JPH0270814A - Water-shield structure and sheet for reclamation - Google Patents

Water-shield structure and sheet for reclamation

Info

Publication number
JPH0270814A
JPH0270814A JP63223839A JP22383988A JPH0270814A JP H0270814 A JPH0270814 A JP H0270814A JP 63223839 A JP63223839 A JP 63223839A JP 22383988 A JP22383988 A JP 22383988A JP H0270814 A JPH0270814 A JP H0270814A
Authority
JP
Japan
Prior art keywords
water
sheet
caisson
blocking
rubble mound
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP63223839A
Other languages
Japanese (ja)
Other versions
JPH0619127B2 (en
Inventor
Yukio Noguchi
野口 幸夫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seibu Polymer Kasei KK
Original Assignee
Seibu Polymer Kasei KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seibu Polymer Kasei KK filed Critical Seibu Polymer Kasei KK
Priority to JP63223839A priority Critical patent/JPH0619127B2/en
Publication of JPH0270814A publication Critical patent/JPH0270814A/en
Publication of JPH0619127B2 publication Critical patent/JPH0619127B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

PURPOSE:To exactly stop water as well as prevent damage to water-shield sheets by a method in which one end of water-shield sheets to be laid on the bottom of water is held between a caisson and a part of rubble mound, and a sheet protector and a water stopper are provided. CONSTITUTION:Alluvial silt layer 2 is removed from the rockbed 1 of the seabed, sand 3 is placed on the rockbed 1, rubble mound 4 is constructed on the sand 3, and a caisson 5 is set on the mound 4. In the reclamation work of water-shield structure, water-shield sheets 7 are provided through the mound 4from a part of the inside bottom of the caisson 5 to a given place of the bottom 6 of water, and the caisson 5 is set by holding one end of each sheet 7. A sheet protector 8 is also set between the downside of the sheets 7 and the upside of the mound 4, and a water stopper 9 is provided between the upside of the sheets 7 and the downside of the caisson 5 to prevent the leakage of water from the uneven portion of the mound 4.

Description

【発明の詳細な説明】 [産業上の利用分野] この発明は、捨石マウンドとケーソンを用いて護岸を形
成し、水面を埋立てする場合の遮水構造及び遮水シート
に関し、海面を埋立てて廃棄物最終処分場とする場合に
適用して好適なものである。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a water-shielding structure and a water-shielding sheet for reclaiming the water surface by forming a seawall using rubble mounds and caissons. It is suitable for use in cases where a waste disposal site is used as a final waste disposal site.

[従来の技術〕 最近の廃棄物最終処理方法として、従来の内陸埋立てに
代り、水面埋立てが行われるようになっており、海面へ
の埋立ても行われるようになっている。
[Prior Art] As a recent final waste disposal method, water surface reclamation has been used instead of conventional inland reclamation, and sea surface reclamation has also come to be performed.

このような廃棄物の最終処理として海面埋立てを行なう
場合には、廃棄物からの有害物質などが外海に流出しな
いようにしなければならない。
When landfilling at sea surface is the final treatment for such waste, it is necessary to prevent harmful substances from the waste from flowing into the open sea.

そこで、従来は、埋立てる部分の外側を囲むように一般
の構造物としての護岸を構築し、その内側部分を相当幅
広く有害物質を含まない浚渫土や建設残土などによって
埋立てるようにし、中央部分に廃棄物を埋立てるように
して廃棄物からの浸出液の透水距離を長くするようにす
ることが行われている。
Conventionally, a revetment as a general structure was constructed to surround the outside of the area to be reclaimed, and the inner part was filled in with dredged soil or construction surplus soil that did not contain harmful substances, and the central part was The current practice is to dispose of waste in landfills so that the water permeation distance for leachate from the waste is increased.

また、矢板を用いて護岸を横築する場合には、二重鋼管
矢板を用い、鋼管自体の腐蝕防止や矢板の継手部分の止
水等に複雑な手法を採用するようにし、さらに、埋立地
の底部分に透水性のない厚い粘土層がある場所を選定し
たり、不透水層に至るまで矢板を深く打ち込むようにし
て水底部からの漫上液の流出も防止するようにしている
In addition, when constructing a seawall horizontally using sheet piles, double steel pipe sheet piles should be used and complicated methods should be used to prevent corrosion of the steel pipes themselves and to stop water at the joints of the sheet piles. The site is selected to have a thick clay layer that is not permeable to water at the bottom, and the sheet piles are driven deep into the impermeable layer to prevent liquid from flowing out from the bottom of the water.

[発明が解決しようとする課題] このような一般構造物としての護岸を構築する場合には
、埋立ての主目的である廃棄物の有効投入容積が護岸の
内側部分に埋立てた浚渫土などで小さくなってしまうと
いう問題がある。
[Problems to be Solved by the Invention] When constructing a seawall as a general structure like this, the effective input volume of waste, which is the main purpose of landfilling, is limited to dredged soil etc. reclaimed in the inner part of the seawall. The problem is that it becomes smaller.

また、矢板を用いる護岸を構築する場合には、護岸の内
側を全て埋め立てに使用することができ、有効投入容積
を大きくすることができるのであるが、護岸の横築に要
する費用がかさむとともに、埋立地として選定できる場
所に大きな制約が生じるという問題がある。
In addition, when constructing a seawall using sheet piles, the entire inside of the seawall can be used for landfill, increasing the effective input volume, but this increases the cost of building the seawall horizontally. There is a problem in that there are major restrictions on the locations that can be selected as landfill sites.

そこで、比較的簡単に護岸を形成することができるケー
ソンによる重力式護岸を用い、これを内陸埋立てに採用
されている遮水シートを用いて遮水し、廃棄物の埋め立
てに使用することが考えられている。
Therefore, it is possible to use a gravity-type revetment using caisson, which is relatively easy to form a revetment, and use it to block water using a water-shielding sheet that is used for inland reclamation, and use it for landfilling waste. It is considered.

ところが、このようなケーソンによる重力式護岸では、
通常、水底地盤上に捨石マウンドを作り、この上にケー
ソンを据え付けることが行われるため、ケーソン底面の
仕上げ状態によってはその凹凸によって遮水シートが破
れたり、捨石マウンドの凹凸によって遮水シートが破れ
るなどの問題がある。
However, with such a gravity type seawall using a caisson,
Normally, a rubble mound is created on the underwater ground and a caisson is installed on top of this, so depending on the finish condition of the bottom of the caisson, the unevenness of the bottom surface of the caisson may cause the impermeable sheet to tear, or the unevenness of the rubble mound may cause the impermeable sheet to tear. There are problems such as.

この発明は、かかる従来技術の課題に鑑みてなされたも
ので、ケーソンを用いて護岸を横築して埋立てる場合に
あっても完全に遮水することができる埋立てにおける遮
水構造を提供しようとするものである。
This invention has been made in view of the problems of the prior art, and provides a water-blocking structure in a landfill that can completely block water even when a bank is built horizontally using caissons to block water. This is what I am trying to do.

・また、水底部への敷設を確実に行なうことができる埋
立てにおける遮水構造を提供しようとするものである。
・It also aims to provide a water-blocking structure in landfills that can be reliably installed at the bottom of the water.

さらに、ケーソン自体の遮水も確実に行なうことができ
る埋立てにおける遮水構造を提供しようとするものであ
る。
Furthermore, it is an object of the present invention to provide a water-shielding structure in a landfill that can reliably water-shield the caisson itself.

また、ケーソンの沈下や水底部の沈下があってもシート
を破損することなく確実に遮水することができる遮水シ
ートを提供しようとするものである。
Another object of the present invention is to provide a water-blocking sheet that can reliably block water without damaging the sheet even if the caisson sinks or the bottom of the water sinks.

[課題を解決するための手段] 上記課題を解決するためこの発明の埋立てにおける遮水
構造は、捨石マウンド上に載置されたケーソンで仕切ら
れた内側を埋立てる場合の遮水構造において、水底部に
敷設される遮水シートの一端部をケーソンと捨石マウン
ドの少なくとも一部分に挾み込んで設置し、この遮水シ
ート下面と捨石マウンド上面との間にシート保護部材を
設けるとともに、前記遮水シート上面とケーソン下面と
の間に止水部材を設けたことを特徴とする。
[Means for Solving the Problems] In order to solve the above problems, the water-blocking structure for landfilling of the present invention includes the following: One end of the water-shielding sheet to be laid at the bottom of the water is sandwiched between the caisson and at least a portion of the rubble mound, and a sheet protection member is provided between the bottom surface of the water-shielding sheet and the top surface of the rubble mound, and It is characterized in that a water stop member is provided between the upper surface of the water sheet and the lower surface of the caisson.

また、この発明の埋立てにおける遮水構造は、前記遮水
シートをおもり固定部材を介して取付けたおもりで水底
部に敷設したことを特徴とする。
Further, the water-blocking structure for landfilling according to the present invention is characterized in that the water-blocking sheet is laid on the bottom of the water using a weight attached via a weight fixing member.

さらに、この発明の埋立てにおける遮水構造は、捨石マ
ウンド上に載置されたケーソンで仕切られた内側を埋立
てる場合の遮水構造において、水底部に敷設した遮水シ
ートの一部を捨石マウンドとケーソンとの間に挾み込ん
で設置し、該挾まれた部分の遮水シートと一体もしくは
接合された遮水シートをケーソンの側壁に沿って配置し
たことを特徴とする。
Furthermore, in the water-blocking structure in the landfill of this invention, in the water-blocking structure when the inside is partitioned by a caisson placed on a rubble mound, a part of the water-blocking sheet laid at the bottom of the water is replaced with rubble. It is characterized in that the water-shielding sheet is sandwiched between the mound and the caisson, and is integrated with or joined to the water-shielding sheet in the sandwiched portion, and is disposed along the side wall of the caisson.

また、この発明の遮水シートは、捨石マウンド上に載置
されたケーソンで仕切られた内側を遮水して埋立てる場
合の遮水シートにおいて、水底部に敷設される不透水性
のシートに変形を許容するひだを形成し、各ひだの間に
敷設状態で形状を保つ保形部材を介装したことを特徴と
するものである。
In addition, the water-blocking sheet of the present invention can be used as a water-blocking sheet to be laid at the bottom of water in a case where the inside of a caisson placed on a rubble mound is water-blocked and reclaimed. It is characterized by forming folds that allow deformation, and interposing a shape-retaining member that maintains the shape when laid between each fold.

[作用] このような埋立てにおける遮水構造によれば、水底部に
敷設される遮水シートの一端部を捨石マウンドとケーソ
ンの間の全体もしくは一部分に挾み、この部分の遮水シ
ートをシート保護部材によって捨石マウンドの凹凸から
保護するとともに、止水部材によってケーソン下面の凹
凸による漏水を防止するようにしており、遮水シートの
損傷を防止しつつ確実に遮水するようにしている。
[Function] According to such a water-blocking structure in a landfill, one end of the water-blocking sheet laid at the bottom of the water is sandwiched between the whole or a part of the space between the rubble mound and the caisson, and the water-blocking sheet in this part is sandwiched between the rubble mound and the caisson. The sheet protection member protects from the unevenness of the rubble mound, and the water stopper prevents water from leaking due to the unevenness of the lower surface of the caisson, ensuring reliable water shutoff while preventing damage to the water shielding sheet.

また、遮水シートにおもりを固定するおもり固定部材を
取付け、これによっておもりを固定して遮水シートの浮
き上がりを防止し、確実な敷設を可能とし、遮水性の良
い遮水構造としている。
In addition, a weight fixing member is attached to the water-shielding sheet, which fixes the weight and prevents the water-shielding sheet from lifting up, allowing reliable installation and creating a water-shielding structure with good water-shielding properties.

さらに、捨石マウンドとケーソンとで挾まれた部分の遮
水シートと一体もしくは接合された遮水シートをケーソ
ンの側壁に沿って配置するようにしており、ケーソン自
体からの浸水をも防止するようにしている。
Furthermore, a water-shielding sheet that is integrated with or joined to the water-shielding sheet in the area sandwiched between the rubble mound and the caisson is placed along the side wall of the caisson to prevent water from seeping in from the caisson itself. ing.

また、遮水シートに変形を許容するひだを形成するとと
もに、このひだの間に保形部材を介装しておき、敷設状
態でもひだを形成した状態としてケーソン自体の沈下や
水底部の沈下によっても返水シートが破損しないように
して、確実な遮水を可能としている。
In addition, in addition to forming folds in the water-shielding sheet to allow deformation, a shape-retaining member is interposed between the folds. This also prevents the water return sheet from being damaged, allowing for reliable water-blocking.

[実施例] 以下、この発明の実施例を図面に基づき詳細に説明する
[Example] Hereinafter, an example of the present invention will be described in detail based on the drawings.

この発明の埋立てにおける遮水S遺が適用される重力式
護岸は、例えば第1図に示すように、海底の岩盤1上の
沖積シルト層2が取り除かれて置換砂3が積まれ、その
上に捨石マウンド4が作られ、この捨石マウンド4上に
ケーソン5が載置されて構成され、大型のケーソン5を
使用する場合には、ケーソン5の両端底部に対応して捨
石マウンド4が分割して作られ、中間部は置換砂3とな
っている。なお、捨石マウンド4は分割せず連続して置
換砂3上に設けられたものでもよい。
For example, as shown in Fig. 1, the gravity type seawall to which the water-blocking S remains of the present invention is applied is constructed by removing the alluvial silt layer 2 on the bedrock 1 of the seabed and piling up replacement sand 3. A rubble mound 4 is made on top, and a caisson 5 is placed on this rubble mound 4. When using a large caisson 5, the rubble mound 4 is divided corresponding to the bottom of both ends of the caisson 5. The middle part is made of replacement sand 3. Note that the rubble mound 4 may be continuously provided on the replacement sand 3 without being divided.

このようなケーソン5による重力式護岸は、海面埋立て
を行なう部分の外周を仕切るように構築されるが、特に
、捨石マウンド4の部分の透水性が高く、この捨石マウ
ンド4部分及び水底部6のケーソン5近傍など、第1図
中破線で示す部分を遮水する必要がある。
Such a gravity-type seawall using the caisson 5 is constructed so as to partition the outer periphery of the area where sea surface reclamation is to be carried out, but the water permeability is particularly high in the rubble mound 4 area, and the rubble mound 4 area and the water bottom 6 It is necessary to block water from the area shown by the broken line in Figure 1, such as the vicinity of caisson 5.

このような埋立てにおける遮水構造は、第2図に拡大し
て示すように、埋立てが行われるケーソン5の内側の底
の一部分(ケーソン5の底金体でも良い)・から捨石マ
ウンド4を経て水底部6の所要位置まで、遮水シート7
を設けることで遮水する。
As shown in an enlarged view in Fig. 2, the water-blocking structure in such a landfill is a part of the inner bottom of the caisson 5 (which may also be the bottom metal body of the caisson 5) where the landfill is carried out, to the rubble mound 4. The water-blocking sheet 7 is
Water is blocked by providing a

この遮水シート7は予め捨石マウンド4の上面から水底
部6の所定の位置まで敷設した後、ケーソン5を据え付
けることで、遮水シート7の一端部を挾み込んで設置す
る。
This water-shielding sheet 7 is laid in advance from the top surface of the rubble mound 4 to a predetermined position on the water bottom 6, and then the caisson 5 is installed so that one end of the water-shielding sheet 7 is sandwiched between the two.

この遮水シート7としては、不透水性のシートが使用さ
れ、厚さについては設計基準に基づいて適宜選択される
ものであり、例えば厚さが1〜31′l1m程度のゴム
シートが使用されるが、この他にも他のゴム系のシート
や合成樹脂系のシート、さらには、アスファルト系のシ
ートなどが使用でき、具体的には、次に示すようなもの
が挙げられる。
A water-impermeable sheet is used as the water-blocking sheet 7, and the thickness is appropriately selected based on design standards. For example, a rubber sheet with a thickness of about 1 to 31'l1m is used. However, other rubber sheets, synthetic resin sheets, asphalt sheets, etc. can also be used, and specific examples include the following.

遮水シートとして使用できるシートの種類合成ゴム系、 加硫ゴム系:エチレンプロピレンゴム 非加硫ゴム系ニブチルゴム、 クロロスルフォン化ポリエチレン 合成樹脂系 塩化ビニル系:ボリ塩化ビニル樹脂 エチレン系:ポリエチレン樹脂 塩素化ポリエチレン樹脂 エチレンビニルアセデート樹脂 アスファルト系 ゴムアスファルト このような遮水シート7を用いて遮水する場合には、ケ
ーソン5の底部分と捨石マウンド4の間を水蜜状態とす
ること及びケーソン5の底部分で遮水シート7が損傷し
ないようにすることが重要であり、特にケーソン5の底
で挾まれる遮水シート7の部分が岩石など凹凸の大きい
捨石マウンド4と接触することによる損傷を防止するよ
うにしなければならない。
Types of sheets that can be used as water-shielding sheets: Synthetic rubber, vulcanized rubber: ethylene propylene rubber, non-vulcanized rubber, nibutyl rubber, chlorosulfonated polyethylene synthetic resin, vinyl chloride: polyvinyl chloride resin, ethylene: polyethylene resin, chlorinated Polyethylene resin Ethylene vinyl acedate resin Asphalt-based rubber Asphalt When using such a water-blocking sheet 7 to block water, the space between the bottom of the caisson 5 and the rubble mound 4 should be kept in a wet state, and the bottom of the caisson 5 should be It is important to prevent the water-shielding sheet 7 from being damaged in some parts, and in particular, to prevent damage caused by the part of the water-shielding sheet 7 that is sandwiched at the bottom of the caisson 5 coming into contact with the rubble mound 4 that has large irregularities such as rocks. You must do so.

このため、ケーソン5と捨石マウンド4との間には、シ
ート保護部材8が設けられ、捨石マウンド4を構成する
岩石の表面を覆うことで、遮水シート7の破損を防止す
るようになっている。なお、保護部材8は少なくともケ
ーソン5の底面の下部に位置する捨石マウンド4上に設
けることが必要であるが、更に、捨石マウンド4の法尻
まで設けておくことが遮水シート7の損傷を防ぐ上で好
ましい。
For this reason, a sheet protection member 8 is provided between the caisson 5 and the rubble mound 4, and by covering the surface of the rocks constituting the rubble mound 4, the water-blocking sheet 7 is prevented from being damaged. There is. Note that it is necessary to provide the protective member 8 at least on the rubble mound 4 located at the lower part of the bottom of the caisson 5, but it is also necessary to provide it up to the bottom of the rubble mound 4 to prevent damage to the water-shielding sheet 7. Preferable for prevention.

このシート保護部材8としては、第2図中に抽出してケ
ーソン5を捨石マウンド4上に設置する前の状態を示す
ように、ゴム板(好ましくは硬度40度以下の軟質ゴム
板)が使用され、その厚さが捨石マウンド4の不陸より
も厚くしてあり、例えば捨石マウンド4の予想される不
陸:±5CIIlに対してシート保護部材8を10Cm
程度の厚さにする。
As this sheet protection member 8, a rubber plate (preferably a soft rubber plate with a hardness of 40 degrees or less) is used, as shown in FIG. 2, which shows the state before the caisson 5 is installed on the rubble mound 4. The thickness of the sheet protection member 8 is made thicker than the unevenness of the rubble mound 4, for example, the expected unevenness of the rubble mound 4: ±5 CIIl, the sheet protection member 8 is made 10 cm thick.
Make it as thick as possible.

こうしてシート保護部材8を遮水シート7の下面と捨石
マウンド4の上面との間に設けることで、第2図に示す
ように、ケーソン5を載せると、捨石マウンド4の不陸
に対してゴム板が変形してなじみ、しかも岩石などの表
面がスポンジ板などで覆われ、クツション効果を持つた
め遮水シート7が破れることがなくなる。
By providing the sheet protection member 8 between the lower surface of the water-shielding sheet 7 and the upper surface of the rubble mound 4 in this way, when the caisson 5 is placed on it, as shown in FIG. The board deforms and adapts, and the surface of the rock or the like is covered with the sponge board, which has a cushioning effect, so that the water-shielding sheet 7 is prevented from tearing.

また、遮水シート7の上面とケーソン5の下面との間に
は、ケーソン5の底面に凹凸があっても完全にシールす
ることができるように、止水部材9が設けられている。
Further, a water stop member 9 is provided between the top surface of the water shield sheet 7 and the bottom surface of the caisson 5 so that even if the bottom surface of the caisson 5 has irregularities, a complete seal can be achieved.

この止水部材9としては、第2図中に抽出してケーソン
5を捨石マウンド4上に設置する前の状態を示すように
、ゴム板(好ましくは硬度40度以下の軟質ゴム板)が
使用され、その厚さがケーソン5の不陸よりも厚くして
あり、例えばケーソン5の予想される不陸:±ICIに
対して止水部材9を3CII程度の厚さにする。
As this water stop member 9, a rubber plate (preferably a soft rubber plate with a hardness of 40 degrees or less) is used as shown in FIG. 2, which shows the state before the caisson 5 is installed on the rubble mound 4. The water stop member 9 is made thicker than the unevenness of the caisson 5, for example, the thickness of the water stop member 9 is about 3 CII with respect to the expected unevenness of the caisson 5: ±ICI.

こうして止水部材9を遮水シート7の上面とケーソン5
の下面との間に設けることで、第2図に示すように、ケ
ーソン5を載せると、ケーソン5の不陸に対して止水部
材9が変形してなじみ、しかもケーソン5と密着するた
め水密状態となり、完全に遮水される。
In this way, the water-stopping member 9 is connected to the top surface of the water-stopping sheet 7 and the caisson 5.
As shown in Fig. 2, when the caisson 5 is placed on the water stop member 9, it deforms and adapts to the unevenness of the caisson 5, and since it is in close contact with the caisson 5, it is watertight. state, completely watertight.

このようなシート保護部材8及び止水部材9は、遮水シ
ート7の所定の位置に耐水性接着剤などによって接着さ
れるなどして遮水シート7の敷設作業の開始からケーソ
ン5の設置までの作業中、離脱しないようにされたり、
溶着など他の接合法により接合されたり、ケーソン5の
底面に接合されたり、あるいは別体のまま敷設されてケ
ーソン5が載せられる。
Such a sheet protection member 8 and a water stop member 9 are adhered to predetermined positions of the water-shielding sheet 7 with a water-resistant adhesive, etc., from the start of the work of laying the water-shielding sheet 7 to the installation of the caisson 5. During the work, you are prevented from leaving,
The caisson 5 may be joined by other joining methods such as welding, joined to the bottom surface of the caisson 5, or laid as a separate body on which the caisson 5 is mounted.

また、これらシート保護部材8及び止水部材9としては
、第2図に示したゴム板を用いる場合のほか、例えば第
3図(、a)に示すように、シート保護部材8として中
空円筒状のゴムホースを複数本並べこれを耐水性の紐な
どを通して縛ることで板状にしたものを使用し、止水部
材9として断面半円状のゴム製の条材を用い、これらを
接着剤で遮水シート7に接着したり、他の方法で接合し
たり、単に並べるなどして遮水シートの保護及び止水を
行なうようにすることもできる。
In addition to using the rubber plate shown in FIG. 2 as the sheet protection member 8 and the water-stopping member 9, for example, as shown in FIG. A plurality of rubber hoses are lined up and tied through a water-resistant string to form a plate. A rubber strip with a semicircular cross section is used as the water stopper 9, and these are blocked with adhesive. It is also possible to protect the water-shielding sheet and stop water by adhering it to the water-shielding sheet 7, joining it by other methods, or simply arranging it.

さらに、同図(b)に示すように、シート保護部材8と
して板状のゴムの下面に断面弁形の湧等面が台形状のゴ
ム製の条材を用い、これらを接着剤で遮水シート7に接
着したり、他の方法で接合したり、単に並べるなどして
遮水シートの保護及び止水を行なうようにすることもで
きる。
Furthermore, as shown in FIG. 2(b), a rubber strip with a valve-shaped cross-section and a trapezoidal spring surface is used as the sheet protection member 8 on the lower surface of the rubber plate, and these are waterproofed with adhesive. It is also possible to protect the water-blocking sheet and stop water by adhering it to the sheet 7, joining it by other methods, or simply arranging it.

また、同図(C)に示すように、シート保護部材8とし
てスポンジ板を用い、止水部材9として断面が三角形状
のゴム製の条材を用い、これらを接着剤で遮水シート7
に接着したり、他の方法で接合したり、単に並べるなど
して遮水シートの保護及び止水を行なうようにすること
もできる。なお、上記保護部材8及び止水部材9の素材
はゴム製に限るものではなく、合成樹脂であってもよい
In addition, as shown in Figure (C), a sponge board is used as the sheet protection member 8, a rubber strip with a triangular cross section is used as the water stopper member 9, and these are glued to the water cutoff sheet 7.
It is also possible to protect the water-shielding sheet and stop water by adhering it to the water-shielding sheet, joining it by other methods, or simply arranging it. Note that the material of the protection member 8 and the water stopper member 9 is not limited to rubber, and may be made of synthetic resin.

さらに、図示省略したが、第2図及び第3図(a)、(
b)、(c)で説明したシート保護部材8及び止水部材
9を相互に組み合わせたものなどを用いて構成しても良
い。
Furthermore, although not shown, FIGS. 2 and 3 (a), (
The sheet protection member 8 and the water stop member 9 described in b) and (c) may be combined with each other.

また、シート保護部材8及び止水部材9として板木、条
材を用いるほか、シート状、マット状のものも使用でき
更に、捨石マウンド4上にアスファルトを被覆したり、
遮水シート7上やケーソン5の底面にアスファルトを被
覆するようにしても良く、これらを予めシート状にした
アスファルトマットを用いるようにしても良い。
In addition to using wood boards and strips as the sheet protection member 8 and the water-stopping member 9, sheet-like and mat-like materials can also be used.
The water-shielding sheet 7 and the bottom of the caisson 5 may be coated with asphalt, or an asphalt mat formed from these sheets in advance may be used.

さらに、シート保護部材8としてゴム(好ましくは硬度
40度以下の軟質ゴム)や合成樹脂などの網状のものや
ハニカム構造のもの、あるいは、不織布などのマット状
のものを用いるようにしてもよい。
Furthermore, the sheet protection member 8 may be made of rubber (preferably soft rubber with a hardness of 40 degrees or less), a synthetic resin, or a net-like or honeycomb structure, or a mat-like material such as a nonwoven fabric.

また、止水部材9として独立気泡のスポンジ板を用いる
ようにしても良い。
Furthermore, a closed cell sponge plate may be used as the water stop member 9.

このようにいずれの構造のシート保護部材8及び止水部
材9を用いる場合にあっても、捨石マウンド4上にシー
ト保護部材8、遮水シート7及び止水部材9を順に置い
てケーソン5を載せると、ケーソン5の荷重によりシー
ト保護部材8が捨石マウンド4に押し付けられてその凹
部に充填され、捨石マウンド4を覆うとともに、全体の
体積が圧縮された状態となり、止水部材9も同様にケー
ソン5の荷重によりその体積が圧縮されケーソン5の許
容される平滑度の範囲の不陸が埋められ、なじんだ状態
となる。
Regardless of which structure of the sheet protection member 8 and the water stoppage member 9 are used, the sheet protection member 8, the waterstop sheet 7, and the waterstop member 9 are placed in this order on the rubble mound 4, and the caisson 5 is installed. When placed, the sheet protection member 8 is pressed against the rubble mound 4 by the load of the caisson 5 and is filled into the recess, covering the rubble mound 4 and compressing the overall volume, and the water stop member 9 is also compressed. The volume of the caisson 5 is compressed by the load, and unevenness within the allowable smoothness range of the caisson 5 is filled, resulting in a smooth state.

したがって、シート保護部材8によって遮水シート7が
保護されると同時に、止水部材9によってケーソン5の
底面に多少の不陸があっても、あるいは遮水シート7に
広幅加工のための継ぎ目などわずかな厚みの差があって
もこれを吸収し、完全な密着状態として止水される。
Therefore, the water-blocking sheet 7 is protected by the sheet protection member 8, and at the same time, the water-blocking member 9 protects the water-blocking sheet 7 even if there is a slight unevenness on the bottom surface of the caisson 5, or if the water-blocking sheet 7 has a seam for widening. Even if there is a slight difference in thickness, this will be absorbed and the water will be completely sealed.

このような遮水シート7による遮水構造では、遮水シー
ト7上にケーソン5を載せるまで及び水底部6の遮水シ
ート7上に廃棄物などの埋立が開始されるまで、遮水シ
ート7を所定の位置に敷設した状態にしておく必要があ
る。
In such a water-shielding structure using the water-shielding sheet 7, the water-shielding sheet 7 is used until the caisson 5 is placed on the water-shielding sheet 7 and until the landfilling of waste and the like is started on the water-shielding sheet 7 at the water bottom 6. must be kept in place.

このため、第4図に示すように、遮水シート7の所定の
縁部分等におもり10を固定できるようにしており、お
もり固定部材11が多数設けられている。
For this reason, as shown in FIG. 4, a weight 10 can be fixed to a predetermined edge portion of the water-blocking sheet 7, and a large number of weight fixing members 11 are provided.

この場合に使用されるおもり10としては、大量に得ら
れ、しかも安価である必要から、例えば土のうやサンド
バックが用いられる。
The weight 10 used in this case is, for example, a sandbag or a sandbag because it can be obtained in large quantities and is inexpensive.

そして、おもり固定部材11としては、例えば第5図(
a)に示すように、遮水シート7の所定の位置に上部に
ファスナllaを備えた合成樹脂製などの袋11bを接
着剤や溶着法などによって接合しておき、この袋flb
の内部にサンドバック等のおもり10を入れた後、ファ
スナllaで綴じることで固定するものが使用される。
As the weight fixing member 11, for example, as shown in FIG.
As shown in a), a bag 11b made of synthetic resin or the like with a fastener lla on the upper part is bonded to a predetermined position of the water-shielding sheet 7 by adhesive or welding, and this bag flb
After putting a weight 10 such as a sandbag inside the bag, it is fixed by binding it with a fastener lla.

また、同図(b)に示すように、合成樹脂などの耐水性
シートllcをおもり固定部材11として用い、この中
央部を遮水シート7に接着したり、接合しておき、おも
り10であるサンドバック等を耐水性シートllcの中
央部に載せた後、この耐水性シートllcを風呂敷のよ
うにしておもり10を包んで固定するものを使用しても
良い。
In addition, as shown in FIG. 2(b), a water-resistant sheet llc made of synthetic resin or the like is used as the weight fixing member 11, and the center portion thereof is adhered or joined to the water-blocking sheet 7 to form the weight 10. It is also possible to use a method in which a sand bag or the like is placed on the center of the water-resistant sheet llc, and then this water-resistant sheet llc is used like a wrapping cloth to wrap and fix the weight 10.

さらに、同図(c)に示すように、おもり固定部材11
として二つのL字状のゴム又は合成樹脂等の係止部材l
idと耐水製合繊バンドlieとを組み合わせたものを
用い、おもり10の大きさに対応して二つのL字状の係
止部材lidを接着するとともに、これらの係止部材1
1dと遮水シート7との間にバンドlieを設けておき
、係止部材lidの上にサンドバック等のおもり10を
置いた後、バンドlieで縛ったり、あるいはバンドl
ieの両端部にベルクロファスナ(マジックテープ)1
1fを取付け、これらベルクロファスナ(マジックテー
プ)11fを係合して連結するようにして固定するもの
であっても良い。
Furthermore, as shown in the same figure (c), the weight fixing member 11
Two L-shaped locking members l made of rubber or synthetic resin, etc.
ID and a waterproof synthetic fiber band lie are used to adhere two L-shaped locking members lid corresponding to the size of the weight 10, and these locking members 1
A band lie is provided between 1d and the water-blocking sheet 7, and after placing a weight 10 such as a sandbag on the locking member lid, it is tied with the band lie or the band l is placed on the locking member lid.
Velcro fastener (magic tape) 1 on both ends of ie
1f may be attached, and these Velcro fasteners (velcro fasteners) 11f may be engaged and connected to be fixed.

このバンドlieを用いる場合には、バンドlieを一
本とする場合のほか、複数本としても良く、平行に配置
したり、交差して配置するようにしても良い。
When using this band lie, instead of using only one band lie, a plurality of bands may be used, and they may be arranged in parallel or intersectingly.

なお、このようなおもり固定部材11に限らず、おもり
10を固定できるものであれば、どのようなものでも良
く、遮水シート7の敷設と同時に船上などでおもり10
を固定する場合や、遮水シート7を敷設後、潜水夫など
による潜水作業で固定する場合にも容易におもり10を
取付けることができるものであることが好ましい。
Note that the weight fixing member 11 is not limited to such a weight fixing member 11, and any member that can fix the weight 10 may be used.
It is preferable that the weight 10 can be easily attached when fixing the water-shielding sheet 7 or when fixing it by a diver or the like during diving work after the water-shielding sheet 7 has been laid down.

このようにおもり10を固定部材11を用いて遮水シー
ト7の所定の縁部分などに取り付けることで、第4図に
示すように、遮水シート7を捨石マウンド4の所定の位
置から捨石マウンド4を覆って水底部6の所定の位置ま
で遮水シート7を敷設することができ、ケーソン5を栽
せるまでや埋立てが開始されるまでの間、進水シート7
を完全に敷設しておくことができる。
By attaching the weight 10 to a predetermined edge of the water-shielding sheet 7 using the fixing member 11 in this way, the water-shielding sheet 7 can be moved from a predetermined position of the rubble mound 4 to the rubble mound, as shown in FIG. The water-blocking sheet 7 can be laid to a predetermined position on the water bottom 6, covering the caisson 5, and until the caisson 5 is planted or the reclamation is started, the water-shielding sheet 7
can be left completely in place.

次に、ケーソン5自体の不透水性が十分でない場合の遮
水構造について、第6図により説明する。
Next, a water-blocking structure when the caisson 5 itself is not sufficiently water-impermeable will be explained with reference to FIG. 6.

このようなケーソン5自体に透水性がある場合には、ケ
ーソン5の側面にも遮水シート7を設ける必要があり、
例えばケーソン5の底部分に遮水シートの一端部を挾む
ことなく、水底部6から捨石マウンド4の所まで敷かれ
た遮水シート7をそのままケーソン5の側面にそって引
き上げるようにすることも考えられるが、このようにす
ると、遮水シート7をケーソン5の下端部から捨石マウ
ンド4に密着させて敷設することが難しく、中空部がで
き、埋立てが開始されたときに、遮水シート7の破損の
原因となる恐れがあることから、かかる構造は採用でき
ない。
If the caisson 5 itself has water permeability, it is necessary to provide a water-blocking sheet 7 on the side of the caisson 5.
For example, the water-shielding sheet 7 that has been laid from the water bottom 6 to the rubble mound 4 can be pulled up along the side of the caisson 5 without pinching one end of the water-shielding sheet at the bottom of the caisson 5. However, if you do this, it will be difficult to lay the water-blocking sheet 7 from the lower end of the caisson 5 in close contact with the rubble mound 4, and a hollow space will be created, which may cause water-blocking when the reclamation starts. Such a structure cannot be adopted because it may cause damage to the sheet 7.

そこで、捨石マウンド4及び水底部6を遮水する遮水シ
ート7のケーソン5fllの端部にケーソン5の遮水す
べき高さに応じた長さの遮水シート12を遮水シート7
の一部分としてと一体に設けなり、あるいは、別体のも
のを接合し、一体の場合の折曲部ないしは別体の接合部
をケーソン5の底部分に挾むか、そのケーソン5の底部
分に接合するようにする。
Therefore, a water-shielding sheet 12 of a length corresponding to the height of the caisson 5 to be water-shielded is attached to the end of the caisson 5fl of the water-shielding sheet 7 that shields the rubble mound 4 and the water bottom 6 from water.
It is provided as one part of the caisson 5, or it is joined as separate parts, and the bent part or the joined part of the separate parts is sandwiched in the bottom part of the caisson 5 or joined to the bottom part of the caisson 5. I'll do what I do.

そして、ケーソン5の設置前は、遮水シート12を遮水
シート7の上に重ねた状態としておき、ケーソン5を捨
石マウンド4上に設置した後、遮水シート12を引き上
げてケーソン5の側面に沿って張るようにするとともに
、順次広幅加工を行なって、上端部をケーソン5に固定
するかあるいは上端部に係止用フックを取付けておいて
ケーソン5上に立設した杭に引っかける等適宜の手段で
取付ける。
Before installing the caisson 5, the water-blocking sheet 12 is stacked on top of the water-blocking sheet 7, and after the caisson 5 is installed on the rubble mound 4, the water-blocking sheet 12 is pulled up and the side of the caisson 5 is placed. At the same time, the upper end is fixed to the caisson 5, or a locking hook is attached to the upper end and hooked to a stake erected on the caisson 5, etc. as appropriate. Attach by means of.

このようにして遮水シート7をケーソン5の底部に挾ん
で遮水シート12をケーソン5の側面に沿って張るよう
にすることで、ケーソン5の側面からの透水を防止する
ことができ、重力式護岸の遮水を完全に行なうことがで
きる。
In this way, by sandwiching the water-blocking sheet 7 at the bottom of the caisson 5 and stretching the water-blocking sheet 12 along the side of the caisson 5, it is possible to prevent water from permeating from the side of the caisson 5. It is possible to completely block water from the seawall.

そして、遮水シート7と遮水シート12とが一体とされ
て折り曲げられたり、別体のものが接合されているので
、ケーソン5の底部と捨石マウンド4との間への漏水が
防止できるため、止水部材9を介装して遮水することな
く完全に遮水できる。
Furthermore, since the water-shielding sheet 7 and the water-shielding sheet 12 are folded together or are joined as separate pieces, leakage of water between the bottom of the caisson 5 and the rubble mound 4 can be prevented. , it is possible to completely block water without interposing the water stop member 9.

したがって、捨石マウンド4上には、前述したシート保
護部材8を設けない場合もあるが、既に説明した種々の
構造のシート保護材8を遮水シート7の下面に介装して
おくことが好ましい。(特に遮水シート12の接合部か
ら捨石マウンド4の法尻にかけては介装することが好ま
しい。)このケーソン5の側面を遮水する遮水シート1
2としては、捨石マウンド4及び水底部6を返水するた
めに使用される遮水シート7と同様、ゴム系や合成樹脂
系、あるいは、アスファルト系の遮水シートなどが使用
できる。
Therefore, although there are cases where the sheet protection member 8 described above is not provided on the rubble mound 4, it is preferable to interpose the sheet protection material 8 having the various structures described above on the lower surface of the water-blocking sheet 7. . (In particular, it is preferable to interpose it from the joint of the water-blocking sheet 12 to the foot of the rubble mound 4.) Water-blocking sheet 1 that blocks water from the side of the caisson 5
Similar to the water-shielding sheet 7 used for returning water to the rubble mound 4 and the water bottom 6, a rubber-based, synthetic resin-based, or asphalt-based water-shielding sheet can be used as the water-shielding sheet 2.

以上説明した埋立てによる遮水構造によれば、水底部6
から捨石マウンド4までやケーソン5の側面を含めた部
分までを完全に遮水することができ、埋め立てによる廃
棄物からの有害物質などが外海に浸透することを防止で
きる。
According to the water-blocking structure by land reclamation explained above, the water bottom 6
It is possible to completely block water from the area to the rubble mound 4 and including the sides of the caisson 5, thereby preventing harmful substances from the waste generated by the landfill from penetrating into the open sea.

こうして埋立てが進むと、第7図に示ずように、埋立て
部分の海底の地盤によっては、捨石マウンド4上のケー
ソン5が沈下しなり、水底部6が沈下することがあり、
遮水シート7に引張力が加わる恐れが生じる。
As the reclamation progresses in this way, the caisson 5 on the rubble mound 4 may sink, and the water bottom 6 may sink, depending on the ground of the seabed in the reclaimed area, as shown in Figure 7.
There is a possibility that tensile force will be applied to the water-blocking sheet 7.

そこで、このような場合にもシートの破損や損傷を招く
ことがない遮水シートについて、第8図及び第9図(a
)、(b)により説明する。
Therefore, regarding water-shielding sheets that will not cause breakage or damage even in such cases, Figures 8 and 9 (a)
) and (b).

この遮水シート13は、ゴム等の不透水性のシート材1
3aの途中にひだ14を形成してシートの変形を許容す
るようにしており、敷設状態でもひだ14の形状を保つ
ことができるようにひだ14の間に保形部材15が介装
しである。
This water-blocking sheet 13 is made of water-impermeable sheet material 1 such as rubber.
A fold 14 is formed in the middle of the sheet 3a to allow the sheet to deform, and a shape retaining member 15 is interposed between the folds 14 so that the shape of the fold 14 can be maintained even in the laid state. .

この不透水性のシート材13aとしては、既に説明した
遮水シート7.12用の素材をそのまま使用することが
でき、ひた14部分についても同様に遮水シート7.1
2用の素材が使用される。
As this water-impermeable sheet material 13a, the material for the water-shielding sheet 7.12 described above can be used as is, and the water-shielding sheet 7.1 can be similarly used for the flap 14 portion.
2 materials are used.

そして、シート材13aが波状に集められてひだ14が
形成され、ひだ14の山部分の裏側にスポンジ等を保形
部材15として入れることでひだ14の形状を保つよう
にしている。
Then, the sheet material 13a is collected in a wavy manner to form pleats 14, and the shape of the pleats 14 is maintained by inserting a sponge or the like as a shape-retaining member 15 on the back side of the ridges of the pleats 14.

このようなひだ14が遮水シート7、あるいは遮水シー
ト12の途中に接合されて設けられて遮水シート13が
構成されたり、遮水シート7゜12とに熱成形等により
ひだ14を設けて遮水シート13が構成される。
The water-shielding sheet 13 is constructed by joining such folds 14 in the middle of the water-shielding sheet 7 or the water-shielding sheet 12, or the folds 14 are formed on the water-shielding sheet 7° 12 by thermoforming or the like. The water-blocking sheet 13 is constructed.

そして、この遮水シート13では、敷設する場合にもそ
の形状を保つことができるようにひだ14の上側及び下
側の遮水シー)13 (7,12)に連結部材16.1
7が取付けられる。
In this water-shielding sheet 13, connecting members 16.
7 is installed.

この上側の連結部材16としては、例えば第9図(a)
、(b)に示すように、バンド16aが使用され、ひだ
14の前後の遮水シート13(7゜12)に接合された
り、あるいは、シート材に多数の孔を形成して切断し易
くしたちの16b等が使用され、バンド16aについて
は、敷設後、作業者が切断するようにしてもよく、遮水
シート13 (7,12)に加わる力によって自動的に
切断するようにしてもよい。また、孔のあいたシート材
16bでは、切断作業を行なわず、遮水シート13 (
7,12)に加わる力によって自動的に切断するように
したものである。また、下側の連結部材17については
、敷設後、切断することができないので、自動的に切断
するようにしなければならず、例えば遮水シート7.1
2より厚さの薄いシート材17aが使用されたり、遮水
シート7.12と厚さの同じシート材に多数の孔を形成
して切断強度を小さくしたシート17bなどが使用され
、敷設された状態で遮水シート7.12に大きな力が加
わったときに自動的に連結部材17が切断するようにし
ている。
For example, the upper connecting member 16 is shown in FIG. 9(a).
, as shown in (b), a band 16a is used and is joined to the water-shielding sheet 13 (7° 12) before and after the pleats 14, or a number of holes are formed in the sheet material to make it easier to cut. The band 16a may be cut by an operator after being laid, or may be cut automatically by the force applied to the water-blocking sheet 13 (7, 12). . In addition, for the perforated sheet material 16b, cutting work is not performed and the water-blocking sheet 13 (
7, 12) is automatically cut by the force applied. Further, since the lower connecting member 17 cannot be cut after being laid, it must be cut automatically. For example, the water-blocking sheet 7.1
A sheet material 17a thinner than 2 was used, or a sheet 17b having the same thickness as the water-shielding sheet 7.12 with many holes formed to reduce cutting strength was used and laid. When a large force is applied to the water-shielding sheet 7.12 in this state, the connecting member 17 is automatically cut.

なお、連結部材16及び17は同じものを使用し、両者
とも自動的に切断するようにしてもよい。
Note that the same connecting members 16 and 17 may be used, and both may be automatically disconnected.

また、連結部材16.17は遮水シート13(7,1・
2)との接合上、遮水シート13(7゜12)と同一素
材からなることが好ましい。
In addition, the connecting members 16 and 17 are connected to the water-blocking sheet 13 (7, 1,
2), it is preferable to be made of the same material as the water-shielding sheet 13 (7°12).

このようにひだ14が形成された遮水シート13は、第
8図に示すように、捨石マウンド4のケーソン5が置か
れる位置の外側に第1のひだ14が位置するとともに、
捨石マウンド4の水底部6ffl!Iの端部の外側部分
に第2のびだ14が配置されて敷設される。敷設中にお
いては、ひだ14は上下の連結部材16.17及び保形
部材15でひだ14の形状が保持され、ひだ14を形成
した状態で敷設できる。そして、敷設後、上側の連結部
材16が切断されても、下側の連結部材17および保形
部材15でひだ14の形状を保持する。
As shown in FIG. 8, the water-shielding sheet 13 in which the pleats 14 are formed in this manner has the first pleats 14 located outside the position where the caisson 5 of the rubble mound 4 is placed, and
Water bottom 6ffl of rubble mound 4! A second stretch 14 is arranged and laid on the outer part of the end of I. During laying, the shape of the pleats 14 is maintained by the upper and lower connecting members 16, 17 and the shape retaining member 15, and the pleats 14 can be laid with the pleats 14 formed. After laying, even if the upper connecting member 16 is cut, the shape of the pleats 14 is maintained by the lower connecting member 17 and the shape retaining member 15.

(連結部材16が切断されない場合は連結部材16.1
7と保形部材15でひだ14の形状を保持する。) このような敷設状態で、ケーソン5が設置され、埋立て
が行われて、ケーソン5の沈下や水底部6の沈下が生じ
ると、進水シート13に大きな引張力が加わり、形状を
保持するための連結部材17又は16及び17が切断さ
れるとともに、保形部材15が抜は出してひだ14の部
分が平坦に引き伸ばされることになり、変形を吸収され
て遮水シート13の破損が防止される。
(If the connecting member 16 is not cut, the connecting member 16.1
7 and shape retaining member 15 to maintain the shape of the pleats 14. ) In such a laying state, when the caisson 5 is installed and reclaimed, and the caisson 5 sinks or the water bottom 6 sinks, a large tensile force is applied to the launching sheet 13 and it retains its shape. The connecting members 17 or 16 and 17 are cut, and the shape retaining member 15 is pulled out and the folds 14 are stretched flat, absorbing deformation and preventing damage to the water-blocking sheet 13. be done.

なお、ひだ14の形状を保持するための保形部材15と
しては、スポンジのほか、ゴム、合成樹脂、金属、木材
等の液体、棒状体又は管状態等でも良く、遮水シート1
3に大きな力が加わる沈下時までひだ14の形状を保持
でき、しかも返水シート13を伸ばして変形を吸収する
必要があるときには、抜は出すようなものであれば良い
The shape-retaining member 15 for maintaining the shape of the pleats 14 may be a sponge, a liquid made of rubber, synthetic resin, metal, wood, etc., a rod-shaped body, a tube, etc.
It is sufficient that the shape of the folds 14 can be maintained until subsidence when a large force is applied to the sheet 3, and that it can be pulled out when the water return sheet 13 needs to be stretched to absorb deformation.

また、連結部材に代え、紐などを用いるようにしても良
く、特に、上側については、切断するようにすれば、強
度や形状の制限は大巾に緩和され、遮水シート13に損
傷を与えないものであれはいかなるものでも良い。
Further, instead of the connecting member, a string or the like may be used. In particular, if the upper part is cut, the restrictions on strength and shape will be greatly relaxed, and there will be no risk of damage to the water-blocking sheet 13. Anything that doesn't exist is fine.

さらに、この遮水シート13においても、必要に応じて
シート保護部材や止水部材を用いて一層完全に遮水でき
るようにするとともに、敷設状態を保つためおもり及び
おもり固定部材を用いてもよい。
Furthermore, in this water-blocking sheet 13, a sheet protection member or a water-stopping member may be used as necessary to further completely block water, and a weight and a weight-fixing member may be used to maintain the laid state. .

なお、各実施例に基づき説明したそれぞれの発明は相互
に組み合わせて構成するようにしても良いことはいうま
でもない。
It goes without saying that the inventions described based on the respective embodiments may be configured in combination with each other.

[発明の効果] 以上、実施例とともに具体的に説明したようにこの発明
の埋立てにおける遮水JfI4造によれば、水底部に敷
設される返水シートの一端部を捨石マウンドとケーソン
の間の全体もしくは一部分に挾み、この部分の遮水シー
トをシート保護部材によって捨石マウンドの凹凸から保
護するとともに、止水部材によってケーソン下面の凹凸
による漏水を防止するようにしたので、遮水シートの損
傷を防止しつつ確実に遮水することができる。
[Effects of the Invention] As described above in detail with the embodiments, according to the impermeable JfI4 structure for land reclamation of the present invention, one end of the water return sheet laid at the bottom of the water is connected between the rubble mound and the caisson. The water-shielding sheet is placed over all or part of the caisson, and the sheet protection member protects the water-shielding sheet from the unevenness of the rubble mound, and the water-stopping member prevents water from leaking due to the unevenness of the bottom surface of the caisson. Water can be reliably blocked while preventing damage.

したがって、海面の埋め立てに適用しても有害物質が外
海に流出することを防止できる。
Therefore, even when applied to sea surface reclamation, harmful substances can be prevented from flowing into the open sea.

また、遮水シートにおもりを固定するおもり固定部材を
取付けたので、これによっておもりを固定して遮水シー
トの浮き上がりを防止し、確実な敷設が可能となり、遮
水性の向上を図ることができる。
In addition, a weight fixing member that fixes the weight to the water-shielding sheet is attached, which fixes the weight and prevents the water-shielding sheet from lifting up, allowing reliable installation and improving water-shielding performance. .

さらに、捨石マウンドとケーソンとで挾まれた部分の遮
水シートと一体もしくは接合された遮水シートをケーソ
ンの側壁に沿って配置したので、ケーソン自体からの透
水をも防止することができ、−層遮水を完全にすること
ができる。
Furthermore, since a water-shielding sheet that is integrated with or joined to the water-shielding sheet in the area sandwiched between the rubble mound and the caisson is placed along the side wall of the caisson, water permeation from the caisson itself can be prevented. Complete layer water shielding can be achieved.

また、遮水シートに変形を許容するひだを形成するとと
もに、このひだの間に保形部材を介装したので、敷設状
態でもひだを形成した状態とすることができ、このひだ
を伸ばすようにしてケーソン自体の沈下や水底部の沈下
によっても遮水シートが破損しないようにすることがで
き、確実な遮水が可能となる。
In addition, the water-blocking sheet has pleats that allow deformation, and a shape-retaining member is interposed between the folds, so the folds can be formed even when laid, and the folds can be stretched. This prevents the water-shielding sheet from being damaged even if the caisson itself sinks or the bottom of the water sinks, making reliable water-shielding possible.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明の埋立てにおける遮水構造が適用され
る重力式護岸の一例にかかる概略断面図、第2図はこの
発明の埋立てにおける遮水構造の一実施例にかかる一部
分を拡大した部分断面図、第3図(a>、(b)、(c
)はそれぞれこの発明の埋立てにおける遮水構造の一実
施例にかかるシート保護部材及び止水部材の断面図、第
4図はこの発明の埋立てにおける遮水構造の一実施例に
かかり、おもりおよびおもり固定部材による敷設状態の
斜視図、第5図(a)、(b)、(c)はそれぞれこの
発明の埋立てにおける遮水構造に用いるおもり固定部材
の斜視図、第6図はこの発明の埋立てにおける遮水構造
の一実施例にかかり、ケーソンの側面を遮水するように
した場合の斜視図、第7図は重力式護岸における沈下状
態の説明図、第8図はこの発明の埋立てにおける返水シ
ートの一実施例の敷設状態の概略断面図、第9図(a)
。 (b)はそれぞれひた部分の斜視図である。 1:岩盤、2:沖積シルト層、3:置換砂、4:捨石マ
ウンド、5:ケーソン、6:水底部、7:遮水シート、
8:シート保護部材、9:止水部材、10:おもり、1
1:おもり固定部材、12:遮水シート、13:遮水シ
ート、14:ひだ、15:保形部材、16.17:連結
部材。
Fig. 1 is a schematic sectional view of an example of a gravity-type seawall to which the water-blocking structure for land reclamation of the present invention is applied, and Fig. 2 is an enlarged view of a portion of the embodiment of the water-blocking structure for land reclamation of the present invention. Figure 3 (a>, (b), (c)
) are sectional views of a sheet protection member and a water-stopping member according to an embodiment of the water-shielding structure for landfilling of this invention, respectively, and FIG. 5(a), (b), and (c) are respectively perspective views of the weight fixing member used in the water-blocking structure in the landfill of this invention, and FIG. 6 is a perspective view of the weight fixing member installed. A perspective view of an embodiment of the water-shielding structure for land reclamation according to the invention, in which the side of the caisson is water-shielded, Figure 7 is an explanatory diagram of the subsidence state in a gravity-type revetment, and Figure 8 is the water-shielding structure of the invention. Schematic cross-sectional view of the installation state of an example of a water return sheet in a landfill, Figure 9 (a)
. (b) is a perspective view of each flap part. 1: bedrock, 2: alluvial silt layer, 3: replacement sand, 4: rubble mound, 5: caisson, 6: water bottom, 7: impermeable sheet,
8: Sheet protection member, 9: Water stop member, 10: Weight, 1
1: weight fixing member, 12: water-blocking sheet, 13: water-blocking sheet, 14: pleats, 15: shape-retaining member, 16.17: connecting member.

Claims (4)

【特許請求の範囲】[Claims] (1)捨石マウンド上に載置されたケーソンで仕切られ
た内側を埋立てる場合の遮水構造において、水底部に敷
設される遮水シートの一端部をケーソンと捨石マウンド
の少なくとも一部分に挾み込んで設置し、この遮水シー
ト下面と捨石マウンド上面との間にシート保護部材を設
けるとともに、前記遮水シート上面とケーソン下面との
間に止水部材を設けたことを特徴とする埋立てにおける
遮水構造。
(1) In a water-blocking structure when reclaiming the inside partitioned by a caisson placed on a rubble mound, one end of the water-blocking sheet laid at the bottom of the water is sandwiched between the caisson and at least part of the rubble mound. A landfill characterized in that a sheet protection member is provided between the bottom surface of the water-blocking sheet and the top surface of the rubble mound, and a water-stopping member is provided between the top surface of the water-blocking sheet and the bottom surface of the caisson. Waterproof structure.
(2)前記遮水シートをおもり固定部材を介して取付け
たおもりで水底部に敷設したことを特徴とする請求項1
記載の埋立てにおける遮水構造。
(2) Claim 1 characterized in that the water-blocking sheet is laid on the bottom of the water by a weight attached via a weight fixing member.
Water-blocking structure in the described landfill.
(3)捨石マウンド上に載置されたケーソンで仕切られ
た内側を埋立てる場合の遮水構造において、水底部に敷
設した遮水シートの一部を捨石マウンドとケーソンとの
間に挾み込んで設置し、該挾まれた部分の遮水シートと
一体もしくは接合された遮水シートをケーソンの側壁に
沿って配置したことを特徴とする埋立てにおける遮水構
造。
(3) In a water-blocking structure when reclaiming the inside partitioned by a caisson placed on a rubble mound, a part of the water-blocking sheet laid at the bottom of the water is sandwiched between the rubble mound and the caisson. A water-blocking structure in a landfill, characterized in that a water-blocking sheet is installed along the side wall of a caisson and is integrated with or joined to the water-blocking sheet in the sandwiched portion.
(4)捨石マウンド上に載置されたケーソンで仕切られ
た内側を遮水して埋立てる場合の遮水シートにおいて、
水底部に敷設される不透水性のシートに変形を許容する
ひだを形成し、各ひだの間に敷設状態で形状を保つ保形
部材を介装したことを特徴とする遮水シート。
(4) In a water-shielding sheet when reclaiming by blocking water from the inside partitioned by a caisson placed on a rubble mound,
A water-shielding sheet characterized by forming folds that allow deformation in a water-impermeable sheet laid on the bottom of a water body, and interposing a shape-retaining member between each fold that maintains the shape when laid.
JP63223839A 1988-09-07 1988-09-07 Impermeable structure and impermeable sheet for landfill Expired - Lifetime JPH0619127B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63223839A JPH0619127B2 (en) 1988-09-07 1988-09-07 Impermeable structure and impermeable sheet for landfill

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63223839A JPH0619127B2 (en) 1988-09-07 1988-09-07 Impermeable structure and impermeable sheet for landfill

Publications (2)

Publication Number Publication Date
JPH0270814A true JPH0270814A (en) 1990-03-09
JPH0619127B2 JPH0619127B2 (en) 1994-03-16

Family

ID=16804532

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63223839A Expired - Lifetime JPH0619127B2 (en) 1988-09-07 1988-09-07 Impermeable structure and impermeable sheet for landfill

Country Status (1)

Country Link
JP (1) JPH0619127B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007009408A (en) * 2005-06-28 2007-01-18 Shibata Ind Co Ltd Leaking-out preventive mat and caisson structure
JP2008080325A (en) * 2006-09-01 2008-04-10 World Engineering Kk Method of constructing impervious layer
JP2009069044A (en) * 2007-09-14 2009-04-02 Okumura Corp Detection system for impermeable flexible membrane break, and break detection method
JP2011156535A (en) * 2006-09-01 2011-08-18 World Engineering Kk Method of constructing impervious layer
JP2012162884A (en) * 2011-02-04 2012-08-30 Toyo Constr Co Ltd Sheet to be laid underwater
US8624332B2 (en) 2004-09-30 2014-01-07 Stmicroelectronics S.R.L. Vertical conduction power electronic device and corresponding realization method
CN108643288A (en) * 2018-05-31 2018-10-12 中国建筑第六工程局有限公司 A kind of subsided rest room secondary drainage waterproof system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60173207A (en) * 1984-02-17 1985-09-06 Ryowa Sanshi Kk Reclamation work

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60173207A (en) * 1984-02-17 1985-09-06 Ryowa Sanshi Kk Reclamation work

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8624332B2 (en) 2004-09-30 2014-01-07 Stmicroelectronics S.R.L. Vertical conduction power electronic device and corresponding realization method
JP2007009408A (en) * 2005-06-28 2007-01-18 Shibata Ind Co Ltd Leaking-out preventive mat and caisson structure
JP2008080325A (en) * 2006-09-01 2008-04-10 World Engineering Kk Method of constructing impervious layer
JP2011156535A (en) * 2006-09-01 2011-08-18 World Engineering Kk Method of constructing impervious layer
JP2009069044A (en) * 2007-09-14 2009-04-02 Okumura Corp Detection system for impermeable flexible membrane break, and break detection method
JP2012162884A (en) * 2011-02-04 2012-08-30 Toyo Constr Co Ltd Sheet to be laid underwater
CN108643288A (en) * 2018-05-31 2018-10-12 中国建筑第六工程局有限公司 A kind of subsided rest room secondary drainage waterproof system

Also Published As

Publication number Publication date
JPH0619127B2 (en) 1994-03-16

Similar Documents

Publication Publication Date Title
JPH0270814A (en) Water-shield structure and sheet for reclamation
JP4287011B2 (en) Impermeable sheet laying structure and impermeable sheet laying method
JP4562065B2 (en) Protection method for supporting ground of offshore structures
US20080219772A1 (en) Berm System
JP2001152425A (en) Impervious structure of revetment
JP2007247309A (en) Construction method of seepage control processing layer
JP3698969B2 (en) Underwater impermeable method
JP2007105618A (en) Water barrier structure of waste landfill site
JP2001011837A (en) Connection method for membranous material for water cutoff
JPH0641686B2 (en) Method of laying water-permeable sheet in landfill
JP3123404B2 (en) Waterproof sheet protection structure
JP2006305414A (en) Waste disposal site structure
EP2663693B1 (en) Method and device for laying down and tensioning an impermeable cover for hydraulic works in loose material
KR101404471B1 (en) Embankment constuction by buoyancy and water pressure on the part prevention of injury and in the force functioning bottom, a mat and execution method for filter
JP2001062420A (en) Fixing structure for protective mat
JPH04194209A (en) Sheet formwork material
JP3225886U (en) Waterproof air bag
JP4749444B2 (en) Impermeable layer connection method
JP2009257073A (en) Civil engineering complex and construction method of earth structure
JP3895581B2 (en) Impermeable structure
JPH09285772A (en) Treating plant for waste
JP4038095B2 (en) Water impervious sheet for water surface landfill site and air venting method
JP3905390B2 (en) Impermeable method for offshore landfill site
JP3999073B2 (en) Laying water-impervious sheet for landfill
JP2982569B2 (en) Method and structure for preventing leakage of sewage from seepage control sheet at waste disposal site