JPH0762392B2 - Vertical tube unit pipe connection method - Google Patents

Vertical tube unit pipe connection method

Info

Publication number
JPH0762392B2
JPH0762392B2 JP15532491A JP15532491A JPH0762392B2 JP H0762392 B2 JPH0762392 B2 JP H0762392B2 JP 15532491 A JP15532491 A JP 15532491A JP 15532491 A JP15532491 A JP 15532491A JP H0762392 B2 JPH0762392 B2 JP H0762392B2
Authority
JP
Japan
Prior art keywords
pipe
unit
unit pipe
vertical
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP15532491A
Other languages
Japanese (ja)
Other versions
JPH04353161A (en
Inventor
正宜 牧島
敏裕 宮崎
Original Assignee
株式会社メデカス工販
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社メデカス工販 filed Critical 株式会社メデカス工販
Priority to JP15532491A priority Critical patent/JPH0762392B2/en
Publication of JPH04353161A publication Critical patent/JPH04353161A/en
Publication of JPH0762392B2 publication Critical patent/JPH0762392B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Sink And Installation For Waste Water (AREA)
  • Supports For Pipes And Cables (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、高層建築物に取り付
けられる竪管ユニットパイプの接続方法に関するもので
ある。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for connecting a vertical unit pipe attached to a high-rise building.

【0002】[0002]

【従来の技術】近年、マンション、オフィスビル等の建
築物はますます高層化が進んでおり、この建築物の高層
化に伴い工期を短縮し、建築コストの低減を図るために
ユニット化が進められている。このユニット化の1つに
配管用パイプをユニット化した竪管ユニットパイプがあ
る。即ち、空調パイプ、上水パイプ、排水パイプ等の竪
管パイプを2〜4階分の長さに取りそろえ、これらのパ
イプをユニット枠に挿通して固定し、スラブの形成と同
時に一度に配管できるようにしたもので、多くの高層建
築物に採用されている。
2. Description of the Related Art In recent years, buildings such as condominiums and office buildings have become more and more high-rise, and due to the higher-rise buildings, the construction period has been shortened, and unitization has been promoted to reduce construction costs. Has been. One of the unitizations is a vertical pipe unit pipe in which a piping pipe is unitized. That is, vertical pipes such as air-conditioning pipes, water supply pipes, drainage pipes, etc. are prepared in lengths of 2 to 4 floors, and these pipes are inserted into the unit frame and fixed, so that slabs can be formed at the same time. It is used in many high-rise buildings.

【0003】従来の竪管ユニットパイプの構造とその組
付方法について図7〜図9に基づいて説明すると、図7
は竪管ユニットパイプの斜視図、図8は接続方法の説明
図、図9はパイプとユニット枠との固定方法を示す一部
を切り欠いた説明斜視図である。
The structure of a conventional vertical unit pipe and its assembling method will be described with reference to FIGS. 7 to 9.
FIG. 8 is a perspective view of a vertical unit pipe, FIG. 8 is an explanatory diagram of a connecting method, and FIG. 9 is an explanatory perspective view with a part cut away showing a method of fixing the pipe and the unit frame.

【0004】竪管ユニットパイプ1は施工する建築物の
各階の高さと同じ間隔で配設したユニット枠3に挿通し
た各種のパイプ5を固定することによって構成されてい
る。そして、ユニット枠3とパイプ5との固定方法は次
のようになされている。即ち、ユニット枠3は方形状フ
レーム7に上板9が取り付けられており、この上板9に
穿設した透孔の周縁にスリーブ11を立設し、フレーム
7の長手方向の外面に梁部13に載置、固定する横架材
17を固着することによって構成されている。
The vertical pipe unit pipe 1 is constructed by fixing various pipes 5 inserted in a unit frame 3 arranged at the same intervals as the height of each floor of the building to be constructed. The method of fixing the unit frame 3 and the pipe 5 is as follows. That is, in the unit frame 3, the upper plate 9 is attached to the rectangular frame 7, the sleeve 11 is provided upright on the periphery of the through hole formed in the upper plate 9, and the beam portion is provided on the outer surface in the longitudinal direction of the frame 7. It is configured by fixing a horizontal member 17 to be placed and fixed on the frame 13.

【0005】パイプ5は前記スリーブ11に挿通され、
二つ割りの固定バンド19を介してスリーブ11に固定
されている。前記スリーブ11の外面には180度隔て
てバンド受け材23が配設されており、このバンド受け
材23にパイプ5に取り付けた固定バンド19の固定板
25を載置して両者をボルト締めすることによってパイ
プ5をユニット枠3に固定している。さらに、最上部の
ユニット枠3においては、二つ割りの固定バンド19の
上方に二つ割りのレベル調整バンド20が取り付けられ
ており、固定バンド19とレベル調整バンド20とをス
タッドボルト27によって連結している。尚、最上部の
フレーム7の四隅には吊りフック29が設けられてい
る。
The pipe 5 is inserted through the sleeve 11,
It is fixed to the sleeve 11 via a fixed band 19 divided into two. On the outer surface of the sleeve 11, band receiving members 23 are arranged 180 degrees apart, and the fixing plate 25 of the fixing band 19 attached to the pipe 5 is placed on the band receiving members 23 and bolted together. As a result, the pipe 5 is fixed to the unit frame 3. Further, in the uppermost unit frame 3, a split level adjustment band 20 is attached above the split fixed band 19, and the fixed band 19 and the level adjustment band 20 are connected by a stud bolt 27. In addition, suspension hooks 29 are provided at the four corners of the uppermost frame 7.

【0006】上記構成の竪管ユニットパイプ1を建築物
に組み付けるには、最上部のユニット枠3に設けた吊り
フック29にワイヤーを掛けてクレーンて所定位置まで
吊り上げ、既に組み付けてある下節ユニットパイプ30
の上端と吊り上げた竪管ユニットパイプ1の下端とを連
結して取り付けるのである。竪管ユニットパイプ1を吊
り上げるときは、横架材17はフレーム7に垂直に取り
付けておき、取り付ける梁部13よりも一端高く吊り上
げてから水平に戻して竪管ユニットパイプ1全体を引き
下げて横架材17を梁部13に載置させる。その後、下
節ユニットパイプ30と溶接等により接続し、スラブ上
の現場打ちコンクリートと同時にユニット枠3にもコン
クリートを打設して床を構成する。
In order to assemble the vertical unit pipe 1 having the above-mentioned structure into a building, a wire is hooked on the suspension hook 29 provided on the uppermost unit frame 3 and the crane is hung up to a predetermined position by a crane, and the lower section unit already assembled. Pipe 30
The upper end of the vertical pipe unit pipe 1 and the lower end of the vertical pipe unit pipe 1 that has been lifted are connected and attached. When hoisting the vertical pipe unit pipe 1, the horizontal member 17 is vertically attached to the frame 7, and is lifted once higher than the beam portion 13 to be mounted and then returned to the horizontal position to pull down the vertical pipe unit pipe 1 as a whole. The material 17 is placed on the beam portion 13. Then, it is connected to the lower section unit pipe 30 by welding or the like, and concrete is also cast on the unit frame 3 at the same time as the cast-in-place concrete on the slab to form a floor.

【0007】[0007]

【発明が解決しようとする課題】しかしながら、上記構
成における従来の竪管ユニットパイプの接続方法には次
のような問題があった。各階の梁部13間の高さ寸法、
及びパイプ5の切断長さには当然寸法誤差が生じるか
ら、予め組み立てた竪管ユニットパイプ1を吊り上げて
既に組み付けてある下節ユニットパイプ30と接続しよ
うとしても、必ずしも下節ユニットパイプ30の上端と
正確に突き合わせることはできない。そこで、竪管ユニ
ットパイプ1はユニット枠3を梁部13上に載置したと
きに、下節ユニットパイプ30との間に予めわずかに間
隔を有するように組み立てられている。
However, the conventional connecting method of the vertical unit pipes in the above-mentioned structure has the following problems. Height dimension between the beams 13 on each floor,
Since the cutting length of the pipe 5 naturally causes a dimensional error, even if the previously assembled vertical pipe unit pipe 1 is lifted and is connected to the lower joint unit pipe 30 already assembled, the upper end of the lower joint unit pipe 30 is not always required. Can't exactly match. Therefore, the vertical unit pipe 1 is assembled so that there is a slight gap in advance between the vertical frame unit pipe 1 and the lower joint unit pipe 30 when the unit frame 3 is placed on the beam portion 13.

【0008】即ち、図8に示すように、全長Lのユニッ
トパイプ5と下節ユニットパイプ30との間に寸法Hの
間隔を持ってユニット枠3が梁部13に載置されるよう
に組み立てられている。そして、接続する際には、ユニ
ット枠3を梁部13上に載置した後にパイプ5に取り付
けた2つ割り固定バンド19の締付ボルト31を緩め、
パイプ5は最上部の2つ割りレベル調整バンド21のみ
で垂下する。次いで、固定バンド19とレベル調整バン
ド21とを連結するスタッドボルト27を回しながらパ
イプ5を徐々に引き下げてパイプ5の下端と下節ユニッ
トパイプ30の上端とを突き合わせ、その後、溶接等に
より接続する構成とされているのである。
That is, as shown in FIG. 8, the unit frame 3 is assembled so that the unit frame 3 is placed on the beam portion 13 with a space of dimension H between the unit pipe 5 having the total length L and the lower joint unit pipe 30. Has been. When connecting, loosen the tightening bolt 31 of the split fixing band 19 attached to the pipe 5 after placing the unit frame 3 on the beam portion 13.
The pipe 5 hangs only by the uppermost split level adjustment band 21. Then, the pipe 5 is gradually pulled down while rotating the stud bolt 27 connecting the fixing band 19 and the level adjusting band 21, and the lower end of the pipe 5 and the upper end of the lower joint unit pipe 30 are abutted, and then connected by welding or the like. It is configured.

【0009】従って、下節のユニットパイプ30と接続
するには、まず、各ユニット枠3においてパイプ5に取
り付けた2つ割り固定バンド19の締付ボルト31を緩
めなければならない。多数のユニットパイプ5が配設さ
れていると締付ボルト31を緩める作業には多くの時間
と労力が必要になる。また、固定バンド19の締め付け
を緩めた後、最上部のレベル調整バンド21と固定バン
ドとを連結するスタッドボルト27を回しながらパイプ
5を徐々に引き下げるには、スタッドボルト27を回す
作業者と下節ユニットパイプ30の上端との突き合わせ
状態を確認する作業者とが必要である。また、このよう
な作業は作業者が3〜4階分の高さで離れているから連
絡を取りながら慎重に行わなければならないという困難
さがあった。
Therefore, in order to connect with the unit pipe 30 in the lower section, first, the tightening bolt 31 of the split fixing band 19 attached to the pipe 5 in each unit frame 3 must be loosened. If a large number of unit pipes 5 are arranged, it takes a lot of time and labor to loosen the tightening bolts 31. Further, after loosening the fastening of the fixing band 19, in order to gradually pull down the pipe 5 while turning the stud bolt 27 that connects the uppermost level adjusting band 21 and the fixing band, the operator who turns the stud bolt 27 and An operator is required to check the state of the joint with the upper end of the joint unit pipe 30. Further, there is a difficulty that such a work must be carried out carefully while keeping contact with each other because the workers are separated by a height of 3 to 4 floors.

【0010】このように、従来の竪管ユニットパイプの
接続方法はユニットパイプ同士を直接接続するものであ
るから、上節ユニットパイプのレベル調節が必要にな
り、そのためにユニット枠3とパイプ5はユニット枠3
を梁部13に載置した後にパイプ5を引き下げられるよ
うに組み立てられていなければならいという制約があ
り、さらに、レベルの調節に多くの時間と労力を費やさ
なければならないという問題があった。
As described above, since the conventional vertical pipe unit pipe connecting method is to directly connect the unit pipes to each other, it is necessary to adjust the level of the upper joint unit pipe. Therefore, the unit frame 3 and the pipe 5 are Unit frame 3
There is a restriction that the pipe 5 must be assembled so that the pipe 5 can be pulled down after it is placed on the beam portion 13, and there is a problem that a lot of time and labor is required for adjusting the level.

【0011】この発明はかかる現況に鑑みてなされたも
ので、工期の短縮と労力の低減を図り、高層建築物に使
用されるユニットとして好適な竪管ユニットパイプを提
供することを目的とする。
The present invention has been made in view of the present situation, and an object thereof is to provide a vertical pipe unit pipe suitable for a unit used in a high-rise building by shortening the construction period and reducing the labor.

【0012】[0012]

【課題を解決するための手段】この発明は、上記目的を
達成するため次のような構成とした。即ち、所定の寸法
よりも短く形成したパイプをユニット枠に挿通、固定し
て竪管ユニットパイプを組み立て、前記竪管ユニットパ
イプを下節ユニットパイプとの間に間隔が生じるように
前記ユニット枠を梁部に載置固定し、前記下節ユニット
パイプとの間に生じた間隔に調整用短管を介在せしめて
接続することを特徴とする。そして、下節ユニットパイ
プ及び上節ユニットパイプと調整用短管との接続は公知
の溶接方法あるいはフランジ継手によってもよいが、メ
カニカルジョイントを用いた接続方法であることが好ま
しい。
The present invention has the following constitution in order to achieve the above object. That is, a pipe formed to be shorter than a predetermined size is inserted into a unit frame and fixed to assemble a vertical pipe unit pipe, and the vertical frame unit pipe is attached to the lower joint unit pipe to form a space between the unit frame. It is characterized in that it is mounted and fixed on the beam portion, and a short pipe for adjustment is interposed and connected at an interval generated with the lower section unit pipe. The lower segment unit pipe and the upper segment unit pipe may be connected to the adjustment short pipe by a known welding method or a flange joint, but a connection method using a mechanical joint is preferable.

【0013】[0013]

【作用】調整用短管を介在させることによって上節ユニ
ットパイプのレベル調整が不要になり、従って、パイプ
を固定している固定バンドを緩める作業やパイプを引き
さげる作業は不要になる。このために、節間接続が容易
になるとともに、接続にメカニカルジョイントを使用し
た場合には、温度差によるパイプの伸縮を吸収し、パイ
プ荷重を分散させることができる。
With the interposition of the adjusting short pipe, the level adjustment of the upper joint unit pipe becomes unnecessary, and therefore, the work of loosening the fixing band fixing the pipe and the work of pulling the pipe are unnecessary. Therefore, the internode connection is facilitated, and when a mechanical joint is used for the connection, expansion and contraction of the pipe due to a temperature difference can be absorbed, and the pipe load can be dispersed.

【0014】[0014]

【実施例】以下、この発明を図示する実施例に基づき詳
細に説明する。図1はこの発明の接続方法の説明図、図
2〜図6は具体的接続構造を示す一部断面説明図であ
る。この発明の竪管ユニットパイプ35は従来のものと
同様に、ユニット枠37に各種パイプ39を挿通、固定
して構成されているが、パイプ39の長さ寸法Lは必
要な長さ寸法Lよりも寸法L分だけ短く形成されてい
る。従って、建築物に組み付けたときには下節ユニット
パイプ42上端との間に長さ寸法Lの間隔が設けら
れる。即ち、この発明ではL=L+Lとなる。そし
て、この発明は前記間隔Lはパイプ39を引き下げて
調整するのではなく、別途形成した調整用短管43を介
在させて接続することを特徴とするものである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below with reference to illustrated embodiments. FIG. 1 is an explanatory view of a connection method of the present invention, and FIGS. 2 to 6 are partial sectional explanatory views showing a specific connection structure. The vertical unit pipe 35 of the present invention is configured by inserting and fixing various pipes 39 in the unit frame 37 as in the conventional one, but the length dimension L 1 of the pipe 39 is the required length dimension L 1. It is formed to be shorter than the size by a dimension L 2 . Therefore, when assembled to a building, the lower joint unit pipe 42 is provided with a space of length L 2 between the lower joint unit pipe 42 and the upper end. That is, in the present invention, L = L 1 + L 2 . The present invention is characterized in that the distance L 2 is not adjusted by pulling down the pipe 39, but is connected by interposing a separately-adjusted short pipe 43.

【0015】さらに、詳述すると竪管ユニットパイプ3
5を吊り上げてユニット枠37の横架材40を梁部41
に載置固定したときに、上節ユニットパイプと下節ユニ
ットパイプとの間に寸法Lの間隔を生じさせ、この間
隔Lに調整用短管43を差し込んで接続するもので、
従来の接続方法のようにパイプを必要長さ寸法に形成し
下節ユニットパイプとの間に生じた間隔をパイプを引き
下げることによって調整するものではない。調整用短管
43の長さ寸法は建築現場で測ってその都度決定すれば
よい。
Further in detail, the vertical pipe unit pipe 3
5 is lifted and the horizontal member 40 of the unit frame 37 is attached to the beam portion 41.
When mounted and fixed on, a space having a dimension L 2 is generated between the upper joint unit pipe and the lower joint unit pipe, and the adjustment short pipe 43 is inserted and connected to the gap L 2 .
Unlike the conventional connection method, the pipe is formed to have a required length dimension, and the space generated between the pipe and the lower joint unit pipe is not adjusted by pulling down the pipe. The length dimension of the adjustment short pipe 43 may be measured at the construction site and determined each time.

【0016】従って、この発明ではユニット枠37とパ
イプ39との固定方法は従来と同様に2つ割りの固定バ
ンド47をスリーブに固定することによって一体に組み
立てているが、最上部におけるレベル調整バンドとパイ
プを引き下げるスタッドボルトは不要である。即ち、い
ずれのユニット枠37においても、ユニット枠37を構
成する上板に立設したスリーブ45にパイプ39を挿通
し、パイプ39に取り付けた2つ割りバンド47によっ
て組み立てられている。
Therefore, in the present invention, the unit frame 37 and the pipe 39 are fixed integrally by assembling them by fixing the split fixing band 47 to the sleeve as in the conventional case. And the stud bolt that pulls down the pipe is unnecessary. That is, in each of the unit frames 37, the pipe 39 is inserted through the sleeve 45 provided upright on the upper plate of the unit frame 37, and the unit frame 37 is assembled by the split band 47 attached to the pipe 39.

【0017】このように、調整用短管43を介在させて
下節ユニットパイプと上節ユニットパイプとを接続すれ
ば、レベル調整のために上節ユニットパイプを引き下げ
るという困難な作業が不要になるから、作業時間の短縮
と労力を省くことができる。また、部品としてはレベル
調整バンド及びスタッドボルトが不要になるばかりでな
く、従来は建築物に組み付け後も前記固定バンドを保持
バンドとしてそのまま使用する場合には、再度締付ボル
トを締め付け直さなければならないが、この発明では固
定バンド47の締付ボルト49を緩める必要がないか
ら、締め付け直す必要もない。
By connecting the lower joint unit pipe and the upper joint unit pipe with the adjusting short pipe 43 interposed, the difficult work of pulling down the upper joint unit pipe for level adjustment becomes unnecessary. Therefore, the working time can be shortened and the labor can be saved. Further, not only the level adjustment band and the stud bolt are not necessary as parts, but when the fixing band is used as it is as a holding band even after it has been assembled to a building, it is necessary to re-tighten the tightening bolt again. However, in the present invention, since it is not necessary to loosen the tightening bolt 49 of the fixing band 47, it is not necessary to retighten it.

【0018】次に、調整用短管43を使用した具体的接
続構造について説明する。図2〜図4はメカニカルジョ
イントを使用した接続構造を示すもので、図2は調整用
短管43の差し込みを示す説明図、図3は一部を省略し
た接続状態の説明図、図4は図3のA−A線断面図であ
る。メカニカルジョイント50は継目をシールするゴム
リング51と、前記ゴムリング51を収納する2つ割り
のハウジング53と、前記ハウジング53を締め付ける
ボルト及びナット55からなり、ハウジング53の内面
には前記ゴムリング51を収納する凹部57と後述のリ
ング61を収納する凹部59が形成されている。
Next, a specific connection structure using the adjusting short pipe 43 will be described. 2 to 4 show a connection structure using a mechanical joint, FIG. 2 is an explanatory view showing insertion of the adjusting short pipe 43, FIG. 3 is an explanatory view of a connection state with a part omitted, and FIG. It is the sectional view on the AA line of FIG. The mechanical joint 50 includes a rubber ring 51 that seals a seam, a split housing 53 that houses the rubber ring 51, and a bolt and a nut 55 that tightens the housing 53. The inner surface of the housing 53 has the rubber ring 51. And a recess 59 for storing a ring 61, which will be described later, are formed.

【0019】このメカニカルジョイント50を使用する
には、予め調整用短管43の両端部、上節ユニットパイ
プ63の下端部、下節ユニットパイプ65の上端部にそ
れぞれ係止用リング61を設ける。次いで、調整用短管
43aの両端部にゴムリング51を装着して上節ユニッ
トパイプ63と下節ユニットパイプ65の間に差し込ん
でゴムリング51をずらして上節ユニットパイプ63と
下節ユニットパイプ65の端部をはめ込む。ゴムリング
51を継目の中央にずらした後にハウジング53を被せ
るとともに、凹部57に前記ゴムリング51を嵌合さ
せ、凹部59に前記リング61を嵌合させ、連結部をボ
ルト及びナット55で締め付ければよい。
In order to use the mechanical joint 50, locking rings 61 are provided in advance on both ends of the adjusting short pipe 43, the lower end of the upper joint unit pipe 63, and the upper end of the lower joint unit pipe 65, respectively. Next, the rubber rings 51 are attached to both ends of the adjustment short pipe 43a and inserted between the upper joint unit pipe 63 and the lower joint unit pipe 65 to shift the rubber ring 51 to shift the upper joint unit pipe 63 and the lower joint unit pipe. Fit the end of 65. After shifting the rubber ring 51 to the center of the seam, the housing 53 is covered, the rubber ring 51 is fitted in the recess 57, the ring 61 is fitted in the recess 59, and the connecting portion is tightened with bolts and nuts 55. Good.

【0020】上記のように、メカニカルジョイント50
を使用して接続した場合には、簡単な構造であるから熟
練を必要とせず簡単に接続することができ、また、伸
縮、曲げが自由であるからパイプの応力を解放すること
ができるばかりでなく、パイプの伸縮、撓みを吸収する
ことができる。
As described above, the mechanical joint 50
When connecting using, since it has a simple structure, it can be easily connected without requiring skill, and since it is free to expand and contract and bend, it can not only release the stress of the pipe. Without, it is possible to absorb the expansion and contraction and bending of the pipe.

【0021】図5はフランジ継手による接続方法を示
し、調整用短管43bと下節ユニットパイプ及び上節ユ
ニットパイプとの接続構造の一部断面説明図である。調
整用短管43bの両端部と下節ユニットパイプ68の端
部にそれぞれ溶接したフランジ73、77と、上節ユニ
ットパイプ66に溶接したラップ板72に係止した割り
フランジ78とにより接続するものである。即ち、調整
用短管43bの両端部にフランジ77を溶接しておき、
下節ユニットパイプ68とは下節ユニットパイプ68の
端部に溶接したフランジ73との間にゴムパッキン69
を挟んでボルト及びナット70により接続する。一方、
調整用短管43bと上節ユニットパイプ66とは上節ユ
ニットパイプ66の下節部にラップ板72を溶接し、こ
のラップ板72に割りフランジ78を係止させ、フラン
ジ77とラップ板72との間にゴムパッキン1を挟んで
ボルト及びナット79により接続するものである。
FIG. 5 shows a connecting method using a flange joint, and is a partial cross-sectional explanatory view of the connecting structure of the adjusting short pipe 43b and the lower joint unit pipe and the upper joint unit pipe. Connection by flanges 73 and 77 welded to both ends of the adjusting short pipe 43b and the end of the lower joint unit pipe 68, respectively, and a split flange 78 locked to the lap plate 72 welded to the upper joint unit pipe 66. Is. That is, the flange 77 is welded to both ends of the adjustment short pipe 43b,
A rubber packing 69 is provided between the lower joint unit pipe 68 and the flange 73 welded to the end of the lower joint unit pipe 68.
And the bolts and nuts 70 are used to connect them. on the other hand,
The short pipe 43b for adjustment and the upper joint unit pipe 66 are welded to the lower joint of the upper joint unit pipe 66 with a lap plate 72, and the split flange 78 is locked to the lap plate 72 to form the flange 77 and the lap plate 72. The rubber packing 1 is sandwiched between them and connected by bolts and nuts 79.

【0022】このフランジ継手による接続方法の場合
は、ラップ板の溶接が必要であるからある程度の熟練と
注意を要するものの、フランジを突き合わせるだけであ
るから接続作業は簡単である。また、一方の接続部に割
りフランジ78を使用したから、フランジ77とのボル
ト孔の位置決めが容易である。
In the case of the connection method using this flange joint, although some skill and attention are required because welding of the lap plate is required, the connection work is simple because only the flanges are butted. Further, since the split flange 78 is used for one of the connecting portions, it is easy to position the bolt hole with the flange 77.

【0023】また、図6は同じくフランジ継手による接
続方法の一部断面図である。この接続方法ではフランジ
継手をパイプ端部にねじ込みによって取り付けている。
即ち、調整用短管43の両端部、上節ユニットパイプ8
5及び下節ユニットパイプ87の端部にそれぞれねじを
切り、このねじにフランジ81をパイプレンチで締め付
けて取り付け、ボルト及びナット83で連結するもので
ある。この接続方法は現場加工で行うことができるから
接続作業が容易である。
FIG. 6 is a partial sectional view of the connection method using the flange joint. In this connection method, the flange joint is attached to the end of the pipe by screwing.
That is, both ends of the adjusting short pipe 43, the upper joint unit pipe 8
5 and the lower section unit pipe 87 are respectively threaded, a flange 81 is fastened to the thread by a pipe wrench, and the bolts and nuts 83 are connected. Since this connection method can be performed in the field, the connection work is easy.

【0024】この発明における調整用短管43と上節ユ
ニットパイプ及び下節ユニットパイプとの接続構造は上
記実施例に限定されるものではなく、従来のように溶接
により直接接続することができ、その他任意の接続構造
とすることができる。
The connecting structure of the adjusting short pipe 43 and the upper joint unit pipe and the lower joint unit pipe in the present invention is not limited to the above-mentioned embodiment, but can be directly connected by welding as in the conventional case. Any other connection structure can be used.

【0025】[0025]

【発明の効果】この発明は以上のように構成してなるの
で次のような具体的効果を奏することができる。即ち、
竪管ユニットパイプは梁部に組み付けたままでレベル調
整することなく接続することができるから、節間接続を
容易に行うことができる。また、ユニットパイプのレベ
ル調整が不要であるから、パイプとユニット枠との固定
方法が限定されず任意の固定方法とすることができる。
さらに、接続作業の単純化によって工期の短縮と労力の
低減を図り、高層建築物に使用される好適な竪管ユニッ
トパイプを得ることができる。
Since the present invention is configured as described above, the following specific effects can be achieved. That is,
Since the vertical unit pipe can be connected to the beam portion without adjusting the level, the internode connection can be easily performed. Further, since the level adjustment of the unit pipe is unnecessary, the fixing method of the pipe and the unit frame is not limited, and any fixing method can be used.
Further, by simplifying the connecting work, the construction period and labor can be shortened, and a vertical pipe unit pipe suitable for high-rise buildings can be obtained.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の竪管ユニットパイプの接続方法の説
明図である。
FIG. 1 is an explanatory view of a method for connecting a vertical unit pipe of the present invention.

【図2】調整用短管の差し込みを示す説明図である。FIG. 2 is an explanatory diagram showing insertion of a short tube for adjustment.

【図3】メカニカルジョイントを用いた接続構造の一例
を示す一部断面説明図である。
FIG. 3 is a partial cross-sectional explanatory view showing an example of a connection structure using a mechanical joint.

【図4】図3におけるA−A線断面図である。4 is a cross-sectional view taken along the line AA in FIG.

【図5】フランジ継手による接続構造の一部断面説明図
である。
FIG. 5 is a partial cross-sectional explanatory view of a connection structure using a flange joint.

【図6】フランジ継手をねじ込みにより取り付けた接続
構造の一部断面説明図である。
FIG. 6 is a partial cross-sectional explanatory view of a connection structure in which a flange joint is attached by screwing.

【図7】従来の竪管ユニットパイプの説明用斜視図であ
る。
FIG. 7 is a perspective view for explaining a conventional vertical unit pipe.

【図8】従来の竪管ユニットパイプの接続方法の説明図
である。
FIG. 8 is an explanatory diagram of a conventional method for connecting a vertical unit pipe.

【図9】従来の竪管ユニットパイプの要部を示す一部切
欠説明斜視図である。
FIG. 9 is a partially cutaway explanatory perspective view showing a main part of a conventional vertical tube unit pipe.

【符号の説明】[Explanation of symbols]

35 竪管ユニットパイプ 37 ユニット枠 39 パイプ 40 横架材 41 梁部 43 調整用短管 45 スリーブ 47 2つ割り固定バンド 49 締付ボルト 50 メカニカルジョイント 61 リング 63 上節ユニットパイプ 65 下節ユニットパイプ 66 上節ユニットパイプ 68 下節ユニットパイプ 69 ゴムパッキン 70 ボルト及びナット 71 ゴムパッキン 72 ラップ板 73 フランジ 77 フランジ 78 割りフランジ 79 ボルト及びナット 81 フランジ 83 ボルト及びナット 85 上節ユニットパイプ 87 下節ユニットパイプ 35 Vertical unit pipe 37 Unit frame 39 Pipe 40 Horizontal material 41 Beam part 43 Short tube for adjustment 45 Sleeve 47 Divided fixed band 49 Tightening bolt 50 Mechanical joint 61 Ring 63 Upper section unit pipe 65 Lower section unit pipe 66 Upper section unit pipe 68 Lower section unit pipe 69 Rubber packing 70 Bolts and nuts 71 Rubber packing 72 Lap plate 73 Flange 77 Flange 78 Split flange 79 Bolts and nuts 81 Flange 83 Bolts and nuts 85 Upper section unit pipe 87 Lower section unit pipe

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 所定の寸法よりも短く形成したパイプを
ユニット枠に挿通、固定して竪管ユニットパイプを組み
立て、前記竪管ユニットパイプを下節ユニットパイプと
の間に間隔が生じるように前記ユニット枠を梁部に載置
固定し、前記下節ユニットパイプとの間に生じた間隔に
調整用短管を介在せしめて接続することを特徴とする竪
管ユニットパイプの接続方法。
1. A vertical pipe unit pipe is assembled by inserting and fixing a pipe formed to be shorter than a predetermined size into a unit frame, and the vertical pipe unit pipe is spaced from the lower joint unit pipe by a gap. A method for connecting a vertical pipe unit pipe, characterized in that a unit frame is placed and fixed on a beam portion, and a short pipe for adjustment is interposed at a space generated between the unit frame and the lower joint unit pipe.
JP15532491A 1991-05-31 1991-05-31 Vertical tube unit pipe connection method Expired - Lifetime JPH0762392B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15532491A JPH0762392B2 (en) 1991-05-31 1991-05-31 Vertical tube unit pipe connection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15532491A JPH0762392B2 (en) 1991-05-31 1991-05-31 Vertical tube unit pipe connection method

Publications (2)

Publication Number Publication Date
JPH04353161A JPH04353161A (en) 1992-12-08
JPH0762392B2 true JPH0762392B2 (en) 1995-07-05

Family

ID=15603404

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15532491A Expired - Lifetime JPH0762392B2 (en) 1991-05-31 1991-05-31 Vertical tube unit pipe connection method

Country Status (1)

Country Link
JP (1) JPH0762392B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017074245A1 (en) * 2015-10-26 2017-05-04 Concentus Properties Ab A shaft pipe collection module
JP2021113468A (en) * 2020-01-21 2021-08-05 清水建設株式会社 Duct construction method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010069640A (en) * 2001-04-24 2001-07-25 강인자 Building vertical shaft in pit structure piping system
FI20205120A1 (en) * 2020-02-05 2021-08-06 Lehto Group Oyj Method of building a pipeline in a pipe shaft line

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017074245A1 (en) * 2015-10-26 2017-05-04 Concentus Properties Ab A shaft pipe collection module
JP2021113468A (en) * 2020-01-21 2021-08-05 清水建設株式会社 Duct construction method

Also Published As

Publication number Publication date
JPH04353161A (en) 1992-12-08

Similar Documents

Publication Publication Date Title
KR20190132406A (en) Building systems
JPH0122417B2 (en)
JP2006214226A (en) Joining method of antenna mast for radio and foundation pillar and its structure
JP2677144B2 (en) Construction method for column-beam joints
JPH0762392B2 (en) Vertical tube unit pipe connection method
JPS6139469B2 (en)
JP3101169B2 (en) Temporary fixing device for column / beam joint members
JP4584498B2 (en) Mounting structure of reinforcing ring and joint plate
JPH0536042Y2 (en)
JPH02243873A (en) Connecting device for supporting pillar and stay
JP3290636B2 (en) Joint structure between steel column base and foundation concrete
JPH0438038Y2 (en)
JP3482531B2 (en) How to build stairs
JP2000017643A (en) Working method for pile head portion of diagonally assembled pile body
JPH01290849A (en) Skeleton structure of basement side wall
JPH0442500B2 (en)
JP2598154Y2 (en) Temporary support
JPH0536041Y2 (en)
JPH0438030Y2 (en)
JP2712023B2 (en) Structure of beam-to-column joints of steel tubular concrete columns with X-shaped reinforcement
JPS6133174Y2 (en)
JPS6321604Y2 (en)
JPH0352380Y2 (en)
JPH0115800Y2 (en)
JP2767012B2 (en) Scaffolding