JPH11236713A - Method of connecting column and pile and connecting structure - Google Patents

Method of connecting column and pile and connecting structure

Info

Publication number
JPH11236713A
JPH11236713A JP10286771A JP28677198A JPH11236713A JP H11236713 A JPH11236713 A JP H11236713A JP 10286771 A JP10286771 A JP 10286771A JP 28677198 A JP28677198 A JP 28677198A JP H11236713 A JPH11236713 A JP H11236713A
Authority
JP
Japan
Prior art keywords
concrete
pile
steel pipe
sheath
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10286771A
Other languages
Japanese (ja)
Inventor
Yasuhisa Imamoto
泰久 今本
Shigeki Ito
茂樹 伊藤
Kazuchika Konno
和近 今野
Kozo Sato
耕造 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP10286771A priority Critical patent/JPH11236713A/en
Publication of JPH11236713A publication Critical patent/JPH11236713A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/34Foundations for sinking or earthquake territories
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/76Graders, bulldozers, or the like with scraper plates or ploughshare-like elements; Levelling scarifying devices
    • E02F3/80Component parts
    • E02F3/815Blades; Levelling or scarifying tools

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve strength by placing concrete into a sheath pipe containing a column member after placing concrete in a steel pipe pile which holds the sheath pipe in the upper portion. SOLUTION: A bottomed cylindrical sheath pipe 5 is fixed to the inside of the upper portion of a steel pipe pile 1 driven into the ground 20, and concrete 3 is placed in the pile 1 and between the pile 1 and the pipe 5. And then a column 10 is joined to the pile 1 by placing concrete 14 in the pipe 5 and solidifying after the column member 10 is installed in the pipe 5 and positioned, after or before the concrete 3 solidifies. Therefor, as construction joints of concrete are eliminated and processing of the construction joints becomes unnecessary, it is possible to form a fault-free strong connecting structure, the double pipe structure helps increase the stiffness and bearing capacity of the joint between a column and a pile, and the sheath pipe facilitates concrete placement. As the level adjustment of concrete, removal of placed concrete and removal of blocks for forming hollow portions, etc., are no long needed, man-hours can be cut and a construction period can be shortened.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鉄骨構造物を構築
する際の柱と杭の接合方法及びその接合構造に関するも
のである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining a column and a pile when constructing a steel structure, and a joint structure thereof.

【0002】[0002]

【従来の技術】地震時におけるせん断抵抗性や曲げ抵抗
性が鉄筋コンクリート杭より優れた鋼管杭において、地
中に埋設されて場所打ちコンクリートが充填された鋼管
杭の中に上部構造である鋼管柱又は鋼管コンクリート柱
からなる柱材を建込み、その後コンクリートを充填する
ことにより鋼管杭と柱材を一体化して、耐震性をより高
めた基礎構造物とする工法が最近注目されている。
2. Description of the Related Art In steel pipe piles, which are superior in shear resistance and bending resistance during an earthquake to reinforced concrete piles, a steel pipe column having a superstructure embedded in a steel pipe pile buried underground and filled with cast-in-place concrete. Recently, a method of building a steel pipe concrete column and then filling it with concrete to integrate the steel pipe pile and the column into a foundation structure with improved earthquake resistance has attracted attention.

【0003】場所打ち鋼管コンクリート杭のコンクリー
トの打設にあたっては、先ず、所定の深さまで鋼管杭を
打ち込んだのち、コンクリート打設のためのトレミー管
を鋼管杭の先端部まで差し込み、トレミー管を徐々に引
き上げながらコンクリートを打設する。打ち上がってく
るコンクリートの上部には、泥水やコンクリートと汚水
が混じり合ったスライムなどのコンクリートにとって好
ましくない不純物が含まれている。
[0003] In placing concrete in a cast-in-place steel pipe concrete pile, first, a steel pipe pile is driven to a predetermined depth, and then a tremy pipe for concrete placement is inserted to the tip of the steel pipe pile, and the tremy pipe is gradually inserted. Concrete while pulling it up. The upper part of the rising concrete contains impurities that are not desirable for concrete, such as muddy water and slime mixed with concrete and sewage.

【0004】コンクリートの打設にあたっては、鋼管杭
の内部に充填するコンクリートのレベルを、建込まれる
柱材の下端部で打ち止めるのが望ましいが、打ち上がっ
てくるコンクリートの上部には、前述のように、コンク
リート打設時に注入されるベントナイト溶液や、泥水、
コンクリートと泥が混じり合ったスライムなどのコンク
リートにとって好ましくない不純物が含まれている。鋼
管杭内のコンクリートの品質を保証するためには、これ
らの不純物を鋼管杭外に排出しなければならず、これら
不純物を鋼管杭外にオーバーフローさせることによって
健全なコンクリートと置き換えており、このため、コン
クリートは杭頭部まで充填されている。
[0004] When placing concrete, it is desirable to stop the level of concrete to be filled in the steel pipe pile at the lower end of the column material to be built. As such, bentonite solution injected during concrete casting, muddy water,
It contains impurities that are undesirable for concrete, such as slime mixed with concrete and mud. In order to guarantee the quality of concrete in steel pipe piles, these impurities must be discharged outside the steel pipe piles, and these impurities are replaced with sound concrete by overflowing the steel pipe piles. Concrete is filled up to the pile head.

【0005】このような場所打ち鋼管コンクリート杭内
に柱材を建込む方法としては、従来、鋼管杭の杭頭部の
コンクリートを除去せずに、コンクリートが柔らかい状
態のときに柱材を所定の深さまで建込む方法が行われて
いた(従来技術1)。また、鋼管杭内に充填されたコン
クリートが固化する前に、柱材を建込むレベルまでコン
クリートを除去して所定深さ(定着長)の空間部を確保
し、この空間部に柱材を建込んで位置決めしたのち再び
コンクリートを打設して、場所打ち鋼管コンクリート杭
に柱材を接合する方法が行われていた(従来技術2)。
[0005] As a method of constructing a column material in such a cast-in-place steel pipe concrete pile, conventionally, without removing the concrete at the pile head of the steel pipe pile, the column material is fixed to a predetermined state when the concrete is in a soft state. A method of building up to the depth has been performed (prior art 1). Before the concrete filled in the steel pipe pile solidifies, the concrete is removed to the level where the pillars can be built to secure a space with a predetermined depth (fixed length), and the pillars are built in this space. After that, a method has been performed in which concrete is cast again after positioning, and a pillar is joined to a cast-in-place steel pipe concrete pile (prior art 2).

【0006】さらに、特開平2−164933号公報に
は、鋼管杭にコンクリートを打設する際に、ポリスチレ
ン発泡体ブロックなどであらかじめ空洞部を形成してお
き、この空洞部に柱材を建て込んだのちコンクリートを
打設して柱材と鋼管杭とを接合する方法が開示されてい
る(従来技術3)。
Further, Japanese Patent Application Laid-Open No. 2-164933 discloses that when concrete is poured into a steel pipe pile, a cavity is formed in advance with a polystyrene foam block or the like, and a column material is built in the cavity. After that, a method is disclosed in which concrete is cast and the column material and the steel pipe pile are joined (prior art 3).

【0007】[0007]

【発明が解決しようとする課題】従来技術1の方法は、
柱材を固定するための特別な治具を必要とし、また、柱
材の建込み時の芯出し精度が得にくいという問題があ
る。また、従来技術2の方法は、鋼管杭の上部のコンク
リートの除去にあたっては、多量のコンクリート(例え
ば、内径1.0〜1.5mの鋼管杭内に充填されたコン
クリートを、柱材の定着長に相当する1.5〜2mの深
さに除去する)を取り除かなければならないため多大の
労力を要し、さらに、コンクリートの除去の際に鋼管杭
を損傷したり、鋼管杭の内面のコンクリートの除去が不
完全なため、柱材の設置後に打設するコンクリートと鋼
管杭の内面との付着性が悪い等、種々問題がある。
The method of the prior art 1 is as follows.
There is a problem that a special jig for fixing the column material is required, and it is difficult to obtain centering accuracy when the column material is built. Further, in the method of the prior art 2, when removing the concrete on the upper part of the steel pipe pile, a large amount of concrete (for example, concrete filled in a steel pipe pile having an inner diameter of 1.0 to 1.5 m, is fixed to the fixing length of the column material). To remove the steel pipe to a depth of 1.5 to 2 m), which requires a great deal of labor. In addition, the steel pipe pile may be damaged when the concrete is removed, or the concrete on the inner surface of the steel pipe pile may be damaged. Since the removal is incomplete, there are various problems such as poor adhesion between the concrete to be poured after the installation of the column and the inner surface of the steel pipe pile.

【0008】さらに、従来技術3においては、空洞部を
形成するためのポリスチレン発泡体ブロックの除去に重
機や人力などの労力を必要とし、また、ポリスチレン発
泡体ブロックの除去後の空洞部において、先に打設した
コンクリートと柱材の建込み後に打設したコンクリート
との打ち継ぎ面の付着が良好でないため、先に打設した
コンクリート表面の目荒しなどの処理作業が必要である
等の問題がある。
Further, in the prior art 3, the removal of the polystyrene foam block for forming the cavity requires labor such as heavy machinery and human power, and the cavity after the removal of the polystyrene foam block has There is a problem that the joint surface between the concrete poured into the concrete and the concrete poured after the column material is installed is not good, and it is necessary to carry out processing work such as roughening the surface of the concrete poured first. is there.

【0009】ところで、上述の従来技術1〜3において
は、いずれも内部にコンクリートが打設された鋼管杭内
に、柱材である鋼管柱を建込んで接合しているが、上部
構造物を鉄骨造とした場合、鉄筋コンクリート柱あるい
は鉄骨鉄筋コンクリート柱に比べて建物が振動し易く、
居住空間に向いていないという問題がある。そこで、こ
のような問題を解決するために、例えば図17に示すよ
うに、場所打ち鋼管コンクリート杭1(以下、鋼管杭と
いう)にH形鋼などの鉄骨材12からなる鉄骨鉄筋コン
クリート柱11を接合することが考えられる。図17に
おいて、1は鋼管杭、3は鋼管杭1内に打設されたコン
クリート、11は鋼管杭1の上部のコンクリートを除去
した空間部gに建込んだ鉄骨鉄筋コンクリート柱で、1
2は鉄骨材、13は形鋼12の外周に配筋された鉄筋で
ある。そして、空間部g内、鉄骨材12及び鉄筋13の
外周にコンクリート14を打設して鉄骨鉄筋コンクリー
ト柱11を構成し、鋼管杭1に接合したものである。し
かしながら、このようにして構成した場合も、依然とし
て鋼管杭1内に充填されたコンクリート3を除去して空
間部gを形成するための多大の労力が必要である。
In each of the above-mentioned prior arts 1 to 3, steel pipe columns as pillars are erected and joined in steel pipe piles in which concrete is cast inside. In the case of steel frame, the building is more likely to vibrate than reinforced concrete columns or steel reinforced concrete columns,
There is a problem that it is not suitable for living space. Therefore, in order to solve such a problem, for example, as shown in FIG. 17, a steel reinforced concrete column 11 made of a steel frame material 12 such as an H-beam is joined to a cast-in-place steel pipe concrete pile 1 (hereinafter referred to as a steel pipe pile). It is possible to do. In FIG. 17, 1 is a steel pipe pile, 3 is concrete cast in the steel pipe pile 1, 11 is a steel reinforced concrete column built in a space g where the concrete on the upper part of the steel pipe pile 1 has been removed.
Reference numeral 2 denotes a steel frame material, and reference numeral 13 denotes a reinforcing bar arranged on the outer periphery of the section steel 12. Then, concrete 14 is cast in the space part g and around the outer periphery of the steel frame material 12 and the reinforcing bar 13 to form the steel frame reinforced concrete column 11 and joined to the steel pipe pile 1. However, even in the case of such a configuration, a large amount of labor is still required for removing the concrete 3 filled in the steel pipe pile 1 and forming the space portion g.

【0010】本発明は、上記の課題を解決するためにな
されたもので、場所打ち鋼管コンクリート杭と柱材との
接合部の強度を向上させると共に、作業を簡略化して労
力の低減と工期の短縮をはかることのできる柱と杭の接
合方法及びその接合構造を得ることを目的としたもので
ある。また、本発明は鉄骨鉄筋コンクリート柱からなる
柱と杭の接合方法及びその接合構造を得ることを目的と
したものである。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems. The present invention improves the strength of a joint between a cast-in-place steel pipe concrete pile and a column material, simplifies the work, reduces labor, and reduces construction time. It is an object of the present invention to obtain a joint method of a pillar and a pile that can be shortened and a joint structure thereof. Another object of the present invention is to obtain a method of joining a pillar and a pile made of steel reinforced concrete columns and a joining structure thereof.

【0011】[0011]

【課題を解決するための手段】本発明に係る柱と杭の接
合方法は、地盤中に打設された鋼管杭内及び該鋼管杭と
該鋼管杭の上部内に取付けられた鞘管との間にコンクリ
ートを打設し、該コンクリートが固化する前又は固化し
たのち前記鞘管内に柱材を建込んで該鞘管内にコンクリ
ートを打設するようにしたものである。
According to the present invention, there is provided a method for joining a pillar and a pile according to the present invention. The method comprises the steps of connecting a steel pipe pile installed in the ground and a sheath pipe mounted in an upper part of the steel pipe pile. Concrete is poured in between, and before or after the concrete solidifies, a pillar is built in the sheath tube and concrete is poured into the sheath tube.

【0012】上記の柱と杭の接合方法において、鋼管杭
の打設後に鞘管を取付け、あるいはあらかじめ鞘管が取
付られた鋼管杭を打設するようにした。
In the above-described method of joining a column and a pile, a sheath pipe is attached after the steel pipe pile is cast, or a steel pipe pile to which a sheath pipe is previously attached is cast.

【0013】また、本発明に係る柱と杭の接合構造は、
地盤中に打設された鋼管杭と、該鋼管杭の上部内に取付
けられ前記鋼管杭との間にコンクリートが打設される鞘
管と、該鞘管内に建て込まれ該鞘管との間にコンクリー
トが打設される柱材とを備えたものである。
Further, the joint structure between the pillar and the pile according to the present invention is as follows.
Between a steel pipe pile installed in the ground, a sheath pipe mounted in the upper part of the steel pipe pile, and concrete cast between the steel pipe pile and a sheath pipe built in the sheath pipe and And a column member on which concrete is cast.

【0014】上記の鞘管を有底筒状に構成し、その底部
を平板状、凸状又は傾斜面状に形成した。また、底部を
鞘管の外形より大きく形成し、該鞘管の周囲から突出さ
せた。さらに、内壁面若しくは外壁面又は内外壁面に凸
部が形成されている鞘管を使用した。また、鞘管を鋼管
又はコルゲート材で構成した。上記の柱材を鉄骨鉄筋コ
ンクリート柱によって構成した。
The above-mentioned sheath tube was formed in a bottomed cylindrical shape, and the bottom was formed in a flat plate shape, a convex shape, or an inclined surface shape. Also, the bottom was formed larger than the outer shape of the sheath tube, and protruded from the periphery of the sheath tube. Further, a sheath tube having a convex portion formed on the inner wall surface, outer wall surface, or inner / outer wall surface was used. The sheath tube was made of a steel tube or a corrugated material. The above-mentioned column members were constituted by steel-framed reinforced concrete columns.

【0015】[0015]

【発明の実施の形態】[実施の形態1]図1は本発明の
実施の形態1の説明図で、本実施の形態は、本発明の基
本的構成を示すものである。先ず、図1(a)に示すよ
うに、地盤20に打設された鋼管杭1の上方から、鋼管
杭1内に有底筒状の鞘管5を挿入し、所定の位置に固定
する。
[First Embodiment] FIG. 1 is an explanatory view of a first embodiment of the present invention. This embodiment shows a basic configuration of the present invention. First, as shown in FIG. 1A, a bottomed tubular sheath tube 5 is inserted into the steel pipe pile 1 from above the steel pipe pile 1 cast on the ground 20, and fixed at a predetermined position.

【0016】ついで、図1(b)に示すように、鋼管杭
1内及び鋼管杭1と鞘管5との間に形成された空間部に
上方からコンクリート3を杭頭部からオーバーフロさせ
て打設する。次に、コンクリート3が固化する前又は固
化したのち、図1(c)に示すように、鞘管5内に柱材
10を挿入して設置し、位置決めする。そして、鞘管5
内にコンクリート14を打設し、コンクリート14が固
化することにより、柱材10を鋼管杭1に接合するよう
にしたものである。
Next, as shown in FIG. 1 (b), concrete 3 is overflowed from the top of the pile from above into a space formed inside the steel pipe pile 1 and between the steel pipe pile 1 and the sheath pipe 5. Cast in. Next, before or after the concrete 3 is solidified, as shown in FIG. 1 (c), the column material 10 is inserted into the sheath tube 5, installed, and positioned. And sheath tube 5
The concrete 14 is cast into the inside, and the concrete 14 is solidified to join the column member 10 to the steel pipe pile 1.

【0017】上記の説明では、鞘管5が挿入された鋼管
杭1内に打設したコンクリート3が固化する前又は固化
後に鞘管5内に柱材10を設置し、ついで鞘管5内にコ
ンクリート14を打設する場合を示したが、例えば、鞘
管5が挿入された鋼管杭1内に打設したコンクリート3
が固化する前又は固化後に鞘管5内にコンクリート14
を打設し、このコンクリート14が固化する前に鞘管5
内に柱材10を設置するようにしてもよい。
In the above description, before or after the concrete 3 cast in the steel pipe pile 1 into which the sheath tube 5 is inserted is solidified, the column member 10 is installed in the sheath tube 5, and then the column member 10 is placed in the sheath tube 5. Although the case where the concrete 14 is cast is shown, for example, the concrete 3 cast into the steel pipe pile 1 into which the sheath pipe 5 is inserted.
Before or after solidification, concrete 14 is placed in sheath tube 5.
Before the concrete 14 solidifies.
You may make it install the pillar material 10 inside.

【0018】上記のように構成した本発明によれば、コ
ンクリート相互の打ち継ぎが発生しないので打ち継ぎ面
の処理が不要であり、欠陥のない接合構造とすることが
できる。また、鞘管5を設けたことにより、鋼管杭1内
及び鞘管5内へのコンクリート3,14の打設が簡単に
なり、コンクリート3のレベル調整も不要である。さら
に、鋼管杭1内に打設したコンクリートを除去したり、
空洞部を形成するためのポリスチレン発泡体ブロックの
除去等の手間が不要であり、工数を低減し、工期を短縮
することができる。
According to the present invention configured as described above, since jointing between concrete does not occur, it is not necessary to treat the jointing surface, and a joint structure free from defects can be obtained. Further, the provision of the sheath pipe 5 simplifies the placing of the concretes 3 and 14 into the steel pipe pile 1 and the sheath pipe 5, and does not require the level adjustment of the concrete 3. Furthermore, concrete poured into the steel pipe pile 1 is removed,
There is no need to remove the polystyrene foam block for forming the cavity, and the like, so that the number of steps can be reduced and the construction period can be shortened.

【0019】[実施の形態2]図2は本発明の実施の形
態2を説明するための模式的平面図及びその縦断面図で
ある。両図において、1は内壁面に凸部2が設けられ、
地盤20に掘削した穴21内に打設されて場所打ち鋼管
コンクリート杭を構成する鋼管杭である。
[Second Embodiment] FIG. 2 is a schematic plan view and a longitudinal sectional view for explaining a second embodiment of the present invention. In both figures, 1 is provided with a convex portion 2 on the inner wall surface,
It is a steel pipe pile which is driven into a hole 21 excavated in the ground 20 to constitute a cast-in-place steel pipe concrete pile.

【0020】5は底板6を有し、内壁面に凸部7が設け
られた断面四角形で筒状の鞘管で、鋼管杭1内に挿入し
て位置決めされ、鋼管杭1内に打設されたコンクリート
3により所定の位置に固定されている。12はH形鋼の
如き形鋼からなり鉄骨鉄筋コンクリート柱11を構成す
る鉄骨材、13は鉄骨材12の外周に配設された鉄筋
で、鉄骨材12は鉄筋13が配筋された鞘管5内に建込
まれ、コンクリート14が打設されて鋼管杭1に接合さ
れ、鉄骨鉄管コンクリート柱11が構成される。
Reference numeral 5 denotes a tubular sheath tube having a bottom plate 6 and a rectangular cross section having a convex portion 7 provided on the inner wall surface. The sheath tube is inserted and positioned in the steel pipe pile 1, and is driven into the steel pipe pile 1. It is fixed at a predetermined position by the concrete 3 which has been set. Reference numeral 12 denotes a steel frame member made of a section steel such as an H-section steel and constituting a steel reinforced concrete column 11, reference numeral 13 denotes a reinforcing bar disposed on the outer periphery of the steel frame member 12, and a steel frame member 12 denotes a sheath tube 5 having a reinforcing bar 13 disposed therein. The concrete 14 is cast into the steel pipe pile 1 and is joined to the steel pipe pile 1 to form the steel column concrete pillar 11.

【0021】次に、上記のような本実施の形態の施工方
法の一例について説明する。 (1)図3(a)に示すように、地盤20に掘削した穴
21に鋼管杭1を打設し、この鋼管杭1内に鞘管5を挿
入して固定する。勿論、鋼管杭1を直接地盤20に打設
してもよい。
Next, an example of the construction method of the present embodiment as described above will be described. (1) As shown in FIG. 3A, the steel pipe pile 1 is driven into a hole 21 excavated in the ground 20, and the sheath pipe 5 is inserted into the steel pipe pile 1 and fixed. Of course, the steel pipe pile 1 may be directly driven into the ground 20.

【0022】鞘管5の固定にあたっては、図4に示すよ
うに、鉄筋、平板あるいはこれに類する部材からなるコ
字状の複数の固定部材15の一方の片を、鞘管5の上部
外壁に溶接などによりそれぞれ固定しておき、鞘管5を
鋼管杭1内に挿入する際に、固定部材15の他方の片を
鋼管杭1の上端部にそれぞれ係止させ、溶接等により固
定する。これにより、鞘管5は鋼管杭1内に保持され、
鞘管5と鋼管杭1との間には空間部gが形成される。
In fixing the sheath tube 5, as shown in FIG. 4, one piece of a plurality of U-shaped fixing members 15 made of a reinforcing bar, a flat plate or a similar member is attached to the upper outer wall of the sheath tube 5. When the sheath tube 5 is inserted into the steel pipe pile 1, the other pieces of the fixing members 15 are respectively engaged with the upper end of the steel pipe pile 1 and fixed by welding or the like. Thereby, the sheath pipe 5 is held in the steel pipe pile 1,
A space g is formed between the sheath pipe 5 and the steel pipe pile 1.

【0023】また、鞘管5の挿入長が長く下部が不安定
の場合は、図5に示すように、鞘管5の挿入長とほぼ等
しい垂直片と、その上端部に設けたL字状の係止片と、
下端部に設けたこれより短いL字状の係止片とによりほ
ぼC字状の複数の固定部材15aを構成し、垂直片を溶
接などにより鞘管5の外壁面に固定しておく。そして、
鞘管5を鋼管杭1内に挿入する際に、固定部材15aの
上端部の係止片を鋼管杭1の上端部にそれぞれ係止させ
ると共に、下端部の係止片を鋼管杭1の内壁面に当接さ
せ、それぞれ溶接等により鋼管杭1の外壁面及び内壁面
に固定する。これにより、鞘管5を鋼管杭1内に安定し
て保持することができる。
When the insertion length of the sheath tube 5 is long and the lower part is unstable, as shown in FIG. 5, a vertical piece substantially equal to the insertion length of the sheath tube 5 and an L-shape provided at the upper end thereof are provided. And a locking piece of
A plurality of substantially C-shaped fixing members 15a are formed by the shorter L-shaped locking pieces provided at the lower end, and the vertical pieces are fixed to the outer wall surface of the sheath tube 5 by welding or the like. And
When the sheath tube 5 is inserted into the steel pipe pile 1, the locking pieces at the upper end of the fixing member 15 a are locked to the upper end of the steel pipe pile 1, and the locking pieces at the lower end are inserted into the steel pipe pile 1. The steel pipe pile 1 is fixed to the outer wall surface and the inner wall surface of the steel pipe pile 1 by welding or the like. Thereby, the sheath pipe 5 can be stably held in the steel pipe pile 1.

【0024】上記何れの場合においても、鞘管5を施工
現場で鋼管杭1に取付けてもよく、あるいは、あらかじ
め工場で鞘管5を鋼管杭1に取付けておき、施工現場に
運搬して鋼管杭1と共に地盤20に打設するようにして
もよい。この場合は、施工現場における鞘管5の取付け
作業を省略できるのでそのための設備が不要になり、迅
速な施工を行うことができる。
In any of the above cases, the sheath pipe 5 may be attached to the steel pipe pile 1 at the construction site, or the sheath pipe 5 may be attached to the steel pipe pile 1 at a factory in advance, and then transported to the construction site. It may be driven into the ground 20 together with the pile 1. In this case, since the work of attaching the sheath tube 5 at the construction site can be omitted, equipment for this is not required, and rapid construction can be performed.

【0025】(2)この状態で、図3(b)に示すよう
に、鋼管杭1内に杭頭部からオーバーフローさせてコン
クリート3を打設し、鞘管5を鋼管杭1内に固定する。
(2) In this state, as shown in FIG. 3B, concrete 3 is poured into the steel pipe pile 1 by overflowing from the pile head, and the sheath pipe 5 is fixed in the steel pipe pile 1. .

【0026】(3)コンクリート3が固化する前又は固
化したのち、図3(c)に示すように、鞘管5内に鉄筋
13を配筋し、内部に鉄骨材12を建込んで位置決め手
段により位置決めする。そして、鞘管5の上部において
鉄筋13の外周に型枠17を配設し、鞘管5及び型枠内
17にコンクリート14を打設する。このとき、鞘管5
の鋼管杭1より上方に位置する部分が型枠17の機能を
有するため、型枠17の数を減らすことができる。な
お、先ず、鉄筋13が配筋され鉄骨材12が建込まれた
鞘管5内にコンクリート14を打設し、ついで型枠17
を配設して鉄骨材12の外周にコンクリート14を打設
してもよい。
(3) Before or after the concrete 3 has solidified, as shown in FIG. 3 (c), a reinforcing bar 13 is arranged in the sheath tube 5 and a steel frame material 12 is buried therein to position the positioning means. Positioning by Then, a formwork 17 is disposed on the outer periphery of the reinforcing bar 13 at the upper part of the sheath tube 5, and concrete 14 is cast into the sheath tube 5 and the inside 17 of the formwork. At this time, the sheath tube 5
Since the portion located above the steel pipe pile 1 has the function of the mold 17, the number of molds 17 can be reduced. First, concrete 14 is cast into the sheath tube 5 in which the reinforcing bar 13 is arranged and the steel frame material 12 is built, and then the form 17
And the concrete 14 may be cast around the steel frame 12.

【0027】(4)コンクリート14が固化したのち型
枠17を取外せば、鉄骨材12及び鉄筋13は鞘管5を
介して鋼管杭1に一体かつ強固に接合され、鉄骨鉄筋コ
ンクリート柱11が構成される。
(4) If the form 17 is removed after the concrete 14 has solidified, the steel frame material 12 and the reinforcing bar 13 are integrally and firmly joined to the steel pipe pile 1 via the sheath tube 5, and the steel frame reinforced concrete column 11 is formed. Is done.

【0028】上記のように構成した本実施の形態によれ
ば、コンクリート相互の打ち継ぎが発生しないので打ち
継ぎ面の処理が不要であり、このため欠陥のない接合構
造を得ることができる。また、鋼管杭1内及び鞘管5内
へのコンクリート3,14の打設が簡単で、コンクリー
トレベルの調整が不要である。さらに、従来ように、鋼
管杭内に打設したコンクリートの除去や空洞部形成のた
めの発泡ブロックを除去する必要がないので、工数を低
減することができる。
According to the present embodiment configured as described above, since the joint between the concretes does not occur, it is not necessary to treat the joint surface, so that a joint structure free from defects can be obtained. In addition, the concrete 3 and 14 are easily poured into the steel pipe pile 1 and the sheath pipe 5, and adjustment of the concrete level is not required. Furthermore, unlike the related art, there is no need to remove the concrete poured into the steel pipe pile or the foam block for forming the cavity, so that the number of steps can be reduced.

【0029】次に、本発明の力学的作用及び効果につい
て説明する。発明者らは、図6(a)に示すように、鋼
管杭1内にコンクリート充填角形鋼管10aを設置して
接合し、載荷試験を行ったところ鋼管杭1内に打設した
コンクリート3に図に示すような初期ひび割れが発生し
た。よって、柱材として鉄骨鉄筋コンクリート柱を用い
た場合も、図7(a)に示すような初期ひび割れが発生
するものと推定した。したがって、図6(b)及び図7
(b)に示すように、柱材10a又は11に外力Qが作
用すれば、柱材10a又は11は、コンクリート3の斜
線で示す部分3aのみを押すことになると考えられる。
Next, the mechanical action and effect of the present invention will be described. As shown in FIG. 6 (a), the inventors installed a concrete-filled rectangular steel pipe 10a in a steel pipe pile 1 and joined it, and performed a loading test. As a result, the concrete 3 was cast into the steel pipe pile 1. Initial cracks occurred as shown in FIG. Therefore, even when a steel-framed reinforced concrete column was used as the column material, it was estimated that an initial crack as shown in FIG. 7A would occur. Therefore, FIGS. 6B and 7
As shown in (b), when an external force Q acts on the column material 10a or 11, it is considered that the column material 10a or 11 pushes only the hatched portion 3a of the concrete 3.

【0030】上記の知見に基いて、先ず、柱と杭の接合
部における剛性について考察する。図8に示すように、
鋼管杭1内に鞘管5を設置し、この鞘管5に鉄骨鉄筋コ
ンクリート柱11を接合した本発明の場合と、図9に示
すように、鋼管杭1に鉄骨鉄筋コンクリート柱11を接
合した場合とにおける剛性について比較した。
Based on the above findings, first, the rigidity at the joint between the column and the pile will be considered. As shown in FIG.
In the case of the present invention in which the sheath pipe 5 is installed in the steel pipe pile 1 and the steel frame reinforced concrete column 11 is joined to the sheath pipe 5, and in the case where the steel frame reinforced concrete column 11 is joined to the steel pipe pile 1 as shown in FIG. The stiffness was compared.

【0031】いま、鉄骨鉄筋コンクリート柱11の鋼管
杭1内への埋め込み長をLとすると、鉄骨鉄筋コンクリ
ート柱11に作用する外力Qは、Q=BLσとなる。本
発明に係る図8の場合、外力Qによる鉄骨鉄筋コンクリ
ート柱11の変位量δa は、 δa =la ・σ/E+lb ・σ/E=Q/EBL・la
+Q/EDL・lb となる。一方、図9の鉄骨鉄筋コンクリート柱11の変
位量δb は、 δc =lc ・σ/E=Q/EBL・lc >δa となる。但し、la +lb =lc 、D>B したがって、外力Qによる鉄骨鉄筋コンクリート柱11
の回転角はθa<θbとなり、図8に示す本発明に係る
柱と杭の接合構造の方が、図9に示す柱と杭の接合構造
よりその剛性が大きいことがわかる。
Now, assuming that the embedded length of the steel reinforced concrete column 11 in the steel pipe pile 1 is L, the external force Q acting on the steel reinforced concrete column 11 is Q = BLσ. For Figure 8 according to the present invention, the displacement amount [delta] a of steel reinforced concrete pillar 11 by an external force Q is, δ a = l a · σ / E + l b · σ / E = Q / EBL · l a
+ The Q / EDL · l b. On the other hand, the displacement amount [delta] b of steel reinforced concrete columns 11 of FIG. 9 is a δ c = l c · σ / E = Q / EBL · l c> δ a. However, l a + l b = l c , D> B Therefore, the steel reinforced concrete column 11 due to the external force Q
Is θa <θb, and it can be seen that the rigidity of the joint structure between the column and the pile according to the present invention shown in FIG. 8 is greater than that of the joint structure between the column and the pile shown in FIG.

【0032】次に、図8、図9を参照して、図10、図
11により耐力について考案する。いま、図10、図1
1に示すように、鋼管杭1の管壁を両端支持の梁1aと
考えると、本発明に係る図10に示す接合構造の場合
は、外力Qによる鉄骨鉄筋コンクリート柱11の変位に
よって鋼管杭1の管壁に生ずる応力σb は、図10
(b)に示すように梁1aに加わる分布荷重ωAとして
表すことができ、また、図11に示す接合構造の場合
は、図11(b)に示すよう梁1aに加わる分布荷重ω
Bとして表すことができる。
Next, with reference to FIGS. 8 and 9, the proof stress will be devised with reference to FIGS. Now, FIGS. 10 and 1
As shown in FIG. 1, assuming that the pipe wall of the steel pipe pile 1 is a beam 1a supported at both ends, in the case of the joint structure shown in FIG. 10 according to the present invention, the displacement of the steel reinforced concrete column 11 due to the external force Q causes the steel pipe pile 1 to move. The stress σ b generated on the pipe wall is shown in FIG.
It can be expressed as a distributed load ωA applied to the beam 1a as shown in (b), and in the case of the joint structure shown in FIG. 11, the distributed load ω applied to the beam 1a as shown in FIG. 11 (b)
B.

【0033】そして、この梁1aにかかる分布荷重はω
A=Qa /b1 、ωB=Qb /b2であり、a1 =l−
1 /2、a2 =l−b2 /2であるから、梁の中央に
加わる曲げモーメントMcは、 Mc1 =Qa (2l−b1 )/8となり、 また、 Mc2 =ω(l2 −4a2 )/8=Qb {l2 −(l−b2 2 }/8b2 =Qb (2lb2 −b2 2 )/8b2 =Qb (2l−b2 )/8となる。 断面係数Zは、どちらも同じであるから、内部応力σ
は、 σb =Mc1 /M=Qa (2l−b1 )/8Z σc =Mc2 /M=Qb (2l−b2 )/8Z であり、b1 >b2 であるから、σb ,σc が共に降伏
応力度σy に達したときQb >Qc となり、降伏耐力は
図10に示す本発明の方が大きいことがわかる。
The distributed load applied to the beam 1a is ω
A = Q a / b 1 , ωB = Q b / b 2 , and a 1 = l−
b 1/2, since it is a 2 = l-b 2/ 2, bending moment Mc exerted on the central beam, Mc 1 = Q a (2l -b 1) / 8 becomes also,, Mc 2 = ω ( l 2 -4a 2 ) / 8 = Q b {l 2 − (l−b 2 ) 2 } / 8b 2 = Q b (2lb 2 −b 2 2 ) / 8b 2 = Q b (2l−b 2 ) / It becomes 8. Since the section modulus Z is the same for both, the internal stress σ
Σ b = Mc 1 / M = Q a (2l−b 1 ) / 8Z σ c = Mc 2 / M = Q b (2l−b 2 ) / 8Z, and b 1 > b 2 , σ b, σ c is Q b> Q c becomes when both reached yield stress of sigma y, yield strength it can be seen that greater in the present invention shown in FIG. 10.

【0034】このように、本発明においては、柱と杭の
接合部は鋼管杭1、鞘管5及び両者の間に充填されたコ
ンクリート3によって二重管を構成しているため、剛性
及び耐力のきわめて高い柱と杭の接合構造を得ることが
できる。
As described above, in the present invention, the joint between the column and the pile forms a double pipe by the steel pipe pile 1, the sheath pipe 5, and the concrete 3 filled between the two, so that the rigidity and the proof stress are increased. It is possible to obtain an extremely high column-pile joint structure.

【0035】[実施例]図12は実施の形態2の一実施
例の説明図である。本実施例における鋼管杭1は、外径
1 :1200mm、肉厚t1 :12mmで、図示して
ないが、内壁面には高さ:2.5mm、ピッチ:40m
mでスパイラル状の凸部2が設けられた鋼管で構成し
た。また、鞘管5は、一辺の長さD2 :600mm、長
さL1 :1100mm、肉厚t2 :12mmで、内壁面
に鋼管杭1と同様の凸部7を有する角形鋼管で構成し
た。なお、鞘管5の下端部には、一辺の長さ650〜6
60mm、板厚22mmの四角形の底板6を取付けた。
また、鉄骨材12は、ウェブ高さH:450mm、ウェ
ブ厚t4 :9mm、フランジ幅W:200mm、フラン
ジ厚t5 :14mmのH形鋼を十字状に接合して構成し
た。
[Embodiment] FIG. 12 is an explanatory diagram of one embodiment of the second embodiment. The steel pipe pile 1 in this embodiment has an outer diameter D 1 : 1200 mm, a wall thickness t 1 : 12 mm, and although not shown, the inner wall surface has a height of 2.5 mm and a pitch of 40 m.
m and a steel pipe provided with a spiral projection 2. The sheath pipe 5 was made of a square steel pipe having a length D 2 of 600 mm, a length L 1 of 1100 mm, a thickness t 2 of 12 mm, and a projection 7 similar to the steel pipe pile 1 on the inner wall surface. . The lower end of the sheath tube 5 has a side length of 650 to 6
A square bottom plate 6 having a thickness of 60 mm and a thickness of 22 mm was attached.
The steel frame 12 was formed by joining an H-shaped steel having a web height H: 450 mm, a web thickness t 4 : 9 mm, a flange width W: 200 mm, and a flange thickness t 5 : 14 mm in a cross shape.

【0036】上記のような鋼管杭1内に鞘管5を挿入し
(挿入長さL2 :900mm)、固定部材15により鋼
管杭1に固定したのち、鋼管杭1内にオーバーフローさ
せて杭頭部までコンクリート3を打設した。次に、鞘管
5内に直径D:22mmの鉄筋13を配筋した(鋼管杭
1の杭頭部からの鉄筋13の挿入長L3 :620m
m)。ついで、コンクリート3が固化したのち鞘管5内
に鉄骨材12を建込んで位置決めし(鞘管5の頭部から
の挿入長L4 :900mm)、鞘管5内にコンクリート
14を打設した。上記のように施工して鉄骨鉄筋コンク
リート柱11を鋼管杭1に接合したところ、前述のよう
な剛性及び耐力に優れた柱と杭の接合構造を得ることが
できた。
The sheath tube 5 is inserted into the steel pipe pile 1 as described above (insertion length L 2 : 900 mm), fixed to the steel pipe pile 1 by the fixing member 15, and then overflowed into the steel pipe pile 1 to make the pile head. Concrete 3 was poured to the part. Next, a reinforcing bar 13 having a diameter D: 22 mm was arranged in the sheath tube 5 (insertion length L 3 of the reinforcing bar 13 from the pile head of the steel pipe pile 1: 620 m).
m). Then, after the concrete 3 was solidified, the steel frame material 12 was built and positioned in the sheath tube 5 (insertion length L 4 from the head of the sheath tube 5: 900 mm), and concrete 14 was poured into the sheath tube 5. . When the steel reinforced concrete column 11 was joined to the steel pipe pile 1 by performing the construction as described above, the joint structure between the column and the pile having excellent rigidity and strength as described above could be obtained.

【0037】[実施の形態3]実施の形態2では、柱材
として鉄骨鉄筋コンクリート柱11を用いた場合を示し
たが、本実施の形態は、柱材として、外壁面若しくは内
壁面又は内外壁面に凸部を有する鋼管柱を用いたもので
ある。本実施の形態の施工方法及び効果は、実施の形態
1の場合とほぼ同様なので、説明を省略する。
[Third Embodiment] In the second embodiment, the case where the steel reinforced concrete column 11 is used as the column material has been described. However, in the present embodiment, the column material is formed on the outer wall surface, the inner wall surface, or the inner and outer wall surfaces. This uses a steel pipe column having a convex portion. The construction method and effects of the present embodiment are almost the same as those of the first embodiment, and thus description thereof will be omitted.

【0038】[実施の形態4]実施の形態1〜3では、
鋼管杭1内に鞘管5を挿入してコンクリート3を打設
し、コンクリート3が固化する前又は固化した後に鞘管
5内に鉄筋13を配筋して柱材を挿入し、コンクリート
14を打設して接合する場合を示したが、本実施の形態
においては、鋼管杭1内に鞘管5を挿入して固定したの
ち鋼管杭1内にコンクリート3を打設し、コンクリート
が固化する前又は固化したのち鞘管5内に鉄筋13を配
筋して鞘管5内にコンクリート14を打設する。そし
て、鞘管5内のコンクリート14が固化する前に鞘管5
内に柱材を建込み、鞘管5の上部に型枠17を設置して
型枠内にコンクリート14を打設し、柱材を鋼管杭1に
接合するようにしたものである。本実施の形態の効果
は、実施の形態1〜3の場合とほぼ同様である。
[Embodiment 4] In Embodiments 1 to 3,
The sheath tube 5 is inserted into the steel pipe pile 1 and the concrete 3 is poured. Before or after the concrete 3 is solidified, the reinforcing steel 13 is arranged in the sheath tube 5 and the column material is inserted, and the concrete 14 is inserted. Although the case of casting and joining is shown, in the present embodiment, after inserting and fixing the sheath tube 5 into the steel pipe pile 1, concrete 3 is poured into the steel pipe pile 1 and the concrete is solidified. Before or after solidification, reinforcing steel 13 is arranged in the sheath tube 5 and concrete 14 is poured into the sheath tube 5. And before the concrete 14 in the sheath tube 5 solidifies, the sheath tube 5
A pillar is built in the inside, a formwork 17 is installed on the upper part of the sheath tube 5, concrete 14 is poured into the formwork, and the pillar material is joined to the steel pipe pile 1. The effects of the present embodiment are almost the same as those of the first to third embodiments.

【0039】次に、本発明の要部をなす鞘管について説
明する。前述の図2に示す鞘管5は、内壁面に凸部7を
設けて鞘管5内に打設したコンクリート14の付着力を
向上させたものである。また、図13に示す鞘管5は外
壁面に凸部7を設けたもので、鋼管杭1内に打設したコ
ンクリート3の付着力を高めることにより、柱材からの
応力を鋼管杭1に円滑に伝達させ、引抜き力に対して抗
力として機能させるようにしたものである。さらに、図
10に示す鞘管5は内外壁面に凸部7を設けたもので、
内外のコンクリート3,14の付着力をさらに高めるこ
とができ、柱材からの応力を鋼管杭1に円滑に伝達さ
せ、引抜き力に対して抗力として機能させるようにした
ものである。
Next, the sheath tube which is a main part of the present invention will be described. The sheath tube 5 shown in FIG. 2 described above is provided with a projection 7 on the inner wall surface to improve the adhesive force of the concrete 14 cast into the sheath tube 5. The sheath pipe 5 shown in FIG. 13 is provided with a convex portion 7 on the outer wall surface, and by increasing the adhesive force of the concrete 3 cast into the steel pipe pile 1, the stress from the column material is applied to the steel pipe pile 1. It transmits smoothly and functions as a drag against the pull-out force. Further, the sheath tube 5 shown in FIG. 10 is provided with a projection 7 on the inner and outer wall surfaces.
The adhesive force between the inside and outside concretes 3 and 14 can be further increased, and the stress from the column material is smoothly transmitted to the steel pipe pile 1 so as to function as a drag against the pulling force.

【0040】ここに凸部7を有する鞘管5とは、内壁面
若しくは外壁面又は内外壁面に独立して突設された複数
の突起、リング状又はスパイラル状に所定の高さで突設
された複数の突部などを有する素材によって形成された
鞘管、あるいは、内壁面若しくは外壁面又は内外壁面に
鉄筋やスタッドなどを溶接等によって取付けて、コンク
リートの十分な付着力を有するように構成したものを総
称したものである。なお、前述の鋼管杭1あるいは鋼管
柱に設けた凸部2も、上記凸部7に準ずるものである。
Here, the sheath tube 5 having the convex portion 7 includes a plurality of protrusions independently protruding from the inner wall surface, the outer wall surface, or the inner and outer wall surfaces, and protrudingly formed at a predetermined height in a ring shape or a spiral shape. A sheath tube formed of a material having a plurality of protrusions or the like, or a reinforcing bar, a stud, or the like is attached to an inner wall surface, an outer wall surface, or an inner or outer wall surface by welding or the like, so as to have a sufficient adhesive force for concrete. It is a generic term for things. In addition, the above-mentioned convex part 2 provided in the steel pipe pile 1 or the steel pipe column also conforms to the above-mentioned convex part 7.

【0041】また、鞘管5の形状は断面多角形の筒状体
又は円筒体で底板6を有し、外部からコンクリートが侵
入しないようになっている。なお、底板6はフラットで
もよいが、コンクリートの流動性を考慮して錐状、球面
状等の凸状あるいは軸方向に対して斜めに形成するなど
してもよい。以下、鞘管5の形状の一例について説明す
る。なお、以下の説明では、内壁面若しくは外壁面又は
内外壁面に設けた凸部7は、図面には省略してある。
The shape of the sheath tube 5 is a cylindrical body or a cylindrical body having a polygonal cross section, and has a bottom plate 6 so that concrete does not enter from outside. Although the bottom plate 6 may be flat, it may be formed in a convex shape such as a conical shape or a spherical shape or formed obliquely with respect to the axial direction in consideration of the fluidity of the concrete. Hereinafter, an example of the shape of the sheath tube 5 will be described. In the following description, the protrusions 7 provided on the inner wall surface, the outer wall surface, or the inner and outer wall surfaces are omitted in the drawings.

【0042】図15(a)に示す鞘管5は、図2に示し
た鞘管5と同様に断面四角形で筒状に形成したもので、
底部には平板状の底板6が設けられている。図15
(b)に示す鞘管5は、図15(a)の鞘管5の底部を
角錐状の底板6aで形成したものである。なお、図15
(a),(b)の断面四角形の筒状の鞘管5は、断面四
角形以外の多角形の筒状体で構成してもよい。
The sheath tube 5 shown in FIG. 15A is formed in a tubular shape with a square cross section, similarly to the sheath tube 5 shown in FIG.
A flat bottom plate 6 is provided at the bottom. FIG.
The sheath tube 5 shown in (b) is obtained by forming the bottom of the sheath tube 5 of FIG. 15 (a) with a pyramidal bottom plate 6a. Note that FIG.
The tubular sheath tube 5 having a square cross section in FIGS. 7A and 7B may be formed of a polygonal cylindrical body other than a square cross section.

【0043】図15(c)の鞘管5は、鋼管等からなる
円筒状のもので、底部に平板状の底板6を設けたもので
ある。また、図15(d)の鞘管5は、図15(c)の
鞘管5の底部を球面状の底板6cで形成したものであ
り、図16(a)の鞘管5は、底部を円錐状の底板6c
で形成したものである。さらに、図16(b)の鞘管5
は、底部を傾斜して切除し、これに楕円形状の底板6d
を設けたものである。なお、図15、図16に示すよう
に、底部を下方に突出する凸状に形成することにより、
鋼管杭1内に打設したコンクリートが底部に沿って流動
し、鞘管5の底部の下方に空隙が生じるのを防止するこ
とができる。
The sheath tube 5 shown in FIG. 15C is a cylindrical tube made of a steel tube or the like, and has a flat bottom plate 6 provided at the bottom. Further, the sheath tube 5 of FIG. 15D is formed by forming the bottom of the sheath tube 5 of FIG. 15C with a spherical bottom plate 6c, and the sheath tube 5 of FIG. Conical bottom plate 6c
It is formed by. Further, the sheath tube 5 shown in FIG.
Cuts off the bottom part at an angle, and adds an elliptical bottom plate 6d.
Is provided. In addition, as shown in FIGS. 15 and 16, by forming the bottom in a convex shape protruding downward,
It is possible to prevent concrete poured into the steel pipe pile 1 from flowing along the bottom and to form a gap below the bottom of the sheath tube 5.

【0044】また、図16(c)の鞘管5は、剛性の高
いコルゲート材で形成したもので、底部には平板状の底
部6が設けられており、コンクリートの付着力を高める
ようにしたものである。なお、底板6を円錐状、球面状
あるいは傾斜面で形成してもよい。
The sheath tube 5 shown in FIG. 16C is made of a corrugated material having high rigidity, and is provided with a flat bottom 6 at the bottom to enhance the adhesive force of concrete. Things. The bottom plate 6 may be formed in a conical shape, a spherical shape, or an inclined surface.

【0045】なお、上述の各鞘管5において、底板6,
6a〜6dを鞘管5の外形より大きく形成して周囲に突
出させれば(図2参照)、コンクリート3の付着力を増
大させることができると共に、この突出部からコンクリ
ート3を介して鋼管杭1の凸部2に応力が伝達されるの
で、鞘管5の外壁面に設けた凸部7と同様に、コンクリ
ート3に埋込まれた鞘管5の引抜き力に対してより大き
い杭力として機能することができる。上記の鞘管5の形
状はその一例を示すもので、柱材の断面形状などにより
適宜選定することができる。
In each of the above-mentioned sheath tubes 5, the bottom plate 6,
If 6a to 6d are formed to be larger than the outer shape of the sheath tube 5 and protrude to the periphery (see FIG. 2), the adhesive force of the concrete 3 can be increased, and the steel pipe pile can be inserted from the protruding portion via the concrete 3. Since the stress is transmitted to the convex portion 2 of 1, as in the case of the convex portion 7 provided on the outer wall surface of the sheath tube 5, the pile force is larger than the pulling force of the sheath tube 5 embedded in the concrete 3. Can work. The shape of the above-mentioned sheath tube 5 shows one example, and can be appropriately selected depending on the cross-sectional shape of the column material and the like.

【0046】[0046]

【発明の効果】本発明に係る柱と杭の接合方法は、地盤
中に打設された鋼管杭内及び鋼管杭と鋼管杭の上部内に
取付けられた鞘管との間にコンクリートを打設し、この
コンクリートが固化する前又は固化したのち鞘管内に柱
材を建込んで鞘管内にコンクリートを打設するように
し、かつ、鋼管杭の打設後に鞘管を取付け、又はあらか
じめ鞘管が取付けられた鋼管杭を打設するようにしたの
で、次のような効果を得ることができる。
According to the method for joining a pillar and a pile according to the present invention, concrete is cast in a steel pipe pile installed in the ground and between a steel pipe pile and a sheath pipe mounted in an upper part of the steel pipe pile. And before or after this concrete is solidified, a pillar is built in the sheath pipe and concrete is poured into the sheath pipe, and after the steel pipe pile is cast, the sheath pipe is attached or the sheath pipe is Since the attached steel pipe pile is cast, the following effects can be obtained.

【0047】コンクリート相互の打ち継ぎが発生しない
ので、打ち継ぎ面の処理が不要であり、欠陥がなく強度
の高い接合構造とすることができる。また、鞘管を設け
たことにより、鋼管杭内及び鞘管内へのコンクリートの
打設が簡単になり、コンクリートのレベル調整も不要で
ある。さらに、鋼管杭内に打設したコンクリートを除去
したり、空洞部を形成するためのブロックを除去するた
めの手間が不要なので、施工工数を低減し、工期を短縮
することができる。また、鋼管杭を二重管構造としたの
で、柱と杭の接合部の剛性及び耐力を増大することがで
きる。
Since splicing between the concretes does not occur, there is no need to treat the splicing surface, and a joint structure having no defect and high strength can be obtained. In addition, the provision of the sheath pipe simplifies the casting of concrete into the steel pipe pile and the sheath pipe, and does not require any concrete level adjustment. Further, since it is not necessary to remove the concrete poured into the steel pipe pile or remove the block for forming the hollow portion, the number of construction steps can be reduced and the construction period can be shortened. In addition, since the steel pipe pile has a double pipe structure, the rigidity and strength of the joint between the column and the pile can be increased.

【0048】また、本発明に係る柱と杭の接合構造は、
地盤中に打設された鋼管杭と、この鋼管杭の上部内に取
付けられ鋼管杭との間にコンクリートが打設される鞘管
と、鞘管内に建込まれ鞘管との間にコンクリートが打設
される柱材とを備えたので、上記の同様の効果を得るこ
とができる。
The joint structure between the pillar and the pile according to the present invention is as follows.
A steel pipe pile installed in the ground, a sheath pipe installed inside the steel pipe pile and concrete poured between the steel pipe pile, and concrete between the sheath pipe built in the sheath pipe and concrete. Since it is provided with the pillar material to be cast, the same effect as described above can be obtained.

【0049】上記の鞘管を有底筒状に構成し、その底部
を平板状、凸状又は傾斜面状に形成したので、鋼管杭内
に打設したコンクリートが鞘管内に侵入するおそれがな
く、また、底部を凸状又は傾斜面状に形成することによ
り、鋼管杭内に打設したコンクリートが凸状部や傾斜面
に沿って流動し、鞘管の下方に空隙が生じるのを防止す
ることができる。
Since the above-mentioned sheath tube is formed in a cylindrical shape with a bottom and the bottom portion is formed in a flat plate shape, a convex shape, or an inclined surface shape, there is no possibility that concrete poured into the steel pipe pile enters the sheath tube. Also, by forming the bottom portion in a convex or inclined surface shape, concrete poured into the steel pipe pile flows along the convex portion and the inclined surface, thereby preventing a void from being formed below the sheath tube. be able to.

【0050】上記の底部を鞘管の外形より大きく形成し
て鞘管の周囲から突出するようにしたので、水平力や曲
げモーメントにより杭先端部に部分的に生じる引抜き力
に対して大きい抗力として機能することができる。
Since the bottom is formed to be larger than the outer shape of the sheath tube so as to protrude from the periphery of the sheath tube, the bottom portion has a large resistance against a pulling force partially generated at the tip of the pile due to a horizontal force or a bending moment. Can work.

【0051】上記の鞘管の内壁面若しくは外壁面又は内
外壁面に凸部を設けたので、コンクリートの付着力を高
め、柱材からの応力を鋼管杭に円滑に伝達することがで
きる。また、上記の鞘管を鋼骨又は剛性の高いコルゲー
ト材で構成したので、剛性を増加させることができる。
Since the inner wall surface, the outer wall surface, or the inner and outer wall surfaces of the above-mentioned sheath tube are provided with a convex portion, the adhesive force of concrete can be increased, and the stress from the column material can be smoothly transmitted to the steel pipe pile. In addition, since the above-mentioned sheath tube is made of a steel frame or a corrugated material having high rigidity, the rigidity can be increased.

【0052】また、上記の柱材を鉄骨鉄筋コンクリート
柱によって構成したので、耐震性に優れた上部構造物を
得ることができる。
Further, since the above-mentioned column member is constituted by a steel-framed reinforced concrete column, it is possible to obtain an upper structure excellent in earthquake resistance.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態1の説明図である。FIG. 1 is an explanatory diagram of a first embodiment of the present invention.

【図2】本発明の実施の形態2の平面図及び縦断面図で
ある。
FIG. 2 is a plan view and a longitudinal sectional view of a second embodiment of the present invention.

【図3】実施の形態2の施工方法の説明図である。FIG. 3 is an explanatory diagram of a construction method according to a second embodiment.

【図4】実施の形態2の鋼管杭に対する鞘管の取付手段
の一例を示す説明図である。
FIG. 4 is an explanatory view showing an example of a means for attaching a sheath pipe to a steel pipe pile according to a second embodiment.

【図5】実施の形態2の鋼管杭に対する鞘管の取付手段
の他の例を示す説明図である。
FIG. 5 is an explanatory view showing another example of the means for attaching the sheath pipe to the steel pipe pile according to the second embodiment.

【図6】本発明の作用効果の説明図である。FIG. 6 is an explanatory diagram of the operation and effect of the present invention.

【図7】本発明の作用効果の説明図である。FIG. 7 is an explanatory diagram of the operation and effect of the present invention.

【図8】本発明の作用効果の説明図である。FIG. 8 is an explanatory diagram of the operation and effect of the present invention.

【図9】本発明の作用効果の説明図である。FIG. 9 is an explanatory diagram of the operation and effect of the present invention.

【図10】本発明の作用効果の説明図である。FIG. 10 is an explanatory diagram of the operation and effect of the present invention.

【図11】本発明の作用効果の説明図である。FIG. 11 is an explanatory diagram of the operation and effect of the present invention.

【図12】実施の形態2の実施例の説明図である。FIG. 12 is an explanatory diagram of an example of the second embodiment.

【図13】実施の形態2の鞘管の他の例を示す平面図及
び縦断面図である。
13A and 13B are a plan view and a longitudinal sectional view showing another example of the sheath tube according to the second embodiment.

【図14】実施の形態2の鞘管の他の例を示す平面図及
び縦断面図である。
14A and 14B are a plan view and a longitudinal sectional view showing another example of the sheath tube according to the second embodiment.

【図15】鞘管の他の例を示す斜視図である。FIG. 15 is a perspective view showing another example of the sheath tube.

【図16】鞘管の他の例を示す斜視図である。FIG. 16 is a perspective view showing another example of the sheath tube.

【図17】従来の柱と杭の接合構造の一例を示す断面図
である。
FIG. 17 is a cross-sectional view showing an example of a conventional joint structure between a pillar and a pile.

【符号の説明】[Explanation of symbols]

1 場所打ち鋼管コンクリート杭(鋼管杭) 2,7 凸部 3,14 コンクリート 5 鞘管 10 柱材 11 鉄骨鉄筋コンクリート柱 12 鉄骨材 13 鉄筋 15,15a 固定部材 DESCRIPTION OF SYMBOLS 1 Cast-in-place steel pipe concrete pile (steel pipe pile) 2,7 Convex part 3,14 Concrete 5 Sheath pipe 10 Column material 11 Steel frame reinforced concrete column 12 Steel frame material 13 Reinforcement 15,15a Fixing member

───────────────────────────────────────────────────── フロントページの続き (72)発明者 佐藤 耕造 東京都千代田区丸の内一丁目1番2号 日 本鋼管株式会社内 ────────────────────────────────────────────────── ─── Continued on the front page (72) Inventor Kozo Sato Inside 1-2-1 Marunouchi, Chiyoda-ku, Tokyo Nihon Kokan Co., Ltd.

Claims (9)

【特許請求の範囲】[Claims] 【請求項1】 地盤中に打設された鋼管杭内及び該鋼管
杭と該鋼管杭の上部内に取付けられた鞘管との間にコン
クリートを打設し、該コンクリートが固化する前又は固
化したのち前記鞘管内に柱材を建込んで該鞘管内にコン
クリートを打設することを特徴とする柱と杭の接合方
法。
1. Concrete is cast in a steel pipe pile placed in the ground and between the steel pipe pile and a sheath pipe mounted in an upper part of the steel pipe pile, and before or after the concrete is solidified. After that, a pillar material is erected in the sheath pipe and concrete is poured into the sheath pipe, thereby joining the pillar and the pile.
【請求項2】 鋼管杭の打設後に鞘管を取付けることを
特徴とする請求項1記載の柱と杭の接合方法。
2. The method according to claim 1, wherein the sheath pipe is attached after the steel pipe pile is driven.
【請求項3】 鞘管があらかじめ鋼管杭に取付けられて
いることを特徴とする請求項1記載の柱と杭との接合方
法。
3. The method according to claim 1, wherein the sheath tube is attached to the steel pipe pile in advance.
【請求項4】 地盤中に打設された鋼管杭と、該鋼管杭
の上部内に取付けられ前記鋼管杭との間にコンクリート
が打設される鞘管と、該鞘管内に建て込まれ該鞘管との
間にコンクリートが打設される柱材とを備えたことを特
徴とする柱と杭の接合構造。
4. A steel pipe pile installed in the ground, a sheath pipe mounted in an upper portion of the steel pipe pile and cast concrete between the steel pipe pile and a steel pipe piled in the sheath pipe. A joint structure between a pillar and a pile, comprising a pillar material into which concrete is poured between the sheath tube and the sheath tube.
【請求項5】 鞘管を有底筒状に構成し、その底部を平
板状、凸状又は傾斜面状に形成したことを特徴とする請
求項4記載の柱と杭の接合構造。
5. The joint structure between a pillar and a pile according to claim 4, wherein the sheath tube is formed in a cylindrical shape with a bottom, and the bottom is formed in a flat plate shape, a convex shape, or an inclined surface shape.
【請求項6】 底部を鞘管の外形より大きく形成し、該
鞘管の周囲から突出させたことを特徴とする請求項5記
載の柱と杭の接合構造。
6. The joint structure between a column and a pile according to claim 5, wherein the bottom portion is formed to be larger than the outer shape of the sheath tube, and protrudes from the periphery of the sheath tube.
【請求項7】 鞘管の内壁面若しくは外壁面又は内外壁
面に凸部が形成されていることを特徴とする請求項4〜
6のいずれかに記載の柱と杭の接合構造。
7. A projection is formed on an inner wall surface, an outer wall surface, or an inner / outer wall surface of a sheath tube.
7. The joint structure between a pillar and a pile according to any one of 6.
【請求項8】 鞘管を鋼管又はコルゲート材で構成した
ことを特徴とする請求項4〜6の何れかに記載の柱と杭
の接合構造。
8. The joint structure between a column and a pile according to claim 4, wherein the sheath tube is made of a steel tube or a corrugated material.
【請求項9】 柱材を鉄骨鉄筋コンクリート柱によって
構成したことを特徴とする請求項4記載の柱と杭の接合
構造。
9. The joint structure between a column and a pile according to claim 4, wherein the column is made of a steel reinforced concrete column.
JP10286771A 1997-12-15 1998-10-08 Method of connecting column and pile and connecting structure Pending JPH11236713A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10286771A JPH11236713A (en) 1997-12-15 1998-10-08 Method of connecting column and pile and connecting structure

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP9-344698 1997-12-15
JP34469897 1997-12-15
JP10286771A JPH11236713A (en) 1997-12-15 1998-10-08 Method of connecting column and pile and connecting structure

Publications (1)

Publication Number Publication Date
JPH11236713A true JPH11236713A (en) 1999-08-31

Family

ID=26556446

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10286771A Pending JPH11236713A (en) 1997-12-15 1998-10-08 Method of connecting column and pile and connecting structure

Country Status (1)

Country Link
JP (1) JPH11236713A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008075385A (en) * 2006-09-22 2008-04-03 Ohbayashi Corp Method and structure for anchoring structural member for supporting
JP2011127344A (en) * 2009-12-18 2011-06-30 Sumitomo Mitsui Construction Co Ltd Joint structure of column and pile
JP2013253471A (en) * 2013-07-30 2013-12-19 Sumitomo Mitsui Construction Co Ltd Joint structure of column and pile
JP2020105762A (en) * 2018-12-27 2020-07-09 日鉄建材株式会社 Driftwood-trapping body and driftwood-trapping body construction method, and driftwood-trapping facility installation structure
JP2020105764A (en) * 2018-12-27 2020-07-09 日鉄建材株式会社 Driftwood-trapping body and driftwood-trapping body construction method, and driftwood-trapping facility installation structure
WO2020189049A1 (en) 2019-03-20 2020-09-24 ヤンマー株式会社 Construction machine

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008075385A (en) * 2006-09-22 2008-04-03 Ohbayashi Corp Method and structure for anchoring structural member for supporting
JP2011127344A (en) * 2009-12-18 2011-06-30 Sumitomo Mitsui Construction Co Ltd Joint structure of column and pile
JP2013253471A (en) * 2013-07-30 2013-12-19 Sumitomo Mitsui Construction Co Ltd Joint structure of column and pile
JP2020105762A (en) * 2018-12-27 2020-07-09 日鉄建材株式会社 Driftwood-trapping body and driftwood-trapping body construction method, and driftwood-trapping facility installation structure
JP2020105764A (en) * 2018-12-27 2020-07-09 日鉄建材株式会社 Driftwood-trapping body and driftwood-trapping body construction method, and driftwood-trapping facility installation structure
WO2020189049A1 (en) 2019-03-20 2020-09-24 ヤンマー株式会社 Construction machine
KR20210137449A (en) 2019-03-20 2021-11-17 얀마 파워 테크놀로지 가부시키가이샤 construction machinery
US12037765B2 (en) 2019-03-20 2024-07-16 Yanmar Power Technology Co., Ltd. Construction machine

Similar Documents

Publication Publication Date Title
JP4185870B2 (en) Pile head joint structure and pile construction method
JPH11236713A (en) Method of connecting column and pile and connecting structure
KR100631363B1 (en) Panel zone system of y shape tied column reinforced with high tension bolts
JP4440497B2 (en) Construction method of underground continuous wall and construction method of underground structure
JP3336295B2 (en) Joining method and joining structure of precast reinforced concrete shear walls
JP3062909B2 (en) Construction method of composite underground wall using soil cement column wall
JP3783386B2 (en) Joint method and foundation structure of column material and steel pipe pile in one pillar and one pile foundation
JPS61122320A (en) Method of coupling continuous underground wall with underground structure
JP3196412B2 (en) Cast-in-place steel pipe concrete pile-column structure and its construction method
JP4449595B2 (en) Column-beam joint structure, method for constructing column-beam joint structure, method for constructing underground structure, and building
JP2007051500A (en) Joint structure of column and pile
JPH0243848B2 (en)
JP4293297B2 (en) Construction method of structural pillars using ready-made piles
JPS61216914A (en) Method of fitting steel tubular pile with diagonal member or beam
JPH07292857A (en) Pc member with irregular-shaped steel pipe for joint, and connecting method thereof
KR102644085B1 (en) Steel outer casing molding jig coated with lining for drilling clearance
JP5054449B2 (en) Rehabilitation method of pile foundation structure
JPS61257529A (en) Underground continuous wall construction work
JP2005171480A (en) Joint structure of pile head part and method of constructing pile body
JP2009007750A (en) Connection structure of pile and column of steel construction building, and its construction method
JP4803438B2 (en) Existing foundation renovation structure and method
JP4178273B2 (en) Construction method of structural pillars using ready-made piles
JPS6135359B2 (en)
JPH08199565A (en) Pile head joint construction of cast-in-place concrete pile
JPH04185816A (en) Construction of beam in underground wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040528

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050920

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060221