JPH0617540A - Trestle for positioning supporting steel frame - Google Patents

Trestle for positioning supporting steel frame

Info

Publication number
JPH0617540A
JPH0617540A JP17352592A JP17352592A JPH0617540A JP H0617540 A JPH0617540 A JP H0617540A JP 17352592 A JP17352592 A JP 17352592A JP 17352592 A JP17352592 A JP 17352592A JP H0617540 A JPH0617540 A JP H0617540A
Authority
JP
Japan
Prior art keywords
steel frame
frame insertion
hole
gantry body
center
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP17352592A
Other languages
Japanese (ja)
Other versions
JP3062976B2 (en
Inventor
Koichi Yamada
幸一 山田
Tomokuni Shibazaki
友邦 芝崎
Michio Sumitomo
みち夫 住友
Makoto Kamei
眞 亀井
Teruaki Hirao
輝明 平尾
Toshiaki Sekida
俊昭 世木田
Toshiro Inoue
俊郎 井上
Takenori Hirano
武範 平野
Tadao Koike
忠夫 小池
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Konoike Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Konoike Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Konoike Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP4173525A priority Critical patent/JP3062976B2/en
Publication of JPH0617540A publication Critical patent/JPH0617540A/en
Application granted granted Critical
Publication of JP3062976B2 publication Critical patent/JP3062976B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To greatly improve a degree of accuracy of positioning of a supporting steel frame in the ground and improve working efficiency. CONSTITUTION:There are provided a trestle 6 disposed on the ground at the upper part of a column hole and a steel frame insertion part 7 which extends vertically downwardly from the middle of the trestle and is disposed in a column bore and which supports a supporting frame 1 inserted by supporting rollers 20 provided in a steel frame insertion passage 7b. And a working floor 14 is provided on the upper surface of the trestle 6 and a steel frame insertion hole surrounded by a reference frame body for insertion of the steel frame 1 is provided through the center of the floor 14. Further, the insertion part 7 is disposed in such a manner-that the center of the steel frame insertion hole is aligned with the core of the steel frame insertion passage.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、下部がコンクリート中
に埋め込まれ、かつ上部が構造物の支持柱として用いら
れる支持鉄骨を建て込むための支持鉄骨建込み用架台に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a support steel erection pedestal for building a support steel frame having a lower part embedded in concrete and an upper part used as a supporting column for a structure.

【0002】[0002]

【従来の技術】一般に、逆巻工法を採用して地下構造物
を構築する際には、初期段階において、所定面積に掘削
された掘削穴の底床版中に複数本の支持鉄骨が建込まれ
る。前記支持鉄骨としては、13m〜18m程の長さの
H型鋼が使用されており、下部がコンクリート中に埋め
込まれ、上部が地下構造物の上床版を支持するか又は作
業用の架設桟橋杭として機能するように建込まれる。前
記支持鉄骨を底床版中に建込む場合には、予め、支持鉄
骨の建込み位置の所定深さに基礎坑(リバース坑)が打
ち込まれて柱穴(地表面から基礎杭の頭部までの深さが
12m〜17m程度)が形成されている。そして、柱穴
から基礎坑の頭部までコンクリートが打設された後、支
持鉄骨を、柱穴上部から高い垂直精度で挿入していくこ
とにより、底面地盤に支持鉄骨が建込まれるようになっ
ている。ここで、建込まれる支持鉄骨の垂直精度は、1
/500以下(鉛直方向500mmの範囲において水平
方向1mm以下)の精度が要求されている。
2. Description of the Related Art Generally, when constructing an underground structure by adopting the reverse winding method, a plurality of supporting steel frames are built in the bottom slab of an excavation hole excavated in a predetermined area in the initial stage. Be done. As the supporting steel frame, H-shaped steel having a length of about 13 m to 18 m is used, the lower part is embedded in concrete, and the upper part supports the upper deck of the underground structure, or as an erection pier pile for work. Built to function. When the support steel frame is built in the floor slab, a foundation pit (reverse pit) is driven in advance at a predetermined depth of the erection position of the support steel frame to form a pillar hole (from the ground surface to the head of the foundation pile). Depth of about 12 m to 17 m) is formed. Then, after the concrete is poured from the pillar hole to the head of the foundation pit, the supporting steel frame is inserted into the bottom ground by inserting the supporting steel frame from the upper part of the pillar hole with high vertical accuracy. ing. Here, the vertical accuracy of the supporting steel frame installed is 1
An accuracy of / 500 or less (1 mm or less in the horizontal direction in the range of 500 mm in the vertical direction) is required.

【0003】[0003]

【発明が解決しようとする課題】ところで、前記のよう
に支持鉄骨を建て込む場合には、以下のような問題が生
じていた。
By the way, when the supporting steel frame is built as described above, the following problems occur.

【0004】すなわち、支持鉄骨を柱穴内部に建て込む
際には、予め、支持鉄骨を臨む少なくとも2方向位置に
トランシットを設置し、複数の作業員がトランシットに
より支持鉄骨の垂直性を確認したうえで、他の作業員が
クレーン等を使用して支持鉄骨を柱穴内部に挿入してい
る。このため、従来技術においては、上述した垂直精度
に支持鉄骨を建込むために、熟練した多くの作業員によ
り多くの施工時間をかけて作業が行われているのが現状
であった。
That is, when the support steel frame is built into the pillar hole, the transits are installed in advance in at least two positions facing the support steel frame, and a plurality of workers confirm the verticality of the support steel frame by the transit. Then, another worker uses a crane or the like to insert the supporting steel frame into the pillar hole. Therefore, in the prior art, in order to build the supporting steel frame with the above-described vertical accuracy, it is the current situation that many skilled workers spend a lot of construction time on the work.

【0005】また、上述した従来の技術では、建て込ま
れるべき支持鉄骨の軸芯を柱穴の軸芯に一致させる作業
(通り芯合わせ作業)、さらには建込まれた支持鉄骨の
高さ調整をも容易に行うことができない。
Further, in the above-mentioned conventional technique, the work of aligning the axis of the supporting steel frame to be built with the axis of the column hole (passing centering work), and further adjusting the height of the built-in supporting steel frame Can't be done easily.

【0006】本発明は、前述の課題に鑑みてなされたも
ので、コンクリート中への支持鉄骨の建込み精度が大幅
に向上し、かつ作業能率を向上させることが可能な支持
鉄骨て建込み用架台を提供することを目的とするもので
ある。
[0006] The present invention has been made in view of the above-mentioned problems, and is used for constructing a supporting steel frame capable of significantly improving the accuracy of constructing the supporting steel frame in concrete and improving work efficiency. The purpose is to provide a mount.

【0007】[0007]

【課題を解決するための手段】本発明の支持鉄骨建込み
用架台は、柱穴上部の地盤上に設置される架台本体と、
架台本体の中央部から鉛直下方に延在して柱穴内部に配
設され、かつ鉄骨挿入路内に設けられた支持ローラーで
挿入された支持鉄骨を支持する鉄骨挿入部とを備えたも
のである。そして、架台本体の上面には作業床が設けら
れ、かつ作業床の中央部には基準枠体に囲まれて支持鉄
骨を挿入する鉄骨挿入孔が貫設されている。また、鉄骨
挿入部は、鉄骨挿入孔の中心と鉄骨挿入路の通り芯とが
一致せしめられて配設されている。架台本体には、架台
本体を水平方向に移動させて柱穴の軸芯と鉄骨挿入孔の
中心とを一致せしめる通り芯合わせ調整機構と、架台本
体のコーナー部を鉛直方向に移動させて基準枠体の水平
レベル出しを行う水平度調整機構と、基準枠体の水平度
を測定する水平レベル測定装置とが配設されている。一
方、鉄骨挿入部の長手方向には、鉄骨挿入部の垂直度を
測定する垂直レベル測定装置が配設されている。
A supporting steel frame erection base of the present invention comprises a base body installed on the ground above a pillar hole,
A steel frame insertion portion that extends vertically downward from the central portion of the gantry body and is disposed inside the pillar hole, and that supports the support steel frame inserted by the support roller provided in the steel frame insertion path. is there. A work floor is provided on the upper surface of the gantry body, and a steel frame insertion hole, which is surrounded by the reference frame body and into which the support steel frame is inserted, is provided at a central portion of the work floor. Further, the steel frame insertion portion is arranged such that the center of the steel frame insertion hole and the core of the steel frame insertion path are aligned with each other. The gantry body has a through-center alignment mechanism that moves the gantry body in the horizontal direction to align the axis of the column hole with the center of the steel frame insertion hole, and the corners of the gantry body in the vertical direction to move the reference frame. A leveling mechanism that adjusts the leveling of the body and a leveling device that measures the leveling of the reference frame are provided. On the other hand, a vertical level measuring device for measuring the verticality of the steel frame insertion portion is arranged in the longitudinal direction of the steel frame insertion portion.

【0008】[0008]

【作用】本発明の支持鉄骨建込み用架台によれば、通り
芯合わせ調整機構により、柱穴の軸芯に架台本体の鉄骨
挿入孔の中心を確実に一致させ、水平レベル測定装置の
傾斜データを元にして水平度調整機構を上下動させるこ
とにより基準枠体の水平レベル出しが容易に行われ、さ
らには、垂直レベル測定装置により垂直レベルを確認し
ながら鉄骨挿入部を架台本体に一体に連結することによ
り、鉄骨挿入部の通り芯が柱穴の軸芯と一致した状態で
極めて高い垂直精度に保持される。それにより、支持鉄
骨の建込み精度が大幅に向上し、支持鉄骨の建込みの工
期を短縮することができる。さらには、従来技術で必要
とされていたトランシットが不要となり、作業人員が減
少されて工費を減少させることができる。
According to the supporting steel frame erection stand of the present invention, the centering of the steel frame insertion hole of the gantry body is surely aligned with the axial center of the column hole by the centering alignment mechanism, and the tilt data of the horizontal level measuring device is obtained. The horizontal level of the reference frame can be easily adjusted by moving the horizontal adjustment mechanism up and down based on the above, and furthermore, while checking the vertical level with the vertical level measuring device, the steel frame insertion part is integrated with the gantry body. By connecting, the passage core of the steel frame insertion portion is held with extremely high vertical accuracy in a state where it coincides with the axis of the column hole. As a result, the accuracy of installing the supporting steel frame is significantly improved, and the construction period of the supporting steel frame can be shortened. Furthermore, the transit required in the prior art is no longer required, and the number of workers can be reduced and the construction cost can be reduced.

【0009】[0009]

【実施例】以下本発明の一実施例を、図1から図9を参
照して説明する。なお、支持鉄骨1が建込まれる柱穴2
は、地盤G中にのスタンドパイプ3(内径が2000m
m)が上縁部3aを地表面4から突出させた状態で埋設
されることにより形成されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to FIGS. In addition, the pillar hole 2 in which the supporting steel frame 1 is built
Is a stand pipe 3 (with an inner diameter of 2000 m
m) is formed by embedding with the upper edge 3a protruding from the ground surface 4.

【0010】図中符号5は、柱穴2の上部に設置された
本実施例の支持鉄骨建込み用架台(以下、架台と略称す
る。)である。
Reference numeral 5 in the figure denotes a supporting steel frame erection base (hereinafter abbreviated as a base) of the present embodiment, which is installed above the pillar hole 2.

【0011】この架台5は、地表面4上に設置された架
台本体6と、架台本体6の中央部下面側から鉛直下方に
延在する鉄骨挿入部7と、架台本体6の下部に設けられ
たジャーナルジャッキ(水平度調整機構)8及び通り芯
合わせ調整機構9と、傾斜装置(水平レベル測定装置)
10、浮き式傾斜計(垂直レベル測定装置)23、さら
には鉄骨挿入部7内に挿入された支持鉄骨1の高さ調整
を行うヤットコ25とが具備されてなるものである。
The pedestal 5 is provided below the gantry body 6, a gantry body 6 installed on the ground surface 4, a steel frame insertion portion 7 extending vertically downward from the lower surface of the central portion of the gantry body 6. Journal jack (horizontal level adjustment mechanism) 8 and centering alignment adjustment mechanism 9, and tilting device (horizontal level measuring device)
10, a float type inclinometer (vertical level measuring device) 23, and a yatco 25 for adjusting the height of the supporting steel frame 1 inserted in the steel frame inserting portion 7.

【0012】架台本体6は、複数本のH形鋼材6a、6
b、6c…が相互に連結されて形成された函状の基台1
1と、基台11の上面中央部に設けられた四角枠状の基
準枠体12と、基準枠体12の内側(鉄骨挿入孔13)
以外の基台11上面にパンチングメタルを取り付けて形
成された作業床14とで構成されている。また、架台本
体6の一側部には、所定高さ(1600mm程)に設定
された作業床14上まで作業員が容易に移動できるよう
に階段15が着脱自在に設けられている。また、作業床
14の周囲には、手摺り16が着脱自在に配設されてい
る。そして、架台本体6の基準枠体12には、鉄骨挿入
部7が一体的に設けられている。
The gantry body 6 includes a plurality of H-shaped steel members 6a, 6a.
A box-shaped base 1 formed by connecting b, 6c ...
1, a rectangular frame-shaped reference frame 12 provided in the center of the upper surface of the base 11, and the inside of the reference frame 12 (steel frame insertion hole 13)
And a work floor 14 formed by attaching punching metal to the upper surface of the base 11. In addition, a stair 15 is detachably provided on one side of the gantry body 6 so that a worker can easily move to a work floor 14 set to a predetermined height (about 1600 mm). A handrail 16 is removably arranged around the work floor 14. The steel frame insertion portion 7 is integrally provided on the reference frame body 12 of the gantry body 6.

【0013】鉄骨挿入部7は、長手方向に所定間隔をあ
けて平行に配設された4本のH型鋼材17a、17b、
17c、17d(鋼材長さが7700mm)間に、複数
の斜材18…及び水平材19…が剛接合されてトラス構
造に形成されたものである。そして、各H型鋼材17a
…の長手方向を鉛直方向に向け、上端部が基準枠体12
の4隅位置でボルト締めされることにより、架台本体6
から吊り下げられた状態で連結される。この場合、基準
枠体12に固定された鉄骨挿入部7は、通り芯7Pが鉄
骨挿入孔13の中心と一致する。
The steel frame insertion portion 7 includes four H-shaped steel members 17a, 17b, which are arranged in parallel in the longitudinal direction at a predetermined interval.
A plurality of diagonal members 18 ... And a horizontal member 19 ... are rigidly joined between 17c and 17d (the steel material length is 7700 mm) to form a truss structure. And each H-shaped steel material 17a
The longitudinal direction of ... is oriented in the vertical direction, and the upper end portion is the reference frame 12
By tightening the bolts at the four corners of the
It is connected in the state of being hung from. In this case, in the steel frame insertion portion 7 fixed to the reference frame body 12, the core 7P coincides with the center of the steel frame insertion hole 13.

【0014】また、鉄骨挿入部7内部の鉄骨挿入路7b
上部及び下部には、H型鋼材17a…に連結された支持
ローラー20、20が対向配置されている。これら対向
する支持ローラー20、29間の距離Lは、挿入される
支持鉄骨1のフランジ1aの幅と略同一に設定されてい
る。そして、鉄骨挿入孔13から挿入された支持鉄骨1
は、係合して回転する上部の支持ローラー20、20に
支持されながら鉄骨挿入部7の下方7b側に移動してい
き、さらに下部の支持ローラー20、20と係合して支
持されることにより、鉄骨挿入部7の通り芯7Pに、支
持鉄骨1の長手方向の軸芯1Pが一致するようになって
いる。
Further, the steel frame insertion path 7b inside the steel frame insertion portion 7
Support rollers 20, 20 connected to the H-shaped steel materials 17a are arranged opposite to each other at the upper and lower portions. The distance L between the opposing support rollers 20 and 29 is set to be substantially the same as the width of the flange 1a of the support steel frame 1 to be inserted. The supporting steel frame 1 inserted through the steel frame insertion hole 13
Is moved to the lower side 7b of the steel frame insertion portion 7 while being supported by the upper supporting rollers 20, 20 which are engaged and rotated, and further engaged with and supported by the lower supporting rollers 20, 20. As a result, the longitudinal core 1P of the supporting steel frame 1 is aligned with the base 7P of the steel-frame inserting portion 7.

【0015】また、ジャーナルジャッキ8…は、架台本
体6の底面側の4箇所のコーナー部に固定されており、
これらジャーナルジャッキ8…のいずれが適宜上下動す
ることにより、架台本体6の上部側の水平度が調整され
るようになっている。
Further, the journal jacks 8 ... Are fixed to four corner portions on the bottom surface side of the gantry body 6,
The horizontalness of the upper portion of the gantry body 6 is adjusted by vertically moving any of these journal jacks 8 ...

【0016】また、通り芯合わせ調整機構9は、架台本
体6の底部側に、平面視において直交するX方向及びY
方向の2方向に一対づつ配設されており、X方向及びY
方向に直線移動する移動棒21と、自身の回転動を移動
軸21に直線運動として伝達するハンドル部22とで構
成されている。そして、柱穴2を形成しているスタンド
パイプ3の上縁部3aに、ハンドル部22…の回転動に
より所定量に伸びた移動棒21…の先端が係合すること
により、柱穴2の軸芯2Pに鉄骨挿入部7の通り芯7P
(または鉄骨挿入孔13の中心)が合わせられるように
なっている。
The centering alignment adjusting mechanism 9 is provided on the bottom side of the gantry body 6 in the X direction and the Y direction orthogonal to each other in plan view.
They are arranged in pairs in two directions, the X direction and the Y direction.
It is composed of a moving rod 21 that linearly moves in the direction, and a handle portion 22 that transmits the rotational movement of itself to the moving shaft 21 as a linear motion. Then, by engaging the upper edge portion 3a of the stand pipe 3 forming the pillar hole 2 with the tip of the movable rod 21 ... The core 7P of the steel insertion part 7 is attached to the shaft core 2P.
(Or the center of the steel frame insertion hole 13) can be aligned.

【0017】また、基準枠体12上には傾斜装置10が
設置されている。この傾斜装置10は、基準枠体12の
X方向の水平度を測定する傾斜計10aと、基準枠体1
2のY方向の水平度を測定する傾斜計10bと、傾斜計
10a、10bから得られた基準枠体12の傾斜データ
を表示する指示計10cとを備えたものである。そし
て、指示計10cから得られた傾斜データを元にして、
前記ジャーナルジャッキ8…のいずれかを上下移動させ
て、基準枠体12(さらには鉄骨挿入部7)の水平度が
矯正されるようになっている。
A tilting device 10 is installed on the reference frame 12. The inclining device 10 includes an inclinometer 10a for measuring the horizontality of the reference frame 12 in the X direction, and the reference frame 1.
2 is provided with an inclinometer 10b for measuring the horizontal degree in the Y direction and an indicator 10c for displaying the inclination data of the reference frame 12 obtained from the inclinometers 10a, 10b. Then, based on the inclination data obtained from the indicator 10c,
By moving any one of the journal jacks 8 up and down, the levelness of the reference frame 12 (further, the steel frame insertion portion 7) is corrected.

【0018】さらに、鉄骨挿入部7には、所定のH型鋼
材17aの長手方向に沿って浮き式傾斜計23が配設さ
れている。この浮き式傾斜計23は、基準枠体12(ま
たは架台本体6)に対して鉄骨挿入部7の垂直度の精度
が高められるように設けられているもので、SGP管等
からなる円筒管(長さが約8000mm)23aの下端
部にキャップ23bが固接され、キャップ23bの内部
中央に円筒管23aの長さと略同一に設定されたつり糸
23cの一端が固接されているとともに、つり糸23c
の他端に円筒管23aの内径より縮径された筒状の発泡
スチロールで形成された浮き23dが固接され、さらに
円筒管23a内部に水23eが充填されてなるものであ
る。そして、円筒管23aの上端周縁には、90度間隔
に基準切り込み23fが設けられている。上記構造の浮
き式傾斜計23により、鉄骨挿入部7の垂直精度が保持
されていない場合(ただし、基準枠体12は水平度が保
持されているものとする。)には、円筒管23a内部の
浮き23dが傾斜方向の上方側に寄ってしまう。この場
合には、円筒管23a内部の浮き23dが中央に位置す
るように、基準枠体12と連結している鉄骨挿入部7の
上部のボルト締め部分の微調整を行う。
Further, a floating type inclinometer 23 is arranged in the steel frame inserting portion 7 along the longitudinal direction of a predetermined H-shaped steel material 17a. The float type inclinometer 23 is provided so that the accuracy of the verticality of the steel frame insertion portion 7 with respect to the reference frame body 12 (or the gantry body 6) is enhanced, and is a cylindrical pipe (such as an SGP pipe). The cap 23b is fixedly attached to the lower end of the cap 23b, and one end of the hanging thread 23c, which is set to be approximately the same as the length of the cylindrical tube 23a, is fixedly attached to the lower end of the cap 23b. Thread 23c
The other end of the cylindrical pipe 23a is fixedly contacted with a float 23d formed of a polystyrene foam having a diameter smaller than the inner diameter of the cylindrical pipe 23a, and water 23e is filled inside the cylindrical pipe 23a. Then, the reference cuts 23f are provided at intervals of 90 degrees on the upper edge of the cylindrical tube 23a. When the vertical accuracy of the steel frame insertion portion 7 is not maintained by the floating type inclinometer 23 having the above structure (however, the reference frame body 12 is maintained at the horizontal degree), the inside of the cylindrical tube 23a. The floating portion 23d of the above-mentioned float approaches the upper side in the inclination direction. In this case, the bolted portion of the upper portion of the steel frame insertion portion 7 connected to the reference frame 12 is finely adjusted so that the float 23d inside the cylindrical tube 23a is located at the center.

【0019】さらに、ヤットコ25は、架台本体6上に
配設されたジャーナルジャッキ26に支持されながら鉄
骨挿入孔13の上部に配設されており、ジャーナルジャ
ッキ26の上下動とともに上下方向に移動する。そし
て、柱穴2内部に挿入された支持鉄骨1の頭部を押圧す
ることにより、支持鉄骨1を所定高さに設定するように
なっている。
Further, the yatco 25 is provided above the steel frame insertion hole 13 while being supported by the journal jack 26 provided on the gantry body 6, and moves in the vertical direction as the journal jack 26 moves up and down. . Then, by pressing the head of the supporting steel frame 1 inserted into the pillar hole 2, the supporting steel frame 1 is set to a predetermined height.

【0020】次に、本実施例の架台10を柱穴2上に設
置する手順と、架台10を用いた支持鉄骨1の建込み方
法を説明する。
Next, a procedure for installing the gantry 10 of the present embodiment on the pillar hole 2 and a method of installing the supporting steel frame 1 using the gantry 10 will be described.

【0021】まず、地盤G中に、スタンドパイプ3を上
縁部3aを地表面4から突出させた状態で埋設して柱穴
2を形成する。そして、柱穴2内部の所定深さに基礎杭
(図示せず)を埋設するとともに、基礎杭の頭部にコン
クリートを打設しておく。
First, the stand pipe 3 is embedded in the ground G with the upper edge 3a thereof protruding from the ground surface 4 to form the pillar hole 2. Then, a foundation pile (not shown) is buried at a predetermined depth inside the pillar hole 2 and concrete is placed on the head of the foundation pile.

【0022】次に、柱穴2上部に架台本体6を設置す
る。なお、架台本体の底部のコーナー部には、予めジャ
ーナルジャッキ8…が取り付けられているものとする。
Next, the gantry body 6 is installed above the pillar hole 2. It is assumed that the journal jacks 8 are previously attached to the corners of the bottom of the gantry body.

【0023】架台本体6の設置後、X方向及びY方向の
2方向に配設されているハンドル部22…を回転させ
て、移動棒21…をスタンドパイプ3の上縁部3aに適
宜係合させ、柱穴2の軸芯2Pと鉄骨挿入孔13の中心
を一致させる。
After the gantry body 6 is installed, the handle portions 22 disposed in the two directions of the X direction and the Y direction are rotated to appropriately engage the moving rods 21 with the upper edge portion 3a of the stand pipe 3. Then, the axis 2P of the column hole 2 and the center of the steel frame insertion hole 13 are aligned.

【0024】また、傾斜装置10の指示計10cから得
られた傾斜データを元にして、ジャーナルジャッキ8…
のいずれかを上下動させ、基準枠体12の水平度を矯正
する。そして、架台本体6に、階段15と手摺り16を
連結する。
Further, based on the tilt data obtained from the indicator 10c of the tilting device 10, the journal jack 8 ...
Either of them is moved up and down to correct the levelness of the reference frame 12. Then, the staircase 15 and the handrail 16 are connected to the gantry body 6.

【0025】次に、クレーン等により架台本体6の上方
に吊り上げられてきた鉄骨挿入部7を、鉄骨挿入孔13
から柱穴2内部へ挿入していく。そして、柱穴2内部に
延在させた鉄骨挿入部7の上端部を、基準枠体12の4
隅位置にて、仮ボルト締めを行う。
Next, the steel frame insertion portion 7 that has been suspended above the gantry body 6 by a crane or the like is inserted into the steel frame insertion hole 13
Insert it into the pillar hole 2 from the inside. Then, the upper end portion of the steel frame insertion portion 7 extending inside the pillar hole 2 is attached to the reference frame 12
Tighten the temporary bolts at the corners.

【0026】ここで、鉄骨挿入部7のH型鋼材17aに
沿って浮き式傾斜計23が配設されているので、鉄骨挿
入部7の垂直精度が保持されていない場合には、円筒管
23a内部の浮き23dが中央に位置するまで、基準枠
体12と、鉄骨挿入部7の上部とのボルト締め部分の微
調整を行う。そして、鉄骨挿入部7の垂直精度が矯正さ
れると、柱穴2の軸芯2Pと鉄骨挿入部7の通り芯7P
(または鉄骨挿入孔13の中心)とが一致した状態で鉄
骨挿入部7が架台本体6に一体化する。
Here, since the float type inclinometer 23 is arranged along the H-shaped steel material 17a of the steel frame inserting portion 7, when the vertical accuracy of the steel frame inserting portion 7 is not maintained, the cylindrical pipe 23a. Fine adjustment of the bolted portion between the reference frame body 12 and the upper portion of the steel frame insertion portion 7 is performed until the inner floating portion 23d is located at the center. When the vertical accuracy of the steel frame insertion portion 7 is corrected, the shaft core 2P of the column hole 2 and the core 7P of the steel frame insertion portion 7 are corrected.
(Or the center of the steel frame insertion hole 13) and the steel frame insertion part 7 is integrated with the gantry body 6.

【0027】そして、クレーン等で吊り上げられて移動
してきた支持鉄骨1を、鉄骨挿入孔13から鉄骨挿入部
7内に挿入していく。徐々に下方側7aに下降していく
支持鉄骨1は、上部及び下部の支持ローラー20、20
と係合して支持されながら、鉄骨挿入部7の通り芯7P
に沿って移動していく。そして、基礎杭頭部に極めて高
い垂直精度とされて建込まれる。
Then, the supporting steel frame 1 that has been lifted and moved by a crane or the like is inserted into the steel frame insertion portion 7 from the steel frame insertion hole 13. The supporting steel frame 1 that gradually descends to the lower side 7a includes the upper and lower supporting rollers 20, 20.
While being supported by being engaged with, the core 7P of the steel insertion portion 7
Move along. Then, it is erected with extremely high vertical accuracy on the foundation pile head.

【0028】さらに、ジャーナルジャッキ26の上下動
によってヤットコ25が支持鉄骨1の頭部を押圧するこ
とにより、支持鉄骨1は所定の高さに設定される。
Further, the yatco 25 presses the head of the supporting steel frame 1 by the vertical movement of the journal jack 26, whereby the supporting steel frame 1 is set to a predetermined height.

【0029】従って、本実施例の柱穴2上に設置された
架台10は、通り芯合わせ調整機構9のハンドル部22
を回動させて所定量に伸長させた移動棒21をスタンド
イパイプ3の上縁部3aに係合することにより、柱穴2
の軸芯2Pに架台本体6の中央部(鉄骨挿入孔13の中
心)を確実に一致させ、傾斜装置10の傾斜データを元
にしてジャーナルジャッキ8…のいずれかを上下動させ
ることにより基準枠体12の水平レベル出しが容易に行
われ、さらには、浮き式傾斜計23内部の浮き23d位
置を確認しながら鉄骨挿入部7を架台本体6に一体に連
結することにより、鉄骨挿入部7の通り芯7Pが柱穴2
の軸芯2Pと一致して極めて高い垂直精度に保持される
ので、支持鉄骨1の建込み精度が大幅に向上し、さらに
は支持鉄骨1の建込みの工期を短縮することができる
Therefore, the gantry 10 installed on the pillar hole 2 of this embodiment has the handle portion 22 of the centering alignment adjusting mechanism 9.
The movable rod 21 that is rotated to extend a predetermined amount is engaged with the upper edge portion 3a of the stand pipe 3 so that the column hole 2
The center portion of the gantry body 6 (the center of the steel frame insertion hole 13) is surely aligned with the axis 2P of the reference frame, and one of the journal jacks 8 is moved up and down based on the inclination data of the inclining device 10 to move the reference frame. The leveling of the body 12 is easily performed, and furthermore, the steel frame inserting portion 7 is integrally connected to the gantry body 6 while confirming the position of the floating portion 23d inside the floating type inclinometer 23. The core 7P has a pillar hole 2
Since it is held with extremely high vertical accuracy in conformity with the shaft core 2P of, the installation accuracy of the support steel frame 1 is significantly improved, and further the construction period of the support steel frame 1 can be shortened.

【0030】また、従来技術で必要とされていたトラン
シットが不要となり、作業人員が減少されて工費を減少
させることができる。
Further, the transit, which is required in the prior art, becomes unnecessary, the number of workers is reduced, and the construction cost can be reduced.

【0031】[0031]

【発明の効果】以上説明したように、本発明の支持鉄骨
建込み用架台は、通り芯合わせ調整機構により柱穴の軸
芯に架台本体の鉄骨挿入孔の中心を確実に一致させ、水
平レベル測定装置の傾斜データを元にして水平度調整機
構を上下動させることにより基準枠体の水平レベル出し
が容易に行われ、さらには、垂直レベル測定装置を確認
しながら鉄骨挿入部を架台本体に一体に連結することに
より、鉄骨挿入部の通り芯が柱穴の軸芯と一致した状態
で極めて高い垂直精度に保持されるため、支持鉄骨の建
込み精度が大幅に向上し、かつ支持鉄骨の建込みの工期
を短縮することができ、さらには、従来技術で必要とさ
れていたトランシットが不要となり、作業人員が減少さ
れて工費を減少させることができる。
As described above, according to the supporting steel frame erection base of the present invention, the center of the steel frame insertion hole of the gantry body is surely aligned with the axial center of the column hole by the centering alignment adjusting mechanism, and the horizontal level. By moving the leveling mechanism up and down based on the tilt data of the measuring device, the horizontal level of the reference frame can be easily set.Furthermore, while checking the vertical level measuring device, the steel frame insertion part can be placed on the gantry body. By connecting them together, the core of the steel frame insertion part is held with extremely high vertical accuracy in a state where it is aligned with the axis of the column hole. The construction period can be shortened, and further, the transit required in the prior art is not required, which reduces the number of workers and reduces the construction cost.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の一実施例を示す正面図である。FIG. 1 is a front view showing an embodiment of the present invention.

【図2】前記側面図である。FIG. 2 is the side view.

【図3】図1におけるIIIーIII矢視図である。FIG. 3 is a view on arrow III-III in FIG.

【図4】図2におけるIVーIV矢視図である。FIG. 4 is a view taken along the line IV-IV in FIG.

【図5】本発明の鉄骨挿入部を示す正面図である。FIG. 5 is a front view showing a steel frame insertion portion of the present invention.

【図6】前記鉄骨挿入部の側面図である。FIG. 6 is a side view of the steel frame insertion portion.

【図7】図5のVIIーVII矢視図である。FIG. 7 is a view on arrow VII-VII in FIG.

【図8】図6のVIIIーVIII矢視図である。FIG. 8 is a view on arrow VIII-VIII in FIG.

【図9】図6のIXーIX矢視図である9 is a view taken along the line IX-IX in FIG.

【符号の説明】[Explanation of symbols]

1 支持鉄骨 2 柱穴 2P 柱穴の軸芯 3 スタンドパイプ 3a スタンドパイプの上縁部 5 架台 6 架台本体 7 鉄骨挿入部 7b 鉄骨挿入路 7P 鉄骨挿入路の通り芯 8 ジャーナルジャッキ(水平度調整機構) 9 通り芯合わせ調整機構 10 傾斜装置(水平レベル測定装置) 11 基台 12 基準枠体 13 鉄骨挿入孔 14 作業床 20 支持ローラー 23 浮き式傾斜計(垂直レベル測定装置) 25 ヤットコ 26 ジャーナルジャッキ G 地盤 1 Support Steel 2 Pillar Hole 2P Shaft Core of Pillar Hole 3 Stand Pipe 3a Upper Edge of Stand Pipe 5 Stand 6 Stand Main Body 7 Steel Insertion Part 7b Steel Insertion Passage 7P Steel Insertion Passage Core 8 Journal Jack (Level Adjustment Mechanism) ) 9 Center alignment adjusting mechanism 10 Tilt device (horizontal level measuring device) 11 Base 12 Reference frame body 13 Steel frame insertion hole 14 Working floor 20 Support roller 23 Floating inclinometer (vertical level measuring device) 25 Yatco 26 Journal jack G ground

───────────────────────────────────────────────────── フロントページの続き (72)発明者 芝崎 友邦 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 住友 みち夫 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 亀井 眞 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 平尾 輝明 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 世木田 俊昭 東京都千代田区神田駿河台二丁目3番地11 号 株式会社鴻池組東京本店内 (72)発明者 井上 俊郎 東京都千代田区神田駿河台二丁目3番地11 号 株式会社鴻池組東京本店内 (72)発明者 平野 武範 東京都千代田区神田駿河台二丁目3番地11 号 株式会社鴻池組東京本店内 (72)発明者 小池 忠夫 東京都千代田区神田駿河台二丁目3番地11 号 株式会社鴻池組東京本店内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Tomokuni Shibazaki 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Michio Sumitomo 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Makoto Kamei 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Teruaki Hirao 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Toshiaki Setida 2-3-11, Kanda Surugadai, Chiyoda-ku, Tokyo Inside Konoike Gumi Co., Ltd., Tokyo Main Store (72) Inventor Toshiro Inoue 2-chome, 3-11 Kanda Surugadai, Chiyoda-ku, Tokyo Konoike Gumi Tokyo In-store (72) Inventor Takenori Hirano 2-3-3, Kanda Sugawadai, Chiyoda-ku, Tokyo No. 3-11, Konoikegumi Co., Ltd. Tokyo Main Store (72) Inventor Tadao Koike 2-3-3 Kanda Surugadai, Chiyoda-ku, Tokyo Konoikegumi Tokyo Main Store

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 下部がコンクリート中に埋め込まれ、上
部が建築物の柱として用いられる支持鉄骨を、地盤を掘
削して形成した柱穴内部に建込む支持鉄骨建込み用架台
であって、 前記柱穴上部の地盤上に設置される架台本体と、該架台
本体の中央部から鉛直下方に延在して柱穴内部に配設さ
れ、かつ鉄骨挿入路内に設けられた支持ローラーで挿入
された支持鉄骨を支持する鉄骨挿入部とを備え、 しかも、前記架台本体の上面に作業床が設けられ、かつ
該作業床の中央部に基準枠体に囲まれて支持鉄骨を挿入
する鉄骨挿入孔が貫設され、前記鉄骨挿入部は、前記鉄
骨挿入孔の中心と前記鉄骨挿入路の通り芯とが一致せし
められて配設されており、 前記架台本体には、架台本体を水平方向に移動させて柱
穴の軸芯と前記鉄骨挿入孔の中心とを一致せしめる通り
芯合わせ調整機構と、架台本体のコーナー部を鉛直方向
に移動させて前記基準枠体の水平レベル出しを行う水平
度調整機構と、前記基準枠体の水平度を測定する水平レ
ベル測定装置とが配設されているとともに、 前記鉄骨挿入部の長手方向には、該鉄骨挿入部の垂直度
を測定する垂直レベル測定装置が配設されていることを
特徴とする支持鉄骨建込み用架台。
1. A support steel frame erection base in which a support steel frame having a lower portion embedded in concrete and an upper portion used as a pillar of a building is erected inside a pillar hole formed by excavating the ground, A gantry body installed on the ground above the pillar hole, and extending vertically downward from the central portion of the gantry body, disposed inside the pillar hole, and inserted by a support roller provided in the steel frame insertion path. And a steel frame insertion portion for supporting the support steel frame, a work floor is provided on the upper surface of the gantry body, and a steel frame insertion hole for inserting the support steel frame is surrounded by a reference frame in the central portion of the work floor. And the steel frame insertion portion is disposed such that the center of the steel frame insertion hole and the core of the steel frame insertion path are aligned with each other, and the frame body is moved horizontally in the frame body. Align the shaft center of the column hole with the center of the steel frame insertion hole. A horizontal alignment adjusting mechanism, a horizontal level adjusting mechanism for vertically moving the corners of the gantry body to level the reference frame, and a horizontal level measuring device for measuring the levelness of the reference frame. And a vertical level measuring device for measuring the verticality of the steel frame insertion part is arranged in the longitudinal direction of the steel frame insertion part. .
JP4173525A 1992-06-30 1992-06-30 Supporting steel frame mounting base Expired - Lifetime JP3062976B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4173525A JP3062976B2 (en) 1992-06-30 1992-06-30 Supporting steel frame mounting base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4173525A JP3062976B2 (en) 1992-06-30 1992-06-30 Supporting steel frame mounting base

Publications (2)

Publication Number Publication Date
JPH0617540A true JPH0617540A (en) 1994-01-25
JP3062976B2 JP3062976B2 (en) 2000-07-12

Family

ID=15962143

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4173525A Expired - Lifetime JP3062976B2 (en) 1992-06-30 1992-06-30 Supporting steel frame mounting base

Country Status (1)

Country Link
JP (1) JP3062976B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4832510A (en) * 1987-03-12 1989-05-23 Nippon Thompson Co., Ltd. Linear motion rolling-contact bearing assembly having a locally reinforced guide wall
CN109208533A (en) * 2018-09-26 2019-01-15 中交第二航务工程局有限公司 Harbour integrated construction system and method based on stake top top pushing platform
WO2024077905A1 (en) * 2023-03-03 2024-04-18 中铁四局集团建筑工程有限公司 Device and construction method for quickly positioning steel pipe pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4832510A (en) * 1987-03-12 1989-05-23 Nippon Thompson Co., Ltd. Linear motion rolling-contact bearing assembly having a locally reinforced guide wall
CN109208533A (en) * 2018-09-26 2019-01-15 中交第二航务工程局有限公司 Harbour integrated construction system and method based on stake top top pushing platform
WO2024077905A1 (en) * 2023-03-03 2024-04-18 中铁四局集团建筑工程有限公司 Device and construction method for quickly positioning steel pipe pile

Also Published As

Publication number Publication date
JP3062976B2 (en) 2000-07-12

Similar Documents

Publication Publication Date Title
US7530176B2 (en) Method and apparatus for monitoring element alignment
CN104264682A (en) Anchor traction wall protection pile base layer concrete beam support pouring technology
JP3062976B2 (en) Supporting steel frame mounting base
JP2005090116A (en) Method for erecting steel frame column and positioning frame body used for it
JPH08120673A (en) Accurate erection method and equipment for steel frame column under ground surface of reverse construction method
JPH09203041A (en) Structural center column erection method and guide pipe used therefor
JP4359909B2 (en) Form raising control method in slip form method
CN116122189A (en) Arch bridge dismantling method
CN216920302U (en) Pre-buried steel column transfers system of hanging down
JP2556215B2 (en) Construction method
JP3616895B2 (en) Construction pillar erection device
JP3750042B2 (en) Construction pillar erection device
JP3030374B2 (en) Construction method and equipment for trussed pillar
JPH07122273B2 (en) Structure pillar built-in stand
GB2261891A (en) Installing columns e.g. below ground
JPH0531631B2 (en)
JP2556216B2 (en) Construction pillar installation jig
CN113832966B (en) Accurate positioning device for large-diameter ultra-long steel casing and accurate installation method thereof
JPH0782892A (en) Build-in method of temporary steel column for reverse placing construction method
CN217630058U (en) Underground structure supporting component and underground construction building
CN213952224U (en) Guide frame for embedding ultra-long steel protection cylinder
CN215669529U (en) Open cut foundation pit continuous beam capable of being rapidly installed with steel support
JP6913269B2 (en) Oblique pile driving stand and diagonal pile driving method
JPH0384165A (en) Execution of setting of anchor bolt and setting apparatus therefor
JP2003129502A (en) Construction device of post-insertion building central column and construction method in inverted construction method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20000314