방수도막을 조성하고, 방수시트(30) 및 방수도막에 접하여 콘크리트 지중구조물(200)을 시공한다. Conventional waterproofing method by simply attaching the
이를 보다 상세히 설명하면 종래의 방수 방법은 도 1에서와 같이 지중(50)에 강관(10)을 압입 추진함으로써 강관루프구조체(100)가 조성되고 도 2에서와 같이 강관루프구조체(100)의 내측(55)의 굴착이 완료된 상태에서 강관루프구조체(100)의 내측의 강관(10) 외부와 강관(10)과 강관(10)을 이어주는 하부 조인트부(27)에 방수시트(30)를 부착하거나 방수도료를 피복하는 방수공정이 이루어진다. In more detail, in the conventional waterproof method, the steel
또한 방수공정이 완료된 후에는 도 3에 도시한 바와 같이 지중구조물(200)의 본체를 축조하기 위하여 콘크리트가 타설되는데 강관루프구조체(100) 내측에 거푸집(210) 및 서포트(220)을 설치한 상태에서 충전형식으로 타설이 이루어진다. 그러므로 강관루프구조체(100)의 벽부(110)는 타설되는 콘크리트의 횡력에 의해 방수시트(30)가 확실하게 고정 밀착되나 천정부(120)는 벽부(110)보다 충전성이 떨어져 방수시트(30)의 밀착효과를 기대할 수 없고, 또한 밀실하게 충전되더라도 콘크리트의 양생에 따른 건조 수축 작용에 의해 방수시트와 콘크리트의 접착부가 분리되는 문제점이 발생하게 된다. 이러한 문제점은 강관루프구조체(100)의 누수 시 방수시트(30)의 기능에 직접적으로 영향을 주게 된다. In addition, after the waterproofing process is completed, concrete is poured in order to build the main body of the
도 4 및 도 5의 기존 방수시트 공법의 누수 개념도에서와 같이 강관루프구조체(100)의 누수는 압입 추진된 강관의 종방향 조인트 부위의 틈새로 지하수가 침투함으로써 발생하게 된다. 누수 경로는 토사(21)→상부 조인트부(23)→강관 외측면(25)→하부 조인트부(27)→방수시트(30)→콘크리트 지중구조물(200) 순으로 누수가 전파되는데 이것은 방수시트(30)의 기능에 직접적으로 영향을 주게 된다. 4 and 5, the leakage of the steel
즉 지하수가 모이는 곳에서는 강관구조체(100) 하면의 방수시트(30)에 가해지는 압력이 점차 증가하게 되므로 장기적으로는 도 4 및 도 5에 도시한 바와 같이 누수의 워터포켓(33)으로 인하여 방수시트(30)의 들뜸 현상(34)이 발생하여 방수시트(30)가 박락되어 방수기능을 상실하게 된다. That is, where the groundwater is collected, the pressure applied to the
또한 방수시트(30)에 의한 방식은 전면 방수 방식으로 방수면적이 넓어져 시공비가 증가하게 되며 방수시트 부착시 상향 작업으로 인해 연속적인 시트의 고정작업이 곤란하고 고온의 여름철 시공시에는 시트의 부착성이 떨어져 시공성이 급격히 저하되는 문제점이 발생하며 내부 가설기둥의 저촉으로 완벽한 방수가 곤란하다. In addition, the method by the
본 발명자가 출원한 종래의 비개착 지중구조물에 관련된 대한민국 특허공개 2009-0114863(2009. 11. 04), 2007-0088172(2007. 08. 29), 2007-0088114(2007. 08. 29), 2006-0029348(2006. 04. 06), 2005-0098338(2005. 10. 12), 및 2005-0092881(2005. 09. 23)에 적용되는 방수기술도 상술한 종래의 단점으로부터 완전히 자유롭지 않다.Korean Patent Publication No. 2009-0114863 (2009. 11. 04), 2007-0088172 (2007. 08. 29), 2007-0088114 (2007. 08. 29), 2006 The waterproofing technique applied to -0029348 (April 06, 2006), 2005-0098338 (October 12, 2005), and 2005-0092881 (September 23, 2005) is also not completely free from the above-mentioned disadvantages.
본 발명은 이와 같은 종래의 기술의 문제점을 해소하고자 하는 것으로서, 지중구조물의 본체 콘크리트 타설 전, 개방형 유도배수관을 강관루프구조체 내측에 설치하여 누수를 외부로 배출시켜 완벽한 구조체의 방수를 이루고자 하는 것이며 또한 시공성과 경제성이 우수한 비개착 지중구조물의 축조를 위한 강관루프구조체의 배수식 방수 방법 및 장치를 제공하는 것을 목적으로 한다. The present invention is to solve the problems of the prior art, and to install the induction drainage pipe inside the steel pipe loop structure before the concrete pouring of the underground structure to discharge the leakage to the outside to achieve a perfect waterproof structure An object of the present invention is to provide a drainage type waterproofing method and apparatus for a steel pipe loop structure for constructing an unattached underground structure having excellent workability and economy.
본 발명은 이와 같은 종래의 기술의 문제점을 해소하고자 하는 것으로서, 지중구조물의 본체 콘크리트 타설 전, 개방형 유도배수관을 강관루프구조체 내측에 설치하여 누수를 외부로 배출시켜 완벽한 구조체의 방수를 이루고자 하는 것이며 또한 시공성과 경제성이 우수한 비개착 지중구조물의 축조를 위한 강관루프구조체의 방수 방법 및 장치를 이용한 지중구조물의 배수식 축조방법을 제공하는 것을 목적으로 한다. The present invention is to solve the problems of the prior art, and to install the induction drainage pipe inside the steel pipe loop structure before the concrete pouring of the underground structure to discharge the leakage to the outside to achieve a perfect waterproof structure It is an object of the present invention to provide a drainage construction method for underground structures using a waterproofing method and apparatus for steel pipe loop structures for construction of non-attached underground structures having excellent workability and economic efficiency.
본 발명은 상기 발명이 해결하려는 과제를 달성하기 위하여, 비개착 지중구조물의 축조를 위한 강관루프구조체의 배수식 방수 방법에 있어서, The present invention, in order to achieve the problem to be solved by the present invention, in the drainage type waterproofing method of the steel pipe loop structure for the construction of the unattached underground structure,
비개착 지중구조물의 축조를 위하여 지중으로 압입 추진된 강관으로 형성된 강관루프구조체를 지보재로 하여 내측의 토사를 굴착제거하는 단계; 및 Excavating and removing the earth soil inside the steel pipe loop structure formed of the steel pipe pushed and pushed into the ground for the construction of the unbonded underground structure as a support; And
상기 강관루프구조체의 내측의 벽부 및/또는 천정부의 강관이음부인 종방향 하부 조인트부에 배수부를 고정설치하는 단계를 포함하는 강관루프구조체의 배수식 방수 방법을 제공한다. It provides a drainage waterproofing method of the steel pipe loop structure comprising the step of fixing the drainage portion in the longitudinal lower joint portion that is the inner wall portion of the steel pipe loop structure and / or the steel pipe joint of the ceiling.
바람직하기로는 강관루프구조체의 내측의 벽부 및/또는 천정부의 종방향 하부 조인트부의 바탕면을 정리하고 청소하는 단계를 더 포함한다. Preferably, the method further comprises cleaning and cleaning the base surface of the inner wall of the steel pipe loop structure and / or the longitudinal lower joint portion of the ceiling.
바람직하기로는 상기 배수부는 강관과 강관의 종방향 하부 조인트부를 따라서 부착되는 개방형 유도배수관으로 하부 조인트부에 탭용접으로 고정됨을 특징으로 한다. Preferably, the drainage portion is an open induction drainage pipe attached along the longitudinal lower joint portion of the steel pipe and the steel pipe, and is fixed by tap welding to the lower joint portion.
바람직하기로는 상기 강관루프구조체의 내측의 불규칙한 벽부 및/또는 천정부와 개방형 유도배수관 간의 틈을 누수가 발생치 않도록 퍼티로 메우는 단계를 더 포함한다. Preferably, the method may further include filling the gap between the irregular wall portion and / or the ceiling and the open induction drain pipe inside the steel pipe loop structure with a putty such that no leakage occurs.
바람직하기로는 상기 유도배수관을 감싸도록 일정 크기의 방수시트를 부착하는 단계를 더 포함한다. Preferably, the method further includes attaching a waterproof sheet of a predetermined size to surround the induction drainage pipe.
바람직하기로는 상기 강관루프구조체의 내측의 천정부에만 강관이음부인 종방향 하부 조인트부에 배수부를 고정설치하는 경우, 상기 강관루프구조체의 내측의 벽부의 강관이음부인 종방향 하부 조인트부에는 방수시트가 부착되거나 강판이 용접부착되는 단계를 더 포함한다.Preferably, when the drainage part is fixed to the longitudinal lower joint part that is a steel pipe fitting part only on the ceiling of the inner side of the steel pipe loop structure, a waterproof sheet is attached to the longitudinal lower joint part that is a steel pipe fitting part of the inner wall part of the steel pipe loop structure. Or the steel sheet is welded.
본 발명은 상기 발명이 해결하려는 과제를 달성하기 위하여, 비개착 지중구조물의 축조를 위하여 지중으로 압입 추진된 강관으로 형성된 강관루프구조체의 배수식 방수 장치에 있어서, In the present invention, in order to achieve the problem to be solved by the present invention, in the drainage waterproofing device of the steel pipe loop structure formed of steel pipes pushed and pushed into the ground for the construction of the non-attached underground structure,
상기 강관루프구조체의 내측의 벽부 및/또는 천정부의 강관이음부인 종방향 하부 조인트부; 및A longitudinal lower joint portion that is an inner wall portion of the steel pipe loop structure and / or a steel pipe fitting portion of a ceiling; And
상기 강관이음부인 종방향 하부 조인트부에 종방향으로 고정설치된 배수부를 포함하는 강관루프구조체의 배수식 방수 장치를 제공한다. It provides a drainage waterproof device of the steel pipe loop structure including a drainage portion fixed in the longitudinal direction in the longitudinal lower joint portion that is the steel pipe joint.
바람직하기로는 상기 배수부는 강관과 강관의 종방향 하부 조인트부를 따라서 부착되는 개방형 유도배수관으로 하부 조인트부에 탭용접으로 고정됨을 특징으로 한다. Preferably, the drainage portion is an open induction drainage pipe attached along the longitudinal lower joint portion of the steel pipe and the steel pipe, and is fixed by tap welding to the lower joint portion.
바람직하기로는 상기 유도배수관을 감싸도록 일정 크기의 방수시트를 부착하는 것을 특징으로 한다. Preferably, the waterproof sheet is attached to a predetermined size to surround the induction drainage pipe.
본 발명은 상기 발명이 해결하려는 과제를 달성하기 위하여, 강관루프구조체를 이용한 비개착 지중구조물의 배수식 축조 방법에 있어서, The present invention, in order to achieve the problem to be solved by the present invention, in the drainage construction method of the non-attached underground structure using a steel pipe loop structure,
지중으로 강관을 압입 추진하여 강관루프구조체를 형성하는 단계; Press-propelling the steel pipe into the ground to form a steel pipe loop structure;
상기 강관루프구조체를 지보재로 하여 내측의 토사를 굴착제거하는 단계; 및 Excavating and removing the soil inside the steel pipe loop structure as a support; And
상기 강관루프구조체의 내측의 벽부 및/또는 천정부의 강관이음부인 종방향 하부 조인트부에 배수부를 고정설치하는 단계; 및 Fixing the drainage portion to a longitudinal lower joint portion that is an inner wall portion of the steel pipe loop structure and / or a steel pipe fitting portion of a ceiling; And
상기 강관루프구조체 내측에 거푸집 및 서포트를 설치한 상태에서 충전 형식으로 콘크리트 타설함으로써 지중구조물을 형성하는 단계를 포함하는 비개착 지중구조물의 배수식 축조 방법을 제공한다. It provides a drainage construction method of the non-attached underground structure comprising the step of forming the underground structure by pouring concrete in the form of filling in the form of the formwork and support inside the steel pipe loop structure.
바람직하기로는 강관루프구조체의 내측의 벽부 및/또는 천정부 종방향 하부 조인트부의 바탕면을 정리하고 청소하는 단계를 더 포함한다. Preferably, the method further comprises cleaning and cleaning the base surface of the inner wall of the steel pipe loop structure and / or the ceiling longitudinal lower joint portion.
바람직하기로는 상기 배수부는 강관과 강관의 종방향 하부 조인트부를 따라서 부착된 개방형 유도배수관으로 하부 조인트부에 탭용접으로 고정됨을 특징으로 한다. Preferably, the drain portion is an open induction drain pipe attached along the longitudinal lower joint portion of the steel pipe and the steel pipe is fixed by tap welding to the lower joint portion.
바람직하기로는 상기 강관루프구조체의 내측의 불규칙한 벽부 및/또는 천정부와 개방형 유도배수관 간의 틈을 누수가 발생치 않도록 퍼티로 메우는 단계를 더 포함한다. Preferably, the method may further include filling the gap between the irregular wall portion and / or the ceiling and the open induction drain pipe inside the steel pipe loop structure with a putty such that no leakage occurs.
바람직하기로는 상기 유도배수관을 감싸도록 일정 크기의 방수시트를 부착하는 단계를 더 포함한다. Preferably, the method further includes attaching a waterproof sheet of a predetermined size to surround the induction drainage pipe.
바람직하기로는 상기 강관루프구조체의 내측의 천정부에만 강관이음부인 종방향 하부 조인트부에 배수부를 고정설치하는 경우, 상기 강관루프구조체의 내측의 벽부의 강관이음부인 종방향 하부 조인트부에는 방수시트가 부착되거나 강판이 용접부착되는 단계를 더 포함한다.Preferably, when the drainage part is fixed to the longitudinal lower joint part that is a steel pipe fitting part only on the ceiling of the inner side of the steel pipe loop structure, a waterproof sheet is attached to the longitudinal lower joint part that is a steel pipe fitting part of the inner wall part of the steel pipe loop structure. Or the steel sheet is welded.
본 발명은 지중으로 강관을 압입 추진하여 형성된 강관루프구조체의 내측의 종방향 하부 조인트부에 배수 목적의 개방형 유도배수관을 예를 들면 10-15cm 간격의 탭용접으로 고정하여, 상기 개방형 유도배수관을 통하여 누수가 배수되게 함으로써, 종래 기술에서의 지하수의 누수 시 강관루프구조체 벽부 및/또는 천정부에 부착된 방수시트의 늘어짐으로 인하여 발생하는 방수 하자 문제를 해결하였다. The present invention secures the open induction drainage pipe for drainage purpose by tap welding at intervals of 10-15 cm, for example, through the open induction drainage pipe in the longitudinally lower joint portion of the inner side of the steel pipe loop structure formed by press-propelling the steel pipe underground. By allowing the water to drain, it solves the problem of water-proof defects caused by sagging of the waterproof sheet attached to the wall of the steel pipe loop structure and / or the ceiling when the groundwater leaks in the prior art.
또한, 지중으로 강관을 압입 추진하여 형성된 강관루프구조체의 내측의 벽부 및/또는 천정부에 고정된 개방형 유도 배수관과 강관루프구조체간의 불규칙한 틈새에 누수가 발생치 않도록 퍼티로 처리하고 개방형 유도배수관을 감싸도록 부분적으로 또는 전체적으로 방수시트를 부착함으로써 종래 기술의 방수 하자 문제를 더욱 완벽히 해결하는 효과가 있다. In addition, by inserting and pushing the steel pipe into the ground, it is treated with a putty so as to prevent leakage in an irregular gap between the open induction drain pipe and the steel pipe loop structure fixed to the inner wall of the steel pipe roof structure and / or the ceiling, and to surround the open induction drain pipe. By attaching the waterproof sheet partially or entirely, there is an effect of more completely solving the problem of waterproof defects of the prior art.
이로써, 본 발명은 완벽한 방수 기능으로 본체구조물의 누수로 인한 동상 피해의 예방, 시설물의 내구 수명 향상, 및 지하 시설물의 사용에 있어 쾌적한 환경을 제공하는 것이다. Thus, the present invention is to provide a comfortable environment in the prevention of frostbite damage caused by the leakage of the main body structure, the durability life of the facility, and the use of underground facilities with a perfect waterproof function.
도 1 내지 도 3은 종래의 비개착 지중구조물의 시공 순서를 설명하기 위한 단면도이다.
도 4 및 도 5는 종래의 비개착 지중구조물의 방수시트 공법을 설명하기 위한 부분 단면도이다.
도 6 내지 도 8은 본 발명에 의한 비개착 지중구조물의 축조를 위하여 지중으로 강관을 압입 추진하여 형성된 강관루프구조체의 배수식 방수 방법을 설명하기 위한 공정 부분 단면도이다.
도 9 및 도 10은 본 발명에 의한 비개착 지중구조물의 축조를 위한 강관루프구조체의 배수식 방수 방법을 보다 상세히 설명하기 위한 부분 상세 단면도이다.
도 11 및 도 12는 본 발명에 의한 비개착 지중구조물의 축조를 위한 강관루프구조체의 방수 장치에 적용되는 배수부의 일실시예에 의한 유로부의 단면이 반원형인 개방형 유도배수관을 도시한 사시도로, 도 11은 날개부가 외측으로 돌출된 유도배수관을 나타내고, 도 12는 날개부가 내측으로 접혀진 유도배수관을 나타낸다.
도 13 및 도 14는 본 발명에 의한 비개착 지중구조물의 축조를 위한 강관루프구조체의 방수 장치에 적용되는 배수부의 일실시예에 의한 유로부의 단면이 V자형인 개방형 유도배수관을 도시한 사시도로, 도 13은 날개부가 외측으로 돌출된 유도배수관을 나타내고, 도 14는 날개부가 내측으로 접혀진 유도배수관을 나타낸다.
도 15 및 도 16은 본 발명에 의한 비개착 지중구조물의 축조를 위한 강관루프구조체의 방수 장치에 적용되는 배수부의 일실시예에 의한 유로부의 단면이 U자형인 개방형 유도배수관을 도시한 사시도로, 도 15은 날개부가 외측으로 돌출된 유도배수관을 나타내고, 도 16은 날개부가 내측으로 접혀진 유도배수관을 나타낸다. 1 to 3 are cross-sectional views illustrating a construction procedure of a conventional non-adhesive underground structure.
4 and 5 are partial cross-sectional views for explaining a waterproof sheet method of the conventional non-attached underground structure.
6 to 8 is a partial cross-sectional view for explaining the drainage waterproof method of the steel pipe loop structure formed by press-propelling the steel pipe to the ground for the construction of the non-attached underground structure according to the present invention.
9 and 10 are partial detailed cross-sectional view for explaining in more detail the drainage waterproofing method of the steel pipe loop structure for the construction of the unattached underground structure according to the present invention.
11 and 12 are perspective views illustrating an open induction drain pipe having a semicircular cross section of a flow path part according to an embodiment of the drainage part applied to the waterproofing device of the steel pipe loop structure for the construction of an unattached underground structure according to the present invention; 11 shows an induction drainage pipe with its wings protruded outward, and FIG. 12 shows an induction drainage pipe with its wings folded inward.
13 and 14 are perspective views illustrating an open induction drain pipe having a V-shaped cross section of a flow path part according to an embodiment of the drainage part applied to the waterproofing device of the steel pipe loop structure for the construction of an unattached underground structure according to the present invention; FIG. 13 shows the induction drainage pipe with its wings protruded outward, and FIG. 14 shows the induction drainage pipe with its wings folded inward.
15 and 16 are perspective views illustrating an open induction drain pipe having a U-shaped cross section of a flow path part according to an embodiment of the drainage part applied to the waterproofing device of the steel pipe loop structure for the construction of an unattached underground structure according to the present invention; 15 shows the induction drainage pipe with its wings protruded outward, and FIG. 16 shows the induction drainage pipe with its wings folded inward.
본 발명은 도로나 철도 하부를 횡단하여 비개착공법으로 지중에 강관을 압입 추진함으로써 시공된 강관루프구조체의 내측에 설치되는 지중구조물의 배수식 방수 방법 및 장치에 관한 것으로서, 첨부된 도면을 참조하여 실시예를 통하여 상세히 설명하기로 한다. The present invention relates to a drainage type waterproofing method and apparatus for underground structures installed inside a steel pipe loop structure constructed by press-propelling steel pipes in the ground by a non-opening method across a road or a railroad, with reference to the accompanying drawings. It will be described in detail through the embodiment.
설명의 편의상 각 도면에서 동일하거나 유사한 구성요소들은 동일한 참조부호로 표시된다. In the drawings, the same or similar elements are denoted by the same reference numerals for convenience of description.
본 발명에 의한 비개착 지중구조물의 축조를 위하여 지중에 강관을 압입 추진하여 형성된 강관 강관루프구조체의 배수식 방수 방법 및 장치는 지중에 압입 추진되는 강관을 이용하여 구축되는 강관루프구조체와 그 강관루프구조체의 내측에 조성되는 콘크리트 지중구조물 사이에 적용되는 배수부에 의해 구현된다. 본 발명의 배수부의 바람직한 실시예들은 다양한 형상의 개방형 유도배수관으로 구현된다. The drainage waterproofing method and apparatus for a steel pipe steel pipe loop structure formed by press-propelling a steel pipe in the ground for the construction of an unattached underground structure according to the present invention is a steel pipe loop structure and a steel pipe loop constructed by using a steel pipe that is press-propelled into the ground. It is realized by a drainage applied between the concrete underground structures formed inside the structure. Preferred embodiments of the drainage of the present invention is implemented as an open induction drainage pipe of various shapes.
개방형 유도배수관의 구성은 도 11 및 도 12와 같이 개방형 유도배수관을 강관과 강관의 조인트 이음부에 고정시키는 날개부(A)와 반달형의 유로부(B)로 구성되며, 도 13 내지 도 16에서와 같이 유로부가 U자형이나 V자형 등 다양한 형태로 적용이 가능하다. The configuration of the open induction drainage pipe is composed of a wing portion (A) and a half moon-shaped flow path portion (B) for fixing the open induction drainage pipe to the joint joint of the steel pipe and the steel pipe as shown in Figure 11 and 12, in Figures 13 to 16 Like this, the flow path portion can be applied in various forms such as U-shaped or V-shaped.
개방형 유도배수관의 재질은 용접이 가능한 강재로 하며 두께는 벽부 및/또는 천정부 변형에 연성적으로 대응하도록 얇은 강판을 사용하는 것이 바람직하며 T=2mm-5mm가 적당하다. 또한 개방형 유도배수관의 제작시 길이는 4-6m가 바람직하다. 물론 강재 이외에 플라스틱, 큰크리트, 강화 플라스틱 등으로 제작되어 다양한 결합재(본드)로 부착될 수도 있다. The open induction drainage pipe is made of steel that can be welded, and the thickness is preferably made of a thin steel sheet to flexibly correspond to wall and / or ceiling deformation, and T = 2mm-5mm is appropriate. In addition, the length of the open induction drainage pipe is preferably 4-6m. Of course, in addition to steel, it may be made of plastic, large concrete, reinforced plastic, etc., and then attached to various binders (bonds).
또한 개방형 유도배수관을 이용한 방수 방법은 도 9 및 도 10과 같이 지중에 가설용으로 구축된 강관루프구조체(100) 내측에 강관의 조인트 이음부에 개방형 유도배수관(35)을 설치하여 강관루프구조체(100)내로 유입된 지하수를 외부로 유도 처리하는 것으로서, 도 9 및 도 10에는 강관루프구조체(100)의 천정부만 도시하였으나, 벽부에도 마찬가지로 개방형 유도배수관이 설치될 수 있다. 도 9 및 도 10에서의 강관루프구조체(100)내로 지하수가 침투함으로써 발생하게 되는 누수 경로는 토사(21)→상부 조인트부(23)→강관 외측면(25)→하부 조인트부(27)→유도배수관(35) 순으로 누수가 전파되는데, 이때 유도배수관(35)의 유로부((B)에 모인 지하수는 유로를 따라 흘러 배수되도록 함으로써 지중구조물로 누수되지 않도록 한다. 이때 물론 개방형 유도배수관(35)을 감싸도록 방수시트(30)를 부착하여 방수효과를 더욱 높일 수 있다. In addition, the waterproof method using the open induction drainage pipe as shown in Figure 9 and 10 by installing an open
본 발명에 적용되는 개방형 유도배수관(35)을 이용한 배수식 방수의 시공 순서는 도 6 내지 도 8과 같다. The construction sequence of the drain type waterproof using the open
도 6 내지 도 8에 도시한 바와 같이, 본 발명의 비개착 지중구조물의 축조를 위하여 지중에 압입 추진하여 형성된 강관루프구조체의 배수식 방수 방법은 강관루프구조체(100)의 내측(55)의 토사(21)를 굴착제거하는 단계, 및 상기 강관루프구조체(100)의 내측(55)의 벽부(도 3의 110) 및/또는 천정부(도 3의 120)의 강관이음부인 종방향 하부 조인트부(27)에 배수부(35)를 고정설치하는 단계를 포함한다. 이 경우, 바람직하기로는 강관루프구조체(100)의 내측(55)의 벽부 및/또는 천정부 종방향 하부 조인트부(27)의 바탕면을 정리하고 청소하는 단계를 더 포함한다. As shown in Figure 6 to 8, the drainage waterproofing method of the steel pipe loop structure formed by press-propelled in the ground for the construction of the non-attached underground structure of the present invention is the earth and sand of the inner 55 of the steel
여기서, 상기 배수부(35)는 강관과 강관의 종방향 하부 조인트부(27)를 따라서 부착되는 개방형 유도배수관(도 11 내지 도 16)으로 하부 조인트부에 탭용접으로 고정된다. Here, the
또한, 본 발명의 배수식 방수 방법은 상기 강관루프구조체(100)의 내측(55)의 불규칙한 벽부 및/또는 천정부와 개방형 유도배수관(35) 간의 틈을 누수가 발생치 않도록 퍼티로 메우는 단계를 더 포함한다. In addition, the drainage waterproof method of the present invention further fills the gap between the irregular wall portion and / or the ceiling and the open
한편, 방수효과를 더욱 높이기 위하여 상기 유도배수관(35)을 감싸도록 일정 크기의 방수시트(30)를 부착하는 단계를 더 포함한다. On the other hand, in order to further enhance the waterproof effect further comprises the step of attaching a predetermined size of the
또한, 상기 강관루프구조체(100)의 내측(55)의 천정부에만 강관이음부인 종방향 하부 조인트부(27)에 배수부(35)를 고정설치하는 경우, 상기 강관루프구조체(100)의 내측(55)의 벽부(도 6 내지 도 8에는 도시되지 않았으나, 종래 기술 도면의 도 3의 참조번호 110에 대응)의 강관이음부인 종방향 하부 조인트부(27)에는 방수시트(30)가 부착되거나 강판이 용접부착되는 단계를 더 포함한다.In addition, when the
본 발명의 강관루프구조체의 배수식 방수 방법에 대하여 보다 상세히 설명하면, 먼저 배수부(35)가 설치될 강관루프구조체(100) 내측 부위(55)의 각종 오물을 제거하고 바탕면 정리와 청소를 실시한다. The drainage type waterproofing method of the steel pipe loop structure of the present invention will be described in more detail. Conduct.
다음으로 강관루프구조체(100)의 벽부(도 3의 110) 및/또는 천정부(120)의 종방향 하부 조인트부(27)에 개방형 유도배수관(35)을 설치한다. 벽부(도 3의 110)는 개방형 유도배수관의 설치없이 기존의 방법대로 방수시트(30)만을 부착하거나 또는 강판만 용접부착하는 것도 가능하다. 개방형 유도배수관(35)은 강관루프구조체(100)의 하부 조인트부(27)에 밀착시킨 후 예를 들면 10-15cm 간격의 탭용접으로 하부 조인트부(27)에 고정시킨다. Next, an open
또한 높낮이 조종이 필요시에는 스페이서를 사용하는 것도 가능하다. 원할한 배수가 이루어지도록 종단 구배를 고려하여 설치하며 종방향의 연결은 개방형 유도배수관을 10mm정도를 중첩시켜서 용접으로 연결하며 전면 용접한다. It is also possible to use spacers when height adjustment is required. It is installed considering the end gradient so that smooth drainage can be achieved. In the longitudinal connection, open induction drainage pipe is overlapped by 10mm and welded to the front.
다음으로 불규칙한 벽부 및/또는 천정부와 개방형 유도배수관 간의 틈을 누수가 발생치 않도록 퍼티로 메운다. Next, fill the gap between the irregular wall and / or the ceiling and the open drain pipe to prevent leakage.
이어 유도배수관(35)을 감싸도록 일정 크기의 방수시트(30)를 부착한다. 방수시트(30)의 폭은 개방형 유도배수관(35)의 횡폭보다 좌우로 20cm 정도 여유폭을 고려한다. Then attach a
도면에서 미설명 부호 15 (체결볼트), 16(강관 이음 고리부재), 23(강관 이음 상부 조인트부)은 본 발명자의 선행 출원인 대한민국 특허공개 2009-0114863(2009. 11. 04), 2007-0088172(2007. 08. 29), 2007-0088114(2007. 08. 29), 2005-0098338(2005. 10. 12)에 자세히 나와 있으므로, 상세한 설명은 하지 않을 것이나, 강관과 강관을 연결하고, 내부에 몰탈을 충전하여 강관루프구조체의 강도를 높이는 역할을 한다. In the drawings, reference numerals 15 (fastening bolt), 16 (steel pipe joint ring member), 23 (steel pipe joint upper joint portion) is disclosed in Korean Patent Application Publication No. 2009-0114863 (2009. 11. 04), 2007-0088172 (2007. 08. 29), 2007-0088114 (2007. 08. 29), 2005-0098338 (October 12, 2005), detailed descriptions will not be given, but the steel pipe and the steel pipe are connected and Filling mortar serves to increase the strength of the steel pipe loop structure.
본 발명의 다른 양태에 의하면 본 발명에 의한 비개착 지중구조물의 축조를 위한 강관루프구조체의 배수식 방수 장치는 상기 강관루프구조체(100)의 내측(55)의 벽부(110) 및/또는 천정부(120)의 강관이음부인 종방향 하부 조인트부(27); 및 상기 강관이음부인 종방향 하부 조인트부(27)에 종방향으로 고정설치된 배수부(35)를 포함한다. According to another aspect of the present invention is a drainage type waterproofing device of the steel pipe loop structure for the construction of the non-attached underground structure according to the present invention is a
상기 배수부(35)는 강관과 강관의 종방향 하부 조인트부(27)를 따라서 부착되는 개방형 유도배수관(35)으로 하부 조인트부(27)에 탭용접으로 고정됨을 특징으로 한다. 더욱이, 방수효과를 높이기 위하여 상기 유도배수관(35)을 감싸도록 일정 크기의 방수시트(30)를 부착한다. The
본 발명의 또다른 양태에 의하면, 본 발명에 의한 강관루프구조체를 이용한 비개착 지중구조물의 배수식 축조 방법은 강관(10)을 압입 추진하여 강관루프구조체(100)를 형성하는 단계; 상기 강관루프구조체(100)의 내측(55)의 토사(21)를 굴착제거하는 단계; 및 상기 강관루프구조체(100)의 내측(55)의 벽부(110) 및/또는 천정부(120)의 강관이음부인 종방향 하부 조인트부(27)에 배수부(35)를 고정설치하는 단계; 및 상기 강관루프구조체(100) 내측에 거푸집(도 3의 210) 및 서포트(도 3의 220)를 설치한 상태에서 충전 형식으로 콘크리트 타설함으로써 지중구조물(200)을 형성하는 단계를 포함한다. According to another aspect of the present invention, the drainage construction method of the non-attached underground structure using the steel pipe loop structure according to the present invention comprises the steps of forming a steel
여기서, 강관루프구조체(100)의 내측(55)의 벽부(110) 및/또는 천정부(120) 종방향 하부 조인트부(27)의 바탕면을 정리하고 청소하는 단계를 더 포함한다. Here, the method may further include arranging and cleaning the base surface of the
또한, 상기 배수부(35)는 강관과 강관의 종방향 하부 조인트부(27)를 따라서 부착된 개방형 유도배수관으로 하부 조인트부(27)에 탭용접으로 고정된다. 또한, 상기 강관루프구조체(100)의 내측(55)의 불규칙한 벽부(110) 및/또는 천정부(120)와 개방형 유도배수관 간의 틈을 누수가 발생치 않도록 퍼티로 메우는 단계를 더 포함한다. In addition, the
또한, 상기 유도배수관(35)을 감싸도록 일정 크기의 방수시트(30)를 부착한다. 더욱이, 상기 강관루프구조체(100)의 내측(55)의 천정부에만 강관이음부인 종방향 하부 조인트부(27)에 배수부(35)를 고정설치하는 경우, 상기 강관루프구조체(100)의 내측의 벽부의 강관이음부인 종방향 하부 조인트부(27)에는 방수시트(30)가 부착되거나 강판이 용접부착되는 단계를 더 포함한다. In addition, a
지금까지 본 발명에 적용되는 배수부인 개방형 유도배수관의 양단은 지중구조물을 축조할 때, 도면에는 도시되지 않았지만 각각 다른 집수배수로에 연결되어 외부로 집수되고 배수되도록 설계하면 된다. 이에 따라서, 당업자에게 이러한 개방형 유도배수관으로부터 배수되는 물을 집수하여 배출하는 집수배수로를 설계하는 것은 명확히 이해될 수 있는 사항이므로 상세한 설명은 하지 않았다. Up to now, both ends of the open induction drainage pipe, which is a drainage part applied to the present invention, may be designed to be collected and drained to the outside by being connected to each other drainage drainage channel, although not shown in the drawing. Accordingly, it will be apparent to those skilled in the art that the design of the sump drainage for collecting and discharging the water drained from the open induction drainage pipe is a matter that can be clearly understood.
상술한 바와 같이, 본 발명의 비개착 지중구조물의 축조를 위한 강관루프구조체의 배수식 방수 방법 및 장치는 개방형 유도배수관을 횡방향 하부 조인트부에 접합함으로써 방수시트만으로 누수를 방지하기 어려운 문제를 해결할 수 있고, 이에 따른 시공이 간편한 점이 장점이다. As described above, the drainage type waterproofing method and apparatus of the steel pipe loop structure for the construction of the non-adhesive underground structure of the present invention solves the problem that it is difficult to prevent leakage by waterproof sheet only by joining the open induction drainage pipe to the transverse lower joint part. It is advantageous in that construction is easy accordingly.
10...강관 21...토사
23...상부 조인트부 27...하부 조인트부
30...방수시트 35...배수부
100...강관루프구조체 110...벽부
120...천정부 200...지중구조물10 ...
23 Upper joint 27 Lower joint
30.
100 Steel
120 ...
Claims (15)
비개착 지중구조물의 축조를 위하여 지중으로 압입 추진된 강관으로 형성된강관루프구조체를 지보재로 하여 내측의 토사를 굴착제거하는 단계;
상기 강관루프구조체의 내측의 벽부 및/또는 천정부 종방향 하부 조인트부의 바탕면을 정리하고 청소하는 단계; 및
상기 강관루프구조체의 내측의 벽부 및/또는 천정부의 강관과 강관의 강관이음부인 종방향 하부 조인트부를 따라 하부 조인트부에 탭용접으로 부착되는 개방형 유도배수관을 고정설치하는 단계를 포함하는 강관루프구조체의 배수식 방수 방법. In the drainage waterproof method of the steel pipe loop structure for the construction of the unattached underground structure,
Excavating and removing the earth soil inside the steel pipe loop structure formed of the steel pipe pushed and pushed into the ground for the construction of the unbonded underground structure;
Arranging and cleaning the base surface of the inner wall of the steel pipe loop structure and / or the ceiling longitudinal lower joint portion; And
Fixing an open induction drainage pipe attached to the lower joint by tab welding along a longitudinal lower joint, which is a steel pipe of the ceiling and / or a steel pipe of the ceiling and the ceiling of the steel pipe loop structure; Drainage waterproof method.
상기 강관루프구조체의 내측의 벽부 및/또는 천정부의 강관과 강관의 강관이음부인 종방향 하부 조인트부; 및
상기 강관이음부인 종방향 하부 조인트부를 따라 하부 조인트부에 탭용접으로 부착되어 종방향으로 고정설치된 개방형 유도배수관을 포함하는 강관루프구조체의 배수식 방수 장치. In the drainage waterproofing device of a steel pipe loop structure formed of steel pipes pushed and pushed into the ground for the construction of the unattached underground structure,
A longitudinal lower joint portion which is a wall portion inside the steel pipe loop structure and / or a steel pipe of the ceiling and a steel pipe joint of the steel pipe; And
A drainage type waterproofing device for a steel pipe loop structure including an open induction drainage pipe fixedly installed in a longitudinal direction by being tab-welded to a lower joint part along a longitudinal lower joint part which is the steel pipe fitting part.
The drainage type waterproofing device of a steel pipe loop structure according to claim 7, wherein a waterproof sheet having a predetermined size is attached to surround the induction drainage pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100085497A KR101017117B1 (en) | 2010-09-01 | 2010-09-01 | Method and device for waterproofing steel pipe loop structure by a water drainage process for constructing underground structure by non-excavation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100085497A KR101017117B1 (en) | 2010-09-01 | 2010-09-01 | Method and device for waterproofing steel pipe loop structure by a water drainage process for constructing underground structure by non-excavation |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100120706A Division KR101200016B1 (en) | 2010-11-30 | 2010-11-30 | Method of constructing underground structure using steel pipe loop structure employing a water drainage process and water drainage type underground structure constructed using the same |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101017117B1 true KR101017117B1 (en) | 2011-02-25 |
Family
ID=43777856
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100085497A KR101017117B1 (en) | 2010-09-01 | 2010-09-01 | Method and device for waterproofing steel pipe loop structure by a water drainage process for constructing underground structure by non-excavation |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101017117B1 (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101285987B1 (en) * | 2011-11-24 | 2013-07-15 | 주식회사 건화 | Improved Compound Roof Tunnel Method |
KR101362465B1 (en) | 2012-02-22 | 2014-02-12 | (주)아리터 | Trenchless construction method of underground structure |
CN109518737A (en) * | 2018-12-27 | 2019-03-26 | 中铁隧道集团三处有限公司 | A kind of construction method that pre-control ultra-deep underground continuous wall seam is permeable |
KR102126647B1 (en) * | 2020-02-03 | 2020-06-24 | (주)신승이앤씨 | Waterproof structure of non-excavation type tunnel improved shearing force and stiffness according to combination of h-beam support material and method of constructing thereof |
KR20220105406A (en) | 2021-01-20 | 2022-07-27 | 주식회사 두성씨엔에이 | Leakage prevention structure and leak prevention construction method of structure |
KR20220140128A (en) | 2021-04-09 | 2022-10-18 | 주식회사 두성씨엔에이 | Perforation device |
KR20230099918A (en) * | 2021-12-28 | 2023-07-05 | 주식회사 스틸코리아 | Steel Pipe Cofferdam and Steel Pipe Cofferdam Installing Method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001073357A (en) * | 1999-09-07 | 2001-03-21 | Tobishima Corp | Coffering structure and constructing method therefor |
JP2007056500A (en) * | 2005-08-23 | 2007-03-08 | Jfe Steel Kk | Joint structure of corrosion-protected steel sheet pile, and joint corrosion protecting method using the structure |
KR20090114863A (en) * | 2008-04-30 | 2009-11-04 | 원하종합건설 주식회사 | Parallelly connected iron tube and construction method for underground structure using the same |
-
2010
- 2010-09-01 KR KR1020100085497A patent/KR101017117B1/en not_active IP Right Cessation
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001073357A (en) * | 1999-09-07 | 2001-03-21 | Tobishima Corp | Coffering structure and constructing method therefor |
JP2007056500A (en) * | 2005-08-23 | 2007-03-08 | Jfe Steel Kk | Joint structure of corrosion-protected steel sheet pile, and joint corrosion protecting method using the structure |
KR20090114863A (en) * | 2008-04-30 | 2009-11-04 | 원하종합건설 주식회사 | Parallelly connected iron tube and construction method for underground structure using the same |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101285987B1 (en) * | 2011-11-24 | 2013-07-15 | 주식회사 건화 | Improved Compound Roof Tunnel Method |
KR101362465B1 (en) | 2012-02-22 | 2014-02-12 | (주)아리터 | Trenchless construction method of underground structure |
CN109518737A (en) * | 2018-12-27 | 2019-03-26 | 中铁隧道集团三处有限公司 | A kind of construction method that pre-control ultra-deep underground continuous wall seam is permeable |
KR102126647B1 (en) * | 2020-02-03 | 2020-06-24 | (주)신승이앤씨 | Waterproof structure of non-excavation type tunnel improved shearing force and stiffness according to combination of h-beam support material and method of constructing thereof |
KR20220105406A (en) | 2021-01-20 | 2022-07-27 | 주식회사 두성씨엔에이 | Leakage prevention structure and leak prevention construction method of structure |
KR20220140128A (en) | 2021-04-09 | 2022-10-18 | 주식회사 두성씨엔에이 | Perforation device |
KR20230099918A (en) * | 2021-12-28 | 2023-07-05 | 주식회사 스틸코리아 | Steel Pipe Cofferdam and Steel Pipe Cofferdam Installing Method |
KR102653012B1 (en) * | 2021-12-28 | 2024-04-01 | 주식회사 스틸코리아 | Steel Pipe Cofferdam and Steel Pipe Cofferdam Installing Method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101017117B1 (en) | Method and device for waterproofing steel pipe loop structure by a water drainage process for constructing underground structure by non-excavation | |
CN202788022U (en) | Wall crack combined type repair structure | |
CN110878700B (en) | Tunnel waterproof structure and construction method thereof | |
CN106120801B (en) | Pipeline crosses the construction method at foundation ditch in water-rich sand layer | |
KR101200016B1 (en) | Method of constructing underground structure using steel pipe loop structure employing a water drainage process and water drainage type underground structure constructed using the same | |
CN211113772U (en) | Post-cast strip structure for top plate of underground chamber | |
CN104482298B (en) | HDPE (high-density polyethylene) steel-plastic composite spiral winding drainage pipe installation construction method | |
CN109944314B (en) | Rapid construction method for rainfall-free large-diameter wound pipe composite joint | |
CN109488371B (en) | Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method | |
CN107327308A (en) | A kind of Railway Tunnel waterproof method | |
CN108661078B (en) | Comprehensive tunnel design construction method | |
KR102126647B1 (en) | Waterproof structure of non-excavation type tunnel improved shearing force and stiffness according to combination of h-beam support material and method of constructing thereof | |
KR100656194B1 (en) | Open cut and cover method applying tunnel cut method | |
CN112081607B (en) | Tunnel primary support and waterproof and drainage combined system and construction method | |
CN207004570U (en) | A kind of tunnel longitudinal drainage blind pipe fixed structure | |
CN112900294A (en) | Lining structure for box culvert repair and construction method thereof | |
JP6183869B2 (en) | Manhole renewal method and manhole new construction method | |
CN115898469A (en) | Tunnel secondary lining construction method | |
KR20200117589A (en) | Waterproofing reinforcement structure of underground structure expansion joint and constructing method thereof | |
KR101817712B1 (en) | A Culvert and method for constructing the culvert | |
CN205954632U (en) | Pipeline crosses supporting construction of foundation ditch department in rich water sand layer | |
KR20100042441A (en) | Inducing waterproof structure of underground diaphragm wall | |
CN205804419U (en) | The tenon formula joint waterproofing structure of concrete waist rail embedded structure side wall | |
CN115012451A (en) | Underground structure induced joint | |
CN113187487A (en) | Double-deck full section of subway freezes secretly digs station structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E902 | Notification of reason for refusal | ||
A107 | Divisional application of patent | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20140206 Year of fee payment: 6 |
|