JPH11270127A JP9853698A JP9853698A JPH11270127A JP H11270127 A JPH11270127 A JP H11270127A JP 9853698 A JP9853698 A JP 9853698A JP 9853698 A JP9853698 A JP 9853698A JP H11270127 A JPH11270127 A JP H11270127A
Authority
JP
Japan
Prior art keywords
vertical frame
frame pipe
scaffold
cylinder member
jack base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP9853698A
Other languages
Japanese (ja)
Inventor
Atsushi Ishikawa
淳 石川
Koji Sasaki
孝治 佐々木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Forestry Co Ltd
Original Assignee
Sumitomo Forestry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Forestry Co Ltd filed Critical Sumitomo Forestry Co Ltd
Priority to JP9853698A priority Critical patent/JPH11270127A/en
Publication of JPH11270127A publication Critical patent/JPH11270127A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

PROBLEM TO BE SOLVED: To easily detach a jack base mounted on a roof of a building. SOLUTION: A connecting foul 11 for a scaffold leg part comprises a nearly hollow cylindrical connecting member constituted by a steel pipe, lightweight aluminum pipe, or the like, and the upper end of the connecting member is provided with a fitting projection 12 for fitting into the lower end of a vertical frame pipe 4 constituting a scaffold and for connecting both of them. The lower end 13 of the connecting tool 11 is abutted on the upper surface of a height adjusting support cylinder 7 screwed in the male screw part 6 of a jack base 5.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、主として木造住宅
の外廻り、特に下屋に使用される足場脚部用連結具に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a connecting device for a scaffolding leg used mainly for the outer periphery of a wooden house, particularly for a shed.

【0002】[0002]

【従来の技術】木造住宅では、和室に続く広縁や廊下部
分などを二階のない平屋とすることがある。このような
平屋部分は下屋と呼ばれているが、下屋のない総二階形
式の住宅では、地面に足場を立設して二階大屋根の軒先
廻りを施工することができるのに対し、下屋のある住宅
では、下屋の奥行きの分だけ足場が二階大屋根の軒先か
ら離れてしまい、作業の安全を十分確保することが困難
となる。
2. Description of the Related Art In a wooden house, a one-story house without a second floor is sometimes used as a wide margin or corridor following a Japanese-style room. Such a one-story building is called a lower house, but in a total two-story house without a lower house, a scaffold can be erected on the ground and the area around the eaves with a large two-story roof can be constructed. In a house with a shed, the scaffold separates from the eaves on the large roof with the depth of the shed, making it difficult to ensure sufficient work safety.

【0003】そのため、下屋のある場合には、図9に示
すように、未だ下地の状態である下屋の屋根1に足場2
を立設して二階大屋根3の瓦を葺いた後、該足場をいっ
たんばらして屋根1の瓦を葺き、しかる後に該瓦の上に
再度足場2を立設して二階大屋根3の軒先廻りを施工す
るのが一般的である。
[0003] Therefore, when there is a scaffold, as shown in FIG.
And the roof of the second-floor large roof 3 is laid, and then the scaffold is once loosened and the roof 1 of the roof is tiled. It is common to construct the surroundings.

【0004】[0004]

【発明が解決しようとする課題】ここで、足場2の解体
を行う際、下屋の屋根1に載っている足場2の脚部であ
るジャッキベースを取り外す必要があるが、ジャッキベ
ースは、通常、足場2を構成する縦枠パイプの内部に嵌
め込んである。
When the scaffold 2 is dismantled, it is necessary to remove the jack base, which is the leg of the scaffold 2 placed on the roof 1 of the shed. , Is fitted inside the vertical frame pipe constituting the scaffold 2.

【0005】そのため、ジャッキベースを取り外すに
は、図10に示すように、足場2の縦枠パイプ4を持ち
上げる必要があるが、足場2は、建物周囲を取り囲む他
の足場とともに水平方向に側方連結されているため、該
足場の縦枠パイプ4だけを持ち上げるのは容易ではな
い。したがって、足場2のみならず、それに側方連結さ
れた足場も一緒に持ち上げるか、それが不可能であれば
足場2やそれに側方連結された足場をいったん解体せざ
るを得ず、いずれにしろ、下屋の屋根1に載っているジ
ャッキベース5を取り外すのに多数の作業員と手間が必
要になるという問題を生じていた。そして、かかる事態
は、下屋の屋根1にジャッキベース5を載せて足場2を
再度立設する際にも同様に生じる。
[0005] Therefore, to remove the jack base, it is necessary to lift the vertical frame pipe 4 of the scaffold 2 as shown in FIG. 10, but the scaffold 2 is horizontally moved along with other scaffolds surrounding the building. Because of the connection, it is not easy to lift only the vertical frame pipe 4 of the scaffold. Therefore, not only the scaffold 2 but also the scaffold laterally connected thereto must be lifted together, or if it is not possible, the scaffold 2 or the scaffold laterally connected thereto must be dismantled once. However, there has been a problem that a large number of workers and labor are required to remove the jack base 5 placed on the roof 1 of the shed. Such a situation also occurs when the jack base 5 is placed on the roof 1 of the shed and the scaffold 2 is erected again.

【0006】本発明は、上述した事情を考慮してなされ
たもので、下屋の屋根に載っているジャッキベースを容
易に着脱可能な足場脚部用連結具を提供することを目的
とする。
The present invention has been made in view of the above circumstances, and has as its object to provide a scaffolding leg connecting device capable of easily removing a jack base mounted on a roof of a shed.

【0007】[0007]

【課題を解決するための手段】上記目的を達成するた
め、本発明に係る足場脚部用連結具は請求項1に記載し
たように、足場を構成する縦枠パイプの下端に上端にて
連結されジャッキベースの雄ねじ部に螺合された高さ調
整用支持筒の上面に下端にて当接されるように構成され
た接続部材からなるものである。
In order to achieve the above object, a connecting device for a scaffold leg according to the present invention is connected to a lower end of a vertical frame pipe constituting a scaffold at an upper end. And a connecting member configured to abut on the upper surface of the height adjusting support cylinder screwed to the male screw portion of the jack base at the lower end.

【0008】また、本発明に係る足場脚部用連結具は、
前記接続部材の上端を前記縦枠パイプの下端に嵌め込む
ように構成したものである。
The scaffolding leg connecting device according to the present invention comprises:
The upper end of the connecting member is fitted to the lower end of the vertical frame pipe.

【0009】また、本発明に係る足場脚部用連結具は請
求項3に記載したように、足場を構成する縦枠パイプの
下端に上端にて当接されジャッキベースの雄ねじ部に螺
合された高さ調整用支持筒の上面に下端にて当接される
内筒部材と、前記縦枠パイプ及び前記内筒部材が嵌め込
まれる外筒部材とから構成するとともに、該外筒部材を
前記縦枠パイプと前記内筒部材との当接位置近傍で保持
自在にかつ該当接位置近傍が露出されるように昇降自在
に構成したものである。
Further, as described in claim 3, the scaffold leg connecting device according to the present invention is in contact with the lower end of the vertical frame pipe constituting the scaffold at the upper end and screwed into the male screw portion of the jack base. The vertical cylinder pipe and the outer cylinder member into which the inner cylinder member is fitted, the inner cylinder member being in contact with the upper surface of the height adjustment support cylinder at the lower end, and the outer cylinder member is vertically The frame pipe is configured so as to be freely held near a contact position between the frame pipe and the inner cylinder member and to be able to move up and down so that the vicinity of the contact position is exposed.

【0010】また、本発明に係る足場脚部用連結具は、
前記外筒部材を前記縦枠パイプと前記内筒部材との当接
位置近傍で保持するための係止機構を設けたものであ
る。
[0010] Also, the scaffold leg connecting tool according to the present invention comprises:
A locking mechanism is provided for holding the outer cylindrical member near a contact position between the vertical frame pipe and the inner cylindrical member.

【0011】また、本発明に係る足場脚部用連結具は、
前記外筒部材を所定の伸縮機構を介して前記内筒部材に
連結したものである。
Further, the scaffold leg connecting device according to the present invention comprises:
The outer cylinder member is connected to the inner cylinder member via a predetermined telescopic mechanism.

【0012】本発明に係る足場脚部用連結具において
は、通常時は、縦枠パイプからの荷重が接続部材を介し
てジャッキベースに伝達されているが、該ジャッキベー
スを取り外したい場合には、ジャッキベースの雄ねじ部
に螺合された高さ調整用支持筒を廻して該支持筒を下げ
るとともに、接続部材の上端と縦枠パイプの下端との連
結を必要に応じて解除しておく。
In the connecting device for a scaffold leg according to the present invention, the load from the vertical frame pipe is normally transmitted to the jack base via the connecting member, but when the jack base is to be removed, Then, the support cylinder for height adjustment screwed to the male screw portion of the jack base is turned to lower the support cylinder, and the connection between the upper end of the connection member and the lower end of the vertical frame pipe is released as necessary.

【0013】このようにすると、高さ調整用支持筒を下
げた分だけ接続部材を下げることができるので、接続部
材の上端と縦枠パイプの下端との間に隙間ができるまで
高さ調整用支持筒を廻して該支持筒を下げ、しかる後に
ジャッキベースを接続部材とともに側方にずらして足場
から撤去する。
With this configuration, the connecting member can be lowered by an amount corresponding to the lowering of the height adjusting support cylinder, so that a height adjusting member is formed until a gap is formed between the upper end of the connecting member and the lower end of the vertical frame pipe. The support tube is turned to lower the support tube, and then the jack base is laterally shifted together with the connecting member and removed from the scaffold.

【0014】ジャッキベースを再設置したい場合には、
高さ調整用支持筒及び接続部材を十分に下げた状態で側
方から縦枠パイプの直下に入れ込み、次いで、高さ調整
用支持筒を逆方向に廻しながら支持部材を上げ、その上
端を縦枠パイプの下端に連結する。
If you want to re-install the jack base,
With the support tube for height adjustment and the connection member sufficiently lowered, insert the tube directly below the vertical frame pipe from the side, then raise the support member while turning the support tube for height adjustment in the opposite direction, and raise the upper end vertically. Connect to the lower end of the frame pipe.

【0015】接続部材の構造や形状は任意であるが、一
例としてジャッキベースの雄ねじ部を挿入できる内径を
有する円筒体で構成することができる。
Although the structure and shape of the connecting member are arbitrary, as an example, the connecting member can be constituted by a cylindrical body having an inside diameter into which the male screw portion of the jack base can be inserted.

【0016】接続部材の上端と縦枠パイプの下端とをど
のように連結するかについても任意であり、縦枠パイプ
からの荷重を接続部材で支持しかつ両者の横ずれが防止
できるのであればどのような連結方法でもよい。例え
ば、接続部材の上端を縦枠パイプの下端にねじ込む方法
も考えられるが、かかる接続部材の上端を縦枠パイプの
下端に嵌め込むように構成したならば、高さ調整用支持
筒の昇降操作に伴って接続部材も自ずと昇降するので、
縦枠パイプと接続部材との連結をわざわざ外す必要がな
くなる。
The connection between the upper end of the connecting member and the lower end of the vertical frame pipe is also optional. If the load from the vertical frame pipe is supported by the connecting member and both sides can be prevented from laterally displacing, Such a connection method may be used. For example, a method of screwing the upper end of the connecting member into the lower end of the vertical frame pipe is also conceivable. However, if the upper end of the connecting member is configured to be fitted into the lower end of the vertical frame pipe, the lifting and lowering operation of the height adjustment support cylinder is performed. As the connection member also rises and falls naturally with
There is no need to remove the connection between the vertical frame pipe and the connecting member.

【0017】また、本発明に係る足場脚部用連結具にお
いては、通常時は、縦枠パイプからの荷重が内筒部材を
介してジャッキベースに伝達されるとともに、縦枠パイ
プ及び内筒部材の当接位置近傍に保持された外筒部材に
よって両者の横ずれが防止される。
In the scaffold leg connecting device according to the present invention, the load from the vertical frame pipe is normally transmitted to the jack base via the internal cylinder member, and the vertical frame pipe and the internal cylinder member are normally used. The lateral displacement between the two is prevented by the outer cylinder member held in the vicinity of the contact position.

【0018】一方、ジャッキベースを取り外したい場合
には、縦枠パイプと内筒部材との当接位置近傍が露出す
るように外筒部材の保持位置を上若しくは下にずらして
待避させる。そして、必要に応じてジャッキベースの雄
ねじ部に螺合された高さ調整用支持筒を若干廻してこれ
を下げる。
On the other hand, when it is desired to remove the jack base, the holding position of the outer cylinder member is shifted upward or downward so that the vicinity of the contact position between the vertical frame pipe and the inner cylinder member is exposed and retracted. Then, if necessary, the height adjusting support cylinder screwed into the male screw portion of the jack base is slightly turned to lower it.

【0019】このようにすると、縦枠パイプの下端と内
筒部材の上端との間に隙間が生じるとともに、外筒部材
が待避位置にずらされた状態となるので、かかる状態に
てジャッキベースを内筒部材、場合によってはさらに外
筒部材とともに側方にずらして足場から撤去する。
With this arrangement, a gap is formed between the lower end of the vertical frame pipe and the upper end of the inner cylinder member, and the outer cylinder member is shifted to the retracted position. The inner cylinder member and, if necessary, the outer cylinder member are shifted to the side and removed from the scaffold.

【0020】ジャッキベースを再設置したい場合には、
高さ調整用支持筒及び内筒部材を必要に応じて若干下げ
た状態で側方から縦枠パイプの直下に入れ込み、次い
で、外筒部材の内部に縦枠パイプ及び内筒部材が嵌め込
まれるようにして外筒部材を保持位置に戻す。そして、
必要に応じて高さ調整用支持筒を逆方向に若干廻して内
筒部材の上端を縦枠パイプの下端に当接させる。
If you want to re-install the jack base,
The support tube for height adjustment and the inner tube member are inserted slightly below the vertical frame pipe from the side while being slightly lowered as necessary, and then the vertical frame pipe and the inner tube member are fitted inside the outer tube member. To return the outer cylinder member to the holding position. And
If necessary, the height adjustment support cylinder is slightly rotated in the reverse direction to bring the upper end of the inner cylinder member into contact with the lower end of the vertical frame pipe.

【0021】内筒部材や外筒部材の構造や形状は任意で
あるが、一例としてジャッキベースの雄ねじ部を挿入で
きる内径を有する円筒体で内筒部材を構成するととも
に、該内筒部材の外径を内径とする円筒体で外筒部材を
構成することができる。
The structure and shape of the inner and outer cylinder members are arbitrary. For example, the inner cylinder member is formed of a cylindrical body having an inner diameter into which the male screw portion of the jack base can be inserted, and the outer cylinder member has an outer shape. The outer cylinder member can be composed of a cylindrical body having an inner diameter.

【0022】外筒部材を、縦枠パイプと内筒部材との当
接位置近傍でどのように保持するかかあるいはかかる保
持を解除してどのように昇降させるかは任意であり、例
えば外筒部材を内筒部材及び縦枠パイプに螺合させるよ
うに構成しておけば、外筒部材を廻してその高さ位置を
調整することによって保持並びに昇降が可能となるが、
かかる外筒部材を縦枠パイプと内筒部材との当接位置近
傍で保持するための係止機構を設けたならば、かかる係
止機構を係止状態と解除状態との間で切り替えることに
より、当接位置近傍での保持並びに昇降による待避を迅
速に行うことが可能となる。係止機構としては、例えば
外筒部材及び内筒部材を貫通するピンを引抜き自在に差
し込む、内筒部材の周面に設けられた飛出し凸部を外筒
部材の嵌込み孔に嵌め込むなどの機構が考えられる。
It is optional how the outer cylinder member is held in the vicinity of the contact position between the vertical pipe and the inner cylinder member, or how the outer cylinder member is released and held up and down. If the member is configured to be screwed into the inner cylinder member and the vertical frame pipe, holding and lifting can be performed by turning the outer cylinder member and adjusting its height position,
If a locking mechanism for holding such an outer cylinder member in the vicinity of the contact position between the vertical frame pipe and the inner cylinder member is provided, by switching the locking mechanism between a locked state and a released state, In addition, it is possible to quickly perform holding in the vicinity of the contact position and evacuation by elevating. As the locking mechanism, for example, a pin that penetrates the outer cylinder member and the inner cylinder member is removably inserted, and a protruding projection provided on the peripheral surface of the inner cylinder member is fitted into a fitting hole of the outer cylinder member. Mechanism is considered.

【0023】また、かかる係止機構に代えて外筒部材を
所定の伸縮機構を介して内筒部材に連結したならば、該
伸縮機構に抵抗するようにして外筒部材を引き下ろすだ
けで内筒部材と縦枠パイプとの当接位置近傍を露出させ
てジャッキベースの撤去が可能となるとともに、ジャッ
キベースを縦枠パイプ直下に位置決めした状態で外筒部
材から手を離すだけで、該外筒部材が伸縮機構の作用で
上方に跳ね上がって縦枠パイプに嵌め込まれ、ジャッキ
ベースの再設置が可能となる。
Further, if the outer cylinder member is connected to the inner cylinder member via a predetermined expansion / contraction mechanism instead of the locking mechanism, the inner cylinder member is simply pulled down so as to resist the expansion / contraction mechanism. The jack base can be removed by exposing the vicinity of the contact position between the cylindrical member and the vertical frame pipe, and the jack base can be removed just by releasing the hand from the outer cylindrical member with the jack base positioned immediately below the vertical frame pipe. The cylinder member jumps upward by the action of the expansion and contraction mechanism and is fitted into the vertical frame pipe, so that the jack base can be reinstalled.

【0024】[0024]

【発明の実施の形態】以下、本発明に係る足場脚部用連
結具の実施の形態について、添付図面を参照して説明す
る。なお、従来技術と実質的に同一の部品等については
同一の符号を付してその説明を省略する。
BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of a scaffold leg connecting device according to the present invention will be described with reference to the accompanying drawings. It is to be noted that the same reference numerals are given to components and the like that are substantially the same as those in the conventional technology, and description thereof will be omitted.

【0025】(第1実施形態)図1は、本実施形態に係
る足場脚部用連結具11を縦枠パイプ4及びジャッキベ
ース5とともに示した全体斜視図である。同図でわかる
ように、本実施形態に係る足場脚部用連結具11は、鋼
管、軽量アルミパイプ等で構成されたほぼ中空円筒状の
接続部材からなり、該接続部材の上端には、足場を構成
する縦枠パイプ4の下端に嵌め込んで両者を連結するた
めの嵌合突起12を設けてあるとともに、その下端13
は、図2でよくわかるように、ジャッキベース5の雄ね
じ部6に螺合された高さ調整用支持筒7の上面に当接さ
れるように構成してある。
(First Embodiment) FIG. 1 is an overall perspective view showing a connecting device 11 for a scaffolding leg according to the present embodiment, together with a vertical frame pipe 4 and a jack base 5. As can be seen from the figure, the scaffold leg connecting tool 11 according to the present embodiment is composed of a substantially hollow cylindrical connecting member made of a steel pipe, a lightweight aluminum pipe, or the like. And a fitting projection 12 for fitting the lower end of the vertical frame pipe 4 to connect the two with each other.
As is well understood in FIG. 2, is configured to be in contact with the upper surface of the height adjustment support cylinder 7 screwed to the male screw portion 6 of the jack base 5.

【0026】本実施形態に係る足場脚部用連結具11に
おいては、通常時は、図2に示したように縦枠パイプ4
からの荷重が接続部材である足場脚部用連結具11を介
してジャッキベース5に伝達されるが、該ジャッキベー
スを取り外したい場合には、図3に示すようにジャッキ
ベース5の雄ねじ部6に螺合された高さ調整用支持筒7
を廻して該支持筒を下げる。
In the connecting device 11 for a scaffold leg according to the present embodiment, the vertical frame pipe 4 is normally used as shown in FIG.
Is transmitted to the jack base 5 via the connecting member 11 for a scaffolding leg, which is a connecting member. When the jack base is to be removed, as shown in FIG. Height adjusting support cylinder 7 screwed to
To lower the support cylinder.

【0027】このようにすると、高さ調整用支持筒7の
下降に伴って接続部材である足場脚部用連結具11の上
端に設けられた嵌合突起12が縦枠パイプ4の下端から
外れる。そして、高さ調整用支持筒7が下降した分だけ
足場脚部用連結具11が下がるので、足場脚部用連結具
11の上端と縦枠パイプ4の下端との間に隙間ができる
まで、すなわち図3のような状況になるまで高さ調整用
支持筒7を廻して該支持筒を下げ、しかる後にジャッキ
ベース5を足場脚部用連結具11とともに側方にずらし
て足場から撤去する。
In this way, the fitting projection 12 provided at the upper end of the connecting member 11 for a scaffolding leg, which is a connecting member, comes off from the lower end of the vertical frame pipe 4 as the height adjusting support cylinder 7 descends. . And since the connecting tool 11 for scaffolding legs is lowered by an amount corresponding to the lowering of the support cylinder 7 for height adjustment, until a gap is formed between the upper end of the connecting tool 11 for scaffolding legs and the lower end of the vertical pipe 4. That is, the height adjustment support cylinder 7 is turned to lower the support cylinder until the situation as shown in FIG. 3 is reached, and then the jack base 5 is laterally shifted together with the scaffolding leg connector 11 and removed from the scaffold.

【0028】一方、ジャッキベース5を再設置したい場
合には、高さ調整用支持筒7及び接続部材である足場脚
部用連結具11を十分に下げた状態で側方から縦枠パイ
プ4の直下に入れ込み、次いで、高さ調整用支持筒7を
逆方向に廻しながら足場脚部用連結具11を上げ、その
上端にある嵌合突起12を縦枠パイプ4の下端に嵌め込
んで連結する。
On the other hand, when it is desired to re-install the jack base 5, the vertical frame pipe 4 can be removed from the side with the height adjustment support cylinder 7 and the connecting member 11 for the scaffolding leg, which is a connecting member, sufficiently lowered. Then, the connecting member 11 for a scaffolding leg is raised while rotating the supporting tube 7 for height adjustment in the opposite direction, and the fitting protrusion 12 at the upper end thereof is fitted to the lower end of the vertical frame pipe 4 to be connected. .

【0029】以上説明したように、本実施形態に係る足
場脚部用連結具11によれば、縦枠パイプ4とジャッキ
ベース5との間に介在させる形で使用し、ジャッキベー
ス5の撤去時あるいは再設置時にはジャッキベース5の
高さ調整用支持筒7を下げることによって縦枠パイプ4
との連結を外すようにしたので、縦枠パイプ4ひいては
足場全体を多人数で持ち上げたり時間を費やして解体し
たりせずとも、ジャッキベース5の撤去や再設置を容易
に行うことが可能となる。
As described above, according to the scaffold leg connecting device 11 of the present embodiment, the connecting device 11 is used so as to be interposed between the vertical frame pipe 4 and the jack base 5 so that the jack base 5 can be removed. Alternatively, at the time of re-installation, the height adjusting support cylinder 7 of the jack base 5 is lowered so that the vertical frame pipe 4
The jack base 5 can be easily removed and re-installed without having to lift the vertical frame pipe 4 and thus the entire scaffold by many people or spend time dismantling it. Become.

【0030】また、本実施形態に係る足場脚部用連結具
11によれば、その上端に嵌合突起12を設けてこれを
縦枠パイプ4の下端に嵌め込むようにしたので、高さ調
整用支持筒7を昇降操作するだけで足場脚部用連結具1
1を縦枠パイプ4に連結したり該連結を外したりするこ
とが可能となる。
Further, according to the scaffold leg connector 11 according to the present embodiment, the fitting projection 12 is provided at the upper end thereof and is fitted to the lower end of the vertical frame pipe 4, so that the height can be adjusted. Just by moving the support cylinder 7 up and down, the scaffold leg connector 1
1 can be connected to or disconnected from the vertical frame pipe 4.

【0031】本実施形態では、足場脚部用連結具11の
適用対象を主として下屋の屋根1に載せられたジャッキ
ベース5としたが、地面に水平に設置されたジャッキベ
ースの撤去並びに再設置にも本発明を適用することがで
きることは言うまでもない。
In the present embodiment, the jack base 5 mounted on the roof 1 of the shed is mainly applied to the connecting device 11 for scaffolding legs, but the jack base horizontally installed on the ground is removed and reinstalled. Needless to say, the present invention can also be applied to the present invention.

【0032】(第2実施形態)次に、第2実施形態につ
いて説明する。なお、上述の実施形態と実質的に同一の
部品等については同一の符号を付してその説明を省略す
る。
(Second Embodiment) Next, a second embodiment will be described. In addition, the same reference numerals are given to components and the like that are substantially the same as those in the above-described embodiment, and description thereof is omitted.

【0033】図4は、本実施形態に係る足場脚部用連結
具21を縦枠パイプ4及びジャッキベース5とともに示
した分解斜視図である。同図でわかるように、本実施形
態に係る足場脚部用連結具21は、鋼管、軽量アルミパ
イプ等でそれぞれ構成されたほぼ中空円筒状の内筒部材
22及び外筒部材23から概ね構成してあり、内筒部材
22の下端24は、ジャッキベース5の雄ねじ部6に螺
合された高さ調整用支持筒7の上面に当接されるように
なっているとともに、上端25については、足場を構成
する縦枠パイプ4の下端に当接されるようになってい
る。かかる内筒部材22は、縦枠パイプ4とほぼ同じ外
径寸法に形成するのがよい。
FIG. 4 is an exploded perspective view showing the scaffold leg connector 21 according to the present embodiment together with the vertical frame pipe 4 and the jack base 5. As can be seen from the figure, the scaffold leg connecting tool 21 according to the present embodiment is generally constituted by a substantially hollow cylindrical inner cylindrical member 22 and an outer cylindrical member 23 each formed of a steel pipe, a lightweight aluminum pipe, or the like. The lower end 24 of the inner cylinder member 22 is configured to be in contact with the upper surface of the height adjustment support cylinder 7 screwed to the male screw portion 6 of the jack base 5. The lower end of the vertical frame pipe 4 constituting the scaffold is abutted. The inner cylinder member 22 is preferably formed to have substantially the same outer diameter as the vertical frame pipe 4.

【0034】一方、外筒部材23は、内筒部材22や縦
枠パイプ4を嵌め込むことができるように、それらの外
径寸法をほぼ内径とした中空円筒状部材として構成して
ある。
On the other hand, the outer cylindrical member 23 is formed as a hollow cylindrical member having an outer diameter substantially equal to the inner diameter so that the inner cylindrical member 22 and the vertical frame pipe 4 can be fitted therein.

【0035】ここで、内筒部材22、外筒部材23には
ピン孔27、28をそれぞれ形成してあり、かかるピン
孔に係止機構としてのピン26を挿通した上で引き抜き
防止用の割ピン29で固定することにより、図5でよく
わかるように縦枠パイプ4と内筒部材22との当接位置
近傍で外筒部材23を保持するとともに、割ピン29を
抜いてピン26を水平に引き抜くことによって外筒部材
23を図6に示すように引き下げて待避させ、該当接位
置近傍を露出させることができるようになっている。
Here, pin holes 27 and 28 are formed in the inner cylinder member 22 and the outer cylinder member 23, respectively. By fixing with the pin 29, the outer cylinder member 23 is held near the contact position between the vertical frame pipe 4 and the inner cylinder member 22, as can be clearly seen in FIG. As shown in FIG. 6, the outer cylinder member 23 is pulled down and retracted to expose the vicinity of the corresponding contact position.

【0036】本実施形態に係る足場脚部用連結具21に
おいては、通常時は、図5に示すように縦枠パイプ4か
らの荷重が内筒部材22を介してジャッキベース5に伝
達されるとともに、係止機構であるピン26の作用によ
って縦枠パイプ4及び内筒部材22の当接位置近傍に保
持された外筒部材23により、縦枠パイプ4と内筒部材
22との横ずれが防止される。
In the scaffold leg connecting device 21 according to the present embodiment, the load from the vertical frame pipe 4 is normally transmitted to the jack base 5 through the inner cylindrical member 22 as shown in FIG. At the same time, lateral displacement between the vertical frame pipe 4 and the inner cylinder member 22 is prevented by the outer cylinder member 23 held near the contact position between the vertical frame pipe 4 and the inner cylinder member 22 by the action of the pin 26 serving as the locking mechanism. Is done.

【0037】一方、ジャッキベース5を取り外したい場
合には、割ピン29を抜いてピン26を図6に示すよう
に水平に引き抜き、外筒部材23を引き下げて下方に待
避させ、縦枠パイプ4と内筒部材22との当接位置近傍
を露出させる。そして、必要に応じて高さ調整用支持筒
7を廻して内筒部材22を若干降ろす。
On the other hand, when it is desired to remove the jack base 5, the split pin 29 is pulled out, the pin 26 is pulled out horizontally as shown in FIG. 6, the outer cylinder member 23 is pulled down and retracted downward, and the vertical frame pipe 4 is removed. The vicinity of the contact position between the inner cylinder member 22 and the inner cylinder member 22 is exposed. Then, if necessary, the height adjustment support cylinder 7 is turned to lower the inner cylinder member 22 slightly.

【0038】このようにすると、縦枠パイプ4の下端と
内筒部材22の上端との間に隙間が生じるとともに、外
筒部材23が待避位置にずらされた状態となるので、か
かる状態にてジャッキベース5を内筒部材22及び外筒
部材23とともに側方にずらして足場から撤去する。
With this arrangement, a gap is formed between the lower end of the vertical frame pipe 4 and the upper end of the inner cylinder member 22, and the outer cylinder member 23 is shifted to the retracted position. The jack base 5 is laterally shifted together with the inner cylinder member 22 and the outer cylinder member 23 and removed from the scaffold.

【0039】ジャッキベース5を再設置したい場合に
は、高さ調整用支持筒7及び内筒部材22を必要に応じ
て若干下げるとともに該内筒部材に外筒部材23を嵌め
込んだ状態で側方から縦枠パイプ4の直下に入れ込み、
次いで、外筒部材23の内部に縦枠パイプ4が嵌め込ま
れるようにして外筒部材23を引き上げて保持位置に戻
す。そして、ピン26を差し込んで外筒部材23を内筒
部材22に係止するとともに、必要に応じて高さ調整用
支持筒7を逆方向に若干廻して内筒部材22の上端を縦
枠パイプ4の下端に当接させる。
When it is desired to re-install the jack base 5, the height adjustment support cylinder 7 and the inner cylinder member 22 are slightly lowered as necessary, and the outer cylinder member 23 is fitted into the inner cylinder member. From below into the pipe 4
Next, the outer tube member 23 is pulled up and returned to the holding position so that the vertical frame pipe 4 is fitted into the outer tube member 23. Then, the pin 26 is inserted to lock the outer cylinder member 23 to the inner cylinder member 22 and, if necessary, the height adjustment support cylinder 7 is slightly rotated in the reverse direction so that the upper end of the inner cylinder member 22 is connected to the vertical frame pipe. 4 to make contact with the lower end.

【0040】以上説明したように、本実施形態に係る足
場脚部用連結具21によれば、縦枠パイプ4とジャッキ
ベース5との間に介在させる形で使用し、ジャッキベー
ス5の撤去時あるいは再設置時には、外筒部材23を待
避位置に引き下げて縦枠パイプ4と内筒部材22との側
方連結を外すようにしたので、縦枠パイプ4ひいては足
場全体を多人数で持ち上げたり時間を費やして解体した
りせずとも、ジャッキベース5の撤去や再設置を容易に
行うことが可能となる。
As described above, according to the scaffold leg connecting device 21 according to the present embodiment, the connecting device 21 is used so as to be interposed between the vertical frame pipe 4 and the jack base 5 when the jack base 5 is removed. Alternatively, at the time of re-installation, the outer tube member 23 is pulled down to the retracted position to disconnect the side connection between the vertical frame pipe 4 and the inner tube member 22, so that the vertical frame pipe 4 and thus the entire scaffold can be lifted by a large number of people or time. , The jack base 5 can be easily removed and re-installed without disassembling it.

【0041】また、本実施形態に係る足場脚部用連結具
21によれば、ピン26をピン孔27、28に差し込む
ことによって係止機構を構成したので、ピン26の抜き
差しによって外筒部材23の係止状態と解除状態とを容
易に切り替えることが可能となり、縦枠パイプ4と内筒
部材22の当接位置近傍における外筒部材23の保持並
びに昇降による待避を迅速に行うことが可能となる。
Further, according to the scaffold leg connecting tool 21 according to the present embodiment, the locking mechanism is constituted by inserting the pin 26 into the pin holes 27 and 28. Can easily be switched between the locked state and the released state, and the holding of the outer cylinder member 23 in the vicinity of the contact position between the vertical frame pipe 4 and the inner cylinder member 22 and the evacuation by raising and lowering can be performed quickly. Become.

【0042】本実施形態では、外筒部材23を下方に待
避させるようにしたが、これを引き上げて上方に待避さ
せてもよいことは言うまでもない。
In the present embodiment, the outer cylindrical member 23 is retracted downward, but it goes without saying that it may be lifted and retracted upward.

【0043】また、本実施形態では、ピン26による係
止を外筒部材23と内筒部材22との間でのみ行うよう
にしたが、縦枠パイプ4の引き抜きが懸念されるのであ
れば、同様の構成によって外筒部材23と縦枠パイプ4
との係止を行うようにしてもよい。なお、かかる構成に
おいては、ピン26、26が二段配置されることとな
る。
In the present embodiment, the locking by the pin 26 is performed only between the outer cylinder member 23 and the inner cylinder member 22. However, if there is a concern that the vertical frame pipe 4 may be pulled out, With the same configuration, the outer cylinder member 23 and the vertical frame pipe 4
May be locked. In this configuration, the pins 26 are arranged in two stages.

【0044】また、本実施形態では、ピン26及び該ピ
ンが差し込まれるピン孔27、28で係止機構を構成す
るようにしたが、かかる構成に代えて、図7に示すよう
に、内筒部材22の周面に図示しないバネで押し出され
るようになっている飛出し凸部31を設けておき、これ
を外筒部材23に形成された嵌込み孔32に嵌め込むこ
とで外筒部材23を内筒部材22に係止するとともに、
飛出し凹部31を押し込んで係止状態を解除し外筒部材
23を引き下げるようにしてもよい。
In this embodiment, the pin 26 and the pin holes 27 and 28 into which the pin is inserted constitute the locking mechanism. However, instead of such a configuration, as shown in FIG. A projection 31 is provided on the peripheral surface of the member 22 so as to be pushed out by a spring (not shown), and is fitted into a fitting hole 32 formed in the outer cylinder member 23 so that the outer cylinder member 23 is formed. To the inner cylinder member 22 and
The protruding recess 31 may be pushed in to release the locked state, and the outer cylinder member 23 may be pulled down.

【0045】また、本実施形態では、外筒部材23を内
筒部材22に係止させることで外筒部材23を縦枠パイ
プ4と内筒部材22との当接位置に保持するように構成
したが、図8に示すように、内筒部材22aの下端に設
けた鍔41と外筒部材23aの下端との間に伸縮機構と
してのコイルバネ42を設けるようにしてもよい。ここ
で、コイルバネ42は、その復元力が解放された状態の
ときに外筒部材23aが縦枠パイプ4と内筒部材22a
の当接位置近傍にちょうど押し上げられるように、その
強さを調整しておく。
Further, in this embodiment, the outer cylinder member 23 is held at the contact position between the vertical frame pipe 4 and the inner cylinder member 22 by locking the outer cylinder member 23 to the inner cylinder member 22. However, as shown in FIG. 8, a coil spring 42 as a telescopic mechanism may be provided between the flange 41 provided at the lower end of the inner cylindrical member 22a and the lower end of the outer cylindrical member 23a. Here, when the restoring force of the coil spring 42 is released, the outer cylindrical member 23a is connected to the vertical frame pipe 4 and the inner cylindrical member 22a.
Is adjusted so that it can be pushed up just near the contact position.

【0046】かかる構成においては、コイルバネ42を
押し込むようにして外筒部材23aを引き下ろすだけで
内筒部材22aと縦枠パイプ4との当接位置近傍が露出
するとともに、ジャッキベース5を縦枠パイプ4の直下
に位置決めした状態で外筒部材23aから手を離すだけ
で、該外筒部材がコイルバネ42の作用で上方に跳ね上
がって縦枠パイプ4に嵌め込まれるので、ジャッキベー
ス5の撤去並びに再設置をきわめて効率よく行うことが
可能となる。
In such a configuration, the vicinity of the contact position between the inner cylindrical member 22a and the vertical frame pipe 4 is exposed only by pulling down the outer cylindrical member 23a while pressing the coil spring 42, and the jack base 5 is connected to the vertical frame. Simply by releasing the outer cylinder member 23a with the positioning just below the pipe 4, the outer cylinder member jumps upward by the action of the coil spring 42 and is fitted into the vertical frame pipe 4, so that the jack base 5 is removed and re-mounted. Installation can be performed very efficiently.

【0047】[0047]

【発明の効果】以上述べたように、請求項1に係る本発
明の足場脚部用連結具によれば、縦枠パイプひいては足
場全体を多人数で持ち上げたり時間を費やして解体した
りせずとも、ジャッキベースの撤去や再設置を容易に行
うことが可能となる。
As described above, according to the connecting device for a scaffolding leg of the present invention according to the first aspect, the vertical frame pipe and, consequently, the entire scaffolding are not lifted by a large number of people or dismantled by spending time. In both cases, it becomes possible to easily remove and re-install the jack base.

【0048】また、請求項2に係る本発明の足場脚部用
連結具によれば、高さ調整用支持筒を昇降操作するだけ
で縦枠パイプへの連結や解除を行うことができるという
効果も奏する。
Further, according to the connecting device for a scaffold leg of the present invention according to the second aspect, it is possible to perform connection and disconnection to and from the vertical frame pipe only by moving the height adjusting support cylinder up and down. Also play.

【0049】また、請求項3に係る本発明の足場脚部用
連結具によれば、縦枠パイプひいては足場全体を多人数
で持ち上げたり時間を費やして解体したりせずとも、ジ
ャッキベースの撤去や再設置を容易に行うことが可能と
なる。
According to the third aspect of the present invention, the jack base can be removed without lifting the vertical frame pipe and thus the entire scaffold by a large number of people or disassembling it by spending time. And re-installation can be easily performed.

【0050】また、請求項4に係る本発明の足場脚部用
連結具によれば、縦枠パイプと内筒部材の当接位置近傍
における外筒部材の保持並びに昇降による待避を迅速に
行うことが可能となるという効果も奏する。
According to the connecting device for a scaffold leg of the present invention according to the fourth aspect, the holding of the outer cylinder member near the contact position between the vertical frame pipe and the inner cylinder member and the evacuation by raising and lowering are performed quickly. This also has the effect that it becomes possible.

【0051】また、請求項5に係る本発明の足場脚部用
連結具によれば、ジャッキベースの撤去並びに再設置を
きわめて効率よく行うことが可能となるという効果も奏
する。
According to the fifth aspect of the present invention, the jack base can be removed and reinstalled very efficiently.

【0052】[0052]

【図面の簡単な説明】[Brief description of the drawings]

【図1】第1実施形態に係る足場脚部用連結具の全体斜
視図。
FIG. 1 is an overall perspective view of a scaffold leg connector according to a first embodiment.

【図2】同じく側面図。FIG. 2 is a side view of the same.

【図3】第1実施形態に係る足場脚部用連結具の作用を
示した側面図。
FIG. 3 is a side view showing the operation of the scaffolding leg connecting device according to the first embodiment.

【図4】第2実施形態に係る足場脚部用連結具の分解斜
視図。
FIG. 4 is an exploded perspective view of a scaffold leg connector according to a second embodiment.

【図5】同じく側面図。FIG. 5 is a side view of the same.

【図6】第2実施形態に係る足場脚部用連結具の作用を
示した側面図。
FIG. 6 is a side view showing the operation of the scaffolding leg connecting device according to the second embodiment.

【図7】変形例に係る足場脚部用連結具の分解斜視図。FIG. 7 is an exploded perspective view of a scaffold leg connector according to a modification.

【図8】別の変形例に係る足場脚部用連結具の側面図。FIG. 8 is a side view of a scaffold leg connector according to another modification.

【図9】下屋に足場を立設した様子を示した側面図。FIG. 9 is a side view showing a state where a scaffold is erected in a shed.

【図10】従来技術におけるジャッキベースの撤去の様
子を示した側面図。
FIG. 10 is a side view showing a state of removing a jack base according to the related art.

【符号の説明】[Explanation of symbols]

4 縦枠パイプ 5 ジャッキベース 6 雄ねじ部 7 高さ調整用支持筒 11 接続部材(足場脚部用
連結具) 12 嵌合突起 21 足場脚部用連結具 22、22a 内筒部材 23、23a 外筒部材 26 ピン(係止機構) 27、28 ピン孔(係止機構) 31 飛出し凸部(係止機
構) 32 嵌込み孔(係止機構) 42 コイルバネ(伸縮機
構)
Reference Signs List 4 vertical frame pipe 5 jack base 6 male thread part 7 support cylinder for height adjustment 11 connection member (connector for scaffold leg) 12 fitting protrusion 21 connector for scaffold leg 22, 22a inner cylinder member 23, 23a outer cylinder Member 26 Pin (locking mechanism) 27, 28 Pin hole (locking mechanism) 31 Projection protrusion (locking mechanism) 32 Fitting hole (locking mechanism) 42 Coil spring (expansion and contraction mechanism)

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 足場を構成する縦枠パイプの下端に上端
にて連結されジャッキベースの雄ねじ部に螺合された高
さ調整用支持筒の上面に下端にて当接されるように構成
された接続部材からなることを特徴とする足場脚部用連
結具。
1. A height adjustment support cylinder connected to the lower end of a vertical frame pipe constituting a scaffold at an upper end thereof and screwed to a male screw portion of a jack base at an upper end thereof. A connecting member for a scaffolding leg, comprising a connecting member.
【請求項2】 前記接続部材の上端を前記縦枠パイプの
下端に嵌め込むように構成した請求項1記載の足場脚部
用連結具。
2. The scaffold leg connecting device according to claim 1, wherein an upper end of the connecting member is fitted into a lower end of the vertical frame pipe.
【請求項3】 足場を構成する縦枠パイプの下端に上端
にて当接されジャッキベースの雄ねじ部に螺合された高
さ調整用支持筒の上面に下端にて当接される内筒部材
と、前記縦枠パイプ及び前記内筒部材が嵌め込まれる外
筒部材とから構成するとともに、該外筒部材を前記縦枠
パイプと前記内筒部材との当接位置近傍で保持自在にか
つ該当接位置近傍が露出されるように昇降自在に構成し
たことを特徴とする足場脚部用連結具。
3. An inner cylindrical member which is in contact with the lower end of a vertical frame pipe constituting a scaffold at an upper end and which is in contact with the upper end of a height adjusting support cylinder screwed to a male screw portion of a jack base at a lower end. And an outer cylinder member into which the vertical frame pipe and the inner cylinder member are fitted, and the outer cylinder member is held freely and in the vicinity of a contact position between the vertical frame pipe and the inner cylinder member. A scaffold leg connecting tool, which is configured to be able to move up and down so that the vicinity of the position is exposed.
【請求項4】 前記外筒部材を前記縦枠パイプと前記内
筒部材との当接位置近傍で保持するための係止機構を設
けた請求項3記載の足場脚部用連結具。
4. The scaffolding leg connecting device according to claim 3, further comprising a locking mechanism for holding the outer cylindrical member near a contact position between the vertical frame pipe and the inner cylindrical member.
【請求項5】 前記外筒部材を所定の伸縮機構を介して
前記内筒部材に連結した請求項3記載の足場脚部用連結
具。
5. The scaffold leg connecting device according to claim 3, wherein the outer cylindrical member is connected to the inner cylindrical member via a predetermined telescopic mechanism.
JP9853698A 1998-03-26 1998-03-26 Connecting tool for scaffold leg part Withdrawn JPH11270127A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9853698A JPH11270127A (en) 1998-03-26 1998-03-26 Connecting tool for scaffold leg part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9853698A JPH11270127A (en) 1998-03-26 1998-03-26 Connecting tool for scaffold leg part

Publications (1)

Publication Number Publication Date
JPH11270127A true JPH11270127A (en) 1999-10-05

Family

ID=14222416

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9853698A Withdrawn JPH11270127A (en) 1998-03-26 1998-03-26 Connecting tool for scaffold leg part

Country Status (1)

Country Link
JP (1) JPH11270127A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030075601A (en) * 2002-03-19 2003-09-26 노민래 Steel pipe scaffolding fixed structure for single pipe scaffolding
JP2017038577A (en) * 2015-08-21 2017-02-23 株式会社クボタ combine
CN107288239A (en) * 2017-07-01 2017-10-24 中建三局集团有限公司 A kind of double pawl case bearing support bearing member installation accuracy adjusting meanss of high-precision L-type
CN109386124A (en) * 2018-12-13 2019-02-26 江苏华淼电子科技有限公司 A kind of construction scaffold connection height adjustment connecting rod

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030075601A (en) * 2002-03-19 2003-09-26 노민래 Steel pipe scaffolding fixed structure for single pipe scaffolding
JP2017038577A (en) * 2015-08-21 2017-02-23 株式会社クボタ combine
CN107288239A (en) * 2017-07-01 2017-10-24 中建三局集团有限公司 A kind of double pawl case bearing support bearing member installation accuracy adjusting meanss of high-precision L-type
CN109386124A (en) * 2018-12-13 2019-02-26 江苏华淼电子科技有限公司 A kind of construction scaffold connection height adjustment connecting rod

Similar Documents

Publication Publication Date Title
EP1587999B1 (en) Concrete slab form system
KR102113599B1 (en) Lifting System
JPH11270127A (en) Connecting tool for scaffold leg part
JP4023615B2 (en) Method for assembling formwork supporting apparatus for placing concrete in tunnel, method for disassembling formwork supporting apparatus for placing concrete in tunnel, elevating apparatus and elevating mechanism for formwork supporting apparatus for placing concrete in tunnel
KR100653229B1 (en) Device for supporting temporary beam of slab form
US4782634A (en) Building construction
KR20080069784A (en) Drop head for construction and constructing method for slab form using the same
JP4623570B2 (en) Construction method of jack base and formwork support
KR20160052475A (en) Supporting device for slab form
US3490189A (en) Scaffold element for use in the construction of scaffolding structures
CN214786234U (en) Temporary supporting device for joist pulling column
KR101171822B1 (en) Drop assembly
JP6258055B2 (en) Beam frame support
JP2723431B2 (en) Construction method of steel framed house
JP2005015159A (en) Climbing method of climbing crane
JP3110904B2 (en) Telescopic stay columns for construction work
JPH11200502A (en) Construction of house
JP2019151986A (en) Handrail device in support
KR101197491B1 (en) Filler panel
JP3546225B2 (en) How to build building structures
JPH11200631A (en) Building method for house
JP3002054U (en) Tower crane with multiple main columns as tower mast
JPH11131811A (en) Method for constructing building
KR20220057812A (en) Support pillar for mounting C-leg
JPH05330792A (en) Lift-up crane

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050607