JPH01146026A - Anchor bolt fixing device - Google Patents
Anchor bolt fixing deviceInfo
- Publication number
- JPH01146026A JPH01146026A JP30277287A JP30277287A JPH01146026A JP H01146026 A JPH01146026 A JP H01146026A JP 30277287 A JP30277287 A JP 30277287A JP 30277287 A JP30277287 A JP 30277287A JP H01146026 A JPH01146026 A JP H01146026A
- Authority
- JP
- Japan
- Prior art keywords
- anchor bolt
- fixed
- plate
- steel
- anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 47
- 239000010959 steel Substances 0.000 claims abstract description 47
- 239000004567 concrete Substances 0.000 claims abstract description 30
- 239000000463 material Substances 0.000 claims abstract description 16
- 238000003466 welding Methods 0.000 claims description 6
- 230000003014 reinforcing effect Effects 0.000 claims description 5
- 238000010276 construction Methods 0.000 description 7
- 230000000694 effects Effects 0.000 description 3
- 229910000746 Structural steel Inorganic materials 0.000 description 2
- 230000000712 assembly Effects 0.000 description 1
- 238000000429 assembly Methods 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000005304 joining Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
Landscapes
- Foundations (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は鉄骨造及び鉄骨鉄筋コンクリート造の建築物に
使用される柱脚部のアンカーボルトを基礎のコンクリー
ト中に固定する装置に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a device for fixing anchor bolts of column bases used in steel-framed and steel-framed reinforced concrete buildings into concrete foundations.
鉄骨構造物の精度は最下階柱の位置精度によって大きく
左右され、その柱は基礎構造部分の精度に大きな影響を
受ける。工場において製作された鉄骨部材は許容誤差範
囲内で納入されるのが一般的であるから、工事現場にお
ける鉄骨建方の誤差はアンカーボルトの精度の影響がそ
のまま現われる場合が多い。従って鉄骨建方の良否は−
に上記アンカーボルトの精度にかかっており、正確な位
置決めを行なう必要がある。このため、例えば鉄骨工事
技術指針・同解説(昭和54年4月25日、日本建築学
会発行)第625頁に記載のようにアンカーボルトを鋼
製フレーム若しくは保持具によって保持し、コンクリー
トの打設による衝撃や流れによる圧力によって移動しな
いようにするアンカーボルト固定装置を使用するのが通
常である。The accuracy of steel structures is greatly influenced by the positional accuracy of the bottom floor columns, which are greatly affected by the accuracy of the foundation structure. Steel frame members manufactured in factories are generally delivered within tolerance limits, so errors in steel frame erection at construction sites are often directly affected by the accuracy of anchor bolts. Therefore, the quality of steel frame construction is -
This depends on the accuracy of the anchor bolt, and accurate positioning is required. For this reason, for example, anchor bolts are held by steel frames or holders as described in the Steel Construction Technical Guidelines and Commentary (April 25, 1974, published by the Architectural Institute of Japan), page 625, and concrete is poured. Typically, anchor bolt fixing devices are used to prevent movement due to shock or flow pressure.
第5図は従来のアンカーボルトの固定装置の一例を示す
要部正面図である。同図において1はフレームであり、
例えば等連山形鋼によって角枠状に構成すると共に、上
部に上部形板2を、下端部から若干の高さの位置に下部
形板3を各々固着し、上部形板2および下部形板3に設
けた保持穴(図示せず)にアンカーボルト4を保持する
ように構成する。なおアンカーボルト4の上下方向の位
置決めは、例えば角片状の定着板5を介してナツト6に
より下部形板3を挟着する手段によって行なう。上記の
構成により、予め打設した捨てコンクリート7上の所定
の位置にフレーム1を載置し、ドリルアンカー9を打込
んで固定した後、鎖線にて示すような基礎8をコンクリ
ート打設により形成するのである。FIG. 5 is a front view of main parts showing an example of a conventional anchor bolt fixing device. In the figure, 1 is a frame,
For example, it is constructed in a rectangular frame shape using regular threaded steel, and an upper shape plate 2 is fixed to the upper part, and a lower shape plate 3 is fixed at a position slightly higher than the lower end. The anchor bolt 4 is configured to be held in a holding hole (not shown) provided in the holder. The vertical positioning of the anchor bolt 4 is carried out by, for example, clamping the lower plate 3 with a nut 6 via a rectangular fixing plate 5. With the above configuration, the frame 1 is placed at a predetermined position on the sacrificial concrete 7 that has been placed in advance, and after driving and fixing the drill anchors 9, a foundation 8 as shown by the chain line is formed by pouring concrete. That's what I do.
上記従来の固定装置を構成するフレーム1は、予め工場
において製作した後、建方現場に運搬するのが通常であ
るが、次のような問題点がある。The frame 1 constituting the above-mentioned conventional fixing device is usually manufactured in advance at a factory and then transported to the construction site, but it has the following problems.
(11フレーム1に突出部分が多いため、工場から現場
までの運搬途中において、フレーム1相互の重合、衝突
等によって変形を生じ、アンカーボルト4を基礎8中に
高精度で埋設することが困難である。(11 Since the frame 1 has many protruding parts, the frames 1 may overlap or collide with each other during transportation from the factory to the site, resulting in deformation, making it difficult to bury the anchor bolt 4 in the foundation 8 with high precision. be.
(2) フレーム1は一般に溶接接合で組立製作され
るため、建方現場におけるアンカーボルト4の水平方向
若しくは垂直方向の位置調整を行なうことができない。(2) Since the frame 1 is generally assembled and manufactured by welding, it is not possible to adjust the horizontal or vertical position of the anchor bolt 4 at the construction site.
(3) アンカーボルト4の下端部は定着板5に固定
するのであるが、定着板5は水平方向に大きな面積を有
するため、これを収納できるようにするためにはフレー
ムl全体を大きくする必要がある。(3) The lower end of the anchor bolt 4 is fixed to the fixing plate 5, but since the fixing plate 5 has a large area in the horizontal direction, the entire frame l needs to be enlarged to accommodate it. There is.
(4) フレームlは基礎コンクリートの打碇によっ
てアンカーボルト4がずれないよう剛性が要求される。(4) The frame l is required to have rigidity so that the anchor bolts 4 do not shift due to the casting of foundation concrete.
このため、用いられる部材は比較的大寸法のものを使用
する必要があるが、基礎コンクリート中に配設する鉄筋
(図示せず)との干渉頻度が高い。For this reason, the members used need to be relatively large in size, but they often interfere with reinforcing bars (not shown) placed in the foundation concrete.
(5) アンカーボルトの外周にはアンボンド用の被
覆スリーブ(第5図では図示せず)によって被覆されて
いる。そして、第6図にて示すようにアンカーボルト4
の上端部はアンカーボルト被覆スリーブ11を介してフ
レームの上部形板2に支持されるようになっている。し
かし、上部形板2とスリーブ11とアンカーボルト4と
の間には隙間があるため、例えば第7図のように傾斜し
てくるいが生じ、アンカーボルト4の固定精度を高める
ことかできない。(5) The outer periphery of the anchor bolt is covered with a covering sleeve (not shown in FIG. 5) for unbonding. Then, as shown in Fig. 6, the anchor bolt 4
The upper end of the anchor bolt is supported on the upper profile plate 2 of the frame via the anchor bolt covering sleeve 11. However, since there is a gap between the upper profile plate 2, the sleeve 11, and the anchor bolt 4, an inclined gap is formed as shown in FIG. 7, for example, and the fixing accuracy of the anchor bolt 4 cannot be improved.
上記問題点を解決するために、本発明においては、基礎
の捨てコンクリート等に固定した複数の鋼材の上部に鋼
材を横方向に渡した状態で溶接し、その横方向の鋼材の
上部に、アンカーボルトの上部ねじ部に上部形板を、下
部ねじ部に定着板と定着板の下に配置した下部形板とを
ナットの締結で一体にしたアンカーボルトフレームを載
せ、横方向の鋼材とアンカーボルトフレームとを固定す
るという技術的手段を採用したのである。In order to solve the above problems, in the present invention, the steel members are welded horizontally to the upper parts of multiple steel members fixed to the concrete of the foundation, etc., and the anchors are attached to the upper parts of the horizontal steel members. An anchor bolt frame is placed on the upper threaded part of the bolt, and an anchor bolt frame is mounted on the lower threaded part, which is made up of a fixing plate and a lower shaped plate placed under the fixing plate, which are integrated by tightening nuts. They adopted a technical means of fixing the frame.
上記の構成とすることにより次の作用効果が得られる。 With the above configuration, the following effects can be obtained.
(1) 工場において予め所定寸法に加工した構成部
材のみを製作して建方現場において組立てることができ
るため、運搬作業が極めて容易となる。(1) Only component parts pre-processed to predetermined dimensions can be manufactured at the factory and assembled at the construction site, making transportation work extremely easy.
(2)従来のフレームのように突出部分が少なく、上記
(1)と関連して運搬中の変形が殆んどないため、保持
具およびアンカーフレームの精度が大幅に向上する。(2) Unlike conventional frames, there are fewer protruding parts and, in relation to (1) above, there is almost no deformation during transportation, so the precision of the holder and anchor frame is greatly improved.
(3) アンカーボルトフレームが主にアンカーボル
トと上部形板、下部形板という少ない要素で構成されて
いるので、従来のようなフレームと基礎コンクリートの
鉄筋との干渉頻度が大幅に低減される。(3) Since the anchor bolt frame is mainly composed of a small number of elements, namely the anchor bolt, upper form plate, and lower form plate, the frequency of interference between the frame and the reinforcing bars of the foundation concrete as in the past is greatly reduced.
(4)本発明では下部形板が定着板の下側に設けられて
いるので、下部形板の直下に設けた横方向の鋼材が定着
板に干渉せず、定着板と下部形板とをアンカーボルトの
下部ねじ部に固定するナットの近隣まで広げた位置に配
置でき、横方向の鋼材の間隔を大きくできる。これがコ
ンクリートの打設によって起こる下部形板の変形を小さ
くし、アンカーボルトの心ずれを防止するのに大きく寄
与する。(4) In the present invention, since the lower profile plate is provided below the fixing plate, the horizontal steel material provided directly below the lower profile plate does not interfere with the fixing plate, and the fixing plate and the lower profile plate are connected. It can be placed in a wider position near the nut that is fixed to the lower threaded part of the anchor bolt, increasing the horizontal spacing between the steel members. This greatly contributes to reducing the deformation of the lower form plate caused by pouring concrete and preventing misalignment of the anchor bolts.
(5)上部形板はアンカーボルト被覆スリーブを介さず
にアンカーボルトに連結されるので、アンカーボルトと
位置決め精度がアンカーボルト被覆スリーブとアンカー
ボルトの間隙に左右されない。(5) Since the upper form plate is connected to the anchor bolt without using the anchor bolt covering sleeve, the positioning accuracy of the anchor bolt is not affected by the gap between the anchor bolt covering sleeve and the anchor bolt.
上記の構成による装置によって、アンカーボルトを正確
に位置決めした状態で基礎コンクリート中に埋設するこ
とができるのである。With the device having the above configuration, the anchor bolt can be buried in the foundation concrete in a precisely positioned state.
第1図は本発明の実施例を示す要部正面図、第2図は第
1図のA−A線断面図であり同一部分は前記第5図と同
一参照符合にて示す。両図において上部形板2、下部形
板3は所定寸法のピンチでアンカーボルト4の挿通穴を
有し、5は例えば角片状の定着板であり、下部形板3の
上部に位置する。アンカーボルト4の下部ねじ部には下
部ナツト6により定着板5とその下に下部形板3を挟着
する。上部形板2は上部ナツト6aによりアンカーボル
ト4に挟着する。また、アンカーボルトの軸部にはアン
カーボルト被覆スリーブ11が設けられている。これら
の組立てによりアンカーボルト七ノド23が形成される
。FIG. 1 is a front view of essential parts showing an embodiment of the present invention, and FIG. 2 is a sectional view taken along line A--A in FIG. 1, and the same parts are designated by the same reference numerals as in FIG. In both figures, the upper shape plate 2 and the lower shape plate 3 each have a hole of a predetermined size for inserting an anchor bolt 4 therethrough, and numeral 5 designates, for example, a rectangular piece-shaped fixing plate located at the upper part of the lower shape plate 3. A fixing plate 5 and a lower form plate 3 are clamped to the lower threaded portion of the anchor bolt 4 by means of a lower nut 6. The upper form plate 2 is clamped to the anchor bolt 4 by an upper nut 6a. Furthermore, an anchor bolt covering sleeve 11 is provided on the shaft portion of the anchor bolt. Anchor bolt seven throats 23 are formed by these assemblies.
次に複数の例えば山形鋼からなる鋼材13を複数の固定
部材21に溶接等により固着し、捨てコンクリート7上
の所定の位置に固定ボルト22により捨てコンクリート
7上に固着する。複数の横方向の鋼材14は所定の高さ
で複数の鋼材13に溶接接合すると共に、上面は実質的
に水平面を形成するように構成する。その後横方向の鋼
材14上に前記アンカーボルトフレーム23を載置し、
芯出し、溶接等によって固着した後、コンクリートを打
設すればアンカーボルトを精度よくかつ強固に、基礎8
中に埋設することができる。Next, a plurality of steel members 13 made of angle iron, for example, are fixed to a plurality of fixing members 21 by welding or the like, and are fixed to the concrete concrete 7 at predetermined positions with fixing bolts 22 on the concrete concrete 7. The plurality of horizontal steel members 14 are welded to the plurality of steel members 13 at a predetermined height, and the upper surfaces thereof are configured to form a substantially horizontal surface. After that, the anchor bolt frame 23 is placed on the horizontal steel material 14,
After fixing by centering, welding, etc., pouring concrete will make the anchor bolts precise and strong.
It can be buried inside.
第3図は本発明の他の実施例を示す要部正面図、第4図
は第3図のA−A線断面図であり同一部分は前記第1図
および第2図に示す実施例と同一の参照符合で示す。ア
ンカーボルト23の構成は前記第1図および第2図の実
施例と同様である。捨てコンクリート7中に例えば山形
鋼からなる4本の鋼材13を埋設し、この鋼材に横方向
の鋼材14を上面が実質的に水平面を形成するように固
着してアンカーフレーム15を構成する。この構成によ
りアンカーボルトフレーム23をアンカーフレーム15
上に載置して、両者をボルト・ナット(図示せず)若し
くは溶接接合により、アンカーフレーム15と共にアン
カーボルト4を精度よくかつ強固に基礎中に埋設するこ
とができる。FIG. 3 is a front view of main parts showing another embodiment of the present invention, and FIG. 4 is a sectional view taken along line A-A in FIG. Indicated by the same reference numeral. The structure of the anchor bolt 23 is similar to the embodiment shown in FIGS. 1 and 2. An anchor frame 15 is constructed by embedding four steel members 13 made of angle iron, for example, in the sacrificial concrete 7, and fixing horizontal steel members 14 to the steel members so that their upper surfaces form a substantially horizontal surface. With this configuration, the anchor bolt frame 23 is connected to the anchor frame 15.
The anchor bolt 4 and the anchor frame 15 can be accurately and firmly embedded in the foundation by placing the two on top and joining them together by bolts and nuts (not shown) or welding.
なお、これらの実施例において、上部形板2は基礎8中
に埋設されず、アンカーボルトに連結される鉄骨柱を建
てる前に、上部ナソ)6aを取外し除去する。In these embodiments, the upper form plate 2 is not buried in the foundation 8, and the upper frame 6a is removed and removed before erecting the steel column connected to the anchor bolt.
本発明は以下に記述の構成によるものであるから、次の
効果が得られる。Since the present invention has the configuration described below, the following effects can be obtained.
(11本発明の装置は建方現場に部材を運搬して組立て
ることができるため、運搬が容易であるほか、組立てに
際しても精度が得られるので、アンカーボルトとの位置
決め精度が向上する。(11) Since the device of the present invention can transport and assemble components to the construction site, it is not only easy to transport, but also provides precision during assembly, improving positioning accuracy with anchor bolts.
(2)部材数が少く全体の構造が簡素であるので基礎コ
ンクリート中に配設する鉄筋との干渉が低減される。(2) Since the number of members is small and the overall structure is simple, interference with reinforcing bars placed in the foundation concrete is reduced.
(3)横方向の鋼材の間隔が広まり、コンクリート打設
の際のコンクリートの流れによる圧力による変形が殆ん
どなくアンカーボルトの高精度な芯出しが可能である。(3) The spacing between the steel members in the lateral direction is widened, and there is almost no deformation due to the pressure caused by the flow of concrete during concrete placement, making it possible to center the anchor bolt with high precision.
(4) アンカーボルトと上部形板とが、アンカーボ
ルト被覆スリーブを介さずに連結されるため、アンカー
ボルトの固定精度が向上する。(4) Since the anchor bolt and the upper form plate are connected without using the anchor bolt covering sleeve, the fixing accuracy of the anchor bolt is improved.
第1図および第2図は各々本発明の実施例を示す要部正
面図およびA−A線断面図、第3図および第4図は各々
本発明の他の実施例を示す要部正面図およびA−A断面
図、第5図は従来のアンカーボルトの固定装置の一例を
示す要部正面図、第6図は第5図要部正面図のアンカー
ボルト上端部における上部形板との関係を示す部分詳細
縦断面図、第7図は同じく間隙によってアンカーボルト
が一方向に片寄った状況を示す部分詳細縦断面図である
。
2二上部形板、3:下部形板、4:アンカーボルト、5
:定着板、6.6a:ナツト、7:捨てコンクリート、
13:鋼材、14:横方向の鋼材、23:アンカーボル
トフレーム。
第1図
第3図
第4図
第5図
第6図 第7図
手続補正書
昭和63年 1月行日
3補正をする者
事件との関係 特許出願人
5補正により増加する発明の数 なし補正の内容
1、 明細書第1頁の特許請求の範囲を下記[j内のと
おり訂正する。
「(1) 基礎の捨てコンクリート等に固定した複数
の鋼材の上部に鋼材を横方向に渡した状態で溶接し、そ
の横方向の鋼材の上部に、アンカーボルトの上部ねじ部
に下部形板を、下部ねじ部に定着板と定着板の下に配置
した下部形板とをナツトの締結で一体にしたアンカーボ
ルトフレームを載せ、横方向の鋼材とアンカーボルトフ
レームとを固定したことを特徴とするアンカーボルト固
定装置。
(2) 複数の鋼材を捨てコンクリート等の中に埋め
込むことにより固定したことを特徴とする特許請求の範
囲髪よ項記載のアンカーボルト固定装置。
(3)複数の鋼材を捨てコンクリート上に固定ボルト等
を用いて固定したことを特徴とする特許請求の範囲第1
項記載のアンカーボルト固定装置。
(4) 複数の鋼材を捨てコンクリートに連結された
鉄筋等により固定したことを特徴とする特許請求の範囲
第1項記載のアンカーボルト固定装置。
(5)横方向の鋼材とアンカーボルトフレームの下部形
板とをボルト・ナツトで固定したことを特徴とする特許
請求の範囲第1項ないし第4項のいずれかに記載のアン
カーボルト固定装置。
(6)横方向の鋼材とアンカーボルトフレームの下部形
板とを溶接で固定したことを特徴とする特許請求の範囲
第1項ないし第4項のいずれかに記載のアンカーボルト
固定装置。」
2、 同書第5頁第18行の「ことかできない。
を「ことができない。」と訂正する。
以上FIGS. 1 and 2 are front views and cross-sectional views taken along the line A-A of main parts showing embodiments of the present invention, and FIGS. 3 and 4 are front views of main parts showing other embodiments of the present invention, respectively. and A-A sectional view, FIG. 5 is a front view of the main part showing an example of a conventional anchor bolt fixing device, and FIG. 6 is a front view of the main part in FIG. FIG. 7 is a partially detailed longitudinal sectional view showing a situation in which the anchor bolt is biased in one direction due to the gap. 2 Upper shape plate, 3: Lower shape plate, 4: Anchor bolt, 5
: Fixing plate, 6.6a: Nut, 7: Discarded concrete,
13: Steel material, 14: Lateral steel material, 23: Anchor bolt frame. Figure 1 Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Procedural amendment document January 1986 Date 3 Relationship with the case of the person making the amendment Patent applicant Number of inventions increased by the 5 amendment None amendment Content 1, the claims on page 1 of the specification are corrected as shown in [j] below. (1) Weld the steel members horizontally to the upper part of multiple steel members fixed to the foundation concrete, etc., and attach the lower form plate to the upper threaded part of the anchor bolt on the upper part of the horizontal steel members. , an anchor bolt frame in which a fixing plate and a lower shape plate disposed below the fixing plate are integrated by tightening nuts is placed on the lower screw portion, and the horizontal steel material and the anchor bolt frame are fixed. Anchor bolt fixing device. (2) Anchor bolt fixing device according to the claims, characterized in that the anchor bolt fixing device is fixed by discarding a plurality of steel materials and embedding them in concrete or the like. Claim 1, characterized in that it is fixed on concrete using fixing bolts, etc.
Anchor bolt fixing device as described in section. (4) The anchor bolt fixing device according to claim 1, characterized in that a plurality of steel members are discarded and fixed by reinforcing bars or the like connected to concrete. (5) The anchor bolt fixing device according to any one of claims 1 to 4, wherein the horizontal steel member and the lower plate of the anchor bolt frame are fixed with bolts and nuts. (6) The anchor bolt fixing device according to any one of claims 1 to 4, wherein the horizontal steel member and the lower plate of the anchor bolt frame are fixed by welding. ” 2. In the same book, page 5, line 18, ``I can't do anything.'' is corrected to ``I can't do it.''that's all
Claims (6)
の上部に鋼材を横方向に渡した状態で溶接し、その横方
向の鋼材の上部に、アンカーボルトの上部ねじ部に上部
形板を、下部ねじ部に定着板と定着板の下に配置した下
部形板とをナットの締結で一体にしたアンカーボルトフ
レームを載せ、横方向の鋼材とアンカーボルトフレーム
とを固定したことを特徴とするアンカーボルト固定装置
。(1) Weld the steel materials horizontally to the top of multiple steel materials fixed to the foundation concrete, etc., and attach the upper shape plate to the upper threaded part of the anchor bolt on the top of the horizontal steel materials. An anchor characterized in that an anchor bolt frame in which a fixing plate and a lower shape plate disposed below the fixing plate are integrated by fastening nuts is mounted on the lower threaded part, and the horizontal steel material and the anchor bolt frame are fixed. Bolt fixing device.
ことにより固定したことを特徴とする特許請求の範囲(
1)項記載のアンカーボルト固定装置。(2) Claims characterized in that a plurality of steel materials are disposed of and fixed by embedding them in concrete or the like (
Anchor bolt fixing device according to item 1).
を用いて固定したことを特徴とする特許請求の範囲第1
項記載のアンカーボルト固定装置。(3) Claim 1 characterized in that a plurality of steel members are discarded and fixed on concrete using fixing bolts or the like.
Anchor bolt fixing device as described in section.
等により固定したことを特徴とする特許請求の範囲第1
項記載のアンカーボルト固定装置。(4) Claim 1, characterized in that a plurality of steel members are discarded and fixed by reinforcing bars or the like connected to concrete.
Anchor bolt fixing device as described in section.
板とをボルト・ナットで固定したことを特徴とする特許
請求の範囲第1項ないし第4項のいずれかに記載のアン
カーボルト固定装置。(5) The anchor bolt fixing device according to any one of claims 1 to 4, wherein the horizontal steel member and the lower plate of the anchor bolt frame are fixed with bolts and nuts.
板とを溶接で固定したことを特徴とする特許請求の範囲
第1項ないし第4項のいずれかに記載のアンカーボルト
固定装置。(6) The anchor bolt fixing device according to any one of claims 1 to 4, wherein the horizontal steel member and the lower plate of the anchor bolt frame are fixed by welding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62302772A JP2555111B2 (en) | 1987-11-30 | 1987-11-30 | Anchor bolt fixing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62302772A JP2555111B2 (en) | 1987-11-30 | 1987-11-30 | Anchor bolt fixing device |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH01146026A true JPH01146026A (en) | 1989-06-08 |
JP2555111B2 JP2555111B2 (en) | 1996-11-20 |
Family
ID=17912943
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP62302772A Expired - Fee Related JP2555111B2 (en) | 1987-11-30 | 1987-11-30 | Anchor bolt fixing device |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2555111B2 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0540336U (en) * | 1991-11-01 | 1993-06-01 | 大和ハウス工業株式会社 | Anchor frame |
JPH0540335U (en) * | 1991-11-01 | 1993-06-01 | 大和ハウス工業株式会社 | Anchor frame |
JP2000008390A (en) * | 1998-06-22 | 2000-01-11 | Okabe Co Ltd | Anchor device for column base |
JP2000199230A (en) * | 1998-09-21 | 2000-07-18 | Okabe Co Ltd | Installing method for anchor bolt |
JP2009014434A (en) * | 2007-07-03 | 2009-01-22 | Toyo Tire & Rubber Co Ltd | Rubber test body for lifetime prediction |
JP2016160680A (en) * | 2015-03-03 | 2016-09-05 | 松沢 庄次 | Anchor bolt adjusting tool and anchor bolt support device |
JP2018066142A (en) * | 2016-10-18 | 2018-04-26 | 中国電力株式会社 | Setting method for structure and foundation for setting structure |
KR20230158891A (en) * | 2022-05-12 | 2023-11-21 | 에스비엔지니어링 주식회사 | Steel Column Foundation Connection Structure with Improved Resistance to Cone Breakage and its Construction Method |
-
1987
- 1987-11-30 JP JP62302772A patent/JP2555111B2/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0540336U (en) * | 1991-11-01 | 1993-06-01 | 大和ハウス工業株式会社 | Anchor frame |
JPH0540335U (en) * | 1991-11-01 | 1993-06-01 | 大和ハウス工業株式会社 | Anchor frame |
JP2000008390A (en) * | 1998-06-22 | 2000-01-11 | Okabe Co Ltd | Anchor device for column base |
JP2000199230A (en) * | 1998-09-21 | 2000-07-18 | Okabe Co Ltd | Installing method for anchor bolt |
JP2009014434A (en) * | 2007-07-03 | 2009-01-22 | Toyo Tire & Rubber Co Ltd | Rubber test body for lifetime prediction |
JP2016160680A (en) * | 2015-03-03 | 2016-09-05 | 松沢 庄次 | Anchor bolt adjusting tool and anchor bolt support device |
JP2018066142A (en) * | 2016-10-18 | 2018-04-26 | 中国電力株式会社 | Setting method for structure and foundation for setting structure |
KR20230158891A (en) * | 2022-05-12 | 2023-11-21 | 에스비엔지니어링 주식회사 | Steel Column Foundation Connection Structure with Improved Resistance to Cone Breakage and its Construction Method |
Also Published As
Publication number | Publication date |
---|---|
JP2555111B2 (en) | 1996-11-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5505033A (en) | Column base structure and connection arrangement | |
US20190226206A1 (en) | Beam-column connection structure and method of making the same | |
JPH01146026A (en) | Anchor bolt fixing device | |
JP2004176482A (en) | Construction method for non-buried column leg and structure of non-buried column leg | |
KR20190084712A (en) | Prefabricated column assembly with foundation reinforcement part | |
JP3298722B2 (en) | Thin-walled precast concrete driving formwork slab wall large construction method | |
JP2021195834A (en) | Column base anchor structure, trestle, and design method for column base anchor structure | |
JP2583740B2 (en) | Fence construction method and framework | |
JPS61233131A (en) | Foundation structure of pole | |
JP2005127064A (en) | Hardware for column base | |
JPH0539616A (en) | Reinforcing steel basket for foundation having reinforcing steel anchor frame | |
JP7274992B2 (en) | Anchor bolt fixture and anchor frame | |
KR100453952B1 (en) | fixing construction of anchor bolt for laying | |
JP3767860B2 (en) | Building basic structure and construction method | |
JP2002097791A (en) | Form support metal | |
JPH0629233Y2 (en) | Anchor bolt installation device | |
JPH028467A (en) | Fixed structure of concrete plate | |
JP2013119701A (en) | Column base part of architectural structure | |
JPH03265800A (en) | Method of installing equipment | |
KR200262035Y1 (en) | fixing construction of anchor bolt for laying | |
JPH06220869A (en) | Drop-in type steel frame bridge pier and process of construction thereof | |
WO2020261342A1 (en) | Plant frame structure | |
JP2782111B2 (en) | Steel framing construction method | |
KR200343574Y1 (en) | Steel Colum Base Using Cast Steel Base Plate | |
JPH01158117A (en) | Column base structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |