JP7503512B2 - Construction method for floating structures - Google Patents

Construction method for floating structures Download PDF

Info

Publication number
JP7503512B2
JP7503512B2 JP2021025836A JP2021025836A JP7503512B2 JP 7503512 B2 JP7503512 B2 JP 7503512B2 JP 2021025836 A JP2021025836 A JP 2021025836A JP 2021025836 A JP2021025836 A JP 2021025836A JP 7503512 B2 JP7503512 B2 JP 7503512B2
Authority
JP
Japan
Prior art keywords
pile
scaffolding
piles
head
precast concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021025836A
Other languages
Japanese (ja)
Other versions
JP2022127702A (en
Inventor
秀幸 新井
宣行 浦崎
弘章 江草
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2021025836A priority Critical patent/JP7503512B2/en
Publication of JP2022127702A publication Critical patent/JP2022127702A/en
Application granted granted Critical
Publication of JP7503512B2 publication Critical patent/JP7503512B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Revetment (AREA)

Description

本発明は、水上構造物の施工方法に関する。 The present invention relates to a construction method for an above-water structure.

海や河川等の水域において水上構造物を構築する場合に、水底に立設した杭を基礎として構築する場合がある。このような水上構造物を施工する際には、杭に足場を固定した状態で作業を行うのが一般的である。例えば、特許文献1には、杭に固定されたブラケットに支保工および型枠を設置し、型枠内に打設したコンクリートが硬化した後、支保工と型枠を撤去する水上構造物の施工方法が開示されている。特許文献1では、支保工と、型枠と、足場とが一体化されたユニットの分割体をブラケットに上載するとともに分割体同士を連結することにより支保工と型枠を構築し、撤去する際には、分割体同士の連結を解除してから横移動させて撤去する。
特許文献1の水上構造物の施工方法では、水上において分割体同士の接合および解体を行う必要があり、その作業に手間と費用がかかる。また、支保工、型枠および足場を構築する際または撤去する際には、別途足場を確保する必要があるため、この足場の設置および撤去にも手間と費用がかかる。
When constructing a floating structure in a body of water such as the sea or a river, the structure may be constructed on piles erected on the bottom of the water as a foundation. When constructing such a floating structure, it is common to perform work with scaffolding fixed to the piles. For example, Patent Document 1 discloses a construction method for a floating structure in which shoring and formwork are installed on brackets fixed to the piles, and the shoring and formwork are removed after concrete poured into the formwork has hardened. In Patent Document 1, the shoring and formwork are constructed by placing the divided bodies of a unit in which the shoring, formwork, and scaffolding are integrated on the brackets and connecting the divided bodies to each other, and when removing the shoring and formwork, the connection between the divided bodies is released and the divided bodies are moved sideways to remove them.
In the construction method for an overwater structure described in Patent Document 1, it is necessary to join and dismantle the divided bodies on the water, which is time-consuming and costly. In addition, when constructing or removing the shoring, formwork, and scaffolding, it is necessary to secure a separate scaffolding, which also requires time and cost to set up and remove.

特開2020-16140号公報JP 2020-16140 A

本発明は、水上構造物を構築する際に、簡易に設置および撤去することができる仮設足場を利用した水上構造物の施工方法を提案することを課題とする。 An object of the present invention is to propose a construction method for an overwater structure that utilizes temporary scaffolding that can be easily installed and removed when constructing an overwater structure.

前記課題を解決するための本発明の水上構造物の施工方法は、水底に立設した杭にブラケットを取り付けるブラケット取付工程と、前記ブラケットに枠状の仮設足場を載置する足場載置工程と、前記杭の頭部にプレキャストコンクリート部材を架設する架設工程と、前記仮設足場を撤去する足場撤去工程とを備えている。前記仮設足場は、前記プレキャストコンクリート部材を挿通可能な大きさの開口部を有しており、前記足場撤去工程では、前記開口部に前記プレキャストコンクリート部材を挿通させながら、前記仮設足場を上方に引き上げる。
かかる水上構造物の施工方法によれば、仮設足場を撤去する際に、仮設足場の開口部内にプレキャストコンクリート部材を位置させながら仮設足場を上昇させるため、仮設足場を解体する必要がない。そのため、仮設足場の設置時および撤去時において、仮設足場の組み立ておよび解体に要する手間を省略でき、工期短縮化および費用の低減化を図ることができる。
なお、前記プレキャストコンクリート部材に前記杭の位置に対応して箱抜きが形成されているとともに補強部材として埋設された補強鉄骨が前記箱抜き内に露出している場合には、前記架設工程において前記杭の頭部を前記箱抜きに挿入するとともに前記杭の頭部に形成した係合部に前記補強鉄骨を係合させた状態で前記杭頭部に載置させた後、前記箱抜きにコンクリートを打設する。かかる水上構造物の施工方法によれば、コンクリート打設時のプレキャストコンクリート部材を支持するための支保工を省略あるいは削減できる。その結果、施工時の手間およびコストの低減化を図ることができる。
The construction method for an overwater structure of the present invention for solving the above-mentioned problems includes a bracket attachment step of attaching brackets to piles erected on the water bottom, a scaffolding placement step of placing a frame-shaped temporary scaffolding on the brackets, an erection step of erecting precast concrete members on the heads of the piles, and a scaffolding removal step of removing the temporary scaffolding. The temporary scaffolding has an opening large enough to allow the precast concrete members to pass through, and in the scaffolding removal step, the temporary scaffolding is pulled up while the precast concrete members are being inserted through the openings.
According to this construction method for an overwater structure, when removing the temporary scaffolding, the temporary scaffolding is raised while the precast concrete member is positioned inside the opening of the temporary scaffolding, so there is no need to dismantle the temporary scaffolding. Therefore, when setting up and removing the temporary scaffolding, the labor required for assembling and dismantling the temporary scaffolding can be omitted, and the construction period can be shortened and costs can be reduced.
In addition, when a box cutout is formed in the precast concrete member corresponding to the position of the pile and a reinforcing steel frame embedded as a reinforcing member is exposed in the box cutout, the head of the pile is inserted into the box cutout in the erection process, and the reinforcing steel frame is placed on the pile head while engaging with the engagement portion formed in the head of the pile, and then concrete is poured into the box cutout. According to this construction method for an above-water structure, shoring for supporting the precast concrete member during concrete pouring can be omitted or reduced. As a result, the labor and cost during construction can be reduced.

本発明の水上構造物の施工方法によれば、水上構造物を構築する際に必要となる足場を、簡易に設置および撤去することが可能となる。 According to the construction method for an offshore structure of the present invention, it is possible to easily install and remove scaffolding required when constructing an offshore structure.

本実施形態の水上構造物を示す斜視図である。FIG. 2 is a perspective view showing the above-water structure of the present embodiment. 本実施形態の水上構造物の施工方法を示すフローチャートである。2 is a flowchart showing a construction method for an offshore structure according to the present embodiment. 水上構造物の各工程を示す斜視図であって、(a)はブラケット取付工程、(b)は足場載置工程、(c)は架設工程、(d)足場撤去工程である。1 is a perspective view showing each process of the construction of an offshore structure, where (a) is the bracket attachment process, (b) is the scaffolding placement process, (c) is the erection process, and (d) is the scaffolding removal process. ブラケットを示す図であって、(a)は側面図、(b)は係止部の拡大斜視図である。5A and 5B are diagrams showing a bracket, in which FIG. 5A is a side view and FIG. 5B is an enlarged perspective view of a locking portion. ブラケットの取付部を示す図であって、(a)は平面図、(b)は側面図である。5A and 5B are diagrams showing a mounting portion of a bracket, in which FIG. 仮設足場を示す平面図である。FIG. (a)は連結部材の設置状況を示す斜視図、(b)は拡大図である。1A is a perspective view showing an installation state of a connecting member, and FIG. 斜杭の杭頭位置調整状況を示す側面図であって、(a)は杭間隔が広い場合、(b)は杭間隔が狭い場合である。11A and 11B are side views showing the pile head position adjustment status of an inclined pile, where (a) is when the pile spacing is wide, and (b) is when the pile spacing is narrow. 杭頭処理工程においてブラケットの一部を撤去する状況を示す斜視図である。FIG. 11 is a perspective view showing a situation in which a part of the bracket is removed in the pile head processing process. 杭頭処理工程を示す側面図である。FIG. 4 is a side view showing the pile head treatment process. 架設工程を示す側面図である。FIG. プレキャストコンクリート部材を斜杭との接合部を示す図であって、(a)は平面図、(b)は部分拡大斜視図である。1A and 1B are diagrams showing a joint between a precast concrete member and a batter pile, in which (a) is a plan view and (b) is a partially enlarged perspective view.

本実施形態では、水底に杭を打設して水上構造物1を構築する場合について説明する。図1に水上構造物1を示す。水上構造物1は、図1に示すように、複数(本実施形態では4本)の斜杭2,2,…と、斜杭2,2,…の頭部に形成されたコンクリート製の構造体3とを備えている。斜杭2は、下に向かうにしたがって他の斜杭2と離れるように傾斜した状態で、水底に打設されている。本実施形態の斜杭2は、鋼管杭からなる。
本実施形態の構造体3は、直方体状を呈していて、複数の斜杭2,2,…の頭部に横架された状態で形成されている。構造体3は、プレキャスト部材を斜杭2の頭部に固定することにより形成されている。
In this embodiment, a case where an overwater structure 1 is constructed by driving piles into the water bottom will be described. Fig. 1 shows the overwater structure 1. As shown in Fig. 1, the overwater structure 1 comprises a plurality of (four in this embodiment) batter piles 2, 2, ... and a concrete structure 3 formed on the heads of the batter piles 2, 2, .... The batter piles 2 are driven into the water bottom at an angle so that they move away from the other batter piles 2 as they go downward. The batter piles 2 in this embodiment are made of steel pipe piles.
The structure 3 of this embodiment has a rectangular parallelepiped shape and is formed in a state where it is horizontally supported on the heads of a plurality of batter piles 2, 2, .... The structure 3 is formed by fixing precast members to the heads of the batter piles 2.

以下、本実施形態の水上構造物1の施工方法について説明する。図2に本実施形態の水上構造物の施工方法を示す。水上構造物は、図2に示すように、杭打設工程S1、ブラケット取付工程S2、足場載置工程S3、杭頭処理工程S4、架設工程S5および足場撤去工程S6を実施することにより構築する。図3(a)~(d)に水上構造物1の施工方法の各工程を示す。
杭打設工程S1は、鋼管杭を水底に打設して、所定の位置に斜杭2を形成する工程である。本実施形態では、図3(a)に示すように、4本の鋼管杭を、下に向かうにしたがって離間するように、傾斜させた状態で打設する。斜杭2は、他の斜杭2と間隔をあけて打設するものとし、隣り合う一対の斜杭2,2は正面視でハ字状を呈している。斜杭2を構成する鋼管杭の寸法は、構造体3の形状、重量や、水上構造物の用途等に応じて適宜決定する。
The construction method of the floating structure 1 of this embodiment will be described below. Fig. 2 shows the construction method of the floating structure of this embodiment. As shown in Fig. 2, the floating structure is constructed by carrying out a pile driving step S1, a bracket mounting step S2, a scaffolding placement step S3, a pile head treatment step S4, an erection step S5, and a scaffolding removal step S6. Figs. 3(a) to (d) show the steps of the construction method of the floating structure 1.
The pile driving step S1 is a step of driving steel pipe piles into the bottom of the water to form the baffle piles 2 at predetermined positions. In this embodiment, as shown in Fig. 3(a), four steel pipe piles are driven in an inclined state so that they move apart as they go downward. The baffle piles 2 are driven at intervals from each other, and a pair of adjacent baffle piles 2, 2 form a V-shape when viewed from the front. The dimensions of the steel pipe piles constituting the baffle piles 2 are appropriately determined depending on the shape and weight of the structure 3, the purpose of the above-water structure, etc.

ブラケット取付工程S2では、図3(a)に示すように、斜杭2にブラケット5を取り付ける。斜杭2に構造体3を形成(設置)する際には、図3(c)に示すように、斜杭2に仮設足場4を設置した状態で行う。仮設足場4は、図3(b)に示すように、斜杭2に取り付けられたブラケット5と、ブラケット5に上載された枠体6と、枠体6上に固定された足場材7とを有している。枠体6には、構造体3を挿通可能な大きさ(構造体3の平面形状よりも大きな平面形状)の開口部61が形成されている。
図4にブラケット5を示す。ブラケット5は、仮設足場5を斜杭2に設置するための支持部材であって、各斜杭2に取り付けられている。ブラケット5は、図4(a)に示すように、斜杭2の外面に添接されるベース部51と、台座を構成する本体部52と、斜杭2の頭部に係止される係止部53と、斜杭2の外周面に添接される取付部54とを備えている。
ベース部51は、斜杭2の上端から下方に向けて斜杭2の外面に沿って延設されている。本実施形態のベース部51は、鋼材(例えば、H形鋼や溝形鋼等)からなる。本実施形態のベース部51は、下部部材51aと上部部材51bとが連結されることにより所定の長さに形成されている。ベース部51は、各斜杭2の外面において、4本の斜杭2,2,…の中心の反対側(各斜杭2の中心軸を結んで形成される矩形状の仮想領域の外側)に添接する。
In the bracket attachment step S2, as shown in Fig. 3(a), a bracket 5 is attached to the batter pile 2. When the structure 3 is formed (installed) on the batter pile 2, as shown in Fig. 3(c), the step is performed with a temporary scaffolding 4 installed on the batter pile 2. As shown in Fig. 3(b), the temporary scaffolding 4 has a bracket 5 attached to the batter pile 2, a frame body 6 placed on the bracket 5, and scaffolding materials 7 fixed on the frame body 6. An opening 61 is formed in the frame body 6, the opening being large enough to insert the structure 3 (having a planar shape larger than the planar shape of the structure 3).
The bracket 5 is shown in Fig. 4. The bracket 5 is a support member for installing the temporary scaffolding 5 on the batter piles 2, and is attached to each batter pile 2. As shown in Fig. 4(a) , the bracket 5 includes a base portion 51 attached to the outer surface of the batter pile 2, a main body portion 52 forming a pedestal, a locking portion 53 locked to the head of the batter pile 2, and an attachment portion 54 attached to the outer circumferential surface of the batter pile 2.
The base portion 51 extends downward from the upper end of the batter pile 2 along the outer surface of the batter pile 2. In this embodiment, the base portion 51 is made of steel (e.g., H-shaped steel or channel steel). In this embodiment, the base portion 51 is formed to a predetermined length by connecting a lower member 51a and an upper member 51b. The base portion 51 is attached to the outer surface of each batter pile 2 on the opposite side of the center of the four batter piles 2, 2, ... (outside the rectangular imaginary area formed by connecting the central axes of each batter pile 2).

本体部52は、足場の一部を構成する枠体を載置するための台座である。本体部52は、ベース部51から横方向(水平あるいは略水平)に張り出す受部52aと受部52aを支持するための斜材52bとを備えている。受部52aの形状は部材(仮設足場4)を載置することが可能であれば限定されるものではないが、本実施形態では平板状を呈している。斜材52bは、一端が受部52aの下面に固定されていて、他端がベース部51に固定されている。本体部52は、斜杭2の頭部に構造体3を形成した状態で、受部52aの上面から構造体3の下面までの間に所定の間隔が確保できる高さ位置に設けられている。また、受部52aは、平面視した状態で、構造体3の側面よりも外側に張り出す長さを有している。 The main body 52 is a base for placing a frame that constitutes part of the scaffolding. The main body 52 includes a receiving portion 52a that extends laterally (horizontally or approximately horizontally) from the base 51, and a diagonal member 52b for supporting the receiving portion 52a. The shape of the receiving portion 52a is not limited as long as it is possible to place a member (temporary scaffolding 4), but in this embodiment, it is flat. One end of the diagonal member 52b is fixed to the lower surface of the receiving portion 52a, and the other end is fixed to the base 51. The main body 52 is provided at a height position that ensures a predetermined distance between the upper surface of the receiving portion 52a and the lower surface of the structure 3 when the structure 3 is formed on the head of the diagonal pile 2. In addition, the receiving portion 52a has a length that extends outward beyond the side surface of the structure 3 when viewed in a plan view.

係止部53は、ベース部51の上端に固定された鉤型部材である。図4(b)に示すように、係止部53は、ベース部51の上端に固定された第一部材53aと、第一部材53aの先端部に形成された第二部材53bとを備えている。本実施形態の第一部材53aは、溝形鋼からなり、ベース部51の先端から斜杭2の中心側に張り出すように設けられている。第二部材53bは、第一部材53aの下面に固定された鋼板であって、斜杭2の内空に挿入される。第二部材53bを斜杭2に挿入することで、ベース部51と第二部材53bとの間に斜杭2を構成する鋼管の一部が挿入された状態で、斜杭2の上端にブラケット5が係止される。なお、本実施形態では、クランプや万力等の挟締治具51cによりベース部51を杭2に取り付ける。 The locking portion 53 is a hook-shaped member fixed to the upper end of the base portion 51. As shown in FIG. 4(b), the locking portion 53 includes a first member 53a fixed to the upper end of the base portion 51 and a second member 53b formed at the tip of the first member 53a. In this embodiment, the first member 53a is made of a channel steel and is provided so as to protrude from the tip of the base portion 51 toward the center of the inclined pile 2. The second member 53b is a steel plate fixed to the lower surface of the first member 53a and is inserted into the inner space of the inclined pile 2. By inserting the second member 53b into the inclined pile 2, the bracket 5 is locked to the upper end of the inclined pile 2 with a part of the steel pipe constituting the inclined pile 2 inserted between the base portion 51 and the second member 53b. In this embodiment, the base portion 51 is attached to the pile 2 by a clamping jig 51c such as a clamp or a vice.

取付部54は、斜杭2の外面に周設される部材であって、ベース部51に固定されている。図5(a)および(b)に取付部を示す。本実施形態の取付部54は、係止部53と本体部52との間の高さ位置において、ベース部51に固定されている。取付部54は、図5(a)に示すように、斜杭2の外面形状に応じて弧状断面(平面視U字状)に形成された板材からなり、斜杭2を囲むように斜杭2の外面に添接することで、ブラケット5(ベース部51の横方向のずれを抑制する。取付部54の端部には、フランジ54aが形成されている。フランジ54aは、斜杭2の外面から側方に張り出すように形成されている。フランジ54aは、取付部54を構成する板材を折り曲げることにより形成してもよいし、取付部54の端部に板材を固定することにより形成してもよい。本実施形態では、ベース部51の下端部にも取付部54を設けている。 The mounting portion 54 is a member that is provided around the outer surface of the diagonal pile 2 and is fixed to the base portion 51. The mounting portion is shown in Figs. 5(a) and (b). In this embodiment, the mounting portion 54 is fixed to the base portion 51 at a height position between the locking portion 53 and the main body portion 52. As shown in Fig. 5(a), the mounting portion 54 is made of a plate material formed with an arc-shaped cross section (U-shaped in plan view) according to the outer surface shape of the diagonal pile 2, and is attached to the outer surface of the diagonal pile 2 so as to surround the diagonal pile 2, thereby suppressing the lateral displacement of the bracket 5 (base portion 51). A flange 54a is formed at the end of the mounting portion 54. The flange 54a is formed so as to protrude laterally from the outer surface of the diagonal pile 2. The flange 54a may be formed by bending the plate material that constitutes the mounting portion 54, or may be formed by fixing a plate material to the end of the mounting portion 54. In this embodiment, the mounting portion 54 is also provided at the lower end of the base portion 51.

足場載置工程S3は、図3(b)に示すように、斜杭2に足場を形成する工程である。
足場載置工程S3では、ブラケット5に枠体6および足場材7(枠状の仮設足場)を載置する。図6に枠体6および足場材7を示す。図6に示すように、枠体6は、鋼材を組み合わせることにより、構造体3挿通可能な大きさの開口部61を有した枠状に形成されている。枠体6は、クレーン等の揚重機を利用して、4本の斜杭2の頭部を開口部61に挿通させた状態でブラケット5に上載する。枠体6をブラケット5に載置したら、斜杭2同士の間において、枠体6を構成する対向する一組の鋼材同士の間に補強鋼材62を横架させる。本実施形態では、2本の補強鋼材62を平行に配設する。次に、枠体6上に足場材7を載置する。すなわち、4本の斜杭2,2,…の周囲に足場材7を配置する。また、本実施形態では、一対の補強鋼材62同士の間にも足場材7を横架する。なお、本実施形態では、作業員の昇降スペースとして、枠体6の四隅のうちの一つの角部において足場材7を省略している。
The scaffolding placement step S3 is a step of forming a scaffolding on the batter pile 2, as shown in FIG. 3(b).
In the scaffolding placement step S3, a frame body 6 and a scaffolding material 7 (frame-shaped temporary scaffolding) are placed on the bracket 5. FIG. 6 shows the frame body 6 and the scaffolding material 7. As shown in FIG. 6, the frame body 6 is formed into a frame shape having an opening 61 large enough for the structure 3 to be inserted by combining steel materials. The frame body 6 is placed on the bracket 5 with the heads of the four diagonal piles 2 inserted into the openings 61 using a lifting machine such as a crane. After the frame body 6 is placed on the bracket 5, a reinforcing steel material 62 is laid horizontally between the diagonal piles 2 and between a pair of opposing steel materials constituting the frame body 6. In this embodiment, two reinforcing steel materials 62 are arranged in parallel. Next, the scaffolding material 7 is placed on the frame body 6. That is, the scaffolding material 7 is arranged around the four diagonal piles 2, 2, .... In this embodiment, the scaffolding material 7 is also laid horizontally between a pair of reinforcing steel materials 62. In this embodiment, the scaffolding 7 is omitted at one of the four corners of the frame body 6 to provide space for workers to climb up and down.

杭頭処理工程S4は、斜杭2の杭頭処理を行う工程である。杭頭処理工程でS4では、図7(a)に示すように、まず、取付部54同士を連結部材55により連結する。図7は、連結部材55の設置状況を示す図である。連結部材55は、斜杭2同士の間に横架されている。本実施形態では、前後方向、左右方向、対角線方向に配設された連結部材55を斜杭2同士の間に横架することにより、4本の斜杭2,2,…を連結する。連結部材55の両端は、図7(b)に示すように、斜杭2の外面に固定された弧状板材56に固定する。弧状板材56は、図5(a)および(b)に示すように、斜杭2の外面形状に対応する形状の板材により構成されていて、端部にフランジ56aが形成されている。フランジ56aは、斜杭2の外面から側方に張り出すように形成されている。フランジ56aは、弧状板材56を構成する板材を折り曲げることにより形成してもよいし、弧状板材56の端部に板材を固定することにより形成してもよい。弧状板材56は、フランジ56aを取付部54のフランジ54aに重ねた状態で、両フランジ54a,56aを貫通するボルト56cにナットを定着することにより、取付部54に固定する。弧状板材56には、連結部材55の端部を固定するための取付板56bが形成されている。連結部材55は、揚重機等により吊下させた状態で、図7(b)に示すように、端部を弧状板材56の取付板56bに挟締治具56dを介して固定することにより、斜杭2同士の間に横架する。すなわち、各斜杭2,2,…に固定されたブラケット5同士を、取付部54(弧状板材56)同士の間に横架された連結部材55を介して連結する。斜杭2同士の間に連結部材55を横架すると、ブラケット5の上下移動が阻止されるようになる。なお、杭が直杭である場合には、杭の外周面に取り付けた支持部材等により連結部材55(ブラケット5)を支持する。 The pile head processing step S4 is a step of processing the pile head of the inclined pile 2. In the pile head processing step S4, as shown in FIG. 7(a), first, the mounting parts 54 are connected to each other by the connecting member 55. FIG. 7 is a diagram showing the installation state of the connecting member 55. The connecting member 55 is horizontally laid between the inclined piles 2. In this embodiment, the connecting members 55 arranged in the front-rear direction, left-right direction, and diagonal direction are horizontally laid between the inclined piles 2 to connect four inclined piles 2, 2, .... As shown in FIG. 7(b), both ends of the connecting member 55 are fixed to an arc-shaped plate material 56 fixed to the outer surface of the inclined pile 2. As shown in FIG. 5(a) and (b), the arc-shaped plate material 56 is made of a plate material having a shape corresponding to the outer surface shape of the inclined pile 2, and a flange 56a is formed at the end. The flange 56a is formed so as to protrude laterally from the outer surface of the inclined pile 2. The flange 56a may be formed by bending the plate material constituting the arc-shaped plate material 56, or may be formed by fixing a plate material to the end of the arc-shaped plate material 56. The arc-shaped plate material 56 is fixed to the mounting part 54 by fixing a nut to a bolt 56c passing through both flanges 54a, 56a with the flange 56a overlapping the flange 54a of the mounting part 54. The arc-shaped plate material 56 is formed with a mounting plate 56b for fixing an end of the connecting member 55. The connecting member 55 is hung between the batter piles 2 by fixing an end to the mounting plate 56b of the arc-shaped plate material 56 via a clamping jig 56d as shown in FIG. 7(b) while being suspended by a lifting machine or the like. That is, the brackets 5 fixed to the batter piles 2, 2, ... are connected to each other via the connecting member 55 horizontally hung between the mounting parts 54 (arc-shaped plate material 56). When the connecting member 55 is placed between the inclined piles 2, the bracket 5 is prevented from moving up and down. If the piles are vertical piles, the connecting member 55 (bracket 5) is supported by a support member or the like attached to the outer periphery of the pile.

なお、杭頭処理工程S4では、必要に応じて杭頭位置の調整を行う。図8は、斜杭2の杭頭位置調整状況を示す図である。斜杭同士の間隔が大きい場合には、図8(a)に示すように、調整装置57(例えばチェーンブロック)を利用して、斜杭2同士の間隔を調整する。斜杭2に固定された弧状板材56同士の間に、ワイヤー57aが連結された調整装置57を横架した状態で、調整装置57を操作することにより斜杭2を引き寄せる。一方、斜杭2同士の間隔が小さい場合には、図8(b)に示すように、斜杭2を押し広げる調整装置(例えばジャッキ)57及び鋼材57bを斜杭2同士の間に介材させて、調整装置57を操作することにより斜杭2を押し広げる。連結部材55は、杭頭位置の調整後に斜杭2同士の間に横架させる。 In the pile head processing step S4, the pile head position is adjusted as necessary. Figure 8 shows the pile head position adjustment status of the inclined piles 2. When the interval between the inclined piles is large, the interval between the inclined piles 2 is adjusted using an adjustment device 57 (e.g., a chain block) as shown in Figure 8 (a). The adjustment device 57 connected to the wire 57a is hung horizontally between the arc-shaped plate materials 56 fixed to the inclined piles 2, and the inclined piles 2 are pulled by operating the adjustment device 57. On the other hand, when the interval between the inclined piles 2 is small, as shown in Figure 8 (b), an adjustment device (e.g., a jack) 57 that pushes the inclined piles 2 apart and a steel material 57b are placed between the inclined piles 2, and the adjustment device 57 is operated to push the inclined piles 2 apart. The connecting member 55 is hung horizontally between the inclined piles 2 after the pile head position adjustment.

次に、図9に示すように、杭2の上端に係止されたブラケット5のベース部51の上部部材51bおよび係止部53を撤去する。上部部材51bは、下部部材51aとの連結を解除した状態で、クレーンなどの揚重機で吊り上げる。なお、ベース部51が1本の鋼材により形成されている場合には、ベース部51を連結部材55の上方において切断する。 Next, as shown in FIG. 9, the upper member 51b and the locking member 53 of the base portion 51 of the bracket 5 that is locked to the upper end of the pile 2 are removed. The upper member 51b is lifted up by a lifting machine such as a crane while being disconnected from the lower member 51a. If the base portion 51 is formed from a single piece of steel material, the base portion 51 is cut above the connecting member 55.

続いて、図10に示すように、斜杭2の杭頭処理を行う。図10は、杭頭処理状況を示す図である。斜杭2の杭頭処理は、斜杭2の上端に水平面が形成されるように、斜杭2の上端部22を切断する。杭頭処理は、仮設足場4上において、作業員が斜杭2の上端を切断することにより、斜杭2の杭頭の位置を調整する。このとき、係合部21として、杭頭に突起を残置させた状態で、斜杭2の上端部22を切断する。 Next, as shown in Figure 10, the head of the diagonal pile 2 is treated. Figure 10 shows the head treatment status. In head treatment of the diagonal pile 2, the upper end 22 of the diagonal pile 2 is cut off so that a horizontal surface is formed at the upper end of the diagonal pile 2. In head treatment, a worker on the temporary scaffolding 4 cuts off the upper end of the diagonal pile 2 to adjust the position of the head of the diagonal pile 2. At this time, the upper end 22 of the diagonal pile 2 is cut off while leaving a protrusion on the head as the engagement part 21.

架設工程S5では、斜杭2の頭部に構造体3を形成する。図11に架設工程S5を示す。構造体3は、図11に示すように、プレキャストコンクリート部材31を4本の斜杭2,2,…の頭部に架設することにより形成する。プレキャストコンクリート部材31は、揚重機Cを利用して、斜杭2の上端に載置する。図12に斜杭2とプレキャストコンクリート部材31の接合部を示す。図12(a)に示すように、プレキャストコンクリート部材31には、斜杭2の位置に対応して箱抜き32が形成されている。箱抜き32内には、プレキャストコンクリート部材31に補強部材として埋設された補強鉄骨33が露出している。プレキャストコンクリート部材31を斜杭2の頭部に設置する際には、斜杭2の頭部を箱抜き32に挿入するとともに、補強鉄骨33を斜杭2の頭部に載置する。このとき、図12(b)に示すように、斜杭2の頭部に形成した係合部21に補強鉄骨33を係合させた状態で斜杭2の頭部にプレキャストコンクリート部材31を載置させる。本実施形態では、箱抜き32内において、補強鉄骨33が十字状に配設されている。係合部21は、補強鉄骨33同士の角部に挿入することで、補強鉄骨33に係止する。 In the erection step S5, a structure 3 is formed on the head of the inclined pile 2. The erection step S5 is shown in FIG. 11. As shown in FIG. 11, the structure 3 is formed by erecting a precast concrete member 31 on the heads of the four inclined piles 2, 2, ... The precast concrete member 31 is placed on the upper end of the inclined pile 2 using a lifting machine C. FIG. 12 shows the joint between the inclined pile 2 and the precast concrete member 31. As shown in FIG. 12(a), a box cutout 32 is formed in the precast concrete member 31 corresponding to the position of the inclined pile 2. In the box cutout 32, a reinforcing steel frame 33 embedded as a reinforcing member in the precast concrete member 31 is exposed. When the precast concrete member 31 is installed on the head of the inclined pile 2, the head of the inclined pile 2 is inserted into the box cutout 32, and the reinforcing steel frame 33 is placed on the head of the inclined pile 2. At this time, as shown in FIG. 12(b), the precast concrete member 31 is placed on the head of the diagonal pile 2 with the reinforcing steel frame 33 engaged with the engagement portion 21 formed on the head of the diagonal pile 2. In this embodiment, the reinforcing steel frame 33 is arranged in a cross shape inside the box cutout 32. The engagement portion 21 is inserted into the corners of the reinforcing steel frames 33 to engage with them.

プレキャストコンクリート部材31を斜杭2の上端に載置させたら、箱抜き32の下側に型枠を設置して、箱抜き32にコンクリートを打設(充填)する。このとき、箱抜き32内に、必要な鉄筋を配筋する。また、斜杭2の内部には、底蓋を設置しておく。底蓋を設置するタイミングは、コンクリートを打設する前であれば限定されるものではなく、例えば、杭頭処理工程において行ってもよい。 Once the precast concrete member 31 has been placed on the top end of the inclined pile 2, a formwork is placed under the box cutout 32, and concrete is poured (filled) into the box cutout 32. At this time, the necessary reinforcing bars are placed inside the box cutout 32. A bottom lid is also placed inside the inclined pile 2. The timing of the bottom lid installation is not limited as long as it is done before the concrete is poured, and it may be done during the pile head treatment process, for example.

足場撤去工程S6は、図2(d)に示すように、仮設足場4を撤去する工程である。
仮設足場の撤去は、まず、補強鋼材62と、補強鋼材62に架設された足場材7を撤去する。このとき、枠体6に載置した足場材7も必要に応じて撤去する。
次に、揚重機を利用して、開口部61に構造体3(プレキャストコンクリート部材31)を挿通させながら、枠体6を上方に引き上げることにより仮設足場4を撤去する。仮設足場4を撤去したら、ブラケット5を撤去する。
The scaffolding removal process S6 is a process of removing the temporary scaffolding 4, as shown in FIG. 2(d).
To remove the temporary scaffolding, first, the reinforcing steel materials 62 and the scaffolding materials 7 erected on the reinforcing steel materials 62 are removed. At this time, the scaffolding materials 7 placed on the frame body 6 are also removed as necessary.
Next, the structure 3 (the precast concrete member 31) is inserted into the opening 61 using a lifting machine while the frame 6 is pulled upward, thereby removing the temporary scaffolding 4. After the temporary scaffolding 4 has been removed, the bracket 5 is removed.

本実施形態の水上構造物の施工方法によれば、仮設足場2を撤去する際に、仮設足場4(枠体6)の開口部61内にプレキャストコンクリート部材を位置させながら仮設足場4を上昇させるため、仮設足場4を解体する必要がない。そのため、仮設足場4の設置時および撤去時において、仮設足場4の組み立ておよび解体に要する手間を省略でき、工期短縮化および費用の低減化を図ることができる。
また、プレキャストコンクリート部材に斜杭2の位置に対応して箱抜きが形成されているため、箱抜きに斜杭の頭部を挿入した状態で箱抜きにコンクリートを打設することで、斜杭2と構造体3とが一体に接合される。また、箱抜き内には、プレキャストコンクリート部材に補強部材として埋設された補強鉄骨が露出していて、杭の頭部に形成した係合部を補強鉄骨に係合させるため、プレキャストコンクリート部材の位置決めが容易である。
According to the construction method for an overwater structure of this embodiment, when removing the temporary scaffolding 2, the temporary scaffolding 4 (frame body 6) is raised while the precast concrete member is positioned inside the opening 61 of the temporary scaffolding 4, so there is no need to dismantle the temporary scaffolding 4. Therefore, when setting up and removing the temporary scaffolding 4, the labor required for assembling and dismantling the temporary scaffolding 4 can be omitted, and the construction period can be shortened and costs can be reduced.
In addition, a box cutout is formed in the precast concrete member corresponding to the position of the diagonal pile 2, and by pouring concrete into the box cutout with the head of the diagonal pile inserted into it, the diagonal pile 2 and the structure 3 are joined together. In addition, reinforcing steel embedded in the precast concrete member as a reinforcing member is exposed inside the box cutout, and the engagement part formed on the head of the pile is engaged with the reinforcing steel, making it easy to position the precast concrete member.

また、本実施形態の仮設足場によれば、構造体3の構築後に、枠体の開口部内に構造体を位置させながら枠体を上昇させることができるため、枠体を解体することなく枠体を撤去できる。そのため、仮設足場の設置時および撤去時において、仮設足場の組み立ておよび解体に要する手間を省略でき、工期短縮化および費用の低減化を図ることができる。
また、仮設足場の支持部材としてのブラケットは、簡易に杭に取り付けることが可能となるので、ブラケット取付時の手間を低減できる。
また、前記構造体が複数の前記杭の頭部に横架された状態で形成される場合には、前記枠体は前記開口部に複数の前記杭の杭頭部を挿通させた状態で前記ブラケットに上載され、複数の前記杭に固定されたブラケット同士は前記取付部同士の間に横架された連結部材を介して連結されているのが望ましい。ブラケットを介して複数の杭を連結すると、水流などの影響によって杭が揺れることを抑制できるので、施工時の安定性を向上させることができる。
Furthermore, according to the temporary scaffolding of this embodiment, after the structure 3 is constructed, the frame body can be raised while the structure is positioned within the opening of the frame body, so that the frame body can be removed without dismantling it. Therefore, when setting up and removing the temporary scaffolding, the labor required for assembling and dismantling the temporary scaffolding can be omitted, and the construction period can be shortened and costs can be reduced.
In addition, the brackets serving as support members for the temporary scaffolding can be easily attached to the piles, reducing the effort required for attaching the brackets.
In addition, when the structure is formed in a state in which it is horizontally mounted on the heads of the plurality of piles, it is preferable that the frame body is placed on the bracket with the heads of the plurality of piles inserted into the openings, and the brackets fixed to the plurality of piles are connected to each other via connecting members horizontally mounted between the mounting parts. By connecting the plurality of piles via brackets, it is possible to suppress the shaking of the piles due to the influence of water currents, etc., thereby improving stability during construction.

以上、本発明の実施形態について説明したが、本発明は、前述の実施形態に限られず、前記の各構成要素については本発明の趣旨を逸脱しない範囲で適宜変更が可能である。
前記実施形態では、杭が斜杭2の場合について説明したが、杭は必ずしも傾斜している必要はなく鉛直であってもよい。また、杭は、必ずしも鋼管杭である必要はなく、例えば、コンクリート杭であってもよい。また、水上構造物が有する杭の本数は、4本に限定されるものではなく、例えば、3本や5本以上であってもよい。
前記実施形態では、ブラケット4のベース部41を1本の鋼材により構成するものとしたが、ベース部41を構成する材料は限定されるものではなく、例えば、複数本の鋼材であってもよし、鋼板であってもよい。なお、ベース部41を鋼板により構成する場合には、杭の外面形状に応じて加工するのが望ましい。
Although an embodiment of the present invention has been described above, the present invention is not limited to the above-described embodiment, and each of the above-described components can be appropriately modified without departing from the spirit of the present invention.
In the above embodiment, the piles are described as inclined piles 2, but the piles do not necessarily have to be inclined and may be vertical. The piles do not necessarily have to be steel pipe piles and may be concrete piles, for example. The number of piles in the above-water structure is not limited to four and may be, for example, three or five or more.
In the above embodiment, the base portion 41 of the bracket 4 is made of a single piece of steel material, but the material constituting the base portion 41 is not limited, and may be, for example, a plurality of pieces of steel material or a steel plate. When the base portion 41 is made of a steel plate, it is preferable to process it according to the outer surface shape of the pile.

1 水上構造物
2 斜杭(杭)
3 構造体
4 ブラケット
41 ベース部
42 本体部
43 係止部
44 取付部
1. Water structure 2. Batter pile (pile)
3 Structure 4 Bracket 41 Base portion 42 Main body portion 43 Locking portion 44 Mounting portion

Claims (2)

水底に立設した杭にブラケットを取り付けるブラケット取付工程と、
前記ブラケットに枠状の仮設足場を載置する足場載置工程と、
前記杭の頭部にプレキャストコンクリート部材を架設する架設工程と、
前記仮設足場を撤去する足場撤去工程と、を備える水上構造物の施工方法であって、
前記仮設足場は、前記プレキャストコンクリート部材を挿通可能な大きさの開口部を有しており、
前記足場撤去工程では、前記開口部に前記プレキャストコンクリート部材を挿通させながら、前記仮設足場を上方に引き上げることを特徴とする、水上構造物の施工方法。
a bracket installation process for installing brackets on piles erected on the bottom of the water;
A scaffolding placement process of placing a frame-shaped temporary scaffolding on the bracket;
An erection step of erecting a precast concrete member on the head of the pile;
A scaffolding removal process for removing the temporary scaffolding,
The temporary scaffolding has an opening large enough to allow the precast concrete member to pass through,
A construction method for an overwater structure, characterized in that in the scaffolding removal process, the temporary scaffolding is pulled upward while the precast concrete member is inserted through the opening.
前記プレキャストコンクリート部材には、前記杭の位置に対応して箱抜きが形成されているとともに、補強部材として埋設された補強鉄骨が前記箱抜き内に露出していて、
前記架設工程では、前記杭の頭部を前記箱抜きに挿入するとともに、前記杭の頭部に形成した係合部に前記補強鉄骨を係合させた状態で前記杭の頭部に載置させた後、前記箱抜きにコンクリートを打設することを特徴とする、請求項に記載の水上構造物の施工方法。
The precast concrete member has a box cutout formed in correspondence with the position of the pile, and a reinforcing steel frame embedded as a reinforcing member is exposed in the box cutout,
2. The construction method for an offshore structure as described in claim 1, characterized in that in the erection process, the head of the pile is inserted into the box cutter, and the reinforcing steel frame is placed on the head of the pile in a state where it is engaged with the engagement portion formed on the head of the pile, and then concrete is poured into the box cutter.
JP2021025836A 2021-02-22 2021-02-22 Construction method for floating structures Active JP7503512B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021025836A JP7503512B2 (en) 2021-02-22 2021-02-22 Construction method for floating structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021025836A JP7503512B2 (en) 2021-02-22 2021-02-22 Construction method for floating structures

Publications (2)

Publication Number Publication Date
JP2022127702A JP2022127702A (en) 2022-09-01
JP7503512B2 true JP7503512B2 (en) 2024-06-20

Family

ID=83061325

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021025836A Active JP7503512B2 (en) 2021-02-22 2021-02-22 Construction method for floating structures

Country Status (1)

Country Link
JP (1) JP7503512B2 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000017643A (en) 1998-06-30 2000-01-18 Takenaka Komuten Co Ltd Working method for pile head portion of diagonally assembled pile body
JP2005264514A (en) 2004-03-17 2005-09-29 Nishimatsu Constr Co Ltd Foundation slab structure of sea berth structure, and its construction method
JP2011038247A (en) 2009-08-06 2011-02-24 Kumagai Gumi Co Ltd Method of constructing mono-pile foundation and joint pipe
JP2020016140A (en) 2019-03-07 2020-01-30 東亜建設工業株式会社 Method for manufacturing erection concrete structure in water area
JP2020180521A (en) 2019-04-26 2020-11-05 スターライト工業株式会社 Temporary scaffold and construction method for temporary scaffold

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000017643A (en) 1998-06-30 2000-01-18 Takenaka Komuten Co Ltd Working method for pile head portion of diagonally assembled pile body
JP2005264514A (en) 2004-03-17 2005-09-29 Nishimatsu Constr Co Ltd Foundation slab structure of sea berth structure, and its construction method
JP2011038247A (en) 2009-08-06 2011-02-24 Kumagai Gumi Co Ltd Method of constructing mono-pile foundation and joint pipe
JP2020016140A (en) 2019-03-07 2020-01-30 東亜建設工業株式会社 Method for manufacturing erection concrete structure in water area
JP2020180521A (en) 2019-04-26 2020-11-05 スターライト工業株式会社 Temporary scaffold and construction method for temporary scaffold

Also Published As

Publication number Publication date
JP2022127702A (en) 2022-09-01

Similar Documents

Publication Publication Date Title
KR101628264B1 (en) Support and frame system using temporary strut for top-down method and construction method thereof
JP6252835B2 (en) Box culvert and its construction method
JP7134070B2 (en) Construction method of top slab of underground structure
JP7503512B2 (en) Construction method for floating structures
JP2764894B2 (en) How to build a cylinder
JP4558138B2 (en) Seismic isolation method for existing buildings
JP7064898B2 (en) How to build a liquid barrier
JP4060947B2 (en) Pile head construction method for diagonally assembled piles
JPH11158813A (en) Concrete pier constructing method
JPH0657710A (en) Construction of concrete main tower
JP4872301B2 (en) Construction method of RC structure
JPH04330119A (en) Building foundation constructing method
JP3581590B2 (en) Retaining wall construction method
JP4060948B2 (en) Pile head construction method for diagonally assembled piles
JP2019218684A (en) Manufacturing method of culvert
JP2002038475A (en) Construction method of caisson type pile
JP6932348B2 (en) Cloth foundation, cloth foundation construction method, solid foundation construction method, and formwork used for the construction method
JP2001342639A (en) Buried form
JP6870905B2 (en) Artificial ground and its construction method
JPH11229614A (en) Concrete wall casting bracket scaffold
JP4185229B2 (en) Concrete stand
JPH028102B2 (en)
JP2023172647A (en) Reinforcement bar mount and construction method of wall
JP5185897B2 (en) Retaining wall construction method
JPH0820936A (en) Erection of concrete wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230322

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20240111

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240116

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240215

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240604

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240610

R150 Certificate of patent or registration of utility model

Ref document number: 7503512

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150