JPH0543028B2 - - Google Patents

Info

Publication number
JPH0543028B2
JPH0543028B2 JP15806386A JP15806386A JPH0543028B2 JP H0543028 B2 JPH0543028 B2 JP H0543028B2 JP 15806386 A JP15806386 A JP 15806386A JP 15806386 A JP15806386 A JP 15806386A JP H0543028 B2 JPH0543028 B2 JP H0543028B2
Authority
JP
Japan
Prior art keywords
construction
light
light receiving
main body
light emitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP15806386A
Other languages
Japanese (ja)
Other versions
JPS6314960A (en
Inventor
Makoto Komori
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP15806386A priority Critical patent/JPS6314960A/en
Publication of JPS6314960A publication Critical patent/JPS6314960A/en
Publication of JPH0543028B2 publication Critical patent/JPH0543028B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 産業上の利用分野 本発明は、鉄骨構造、鉄骨鉄筋コンクリート造
等の建築物、鉄骨製タワー又はカーテンウオール
等の構築材の建方装置に関するものである。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention relates to an apparatus for constructing construction materials such as steel structures, steel reinforced concrete buildings, steel towers, curtain walls, and the like.

従来の技術 従来、例えば鉄骨の建方方法としては、第9図
に示すように、工場にて数層分を1筋として加工
された鉄骨柱を、構築現場にてタワークレーン等
の建方機械により建込むと共に、これに鉄骨梁等
の横架材を掛け渡し、各接合部を本締ボルトの1/
5〜1/3本数のボルトで仮締めし、その後、鉄骨の
要所にワイヤーで筋かいを張つてトランシツト・
下げ振り等で歪を修正しながら本締め、溶接また
はリベツト打ちしていた。
Conventional technology In the past, for example, as shown in Figure 9, the method of constructing a steel frame was to use a steel column that was processed in a factory with several layers as one bar, and then used a construction machine such as a tower crane at the construction site. At the same time, horizontal structural members such as steel beams are stretched over this, and each joint is tightened to 1/2 of the final tightening bolt.
Temporarily tighten 5 to 1/3 bolts, then brace the steel frame at key points with wire and install the transit.
Welding or riveting was performed while correcting distortion using plumb bobbing and other means.

そして、上記鉄骨柱の建込みに際しては、各接
合部の位置に誘導作業員が居て、建方機械のオペ
レーターに手・笛・旗等で合図をしたり、トラン
シーバー等の無線機を用いて誘導していた。
When erecting the above-mentioned steel columns, guidance workers are placed at each joint to give signals to the operator of the erecting machinery with hands, whistles, flags, etc., and use radio equipment such as walkie-talkies. It was guiding me.

発明が解決しようとする問題点 しかしながら、上記現場作業員の手・笛・旗・
無線機等による誘導は、特に微妙な誘導が困難で
相当の熟練を要するばかりでなく、誘導に手間取
つて時間がかかつたり危険を伴ない、特に風が強
いと建込作業が出来なかつた。
Problems to be solved by the invention However, the above-mentioned field workers' hands, whistles, flags,
Guidance using radio equipment, etc. is not only difficult, especially in delicate guidance, and requires a great deal of skill, but it is also time-consuming and dangerous, and construction work is impossible especially when the wind is strong. .

また、上記従来の建方方法は、一旦仮締めして
から歪直し作業を行なつていたため、建方完了ま
でに多くの手間と時間を要し、作業能率が悪くて
建設費が高価になり工期が長くなる等の問題点が
あつた。
In addition, in the conventional construction method mentioned above, the distortion is corrected after temporary tightening, which requires a lot of effort and time to complete the construction, resulting in poor work efficiency and high construction costs. There were problems such as a long construction period.

本発明は、上記従来の建方方法の問題点を解決
するためになされたもので、その目的とするとこ
ろは、鉄骨柱等の構築材の建込状態を建方機械の
オペレーターが適確に把握して遠隔操作により所
定建込位置に迅速かつ正確に誘導し、その構築材
の建方位置や姿勢を保つことにより仮締め及び歪
直し作業を省略して、直接本締めを行ない、誘導
作業員の負担と作業工程を軽減して建設費を大幅
に低減せしめ、建方能率を飛躍的に向上せしめる
ことが出来る構築材の建方装置を提供することに
ある。
The present invention was made in order to solve the problems of the conventional erection method, and its purpose is to enable the operator of the erection machine to accurately check the erection condition of construction materials such as steel columns. By grasping the construction materials and quickly and accurately guiding them to the predetermined erection position by remote control, and maintaining the erection position and posture of the construction materials, temporary tightening and straightening work can be omitted, and final tightening can be performed directly, leading to guidance work. To provide a device for erecting construction materials that can significantly reduce construction costs by reducing the burden on personnel and work processes, and dramatically improve erecting efficiency.

問題点を解決するための手段 本発明の構築材の建方装置は、既設の構築材に
取付けられる発光部と、タワークレーン等の建方
機械により吊込まれる別の構築材に取付けられ上
記発光部からのレーザー光やLED光等の基準光
線を受光する受光部と、該受光部からの受光信号
を上記建方機械のオペレーターに表示する建方精
度読取器から構成されていることを特徴とするも
のであり、上記発光部が、基準光線を発光する発
光部本体と、該発光部本体を支持し構築材に着脱
自在に取付ける手段と、該発光部本体を所定角度
に維持する手段から構成され、また、上記受光部
が、受光ターゲツトを有する受光部本体と、該受
光部本体を支持し構築材に着脱自在に取付ける手
段から構成され、さらに、上記建方精度読取器
が、基準光線の受光スポツトを映し出すスクリー
ンと、該スクリーンに描かれたX,Y方向の照準
線と、該照準線の交点の照準点から構成されてい
ることを特徴とするものである。
Means for Solving the Problems The construction material erecting device of the present invention has a light emitting section attached to an existing construction material and a light emitting section attached to another construction material suspended by a construction machine such as a tower crane. The method is characterized by comprising a light receiving section that receives a reference beam such as a laser beam or an LED light from the section, and an erection accuracy reader that displays the received light signal from the light receiving section to the operator of the erection machine. The light emitting section is composed of a light emitting section main body that emits a reference beam, means for supporting the light emitting section main body and detachably attaching it to the construction material, and means for maintaining the light emitting section main body at a predetermined angle. Further, the light receiving section is composed of a light receiving section main body having a light receiving target, and a means for supporting the light receiving section main body and detachably attaching it to the construction material, and further, the above-mentioned construction accuracy reader is configured to detect the reference beam. It is characterized by comprising a screen that projects a light-receiving spot, a sight line drawn on the screen in the X and Y directions, and a sight point at the intersection of the sight lines.

実施例 以下、本発明装置の一実施例について図面を参
照しながら説明する。
Embodiment Hereinafter, an embodiment of the apparatus of the present invention will be described with reference to the drawings.

第1図において、1は基礎または既設の下層鉄
骨柱の頭部であつて、その上に接続される別の鉄
骨柱2がタワークレーン、トラツククレーン等の
建込機械(図示せず)により吊込まれている。
In Figure 1, 1 is the head of a foundation or an existing lower steel column, and another steel column 2 connected to it is lifted by construction machinery (not shown) such as a tower crane or a truck crane. It's included.

上記鉄骨柱1の頭部の一側面には、レーザー発
光源またはLED発光素子等の発光部3が取付け
られている。
A light emitting unit 3 such as a laser light source or an LED light emitting element is attached to one side of the head of the steel column 1.

該発光部3は、第2図に示すように、上記鉄骨
柱1に着脱自在に付着することが出来るマグネツ
トブロツク3aと、該マグネツトブロツク3aに
突設された取付杆3bと、該取付杆3bに摺動可
能に取付けられた支持本体3cと、該支持本体3
cに枢着されたユニバーサルジヨイント3dと、
該ユニバーサルジヨイント3dに枢着された発光
部本体3eと、該発光部本体3eの下端部に取付
けられた重錘3f等により構成されている。
As shown in FIG. 2, the light emitting section 3 includes a magnetic block 3a that can be detachably attached to the steel column 1, a mounting rod 3b protruding from the magnetic block 3a, and a mounting rod 3b. A support body 3c slidably attached to the rod 3b, and the support body 3
a universal joint 3d pivotally connected to c;
It is composed of a light emitting section main body 3e pivotally attached to the universal joint 3d, a weight 3f attached to the lower end of the light emitting section main body 3e, etc.

上記マグネツトブロツク3aは、これに付設し
たレバーを操作することにより容易に鉄骨柱1か
ら取外したり付着させたりすることができる。ま
た、支持本体3cを取付杆3bに沿つて調節移動
させ、該取付棒3bに刻設した目盛に合わせて支
持本体3eを所定位置にセツトすることが出来
る。さらに、上記発光部本体3eは、ユニバーサ
ルジヨイント3dと重錘3fにより常に鉛直姿勢
を保つことが出来るようになつており、該発光部
本体3eからのレーザー光等の基準光線Lが鉛直
方向に正確に発射される。
The magnetic block 3a can be easily removed from or attached to the steel column 1 by operating a lever attached to it. Further, the support body 3c can be adjusted and moved along the mounting rod 3b, and the support body 3e can be set at a predetermined position in accordance with the scale engraved on the attachment rod 3b. Furthermore, the light emitting unit main body 3e can always maintain a vertical posture due to the universal joint 3d and the weight 3f, so that the reference light beam L such as a laser beam from the light emitting unit main body 3e is directed in the vertical direction. fired accurately.

一方、上記鉄骨柱2の頭部の一側面には、
CCDカメラ等の受光部4が取付けられている。
On the other hand, on one side of the head of the steel column 2,
A light receiving section 4 such as a CCD camera is attached.

該受光部4は、第3図に示すように、上記鉄骨
柱2に着脱自在に付着することが出来るマグネツ
トブロツク4aと、該マグネツトブロツク4aに
突設された取付杆4bと該取付杆4bに摺動可能
に取付けられた受光部本体4cから構成されてお
り、該受光部本体4cには受光ターゲツト4dが
設けられている。上記マグネツトブロツク4a
も、これに付設したレバーを操作することによ
り、鉄骨柱2に着脱することが出来、また、受光
部本体4cを取付杆4bに沿つて調節移動させる
ことが出来るようになつている。
As shown in FIG. 3, the light receiving section 4 includes a magnetic block 4a that can be detachably attached to the steel column 2, a mounting rod 4b protruding from the magnetic block 4a, and a mounting rod 4b. The light receiving section main body 4c is slidably attached to the light receiving section 4b, and a light receiving target 4d is provided on the light receiving section main body 4c. The above magnetic block 4a
By operating a lever attached to this, it can be attached to and removed from the steel column 2, and the light receiving section main body 4c can be adjusted and moved along the mounting rod 4b.

上記受光部本体4cは、ケーブル5を通じて建
方精度読取器6に接続されている。該建方精度読
取器6は、第4図に示すように、そのスクリーン
にX方向、Y方向の照準線6a,6bと、その交
点である照準点6cと、これを中心とする同心円
状の偏位環線6dが描かれていて、上記受光部4
の受光ターゲツト4dで受光した基準光線Lのス
ポツトSの位置が表示されるようになつている。
The light receiving section main body 4c is connected to a construction accuracy reader 6 through a cable 5. As shown in FIG. 4, the construction accuracy reader 6 has sight lines 6a and 6b in the X direction and Y direction, a sight point 6c which is the intersection of the sight lines 6a and 6b, and a concentric circle centered on the sight lines 6a and 6b, as shown in FIG. A deviation ring line 6d is drawn, and the light receiving section 4
The position of the spot S of the reference light beam L received by the light receiving target 4d is displayed.

上記建方精度読取器6は建包機械のオペレータ
ー室に配置され、オペレーターがこれを直接見
て、鉄骨柱2の位置を常に正確に確認することが
できるようになつている。尚、上記建方精度読取
器6と同様の建方精度読取器6′が接続位置にも
配置されており、接続作業員が鉄骨柱2の鉛直度
を確認できるようになつている。
The erection accuracy reader 6 is placed in the operator's room of the construction machine, so that the operator can directly view it and always accurately confirm the position of the steel column 2. A construction accuracy reader 6' similar to the construction accuracy reader 6 described above is also placed at the connection position so that the connection worker can confirm the verticality of the steel column 2.

次に、上記装置による鉄骨建方作業について説
明する。
Next, steel frame erection work using the above device will be explained.

まず、鉄骨柱1および2の頭部に、それぞれ発
光部3および受光部4をセツトする。この際、発
光部3の基準光線Lの発射位置と発光部4の受光
ターゲツト4dの中心位置を接続すべき両鉄骨柱
1,2の基準面から同じ距離にあるように発光部
本体3eと受光部本体4cの位置を調整してお
く。
First, the light emitting section 3 and the light receiving section 4 are set on the heads of the steel columns 1 and 2, respectively. At this time, the emission position of the reference beam L of the light emitting part 3 and the center position of the light receiving target 4d of the light emitting part 4 are at the same distance from the reference plane of both the steel columns 1 and 2 to be connected. Adjust the position of the main body 4c.

上記準備作業が完了したら、鉄骨柱2の上端部
に吊りワイヤー7を掛けてタワークレーン等の建
方機械により吊り込む。この場合、該鉄骨柱2は
出来るだけ鉛直状態を保つように吊設するのが好
ましい。
When the above preparatory work is completed, a hanging wire 7 is hung on the upper end of the steel column 2 and the column is suspended by a construction machine such as a tower crane. In this case, it is preferable that the steel column 2 is suspended so as to maintain a vertical state as much as possible.

この状態で、接続すべき鉄骨柱1のほぼ真上ま
で移動させる。尚、発光部3からの基準光線Lを
受光部4の受光ターゲツト4dが受光するまでの
大まかな誘導は、従来通りトランシーバー等を使
つて誘導員の合図にしたがつて行なつても良い。
In this state, it is moved to almost directly above the steel column 1 to be connected. Incidentally, rough guidance until the reference light beam L from the light emitting section 3 is received by the light receiving target 4d of the light receiving section 4 may be performed as usual using a transceiver or the like and following a signal from a guide.

基準光線Lが受光部4に受光されると、その受
光信号がケーブル5を通じて建方精度読取器6に
映し出される。建方精度読取器6は、建方機械の
オペレーター室に配置してあるので、オペレータ
ーは建方精度読取器6に映し出された基準光線L
の受光スポツトSが建方精度読取器6の視界から
外れないように鉄骨柱2の吊込位置を調整・保持
しながら徐々に降し、鉄骨柱1上に建込む。
When the reference light beam L is received by the light receiving section 4, the received light signal is reflected on the construction accuracy reader 6 through the cable 5. The construction accuracy reader 6 is located in the operator's room of the construction machine, so the operator can read the reference light beam L reflected on the construction accuracy reader 6.
The steel column 2 is gradually lowered and erected onto the steel column 1 while adjusting and maintaining the hanging position so that the light receiving spot S does not come out of the field of view of the erection accuracy reader 6.

この場合、上記受光スポツトSが建方精度読取
器6の視界から外れたら、警報ブザーが鳴るよう
にしてもよい。
In this case, an alarm buzzer may sound when the light receiving spot S goes out of the field of view of the construction accuracy reader 6.

尚、2つの鉄骨柱1,2の間に近接センサーを
取付けておけば、オペレーターがこの情況も正確
に把握しながら降下させることが出来る。
If a proximity sensor is installed between the two steel columns 1 and 2, the operator can accurately grasp this situation while descending.

鉄骨柱2が鉄骨柱1上に建込まれると、直ちに
接続作業に入る。
When the steel column 2 is erected on the steel column 1, connection work begins immediately.

接続作業に於いては、まず、仮締状態にボルト
を締めてから、建方精度読取器6の照準位置6c
に基準光線Lの受光スポツトSを一致せしめると
共に、その状態を維持して鉄骨柱2を鉛直状態に
保ちながらボルトを本締めする。
In the connection work, first tighten the bolts temporarily, and then check the aiming position 6c of the construction accuracy reader 6.
The light receiving spot S of the reference light beam L is made to coincide with the reference beam L, and the bolts are fully tightened while maintaining this state and keeping the steel column 2 in a vertical state.

上記吊込情況は接続位置にいる作業員にも建方
精度読取器6′を通じて看取される。
The above-mentioned lifting situation can also be observed by the worker at the connection position through the construction accuracy reader 6'.

鉄骨柱2の接続が終了したら、発光部3および
受光部4を取外して、次の建方作業に移る。
When the connection of the steel column 2 is completed, the light emitting part 3 and the light receiving part 4 are removed and the next erection work is started.

尚、これらの発光部3および受光部4を複数組
揃えておき、1組の発光部3および受光部4の取
外し取付けの準備作業中に、別組の発光部3およ
び受光部4により建方作業をすることが出来て、
建方全体の作業能率を向上せしめることが出来
る。
It should be noted that a plurality of sets of these light emitting parts 3 and light receiving parts 4 are prepared, and during preparation work for removing and installing one set of light emitting parts 3 and light receiving parts 4, another set of light emitting parts 3 and light receiving parts 4 is assembled. be able to work,
It is possible to improve the work efficiency of the entire construction work.

第5図に示すように、鉄骨柱がH型鋼のような
フランジ部を有する鉄骨の場合には、上記マグネ
ツトブロツクにより鉄骨柱に取付ける代りに、そ
のフランジ部にネジ止め等で挟着するようにして
もよい。また、第6図に示すように、鉄骨柱が梁
接続部や梁の一部等を一体的に設けた場合には、
上記発光部3および受光部4を鉄骨柱の角部や接
続部に取付けて、レーザー光等の基準光線Lの通
過の邪魔にならない工夫を要する。
As shown in Figure 5, if the steel frame is a steel frame with a flange, such as an H-beam, instead of being attached to the steel column using the magnetic block described above, it may be clamped to the flange using screws, etc. You can also do this. In addition, as shown in Figure 6, when a steel frame column has a beam connection part or a part of the beam, etc.,
The light emitting section 3 and the light receiving section 4 need to be attached to corners or connecting parts of a steel column so that they do not interfere with the passage of the reference light beam L such as a laser beam.

また、上記発光部3のユニバーサルジヨイント
3dと重錘3fとの組合わせによるものに限ら
ず、基準光線Lの鉛直度を自動的に保つ手段であ
ればいずれでもよい。
Further, the method is not limited to the combination of the universal joint 3d of the light emitting section 3 and the weight 3f, but any means that automatically maintains the verticality of the reference light beam L may be used.

第7図はカーテンウオール取付け作業に応用し
た別の実施例を示すものであつて、既設のカーテ
ンウオール8または建築物躯体に発光部3を取付
け、建込むべきカーテンウオール9に上記受光部
4を取付け、上記実施例と同様の方法によりカー
テンウオールを正確な位置に正確な姿勢で取り付
けることが出来る。
FIG. 7 shows another embodiment applied to curtain wall installation work, in which a light emitting section 3 is attached to an existing curtain wall 8 or a building frame, and the light receiving section 4 is attached to a curtain wall 9 to be built. Attachment: The curtain wall can be attached at a precise position and in a precise posture by the same method as in the above embodiment.

第8図は鉄骨製タワー構築の実施例を示すもの
であつて、既設のタワー鉄骨材10に発光部3を
取付け、建込むべき鉄骨材11に上記受光部4を
取付けて、上記鉄骨建築物の実施例と同様の方法
により鉄骨材の建て方を行う。
FIG. 8 shows an example of constructing a steel frame tower, in which the light emitting part 3 is attached to the existing tower steel frame 10, the light receiving part 4 is attached to the steel frame 11 to be built, and the above steel frame building is constructed. The steel frame is erected using the same method as in the example.

発明の効果 (1) 鉄骨の建込オペレーター自身の遠隔操作によ
り、建方が迅速かつ正確にできるだけでなく、
建込鉄骨の鉛直精度を正確に維持しながら直ち
に本締めして立柱することが出来る。
Effects of the invention (1) Not only can erection be done quickly and accurately by the remote control of the steel erection operator himself, but also
While accurately maintaining the vertical accuracy of the erected steel frame, it can be fully tightened and erected immediately.

(2) 作業が安全で且つ省力化が図れる。(2) Work is safe and labor-saving.

(3) 多少の風速中でも安全に建方が出来、工期を
短縮することが出来る。
(3) Construction can be carried out safely even in moderate wind speeds, and the construction period can be shortened.

(4) カーテンウオール取付け等の外壁面の面出し
や、鉄骨製タワーの組立等にも適用できる。
(4) It can also be applied to surfacing external walls such as installing curtain walls, and assembling steel towers.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明装置による建方作業状態を示す
斜視図、第2図は発光部の拡大斜視図、第3図は
受光部の拡大斜視図、第4図は建方精度読取器の
説明図、第5図および第6図は別の実施例の要部
斜視図、第7図はカーテンウオール取付け作業に
応用した説明図、第8図は鉄骨製タワーの組立に
応用した説明図、第9図は従来の建方作業の説明
図である。 1,2……鉄骨柱、3……発光部、3a……マ
グネツトブロツク、3b……取付杆、3c……支
持本体、3d……ユニバーサルジヨイント、3e
……発光部本体、3f……重錘、4……受光部、
4a……マグネツトブロツク、4b……取付杆、
4c……受光部本体、4d……受光ターゲツト、
5,5′……ケーブル、6,6′……建方精度読取
器、6a,6b……照準線、6c……照準位置、
6d……偏位環線、7……吊りワイヤー、8,9
……カーテンウオール、10,11……鉄骨材、
L……基準光線、S……受光スポツト。
Fig. 1 is a perspective view showing the construction work performed by the device of the present invention, Fig. 2 is an enlarged perspective view of the light emitting section, Fig. 3 is an enlarged perspective view of the light receiving section, and Fig. 4 is an explanation of the erection accuracy reader. Figures 5 and 6 are perspective views of main parts of another embodiment, Figure 7 is an explanatory diagram applied to curtain wall installation work, Figure 8 is an explanatory diagram applied to the assembly of a steel frame tower, Figure 9 is an explanatory diagram of conventional erection work. 1, 2... Steel column, 3... Light emitting part, 3a... Magnetic block, 3b... Mounting rod, 3c... Support body, 3d... Universal joint, 3e
... Light emitting part main body, 3f ... Weight, 4 ... Light receiving part,
4a...Magnetic block, 4b...Mounting rod,
4c... Light receiving unit main body, 4d... Light receiving target,
5, 5'... Cable, 6, 6'... Construction accuracy reader, 6a, 6b... Sighting line, 6c... Sighting position,
6d...Deflection ring wire, 7...Hanging wire, 8,9
...Curtain wall, 10,11...Steel frame material,
L...Reference light beam, S...Light receiving spot.

Claims (1)

【特許請求の範囲】 1 既設の構築材に取付けられる発光部と、タワ
ークレーン等の建方機械により吊込まれる別の構
築材に取付けられ上記発光部からのレーザー光や
LED光等の基準光線を受光する受光部と、該受
光部からの受光信号を上記建方機械のオペレータ
ーに表示する建方精度読取器から構成されている
ことを特徴とする構築材の建方装置。 2 上記発光部が、基準光線を発光する発光部本
体と、該発光部本体を支持し構築材に着脱自在に
取付ける手段と、該発光部本体を所定角度に維持
する手段から構成されていることを特徴とする前
記特許請求の範囲第1項に記載の構築材の建方装
置。 3 上記受光部が、受光ターゲツトを有する受光
部本体と、該受光部本体を支持し構築材に着脱自
在に取付ける手段から構成されていることを特徴
とする前記特許請求の範囲第1項に記載の構築材
の建方装置。 4 上記建方精度読取器が、基準光線の受光スポ
ツトを映し出すスクリーンと、該スクリーンに描
かれたX,Y方向の照準線と、該照準線の交点の
照準点から構成されていることを特徴とする前記
特許請求の範囲第1項に記載の構築材の建方装
置。
[Scope of Claims] 1. A light-emitting section attached to an existing construction material, and a laser light emitted from the light-emitting section attached to another construction material suspended by a construction machine such as a tower crane.
Erecting construction materials characterized by comprising a light receiving section that receives a reference light beam such as an LED light, and a construction accuracy reader that displays the received light signal from the light receiving section to the operator of the erection machine. Device. 2. The light emitting section is composed of a light emitting section main body that emits a reference beam, means for supporting the light emitting section main body and detachably attaching it to the construction material, and means for maintaining the light emitting section main body at a predetermined angle. An apparatus for erecting construction materials according to claim 1, characterized in that: 3. According to claim 1, the light receiving section is comprised of a light receiving section main body having a light receiving target, and means for supporting the light receiving section main body and detachably attaching it to a construction material. Construction equipment for construction materials. 4. The above-mentioned construction accuracy reader is characterized by comprising a screen that projects the light receiving spot of the reference beam, a sight line drawn on the screen in the X and Y directions, and a sight point at the intersection of the sight lines. An apparatus for erecting construction materials according to claim 1.
JP15806386A 1986-07-07 1986-07-07 Apparatus for building construction material Granted JPS6314960A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15806386A JPS6314960A (en) 1986-07-07 1986-07-07 Apparatus for building construction material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15806386A JPS6314960A (en) 1986-07-07 1986-07-07 Apparatus for building construction material

Publications (2)

Publication Number Publication Date
JPS6314960A JPS6314960A (en) 1988-01-22
JPH0543028B2 true JPH0543028B2 (en) 1993-06-30

Family

ID=15663487

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15806386A Granted JPS6314960A (en) 1986-07-07 1986-07-07 Apparatus for building construction material

Country Status (1)

Country Link
JP (1) JPS6314960A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2559257B2 (en) * 1988-06-29 1996-12-04 東急建設株式会社 Construction method of construction materials
JPH0826666B2 (en) * 1989-06-02 1996-03-13 学校法人早稲田大学 Column steel verticality measuring device
JP5724235B2 (en) * 2010-07-23 2015-05-27 株式会社大林組 Connection method and structure

Also Published As

Publication number Publication date
JPS6314960A (en) 1988-01-22

Similar Documents

Publication Publication Date Title
JP3015910B2 (en) Adjustment method for steel columns
JPH0543028B2 (en)
JP2559257B2 (en) Construction method of construction materials
JPH0543027B2 (en)
JP2699114B2 (en) Verticality measurement system for construction materials
JPH09203041A (en) Structural center column erection method and guide pipe used therefor
JPH0543029B2 (en)
JPH08312148A (en) Erection device for building material
JP2604206B2 (en) Construction material construction equipment
JPH08120941A (en) Erection method for construction material and its device
JPH09242339A (en) Vertical positioning method of building main post
JP3235718B2 (en) Exterior wall panel mounting method
JP2745004B2 (en) Steel construction method
JPH066861B2 (en) Construction method of Kumashindai
JPH06147896A (en) Erection measuring system for steel column
JP3053296B2 (en) Pillar hanging jig
CN117127814B (en) Cloud building factory manipulator for concrete leveling construction and construction method
JP2000045297A (en) Construction method of turbine frame
CN110835955B (en) Installation method for butt joint of steel beams at top of umbrella-shaped steel pipe column
JP2912585B2 (en) Adjustment jig for column installation, lifting jig and drive jig for installation
WO2008135635A1 (en) Method and apparatus for raising a steel frame
JP4250073B2 (en) Level adjustment jig
JPS62244971A (en) Reinforcement building apparatus and system
JPH10299019A (en) Joining method for permanent sub-structural column and main steel in inverted construction method
JP3152800B2 (en) H-section framing method, framing gantry used therefor, and fall prevention jig

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees