JPH0718734A - Constructing method for reinforced concrete building structure - Google Patents

Constructing method for reinforced concrete building structure

Info

Publication number
JPH0718734A
JPH0718734A JP15973493A JP15973493A JPH0718734A JP H0718734 A JPH0718734 A JP H0718734A JP 15973493 A JP15973493 A JP 15973493A JP 15973493 A JP15973493 A JP 15973493A JP H0718734 A JPH0718734 A JP H0718734A
Authority
JP
Japan
Prior art keywords
steel core
girders
girder
column
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15973493A
Other languages
Japanese (ja)
Inventor
Yukihiro Sakuta
幸弘 作田
Kiyomitsu Okada
清光 岡田
Susumu Mizuguchi
進 水口
Yasuharu Maeda
安治 前田
Keiju Kobayashi
桂樹 小林
Hiroshi Motoda
弘 元田
Masatoshi Fujiyoshi
雅利 藤吉
Makoto Nagao
真 永尾
Hirotaka Ootake
弘嵩 大竹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP15973493A priority Critical patent/JPH0718734A/en
Publication of JPH0718734A publication Critical patent/JPH0718734A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To reduce construction period by connecting beam brackets of precast concrete girders with column brackets of both upstairs and downstairs side of steel core columns and installing the precase concrete girders, and placing concrete into the hollows of the precast concrete girders. CONSTITUTION:Steel core columns 1 composed of round steel pipes are erected at the erection positions of respective columns 1, and beam brackets 5 of precast concrete girders 4 are connected with the column brackets 2 at the downstair sides of the steel core columns 1 and the precast concrete girders 4 are installed. Precast concrete girders 4 are also installed at the corresponding column brackets 2 of the upstair sides, and beams are installed between these girders 4 and composite floor foards are installed over the girders 4 and beams of both sides of the downstairs and upstairs. Then, bar arrangement works for the steel core columns 1 and wall reinforcement are performed, and concrete is placed from the hollow 4c of the precase concrete girder 4 of the downstair side to beam joint form and column shaped bars, and further to the inside of the forms of upstair side and a two-storied reinforced concrete structure is constructed. Therefore, the cost is saved.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、工期短縮及び構築コス
トの削減が可能なRC造建築構造物の構築方法に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an RC building structure capable of shortening the construction period and reducing the construction cost.

【0002】[0002]

【従来の技術】一般に、RC(鉄筋コンクリート)造建
築物は、一層のRC柱、RC梁及びC床スラブを形成し
ていき、構築された一層分の構造体の構造強度が得られ
た後、その一層分の構造体の上部にさらに一層の構造体
を積み上げて構築していくものである。すなわち、周囲
に支保工を組み立てた後、一層分の柱型枠、梁型枠、床
スラブ型枠など(内部に鉄筋が配筋されている)を組み
込んでいき、それら型枠内部にコンクリートを現場打ち
していくことにより一層の構造物を構築していく。そし
て、型枠が取り外されて構造体となった一層の構造物上
に、さらに上層の構造物を順次型枠を組み立てるなどの
施工を経て構築されていく構造体である。
2. Description of the Related Art Generally, an RC (reinforced concrete) building is formed by forming one layer of RC columns, RC beams and C floor slabs, and after obtaining the structural strength of the constructed one layer structure, The structure is built up by stacking one more layer on top of the one layer structure. In other words, after assembling the support work around the surroundings, we built in one layer of column formwork, beam formwork, floor slab formwork, etc. (with reinforcing bars inside) and put concrete inside these formwork. We will build more structures by driving on-site. Then, the structure is constructed by performing construction such as assembling the structures of upper layers in order on the one-layer structure in which the form is removed to form the structure.

【0003】[0003]

【発明が解決しようとする課題】このようなRC造建築
物は、構築材料コストの面でメリットはあるものの、一
層毎に構造体を構築していかなければならないため工期
の短縮化の面で問題がある。したがって、超高層建築物
を構築する場合には、工期短縮が容易に図られるSRC
(鉄骨鉄筋コンクリート)造建築物が主流となっている
のが現状である。
Such an RC building has an advantage in terms of construction material cost, but since it is necessary to construct the structure one by one, the construction period is shortened. There's a problem. Therefore, when constructing a super high-rise building, the SRC can easily shorten the construction period.
The current situation is that (steel-framed reinforced concrete) structures are the mainstream.

【0004】本発明は上記事情に鑑みてなされたもの
で、SRC工法と略同程度の工期短縮を図ることが可能
であり、さらに構築コストの削減を図ることが可能なR
C造建築構造物の構築方法を提供することを目的とす
る。
The present invention has been made in view of the above circumstances, and it is possible to shorten the construction period to the same extent as the SRC construction method, and further to reduce the construction cost.
It is intended to provide a method for constructing a C building structure.

【0005】[0005]

【課題を解決するための手段】本発明のRC造建築構造
物の構築方法は、柱の建方位置に、構築される建築構造
物の少なくとも2層にわたる長さに設定され、かつ各層
の梁架設位置と交差する外周位置に柱ブラケットが突設
された鋼芯柱を建て込んでいく鋼芯柱建方工程と、隣接
する鋼芯柱どうしの上層側の柱ブラケットに、内部が空
洞化され長手方向の両端部に梁ブラケットが突設されて
いるプレキャストPC大梁の該梁ブラケットを連結して
プレキャストPC大梁を架設し、下層側の柱ブラケット
どうしにもプレキャストPC大梁を架設していくととも
に、架設されたプレキャストPC大梁間に小梁を架設し
ていく大梁、小梁架設工程と、上層側及び下層側の大
梁、小梁上に、複合床版を敷設して下層の床部と上層の
床部を形成していく床版敷設工程と、梁接合位置におい
て対向するプレキャストPC大梁どうしの長手方向端部
から突出している梁端部鉄筋どうしを連結し、鋼芯柱の
周囲に柱筋を配設し、大梁、小梁の下方に壁筋を配設し
ていく配筋工程と、梁接合位置を囲繞する梁接合型枠、
柱筋を囲繞する柱型枠及び壁筋を囲繞する壁型枠を組み
立てていく型枠組立て工程と、下層側のプレキャストP
C大梁の空洞部よりコンクリートを梁接合型枠、柱型枠
及び壁型枠内部に連続して打設していき、順次上層側の
型枠内部へもコンクリートを連続して打設していくコン
クリート打設工程とを備え、鋼芯柱建方工程からコンク
リート打設工程までの1サイクルの連続工程により少な
くとも2層の構造物を構築していくとともに、形成され
た上層側の構造物より上部に露出している鋼芯柱の上端
部に、他の鋼芯柱を同一軸線上に連結して鋼芯柱建方工
程を行い、さらにコンクリート打設工程までの各工程を
繰り返し行うことを特徴とする構築方法である。また、
前記鋼芯柱には、高強度コンクリートが充填されている
ことが望ましい。
According to the method for constructing an RC building structure of the present invention, a length of at least two layers of the building structure to be constructed is set at a erected position of a column, and a beam of each layer. The interior is hollowed out in the steel core pillar erection process of building the steel core pillar in which the pillar bracket is projected at the outer peripheral position intersecting the erection position and the pillar bracket on the upper layer side between adjacent steel core pillars. Precast PC girders are installed by connecting the beam brackets of precast PC girders with beam brackets protruding from both ends in the longitudinal direction, and precast PC girders are installed between the lower-layer pillar brackets as well. A girder and a girder erection process in which a girder is erected between the precast PC girders that have been erected, and a composite floor slab is laid on the girders and girders on the upper and lower layers and Forming the floor The plate laying process and the beam end reinforcing bars protruding from the longitudinal ends of the precast PC girders facing each other at the beam joining position are connected to each other, and the column reinforcing bars are arranged around the steel core column to form the girder and the girder. Bar arrangement process for arranging wall reinforcements underneath, and beam connection form surrounding the beam connection position,
Formwork assembly process of assembling the column formwork surrounding the column reinforcement and the wall formwork surrounding the wall reinforcement, and the precast P on the lower layer side
C Concrete is continuously cast into the beam joint form, column form and wall form from the cavity of the large beam, and concrete is also sequentially placed inside the form on the upper layer side. With a concrete pouring process, the structure of at least two layers is constructed by the continuous process of one cycle from the steel core pillar erection process to the concrete pouring process, and the structure above the upper layer side is formed. It is characterized in that the steel core column erection process is performed by connecting other steel core columns on the same axis to the upper end of the steel core column that is exposed to the ground, and each process up to the concrete placing process is repeated. Is the construction method. Also,
It is desirable that the steel core column is filled with high-strength concrete.

【0006】[0006]

【作用】本発明のRC造建築構造物の構築方法によれ
ば、鋼芯柱建方工程において柱の建方位置に鋼芯柱が建
て込まれているので、この鋼芯柱の柱ブラケットにプレ
キャストPC大梁の梁ブラケットを連結させながら、同
時に少なくとも2層分の大梁小梁架設工程を行うことが
できる。それとともに、床版敷設工程、配筋工程、型枠
組立て工程を、上層及び下層において同時に行うことが
できる。そして、コンクリート打設工程において下部層
の型枠内部から順次上側の型枠内部にコンクリートが打
設されることにより、少なくとも2層分の構造物が一度
に構築されるので、従来のRC造建築物と比較して工期
が大幅に短縮し、かつ構築コストも削減される。また、
従来のRC造建築物のような周囲を囲む足場や支保工を
必要としないので、さらに工期が短縮する。さらに、内
部に高強度コンクリートが充填されている鋼芯柱内は、
十分にプレキャストPC大梁、小梁、複合床版の荷重を
受けることができる。
According to the method of constructing an RC building structure of the present invention, the steel core pillar is built in the erected position of the pillar in the steel core pillar erection process. While connecting the beam brackets of the precast PC girder, at least two layers of girder and girder installation steps can be performed at the same time. At the same time, the floor slab laying step, the bar arrangement step, and the formwork assembling step can be performed simultaneously in the upper layer and the lower layer. Then, in the concrete placing step, concrete is sequentially placed inside the lower formwork into the upper formwork, whereby at least two layers of structures are constructed at once, so that the conventional RC construction The construction period is greatly shortened and the construction cost is also reduced compared to the products. Also,
Since the scaffolding surrounding the surroundings and supporting work unlike the conventional RC building is not required, the construction period is further shortened. Furthermore, inside the steel core column filled with high strength concrete,
Precast PC girders, girders, and composite deck slabs can be fully loaded.

【0007】[0007]

【実施例】以下、本発明のRC造建築構造物の構築方法
の実施例について図1から図10を参照して説明する。
なお、複数層に構築されるRC造建築構造物の一層は、
図5に示すように、高さHに設定されている。
EXAMPLES Examples of the method for constructing an RC building structure of the present invention will be described below with reference to FIGS. 1 to 10.
In addition, one layer of the RC building structure constructed in multiple layers,
As shown in FIG. 5, the height H is set.

【0008】図1及び図5で示す符号1…は、本実施例
の第1の主要部材である鋼芯柱を示すものである。これ
ら鋼芯柱1は、長尺な丸型鋼管であり、少なくとも上層
2F及び下層1Fの梁架設位置1P、2Pにわたる長さ
に設定されている。すなわち、一層分の高さHが3〜4
mである場合には、鋼芯柱1の長さは2層の場合6〜8
mに設定される。
Reference numerals 1 ... In FIGS. 1 and 5 indicate steel core columns which are the first main members of this embodiment. These steel core columns 1 are long round steel pipes, and are set to have a length extending over at least the beam installation positions 1P and 2P of the upper layer 2F and the lower layer 1F. That is, the height H for one layer is 3 to 4
If the length is m, the length of the steel core column 1 is 6 to 8 in the case of two layers.
set to m.

【0009】そして、これら鋼芯柱1…は、図5に示す
ように基礎床部Bから立設する最下鋼芯柱1Bと軸線を
一致させて連結されるが、前記梁架設位置1P、2Pと
交差する外周部には、図1にも示すように、大梁との接
続方向(四方)に突出する板状の柱ブラケット2…が、
面方向を軸方向に向けて固定されている。これら柱ブラ
ケット2には、上下方向に所定間隔をあけてボルト孔2
a…が穿設されている。また、この鋼芯柱1の内部に
は、架設されるプレキャストPC大梁4、複合床版11
の荷重に対して軸力を発揮する高強度コンクリート3が
充填されており、工場等で充填コンクリート鋼芯柱とさ
れて現場に搬入されるようになっている。
As shown in FIG. 5, the steel core pillars 1 are connected to the lowermost steel core pillar 1B standing upright from the foundation floor B with their axes aligned. As shown in FIG. 1, plate-shaped pillar brackets 2 ... Which project in the connecting direction (four directions) with the girders are provided on the outer peripheral portion intersecting with 2P.
It is fixed with the surface direction facing the axial direction. These pillar brackets 2 have bolt holes 2 at predetermined intervals in the vertical direction.
a ... is drilled. Further, inside the steel core pillar 1, the precast PC girder 4 and the composite floor slab 11 to be installed are installed.
It is filled with high-strength concrete 3 that exerts an axial force against the load, and is used as a filled concrete steel core column at a factory or the like and is carried to the site.

【0010】また、図1から図3で示す符号4は、本実
施例の第2の主要部材であるプレキャストPC大梁(以
下、PC大梁と略称する。)を示している。このPC大
梁4は、長手方向に沿ってPC鋼線4aが内部配筋され
ているとともに、長手方向の両端部のみに肉部4bを残
して上部で開口する横断面U字状の空洞部4cが形成さ
れた船型形状のプレキャスト部材である。このPC大梁
4の上端面には、多数の縦筋4e…が突出している。そ
して、このPC大梁4の長手方向の両端面には、肉部4
b内部から突出する板状の梁ブラケット5が設けられて
おり、この梁ブラケット5には上下方向に所定間隔をあ
けてボルト孔5a…が穿設されている。これらボルト孔
5a…の穿設間隔は、柱ブラケット2のボルト孔2a…
の穿設間隔と同一に設定されている。また、このPC大
梁4の長手方向の両端面には、空洞部4cと連通する貫
通孔4dが形成されており、この貫通孔4dは端面で開
口部5bを設けて開口している。そして、この開口部5
bには空洞部4cから延在してきている梁端部鉄筋6が
突出している。なお、前記開口部5bの周縁上部には、
打設されるコンクリートとPC大梁4の端部の接合強度
が高められるコッタ7が形成されている。
Further, reference numeral 4 shown in FIGS. 1 to 3 denotes a precast PC girder (hereinafter abbreviated as PC girder) which is the second main member of this embodiment. In this PC girder 4, a PC steel wire 4a is internally reinforced along the longitudinal direction, and a hollow portion 4c having a U-shaped cross section opened at the upper portion leaving a meat portion 4b only at both ends in the longitudinal direction. Is a ship-shaped precast member in which On the upper end surface of the PC girder 4, a large number of vertical stripes 4e ... Then, on both end faces in the longitudinal direction of the PC girder 4, the meat portion 4
A plate-shaped beam bracket 5 protruding from the inside of the b is provided, and the beam bracket 5 is provided with bolt holes 5a ... At predetermined intervals in the vertical direction. The intervals between the bolt holes 5a ... Are such that the bolt holes 2a ...
It is set to be the same as the drilling interval. A through hole 4d communicating with the cavity 4c is formed on both longitudinal end faces of the PC girder 4, and the through hole 4d has an opening 5b at the end face to open. And this opening 5
A beam end reinforcing bar 6 extending from the hollow portion 4c is projected in b. In addition, in the upper part of the peripheral edge of the opening 5b,
A cotter 7 is formed to increase the joint strength between the concrete to be cast and the end of the PC girder 4.

【0011】次に、上記構成とされた鋼芯柱1及びPC
大梁4を使用して本実施例のRC造建築構造物を構築す
る方法を、工程順に図を参照して説明する。 鋼芯柱建方工程(図5参照) 予め、工場等で内部に高強度コンクリート3が充填され
た鋼芯柱1…を、現場に搬入し、それらを基礎床部Bか
ら立設している最下鋼芯柱1Bと軸線を一致させて連結
するとともに、ワイヤ8を所定位置に係合して支持す
る。立設した各鋼芯柱1…は、梁架設位置1P、2Pと
交差する高さに柱ブラケット2…が位置する。
Next, the steel core column 1 and the PC having the above structure
A method of constructing the RC building structure of this embodiment using the girders 4 will be described in the order of steps with reference to the drawings. Steel core pillar erection process (see Fig. 5) Steel core pillars 1 filled with high-strength concrete 3 in the factory are brought in to the site in advance, and they are erected from the foundation floor B. The lowermost steel core column 1B is connected with its axis aligned with each other, and the wire 8 is engaged and supported at a predetermined position. In each of the steel core columns 1 that are erected, the column brackets 2 are located at a height that intersects the beam installation positions 1P and 2P.

【0012】大梁、小梁架設工程(図6、図2及び図
3参照) 鋼芯柱1の上層側の柱ブラケット2(梁架設位置2P)
とPC大梁4の梁ブラケット5のボルト孔2a、5aど
うしを対応させ、それらにボルト9aを挿通してナット
9bで締結していく。また、鋼芯柱1の下層側の柱ブラ
ケット2(梁架設位置1P)とPC大梁4の梁ブラケッ
ト5も同様にボルト締結していく。これにより、梁架設
位置2Pの上層及び梁架設位置1Pの下層のPC大梁4
…が架設されるが、PC大梁4、4間にも、PC小梁1
0…を架設していく。
Large beam and small beam erection process (see FIGS. 6, 2 and 3) Column bracket 2 on upper layer side of steel core column 1 (beam erection position 2P)
Then, the bolt holes 2a and 5a of the beam bracket 5 of the PC girder 4 are made to correspond to each other, the bolt 9a is inserted through them, and the nut 9b is fastened. Further, the column bracket 2 (beam installation position 1P) on the lower layer side of the steel core column 1 and the beam bracket 5 of the PC girder 4 are similarly bolted. As a result, the PC girders 4 in the upper layer of the beam erection position 2P and the lower layer of the beam erection position 1P are
... is erected, but between the PC girders 4 and 4, the PC girder 1
0 ... will be installed.

【0013】床版敷設工程(図7参照) 架設されたPC大梁4、小梁10上に、デッキプレート
またはハーフPC床版等の複合床版11を敷設して下層
の床部と上層の床部を形成していく。
Floor slab laying step (see FIG. 7) A composite floor slab 11, such as a deck plate or a half PC floor slab, is laid on the erected PC girders 4 and girders 10 to form a lower floor and an upper floor. To form parts.

【0014】配筋工程(図8及び図3参照) 図3に示すように、梁架設位置1P、2Pと鋼芯柱1と
の交差位置において梁端部鉄筋6を重ね継手接合する。
この際、コンクリートが打設される前の梁端部鉄筋6、
6は開口部5b内で移動自在なので、位置合わせが容易
となり接続作業を極めて短時間で行うことができる。ま
た、図8に示すように、梁架設位置1P、2Pと鋼芯柱
1との交差位置を含めながら鋼芯柱1…の周囲に柱筋1
4…を配筋していく。さらに、PC大梁4…の下方にも
壁筋15…を配筋していく。
Reinforcing Step (See FIGS. 8 and 3) As shown in FIG. 3, the beam end reinforcing bars 6 are lap jointed at the intersections of the beam installation positions 1P, 2P and the steel core columns 1.
At this time, beam end rebar 6 before concrete is placed,
Since 6 can be moved within the opening 5b, the positioning can be facilitated and the connection work can be performed in an extremely short time. In addition, as shown in FIG. 8, the column bars 1 are provided around the steel core columns 1 while including the crossing positions of the beam installation positions 1P, 2P and the steel core columns 1.
Arrange 4 ... Further, wall reinforcements 15 are also arranged below the PC girders 4 ...

【0015】型枠組立て工程(図8参照) 梁架設位置1P、2Pと鋼芯柱1との交差位置を含む柱
筋14の周囲に、合板等の型枠板16aを設け、型枠板
16aの外側に縦バタ及び横バタ16b…を水平方向に
延在させて柱型枠16を組み立てていく。また、壁筋1
5の周囲にも、型枠板17a、縦枠17b、17cを配
設して壁型枠17を組み立てていく。
Formwork assembling process (see FIG. 8) Formwork plates 16a such as plywood are provided around the column bars 14 including the crossing positions of the beam installation positions 1P and 2P and the steel core columns 1, and formwork plates 16a The pillar form frame 16 is assembled by extending the vertical flaps and the horizontal flaps 16b ... Also, the wall muscle 1
The wall form 17 is assembled by arranging the form plates 17a and the vertical frames 17b and 17c around the periphery of the wall 5.

【0016】コンクリート打設工程(図9) 下層(梁架設位置1P)に配設されたPC大梁4、4間
若しくはPC大梁4の空洞部4cよりコンクリートを連
続して流し込んでいく。これにより、コンクリートは、
空洞部4c内部から充填されていくとともに(図4参
照)、貫通孔4dを通過して開口部5bから下層(梁架
設位置1P)側の柱型枠16…、壁型枠17…内部に充
填されていく。さらに上層(梁架設位置2P)側の柱型
枠16…、壁型枠17…内部にも連続してコンクリート
を充填していく。そして、所定時間のコンクリート養生
の後、全ての柱型枠16…、壁型枠17…を取り外すこ
とにより、2層分のRC造構造物18が構築される。
Concrete placing step (FIG. 9) Concrete is continuously poured between the PC girders 4, 4 arranged in the lower layer (beam erection position 1P) or from the cavity 4c of the PC girder 4. This gives concrete
While being filled from the inside of the hollow portion 4c (see FIG. 4), it is filled into the pillar form frame 16 on the lower layer (beam installation position 1P) side, the wall form frame 17 ... Will be done. Further, concrete is continuously filled inside the pillar formwork 16 on the side of the upper layer (beam erection position 2P), the wall formwork 17 ... Then, after concrete curing for a predetermined time, all of the column formwork 16 ... And the wall formwork 17 ... Are removed to construct the RC structure 18 for two layers.

【0017】そして、図9に示すように、2層分のRC
造構造物18の上部に露出している鋼芯柱1の上端部
に、他の鋼芯柱1を同一軸線上に連結して前述したの
鋼芯柱建方工程を行い、さらにからの工程を繰り返
し行うことにより、2層分のRC造構造物18の上にさ
らに2層分の構造物を構築することができる。
Then, as shown in FIG. 9, RC for two layers is formed.
Another steel core column 1 is connected to the upper end portion of the steel core column 1 exposed at the upper part of the building structure 18 on the same axis line, and the above-described steel core column erection process is performed. By repeating the above, it is possible to build a structure for two more layers on the RC structure 18 for two layers.

【0018】本実施例のRC造建築構造物の構築方法に
よれば、鋼芯柱建方工程において柱の建方位置に鋼芯柱
1…が建て込まれているので、これら鋼芯柱1…の柱ブ
ラケット2…にPC大梁4…の梁ブラケット5…を連結
させて同時に2層分の大梁小梁架設工程を進めることが
できる。それとともに、床版敷設工程、配筋工程、型枠
組立て工程を、2層分同時に進めることができる。そし
て、コンクリート打設工程において下層(梁架設位置1
P)、上層(梁架設位置2P)よりコンクリートが打設
されることにより、2層分の構造物18が一度に構築さ
れるので、従来のRC造建築物と比較して工期が大幅に
短縮する。これにより、超高層建築物を構築する場合で
も、SRC工法と同程度の工期で構築を完了することが
できる。
According to the method of constructing an RC building structure of this embodiment, since the steel core columns 1 ... Are built in the erected position of the columns in the steel core column erection process, these steel core columns 1 It is possible to connect the beam brackets 5 of the PC girders 4 to the pillar brackets 2 of the ... and simultaneously perform the girder small beam erection process for two layers. At the same time, the floor slab laying process, the bar arrangement process, and the formwork assembling process can be simultaneously performed for two layers. Then, in the concrete placing process, the lower layer (beam erection position 1
P), the concrete is placed from the upper layer (beam erection position 2P), so that the structure 18 for two layers is constructed at once, so the construction period is significantly shortened compared to the conventional RC building. To do. As a result, even when constructing a super high-rise building, the construction can be completed in the same construction period as the SRC construction method.

【0019】また、梁架設位置1P、2Pと鋼芯柱1と
の交差位置において対向する梁端部鉄筋6、6どうしを
機械式継手等により接続する際には、接続される前の梁
端部鉄筋6、6が開口部5b内で移動自在とされている
ので、互いの梁端部鉄筋6、6の位置合わせが容易とな
り、接続作業が極めて短時間で行うことができる。さら
に、内部に高強度コンクリート3が充填された鋼芯柱1
は、架設されるPC大梁4…、複合床版11…等の荷重
を十分に受けることができることが可能な軸力を発揮す
ることができる。
Further, when connecting the beam end reinforcing bars 6, 6 facing each other at the intersecting positions of the beam erection positions 1P, 2P and the steel core column 1, by a mechanical joint or the like, the beam ends before the connection are connected. Since the partial reinforcing bars 6, 6 are movable within the opening 5b, the beam end reinforcing bars 6, 6 can be easily aligned with each other, and the connecting work can be performed in an extremely short time. Further, a steel core column 1 filled with high strength concrete 3 inside
Can exert an axial force capable of sufficiently receiving the loads of the PC girders 4, ..., The composite floor slab 11 ...

【0020】図10に示すものは、本発明で使用される
PC大梁の他の実施例である。本実施例のPC大梁19
によれば、長手方向の下端部が削り落されて凹所20が
画成されている。そして、この凹所20の垂直壁20b
から梁端部鉄筋6…が露出する構造とされている。そし
て、梁架設位置1P、2Pと鋼芯柱1との交差位置にお
いて対向する梁端部鉄筋6、6どうしがネジテッコン1
3を使用して機械式継手により接続されている。上記構
造とされることにより、接続する前の梁端部鉄筋6は、
凹所20内で移動自在となるので、互いの梁端部鉄筋
6、6の位置合わせが容易となり、接続作業が極めて短
時間で行うことができる。
FIG. 10 shows another embodiment of the PC girder used in the present invention. PC girder 19 of this embodiment
According to the method, the lower end in the longitudinal direction is scraped off to define the recess 20. And the vertical wall 20b of this recess 20
The beam end reinforcing bars 6 ... Are exposed. Then, at the intersections of the beam erection positions 1P, 2P and the steel core column 1, the beam end rebars 6, 6 facing each other are screwed with the screw tecton 1.
3 are connected by mechanical joints. With the above structure, the beam end rebar 6 before connection is
Since it is movable in the recess 20, it is easy to align the beam end reinforcing bars 6 with each other, and the connecting work can be performed in an extremely short time.

【0021】なお、本発明の鋼芯柱1は自身が構造柱と
して機能せず、主として、PC大梁4、複合床版11等
を架設する際の架設支持体として機能するので、鋼芯柱
1の肉厚tを薄肉に設定することが可能である。また、
本発明を超高層RC造建築構造物に採用する際には、下
層側の鋼芯柱1…の肉厚tを厚肉として軸力に耐え得る
構造とし、上層側の鋼芯柱1…の肉厚tを薄肉構造とし
てもよい。また、本実施例では、2層分の構造物18が
構築される例を示したが、3層以上の構造物を同時に構
築してもよく、さらには、鋼芯柱1として丸型鋼管を使
用したが、角型鋼管を使用しても上述したものと同様の
作用効果を得ることができる。
The steel core pillar 1 of the present invention does not function as a structural pillar by itself, but mainly functions as an erection support when the PC girder 4, the composite floor slab 11, etc. are erected. It is possible to set the wall thickness t of the above to be thin. Also,
When the present invention is applied to a super high-rise RC building structure, the thickness t of the lower-layer side steel core columns 1 ... Is made thick so as to withstand axial force, and the upper-layer side steel core columns 1 ... The wall thickness t may be a thin wall structure. Further, in the present embodiment, an example in which the structure 18 for two layers is constructed has been shown, but a structure having three or more layers may be constructed at the same time, and further, a round steel pipe is used as the steel core column 1. Although used, a rectangular steel pipe can be used to obtain the same effects as those described above.

【0022】[0022]

【発明の効果】以上説明したように、本発明において
は、鋼芯柱建方工程において柱の建方位置に鋼芯柱が建
て込まれるため、この鋼芯柱の柱ブラケットにプレキャ
ストPC大梁の梁ブラケットを連結させ、同時に少なく
とも2層分の大梁小梁架設工程を行うことができる。そ
れとともに、床版敷設工程、配筋工程、型枠組立て工程
を、下層及び上層において同時に行うことができる。そ
して、コンクリート打設工程において下部層より上部層
へと順次コンクリートを打設することにより、少なくと
も2層分の構造物が一度に構築されるので、従来のRC
造建築物と比較して、工期が大幅に短縮しかつ構築コス
トも大幅に削減する。また、内部に高強度コンクリート
が充填されている鋼芯柱内は、十分にプレキャストPC
大梁、小梁、複合床版等の荷重を受けることができる。
したがって、本発明のRC造建築構造物の構築方法は、
超高層建築物を構築する場合でも、SRC工法と同程度
の工期で構築を完了することができる。
As described above, in the present invention, since the steel core pillar is built in the erection position of the pillar in the steel core pillar erection process, the pillar bracket of this steel core pillar is provided with the precast PC girder. It is possible to connect the beam brackets and simultaneously perform at least two layers of the girder / girder installation process. At the same time, the floor slab laying step, the bar arrangement step, and the formwork assembling step can be simultaneously performed in the lower layer and the upper layer. Then, in the concrete placing step, concrete is sequentially placed from the lower layer to the upper layer to construct a structure for at least two layers at a time.
Compared with building construction, the construction period is greatly shortened and the construction cost is also drastically reduced. In addition, the inside of the steel core column filled with high-strength concrete is fully precast PC.
Can receive loads such as large beams, small beams, and composite floor slabs.
Therefore, the construction method of the RC building structure of the present invention is
Even when constructing a super high-rise building, the construction can be completed in the same construction period as the SRC method.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る鋼芯柱とプレキャストPC大梁を
示す斜視図である。
FIG. 1 is a perspective view showing a steel core column and a precast PC girder according to the present invention.

【図2】鋼芯柱とプレキャストPC大梁の接合構造を示
す平面図である。
FIG. 2 is a plan view showing a joint structure of a steel core column and a precast PC girder.

【図3】鋼芯柱とプレキャストPC大梁の接合構造を示
す一部断面正面図である。
FIG. 3 is a partially sectional front view showing a joint structure of a steel core column and a precast PC girder.

【図4】コンクリートが充填されたプレキャストPC大
梁を示す断面図である。
FIG. 4 is a cross-sectional view showing a precast PC girder filled with concrete.

【図5】本発明に係る鋼芯柱建方工程を示す正面図であ
る。
FIG. 5 is a front view showing a steel core column erection process according to the present invention.

【図6】本発明に係る大梁、小梁架設工程を示す正面図
である。
FIG. 6 is a front view showing a girder and girder installation process according to the present invention.

【図7】本発明に係る床版敷設工程を示す正面図であ
る。
FIG. 7 is a front view showing a floor slab laying step according to the present invention.

【図8】本発明に係る配筋工程と型枠組立工程を示す正
面図である。
FIG. 8 is a front view showing a reinforcement step and a mold assembly step according to the present invention.

【図9】本発明の工法により構築された2層分の構築物
をを示す正面図である。
FIG. 9 is a front view showing a two-layer structure constructed by the method of the present invention.

【図10】本発明に係るプレキャストPC大梁の他の実
施例を示す図である。
FIG. 10 is a view showing another embodiment of the precast PC girder according to the present invention.

【符号の説明】[Explanation of symbols]

1 鋼芯柱 2 柱ブラケット 2a ボルト孔 3 高強度コンクリート 4 プレキャストPC大梁(PC大梁) 5 梁ブラケット 5a ボルト孔 5b 開口部 6 梁端部鉄筋 10 小梁(PC小梁) 11 複合床版 14 柱筋 15 壁筋 16 柱型枠 17 壁型枠 18 2層分のRC造構造物 H 1層の高さ 1F 下層 2F 上層 1P、2P 梁架設位置 1 Steel core column 2 Column bracket 2a Bolt hole 3 High-strength concrete 4 Precast PC girder (PC girder) 5 Beam bracket 5a Bolt hole 5b Opening 6 Beam end rebar 10 Small beam (PC small beam) 11 Composite floor slab 14 Pillar Muscle 15 Wall muscle 16 Column formwork 17 Wall formwork 18 RC structure for 2 layers H Height of 1st layer 1F Lower layer 2F Upper layer 1P, 2P Beam installation position

───────────────────────────────────────────────────── フロントページの続き (72)発明者 前田 安治 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 小林 桂樹 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 元田 弘 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 藤吉 雅利 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 永尾 真 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 (72)発明者 大竹 弘嵩 東京都千代田区富士見二丁目10番26号 前 田建設工業株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Aiji Maeda 2-10-10 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. (72) Katsura Kobayashi 2--10-10 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. (72) Inventor Hiroshi Motoda 2-10-10 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. (72) Inventor Masatoshi Fujiyoshi 2-10-26 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. (72) Inventor Makoto Nagao 2-10-10 Fujimi, Chiyoda-ku, Tokyo Maeda Construction Industry Co., Ltd. (72) Hirotake Otake 2-10-10 Fujimi, Chiyoda-ku, Tokyo No.26 Maeda Construction Industry Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 柱の建方位置に、構築される建築構造物
の少なくとも2層にわたる長さに設定され、かつ各層の
梁架設位置と交差する外周位置に柱ブラケットが突設さ
れた鋼芯柱を建て込んでいく鋼芯柱建方工程と、 隣接する鋼芯柱どうしの下層側の柱ブラケットに、内部
が空洞化され長手方向の両端部に梁ブラケットが突設さ
れているプレキャストPC大梁の該梁ブラケットを連結
してプレキャストPC大梁を架設し、上層側の柱ブラケ
ットどうしにもプレキャストPC大梁を架設していくと
ともに、架設されたプレキャストPC大梁間に小梁を架
設していく大梁、小梁架設工程と、 上層側及び下層側の大梁、小梁上に、複合床版を敷設し
て上層の床部と下層の床部を形成していく床版敷設工程
と、 梁接合位置において対向するプレキャストPC大梁どう
しの長手方向端部から突出している梁端部鉄筋どうしを
連結し、鋼芯柱の周囲に柱筋を配設し、大梁、小梁の下
方に壁筋を配設していく配筋工程と、 梁接合位置を囲繞する梁接合型枠、柱筋を囲繞する柱型
枠及び壁筋を囲繞する壁型枠を組み立てていく型枠組立
て工程と、 下層側のプレキャストPC大梁の空洞部よりコンクリー
トを梁接合型枠、柱型枠及び壁型枠内部に連続して打設
していき、順次上層側の型枠内部へもコンクリートを連
続して打設していくコンクリート打設工程とを備え、 鋼芯柱建方工程からコンクリート打設工程までの1サイ
クルの連続工程により少なくとも2層の構造物を構築し
ていくとともに、 形成された上層側の構造物より上部に露出している鋼芯
柱の上端部に、他の鋼芯柱を同一軸線上に連結して鋼芯
柱建方工程を行い、さらにコンクリート打設工程までの
各工程を繰り返し行うことを特徴とするRC造建築構造
物の構築方法。
1. A steel core having a pillar erected position with a length extending over at least two layers of a building structure to be constructed, and a column bracket projecting at an outer peripheral position intersecting a beam erection position of each layer. Precast PC girder with a steel core pillar erection process for building pillars and a hollow bracket inside, and beam brackets projecting at both ends in the longitudinal direction, between pillar brackets on the lower layer side between adjacent steel core pillars A girder that connects the beam brackets to build a precast PC girder, and builds a precast PC girder between the pillar brackets on the upper layer side as well as a girder between the installed precast PC girders. The girder erection process, the slab laying process of laying a composite floor slab on the upper and lower layer large girders and girders to form the upper and lower floor parts, and Opposing precas G. Reinforcing bar reinforcements connecting from the longitudinal ends of the PC girders are connected to each other, column reinforcements are arranged around the steel core columns, and wall reinforcements are arranged below the girders and girders. The bar arrangement process, the beam connection form surrounding the beam connection position, the form forming process that assembles the column form surrounding the column reinforcement and the wall form surrounding the wall reinforcement, and the precast PC girder on the lower layer side. Concrete pouring from the cavity into the beam-joined formwork, pillar formwork, and wall formwork continuously, and then concretely into the formwork on the upper layer side. And a structure of at least two layers is constructed by a continuous process of one cycle from the steel core pillar erection process to the concrete placing process, and the structure is exposed above the formed upper structure. The other steel core column is connected to the upper end of the existing steel core column on the same axis. Then, the method of constructing an RC building structure is characterized in that the steel core pillar erection process is performed, and then each process up to the concrete placing process is repeatedly performed.
【請求項2】 請求項1記載のRC造建築構造物の構築
方法において、鋼芯柱には、高強度コンクリートが充填
されていることを特徴とするRC造建築構造物の構築方
法。
2. The method for constructing an RC building structure according to claim 1, wherein the steel core column is filled with high-strength concrete.
JP15973493A 1993-06-29 1993-06-29 Constructing method for reinforced concrete building structure Pending JPH0718734A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15973493A JPH0718734A (en) 1993-06-29 1993-06-29 Constructing method for reinforced concrete building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15973493A JPH0718734A (en) 1993-06-29 1993-06-29 Constructing method for reinforced concrete building structure

Publications (1)

Publication Number Publication Date
JPH0718734A true JPH0718734A (en) 1995-01-20

Family

ID=15700111

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15973493A Pending JPH0718734A (en) 1993-06-29 1993-06-29 Constructing method for reinforced concrete building structure

Country Status (1)

Country Link
JP (1) JPH0718734A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7698956B2 (en) 2006-03-14 2010-04-20 Oval Corporation Coriolis flow meter with vibrating direction restriction means
CN102102396A (en) * 2010-12-28 2011-06-22 哈尔滨工业大学 Node connection method for circular steel tube concrete column and reinforced concrete shear wall
US20110191967A1 (en) * 2008-10-24 2011-08-11 Mitsuhiro Tokuno Rigid connection structure of bridge pier and concrete girder
CN107558617A (en) * 2017-10-23 2018-01-09 上海市城市建设设计研究总院(集团)有限公司 Prefabricated beam-column node structure and its construction method in contrary sequence method foundation ditch
CN109518952A (en) * 2018-12-28 2019-03-26 云南建投第二建设有限公司 One kind is for the support of assembled architecture primary and secondary beam nodes, positioning, plate device
CN110424632A (en) * 2019-08-13 2019-11-08 北京矿冶科技集团有限公司 Prefabricated foamed aluminum-core concrete-filled circular steel tube column and its assembling structure

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7698956B2 (en) 2006-03-14 2010-04-20 Oval Corporation Coriolis flow meter with vibrating direction restriction means
US20110191967A1 (en) * 2008-10-24 2011-08-11 Mitsuhiro Tokuno Rigid connection structure of bridge pier and concrete girder
US8370983B2 (en) * 2008-10-24 2013-02-12 Asahi Engineering Co., Ltd. Rigid connection structure of bridge pier and concrete girder
CN102102396A (en) * 2010-12-28 2011-06-22 哈尔滨工业大学 Node connection method for circular steel tube concrete column and reinforced concrete shear wall
CN107558617A (en) * 2017-10-23 2018-01-09 上海市城市建设设计研究总院(集团)有限公司 Prefabricated beam-column node structure and its construction method in contrary sequence method foundation ditch
CN109518952A (en) * 2018-12-28 2019-03-26 云南建投第二建设有限公司 One kind is for the support of assembled architecture primary and secondary beam nodes, positioning, plate device
CN109518952B (en) * 2018-12-28 2023-10-20 云南建投第二建设有限公司 Be used for assembled building primary and secondary beam node to support, location, template device
CN110424632A (en) * 2019-08-13 2019-11-08 北京矿冶科技集团有限公司 Prefabricated foamed aluminum-core concrete-filled circular steel tube column and its assembling structure
CN110424632B (en) * 2019-08-13 2024-04-09 北京矿冶科技集团有限公司 Prefabricated foam aluminum core round steel pipe concrete column of assembled and assembly structure thereof

Similar Documents

Publication Publication Date Title
US4147009A (en) Precast panel building construction
JP2018520285A (en) Prefabricated column and beam type construction
KR100712354B1 (en) PC Integrating Construction Method of an Underground Parking Lot and PC Column-Beam Joint System for Long Span PC Beam therein
JP3069753B2 (en) Construction method of framed reinforced concrete structure
JPH0718734A (en) Constructing method for reinforced concrete building structure
JPH02300439A (en) Prefabricating method
CN111395519A (en) Construction method of assembled beam column
JPH0781307B2 (en) How to build a skyscraper
JP2566176B2 (en) Building construction method
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JPH01287336A (en) Steel frame reinforced concrete lamination construction
JP3094198B2 (en) Precast reinforced concrete member and method of constructing structure using the same
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JPH09273317A (en) Vibration-resistant reinforcing method of existing concrete structure
JPH07279244A (en) Joint construction between column and beam in multi-story building
JPS5891246A (en) Concrete ramen prefabricating construction
JP2674442B2 (en) Structure of column-beam joint of steel reinforced concrete structure
JPS6254943B2 (en)
JPH032435A (en) Construction method for jointing column and steel frame reinforced-concrete beam to each other
JP3582027B2 (en) Construction method for concrete houses, etc.
JPH0781315B2 (en) Construction method of composite structure with precast reinforced concrete columns and steel beams
JPH01190842A (en) Method for constructing reinforced concrete column and steel girder structure
JPS6116827B2 (en)
JPH04309630A (en) Skeleton construction method using pc member
JPH03235837A (en) Method of construction for pillar and beam

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20030212