KR100738410B1 - Support system for Flying form and Concreate slab construction method using the same - Google Patents

Support system for Flying form and Concreate slab construction method using the same Download PDF

Info

Publication number
KR100738410B1
KR100738410B1 KR1020050108551A KR20050108551A KR100738410B1 KR 100738410 B1 KR100738410 B1 KR 100738410B1 KR 1020050108551 A KR1020050108551 A KR 1020050108551A KR 20050108551 A KR20050108551 A KR 20050108551A KR 100738410 B1 KR100738410 B1 KR 100738410B1
Authority
KR
South Korea
Prior art keywords
flying
self
steel pipe
supporting
slab
Prior art date
Application number
KR1020050108551A
Other languages
Korean (ko)
Other versions
KR20070051104A (en
Inventor
박정진
박정호
Original Assignee
깨뱉시스템주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 깨뱉시스템주식회사 filed Critical 깨뱉시스템주식회사
Priority to KR1020050108551A priority Critical patent/KR100738410B1/en
Publication of KR20070051104A publication Critical patent/KR20070051104A/en
Application granted granted Critical
Publication of KR100738410B1 publication Critical patent/KR100738410B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

본 발명은 콘크리트 건물의 시공시 특히 슬래브 시공에 사용되는 플라잉 폼 용 자립형 동바리 구조에 관한 것으로서, 지주를 구성하는 것으로 길이 조절이 가능한 강관기둥;과 상기 강관기둥 상단에 연결되는 받침대; 및 상기 강관기둥의 하단에 연결되는 자립형의 세움 지지대;의 구성요소를 포함하는 것을 특징으로 하는 플라잉 폼 용 자립형 동바리 구조를 제공한다.The present invention relates to a self-supporting structure for flying foam used for the construction of concrete buildings, in particular for slab construction, the length of the steel pipe pillars can be adjusted to constitute a strut; and a pedestal connected to the top of the steel pipe pillar; And a freestanding upright support structure connected to the lower end of the steel pipe pillar.

본 발명의 플라잉 폼 용 자립형 동바리 구조를 사용함으로써, 기 시공되어 초기 양생중인 하부층의 콘크리트 슬래브에서 플라잉 폼을 조기에 탈형하여, 상부층의 슬래브 시공에 이용하여 상부층 슬래브의 콘크리트 타설작업을 조기에 착수할 수 있으므로 종래 골조공사에 소요되는 공기의 50%를 단축할 수 있게 된다. 또한 본 발명은 플라잉 폼을 탈형하여도 기설치된 자립형 동바리들을 설치상태대로 잔존시킴으로써 양생중인 콘크리트 구조물의 내구성을 확보할 수 있게 하므로, 공사품질을 향상시키고 공사비를 절약할 수 있는 경제성이 뛰어난 콘크리트 슬래브 시공 방법을 제공한다.By using the self-supporting copper cladding structure for the flying foam of the present invention, demolding the flying foam early in the concrete slab of the lower layer, which is being constructed and initially cured, can be used for the slab construction of the upper layer to start concrete pouring work of the upper layer slab early. As a result, it is possible to shorten 50% of the air required for the conventional frame construction. In addition, the present invention is to ensure the durability of the concrete structure being cured by remaining the self-supporting clubs installed even in demolding the flying foam in the installation state, thereby improving the construction quality and construction cost-effective concrete slab construction Provide a method.

플라잉 폼의 구조, 동바리 구조 Structure of flying form, group structure

Description

플라잉 폼 용 자립형 동바리 구조 및 이를 이용한 콘크리트 슬래브 시공방법{Support system for Flying form and Concreate slab construction method using the same}Self-supporting structure for flying foam and concrete slab construction method using it {Support system for Flying form and Concreate slab construction method using the same}

도1은 플라잉 폼 용 자립형 동바리 구조의 실시예를 나타낸 사시도이다.1 is a perspective view showing an embodiment of a self-supporting clubbing structure for flying foam.

도 2a는 본 발명의 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 설치한 실시예를 나타낸 사시도이다.Figure 2a is a perspective view showing an embodiment in which a flying foam is installed using the self-supporting copper clad structure for flying foam of the present invention.

도 2b는 본 발명의 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 설치한 실시예로서 받침대인 평면 트러스를 회전시켜 거푸집을 해체하는 모습을 나타낸 사시도이다.Figure 2b is a perspective view showing a state of disassembling the formwork by rotating a flat truss as a pedestal as an embodiment in which the flying foam is installed using the self-supporting copper clad structure for flying foam of the present invention.

도 3a는 형강 받침대를 이용한 플라잉 폼 용 자립형 동바리 구조의 실시예를 나타낸 사시도이다.Figure 3a is a perspective view showing an embodiment of a self-supporting copper cladding structure for flying foam using a steel beam support.

도 3b는 형강 받침대를 이용한 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 설치한 실시예로서 평면 형강 받침대를 회전시켜 거푸집을 해체하는 모습을 나타낸 사시도이다.Figure 3b is a perspective view showing a state of disassembling the formwork by rotating the flat-shaped steel pedestal as an embodiment in which the flying foam is installed by using a self-supporting copper clad structure for flying foam using a steel pedestal.

도 4a, 도 4b는 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 설치한 현장의 시공 과정을 도시한 단면도이다.4A and 4B are sectional views showing a construction process of a site in which a flying foam is installed using a self-supporting copper clad structure for flying foam.

도 5는 플라잉 폼 용 자립형 동바리 구조를 사용하여 현장의 콘크리트 슬래브 시공 시에 하강 도르래를 사용하는 예를 나타낸 사시도이다.Figure 5 is a perspective view showing an example of using a pulley for the construction of a concrete slab construction in the field using a self-supporting structure for flying foam.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

10 : 받침대 11 : 주연결부10: pedestal 11: main connection

12 : 보조연결부 13 : 받침대 결속부12: auxiliary connection 13: pedestal binding unit

20 : 강관기둥 21 : 상부 조절부 20: steel pipe column 21: upper control unit

22 : 하부 조절부 30 : 지지대 22: lower adjustment portion 30: support

31 : 하강 도르래 32 : 지지대 결속부31: lowering pulley 32: support binding unit

41 : 고정 장선 42 : 탈, 부착 장선41: fixed joists 42: detachment, attachment joists

43 : 거푸집 판넬 44 : 콘크리트 슬래브43: formwork panel 44: concrete slab

50 : 가새 51 : 이동바퀴50: brace 51: moving wheel

60 : 형강 받침대 62 : 형강 장선60: section steel pedestal 62: section steel joist

63 : 와이어로프 64 : 하강 윈치63: wire rope 64: lowering winch

본 발명은 콘크리트 건물의 시공시 특히 슬래브 콘크리트 타설시에 거푸집을 사용할 때, 양생중인 하층의 콘크리트 슬래브에 구조적인 무리를 주지 않으며 차 상부층의 거푸집 설치 작업을 조기에 착수할 수 있게 하여 골조공사에 소요되는 공기를 단축할 수 있게 하는 플라잉 폼(Flying form, 일명 테이블 폼)의 동바리 구조 에 관한 것이다.The present invention, when using the formwork in the construction of concrete buildings, in particular when slab concrete laying, it does not give structural structural burden to the lower concrete slab during curing, it is possible to start the formwork installation of the upper layer of the car early to frame construction work It relates to a group structure of flying foams (also known as table forms) that can shorten the air that is released.

근래에는 사무소, 상가 건물이나 아파트 등의 주거용 공동건물의 축조시 선 시공 후 분양 제도에 의하므로 건설사의 비용부담이 증가되고 있다. 그런데 이러한 대형 건물의 축조시에는 시공속도가 경제성과 직결되는 문제이므로 시공속도 향상이 강력히 요구되고, 또한 철근콘크리트 구조물의 공사비용에는 가설공사 비용이 차지하는 비율이 상당한데 이러한 가설공사 비용을 줄이며 노동생산성 향상의 경제적인 시공을 하기 위해서는 가설 부자재의 효율적인 재활용이 요구된다. Recently, the cost burden of construction companies is increasing due to the pre-construction and pre-construction system for the construction of residential communal buildings such as offices, shopping malls, and apartments. However, when constructing such a large building, the construction speed is directly related to economic efficiency. Therefore, the construction speed is strongly required. Also, the construction cost of the reinforced concrete structure accounts for a large proportion of the construction cost. Economical construction of improvement requires efficient recycling of temporary subsidiary materials.

이러한 시공속도 향상 및 가설공사 비용 절감을 위해 반복적인 평면구조의 대형 콘크리트 건물의 슬래브 시공시 플라잉 폼을 사용하는 것이 일반적이다. 플라잉 폼이란 바닥에 콘크리트를 타설하기 위해 거푸집 널과 장선, 멍에의 보강재가 일체로 된 거푸집 판, 거푸집 판을 지지하는 지지구조인 동바리 등을 일체로 제작한 거푸집을 일컫는다. 이러한 플라잉 폼 사용시 매 층마다 거푸집의 조립과 해체가 불요한 조립된 플라잉 폼을 사용하므로 공기가 단축되고 인력이 절감되며, 시공 시 거푸집의 처짐이 적고 합판을 제외한 주요 부재자의 재사용이 가능하다는 장점이 있다. In order to improve the construction speed and to reduce the construction cost, it is common to use a flying foam for slab construction of a large concrete building having a repetitive planar structure. Flying foam refers to the formwork that is made of formwork board, joist, yoke reinforcement to form concrete, and the copper bar, which is supporting structure. When using such a flying foam, the use of assembled flying foam that does not require assembly and disassembly of the formwork on each floor reduces the air and manpower, and reduces the deflection of formwork during construction and enables the reuse of key members except plywood. have.

그러나 플라잉 폼을 비롯한 거푸집은 콘크리트가 경화하여 충분한 강도가 발현될 때까지 형태 유지 및 지지의 역할을 하게 되므로 상당 기간 존치되어야 한다. 존치기간은 시멘트의 종류, 천후, 기온, 하중 등에 따라 차이가 있으나, 슬래브 거푸집의 경우 타설된 콘크리트가 설계 기준 재령 28일 강도의 2/3 이상의 강도를 발휘하는 초기 경화기간이 경과할 때까지 존치하게 되며, 상온 10℃ 이상에서는 대략 7~8일 이상이 소요된다. 이러한 존치기간은 타설된 콘크리트가 어느 정도 초기 양생 되어 거푸집을 해체하는 것이 가능할 정도임을 의미하는 것이고, 존치 기간이 경과하였다 하여 거푸집 제거 후 그 상부에 거푸집을 재설치하여 콘크리트를 타설하기에 충분한 강도를 가짐을 의미하는 것은 아니다. 따라서 거푸집 존치 초기 양생 기간이 경과하여 거푸집을 해체하더라도 상층의 거푸집 공사를 하기 위해서는 슬래브 구조체가 충분한 강도를 가지도록 추가의 잔존 양생 기간을 거쳐야하므로 공기 지연이 발생하게 되고, 또한 상부층 거푸집 공사를 조기에 착수하기 위해서는 슬래브 거푸집을 해체한 후에, 슬래브 구조체의 하부에 별도의 지지 보강 수단을 설치해야 하므로 추가 작업 및 비용이 소요된다는 문제점이 있다. However, the formwork, including the flying foam, has to be retained for a considerable period of time as it will act as a shape retainer and support until the concrete hardens to develop sufficient strength. The period of durability varies depending on the type of cement, weather, temperature, and load.However, in the case of slab formwork, it is maintained until the initial curing period after the cast concrete exhibits at least 2/3 of the 28-day strength of design standards. It takes about 7 to 8 days or more at room temperature 10 ℃ or more. This period of retention means that the cast concrete is cured to a certain extent so that it is possible to dismantle the form. After the period of elimination has elapsed, it has sufficient strength to re-install the formwork on top of it. It does not mean. Therefore, even if the formwork is dismantled after the initial curing period has elapsed, an air delay occurs because the slab structure has to go through an additional remaining curing period so that the slab structure has sufficient strength. In order to undertake, after dismantling the slab formwork, it is necessary to install a separate support reinforcing means in the lower part of the slab structure, there is a problem that additional work and costs are required.

본 발명은 상기의 문제점을 해결하고, 콘크리트 구조물 축조 공사시 별도의 지지 보강 수단의 설치 없이 하층의 초기 양생과 동시에 상층의 시공을 가능하게 하여 공기를 획기적으로 단축할 수 있는 플라잉 폼 용 자립형 동바리 구조를 제공하는데 목적이 있다. 또한 플라잉 폼의 일부분의 조기 탈형이 가능하므로 거푸집의 설치 후 해체 및 재조립 사용에 이르는 시간이 단축되고, 잔존하는 동바리 구조 부분은 기설치 상태대로 존치되어 양생중인 콘크리트의 품질 향상에 크게 기여하므로 가설공사 비용을 절감하여 시공경제성을 높이는 데 기여하도록 한다. The present invention solves the above problems, and enables the construction of the upper floor at the same time as the initial curing of the lower floor without the installation of a separate support reinforcing means when constructing a concrete structure, the self-supporting dynamic structure for flying foam can significantly shorten the air The purpose is to provide. In addition, it is possible to premature demoulding of a part of the flying foam, which shortens the time required for dismantling and reassembling after installation of the formwork, and the remaining part of the copper structure remains as it is installed, contributing to the improvement of the quality of the cured concrete. To reduce construction costs and contribute to improving construction economics.

본 발명은 콘크리트 건물의 시공시 특히 슬래브 시공에 사용되는 플라잉 폼 용 자립형 동바리 구조에 관한 것이다. 플라잉 폼은 바닥에 콘크리트를 타설하기 위해 거푸집 널과 장선, 멍에의 보강재가 일체로 된 거푸집 판, 거푸집 판을 지지하는 지지구조인 동바리 등을 일체로 제작한 거푸집을 일컫는다. 본 발명은 이러한 플라잉 폼에서 플라잉 폼 용 자립형 동바리 구조를 제공하데, 지주가 되는 것으로 길이 조절이 자유로운 강관기둥;과 상기 강관기둥의 상단에서 강관기둥과 연결되어 차후 거푸집 판에 연결되어 거푸집 판을 지지하는 역할을 하는 받침대; 및 강관기둥 하부에서 바닥에 강관기둥을 수직으로 고정시키는 지지대;의 구성요소를 포함하는 것을 특징으로 한다. 이때 상기 강관기둥은 길이 조절이 가능하도록 하여 상기 받침대의 높낮이를 조절할 수 있고, 상기 강관기둥과 상기 받침대 및 지지대의 연결부에서는 상기 받침대 및 지지대의 회전이 가능하게 함으로써 거푸집 해체를 용이하게 할 수 있다. 또 기 강관기둥과 상기 받침대 및 지지대의 연결부와 회전구조는 다양한 배열이 가능하므로 종래의 철근트러스를 사용하는 합판 거푸집 공법과 접목시공하면 소요공기 및 노동력을 획기적으로 절감한다. 이러한 기능을 동시에 수행하도록 바람직한 실시예로서 상기 강관기둥의 상부 및 하부에 스크류관을 사용할 수 있다. 강관기둥 하부의 지지대는 여러 가지 형태가 가능한데, 판재를 연결시켜 사용하거나 평면 트러스 형태로서 지지대를 구성하거나 강관기둥을 중심으로 방사형의 보조지지수단을 둘 수 있다.The present invention relates to a self-supporting structure for flying foam used in the construction of concrete buildings, in particular for slab construction. Flying foam refers to the formwork that is integrally made of formboard, joist, yoke reinforcement to form concrete on the floor, and copper bar, which is a supporting structure for supporting formwork. The present invention provides a self-supporting copper clad structure for the flying foam in such a flying foam, the length of the steel pipe pillar is freely adjustable to be a support; and is connected to the steel pipe pillar at the top of the steel pipe pillar and then connected to the formwork plate to support the formwork plate Pedestals that play a role; And a support for vertically fixing the steel pipe pillars to the bottom from the steel pipe pillars. In this case, the steel pipe column can adjust the height of the pedestal by allowing the length adjustment, and in the connection portion of the steel pipe pillar and the pedestal and the support can facilitate the disassembly of the formwork by enabling the pedestal and the support. In addition, since the steel pipe column and the connection portion and the rotation structure of the pedestal and support can be arranged in various ways, when combined with a plywood formwork method using a conventional reinforcing truss, the required air and labor force is greatly reduced. As a preferred embodiment to perform this function at the same time it is possible to use a screw pipe on the top and bottom of the steel pipe pillar. The support of the lower part of the steel pipe column may have various shapes, and may be used by connecting plates, forming a support in the form of a flat truss, or providing a radial auxiliary supporting means about the steel pipe pillar.

또한 본 발명은 상기 플라잉 폼 용 자립형 동바리 구조에서, 상기 강관기둥의 상단에 연결되어 거푸집 판을 지지하는 역할을 하는 받침대로서 H형강으로 구성 된 것으로, 상기 강관기둥의 상단에 H형강의 플랜지 바닥면이 오도록 하여 상기 강관기둥과 연결되는 형강 받침대를 사용하는 것을 부가적인 특징으로 하는 플라잉 폼 용 자립형 동바리 구조를 제공한다. 받침대로서 H형강을 사용하는 경우 장선으로 형강을 이용하여 장선과 받침대 간의 결합구조가 간단해 질 수 있는 장점이 있다. 또, 받침대로서는 다양한 형태의 평면 트러스를 사용할 수 있는데, 이는 소량의 부재를 사용하여 높은 강성을 얻게 할 수 있다는 경제상의 이점이 있다.In another aspect, the present invention is a stand-alone copper clad structure for the flying foam, which is connected to the upper end of the steel pipe pillar is a pedestal that serves to support the form plate, consisting of H-shaped steel, the flange bottom surface of the H-shaped steel on the top of the steel pipe pillar It is to provide a self-supporting structure for the flying foam, characterized in that the additional use of the steel pedestal connected to the steel pipe pillar. When using H-beam as a pedestal, there is an advantage that the coupling structure between the joist and the pedestal can be simplified by using the steel as the joist. In addition, various types of flat trusses can be used as the pedestal, which has an economic advantage that high rigidity can be obtained by using a small amount of members.

또, 본 발명은 슬래브 콘크리트 타설 구간의 하층 바닥에 일정한 간격으로 상기 플라잉 폼 용 자립형 동바리 구조를 설치하는 제1단계;와 상기 설치된 플라잉 폼 용 자립형 동바리 구조 사이에 가새를 설치하는 제2단계; 상기 설치된 플라잉 폼 용 자립형 동바리 구조의 받침대에 장선을 연결하는 제3단계; 상기 설치된 장선 위에 조립된 거푸집 판을 인양하여 설치하는 제4단계; 상기 설치된 거푸집 판 위에 슬래브 콘크리트를 시공하는 제5단계; 상기 시공된 슬래브 콘크리트의 지지에 필요한 최소한의 플라잉 폼 용 자립형 동바리 구조를 잔존시키고 나머지는 해체하는 제6단계; 상기 해체된 플라잉 폼 용 자립형 동바리 구조를 다른 콘크리트 슬래브 시공 구간으로 이동시켜 제1단계 내지 제6단계를 반복하는 제7단계;의 과정을 포함하는 것을 특징으로 하는 플라잉 폼 용 자립형 동바리 구조를 이용한 콘크리트 슬래브 시공 방법을 제공한다. 그리고 제6단계에서 하강용 도르래를 부가적으로 사용하는 것을 부가적인 특징으로 하는 플라잉 폼 용 자립형 동바리 구조를 이용한 콘크리트 슬래브 시공 방법을 제공한다.In another aspect, the present invention is the first step of installing the self-supporting group for the flying foam structure at a predetermined interval on the bottom floor of the slab concrete pouring section; and a second step of installing a brace between the installed self-supporting structure for flying foam; A third step of connecting a joist to the pedestal of the installed self-supporting copper frame structure for the flying foam; A fourth step of lifting and installing the formwork plate assembled on the installed joist; A fifth step of constructing slab concrete on the installed formwork plate; A sixth step of remaining a self-supporting copper cladding structure for flying foam required for supporting the constructed slab concrete and dismantling the rest; The seventh step of repeating the first step to the sixth step by moving the dismantled floating foam structure for the flying foam to another concrete slab construction section; concrete using the self-supporting copper structure for flying foam Provide a method of slab construction. In addition, the present invention provides a concrete slab construction method using a self-supporting copper cladding structure for flying foam, in which the additional use of the lowering pulley is performed in the sixth step.

이러한 본 발명의 플라잉 폼 용 자립형 동바리 구조를 이용함으로써, 양생중 인 하층의 콘크리트 슬래브에 구조적인 무리를 주지 않으며, 상층 슬래브의 거푸집 설치 작업을 조기에 착수할 수 있어, 골조공사에 소요되는 공기를 단축할 수 있게 된다. 또한 양생되는 하층의 콘크리트 슬래브가 충분한 설계강도를 발현할 때까지의 양생 기간 동안 상기 하층의 콘크리트 슬래브 하부에 슬래브 지지부재, 존치 형틀 및 지주를 설치상태대로 존치시킴으로써 별도의 지지 보강 수단의 설치 없이도 슬래브 축조 시 사용되었던 거푸집의 부분 부재들을 이용하여 구조물의 내구성을 확보할 수 있다. 또 본 발명의 플라잉 폼 용 자립형 동바리 구조는 높이 조절 및 고정부의 회전을 가능케 하므로 거푸집 판넬의 탈형과 반출이 용이하게 이루어져 우수한 품질의 건축물을 시공할 수 있게 한다. 아울러 양생중인 하층의 설계 강도의 발현이 완성되기 전에 조기에 탈형 가능한 일부 플라잉 폼을 재활용하여 상층의 거푸집으로 설치함으로써 소정의 플라잉 폼만으로도 구조물 축조가 가능하여 공사비를 절약할 수 있어 경제성이 뛰어난 콘크리트 슬래브 시공 방법을 제공할 수 있다.By using such a self-supporting copper clad structure for flying foam of the present invention, it is possible to undertake structural installation of the upper slab without any structural burden on the lower concrete slab under curing, and to provide air for the construction work. It can be shortened. In addition, the slab support member, the retaining mold and the posts are placed under the concrete slab of the lower layer in the state of curing until the concrete slab of the lower layer to be cured exhibits sufficient design strength. Partial parts of the formwork used during construction can be used to ensure the durability of the structure. In addition, the self-supporting structure for flying foam of the present invention enables the height adjustment and rotation of the fixing portion, so that the mold panel can be easily demolded and taken out, allowing construction of excellent quality buildings. In addition, before the development of the design strength of the lower layer in curing is completed, some of the pre-demolable flying foam can be recycled and installed as formwork on the upper layer. Construction method can be provided.

이하에서는 첨부된 도면을 참고하여 본 발명을 더욱 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings will be described in more detail the present invention.

도1은 플라잉 폼 용 자립형 동바리 구조의 실시예로서 받침대 및 지지대로 평면 트러스를 사용한 예를 나타낸 사시도이다.1 is a perspective view showing an example of using a flat truss as a pedestal and a support as an embodiment of a self-supporting copper clad structure for a flying foam.

지주가 되는 강관기둥(20)의 상단에는 받침대(10)가 연결된다. 이때 상기 받침대(10)는 차후 거푸집 판을 지지하여 강관기둥(20)으로 그 하중을 이동시키는 역 할을 하게 되는 것이다. 상기 강관기둥(20)의 하단에는 상기 강관기둥(20)과 연결되어 바닥에 상기 강관기둥(20)을 수직으로 고정시키는 역할을 하는 자립형의 하부 지지대(30)가 하부 조절부(22)의 연결나사로 높이를 조절 결속하게 된다. 도1에 도시된 상부와 하부의 평면 트러스는 사용될 수 있는 받침대(10) 및 자립형의 지지대(30) 형태의 실시예를 보여준다. 상기 받침대(10)는 상부에 돌출부로서 차후 거푸집 판을 지지하는 장선을 연결할 수 있도록 하는 연결부(11,12)와 조절부(21)의 높이를 제어하는 받침대 결속부(13)를 포함한다. 상기 강관기둥(20)에는 상기 받침대(10) 및 상기 지지대(30)와의 연결부로서 상기 받침대(10) 및 상기 지지대(30)가 각각 회전 가능하도록 하는 한편 상기 강관기둥(20)의 길이 조절이 자유롭도록 하는 강관기둥 상부와 하부의 조절부(21, 22)를 포함하는 것을 특징으로 한다. 이때 조절부(21, 22)에서는 바람직한 일실시예로서 선등록특허 "건설용 동바리 시스템(20-358791)", 선출원 특허 "동바리 조립용 브라켓과 이를 이용한 동바리시스템(10-2005-0030404)", "슬래브거푸집의 조기탈형이 가능한 시스템동바리의 가변지지재(10-2004-0057460)"의 회전가능한 4분할 스크류를 사용할 수 있다. A pedestal 10 is connected to the upper end of the steel pipe pillar 20 to be a support. At this time, the pedestal 10 is to serve to move the load to the steel pipe pillar 20 to support the formwork afterwards. The lower support 30 of the self-supporting lower portion 30 is connected to the lower portion of the steel pipe pillar 20 and serves to vertically fix the steel pipe pillar 20 to the bottom of the lower adjustment portion 22. Adjust the height with screws. The top and bottom planar trusses shown in FIG. 1 show an embodiment in the form of a pedestal 10 and a self-supporting support 30 that can be used. The pedestal 10 includes a pedestal binding portion 13 for controlling the height of the connecting portion (11, 12) and the adjusting portion 21 to connect the joist supporting the formwork plate as a projection on the top. The pedestal 10 and the support 30 are rotatably connected to the pedestal 10 and the support 30, respectively, and the length of the steel pipe pillar 20 can be freely adjusted. It characterized in that it comprises a control portion (21, 22) of the upper and lower steel pipe column to be. At this time, the control unit (21, 22) as a preferred embodiment in the registered patent "construction copper system for construction (20-358791)", patent application "copper assembly bracket and copper bar system using the same (10-2005-0030404)", A rotatable four-segment screw of "variable support material of the system group (10-2004-0057460) capable of early demolding of slab formwork" can be used.

도 2a는 본 발명의 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 설치한 실시예를 나타낸 사시도이다.Figure 2a is a perspective view showing an embodiment in which a flying foam is installed using the self-supporting copper clad structure for flying foam of the present invention.

상기 플라잉 폼 용 자립형 동바리 구조 한 쌍이 거리를 두고 평행하게 설치되고, 상기 설치된 한 쌍의 지지 동바리 구조는 가새(50)에 의해 이격거리 조정 및 형태 고정이 이루어진다. 상기 설치된 한 쌍의 지지 동바리 구조 중 어느 한 지지 동바리 구조의 받침대(10)의 주연결부(11)에서 타 지지 동바리 구조의 주연결부(11)에 거푸집 판을 지지하기 위한 고정 장선(41)이 연결된다. 상기 고정 장선(41)에 평행하게 거푸집 판을 지지하는 탈, 부착 장선(42)이 한 쌍의 보조연결부(12)에 설치된다. 상기 한 쌍의 탈, 부착 장선(42) 위에는 조기 탈형할 거푸집 판넬(43)이 설치되고, 상기 고정장선(41) 위에는 향후 잔존하게 되는 거푸집 판넬(43)이 설치되어 콘크리트 슬래브가 시공된다. 또한 상기 고정장선(41)의 주연결부(11)는 동바리 구조의 받침대(10)와는 독립되도록 구성하여 고정장선(41) 위의 거푸집 판넬이 잔존된 채로 조기 탈형 가능한 타 거푸집 판넬들만이 탈형, 하강되도록 할 수 있다. 상기 동바리 구조의 받침대(10)는 상부 조절대(21)의 높이 조절을 가능케 하여 상부 조절대(21)의 높낮이를 조절하여 탈, 부착 장선(42)의 탈착을 용이하게 한다. 또한 받침대(10)의 90°회전이 가능하므로 조기 탈형의 거푸집 판넬(43) 하강이 용이하다.The pair of self-supporting copper fly structure for the flying foam is installed in parallel with a distance, the pair of supporting support structure is installed by the braces 50 to adjust the distance and shape fixed. A fixed joist 41 for supporting the formwork plate is connected to the main connecting portion 11 of the other supporting moving structure in the main connecting portion 11 of the pedestal 10 of the supporting paired support structure. do. A detachment and attachment joist 42 for supporting the formwork plate parallel to the fixed joist 41 is provided at the pair of auxiliary connecting portions 12. On the pair of detachment and attachment joists 42, formwork panels 43 for early demoulding are installed, and formwork panels 43, which remain in the future, are installed on the fixed joists 41, thereby constructing concrete slabs. In addition, the main connection portion 11 of the fixed joist 41 is configured to be independent of the base 10 of the copper bar structure structure, only the other formwork panels that can be demoulded prematurely, while the formwork panel on the fixed joist 41 remains, demoulding, descending You can do that. The pedestal 10 of the copper bar structure enables the height adjustment of the upper control unit 21 to adjust the height of the upper control unit 21 to facilitate the removal of the detachment, attachment joist 42. In addition, since the 90 ° rotation of the pedestal 10 is possible, it is easy to lower the formwork panel 43 of early demoulding.

도 2b는 본 발명의 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 설치한 실시예로서 동바리의 받침대(10)인 트러스를 회전시켜 거푸집 판넬(43)을 해체하고 고정장선(41) 위에는 거푸집 판넬(43)이 잔존되는 모습을 나타낸 사시도이다.Figure 2b is an embodiment in which the flying foam is installed using a self-supporting copper cladding structure for flying foam of the present invention, by rotating the truss of the base 10 of the copper bar to dismantle the die panel 43 and the die panel on the fixed joist 41 It is a perspective view which shows a mode in which 43 remains.

콘크리트 슬래브의 경화가 진행된 부분의 플라잉 폼의 해체시에는 플라잉 폼 용 자립형 동바리 구조의 상부 조절부(21)에서 강관기둥(20)의 길이를 짧게 조절하여 상기 설치된 장선(42)을 제거하고, 상부 받침대(10)를 회전시켜 손쉽게 거푸집 판을 떼어낼 수 있다. 이때 고정 장선(41)은 주연결부(11)로 플라잉 폼 용 자립형 동바리 구조에 계속하여 고정되어 있어야 한다. 이와 같이 본 플라잉 폼 용 자립형 동바리 구조에서는 강관기둥(20)의 길이 조절 및 상부 받침대(10)의 회전으로 거푸집의 해체가 용이하게 이루어질 수 있다. 또한 이 과정에서 상기 강관기둥(20) 하부의 지지대(30) 역시 상부의 거푸집 판넬(43)의 하강 반출에 지장이 되지 않도록 회전이 가능하다. When dismantling the flying foam of the part where the hardening of the concrete slab is advanced, the length of the steel pipe pillar 20 is shortly adjusted in the upper control part 21 of the self-supporting copper cladding structure for the flying foam to remove the installed joists 42, and the upper part. The formwork plate can be easily removed by rotating the base 10. At this time, the fixed joist 41 should be continuously fixed to the self-supporting structure for flying foam as the main connecting portion (11). As described above, the self-supporting copper clad structure for the flying foam can be easily dismantled by adjusting the length of the steel pipe pillar 20 and rotating the upper pedestal 10. In addition, in this process, the support 30 of the lower portion of the steel pipe pillar 20 may also be rotated so as not to interfere with the lowering of the upper formwork panel 43.

도 3a는 형강 받침대를 이용한 플라잉 폼 용 자립형 동바리 구조를 나타낸 사시도이다.Figure 3a is a perspective view showing a self-supporting clubbing structure for flying foam using a steel beam bracket.

지주를 구성하는 강관기둥(20)의 상부 끝단에는 H형강으로 이루어진 형강 받침대(60)가 H형강의 플랜지 바닥면이 강관기둥(20)의 상부 끝단에 놓이도록 하여 연결된다. 이때 상기 형강 받침대(60)는 도1의 받침대(10)와 같이 차후 거푸집 판을 지지하는 역할을 하게 되는 것이다. 상기 형강 받침대(60)에는 도1의 보조연결부(12)가 불필요한데, 거푸집 판의 받침으로서 형강을 이용한 형강 장선(62)을 사용하기 때문에 상기 형강 장선(62)과 상기 형강 받침대(60) 간의 결합이 간단해지는 것이다. 한편 주연결부(11)는 형강 받침대(60)의 중앙에 설치되어 고정 장선(41)을 연결하는 데 필요하다. 상기 강관기둥(20)의 하부 끝단에는 상기 강관기둥(20)과 연결되어 바닥에 상기 강관기둥(20)을 수직으로 고정시키는 역할을 하는 하부 지지대(30)가 연결된다. 도1에서와 같이 강관기둥(20)은 상기 형강 받침대(60) 및 하부 동바리 지지대(30)가 각각 회전가능하게 상기 강관기둥(20)에 연결되고, 상기 강관기둥(20)의 길이 조절이 자유롭도록 상기 강관기둥(20) 상부와 하부의 조절부(21, 22)를 포함하는 것을 특징으로 한다. 이때 조절부(21, 22)에서는 바람직한 일실시예로서 스크류를 사용할 수 있다. The upper end of the steel pipe pillar 20 constituting the support is connected to the steel pedestal 60 made of H-shaped steel so that the flange bottom surface of the H-shaped steel is placed on the upper end of the steel pipe pillar 20. At this time, the form steel pedestal 60 is to serve to support the formwork plate in the future as the pedestal 10 of FIG. The auxiliary connection part 12 of FIG. 1 is unnecessary in the steel pedestal 60, but since the steel joist 62 using the steel is used as a support for the form plate, between the steel joist 62 and the steel pedestal 60. Joining is simple. On the other hand, the main connection portion 11 is installed in the center of the steel beam pedestal 60 is required to connect the fixed joist 41. The lower end 30 of the steel pipe pillar 20 is connected to the steel pipe pillar 20 so as to vertically fix the steel pipe pillar 20 to the bottom. As shown in FIG. 1, the steel pipe pillar 20 is connected to the steel pipe pillar 20 so that the section steel pedestal 60 and the lower club support 30 are rotatable, respectively, and the length of the steel pipe pillar 20 can be freely adjusted. It characterized in that it comprises a control unit (21, 22) of the upper and lower portion of the steel pipe pillar (20). At this time, the adjusting unit (21, 22) can be used as a preferred embodiment of the screw.

도 3b는 형강 받침대를 이용한 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 설치한 실시예로서 평면 트러스를 회전시켜 거푸집을 해체하는 모습을 나타낸 사시도이다.Figure 3b is a perspective view showing a state of disassembling the formwork by rotating a flat truss as an embodiment in which the flying foam is installed using a self-supporting copper clad structure for flying foam using a steel beam pedestal.

콘크리트 슬래브의 경화가 진행된 부분의 플라잉 폼의 해체시에는 상부 조절부(21)에서 강관기둥(20)의 길이를 짧게 조절하여 상기 설치된 형강 장선(42)을 제거하고, 상기 형강 받침대(60)를 회전시켜 손쉽게 거푸집 판을 떼어낼 수 있다. 이 때 고정 장선(41)은 플라잉 폼 용 자립형 동바리 구조에 계속하여 고정되어 있어야 한다. 이와 같이 플라잉 폼 용 자립형 동바리 구조에 있어 강관기둥(20)의 길이 조절 및 형강 받침대(60)의 회전으로 거푸집 판넬(43)의 탈형이 용이하게 이루어질 수 있다. 또한 이 과정에서 상기 강관기둥(20) 하부의 지지대(30) 역시 회전이 가능하므로 거푸집 판넬(43)의 하강 반출이 용이하게 이루어진다.When dismantling the flying foam of the part where the hardening of the concrete slab is advanced, the length of the steel pipe pillar 20 is shortly adjusted in the upper adjusting part 21 to remove the installed section steel joists 42, and the steel beam pedestal 60 is removed. It can be easily rotated to remove the formwork plate. At this time, the fixed joist 41 should be continuously fixed to the self-supporting structure for flying foam. As described above, in the self-supporting copper cladding structure for the flying foam, the formwork panel 43 can be easily demolded by adjusting the length of the steel pipe pillar 20 and rotating the shaped steel pedestal 60. In addition, in this process, since the support 30 of the lower portion of the steel pipe pillar 20 can also be rotated, the formwork panel 43 can be easily taken out and lowered.

도 4a 및 도 4b는 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 설치한 현장의 시공 과정을 도시한 단면도이다.4A and 4B are sectional views showing a construction process of a site in which a flying foam is installed using a self-supporting copper clad structure for flying foam.

본 발명의 플라잉 폼 용 자립형 동바리 구조를 사용하여 플라잉 폼을 현장 시공에 적용하는 시공 과정은 다음과 같다. 도4a의 (가)와 같이 우선 슬래브 콘크 리트 타설 예정 구간에 일정한 간격으로 본 발명의 플라잉 폼 용 자립형 동바리 구조의 지지대(30)를 설치하고, 상기 지지대(30) 위에 강관기둥(20)을 세운다. 다음으로 상기 설치된 강관기둥(20)의 사이에 가새(50) 등을 설치하여 상기 강관기둥(20) 간의 이격 거리를 유지하고 자립구조가 고정되도록 한다. 이때 상기 지지대(30)는 회전이 가능하므로 자립구조로 세움이 용이한 형태를 갖도록 하고, 거푸집 판넬(43)의 탈형, 하강, 반출시에는 회전하여 반출 장애물을 간편하게 제거할 수 있도록 하며 거푸집 판넬(43)의 반출 후에는 역회전하여 원상태로 복귀할 수 있다. The construction process of applying a flying foam to field construction using the self-supporting copper clad structure for flying foam of the present invention is as follows. First, as shown in (a) of FIG. 4A, the support 30 of the self-supporting structure for flying foam of the present invention is installed at a predetermined interval in the slab concrete casting scheduled section, and the steel pipe pillar 20 is erected on the support 30. . Next, the braces 50 are installed between the installed steel pipe pillars 20 to maintain the separation distance between the steel pipe pillars 20 so that the self-supporting structure is fixed. At this time, the support 30 can be rotated to have a form that is easy to stand as a self-supporting structure, and when the form panel 43, demolding, descending, unloading to rotate to remove the obstacle to remove easily and formwork panel ( After discharging 43), it can be reversed and returned to its original state.

강관기둥(20) 상단에는 도4a의 (나)와 같이 받침대(10)를 연결하고, 받침대의 연결부(11, 12)에는 장선(41, 42)을 설치하여 추후 거푸집 판을 받칠 수 있도록 하여 F-1슬래브 콘크리트(44)를 타설한다. 도4b의 (다)와 같이 상기 설치된 장선 위에 조립된 거푸집 판(43)을 인양하여 설치하고, F-2 슬래브 콘크리트(44) 타설을 위한 본 발명의 플라잉 폼 용 자립형 동바리 구조를 설치한다.The pedestal 10 is connected to the top of the steel pipe pillar 20 as shown in (b) of FIG. 4a, and the joists (41, 42) are installed at the connection portions 11 and 12 of the pedestal so as to support the formwork plate later. -1 Slab concrete (44) is poured. As shown in Figure 4b (c) is installed by lifting the formwork plate 43 assembled on the installed joist, and the self-supporting copper structure for flying foam of the present invention for placing the F-2 slab concrete 44 is installed.

도4b의 (라)와 같이 F-2 슬래브 콘크리트(44) 타설 후에는 필요한 최소한의플라잉 폼 용 자립형 동바리 구조를 슬래브 지지부재로서 잔존시키고, 나머지는 상기 플라잉 폼 용 자립형 동바리 구조의 받침대(10)의 회전 및 강관기둥(20)의 길이를 조절하여 손쉽게 부분 해체시킨다(도4b의 (마)참조). 해체된 상기 플라잉 폼 용 자립형 동바리 구조는 다른 슬래브 콘크리트 타설 위치로 이동되어 현장 내에서 동일 과정을 반복하여 재조립, 재활용된다.After pouring the F-2 slab concrete 44 as shown in FIG. 4B, the minimum required self-supporting copper frame structure for flying foam is left as the slab support member, and the rest of the self-supporting copper frame structure for the flying foam is supported. Rotate and adjust the length of the steel pipe column 20 to easily dismantle (see (e) of Figure 4b). The dismantled self-supporting copper structure for the disassembled flying foam is moved to another slab concrete placing position and is reassembled and recycled by repeating the same process in the field.

도 5는 플라잉 폼 용 자립형 동바리 구조를 사용하여 현장의 콘크리트 슬래 브 시공 시에 하강 도르래(31)를 사용하는 예를 나타낸 사시도이다.5 is a perspective view showing an example of using the lowering pulley 31 when constructing a concrete slab in the field using a self-supporting copper clad structure for flying foam.

플라잉 폼 용 자립형 동바리 구조를 사용하여 현장의 콘크리트 슬래브 시공 시 슬래브의 철근 배근 작업중에 하강용 도르래(31)를 설치한다. 슬래브 거푸집(43)은 도르래의 홈에 맞도록 제작하여 설치한다. 슬래브 콘크리트 타설 후 도 4b의 공정과 같이 F-1층의 플라잉 폼을 탈형하여 바닥으로 하강할 때에 상기 하강 도르래(31)를 사용한다. 그리고 하강된 플라잉 폼은 도4에 표현된 플라잉 폼의 형강 장선(62)에 일체화 되어 있는 이동바퀴(51)를 이용하여 용이하게 인양 작업장까지 반출할 수 있다. 상기 하강 도르래(31)는 도르래 부분과 받침부분으로 구분되는데 플라잉 폼의 탈형 작업 후 하강 도르래(31)의 받침부분을 제거하고, 상기 거푸집(43)의 홈이 있었던 부분에는 시멘트 모르타르를 충진하여 마감 처리한다.Using the self-supporting copper cladding structure for the flying foam, the lowering pulley (31) is installed during the reinforcement of the slab when constructing the concrete slab on the site. Slab formwork 43 is manufactured and installed to fit the groove of the pulley. After the slab concrete is poured, the lowering pulley 31 is used when demolding the flying foam of the F-1 layer and descending to the floor as in the process of FIG. 4B. And the lowered flying foam can be easily carried out to the lifting work site by using the moving wheel 51 which is integrated in the section steel line 62 of the flying foam shown in FIG. The lowering pulley 31 is divided into a pulley part and a supporting part. After demolding the flying foam, the supporting part of the lowering pulley 31 is removed, and the groove of the form 43 is filled with cement mortar to finish. Process.

본 발명의 플라잉 폼 용 자립형 동바리 구조를 사용함으로써, 양생중인 하층의 콘크리트 슬래브에 구조적인 무리를 주지 않으며, 상층 슬래브의 거푸집 설치 작업을 조기에 착수할 수 있어, 골조공사에 소요되는 공기를 단축할 수 있게 된다.By using the self-supporting copper cladding structure for flying foam of the present invention, it is possible to undertake structural installation of the upper slab without any structural burden, and to start the formwork of the upper slab at an early stage, thereby reducing the air required for the construction work. It becomes possible.

또한 본 발명의 플라잉 폼을 이용하는 경우, 하층의 콘크리트 슬래브가 충분한 설계강도를 발현할 때까지의 양생 기간 동안 하층의 콘크리트 슬래브 하부에 슬래브 지지부재, 존치 형틀 및 지주를 존치시키므로 별도의 지지 보강 수단의 설치 없이도 슬래브 축조 시 사용되었던 거푸집의 부분 부재들을 이용하여 구조물의 내구성을 확보할 수 있다. 또 본 발명의 플라잉 폼 용 자립형 동바리 구조는 높이 조 절 및 고정부의 회전을 가능케 하여 거푸집 판의 원형에 손상 없이 탈형이 용이하게 이루어져 우수한 품질의 건축물을 시공할 수 있는 콘크리트 슬래브 시공 방법을 제공한다.In addition, in the case of using the flying foam of the present invention, since the slab support member, the retaining mold and the support stay in the lower part of the concrete slab during the curing period until the lower concrete slab exhibits sufficient design strength, Partial parts of the formwork used in building the slab can be secured without installation. In addition, the self-supporting copper cladding structure for the flying foam of the present invention enables the height adjustment and the rotation of the fixing part to provide a concrete slab construction method that can be easily demolded without damaging the circular form of the formwork plate to construct a building of excellent quality. .

또 본 발명의 플라잉 폼 용 자립형 동바리 구조는 양생중인 하층의 콘크리트 슬래브의 설계 강도의 발현이 완성되기 전에, 조기에 탈형 가능한 일부 플라잉 폼을 부분적으로 손쉽게 우선 탈형하고 이를 재활용하여 상층의 거푸집으로 설치할 수 있게 함으로써, 소정의 플라잉 폼만으로도 구조물 축조가 가능케 하여 가설공사비를 절감케 하므로, 경제성이 뛰어난 콘크리트 슬래브 시공 방법을 제공하는데 또 다른 효과가 있다.In addition, the self-supporting copper cladding structure for the flying foam of the present invention can be easily demolded and recycled to some form of upper layer before the development of the design strength of the cured lower concrete slab is completed. By doing so, it is possible to construct the structure with only a predetermined flying foam, thereby reducing the construction cost, and there is another effect to provide a concrete slab construction method with excellent economic efficiency.

Claims (6)

슬래브 콘크리트 타설에 이용되는 것으로 거푸집 판, 지주, 해체와 이동을 위한 보조장비로 구성되는 플라잉 폼에서,In flying foams, which are used for slab concrete pouring, consisting of formwork plates, struts, and auxiliary equipment for dismantling and moving, 지주를 구성하는 것으로 길이 조절이 가능한 강관기둥; Steel pipe pillar which can adjust length by constituting prop; 상기 강관기둥의 상단에 연결되는 받침대; 및Pedestal connected to the top of the steel pipe pillar; And 상기 강관기둥의 하단에 연결되는 지지대; 를 포함하여 구성되되,A support connected to a lower end of the steel pipe column; Consists of including 상기 받침대는 평면 트러스로 구성되고, 상기 평면 트러스는 상기 강관기둥의 상단에 연결되며 회전 및 높이조절이 가능하도록 한 것을 사용하는 것을 부가적인 특징으로 하는 플라잉 폼 용 자립형 동바리 구조. The pedestal is composed of a flat truss, the flat truss is connected to the upper end of the steel pipe pillars, the self-supporting copper structure for flying foams, characterized in that additionally using the one to enable the rotation and height adjustment. 슬래브 콘크리트 타설에 이용되는 것으로 거푸집 판, 지주, 해체와 이동을 위한 보조장비로 구성되는 플라잉 폼에서,In flying foams, which are used for slab concrete pouring, consisting of formwork plates, struts, and auxiliary equipment for dismantling and moving, 지주를 구성하는 것으로 길이 조절이 가능한 강관기둥; Steel pipe pillar which can adjust length by constituting prop; 상기 강관기둥의 상단에 연결되는 받침대; 및Pedestal connected to the top of the steel pipe pillar; And 상기 강관기둥의 하단에 연결되는 지지대; 를 포함하여 구성되되,A support connected to a lower end of the steel pipe column; Consists of including 상기 받침대는 H형강으로 구성되고, 상기 H형강은 상기 강관기둥의 상단에 H형강의 플랜지 바닥이 오도록 하여 연결되며 회전 및 높이조절이 가능하도록 한 것을 사용하는 것을 부가적인 특징으로 하는 플라잉 폼 용 자립형 동바리 구조.The pedestal is composed of the H-shaped steel, the H-shaped steel is connected to the bottom of the flange of the H-shaped steel on the top of the steel pipe pillar, and the independent type for flying foam, characterized in that the use of the rotation and height adjustment is used. Club structure. 제1항 또는 제2항에서,The method of claim 1 or 2, 상기 지지대는 평면 트러스의 보조 지지수단을 부가적으로 구비하고, 상기 지지대는 강관기둥 하부에 연결되며 회전이 가능한 것을 사용하는 것을 부가적인 특징으로 하는 플라잉 폼 용 자립형 동바리 구조.The support is additionally provided with an auxiliary support means of a flat truss, the support is connected to the lower portion of the steel pipe pillars, the self-supporting copper structure for flying foams, characterized in that additionally using the rotatable. 삭제delete 슬래브 콘크리트 타설 구간의 하층 바닥에 일정한 간격으로 제1항 또는 제2항의 플라잉 폼 용 자립형 동바리 구조를 설치하는 제1단계;A first step of installing a self-supporting copper cladding structure for flying foam of claim 1 or 2 at regular intervals on a lower floor of a slab concrete pouring section; 상기 설치된 플라잉 폼 용 자립형 동바리 구조 사이에 가새를 설치하는 제2단계;A second step of installing braces between the installed self-supporting floating structure for flying foam; 상기 설치된 플라잉 폼 용 자립형 동바리 구조의 받침대에 장선을 연결하는 제3단계;A third step of connecting a joist to the pedestal of the installed self-supporting copper frame structure for the flying foam; 상기 설치된 장선 위에 조립된 거푸집 판을 인양하여 설치하는 제4단계;A fourth step of lifting and installing the formwork plate assembled on the installed joist; 상기 설치된 거푸집 판 위에 슬래브 콘크리트를 시공하는 제5단계;A fifth step of constructing slab concrete on the installed formwork plate; 상기 시공된 슬래브 콘크리트의 지지에 필요한 최소한의 플라잉 폼 용 자립형 동바리 구조를 잔존시키고 나머지는 해체하는 제6단계;A sixth step of remaining a self-supporting copper cladding structure for flying foam required for supporting the constructed slab concrete and dismantling the rest; 상기 해체된 플라잉 폼 용 자립형 동바리 구조를 다른 콘크리트 슬래브 시공 구간으로 이동시켜 제1단계 내지 제6단계를 반복하는 제7단계;A seventh step of repeating the first to sixth steps by moving the disassembled flying foam for self-supporting structure to another concrete slab construction section; 상기 과정을 포함하는 것을 특징으로 하는 플라잉 폼 용 자립형 동바리 구조를 이용한 콘크리트 슬래브 시공 방법. Concrete slab construction method using a self-supporting copper cladding structure for flying foam, characterized in that it comprises the above process. 제 5항에서,In claim 5, 제4단계의 거푸집 판 설치시에 도르래를 부가설치하여 제6단계의 플라잉 폼의 탈형, 하강시에 상기 도르래를 사용하는 것을 부가적인 특징으로 하는 플라잉 폼 용 자립형 동바리 구조를 이용한 콘크리트 슬래브 시공 방법.A method of constructing a concrete slab using a self-supporting copper cladding structure for flying foams, wherein the pulleys are additionally installed at the time of installing the formwork plate of the fourth step to use the pulleys for demolding and descending the flying foam of the sixth step.
KR1020050108551A 2005-11-14 2005-11-14 Support system for Flying form and Concreate slab construction method using the same KR100738410B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050108551A KR100738410B1 (en) 2005-11-14 2005-11-14 Support system for Flying form and Concreate slab construction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050108551A KR100738410B1 (en) 2005-11-14 2005-11-14 Support system for Flying form and Concreate slab construction method using the same

Publications (2)

Publication Number Publication Date
KR20070051104A KR20070051104A (en) 2007-05-17
KR100738410B1 true KR100738410B1 (en) 2007-07-11

Family

ID=38274380

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050108551A KR100738410B1 (en) 2005-11-14 2005-11-14 Support system for Flying form and Concreate slab construction method using the same

Country Status (1)

Country Link
KR (1) KR100738410B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587648A (en) * 2012-03-17 2012-07-18 浙江城建建设集团有限公司 Gate-type steel pipe and fastener-type steel pipe fabricated formwork support device and construction method

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104422231B (en) 2013-09-05 2017-06-23 Lg电子株式会社 Refrigerator and its control method
CN103806659B (en) * 2013-09-12 2016-02-24 中如建工集团有限公司 Super thick prestressing force change-over panel individual layer comprehensively supports and splits temperature control construction technology with control
CN105735637A (en) * 2014-12-11 2016-07-06 中冶天工集团有限公司 Double-layer bracket supporting system for silo heavy beam formwork
CN104847109A (en) * 2015-03-20 2015-08-19 福建工程学院 Concrete formwork tool type framework support system and construction method
CN106013780A (en) * 2016-06-30 2016-10-12 上海二十冶建设有限公司 Safe slab formwork supporting device
CN106150083A (en) * 2016-08-21 2016-11-23 中铁四局集团建筑工程有限公司 A kind of slip form platform of metro depot beam slab concrete structure construction
CN106759966A (en) * 2016-12-28 2017-05-31 山东万鑫建设有限公司 Pouring after settlement shaped steel transition mast temporary support construction method
CN109457952A (en) * 2018-11-20 2019-03-12 中建四局第六建筑工程有限公司 A kind of return back to top ruggedized construction and its construction method for post-cast strip cantilever
CN114790755B (en) * 2022-05-18 2023-11-07 中国机械工业第二建设工程有限公司 Concrete raft post-pouring strip construction joint template

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0162033B1 (en) * 1995-09-12 1998-12-15 김재연 Strut for slabforms
KR200257105Y1 (en) 1999-02-22 2001-12-24 최영근 Accordion type support assembly

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0162033B1 (en) * 1995-09-12 1998-12-15 김재연 Strut for slabforms
KR200257105Y1 (en) 1999-02-22 2001-12-24 최영근 Accordion type support assembly

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587648A (en) * 2012-03-17 2012-07-18 浙江城建建设集团有限公司 Gate-type steel pipe and fastener-type steel pipe fabricated formwork support device and construction method

Also Published As

Publication number Publication date
KR20070051104A (en) 2007-05-17

Similar Documents

Publication Publication Date Title
KR100738410B1 (en) Support system for Flying form and Concreate slab construction method using the same
WO2014182539A2 (en) Method and system for rapid construction of structurally reinforced concrete structures using prefabricated assemblies and method of making the same
CN110905113A (en) Construction method of large-span concrete dome structure
KR20070010449A (en) Construction method for arched bridge
KR101140884B1 (en) Gangform device constructed for wall and constructing method this using
CN109610707B (en) Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method
KR102430362B1 (en) Structure for precast construction of inner cone of silo and precast construction method of inner cone of silo using the same
CN110777659A (en) Construction method of box culvert template system
KR20200107332A (en) The Simultaneous Construction Method for Wall and Slab of Building
CN110093948A (en) Variable cross-section Pipe rack and its construction method suitable for rapid construction
JP2002030615A (en) Construction method of tower structure
KR100361047B1 (en) Construction mold
CN114263275A (en) High-rise assembled steel structure-core tube same-layer construction method
KR20040102272A (en) Prestressed concrete double-t beam bridge &amp; formwork applying incremental launching method
JPH116296A (en) Concrete placing work execution method
KR200184988Y1 (en) Establishment structure forming system using kicker block
CN110185254A (en) A kind of Combined aluminum alloy template system and its application method
AU2005287894B2 (en) Method and apparatus for construction
JP2884440B2 (en) Formwork for construction of concrete prism and construction method of column using it
KR102425501B1 (en) Silo construction method using precast and slip foam
JP2003119806A (en) Device and method for constructing sidewall of underground tank
CN215594550U (en) Disassembly-free laminated slab
JP2002250130A (en) Method for construction multilayer concrete structure
Figovskij et al. Erecting multistory buildings with monolithic reinforced concrete slab floors by using precast large-sized spatial structures
CN115637776B (en) Pavement sandwich structure building and construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right