JPH05321257A - Method and structure for timbering of underground continuous wall - Google Patents

Method and structure for timbering of underground continuous wall

Info

Publication number
JPH05321257A
JPH05321257A JP15015092A JP15015092A JPH05321257A JP H05321257 A JPH05321257 A JP H05321257A JP 15015092 A JP15015092 A JP 15015092A JP 15015092 A JP15015092 A JP 15015092A JP H05321257 A JPH05321257 A JP H05321257A
Authority
JP
Japan
Prior art keywords
anchor
continuous wall
underground continuous
hole
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15015092A
Other languages
Japanese (ja)
Other versions
JP2992914B2 (en
Inventor
Kunito Sakai
邦登 酒井
Shigehiko Shibusawa
重彦 渋沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP4150150A priority Critical patent/JP2992914B2/en
Publication of JPH05321257A publication Critical patent/JPH05321257A/en
Application granted granted Critical
Publication of JP2992914B2 publication Critical patent/JP2992914B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To establish easiness in installing an anchor and enhance the working effectiveness. CONSTITUTION:In constructing a timbering for an underground continuous wall using anchor, a through hole 5 is provided penetrating the wall from its excavation side face to sheathing side face. Through this through hole, anchor 3 is installed to the back ground of this underground wall, and pressure supporting plates 1 are installed around the excavation side face of the through hole. An anchor pedestal 2 is installed which is fixed with the pressure supporting plates pinched between the underground walls. The head of the anchor is allowed to penetrate this anchor pedestal, is tightened, and secured to the pedestal surface.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、土留めアンカ−を用い
た地下連続壁の支保工法及び支保構造に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a supporting method for a continuous underground wall and a supporting structure using earth retaining anchors.

【0002】[0002]

【従来の技術】土留め用の地下連続壁工法において、鋼
製の連続壁体を用いてこれを行う場合がある。この鋼製
地下連続壁工法の支保工としてはアンカ−が多用されて
いるが、アンカ−の施工は従来以下のようになされてい
た。地盤を掘削して溝を形成し、この溝内に鋼製地下連
続壁(以下『連続壁』という)を建込む。建込んだ連続
壁の一方の側部を掘削して行き、ある程度掘削したとこ
ろで連続壁にアンカーを打設する。打設したアンカーを
緊張してアンカー頭部を定着する際に、アンカー頭部と
壁面との間に腹起しを設置し、連続壁背面の地盤の土圧
により生ずる押抜き剪断力を腹起しで分散させて、壁体
を支保する。そして、連続壁側方をさらに掘削して上記
作業を繰り返し、所定深度まで施工する。
2. Description of the Related Art In an underground continuous wall construction method for retaining soil, a continuous wall body made of steel may be used. Although anchors are often used as support works for this steel underground continuous wall construction method, the anchors have been conventionally constructed as follows. The ground is excavated to form a groove, and a steel underground continuous wall (hereinafter referred to as "continuous wall") is built in this groove. One side of the built continuous wall is excavated, and after excavating to some extent, an anchor is placed on the continuous wall. When tensioning the placed anchor to fix the anchor head, install a bulge between the anchor head and the wall surface to pierce the punching shear force generated by the earth pressure of the ground behind the continuous wall. Disperse with a brush to support the wall. Then, the side wall of the continuous wall is further excavated, the above-mentioned work is repeated, and the work is carried out to a predetermined depth.

【0003】[0003]

【発明が解決しようとする問題点】上記の従来技術に
は、次のような問題点が存在する。 <イ>腹起し材として用いられるH鋼は重量があり、複
数のアンカーを同時に支保する様に横長状に設置する必
要があり、その設置作業は非常に困難である。
Problems to be Solved by the Invention The above-mentioned conventional techniques have the following problems. <A> The H steel used as a waving material is heavy and needs to be installed in a horizontally long shape so as to simultaneously support a plurality of anchors, and the installation work is extremely difficult.

【0004】<ロ>H鋼を設置するためには、余掘り量
を多くとる必要があり、設置作業の効率が損なわれる。
<B> In order to install H steel, it is necessary to take a large amount of excess digging, which impairs the efficiency of installation work.

【0005】[0005]

【本発明の目的】本発明は、以上のような問題点を解決
するために成されたもので、その目的は、アンカーの設
置作業性に優れ、作業効率が向上する地下連続壁の支保
工法及び支保構造を提供する事である。
SUMMARY OF THE INVENTION The present invention has been made to solve the above problems, and an object thereof is a method of supporting a continuous underground wall, which has excellent workability for installing anchors and improves work efficiency. And to provide a support structure.

【0006】[0006]

【問題点を解決するための手段】本発明は、地下連続壁
をアンカーにより支保する工法において、地下連続壁の
掘削側面から土留め側面に貫通する孔を設け、この貫通
孔を介して地下連続壁の背面地盤にアンカーを設置し、
貫通孔の掘削側面の周囲に支圧板を取り付け、さらに地
下連続壁面との間に支圧板を挟んで取り付けたアンカー
台座を取り付け、このアンカー台座にアンカー頭部を貫
通させて緊張した後、アンカー頭部を台座面に定着する
ことを特徴とする、地下連続壁の支保工法である。更に
本発明は、地下連続壁の掘削側面から土留め側面に貫通
する貫通孔内を介して、地下連続壁の背面地盤に打設す
るアンカーと、前記貫通孔の掘削側面の周囲に配置した
支圧板と、地下連続壁面との間に前記支圧板を挟んで取
り付けたアンカー台座と、緊張したアンカーの頭部を台
座面に定着する定着具とにより構成する、地下連続壁の
支保構造である。
[Means for Solving the Problems] The present invention relates to a construction method for supporting an underground continuous wall by an anchor, in which a hole penetrating from the excavation side of the underground continuous wall to the earth retaining side is provided, and the underground continuation is performed through this through hole. Install an anchor on the back ground of the wall,
Attach a bearing plate around the excavated side surface of the through hole, and further attach an anchor pedestal with the bearing plate sandwiched between the underground wall and the anchor head after passing through the anchor head and tightening it. This is a method of supporting the continuous underground wall, characterized by fixing the part to the pedestal surface. Furthermore, the present invention provides an anchor that is placed on the back ground of the underground continuous wall through a through hole that penetrates from the excavation side surface of the underground continuous wall to the earth retaining side surface, and a support arranged around the excavation side surface of the through hole. A support structure for an underground continuous wall, which is composed of a pressure plate and an anchor pedestal attached between the pressure wall and an underground continuous wall by sandwiching the pressure bearing plate, and a fixing tool for fixing the tensioned head of the anchor to the pedestal surface.

【0007】[0007]

【実施例】以下、図面を参照しながら、本発明について
説明する。 <イ>地下連続壁の支保構造 地盤7に掘削して形成した溝内に地下連続壁4を建込
み、前記地下連続壁4の側方を掘削すると共に、地下連
続壁4に設置される貫通孔5を介してアンカー3を地下
連続壁4背面地盤に打設する。そして本発明は、図1及
び図2に示す様に地下連続壁4から突出した前記アンカ
ー3の頭部に支持板1、アンカー台座2及び定着具6を
挿入して装着し、緊張させたアンカー3を定着させて、
地下連続壁4を支保する支保構造である。以下詳述す
る。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the drawings. <B> Supporting structure of underground continuous wall The underground continuous wall 4 is built in the groove formed by excavating in the ground 7, the side of the underground continuous wall 4 is excavated, and the penetration is installed in the underground continuous wall 4. Anchor 3 is placed through the hole 5 on the back ground of the underground continuous wall 4. And the present invention, as shown in FIG. 1 and FIG. 2, is a tensioned anchor in which the support plate 1, the anchor pedestal 2 and the fixing tool 6 are inserted into the head of the anchor 3 protruding from the underground continuous wall 4 and attached. Fix 3
It is a support structure that supports the continuous underground wall 4. This will be described in detail below.

【0008】<ロ>支圧板 支圧板1は、矩形の板体であり、その中央部に前記貫通
孔5とほぼ同じ大きさで円形のアンカー孔が開設されて
いる。支圧板1は、後述するアンカー台座2から受ける
押抜き剪断力を分散して地下連続壁4に伝達する部位で
ある。支圧板1の板面積及び板厚は、前記押抜き剪断力
に十分耐え得るように設定されている。本実施例の支圧
板1の形状は矩形であるが円形または多角形等であって
もよく、支圧板1に開設されるアンカー孔も円形以外の
形状でも採用できる。
<B> Pressure Bearing Plate The pressure bearing plate 1 is a rectangular plate body, and a circular anchor hole having substantially the same size as the through hole 5 is formed in the center thereof. The pressure bearing plate 1 is a part that disperses a punching shearing force received from an anchor pedestal 2 to be described later and transmits it to the underground continuous wall 4. The plate area and plate thickness of the pressure bearing plate 1 are set so as to sufficiently withstand the punching shearing force. The bearing plate 1 of this embodiment has a rectangular shape, but may have a circular shape or a polygonal shape, and the anchor holes formed in the bearing plate 1 may have a shape other than a circular shape.

【0009】<ハ>アンカー台座 アンカー台座2は、内部が中空で、背部に支圧板1の孔
に嵌合する円柱形の突起部21を有し、前部上方に定着
面22を有し、前記定着面22に孔23を開設した部材
である。アンカー台座2は、緊張したアンカー3の引張
り力を支圧板1に伝達する部位である。また、前記突起
部21は支圧板1の孔及び地下連続壁4の貫通孔5に嵌
合する様に成されているので、アンカー台座2を設置す
る際支圧板1のアンカー孔及び地下連続壁4の貫通孔5
がソケットの役割を果たし、非常に作業性がよい。本実
施例のアンカー台座2は、内部が中空であるが、定着面
22から突起部21までアンカー3が貫通できるもので
あれば、内部が中空でないものでもよい。定着面22
は、打設するアンカー3に直交するように設定される。
また、図3に示すように、定着面22を湾曲形に形成
し、円錐状の可変支持具7をその定着面22に摺動可能
に嵌合するよう構成する。このように構成することによ
って、アンカー3の打設角度を調整できる。
<C> Anchor pedestal The anchor pedestal 2 has a hollow interior, a cylindrical projection 21 that fits into the hole of the pressure bearing plate 1 in the back, and a fixing surface 22 above the front, It is a member having holes 23 formed in the fixing surface 22. The anchor pedestal 2 is a part that transmits the tensile force of the tensioned anchor 3 to the bearing plate 1. Further, since the protrusion 21 is configured to fit into the hole of the bearing plate 1 and the through hole 5 of the underground continuous wall 4, when the anchor pedestal 2 is installed, the anchor hole of the bearing plate 1 and the underground continuous wall are installed. 4 through holes 5
Plays the role of a socket and has very good workability. Although the anchor pedestal 2 of the present embodiment has a hollow interior, the anchor pedestal 2 may not have a hollow interior as long as the anchor 3 can penetrate from the fixing surface 22 to the protrusion 21. Fixing surface 22
Is set to be orthogonal to the anchor 3 to be placed.
Further, as shown in FIG. 3, the fixing surface 22 is formed in a curved shape, and the variable support 7 having a conical shape is slidably fitted to the fixing surface 22. With this configuration, the driving angle of the anchor 3 can be adjusted.

【0010】<ニ>定着具 定着具6は、アンカー3の頭部を定着面22に定着する
部位であり、ネジ及びくさび等の公知の手段で採用でき
る。
<D> Fixing Tool The fixing tool 6 is a portion for fixing the head of the anchor 3 to the fixing surface 22, and can be adopted by a known means such as a screw or a wedge.

【0011】<ホ>地下連続壁 地下連続壁4は、連結継手を有する角型鋼管からなる鋼
製の連続壁体である。地下連続壁4には、掘削側面から
土留め側面に貫通する貫通孔5が一定間隔で設置されて
いる。前記貫通孔5は、地下連続壁4内に埋設され、中
空部を有する円筒形部材であり、例えばスリーブ管等が
採用される。貫通孔5は、地下連続壁4にアンカー3を
貫通させる為の部位であり、アンカー3の打設角度に合
わせ傾斜させて設置する。
<E> Underground continuous wall The underground continuous wall 4 is a continuous wall made of steel made of a square steel pipe having a connecting joint. The underground continuous wall 4 is provided with through holes 5 penetrating from the excavation side surface to the earth retaining side surface at regular intervals. The through hole 5 is a cylindrical member that is embedded in the underground continuous wall 4 and has a hollow portion, and for example, a sleeve pipe or the like is adopted. The through hole 5 is a portion for penetrating the anchor 3 through the underground continuous wall 4, and is installed so as to be inclined according to the driving angle of the anchor 3.

【0012】<ヘ>アンカー アンカー3は、貫通孔5に挿入し、グラウトにより地下
連続壁4の背面地盤7に定着された後、支圧板1、アン
カー台座2及び定着具6により頭部を定着され、地下連
続壁4を支保する部材である。本実施例のアンカー3は
公知のアンカーを採用できる。
<F> Anchor The anchor 3 is inserted into the through hole 5 and fixed to the back ground 7 of the continuous underground wall 4 by the grout, and then the head is fixed by the bearing plate 1, the anchor pedestal 2 and the fixing tool 6. It is a member that supports the continuous underground wall 4. As the anchor 3 of this embodiment, a known anchor can be adopted.

【0013】[0013]

【施工方法】次に本発明に係る地下連続壁の支保工法の
設置工程について説明する。 <イ>地下連続壁の建込み 掘削した地盤7の溝内に地下連続壁4を建込む。建込ん
だ地下連続壁4の地盤7の側方を掘削する。また、地下
連続壁4の中空の内部にグラウトを注入すれば、地下連
続壁4の剛性を向上する事ができる。
[Construction method] Next, the installation process of the method of supporting the continuous underground wall according to the present invention will be described. <A> Construction of underground continuous wall The underground continuous wall 4 is built in the trench of the excavated ground 7. The side of the ground 7 of the built underground continuous wall 4 is excavated. If the grout is injected into the hollow inside of the underground continuous wall 4, the rigidity of the underground continuous wall 4 can be improved.

【0014】<ロ>アンカー打設 ある程度地盤7を掘削した後、アンカー3の打設を行
う。地下連続壁4には、予め貫通孔5が埋設されている
ので、アンカー3打設用の孔を別途に削孔する必要な
い。貫通孔5から掘削装置を挿入して地盤7にアンカー
3打設用の孔を削孔する。そして前記孔にアンカー3を
奥まで挿入し、グラウトを注入する。
<B> Anchor placement After excavating the ground 7 to some extent, the anchor 3 is placed. Since the through hole 5 is embedded in the underground continuous wall 4 in advance, it is not necessary to separately drill a hole for placing the anchor 3. A drilling device is inserted from the through hole 5 to drill a hole for placing the anchor 3 in the ground 7. Then, the anchor 3 is inserted all the way into the hole, and grout is injected.

【0015】<ハ>アンカー定着 グラウトが硬化した後、アンカー3頭部に支圧板1のア
ンカー孔を貫通させて、支圧板1を設置する。次にアン
カー台座2を突起部21側からアンカー3頭部に貫通さ
せて装着する。 このとき、地下連続壁4の貫通孔5及
び支圧板1のアンカー孔がアンカー台座2の突起部21
に調度嵌合するように形成しているので、地下連続壁4
の貫通孔5及び支圧板1のアンカー孔がアンカー台座2
のソケットの役割を果たし、設置作業性が非常によい。
また、支圧板1及びアンカー台座2は比較的軽量である
ので装着作業が容易に行える。アンカー3に緊張を与え
る。そして定着具6でアンカー3頭部を定着する。その
他のアンカー定着が終了したら、さらに地盤7を掘削
し、所定深度に達するまで上記工程を順次繰り返す。
<C> Anchor fixing After the grout is hardened, the pressure bearing plate 1 is installed by penetrating the anchor holes of the pressure bearing plate 1 through the heads of the anchors 3. Next, the anchor pedestal 2 is attached by penetrating the head of the anchor 3 from the protrusion 21 side. At this time, the through hole 5 of the underground continuous wall 4 and the anchor hole of the bearing plate 1 are the protrusions 21 of the anchor base 2.
Since it is formed so as to be fitted to the
Through hole 5 and the anchor hole of bearing plate 1 are anchor pedestal 2
It plays the role of a socket and has very good installation workability.
Further, since the bearing plate 1 and the anchor pedestal 2 are relatively lightweight, the mounting work can be easily performed. Tension the anchor 3. Then, the fixing tool 6 fixes the head of the anchor 3. When other anchor fixing is completed, the ground 7 is further excavated, and the above steps are sequentially repeated until a predetermined depth is reached.

【0016】[0016]

【本発明の効果】本発明は以上説明したようになるた
め、次のような効果を得ることができる。 <イ>従来の様に重量のある腹起しを使用せず、支圧板
によりアンカー単位で土圧作用時の押抜き剪断力を分散
させることができる。また、支圧板は小型でありなが
ら、十分な面積により押抜き剪断力に耐える事ができ
る。
Since the present invention is as described above, the following effects can be obtained. <B> Unlike the conventional method, it is possible to disperse the punching shearing force at the time of earth pressure action in anchor units by using the pressure bearing plate without using a heavy uprising. Further, the pressure bearing plate is small in size, but has a sufficient area to withstand the punching shearing force.

【0017】<ロ>支圧板は小型、軽量であるので、ア
ンカー頭部の支圧板及びアンカー台座等の定着部設置作
業が容易に行える。
<B> Since the pressure bearing plate is small and lightweight, the work of installing the fixing portion such as the pressure bearing plate of the anchor head and the anchor pedestal can be easily performed.

【0018】<ハ>従来のH鋼に比べ支圧板は、あまり
設置場所を取らないので、使用できる空間が広がり、用
地を有効利用できる。
<C> Compared with the conventional H steel, the bearing plate does not occupy much space, so the usable space is expanded and the site can be effectively used.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明による地下連続壁の支保状態を示す斜視
FIG. 1 is a perspective view showing a supporting state of an underground continuous wall according to the present invention.

【図2】本発明の地下連続壁における支保構造を示す斜
視図
FIG. 2 is a perspective view showing a support structure for an underground continuous wall of the present invention.

【図3】本発明の地下連続壁における支保構造を示す斜
視図
FIG. 3 is a perspective view showing a support structure for an underground continuous wall of the present invention.

【図4】従来の地下連続壁の支保状態を示す斜視図FIG. 4 is a perspective view showing a conventional supporting state of an underground continuous wall.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】地下連続壁をアンカーにより支保する工法
において、 地下連続壁の掘削側面から土留め側面に貫通する孔を設
け、 この貫通孔を介して地下連続壁の背面地盤にアンカーを
設置し、 貫通孔の掘削側面の周囲に支圧板を取り付け、 さらに地下連続壁面との間に支圧板を挟んで取り付けた
アンカー台座を取り付け、 このアンカー台座にアンカー頭部を貫通させて緊張した
後、 アンカー頭部を台座面に定着することを特徴とする、 地下連続壁の支保工法。
1. A method of supporting an underground continuous wall with an anchor, wherein a hole is provided through the excavation side of the underground continuous wall to the earth retaining side, and the anchor is installed on the back ground of the underground continuous wall through this through hole. A pressure plate is attached around the excavated side surface of the through hole, and an anchor pedestal is attached with the pressure plate sandwiched between the underground wall and the anchor head. A method of supporting underground continuous walls, characterized by fixing the head to the pedestal surface.
【請求項2】地下連続壁の掘削側面から土留め側面に貫
通する貫通孔内を介して、地下連続壁の背面地盤に打設
するアンカーと、 前記貫通孔の掘削側面の周囲に配置した支圧板と、 地下連続壁面との間に前記支圧板を挟んで取り付けたア
ンカー台座と、 緊張したアンカーの頭部を台座面に定着する定着具とに
より構成する、 地下連続壁の支保構造。
2. An anchor that is placed on the back ground of the underground continuous wall through a through hole that penetrates from the excavation side surface of the underground continuous wall to the earth retaining side surface, and a support arranged around the excavation side surface of the through hole. A support structure for an underground continuous wall, which is composed of a pressure plate and an anchor pedestal mounted with the pressure bearing plate sandwiched between the underground continuous wall surface and a fixing device for fixing the tensioned anchor head to the pedestal surface.
JP4150150A 1992-05-19 1992-05-19 Support method and support structure for steel underground continuous wall Expired - Lifetime JP2992914B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4150150A JP2992914B2 (en) 1992-05-19 1992-05-19 Support method and support structure for steel underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4150150A JP2992914B2 (en) 1992-05-19 1992-05-19 Support method and support structure for steel underground continuous wall

Publications (2)

Publication Number Publication Date
JPH05321257A true JPH05321257A (en) 1993-12-07
JP2992914B2 JP2992914B2 (en) 1999-12-20

Family

ID=15490594

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4150150A Expired - Lifetime JP2992914B2 (en) 1992-05-19 1992-05-19 Support method and support structure for steel underground continuous wall

Country Status (1)

Country Link
JP (1) JP2992914B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07166546A (en) * 1993-12-15 1995-06-27 Kajima Corp Soldier beam lock anchor type earth retaining soldier beam
JP2008255615A (en) * 2007-04-03 2008-10-23 Ohbayashi Corp Head anchoring structure of anchor, head anchoring method of anchor and injection method of grout material
KR100907904B1 (en) * 2009-03-05 2009-07-16 이석용 Movable Temporary Temper Structure
CN107882040A (en) * 2017-11-23 2018-04-06 北京地矿工程建设有限责任公司 A kind of construction method of foundation ditch prestress anchorage cable
CN113882389A (en) * 2021-09-03 2022-01-04 武汉中科岩土工程有限责任公司 Deep foundation pit supporting structure and construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442427A (en) * 2018-05-02 2018-08-24 中国十七冶集团有限公司 A kind of bracing means for preventing diaphram wall from settling

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07166546A (en) * 1993-12-15 1995-06-27 Kajima Corp Soldier beam lock anchor type earth retaining soldier beam
JP2008255615A (en) * 2007-04-03 2008-10-23 Ohbayashi Corp Head anchoring structure of anchor, head anchoring method of anchor and injection method of grout material
KR100907904B1 (en) * 2009-03-05 2009-07-16 이석용 Movable Temporary Temper Structure
CN107882040A (en) * 2017-11-23 2018-04-06 北京地矿工程建设有限责任公司 A kind of construction method of foundation ditch prestress anchorage cable
CN113882389A (en) * 2021-09-03 2022-01-04 武汉中科岩土工程有限责任公司 Deep foundation pit supporting structure and construction method thereof

Also Published As

Publication number Publication date
JP2992914B2 (en) 1999-12-20

Similar Documents

Publication Publication Date Title
KR101766166B1 (en) PHC pile construction method using removeable auxiliary pile
KR20120046666A (en) Base construct method of building and base construct member of building
KR100992942B1 (en) Multipurpose earth anchor bracket
JP3705903B2 (en) Earth anchor combined earth retaining structure
KR101494132B1 (en) Self reliance type sheathing structure
JP2007177517A (en) Earth anchor method
JPH05321257A (en) Method and structure for timbering of underground continuous wall
KR101633289B1 (en) Head anchor device of micro pile and reinforced method of foundation concrete using the same
KR100773920B1 (en) Pre-tention soil nailing system and method for reinforcing inclined earth using the same
JP3534928B2 (en) Construction method of seismic isolation pit for existing building
JP2007247308A (en) Pulling-out bearing strength reinforcing for pile group comprised of inclined piles and structure constructed according to the same
KR101662694B1 (en) Construction Method for PHC Pile by Inner Excavation
JP7136597B2 (en) reinforcement anchor
KR20130038461A (en) Variable supporting device for sheathing work pile
KR101623342B1 (en) Earth retaining structure utilizing in-situ soil and earth retaining structure construction Method
KR100989023B1 (en) Supporting apparatus having in between two belts and constructing method thereof
JP2992915B2 (en) Supporting method for underground continuous wall
JP3782180B2 (en) Support structure using sheet piles for earth retaining bells
JPH0119045Y2 (en)
JP2001182026A (en) Enclosure for safety
JPH06173284A (en) Construction method for self-standing continuous wall
KR100901437B1 (en) Supporting apparatus having in between two belts and constructing method thereof
KR20230063107A (en) Earth retaining wall without wale and construction method thereof
JP2893422B2 (en) Construction method of underground structure
JP2992913B2 (en) Support method for steel underground continuous wall

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 8

Free format text: PAYMENT UNTIL: 20071022

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081022

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20091022

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20101022

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101022

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 12

Free format text: PAYMENT UNTIL: 20111022

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111022

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20121022

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20121022