JPH0468167A - Building method - Google Patents

Building method

Info

Publication number
JPH0468167A
JPH0468167A JP17780290A JP17780290A JPH0468167A JP H0468167 A JPH0468167 A JP H0468167A JP 17780290 A JP17780290 A JP 17780290A JP 17780290 A JP17780290 A JP 17780290A JP H0468167 A JPH0468167 A JP H0468167A
Authority
JP
Japan
Prior art keywords
wire
girder
load
building
structural steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP17780290A
Other languages
Japanese (ja)
Other versions
JP2916585B2 (en
Inventor
Makio Yoshihara
吉原 牧夫
Katsuyuki Mitani
三谷 勝之
Akemasa Miyauchi
宮内 明正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP17780290A priority Critical patent/JP2916585B2/en
Publication of JPH0468167A publication Critical patent/JPH0468167A/en
Application granted granted Critical
Publication of JP2916585B2 publication Critical patent/JP2916585B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To promote workability by building a girder between columns in a state to warp the central part of the girder upward, tensing a wire interlocked with the center thereof, and assembling the remains of building members on the girder after a downward load is applied to the wire to make the girder approximately horizontal. CONSTITUTION:A structural steel 15 is assembled on the floor of a large space 20 so that the central part 15a of the structural steel is displaced upward by having a curve therein, and the structural steel 15 is lifted to build it between columns 18. After that,hydraulic jacks 40 are operated, the top of a wire 41 is pushed up to tense, and a downward antecedent load is applied to the structural steel 15 to reduce warp. Then, vertical members 13, diagonal members 14 and upper chords 12 are mounted to the structural steel 15 to form a truss. After reinforcing bars are placed to the outside of the structural steel 15 to assemble a form, concrete is placed to form lower chords, and a girder is constructed. In addition, after the antecedent load is applied to the girder through the wire 41, a skeleton of an upper floor is executed on the upper part of the girder and, at the same time, building members are mounted, and the wire 41 is gradually loosened to reduce the antecedent load.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、長大スパンの梁を有し、その梁に各種建築部
材の荷重が負荷される形態の建築物の施工方法に関する
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a method of constructing a building having a long span beam, on which the loads of various building members are applied.

「従来の技術」 近年、建築物の構造形式として、いわゆるメガストラク
チコア(巨大架構)と称するものが検討されている。第
21図はメガストラクチュアが採用された建築物の一例
を示すもので、4本の鉄骨造の柱1と、それらの上端間
に架設された鉄骨造のトラス梁2とによって巨大な門型
フレームであるメガストラクチュアを構成し、そのメガ
ストラクチュアの上部に、通常の柱3、梁4によって上
層階の躯体を構築した形態のものであって、メガストラ
クチュアの下部にたとえば自由度の高い大空間を得るよ
うになしたものである。
"Prior Art" In recent years, a so-called megastructural structure (huge frame) has been studied as a structural form of buildings. Figure 21 shows an example of a building in which megastructure has been adopted.A huge gate-shaped frame is constructed by four steel-framed columns 1 and a steel-framed truss beam 2 installed between their upper ends. It consists of a megastructure, and on the top of the megastructure, the frame of the upper floor is constructed using ordinary columns 3 and beams 4, and the lower part of the megastructure has a large space with a high degree of freedom, for example. I did it so that I could get it.

この第21図に示す建築物にあっては、メガストラクチ
ュアを構成しているトラス梁2のスパンは数十メートル
にも及ぶ長大なものとされ、その梁成は数メートルにも
及ぶものとされている。そして、このような建築物を施
工するに当たっては、トラス梁2に予め上方に反るよう
なむくりをつけておき、施工途中段階においては、トラ
ス梁2の両端部に設置したジヤツキによって山形に張っ
たワイヤ5を緊張することにより、トラス梁2の中央部
に下向きの先行荷重を加えてトラス梁2がほぼ水平とな
るように変形させておくようにしている。そして、上層
階の施工が進むにつれてワイヤを緩めていって先行荷重
を低減させていき、上層階が完成した時点でトラス梁2
が自ずと水平となるようにしている。
In the building shown in Figure 21, the span of the truss beams 2 that make up the megastructure is long, reaching several tens of meters, and the beam length is said to be several meters. ing. When constructing such a building, the truss beam 2 is curved upward in advance, and during construction, the truss beam 2 is stretched into a chevron shape using jacks installed at both ends. By tensioning the wire 5, a downward preliminary load is applied to the center of the truss beam 2, so that the truss beam 2 is deformed to become approximately horizontal. Then, as the construction of the upper floor progresses, the wires are loosened to reduce the preceding load, and when the upper floor is completed, the truss beam 2
is naturally level.

「発明が解決しようとする課題」 ところで、上記の建築物を施工するに際しては、第21
図に示されているように、トラス梁2に対する先行荷重
をそのトラス梁2の中央に位置して立設される柱3を介
して加えるようにしており、このため、先行荷重を加え
てむくりを解消させるに先立ってトラス梁2の上部に3
層分の躯体を施工するようにしていたが、むくりの付い
たままのトラス梁2の上部において躯体の施工を行うこ
とは、中央に位置するもの以外の柱3が外側に傾いてし
まうことになるので、その施工が極めて困難であった。
"Problem to be solved by the invention" By the way, when constructing the above building, the 21st
As shown in the figure, the preload to the truss beam 2 is applied via the column 3 located at the center of the truss beam 2. 3 on the top of the truss beam 2 before removing the hollow.
We were trying to construct the frame for each layer, but constructing the frame at the top of the truss beam 2, which is still exposed, would cause the columns 3 other than the one located in the center to tilt outward. Therefore, its construction was extremely difficult.

また、先行荷重を加えた後は、ワイヤ5が邪魔になって
外壁等の取りイ」け作業に支障をきたし、工期が長弓1
いてしまう、という不具合もあった。
In addition, after applying the preliminary load, the wire 5 gets in the way and interferes with the removal work of the outer wall, etc., and the construction period is reduced to 1.
There was also the problem that it would get stuck.

本発明は上記の事情に鑑みてなされたもので、長大スパ
ンの梁を有する建築物を構築するために採用して好適な
施工方法を提供することを目的としている。
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a construction method suitable for use in constructing buildings having long span beams.

「課題を解決するための手段」 本発明は、長大スパンの梁をその中央部が上方に反る形
状に予めむくりをつけた状態で柱間に架設し、その梁の
中央部に係合させたワイヤを、前記梁より下階に位置す
る他の梁と前記柱との仕口部近傍に設けたジヤツキによ
り緊張することによって、前記梁の中央部に下向きの先
行荷重を加えてその梁をほぼ水平となした後、この梁に
負荷される荷重となる残余の建築部材を組み立てること
を特徴とするものである。
``Means for Solving the Problems'' The present invention involves constructing a long-span beam between pillars with the central part curved upward in advance, and engaging the central part of the beam. By tensioning the wire with a jack installed near the joint between the pillar and another beam located on the lower floor than the beam, a downward preload is applied to the center of the beam, and the beam is tightened. After the beam is made almost horizontal, the remaining building members that will be the load that will be applied to the beam are assembled.

「実施例」 以下、本発明の一実施例を第1図〜第11図を参照して
説明する。
"Embodiment" An embodiment of the present invention will be described below with reference to FIGS. 1 to 11.

第1図は本発明方法により構築された建築物の躯体を示
す部分立面図であって、図中符号10はその下方に大空
間20を形成するために設けられた長大スパンかつ大断
面の梁である。
FIG. 1 is a partial elevation view showing the framework of a building constructed by the method of the present invention, and the reference numeral 10 in the figure is a long span and large section provided to form a large space 20 below. It is a beam.

この梁10は、基本的には下弦材11、上弦材12、垂
直材】3、斜材14から構成されるトラス構造のもので
あるが、その断面を第2図に示すように、下弦材11は
ボックス状の鉄骨15の内側にコンクリートが充填され
るとともに、外側に鉄筋16が配筋されたうえでコンク
リートが打設されて形成された鉄骨鉄筋コンクリート造
(より厳密には充填被覆型鋼管コンクリート造)のもの
とされ、上弦材12、垂直材13、斜材14はいずれも
鉄骨造とされている。
This beam 10 basically has a truss structure consisting of a lower chord member 11, an upper chord member 12, a vertical member 3, and a diagonal member 14. 11 is a steel-framed reinforced concrete structure (more precisely, filled-covered steel pipe concrete), which is formed by filling concrete inside a box-shaped steel frame 15, placing reinforcing bars 16 on the outside, and then pouring concrete. The upper chord members 12, vertical members 13, and diagonal members 14 are all of steel frame construction.

この梁lOは、第1図に示されるように下弦材11の両
端が鉄骨鉄筋コンクリート造の大断面の柱18,1.8
に接合されてそれらの上端相互間に架設され、この梁1
0の下方に、この建築物の4スパンにわたる幅を有し、
かつ、5層分が吹き抜けた無柱の大空間20が形成され
るようになっている。すなわち、この梁10および柱1
8.]、8によって、そのよ)な大空間20を形成する
とともに上層階の躯体を支持するための門型フレームで
ある4メガストラクチユアが構成されている。
As shown in FIG.
This beam 1
has a width spanning four spans of this building below 0;
In addition, a large column-free space 20 is formed that extends through five floors. That is, this beam 10 and column 1
8. ], 8 constitute a 4-mega structure which is a gate-shaped frame for forming a large space 20 and supporting the frame of the upper floor.

そして、この梁10の下弦材11の上面の位置には上記
大空間20の直上階の床が形成され、上弦材12の上面
の位置にはさらにその上階の床が形成されるようになっ
ていて、この梁10の下弦材11はそれ自身で大空間2
0の直上階の床梁を兼ねるとともに、垂直材13および
斜材14はそれら自身でそれぞれこの階の柱およびプレ
ースを兼ねるものとされ、上弦材J2はそれ自身でその
上階の床梁を兼ねるものとされている。
The floor of the floor directly above the large space 20 is formed at the upper surface of the lower chord member 11 of this beam 10, and the floor of the upper floor is formed at the upper surface of the upper chord member 12. The lower chord member 11 of this beam 10 is itself a large space 2.
0, the vertical members 13 and the diagonal members 14 themselves also serve as columns and places for this floor, respectively, and the upper chord member J2 itself serves as the floor beam for the floor above. It is considered a thing.

なお、第1図において符号30.31はメガストラクチ
ュア以外の躯体である柱および梁であり、これらは通常
の鉄骨造とされている。
Note that in FIG. 1, reference numerals 30 and 31 indicate columns and beams that are the building blocks other than the megastructure, and these are made of normal steel structures.

上記の建築物の施工手順の一例を第3図〜第11図を参
照して説明する。
An example of the construction procedure for the above building will be explained with reference to FIGS. 3 to 11.

第3図に示すように、柱18.18および大空間20の
床面までの躯体を構築した後、大空間20の床面上にお
いて梁10の下弦材11となる鉄骨15を組み立てる。
As shown in FIG. 3, after constructing the frame up to the columns 18, 18 and the floor of the large space 20, the steel frame 15 that will become the lower chord member 11 of the beam 10 is assembled on the floor of the large space 20.

この鉄骨15は、図示されるように、中央部1.5 a
と両側部15b、15bとの3ピースにより構成し、そ
の中央部15aが上方に変位するようにむくりをつけて
おく。そのむくり寸法d、は、後述するようにトラスの
剛性やコンクリートの重量等を考慮したうえで、梁】0
が建築物の荷重を最終的に受けたときにほぼ水平となる
ように設定しておく。また、梁10の中央に位置して設
けられる垂直材13を予めこの鉄骨15の中央部15a
に取り付けておく。
As shown in the figure, this steel frame 15 has a central portion 1.5 a
It is composed of three pieces, ie, and both side parts 15b, 15b, and is curved so that the central part 15a is displaced upward. The peeling dimension d is determined by taking into account the rigidity of the truss and the weight of concrete, etc., as described below.
It is set so that it will be almost horizontal when it finally receives the load of the building. In addition, the vertical member 13 provided at the center of the beam 10 is installed in advance at the central portion 15a of the steel frame 15.
Attach it to

そして、そのように組み立てた鉄骨15を、柱18.1
8から反力をとってリフトアップしていき、第4図に示
すようにそれら柱18.18の上端間に架設する。
Then, the steel frame 15 assembled in this way is attached to the column 18.1.
The reaction force is removed from 8 and lifted up, and as shown in FIG.

次に、上記のように架設した鉄骨15に下向きの先行荷
重をかけ、むくり寸法がa2(d2<a+)となるまで
むくりを低減させる。それには、第5図に示すように、
上記垂直材13の上端部にワイヤ41の中央部を係合さ
せ、そのワイヤ41の両端を柱18.18の基部(大空
間20の床面に位置して設(プられる他の粱:11と柱
18.18との仕口部近傍)に斜め上向きに取り付けた
油圧ジヤツキ40 、4− Ofこそれぞれ連結し、そ
れら油圧ジヤツキ40.40を作動させてワイヤ41を
緊張することにより、垂直材13を介して鉄骨J5の中
央部15aに下向きの荷重を加えるようになすと良い。
Next, a downward preliminary load is applied to the steel frame 15 constructed as described above, and the bulge is reduced until the bulge dimension becomes a2 (d2<a+). To do this, as shown in Figure 5,
The center part of the wire 41 is engaged with the upper end of the vertical member 13, and both ends of the wire 41 are connected to the base of the pillar 18. Hydraulic jacks 40 and 4-Of installed diagonally upwards (near the joint with column 18. It is preferable to apply a downward load to the center portion 15a of the steel frame J5 via the steel frame J5.

なお、油圧ジヤツキ40.40を上記のように他の梁3
1との仕口部近傍の位置に設けるようにしたのは、ワイ
ヤ41を緊張した際に受ける反力によって柱18.18
が変形してしまうことを防止するためである。
In addition, the hydraulic jack 40.40 is attached to the other beam 3 as described above.
The reason why the pillars 18 and 18 are installed near the joint with the wire 41 is because of the reaction force received when the wire 41 is tensed.
This is to prevent deformation.

垂直材13に対するワイヤ41の保合は、第10図およ
び第11図に示すように、垂直材13の表面にワイヤ4
1の曲率に沿う形状の湾曲板42を予め溶接しておいて
その湾曲板42にワイヤ41を巻回するとともに、ガイ
ドプレート43によりワイヤ41の湾曲板42からの脱
落を防止するようになすと良い。この場合、湾曲板42
の表面にグリースを塗布しておくか、もしくはたとえば
テフロン等の樹脂をコーティングしておいて、ワイヤ4
1が湾曲板42に対して自由に滑動するようにしておけ
ば、油圧ジヤツキ40.40を作動させた際にワイヤ4
1が湾曲板42に対して滑っていってワイヤ41の両側
に加わる緊張力が自ずと均等になる。なお、第1O図、
第11図において符号44は補強用のリブである。
The wire 41 is secured to the vertical member 13 by attaching the wire 41 to the surface of the vertical member 13, as shown in FIGS. 10 and 11.
A curved plate 42 having a shape along the curvature of 1 is welded in advance, and the wire 41 is wound around the curved plate 42, and a guide plate 43 is used to prevent the wire 41 from falling off the curved plate 42. good. In this case, the curved plate 42
Apply grease to the surface of the wire 4 or coat it with a resin such as Teflon.
If the wire 4 is made to slide freely on the curved plate 42, when the hydraulic jack 40.40 is operated, the wire 4
1 slides against the curved plate 42, and the tension applied to both sides of the wire 41 naturally becomes equal. Furthermore, Figure 1O,
In FIG. 11, reference numeral 44 indicates a reinforcing rib.

上記のように、鉄骨15のむくりを低減させた状態で、
第6図に示すように、他の垂直材13、科料14、上弦
材12をそれぞれ鉄骨15に取り付け、トラスを形成す
る。
As mentioned above, with the swelling of the steel frame 15 reduced,
As shown in FIG. 6, other vertical members 13, members 14, and upper chord members 12 are each attached to the steel frame 15 to form a truss.

その後、鉄骨15に加えた先行荷重を一旦解除する。こ
れにより、第7図に示すように鉄骨15のむくりは大き
くなるが、そのむくり寸法d3は、形成されたトラスの
剛性分だけ当初のむくり寸法d1よりは小さくなる。
Thereafter, the preceding load applied to the steel frame 15 is temporarily released. As a result, as shown in FIG. 7, the bulge of the steel frame 15 increases, but the bulge dimension d3 becomes smaller than the original bulge dimension d1 by the rigidity of the formed truss.

その後、鉄骨15の外側に鉄筋16を配筋してを枠を組
み立てたうえで、鉄骨15の内側にコンクリ−1・を充
填するとともに外側にコンクリートを打設し、鉄骨鉄筋
コンクリート造の下弦側11を形成する。これにより、
第8図に示すように、果10がむくりのイスいた状態で
形成されるが、この段階における梁10のむくり寸法d
、はコンクリ−1・の重量分だけ上記のむくり寸法d、
より小さくなり、当然ながら鉄骨15に当初に付与され
ていたむくり寸法d1より小さくなる。この段階のむく
り寸法d、が、この後に梁10に負荷される上層階の躯
体およびその他の各種建築部材の荷重に対応するものと
なっていて、最終的にその荷重が梁10に加わることで
梁10が自ずとほぼ水平となるように設定されている。
After that, reinforcing bars 16 are arranged on the outside of the steel frame 15 to assemble the frame, and then concrete 1 is filled inside the steel frame 15 and concrete is poured on the outside. form. This results in
As shown in FIG. 8, the beam 10 is formed in an exposed state, but the exposed dimension d of the beam 10 at this stage is
, is the above peeling dimension d for the weight of concrete 1.
It becomes smaller, and of course becomes smaller than the exposed dimension d1 originally given to the steel frame 15. The exposed dimension d at this stage corresponds to the load of the upper floor frame and other various building components that will be applied to the beam 10 after this, and that load will finally be applied to the beam 10. The beam 10 is set so that it is naturally almost horizontal.

そこで、コンクリート強度が確保された後、梁10より
上階の施工により梁10が撓むとされるレベルよりやや
高めのレベルまで(第9図に示すようにほぼ水平となる
まで)むくりを低減さぜるべく、ワイヤ41を介して梁
10に先行荷重をかける。その後、梁10の上部に上層
階の躯体を施工するとともに各種建築部材を取り付けて
いき、その荷重に応じて順次ワイヤ41を段階的に緩め
ていって先行荷重を低減させていくことにより、梁10
を常にほぼ水平に保持する。
Therefore, after the concrete strength is ensured, the bulging is reduced to a level slightly higher than the level at which the beam 10 would be deflected (until it becomes almost horizontal as shown in Figure 9) by construction on the floor above the beam 10. A preload is applied to the beam 10 via the wire 41 in order to warm it up. After that, the upper floor frame is constructed on top of the beam 10 and various building components are attached, and the wires 41 are gradually loosened according to the load to reduce the preceding load. 10
Always keep it almost horizontal.

以上により、上層階が所定階まで組み立てられた時点で
采10に加えた先行荷重を全て解除して、梁lOを上層
階の躯体および各種の建築部材の荷重によりほぼ水平と
して完了するか、または残余の負荷荷重の分だけやや上
むくり状態とした後、残余の建築材料を組み立てて完成
する。
As a result of the above, when the upper floor is assembled to a predetermined level, all the preceding loads applied to the clasp 10 are released, and the beam IO is completed as being almost horizontal due to the loads of the upper floor frame and various building members, or After the building is slightly raised to accommodate the remaining load, the remaining building materials are assembled and completed.

」1記の梁10では、下弦材11および上弦材12とに
より全体としては十分な梁成寸法が確保されて十分な剛
性が得られ、これによって、梁10の下方に上記のよう
な大空間20が確保できることは勿論のこと、下弦材1
1を鉄骨鉄筋コンクリート造とし、かつ、この下弦材1
1の鉄骨15には梁10の撓み方向と逆方向の曲げモー
メントが付与されたものとなるので、第21図に示した
もののように梁全体を単純なトラス構造とする場合に比
して鉄骨量を削減できるとともに鉄骨加工が簡略化され
、工費、施工手間の点で有利である。
In the beam 10 described in item 1, the lower chord member 11 and the upper chord member 12 ensure sufficient beam dimensions as a whole and obtain sufficient rigidity, thereby creating a large space below the beam 10 as described above. Not only can you secure 20, but also the lower chord 1
1 is of steel-framed reinforced concrete construction, and this lower chord member 1
Since a bending moment is applied to the steel frame 15 in the direction opposite to the direction of deflection of the beam 10, the steel frame 15 is It is possible to reduce the amount of steel and simplify the steel processing, which is advantageous in terms of construction costs and labor.

しかも、下弦材11、上弦材12、垂直材13、斜材1
4がそれぞれこの建築物の梁、柱、プレースを兼ねるの
で、建築物全体の躯体が簡略化されるという利点もある
Moreover, the lower chord member 11, the upper chord member 12, the vertical member 13, and the diagonal member 1
4 also serve as the beams, columns, and places of this building, so there is also the advantage that the frame of the entire building can be simplified.

また、上記実施例の施工手順によれば、鉄骨15に先行
荷重をかけてむくりを低減させた後に、垂直材13、斜
材14、上弦材12を組み立ててトラスを形成するので
、その作業を容易に行うことができるものである。すな
わち、鉄骨15に当初の大きなむくり(むくり寸法d、
)が付いている状態のままでトラスを組み立てる場合に
あっては、垂直材13が外側に傾いてしまうことになっ
てトラスの建方が非常に困難となるのに対し、上記の場
合には、むくり寸法がd2となるまでむくりを低減させ
てからI・ラスを組み立てるので、垂直材13を支障な
く鉛直に建てることができるのでトラスを容易に組み立
てることができる。
Further, according to the construction procedure of the above embodiment, after applying a preliminary load to the steel frame 15 to reduce swelling, the vertical members 13, diagonal members 14, and upper chord members 12 are assembled to form a truss, so the work can be easily carried out. That is, the steel frame 15 has an initial large bulge (the bulge dimension d,
) If the truss is assembled with the vertical members 13 still attached, the vertical members 13 will tilt outward, making it extremely difficult to construct the truss. Since the I lath is assembled after reducing the bulge until the bulge dimension becomes d2, the vertical members 13 can be erected vertically without any hindrance, and the truss can be easily assembled.

また、上記の場合、ワイヤ41はほぼ梁1oの下方に納
まるから、第21図に示した従来のもののように上層階
の躯体に対する外壁の取り付は作業の際にワイヤ41が
邪魔になってその作業に支障をきたすようなことがない
。また、既に述べたように、油圧ジヤツキ4.0.40
を柱18.18と他の梁31との化1部近傍の位置に設
けるようにしたので、ワイヤ41を緊張した際に受ける
反力によって柱18,18が変形してしまうようなこと
が確実に防止されるとともに、その仕口部に対する油圧
ジヤツキ40の取り付は作業や、油圧ジヤツキ40に対
するワイヤ41の連結作業は、大空間20の床面を足場
として行うことができ、作業性が良い。また、垂直材1
3に対するワイヤ41の保合は、鉄骨15を足場として
これも容易に行うことができる。
Furthermore, in the above case, since the wire 41 is almost located below the beam 1o, the wire 41 becomes an obstacle when attaching the outer wall to the upper floor frame as in the conventional case shown in FIG. 21. There will be no hindrance to the work. Also, as already mentioned, hydraulic jack 4.0.40
Since the wires 18 and 18 are provided in the vicinity of the junction between the pillars 18 and the other beams 31, it is certain that the pillars 18 and 18 will be deformed by the reaction force received when the wire 41 is tensed. In addition, the installation work of the hydraulic jack 40 to the joint part and the work of connecting the wire 41 to the hydraulic jack 40 can be performed using the floor surface of the large space 20 as a foothold, and the work efficiency is good. . Also, vertical member 1
The wire 41 can be easily secured to the steel frame 15 using the steel frame 15 as a scaffold.

また、鉄骨15に対してコンクリートを打設して下弦材
11を形成するに際し、鉄骨15に加えた先行荷重を一
旦解除して大きなむくりの付いた状態に戻し、その状態
でコンクリートを打設するようにしたので、鉄骨15の
むくりを低減させた状態でコンクリートを打設して下弦
材11を形成する場合に比して、梁10の剛性をより高
めることができる。
In addition, when pouring concrete to the steel frame 15 to form the lower chord member 11, the preliminary load applied to the steel frame 15 is temporarily released to return it to a state with a large bulge, and concrete is poured in that state. As a result, the rigidity of the beam 10 can be further increased compared to the case where the lower chord member 11 is formed by pouring concrete with the steel frame 15 having reduced bulge.

以上で本発明方法の一実施例を説明したが、以下のよう
な変形例が考えられる。
Although one embodiment of the method of the present invention has been described above, the following modifications can be considered.

たとえば、第12図および第13図に示すように、上記
実施例における湾曲板42に代えて、垂直材13の表面
にワイヤピロー50をブラケッ1−51によって取り付
け、そのワイヤピロー50にワイヤ41を係合させるこ
とでも良い。
For example, as shown in FIGS. 12 and 13, instead of the curved plate 42 in the above embodiment, a wire pillow 50 is attached to the surface of the vertical member 13 with a bracket 1-51, and the wire 41 is attached to the wire pillow 50. It may also be engaged.

また、上記実施例では1本のワイヤ41を用いたが、ワ
イヤ41としてPC鋼線等を用いる場合のようにワイヤ
41の曲率を余り大きくできないときには、第14図お
よび第15図に示すようにワイヤ41を2分割して、そ
れらの端部を垂直材13に固定した定着具60にそれぞ
れスペーサ61を介してストッパ62により定着させる
ことでその定着具60を介して相互に連結するようにな
し、それらワイヤ41.41の他端をそれぞれ油圧ジヤ
ツキ40.40に連結すれば良い。この場合、双方のワ
イヤ41.41の長さは厳密に均等であることが必要で
あるので、スペーサ61,61の厚みを調節することに
より各ワイヤ41,41の長さを微調整すれば良い。
In addition, although one wire 41 was used in the above embodiment, when the curvature of the wire 41 cannot be made too large, such as when a PC steel wire or the like is used as the wire 41, a wire 41 as shown in FIGS. 14 and 15 may be used. The wire 41 is divided into two parts, and the ends thereof are fixed to a fixing device 60 fixed to the vertical member 13 through a spacer 61 and a stopper 62, so that they are interconnected via the fixing device 60. , the other ends of these wires 41, 41 may be connected to hydraulic jacks 40, 40, respectively. In this case, the lengths of both wires 41, 41 must be strictly equal, so the length of each wire 41, 41 can be finely adjusted by adjusting the thickness of the spacers 61, 61. .

また、第16図に示すように、垂直材13に2本のワイ
ヤ4.1 、4.1を上下2段に係合させたり、梁10
の中央に垂直材13が位置しない場合にあっては、第1
7図に示すように、中央部に位置する2本の垂直材13
.13に対して1本のワイヤ41をかけて緊張するか、
あるいは、第18図に示すように、各垂直材13.13
にそれぞれワイヤ41.41をかけてそれらを緊張させ
ることでも良い。この場合、ワイヤ41の反力が垂直材
13.13iこ対して偏芯するので双方の垂直材13゜
13を梁により連結しておくと良い。
In addition, as shown in FIG.
If the vertical member 13 is not located in the center of the
As shown in Figure 7, two vertical members 13 located in the center
.. Put one wire 41 against 13 and put tension on it, or
Alternatively, as shown in Figure 18, each vertical member 13.13
It is also possible to apply wires 41 and 41 to each to tension them. In this case, since the reaction force of the wire 41 is eccentric with respect to the vertical members 13.13i, it is preferable to connect both vertical members 13.13 with a beam.

また、上記各実施例では、いずれも垂直材13を介して
梁10の中央部に先行荷重を加えるようにしたが、第1
9図おにび第20図に示すように、垂直材13を介さず
に梁10となる鉄骨15の側面や下部に対してワイヤ4
1を直接的に係合させて緊張することでも勿論良い。
Further, in each of the above embodiments, a preliminary load is applied to the center of the beam 10 via the vertical member 13, but the first
As shown in FIG. 9 and FIG.
Of course, it is also possible to directly engage and tension 1.

また、上記実施例では、梁lOを下弦材11が鉄骨鉄筋
コンクリート造とされたトラス構造のものとしたが、梁
lQの構造は上記実施例に限定されることなく適宜で良
いし、その梁を支持する柱18も鉄骨鉄筋コンクリート
造に限らず適宜の構造を採用し得る。勿論、梁10は柱
18の上端部のみならずその途中に架設することもでき
る。さらに、上記実施例では、梁10の下弦材11とな
る鉄骨15をリフトアップして柱18上端間に架設する
ようにしたが、スパンが比較的小さい場合等においては
必ずしもリフトアップ工法によることはない。
Furthermore, in the above embodiment, the beam lO has a truss structure in which the lower chord member 11 is made of steel-framed reinforced concrete, but the structure of the beam IQ is not limited to the above embodiment, and any suitable structure may be used. The supporting columns 18 are not limited to steel-framed reinforced concrete construction, and may have any suitable structure. Of course, the beam 10 can be installed not only at the upper end of the column 18 but also in the middle thereof. Furthermore, in the above embodiment, the steel frame 15 serving as the lower chord member 11 of the beam 10 is lifted up and installed between the upper ends of the columns 18, but in cases where the span is relatively small, etc., the lift-up method may not necessarily be used. do not have.

また、上記実施例は、本発明の施工方法を、梁の下方に
無柱の大空間が設けられるとともに梁の上部(こ上層階
の躯体が設けられる形態の建築物に適用した場合の例で
あるが、本発明はそのような形態の建築物に適用される
のみならず種々の形態の建築物全般に対して同様に適用
できることはいうまでもない。
In addition, the above embodiment is an example in which the construction method of the present invention is applied to a building in which a large column-free space is provided below the beam, and a frame of the upper floor is provided above the beam. However, it goes without saying that the present invention is not only applicable to such types of buildings, but can also be similarly applied to various types of buildings in general.

「発明の効果」 以上で詳細に説明したように、本発明によれば、長大ス
パンの梁をその中央部が上方に反る形状に予めむくりを
つけた状態で柱間に架設し、その梁の中央部に保合さセ
たワイヤを、前記梁より下階に位置する他の梁と前記柱
との仕口部近傍に設けG たジヤツキにより緊張することによって、前記梁の中央
部に下向きの先行荷重を加えるようにしたので、施工途
中においては梁を常にほぼ水平に保持できて梁の上部に
おける柱の建方等の作業を何等のさまたげなく容易に行
えることは勿論のこと、下階の前記柱の階高中間部や下
階の梁の柱間の中央部番こジヤツキを設けていない故に
、長大スノ<ンの梁に対して先行荷重をかけた際の反力
により下階の柱や梁が変形してしまうようなことがない
ととも(こジャツギの取り付は作業やジャ・ンキに対す
るワイヤの連結作業を事前の工程により設けられている
床面上で安全にかつ容易に行え、また、ワイヤは長大ス
パンの梁の下方に納まるので上層階の外壁を取り付ける
際にワイヤが邪魔になるようなことがない、という利点
がある。
"Effects of the Invention" As explained in detail above, according to the present invention, a long-span beam is erected between columns with the central part curved upward in advance, and By tensioning the wire fixed to the center of the beam with a jack installed near the joint between the pillar and another beam located on the lower floor than the beam, the wire is fixed to the center of the beam. Since a downward preload is applied, the beam can always be held almost horizontally during construction, and it goes without saying that work such as erecting columns on the top of the beam can be done easily without any hindrance. Because there is no adjustment at the middle part of the floor height of the above-mentioned pillars of the floor or the middle part of the beams of the lower floor, the lower floor is affected by the reaction force when a preload is applied to the long snow beam. The pillars and beams of the building will not be deformed (the installation of the kojatsugi and the work of connecting the wires to the jacks will be done safely and easily on the floor surface that has been prepared in advance). Another advantage is that the wires do not get in the way when attaching the exterior walls of the upper floors, since the wires fit under the long span beams.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第2図は本発明に係る施工方法により構築
された建染物の一例を示すもので、第1図は部分立面図
、第2図は大空間を形成するための梁の断面図(第1図
のn−m線矢視図)である。 第3図〜第9図は上記建築物の施工方法の一例を工程順
に説明するだめの図、第10図は第5図のX部の拡大図
、第11図はその側面図である。 第12図および第13図は本発明方法の他の実施例を示
すもので、第12図は部分拡大正面図、第13図はその
側面図である。第14図および第15図は本発明方法の
さらに他の実施例を示すもので、第14図は部分拡大正
面図、第15図はその側面図である。第16図ないし第
20図はいずれも本発明方法のさらに他の実施例を説明
するための図である。 第21図は、メガストラクチュアによる建築物の一従来
例を示す斜視図である。 10・・・・・・梁、18・・・・・・柱、31・・・
・・・他の梁、40・・・・・・ジヤツキ、41・・・
・・・ワイヤ。
Figures 1 and 2 show an example of a building constructed using the construction method according to the present invention. Figure 1 is a partial elevation view, and Figure 2 is a cross-section of a beam for forming a large space. FIG. 2 is a diagram (view taken along line nm in FIG. 1). FIGS. 3 to 9 are diagrams for explaining an example of the construction method of the above-mentioned building in the order of steps, FIG. 10 is an enlarged view of section X in FIG. 5, and FIG. 11 is a side view thereof. 12 and 13 show another embodiment of the method of the present invention, with FIG. 12 being a partially enlarged front view and FIG. 13 being a side view thereof. 14 and 15 show still another embodiment of the method of the present invention, with FIG. 14 being a partially enlarged front view and FIG. 15 being a side view thereof. 16 to 20 are diagrams for explaining still other embodiments of the method of the present invention. FIG. 21 is a perspective view showing a conventional example of a building using a megastructure. 10...Beam, 18...Column, 31...
...Other beams, 40... Jackpots, 41...
...Wire.

Claims (1)

【特許請求の範囲】[Claims]  長大スパンの梁をその中央部が上方に反る形状に予め
むくりをつけた状態で柱間に架設し、その梁の中央部に
係合させたワイヤを、前記梁より下階に位置する他の梁
と前記柱との仕口部近傍に設けたジャッキにより緊張す
ることによって、前記梁の中央部に下向きの先行荷重を
加えてその梁をほぼ水平となした後、この梁に負荷され
る荷重となる残余の建築部材を組み立てることを特徴と
する建築物の施工方法。
A long span beam is erected between the pillars with the central part curved upward in advance, and a wire engaged with the central part of the beam is placed at a lower floor than the beam. By applying tension with a jack installed near the joint between another beam and the column, a downward preload is applied to the center of the beam to make it almost horizontal, and then the load is applied to this beam. A construction method for a building characterized by assembling the remaining building members that will carry the load.
JP17780290A 1990-07-05 1990-07-05 Construction method of building Expired - Fee Related JP2916585B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17780290A JP2916585B2 (en) 1990-07-05 1990-07-05 Construction method of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP17780290A JP2916585B2 (en) 1990-07-05 1990-07-05 Construction method of building

Publications (2)

Publication Number Publication Date
JPH0468167A true JPH0468167A (en) 1992-03-03
JP2916585B2 JP2916585B2 (en) 1999-07-05

Family

ID=16037347

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17780290A Expired - Fee Related JP2916585B2 (en) 1990-07-05 1990-07-05 Construction method of building

Country Status (1)

Country Link
JP (1) JP2916585B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010084471A (en) * 2008-10-01 2010-04-15 Kajima Corp Suspension structure type frame
CN114439248A (en) * 2022-04-07 2022-05-06 北京建工集团有限责任公司 Steel column installation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010084471A (en) * 2008-10-01 2010-04-15 Kajima Corp Suspension structure type frame
CN114439248A (en) * 2022-04-07 2022-05-06 北京建工集团有限责任公司 Steel column installation method

Also Published As

Publication number Publication date
JP2916585B2 (en) 1999-07-05

Similar Documents

Publication Publication Date Title
US7219474B2 (en) Load bearing building panel
JP2934668B2 (en) Beam structure
JPH05287901A (en) Construction of stairs
JPH0468167A (en) Building method
JP2916587B2 (en) Construction method of building
JPS6314937A (en) Reinforcing bar composite pillar
JPH04368528A (en) Frame construction using void beam
JP2974025B1 (en) Construction method of large span large beam upper frame
JP3116767B2 (en) Existing building seismic isolation structuring method
JP2522708B2 (en) Reinforcing bar tip assembly beam with formwork and reinforcing bar tip assembly method with formwork
JPH084196A (en) Panel for building
JPH06193133A (en) Mixed structure of building mainly made of reinforced concrete
JPH0468168A (en) Building method
JP2641836B2 (en) Precast prestressed concrete U-beam
JPH07238593A (en) Building of tube structure
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JPH09264050A (en) Building structure
JP3187618B2 (en) How to assemble beam reinforcement
JP2916588B2 (en) Construction method of building
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPH0447737B2 (en)
JP2022163290A (en) Structure
AU2002234421B2 (en) A load bearing building panel
JPH0222819B2 (en)