Specific embodiment
Come below with reference to accompanying drawings each embodiment of the present invention is described in detail.
Fig. 1 shows that the flow chart meeting spiral winding drainpipe construction method of installation moulded by hdpe steel of the present invention, as schemed institute
Show, methods described comprises the steps:
First, in step s100, preparation of construction, specifically, before hdpe steel plastic compount spiral winding drainpipe is installed, right
The tolerance of its outward appearance and joint cooperation is checked, eliminates the dirt inside and outside drainpipe and pipe fitting and debris, job site and material
When the material storing place temperature difference is larger, before installing, drainpipe and pipe fitting should be placed certain time at the scene so as to temperature is close applies
The environment temperature of work.
After preparation of construction is good, in step s110, fluting of cutting the earth, control substrate elevation, the above 0.2-0.3 of substrate elevation
The surface dust of rice will be cleared up to designed elevation.If backbreaking or disturbance, the interchangeable sand filling out particle diameter 10-15mm prototype gradation occur in local
Stone or in, coarse sand tamping;When channel bottom is if any objects such as block stone, rubble, bricks, 0.2 meter of below designed elevation should be rooted out,
And mix prototype gradation sand material, surface layer spreads sand compacting;Rainy season construction, by the way of " dig and fill out ", it is to avoid groove
Open-assembly time is long;Once occur bubble groove, water should be excluded, substrate is removed by the topsoil of maceration, change back-up sand building stones or
In, coarse sand, carry out based process, then down tube install.
After the groove of placement drainpipe digs, in step s120, down tube is installed, and down tube can use manually or crane enters
OK, pipe shaft to be kept and groove are placed in parallel in groove, are adjusted according to the distance between bilge well or catch-basin in groove
The length of entire row water pipe simultaneously adjusts smooth and perpendicular to the ground to its end face, can cut with a chainsaw and complete said process.
After drainpipe is placed into groove, in step s130, the connection of drainpipe, multiple using Electric thermal smelting belt and shrink belt
Close connected mode to be attached adjacent row water pipe, i.e. using pipe fitting by adjacent two drainpipe hot-melt adhesive paste, at two formed
Around Electric thermal smelting belt between connector position, it is heated to melt temperature, between two joints, be then wound around shrink belt, therefrom
Between so that contraction band is combined closely with drainpipe and pipe fitting to surrounding heating, wherein said pipe fitting is threeway, directly first-class, specifically
Connection procedure will describe in detail in the description of fig. 2.
After drainpipe connects, in step s140, experiment of pouring water is carried out to the drainpipe connecting, prevent leak from oozing
Water, specifically, the pre- closure of leaving a blank of drainpipe and catch-basin or bilge well junction is separated by well spacing, sampling is chosen, band
Well is tested, and water is poured into the drainpipe that sampling is chosen, no ponding in pipeline end backfill and groove;Pipe ends closure plate bearing capacity
Making a concerted effort of water pressure should be not more than through adjusting, in addition to reserved turnover drainpipe, should block firm, must not seep water.
After Pipe installing and laying finish, in step s150, backfill, the debris in groove are cleaned out, and should be first
From the structures such as pipeline, inspection shaft both sides are symmetrically inserted, coarse sand, stone fragment or original soil, described groove is filled up.Pipeline two
Backfill in side and the above 0.5m in pipe top, must not be containing the big rubble of particle diameter, fragment of brick, frozen soil block and other miscellaneous hard objects.Pipe
After road lays, build high grade pavement immediately or other require road surface.Backfill soil compactness will meet following requirements: pipeline is effective
In backfilling in the range of strut angle, coarse sand, every 100m measures a compactness, all compactnesss 95;Every two wells in pipeline both sides it
Between backfill in, coarse sand, stone fragment, maximum particle diameter be less than the grit of 40mm or satisfactory original soil, compactness 95;Pipe top with
Upper 500mm, in backfill, coarse sand, stone fragment, maximum particle diameter is less than the grit of 40mm or satisfactory original soil, compactness 90;
Pipe top 500-1000mm, backfills original soil, compactness 90.
The flow chart that Fig. 2 is Electric thermal smelting belt of the present invention and shrink belt composite joint hdpe steel-plastics composite pipe, as illustrated,
The method of Electric thermal smelting belt and shrink belt composite joint hdpe steel-plastics composite pipe includes:
First in step s 200, drainpipe is placed on sleeper or bracing frame, by the center line of drainpipe and groove
Center line overlap, the gradient of drainpipe is 0.8 ‰, and the pipeline opening alignment of two adjacent drainpipes stretches out 80 respectively
The length of 100mm.
After drainpipe places according to above-mentioned requirements, in step s210, will have identical melting with drainpipe and refer to
The pipe fitting of number inserts the mouth of pipe of two drainpipes, using electric melting unit, drainpipe two ends is heated to melt temperature, is entered with the power of 4mpa
Row drainpipe is docked to pipe fitting two ends.
Two drainpipes are docked to two joints of formation behind pipe fitting two ends, in step s220, check joint after hot melt
The quality at place, docking unfitness of butt joint is not more than the 10% of draining thickness of pipe wall, and no more than 3mm, should be formed convex after melting connection
Edge, and flange shape is uniform in size consistent, pore-free, bubbling and crack, joint has and smooths symmetrical turning up along tube coupling circumference
Side, the depth of flanging lowest part is not less than tube coupling outer surface, evens in-flanges out.
Then, in step s230, Electric thermal smelting belt on ring between two joints, it is heated to melt temperature, make electric heating
Molten band is closely connected with joint.
After electric melting connection completes, in step s240, by shrink belt on ring between two joints, from centre
Toward surrounding by shrink belt heating one circle, gently smoothed with hand, sturdy.
In order to ensure that shrink belt is closely pasted at drain interface it is preferable that heating toward surrounding according to from middle again
One time, still press and comfort an annulus, so that contraction band and drainpipe is combined closely.
Furthermore it is preferred that caliber >=φ 500mm, in step s210, before pipe fitting insertion drainpipe, adjacent two
One layer of shrink belt is wound around on the port inner wall of individual drainpipe, according in step s240, toward surrounding, the heat of inner side is received from middle
Contracting band heating one circle, the thermal contraction of inwall takes up liner effect, and after step s240, forms inside and outside two layers thermal contraction
Band, increased the bearing capacity of joint, extends service life.
The present invention solves the crisp easy generation of independent Electric thermal smelting belt interface by winding heat-shrinkable tube outside Electric thermal smelting belt and splits
The problem of line, by heating shrink belt from central authorities toward surrounding, solves the problems, such as that shrink belt produces bubble, using electric heating melting
Band and shrink belt duplicate protection, make the joint life-span be up to 50 years and improve resistance to water.
Although content disclosed above shows the exemplary embodiment of the present invention, it should be noted that without departing substantially from power
On the premise of profit requires the scope of the present invention limiting, may be many modifications and change.Real according to invention described herein
Function, step and/or the action of applying the claim to a method of example are not required to execute with any particular order.Although additionally, the present invention
Element with the description of individual form or can require, it is also contemplated that multiple, unless explicitly limited for odd number.