JPS58204246A - Construction of reinforced concrete structure - Google Patents

Construction of reinforced concrete structure

Info

Publication number
JPS58204246A
JPS58204246A JP8839182A JP8839182A JPS58204246A JP S58204246 A JPS58204246 A JP S58204246A JP 8839182 A JP8839182 A JP 8839182A JP 8839182 A JP8839182 A JP 8839182A JP S58204246 A JPS58204246 A JP S58204246A
Authority
JP
Japan
Prior art keywords
reinforcing bars
steel
reinforced concrete
steel frame
steel frames
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP8839182A
Other languages
Japanese (ja)
Other versions
JPS645134B2 (en
Inventor
二階 盛
小島 雄
水原 研三
襄 藤居
恵二 氷見
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP8839182A priority Critical patent/JPS58204246A/en
Publication of JPS58204246A publication Critical patent/JPS58204246A/en
Publication of JPS645134B2 publication Critical patent/JPS645134B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 この発明は鉄骨鉄筋コンクリート構造物の施工法lこ関
するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a steel reinforced concrete structure.

従来鉄筋コンクリート構造あるいは鉄骨構造では地上で
所要の大きさに先組みしたものを現場で組立てることは
屡々実施されている。し力1し鉄骨、鉄筋コンクリート
構造物の場合鉄骨は先組しても鉄筋は建込んだ鉄骨周縁
に現場配筋しており、省力化、工期短縮等71)ら改讐
が要望された。
Conventionally, reinforced concrete or steel structures are often pre-assembled to the required size on the ground and then assembled on site. However, in the case of steel frames and reinforced concrete structures, even if the steel frames are pre-assembled, reinforcing bars are placed on-site around the erected steel frames, and improvements have been requested to save labor and shorten the construction period71).

この発明は鉄骨と鉄筋とを可能な限りプレハブ化して前
記要望lこ対処すべくしたもので、以下その詳細を図示
した実施例によって説明する。
This invention is intended to meet the above-mentioned demand by prefabricating the steel frames and reinforcing bars as much as possible, and details thereof will be explained below with reference to illustrated embodiments.

図においてH形鋼等力)らなる柱鉄骨1の周囲には主鉄
筋2およびフープ筋3を筆状をなすように先組しである
。その際鉄骨1を支持材とし、鉄骨1の周辺に保持杆4
を井桁状に組み、この保持杆4Iこ主鉄筋2を結束して
取付ける。
In the figure, main reinforcing bars 2 and hoop bars 3 are pre-assembled in a brush-like manner around a column steel frame 1 made of H-shaped steel. At that time, the steel frame 1 is used as a support material, and retaining rods 4 are placed around the steel frame 1.
The holding rods 4I and the main reinforcing bars 2 are tied together and attached.

以上のようにしてプレハブ化した鉄骨、鉄筋を同時に吊
上げ、先ず鉄骨1,1相互を連結板5を添わせハイテン
ションボルト締めして連結自立させた後、主鉄筋2相互
をガス圧接あるいはスクイズジヨイント等fこより接合
する。
The prefabricated steel frames and reinforcing bars are lifted at the same time as described above. First, the steel frames 1 and 1 are attached to each other with the connecting plates 5 and tightened with high tension bolts to make them independent. After that, the main reinforcing bars 2 are welded together by gas pressure welding or squeeze jig. Int etc. are joined together.

次いで柱型枠6を組立て一方向梁型枠7を組立て、かっ
梁床型枠8を組立てる。
Next, the column formwork 6 is assembled, the one-way beam formwork 7 is assembled, and the beam floor formwork 8 is assembled.

次いで柱コンクリートを打設し、プレハブ化した梁鉄筋
9を配筋し、かつ床鉄筋を配筋して梁、床コンクリート
を打設する。
Next, column concrete is placed, prefabricated beam reinforcing bars 9 are placed, floor reinforcing bars are placed, and beams and floor concrete are placed.

第4図は他の実施例を示したもので柱鉄骨1と一方の梁
鉄骨10を一体的に結合しておき、柱鉄骨1には主鉄筋
2およびフープ筋を蹄状をなすように先組しておくとと
もに梁鉄骨10にも梁上鉄筋12およびスターラップ1
3を蹄状をなすよう番こ先組しておき、同時に吊上げる
Fig. 4 shows another embodiment, in which a column steel frame 1 and one beam steel frame 10 are integrally connected, and the main reinforcing bars 2 and hoop reinforcements are attached to the column steel frame 1 so as to form a hoof shape. In addition to assembling, the beam reinforcement 12 and stirrup 1 are also attached to the beam steel frame 10.
Assemble the parts 3 in a hoof shape and lift them at the same time.

この場合他方向の梁は鉄筋コンクリート構造、鉄骨鉄筋
コンクリート構造の何れでもよい0また一方梁鉄骨は梁
型枠、床型枠の支保工として利用できる。
In this case, the beam in the other direction may have either a reinforced concrete structure or a steel-framed reinforced concrete structure.On the other hand, the beam steel can be used as a support for beam formwork and floor formwork.

第5図は梁鉄骨10を二方向とも柱鉄骨1と一体的番こ
結合しておき各社、梁の鉄筋も蹄状をなすように先組し
ておき同時に吊上げるなお第2、第3の実施例では柱、
梁、床コンクリートを同時に打設するがその他の施工手
順は最初の(3) バネルゾ・−ン部の配筋が簡略化され、あるいは現場作
業がなくなり、より施工が容易である。
Figure 5 shows that the beam steel frame 10 is integrally joined to the column steel frame 1 in both directions, and the reinforcing bars of the beam are also preassembled to form a hoof shape, and the second and third beams are hoisted at the same time. In the example, the pillar,
The beams and floor concrete are cast at the same time, but the rest of the construction procedure is the first step (3).The reinforcement in the vannel zone is simplified and there is no on-site work, making construction easier.

この発明は以上の構成よりなり、鉄骨鉄筋コンクリート
構造の施工1こ際して鉄骨と鉄筋が先組され可能な限り
プレハブ化されているので現場での省力化が著しく、ま
た鉄骨を自立させてから鉄筋を連結するので施工が安全
であり、またプレハブ化Eこよって精度が向上し、工期
が短縮し1作業能率が向上する。
This invention has the above-mentioned configuration, and when constructing a steel-framed reinforced concrete structure, the steel frames and reinforcing bars are pre-assembled and prefabricated as much as possible, resulting in significant labor savings on site. Construction is safe because the reinforcing bars are connected, and prefabrication improves accuracy, shortens the construction period, and improves work efficiency.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図、第2図は鉄骨、鉄筋の平面図と立面図、第3図
、第4図、第5図は施工状態の概要を示した斜視図、第
6図は鉄骨、鉄筋の斜視図である。 1・・鉄骨、2・・主鉄筋、3・・フープ筋。 4・・保持杆、5・・連結板、6・・柱型枠。 7・・梁型枠、8・・梁床型枠、9・・梁鉄筋。 10・・梁鉄骨、12・・梁上鉄筋、13・・スターラ
ップ 、4 ) 第 第 4 248− 3 コ7−77
Figures 1 and 2 are plan and elevation views of the steel frame and reinforcing bars, Figures 3, 4, and 5 are perspective views showing an overview of the construction status, and Figure 6 is a perspective view of the steel frames and reinforcing bars. It is a diagram. 1. Steel frame, 2. Main reinforcement, 3. Hoop reinforcement. 4. Holding rod, 5. Connecting plate, 6. Column formwork. 7. Beam formwork, 8. Beam floor formwork, 9. Beam reinforcement. 10... Steel beam beam, 12... Rebar on beam, 13... Stirrup, 4) No. 4 248-3 Co7-77

Claims (2)

【特許請求の範囲】[Claims] (1)柱鉄骨と柱鉄筋とを、鉄骨を支持材とし。 その周囲に鉄筋を罎状をなすように先組し。 次いで前記鉄骨、鉄筋を同時に吊上げ、先ず鉄骨をボル
ト締めして連結自立させた後鉄筋を接続することを特徴
とする鉄骨、鉄筋コンクリート構造物の施工法。
(1) Column steel frame and column reinforcing bar, with the steel frame as the supporting material. Pre-assemble the reinforcing bars around it in a circular shape. A method of constructing a steel frame or reinforced concrete structure, characterized in that the steel frame and the reinforcing bars are then lifted simultaneously, and the steel frames are first tightened with bolts to make them independent and then the reinforcing bars are connected.
(2)柱鉄骨と一方向または二方向の梁鉄骨とを一体と
し、それら鉄骨と鉄筋とを、鉄骨を支持材とし、その周
囲に鉄筋を筆状をなすように先組し1次いで前記鉄骨、
鉄筋を同時Iこ吊上げ、先ず鉄骨をボルト締めして連結
自立させた後、鉄筋を接続することを特徴とする鉄骨、
鉄筋コンクリート構造物の施工法。
(2) Column steel frames and beam steel frames in one direction or two directions are integrated, and these steel frames and reinforcing bars are assembled in advance so that the steel frames are used as supporting materials and the reinforcing bars are formed around the steel frames in a brush shape. ,
A steel frame characterized in that the reinforcing bars are lifted simultaneously, the steel frames are first tightened with bolts to make the connection self-supporting, and then the reinforcing bars are connected.
Construction method for reinforced concrete structures.
JP8839182A 1982-05-25 1982-05-25 Construction of reinforced concrete structure Granted JPS58204246A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8839182A JPS58204246A (en) 1982-05-25 1982-05-25 Construction of reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8839182A JPS58204246A (en) 1982-05-25 1982-05-25 Construction of reinforced concrete structure

Publications (2)

Publication Number Publication Date
JPS58204246A true JPS58204246A (en) 1983-11-28
JPS645134B2 JPS645134B2 (en) 1989-01-27

Family

ID=13941492

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8839182A Granted JPS58204246A (en) 1982-05-25 1982-05-25 Construction of reinforced concrete structure

Country Status (1)

Country Link
JP (1) JPS58204246A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61158537A (en) * 1984-12-28 1986-07-18 東急建設株式会社 Building of iron skeletal
JPS62260931A (en) * 1986-05-07 1987-11-13 鹿島建設株式会社 Construction of reinforced concrete body

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4913914A (en) * 1972-05-18 1974-02-06
JPS5238331A (en) * 1975-09-23 1977-03-24 Nippon Beet Sugar Mfg Attitude control device for farm machinery

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4913914A (en) * 1972-05-18 1974-02-06
JPS5238331A (en) * 1975-09-23 1977-03-24 Nippon Beet Sugar Mfg Attitude control device for farm machinery

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61158537A (en) * 1984-12-28 1986-07-18 東急建設株式会社 Building of iron skeletal
JPH0414218B2 (en) * 1984-12-28 1992-03-12 Tokyu Kensetsu Kk
JPS62260931A (en) * 1986-05-07 1987-11-13 鹿島建設株式会社 Construction of reinforced concrete body

Also Published As

Publication number Publication date
JPS645134B2 (en) 1989-01-27

Similar Documents

Publication Publication Date Title
JPS58204246A (en) Construction of reinforced concrete structure
JPS62178634A (en) Framework construction method of structure
JP2001020376A (en) Sc beam construction method for building
JP2000265548A (en) Structure of joining part of column and beam and construction method for frame
JP2506294Y2 (en) Structure of column / beam connection
JPH0460183B2 (en)
JPH0118229B2 (en)
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPH044091Y2 (en)
JPH0546561Y2 (en)
JPH03151429A (en) Reinforcement preassembled beam with formwork and working method thereof
JPH0213694B2 (en)
JPH0830360B2 (en) Connection method for columns and beams
JPH0528815U (en) Precast steel reinforced concrete columns
JPS6110682A (en) Construction of reinforced concrete building
JP2723011B2 (en) Construction method of steel frame reinforced concrete structure
JPH02236328A (en) Construction method for super-highrice building
JP2556757B2 (en) Reinforcement structure of column / beam connection and its construction method
JPH06306951A (en) Frame for multistoried building
JPH0410954B2 (en)
JPS62121249A (en) Construction of pillar/beam connection part
JPH093914A (en) Structure of underground beam and underground beam construction method
JPH04309630A (en) Skeleton construction method using pc member
JPS61250240A (en) Connection of pc pillar and beam
JPH1068133A (en) Construction method of foundation structure in lightweight building