KR100662011B1 - Construction method of shore protector using reinforcing strip - Google Patents

Construction method of shore protector using reinforcing strip Download PDF

Info

Publication number
KR100662011B1
KR100662011B1 KR1020050081709A KR20050081709A KR100662011B1 KR 100662011 B1 KR100662011 B1 KR 100662011B1 KR 1020050081709 A KR1020050081709 A KR 1020050081709A KR 20050081709 A KR20050081709 A KR 20050081709A KR 100662011 B1 KR100662011 B1 KR 100662011B1
Authority
KR
South Korea
Prior art keywords
wood
installing
pile
river
protector
Prior art date
Application number
KR1020050081709A
Other languages
Korean (ko)
Inventor
서동현
윤종우
Original Assignee
(주)현이앤씨
서동현
윤종우
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)현이앤씨, 서동현, 윤종우 filed Critical (주)현이앤씨
Priority to KR1020050081709A priority Critical patent/KR100662011B1/en
Application granted granted Critical
Publication of KR100662011B1 publication Critical patent/KR100662011B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

A shore protector construction method using a reinforcing strip is provided to improve structural stability of a bank, and implement a more environment-friendly shore protector by using timber. A shore protector construction method using a reinforcing strip comprises the steps of arranging a site for installing a shore protector thereon, installing timber piles(10) as a main pile at constant intervals, bonding horizontal timber shafts(20) at constant intervals to an inside of the timber pile by a bolt, installing vertical timber shafts(30) between the timber piles at constant intervals, installing a coconut planting mat(100) and a taxol retaining wall(70) to a front side of the vertical timer shaft, connecting reinforcing strips(40,50) to the timber pile and the horizontal timber shaft, respectively, to minimize deformation of a wall by an external force, by welding frictional resistant bars(60) at constant intervals.

Description

보강스트립을 이용한 하천 호안보호공의 시공방법{Construction method of shore protector using reinforcing strip}Construction method of shore protector using reinforcing strip}

도1은 본 발명의 보강스트립을 이용한 하천 호안보호공을 도시한 정면도,1 is a front view showing a river bank protection ball using a reinforcing strip of the present invention,

도2는 본 발명의 보강스트립을 이용한 하천 호안보호공을 도시한 평면도,Figure 2 is a plan view showing a river bank protection hole using the reinforcing strip of the present invention,

도3은 본 발명의 보강스트립을 이용한 하천 호안보호공을 도시한 단면도,3 is a cross-sectional view showing a river bank protection hole using the reinforcing strip of the present invention,

도4는 본 발명의 마찰저항바가 접합된 가로목재봉용 보강스트립이 가로목재봉에 연결된 상세도,Figure 4 is a detailed view of the reinforcing strip for horizontal wood sewing bar is bonded to the frictional resistance bar of the present invention,

도5는 본 발명의 목재말뚝에 연결된 목재말뚝용 보강스트립의 연결상세도,Figure 5 is a connection detail of the reinforcing strip for the wooden pile connected to the wooden pile of the present invention,

도6은 본 발명의 보강스트립을 이용한 하천 호안보호공의 사시도,Figure 6 is a perspective view of the river bank protection ball using the reinforcing strip of the present invention,

도7은 본 발명의 하천 호안의 다짐기로 다짐층을 형성한 하천 호안 보호공을 도시한 사시도이다. 7 is a perspective view illustrating a river bank protection hole in which a compaction layer is formed by a compactor in a river bank of the present invention.

<도면의 주요 부분에 대한 부호의 설명>        <Explanation of symbols for the main parts of the drawings>

10 : 목재말뚝 20 : 가로목재봉        10: wood pile 20: horizontal wood sewing

30 : 세로목재봉 40 : 목재말뚝용 보강스트립        30: longitudinal wood rod 40: reinforcement strip for wood pile

50 : 가로목재봉용 보강스트립 60 : 마찰저항바        50: reinforcing strip for horizontal wood sewing 60: friction resistance bar

70 : 텍솔옹벽 80 : 볼트접합        70: texol retaining wall 80: bolted joint

90 : 용접접합 100 : 코코넛 식생매트        90: welded joint 100: coconut vegetation mat

본 발명은 하천제방의 호안 보호를 위한 하천 호안 보호공의 시공방법에 관한 것이다.The present invention relates to a method for constructing a river bank protection hole for protection of the banks of the river banks.

한국의 강우량은 여름철인 7월에서 8월경의 장마철에 집중되어 태풍과 집중호우로 많은 양의 비를 내리고 있다. 갈수기에는 바닥을 보이던 하천의 수위가 호우가 집중되는 장마철에는 급격히 증가하게 되어 하천 제방의 침식 및 붕괴사고가 매년 일어나고 있으며 이로 인한 대형 인명사고 및 재산상의 손실 사고가 매년 되풀이 되고 있는 실정이다. Rainfall in Korea is concentrated during the rainy season in July and August, which is summer, and it rains a lot of rain due to typhoons and heavy rains. During the rainy season, the level of rivers, which had been bottomed out, increased sharply during the rainy season, and erosion and collapse of river banks occurred every year, resulting in large-scale personal injury and property loss.

이를 방지하기 위하여 기존의 호안 보호공의 형태로 콘크리트로 제작된 호안 블록을 이용한 방법, 철망에 돌을 담아 시공하는 돌망태를 이용한 방법, 자연석 또는 나무말뚝을 이용한 방법 등을 적용하여 상류에서 발생한 홍수를 안전하게 하류로 소통하기 위한 치수 목적으로 시공되어 왔다.In order to prevent this, flooding generated from the upstream by applying the method using the revetment block made of concrete in the form of the existing revetment protector, the method using the gabion to build the stone in the wire mesh, the method using the natural stone or the wooden pile, etc. It has been constructed for the purpose of dimensionally communicating safely downstream.

그러나, 상기의 호안 블록, 돌망태, 자연석을 이용한 호안 보호공은 하천 수위가 줄어들어 제방이 노출되는 갈수기에는 콘크리트, 철망, 돌등으로 덮여있는 제방의 형태로 하천의 경관을 훼손하며 식생이 가능한 공간이 부족하여 환경친화적인 자연형 하천을 조성할 수 없어 수생식물 및 어패류의 생식에도 많은 영향을 주어 자연생태계에 악영향을 주고 있다.However, the shelter protector using the shelter block, gabion, and natural stone above the river level is reduced, and in the dry season during which the dike is exposed, the river is covered with concrete, wire mesh, stones, etc., damaging the landscape of the river and lacking space for vegetation. Therefore, it is not possible to create an environment-friendly natural stream, which affects the reproduction of aquatic plants and fish and shellfish, which adversely affects the natural ecosystem.

또한 상기의 돌망태를 이용한 방법에는 돌망태가 철선으로 제작되어 수중에 서 쉽게 부식되며 철선이 외부요건으로 쉽게 늘어나거나 끊어져서 돌들이 이탈되는 등 호안 보호공의 역할을 제대로 하지 못하는 경우가 빈번하게 일어나며, 돌망태 안으로 이물질들이 많이 부착하게 되어 수질이 악화되는 문제점이 발생되고 있다.In addition, in the method using the gabions, the gabions are made of iron wire, which is easily corroded in the water, and the wires are easily stretched or broken due to external requirements, and the stones are separated. There is a problem that deteriorates the water quality due to the adhesion of a lot of foreign matter inside.

상기 기존의 호안 보호 공법들은 재료적인 취약점 및 구조적인 불안정함으로 인하여 하천 제방의 보호 기능 및 환경친화적인 자연형 하천을 조성하여 주지 못하고 있으며, 이로 인한 제방의 붕괴와 생태환경의 파괴가 일어나고 있는 실정이다.Due to material weakness and structural instability, the existing shore protection methods do not provide protection of river banks and environmentally friendly natural rivers, resulting in the collapse of banks and the destruction of ecological environment. .

따라서, 본 발명은 상기와 같은 문제점을 해결하기 위한 것으로써, 자연 친화적인 재료인 목재를 이용하여 목재말뚝과 목재봉으로 형성되는 전면 벽체를 구성하고 코코넛 식생매트와 텍솔옹벽 등을 이용하여 전면의 식생을 유도함으로써 환경친화적인 자연형 하천을 조성함은 물론 마찰저항력이 발휘되는 보강스트립을 사용하여 전면 벽체에 연결 시공함으로써 보강토 옹벽의 구조적 안정성을 도입하여 보다 안정적인 하천 호안 보호공의 시공방법을 제공하는데 있다.Therefore, the present invention is to solve the problems as described above, by using a wood, which is a natural friendly material to form a front wall formed of wood piles and wooden rods and the front of the coconut vegetation mat and texol retaining wall Induces vegetation to create an eco-friendly natural river and connects it to the front wall using a friction-reinforced reinforcement strip to introduce structural stability of the reinforced earth retaining wall to provide a more stable method for constructing a river bank protection work. It is.

이하, 본 발명의 실시예를 첨부된 도면을 참조하면서 상세하게 설명하면 다음과 같다.Hereinafter, an embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도1은 본 발명에 의한 보강스트립을 이용한 호안 보호공의 정면도이고, 도2는 보강스트립을 이용한 호안 보호공의 평면도이며, 도3와 도6은 보강스트립을 이용한 호안 보호공의 단면도와 사시도이다. 1 is a front view of a rake protection hole using a reinforcing strip according to the present invention, Figure 2 is a plan view of a rake protection hole using a reinforcing strip, Figure 3 and 6 are a cross-sectional view and a perspective view of the rake protection hole using a reinforcing strip. .

목재말뚝(10)을 하천바닥에 일정 간격으로 설치하여 주 기중을 세운 후 한단 의 높이에 따라 토류벽의 띠장 역할을 하는 가로목재봉(20)을 일정 간격으로 볼트접합(80)하여 설치함으로 주 기둥인 목재말뚝(10)의 간격을 유지하여 주며, 주 기둥인 목재말뚝(10)과 목재말뚝(10) 사이에는 도1에서 보는 바와 같이 세로목재봉(30)을 일정간격 설치하여 줌으로써 배면 성토재의 흘러내림을 막아주는 토류벽의 역할을 하게 된다. 세로목재봉(30)은 산림간벌시 발생하는 나뭇가지를 이용하거나 규격목재를 사용한다.After installing the wooden pile (10) at the river floor at regular intervals to set up the main weight, according to the height of the end by installing the horizontal wood rods (20) that serve as the band of the earth wall bolts at certain intervals to install the bolts (80) Phosphorus to maintain the gap of the wooden pile (10), and between the main wooden timber pile 10 and the wooden pile (10) as shown in Figure 1 vertical wood rods 30 by installing a predetermined interval of the backing soil material It acts as an earth wall to prevent it from flowing down. Longitudinal wood rod 30 uses a tree branch generated during deforestation or using standard wood.

메인 말뚝인 목재말뚝(10)은 하천바닥에 말뚝의 크기보다 20mm정도 더 큰 철재 파이프를 이용하여 일정의 깊이까지 항타기로 항타시켜 목재말뚝(10)의 구멍을 형성시킨 후 목재말뚝(10)을 삽입하여 메인 말뚝을 세운다.Wood pile 10, which is the main pile, is driven to a certain depth using a steel pipe about 20 mm larger than the size of the pile on the bottom of the river, and then formed a hole in the wooden pile 10 after the wood pile 10 is formed. Insert the main pile up.

또한, 도2에서와 같이 주 기둥인 목재말뚝(10) 상부에 목재말뚝용 보강스트립(40)을 이용하여 배면의 목재말뚝(10)과 도5와 같이 연결시켜 기둥의 상부를 고정함으로써 외부 작용하중에 의한 주 기둥의 횡방향 변위를 최대한 억재 할 수 있고 일체화된 호안 구조물을 조성할 수 있도록 구성되어 있으며, 목재말뚝(10) 사이의 가로목재봉(40)에는 가로목재봉용 보강스트립(50)을 도4와 같은 방법으로 연결하여 보강하고, 도7과 같이 층다짐하여 보강스트립(50)에 용접으로 접합시킨 마찰저항바(60)에 의한 마찰저항력이 발휘됨에 따라 보강토 옹벽과 같은 구조적 안정성을 가지도록 구성되어 있다. In addition, by using the wood pile reinforcement strip 40 on the top of the wooden pile 10, the main pillar as shown in Figure 2 connected to the wooden pile 10 on the back as shown in Figure 5 to secure the top of the column The transverse displacement of the main column due to the load can be restrained to the maximum, and is configured to form an integrated revetment structure, and the horizontal wood rods 40 between the wooden piles 10 are reinforcing strips for the horizontal wood rods 50. 4 is reinforced by the method as shown in FIG. 4, and as shown in FIG. 7, the frictional resistance by the frictional resistance bar 60 bonded to the reinforcing strip 50 by welding is exerted, thereby improving structural stability such as a reinforced soil retaining wall. It is configured to have.

본 발명에 적용된 보강스트립(40,50)은 철근을 이용하여 제작되며 마찰저항바(60)는 보강스트립의 하부면에 용접(90)으로 접합하고, 양부재의 교각은 90ㅀ로 한다. 모든 철근은 용융아연도금을 하여 철근의 부식을 방지하도록 구성되어 있다. 마찰저항바는 20㎝~100㎝마다 설치되고 마찰저항바의 굵기는 10㎜, 13㎜, 16㎜를 사용하고 길이는 50㎜에서 100㎜로 하고, 보강스트립의 굵기는 마찰저항바의 굵기와 동일하게 한다. The reinforcing strips 40 and 50 applied to the present invention are manufactured using reinforcing bars, and the frictional resistance bar 60 is joined to the lower surface of the reinforcing strip by welding 90, and the piers of both members are 90 °. All rebars are hot dip galvanized to prevent corrosion of the rebars. The friction resistance bar is installed every 20cm ~ 100㎝ and the thickness of the friction resistance bar is 10mm, 13mm, 16mm, and the length is 50mm to 100mm, and the thickness of the reinforcing strip is the thickness of the friction resistance bar. Do the same.

도3에서 보는 바와 같이, 보강스트립을 이용한 호안보호공 전면을 코코넛 식생매트(70)를 전면 포설한 후 텍솔옹벽(70)을 층다짐 높이에 따라서 10~20cm의 폭으로 설치하도록 시공함으로써 하천 유수에 의한 배면 성토재의 침식 방지 및 식생 기반재 역할을 하도록 구성되어 있다. 텍솔옹벽(70)은 고강도 나일론 실과 토립자를 함깨 취부하는 공법으로 전단강도 증가와 기존의 호안 보호공에서는 재료적 특성 때문에 불가능한 식생이 가능하도록 구성됨에 따라 우기시 수생식물 및 어패류의 생식이 가능해지며, 건기시 하천 호안이 들어날 경우에도 전면 및 배면이 식생됨에 따라 보다 자연 친화적인 구조물을 조성할 수 있도록 되어 있다.As shown in Figure 3, the front of the revetment strip using the reinforcing strip to install the coconut vegetation mat 70 in front of the river by installing the texol retaining wall 70 in a width of 10 ~ 20cm depending on the height of the stratification It is configured to act as a vegetation foundation and prevention of erosion of the backfill soil by. The texol retaining wall 70 is a method of attaching high-strength nylon thread and granules together to increase the shear strength and to enable vegetation that is impossible due to the material characteristics of the existing shore protection work, so that aquatic plants and seafood can be reproduced during the rainy season. Even in the dry season, when the riverbank enters, the front and the back are vegetated to create a more natural structure.

상기한 바와 같이 구성된 본 발명의 보강스트립을 이용한 하천 호안보호공과 그 시공방법에 의하면, 종래에는 호안보호공의 재료적 특성 때문에 실질적인 식생이 불가능하여 자연하천의 생태환경에 악영향을 주는 경우가 많았으나, 본 발명은 목재말뚝(10), 세로목재봉(20), 가로목재봉(30) 등의 벽체를 이루는 주재료가 목재로 구성되어 있어 장기적으로 하천 제방이 침식과 퇴적을 반복하면서 하천 제방이 안정 구배를 이룰 때 썩어 없어지게 되어 환경적으로 우수한 재료로 구성되어 있으며, 홍수시 목재말뚝(10)과 세로목재봉(30)의 형태적 특성으로 물과의 마찰력을 증가시켜 세굴을 방지하게 하는 효과가 있다.According to the river revetment protection ball and the construction method using the reinforcing strip of the present invention configured as described above, in the past, due to the material properties of the revetment protection ball, the actual vegetation is impossible, which often adversely affects the ecological environment of the natural river. In the present invention, the main material constituting the wall, such as the wooden pile (10), longitudinal wooden rods (20), horizontal wooden rods (30) is composed of wood, so that the river banks are eroded and deposited in the long term, the river banks are stable. It is made of environmentally superior materials that will rot away when forming a gradient, and the effect of preventing scouring by increasing the frictional force with water due to the morphological characteristics of the wood pile 10 and the longitudinal wood rod 30 during flooding. There is.

또한, 벽체의 전면을 코코넛 식생매트(70)를 배면 성토 층다짐 높이에 따라서 10~20cm의 폭으로 텍솔옹벽을 설치함으로써 하천의 유수에 의한 침식을 방지할 수 있으며, 식생 기반재의 역할을 하게 되어 식생이 가능함에 따라 우기시 수생식물 및 어패류의 생식이 가능해지고 건기시 호안의 녹화를 유도할 수 있어 보다 자연 친화적인 호안 보호공을 조성할 수 있다.In addition, by installing a texol retaining wall in the width of 10 ~ 20cm depending on the height of the soil fillet on the back of the coconut vegetation mat 70 on the front of the wall can prevent the erosion by the flow of the river, and serves as a vegetation base material As vegetation is possible, aquatic plants and shellfish can be reproduced during the rainy season, and the greening of the shoreline during the dry season can lead to the creation of more natural friendly shore protection.

종래의 호안보호공이 가지는 구조적인 불안정성을 본 발명에서는 목재말뚝(10) 및 가로목재봉(20)에 보강스트립(40,50)을 연결시켜 마찰 저항력을 이용한 보강토 옹벽의 구조계념을 도입함으로써 벽체의 변위를 최소화하고 일체화된 구조물을 조성할 수 있어 외력에 대한 저항력이 큰 구조적으로 안정한 호안 보호 구조물을 조성할 수 있는 효과가 있는 것이다.In the present invention, the structural instability of the revetment protector by connecting the reinforcing strips (40, 50) to the wooden pile (10) and the horizontal wood rod (20) by introducing the structural concept of the reinforced soil retaining wall using frictional resistance of the wall Minimize the displacement and create an integrated structure has the effect of creating a structurally stable shore protection structure with high resistance to external forces.

Claims (3)

하천 호안 보호공을 설치하기 위한 부지정리의 단계와;Site clean-up for installing river shelter protectors; 하천 호안에 메인 말뚝인 목재말뚝(10)을 일정간격으로 설치하는 단계와;Installing a wooden pile (10) which is a main pile in a river lake at regular intervals; 상기 목재말뚝(10)의 내측면에 가로목재봉(20)을 볼트로 접합 설치하되, 가로복재봉(20)을 한 단의 높이를 고려하여 일정간격으로 설치하는 단계와;Installing a horizontal wood rod 20 on the inner side of the wood pile 10 with bolts, and installing the horizontal wood rod 20 at a predetermined interval in consideration of the height of one end; 상기 목재말뚝(10)과의 사이에 세로목재봉(30)을 일정간격으로 설치하는 단계와;Installing the longitudinal wood rods 30 at regular intervals between the wood piles 10; 상기 세로목재봉(30)의 전면부에 코코넛 식생매트(100)와 텍솔옹벽(70)을 성토재 침식방지와 식생기반재 역할을 하도록 설치하는 단계와;Installing the coconut vegetation mat 100 and the texol retaining wall 70 on the front surface of the longitudinal wood rod 30 to prevent soil erosion and serve as a vegetation base material; 철근에 부식방지를 위하여 용융아연도금을 하여 제작하고, 일정간격으로 마찰저항바(60)를 용접하여 접합함으로써 각각의 마찰저항바(60)에서 발휘되는 마찰 저항력이 외력에 의한 벽체의 변형을 최소화할 수 있도록 된 보강스트립(40, 50)을 상기 목재말뚝(10) 및 가로목재봉(20)에 각각 연결 설치하는 단계와; It is manufactured by hot-dip galvanizing to prevent corrosion of reinforcing bars, and by welding the frictional resistance bar 60 at regular intervals and joining them, the frictional resistance exerted by each frictional resistance bar 60 minimizes the deformation of walls caused by external force. Connecting the reinforcing strips 40 and 50 so as to be connected to the wood piles 10 and the horizontal wood rods 20; 다짐기로 하천 호안에 뒤채움 다짐을 하는 단계로 이루어지는 하천 호안 보호공의 시공방법.A method for constructing a river shelter protector, comprising a step of backfilling a river lag with a compactor. 제1항에 있어서, 상기 목재말뚝(10)은, 목재말뚝(10)의 크기보다 약 20mm정도 더 큰 철재 파이프를 이용하여 일정 깊이까지 항타기로 항타시켜 형성된 구멍에 상기 목재말뚝(10)을 삽입 설치하는 것을 특징으로 하는 하천 호안 보호공의 시공 방법.According to claim 1, The wood pile 10, Using the steel pipe about 20mm larger than the size of the wood pile 10, the wood pile 10 is inserted into the hole formed by driving to a certain depth The construction method of the river raft protector which installs. 제1항에 있어서, 상기 세로목재봉(20)의 전면부의 식생은 상기 코코넛 식생매트(100)를 전면 포설하는 단계와, 일정 높이의 배면 성토 층다짐 높이에 따라서 10~20cm의 폭으로 텍솔옹벽(70)을 설치하는 단계로 이루어진 것을 특징으로 하는 하천 호안 보호공의 시공 방법.According to claim 1, The vegetation of the front portion of the longitudinal wood rod 20 is the front step of laying the coconut vegetation vegetation mat 100, the texsol retaining wall in a width of 10 ~ 20cm depending on the height of the back fill layer of a certain height Construction method of the river raft protector, characterized in that consisting of the step of installing (70).
KR1020050081709A 2005-09-02 2005-09-02 Construction method of shore protector using reinforcing strip KR100662011B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050081709A KR100662011B1 (en) 2005-09-02 2005-09-02 Construction method of shore protector using reinforcing strip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050081709A KR100662011B1 (en) 2005-09-02 2005-09-02 Construction method of shore protector using reinforcing strip

Publications (1)

Publication Number Publication Date
KR100662011B1 true KR100662011B1 (en) 2006-12-28

Family

ID=37815748

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050081709A KR100662011B1 (en) 2005-09-02 2005-09-02 Construction method of shore protector using reinforcing strip

Country Status (1)

Country Link
KR (1) KR100662011B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102484636B1 (en) * 2021-09-08 2023-01-03 이계일 Retain wall structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102484636B1 (en) * 2021-09-08 2023-01-03 이계일 Retain wall structure
WO2023038449A1 (en) * 2021-09-08 2023-03-16 이계일 Retaining wall structure

Similar Documents

Publication Publication Date Title
KR100818758B1 (en) Structure for establish mat of river slope
KR20080000156A (en) Construction method of shore block
CN212506156U (en) Anti-impact protection structure capable of being constructed quickly
JP4871645B2 (en) Drain structure and construction method of drain structure
CN210216318U (en) Ecological river course side slope protective structure
CN109056784B (en) Construction method of stable gabion retaining wall
KR100662011B1 (en) Construction method of shore protector using reinforcing strip
CN111622234A (en) Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process
JP2963654B2 (en) Ishiwari net revetment method
CN208857768U (en) A kind of protection slope structure being easily installed
Abdelgader et al. State-of-the-Art Report on fabric formwork
EP0343913A2 (en) Methods of construction
JP5097249B2 (en) Drain structure and construction method of drain structure
KR102294870B1 (en) Core wall structure of composite cassion for offshore runway
KR102138839B1 (en) Cast-in-place concrete blocks using large scales and revetment methods using them
JP3364432B2 (en) Stone retaining wall
US7670087B1 (en) Sheet piling wall having facade
KR101684340B1 (en) Scour protection system for shore and its installation methods
JP2007138564A (en) Drain structure and construction method of drain structure
CN219992335U (en) Flood control dike
CN217678877U (en) Fabricated support structure for dredging river course for drainage of waterlogging in coastal cities
CN214061687U (en) Flexible water-permeable cutting retaining wall
KR100458721B1 (en) Vegetation bank protection structures well-matched in nature environment and constructing method thereof
CN210857100U (en) Landscape type dike reinforcing structure
KR20140080597A (en) Precast fabric form for assembling in field, and method for constructing planted slope protection using the same

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120106

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee