JPS56142921A - Construction work of foundation of structure - Google Patents

Construction work of foundation of structure

Info

Publication number
JPS56142921A
JPS56142921A JP4279280A JP4279280A JPS56142921A JP S56142921 A JPS56142921 A JP S56142921A JP 4279280 A JP4279280 A JP 4279280A JP 4279280 A JP4279280 A JP 4279280A JP S56142921 A JPS56142921 A JP S56142921A
Authority
JP
Japan
Prior art keywords
steel pipe
iron bar
bar cage
end portion
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4279280A
Other languages
Japanese (ja)
Inventor
Yoshio Wakamei
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP4279280A priority Critical patent/JPS56142921A/en
Publication of JPS56142921A publication Critical patent/JPS56142921A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE: To eliminate vibration and noise resulting form the breaking of excess long portion, simplify construction work, and shorten the period of construction by attaching a steel pipe to the periphery of an iron bar cage in such a way as to project the end portion of the iron bar cage from the steel pipe.
CONSTITUTION: A steel pipe 2 is welded (w) to the inner or outer surface of an iron bar cage 1 in such a way as to project the end portion of the iron bar cage 1 from the end of the steel pipe 2 to form the iron bar cage 1 with the steel pipe 2. Mud water 4 is filled in a bored pit 3 and then the iron bar cage 1 with the steel pipe 2 is inserted into the bored bit 3. In this case, the footing bottom A-A is positioned at the upper end portion in the longitudinal direction of the steel pipe 2. Then, concrete 5 is placed up to the footing bottom A-A to construct concrete pile B, where slime mixed concrete 5' stagnates at the top of the pile B. Then, footing work is conducted, base concrete is placed on the in-site placed concrete pile B, and the steep pipe 2 and the end portion of the iron bar cage 1 are anchored.
COPYRIGHT: (C)1981,JPO&Japio
JP4279280A 1980-04-03 1980-04-03 Construction work of foundation of structure Pending JPS56142921A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4279280A JPS56142921A (en) 1980-04-03 1980-04-03 Construction work of foundation of structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4279280A JPS56142921A (en) 1980-04-03 1980-04-03 Construction work of foundation of structure

Publications (1)

Publication Number Publication Date
JPS56142921A true JPS56142921A (en) 1981-11-07

Family

ID=12645805

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4279280A Pending JPS56142921A (en) 1980-04-03 1980-04-03 Construction work of foundation of structure

Country Status (1)

Country Link
JP (1) JPS56142921A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013221369A (en) * 2012-04-19 2013-10-28 Japan Pile Corp Cast-in-place steel pipe concrete pile and steel pipe therefor
JP2017172328A (en) * 2017-07-10 2017-09-28 ジャパンパイル株式会社 Cast-in-place steel pipe concrete pile and steel pipe thereof
CN107905221A (en) * 2017-11-28 2018-04-13 重庆建工集团股份有限公司 A kind of method for being accurately positioned percussive drilling bored concrete pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013221369A (en) * 2012-04-19 2013-10-28 Japan Pile Corp Cast-in-place steel pipe concrete pile and steel pipe therefor
JP2017172328A (en) * 2017-07-10 2017-09-28 ジャパンパイル株式会社 Cast-in-place steel pipe concrete pile and steel pipe thereof
CN107905221A (en) * 2017-11-28 2018-04-13 重庆建工集团股份有限公司 A kind of method for being accurately positioned percussive drilling bored concrete pile

Similar Documents

Publication Publication Date Title
NO892896L (en) DEVICABLE OIL EQUIPMENT DEVICE.
DE3462348D1 (en) Retaining wall for earth and similar materials
JPS56142921A (en) Construction work of foundation of structure
JPS5771923A (en) Construction work of continuous underground wall
GB2070668B (en) Auger drill for the manufacturing of concrete foundation piles
JPS56128808A (en) Depositing method of concrete in water
JPS56142922A (en) Treatment of top of in-place concrete pile
JPS5792217A (en) Preventing device for settling of reinforced concrete pile cast in site
JPS5768415A (en) Ground improving method
JPS5761111A (en) Reduction of extra-banking concrete for head of pile driven in situ
SU755956A1 (en) Foundation for column
JPS57108324A (en) Construction of concrete foundation
JPS5648413A (en) Harbor structure such as quay wall on a cement blended foundation and construction method thereof
JPS641829A (en) Construction foundation
HU187453B (en) Apparatus for stabilizing against floating up construction being under water table, particularly reinforced concrete engineering structure and method for producing the structure
JPS5664030A (en) Placement of soil-sheathing fence
JPS5631941A (en) Building of underground storage tank
JPS56156328A (en) Construction of underground storage tank
JPS56105016A (en) Executing method for reinforced foundation pile and reinforcing steel pipe
JPS57143016A (en) Construction of retaining wall built with hoop steel acting as guide
JPS5736212A (en) Construction of in-situ foundation pile
JPS5670322A (en) Construction of underground wall by column strip
JPS5751331A (en) Construction of continuous underground wall
JPS5530058A (en) Process for piling into big bore
JPS56135627A (en) Construction of foundation pile