JPH0561409B2 - - Google Patents

Info

Publication number
JPH0561409B2
JPH0561409B2 JP61169200A JP16920086A JPH0561409B2 JP H0561409 B2 JPH0561409 B2 JP H0561409B2 JP 61169200 A JP61169200 A JP 61169200A JP 16920086 A JP16920086 A JP 16920086A JP H0561409 B2 JPH0561409 B2 JP H0561409B2
Authority
JP
Japan
Prior art keywords
pile
wall
hole
concrete
concrete pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP61169200A
Other languages
Japanese (ja)
Other versions
JPS6327617A (en
Inventor
Nakamasa Murakami
Chikao Watabe
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitani Sekisan Co Ltd
Original Assignee
Mitani Sekisan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitani Sekisan Co Ltd filed Critical Mitani Sekisan Co Ltd
Priority to JP16920086A priority Critical patent/JPS6327617A/en
Publication of JPS6327617A publication Critical patent/JPS6327617A/en
Publication of JPH0561409B2 publication Critical patent/JPH0561409B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、プレボーリングによるコンクリー
トくいの設置工法に関する。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a method for installing concrete piles by pre-boring.

(従来の技術) 従来プレボーリングによるコンクリートくいの
設置工法においては、くい周固定液として、例え
ば所定量のセメントミルクをくい穴の下部に注入
しておき、くいの挿入によつて、くい穴内壁と、
くい外壁との間に、前記注入セメントミルクを上
昇させるようにしている。
(Prior art) In the conventional method of installing concrete piles by pre-boring, a predetermined amount of cement milk, for example, is poured into the lower part of the pile hole as a fixing liquid around the pile, and by inserting the pile, the inner wall of the pile is fixed. and,
The injected cement milk is allowed to rise between the pile and the outer wall.

(発明が解決しようとする課題) 然し乍ら、くいの下端を所定長さに亘つて大径
にしたくいにあつては、くいの上部外径に対し
て、くい穴の上部内径が大きく、くいの上部を不
安定にするおそれがあつた。例えばくい穴上部に
おける間隙は暫々5cm(直径10cm)以上になるこ
とがある。このような場合に、くい穴底から上部
まで、くい周固定液を充填すると、厖大な量のセ
メントミルクを必要とし(くいの中空部にも入る
ので一層大量になる)、施工費の増大と、施工労
力および時間の増大を招くなどの問題点があつ
た。
(Problem to be Solved by the Invention) However, when the lower end of the pile is made to have a large diameter over a predetermined length, the upper inner diameter of the hole in the pile is larger than the outer diameter of the upper part of the pile. There was a risk that the upper part would become unstable. For example, the gap at the top of the hole may be more than 5 cm (10 cm in diameter). In such a case, filling the pile circumferential fixative from the bottom to the top of the hole would require a huge amount of cement milk (the amount would be even larger since it would also enter the hollow part of the pile), which would increase construction costs. However, there were problems such as increased construction labor and time.

(課題を解決する為の手段) 然るにこの発明は、くい穴にコンクリートくい
を挿入した後に、くい穴上端内壁と、コンクリー
トくいの外壁との間に、くい周固定液を注入する
ようにして、前記従来の問題点を解決したのであ
る。
(Means for Solving the Problems) However, in this invention, after inserting a concrete pile into a pile hole, a pile circumferential fixing liquid is injected between the inner wall at the upper end of the pile hole and the outer wall of the concrete pile, This solves the conventional problems mentioned above.

即ちこの発明は、くいの設置予定地へ、所定の
くい穴を掘削し、このくい穴に、下端部へ所定長
さに亘つて大径部を連設したコンクリートくいを
挿入設置する工法において、コンクリートくいを
挿入後、くい穴内壁又はコンクリートくいの外壁
に案内させながら、支持材により支持されたノズ
ル付の注液管を下降させ、前記ノズルからくい周
固定液を注入しつつ該固定液を前記支持材により
攪拌してコンクリートくいの外側壁と、くい穴内
壁との間隙部へ所定長さに亘つてくい周固定液を
充填し、コンクリートくいを固定することを特徴
としたプレボーリングによるくい設置工法であ
る。前記支持材は、例えば合成樹脂製又は鋼製の
円筒或いは支杆などの枠材を用いる。前記円筒の
外壁には突片が千鳥状に突設してあり、円筒を回
転することによつてセメントミルク又はセメント
ミルク間隙介在液とを混合できるようになつてい
る。
That is, the present invention provides a construction method in which a predetermined pile hole is excavated at a site where the pile is planned to be installed, and a concrete pile having a large diameter section connected to the lower end over a predetermined length is inserted and installed into the hole. After inserting the concrete pile, lower the liquid injection pipe with a nozzle supported by the support material while guiding it to the inner wall of the pile or the outer wall of the concrete pile, and inject the fixing liquid around the pile from the nozzle. A pre-boring pile characterized in that the concrete pile is fixed by filling the gap between the outer wall of the concrete pile and the inner wall of the pile with a fixing liquid over a predetermined length by stirring with the support material. This is an installation method. As the support material, a frame material such as a cylinder or a support rod made of synthetic resin or steel is used, for example. Projections are provided on the outer wall of the cylinder in a staggered manner, and by rotating the cylinder, the cement milk or cement milk interstitial liquid can be mixed.

(作用) 即ちこの発明によれば、くい穴上端部内壁と、
くいの上端部外壁との間に、くい周固定液を注入
するので、くいの上端部はくい穴上端部に安定固
定される。然して、くい周固定液を攪拌しつつ注
入すれば、液の硬化により均質固定材を介在した
ものということができる。
(Function) That is, according to the present invention, the inner wall of the upper end of the hole;
Since the pile circumferential fixing liquid is injected between the upper end of the pile and the outer wall, the upper end of the pile is stably fixed to the upper end of the pile hole. However, if the circumferential fixing liquid is injected while stirring, it can be said that a homogeneous fixing material is interposed as the liquid hardens.

(実施例) 次にこの発明の実施例について説明する。(Example) Next, embodiments of this invention will be described.

コンクリートくい1の設置予定地2へ、くい穴
3を掘削し、くい穴3内へ、コンクリートくい1
を挿入し、その下端をくい穴底へ固定する。前記
コンクリートくい1は、下端部へ所定長さに亘つ
て大径部1aを連設してある。この固定について
は、拡底し、該部へセメントミルクを注入して固
定し、或いはその他の根固め工法又は最終軽打工
法等を用いる。次に鋼管4の下端に注液管5を埋
設した案内環6を嵌挿固定し、前記案内環6の外
側壁には、外壁が、くい穴壁に案内できる複数の
突条7を等間隔に縦設し、前記案内環6の下側に
は注液管5のノズル口8を穿設し、注液管5に
は、前記鋼管4の外壁にはセメントミルクの移送
管9を設ける。
Dig a hole 3 in the planned installation site 2 of concrete pile 1, and insert concrete pile 1 into the hole 3.
and fix its lower end to the bottom of the hole. The concrete pile 1 has a large diameter portion 1a extending over a predetermined length toward the lower end thereof. For this fixation, the bottom is widened and cement milk is injected into the area to fix it, or other methods such as root hardening or final pounding are used. Next, a guide ring 6 with a liquid injection pipe 5 buried therein is inserted and fixed into the lower end of the steel pipe 4, and the outer wall of the guide ring 6 has a plurality of protrusions 7 arranged at equal intervals so as to be able to guide the hole wall. A nozzle port 8 of a liquid injection pipe 5 is provided on the lower side of the guide ring 6, and a cement milk transfer pipe 9 is provided on the outer wall of the steel pipe 4 of the liquid injection pipe 5.

前記鋼管4をコンクリートくい1の上部に嵌挿
しつつ下降し、適度に下降した位置から、前記鋼
管4を回転し、かつ緩徐に上昇しつつ、前記ノズ
ル口8から、前記コンクリートくい1と前記くい
穴3壁との間隙部10に、セメントミルクを注出
する。このようにすると、セメントミルクは、前
記コンクリートくい1の外壁と、くい穴3の内壁
との間の間隙部10に順次充填されると共に、鋼
管4を回転しつつ、上下することによつて、前記
間隙部10へセメントミルクを均等に分布させる
ことができる。
The steel pipe 4 is lowered while being inserted into the upper part of the concrete pile 1, and from the moderately lowered position, the steel pipe 4 is rotated and slowly raised, the concrete pile 1 and the concrete pile are inserted through the nozzle port 8. Cement milk is poured into the gap 10 between the hole 3 and the wall. In this way, the cement milk is sequentially filled into the gap 10 between the outer wall of the concrete pile 1 and the inner wall of the pile hole 3, and by moving the steel pipe 4 up and down while rotating, Cement milk can be evenly distributed in the gap 10.

前記実施例においては、注液管5の支持材に鋼
管4を用いたが、適宜の杆体又は枠体によつて注
液管5を支持してもよいことは勿論である。
In the embodiment described above, the steel pipe 4 was used as the support material for the liquid injection pipe 5, but it goes without saying that the liquid injection pipe 5 may be supported by an appropriate rod or frame.

(発明の効果) 即ちこの発明によれば、プレボーリングによる
コンクリートくいの設置工法において、くい穴へ
くいを挿入した後、その上部外側へセメントミル
クを注入して、くいを保定するので、くいは安定
保持され、確実に支持効果を発揮すると共に、比
較的少量の材料で有効な基礎を造成し得る効果が
ある。
(Effect of the invention) That is, according to the present invention, in the method of installing concrete piles by pre-boring, after inserting the pile into the hole, cement milk is injected to the outside of the upper part to hold the pile. It is stably held, provides reliable support, and can create an effective foundation with a relatively small amount of material.

次にくい周固定液は支持材で攪拌するので、均
質固定材ができる効果がある。
Since the next weaker peripheral fixative is stirred by the support material, it has the effect of creating a homogeneous fixative.

また、くい穴壁とコンクリートくい外壁との間
に、くい周固定液を注入するので、間隙部が大き
い場合でも、くい穴がくずれるおそれがなく、く
いを所定位置に保つたまま、くい周固定液を注入
できる効果がある。次に、くいの挿入位置が多少
ずれた場合でも、位置を調節できる効果がある。
更にくいの下端部を大径にしたので、くい挿入時
にくいをくい穴の中心に設置し易く、かつ拡底時
に根固めが確実にできるなどの諸効果がある。
In addition, since the pile circumference fixing liquid is injected between the pile hole wall and the concrete pile outer wall, there is no risk of the pile hole collapsing even if the gap is large, and the pile circumference is fixed while keeping the pile in the specified position. It has the effect of injecting liquid. Secondly, even if the insertion position of the stake is slightly shifted, the position can be adjusted.
Since the lower end of the pile has a large diameter, it is easy to place the pile in the center of the pile hole when inserting the pile, and it is also possible to reliably secure the footing when expanding the bottom.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の実施中途における一部断面
図、第2図は同じくこの発明の実施に用いる鋼管
の一部正面図、第3図は同じく下面図、第4図は
同じく一部断面拡大図である。 1……コンクリートくい、1a……大径部、3
……くい穴、4……鋼管、5……注液管、8……
ノズル口、10……間隙部。
Fig. 1 is a partial sectional view of a steel pipe in the middle of implementation of this invention, Fig. 2 is a partial front view of a steel pipe used in the implementation of this invention, Fig. 3 is a bottom view, and Fig. 4 is a partially enlarged cross-sectional view. It is a diagram. 1... Concrete pile, 1a... Large diameter part, 3
...Drilled hole, 4... Steel pipe, 5... Liquid injection pipe, 8...
Nozzle opening, 10... gap portion.

Claims (1)

【特許請求の範囲】 1 くいの設置予定地へ、所定のくい穴を掘削
し、このくい穴に、下端部へ所定長さに亘つて大
径部を連設したコンクリートくいを挿入設置する
工法において、コンクリートくいを挿入後、くい
穴内壁又はコンクリートくいの外壁に案内させな
がら、支持材により支持されたノズル付の注液管
を下降させ、前記ノズルからくい周固定液を注入
しつつ、該固定液を前記支持材により攪拌してコ
ンクリートくいの外側壁と、くい穴内壁との間隙
部へ、所定長さに亘つてくい周固定液を充填し、
コンクリートくいを固定することを特徴としたプ
レボリーングによるくい設置工法。 2 支持材は円筒とした特許請求の範囲第1項記
載のプレボーリングによるくい設置工法。
[Scope of Claims] 1. A construction method in which a specified pile hole is excavated at the site where the pile is planned to be installed, and a concrete pile with a large diameter section connected to the lower end over a specified length is inserted into the hole. After inserting the concrete pile, a liquid injection pipe with a nozzle supported by a support material is lowered while being guided by the inner wall of the pile or the outer wall of the concrete pile, and while injecting a fixing liquid around the pile from the nozzle, Stirring the fixing solution with the support material and filling the gap between the outer wall of the concrete pile and the inner wall of the concrete pile with the fixing solution over a predetermined length;
A pile installation method using pre-boiling, which is characterized by fixing concrete piles. 2. The pile installation method by pre-boring as set forth in claim 1, wherein the support material is cylindrical.
JP16920086A 1986-07-18 1986-07-18 Setting work of pile by preboring Granted JPS6327617A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16920086A JPS6327617A (en) 1986-07-18 1986-07-18 Setting work of pile by preboring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16920086A JPS6327617A (en) 1986-07-18 1986-07-18 Setting work of pile by preboring

Publications (2)

Publication Number Publication Date
JPS6327617A JPS6327617A (en) 1988-02-05
JPH0561409B2 true JPH0561409B2 (en) 1993-09-06

Family

ID=15882063

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16920086A Granted JPS6327617A (en) 1986-07-18 1986-07-18 Setting work of pile by preboring

Country Status (1)

Country Link
JP (1) JPS6327617A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4604698B2 (en) * 2004-12-16 2011-01-05 Jfeスチール株式会社 Screwed pile and its construction method
JP6006110B2 (en) * 2012-12-26 2016-10-12 鹿島建設株式会社 Foundation pile construction method
CN106522210B (en) * 2016-11-09 2018-12-18 中交路桥华东工程有限公司 A kind of naked rock geology stress steel-pipe pile stake bottom anchoring structure
JP2018135683A (en) * 2017-02-21 2018-08-30 株式会社三誠 Ground improvement device and ground improvement method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57133920A (en) * 1981-02-12 1982-08-18 Takechi Koumushiyo:Kk Method and apparatus for strengthening horizontal bearing force of pile

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57133920A (en) * 1981-02-12 1982-08-18 Takechi Koumushiyo:Kk Method and apparatus for strengthening horizontal bearing force of pile

Also Published As

Publication number Publication date
JPS6327617A (en) 1988-02-05

Similar Documents

Publication Publication Date Title
JPH0561409B2 (en)
JPH0460022A (en) Sheathing method and sheathing pile therefor
GB1603637A (en) Supporting building structures
JP3129676B2 (en) Piling columns in building structures using piles as pillars
JPS615125A (en) Foundation of building
KR102335023B1 (en) pulling up device for restoration structure
US4588327A (en) Precast concrete pile and method of placing it in the ground
JPH0841870A (en) Method of connection precast concrete pile
JP2000120065A (en) Pile and its execution method
JP2884273B2 (en) Construction method for high strength cast-in-place concrete piles
JPS61254716A (en) Setting of in-place concrete pile
JPH03250114A (en) Construction method of cast-in-place concrete pile
JPS58120918A (en) Burying method for pile
JPS6198824A (en) Method of installing reinforcing steel pipe to upper part of pile
JP2881501B2 (en) Construction method for high strength cast-in-place concrete piles
SU914723A1 (en) Method of erecting a structure on pile foundation
JPH0565652B2 (en)
KR19990048467A (en) Auger pile method using expandable mortar
JPH0351365Y2 (en)
JPS6214186Y2 (en)
JP3697641B2 (en) Hollow pile for excavation
JPS5826453B2 (en) Foundation construction method
JP2530160Y2 (en) Pile for rotary burial method with pre-boring
JPS61286414A (en) Constructing method for multispindle soil cement column line
SU1411373A1 (en) Method of constructing cast-in-place hollow pile

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term