JPH0796786B2 - Construction method of cloth foundation concrete having footing and waste form used therefor - Google Patents

Construction method of cloth foundation concrete having footing and waste form used therefor

Info

Publication number
JPH0796786B2
JPH0796786B2 JP63311917A JP31191788A JPH0796786B2 JP H0796786 B2 JPH0796786 B2 JP H0796786B2 JP 63311917 A JP63311917 A JP 63311917A JP 31191788 A JP31191788 A JP 31191788A JP H0796786 B2 JPH0796786 B2 JP H0796786B2
Authority
JP
Japan
Prior art keywords
footing
concrete
cloth foundation
frame
foundation concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP63311917A
Other languages
Japanese (ja)
Other versions
JPH02157325A (en
Inventor
雄一 飯塚
靖公 福原
日出男 室
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Nisshin Co Ltd
Original Assignee
Nisshin Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nisshin Steel Co Ltd filed Critical Nisshin Steel Co Ltd
Priority to JP63311917A priority Critical patent/JPH0796786B2/en
Publication of JPH02157325A publication Critical patent/JPH02157325A/en
Publication of JPH0796786B2 publication Critical patent/JPH0796786B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Foundations (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は短時間内に行うコンクリート打設により、そし
て少なくとも直立部の型枠を回収することなく一挙に築
造することのできるフーチング部を有する布基礎コンク
リートの築造方法及び該方法の実施に使用する布基礎コ
ンクリート用の捨型枠に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention has a footing portion that can be built at once by concrete pouring within a short time, and at least without collecting the formwork of the upright portion. The present invention relates to a method for constructing a cloth-based concrete and a scrap frame for the cloth-based concrete used for carrying out the method.

〔従来の技術〕[Conventional technology]

エキスパンドメタルやメタルラスなど金網類や波形金属
板などを型枠に使用する布基礎コンクリートの築造は、
例えば特開昭52−42605号などに開示されている如く広
く実施されている。第4図は従来の布基礎コンクリート
の1例を長さ方向に直角に切断して示す斜視図である。
この第4図のように割栗石8上にフーチング部1aを有す
る直立部1bから成る布基礎コンクリート1(以下、フー
チング部付布基礎コンクリートと言うことがある)を築
造する場合には、従来は先ず割栗石8上に捨コンクリー
ト9を打設した後、フーチング部1aの側面1aaを形成さ
せる堰坂を捨コンクリート9上の両側に配置固定しコン
クリートを打設してその打設したコンクリートが一定の
強度を発現してフーチング部1aとなると、次にこのフー
チング部1aの上に直立部1bの側面1baを形成される型枠
を設置してコンクリートを打設してその打設したコンク
リートが一定の強度を発現して直立部1bとなつて布基礎
コンクリートが築造されていたのである。
Construction of cloth foundation concrete using wire mesh such as expanded metal and metal lath and corrugated metal plate as the formwork,
For example, it is widely practiced as disclosed in JP-A-52-42605. FIG. 4 is a perspective view showing an example of a conventional cloth foundation concrete cut at a right angle to the length direction.
In the case of constructing a cloth foundation concrete 1 (hereinafter sometimes referred to as a footing portion cloth foundation concrete) consisting of an upright portion 1b having a footing portion 1a on a split stone 8 as shown in FIG. First of all, after pouring the waste concrete 9 on the split stones 8, the weir slopes that form the side surface 1aa of the footing portion 1a are arranged and fixed on both sides of the waste concrete 9 and the concrete is poured, and the cast concrete is constant. When the footing portion 1a is developed by exhibiting the strength of, the side face 1ba of the upright portion 1b is installed on the footing portion 1a, and the concrete is placed by placing the concrete, and the placed concrete is constant. That is, the cloth foundation concrete was constructed by connecting the upright portion 1b with the strength of.

このように従来はフーチング部用と直立部用との2度に
分けてコンクリートを打設していたため、第1回目のコ
ンクリートを打設した後に養生期間が必要で、速やかに
次の作業に移れないため工期が長びき、しかも直立部1b
とフーチング部1aとの間にコンクリートの打ち継目がで
きて強度が弱くなるという欠点があつた。
In this way, conventionally, the concrete was placed twice for the footing part and for the upright part. Therefore, a curing period is required after the first concrete is placed, and the next work can be promptly performed. Since it does not have a long construction period, the upright part 1b
However, there is a drawback that a concrete joint is formed between the footing part 1a and the footing part 1a, and the strength is weakened.

このような欠点の解消を目指し、布基礎コンクリート1
を一度に築造しようとしてフーチング部1aと直立部1bと
の各側面1aa,1baを形成させる全ての型枠を組んでから
全コンクリートを一度に打設することも考えられるが、
この場合には打設時にコンクリートの圧力により型枠が
浮き上がつたり、フーチング部1aの側面1aaを形成され
る堰坂上縁から打設したコンクリートが流出する現象が
発生し、このような現象の発生を防止するためには特殊
な対策を必要とするなどのためコストアツプとなり、一
挙に全コンクリートを打設することの実施は事実上極め
て困難であつた。
Aiming to eliminate such defects, cloth foundation concrete 1
It is conceivable to construct all the forms at once by assembling all the formwork that forms each side surface 1aa, 1ba of the footing portion 1a and the upright portion 1b in an attempt to build at once.
In this case, the formwork may float due to the pressure of the concrete during pouring, or the poured concrete may flow out from the upper edge of the weir slope that forms the side surface 1aa of the footing portion 1a. Since it requires special measures to prevent the occurrence of the above, it is costly and it is virtually difficult to place all the concrete at once.

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

本発明は上記従来技術の欠点を解消し、短時間内に行う
コンクリート打設によりそして少なくとも直立部の型枠
を回収することなく、フーチング部付布基礎コンクリー
トの築造を竪固に且つ工期短く実施できるようにするこ
とを課題とする。
The present invention solves the above-mentioned drawbacks of the prior art, and by constructing concrete with footing parts firmly and in a short period of time, by performing concrete pouring within a short time and at least without collecting the formwork of the upright part. The challenge is to be able to do so.

〔課題を解決するための手段〕[Means for Solving the Problems]

本発明者らは種々検討した結果、2個のハツト形状を連
結した特殊な形状の金属条を所定の間隔で平行に捨コン
クリート上に固定すれば、この金属条に型枠を固定又は
保持させることによつて型枠の位置決めが容易であると
共に、直立部の側面形成に主要部が金網から成る網枠を
使用すればその網枠は以後取り外すことの無い捨型枠と
して使用出来てその直立部はその外面に露出する側面を
モルタル仕上げするだけで済み、更にこの網枠の金網の
下縁をフーチング部の堰板上縁以下の高さに位置せしめ
ることにより直立部とフーチング部との間にコンクリー
トの打ち継目ができなくなつて、前記課題を解決できる
ことを究明して本発明を完成したのである。
As a result of various studies by the present inventors, if metal strips of a special shape in which two hat shapes are connected are disposed in parallel at a predetermined interval and fixed on concrete, the metal strips fix or hold the formwork. As a result, it is easy to position the formwork, and if a mesh frame whose main part is a wire mesh is used to form the side surface of the upright portion, the mesh frame can be used as a scrap frame that will not be removed later, The part only needs to be mortared on the side exposed on the outer surface, and the lower edge of the wire mesh of this net frame is positioned at a height below the upper edge of the dam plate of the footing part so that the space between the upright part and the footing part is The present invention has been completed by clarifying that the above-mentioned problems can be solved by making concrete joints impossible.

以下、本発明方法の実施に好適な本発明に係る捨型枠を
図面により説明する。
Hereinafter, a scrap frame according to the present invention suitable for carrying out the method of the present invention will be described with reference to the drawings.

第1図は本発明に係るフーチング部を有する布基礎コン
クリート用の捨型枠の1実施例を組立て途中の状態で示
す斜視図、第2図は第1図の捨型枠中に使用されている
2連門型金属条の1例を示す斜視図、第3図は本発明方
法によつて築造されたフーチング部付布基礎コンクリー
トの斜視図である。
FIG. 1 is a perspective view showing an embodiment of a scrap frame for a cloth foundation concrete having a footing portion according to the present invention in a state of being assembled, and FIG. 2 is used in the scrap frame of FIG. FIG. 3 is a perspective view showing an example of a double-barrier type metal strip, and FIG. 3 is a perspective view of a cloth foundation concrete with a footing portion built by the method of the present invention.

図面中、3は本発明において使用する2連門型金属条で
あって、第2図に示す如くウエブ部3bとその両側のフラ
ンジ部3cと更にその両側のリツプ部3aとから成るハツト
形状の2つがリツプ部3aで直列で連結された形状を成し
ていてそれらのウエブ部3bとフランジ部3cとで2つの門
部が形成されている。この2連門型金属条3は、後に説
明する単位網枠5の取付けのために図例の如く細幅の金
属帯をその長手方向に対して直角に順次折曲して製作さ
れたものであり、捨コンクリート9へ固定する場合のた
めに各リツプ部3aに固定用穴3aaが穿設されていること
が好ましい。また、この2連門型金属条3はその素材が
変形し難いものであれば、両端のリツプ部3aの一方又は
両方がなくても実用上差し支えはない。また2連門型金
属条3の両側の門を構成する各2つのフランジ部3cのう
ちの内側のフランジ部3cには、後に説明する単位網枠5
の竪枠5bの下部を固定するためのボルト挿通用の竪長穴
3caが穿設されており、更にその内側のフランジ部3cの
両縁にはそれぞれ相対向する内側のフランジ部3c側に向
けて後に説明する単位網枠5の竪枠5bの下部を挟持する
挟持片3cbが突設されていることが好ましい。このよう
な2連門型金属条3の複数個が第1図に示す如くウエブ
部3bを上にして平行に所定の間隔(後記する単位網枠5
の長さに相当する)に捨コンクリート9上にコンクリー
ト釘で固定される。
In the drawings, reference numeral 3 denotes a double-barrier metal strip used in the present invention, which has a hat-like shape composed of a web portion 3b, flange portions 3c on both sides thereof, and lip portions 3a on both sides thereof as shown in FIG. The two have a shape in which they are connected in series by a rip portion 3a, and the web portion 3b and the flange portion 3c form two gate portions. The double-barbed metal strip 3 is manufactured by sequentially bending a narrow metal strip at right angles to its longitudinal direction as shown in the figure for mounting the unit mesh frame 5 described later. Therefore, it is preferable that fixing holes 3aa are formed in each of the lip portions 3a for fixing to the waste concrete 9. Further, as long as the material of the double gate type metal strip 3 is hard to be deformed, there is no practical problem even if one or both of the lip portions 3a at both ends are not provided. Further, a unit mesh frame 5 to be described later is provided on the inner flange portion 3c of the two flange portions 3c forming the gates on both sides of the double-barbed metal strip 3.
Vertical hole for bolt insertion to fix the lower part of vertical frame 5b
3ca is punched, and further, on both edges of the inner flange portion 3c, the lower portion of the vertical frame 5b of the unit mesh frame 5, which will be described later, is clamped toward the inner flange portion 3c side facing each other. It is preferable that the piece 3cb is provided so as to project. As shown in FIG. 1, a plurality of such double-barbed metal strips 3 are arranged in parallel with the web portion 3b facing upward at a predetermined interval (a unit mesh frame 5 to be described later).
(Corresponding to the length of 1) is fixed to the concrete 9 with concrete nails.

4は布基礎コンクリート1のフーチング部1aの側面1aa
を形成させる堰板であつて、2連門型金属条3の2つの
門部のそれぞれの外側部に沿つて配置される。この堰板
4としては第1図に示す如き波型金属板の他、フーチン
グ部1aの幅や高さに応じて平面状の金属板や木質合板等
の材料を適宜選ぶことができ、この堰坂4は2連門型金
属条3の門部の外側部すなわち門部を構成する各2つの
フランジ部3cのうちの外側のフランジ部3cの内面に沿つ
て配置される場合にはコンクリートの打設後に取り外さ
れることは無いが、2連門型金属条3の門部の外側部の
外面に沿つて配置される場合にはコンクリートの打設後
に取り外して再使用されるものが一般に使用される。
4 is a side surface 1aa of the footing portion 1a of the cloth foundation concrete 1.
And a barrier plate for forming the two gates of the double-barbed metal strip 3 arranged along the outer sides of the respective gates. As the weir plate 4, in addition to the corrugated metal plate as shown in FIG. 1, materials such as a flat metal plate and wood plywood can be appropriately selected according to the width and height of the footing portion 1a. When the slope 4 is arranged along the inner surface of the outer flange portion 3c of the two flange portions 3c forming the gate portion, that is, the outside portion of the gate portion of the double-barbed metal strip 3, the concrete is poured. It is not removed after installation, but if it is placed along the outer surface of the outer part of the gate of the double-barbed metal strip 3, it is generally used after removal of concrete and reuse. .

5は布基礎コンクリート1の直立部1bの側面1baを形成
する網枠を構成する単位網枠であつて、主要部が矩形状
の金網、好ましくは長手方向に平行に所定間隔で補強帯
5cが設けられている金網から成つていて、少なくとも金
網の長さ方向の両側縁に溶接やボルト・ナツトやブライ
ンドリベツトなどの手段で固定されている竪枠5bが金網
の下縁5aより下方に突設されており、その突設部に前記
2連門型金属条3の内側のフランジ部3cに穿設されてい
る竪長穴3caに挿通されるボルト挿通用のボルト穴5baが
穿設されている。そしてこのような単位網枠5は、第1
図に示す如く2連門型金属条3の両側の門部それぞれの
内側のフランジ部3cの内側面に接して単位網枠5の竪枠
5bの下部を位置せしめ、金網の下縁5aがフーチング部1a
の側面1aaの上縁以下の高さとなり且つ単位網枠5の上
縁が直立部1bのほぼ上縁の高さとなるように高さ調整し
て2連門型金属条3の内側のフランジ部3cに穿設されて
いる竪長穴3caと単位網枠5の竪枠5bの下部に穿設され
ているボルト穴5baに挿通して螺合されるボルト・ナツ
ト7によつて固定される。この単位網枠5は、布基礎コ
ンクリート1の直立部1bの両側面1baを形成する両側の
単位網枠5同士が、細幅の金属帯をその長手方向に対し
て順次所定の角度で折曲して製作された連続帯状体やハ
ツト形状やみぞ形状やZ形状などの折板金属材より成る
間隔維持手段6により所定の間隔(直立部1bの厚さに相
当する)を隔てて相対して並立されている。この間隔維
持手段6の取付個所数は、打設するコンクリートの難度
や布基礎コンクリート1の直立部1bの大きさにもよる
が、打設するコンクリートにより単位網枠5が変形しな
いように補強できる数が必要で、通常上下方向で少なく
とも1ケ所、多くとも4ケ所で良い。そして最終的には
前記の位置にある単位網枠5が各側においてその長さ方
向に隙間なく隣接し連結されて相対する網枠を形成する
のである。この際、フーチング部材布基礎コンクリート
1の或る箇所において次に連続する部分の存在しない切
断面状の端部が存在する場合には、その築造に使用する
捨型枠2の当該端部はコンクリート打設時にコンクリー
トの流出を防止してフーチング部1a及び直立部1bの形状
を正常に形成させるためにそれぞれの端面の位置におい
て第1図中に示す如く堰坂4及び単位網枠5により閉塞
される。
Reference numeral 5 is a unit mesh frame that constitutes a mesh frame that forms the side surface 1ba of the upright portion 1b of the cloth foundation concrete 1. The main portion of the mesh frame is a rectangular metal mesh, preferably a reinforcing band at predetermined intervals parallel to the longitudinal direction.
The vertical frame 5b is made of wire mesh provided with 5c and is fixed to at least both side edges in the length direction of the wire mesh by means such as welding or bolt nuts or blind rivets. A bolt hole 5ba for inserting a bolt is formed in the protruding portion, and the protruding portion has a vertical elongated hole 3ca formed in a flange portion 3c on the inner side of the double-barbed metal strip 3. It is set up. In addition, such a unit net frame 5 has a first
As shown in the figure, the vertical frame of the unit mesh frame 5 is in contact with the inner side surfaces of the flange portions 3c on the inner sides of the gate portions on both sides of the double-barbed metal strip 3.
Position the lower part of 5b so that the bottom edge 5a of the wire mesh is the footing part 1a.
Adjust the height so that the height is less than the upper edge of the side surface 1aa of the unit and the upper edge of the unit net frame 5 is almost the height of the upper edge of the upright portion 1b, and the inner flange portion of the double-gate metal strip 3 is adjusted. It is fixed by a bolt nut 7 which is inserted through and screwed into a vertical hole 3ca formed in 3c and a bolt hole 5ba formed in the lower portion of the vertical frame 5b of the unit mesh frame 5. In this unit mesh frame 5, the unit mesh frames 5 on both sides forming the both side surfaces 1ba of the upright portion 1b of the cloth foundation concrete 1 are formed by bending a narrow metal strip at a predetermined angle in the longitudinal direction. The distance maintaining means 6 made of a continuous strip or a bent plate metal material having a hat shape, a groove shape, a Z shape, etc., which are manufactured by the above, are opposed to each other at a predetermined interval (corresponding to the thickness of the upright portion 1b). It is lined up. The number of places where the spacing maintaining means 6 is attached depends on the difficulty of the concrete to be placed and the size of the upright portion 1b of the cloth foundation concrete 1, but can be reinforced so that the unit mesh frame 5 is not deformed by the concrete to be placed. The number is required, and usually at least one place in the vertical direction, and at most four places is sufficient. Finally, the unit mesh frames 5 at the above-mentioned positions are adjacently connected to each other without gaps in the lengthwise direction on each side to form a mesh frame facing each other. At this time, if there is a cut surface-shaped end portion where there is no next continuous portion at a certain portion of the footing member cloth foundation concrete 1, the end portion of the scrap frame 2 used for the construction is made of concrete. In order to prevent concrete from flowing out during pouring and to properly form the shapes of the footing portion 1a and the upright portion 1b, they are closed by weir slopes 4 and unit mesh frames 5 at the positions of the respective end faces as shown in FIG. It

〔作 用〕[Work]

本発明に係るフーチング部を有する布基礎コンクリート
用の捨型枠2を前記の如く構成する各部材の具体的な連
結態様の1例を以下に第1図によつて組立て手順と共に
説明する。
An example of a concrete connection mode of each member constituting the scrap frame 2 for cloth foundation concrete having a footing portion according to the present invention will be described below with reference to FIG. 1 together with an assembling procedure.

先ず、金網の少なくとも両側縁にその下縁5aより下部が
下方に突設された状態に竪枠5bを固定されている単位網
枠5を準備する。図例では、軽量溝型鋼より成る竪枠5b
が使用されていてそのウエブ部が端面となつており、長
手方向に平行に所定間隔で補強帯5cが設けられている金
網の側部が竪枠5bの外側フランジ部の内面に固着されて
いて、竪枠5bの金網の下縁5aより下方に突設されている
突設部にはボルト挿通用のボルト穴5baが突設されてい
ると共に、金網の側縁が位置していないウエブ部には所
定間隔で隣接する単位網枠5同士を連結するボルト挿通
用のボルト穴が穿設されている。そしてこの単位網枠5
同士は、相対向せしめられてその相対向している単位網
枠5同士をハツト形状とZ形状との折板金属材とより成
る間隔維持手段6によりボルト・ナツトやブラインドリ
ベツトにより連結せしめられて、相対向している単位網
枠5間の間隔が一定となりその間にコンクリートが打設
されても金網が膨れることがないように維持されてい
る。
First, a unit mesh frame 5 having a vertical frame 5b fixed to at least both side edges of a wire mesh so that a lower portion thereof is projected downward from its lower edge 5a is prepared. In the example shown, the vertical frame 5b made of lightweight channel steel
The web part is used as an end face, and the side part of the wire mesh provided with the reinforcing bands 5c at predetermined intervals parallel to the longitudinal direction is fixed to the inner surface of the outer flange part of the vertical frame 5b. , A bolt hole 5ba for inserting a bolt is projected on the projecting portion projecting below the lower edge 5a of the wire mesh of the vertical frame 5b, and at the web portion where the side edge of the wire mesh is not located. Has a bolt hole for inserting a bolt that connects the unit net frames 5 adjacent to each other at a predetermined interval. And this unit net frame 5
The unit mesh frames 5 facing each other are connected to each other by bolts, nuts or blind rivets by means of a spacing maintaining means 6 made of a hat-shaped and Z-shaped folded plate metal material. Thus, the interval between the unit mesh frames 5 facing each other becomes constant, and it is maintained so that the wire net does not swell even if concrete is poured in the interval.

次に、第1図に示す如く2連門型金属条3を所定の間隔
(単位網枠5の長さ)で捨コンクリート9の上面9aに平
行に置いて並べ、2連門型金属条件3のリツプ部3aに固
定用穴3aaが穿設されている場合にはこの固定用穴3aaを
貫通させて、また2連門型金属条3のリツプ部3aに固定
用穴3aaが穿設されていない場合にはリツプ部3aにコン
クリート用釘を打ち込んで2連門型金属条3を捨コンク
リート9に固定する。この場合、2連門型金属条3の固
定位置を調整する必要が生じる場合があるので、リツプ
部3aに固定用穴3aaが穿設されている場合にはこの固定
用穴3aaは2連門型金属条3を構成する細幅の金属帯の
長さ方向に平行な長穴であることが好ましい。次いでフ
ーチング部1aの側面1aaを形成する堰板4を、前記2連
門型金属条3の最外側のフランジ部3cの内側に沿つてそ
れぞれ配置するのであるが、フーチング部1aの側面1aa
を形成する堰板4を前記2連門型金属条3の最外側のフ
ランジ部3cの内側に沿つてそれぞれ配置する場合には、
先ず堰板4を2連門型金属条3の両側の門部内に挿通し
ておいてから捨コンクリート9に2連門型金属条3を固
定する作業を行うことが好ましい。しかる後単位網枠5
の両側の竪枠5bの下部の側面に穿設されているボルト穴
5baを2連門型金属条3の内側のフランジ部3cの縦長穴3
caに合わせてボルト7を貫通させ、単位網枠5の金網の
下縁5aが堰板4の上縁4a以下の高さに位置し且つ単位網
枠5の金網の下縁5aがフーチング部1aの上縁とほぼ合致
するようにその上下方向の位置に調節してボルト・ナツ
ト7で固定する。相対する側についても同様に行い2つ
の単位網枠5を相対して並立せしめる。そして隣接する
2連門型金属条3についても前記と同様に2つの単位網
枠5を取り付け、長さ方向に隣接する単位網枠5の竪枠
5b同士に穿設されているボルト穴にボルトを挿通してナ
ツトにより両者を間隔なく連結する。このようにして本
発明に係るフーチング部を有する布基礎コンクリート用
の捨型枠2は組み立てられる。
Next, as shown in FIG. 1, the two-barrier type metal strips 3 are arranged at predetermined intervals (the length of the unit mesh frame 5) in parallel with the upper surface 9a of the waste concrete 9, and the two-barrier type metal condition 3 When the fixing hole 3aa is formed in the lip portion 3a of the above, the fixing hole 3aa is penetrated, and the fixing hole 3aa is formed in the lip portion 3a of the double-gate type metal strip 3. If not, the nail for concrete is driven into the rip portion 3a to fix the double-barbed metal strip 3 to the scrap concrete 9. In this case, it may be necessary to adjust the fixing position of the double-barrel type metal strip 3. Therefore, when the fixing hole 3aa is formed in the lip portion 3a, the fixing hole 3aa has two double gates. It is preferably an elongated hole parallel to the length direction of the narrow metal strip forming the metal mold strip 3. Then, the barrier plates 4 forming the side surface 1aa of the footing portion 1a are respectively arranged along the inner side of the outermost flange portion 3c of the double-barrier metal strip 3, and the side surface 1aa of the footing portion 1a is arranged.
In the case of arranging the barrier plates 4 forming the above along the inside of the outermost flange portion 3c of the double-barrier metal strip 3,
First, it is preferable to insert the dam plate 4 into the gate portions on both sides of the double-barrier metal strip 3 and then fix the double-barrel metal strip 3 to the waste concrete 9. After that, the unit net frame 5
Bolt holes formed on the lower side surfaces of the vertical frame 5b on both sides of the
5ba is a vertical hole 3 in the flange 3c inside the double-barbed metal strip 3
The bolt 7 is penetrated according to ca, the lower edge 5a of the wire mesh of the unit mesh frame 5 is located at a height lower than the upper edge 4a of the dam plate 4, and the lower edge 5a of the wire mesh of the unit mesh frame 5 is the footing portion 1a. Adjust it to the vertical position so that it almost coincides with the upper edge, and fix it with bolts and nuts 7. The same is done for the opposite sides, and the two unit net frames 5 are made to stand side by side. Then, for the two adjacent double-bar type metal strips 3, two unit net frames 5 are attached in the same manner as described above, and the vertical frames of the unit net frames 5 adjacent in the length direction are attached.
Insert the bolts into the bolt holes that are drilled between the 5b's, and connect the two without gaps with a nut. In this way, the scrap frame 2 for the cloth foundation concrete having the footing portion according to the present invention is assembled.

このようにして組み立てられた本発明に係るフーチング
部を有する布基礎コンクリート用の捨型枠2にコンクリ
ートを打設するには、並立する単位網枠5の間及び堰板
4と単位網枠5との間に、前者では網枠の上縁まで、後
者では堰板4の上縁4aまでそれぞれコンクリートを流し
込めば良い。このとき、前者と後者とは下部で通じてい
て且つ前者の方が流し込み完了時の高さが高く、下部で
コンクリートの若干量が前者から後者へ移動するので、
コンクリート流し込みの完了は後者を先に、前者を後に
するのが好ましい。
In order to place concrete in the waste form frame 2 for cloth foundation concrete having the footing portion according to the present invention assembled in this way, between the unit mesh frames 5 standing in parallel and between the weir plate 4 and the unit mesh frame 5 In the former, concrete may be poured to the upper edge of the net frame in the former, and to the upper edge 4a of the dam plate 4 in the latter. At this time, the former and the latter communicate with each other at the bottom and the former has a higher height when pouring is completed, and some amount of concrete moves from the former to the latter at the bottom,
It is preferable to complete the concrete pouring with the latter first and the former later.

なお、フーチング部付布基礎コンクリート1中に鉄筋を
入れるのが普通であり、この場合は予め鉄筋を組んでか
ら両側に堰板4間の底面に沿つて及び単位網枠5間に竪
方向に沿つて鉄筋を配置してからコンクリートを打設す
る。
In addition, it is usual to put reinforcing bars in the cloth foundation concrete with footing part 1. In this case, after reinforcing bars are assembled in advance, the reinforcing bars are arranged on both sides along the bottom surface between the weir plates 4 and in the vertical direction between the unit mesh frames 5. Place the reinforcing bars alongside and then place concrete.

そしてフーチング部用の及び直立部用のコンクリートを
打設した後に、堰板4を2連門型金属条3の門部を構成
する各2つのフランジ部3cのうちの外側のフランジ部3c
の内面に沿つて配置される場合にはそのまま、2連門型
金属条3の門部を構成する各2つのフランジ部3cのうち
の外側のフランジ部3cの外面に沿つ配置される場合には
必要に応じて取り外した後、直立部1bの側面1baをモル
タル仕上げし、フーチング部1aの面又はそれ以上の高さ
まで埋め戻せば、第3図に示す如きフーチング部付布基
礎コンクリート1が完成するのである。
Then, after placing concrete for the footing portion and for the upright portion, the weir plate 4 is placed on the outer flange portion 3c of the two flange portions 3c that form the gate portion of the double-barbed metal strip 3.
When it is arranged along the outer surface of the outer flange portion 3c of the two flange portions 3c forming the gate portion of the double-barbed metal strip 3 when arranged along the inner surface of the After removing as needed, mortar finish the side surface 1ba of the upright portion 1b and backfill to the surface of the footing portion 1a or a height higher than that, to complete the cloth foundation concrete 1 with footing portion as shown in Fig. 3. To do.

〔発明の効果〕〔The invention's effect〕

以上詳述した如き本発明に係るフーチング部を有する布
基礎コンクリートの築造方法によれば、フーチング部付
布基礎コンクリート1を築造するに当り、2つのハツト
形状がリツプ部3aで直列に連結された形状の2連門型金
属条3の複数個をウエブ部3bを上にして所定の間隔で平
行に捨コンクリート9上に固定することによつて、フー
チング部1aの側面1aaを形成させる堰板4をこの2連門
型金属条3の最外側のフランジ部3cに沿つてそれぞれ配
置し、直立部1bの側面1baを形成するための主要部が金
網から成り両側縁に少なくとも竪枠5bが固定されている
と共にその竪枠5bの下端が金網の下縁5aより下方に突出
されている単位網枠5を金網の下縁5aがフーチング部1a
の側面1aaの上縁以下の高さとなり且つ金網の上縁が直
立部1bのほぼ上縁の高さとなるように高さ調整して前記
2連門型金属条3の両側の門を構成する各2つのフラン
ジ部3cのうちの内側のフランジ部3cの内側面にそれぞれ
前記竪枠5bを固定することによつて両単位網枠5間に所
定の間隔を維持させて相対して並立せしめることができ
るので、フーチング部用及び直立部用のコンクリートを
短時間内に打設できるためフーチング部用と直立部用と
の2度に分けてコンクリートを打設する必要がないので
第1回目のコンクリートを打設した後の養生期間が必要
なくなつて速やかに次の作業に移れて工期を大幅に短縮
できると共に直立部1bとフーチング部1aとの間にコンク
リートの打ち継目が生じないので強度が弱くなるという
欠点もなく、本発明に係るフーチング部を有する布基礎
コンクリートの捨型枠2を使用すれば比較的安価な材料
を使用して組立が容易であると共に諸部材を回収使用し
ないから施工全体を非常に能率良く実施することができ
るのであり、しかも打設されたコンクリートは直立部1b
の外面に露出する側面をモルタル仕上げすることより外
観も良好なものとなるのであり、建築分野に貢献すると
ころの非常に大きなものである。
According to the method for constructing the cloth foundation concrete having the footing portion according to the present invention as described in detail above, when the cloth foundation concrete 1 with the footing portion is constructed, two hat shapes are connected in series by the rip portion 3a. The weir plate 4 for forming the side surface 1aa of the footing portion 1a by fixing a plurality of double-barrel-shaped metal strips 3 in a parallel shape with the web portion 3b facing upward at predetermined intervals in parallel on the waste concrete 9 Are arranged along the outermost flange portion 3c of the double-barbed metal strip 3, and the main part for forming the side surface 1ba of the upright portion 1b is made of wire mesh and at least the vertical frame 5b is fixed to both side edges. In addition, the lower edge of the vertical frame 5b is projected downward from the lower edge 5a of the wire mesh.
The gates on both sides of the double-barbed metal strip 3 are formed by adjusting the height so that the height is equal to or lower than the upper edge of the side surface 1aa and the upper edge of the wire mesh is almost the same as the upper edge of the upright portion 1b. By fixing the vertical frame 5b to the inner surface of the inner flange portion 3c of each of the two flange portions 3c, the unit mesh frames 5 can be maintained in parallel with each other while maintaining a predetermined space. Since it is possible to place the concrete for the footing part and the upright part in a short time, it is not necessary to place the concrete for the footing part and the upright part separately in two times. There is no need for a curing period after pouring, and the work can be moved to the next work promptly, and the construction period can be greatly shortened.Because there is no concrete joint between the upright part 1b and the footing part 1a, the strength is weak. The present invention has no drawback that If the scrap frame 2 of the cloth foundation concrete having the footing part is used, the relatively inexpensive material is used, the assembling is easy, and the members are not collected and used, so that the entire construction can be carried out very efficiently. Moreover, the placed concrete is upright part 1b.
The appearance is improved by mortaring the side exposed on the outer surface of the building, which is a great contribution to the construction field.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明に係るフーチング部を有する布基礎コン
クリート用の捨型枠1の実施例を組立て途中の状態で示
す斜視図、第2図は第1図の捨型枠中に使用されている
2連門型金属条の1例を示す斜視図、第3図は本発明方
法によつて築造されたフーチング部付布基礎コンクリー
トの斜視図、第4図は従来の布基礎コンクリートの1例
を長さ方向に直角に切断して示す斜視図である。 図面中 1……フーチング部付布基礎コンクリート 1a……フーチング部 1aa……フーチング部の側面 1b……直立部 1ba……直立部の側面 2……本発明に係る捨型枠 3……2連門型金属条 3a……リツプ部 3aa……固定用穴 3b……ウエブ部 3c……フランジ部 3ca……竪長穴 3cb……狭持片 4……堰板 4a……上縁 5……単位網枠 5a……金網の下縁 5b……竪枠 5ba……ボルト穴 5c……補強帯 6……間隔維持手段 7……ボルト・ナツト 8……割栗石 9……捨コンクリート 9a……上面
FIG. 1 is a perspective view showing an embodiment of a scrap frame 1 for cloth foundation concrete having a footing portion according to the present invention in a state of being assembled, and FIG. 2 is used in the scrap frame of FIG. Fig. 3 is a perspective view showing an example of a double-barreled metal strip, Fig. 3 is a perspective view of a cloth foundation concrete with a footing portion built by the method of the present invention, and Fig. 4 is an example of a conventional cloth foundation concrete. It is a perspective view which cuts and is perpendicular to a length direction. In the drawing 1 …… Fabric concrete with footing part 1a …… Footing part 1aa …… Side of footing part 1b …… Upright part 1ba …… Side surface of upright part 2 …… Scraping frame according to the present invention 3 …… Two stations Gate-shaped metal strip 3a ...... Rip part 3aa …… Fixing hole 3b …… Web part 3c …… Flange part 3ca …… Vertical slot 3cb …… Holding piece 4 …… Weir plate 4a …… Upper edge 5 …… Unit mesh frame 5a …… Lower edge of wire mesh 5b …… Vertical frame 5ba …… Bolt hole 5c …… Reinforcing band 6 …… Interval maintenance means 7 …… Bolts and nuts 8 …… Split quarry stones 9 …… Waste concrete 9a …… Top

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 昭58−168725(JP,A) 実開 昭62−175152(JP,U) 実開 昭56−159447(JP,U) 実開 昭62−89331(JP,U) 実公 昭62−12032(JP,Y2) ─────────────────────────────────────────────────── ─── Continuation of the front page (56) Reference JP-A-58-168725 (JP, A) Actually open 62-175152 (JP, U) Actually open 56-159447 (JP, U) Actually open 62- 89331 (JP, U) Actual public Sho 62-12032 (JP, Y2)

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】フーチング部(1a)とその上に一体に設け
られる直立部(1b)とから成る布基礎コンクリート
(1)を築造するに際し、2つのハツト形状がリツプ部
(3a)で直列に連結された形状の2連門型金属条(3)
の複数個をウエブ部(3b)を上にして所定の間隔で平行
に捨コンクリート(9)上に固定した後、フーチング部
(1a)の側面(1aa)を形成させる堰坂(4)をこの2
連門型金属条(3)の最外側のフランジ部(3c)に沿つ
てそれぞれ配置し、直立部(1b)の側面(1ba)を形成
するための主要部が金網から成り両側縁に少なくとも竪
枠(5b)が固定されていると共にその竪枠(5b)の下端
が金網の下縁(5a)より下方に突出されている単位網枠
(5)を金網の下縁(5a)フーチング部(1a)の側面
(1aa)の上縁以下の高さとなり且つ金網の上縁が直立
部(1b)のほぼ上縁の高さとなるように高さ調整して前
記2連門型金属条(3)の両側の門を構成する各2つの
フランジ部(3c)のうちの内側のフランジ部(3c)の内
側面にそれぞれ前記竪枠(5b)を固定することによつて
両単位網枠(5)間に所定の間隔を維持させて相対して
並立せしめ、しかる後にフーチング部用及び直立部用の
コンクリートを短時間内に打設した後に、少なくとも直
立部(1b)の外面に露出する側面をモルタル仕上げする
ことを特徴とするフーチング部を有する布基礎コンクリ
ートの築造方法。
1. When building a cloth foundation concrete (1) consisting of a footing portion (1a) and an upright portion (1b) integrally provided on the footing portion, two hat shapes are connected in series at the rip portion (3a). Two-bar type metal strips of linked shape (3)
After fixing a plurality of these to the concrete (9) in parallel at a predetermined interval with the web part (3b) facing up, the weir slope (4) forming the side surface (1aa) of the footing part (1a) is formed. Two
They are arranged along the outermost flange part (3c) of the articulated metal strip (3), and the main part for forming the side surface (1ba) of the upright part (1b) is made of wire mesh and has at least a vertical edge on both sides. The unit mesh frame (5), in which the frame (5b) is fixed and the lower end of the vertical frame (5b) is projected below the lower edge (5a) of the wire mesh, is used as a footing portion (5a) of the wire mesh. The height is adjusted to be lower than the upper edge of the side surface (1aa) of 1a) and the upper edge of the wire mesh is substantially the same as the upper edge of the upright portion (1b). ), The vertical frame (5b) is fixed to the inner side surface of the inner flange portion (3c) of the two flange portions (3c) that form the gates on both sides, so that both unit mesh frames (5 ) And make them stand side by side at a predetermined interval, and then pour concrete for footing and upright within a short time. A method for constructing a cloth foundation concrete having a footing portion, characterized by mortaring at least the side surface exposed to the outer surface of the upright portion (1b).
【請求項2】2連門型金属条(3)の両側の門を構成す
る各2つのフランジ部(3c)のうちの内側のフランジ部
(3c)の内側面にそれぞれ竪枠(5b)を固定することに
よつて所定の間隔を維持させて相対して並立せしめる両
単位網枠(5)にその間隔を規定する間隔維持手段
(6)を固定せしめておく請求項1に記載のフーチング
部を有する布基礎コンクリートの築造方法。
2. A vertical frame (5b) is provided on the inner surface of the inner flange portion (3c) of the two flange portions (3c) forming the gates on both sides of the double-barbed metal strip (3). 2. The footing part according to claim 1, wherein the spacing maintaining means (6) for defining the spacing is fixed to both unit mesh frames (5) which are fixed to each other so as to be parallel to each other while maintaining a predetermined spacing. Method of constructing cloth foundation concrete having.
【請求項3】両側の堰坂(4)間の底面に沿つて及び単
位網枠(5)間に縦方向に沿つて鉄筋が組まれている状
態でコンクリートを打設する請求項1又は2に記載のフ
ーチング部を有する布基礎コンクリートの築造方法。
3. The concrete is placed in a state where rebars are assembled along the bottom surface between the weir slopes (4) on both sides and along the longitudinal direction between the unit mesh frames (5). A method for constructing a cloth foundation concrete having a footing part according to.
【請求項4】フーチング部(1a)とその上に一体に設け
られる直立部(1b)とから成る布基礎コンクリート
(1)を築造するのに使用されるコンクリート打設用の
捨型枠であつて、捨コンクリート(9)上にウエブ部
(3b)を上にして所定の間隔で平行に固定される2つの
ハツト形状がリツプ部(3a)で直列に連結された形状の
複数個の2連門型金属条(3)と、両側縁に少なくとも
竪枠(5b)が固定されていると共にその竪枠(5b)の下
端が金網の下縁(5a)より下方に突出されていて金網の
下縁(5a)がフーチング部(1a)の側面(1aa)の上縁
以下の高さとなり且つ金網の上縁が直立部(1b)のほぼ
上縁の高さとなるように高さ調整されて前記2連門型金
属条(3)の両側の門を構成する各2つのフランジ部
(3c)のうちの内側のフランジ部(3c)の内側面にそれ
ぞれ前記竪枠(5b)を固定される直立部(1b)の側面
(1ba)を形成するための主要部が金網から成る単位網
枠(5)と、該両側の単位網枠(5)に固着されて該両
側の単位網(5)を所定の間隔を隔てて相対して並立せ
しめる間隔維持手段(6)とより成ることを特徴とする
フーチング部を有する布基礎コンクリート用の捨型枠
(2)。
4. A waste formwork for concrete pouring used for constructing a cloth foundation concrete (1) comprising a footing portion (1a) and an upright portion (1b) integrally provided on the footing portion (1a). The two hat shapes, which are fixed in parallel on the waste concrete (9) with the web portion (3b) facing upward at a predetermined interval, are connected in series at the rip portion (3a). At least the vertical frame (5b) is fixed to the gate-shaped metal strip (3) and both side edges, and the lower end of the vertical frame (5b) is projected below the lower edge (5a) of the wire mesh so that it is below the wire mesh. The height is adjusted so that the edge (5a) is lower than or equal to the upper edge of the side surface (1aa) of the footing portion (1a) and the upper edge of the wire mesh is almost equal to the upper edge of the upright portion (1b). The inner flange part (3c) of the two flange parts (3c) forming the gates on both sides of the double-barbed metal strip (3) A unit mesh frame (5) whose main part is a wire mesh for forming a side surface (1ba) of an upright portion (1b) to which the vertical frame (5b) is fixed, and unit mesh frames on both sides thereof. A cloth foundation concrete having a footing portion, characterized in that it comprises a space maintaining means (6) fixed to (5) and arranging the unit nets (5) on both sides of the unit nets (5) so as to face each other at a predetermined interval. Abandoned formwork (2).
【請求項5】2連門型金属条(3)の両側の門を構成す
る各2つのフランジ部(3c)のうちの内側のフランジ部
(3c)の両縁にそれぞれ相対向する内側のフランジ部
(3c)側に向けて単位網枠(5)の両側縁に固定されて
いる竪枠(5b)の下部を挟持する狭持片(3cb)が突設
されている請求項4に記載のフーチング部を有する布基
礎コンクリート用の捨型枠(2)。
5. Inner flanges that oppose each other on both edges of the inner flange portion (3c) of the two flange portions (3c) forming the gates on both sides of the double-barrier metal strip (3). The sandwiching piece (3cb) for sandwiching the lower part of the vertical frame (5b) fixed to both side edges of the unit mesh frame (5) toward the part (3c) side is projectedly provided. Waste formwork (2) for cloth foundation concrete with footing.
【請求項6】2連門型金属条(3)の最外側のフランジ
部(3c)の内側に沿つてそれぞれ配置されてフーチング
部(1a)の側面(1aa)を形成させる堰坂(4)を備え
ている請求項4又は5に記載のフーチング部を有する布
基礎コンクリート用の捨型枠(2)。
6. A weir slope (4) which is arranged along the inside of the outermost flange portion (3c) of the double-barrier metal strip (3) to form the side surface (1aa) of the footing portion (1a). A waste formwork (2) for a cloth foundation concrete having a footing portion according to claim 4 or 5.
JP63311917A 1988-12-12 1988-12-12 Construction method of cloth foundation concrete having footing and waste form used therefor Expired - Lifetime JPH0796786B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63311917A JPH0796786B2 (en) 1988-12-12 1988-12-12 Construction method of cloth foundation concrete having footing and waste form used therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63311917A JPH0796786B2 (en) 1988-12-12 1988-12-12 Construction method of cloth foundation concrete having footing and waste form used therefor

Publications (2)

Publication Number Publication Date
JPH02157325A JPH02157325A (en) 1990-06-18
JPH0796786B2 true JPH0796786B2 (en) 1995-10-18

Family

ID=18022976

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63311917A Expired - Lifetime JPH0796786B2 (en) 1988-12-12 1988-12-12 Construction method of cloth foundation concrete having footing and waste form used therefor

Country Status (1)

Country Link
JP (1) JPH0796786B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2539736B2 (en) * 1993-05-20 1996-10-02 株式会社大周建設 Fabric foundation construction method and formwork support used for it
JP5903688B2 (en) * 2011-10-03 2016-04-13 株式会社 ダンネツ Insulation formwork support for construction of insulation foundation
JP6442725B2 (en) * 2014-10-17 2018-12-26 大和ハウス工業株式会社 Embankment structure for embankment and integrated foundation between soil and foundation

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58168725A (en) * 1982-03-27 1983-10-05 Ryusuke Nojima Formation of concrete foundation for housing
JPS62175152U (en) * 1986-04-18 1987-11-07

Also Published As

Publication number Publication date
JPH02157325A (en) 1990-06-18

Similar Documents

Publication Publication Date Title
DE69913977T2 (en) METHOD FOR PRODUCING A PANEL BOTTOM AND A PANEL BOTTOM
JPH0754428A (en) Method of constructing wall by truss reinforcing bar embedded form
US3849957A (en) Reinforced concrete ribbed ceiling
JPH0796786B2 (en) Construction method of cloth foundation concrete having footing and waste form used therefor
US5644891A (en) Mortar plow for use in the manufacture of brick wall panels
JP3208530B2 (en) Precast concrete formwork and structure using the same
JPH07504727A (en) Ceiling structure and method of manufacturing the same
JP3315492B2 (en) Floor beam construction method
RU2053334C1 (en) Grate reinforcement for concrete slab and plate-type member of a wall concrete form for monolithic shell building
JP2786965B2 (en) Precast concrete board for reinforced concrete wall
JPS6054459B2 (en) Slope protection method
JP3824242B2 (en) Viaduct-free support construction method
JPS6151524B2 (en)
JP2001049616A (en) Precast pc web for use in concrete bridge and prestressed concrete bridge having the pc web
JP2939787B2 (en) Method of manufacturing PCa plate for building, PCa plate for building, and mounting method of PCa plate for building
AU647783B2 (en) Improved building techniques
JP2942370B2 (en) Formwork method for vertical joints such as reinforced concrete beams and walls and guide metal fittings used in this method
JP3142180B2 (en) Concrete construction method
JPH0893218A (en) Construction of individual footing and folding form for individual footing
DE29602697U1 (en) formwork
JPH06322778A (en) Footing beam/foundation concrete form construction method
JPS60144439A (en) Construction of outer concrete wall using truss panel for outer wall
KR930005630B1 (en) Assembling slab of building
AT352958B (en) PREFABRICATED CEILING ELEMENT
CA1174091A (en) Concrete wall panel system