JPH11190022A - Working method for foundation pile - Google Patents

Working method for foundation pile

Info

Publication number
JPH11190022A
JPH11190022A JP9359085A JP35908597A JPH11190022A JP H11190022 A JPH11190022 A JP H11190022A JP 9359085 A JP9359085 A JP 9359085A JP 35908597 A JP35908597 A JP 35908597A JP H11190022 A JPH11190022 A JP H11190022A
Authority
JP
Japan
Prior art keywords
steel pipe
pile
pipe pile
tip
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9359085A
Other languages
Japanese (ja)
Inventor
Toshio Enoki
敏男 榎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ENOKI KINUE
Original Assignee
ENOKI KINUE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ENOKI KINUE filed Critical ENOKI KINUE
Priority to JP9359085A priority Critical patent/JPH11190022A/en
Publication of JPH11190022A publication Critical patent/JPH11190022A/en
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a working method for foundation pile capable of fully preventing corrosion of steel pipe pile, of creating a high bearing power by tip with the smallest discharge of surplus soil. SOLUTION: After inserting a steel pipe casing 1 into ground, sediment inside is taken out, a steel pipe pile 3 having an enlarged shoe 7 and apertures in the peripheral wall is inserted until the enlarged shoe 7 at the bottom tip reaches a predetermined depth, thereafter, the steel pipe casing 1 is pulled out by a predetermined distance, a screw type filling machine is inserted to the inside of the steel pipe pile, wet concrete is poured to the outer side through the inner side of the tip portion and apertures 9 to a predetermined height, then the steel pipe casing 1 is pulled out, and the foundation pipe is completed after backfilling to the inner and outer sides of the steel pipe pile 3. Then, the foundation pile having the steel pipe pile 1 with strong, thick wall, its enlarged shoe 7 at the tip, and concrete masses inside and outside the tip portion are firmly set in the bearing layer, thereby providing a high tip bearing power, and the vicinities of the foundation pile are fully covered with cement milk, and the occurrence of corrosion at the steel pipe pile 3 can be completely prevented.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、強大な支持力と
耐久性に優れ、コスト的にも有利な基礎杭の施工法に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a foundation pile, which has excellent bearing capacity and durability, and is advantageous in cost.

【0002】[0002]

【従来の技術】日本列島の活断層は、北海道から九州ま
で全国に分布しており、主なものだけでも約1500箇
所あるといわれている。
2. Description of the Related Art Active faults in the Japanese archipelago are distributed nationwide from Hokkaido to Kyushu, and it is said that there are about 1,500 active faults alone.

【0003】活断層の活動で起きた最近の地震では、福
井地震、伊豆大島近海地震、ごく最近の阪神淡路大震災
があり、阪神淡路大震災では、鉄筋、鉄骨コンクリート
の建造物の基礎構造が不完全なため、大小の建物や構造
物が崩壊している。
[0003] Recent earthquakes caused by the activity of active faults include the Fukui earthquake, the Izu-Oshima coastal earthquake, and the very recent Hanshin-Awaji earthquake. In the Great Hanshin-Awaji earthquake, the basic structure of steel bars and steel-framed concrete structures is incomplete. For this reason, large and small buildings and structures have collapsed.

【0004】今回の阪神淡路大震災後の調査によると、
PHCコンクリート杭による基礎杭や場所打ちコンクリ
ート杭の基礎杭では、強力地震エネルギーには、中高層
建物や一般高架高速道路でも、強度不足である結果が現
れているという事実が多く判明した。これからは、中高
層建物や一般高架高速道路は勿論、特に高層建物には地
震エネルギーに十分耐えられる基礎杭が不可欠である。
According to a survey after the Great Hanshin-Awaji Earthquake,
It has become clear that the strong seismic energy of the foundation pile made of the PHC concrete pile and the cast-in-place concrete pile has a result that the strength is insufficient even in middle-high-rise buildings and general elevated expressways. From now on, foundation piles that can withstand earthquake energy are indispensable for high-rise buildings as well as middle- and high-rise buildings and general elevated expressways.

【0005】従来、鋼管杭を用いた基礎杭の施工法は、
鋼管杭を地中に挿入し、鋼管杭の先端が支持層に侵入し
てから先端掘削ヘッドで拡掘し、鋼管杭内に挿入したト
レミー管で拡掘した部分に根固めセメントミルクを注入
し、先端支持力の増大を図った後、鋼管杭内をコンクリ
ートで埋めるようにしていた。
Conventionally, a method of constructing a foundation pile using a steel pipe pile is as follows.
After inserting the steel pipe pile into the ground, the tip of the steel pipe pile penetrates into the support layer, then excavate with the tip excavation head, and inject the cement milk into the part excavated with the tremy pipe inserted into the steel pipe pile. After increasing the bearing capacity at the tip, the inside of the steel pipe pile was filled with concrete.

【0006】[0006]

【発明が解決しようとする課題】ところで、上記のよう
な、従来の施工法による基礎杭は、根固めのためのセメ
ントミルクが、地下水の浸透などで十分な大きさに固ま
らず、強固な先端支持力が得られないと共に、鋼管杭の
地中への挿入によって発生する残土の排出量が多く、そ
の処理コストが高くつき、しかも、鋼管杭の外周面は直
接土砂に接触するので、腐食の発生が甚だしく、耐久性
に劣るという問題がある。
In the above-mentioned foundation pile made by the conventional construction method, cement milk for consolidation does not harden to a sufficient size due to infiltration of groundwater or the like. In addition to the lack of bearing capacity, the amount of residual soil generated when the steel pipe pile is inserted into the ground is large, and the disposal cost is high.Moreover, since the outer peripheral surface of the steel pipe pile is in direct contact with soil, corrosion There is a problem that the occurrence is extremely large and the durability is poor.

【0007】そこで、この発明の課題は、強固な先端支
持力が得られると共に、残土の排出量が少なく、かつ、
鋼管杭の腐食発生を完全に防止できる基礎杭の施工法を
提供することにある。
Therefore, an object of the present invention is to provide a strong tip supporting force, a small amount of residual soil discharged, and
An object of the present invention is to provide a method for constructing a foundation pile that can completely prevent corrosion of steel pipe piles.

【0008】[0008]

【課題を解決するための手段】上記のような課題を解決
するため、請求項1の発明は、地中に鋼管ケーシングを
所定深度に達するまで挿入する工程と、地中に挿入した
鋼管ケーシング内の土砂を排土する工程と、下部先端に
拡大部と周壁に通孔を有する鋼管杭を、排土後の鋼管ケ
ーシング内に上記下部先端の拡大部が所定深度まで達す
るように挿入する工程と、鋼管ケーシングを所定量引き
抜くと共に、鋼管杭内にスクリュー式の充填機を挿入
し、鋼管杭の先端部内側および通孔を介して外側にコン
クリートを所定高さまで充填する工程と、鋼管ケーシン
グを引き抜くと共に、鋼管杭の内外を埋め戻す工程とを
経る構成を採用したものである。
In order to solve the above-mentioned problems, the invention of claim 1 comprises a step of inserting a steel pipe casing into the ground until a predetermined depth is reached, and a step of inserting the steel pipe casing into the ground. Removing the earth and sand, and inserting a steel pipe pile having an enlarged portion at the lower end and a through hole in the peripheral wall, so that the enlarged portion at the lower end reaches a predetermined depth in the steel pipe casing after the earth discharging. A step of extracting the steel pipe casing by a predetermined amount, inserting a screw-type filling machine into the steel pipe pile, filling concrete to a predetermined height inside the tip end of the steel pipe pile and outside through the through hole, and pulling out the steel pipe casing. In addition, a configuration is adopted in which a step of backfilling the inside and outside of the steel pipe pile is performed.

【0009】ここで、鋼管ケーシングの地中への挿入
は、地上に設置した圧入機によって行い、鋼管ケーシン
グ内の排土は、クレーンにつり下げたバケットで掘り出
すと共に、鋼管杭の外側は砂とセメント溶液の混合物
で、同じく内側は掘削土とセメント溶液の混合物で埋め
戻すことにより、鋼管杭の内外を覆って該鋼管杭の腐食
発生を完全に防止する。
[0009] Here, the steel pipe casing is inserted into the ground by a press-fitting machine installed on the ground, and the soil in the steel pipe casing is excavated by a bucket suspended by a crane. The mixture of the cement solution, which is also backfilled with the mixture of the excavated soil and the cement solution, covers the inside and outside of the steel pipe pile and completely prevents the corrosion of the steel pipe pile.

【0010】[0010]

【発明の実施の形態】以下、この発明の実施の形態を図
示例と共に説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0011】この発明の施工法には、鋼管ケーシング1
と、この鋼管ケーシング1を地中に圧入する圧入機2
と、鋼管ケーシング1内に挿入する鋼管杭3と、鋼管ケ
ーシング1内の土砂を排土するためのバケット4と、鋼
管杭3内にコンクリートを投入するためのスクリュー式
の充填機5と、これらの各部材を吊り下げるためのクレ
ーン6とが用いられる。
[0011] In the construction method of the present invention, the steel pipe casing 1
And a press-fitting machine 2 for press-fitting the steel pipe casing 1 into the ground.
A steel pipe pile 3 inserted into the steel pipe casing 1, a bucket 4 for discharging earth and sand in the steel pipe casing 1, a screw-type filling machine 5 for putting concrete into the steel pipe pile 3, And a crane 6 for suspending each member.

【0012】図1は、鋼管杭3の先端構造を示し、厚肉
で大口径の鋼管杭3の先端部外周面に拡大シュー7が電
弧溶接によって強固に固定され、この鋼管杭3の先端内
部に拡大シュー7と略等しい高さの補強板8が十字状等
に設けてある。
FIG. 1 shows the tip structure of the steel pipe pile 3. An enlarged shoe 7 is firmly fixed to the outer peripheral surface of the tip of the thick steel pipe pile 3 by electric arc welding. A reinforcing plate 8 having a height substantially equal to that of the enlarged shoe 7 is provided in a cross shape or the like.

【0013】上記拡大シュー7は、鋼管杭3の外周面で
四箇所の位置に固定し、拡大シュー7の外径Dは、鋼管
杭3の外径dに対し、D=d×(1.25〜1.3)が
適当であり、高さは2dとする。
The enlarged shoes 7 are fixed at four positions on the outer peripheral surface of the steel pipe pile 3, and the outer diameter D of the enlarged shoes 7 is D = d × (1. 25-1.3) is appropriate, and the height is 2d.

【0014】また、鋼管杭3の周壁で先端から2.5d
〜3dの位置に通孔9が設けられ、この通孔9の周囲は
溶接した鋼板10で補強してある。なお、拡大シュー7
の数や外径、高さ等は支持層地盤の条件によって適宜選
択すればよい。
Further, 2.5 d from the tip of the peripheral wall of the steel pipe pile 3.
A through hole 9 is provided at a position of ~ 3d, and the periphery of the through hole 9 is reinforced with a welded steel plate 10. In addition, the expansion shoe 7
, The outer diameter, the height, etc. may be appropriately selected depending on the conditions of the ground of the support layer.

【0015】鋼管ケーシング1は、拡大シュー7の外径
に対して内径が約15〜30cm程度大径の鋼管を用い、
継ぎ足すための連結部分がねじれに対して十分な強度を
有する構造になっている。この鋼管ケーシング1を地中
に圧入する圧入機2は、図示詳細を略したが、鋼管ケー
シング1を強固にチャッキングし、該ケーシング1に全
回転又は半回転を与えると同時に、これを地中に押し込
み又は引き抜く周知の機能と構造を有するものである。
The steel pipe casing 1 uses a steel pipe having an inner diameter of about 15 to 30 cm with respect to the outer diameter of the enlarged shoe 7.
The connecting portion for adding is configured to have sufficient strength against torsion. The press-fitting machine 2 for press-fitting the steel pipe casing 1 into the ground, which is not shown in the drawings, firmly chucks the steel pipe casing 1 and gives the casing 1 a full rotation or a half rotation, and simultaneously presses the casing 1 under the ground. It has a well-known function and structure for pushing or pulling it out.

【0016】上記スクリュー式の充填機5は、鋼管杭3
内に挿入するケーシング11の内部にピッチの大きいス
クリュー12を組み込み、ケーシング11の上端にホッ
パー13を設け、ケーシング11の上部にスクリュー1
2を回転させる減速モータ14を取り付けた構造になっ
ている。
The screw-type filling machine 5 includes a steel pipe pile 3
A screw 12 having a large pitch is incorporated into a casing 11 inserted into the casing 11, a hopper 13 is provided at an upper end of the casing 11, and a screw 1 is provided at an upper part of the casing 11.
2 is equipped with a deceleration motor 14 for rotating the motor 2.

【0017】次に、この発明の施工法を図2と図3を用
いて説明する。
Next, the construction method of the present invention will be described with reference to FIGS.

【0018】先ず、図2(A)のように、地上に圧入機
2を設置し、クレーン6で吊り込んだ鋼管ケーシング1
を圧入機2にセットし、圧入機2の作動で鋼管ケーシン
グ1を地中に圧入し、該ケーシング1の圧入と継ぎ足し
を繰り返すことにより、図2(B)の如く、鋼管ケーシ
ング1の下部先端が支持地盤15に達するように圧入す
る。
First, as shown in FIG. 2A, a press-fitting machine 2 is installed on the ground, and a steel pipe casing 1 suspended by a crane 6.
Is set in the press-fitting machine 2, the steel pipe casing 1 is press-fitted into the ground by the operation of the press-fitting machine 2, and the press-fitting and adding of the casing 1 are repeated, as shown in FIG. Is press-fitted so as to reach the support ground 15.

【0019】図2(B)の如く、地中に鋼管ケーシング
1の圧入が完了すると、クレーン6にバケット4をセッ
トし、鋼管ケーシング1内の土壌や荒石土、大径の玉石
を砕きながら鋼管ケーシング1の外部に排土する。
As shown in FIG. 2 (B), when the press-fitting of the steel pipe casing 1 into the ground is completed, the bucket 4 is set on the crane 6, and the steel pipe is crushed while crushing the soil, rubble soil and large-diameter cobblestone in the steel pipe casing 1. The soil is discharged outside the casing 1.

【0020】鋼管ケーシング1内の底部における残存土
壌を入念にかきだし、排土が完了すると、図2(C)の
如く、クレーン6に鋼管杭3をセットし、該鋼管杭3の
下部先端の拡大シュー7が支持地盤15に達するよう
に、鋼管ケーシング1内に鋼管杭3を挿入する。
When the residual soil at the bottom of the steel pipe casing 1 is carefully scraped out and the discharge is completed, the steel pipe pile 3 is set on the crane 6 as shown in FIG. The steel pipe pile 3 is inserted into the steel pipe casing 1 so that the shoe 7 reaches the support ground 15.

【0021】次に、図3(A)のように、鋼管杭3の内
部に充填機5をケーシング11の下端が補強板8に近接
するように挿入し、この状態で、軟状セメントをホッパ
ー13に投入し、スクリュー12の回転でこれを鋼管杭
3の拡底部分に送りこむ。
Next, as shown in FIG. 3A, the filling machine 5 is inserted into the steel pipe pile 3 such that the lower end of the casing 11 is close to the reinforcing plate 8, and in this state, the soft cement is put into the hopper. The steel pipe pile 3 is fed into the steel pipe pile 3 by the rotation of the screw 12.

【0022】充填機5は、ケーシング11の内部にピッ
チの大きなスクリュー12を組み込み、これを回転させ
て軟状セメントを送るので、従来のトレミー管に比べ
て、軟状セメントを分離することのないよう、円滑かつ
迅速に拡底部に送り込むことができる。
The filling machine 5 incorporates a screw 12 having a large pitch inside the casing 11 and rotates the screw 12 to feed the soft cement, so that the soft cement is not separated as compared with the conventional tremy tube. As a result, it is possible to smoothly and promptly feed into the expanded bottom portion.

【0023】図3(B)のように、軟状セメントは、鋼
管杭3の内部に拡底部から4dの高さ程度まで打ち込
み、このとき、鋼管ケーシング1を拡底から4dの高さ
程度まで引き抜くことにより、軟状セメントは通孔9を
通って鋼管杭3の外部にも流出し、鋼管杭3と土壌の間
を拡底部から4dの高さ程度まで埋めることになり、こ
れによって、軟状セメントの硬化で鋼管杭3の先端に杭
頭ができる。
As shown in FIG. 3 (B), the soft cement is driven into the inside of the steel pipe pile 3 to a height of about 4 d from the expanded bottom, and at this time, the steel pipe casing 1 is pulled out to a height of about 4 d from the expanded bottom. As a result, the soft cement flows out of the steel pipe pile 3 through the through-hole 9 and fills the space between the steel pipe pile 3 and the soil to a height of about 4d from the expanded bottom, whereby the soft cement is softened. A pile head is formed at the tip of the steel pipe pile 3 by hardening of the cement.

【0024】この後、鋼管ケーシング1と鋼管杭3の間
の隙間に良質の砂を充填しつつ、鋼管ケーシング1を引
き抜くと共に、鋼管杭3の内部には先に掘削排土した残
土をユンボ等の重機を用いて充填する。上記砂と残土に
は適量のセメント溶液を混合しておき、図3(C)の如
く、鋼管杭3の内外をセメント硬化物で覆って施工を完
了し、基礎杭を完成する。
After that, while filling the gap between the steel pipe casing 1 and the steel pipe pile 3 with good-quality sand, the steel pipe casing 1 is pulled out, and the excavated and excavated soil is removed into the inside of the steel pipe pile 3 by a dumbbell or the like. Using a heavy machine. An appropriate amount of a cement solution is mixed in the sand and the residual soil, and as shown in FIG. 3 (C), the inside and outside of the steel pipe pile 3 is covered with a hardened cement to complete the construction, thereby completing the foundation pile.

【0025】上記のように構築された基礎杭の先端は、
強靱な厚肉鋼管杭とその先端拡大シュー7及び先端部内
外のコンクリート塊が堅固に支持地盤15にセットさ
れ、先端は強大な支持力を発揮し、かつ、基礎杭の周辺
は完全にセメントミルクで覆われ、強力なフリクション
効果を発揮する。
The tip of the foundation pile constructed as described above is
The tough steel pipe pile, its tip-enlarged shoe 7 and the concrete mass inside and outside the tip are firmly set on the supporting ground 15, the tip exerts a strong supporting force, and the periphery of the foundation pile is completely cement milk. Covered with a powerful friction effect.

【0026】また、基礎杭の内外は、セメントミルクで
固められた永久腐食のない状態となり、強大な地震エネ
ルギーに最も適した強力な基礎杭となる。
In addition, the inside and outside of the foundation pile are in a state without permanent corrosion hardened with cement milk, and become a strong foundation pile most suitable for strong earthquake energy.

【0027】[0027]

【発明の効果】以上のように、この発明によると、地中
に鋼管ケーシングを所定深度に達するまで挿入した後内
部の土砂を排土し、下部先端に拡大部と周壁に通孔を有
する鋼管杭を、排土後の鋼管ケーシング内に上記下部先
端の拡大部が所定深度まで達するように挿入し、この
後、鋼管ケーシングを所定量引き抜くと共に、鋼管杭内
にスクリュー式の充填機を挿入し、鋼管杭の先端部内側
および通孔を介して外側にコンクリートを所定高さまで
充填し、鋼管ケーシングを引き抜くと共に、鋼管杭の内
外を埋め戻すようにしたので、完成した基礎杭は、強靱
な厚肉の鋼管杭とその先端拡大シュー及び先端部内外の
コンクリート塊が堅固に支持層にセットされ、強固な先
端支持力が得られると共に、基礎杭の周辺は完全なセメ
ントミルクにより覆われ、鋼管杭の腐食発生を完全に防
止できる。
As described above, according to the present invention, after inserting a steel pipe casing into the ground until the steel pipe reaches a predetermined depth, the inside of the steel pipe is discharged, and the steel pipe having an enlarged portion at the lower end and a through hole in the peripheral wall is provided. The pile is inserted into the steel pipe casing after discharging so that the enlarged portion at the lower end reaches a predetermined depth, and thereafter, the steel pipe casing is pulled out by a predetermined amount, and a screw-type filling machine is inserted into the steel pipe pile. The concrete was filled to the specified height inside and outside through the steel pipe pile tip and through the through hole, the steel pipe casing was pulled out, and the inside and outside of the steel pipe pile were backfilled. The meat steel pipe pile, its tip expansion shoe, and the concrete mass inside and outside the tip are firmly set on the support layer to obtain a strong tip support force, and the periphery of the foundation pile is covered with complete cement milk. It is, completely prevent corrosion occurrence of the steel pipe pile.

【0028】また、鋼管ケーシング内の掘削で生じた排
土は、鋼管杭内に埋め戻し使用するので、残土の発生が
少ないと共に、残土は汚泥化されていないので、処理コ
ストも少なくてすむ。
Further, since the earth removal generated by excavation in the steel pipe casing is backfilled in the steel pipe pile, the generation of the remaining soil is small, and the remaining soil is not sludge, so that the processing cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】(A)は鋼管杭の下部構造を示す正面図、
(B)は同上の横断平面図
FIG. 1A is a front view showing a lower structure of a steel pipe pile,
(B) is a cross-sectional plan view of the above.

【図2】(A)乃至(C)は基礎杭の構築法の前半の工
程を順番に示す説明図
FIGS. 2A to 2C are explanatory diagrams sequentially showing the first half steps of a method for constructing a foundation pile.

【図3】(A)乃至(C)は基礎杭の構築法の後半の工
程を順番に示す説明図
FIGS. 3A to 3C are explanatory diagrams sequentially showing the second half of the steps of the method for constructing a foundation pile.

【符号の説明】[Explanation of symbols]

1 鋼管ケーシング 2 圧入機 3 鋼管杭 4 バケット 5 充填機 6 クレーン 7 拡大シュー 8 補強板 9 通孔 10 鋼板 11 ケーシング 12 スクリュー 13 ホッパー 14 減速モータ REFERENCE SIGNS LIST 1 steel pipe casing 2 press-fitting machine 3 steel pipe pile 4 bucket 5 filling machine 6 crane 7 magnifying shoe 8 reinforcing plate 9 through hole 10 steel plate 11 casing 12 screw 13 hopper 14 deceleration motor

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地中に鋼管ケーシングを所定深度に達す
るまで挿入する工程と、地中に挿入した鋼管ケーシング
内の土砂を排土する工程と、下部先端に拡大部と周壁に
通孔を有する鋼管杭を、排土後の鋼管ケーシング内に上
記下部先端の拡大部が所定深度まで達するように挿入す
る工程と、鋼管ケーシングを所定量引き抜くと共に、鋼
管杭内にスクリュー式の充填機を挿入し、鋼管杭の先端
部内側および通孔を介して外側にコンクリートを所定高
さまで充填する工程と、鋼管ケーシングを引き抜くと共
に、鋼管杭の内外を埋め戻す工程とを経ることを特徴と
する基礎杭の施工法。
1. A step of inserting a steel pipe casing into the ground until a predetermined depth is reached, a step of discharging earth and sand in the steel pipe casing inserted into the ground, and an enlarged portion at a lower end and a through hole in a peripheral wall. A step of inserting the steel pipe pile into the steel pipe casing after discharging so that the enlarged portion at the lower end reaches a predetermined depth, and withdrawing the steel pipe casing by a predetermined amount, and inserting a screw-type filling machine into the steel pipe pile. A step of filling concrete to the predetermined height inside and outside through the tip end of the steel pipe pile and a step of pulling out the steel pipe casing and backfilling the inside and outside of the steel pipe pile, Construction method.
JP9359085A 1997-12-26 1997-12-26 Working method for foundation pile Pending JPH11190022A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9359085A JPH11190022A (en) 1997-12-26 1997-12-26 Working method for foundation pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9359085A JPH11190022A (en) 1997-12-26 1997-12-26 Working method for foundation pile

Publications (1)

Publication Number Publication Date
JPH11190022A true JPH11190022A (en) 1999-07-13

Family

ID=18462671

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9359085A Pending JPH11190022A (en) 1997-12-26 1997-12-26 Working method for foundation pile

Country Status (1)

Country Link
JP (1) JPH11190022A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040048710A (en) * 2002-12-04 2004-06-10 주식회사 스마텍엔지니어링 End Tip Apparatus for Reducing Opening Cross Section of Pipe Pile
JP2012112163A (en) * 2010-11-24 2012-06-14 Takenaka Komuten Co Ltd Pile construction method in contaminated soil
JP2015137472A (en) * 2014-01-21 2015-07-30 株式会社技研製作所 Steel pipe pile and press-in method for the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040048710A (en) * 2002-12-04 2004-06-10 주식회사 스마텍엔지니어링 End Tip Apparatus for Reducing Opening Cross Section of Pipe Pile
JP2012112163A (en) * 2010-11-24 2012-06-14 Takenaka Komuten Co Ltd Pile construction method in contaminated soil
JP2015137472A (en) * 2014-01-21 2015-07-30 株式会社技研製作所 Steel pipe pile and press-in method for the same

Similar Documents

Publication Publication Date Title
JPH11107273A (en) Construction method of cast-in-place pile
GB2154630A (en) Construction method for foundation piling
JPH11190022A (en) Working method for foundation pile
JPS62242011A (en) Method and apparatus for constructing shallow ground-improving pile
KR101765879B1 (en) Composite block for ground reinforcement and reinforceing method of the foundation bottom using the same
GB2132667A (en) Method of installing precast concrete piles
JP3702435B2 (en) How to build the foundation
JP3144767B2 (en) Underground pile forming method and apparatus
JP2000352053A (en) Existing pile dismantling construction method
JP7160297B1 (en) Pile foundation with soil improvement and its construction method
JPH0280710A (en) Preparing cast-in-place concrete pile
JPH03257215A (en) Pile constructing method
JP3794097B2 (en) Construction method for underground structures
JP4132320B2 (en) Foundation construction method
JP7462531B2 (en) Pile extraction method
JP2881501B2 (en) Construction method for high strength cast-in-place concrete piles
JP3637945B2 (en) Construction method of base-isolated building by reverse driving method
JP3065228B2 (en) How to build a building foundation
JP2810957B2 (en) Pile foundation method
JPS6110624A (en) Pile erecting method
JP2019143328A (en) Building installation structure and installation method
JP2006138091A (en) Construction method for burying tank and the like
JP2022108444A (en) Reinforcement method for existing bank
JPH1077642A (en) Foundation structure of building and construction method therefor and excavating machine for soil improvement
JPS59233028A (en) Residential land formation work on sloped ground

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees