JPH05346068A - Construction material conveyor device - Google Patents

Construction material conveyor device

Info

Publication number
JPH05346068A
JPH05346068A JP15701392A JP15701392A JPH05346068A JP H05346068 A JPH05346068 A JP H05346068A JP 15701392 A JP15701392 A JP 15701392A JP 15701392 A JP15701392 A JP 15701392A JP H05346068 A JPH05346068 A JP H05346068A
Authority
JP
Japan
Prior art keywords
floor
carriage
hoistway
trolley
construction material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15701392A
Other languages
Japanese (ja)
Inventor
Makoto Ichikawa
誠 市川
Tadayoshi Honda
忠義 本田
Tadashi Okano
岡野  正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP15701392A priority Critical patent/JPH05346068A/en
Publication of JPH05346068A publication Critical patent/JPH05346068A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

PURPOSE:To cope with the mass conveyance of material required at the time of constructing a high-rise building by providing a hoistway having two systems, that is, an ascent-exclusive system and a descent-exclusive system, with plural elevating units provided vertically in line therein while the self-weight of each unit is supported at each floor. CONSTITUTION:A hoisting 2 with two systems, that is, an ascent-exclusive system and a descent-exclusive system, is hangingly provided at the flat area of temporary lifting equipment similar to an existing high-speed lift. In this ascent-exclusive or descent-exclusive hoisting 2, plural trucks 20 loaded with material move to the specified floors. The truck 20 reaching the floor is placed in the state of travelable onto the floor by the operation of a draw bridge disposed at the hoisting entrance of the floor. The truck 20 is then towed by a tractor 60 installed at the floor and conveyed into the specified place. Material elevating action from the carry-in floor to the designated floor can be thereby performed in a short time.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は建設用資材搬送システム
に係わり、特に、多数階のフロアを有しかつ各フロア
(床版)の構築までが完了された超高層建築物等に適用
して好適な建設用資材搬送装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction material conveying system, and in particular, it is applied to a super high-rise building having a large number of floors and construction of each floor (slab) is completed. The present invention relates to a suitable construction material conveying device.

【0002】[0002]

【従来の技術】従来、各フロアの構築までをほぼ完了し
た後、最下階から指定フロアまで内装資材を搬送する手
段としては、建築内部に設置される既設高速リフト、あ
るいは本設のエレベータを早期に使用する方法があっ
た。既設高速リフトは、一基に1系統の昇降路を有し、
その昇降路に一台の荷台が昇降する構造とされている。
前記既設高速リフトを超高層ビル建築に適用する場合に
は、その昇降速度の制約から、多量の内装資材を搬送す
るには非常に時間がかかるものとなる。
2. Description of the Related Art Conventionally, an existing high-speed lift installed inside a building or a permanently installed elevator has been used as a means for transporting interior materials from the lowest floor to a designated floor after almost completing the construction of each floor. There was a method to use early. The existing high speed lift has one system of hoistway,
It has a structure in which one loading platform moves up and down the hoistway.
When the existing high-speed lift is applied to a skyscraper building, it takes a very long time to transport a large amount of interior materials due to the restriction of the lifting speed.

【0003】[0003]

【発明が解決しようとする課題】ところが、前記既設高
速リフトを多量の資材を搬送するために複数基設置する
ことは、建設現場の設置面積の制限等から難しい。ここ
で、昇降路に、複数の荷台を搭載して内装資材の搬送能
力を向上させる方法が考えられるが、現在まで、一基の
高速リフトに複数台の台車を搭載するシステムは実現化
されていなかった。
However, it is difficult to install a plurality of existing high-speed lifts in order to convey a large amount of materials, because of a limited installation area at a construction site. Here, it is conceivable to mount multiple cargo beds on the hoistway to improve the transportation capacity of interior materials, but to date, a system that mounts multiple carriages on one high-speed lift has been realized. There wasn't.

【0004】本発明は上記の事情に鑑みてなされたもの
で、従来の高速リフトと同様の仮設揚重設備の平面積を
保ながら、複数台の台車を搭載することで超高層建築物
構築の際に必要とされる大量の資材搬送に対応でき、ま
た複数台の台車の安全自動運転が可能とされた建設用資
材搬送装置を提供することを目的とするものである。
The present invention has been made in view of the above circumstances, and it is possible to construct a super high-rise building by mounting a plurality of trolleys while maintaining the flat area of the temporary lifting equipment similar to the conventional high speed lift. It is an object of the present invention to provide a construction material transporting device that can handle a large amount of material transport required at that time, and that can safely and automatically drive a plurality of trucks.

【0005】[0005]

【課題を解決するための手段】本発明の請求項1記載の
建設用資材搬送装置は、超高層建築物を構築する際に、
該建築物を構築するのに必要な資材等を、既に形成され
たフロア上の所定場所に搬送するための建設用資材搬送
装置であって、登り専用と下り専用の2系統を有し、複
数の昇降ユニットが各フロアで自重が支持されながら鉛
直方向に連設されてなる昇降路と、昇降路内を昇降し、
資材を搭載して所定のフロアまで搬送する台車と、各フ
ロアの昇降路入口に配設され、昇降路入口に移動してき
た台車をフロア上へ走行可能とさせる台車移行機構と、
台車及び台車移行機構のそれぞれに対して所定の動作信
号を送出する命令手段と、命令手段に所定の動作信号を
入力する入力手段と、昇降路内の台車および各フロア上
の台車の運行状況さらには台車移行部の動作状況を表示
する表示手段とを備えた運転管理装置とを有してなるも
のである。
A construction material conveying apparatus according to claim 1 of the present invention is used for constructing a super high-rise building.
A construction material transporting device for transporting materials and the like necessary for constructing the building to a predetermined place on an already formed floor, which has two systems dedicated to climbing and descending, The hoisting units are vertically connected while supporting their own weight on each floor, and hoisting inside the hoistway,
A trolley for loading materials and transporting them to a predetermined floor, and a trolley transfer mechanism that is arranged at the hoistway entrance of each floor and allows the dolly that has moved to the hoistway entrance to travel on the floor,
Command means for sending a predetermined operation signal to each of the carriage and the carriage transfer mechanism, an input means for inputting a predetermined operation signal to the command means, an operation status of the carriage in the hoistway and the carriage on each floor, and And an operation management device having a display unit for displaying the operation status of the trolley transfer unit.

【0006】請求項2記載の建設資材用搬送装置は、請
求項1記載において、台車及び台車移行機構のそれぞれ
に対して所定の動作信号を送出する命令手段と、命令手
段に所定の動作信号を入力する入力手段と、昇降路内の
台車および各フロア上の台車の運行状況さらには前記台
車移行部の動作状況を表示する表示手段とを備えてなる
ものである。
According to a second aspect of the present invention, there is provided a construction material transporting apparatus according to the first aspect, wherein a command means for sending a predetermined operation signal to each of the carriage and the carriage shifting mechanism and a predetermined operation signal for the command means. It is provided with an input means for inputting and a display means for displaying the operation status of the carriage in the hoistway and the carriage on each floor and the operation status of the carriage transition section.

【0007】請求項3記載の建設資材用搬送装置は、請
求項1記載において、昇降ユニットは一対のレール軌道
が離間配置されて構成され、それらレール軌道が鉛直方
向に連設されてなる昇降路内を台車が昇降し、台車に
は、昇降路のレール軌道に連結されることにより昇降移
動が可能となる昇降機構と、昇降機構をレール軌道に着
脱自在に連結させる連結機構とが具備され、台車移行機
構は、その動作により台車を各フロアから昇降路に乗り
移り、あるいはその逆の方向に引き出すことを可能とさ
せるはね橋により構成されていることを特徴とするもの
である。
A construction material conveying apparatus according to a third aspect of the present invention is the construction material conveying apparatus according to the first aspect, wherein the elevating unit comprises a pair of rail tracks spaced apart from each other, and the rail tracks are vertically connected to each other. The dolly moves up and down in the dolly, and the dolly is equipped with an elevating mechanism that can be moved up and down by being connected to a rail track of a hoistway, and a connecting mechanism that detachably connects the elevating mechanism to the rail track. The trolley transfer mechanism is characterized by being constituted by a flybridge that allows the trolley to be transferred from each floor to the hoistway or pulled out in the opposite direction by its operation.

【0008】請求項4記載の建設資材用搬送装置は、請
求項1記載において、昇降ユニットが、前後面を登り専
用路及び下り専用路とし、登り専用路から下り専用路に
わたって上下方向に巻装された駆動チェーンと、登り専
用路及び下り専用路のそれぞれの上下方向に配設された
ガイドレール若しくはガイドローラとを具備したマスト
ユニットにより構成され、台車には、ガイドレール若し
くはガイドローラと摺動自在に係合して台車を前記マス
トユニットに沿わせるガイドローラー若しくはガイドレ
ールと、前記駆動チェーンに着脱自在に嵌合する嵌合部
と、台車がフロア側へ移行する際に台車移行機構上を転
動する台車水平移行用ローラーとが具備され、台車移行
機構が、水平移動により各フロアの昇降路内に引き出し
若しくは引き込まれ、引き出し動作により昇降路を移動
してきた台車の前記ガイドローラー及び前記台車移行用
ローラーを転動させて台車をフロア上に走行可能とさせ
る移行フレームにより構成されていることを特徴とする
ものである。
According to a fourth aspect of the present invention, there is provided a construction material transporting apparatus as set forth in the first aspect, in which the elevating unit winds the front and rear surfaces into an exclusive climbing path and an exclusive descending path, and winds vertically from the exclusive climbing path to the exclusive descending path. Drive chain and a guide rail or guide roller vertically arranged on the ascending-only path and the descending-only path, respectively. A guide roller or guide rail that freely engages to move the bogie along the mast unit, a fitting portion that detachably fits to the drive chain, and a bogie transition mechanism when the bogie moves to the floor side. It is equipped with a roller for horizontal movement of the bogie that rolls, and the bogie transition mechanism pulls or pulls it into the hoistway of each floor by horizontal movement. A transfer frame that rolls the guide roller and the trolley transfer roller of the trolley that has moved in the hoistway by the pulling operation to allow the trolley to travel on the floor. ..

【0009】請求項5記載の建設資材用搬送装置は、請
求項1記載において、昇降ユニットは、3基のマストユ
ニットを離間配置し、それらマストユニット間を登り専
用路及び下り専用路とし、各マストユニットに、複数枚
の昇降板が突設された上下方向に回動する駆動ベルトを
配設した構成とされ、台車には、所定の昇降板との係合
により台車の昇降が可能とされる係合板と、係合板の下
面に設けられて台車がフロア側へ移行する際に昇降板上
を転動する台車移行用ローラーとが具備されているとと
もに、係合板には、該係合板と前記昇降板との係合状態
を保持するストッパー機構が設けられており、ストッパ
ー機構が係合状態を解除することにより台車移行機構と
して作用することを特徴とするものである。
A construction material carrying device according to a fifth aspect of the present invention is the construction material conveying device according to the first aspect, wherein the lifting unit has three mast units spaced apart from each other, and the mast units serve as an ascending-only path and a descending-only path. The mast unit has a structure in which a plurality of lift plates are provided so as to project vertically, and a drive belt that rotates in the vertical direction is arranged.The carriage is capable of lifting and lowering by being engaged with a predetermined lift plate. And an engaging plate provided on the lower surface of the engaging plate, which rolls on the elevating plate when the dolly moves to the floor side. A stopper mechanism for holding the engaged state with the elevating plate is provided, and when the stopper mechanism releases the engaged state, it acts as a trolley transfer mechanism.

【0010】[0010]

【作用】本発明の建設用資材搬送装置によれば、従来の
高速リフトと同様の仮設揚重設備の平面積に、登り専用
と下り専用の2系統を有する昇降路が垂設される。この
昇降路の登り専用若しくは下り専用を、資材を搭載した
複数の台車が所定のフロアまで移動していく。
According to the construction material conveying apparatus of the present invention, a hoistway having two systems, one for climbing and the other for descending, is hung vertically on the flat area of the temporary lifting equipment similar to the conventional high speed lift. A plurality of trolleys carrying materials move to a predetermined floor in the ascending or descending of the hoistway.

【0011】そして、台車が所定のフロアまで移動する
と、フロアの昇降路入口に配設された台車移行機構の作
動により、移動してきた台車がフロア上へ走行可能とな
る。そして、台車移行機構によりフロア上へ走行可能と
された台車は、所定のフロアに設置されている牽引車に
より牽引されて、あるいは台車に内蔵の昇降機構により
所定の場所まで搬送される。
When the truck moves to a predetermined floor, the truck moving mechanism arranged at the entrance of the hoistway of the floor allows the truck to move on the floor. Then, the trolley which can be moved to the floor by the trolley transfer mechanism is towed by a towing vehicle installed on a predetermined floor or is transported to a predetermined place by an elevating mechanism built into the trolley.

【0012】したがって、本発明は、搬入階から指定階
(揚重階)までの資材の昇降動作を短時間で行うことが
でき、それにより、超高層建築物を構築する際に必要と
される資材の大量搬送に十分に対応可能となる。また、
前記台車は、昇降路への増設若しくは減少を容易に行う
ことができるので、構築される建築物の規模に見合った
台車の使用台数を設定することができる。
Therefore, according to the present invention, it is possible to raise and lower the material from the loading floor to the designated floor (lifting floor) in a short time, which is required when constructing a super high-rise building. It becomes possible to sufficiently cope with large-scale transportation of materials. Also,
Since the trolleys can be easily added or reduced to the hoistway, the number of trolleys to be used can be set according to the scale of the building to be constructed.

【0013】[0013]

【実施例】以下、本発明の実施例について図面を参照し
て説明する。図1ないし図10は、本発明の請求項1及
び2記載に係る建設用資材搬送装置の第1の実施例を示
したものである。図1において、符号F1,F2,…で
示すものは、建造すべき建築物1(図2)における既に
構築されたフロア(床スラブ)である。
Embodiments of the present invention will be described below with reference to the drawings. 1 to 10 show a first embodiment of a construction material conveying device according to claims 1 and 2 of the present invention. In FIG. 1, reference numerals F1, F2, ... Show floors (floor slabs) already built in the building 1 (FIG. 2) to be built.

【0014】また、符号2は、前記各フロアF1,F
2,…にわたって設置された昇降路である。本実施例の
昇降路2は、登り用と下り用の2系統を有している(図
1は、1系統のみを示したものである。)。そして、昇
降路2は、図2に示すように、2本のレール3、3によ
り構成された一対のレール軌道(昇降ユニット)4、4
が、各フロアF1,F2…に対向配置させた状態で固定
され、これらレール軌道4、4を鉛直方向に複数連続さ
れることにより、建築物1の各フロアF1,F2…を貫
通した状態で配設されている。さらに、各昇降軌道4、
4の昇降路2内には、長手方向に連続してラック5が形
成されている。
Further, reference numeral 2 is each floor F1, F
It is a hoistway installed over 2, ... The hoistway 2 of this embodiment has two systems, one for climbing and one for descending (FIG. 1 shows only one system). The hoistway 2 is, as shown in FIG. 2, a pair of rail tracks (hoisting units) 4 and 4 composed of two rails 3 and 3.
, Are fixed in a state of being arranged to face each floor F1, F2 ... And a plurality of these rail tracks 4 and 4 are continuous in the vertical direction so that each floor F1, F2 ... It is arranged. Furthermore, each lifting track 4,
In the hoistway 2 of 4, racks 5 are formed continuously in the longitudinal direction.

【0015】また、昇降路2全体には、図9に示すよう
に、給電線6(トロリー電線)が配設されている。この
給電線6は、昇降路2内を移動する台車20と電気的に
接続するとともに、台車20に動作信号を送るための信
号線として使用されている。また、レール軌道4、4間
に架設されたフレーム7には、前記給電線6と電気的に
接続する給電バー8、8が昇降路2内に突設されてお
り、これら給電バー8は、昇降路2を移動する台車20
…の集電ブラシ21と常時接触状態となる。
Further, as shown in FIG. 9, a power supply line 6 (trolley wire) is arranged in the entire hoistway 2. The power supply line 6 is electrically connected to the truck 20 moving in the hoistway 2 and is used as a signal line for sending an operation signal to the truck 20. Further, on a frame 7 laid between the rail tracks 4 and 4, feed bars 8 and 8 electrically connected to the feed line 6 are provided to project in the hoistway 2. These feed bars 8 are A dolly 20 moving on the hoistway 2
It is always in contact with the current collecting brush 21.

【0016】そして、図3に示すように、各フロアF
1,F2,…の昇降路入口9には、各フロアの階数を表
示するフロア表示ラベル10…が設置されている。この
フロア表示ラベル10は、後述する台車20のフロア読
取センサー22により読み取り可能とされている。ま
た、昇降路入口9上下部には、はね橋(台車移行機構)
50の付近で台車20が停止する位置を(退避位置)を
示すストライカー11が設けられている。
Then, as shown in FIG. 3, each floor F
At the hoistway entrances 9 of 1, F2, ..., Floor display labels 10 ... Which display the number of floors of each floor are installed. The floor display label 10 can be read by a floor reading sensor 22 of a carriage 20 described later. In addition, at the upper and lower parts of the hoistway entrance 9, a drawbridge (carriage transfer mechanism)
A striker 11 is provided which indicates a position (retracted position) where the carriage 20 stops near 50.

【0017】また、図4および図7において示す台車2
0は、昇降路2の登り用若しくは下り用のそれぞれの系
統に昇降自在に複数台配設され、資材を所定のフロアF
1,F2,…まで搬送するものである。
Further, the carriage 2 shown in FIGS. 4 and 7
A plurality of 0s are arranged in each system for climbing or descending the hoistway 2 so as to be able to move up and down, and materials are provided on a predetermined floor F.
1, F2, ...

【0018】台車20は、台車本体23を昇降路2内で
移動させる昇降機構24、24と、これら昇降機構2
4、24と連設されて昇降機構24、24をレール3、
3のラック5に離脱可能に連結する機構25(以下、連
結機構25と略称する。)と、昇降路2の給電バー8と
接触する集電ブラシ21、フロア読取センサー22、昇
降路2内の障害物を検出する近接センサー26、台車の
傾斜を矯正する台車傾斜計(図示せず)、前記昇降路2
のストライカー11と接触するリミットスイッチ28
と、台車20がはね橋50に接地したことを検出する着
床検出センサー(図示せず)とで概略構成されている。
すなわち、前記台車本体23は、内部に資材が搭載可能
なボックス型形状を有しており、図5に示すように、底
部には台車20が各フロアF1,F2,…で走行可能と
なるキャスター29が設けられている。
The trolley | bogie 20 is the raising / lowering mechanism 24, 24 which moves the trolley | bogie main body 23 in the hoistway 2, and these raising / lowering mechanism 2
4 and 24 are connected to each other, and the lifting mechanisms 24 and 24 are connected to the rails 3,
A mechanism 25 (hereinafter, simply referred to as a coupling mechanism 25) that is detachably coupled to the rack 5 of No. 3, a current collecting brush 21 that contacts the power supply bar 8 of the hoistway 2, a floor reading sensor 22, and a hoistway 2 inside. Proximity sensor 26 for detecting obstacles, truck inclinometer (not shown) for correcting the inclination of the truck, the hoistway 2
Limit switch 28 that comes into contact with the striker 11
And a landing detection sensor (not shown) that detects that the carriage 20 is grounded on the drawbridge 50.
That is, the trolley body 23 has a box shape in which materials can be loaded, and as shown in FIG. 5, the trolley 20 is a caster on the bottom of which can travel on each floor F1, F2, .... 29 are provided.

【0019】また、昇降機構24は、台車底部の昇降路
2のレール軌道4、4と対向する位置に一対設けられて
おり、図6および図7に示すように、ラック5と噛み合
う昇降用ピニオンギア30と、昇降用ピニオンギア30
をギアボックス31を介して所定方向に回転させ、かつ
ブレーキ機構(図示せず)が内蔵されたギアドモーター
(駆動モーター)33と、昇降用ピニオンギア30がラ
ック5と嵌合若しくは離脱するように回動自在に支持す
る支持部34とで構成されている。
A pair of elevating mechanisms 24 are provided at positions facing the rail tracks 4 and 4 of the hoistway 2 at the bottom of the bogie, and as shown in FIGS. 6 and 7, an elevating pinion that meshes with the rack 5. Gear 30 and lifting pinion gear 30
The geared motor (driving motor) 33 having a built-in brake mechanism (not shown) and the pinion gear 30 for lifting and lowering the gear 5 to rotate in a predetermined direction through the gearbox 31 And a supporting portion 34 that rotatably supports it.

【0020】駆動モーター33は、インバータ制御方式
を採用してモーター回転数が制御可能とされており、そ
れにより台車20の移動速度を変化させることができ
る。これにより、台車20の昇降速度は、停止フロアま
での距離により、高速運転、低速運転の自動切り換えが
可能となる。なお、インバーター制御方式を採用せず、
減速比可変式のギアボックス31を使用して減速比の微
調整により台車20の移動速度制御を行うことも可能で
ある。また、この駆動モーター33に内蔵されているブ
レーキ機構は、駆動モーター33とインターロックされ
るようになっている。さらに、昇降用ピニオンギア30
をラック5に押し付ける際の歯の噛み合いは、図7に示
すように、円弧運動しながら噛み合う方式とされてお
り、駆動モーター33のブレーキ機構を解除することに
よって歯先に無理な力がかかることなく容易に噛み合わ
せができる。そして、昇降用ピニオンギア30とラック
5との噛み合わせ後に、ブレーキ機構が投入されるよう
になっている。
The drive motor 33 employs an inverter control system so that the number of rotations of the motor can be controlled, whereby the moving speed of the carriage 20 can be changed. As a result, the vertical speed of the carriage 20 can be automatically switched between high speed operation and low speed operation depending on the distance to the stop floor. In addition, without adopting the inverter control method,
It is also possible to control the moving speed of the carriage 20 by finely adjusting the reduction ratio using the gearbox 31 of the variable reduction ratio type. The brake mechanism built in the drive motor 33 is interlocked with the drive motor 33. Furthermore, the lifting pinion gear 30
As shown in FIG. 7, the teeth are meshed with each other when they are pressed against the rack 5. The teeth are meshed with each other while making an arc motion. When the brake mechanism of the drive motor 33 is released, excessive force is applied to the tooth tips. Can be easily engaged without The brake mechanism is adapted to be engaged after the lifting pinion gear 30 and the rack 5 are engaged with each other.

【0021】押圧機構25は、図7に示すように、台車
20の底部に固定された支持部材35と、支持部材35
にピン接合された電動ジャッキ36とで構成され、電動
ジャッキ36のシリンダアーム36aが前記支持部35
とピン接合されて連結している。そして、シリンダーア
ーム36aが伸長することにより、昇降用ピニオンギア
30がラック5に押圧され、昇降機構24が確実に昇降
路2に連結する構造になっている。集電ブラシ21は、
図2に示すように、昇降路2の給電バー8と対峙する台
車20の側部に設けられ、給電線8から供給された電力
が常時駆動モーター33及び電動ジャッキ36に供給さ
れるようになっている。
As shown in FIG. 7, the pressing mechanism 25 includes a support member 35 fixed to the bottom of the carriage 20 and a support member 35.
And a cylinder arm 36a of the electric jack 36 is connected to the supporting portion 35.
It is connected by being pin-joined with. When the cylinder arm 36a extends, the lifting pinion gear 30 is pressed against the rack 5, and the lifting mechanism 24 is reliably connected to the lifting path 2. The current collecting brush 21 is
As shown in FIG. 2, it is provided on the side portion of the trolley 20 facing the power feeding bar 8 of the hoistway 2, and the power supplied from the power feeding line 8 is constantly supplied to the drive motor 33 and the electric jack 36. ing.

【0022】フロア読取センサー22は、図4に示すよ
うに、各フロアF1,F2,…の昇降路入口9に設けら
れたフロア表示ラベル10を望むことが可能な台車位置
に設けられている。そして、フロア読取センサー22は
自身の行き先の指定階数を記憶しており、各フロアF
1,F2,…のフロア表示ラベルを光学手段等で読み取
りながら、記憶したフロア階数と比較検知する。そし
て、フロア階数が一致した場合には、台車20の駆動モ
ーター33に停止信号が送られるようになっている。
As shown in FIG. 4, the floor reading sensor 22 is provided at a carriage position where the floor display label 10 provided at the hoistway entrance 9 of each floor F1, F2, ... Can be desired. Then, the floor reading sensor 22 stores the designated number of floors of its own destination, and each floor F
The floor display labels of 1, F2, ... Are read by optical means or the like and compared with the stored floor number for detection. When the number of floors is the same, a stop signal is sent to the drive motor 33 of the truck 20.

【0023】近接センサー26は、例えば超音波センサ
ー等からなるもので、図4に示すように、台車20の上
部(天板)及び下部(底板)に設置されている。そし
て、台車20が上昇する際には上部の近接センサー26
が常時作動し、下降する際には下部の近接センサー26
(図5参照)が常時作動し、昇降路2に停止している他
の台車20や引き出されているはね橋50などの障害物
を検知するようになっている。そして、障害物を検知し
た場合には、台車20の駆動モーター33に停止信号が
送られるようになっている。
The proximity sensor 26 is composed of, for example, an ultrasonic sensor or the like, and is installed on the upper part (top plate) and the lower part (bottom plate) of the carriage 20, as shown in FIG. Then, when the carriage 20 rises, the proximity sensor 26 on the upper side
Always operates, and when descending, the proximity sensor 26
(See FIG. 5) is constantly operated to detect obstacles such as another bogie 20 stopped in the hoistway 2 and the spring bridge 50 that is pulled out. When an obstacle is detected, a stop signal is sent to the drive motor 33 of the carriage 20.

【0024】台車傾斜計は駆動モーター33に内蔵され
ており、搭載している資材の荷重が不均衡となって台車
20が傾いている場合、左右の駆動モーター33、33
のそれぞれの速度を変化せしめることにより、台車20
の傾斜を矯正するものである。なお、この台車傾斜計2
7を使用せず、例えば、水銀スイッチによる制御回路
で、台車の傾斜を補正することも可能である。着床検出
センサーは、台車20の底部に設けられ、はね橋50の
走行部53を検出して、台車20がはね橋50上にに接
地したことを検出するものである。
The trolley inclinometer is built in the drive motor 33, and when the load of the mounted materials is unbalanced and the trolley 20 is tilted, the left and right drive motors 33, 33.
By changing the speed of each of the
The inclination of is corrected. In addition, this trolley inclinometer 2
It is also possible to correct the inclination of the carriage by using a control circuit using a mercury switch, for example, without using 7. The landing detection sensor is provided at the bottom of the bogie 20, and detects the traveling portion 53 of the splash bridge 50 to detect that the bogie 20 is grounded on the splash bridge 50.

【0025】また、図1および図3において符号50で
示すはね橋は、はね橋本体51と、昇降路2内へはね橋
本体51を回動させる電動ジャッキ52とで構成されて
いる。はね橋本体51は、台車20が載置される走行部
53と、走行部53、53間に架け渡されたフレーム5
4とで構成され、走行部53には、台車20の停車位置
を設定する走行ストッパー55が設けられている。そし
て、はね橋本体51の一端は、フロアF1,F2,…側
に回動自在にピン接合されている。
1 and 3, a drawbridge indicated by reference numeral 50 is composed of a drawbridge main body 51 and an electric jack 52 for rotating the drawbridge main body 51 into the hoistway 2. The drawbridge main body 51 includes a traveling section 53 on which the trolley 20 is placed, and a frame 5 bridged between the traveling sections 53, 53.
4 and the traveling portion 53 is provided with a traveling stopper 55 for setting the stop position of the carriage 20. One end of the drawbridge main body 51 is rotatably pin-joined to the floors F1, F2, ...

【0026】電動ジャッキ52は、はね橋本体51の下
面側にシリンダーアーム52aを連結して配設されてお
り、シリンダアーム52aの伸縮動作により、はね橋本
体51の一端部を支点として、はね橋本体51の引き出
し、及び引き込み動作が行われるようになっている。
The electric jack 52 is arranged on the lower surface side of the drawbridge main body 51 by connecting the cylinder arm 52a, and by the extension and contraction of the cylinder arm 52a, one end of the drawbridge main body 51 is used as a fulcrum to support the drawbridge main body 51. The pull-out and pull-in operations are performed.

【0027】また、昇降路2には、昇降路2内に引き出
されたはね橋本体51の先端部を指示する受け金具56
が配設されている。そして、電動ジャッキ52には、給
電線6から電力が供給されるようになっている。
Further, in the hoistway 2, a receiving metal fitting 56 for indicating the tip portion of the drawbridge main body 51 drawn into the hoistway 2.
Are arranged. Then, electric power is supplied to the electric jack 52 from the power supply line 6.

【0028】また、図1および図8において符号60で
示すものは、各フロアF1,F2,…に配設され、はね
橋50上の台車20を昇降路2に出し入れするととも
に、台車20を各フロアF1,F2,…の所定場所まで
牽引する牽引車である。この牽引車60は、走行用モー
ターを内蔵した自動車であり、人的操作若しくは遠隔操
作により走行する。この牽引車60には、台車出し入れ
用ロッド61が備えられており、この台車出し入れ用ロ
ッド61を台車20のフック37に係合して自走するこ
とにより、台車20が所定場所に牽引される。
In FIGS. 1 and 8, the reference numeral 60 is arranged on each floor F1, F2, ... To move the carriage 20 on the drawbridge 50 into and out of the hoistway 2 and to move the carriage 20 to each floor. It is a towing vehicle that pulls to a predetermined location of F1, F2, .... The towing vehicle 60 is an automobile having a built-in motor for traveling and travels by a human operation or a remote operation. The towing vehicle 60 is provided with a trolley loading / unloading rod 61. By engaging the trolley loading / unloading rod 61 with the hook 37 of the trolley 20 to move by itself, the trolley 20 is towed to a predetermined location. ..

【0029】また、図9において符号70で示すもの
は、台車20の行き先階を入力して台車20…及びはね
橋50…に動作信号を送るとともに、台車20…及びは
ね橋50…の運転状況を把握することが可能な運転管理
装置である。運転管理装置70は、マイクロコンピュー
ター71と、PC(プログラマブルコントローラ)機器
72を主構成装置としている。マイクロコンピューター
71は、台車20の行き先階を入力するキーボード(入
力手段)73と、台車20…及びはね橋50…の状況が
表示盤で表示されるディスプレイ装置(表示手段)74
が備えられたものである。また、PC機器72は、複数
のフロアF1,F2,…のはね橋50…と、光ファイバ
ー76、PC(プログラマブルコントローラ)子器77
…を介して接続されている。
In FIG. 9, the reference numeral 70 indicates the destination floor of the trolley 20 and sends an operation signal to the trolley 20 ... and the splash bridge 50, and at the same time grasps the operating conditions of the trolley 20 ... and the splash bridge 50. It is an operation management device that can perform. The operation management device 70 has a microcomputer 71 and a PC (programmable controller) device 72 as main constituent devices. The microcomputer 71 has a keyboard (input means) 73 for inputting a destination floor of the carriage 20 and a display device (display means) 74 for displaying the statuses of the carriage 20 and the drawbridge 50 on a display panel.
Is provided. Further, the PC device 72 includes the splash bridges 50 of the plurality of floors F1, F2, ..., The optical fiber 76, and the PC (programmable controller) slave 77.
Are connected via.

【0030】また、PC機器72は、通信装置78を介
して給電線6と接続されている。すなわち、本実施例の
給電線6は信号併送給電方式が採用されており、図10
に示すように、給電線6と台車20のフロア読取センサ
ー22や近接センサー26等の送信機器間にハイパスフ
ィルター(H.P.F)79が設けられている。また、
給電線6と駆動モーター33、電動ジャッキ36等の動
力機器間にローパスフィルター(L.P.F)80が設
けられている。
Further, the PC device 72 is connected to the power supply line 6 via the communication device 78. That is, the power supply line 6 of the present embodiment employs the signal simultaneous transmission power supply system.
As shown in FIG. 3, a high-pass filter (HPF) 79 is provided between the power supply line 6 and the transmission device such as the floor reading sensor 22 and the proximity sensor 26 of the trolley 20. Also,
A low-pass filter (LPF) 80 is provided between the power supply line 6 and the power equipment such as the drive motor 33 and the electric jack 36.

【0031】これにより、運転管理装置70とはね橋5
0…との信号授受は、PC機器75、光ファイバー7
6、PC子器77…を介して行われ、運転管理装置70
からはね橋50…に対する所定の動作信号が自動的に送
られるとともに、はね橋50…の動作が逐次ディスプレ
イ装置74の表示盤で表示されるようになっている。
As a result, the operation management device 70 and the splash bridge 5
Signal exchange with 0 ... PC device 75, optical fiber 7
6. The operation management device 70 is performed via the PC slave 77.
A predetermined operation signal to the spring bridge 50 is automatically sent, and the operation of the spring bridge 50 is sequentially displayed on the display panel of the display device 74.

【0032】また、運転管理装置70と台車20…との
信号授受は、PC機器75、通信装置78、給電線6を
介して行われ、運転管理装置70から台車20…に対す
る所定の動作信号が自動的に送られるとともに、台車2
0…の動作が逐次ディスプレイ装置74の表示盤で表示
されるようになっている。
Signals are exchanged between the operation management device 70 and the carriage 20 via the PC device 75, the communication device 78, and the power supply line 6, and a predetermined operation signal from the operation management device 70 to the carriage 20 is transmitted. Automatically sent and trolley 2
The operations of 0 ... Are sequentially displayed on the display panel of the display device 74.

【0033】さらに、フロア読み取りセンサー22、近
接センサー26、リミットスイッチ、着床検出センサー
が検出した信号は、給電線6を介して運転管理装置70
に逐次送り込まれディスプレイ装置74の表示盤で表示
されるようになっている。なお、前述した給電線6によ
る信号併送給電方式を採用せず、誘導無線ケーブルを昇
降路2に敷設し、台車20の送受機器と運転管理装置7
0とを無線によりデータ授受を行うようにしてもよい。
Further, the signals detected by the floor reading sensor 22, the proximity sensor 26, the limit switch, and the landing detection sensor are transmitted through the power supply line 6 to the operation management device 70.
Are sequentially sent to the display device 74 and displayed on the display panel of the display device 74. It should be noted that an inductive wireless cable is laid in the hoistway 2 instead of adopting the above-described signal simultaneous power feeding system by the power feeding line 6, and the transmission / reception device of the carriage 20 and the operation management device 7 are provided.
Data may be exchanged between 0 and 0 wirelessly.

【0034】次に、本実施例のシステムによる、資材を
所定のフロアまで搬送する手順について説明する。な
お、説明は一台の台車20の動作についておこなうが、
搬送路2の登り用の系統及び下り用の系統には、それぞ
れ複数の台車20…が上昇(登り用系統)若しくは下降
(下り用系統)して資材を連続的に所定のフロアF1,
F2,…に搬送するものとする。 1) 荷積みフロアF1に設置されている台車20に資
材を搭載する。そして、牽引車60により、台車20の
フック37に台車出し入れロッド61を係合させて、フ
ロアF1の昇降路入口9まで台車20を移動する。この
時、フロアF1の昇降路入口9には既にはね橋50が引
き出されている状態としておき、走行部53の走行スト
ッパー55に台車20のキャスター29を当接させて、
台車20をはね橋50上に簡単に位置決めさせる。 2) 台車20がはね橋50上に配設されると、台車2
0の昇降機構24が昇降路2のレール3、3と対向配置
される。そして、押圧機構25の作動により昇降機構2
4の昇降用ピニオンギア30をラック5に噛み合わせ
る。ここで、昇降用ピニオンギア30の停止位置は、台
車20に内蔵されたリミットスイッチで設定される。な
お、昇降用ピニオンギア30がラック5と噛み合う際に
は、駆動モーター33に内蔵されているブレーキ機構3
2が解除された状態で昇降用ピニオンギア30が円弧運
動してラック5と噛み合うので、昇降用ピニオンギア3
0の歯先に無理な力が加わらない。また、昇降用ピニオ
ンギア30とラック5との噛み合わせ後に、ブレーキ機
構32が投入される。 3) 駆動モーター32の駆動によって昇降用ピニオン
ギア30が回転し、それにより台車20は上昇若しくは
下降していく。ここで、台車20が上昇する際には、台
車20はそのまま上昇動作に移行していく。また、台車
20が下降する場合には、台車20は、一旦、はね橋5
0の回転半径(はね橋50を引き込む際に移動する領
域)と干渉しない位置まで上昇し、はね橋50が引き込
まれた後に、下降動作に移行していく。 3) 台車20が下降して所定のフロアまで移動してく
ると、先に所定のフロアのはね橋50を昇降路2内に引
き出しておき、はね橋20の走行部53上に台車20を
載せる。この時、台車20は近接センサー26により所
定のフロアのはね橋50の位置を検出して過走しないよ
うにする。また、台車20がはね橋50上に載置される
際には、台車20の着床検出センサー38が、台車20
がはね橋50に接地したことを確認する。一方、台車2
0が上昇しながら所定のフロアまで移動してくると、一
旦、台車20はフロアのはね橋50と干渉しない位置ま
で上昇し、はね橋50が引き出された後に、再度下降し
てはね橋50の走行部53上に載る。 4) 台車20がはね橋50上に載ると、押圧機構25
の離脱作動により昇降機構24が昇降路2のレール3か
ら離脱し、台車20は所定のフロア上に引き出し可能な
状態となる。 5) 台車20のフック37に台車出し入れロッド61
を係合させた状態で、牽引車60により昇降路2から台
車20を引き出し、所定のフロアのの指定場所まで移動
させる。
Next, a procedure for carrying materials to a predetermined floor by the system of this embodiment will be described. In addition, although the explanation will be made about the operation of one trolley 20,
In the climbing system and the descending system of the transport path 2, a plurality of carts 20 ... Ascend (climb system) or descend (descend system) to continuously load materials onto a predetermined floor F1,
It shall be transported to F2, .... 1) The materials are mounted on the trolley 20 installed on the loading floor F1. Then, the tow vehicle 60 engages the trolley loading / unloading rod 61 with the hook 37 of the trolley 20 to move the trolley 20 to the hoistway entrance 9 of the floor F1. At this time, the drawbridge 50 is already pulled out to the hoistway entrance 9 of the floor F1, and the caster 29 of the carriage 20 is brought into contact with the travel stopper 55 of the travel part 53,
The carriage 20 is easily positioned on the spring bridge 50. 2) When the carriage 20 is installed on the splash bridge 50, the carriage 2
The lifting mechanism 24 of 0 is arranged to face the rails 3 and 3 of the hoistway 2. Then, the lifting mechanism 2 is operated by the operation of the pressing mechanism 25.
The lifting pinion gear 30 of 4 is engaged with the rack 5. Here, the stop position of the lifting pinion gear 30 is set by the limit switch built in the carriage 20. When the lifting pinion gear 30 meshes with the rack 5, the brake mechanism 3 incorporated in the drive motor 33 is used.
2 is released, the lifting pinion gear 30 makes an arc motion and meshes with the rack 5, so that the lifting pinion gear 3
Unreasonable force is not applied to the tooth tip of 0. In addition, the brake mechanism 32 is closed after the lifting pinion gear 30 and the rack 5 are engaged with each other. 3) The driving motor 32 drives the lifting pinion gear 30 to rotate, whereby the carriage 20 moves up or down. Here, when the trolley | bogie 20 raises, the trolley | bogie 20 transfers to a raising operation as it is. In addition, when the carriage 20 descends, the carriage 20 once
It rises to a position where it does not interfere with the turning radius of 0 (the region that moves when retracting the spring bridge 50), and after the spring bridge 50 is retracted, it moves to the lowering operation. 3) When the carriage 20 descends and moves to a predetermined floor, the drawbridge 50 on the predetermined floor is first pulled out into the hoistway 2, and the carriage 20 is placed on the traveling portion 53 of the drawbridge 20. At this time, the trolley | bogie 20 detects the position of the drawbridge 50 of a predetermined floor with the proximity sensor 26, and it prevents it from running excessively. Further, when the carriage 20 is placed on the splash bridge 50, the landing detection sensor 38 of the carriage 20 is
Make sure that Gagane Bridge 50 is grounded. On the other hand, trolley 2
When 0 moves up to a predetermined floor while rising, the dolly 20 once rises to a position where it does not interfere with the splash bridge 50 on the floor, and after the splash bridge 50 is pulled out, it is lowered again and the traveling portion 53 of the splash bridge 50 Listed above. 4) When the carriage 20 is placed on the splash bridge 50, the pushing mechanism 25
The lifting mechanism 24 is lifted from the rail 3 of the hoistway 2 by the detaching operation, and the carriage 20 is ready to be pulled out onto a predetermined floor. 5) A rod 61 for loading and unloading the dolly on the hook 37 of the dolly 20.
In a state in which is engaged, the trolley 60 pulls the dolly 20 out of the hoistway 2 and moves it to a designated place on a predetermined floor.

【0035】次に、本実施例の運転管理装置70から台
車20…への制御動作と、各センサーの作用について説
明する。 a) 運転管理装置70には、PC機器75、PC子器
77…、光ファイバー76を介して各はね橋50…の信
号(はね橋50が引き出されている状態を示す信号、若
しくは引き込まれている状態を示す信号)が常時送られ
てきており、全てのはね橋50…の動作状況はディスプ
レイ装置74の表示盤で表示される。また、昇降路2を
移動する台車20…及び各フロアF1,F2,…上の台
車20…の状況は、給電線6から送られてくる信号(台
車20…の位置を示す信号)がディスプレイ装置74の
表示盤で表示されることにより判断される。 b) 台車20に行き先階(指定階)を指定するには、
マイクロコンピューター71のキーボード73に台車2
0の行き先階数を入力する。それにより、台車20の階
数信号が、PC機器75から給電線6を介して台車20
のコントローラ(図示せず)に送られて記憶される。そ
して、台車20が昇降すると、フロア読取センサー22
が各フロアF1,F2,…のフロア表示ラベル10…を
常時読み取っていき、前記コントローラで記憶している
階数信号とフロア表示ラベル10…とを比較して、階数
信号と所定のロア表示ラベル10とが一致した場合に台
車20を停止させる。ここで、行き先階数の指定の誤り
(例えば、指定階のし忘れで先に指定した同一階のま
ま、あるいは上昇系統の搬送路2に下階の数値を設定、
または存在しない階を指定)を行った場合には、台車2
0は停止した状態を保ち、表示盤に入力の誤りを表示す
る。 c) 資材の荷重の不均衡によって昇降する台車20が
傾いている場合には、駆動モーター33に内蔵されてい
る台車傾斜計により、左右の駆動モーター33、33の
速度制御が行われ、それにより台車20の傾きが矯正さ
れる。 d) 昇降路2に他の台車20…や昇降途中において他
のはね橋50が引き出されている場合には、近接センサ
ー26が障害物(他の台車20、はね橋50)を検出
し、台車20の昇降を停止させる。 e) 台車20の昇降機構24を昇降路2のレール3か
ら離脱する際には、台車20の下部にはね橋50が引き
出されていることが必須条件である。したがって、運転
制御装置70からはね橋50の状況(台車20が載るべ
きはね橋50の引き出しが完了している状態)を自動的
に判断し、さらに台車20の着床検出センサー38がは
ね橋50の存在を確認するという複数段階の確認動作を
組み合わせて行い、その後に昇降機構24がレール3か
ら離脱するシステムになっている。
Next, the control operation from the operation management device 70 of this embodiment to the carriage 20 and the operation of each sensor will be described. a) The operation management device 70 sends a signal of each splash bridge 50 ... (a signal indicating a state where the splash bridge 50 is pulled out or a pulled-in state via the PC device 75, the PC slave 77 ..., and the optical fiber 76). The signal indicating) is constantly sent, and the operation status of all the drawbridges 50 ... Is displayed on the display panel of the display device 74. Further, regarding the situation of the carriage 20 moving on the hoistway 2 and the carriages 20 on each floor F1, F2, ..., a signal sent from the power supply line 6 (a signal indicating the position of the carriage 20 ...) is displayed on the display device. It is judged by being displayed on the display panel 74. b) To specify the destination floor (designated floor) for the dolly 20,
Truck 2 on the keyboard 73 of the microcomputer 71
Enter the destination floor number of 0. As a result, the floor signal of the carriage 20 is transmitted from the PC device 75 via the power supply line 6 to the carriage 20.
And stored in a controller (not shown). When the carriage 20 moves up and down, the floor reading sensor 22
Constantly reads the floor display label 10 of each floor F1, F2, ..., Compares the floor signal and the floor display label 10 stored in the controller, and compares the floor signal and the predetermined lower label 10 When and match, the dolly 20 is stopped. Here, the destination floor number is wrongly specified (for example, if the designated floor is forgotten, the same floor as previously specified remains, or the lower floor numerical value is set in the ascending route 2).
Or if you specify a floor that does not exist), dolly 2
0 keeps stopped and displays an input error on the display board. c) When the trolley 20 that moves up and down due to the imbalance of the material load is tilted, the trolley inclinometer built in the drive motor 33 controls the speed of the left and right drive motors 33, 33. The inclination of the carriage 20 is corrected. d) When another bogie 20 ... or another splash bridge 50 is pulled out to the hoistway 2 while being raised or lowered, the proximity sensor 26 detects an obstacle (other bogie 20, splash bridge 50) and Stop lifting. e) When the lifting mechanism 24 of the trolley 20 is detached from the rail 3 of the hoistway 2, it is an essential condition that the splash bridge 50 is pulled out to the lower portion of the trolley 20. Therefore, the operation control device 70 automatically determines the situation of the drawbridge 50 (the state in which the drawbridge 50 on which the carriage 20 should be mounted is completed), and the landing detection sensor 38 of the carriage 20 detects the presence of the drawbridge 50. This is a system in which confirmation operations of a plurality of stages of confirmation are performed in combination, and then the lifting mechanism 24 is separated from the rail 3.

【0036】以上の建設用資材の搬送システムによれ
ば、従来の高速リフトと同様の仮設揚重設備の平面積を
保ちながら、搬入階から指定階(揚重階)までの大量の
資材の搬送を行うことができ、超高層建築物を構築する
際に必要とされる資材の大量搬送に、十分に対応するこ
とができる。
According to the construction material transfer system described above, a large amount of material is transferred from the loading floor to the designated floor (lifting floor) while maintaining the flat area of the temporary lifting equipment similar to the conventional high-speed lift. Therefore, it is possible to sufficiently cope with a large amount of transportation of materials required when constructing a super high-rise building.

【0037】また、昇降路2内を移動する昇降機構24
を内蔵した台車20…の増設若しくは減少を、容易に行
うことができるので、構築される建築物1の規模に見合
った台車20の使用台数を設定することができる。
Further, an elevating mechanism 24 which moves in the hoistway 2
Since it is possible to easily add or reduce the trolleys 20 ... Incorporating therein, it is possible to set the number of trolleys 20 to be used, which corresponds to the scale of the building 1 to be constructed.

【0038】また、本実施例は、登り専用と下り専用の
2系統の昇降路2を設けて、この昇降路2を移動する台
車20…と、昇降路2の昇降路入口9に配設されたはね
橋50…に運転管理装置70から所定の動作信号を送出
することにより、台車20、はね橋50の運転制御が行
われ、かつ台車状況とはね橋50の動作を運転管理装置
70で集中的に管理することがので、資材を搬送する複
数の台車20…の安全性が高められた自動運転が可能と
されながら超高層ビル用の自動化された資材搬送装置を
提供することができる。
Further, in this embodiment, two hoistways 2 for ascending and descending are provided, and the carriages 20 moving on the hoistways 2 and the hoistway entrances 9 of the hoistways 2 are provided. The operation control device 70 sends a predetermined operation signal to the tongue bridge 50 to control the operation of the carriage 20 and the drawbridge 50, and the operation management device 70 centrally manages the carriage condition and the operation of the drawbridge 50. As a result, it is possible to provide an automated material transfer device for a skyscraper while enabling automatic operation with improved safety of a plurality of trolleys 20 that transfer materials.

【0039】また、本実施例の装置においては、台車2
0に耐火被覆吹き付け用のプラント等を搭載することに
より、建築物1の内部の工事で使用される工事設備の移
動を容易にすることも可能である。
In the apparatus of this embodiment, the carriage 2
It is also possible to facilitate the movement of the construction equipment used in the construction inside the building 1 by mounting a plant for spraying a fireproof coating on the No. 0.

【0040】次に、第11図ないし図31は、本発明の
請求項1と請求項3に係る発明の第2の実施例を示すも
のである。なお、本実施例においては、説明は省略する
が、第1の実施例で示した構成部材、例えば昇降路入口
のフロア表示ラベル10、台車に配設されたフロア読取
センサー22、牽引車60、運転管理装置70等は配設
されおり、それにより自動化された搬送装置を提供する
ものとする。
Next, FIGS. 11 to 31 show a second embodiment of the invention according to claims 1 and 3 of the present invention. Although not described in this embodiment, the components shown in the first embodiment, such as the floor display label 10 at the entrance of the hoistway, the floor reading sensor 22 mounted on the truck, the towing vehicle 60, The operation management device 70 and the like are provided, and thereby an automated transport device is provided.

【0041】本実施例の昇降路80は、図11に示すよ
うに、マストユニット81…が、各フロアF1,F2,
…で自重が支持されながら鉛直方向に複数連結されてな
るものである。各マストユニット81は、前面側81a
が、台車20が上昇する登り専用路とされ、後面側81
bが、台車20が下降する下り専用路とされている。そ
して、各マストユニット81の登り専用路81aから下
り専用路81bにわたって、上下方向に駆動チェーン8
2が回動自在に巻装されている。
In the hoistway 80 of this embodiment, as shown in FIG. 11, the mast units 81 ...
A plurality of them are vertically connected while supporting their own weight. Each mast unit 81 has a front side 81a.
However, it is designated as a climbing road for the dolly 20 to rise, and the rear side 81
The road b is a dedicated road for descending the truck 20. Then, the drive chain 8 is vertically moved from the ascending-only path 81a to the descending-only path 81b of each mast unit 81.
2 is rotatably wound.

【0042】すなわち、図12に示すように、各マスト
ユニット81の一部に駆動モーター83が配設され、こ
れら駆動モーター83の駆動ギア84と、回転ギア85
に無端状の駆動チェーン82が配設されている。そし
て、駆動モーター83の駆動により、駆動チェーン82
が矢印A方向に回動するようになっている。なお、駆動
チェーン82は、図13に示すように、歯形の形状を有
している各リンク82aが相互にリンク結合されて構成
されている。そして、隣接するマストユニット81、8
1は、図12に示すように、巻装された駆動チェーン8
2、82どうしが干渉しないように、平面視において互
いの位置がずらされている。また、登り専用路81a及
び下り専用路81bの上下方向には、断面L字状のガイ
ドレール86が配設されている。
That is, as shown in FIG. 12, a drive motor 83 is provided in a part of each mast unit 81, and the drive gear 84 and the rotary gear 85 of these drive motors 83 are arranged.
An endless drive chain 82 is disposed in the. The drive chain 82 is driven by the drive motor 83.
Rotate in the direction of arrow A. As shown in FIG. 13, the drive chain 82 is configured by linking each link 82a having a tooth shape with each other. And the adjacent mast units 81, 8
1 is a wound drive chain 8 as shown in FIG.
The positions of the two 82 are offset from each other in plan view so that the two 82 do not interfere with each other. A guide rail 86 having an L-shaped cross section is arranged in the up-down direction of the ascending-only path 81a and the descending-only path 81b.

【0043】また、本実施例の台車20には、図14に
示すように、マストユニット81のガイドレール86と
摺動自在に係合し、かつ台車20を昇降路80(各マス
トユニット81)に沿わせるガイドローラ87と、駆動
チェーン82に着脱自在に嵌合するラック88と、台車
20がフロア側へ移行する際に横引き機構90(台車移
行機構)と係合する台車移行用ローラー91とが具備さ
れている。ガイドローラー87は、台車本体23の側面
縁部に固定されているローラー軸に回転自在に配設され
ており、側面がマストユニット81に近接すると、前記
ガイドレール86の内部に遊嵌されるようになってい
る。
As shown in FIG. 14, the bogie 20 of this embodiment is slidably engaged with the guide rail 86 of the mast unit 81, and the bogie 20 is moved up and down 80 (each mast unit 81). Along with the guide roller 87, the rack 88 that is detachably fitted to the drive chain 82, and the carriage transfer roller 91 that engages with the lateral pulling mechanism 90 (carriage transfer mechanism) when the carriage 20 moves to the floor side. And are provided. The guide roller 87 is rotatably arranged on a roller shaft fixed to a side edge portion of the carriage main body 23. When the side surface approaches the mast unit 81, the guide roller 87 is loosely fitted inside the guide rail 86. It has become.

【0044】また、図15および図16に示す横引き機
構90は、各フロアF1,F2,…の昇降路入口9に移
動してきた台車20を、フロア上へ移動させる機構であ
る。この横引き機構90は、昇降路入口9からマストユ
ニット81に向けて配設された一対の横引きフレーム9
2と、これら横引きフレーム92を僅かに水平移動させ
る移動手段(図示せず)とで構成されている。横引きフ
レーム92は、図16に示すように、切り込み93が形
成された底面部92aと、底面部92aの縁部から垂直
に立ち上がる側面部92b、92cとからなる部材であ
る。そして、台車20が昇降路80内を昇降する場合に
は、側面92cがガイドレール86の一部となる。ここ
で、上下方向に移動する台車移行用ローラー91は、切
り込み93内を通過する構造とされているので、台車2
0は横引きフレーム92と干渉しない。
The horizontal pulling mechanism 90 shown in FIGS. 15 and 16 is a mechanism for moving the carriage 20 that has moved to the hoistway entrance 9 of each floor F1, F2, ... The horizontal pulling mechanism 90 includes a pair of horizontal pulling frames 9 arranged from the hoistway inlet 9 toward the mast unit 81.
2 and moving means (not shown) for moving the horizontal pulling frame 92 slightly horizontally. As shown in FIG. 16, the horizontal pulling frame 92 is a member including a bottom surface portion 92a in which a notch 93 is formed and side surface portions 92b and 92c which vertically rise from the edge portion of the bottom surface portion 92a. When the carriage 20 moves up and down in the hoistway 80, the side surface 92c becomes a part of the guide rail 86. Here, since the trolley transition roller 91 that moves in the vertical direction has a structure that passes through the inside of the notch 93, the trolley 2
0 does not interfere with the horizontal frame 92.

【0045】本実施例の横引き機構90により台車20
をフロア上に横引きする手順は、先ず、マストユニット
81の駆動チェーン82を、台車20の上部側のガイド
ローラ87が横引きフレームより若干上方となる位置で
停止させる(図17参照)。次に、移動手段により横引
きフレーム92をマストユニット81側に押し入れる。
そして、駆動チェーン82の回動により台車20を下降
させ、横引きフレーム92の底面部92aに台車20の
荷重を預ける(図18参照)。次に、ラック88と駆動
チェーン82とを離脱させた状態で、台車20のガイド
ローラー87及び台車移行用ローラー91を転動させて
台車20をフロア側へ移行させる。
The trolley 20 is driven by the horizontal pulling mechanism 90 of this embodiment.
In the procedure for laterally pulling the carriage onto the floor, first, the drive chain 82 of the mast unit 81 is stopped at a position where the guide roller 87 on the upper side of the carriage 20 is slightly above the horizontal pulling frame (see FIG. 17). Next, the horizontal pulling frame 92 is pushed into the mast unit 81 side by the moving means.
Then, the truck 20 is lowered by the rotation of the drive chain 82, and the load of the truck 20 is stored on the bottom surface portion 92a of the horizontal pulling frame 92 (see FIG. 18). Next, with the rack 88 and the drive chain 82 separated from each other, the guide roller 87 of the carriage 20 and the carriage shifting roller 91 are rolled to shift the carriage 20 to the floor side.

【0046】したがって、第1の実施例と同様の効果を
得ることができるとともに、マストユニット81の前後
面で登り専用路81aと下り専用路81bの2系統の昇
降路80を設けることができ、昇降路80内を移動する
台車20…の増設若しくは減少を、容易に行うことがで
きるので、構築される建築物1の規模に見合った台車2
0の使用台数を設定することができる。
Therefore, it is possible to obtain the same effect as that of the first embodiment, and it is possible to provide the two hoistways 80 of the ascending-only path 81a and the descending-only path 81b on the front and rear surfaces of the mast unit 81, Since it is possible to easily add or reduce the trolleys 20 moving in the hoistway 80, the trolleys 2 suitable for the scale of the building 1 to be constructed.
It is possible to set the number of used vehicles to zero.

【0047】また、図19ないし図25に示すものは、
図16ないし図18で示した横引き機構の他の実施例で
ある。
The ones shown in FIGS. 19 to 25 are
It is another embodiment of the horizontal pulling mechanism shown in FIGS.

【0048】図19ないし図21に示す横引き機構フレ
ーム95は、大小の切り込み96、97が形成された底
面部95a及び上面部95bと、側面部95c、95d
とからなる部材であり、台車20が昇降路80内を移動
する場合には、側面部95dがガイドレール86の一部
となる。ここで、切り込み96の切り込み大きさは、ガ
イドローラー87が上下方向に通過可能な大きさとされ
ており、切り込み9の切り込み大きさは、台車移行用ロ
ーラー91のみが上下方向に通過可能な大きさとされて
いる。
The horizontal pulling mechanism frame 95 shown in FIGS. 19 to 21 has a bottom surface portion 95a and a top surface portion 95b having large and small cuts 96 and 97, and side surface portions 95c and 95d.
When the carriage 20 moves in the hoistway 80, the side surface portion 95d becomes a part of the guide rail 86. Here, the cut size of the cut 96 is set to a size that allows the guide roller 87 to pass through in the vertical direction, and the cut size of the cut 9 is set to a size that allows only the carriage transfer roller 91 to pass through in the vertical direction. Has been done.

【0049】そして、台車をフロアまで横引きする場合
には、移動手段により横引きフレーム95をマストユニ
ット81側に押し入れ、台車20の上昇によりガイドロ
ーラー87および台車移行用ローラー91を横引きフレ
ーム95内に位置させ、それらガイドローラー87及び
台車移行用ローラー91を底面部96a上で転動させる
ことにより、フロア側へ台車20を移行させる。
When the truck is horizontally pulled to the floor, the horizontal pulling frame 95 is pushed into the mast unit 81 side by the moving means, and the guide roller 87 and the truck shifting roller 91 are pushed horizontally by the lifting of the truck 20. The carriage 20 is moved to the floor side by being positioned inside and rolling the guide roller 87 and the carriage moving roller 91 on the bottom surface portion 96a.

【0050】また、図22及び図24に示す実施例は、
各フロアの昇降路入口とマストユニット間に配設された
横引き機構である。この横引き機構は、ガイドレール8
6にガイドローラー87が通過可能な大きさに形成され
た切欠部99と、この切欠部99を閉塞する閉塞板10
0と、ガイドローラー87と台車移行用ローラー91が
転動可能な移行フレーム101とが備えられた機構であ
る。また、閉塞板100と移行フレーム101は支持部
102に対して略対角線上に配設され、かつそれらが支
持部102に回転自在となるように支持されている。こ
れにより、閉塞板100が切欠部99を閉塞すると移行
フレーム101はガイドレール86の外側に移動し(図
23及び図24参照)、移行フレーム101がガイドフ
レール86側に移動すると、閉塞板100が移動して切
欠部99の閉塞が解除されるようになっている(図24
参照)。
The embodiment shown in FIGS. 22 and 24 is
It is a horizontal pulling mechanism disposed between the hoistway entrance of each floor and the mast unit. This horizontal pulling mechanism uses the guide rail 8
6, a notch 99 formed to have a size through which the guide roller 87 can pass, and a closing plate 10 that closes the notch 99.
0, a guide roller 87, and a transition frame 101 on which a cart transition roller 91 can roll. Further, the closing plate 100 and the transition frame 101 are arranged on a substantially diagonal line with respect to the support portion 102, and are supported by the support portion 102 so as to be rotatable. Accordingly, when the closing plate 100 closes the notch 99, the transition frame 101 moves to the outside of the guide rail 86 (see FIGS. 23 and 24), and when the transition frame 101 moves to the guide flare 86 side, the closing plate 100 moves. It moves so that the blockage of the notch 99 is released (FIG. 24).
reference).

【0051】これにより、台車20をフロア上に横引き
するには、切欠部99を閉塞してガイドレール86の一
部としていた閉塞板100を移動させ、移行フレーム1
010をガイドレール86側に移動させることにより
(図23及び図24参照)、台車20の台車移行用ロー
ラー91を移行フレーム101上に載せる。そして、台
車20のガイドローラー87も、切欠部99を通過させ
て移行フレーム101上で転動させることにより、台車
20はフロア側に移行していく。
Thus, in order to laterally pull the carriage 20 on the floor, the notch 99 is closed to move the closing plate 100 which is a part of the guide rail 86, and the transition frame 1 is moved.
By moving 010 to the guide rail 86 side (see FIGS. 23 and 24), the trolley transition roller 91 of the trolley 20 is placed on the transition frame 101. Then, the guide roller 87 of the dolly 20 also passes through the notch 99 and rolls on the transition frame 101, whereby the trolley 20 moves to the floor side.

【0052】また、図25ないし図30に示すものは、
図12ないし図15に示したマストユニット81と台車
20の実施例の変形例である。この実施例においては、
図25に示すように、マストユニット81に支持プレー
ト105を介して複数のガイドローラー87…が配設さ
れ、台車20にガイドレール86が配設された構造とさ
れている。そして、昇降路入口9を望む位置の支持プレ
ート105には、開口部106が形成されているととも
に、開口部106の位置に配設されたガイドローラー8
7aが、アクチュエーター機構107の作動により支持
プレート105から外れる構造になっている。なお、本
実施例で台車20を各フロアに移行させる台車移行装置
としては、図1で示したはね橋50が配設されているも
のとする。これにより、本実施例においては、はね橋5
0が台車20の下部に引きだされた状態で、昇降路入口
9のガイドローラー87aがアクチュエーター機構10
7により支持プレート105から外れると、台車20が
昇降路80から離脱する構造になっている。
The ones shown in FIGS. 25 to 30 are
It is a modification of the embodiment of the mast unit 81 and the carriage 20 shown in FIGS. 12 to 15. In this example,
As shown in FIG. 25, the mast unit 81 is provided with a plurality of guide rollers 87 through the support plate 105, and the carriage 20 is provided with a guide rail 86. An opening 106 is formed in the support plate 105 at a position where the hoistway entrance 9 is desired, and the guide roller 8 arranged at the position of the opening 106.
The structure 7 a is detached from the support plate 105 by the operation of the actuator mechanism 107. In the present embodiment, it is assumed that the spring bridge 50 shown in FIG. 1 is provided as a carriage transfer device for transferring the carriage 20 to each floor. Thus, in this embodiment, the splash bridge 5
In the state where 0 is pulled out to the lower part of the carriage 20, the guide roller 87a at the entrance 9 of the hoistway moves the actuator mechanism 10
When the carriage 20 is disengaged from the support plate 105, the carriage 20 is separated from the hoistway 80.

【0053】また、図31ないし図36に示すものは、
本発明の請求項1と請求項4に係る発明の第3の実施例
を示すものである。
The ones shown in FIGS. 31 to 36 are
It shows a third embodiment of the invention according to claim 1 and claim 4 of the present invention.

【0054】本実施例の昇降路109は、図31に示す
ように、各フロアで自重が支持され、かつ相互に離間配
置された3基のマストユニット110a、110b、1
10cが、鉛直方向に複数連結されてなるものである。
また、各マストユニット110には、図32に示すよう
に、上下方向に回動する駆動ベルト111が配設されて
おり、この駆動ベルト111には、複数枚の昇降板11
2が突設されている。そして、マストユニット110a
の駆動ベルト111は図31に示す矢印R1方向に回動
し、マストユニット110bの駆動ベルト111が矢印
R2方向、マストユニット110cの駆動ベルト111
が矢印R3方向に回動することにより。マストユニット
110a、110b間が下り専用路109aとされ、マ
ストユニット110b、110c間が登り専用路109
bとされる。
As shown in FIG. 31, the hoistway 109 of this embodiment has three mast units 110a, 110b, 1b, each of which has its own weight supported on each floor and is spaced from each other.
A plurality of 10c are connected in the vertical direction.
Further, as shown in FIG. 32, each mast unit 110 is provided with a drive belt 111 that rotates in the vertical direction. The drive belt 111 includes a plurality of lift plates 11
2 is projected. And the mast unit 110a
31 is rotated in the direction of arrow R1 shown in FIG. 31, the drive belt 111 of the mast unit 110b is moved in the direction of arrow R2, and the drive belt 111 of the mast unit 110c is rotated.
By rotating in the direction of arrow R3. Between the mast units 110a and 110b is a down path 109a, and between the mast units 110b and 110c is an up path 109.
b.

【0055】また、本実施例の台車20は、図33に示
すように、その側部に駆動ベルト111の昇降板112
と係合する係合板113が設けられている。そして、係
合板113の下面には台車移行用ローラー114…が配
設されている。ここで、駆動ベルト111の各昇降板1
12…には、図34及び図35に示すストッパー機構1
15が配設されている。このストッパー機構115は、
昇降板112の長手方向の縁部にピン接合された停止板
116と、停止板を116を台車20の係合板113に
向けて押圧するスプリング117とで構成されている。
そして、図35に示すように、一対のストッパー機構1
15、115が、係合板113の長さ方向の縁部にそれ
ぞれ配設されることにより、スプリング117の付勢力
により停止板116、116が係合板113を挟持し、
昇降路109を移動する台車20の脱落が防止される。
また、ストッパー機構115を解除するには、図36に
示すように、停止板116の一端側を解除バー118で
押圧されることにより、スプリングが伸びた状態で停止
板116の係合板113への挟持状態が解除される。そ
れにより、矢印M方向への台車20が移行が可能とされ
る。
Further, as shown in FIG. 33, the truck 20 of the present embodiment has an elevating plate 112 of a drive belt 111 on its side.
An engaging plate 113 that engages with is provided. Further, on the lower surface of the engagement plate 113, rollers 114 for transferring the carriage are arranged. Here, each lifting plate 1 of the drive belt 111
12 ... has the stopper mechanism 1 shown in FIGS. 34 and 35.
15 are provided. This stopper mechanism 115
The lift plate 112 includes a stop plate 116 that is joined to the longitudinal edge of the lift plate 112 by a pin, and a spring 117 that presses the stop plate 116 toward the engagement plate 113 of the carriage 20.
Then, as shown in FIG. 35, the pair of stopper mechanisms 1
15 and 115 are arranged at the edges of the engagement plate 113 in the lengthwise direction, so that the stop plates 116 and 116 sandwich the engagement plate 113 by the urging force of the spring 117.
It is possible to prevent the carriage 20 moving in the hoistway 109 from falling off.
Further, in order to release the stopper mechanism 115, as shown in FIG. 36, one end side of the stop plate 116 is pressed by the release bar 118, so that the stop plate 116 is pushed to the engagement plate 113 in a state where the spring is extended. The sandwiched state is released. Thereby, the carriage 20 can be moved in the direction of the arrow M.

【0056】本実施例により台車20をフロア上に移行
させる手順は、先ず、ストッパー機構115、115に
より、台車20の係合板113を挟持しながら昇降路1
09内に台車20を昇降させる。そして、駆動ベルト1
11を停止させることによりフロアの昇降路入口9に台
車20を位置させる。次に、解除バー118によりスト
ッパー機構115の停止板116を水平状態とすること
によりストッパー機構115、115の挟持状態を解除
する。そして、昇降板112上を台車移行用ローラー1
14…が転動することにより、台車20がフロア側へ移
行する。
In the procedure for moving the truck 20 to the floor according to the present embodiment, first, the hoistway 1 is carried out while the engaging plate 113 of the truck 20 is held by the stopper mechanisms 115, 115.
The carriage 20 is raised and lowered within 09. And drive belt 1
By stopping 11 the carriage 20 is positioned at the hoistway entrance 9 on the floor. Next, the stop bar 116 of the stopper mechanism 115 is brought into a horizontal state by the release bar 118 to release the sandwiched state of the stopper mechanisms 115, 115. Then, on the lift plate 112, the roller 1 for trolley transfer
By rolling 14 ..., the truck 20 moves to the floor side.

【0057】したがって、本実施例においては、第1の
実施例と同様の効果を得ることができるとともに、昇降
路109内を移動する台車20…の増設若しくは減少
を、容易に行うことができるので、構築される建築物1
の規模に見合った台車20の使用台数を設定することが
できる。
Therefore, in this embodiment, the same effect as that of the first embodiment can be obtained, and the trolleys 20 moving in the hoistway 109 can be easily added or reduced. , The building to be built 1
It is possible to set the number of trolleys 20 to be used that matches the scale of

【0058】[0058]

【発明の効果】以上説明したように、本発明の建設用資
材搬送装置は、従来の高速リフトと同様の仮設揚重設備
の平面積を保ちながら、搬入階から指定階(揚重階)ま
での大量の資材の搬送を行うことができ、超高層建築物
を構築する際に必要とされる資材の大量搬送に、十分に
対応することができる。
As described above, the construction material conveying apparatus of the present invention is capable of maintaining the flat area of the temporary hoisting equipment similar to the conventional high-speed lift, from the loading floor to the designated floor (hoisting floor). It is possible to carry a large amount of materials, and it is possible to sufficiently cope with a large quantity of materials needed when constructing a super high-rise building.

【0059】また、昇降路内を移動する昇降機構を内蔵
した台車の増設若しくは減少を、容易に行うことができ
るため、構築される建築物の規模に見合った台車の使用
台数を設定することができる。
Further, since it is possible to easily add or reduce the number of trolleys having a built-in lifting mechanism for moving in the hoistway, it is possible to set the number of trolleys to be used according to the scale of the building to be constructed. it can.

【0060】また、登り専用と下り専用の2系統の昇降
路を移動する台車と、昇降路の昇降路入口に配設された
台車移行機構に運転管理装置から所定の動作信号が送出
されることにより、台車及び台車移行機構の運転制御が
確実に行われ、かつ台車状況と台車移行機構の動作を運
転管理装置で集中的に管理することができるため、資材
を搬送する複数の台車の安全性が高められた自動化され
た超高層ビル用の建設用資材搬送装置を提供することが
できる。また、本装置において、台車に耐火被覆吹き付
け用のプラント等を搭載することにより、建築物の内部
の工事で使用される工事設備の移動を容易にすることも
可能となる。
Further, a predetermined operation signal should be sent from the operation management device to the trolley that moves in the two hoistways for climbing and down, and the trolley transition mechanism provided at the hoistway entrance of the hoistway. By this, the operation control of the bogie and the bogie transfer mechanism can be reliably performed, and the operation status of the bogie and the bogie transfer mechanism can be centrally managed by the operation management device. It is possible to provide an automated construction material conveying device for a skyscraper with improved height. Further, in the present apparatus, by mounting a plant for spraying a fireproof coating on the carriage, it becomes possible to facilitate the movement of the construction equipment used in the construction work inside the building.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の請求項2記載の装置全体を示す斜視図
である。
FIG. 1 is a perspective view showing an entire apparatus according to claim 2 of the present invention.

【図2】請求項2記載の装置のレール軌道を示す平面図
である。
FIG. 2 is a plan view showing a rail track of the device according to claim 2;

【図3】請求項2記載の装置のはね橋を示す側面図であ
る。
FIG. 3 is a side view showing a drawbridge of the device according to claim 2;

【図4】請求項2記載の台車を示す平面図である。FIG. 4 is a plan view showing a trolley according to claim 2;

【図5】請求項2記載の台車の昇降機構及び連結機構を
示す図である。
FIG. 5 is a view showing an elevating mechanism and a connecting mechanism of the bogie according to claim 2;

【図6】請求項2記載の台車の昇降機構を示す図であ
る。
FIG. 6 is a view showing a lifting mechanism for a bogie according to claim 2;

【図7】請求項2記載の台車の連結機構を示す図であ
る。
FIG. 7 is a view showing a connecting mechanism of the bogie according to claim 2;

【図8】本発明に使用される牽引車を示す図である。FIG. 8 is a diagram showing a towing vehicle used in the present invention.

【図9】本発明に使用される種々の制御装置を示す図で
ある。
FIG. 9 is a diagram showing various control devices used in the present invention.

【図10】本発明に採用されている信号併送給電方式を
示す概略図である。
FIG. 10 is a schematic diagram showing a signal simultaneous transmission power supply system adopted in the present invention.

【図11】本発明の請求項3記載の装置全体を示す斜視
図である。
FIG. 11 is a perspective view showing the entire apparatus according to claim 3 of the present invention.

【図12】請求項3記載の装置に使用されるマストユニ
ットを示す斜視図である。
FIG. 12 is a perspective view showing a mast unit used in the device according to claim 3;

【図13】請求項3記載の装置に使用されるマストユニ
ットと台車の嵌合部との係合状態を示す図である。
FIG. 13 is a view showing an engagement state of a mast unit used in the device according to claim 3 and a fitting portion of the trolley.

【図14】請求項3記載の装置に使用される台車を示す
斜視図である。
FIG. 14 is a perspective view showing a carriage used for the apparatus according to claim 3;

【図15】請求項3記載の装置におけるマストユニット
と台車の配置関係を示す図である
FIG. 15 is a diagram showing a positional relationship between a mast unit and a carriage in the device according to claim 3;

【図16】請求項3記載の装置における台車移行機構の
走行フレームを示す図である。
FIG. 16 is a diagram showing a traveling frame of the carriage transfer mechanism in the device according to claim 3;

【図17】請求項3記載の装置における走行フレームの
台車との係合前を示す図である。
FIG. 17 is a diagram showing a state in which the traveling frame in the apparatus according to claim 3 is not yet engaged with the carriage.

【図18】請求項3記載の装置における走行フレームの
台車との係合後を示す図である。
FIG. 18 is a diagram showing the traveling frame of the device according to claim 3 after being engaged with the trolley.

【図19】請求項3記載の装置における走行フレームの
第2の実施例を示す図である。
FIG. 19 is a diagram showing a second embodiment of the traveling frame in the device according to claim 3;

【図20】請求項3記載の装置における走行フレームの
第2の実施例が台車と係合する前を示す図である。
FIG. 20 is a view showing the second embodiment of the traveling frame in the device according to claim 3 before being engaged with the carriage.

【図21】請求項3記載の装置における走行フレームの
第2の実施例が台車と係合した後を示す図である。
FIG. 21 is a diagram showing the second embodiment of the traveling frame in the device according to claim 3 after being engaged with the carriage.

【図22】請求項3記載の装置における走行フレームの
第3の実施例を示す図である。
FIG. 22 is a view showing a third embodiment of the traveling frame in the device according to claim 3;

【図23】請求項3記載の装置における走行フレームの
第3の実施例の台車移行動作を示す図である。
FIG. 23 is a diagram showing a trolley transfer operation of the third embodiment of the traveling frame in the apparatus according to claim 3;

【図24】請求項3記載の装置における走行フレームの
第3の実施例の台車移行前の動作を示す図である。
FIG. 24 is a diagram showing an operation of the traveling frame in the device according to the third aspect of the present invention before the bogie shifts to the third embodiment;

【図25】請求項3記載におけるマストユニットの第2
の実施例を示す斜視図である。
FIG. 25 is a second mast unit according to claim 3;
It is a perspective view showing an example of.

【図26】請求項3記載における台車の第2の実施例を
示す斜視図である。
FIG. 26 is a perspective view showing a second embodiment of the bogie according to claim 3;

【図27】請求項3記載における第2の実施例の装置の
昇降路と台車の配置関係を示す図である。
FIG. 27 is a diagram showing an arrangement relationship between a hoistway and a carriage of the device of the second embodiment according to claim 3;

【図28】請求項3記載における第2の実施例の装置の
ガイドレールとガイドローラーとの係合状態を示す図で
ある。
FIG. 28 is a view showing an engaged state of the guide rail and the guide roller of the device of the second embodiment according to claim 3;

【図29】図28におけるBーB矢視断面を示す図であ
る。
29 is a view showing a cross section taken along the line BB in FIG.

【図30】図28におけるCーC矢視断面を示す図であ
る。
30 is a view showing a cross section taken along the line CC of FIG.

【図31】本発明の請求項4記載の装置を示す平面図で
ある。
FIG. 31 is a plan view showing an apparatus according to claim 4 of the present invention.

【図32】本発明の請求項4記載の装置のマストユニッ
トを示す斜視図である。
FIG. 32 is a perspective view showing a mast unit of the device according to claim 4 of the present invention.

【図33】本発明の請求項4記載の装置の台車を示す斜
視図である。
FIG. 33 is a perspective view showing a carriage of the device according to claim 4 of the present invention.

【図34】請求項4記載の装置のストッパー機構が作動
している状態を示す図である。
FIG. 34 is a view showing a state in which the stopper mechanism of the device according to claim 4 is operating.

【図35】請求項4記載の装置のストッパー機構が解除
された状態を示す図である。
FIG. 35 is a view showing a state in which the stopper mechanism of the device according to claim 4 is released.

【図36】請求項4記載の装置の台車が昇降路入口まで
移動してきた状態を示す斜視図である。
FIG. 36 is a perspective view showing a state where the carriage of the device according to claim 4 has moved to the entrance of the hoistway.

【符号の説明】[Explanation of symbols]

1 建築物 2 昇降路 4 レール軌道 5 ラック 6 給電線 8 給電バー 9 昇降路入口 10 フロア表示ラベル 20 台車 21 集電ブラシ 22 近接センサー 24 昇降機構 25 連結機構 30 昇降用ピニオンギア 33 駆動モーター 50 はね橋(台車移行機構) 53 走行部 60 牽引車 70 運転管理装置 73 キーボード(入力手段) 74 ディスプレイ装置(表示手段) F1,F2,… フロア 1 Building 2 Hoistway 4 Rail track 5 Rack 6 Power supply line 8 Power supply bar 9 Hoistway entrance 10 Floor display label 20 Bogie 21 Current collecting brush 22 Proximity sensor 24 Elevating mechanism 25 Coupling mechanism 30 Elevating pinion gear 33 Drive motor 50 Spring bridge (Truck transfer mechanism) 53 Traveling unit 60 Towing vehicle 70 Operation management device 73 Keyboard (input means) 74 Display device (display means) F1, F2, ... Floor

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 超高層建築物を構築する際に、該建築物
を構築するのに必要な資材等を、既に形成されたフロア
上の所定場所に搬送するための建設用資材搬送装置であ
って、 登り専用と下り専用の2系統を有し、各フロアで自重が
支持された複数の昇降ユニットを鉛直方向に連設してな
る昇降路と、 前記昇降路内を昇降し、資材を搭載して所定のフロアま
で搬送する台車と、 各フロアの昇降路入口に配設され、前記昇降路入口に移
動してきた台車をフロア上へ走行可能とさせる台車移行
機構と、を備えた建設用資材搬送装置。
1. A construction material transporting device for transporting materials and the like necessary for constructing a super high-rise building to a predetermined place on an already-formed floor when constructing a super high-rise building. And a hoistway that has two systems, one for climbing and one for descending, in which a plurality of hoisting units, each of which has its own weight supported on each floor, are vertically connected, and hoisting inside the hoistway, and loading materials And a carriage for transporting to a predetermined floor, and a trolley transfer mechanism that is disposed at the hoistway entrance of each floor and that allows the carriage that has moved to the hoistway entrance to travel on the floor Transport device.
【請求項2】 請求項1記載の建設用資材搬送装置にお
いて、 台車及び台車移行機構のそれぞれに対して所定の動作信
号を送出する命令手段と、 命令手段に所定の動作信号を入力する入力手段と、 昇降路内の台車および各フロア上の台車の運行状況さら
には前記台車移行部の動作状況を表示する表示手段と、
を備えた運転管理装置が設けられていることを特徴とす
る建設用資材搬送装置。
2. The construction material conveying apparatus according to claim 1, wherein a command means for sending a predetermined operation signal to each of the carriage and the carriage transfer mechanism, and an input means for inputting a predetermined operation signal to the command means. And display means for displaying the operation status of the carriage in the hoistway and the carriage on each floor, and further the operation status of the carriage transition section,
A construction material transporting apparatus, which is provided with an operation management apparatus provided with.
【請求項3】 請求項1記載の建設資材用搬送装置にお
いて、 昇降ユニットは一対のレール軌道が離間配置されて構成
され、それらレール軌道が鉛直方向に連設されてなる昇
降路内を台車が昇降し、 前記台車には、昇降路の前記レール軌道に連結されるこ
とにより昇降移動が可能となる昇降機構と、該昇降機構
を前記レール軌道に着脱自在に連結させる連結機構とが
具備され、 台車移行機構が、回転動作により各フロアの前記昇降路
内に引き出し若しくは引き込まれ、引き出し動作により
昇降路内を移動してきた台車を自身に載せてフロア上に
走行可能とさせるはね橋により構成されていることを特
徴とする建設資材用搬送装置。
3. The construction material conveying apparatus according to claim 1, wherein the lifting unit is configured by a pair of rail tracks spaced apart from each other, and a carriage is provided in a hoistway formed by vertically connecting the rail tracks. Elevating and lowering, the carriage is provided with an elevating mechanism that can be moved up and down by being connected to the rail track of the hoistway, and a connecting mechanism that detachably connects the elevating mechanism to the rail track, The trolley transfer mechanism is constituted by a fly bridge that allows the trolley to be pulled out or pulled into the hoistway of each floor by a rotating operation, and allows the trolley that has moved in the hoistway by the pulling operation to be placed on itself and run on the floor. A transporting device for construction materials, which is characterized in that
【請求項4】 請求項1記載の建設資材用搬送装置にお
いて、 昇降ユニットは、前後面を登り専用路及び下り専用路と
し、登り専用路から下り専用路にわたって上下方向に巻
装された駆動チェーンと、登り専用路及び下り専用路の
それぞれの上下方向に配設されたガイドレール若しくは
ガイドローラとを具備したマストユニットにより構成さ
れ、 台車には、前記ガイドレール若しくはガイドローラと摺
動自在に係合して台車を前記マストユニットに沿わせる
ガイドローラー若しくはガイドレールと、前記駆動チェ
ーンに着脱自在に嵌合する嵌合部と、台車がフロア側へ
移行する際に台車移行機構上を転動する台車水平移行用
ローラーとが具備され、 前記台車移行機構が、水平移動により各フロアの昇降路
内に引き出し若しくは引き込まれ、引き出し動作により
昇降路を移動してきた台車の前記ガイドローラー及び前
記台車移行用ローラーを転動させて台車をフロア上に走
行可能とさせる移行フレームにより構成されていること
を特徴とする建設資材用搬送装置。
4. The construction material transporting apparatus according to claim 1, wherein the lifting unit has a front and rear surface as a climbing-only path and a descending-only path, and a drive chain wound in a vertical direction from the climbing-only path to the descending-only path. And a guide rail or guide roller provided in the vertical direction of each of the ascending-only road and the descending-only road, and the carriage is slidably engaged with the guide rail or the guide roller. A guide roller or a guide rail that fits the bogie along the mast unit, a fitting portion that is detachably fitted to the drive chain, and rolls on the bogie transfer mechanism when the bogie moves to the floor side. A carriage horizontal transfer roller, wherein the carriage transfer mechanism is horizontally moved to pull out or pull in the hoistway of each floor, For construction materials, characterized by comprising a transition frame that rolls the guide roller and the trolley transition roller of the trolley that has moved in the hoistway by the feeding operation to enable the trolley to travel on the floor Transport device.
【請求項5】 請求項1記載の建設資材用搬送装置にお
いて、 昇降ユニットは、3基のマストユニットを離間配置し、
それらマストユニット間を登り専用路及び下り専用路と
し、各マストユニットに、複数枚の昇降板が突設された
上下方向に回動する駆動ベルトを配設した構成とされ、 台車には、所定の昇降板との係合により台車の昇降が可
能とされる係合板と、前記係合板の下面に設けられて台
車がフロア側へ移行する際に昇降板上を転動する台車移
行用ローラーとが具備されているとともに、 前記係合板には、該係合板と前記昇降板との係合状態を
保持するストッパー機構が設けられており、該ストッパ
ー機構が係合状態を解除することにより台車移行機構と
して作用することを特徴とする建設資材用搬送装置。
5. The construction material carrying device according to claim 1, wherein the lifting unit has three mast units spaced apart from each other,
The mast units are designated as an ascending-only path and a descending-only path, and each mast unit is provided with a vertically rotating drive belt with a plurality of lifting plates protruding from it. An engaging plate that allows the carriage to be lifted and lowered by engaging with the lifting plate, and a carriage transfer roller that is provided on the lower surface of the engaging plate and rolls on the lifting plate when the carriage moves to the floor side. And a stopper mechanism for holding the engagement state between the engagement plate and the elevating plate is provided on the engagement plate, and the trolley transitions by releasing the engagement state of the stopper mechanism. A construction material carrying device characterized by acting as a mechanism.
JP15701392A 1992-06-16 1992-06-16 Construction material conveyor device Pending JPH05346068A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15701392A JPH05346068A (en) 1992-06-16 1992-06-16 Construction material conveyor device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15701392A JPH05346068A (en) 1992-06-16 1992-06-16 Construction material conveyor device

Publications (1)

Publication Number Publication Date
JPH05346068A true JPH05346068A (en) 1993-12-27

Family

ID=15640276

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15701392A Pending JPH05346068A (en) 1992-06-16 1992-06-16 Construction material conveyor device

Country Status (1)

Country Link
JP (1) JPH05346068A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040007912A (en) * 2002-07-11 2004-01-28 최윤수 form omitted
KR100942560B1 (en) * 2009-05-04 2010-02-12 김관정 Elevator with cage operated by power source loaded on it
JP2010236293A (en) * 2009-03-31 2010-10-21 Sankyo Tateyama Aluminium Inc Mounting method and moving method for exterior wall panel
JP4796198B1 (en) * 2010-07-26 2011-10-19 株式会社川瀬工務店 Work scaffold equipment
CN105133836A (en) * 2015-07-31 2015-12-09 中建安装工程有限公司 Gravity type speed-limiting down-sliding material transferring method and apparatus
EP3077314A4 (en) * 2013-12-05 2018-04-04 Otis Elevator Company Ropeless high-rise elevator installation approach
KR20180053047A (en) * 2016-11-11 2018-05-21 유장욱 Circulation type elevator system
FR3123336A1 (en) * 2021-05-31 2022-12-02 Fives Syleps CLIMBING DEVICE FOR AUTOMATED ARTICLES STORAGE SYSTEM

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040007912A (en) * 2002-07-11 2004-01-28 최윤수 form omitted
JP2010236293A (en) * 2009-03-31 2010-10-21 Sankyo Tateyama Aluminium Inc Mounting method and moving method for exterior wall panel
KR100942560B1 (en) * 2009-05-04 2010-02-12 김관정 Elevator with cage operated by power source loaded on it
JP4796198B1 (en) * 2010-07-26 2011-10-19 株式会社川瀬工務店 Work scaffold equipment
EP3077314A4 (en) * 2013-12-05 2018-04-04 Otis Elevator Company Ropeless high-rise elevator installation approach
CN105133836A (en) * 2015-07-31 2015-12-09 中建安装工程有限公司 Gravity type speed-limiting down-sliding material transferring method and apparatus
CN105133836B (en) * 2015-07-31 2024-01-30 中建安装集团有限公司 Gravity type speed-limiting sliding material transferring method and device
KR20180053047A (en) * 2016-11-11 2018-05-21 유장욱 Circulation type elevator system
FR3123336A1 (en) * 2021-05-31 2022-12-02 Fives Syleps CLIMBING DEVICE FOR AUTOMATED ARTICLES STORAGE SYSTEM
WO2022253812A1 (en) * 2021-05-31 2022-12-08 Fives Syleps Climbing device for an automated article storage system

Similar Documents

Publication Publication Date Title
WO1992010629A1 (en) Driving mechanism of motor vehicle conveying truck for multistory parking system
JPH05346068A (en) Construction material conveyor device
CN218744825U (en) Iron liquid package overline conveying system
JP2007126835A (en) Mechanical multistory parking device
JPH10339049A (en) Multi-storied automatic parking device
JP3428887B2 (en) Article storage facility
JPH08157192A (en) Forklift type carriage to transfer cargo inside and outside of elevator
CN213676631U (en) Carry car platform convenient to access car
JP3017704B2 (en) Parking device and control method thereof
JP2545270B2 (en) Hawk-type storage cart drive
CN219279180U (en) Material lifting machine encoder mounting structure and flat layer control system
CN114601638B (en) Remains receiving and transporting device and receiving and transporting method
JP2004263443A (en) Elevator type parking equipment
JP2001065185A (en) Mechanical parking equipment
JP2673282B2 (en) Elevator parking system
JP4791719B2 (en) Gas cylinder changer
JPH06211314A (en) Take-in and out device with cab
JP2838078B2 (en) Multi-level parking device
JPH07157073A (en) Conveying facility
JP2899546B2 (en) Storage system
JPH0467551B2 (en)
JP4369823B2 (en) Elevator parking system
JP3468342B2 (en) Article storage facility
JP3037643B2 (en) Parking equipment