JP7447328B1 - Construction method of steel pipe piles and steel pipe piles - Google Patents

Construction method of steel pipe piles and steel pipe piles Download PDF

Info

Publication number
JP7447328B1
JP7447328B1 JP2023033828A JP2023033828A JP7447328B1 JP 7447328 B1 JP7447328 B1 JP 7447328B1 JP 2023033828 A JP2023033828 A JP 2023033828A JP 2023033828 A JP2023033828 A JP 2023033828A JP 7447328 B1 JP7447328 B1 JP 7447328B1
Authority
JP
Japan
Prior art keywords
stop plate
water stop
water
steel pipe
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2023033828A
Other languages
Japanese (ja)
Inventor
直志 中村
健次 堀越
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Engineering Co Ltd
Original Assignee
Nippon Steel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Engineering Co Ltd filed Critical Nippon Steel Engineering Co Ltd
Priority to JP2023033828A priority Critical patent/JP7447328B1/en
Application granted granted Critical
Publication of JP7447328B1 publication Critical patent/JP7447328B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

【課題】運搬性及び作業性を向上し、更に鋼管杭の施工に用いるクレーン等に求められる性能を抑えることができる鋼管杭及び鋼管杭の施工方法を提供する。【解決手段】鋼製の円筒部10と、円筒部10の内部に水が流れ込むことを防止可能な第1止水板20であって、円筒部10の内周面に設けられる第1止水板20と、を備え、水底に打設される鋼管杭100であって、第1止水板20は、所定条件で壊されることを特徴とする。【選択図】図1The present invention provides a steel pipe pile and a method for constructing the steel pipe pile, which can improve transportability and workability and further reduce the performance required of a crane or the like used for constructing the steel pipe pile. [Solution] A cylindrical part 10 made of steel, a first water stop plate 20 that can prevent water from flowing into the inside of the cylindrical part 10, and a first water stop plate 20 provided on the inner peripheral surface of the cylindrical part 10. A steel pipe pile 100 is provided with a plate 20 and is driven into the bottom of the water, and is characterized in that the first water stop plate 20 is broken under predetermined conditions. [Selection diagram] Figure 1

Description

本発明は、鋼管杭及び鋼管杭の施工方法に関する。 The present invention relates to a steel pipe pile and a method for constructing a steel pipe pile.

水上にジャケット構造体等を支持するために、水底に鋼管杭を打設することがある。
特許文献1では、杭を立て起こす際にクレーンに作用する荷重を制御することを目的として、クレーンによって杭の上端を持ち上げた状態で杭の下端の流入口を開放し、杭の内部に水を流入させる方法が開示されている。
特許文献2では、経済的に、かつ急速施工が可能な水中基礎として、メインコラムとメインコラム基部の外側に配置された複数のスカートコラムの内部にパイルを挿通して水底地盤中に貫入させ、コラムとパイルの隙間をグラウト材で結合し、コラム内に中詰コンクリートを充填した構造が開示されている。
Steel pipe piles are sometimes driven at the bottom of the water to support jacket structures, etc. above the water.
In Patent Document 1, for the purpose of controlling the load acting on a crane when raising a pile, an inlet at the lower end of the pile is opened while the upper end of the pile is lifted by a crane, and water is poured into the inside of the pile. A method is disclosed.
In Patent Document 2, as an underwater foundation that can be constructed economically and quickly, piles are inserted into the inside of a main column and a plurality of skirt columns arranged outside the main column base to penetrate into the underwater ground. A structure is disclosed in which the gap between the column and the pile is joined with grout, and the column is filled with filling concrete.

特許第6914411号公報Patent No. 6914411 特開平6-146305号公報Japanese Patent Application Publication No. 6-146305

前記従来の杭の施工方法では、杭の立て起こしの最中に流入口を操作する必要があることから、作業性の向上に課題がある。また、施工する杭が大きいと、水上における杭の運搬性が低下する課題がある。水上の作業船に搭載されるクレーンの揚程や吊り上げ荷重が不足する課題がある。 In the conventional pile construction method described above, there is a problem in improving work efficiency because it is necessary to operate the inlet while the pile is being erected. Additionally, if the piles to be constructed are large, there is a problem in that the transportability of the piles on water is reduced. There is an issue of insufficient lift height and lifting load for cranes mounted on waterborne work vessels.

本発明は、前述した事情に鑑みてなされたものであって、運搬性及び作業性を向上し、更に鋼管杭の施工に用いるクレーン等に求められる性能を抑えることができる鋼管杭及び鋼管杭の施工方法を提供することを目的とする。 The present invention has been made in view of the above-mentioned circumstances, and is a method for producing steel pipe piles and steel pipe piles that can improve transportability and workability, and further reduce the performance required of cranes, etc. used for the construction of steel pipe piles. The purpose is to provide a construction method.

<1>本発明の態様1に係る鋼管杭は、鋼製の円筒部と、前記円筒部の内部に水が流れ込むことを防止可能な第1止水板であって、前記円筒部の内周面に設けられる第1止水板と、を備え、水底に打設される鋼管杭であって、前記第1止水板は、所定条件で壊されることを特徴とする。 <1> The steel pipe pile according to Aspect 1 of the present invention includes a cylindrical portion made of steel and a first water stop plate capable of preventing water from flowing into the cylindrical portion, and the inner periphery of the cylindrical portion. A steel pipe pile is provided with a first water stop plate provided on a surface, and is driven into the bottom of the water, wherein the first water stop plate is broken under predetermined conditions.

この発明によれば、鋼管杭は、円筒部の内部に水が流れ込むことを防止可能な第1止水板を備える。鋼管杭を、第1止水板によって鋼管杭の内部に水が流れ込むことを防止された状態とすることで、鋼管杭を水上に浮かべることができる。これにより、例えば、鋼管杭を水上に浮かべた状態のまま作業船等で引っ張ることで、水上で鋼管杭を運搬する際に必要な力を抑えることができる。 According to this invention, the steel pipe pile includes the first water stop plate that can prevent water from flowing into the cylindrical portion. By setting the steel pipe pile in a state where water is prevented from flowing into the steel pipe pile by the first water stop plate, the steel pipe pile can be floated on water. Thereby, for example, by pulling the steel pipe pile with a work boat or the like while floating on the water, the force required when transporting the steel pipe pile on water can be suppressed.

第1止水板は、所定条件で壊される。これにより、第1止水板を壊すことで、円筒部の内部に水を流入させることができる。よって、杭に設けられた流入口を施工中に操作する方法と比較して、作業を容易にすることができる。
例えば、鋼管杭を施工現場まで運搬した後に、第1止水板を壊す。このことで、円筒部の内部に水が流入すると、円筒部の、水が流入した側の端部が水中に沈む。これにより、水上において鋼管杭を立てることができる。したがって、クレーン等を用いて鋼管杭の端部を吊り上げることで水上に鋼管杭を立てる場合と比較して、必要な吊り上げ力を小さくすることができる。よって、鋼管杭の施工に用いるクレーン等に求められる性能を抑えることができる。
The first water stop plate is broken under predetermined conditions. This allows water to flow into the cylindrical portion by breaking the first water stop plate. Therefore, compared to a method in which an inlet provided in a pile is operated during construction, the work can be made easier.
For example, after transporting the steel pipe pile to the construction site, the first water stop plate is broken. As a result, when water flows into the cylindrical part, the end of the cylindrical part on the side where the water flows sinks into the water. This allows steel pipe piles to be erected on water. Therefore, by lifting the end of the steel pipe pile using a crane or the like, the required lifting force can be reduced compared to the case where the steel pipe pile is erected on water. Therefore, the performance required of a crane or the like used for constructing steel pipe piles can be suppressed.

<2>本発明の態様2に係る鋼管杭は、態様1に係る鋼管杭において、前記第1止水板は、前記円筒部の外部から引っ張られることで壊されることを特徴とする。 <2> The steel pipe pile according to Aspect 2 of the present invention is characterized in that, in the steel pipe pile according to Aspect 1, the first water stop plate is broken by being pulled from the outside of the cylindrical portion.

この発明によれば、第1止水板は、円筒部の外部から引っ張られることで壊される。これにより、例えば、鋼管杭が水上に浮かべられた状態で、第1止水板に取り付けられたロープを作業船等によって引っ張ることで、第1止水板を壊すことができる。したがって、鋼管杭をクレーン等で吊り上げることなく、鋼管杭のいずれかの端部を水中に沈ませることで、鋼管杭を立てることができる。 According to this invention, the first water stop plate is broken by being pulled from the outside of the cylindrical portion. Thereby, for example, the first water stop plate can be broken by pulling the rope attached to the first water stop plate with a work boat or the like while the steel pipe pile is floating on water. Therefore, the steel pipe pile can be erected by submerging either end of the steel pipe pile in water without lifting the steel pipe pile with a crane or the like.

<3>本発明の態様3に係る鋼管杭は、態様1又は態様2に係る鋼管杭において、前記第1止水板は、所定圧力で壊れることを特徴とする。 <3> The steel pipe pile according to Aspect 3 of the present invention is the steel pipe pile according to Aspect 1 or Aspect 2, wherein the first water stop plate breaks at a predetermined pressure.

この発明によれば、第1止水板は、所定圧力で壊れる。これにより、例えば、鋼管杭が水上に浮かべられた状態で、鋼管杭における第1止水板が設けられた側と反対側の端部を、クレーン等で持ち上げる。すると、鋼管杭における第1止水板が設けられた側の端部が水中に沈む。このことで、第1止水板に水圧を付加することで、第1止水板を壊すことができる。したがって、クレーン等によって鋼管杭を吊り上げることのみによって鋼管杭を水上に立てる場合と比較して、クレーン等が鋼管杭を吊り上げる量や、吊り上げに必要な力を小さくすることができる。 According to this invention, the first water stop plate breaks at a predetermined pressure. As a result, for example, with the steel pipe pile floating on water, the end of the steel pipe pile on the opposite side to the side where the first water stop plate is provided is lifted up by a crane or the like. Then, the end of the steel pipe pile on the side where the first water stop plate is provided sinks into the water. With this, the first water stop plate can be broken by applying water pressure to the first water stop plate. Therefore, compared to the case where the steel pipe pile is erected on water only by lifting the steel pipe pile with a crane or the like, the amount of lifting of the steel pipe pile by the crane or the like and the force required for lifting can be reduced.

<4>本発明の態様4に係る鋼管杭は、態様1から態様3のいずれか1つに係る鋼管杭において、前記第1止水板には、綱状部材が設けられ、前記第1止水板は、前記綱状部材が引っ張られることで壊されることを特徴とする。 <4> The steel pipe pile according to Aspect 4 of the present invention is the steel pipe pile according to any one of Aspects 1 to 3, wherein the first water stop plate is provided with a rope-like member, and the first water stop plate is provided with a rope-like member. The water plate is characterized in that it is broken by pulling the rope member.

この発明によれば、第1止水板には、綱状部材が設けられ、第1止水板は、綱状部材が引っ張られることで壊される。これにより、円筒部の外部から、容易に第1止水板を引っ張ることができる。よって、第1止水板を容易に壊すことができる。 According to this invention, the first water stop plate is provided with a rope-like member, and the first water stop plate is broken when the rope-like member is pulled. Thereby, the first water stop plate can be easily pulled out from the outside of the cylindrical portion. Therefore, the first water stop plate can be easily broken.

<5>本発明の態様5に係る鋼管杭は、態様4に係る鋼管杭において、前記第1止水板には、係合部材が設けられ、前記係合部材は、係合部を備え、前記綱状部材は、前記係合部と係合することを特徴とする。 <5> The steel pipe pile according to Aspect 5 of the present invention is the steel pipe pile according to Aspect 4, wherein the first water stop plate is provided with an engagement member, the engagement member includes an engagement part, The above-mentioned rope-like member is characterized in that it engages with the above-mentioned engagement part.

この発明によれば、第1止水板には、係合部材が設けられ、綱状部材は、係合部材と係合する。これにより、第1止水板を綱状部材によってより容易且つ確実に引っ張ることができる。 According to this invention, the first water stop plate is provided with the engagement member, and the rope member engages with the engagement member. Thereby, the first water stop plate can be pulled more easily and reliably by the rope member.

<6>本発明の態様6に係る鋼管杭は、態様5に係る鋼管杭において、前記係合部材は、凸部を備え、前記凸部は、前記第1止水板を挟んで、前記第1止水板が引っ張られる側とは反対側に設けられ、前記凸部は、前記係合部材が前記綱状部材で引っ張られることで、前記第1止水板に押し付けられ、前記第1止水板を壊すことを特徴とする。 <6> In the steel pipe pile according to Aspect 6 of the present invention, in the steel pipe pile according to Aspect 5, the engaging member includes a convex portion, and the convex portion is arranged such that the first water stop plate is sandwiched between the steel pipe pile and the first water stop plate. 1 is provided on the opposite side to the side on which the water stop plate is pulled, and the convex portion is pressed against the first water stop plate when the engagement member is pulled by the rope-like member, and the convex portion is pressed against the first water stop plate and Characterized by breaking the water plate.

この発明によれば、凸部は、係合部材が綱状部材で引っ張られることで、第1止水板に押し付けられ、第1止水板を壊す。これにより、更に第1止水板を容易に壊すことができる。 According to this invention, when the engagement member is pulled by the rope-like member, the convex portion is pressed against the first water stop plate and breaks the first water stop plate. Thereby, the first water stop plate can be further easily broken.

<7>本発明の態様7に係る鋼管杭は、態様5又は態様6に係る鋼管杭において、前記係合部は、前記第1止水板の面のうち、前記第1止水板が引っ張られる側の面に設けられていることを特徴とする。 <7> In the steel pipe pile according to Aspect 7 of the present invention, in the steel pipe pile according to Aspect 5 or Aspect 6, the engaging portion is arranged so that the first water stop plate is pulled out of the surface of the first water stop plate. It is characterized by being provided on the side that is exposed.

この発明によれば、係合部は、第1止水板の面のうち、第1止水板が引っ張られる側の面に設けられている。これにより、綱状部材を係合部に係合しやすくすることができる。 According to this invention, the engaging portion is provided on the surface of the first water stop plate on the side where the first water stop plate is pulled. Thereby, it is possible to easily engage the rope member with the engagement portion.

<8>本発明の態様8に係る鋼管杭は、態様1から態様7のいずれか1つに係る鋼管杭において、前記円筒部の内周面に設けられ、且つ、前記円筒部の両端のうち水底に遠い方の端の側に設けられる第2止水板を更に備え、前記第1止水板は、前記両端のうち前記水底に近い方の端の側に設けられることを特徴とする。 <8> The steel pipe pile according to Aspect 8 of the present invention is the steel pipe pile according to any one of Aspects 1 to 7, wherein the steel pipe pile is provided on the inner peripheral surface of the cylindrical part, and It is further provided with a second water stop plate provided on the side of the end farthest from the bottom of the water, and the first water stop plate is provided on the side of the end near the bottom of the water between the two ends.

この発明によれば、円筒部の内周面に設けられ、且つ、円筒部の両端のうち水底に遠い方の端の側に設けられる第2止水板を更に備える。これにより、第1止水板と第2止水板とによって、円筒部の内部に空気を密封することができる。よって、鋼管杭を水上に浮かべることができる。第1止水板は、円筒部の両端のうち水底に近い方の端の側に設けられる。これにより、第1止水板を壊すことで、円筒部の両端のうち水底に近い方の端の側から、円筒部の内部に水を流入させることができる。また、例えば、第1止水板を円筒部の端に設けることで、第1止水板を引っ張りやすくすることができる。 According to this invention, the water tank further includes a second water stop plate provided on the inner circumferential surface of the cylindrical portion and provided on the side of the end farther from the bottom of the water among both ends of the cylindrical portion. Thereby, air can be sealed inside the cylindrical portion by the first water stop plate and the second water stop plate. Therefore, steel pipe piles can be floated on water. The first water stop plate is provided on the side of the end closer to the bottom of the water out of both ends of the cylindrical part. Thereby, by breaking the first water stop plate, water can flow into the interior of the cylindrical portion from the side of the end closer to the bottom of the water out of both ends of the cylindrical portion. Further, for example, by providing the first water stop plate at the end of the cylindrical portion, the first water stop plate can be easily pulled.

<9>本発明の態様9に係る鋼管杭は、態様8に係る鋼管杭において、前記第2止水板は、ゴム製であり、且つ、所定圧力で壊れることを特徴とする。 <9> A steel pipe pile according to aspect 9 of the present invention is the steel pipe pile according to aspect 8, wherein the second water stop plate is made of rubber and breaks at a predetermined pressure.

この発明によれば、第2止水板は、ゴム製であり、且つ、所定圧力で壊れる。例えば、鋼管杭を水上に立てる際、まず、第1止水板を壊すことで、鋼管杭の第1止水板が設けられた側の端部を沈ませる。このとき、第2止水板によって、円筒部の内部に空気を残すことで、鋼管杭の見かけの重さを軽くすることができる。よって、クレーン等による鋼管杭の吊り上げを容易にすることができる。また、鋼管杭を水上に立てた後に第2止水板を壊すことで、円筒部の内部から空気を取り除き、円筒部の内外の気圧を同じにすることができる。よって、水底に打設された後の鋼管杭を安定した状態とすることができる。 According to this invention, the second water stop plate is made of rubber and breaks at a predetermined pressure. For example, when a steel pipe pile is erected on water, first, by breaking the first water stop plate, the end of the steel pipe pile on the side where the first water stop plate is provided is sunk. At this time, by leaving air inside the cylindrical portion using the second water stop plate, the apparent weight of the steel pipe pile can be reduced. Therefore, the steel pipe pile can be easily lifted by a crane or the like. Moreover, by breaking the second water stop plate after the steel pipe pile is erected on the water, air can be removed from the inside of the cylindrical part and the air pressure inside and outside the cylindrical part can be equalized. Therefore, the steel pipe pile can be kept in a stable state after being driven into the water bottom.

<10>本発明の態様10に係る鋼管杭は、態様8又は態様9に係る鋼管杭において、前記第2止水板は、前記円筒部の外部から引っ張られることで壊されることを特徴とする。 <10> The steel pipe pile according to Aspect 10 of the present invention is the steel pipe pile according to Aspect 8 or Aspect 9, wherein the second water stop plate is broken by being pulled from the outside of the cylindrical portion. .

この発明によれば、第2止水板は、円筒部の外部から引っ張られることで壊される。これにより、例えば、水上に鋼管杭を立てた後、第2止水板を円筒部の外部から引っ張ることで壊すことができる。これにより、円筒部の内部から空気を取り除く作業を、鋼管杭が安定した状態で行うことができる。 According to this invention, the second water stop plate is broken by being pulled from the outside of the cylindrical portion. Thereby, for example, after a steel pipe pile is erected on the water, the second water stop plate can be broken by pulling it from the outside of the cylindrical part. Thereby, the work of removing air from the inside of the cylindrical portion can be performed while the steel pipe pile is in a stable state.

<11>本発明の態様11に係る鋼管杭は、態様8から態様10のいずれか1つに係る鋼管杭において、前記円筒部の内周面に設けられ、且つ、前記第1止水板と前記第2止水板との間に設けられる第3止水板、を更に備え、前記第3止水板は、ゴム製であり、且つ、前記円筒部の外部から引っ張られることで壊されることを特徴とする。 <11> The steel pipe pile according to Aspect 11 of the present invention is the steel pipe pile according to any one of Aspects 8 to 10, wherein the steel pipe pile is provided on the inner peripheral surface of the cylindrical part, and is provided with the first water stop plate. It further includes a third water stop plate provided between the second water stop plate, and the third water stop plate is made of rubber and cannot be broken by being pulled from the outside of the cylindrical portion. It is characterized by

この発明によれば、円筒部の内周面に設けられ、且つ、第1止水板と第2止水板との間に設けられる第3止水板を更に備え、第3止水板は、ゴム製であり、且つ、円筒部の外部から引っ張られることで壊される。これにより、円筒部の内部に水を流入させる作業を段階的に行うことができる。よって、鋼管杭の、第1止水板が設けられた側の端部が水中に沈む速度を遅くすることができる。よって、鋼管杭を水上に立てる作業をより安定して行うことができる。また、第3止水板が壊れる前の状態において、第3止水板と第2止水板との間に空気を残すことができる。したがって、第3止水板が壊れた後も、円筒部の内部に空気を確実に残すことができる。よって、鋼管杭を立てる際に、空気による浮力を利用しやすくすることができる。よって、より鋼管杭の見かけの重さを軽くすることができる。 According to this invention, the third water stop plate is further provided on the inner circumferential surface of the cylindrical portion and provided between the first water stop plate and the second water stop plate, and the third water stop plate is , is made of rubber, and can be broken by being pulled from the outside of the cylindrical part. Thereby, the work of flowing water into the interior of the cylindrical portion can be performed in stages. Therefore, it is possible to slow down the speed at which the end of the steel pipe pile on the side where the first water stop plate is provided sinks into water. Therefore, the work of erecting steel pipe piles on water can be performed more stably. Furthermore, air can be left between the third water stop plate and the second water stop plate before the third water stop plate is broken. Therefore, even after the third water stop plate is broken, air can be reliably left inside the cylindrical portion. Therefore, when setting up a steel pipe pile, it is possible to easily utilize the buoyancy of the air. Therefore, the apparent weight of the steel pipe pile can be further reduced.

<12>本発明の態様12に係る鋼管杭は、態様11に係る鋼管杭において、前記第2止水板は、前記第3止水板より低い圧力で壊れることを特徴とする。 <12> The steel pipe pile according to aspect 12 of the present invention is the steel pipe pile according to aspect 11, characterized in that the second water stop plate breaks at a lower pressure than the third water stop plate.

この発明によれば、第2止水板は、第3止水板より低い圧力で壊れる。つまり、第3止水板の強度は、第2止水板の強度よりも高い。これにより、第3止水板を、鋼管杭の第1止水板が設けられた側の端部が水中に沈む際に、円筒部の内部に流入した水や、円筒部の内部に流入した水によって圧縮された空気によって付加される圧力に対して、十分な強度とすることができる。 According to this invention, the second water stop plate breaks at a lower pressure than the third water stop plate. That is, the strength of the third water stop plate is higher than the strength of the second water stop plate. As a result, when the end of the steel pipe pile on the side where the first water stop plate is installed is submerged in water, the third water stop plate is protected against water that has flowed into the inside of the cylindrical part, and water that has flowed into the inside of the cylindrical part. It can have sufficient strength against the pressure applied by air compressed by water.

<13>本発明の態様13に係る鋼管杭は、態様4から態様12のいずれか1つに係る鋼管杭において、前記綱状部材は、作業船に据え付けられる牽引装置で牽引されることを特徴とする。 <13> The steel pipe pile according to aspect 13 of the present invention is the steel pipe pile according to any one of aspects 4 to 12, wherein the rope-like member is towed by a towing device installed on a work boat. shall be.

この発明によれば、綱状部材は、作業船に据え付けられる牽引装置で牽引される。これにより、第1止水板をより大きな力で引っ張ることを容易に行うことができる。 According to this invention, the rope member is towed by a towing device installed on a work boat. Thereby, it is possible to easily pull the first water stop plate with a larger force.

<14>本発明の態様14に係る鋼管杭は、態様1から態様13のいずれか1つに係る鋼管杭において、前記第1止水板は、前記円筒部に設けられた第1止水板押さえプレートと、前記円筒部に設けられた第1止水板受けプレートと、に挟まれることを特徴とする。 <14> The steel pipe pile according to aspect 14 of the present invention is the steel pipe pile according to any one of aspects 1 to 13, in which the first water stop plate is a first water stop plate provided in the cylindrical part. It is characterized in that it is sandwiched between a holding plate and a first water stop plate receiving plate provided on the cylindrical portion.

この発明によれば、第1止水板は、円筒部に設けられた第1止水板押さえプレートと、円筒部に設けられた第1止水板受けプレートと、に挟まれる。これにより、第1止水板を円筒部の内周面に確実に固定することができる。したがって、第1止水板をより強く引っ張ることができる。よって、より第1止水板を壊しやすくすることができる。 According to this invention, the first water stop plate is sandwiched between the first water stop plate holding plate provided on the cylindrical portion and the first water stop plate receiving plate provided on the cylindrical portion. Thereby, the first water stop plate can be reliably fixed to the inner circumferential surface of the cylindrical portion. Therefore, the first water stop plate can be pulled more strongly. Therefore, the first water stop plate can be made easier to break.

<15>本発明の態様15に係る鋼管杭は、態様14に係る鋼管杭において、前記第1止水板押さえプレートは、環状であり、前記第1止水板押さえプレートの内径は、前記円筒部の両端のうち水底に近い方の端に向かうにつれ、大きくなる、ことを特徴とする。 <15> In the steel pipe pile according to Aspect 15 of the present invention, in the steel pipe pile according to Aspect 14, the first waterstop retaining plate is annular, and the inner diameter of the first waterstop retaining plate is equal to that of the cylinder. It is characterized by increasing in size toward the end closer to the bottom of the water.

この発明によれば、第1止水板押さえプレートは、環状であり、第1止水板押さえプレートの内径は、円筒部の両端のうち水底に近い方の端に向かうにつれ、大きくなる。よって、円筒部の第1止水板が設けられた側の端部から水が流入した時、第1止水板押さえプレートが水流の抵抗となることを抑えることができる。また、例えば、鋼管杭を水底に打設する時、第1止水板押さえプレートが抵抗となることを抑えることもできる。 According to this invention, the first waterstop retainer plate is annular, and the inner diameter of the first waterstop retainer plate increases toward the end closer to the bottom of the water of both ends of the cylindrical portion. Therefore, when water flows in from the end of the cylindrical portion on the side where the first water stop plate is provided, it is possible to prevent the first water stop plate holding plate from becoming a resistance to the water flow. Further, for example, when driving a steel pipe pile into the bottom of water, it is possible to prevent the first waterstop plate from acting as resistance.

<16>本発明の態様16に係る鋼管杭は、態様1から態様15のいずれか1つに係る鋼管杭において、前記第1止水板は、ゴム製であることを特徴とする。 <16> A steel pipe pile according to aspect 16 of the present invention is the steel pipe pile according to any one of aspects 1 to 15, wherein the first water stop plate is made of rubber.

この発明によれば、第1止水板は、ゴム製である。これにより、第1止水板を壊しやすくすることができる。 According to this invention, the first water stop plate is made of rubber. Thereby, the first water stop plate can be easily broken.

<17>本発明の態様17に係る鋼管杭の施工方法は、鋼製の円筒部と、前記円筒部の内部に水が流れ込むことを防止可能な第1止水板であって、前記円筒部の内周面に設けられる第1止水板と、を備え、水底に打設される鋼管杭の施工方法であって、前記第1止水板は、ゴム製であり、且つ、所定条件で壊され、水上に横たわる前記鋼管杭の一端を吊り上げる吊り上げ工程と、前記吊り上げ工程が実施されることで前記鋼管杭の他端が水に沈んだ状態で、前記第1止水板が壊されることで前記鋼管杭に水を流入させる注水工程と、前記注水工程の後、前記鋼管杭を、前記第1止水板が壊された状態で、前記水底に打設する打設工程と、を備えることを特徴とする。 <17> A method for constructing a steel pipe pile according to aspect 17 of the present invention includes a cylindrical portion made of steel, and a first waterstop plate capable of preventing water from flowing into the cylindrical portion, the cylindrical portion a first water stop plate provided on the inner circumferential surface of the steel pipe pile, the first water stop plate is made of rubber, and the first water stop plate is made of rubber, and a lifting step of lifting one end of the steel pipe pile that has been broken and is lying on water, and the first water stop plate is broken with the other end of the steel pipe pile submerged in water by carrying out the lifting step. a water injection step of causing water to flow into the steel pipe pile; and a driving step of driving the steel pipe pile into the water bottom with the first water stop plate broken after the water injection step. It is characterized by

この発明によれば、吊り上げ工程と、注水工程と、を備える。吊り上げ工程によって鋼管杭の他端を水に沈ませることで、鋼管杭の見かけの重さを軽くすることができる。注水工程によって鋼管杭に水を流入させることで、水上に鋼管杭を立てやすくすることができる。よって、鋼管杭を立てる際に必要な鋼管杭の吊り上げ量を少なくすることができる。これにより、鋼管杭を打設する作業をより容易にすることができる。 According to this invention, the lifting process and the water injection process are provided. By submerging the other end of the steel pipe pile in water during the lifting process, the apparent weight of the steel pipe pile can be reduced. By allowing water to flow into the steel pipe pile through the water injection process, it becomes easier to erect the steel pipe pile above water. Therefore, the amount of lifting of the steel pipe pile required when setting the steel pipe pile can be reduced. This makes it easier to drive steel pipe piles.

本発明によれば、運搬性及び作業性を向上し、更に鋼管杭の施工に用いるクレーン等に求められる性能を抑えることができる鋼管杭及び鋼管杭の施工方法を提供することができる。 According to the present invention, it is possible to provide a steel pipe pile and a method for constructing a steel pipe pile, which can improve transportability and workability, and further reduce the performance required of a crane or the like used for constructing the steel pipe pile.

鋼管杭を破断した正面図である。It is a front view of a steel pipe pile broken. 図1に示すII部の拡大図である。FIG. 2 is an enlarged view of section II shown in FIG. 1. FIG. 図1に示す鋼管杭が立てられる途中の状態を示す図である。FIG. 2 is a diagram showing a state in which the steel pipe pile shown in FIG. 1 is being erected. 図1に示す鋼管杭が立てられた状態を示す図である。FIG. 2 is a diagram showing a state in which the steel pipe pile shown in FIG. 1 is erected. 係合部材の第1例である。This is a first example of an engaging member. 係合部材の第2例である。This is a second example of the engagement member. 係合部材の第3例である。This is a third example of the engagement member. 係合部材の第4例である。This is a fourth example of the engagement member. 第2鋼管杭を破断した正面図である。It is a front view of the second steel pipe pile being broken. 図9に示す第2鋼管杭が立てられる途中の状態を示す図である。10 is a diagram showing a state in which the second steel pipe pile shown in FIG. 9 is being erected. FIG. 図9に示す第2鋼管杭が立てられた状態を示す図である。It is a figure which shows the state where the 2nd steel pipe pile shown in FIG. 9 is erected.

(第1実施形態)
以下、図面を参照し、本発明の一実施形態に係る鋼管杭100を説明する。本実施形態に係る鋼管杭100は、例えば、下端が水底に打設される。鋼管杭100は、例えば、上端にジャケット構造体のレグが接続される。これにより、鋼管杭100は、水上に配置されるジャケット構造体等を支持する。なお、鋼管杭100の上端には、風車タワーやトランジションピース等の円筒型の構造体が取り付けられても良い。
(First embodiment)
Hereinafter, a steel pipe pile 100 according to an embodiment of the present invention will be described with reference to the drawings. For example, the lower end of the steel pipe pile 100 according to this embodiment is driven into the water bottom. For example, a leg of a jacket structure is connected to the upper end of the steel pipe pile 100. Thereby, the steel pipe pile 100 supports the jacket structure etc. placed on the water. Note that a cylindrical structure such as a wind turbine tower or a transition piece may be attached to the upper end of the steel pipe pile 100.

図1に示すように、鋼管杭100は、円筒部10と、第1止水板20と、第2止水板30と、を備える。
円筒部10は、鋼製である。円筒部10の外径は、例えば、2.5m~15.0mである。円筒部10の長さは、例えば、30m~120mである。円筒部10の板厚は、例えば、直径と板厚との比(d/t)が、30~150の範囲内となる厚さである。
As shown in FIG. 1, the steel pipe pile 100 includes a cylindrical portion 10, a first water stop plate 20, and a second water stop plate 30.
The cylindrical portion 10 is made of steel. The outer diameter of the cylindrical portion 10 is, for example, 2.5 m to 15.0 m. The length of the cylindrical portion 10 is, for example, 30 m to 120 m. The thickness of the cylindrical portion 10 is, for example, such that the ratio of diameter to thickness (d/t) is within the range of 30 to 150.

第1止水板20は、円筒部10の内周面に設けられる。第1止水板20は、円筒部10の長手方向の両端のうち、水底に近い方の端の側に設けられる。つまり、第1止水板20は、円筒部10を立てた時、下側になる端の側に設けられる。
第1止水板20は、円筒部10の内部に水Wが流れ込むことを防止可能である。これにより、例えば、鋼管杭100を立てる時、浮力を利用して鋼管杭100の見かけの重さを軽くする。
第1止水板20は、樹脂製である。例えば、第1止水板20には、ゴムや、プラスチックが好適に用いられる。本実施形態において、第1止水板20は、ゴム製である。
The first water stop plate 20 is provided on the inner circumferential surface of the cylindrical portion 10 . The first water stop plate 20 is provided on the end closer to the bottom of the water of both ends of the cylindrical portion 10 in the longitudinal direction. That is, the first water stop plate 20 is provided on the lower end side when the cylindrical portion 10 is erected.
The first water stop plate 20 can prevent water W from flowing into the cylindrical portion 10 . Thereby, for example, when the steel pipe pile 100 is erected, the apparent weight of the steel pipe pile 100 is reduced using buoyancy.
The first water stop plate 20 is made of resin. For example, rubber or plastic is preferably used for the first water stop plate 20. In this embodiment, the first water stop plate 20 is made of rubber.

第1止水板20は、図2に示すように、円筒部10に設けられた第1止水板受けプレート21と、円筒部10に設けられた第1止水板押さえプレート22と、に挟まれることで、円筒部10の内周面に固定される。
第1止水板受けプレート21は、環状である。図2に示すように、第1止水板受けプレート21は、第1止水板20よりも円筒部10の長手方向における第1止水板20が設けられた側の端から遠い側に配置される。第1止水板受けプレート21は、例えば、円筒部10の内周面に溶接により固定される。第1止水板20は、上述のように設けられた第1止水板受けプレート21に当接する。このことで、円筒部10の内周面において、第1止水板20が、第1止水板受けプレート21よりも奥側に移動しないようにする。
As shown in FIG. 2, the first water stop plate 20 includes a first water stop plate receiving plate 21 provided on the cylindrical portion 10 and a first water stop plate holding plate 22 provided on the cylindrical portion 10. By being sandwiched, it is fixed to the inner circumferential surface of the cylindrical portion 10.
The first water stop plate receiving plate 21 has an annular shape. As shown in FIG. 2, the first water stop plate receiving plate 21 is disposed on the side farther from the end of the cylindrical portion 10 in the longitudinal direction on which the first water stop plate 20 is provided than the first water stop plate 20. be done. The first water stop plate receiving plate 21 is fixed to the inner peripheral surface of the cylindrical portion 10 by, for example, welding. The first water stop plate 20 contacts the first water stop plate receiving plate 21 provided as described above. This prevents the first water stop plate 20 from moving further back than the first water stop plate receiving plate 21 on the inner circumferential surface of the cylindrical portion 10.

第1止水板押さえプレート22は、環状である。図2に示すように、第1止水板押さえプレート22は、第1止水板20よりも円筒部10の長手方向における第1止水板受けプレート21が設けられた側の端に近い側に配置される。第1止水板押さえプレート22は、例えば、図2に示すように、第1止水板受けプレート21にボルトBとナットNとで固定される。このとき、第1止水板20は、第1止水板押さえプレート22と、第1止水板受けプレート21と、の間に挟まれる。このことで、第1止水板20は、円筒部10の内周面に固定される。 The first waterstop plate 22 has an annular shape. As shown in FIG. 2, the first water stop plate holding plate 22 is located at a side closer to the end of the cylindrical portion 10 in the longitudinal direction on the side where the first water stop plate receiving plate 21 is provided than the first water stop plate 20. will be placed in The first water stop plate holding plate 22 is fixed to the first water stop plate receiving plate 21 with bolts B and nuts N, for example, as shown in FIG. At this time, the first water stop plate 20 is sandwiched between the first water stop plate holding plate 22 and the first water stop plate receiving plate 21. With this, the first water stop plate 20 is fixed to the inner circumferential surface of the cylindrical portion 10.

図2に示すように、第1止水板押さえプレート22の内径は、円筒部10の両端のうち水底に近い方の端に向かうにつれ、大きくなる。つまり、第1止水板押さえプレート22の内径は、円筒部10の長手方向において、第1止水板押さえプレート22が設けられた側の端に向かうにつれ、小さくなる。このことで、円筒部10の内部に水Wが流れ込む時、第1止水板押さえプレート22に水Wが衝突して水Wの流れが妨げられることを抑える。また、第1止水板押さえプレート22をこのような形状とすることで、鋼管杭100を海底に打設するとき、第1止水板押さえプレート22に作用する抵抗力を減らす。 As shown in FIG. 2, the inner diameter of the first waterstop plate 22 increases toward the end closer to the bottom of the water of both ends of the cylindrical portion 10. In other words, the inner diameter of the first water stop plate 22 becomes smaller in the longitudinal direction of the cylindrical portion 10 toward the end on the side where the first water stop plate 22 is provided. This prevents the water W from colliding with the first waterstop plate 22 and blocking the flow of the water W when it flows into the cylindrical portion 10. Further, by forming the first water stop plate 22 in such a shape, the resistance force acting on the first water stop plate 22 is reduced when the steel pipe pile 100 is driven into the seabed.

第1止水板20は、所定条件で壊される。つまり、第1止水板20は、所定条件を満たすことで、不可逆的に破断する。このことで、円筒部10の内部に水Wを流入させる。例えば、鋼管杭100を水Wの上に立てる時に、第1止水板20を壊して円筒部10の内部に水Wを流入させる。これにより、図3に示すように、円筒部10の端部を沈ませる。このことで、図4に示すように鋼管杭100を水Wの上に立てる時、円筒部10をクレーン等で吊り上げる量を少なくする。本実施形態において、第1止水板20が壊される所定条件は、以下の2態様を備える。 The first water stop plate 20 is broken under predetermined conditions. That is, the first water stop plate 20 is irreversibly broken when a predetermined condition is satisfied. This allows water W to flow into the cylindrical portion 10 . For example, when the steel pipe pile 100 is erected on water W, the first water stop plate 20 is broken to allow water W to flow into the cylindrical portion 10. Thereby, as shown in FIG. 3, the end of the cylindrical portion 10 is sunk. With this, when the steel pipe pile 100 is erected on the water W as shown in FIG. 4, the amount by which the cylindrical portion 10 is lifted by a crane or the like is reduced. In this embodiment, the predetermined conditions under which the first water stop plate 20 is broken include the following two aspects.

第1止水板20が壊される所定条件の第1態様として、第1止水板20は、円筒部10の外部から引っ張られることで壊される。この態様を執る場合、第1止水板20には、図2に示すように、綱状部材23と、係合部材24と、が設けられる。
綱状部材23は、第1止水板20を引っ張る為に設けられる。つまり、第1止水板20は、綱状部材23が引っ張られることで壊される。綱状部材23には、例えば、ロープやチェーンが用いられる。綱状部材23は、一方の端部が第1止水板20に設けられた係合部材24に取付けられる。この状態で、綱状部材23の他方の端部を引っ張ることで、第1止水板20を引っ張る。綱状部材23は、例えば、水Wの上において、不図示の作業船に据え付けられる牽引装置で牽引されることで引っ張られる。綱状部材23は、綱状部材23の他方の端部が繋がれた作業船が、鋼管杭100から離れる方向に移動することで引っ張られてもよい。
As a first aspect of the predetermined condition under which the first water stop plate 20 is broken, the first water stop plate 20 is broken by being pulled from the outside of the cylindrical portion 10 . In this case, the first water stop plate 20 is provided with a rope member 23 and an engagement member 24, as shown in FIG.
The rope member 23 is provided to pull the first water stop plate 20. In other words, the first water stop plate 20 is broken when the rope member 23 is pulled. For example, a rope or a chain is used as the rope member 23. One end of the rope member 23 is attached to an engagement member 24 provided on the first water stop plate 20 . In this state, by pulling the other end of the rope member 23, the first water stop plate 20 is pulled. The rope member 23 is pulled, for example, on the water W by being towed by a towing device installed on a work boat (not shown). The rope member 23 may be pulled when the work boat to which the other end of the rope member 23 is connected moves in a direction away from the steel pipe pile 100.

係合部材24は、図2に示すように、第1止水板20の中央に設けられる。係合部材24は、図5に示すように、中心軸24aと、係合部24bと、凸部24cと、を備える。
中心軸24aには、係合部24b及び凸部24cが取付けられる部位である。中心軸24aは、第1止水板20の中心に設けられた穴に挿通される。
係合部24bは、図2及び図5に示すように、第1止水板20の面のうち、第1止水板20が引っ張られる側の面に設けられる。係合部24bは、例えば、環状の部材である。係合部24bは、図2及び図5に示すように、中心軸24aの一方の端部に設けられる。綱状部材23は、係合部24bと係合することで、係合部材24に取付けられる。
The engagement member 24 is provided at the center of the first water stop plate 20, as shown in FIG. As shown in FIG. 5, the engaging member 24 includes a central axis 24a, an engaging portion 24b, and a convex portion 24c.
The center shaft 24a is a portion where an engaging portion 24b and a convex portion 24c are attached. The central shaft 24a is inserted into a hole provided at the center of the first water stop plate 20.
As shown in FIGS. 2 and 5, the engaging portion 24b is provided on the surface of the first water stop plate 20 on the side where the first water stop plate 20 is pulled. The engaging portion 24b is, for example, an annular member. The engaging portion 24b is provided at one end of the central shaft 24a, as shown in FIGS. 2 and 5. The rope member 23 is attached to the engagement member 24 by engaging with the engagement portion 24b.

凸部24cは、図2及び図5に示すように、第1止水板20を挟んで、第1止水板20が引っ張られる側とは反対側に設けられる。凸部24cは、図2及び図5に示すように、中心軸24aの他方の端部に設けられる。凸部24cは、第1止水板20を壊す為に設けられる。
凸部24cは、本実施形態において、下記の4例のうちのいずれかを適宜選択して用いられる。
As shown in FIGS. 2 and 5, the convex portion 24c is provided on the opposite side of the first water stop plate 20 from the side on which the first water stop plate 20 is pulled. The convex portion 24c is provided at the other end of the central shaft 24a, as shown in FIGS. 2 and 5. The convex portion 24c is provided to break the first water stop plate 20.
In this embodiment, the convex portion 24c is used by appropriately selecting one of the following four examples.

凸部24cの第1例は、図5に示すように、円筒状の部材の端部に凹凸を設けることで形成される。
凸部24cの第2例は、図6に示すように、円筒状の部材を前記円筒状の軸方向に対して斜めに切断した形状とすることで形成される。
A first example of the convex portion 24c is formed by providing unevenness at the end of a cylindrical member, as shown in FIG.
As shown in FIG. 6, a second example of the convex portion 24c is formed by cutting a cylindrical member obliquely with respect to the axial direction of the cylindrical member.

凸部24cの第3例は、図7に示すように、四角形状の部材が、前記四角形状の辺の1つが中心軸24aに沿うようにして中心軸24aに取り付けられ、前記四角形状の頂点のうち、係合部24bに近い側に位置し、かつ中心軸24aに接している頂点が、係合部24bに近い側に位置し、かつ中心軸24aに接していない頂点よりも、より係合部24bに近い位置にあることで形成される。 In the third example of the convex portion 24c, as shown in FIG. 7, a quadrangular member is attached to the central axis 24a such that one of the sides of the quadrangular shape is along the central axis 24a, and the apex of the quadrangular shape is attached to the central axis 24a. Among these, the vertex located on the side closer to the engaging part 24b and in contact with the central axis 24a is more engaged than the vertex located on the side closer to the engaging part 24b and not in contact with the central axis 24a. It is formed by being located close to the joint portion 24b.

凸部24cの第3例は、図8に示すように、四角形状の部材が、前記四角形状の辺の1つが中心軸24aに沿うようにして中心軸24aに取り付けられ、前記四角形状の頂点のうち、係合部24bに近い側に位置し、かつ中心軸24aに接していない頂点が、係合部24bに近い側に位置し、かつ中心軸24aに接している頂点よりも、より係合部24bに近い位置にあることで形成される。 In the third example of the convex portion 24c, as shown in FIG. 8, a rectangular member is attached to the central axis 24a such that one of the sides of the rectangular shape is along the central axis 24a, and the apex of the rectangular shape is attached to the central axis 24a. Among these, the vertex located on the side closer to the engaging part 24b and not in contact with the central axis 24a is more engaged than the vertex located on the side closer to the engaging part 24b and in contact with the central axis 24a. It is formed by being located close to the joint portion 24b.

凸部24cは、係合部材24が綱状部材23で引っ張られることで、第1止水板20に押し付けられる。このことで、凸部24cは、第1止水板20を突き破るようにして壊す。このため、凸部24cの先端は、表面積が小さいことが好ましい。これにより、第1止水板20に付加される圧力を高くすることが好ましい。 The protrusion 24c is pressed against the first water stop plate 20 when the engagement member 24 is pulled by the rope member 23. As a result, the convex portion 24c breaks through the first water stop plate 20. For this reason, it is preferable that the tip of the convex portion 24c has a small surface area. As a result, it is preferable to increase the pressure applied to the first water stop plate 20.

第1止水板20が壊される所定条件の第2態様として、第1止水板20は、所定圧力で壊れる。所定圧力は、例えば、以下のようにして第1止水板20に付加される。
すなわち、図1に示すように、鋼管杭100が水Wの上に浮かべられた状態から、円筒部10を立てた時に上側になる端部を不図示のクレーン等で吊り上げると、図2に示すように、円筒部10の第1止水板20が設けられた側の端部が水Wの上に沈む。これにより、第1止水板20に対して水圧が付加される。この時の水圧が所定値に達することで、第1止水板20が壊れる。この態様を執る場合、第1止水板20の強度は、第1止水板20に付加される水圧を適宜計算の上設定されることが好ましい。
本実施形態では、上述の所定条件の第1態様又は第2態様によって、第1止水板20を壊す。これにより、円筒部10の内部に水Wを流入させることで、鋼管杭100を水Wの上に立て易くする。
As a second aspect of the predetermined condition under which the first water stop plate 20 is broken, the first water stop plate 20 is broken under a predetermined pressure. The predetermined pressure is applied to the first water stop plate 20, for example, as follows.
That is, as shown in FIG. 1, when the steel pipe pile 100 is floating on water W, the upper end when the cylindrical portion 10 is erected is lifted by a crane (not shown), as shown in FIG. As such, the end of the cylindrical portion 10 on the side where the first water stop plate 20 is provided sinks above the water W. As a result, water pressure is applied to the first water stop plate 20. When the water pressure at this time reaches a predetermined value, the first water stop plate 20 is broken. In this case, the strength of the first water stop plate 20 is preferably set by appropriately calculating the water pressure applied to the first water stop plate 20.
In this embodiment, the first water stop plate 20 is broken according to the first or second aspect of the above-mentioned predetermined conditions. This allows water W to flow into the cylindrical portion 10, thereby making it easier to erect the steel pipe pile 100 on top of the water W.

第2止水板30は、円筒部10の内周面に設けられる。第2止水板30は、円筒部10の長手方向の両端のうち、水底に遠い方の端の側に設けられる。つまり、第2止水板30は、円筒部10を立てた時、上側になる端の側に設けられる。
第2止水板30は、円筒部10の内部に水Wが流れ込むことを防止可能である。これにより、第1止水板20と第2止水板30とによって、円筒部10の内部を密封する。このことで、例えば、鋼管杭100を水Wの上に浮かべることができるようにする。
第2止水板30は、樹脂製である。例えば、第2止水板30には、ゴムや、プラスチックが好適に用いられる。本実施形態において、第2止水板30は、ゴム製である。
The second water stop plate 30 is provided on the inner peripheral surface of the cylindrical portion 10. The second water stop plate 30 is provided on the side of the end farthest from the bottom of the water, of both longitudinal ends of the cylindrical portion 10 . That is, the second water stop plate 30 is provided on the upper end side when the cylindrical portion 10 is erected.
The second waterstop plate 30 can prevent water W from flowing into the cylindrical portion 10 . Thereby, the inside of the cylindrical portion 10 is sealed by the first water stop plate 20 and the second water stop plate 30. This allows the steel pipe pile 100 to float on the water W, for example.
The second water stop plate 30 is made of resin. For example, rubber or plastic is preferably used for the second water stop plate 30. In this embodiment, the second water stop plate 30 is made of rubber.

第2止水板30は、円筒部10に設けられた不図示の第2止水板受けプレートと、第2止水板押さえプレートと、に挟まれることで、円筒部10の内周面に固定される。第2止水板受けプレート及び第2止水板押さえプレートは、それぞれ第1止水板受けプレート21及び第1止水板押さえプレート22に対応する構成である。 The second water stop plate 30 is sandwiched between a second water stop plate receiving plate (not shown) provided on the cylindrical part 10 and a second water stop plate pressing plate, so that the second water stop plate 30 is attached to the inner circumferential surface of the cylindrical part 10. Fixed. The second water stop plate receiving plate and the second water stop plate holding plate have structures corresponding to the first water stop plate receiving plate 21 and the first water stop plate holding plate 22, respectively.

第2止水板30は、所定条件で壊される。つまり、第2止水板30は、所定条件を満たすことで、不可逆的に破断する。このことで、例えば、上述のように第1止水板20を壊して円筒部10の内部に水Wを流入させることで図4に示すように鋼管杭100を水Wの上に立てた後、第2止水板30を壊して円筒部10の内部に残った空気を抜く。このことで、円筒部10の内外の気圧を同じにする。本実施形態において、第2止水板30が壊される所定条件は、以下の2態様を備える。 The second water stop plate 30 is broken under predetermined conditions. That is, the second water stop plate 30 is irreversibly broken when a predetermined condition is satisfied. With this, for example, after the steel pipe pile 100 is erected on the water W as shown in FIG. , the second water stop plate 30 is broken to release the air remaining inside the cylindrical portion 10. This makes the air pressure inside and outside the cylindrical portion 10 the same. In this embodiment, the predetermined conditions under which the second water stop plate 30 is broken include the following two aspects.

第2止水板30が壊される所定条件の第1態様として、第2止水板30は、円筒部10の外部から引っ張られることで壊される。この場合、第2止水板30には、上述した綱状部材23と、係合部材24と、が設けられる。第2止水板30に設けられた綱状部材23は、鋼管杭100が立てられた後、クレーン等によって引っ張られる点で、第1止水板20が壊される所定条件の第1態様と相違する。 As a first aspect of the predetermined condition under which the second water stop plate 30 is broken, the second water stop plate 30 is broken by being pulled from the outside of the cylindrical portion 10 . In this case, the second water stop plate 30 is provided with the above-described rope member 23 and the engagement member 24. The rope member 23 provided on the second water stop plate 30 is different from the first aspect of the predetermined condition in which the first water stop plate 20 is broken in that it is pulled by a crane or the like after the steel pipe pile 100 is erected. do.

第2止水板30が壊される所定条件の第2態様として、第2止水板30は、所定圧力で壊れる。所定圧力は、例えば、以下のようにして第2止水板30に付加される。
すなわち、鋼管杭100が立てられる途中に、第1止水板20が壊され、円筒部10の内部に水Wが流入すると、円筒部10の内部の気圧が上昇する。これにより、第2止水板30に気圧が付加される。この時の気圧が所定値に達することで、第2止水板30が壊れる。この態様を執る場合、第2止水板30の強度は、第2止水板30に付加される気圧を適宜計算の上設定されることが好ましい。
本実施形態では、上述の所定条件の第1態様又は第2態様によって、第2止水板30を壊す。これにより、円筒部10の内外の気圧を同じにして、水底に打設された後の鋼管杭100を安定した状態とする。
As a second aspect of the predetermined condition under which the second water stop plate 30 is broken, the second water stop plate 30 is broken under a predetermined pressure. The predetermined pressure is applied to the second water stop plate 30, for example, as follows.
That is, when the first water stop plate 20 is broken while the steel pipe pile 100 is being erected and water W flows into the cylindrical part 10, the air pressure inside the cylindrical part 10 increases. As a result, air pressure is applied to the second water stop plate 30. When the atmospheric pressure at this time reaches a predetermined value, the second water stop plate 30 is broken. When adopting this aspect, it is preferable that the strength of the second water stop plate 30 is set by appropriately calculating the air pressure applied to the second water stop plate 30.
In this embodiment, the second water stop plate 30 is broken according to the first or second aspect of the above-mentioned predetermined conditions. This makes the air pressure inside and outside the cylindrical part 10 the same, and makes the steel pipe pile 100 stable after being driven to the bottom of the water.

(鋼管杭100の施工方法)
次に、本実施形態に係る鋼管杭100の施工方法について説明する。鋼管杭100の施工方法は、吊り上げ工程と、注水工程と、打設工程と、を備える。なお、この工程は、鋼管杭100の打設場所まで、作業船によって鋼管杭100を運搬した後に行われる。鋼管杭100の運搬は、例えば、鋼管杭100を水Wの上に浮かべた状態で、作業船によって曳航することで行われる。
吊り上げ工程は、水Wの上に横たわる鋼管杭100の一端を吊り上げる工程である。吊り上げ工程は、例えば、不図示の作業船に設けられたクレーン等によって行われる。これにより、鋼管杭100の他端が水Wの中に沈む。
(Construction method of steel pipe pile 100)
Next, a method for constructing the steel pipe pile 100 according to this embodiment will be explained. The method for constructing the steel pipe pile 100 includes a lifting process, a water injection process, and a driving process. Note that this step is performed after the steel pipe pile 100 is transported by a work boat to the location where the steel pipe pile 100 is to be driven. The steel pipe pile 100 is transported, for example, by floating the steel pipe pile 100 on water W and towing it by a work boat.
The lifting process is a process of lifting one end of the steel pipe pile 100 lying on the water W. The lifting process is performed by, for example, a crane installed on a work boat (not shown). As a result, the other end of the steel pipe pile 100 sinks into the water W.

注水工程は、図3に示すように、吊り上げ工程が実施されることで鋼管杭100の他端が水Wに沈んだ状態で、第1止水板20が壊されることで鋼管杭100に水Wを流入させる工程である。上述のように、第1止水板20は、所定条件で壊される。すなわち、例えば、綱状部材23によって第1止水板20を引っ張ることで壊す。あるいは、第1止水板20に付加される水圧が所定値に達することで、第1止水板20が壊れる。これにより、円筒部10の内部に水Wを流入させる。これにより、図4に示すように、鋼管杭100が水Wの上に立てられる。
鋼管杭100が水Wの上に立った後、第2止水板30は、上述の所定条件によって壊される。すなわち、例えば、綱状部材23によって第2止水板30を引っ張ることで壊す。あるいは、第2止水板30に付加される気圧が所定値に達することで、第2止水板30が壊れる。これにより、円筒部10の内外の気圧を同じにする。
In the water injection process, as shown in FIG. 3, the other end of the steel pipe pile 100 is submerged in water W by carrying out the lifting process, and the first water stop plate 20 is broken so that water is poured into the steel pipe pile 100. This is a process of flowing W into the process. As described above, the first water stop plate 20 is broken under predetermined conditions. That is, for example, the first water stop plate 20 is broken by pulling it with the rope member 23. Alternatively, the first water stop plate 20 is broken when the water pressure applied to the first water stop plate 20 reaches a predetermined value. Thereby, water W is caused to flow into the inside of the cylindrical portion 10. Thereby, as shown in FIG. 4, the steel pipe pile 100 is erected on the water W.
After the steel pipe pile 100 stands on the water W, the second water stop plate 30 is broken according to the above-mentioned predetermined conditions. That is, for example, the second water stop plate 30 is broken by pulling it with the rope member 23. Alternatively, the second water stop plate 30 is broken when the air pressure applied to the second water stop plate 30 reaches a predetermined value. This makes the air pressure inside and outside the cylindrical portion 10 the same.

打設工程は、注水工程の後、鋼管杭100を、第1止水板20が壊された状態で、水底に打設する工程である。打設工程は、例えば、不図示の油圧ハンマーによって鋼管杭100を水底に打ち込むことで行われる。油圧ハンマーは、例えば、IQIP社製のS-2000、IQ2、IQ4等が用いられる。
上記各工程により、鋼管杭100は水底に打設される。
The driving process is a process of driving the steel pipe pile 100 into the water bottom with the first water stop plate 20 broken after the water injection process. The driving process is performed, for example, by driving the steel pipe pile 100 into the water bottom using a hydraulic hammer (not shown). As the hydraulic hammer, for example, S-2000, IQ2, IQ4, etc. manufactured by IQIP are used.
Through each of the above steps, the steel pipe pile 100 is driven into the water bottom.

以上説明したように、本実施形態に係る鋼管杭100によれば、鋼管杭100は、円筒部10の内部に水Wが流れ込むことを防止可能な第1止水板20を備える。鋼管杭100を、第1止水板20によって鋼管杭100の内部に水Wが流れ込むことを防止された状態とすることで、鋼管杭100を水Wの上に浮かべることができる。これにより、例えば、鋼管杭100を水Wの上に浮かべた状態のまま作業船等で引っ張ることで、水Wの上で鋼管杭100を運搬する際に必要な力を抑えることができる。 As described above, according to the steel pipe pile 100 according to the present embodiment, the steel pipe pile 100 includes the first water stop plate 20 that can prevent water W from flowing into the cylindrical portion 10. By setting the steel pipe pile 100 in a state where water W is prevented from flowing into the steel pipe pile 100 by the first water stop plate 20, the steel pipe pile 100 can be floated on the water W. Thereby, for example, by pulling the steel pipe pile 100 floating on the water W with a work boat or the like, the force required when transporting the steel pipe pile 100 on the water W can be suppressed.

第1止水板20は、所定条件で壊される。これにより、第1止水板20を壊すことで、円筒部10の内部に水Wを流入させることができる。よって、杭に設けられた流入口を施工中に操作する方法と比較して、作業を容易にすることができる。
例えば、鋼管杭100を施工現場まで運搬した後に、第1止水板20を壊す。このことで、円筒部10の内部に水Wが流入すると、円筒部10の、水Wが流入した側の端部が水Wの中に沈む。これにより、水Wの上において鋼管杭100を立てることができる。したがって、クレーン等を用いて鋼管杭100の端部を吊り上げることで水Wの上に鋼管杭100を立てる場合と比較して、必要な吊り上げ力を小さくすることができる。よって、鋼管杭100の施工に用いるクレーン等に求められる性能を抑えることができる。
The first water stop plate 20 is broken under predetermined conditions. Thereby, by breaking the first water stop plate 20, water W can flow into the inside of the cylindrical portion 10. Therefore, compared to a method in which an inlet provided in a pile is operated during construction, the work can be made easier.
For example, after the steel pipe pile 100 is transported to the construction site, the first water stop plate 20 is broken. As a result, when water W flows into the cylindrical portion 10, the end of the cylindrical portion 10 on the side into which the water W has flowed sinks into the water W. Thereby, the steel pipe pile 100 can be erected on the water W. Therefore, by lifting the end of the steel pipe pile 100 using a crane or the like, the required lifting force can be reduced compared to the case where the steel pipe pile 100 is erected on the water W. Therefore, the performance required of a crane or the like used for constructing the steel pipe pile 100 can be suppressed.

また、第1止水板20は、円筒部10の外部から引っ張られることで壊される。これにより、例えば、鋼管杭100が水Wの上に浮かべられた状態で、第1止水板20に取り付けられたロープを作業船等によって引っ張ることで、第1止水板20を壊すことができる。したがって、鋼管杭100をクレーン等で吊り上げることなく、鋼管杭100のいずれかの端部を水Wの中に沈ませることで、鋼管杭100を立てることができる。 Further, the first waterstop plate 20 is broken by being pulled from the outside of the cylindrical portion 10. Thereby, for example, when the steel pipe pile 100 is floating on water W, the first water stop plate 20 can be broken by pulling the rope attached to the first water stop plate 20 by a work boat or the like. can. Therefore, the steel pipe pile 100 can be erected by sinking either end of the steel pipe pile 100 into water W without lifting the steel pipe pile 100 with a crane or the like.

また、第1止水板20は、所定圧力で壊れる。これにより、例えば、鋼管杭100が水Wの上に浮かべられた状態で、鋼管杭100における第1止水板20が設けられた側と反対側の端部を、クレーン等で持ち上げる。すると、鋼管杭100における第1止水板20が設けられた側の端部が水Wの中に沈む。このことで、第1止水板20に水圧を付加することで、第1止水板20を壊すことができる。したがって、クレーン等によって鋼管杭100を吊り上げることのみによって鋼管杭100を水Wの上に立てる場合と比較して、クレーン等が鋼管杭100を吊り上げる量や、吊り上げに必要な力を小さくすることができる。 Moreover, the first water stop plate 20 breaks under a predetermined pressure. Thereby, for example, with the steel pipe pile 100 floating on the water W, the end of the steel pipe pile 100 on the side opposite to the side where the first water stop plate 20 is provided is lifted up by a crane or the like. Then, the end of the steel pipe pile 100 on the side where the first water stop plate 20 is provided sinks into the water W. With this, by applying water pressure to the first water stop plate 20, the first water stop plate 20 can be broken. Therefore, compared to the case where the steel pipe pile 100 is erected on water W only by lifting the steel pipe pile 100 with a crane or the like, the amount of lifting of the steel pipe pile 100 by the crane or the like and the force required for lifting can be reduced. can.

また、第1止水板20には、綱状部材23が設けられ、第1止水板20は、綱状部材23が引っ張られることで壊される。これにより、円筒部10の外部から、容易に第1止水板20を引っ張ることができる。よって、第1止水板20を容易に壊すことができる。 Further, the first waterstop plate 20 is provided with a rope-like member 23, and the first waterstop plate 20 is broken when the rope-like member 23 is pulled. Thereby, the first water stop plate 20 can be easily pulled from the outside of the cylindrical portion 10. Therefore, the first water stop plate 20 can be easily broken.

また、第1止水板20には、係合部材24が設けられ、綱状部材23は、係合部材24と係合する。これにより、第1止水板20を綱状部材23によってより容易且つ確実に引っ張ることができる。 Further, the first water stop plate 20 is provided with an engaging member 24, and the rope member 23 engages with the engaging member 24. Thereby, the first water stop plate 20 can be pulled more easily and reliably by the rope member 23.

また、凸部24cは、係合部材24が綱状部材23で引っ張られることで、第1止水板20に押し付けられ、第1止水板20を壊す。これにより、更に第1止水板20を容易に壊すことができる。 Furthermore, the protrusion 24c is pressed against the first water stop plate 20 when the engagement member 24 is pulled by the rope member 23, and breaks the first water stop plate 20. Thereby, the first water stop plate 20 can be further easily broken.

また、係合部24bは、第1止水板20の面のうち、第1止水板20が引っ張られる側の面に設けられている。これにより、綱状部材23を係合部24bに係合しやすくすることができる。 Furthermore, the engaging portion 24b is provided on the surface of the first water stop plate 20 on the side where the first water stop plate 20 is pulled. Thereby, the rope member 23 can be easily engaged with the engaging portion 24b.

また、円筒部10の内周面に設けられ、且つ、円筒部10の両端のうち水底に遠い方の端の側に設けられる第2止水板30を更に備える。これにより、第1止水板20と第2止水板30とによって、円筒部10の内部に空気を密封することができる。よって、鋼管杭100を水Wの上に浮かべることができる。第1止水板20は、円筒部10の両端のうち水底に近い方の端の側に設けられる。これにより、第1止水板20を壊すことで、円筒部10の両端のうち水底に近い方の端の側から、円筒部10の内部に水Wを流入させることができる。また、例えば、第1止水板20を円筒部10の端に設けることで、第1止水板20を引っ張りやすくすることができる。 Further, a second water stop plate 30 is provided on the inner circumferential surface of the cylindrical portion 10 and on the side of the end farther from the bottom of the water of both ends of the cylindrical portion 10. Thereby, air can be sealed inside the cylindrical portion 10 by the first water stop plate 20 and the second water stop plate 30. Therefore, the steel pipe pile 100 can be floated on the water W. The first water stop plate 20 is provided on the side of the end closer to the bottom of the water out of both ends of the cylindrical portion 10 . Thereby, by breaking the first water stop plate 20, water W can flow into the inside of the cylindrical portion 10 from the side of the end closer to the bottom of the water out of both ends of the cylindrical portion 10. Further, for example, by providing the first water stop plate 20 at the end of the cylindrical portion 10, the first water stop plate 20 can be easily pulled.

また、第2止水板30は、ゴム製であり、且つ、所定圧力で壊れる。例えば、鋼管杭100を水Wの上に立てる際、まず、第1止水板20を壊すことで、鋼管杭100の第1止水板20が設けられた側の端部を沈ませる。このとき、第2止水板30によって、円筒部10の内部に空気を残すことで、鋼管杭100の見かけの重さを軽くすることができる。よって、クレーン等による鋼管杭100の吊り上げを容易にすることができる。また、鋼管杭100を水Wの上に立てた後に第2止水板30を壊すことで、円筒部10の内部から空気を取り除き、円筒部10の内外の気圧を同じにすることができる。よって、水底に打設された後の鋼管杭100を安定した状態とすることができる。 Further, the second water stop plate 30 is made of rubber and breaks under a predetermined pressure. For example, when the steel pipe pile 100 is erected on water W, first, the first water stop plate 20 is broken to sink the end of the steel pipe pile 100 on the side where the first water stop plate 20 is provided. At this time, by leaving air inside the cylindrical portion 10 using the second water stop plate 30, the apparent weight of the steel pipe pile 100 can be reduced. Therefore, the steel pipe pile 100 can be easily lifted by a crane or the like. Moreover, by breaking the second water stop plate 30 after the steel pipe pile 100 is erected on the water W, air can be removed from the inside of the cylindrical part 10 and the air pressure inside and outside the cylindrical part 10 can be made the same. Therefore, the steel pipe pile 100 can be kept in a stable state after being driven into the water bottom.

また、第2止水板30は、円筒部10の外部から引っ張られることで壊される。これにより、例えば、水Wの上に鋼管杭100を立てた後、第2止水板30を円筒部10の外部から引っ張ることで壊すことができる。これにより、円筒部10の内部から空気を取り除く作業を、鋼管杭100が安定した状態で行うことができる。 Further, the second water stop plate 30 is broken by being pulled from the outside of the cylindrical portion 10. Thereby, for example, after the steel pipe pile 100 is erected on the water W, the second water stop plate 30 can be broken by pulling it from the outside of the cylindrical part 10. Thereby, the work of removing air from the inside of the cylindrical portion 10 can be performed while the steel pipe pile 100 is in a stable state.

また、綱状部材23は、作業船に据え付けられる牽引装置で牽引される。これにより、第1止水板20をより大きな力で引っ張ることを容易に行うことができる。 Further, the rope member 23 is towed by a towing device installed on the work boat. Thereby, it is possible to easily pull the first water stop plate 20 with a larger force.

また、第1止水板20は、円筒部10に設けられた第1止水板押さえプレート22と、円筒部10に設けられた第1止水板受けプレート21と、に挟まれる。これにより、第1止水板20を円筒部10の内周面に確実に固定することができる。したがって、第1止水板20をより強く引っ張ることができる。よって、より第1止水板20を壊しやすくすることができる。 Further, the first water stop plate 20 is sandwiched between a first water stop plate holding plate 22 provided on the cylindrical portion 10 and a first water stop plate receiving plate 21 provided on the cylindrical portion 10 . Thereby, the first water stop plate 20 can be reliably fixed to the inner circumferential surface of the cylindrical portion 10. Therefore, the first water stop plate 20 can be pulled more strongly. Therefore, the first water stop plate 20 can be made easier to break.

また、第1止水板押さえプレート22は、環状であり、第1止水板押さえプレート22の内径は、円筒部10の両端のうち水底に近い方の端に向かうにつれ、大きくなる。よって、円筒部10の第1止水板20が設けられた側の端部から水Wが流入した時、第1止水板押さえプレート22が水流の抵抗となることを抑えることができる。また、例えば、鋼管杭100を水底に打設する時、第1止水板押さえプレート22が抵抗となることを抑えることもできる。 Further, the first water stop plate holding plate 22 has an annular shape, and the inner diameter of the first water stop holding plate 22 increases toward the end closer to the bottom of the water of both ends of the cylindrical portion 10. Therefore, when water W flows in from the end of the cylindrical portion 10 on the side where the first water stop plate 20 is provided, it is possible to prevent the first water stop plate holding plate 22 from acting as resistance to the water flow. Further, for example, when driving the steel pipe pile 100 into the water bottom, it is possible to prevent the first water stop plate holding plate 22 from acting as resistance.

また、第1止水板20は、ゴム製である。これにより、第1止水板20を壊しやすくすることができる。 Moreover, the first water stop plate 20 is made of rubber. Thereby, the first water stop plate 20 can be easily broken.

また、吊り上げ工程と、注水工程と、を備える。吊り上げ工程によって鋼管杭100の他端を水Wに沈ませることで、鋼管杭100の見かけの重さを軽くすることができる。注水工程によって鋼管杭100に水Wを流入させることで、水Wの上に鋼管杭100を立てやすくすることができる。よって、鋼管杭100を立てる際に必要な鋼管杭100の吊り上げ量を少なくすることができる。これにより、鋼管杭100を打設する作業をより容易にすることができる。 It also includes a lifting process and a water injection process. By sinking the other end of the steel pipe pile 100 into water W during the lifting process, the apparent weight of the steel pipe pile 100 can be reduced. By causing water W to flow into the steel pipe pile 100 through the water injection process, the steel pipe pile 100 can be easily erected on top of the water W. Therefore, the amount of lifting of the steel pipe pile 100 required to erect the steel pipe pile 100 can be reduced. Thereby, the work of driving the steel pipe pile 100 can be made easier.

(第2実施形態)
次に、本発明に係る第2実施形態の第2鋼管杭200を、図9、図10、図11を参照して説明する。
なお、この第2実施形態においては、第1実施形態における構成要素と同一の部分については同一の符号を付し、その説明を省略し、異なる点についてのみ説明する。
(Second embodiment)
Next, a second steel pipe pile 200 according to a second embodiment of the present invention will be described with reference to FIGS. 9, 10, and 11.
In addition, in this 2nd embodiment, the same code|symbol is attached|subjected to the same component as the component in 1st Embodiment, the description is abbreviate|omitted, and only a different point will be described.

第2鋼管杭200は、図9に示すように、上述の鋼管杭100が備える各構成に加えて、第3止水板40を更に備える点で、鋼管杭100と異なる。
第3止水板40は、円筒部10の内周面に設けられる。第3止水板40は、第1止水板20と第2止水板30との間に設けられる。
第3止水板40は、樹脂製である。例えば、第3止水板40には、ゴムや、プラスチックが好適に用いられる。本実施形態において、第3止水板40は、ゴム製である。
As shown in FIG. 9, the second steel pipe pile 200 differs from the steel pipe pile 100 in that it further includes a third water stop plate 40 in addition to the components of the steel pipe pile 100 described above.
The third water stop plate 40 is provided on the inner circumferential surface of the cylindrical portion 10. The third water stop plate 40 is provided between the first water stop plate 20 and the second water stop plate 30.
The third water stop plate 40 is made of resin. For example, rubber or plastic is preferably used for the third water stop plate 40. In this embodiment, the third water stop plate 40 is made of rubber.

第3止水板40は、円筒部10に設けられた不図示の第3止水板受けプレートと、第3止水板押さえプレートと、に挟まれることで、円筒部10の内周面に固定される。第3止水板受けプレート及び第3止水板押さえプレートは、それぞれ上述の第1止水板受けプレート21及び第1止水板押さえプレート22に対応する構成である。なお、第3止水板受けプレートは、円筒部10を立てた時、第3止水板40の上側になる側に設けられることが好ましい。第3止水板押さえプレートは、円筒部10を立てた時、第3止水板40の下側になる側に設けられることが好ましい。 The third water stop plate 40 is sandwiched between a third water stop plate receiving plate (not shown) provided on the cylindrical part 10 and a third water stop plate pressing plate, so that the third water stop plate 40 is attached to the inner peripheral surface of the cylindrical part 10. Fixed. The third waterstop receiving plate and the third waterstop holding plate have structures corresponding to the above-described first waterstop receiving plate 21 and first waterstop holding plate 22, respectively. In addition, it is preferable that the third water stop plate receiving plate is provided on the side that becomes the upper side of the third water stop plate 40 when the cylindrical portion 10 is erected. It is preferable that the third water stop plate holding plate is provided on the lower side of the third water stop plate 40 when the cylindrical portion 10 is erected.

第3止水板40は、所定条件で壊される。つまり、第3止水板40は、所定条件を満たすことで、不可逆的に破断する。このことで、例えば、第1止水板20と第2止水板30のみが円筒部10に設けられた場合と比較して、円筒部10の内部に水Wを流入させる作業を段階的に行うことができるようにする。本実施形態において、第3止水板40が壊される所定条件は、以下の2態様を備える。 The third water stop plate 40 is broken under predetermined conditions. That is, the third water stop plate 40 is irreversibly broken when a predetermined condition is satisfied. With this, for example, compared to the case where only the first water stop plate 20 and the second water stop plate 30 are provided in the cylindrical part 10, the work of flowing water W into the inside of the cylindrical part 10 can be performed in stages. be able to do so. In this embodiment, the predetermined conditions under which the third water stop plate 40 is broken include the following two aspects.

第3止水板40が壊される所定条件の第1態様として、第3止水板40は、円筒部10の外部から引っ張られることで壊される。この場合、第3止水板40には、上述した綱状部材23と、係合部材24と、が設けられる。第3止水板40に設けられた綱状部材23は、作業船又は作業船に設けられた牽引装置によって、鋼管杭100が立てられる途中の段階において引っ張られる点で、第1止水板20が壊される所定条件の第1態様と相違する。 As a first aspect of the predetermined condition under which the third water stop plate 40 is broken, the third water stop plate 40 is broken by being pulled from the outside of the cylindrical portion 10 . In this case, the third water stop plate 40 is provided with the above-described rope member 23 and the engagement member 24. The rope member 23 provided on the third water stop plate 40 is pulled by a work boat or a traction device provided on the work boat during the stage when the steel pipe pile 100 is being erected. This is different from the first aspect of the predetermined condition in which the condition is broken.

第3止水板40が壊される所定条件の第2態様として、第3止水板40は、所定圧力で壊れる。所定圧力は、例えば、以下のようにして第3止水板40に付加される。
すなわち、鋼管杭100が立てられる途中に、第1止水板20が壊され、円筒部10の内部に水Wが流入すると、円筒部10の内部の気圧が上昇する。これにより、第3止水板40に気圧が付加される。この時の気圧が所定値に達することで、第3止水板40が壊れる。この態様を執る場合、第3止水板40の強度は、第3止水板40に付加される気圧を適宜計算の上設定されることが好ましい。
As a second aspect of the predetermined condition under which the third water stop plate 40 is broken, the third water stop plate 40 is broken under a predetermined pressure. The predetermined pressure is applied to the third water stop plate 40, for example, as follows.
That is, when the first water stop plate 20 is broken while the steel pipe pile 100 is being erected and water W flows into the cylindrical part 10, the air pressure inside the cylindrical part 10 increases. As a result, air pressure is applied to the third water stop plate 40. When the atmospheric pressure at this time reaches a predetermined value, the third water stop plate 40 is broken. When this aspect is adopted, it is preferable that the strength of the third water stop plate 40 is set after appropriately calculating the air pressure applied to the third water stop plate 40.

なお、本実施形態において、第2止水板30は、第3止水板40より低い圧力で壊れる。つまり、第3止水板40の強度は、第2止水板30よりも高い。
本実施形態では、上述の所定条件の第1態様又は第2態様によって、第3止水板40を壊す。これにより、円筒部10の内部への水Wの流入を段階的に行うようにして、鋼管杭100を水Wの上に立てる作業をより安定して行えるようにする。
In addition, in this embodiment, the second water stop plate 30 breaks at a lower pressure than the third water stop plate 40. That is, the strength of the third water stop plate 40 is higher than that of the second water stop plate 30.
In this embodiment, the third water stop plate 40 is broken according to the first or second aspect of the above-mentioned predetermined conditions. Thereby, the water W flows into the inside of the cylindrical part 10 in stages, so that the work of erecting the steel pipe pile 100 on the water W can be performed more stably.

(第2鋼管杭200の施工方法)
次に、本実施形態に係る第2鋼管杭200の施工方法について説明する。第2鋼管杭200の施工方法は、鋼管杭100の施工方法における注水工程において、第3止水板40を壊す工程を更に含む点で、鋼管杭100の施工方法と相違する。
上述のように、第3止水板40は、所定条件で壊される。すなわち、例えば、図10に示すように、第1止水板20が壊れて、円筒部10の内部に水Wが流入した後、綱状部材23によって第3止水板40を引っ張ることで壊す。あるいは、円筒部10の内部に水Wが流入することで第3止水板40に付加される空気圧が所定値に達することで、第3止水板40が壊れる。これにより、図10及び図11に示すように、円筒部10の内部に段階的に水Wを流入させる。
(Construction method of second steel pipe pile 200)
Next, a method for constructing the second steel pipe pile 200 according to the present embodiment will be described. The construction method for the second steel pipe pile 200 differs from the construction method for the steel pipe pile 100 in that the construction method for the steel pipe pile 100 further includes a step of breaking the third water stop plate 40 in the water injection step in the construction method for the steel pipe pile 100.
As described above, the third water stop plate 40 is broken under predetermined conditions. That is, for example, as shown in FIG. 10, after the first water stop plate 20 is broken and water W flows into the cylindrical part 10, the third water stop plate 40 is pulled by the rope member 23 and broken. . Alternatively, the third water stop plate 40 is broken when the air pressure applied to the third water stop plate 40 reaches a predetermined value due to water W flowing into the inside of the cylindrical portion 10 . Thereby, as shown in FIGS. 10 and 11, water W is caused to flow into the interior of the cylindrical portion 10 in stages.

第2止水板30は、第3止水板40が壊れた後に、所定条件で壊される。つまり、第3止水板40を備える第2鋼管杭200を立てる際は、注水工程において、第1止水板20、第3止水板40、第2止水板30の順番に壊される。
その後、上述の打設工程によって、第2鋼管杭200を水底に打設する。
上記各工程により、第2鋼管杭200は水底に打設される。
The second water stop plate 30 is broken under predetermined conditions after the third water stop plate 40 is broken. That is, when erecting the second steel pipe pile 200 provided with the third water stop plate 40, the first water stop plate 20, the third water stop plate 40, and the second water stop plate 30 are broken in this order in the water injection process.
Thereafter, the second steel pipe pile 200 is driven into the water bottom by the above-described driving process.
Through each of the above steps, the second steel pipe pile 200 is driven into the water bottom.

以上説明したように、本実施形態に係る第2鋼管杭200によれば、円筒部10の内周面に設けられ、且つ、第1止水板20と第2止水板30との間に設けられる第3止水板40を更に備え、第3止水板40は、ゴム製であり、且つ、円筒部10の外部から引っ張られることで壊される。これにより、円筒部10の内部に水Wを流入させる作業を段階的に行うことができる。よって、鋼管杭100の、第1止水板20が設けられた側の端部が水Wの中に沈む速度を遅くすることができる。よって、鋼管杭100を水Wの上に立てる作業をより安定して行うことができる。また、第3止水板40が壊れる前の状態において、第3止水板40と第2止水板30との間に空気を残すことができる。したがって、第3止水板40が壊れた後も、円筒部10の内部に空気を確実に残すことができる。よって、鋼管杭100を立てる際に、空気による浮力を利用しやすくすることができる。よって、より鋼管杭100の見かけの重さを軽くすることができる。 As explained above, according to the second steel pipe pile 200 according to the present embodiment, the pile is provided on the inner peripheral surface of the cylindrical portion 10 and between the first water stop plate 20 and the second water stop plate 30. The third water stop plate 40 is further provided, and the third water stop plate 40 is made of rubber and is broken by being pulled from the outside of the cylindrical portion 10 . Thereby, the work of causing water W to flow into the inside of the cylindrical portion 10 can be performed in stages. Therefore, the speed at which the end of the steel pipe pile 100 on the side where the first water stop plate 20 is provided sinks into the water W can be reduced. Therefore, the work of erecting the steel pipe pile 100 on the water W can be performed more stably. Moreover, air can remain between the third water stop plate 40 and the second water stop plate 30 in a state before the third water stop plate 40 is broken. Therefore, even after the third water stop plate 40 is broken, air can be reliably left inside the cylindrical portion 10. Therefore, when erecting the steel pipe pile 100, it is possible to easily utilize the buoyancy of the air. Therefore, the apparent weight of the steel pipe pile 100 can be further reduced.

また、第2止水板30は、第3止水板40より低い圧力で壊れる。つまり、第3止水板40の強度は、第2止水板30の強度よりも高い。これにより、第3止水板40を、鋼管杭100の第1止水板20が設けられた側の端部が水Wの中に沈む際に、円筒部10の内部に流入した水Wや、円筒部10の内部に流入した水Wによって圧縮された空気によって付加される圧力に対して、十分な強度とすることができる。 Further, the second water stop plate 30 breaks at a lower pressure than the third water stop plate 40. That is, the strength of the third water stop plate 40 is higher than the strength of the second water stop plate 30. Thereby, when the end of the steel pipe pile 100 on the side where the first water stop plate 20 is provided sinks into the water W, the third water stop plate 40 is connected to the water W that has flowed into the inside of the cylindrical part 10. It is possible to provide sufficient strength against the pressure applied by the air compressed by the water W flowing into the cylindrical portion 10.

なお、本発明の技術的範囲は前記実施形態に限定されるものではなく、本発明の趣旨を逸脱しない範囲において種々の変更を加えることが可能である。
例えば、第1止水板20と作業船とをロープで繋いだ状態で、鋼管杭100におけるロープが繋がれていない側の端部をクレーン等で持ち上げることで、鋼管杭100におけるロープが繋がれた第1止水板20の設けられた側の端部を沈ませる。このことで、ロープに張力を発生させることで、第1止水板20を壊してもよい。
Note that the technical scope of the present invention is not limited to the embodiments described above, and various changes can be made without departing from the spirit of the present invention.
For example, with the first water stop plate 20 and the work boat connected with a rope, the end of the steel pipe pile 100 on the side to which the rope is not connected is lifted with a crane or the like, so that the rope on the steel pipe pile 100 is connected. The end on the side where the first water stop plate 20 is provided is sunk. This may cause the first water stop plate 20 to break by generating tension in the rope.

また、第3止水板40は、第2止水板30より低い圧力で壊れてもよい。これにより、鋼管杭100の第1止水板20が設けられた側の端部が水Wの中に沈む際に、円筒部10の内部に流入した水Wや、円筒部10の内部に流入した水Wによって圧縮された空気によって第3止水板40に付加される圧力によって、第3止水板40を壊しやすくしてもよい。 Further, the third water stop plate 40 may be broken at a pressure lower than that of the second water stop plate 30. As a result, when the end of the steel pipe pile 100 on the side where the first water stop plate 20 is provided sinks into the water W, the water W that has flowed into the inside of the cylindrical portion 10 and the water that has flowed into the inside of the cylindrical portion 10 can be The third water stop plate 40 may be easily broken by the pressure applied to the third water stop plate 40 by the air compressed by the water W.

その他、本発明の趣旨に逸脱しない範囲で、前記実施形態における構成要素を周知の構成要素に置き換えることは適宜可能であり、また、前記した変形例を適宜組み合わせてもよい。 In addition, without departing from the spirit of the present invention, the components in the embodiments described above may be replaced with well-known components as appropriate, and the modifications described above may be combined as appropriate.

10 円筒部
20 第1止水板
21 第1止水板受けプレート
22 第1止水板押さえプレート
23 綱状部材
24 係合部材
24a 中心軸
24b 係合部
24c 凸部
30 第2止水板
40 第3止水板
100 鋼管杭
200 第2鋼管杭
B ボルト
N ナット
10 Cylindrical portion 20 First water stop plate 21 First water stop plate receiving plate 22 First water stop plate holding plate 23 Rope-like member 24 Engagement member 24a Central shaft 24b Engagement portion 24c Convex portion 30 Second water stop plate 40 Third water stop plate 100 Steel pipe pile 200 Second steel pipe pile B Bolt N Nut

Claims (12)

鋼製の円筒部と、
前記円筒部の内部に水が流れ込むことを防止可能な第1止水板であって、前記円筒部の両端部のうち一方の端部における内周面に設けられる第1止水板と、
前記円筒部の内部に水が流れ込むことを防止可能な第2止水板であって、前記円筒部の両端部のうち他方の端部における内周面に設けられる第2止水板と、
を備え、水底に打設される鋼管杭であって、
前記第1止水板には、綱状部材と、係合部材と、が設けられ、
前記係合部材は、係合部を備え、
前記綱状部材は、前記係合部と係合し、
前記係合部は、前記第1止水板の面のうち、前記第1止水板が引っ張られる側の面に設けられ、
前記第1止水板は、前記円筒部の外部から前記綱状部材が引っ張られることで破壊可能である、
ことを特徴とする鋼管杭。
A steel cylindrical part,
a first water stop plate capable of preventing water from flowing into the cylindrical part, the first water stop plate being provided on an inner circumferential surface of one of both ends of the cylindrical part;
a second water stop plate capable of preventing water from flowing into the cylindrical portion, the second water stop plate being provided on an inner circumferential surface of the other of both ends of the cylindrical portion;
A steel pipe pile driven into the bottom of the water,
The first water stop plate is provided with a rope-like member and an engagement member,
The engagement member includes an engagement portion,
The rope member engages with the engagement portion,
The engaging portion is provided on a side of the first water stop plate on which the first water stop plate is pulled,
The first water stop plate can be destroyed by pulling the rope member from outside the cylindrical part.
A steel pipe pile characterized by:
鋼製の円筒部と、
前記円筒部の内部に水が流れ込むことを防止可能な第1止水板であって、前記円筒部の両端部のうち一方の端部における内周面に設けられる第1止水板と、
前記円筒部の内部に水が流れ込むことを防止可能な第2止水板であって、前記円筒部の両端部のうち他方の端部における内周面に設けられる第2止水板と、
を備え、水底に打設される鋼管杭であって、
前記第1止水板には、綱状部材と、係合部材と、が設けられ、
前記係合部材は、係合部と、凸部と、を備え、
前記凸部は、前記第1止水板を挟んで、前記第1止水板が引っ張られる側とは反対側に設けられ、
前記綱状部材は、前記係合部と係合し、
前記凸部は、前記円筒部の外部から前記係合部材が前記綱状部材で引っ張られることで、前記第1止水板に押し付けられ、前記第1止水板を破壊可能である、
ことを特徴とする鋼管杭。
A steel cylindrical part,
a first water stop plate capable of preventing water from flowing into the cylindrical part, the first water stop plate being provided on an inner circumferential surface of one of both ends of the cylindrical part;
a second water stop plate capable of preventing water from flowing into the cylindrical portion, the second water stop plate being provided on an inner circumferential surface of the other of both ends of the cylindrical portion;
A steel pipe pile driven into the bottom of the water,
The first water stop plate is provided with a rope-like member and an engagement member,
The engagement member includes an engagement portion and a convex portion,
The convex portion is provided on the opposite side of the first water stop plate from the side on which the first water stop plate is pulled,
The rope member engages with the engagement portion,
The convex portion is pressed against the first water stop plate when the engagement member is pulled by the rope member from the outside of the cylindrical part, and the first water stop plate can be destroyed.
A steel pipe pile characterized by:
前記第1止水板は、前記円筒部の両端のうち前記水底に近い方の端の側に設けられる、
ことを特徴とする請求項2に記載の鋼管杭。
The first water stop plate is provided on the side of the end closer to the bottom of the water out of both ends of the cylindrical part .
The steel pipe pile according to claim 2, characterized in that:
前記第2止水板は、ゴム製であり、且つ、所定圧力で壊れる、
ことを特徴とする請求項3に記載の鋼管杭。
The second water stop plate is made of rubber and breaks at a predetermined pressure.
The steel pipe pile according to claim 3, characterized in that:
前記第2止水板は、前記円筒部の外部から引っ張られることで破壊可能である、
ことを特徴とする請求項4に記載の鋼管杭。
The second water stop plate can be destroyed by being pulled from the outside of the cylindrical part.
The steel pipe pile according to claim 4, characterized in that:
前記円筒部の内周面に設けられ、且つ、前記第1止水板と前記第2止水板との間に設けられる第3止水板、
を更に備え、
前記第3止水板は、ゴム製であり、且つ、前記円筒部の外部から引っ張られることで破壊可能である、
ことを特徴とする請求項5に記載の鋼管杭。
a third water stop plate provided on the inner circumferential surface of the cylindrical portion and provided between the first water stop plate and the second water stop plate;
further comprising;
The third water stop plate is made of rubber and can be destroyed by being pulled from the outside of the cylindrical part.
The steel pipe pile according to claim 5, characterized in that:
前記第2止水板は、前記第3止水板より低い圧力で壊れる、
ことを特徴とする請求項6に記載の鋼管杭。
the second water stop plate breaks at a lower pressure than the third water stop plate;
The steel pipe pile according to claim 6, characterized in that:
鋼製の円筒部と、
前記円筒部の内部に水が流れ込むことを防止可能な第1止水板であって、前記円筒部の両端部のうち一方の端部における内周面に設けられる第1止水板と、
前記円筒部の内部に水が流れ込むことを防止可能な第2止水板であって、前記円筒部の両端部のうち他方の端部における内周面に設けられる第2止水板と、
を備え、水底に打設される鋼管杭であって、
前記第1止水板は、前記円筒部に設けられた第1止水板押さえプレートと、前記円筒部に設けられた第1止水板受けプレートと、に挟まれ、
前記第1止水板は、破壊可能である、
ことを特徴とする鋼管杭。
A steel cylindrical part,
a first water stop plate capable of preventing water from flowing into the cylindrical portion, the first water stop plate being provided on an inner circumferential surface of one of both ends of the cylindrical portion;
a second water stop plate capable of preventing water from flowing into the cylindrical portion, the second water stop plate provided on an inner circumferential surface of the other end of the cylindrical portion;
A steel pipe pile driven into the bottom of the water,
The first water stop plate is sandwiched between a first water stop plate holding plate provided on the cylindrical portion and a first water stop plate receiving plate provided on the cylindrical portion,
the first water stop plate is destructible;
A steel pipe pile characterized by:
前記第1止水板押さえプレートは、環状であり、
前記第1止水板押さえプレートの内径は、前記円筒部の両端のうち水底に近い方の端に向かうにつれ、大きくなる、
ことを特徴とする請求項8に記載の鋼管杭。
The first water stop plate has an annular shape,
The inner diameter of the first waterstop plate becomes larger toward the end closer to the bottom of the water of both ends of the cylindrical portion.
The steel pipe pile according to claim 8, characterized in that:
前記綱状部材は、作業船に据え付けられる牽引装置で牽引される、
ことを特徴とする請求項1乃至7のいずれか1項に記載の鋼管杭。
The rope member is towed by a towing device installed on a work boat.
The steel pipe pile according to any one of claims 1 to 7, characterized in that:
前記第1止水板は、ゴム製である、
ことを特徴とする請求項1乃至9のいずれか1項に記載の鋼管杭。
The first water stop plate is made of rubber.
The steel pipe pile according to any one of claims 1 to 9, characterized in that:
鋼製の円筒部と、
前記円筒部の内部に水が流れ込むことを防止可能な第1止水板であって、前記円筒部の内周面に設けられる第1止水板と、
凸部と、係合部と、を備え、前記第1止水板に設けられる係合部材と、
前記係合部と係合する綱状部材と、
を備え、水底に打設される鋼管杭の施工方法であって、
前記第1止水板は、ゴム製であり、且つ、前記係合部材が前記綱状部材で引っ張られることで、前記係合部材が備える前記凸部が、前記第1止水板に押し付けられることで破壊可能であり、
水上に横たわる前記鋼管杭の一端を吊り上げる吊り上げ工程と、
前記吊り上げ工程が実施されることで前記鋼管杭の他端が水に沈んだ状態で、前記綱状部材で前記係合部材を引っ張ることで前記第1止水板を破壊して前記鋼管杭に水を流入させる注水工程と、
前記注水工程の後、前記鋼管杭を、前記第1止水板が壊された状態で、前記水底に打設する打設工程と、
を備えることを特徴とする鋼管杭の施工方法。
A steel cylindrical part,
a first water stop plate capable of preventing water from flowing into the cylindrical part, the first water stop plate provided on the inner circumferential surface of the cylindrical part;
an engaging member provided on the first water stop plate, including a convex portion and an engaging portion;
a rope-like member that engages with the engaging portion;
A construction method for steel pipe piles driven into the water bottom, comprising:
The first water stop plate is made of rubber, and when the engagement member is pulled by the rope-like member, the protrusion of the engagement member is pressed against the first water stop plate. can be destroyed by
a lifting step of lifting one end of the steel pipe pile lying on water;
When the other end of the steel pipe pile is submerged in water by carrying out the lifting step, the first water stop plate is destroyed by pulling the engagement member with the rope member, and the steel pipe pile is attached to the steel pipe pile. A water injection process for introducing water;
After the water injection step, a driving step of driving the steel pipe pile into the water bottom with the first water stop plate broken;
A method of constructing a steel pipe pile, characterized by comprising:
JP2023033828A 2023-03-06 2023-03-06 Construction method of steel pipe piles and steel pipe piles Active JP7447328B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2023033828A JP7447328B1 (en) 2023-03-06 2023-03-06 Construction method of steel pipe piles and steel pipe piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2023033828A JP7447328B1 (en) 2023-03-06 2023-03-06 Construction method of steel pipe piles and steel pipe piles

Publications (1)

Publication Number Publication Date
JP7447328B1 true JP7447328B1 (en) 2024-03-11

Family

ID=90183490

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2023033828A Active JP7447328B1 (en) 2023-03-06 2023-03-06 Construction method of steel pipe piles and steel pipe piles

Country Status (1)

Country Link
JP (1) JP7447328B1 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6914411B1 (en) 2020-11-10 2021-08-04 日鉄エンジニアリング株式会社 Pile construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6914411B1 (en) 2020-11-10 2021-08-04 日鉄エンジニアリング株式会社 Pile construction method

Similar Documents

Publication Publication Date Title
CN102482860B (en) Offshore support structure and associated method of installing
JP6619204B2 (en) Deadline method and water barrier structure
US9428876B2 (en) Multi-suction-pile anchor and flat plate anchor having suction piles
EP2354536A1 (en) Support structure for supporting an offshore wind turbine
CN103362113B (en) Offshore wind farm, bridge and marine works local buoyancy ocean platform and construction method
WO2019218640A1 (en) Deep-water anchoring body and construction process therefor
CN109736343B (en) Offshore wind power foundation, installation method thereof and wind generating set
EP3924159A2 (en) Suction anchors and their methods of manufacture
CN110397069A (en) A kind of more cabin combination foundation structures of the monotubular with support construction and its construction method
KR20110002998A (en) Pier basis caisson structure using a pulling oil jack system
CN111412113A (en) Offshore wind power suction pile foundation
JPS6149029A (en) Underwater foundation fixer
CN101876174A (en) Foundation structure of marine wind electric field fan
JP7447328B1 (en) Construction method of steel pipe piles and steel pipe piles
CN103119222A (en) Surface-breaking re-usable submergeable template for installing one or more submerged columns/piles
CN116927236A (en) Integrated sleeve cage structure of single pile foundation of fan
CN111197319A (en) Multidirectional prestress prefabricated assembled beam slab foundation of wind power generation tower
CN105401564A (en) Construction method for fixing tidal current energy power generation device to water bottom and tidal current energy power generation device
JP3135208U (en) Towing self-sinking anchor block
CN113431081A (en) Integral ship-leaning anti-collision structure of offshore wind power multi-pile foundation and construction method
JP5820861B2 (en) Construction method of offshore building
CN114162273A (en) Independent type marine towing and installation dual-purpose buoyancy adjustable buoy and construction method
CN111962543A (en) Rapid connection and separation process of pile stabilizing platform and mother ship
CN220013757U (en) Anchor chain type offshore wind power foundation and construction facility thereof
JP3790451B2 (en) Underwater foundation and installation method of underwater foundation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230320

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20230320

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230509

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20230628

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230906

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231024

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231115

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240130

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240228

R150 Certificate of patent or registration of utility model

Ref document number: 7447328

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150