JPH04265625A - Plant managing device - Google Patents

Plant managing device

Info

Publication number
JPH04265625A
JPH04265625A JP3044081A JP4408191A JPH04265625A JP H04265625 A JPH04265625 A JP H04265625A JP 3044081 A JP3044081 A JP 3044081A JP 4408191 A JP4408191 A JP 4408191A JP H04265625 A JPH04265625 A JP H04265625A
Authority
JP
Japan
Prior art keywords
power demand
power
level
screen
power system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3044081A
Other languages
Japanese (ja)
Other versions
JP2736826B2 (en
Inventor
Hironori Fukushima
裕基 福島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Azbil Corp
Original Assignee
Azbil Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Azbil Corp filed Critical Azbil Corp
Priority to JP4408191A priority Critical patent/JP2736826B2/en
Publication of JPH04265625A publication Critical patent/JPH04265625A/en
Application granted granted Critical
Publication of JP2736826B2 publication Critical patent/JP2736826B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE:To know easily the cut-off condition under the present power demand control. CONSTITUTION:First, a power system screen 102 is displayed. Then, the power demand level and the cut-off condition of the power loads at that level are displayed in a power demand displaying part 102-34 of the power system screen 102. To be more specific, it can be known at a glance from the reversal display of a breaker mark I that the power demand control is going on at the present level (1).

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】この発明は、電力系統画面を表示
し得る表示手段を備えた施設管理装置に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a facility management device equipped with display means capable of displaying an electric power system screen.

【0002】0002

【従来の技術】高層ビル,集合住宅,病院,工場などの
施設においては、各種の設備が配置されている。例えば
、その設備として空調設備,防犯設備,防災設備,熱源
設備などの設備系統が挙げられ、これら設備は設備機器
としての各種機器を多数備えている。一方、これらの施
設においては、最近、目標電力以内にその電力系統の消
費電力を抑圧制御する電力デマンド制御が行われている
。この電力デマンド制御では、電力デマンドレベルとし
て例えばレベル■〜■を設け、これら電力デマンドレベ
ルの各々に所定の電力負荷群を割り当てている。すなわ
ち、予想電力が目標電力よりも上回る場合、先ずレベル
■に応ずる電力負荷群を遮断する。このレベル■の電力
負荷群の遮断で補えなければ、レベル■に応ずる電力負
荷群を遮断し、以下同様にしてレベル■に応ずる電力負
荷群を遮断する。このような状況下において、現在の電
力デマンド制御による遮断状態を知りたい場合、施設管
理装置のディスプレイ上に制御リストを出す。そして、
この制御リストから電力デマンド制御の項目を指定し、
そのプログラム画面を出す。そして、このプログラム画
面の頁をめくって、電力デマンドレベルに関する頁を写
し出し、その内容を確認して、現在どのレベルで電力デ
マンド制御が行われているかを知る。
2. Description of the Related Art Various types of equipment are installed in facilities such as high-rise buildings, housing complexes, hospitals, and factories. Examples of such equipment include equipment systems such as air conditioning equipment, crime prevention equipment, disaster prevention equipment, and heat source equipment, and these equipment are equipped with a large number of various types of equipment. On the other hand, in these facilities, power demand control has recently been performed to suppress the power consumption of the power system to within the target power level. In this power demand control, levels 1 to 2, for example, are provided as power demand levels, and a predetermined power load group is assigned to each of these power demand levels. That is, if the expected power exceeds the target power, first the power load group corresponding to level (2) is shut off. If this cannot be compensated for by cutting off the power load group of level (2), then the power load group corresponding to level (2) is cut off, and thereafter, the power load group corresponding to level (2) is cut off in the same manner. Under such circumstances, if one wants to know the current power demand control cutoff state, a control list is displayed on the display of the facility management device. and,
Specify the power demand control items from this control list,
Display the program screen. Then, the user turns over the page on this program screen to reveal the page related to the power demand level, confirms its contents, and learns at what level power demand control is currently being performed.

【0003】0003

【発明が解決しようとする課題】しかしながらこのよう
な従来の施設管理装置によると、現在の電力デマンド制
御による遮断状態を知るまでにかなりの労力を必要とし
、非常に手間がかかるものであった。また、従来の施設
管理装置においては、電力デマンドレベルの各々につい
てその電力負荷群の発停を、任意のタイミングで一括し
て簡単に行うことができず、状況に応じてフレキシブル
に対応することができなかった。
[Problems to be Solved by the Invention] However, with such a conventional facility management device, it takes a considerable amount of effort and effort to know the shutoff state due to the current power demand control. Furthermore, with conventional facility management devices, it is not possible to easily start and stop a group of power loads for each power demand level all at once at an arbitrary timing, and it is difficult to respond flexibly depending on the situation. could not.

【0004】0004

【課題を解決するための手段】本発明はこのような課題
を解決するために提案されたもので、その第1発明(請
求項1に係る発明)は、電力系統画面を表示し得るもの
とし、この電力系統画面の電力デマンド表示部にて、電
力デマンドレベルおよびそのレベルに応ずる電力負荷群
の遮断の有無を視覚的に表するようにしたものである。 また、その第2発明(請求項2に係る発明)は、第1発
明において、電力デマンド表示部をキーとして所望の電
力デマンドレベルを選択できるものとし、その選択した
レベルに応ずる電力負荷群の発停を一括して行うことが
できるようにしたものである。
[Means for Solving the Problems] The present invention has been proposed to solve such problems, and the first invention (invention according to claim 1) is capable of displaying an electric power system screen. The power demand display section of the power system screen visually displays the power demand level and whether or not a power load group corresponding to the level is shut off. Further, the second invention (invention according to claim 2) is the first invention, in which a desired power demand level can be selected using the power demand display section as a key, and the power load group is generated according to the selected level. This makes it possible to perform all stops at once.

【0005】[0005]

【作用】したがって、その第1発明によると、電力系統
画面を表示することにより、その電力デマンド表示部に
て、一目で現在の電力デマンド制御による遮断状態を知
ることができる。また、その第2発明によると、電力系
統画面を表示することにより、その電力デマンド表示部
をキーとして、所望の電力デマンドレベルに応ずる電力
負荷群を、任意のタイミングで一括して発停することが
できる。
Therefore, according to the first invention, by displaying the power system screen, it is possible to know at a glance the current cut-off state due to power demand control on the power demand display section. Further, according to the second invention, by displaying the power grid screen, a group of power loads corresponding to a desired power demand level can be started and stopped all at once at any timing using the power demand display section as a key. Can be done.

【0006】[0006]

【実施例】以下、本発明に係る施設管理装置を詳細に説
明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS A facility management apparatus according to the present invention will be explained in detail below.

【0007】図2はこの施設管理装置の一実施例を示す
統合化ビルディング・オートメーションシステム(以下
、セイビック装置と云う)の外観斜視図である。
FIG. 2 is an external perspective view of an integrated building automation system (hereinafter referred to as Sabic device) showing one embodiment of this facility management device.

【0008】このセイビック装置は、中小規模建築物の
空調設備,電力設備,防犯設備,防災設備,熱源設備,
給排水設備,衛生設備などを一括管理するものとして、
一般事務所,テナントビル,工場,病院,その他の用途
の施設で、省エネルギ,省力化をはじめ安全管理,運営
管理などに使用される。本実施例においては、特に中小
規模テナントビル管理に必要な機能を備え、さらに中小
規模建築物には専任のオペレータが不在であることを考
慮して、誰でも簡単に扱えるようにフレンドリーオペレ
ーションのマン・マシン・インタフェイスを有している
。また、専用の管理室が確保されにくいことを考慮して
、省スペースの薄型壁掛構造となっている。
[0008] This Sabic device is used for air conditioning equipment, electric power equipment, crime prevention equipment, disaster prevention equipment, heat source equipment,
As a unit that manages water supply and drainage equipment, sanitary equipment, etc.
It is used in general offices, tenant buildings, factories, hospitals, and other facilities for energy saving, labor saving, safety management, operational management, etc. In this example, it is equipped with functions especially necessary for managing small and medium-sized tenant buildings, and considering the fact that small and medium-sized buildings do not have full-time operators, the system is equipped with a friendly operation system that anyone can easily use. - Has a machine interface. In addition, considering that it is difficult to secure a dedicated management room, the system has a thin, wall-mounted structure that saves space.

【0009】図2において、1はタッチパネル付LCD
、2はアナンシェータ、3は組み込みプリンタである。
In FIG. 2, 1 is an LCD with a touch panel.
, 2 is an annunciator, and 3 is a built-in printer.

【0010】図3は、このセイビック装置10のブロッ
ク図であり、MMI制御装置4を介して、タッチパネル
付LCD1および組み込みプリンタ3がCPU5と接続
されている。また、CPU5には、インターフェイス6
を介して外付け電話11および公衆回線/専用回線12
が接続され、外部インターフェイス7を介してリモート
アナンシェータ13,外付けプリンタ14,外付けパソ
コン15およびサービスツール16が接続されている。 なお、8は伝送制御装置であり、伝送系NC−busと
CPU5との間のデータ伝送を可能とする。
FIG. 3 is a block diagram of this Sabic device 10, in which an LCD 1 with a touch panel and a built-in printer 3 are connected to a CPU 5 via an MMI control device 4. In addition, the CPU 5 has an interface 6.
via external telephone 11 and public line/private line 12
A remote annunciator 13, an external printer 14, an external personal computer 15, and a service tool 16 are connected via an external interface 7. Note that 8 is a transmission control device that enables data transmission between the transmission system NC-bus and the CPU 5.

【0011】タッチパネル付LCD1は、バックライト
付LCD1−1の画面上全面にタッチパネル1−2を組
み付けて構成され、その画面上での表示に従いパネル面
を直接指でタッチすることにより、入力操作が可能であ
る。
[0011] The touch panel LCD 1 is constructed by assembling a touch panel 1-2 on the entire surface of the screen of a backlit LCD 1-1, and input operations can be performed by directly touching the panel surface with a finger according to the display on the screen. It is possible.

【0012】アナンシェータ2は、各種管理ポイントの
状態を各個に仕切られた仕切領域2−1〜2−mn に
て発光表示する赤色LED2a−1〜2a−mn およ
び緑色LED2b−1〜2b−mn を備え、仕切領域
2−1〜2−mn にはポイント名称が書き込まれてい
る。また、このポイント名称の書き込まれた仕切領域2
−1〜2−mn にはタッチセンサが敷設されており、
このタッチセンサをオンとすることにより、すなわち仕
切領域2−1〜2−mn にタッチすることにより、そ
のタッチした仕切領域の書き込みポイントに関してのア
ナログ情報が、7セグメントから構成されてなるディス
プレイ部2cに表示されるものとなっている。
The annunciator 2 has red LEDs 2a-1 to 2a-mn and green LEDs 2b-1 to 2b-mn that emit light to display the status of various management points in partitioned areas 2-1 to 2-mn. In addition, point names are written in the partition areas 2-1 to 2-mn. Also, partition area 2 where this point name is written
-1 to 2-mn are equipped with touch sensors.
By turning on this touch sensor, that is, by touching the partition areas 2-1 to 2-mn, analog information regarding the writing point of the touched partition area is displayed on the display section 2c, which is composed of 7 segments. This is what will be displayed on the screen.

【0013】組み込みプリンタ3としては、ストリップ
・チャート・プリンタを用いており、警報発生記録や操
作記録などを漢字(第1,第2水準)印字できる。
A strip chart printer is used as the built-in printer 3, and can print alarm occurrence records, operation records, etc. in Chinese characters (first and second level).

【0014】次に、このように構成されたセイビック装
置10において、その特徴とする機能について説明する
。すなわち、現在の電力デマンド制御による遮断状態を
知りたい場合について、その機能について説明する。
Next, the characteristic functions of the Sabic device 10 configured as described above will be explained. That is, when it is desired to know the current cut-off state due to power demand control, the function will be explained.

【0015】現在の電力デマンド制御による遮断状態を
知りたい場合、先ず、初期メニュー画面(図示せず)か
ら図1に示す電力系統画面102をタッチパネル付LC
D1上に出す。この電力系統画面102は、その電力系
統における各種ポイントを示すアイコン(絵文字)10
2−11〜102−17より構成されるポイント群表示
部102−1と、各種の関連グラフメニューを示すアイ
コン102−21〜102−23より構成される第1の
関連画面移行部102−2と、各種の制御プログラムメ
ニューを示すアイコン102−31〜102−34より
構成される第2の関連画面移行部102−3と、アイコ
ン102−41〜102−44より構成される操作キー
部102−4と、画面移行シンボルS1〜S4とを有す
る。
[0015] If you want to know the current cut-off state due to power demand control, first select the power system screen 102 shown in FIG. 1 from the initial menu screen (not shown) on the LC with touch panel.
Put it on D1. This power system screen 102 includes icons (pictograms) 10 indicating various points in the power system.
A point group display section 102-1 composed of points 2-11 to 102-17, and a first related screen transition section 102-2 composed of icons 102-21 to 102-23 indicating various related graph menus. , a second related screen transition section 102-3 consisting of icons 102-31 to 102-34 indicating various control program menus, and an operation key section 102-4 consisting of icons 102-41 to 102-44. and screen transition symbols S1 to S4.

【0016】この電力系統画面102において、関連画
面移行部102−3でのアイコンを選択してタッチする
と、そのタッチしたアイコンで示される関連制御プログ
ラムメニューの詳細情報が画面に移行表示されるものと
なり、その表示される詳細情報での設定内容を変更する
などして、電力系統の制御設定を行うことができる。但
し、電力デマンドを示すアイコン(電力デマンド表示部
)102−34については、このアイコン102−34
と操作キー部102−4でのアイコン(電デマ制御画面
移行キー)102−44をタッチすることにより、電力
デマンドの制御画面へ移行することができる。
On this power system screen 102, when an icon in the related screen transition section 102-3 is selected and touched, detailed information of the related control program menu indicated by the touched icon is transferred to the screen and displayed. It is possible to perform control settings for the power system by, for example, changing the settings in the displayed detailed information. However, regarding the icon 102-34 indicating power demand (power demand display section), this icon 102-34
By touching the icon (electronic hoax control screen transition key) 102-44 in the operation key section 102-4, it is possible to transition to the power demand control screen.

【0017】ここで、電力デマンド表示部102−34
での表示状態を見れば明らかなように、図示左側のブレ
ーカマークIが他のブレーカマークIIおよびIIIに
対し反転表示されている。ブレーカマークIはレベル■
での電力負荷群の遮断の有無を示し、ブレーカマークI
IおよびIIIはレベル■および■での電力負荷群の遮
断の有無を示す。すなわち、この例ではブレーカマーク
Iのみが反転表示されており、これにより、現在レベル
■で電力デマンド制御が行われているということを、視
覚的に一目で知ることができる。
[0017] Here, the power demand display section 102-34
As is clear from the display state, the breaker mark I on the left side of the figure is displayed in reverse with respect to the other breaker marks II and III. Breaker mark I is level ■
Breaker mark I indicates whether or not the power load group is interrupted at
I and III indicate whether or not the power load group is interrupted at levels ■ and ■. That is, in this example, only the breaker mark I is displayed in reverse video, so that it can be visually recognized at a glance that power demand control is currently being performed at level ■.

【0018】また、本実施例においては、ブレーカマー
クI〜IIIをキーとして、所望の電力デマンドレベル
に応ずる電力負荷群を、任意のタイミングで一括して発
停することができるものとなっている。例えば、ブレー
カマークIをタッチして、操作キー102−4でのアイ
コン(起動キー)102−41をタッチすると、レベル
■に応ずる電力負荷群の全てを起動させることができる
。また、ブレーカマークIをタッチして、アイコン(停
止キー)102−42をタッチすると、レベル■に応ず
る電力負荷群の全てを停止させることができる。
Furthermore, in this embodiment, using breaker marks I to III as keys, a group of power loads corresponding to a desired power demand level can be started and stopped all at once at any timing. . For example, by touching the breaker mark I and then touching the icon (activation key) 102-41 on the operation key 102-4, it is possible to activate all the power load groups corresponding to the level ■. Furthermore, by touching the breaker mark I and then touching the icon (stop key) 102-42, all of the power load groups corresponding to the level ■ can be stopped.

【0019】[0019]

【発明の効果】以上説明したことから明らかなように本
発明によると、その第1発明によると、電力系統画面を
表示することにより、その電力デマンド表示部にて一目
で現在の電力デマンド制御による遮断状態を知ることが
できるものとなり、過大な労力を必要とせず、手間がか
からないものとなる。また、その第2発明によると、電
力系統画面を表示することにより、その電力デマンド表
示部をキーとして所望の電力デマンドレベルに応ずる電
力負荷群を、任意のタイミングで一括して発停すること
ができ、状況に応じてフレキシブルに対応することがで
きるようになる。
Effects of the Invention As is clear from the above explanation, according to the first aspect of the present invention, by displaying the power system screen, it is possible to check the current power demand control at a glance on the power demand display section. It becomes possible to know the cut-off state, and it does not require excessive labor and time. Further, according to the second invention, by displaying the power grid screen, it is possible to collectively start and stop a group of power loads corresponding to a desired power demand level at any timing using the power demand display section as a key. You will be able to respond flexibly depending on the situation.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】図2に示したセイビック装置においてそのタッ
チパネル付LCD上に表示される電力系統画面を示す図
FIG. 1 is a diagram showing a power system screen displayed on an LCD with a touch panel in the Sabic device shown in FIG. 2;

【図2】本発明に係る施設管理装置の一実施例を示すセ
イビック装置の外観斜視図。
FIG. 2 is an external perspective view of a Sabic device showing an embodiment of the facility management device according to the present invention.

【図3】このセイビック装置のブロック図。FIG. 3 is a block diagram of this Sabic device.

【符号の説明】[Explanation of symbols]

1      タッチパネル付LCD 10      セイビック装置 102      電力系統画面 102−34   電力デマンド表示部102−41 
  起動キー 102−42   停止キー 102−44   電デマ制御画面移行キーI    
  ブレーカマーク II      ブレーカマーク III     ブレーカマーク
1 LCD with touch panel 10 Sabic device 102 Power system screen 102-34 Power demand display section 102-41
Start key 102-42 Stop key 102-44 Telephone hoax control screen transition key I
Breaker Mark II Breaker Mark III Breaker Mark

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】    電力系統画面を表示し得る表示手
段を備えた施設管理装置であって、前記電力系統画面は
、その電力系統における電力デマンドレベルおよびその
レベルに応ずる電力負荷群の遮断の有無を視覚的に表示
する電力デマンド表示部を有していることを特徴とする
施設管理装置。
1. A facility management device comprising display means capable of displaying an electric power system screen, wherein the electric power system screen displays the electric power demand level in the electric power system and the presence or absence of interruption of electric power load groups corresponding to the level. A facility management device comprising a power demand display unit that visually displays power demand.
【請求項2】    請求項1において、電力デマンド
表示部をキーとして所望の電力デマンドレベルを選択で
きるものとし、その選択したレベルに応ずる電力負荷群
の発停を一括して行い得ることを特徴とする施設管理装
置。
2. Claim 1, characterized in that a desired power demand level can be selected using the power demand display section as a key, and a group of power loads can be started and stopped in a batch according to the selected level. facility management equipment.
JP4408191A 1991-02-18 1991-02-18 Power demand controller Expired - Lifetime JP2736826B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4408191A JP2736826B2 (en) 1991-02-18 1991-02-18 Power demand controller

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4408191A JP2736826B2 (en) 1991-02-18 1991-02-18 Power demand controller

Publications (2)

Publication Number Publication Date
JPH04265625A true JPH04265625A (en) 1992-09-21
JP2736826B2 JP2736826B2 (en) 1998-04-02

Family

ID=12681670

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4408191A Expired - Lifetime JP2736826B2 (en) 1991-02-18 1991-02-18 Power demand controller

Country Status (1)

Country Link
JP (1) JP2736826B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003244849A (en) * 2002-02-14 2003-08-29 Yanmar Co Ltd Control system for generator system
WO2009066740A1 (en) * 2007-11-20 2009-05-28 Panasonic Electric Works Co., Ltd. Energy management system
JP2016158494A (en) * 2016-04-01 2016-09-01 ソニー株式会社 Control apparatus, control method, and program

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5649611A (en) * 1977-04-25 1981-05-06 Hitachi Ltd Method of indicating system configuration for power system
JPS56115134A (en) * 1980-02-15 1981-09-10 Matsushita Electric Works Ltd Power distributing device
JPS6096138A (en) * 1983-10-28 1985-05-29 株式会社東芝 Generator plant automatic operation monitoring and operating device
JPS6225839A (en) * 1985-07-24 1987-02-03 株式会社東芝 Power system data display for receiving substation equipment
JPH01234028A (en) * 1988-03-15 1989-09-19 Kyushu Electric Power Co Inc Apparatus for displaying distributing-line recovery data

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5649611A (en) * 1977-04-25 1981-05-06 Hitachi Ltd Method of indicating system configuration for power system
JPS56115134A (en) * 1980-02-15 1981-09-10 Matsushita Electric Works Ltd Power distributing device
JPS6096138A (en) * 1983-10-28 1985-05-29 株式会社東芝 Generator plant automatic operation monitoring and operating device
JPS6225839A (en) * 1985-07-24 1987-02-03 株式会社東芝 Power system data display for receiving substation equipment
JPH01234028A (en) * 1988-03-15 1989-09-19 Kyushu Electric Power Co Inc Apparatus for displaying distributing-line recovery data

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003244849A (en) * 2002-02-14 2003-08-29 Yanmar Co Ltd Control system for generator system
WO2009066740A1 (en) * 2007-11-20 2009-05-28 Panasonic Electric Works Co., Ltd. Energy management system
JP2009130983A (en) * 2007-11-20 2009-06-11 Panasonic Electric Works Co Ltd Energy management system
JP2016158494A (en) * 2016-04-01 2016-09-01 ソニー株式会社 Control apparatus, control method, and program

Also Published As

Publication number Publication date
JP2736826B2 (en) 1998-04-02

Similar Documents

Publication Publication Date Title
US5295062A (en) Facility management apparatus having touch responsive display screens
KR960007511B1 (en) Building management system
US20110126144A1 (en) Equipment management apparatus
RU2010153223A (en) EXCHANGE OF INFORMATION BETWEEN THE USER INTERFACE OF THE DOCUMENT EDITOR'S INTERIOR SPACE AND THE USER INTERFACE OF THE DOCUMENT EDITOR'S EXTERNAL INTERFACE
JP6079358B2 (en) Air conditioner remote control device
JPH04265625A (en) Plant managing device
JP2563210B2 (en) Facility management device
JP3721628B2 (en) Equipment management device
CN107017703A (en) A kind of Auto-Test System Alternating Current Power Supply management and environmental monitoring installation
RU140341U1 (en) MICROPROCESSOR RELAY PROTECTION AND AUTOMATION SYSTEMS
JP2612778B2 (en) Facility management device
JP2011214775A (en) Centralized controller for air conditioner
JP2016018395A (en) Device management apparatus, device management method, and display device
US20120133481A1 (en) Modular Control and Indicating Panel, Its Use and a Method of Controlling Building Alarm Systems
JPH0338715A (en) Intelligent switch system
JPH09222914A (en) Facility managing device
JPH01240904A (en) Building control system
JP3018306B2 (en) Facility management device
US11740762B2 (en) Equipment management apparatus and equipment management screen generating method
JPH03214397A (en) Facility managing device
JPH03214396A (en) Annunciator
JPH07129873A (en) Monitor and control equipment of building managing system
JPH04116800A (en) Indicating lamp test system
JPH06222882A (en) Liquid crystal operation display switch terminal equipment
KR20230161260A (en) Household power controller

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080116

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090116

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100116

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100116

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110116

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110116

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120116

Year of fee payment: 14

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120116

Year of fee payment: 14