JPS5595718A - Setting method for steel wire cylinder, sheet pile etc. - Google Patents
Setting method for steel wire cylinder, sheet pile etc.Info
- Publication number
- JPS5595718A JPS5595718A JP367979A JP367979A JPS5595718A JP S5595718 A JPS5595718 A JP S5595718A JP 367979 A JP367979 A JP 367979A JP 367979 A JP367979 A JP 367979A JP S5595718 A JPS5595718 A JP S5595718A
- Authority
- JP
- Japan
- Prior art keywords
- steel wire
- cylinder
- wire cylinder
- guide rails
- digged
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
PURPOSE: To set a steel wire cylinder or sheet pile along guide rails without bringing it into contact with a bored wall surface, by locating vertically the guide rails in a excavated trench or bored hole after sliming the trench or the hole.
CONSTITUTION: After sliming an excavated trench 1, guide rails 2 such as shape steels or sheet piles are set vertically along both digged wall surfaces by means of a crane or the like. In the case of, for example, a steel wire cylinder 3 being set, the steel wire cylinder 3 is placed such that the cylinder is supported vertically, keeping a given distance between the cylinder and the digged wall surface with the guide rails 2 guiding and serving as a spacer between the cylinder 3 and the digged wall surface. A hair-pin member 5 is placed on a ground surface at an upper portion of the steel wire cylinder so that an erecting condition of the steel wire cylinder 3 can be maintained, the guide rails 2 being then pulled off by means of a crane or the like. This prevents the steel wire cylinder 3 from being brought into contact with the digged wall surface, and thus, various effects can be obtained.
COPYRIGHT: (C)1980,JPO&Japio
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP367979A JPS5595718A (en) | 1979-01-16 | 1979-01-16 | Setting method for steel wire cylinder, sheet pile etc. |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP367979A JPS5595718A (en) | 1979-01-16 | 1979-01-16 | Setting method for steel wire cylinder, sheet pile etc. |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS5595718A true JPS5595718A (en) | 1980-07-21 |
Family
ID=11564091
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP367979A Pending JPS5595718A (en) | 1979-01-16 | 1979-01-16 | Setting method for steel wire cylinder, sheet pile etc. |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5595718A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105862893A (en) * | 2016-04-07 | 2016-08-17 | 中国十七冶集团有限公司 | Conveying device for concrete filter tubes in well dewatering |
-
1979
- 1979-01-16 JP JP367979A patent/JPS5595718A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105862893A (en) * | 2016-04-07 | 2016-08-17 | 中国十七冶集团有限公司 | Conveying device for concrete filter tubes in well dewatering |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS5595718A (en) | Setting method for steel wire cylinder, sheet pile etc. | |
JPS55114717A (en) | Combination method of support and foundation | |
JPS5721623A (en) | Treatment work for top of pile | |
JPS55119822A (en) | Method for reinforcing bearing capacity of concrete pile and reinforcing member thereof | |
JPS5275010A (en) | Apparatus which has driving hammer and pipe for forming concrete or compressed concrete pile in excavated hole of ground and executing method using same | |
JPS5568918A (en) | Steel sheet pile | |
JPS5536147A (en) | Method of constructing structure on sea-surface | |
ES461825A1 (en) | Method of driving piles underwater | |
JPS5771931A (en) | Soil sheathing work | |
JPS5646031A (en) | Constructing method for pile foundation footing with erected trunk | |
JPS5789027A (en) | Multipillar type foundation construction method | |
JPS5532809A (en) | Pile foundation practice | |
JPS5257491A (en) | Pipe arrangement penetration | |
JPS51138914A (en) | Method of construction of an underground tank for liquid natural gas | |
JPS55114715A (en) | Method for construction of steel pipe sheet pile well foundation | |
JPS57108326A (en) | Construction of pile foundation with underground wall | |
JPS57130622A (en) | Construction of continuous underground wall | |
JPS5338101A (en) | Method of excavating inside of steel pipe pile | |
JPS5622815A (en) | Construction method of continuous earth wall | |
JPS5595712A (en) | Shoring wall by concrete | |
JPS5724728A (en) | Sheathing method and waling structure for use in said method | |
JPS5686886A (en) | Fixing method of plant barge onto foundation piles | |
JPS52107107A (en) | Method of and apparatus for reinforcing soil at lower end of pile foundation | |
JPS5585738A (en) | Driving method for ground beam | |
JPS56122433A (en) | Laying work of pipe |