JP7375501B2 - Construction method of large cross-section tunnel structure - Google Patents

Construction method of large cross-section tunnel structure Download PDF

Info

Publication number
JP7375501B2
JP7375501B2 JP2019215252A JP2019215252A JP7375501B2 JP 7375501 B2 JP7375501 B2 JP 7375501B2 JP 2019215252 A JP2019215252 A JP 2019215252A JP 2019215252 A JP2019215252 A JP 2019215252A JP 7375501 B2 JP7375501 B2 JP 7375501B2
Authority
JP
Japan
Prior art keywords
tunnel
frame
section
cargo handling
large cross
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019215252A
Other languages
Japanese (ja)
Other versions
JP2021085237A (en
Inventor
克洋 宮元
邦靖 足立
吾郎 磐田
勉 屋代
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2019215252A priority Critical patent/JP7375501B2/en
Publication of JP2021085237A publication Critical patent/JP2021085237A/en
Priority to JP2023137242A priority patent/JP2023156523A/en
Application granted granted Critical
Publication of JP7375501B2 publication Critical patent/JP7375501B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

本発明は、資材を荷役搬送する荷役搬送装置を用いた大断面トンネル躯体の構築方法に関する。 The present invention relates to a method for constructing a large cross-section tunnel frame using a material handling and transporting device for handling and transporting materials.

従来より、大深度地下に設けられた既設トンネルの一部分に大断面トンネルを構築する方法として、様々な方法が検討されている。 Conventionally, various methods have been studied as a method for constructing a large cross-section tunnel in a portion of an existing tunnel located deep underground.

例えば、特許文献1では、本線シールドトンネルと支線シールドトンネルの分岐合流部となる部分を大断面トンネルの構築予定領域とし、これを囲繞するようにして小断面の外殻トンネルを並列に複数構築する。次に、これら複数の外殻トンネルに跨るトンネル躯体を構築する。こうして、トンネル躯体が構築されたのち、トンネル躯体の内側を掘削して大断面トンネルを構築する。 For example, in Patent Document 1, a portion where a main line shield tunnel and a branch line shield tunnel branch and merge is set as an area where a large cross-section tunnel is planned to be constructed, and a plurality of small cross-section shell tunnels are constructed in parallel to surround this area. . Next, a tunnel frame is constructed that spans these plurality of outer shell tunnels. After the tunnel body is constructed in this manner, the inside of the tunnel body is excavated to construct a large-section tunnel.

ここで、トンネル躯体は、複数の躯体分割体を、周方向及びトンネル軸線方向に接続することにより構築され、躯体分割体は、トンネル躯体の内周面を形成する内側鋼殻板と、外周面を形成する外側鋼殻板と、せん断補強筋とを備える鋼殻分割体に、コンクリートを打設することにより構築される。 Here, the tunnel body is constructed by connecting a plurality of body division bodies in the circumferential direction and the tunnel axis direction, and the body body division body includes an inner steel shell plate forming the inner peripheral surface of the tunnel skeleton, and an outer peripheral surface of the tunnel body. It is constructed by pouring concrete into a steel shell split body comprising an outer steel shell plate and shear reinforcing bars.

特開2018-109329号公報Japanese Patent Application Publication No. 2018-109329

特許文献1において、躯体分割体を構成する鋼殻分割体は重量物であるから、小断面の外殻トンネル内での荷役搬送は煩雑となる。このため、外殻トンネル内に内側鋼殻板と外側鋼殻板とを別途搬送し、外殻トンネル内の所定位置で各々の位置決めを行い、鋼殻分割体に組み立てる。しかし、このような作業は煩雑であるとともに、位置ズレが生じやすく、位置ズレが生じたままトンネル躯体まで構築すると、トンネル躯体の内部空間に構築される大断面トンネルの出来形に影響を及ぼしかねない。 In Patent Document 1, since the steel shell segments constituting the frame segment are heavy objects, cargo handling and transportation within the outer shell tunnel having a small cross section becomes complicated. For this purpose, the inner steel shell plate and the outer steel shell plate are separately transported into the outer shell tunnel, each is positioned at a predetermined position within the outer shell tunnel, and assembled into a steel shell divided body. However, such work is complicated and tends to cause misalignment, and if the tunnel frame is built with misalignment, it may affect the final shape of the large-section tunnel that will be constructed in the internal space of the tunnel frame. do not have.

本発明は、かかる課題に鑑みなされたものであって、その主な目的は、トンネル躯体を構築する際に必要な資材の荷役搬送作業を容易なものとし、作業効率を向上することの可能な、大断面トンネル躯体の構築方法を提供することである。 The present invention has been made in view of such problems, and its main purpose is to facilitate the cargo handling and transportation work of materials necessary when constructing a tunnel frame, and to improve work efficiency. , it is an object of the present invention to provide a method for constructing a large cross-section tunnel frame .

かかる目的を達成するため本発明の大断面トンネル躯体の構築方法で用いる荷役搬送装置は、トンネル躯体内をトンネル軸線方向に移動可能な走行体と、該走行体からトンネル軸線に直交する方向に相反して張出し、前記走行体を前記トンネル躯体に固定する一対のアウトリガーと、前記走行体に設置され、該走行体の進行方向前方もしくは後方で資材の荷役作業を行う荷役装置本体と、を備え、前記走行体は、前記トンネル軸線方向からみた断面が矩形状のフレームと、該フレームの前記トンネル軸線方向に延在する外隅各々の近傍に設けられ、前記トンネル躯体に当接する車輪と、を備える。 In order to achieve such an object, the cargo handling and conveying device used in the method of constructing a large cross-section tunnel skeleton of the present invention includes a traveling body that is movable in the tunnel axis direction within the tunnel skeleton, and a moving body that moves in a direction perpendicular to the tunnel axis from the traveling body. a pair of outriggers that extend out and fix the traveling body to the tunnel frame; and a cargo handling device main body that is installed on the traveling body and performs material handling work in front or behind the traveling body of the traveling body, The traveling body includes a frame having a rectangular cross section when viewed from the tunnel axis direction, and wheels that are provided near each outer corner of the frame that extends in the tunnel axis direction and that come into contact with the tunnel body. .

上述する荷役搬送装置によれば、走行体を構成するフレームの外隅各々の近傍にトンネル躯体に当接する車輪を備えるとともに、トンネル軸線に直交する方向に相反して張出し走行体をトンネル躯体に固定する一対のアウトリガーを備える。これにより、走行体をトンネル軸線方向からみて左右9 0 度の範囲でいずれに傾けても、走行させることができるとともにアウトリガーにより確実に停止させ位置決めできる。したがって、資材が重量物であり、かつ資材の供給位置がトンネル躯体の何れの位置であった場合にも、荷役搬送装置をトンネル躯体内で、荷役装置本体が資材の供給位置に向けて動作可能となる姿勢にしつつ、安定して資材の荷役搬送作業を行うことが可能となる。 According to the above-mentioned cargo handling and conveying device, the wheels that come into contact with the tunnel body are provided near each outer corner of the frame that constitutes the traveling body, and the overhanging traveling body is fixed to the tunnel body in a direction perpendicular to the tunnel axis. Equipped with a pair of outriggers. As a result, even if the traveling body is tilted in any direction within a range of 90 degrees to the left or right when viewed from the tunnel axis direction, it can be made to travel, and the outriggers can reliably stop and position the traveling body. Therefore, even if the material is heavy and the material supply position is anywhere in the tunnel structure, the cargo handling and conveyance device can be operated within the tunnel structure with the main body of the material handling device pointing toward the material supply position. This makes it possible to stably carry out material handling and transport work while maintaining the following posture.

本発明の大断面トンネル躯体の構築方法で用いる荷役搬送装置は、前記荷役装置本体が、前記資材を所定位置に向けて送り出す送出し機構と、送り出した前記資材を所定位置に押し込む押込み機構と、を備え、前記送出し機構による前記資材の送り方向は、前記アウトリガーの張出し方向に直交している。 The cargo handling and transporting device used in the method for constructing a large cross-section tunnel frame according to the present invention includes: the cargo handling device main body includes a delivery mechanism that sends out the material toward a predetermined position, and a pushing mechanism that pushes the delivered material into a predetermined position. The feeding direction of the material by the feeding mechanism is perpendicular to the extending direction of the outrigger.

上述する荷役搬送装置によれば、資材の送出し方向が略水平方向であった場合に、張出し方向が略鉛直方向となるアウトリガーを介して、荷役搬送装置の荷重を外殻トンネル躯体に伝達できることから、荷役搬送装置を安定させた状態で、略水平方向への資材の送出し作業を実施することが可能となる。
According to the cargo handling and transporting device described above , when the material is sent out in a substantially horizontal direction, the load of the material handling and transporting device can be transmitted to the outer shell tunnel frame via the outrigger whose projecting direction is substantially vertical. Therefore, it becomes possible to carry out the work of sending out materials in a substantially horizontal direction while keeping the cargo handling and conveyance device stable.

本発明の大断面トンネル躯体の構築方法は、本発明の荷役搬送装置を用いた大断面トンネル躯体の構築方法であって、小断面の外殻トンネル躯体を並列に複数配置して、大断面トンネルの構築予定領域を囲繞し、前記外殻トンネル躯体内で前記荷役搬送装置を走行させて資材の荷役搬送を行って、前記大断面トンネルの構築予定領域を取り囲む大断面トンネル躯体を構築することを特徴とする。 The method for constructing a large cross-section tunnel frame according to the present invention is a method for constructing a large cross-section tunnel frame using the cargo handling and transporting device according to the present invention, in which a plurality of small cross-section outer shell tunnel bodies are arranged in parallel to form a large cross-section tunnel. and constructing a large cross-section tunnel frame surrounding the planned construction area of the large-section tunnel by running the cargo handling and transporting device within the outer shell tunnel structure to handle and transport materials. Features.

本発明の大断面トンネル躯体の構築方法によれば、大断面トンネル躯体を構築する際に必要となる材料や装備、支保工等の資材の搬送及び荷役作業を迅速化することができ、大断面トンネル躯体の構築作業全体の、作業効率の向上及び工期短縮に寄与することが可能となる。 According to the method for constructing a large cross-section tunnel skeleton of the present invention, it is possible to speed up the transportation and cargo handling work of materials, equipment, shoring, and other materials required when constructing a large cross-section tunnel skeleton, and It is possible to contribute to improving the work efficiency and shortening the construction period of the entire tunnel frame construction work.

また、1つの外殻トンネル躯体での作業が終了次第、他の外殻トンネル躯体に荷役搬送装置を移動させて再利用することが可能となる。 Further, as soon as the work on one outer tunnel skeleton is completed, the cargo handling and conveying device can be moved to another outer tunnel skeleton and reused.

本発明の大断面トンネル躯体の構築方法は、前記大断面トンネル躯体が、該大断面トンネルの周方向及び軸線方向に接続される複数の鋼殻分割体を備え、該鋼殻分割体が、前記大断面トンネル躯体の外周面を形成する外側鋼殻板と、内周面を形成する内側鋼殻板と、該内側鋼殻板と前記外側鋼殻板とを連結する連結材と、を有し、該連結材を前記荷役搬送装置の前記荷役装置本体で把持しつつ、前記鋼殻分割体を前記荷役搬送装置で荷役搬送することを特徴とする。 In the method for constructing a large cross-section tunnel skeleton of the present invention, the large cross-section tunnel skeleton includes a plurality of steel shell division bodies connected in the circumferential direction and the axial direction of the large cross-section tunnel, and the steel shell division bodies include the It has an outer steel shell plate forming an outer circumferential surface of a large-section tunnel frame, an inner steel shell plate forming an inner circumferential surface, and a connecting member connecting the inner steel shell plate and the outer steel shell plate. , the steel shell segment is handled and transported by the cargo handling and transporting device while the connecting member is held by the cargo handling device main body of the cargo handling and transporting device.

本発明の大断面トンネル躯体の構築方法によれば、あらかじめ連結材を介して内側鋼殻板と外側鋼殻板とを一体に固定した鋼殻分割体を製作しておき、この連結材を荷役装置本体で把持することにより、鋼殻分割体を荷役搬送装置で荷役搬送できる。これにより、狭隘な外殻トンネル内で外側鋼殻板と内側鋼殻板の組立て設置作業を省略できるとともに、鋼殻分割体の搬送及び荷役作業も容易となるため、大断面トンネル躯体の構築に係る作業の省力化を図ることが可能となる。 According to the method for constructing a large cross-section tunnel frame of the present invention, a steel shell split body in which an inner steel shell plate and an outer steel shell plate are fixed together via a connecting member is manufactured in advance, and this connecting member is used for cargo handling. By gripping it with the device main body, the steel shell segment can be handled and transported by the cargo handling and transporting device. This makes it possible to omit the assembly and installation work of the outer steel shell plate and inner steel shell plate in a narrow outer shell tunnel, and also facilitates the transportation and cargo handling of the steel shell segments, making it suitable for constructing large-section tunnel frames. It becomes possible to save labor in such work.

また、外側鋼殻板と内側鋼殻板の組立て設置作業を省略できることにより、建て込み時に位置ズレ等を生じることがない。したがって、大断面トンネル躯体を精度よく構築することができ、大断面トンネルに所望の出来形を確保することが可能となる。 Furthermore, since the assembly and installation work of the outer steel shell plate and the inner steel shell plate can be omitted, misalignment and the like will not occur during erection. Therefore, it is possible to construct a large cross-section tunnel frame with high precision, and it is possible to ensure a desired finished shape of the large-section tunnel.

さらに、鋼殻分割体の送り出しもしくは建込み位置が、外殻トンネル躯体の何れの位置にあっても、これに対応する姿勢で荷役搬送装置を走行させ、荷役装置本体を用いて鋼殻分割体を送り出し建て込むことが可能となる。 Furthermore, no matter where the steel shell segment is to be sent out or erected, the cargo handling and conveying equipment is run in the corresponding posture, and the steel shell segment is moved using the cargo handling equipment main body. It becomes possible to send out and build.

本発明によれば、走行体を構成するフレームの外隅各々の近傍に設けたトンネル躯体に当接する車輪と、走行体をトンネル躯体に固定する一対のアウトリガーとを備えるから、資材が重量物であり、かつ資材の供給位置がトンネル躯体の何れの位置であっても、荷役搬送装置をトンネル躯体内で、荷役装置本体が資材の供給位置に向けて動作可能となる姿勢にしつつ、安定して資材の荷役搬送作業を行うことが可能となる。 According to the present invention, since the wheels that come into contact with the tunnel body are provided in the vicinity of each outer corner of the frame constituting the traveling body, and the pair of outriggers that fix the traveling body to the tunnel body are provided, the materials can be used as heavy objects. No matter where the material supply position is in the tunnel structure, the cargo handling and conveying device must be kept in a stable position within the tunnel structure while being in a position where the main body of the material handling device can move towards the material supply position. It becomes possible to carry out material handling and transportation work.

本発明の実施の形態における大断面トンネル躯体の概略を示す図である。FIG. 1 is a diagram schematically showing a large cross-section tunnel frame in an embodiment of the present invention. 本発明の実施の形態における大断面トンネル躯体の詳細を示す図である。FIG. 3 is a diagram showing details of a large cross-section tunnel frame in an embodiment of the present invention. 本発明の実施の形態における鋼殻分割体の詳細を示す図である。It is a figure showing the details of the steel shell division body in an embodiment of the present invention. 本発明の実施の形態における荷役搬送装置の詳細を示す図である(その1)。FIG. 1 is a diagram (part 1) showing details of the cargo handling and conveying device in the embodiment of the present invention. 本発明の実施の形態における荷役搬送装置の詳細を示す図である(その2)。FIG. 2 is a diagram (part 2) showing details of the cargo handling and conveying device in the embodiment of the present invention. 本発明の実施の形態における大断面トンネル躯体の構築手順を示す図である(その1)。FIG. 3 is a diagram (part 1) showing a procedure for constructing a large cross-section tunnel frame in an embodiment of the present invention. 本発明の実施の形態における大断面トンネル躯体の構築手順を示す図である(その2)。FIG. 2 is a diagram showing a procedure for constructing a large cross-section tunnel frame in an embodiment of the present invention (Part 2). 本発明の実施の形態における大断面トンネル躯体の構築手順を示す図である(その3)。It is a figure which shows the construction procedure of the large cross-sectional tunnel frame in embodiment of this invention (part 3). 本発明の実施の形態における大断面トンネル躯体の構築手順を示す図である(その4)。FIG. 4 is a diagram illustrating a procedure for constructing a large cross-section tunnel frame according to an embodiment of the present invention (Part 4). 本発明の実施の形態における荷役搬送装置の他の事例を示す図である(その1)。It is a figure which shows another example of the cargo handling and conveyance apparatus in embodiment of this invention (1). 本発明の実施の形態における荷役搬送装置の他の事例を示す図である(その2)。It is a figure which shows another example of the cargo handling and conveyance apparatus in embodiment of this invention (part 2). 本発明の実施の形態における荷役搬送装置の他の事例を示す図である(その3)。It is a figure which shows another example of the cargo handling and conveyance apparatus in embodiment of this invention (part 3). 本発明の実施の形態における荷役搬送装置の使用状態を示す図である(その1)。FIG. 1 is a diagram (part 1) showing the usage state of the cargo handling and conveyance device in the embodiment of the present invention. 本発明の実施の形態における荷役搬送装置の使用状態を示す図である(その2)。It is a figure (part 2) showing the usage state of the cargo handling conveyance device in an embodiment of the present invention.

本発明は、大断面トンネルの構築予定領域を囲繞するようにして、小断面の外殻トンネルを並列に複数構築し、この外殻トンネルを利用して、大断面トンネル躯体を構築する際に好適な装置および方法である。 The present invention is suitable for constructing a plurality of small-section outer shell tunnels in parallel so as to surround an area where a large-section tunnel is planned to be constructed, and using these outer shell tunnels to construct a large-section tunnel frame. This is a unique device and method.

構築予定の大断面トンネルは、いずれの用途に用いられるものであってもよいが、本実施の形態では、既設の本線トンネルと支線トンネルとの分岐合流部として大断面トンネルを用いる場合を事例に挙げ、図1~図14を参照しつつ、荷役搬送装置、及び大断面トンネル躯体の構築方法について、その詳細を説明する。 The large cross-section tunnel to be constructed may be used for any purpose, but in this embodiment, the case where the large cross-section tunnel is used as a junction between an existing main line tunnel and a branch tunnel will be used as an example. 1 to 14, details of the cargo handling and conveying device and the method of constructing a large cross-section tunnel frame will be described.

図1で示すように、既設の本線トンネル1には、支線トンネル2との分岐合流部となる範囲に、大断面トンネル構築予定領域3が設定されており、この大断面トンネル構築予定領域3に沿って、複数の外殻トンネル躯体5が構築されている。これら複数の外殻トンネル躯体5には、その内部空間である外殻トンネル4を利用して大断面トンネル構築予定領域3を取り囲む大断面トンネル躯体9が構築されている。大断面トンネルは、大断面トンネル躯体9の内方を掘削することで構築される。 As shown in Fig. 1, a large-section tunnel construction area 3 is set in the existing main line tunnel 1 in the area where it branches and merges with the branch tunnel 2. A plurality of outer shell tunnel bodies 5 are constructed along the tunnel. In these plurality of outer shell tunnel bodies 5, a large cross-section tunnel frame 9 is constructed which surrounds the large cross-section tunnel construction planned area 3 by using the outer shell tunnel 4, which is an internal space thereof. The large-section tunnel is constructed by excavating the inside of the large-section tunnel body 9.

大断面トンネル躯体9は、図2で示すように、鋼殻分割体7とその内方に打設充填されたコンクリート8とによりなる躯体分割体6を、大断面トンネル構築予定領域3の周方向に複数接続するとともに、大断面トンネル構築予定領域3のトンネル軸線方向にも複数接続することにより構築される筒状構造体である。 As shown in FIG. 2, the large cross-section tunnel body 9 is constructed by inserting a frame body divided body 6 consisting of a steel shell divided body 7 and concrete 8 cast and filled inwardly in the circumferential direction of the large cross-section tunnel construction area 3. It is a cylindrical structure that is constructed by connecting a plurality of tunnels to each other and also connecting a plurality of tunnels in the tunnel axis direction of the large-section tunnel construction area 3.

そして、躯体分割体6を構成する鋼殻分割体7は、大断面トンネル躯体9の内周面を形成する内側鋼殻板71と、大断面トンネル躯体9の外周面を形成する外側鋼殻板72と、両者の間に設置されるせん断補強筋73及び連結材74と、により構成される。 The steel shell divisions 7 constituting the main body division 6 are comprised of an inner steel shell plate 71 forming the inner circumferential surface of the large cross-section tunnel frame body 9 and an outer steel shell plate forming the outer circumferential surface of the large cross-section tunnel frame body 9. 72, and shear reinforcing bars 73 and connecting members 74 installed between the two.

内側鋼殻板71は、図3で示すように、長さ方向が大断面トンネル躯体9の内周面を形成する円弧状に形成された矩形鋼板よりなるスキンプレート711と、スキンプレート711の幅方向の両端部各々に設置される一対の主桁712と、スキンプレート711の長さ方向の両端部各々に設置される一対の継手板713と、主桁712同士を連結するようにスキンプレート711上に設置される複数の縦リブ(図示せず)と、を備える。これら主桁712、継手板713および縦リブはいずれも、スキンプレート711の凸面側に設置される。 As shown in FIG. 3, the inner steel shell plate 71 includes a skin plate 711 made of a rectangular steel plate formed in an arc shape whose longitudinal direction forms the inner circumferential surface of the tunnel body 9 with a large cross section, and a skin plate 711 whose width is the same as that of the skin plate 711. A pair of main girders 712 installed at each end in the direction, a pair of joint plates 713 installed at each end in the length direction of the skin plate 711, and a skin plate 711 so as to connect the main girders 712 to each other. and a plurality of vertical ribs (not shown) installed thereon. These main beams 712, joint plates 713, and vertical ribs are all installed on the convex side of the skin plate 711.

外側鋼殻板72も内側鋼殻板71と同様に、スキンプレート721、一対の主桁722、一対の継手板723、および縦リブ(図示せず)を備えるが、スキンプレート721は、長さ方向が大断面トンネル躯体9の外周面を形成する円弧状に形成される。また、主桁722、継手板723および縦リブはいずれも、スキンプレート721の凹面側に設置される。 Like the inner steel shell plate 71, the outer steel shell plate 72 also includes a skin plate 721, a pair of main girders 722, a pair of joint plates 723, and vertical ribs (not shown). The direction is formed into an arc shape forming the outer circumferential surface of the large cross-section tunnel frame 9. Further, the main girder 722, the joint plate 723, and the vertical rib are all installed on the concave side of the skin plate 721.

せん断補強筋73は、間隔を設けて配置した内側鋼殻板71と外側鋼殻板72との間で、両者を連結するように間隔を設けて複数設置されている。こうして構築された鋼殻分割体7には、さらに、連結材74が設けられている。 A plurality of shear reinforcing bars 73 are installed at intervals between the inner steel shell plate 71 and the outer steel shell plate 72, which are arranged at intervals, so as to connect the two. The thus constructed steel shell segment 7 is further provided with a connecting member 74.

連結材74は、内側鋼殻板71と外側鋼殻板72とを、コンクリート8を打設する前の状態で一体に連結し、後述する荷役搬送装置100を用いた荷役搬送作業を可能にするものであり、H形鋼等の鋼材を採用している。本実施の形態では、連結材74を、せん断補強筋73と平行にして、鋼殻分割体7における長さ方向の一端側近傍に設置しているが、これに限定されるものではなく、両端近傍各々に設置してもよい。 The connecting member 74 connects the inner steel shell plate 71 and the outer steel shell plate 72 together in a state before concrete 8 is poured, and enables cargo handling and transportation work using the cargo handling and transportation device 100 described later. It is made of steel such as H-beam steel. In this embodiment, the connecting member 74 is installed in parallel with the shear reinforcing bar 73 near one end in the longitudinal direction of the steel shell split body 7; however, the connecting member 74 is not limited thereto; They may be installed in each neighborhood.

このような構造の鋼殻分割体7を含め、大断面トンネル躯体9を構築する際に必要となる材料や装備、支保工等の資材は、外殻トンネル躯体5を走行通路とする荷役搬送装置100により荷役搬送される。以下に、荷役搬送装置100についてその詳細を説明する。 Materials, equipment, shoring, and other materials necessary for constructing the large cross-section tunnel body 9, including the steel shell division body 7 having such a structure, are provided by a cargo handling and transporting device that uses the outer shell tunnel body 5 as a traveling path. The cargo is handled and transported by 100. The details of the cargo handling and conveying apparatus 100 will be explained below.

≪荷役搬送装置≫
荷役搬送装置100は、図4で示すように、外殻トンネル躯体5の軸線方向に移動自在な構成を有しており、走行体110と、アウトリガー120と、荷役装置本体130とを備えている。
≪Cargo handling and conveyance device≫
As shown in FIG. 4, the cargo handling and conveying device 100 has a configuration that is movable in the axial direction of the outer shell tunnel body 5, and includes a traveling body 110, an outrigger 120, and a cargo handling device main body 130. .

走行体110は、フレーム111と、主車輪116と、副車輪117とを有し、フレーム111は、外形が直方体もしくは立方体のごとく形成された車体であり、2体の下桁部材112、2体の上桁部材113、複数の柱部材114、及び複数の梁部材115とにより構成されている。 The traveling body 110 has a frame 111, a main wheel 116, and a subwheel 117. The frame 111 is a vehicle body whose outer shape is shaped like a rectangular parallelepiped or a cube, and the frame 111 has a rectangular parallelepiped or a cube shape. It is composed of an upper girder member 113, a plurality of column members 114, and a plurality of beam members 115.

下桁部材112及び上桁部材113はそれぞれ、外殻トンネル躯体5のトンネル軸線方向に延在する長尺部材であり、下桁部材112と上桁部材113とを連結するようにして柱部材114が複数設置され、下桁部材112同士もしくは上桁部材113同士を連結するようにして梁部材115が複数設置されている。 The lower girder member 112 and the upper girder member 113 are each elongated members extending in the tunnel axis direction of the outer shell tunnel frame 5, and the column member 114 connects the lower girder member 112 and the upper girder member 113. A plurality of beam members 115 are installed so as to connect the lower girder members 112 or the upper girder members 113 to each other.

これにより、フレーム111は、外殻トンネル躯体5のトンネル軸線方向の断面が矩形状で中空部を有し、また、フレーム111の外隅を形成する下桁部材112及び上桁部材113各々には、主車輪116及び副車輪117が設置されている。これら主車輪116及び副車輪117はそれぞれ、下桁部材112及び上桁部材113の長手方向に間隔を設けて複数設置されている。 As a result, the frame 111 has a rectangular cross section in the tunnel axis direction of the outer shell tunnel body 5 and a hollow portion, and each of the lower girder member 112 and the upper girder member 113 forming the outer corner of the frame 111 has a rectangular cross section in the tunnel axis direction. , a main wheel 116 and a subwheel 117 are installed. A plurality of these main wheels 116 and secondary wheels 117 are installed at intervals in the longitudinal direction of the lower girder member 112 and the upper girder member 113, respectively.

アウトリガー120は、図5で示すように、柱部材114と平行な方向に伸縮する油圧ジャッキ121と、柱部材114の周りを回動自在に設置されている取付部材122とにより構成され、油圧ジャッキ121のピストン121aが取付部材122に固定されている。これにより、油圧ジャッキ121は、図4及び図5で示すように、柱部材114の周りを回動し、フレーム111から側方に出没自在となる。 As shown in FIG. 5, the outrigger 120 includes a hydraulic jack 121 that expands and contracts in a direction parallel to the column member 114, and a mounting member 122 that is rotatably installed around the column member 114. 121 pistons 121a are fixed to the mounting member 122. As a result, the hydraulic jack 121 rotates around the column member 114, as shown in FIGS. 4 and 5, and can freely protrude and retract from the frame 111 laterally.

このようなアウトリガー120は2体が対をなして一組となり、フレーム111の両側方各々に一組ずつ合計4体設置されている。そして、この対をなすアウトリガー120は油圧ジャッキ121のロッド121bが、図5で示すように、互いに外殻トンネル躯体5のトンネル軸線方向と直交しつつ、相反する方向に伸長するよう配置されている。 Two such outriggers 120 form a pair, and a total of four outriggers 120 are installed, one set on each side of the frame 111. The outriggers 120 forming this pair are arranged such that the rods 121b of the hydraulic jacks 121 extend in opposite directions while being orthogonal to the tunnel axis direction of the outer shell tunnel body 5, as shown in FIG. .

荷役装置本体130は、フレーム111の前方側(荷役搬送装置100の前進方向)に設けられており、梁部材115と平行な軸部材131と、軸部材131に対して回動自在に設置された資材把持機構132とを備える。資材把持機構132は、ブーム133及びアーム134と、アーム134の先端に設けられて資材を把持する把持部135とを備える。 The cargo handling device main body 130 is provided on the front side of the frame 111 (in the forward direction of the cargo handling and conveyance device 100), and is rotatably installed with respect to the shaft member 131 parallel to the beam member 115. A material gripping mechanism 132 is provided. The material gripping mechanism 132 includes a boom 133, an arm 134, and a grip section 135 provided at the tip of the arm 134 to grip the material.

そして、軸部材131がフレーム111の内空部に設置されることにより、荷役装置本体130はブーム133及びアーム134を、折り畳むと図4で示すように、フレーム111内に収納され、展開すると図5で示すように、軸部材131周りに回動しながら、把持部135をフレーム111より上方及び下方へ昇降させることができる。また、資材把持機構132は、軸部材131の長手方向(梁部材115と平行な方向)に沿って移動させることもでき、フレーム111内で側方への位置調整を行うことができる。 By installing the shaft member 131 in the inner space of the frame 111, the cargo handling device main body 130 has the boom 133 and the arm 134 stored in the frame 111 as shown in FIG. 4 when folded, and as shown in FIG. 4 when unfolded. As shown at 5, the grip portion 135 can be raised and lowered from the frame 111 while rotating around the shaft member 131. Further, the material gripping mechanism 132 can also be moved along the longitudinal direction of the shaft member 131 (in a direction parallel to the beam member 115), and its position can be adjusted laterally within the frame 111.

なお、把持部135は、チャック式もしくは電磁石式等いずれでもよく、また、アタッチメント式に構成され、把持しようとする資材の形状に応じた部材を取り替え自在な構成となっていてもよい。また、荷役装置本体130は、フレーム111の後方側(荷役搬送装置100の後進方向)に設けてもよい。 Note that the gripping portion 135 may be of either a chuck type or an electromagnetic type, or may be configured as an attachment type, so that members can be replaced depending on the shape of the material to be gripped. Further, the cargo handling device main body 130 may be provided on the rear side of the frame 111 (in the backward direction of the cargo handling and conveying device 100).

上述する構成の荷役搬送装置100は、図4で示すように、外殻トンネル躯体5の内周面であってトンネル軸線方向に延在するように設置された4体の長尺架台10をガイドにしてトンネル軸線方向に移動する。具体的には、主車輪116が、4体の長尺架台10のうちの2台に張り出して設置されたレール13上を走行する。一方、副車輪117は、他の2体の長尺架台10各々に当接し走行する。 As shown in FIG. 4, the cargo handling and transporting apparatus 100 having the above-mentioned configuration guides four elongated frames 10 that are installed on the inner circumferential surface of the outer tunnel body 5 and extend in the tunnel axis direction. and move in the direction of the tunnel axis. Specifically, the main wheels 116 run on rails 13 that are installed so as to overhang two of the four elongated frames 10. On the other hand, the secondary wheels 117 travel while abutting on each of the other two elongated frames 10.

一方、走行を停止して荷役作業を行う際は、図5で示すように、アウトリガー120を展開する。つまり、柱部材114周りに取付部材122を介して油圧ジャッキ121を回動し、フレーム111から側方に張り出させ、さらに、油圧ジャッキ121のロッド121bを伸張させる。すると、油圧ジャッキ121が、上下に位置する長尺架台10の間に形成された空間でこれら上下の長尺架台10を押圧することにより、荷役搬送装置100は停止位置で位置決めされる。 On the other hand, when the vehicle stops traveling and performs cargo handling work, the outriggers 120 are deployed as shown in FIG. In other words, the hydraulic jack 121 is rotated around the column member 114 via the mounting member 122 to project laterally from the frame 111, and the rod 121b of the hydraulic jack 121 is further extended. Then, the hydraulic jack 121 presses the upper and lower elongate frames 10 in the space formed between the upper and lower elongate frames 10, thereby positioning the cargo handling and transporting apparatus 100 at the stop position.

なお、外殻トンネル躯体5を構成する長尺架台10は、外殻トンネル躯体5の内周面を略外接円とする仮想の正方形もしくは長方形の4隅に対して、外殻トンネル躯体5の軸線方向に延在するようにして設けられた、断面視四分円に形成された長尺部材である。 Note that the elongated frame 10 constituting the outer shell tunnel frame 5 is arranged so that the axis of the outer shell tunnel frame 5 It is an elongated member formed in a quadrant in cross-sectional view and provided so as to extend in the direction.

このように荷役搬送装置100は、フレーム111の4つの外隅それぞれに設けた主車輪116もしくは副車輪117が、長尺架台10を介して外殻トンネル躯体5の内周面に当接した状態で走行する。これにより、長尺架台10の位置に応じてフレーム111を外殻トンネル4のトンネル軸線方向からみて左右90度の範囲でいずれに傾けても、荷役搬送装置100は走行することができるとともにアウトリガー120により確実に停止させ位置決めできる。 In this way, the cargo handling and transporting device 100 is in a state in which the main wheels 116 or the secondary wheels 117 provided at each of the four outer corners of the frame 111 are in contact with the inner circumferential surface of the outer shell tunnel body 5 via the elongated frame 10. Run with As a result, even if the frame 111 is tilted in any direction within a range of 90 degrees to the left or right when viewed from the tunnel axis direction of the outer shell tunnel 4 according to the position of the long frame 10, the cargo handling and conveying device 100 can run, and the outriggers 120 This allows for reliable stopping and positioning.

したがって、資材が重量物であり、かつ資材の供給位置が外殻トンネル躯体5における内周面の何れの位置であっても、荷役搬送装置100を外殻トンネル躯体5内で、荷役装置本体130が資材の供給位置に向けて動作可能となる姿勢にして、資材の荷役搬送をすることが可能となる。 Therefore, even if the material is heavy and the material is supplied at any position on the inner circumferential surface of the outer shell tunnel body 5, the cargo handling and conveyance device 100 can be moved within the outer shell tunnel body 5 to the material handling device main body 130. It becomes possible to carry out cargo handling and transportation of materials by setting the robot in a position where it can move towards the material supply position.

≪大断面トンネル躯体の構築方法≫
上記の荷役搬送装置100を利用して、大断面トンネル躯体9を構築する手順を、図6~図9を参照しつつ説明する。
≪Method for constructing large cross-section tunnel structure≫
The procedure for constructing the large cross-section tunnel frame 9 using the above-mentioned cargo handling and transporting apparatus 100 will be explained with reference to FIGS. 6 to 9.

なお、図6(a)で示すように、大断面トンネル構築予定領域3にはこれを囲繞するようにして、小断面の外殻トンネル躯体5がトンネル軸線方向を、大断面トンネル構築予定領域3の軸線方向に合わせて、複数並列配置されている。本実施の形態では、図1で示すように、大断面トンネル構築予定領域3を軸線方向で複数の区画A、B・・に区割りする。そして、この区画ごとに、図2で示すような隣り合う外殻トンネル躯体5同士を跨ぐようにして、躯体分割体6を構築しリング状の構造体を構築する。 As shown in FIG. 6(a), the large cross-section tunnel construction planned area 3 is surrounded by a small cross-section outer shell tunnel body 5 that extends in the tunnel axis direction from the large cross-section tunnel construction planned area 3. A plurality of them are arranged in parallel along the axial direction. In this embodiment, as shown in FIG. 1, the large-section tunnel construction area 3 is divided into a plurality of sections A, B, etc. in the axial direction. Then, for each section, a ring-shaped structure is constructed by constructing a frame divided body 6 so as to straddle adjacent outer shell tunnel bodies 5 as shown in FIG. 2.

〈前処理工程〉
大断面トンネル躯体9の構築に先立ち、複数の外殻トンネル躯体5の周囲地盤には、図6(a)で示すような凍結工法もしくは薬液注入工法による地盤改良部15を形成し、止水対策を施す。また、外殻トンネル躯体5には、前述した4体の長尺架台10を設置しておく。
<Pre-treatment process>
Prior to construction of the large cross-section tunnel body 9, ground improvement sections 15 are formed in the ground surrounding the plurality of outer shell tunnel bodies 5 by freezing method or chemical injection method as shown in FIG. 6(a) to prevent water leakage. administer. Furthermore, the four elongated frames 10 described above are installed in the outer shell tunnel body 5.

〈第1の工程〉
図6(b)で示すように、隣り合う一方の外殻トンネル躯体5に、長尺架台10を利用して、トンネル軸線方向からみて3体の支保工11を設置する。支保工11は、図7(a)で示すように、外殻トンネル躯体5の軸線方向にも間隔を設けて複数設置している。このように、長尺架台10を介して支保工11を設置すると、外殻トンネル躯体5のセグメント51の目地位置等を考慮することなく、所望の位置に支保工11を配置できるため、作業性を大幅に向上できる。
<First step>
As shown in FIG. 6(b), three supports 11 are installed on one of the adjacent outer shell tunnel bodies 5 using long frames 10 when viewed from the tunnel axis direction. As shown in FIG. 7(a), a plurality of supports 11 are installed at intervals in the axial direction of the outer shell tunnel body 5. In this way, when the shoring 11 is installed via the long frame 10, the shoring 11 can be placed at a desired position without considering the joint positions of the segments 51 of the outer shell tunnel body 5, so work efficiency is improved. can be significantly improved.

こののち、図6(b)で示すように、隣り合う外殻トンネル躯体5,5’各々の対向する一部分について切り開きを行い、相互に連通する連通空間12を設ける。この切り開き工は、図1で示すように、外殻トンネル4のトンネル軸線方向に設定した区画Aの範囲に対して行い、トンネル軸線方向に連通空間12を連続させる。なお、連通空間12には、隣り合う外殻トンネル躯体5、5’を連結する止水板14を設けておき、地山から連通空間12への漏水を抑止する。 Thereafter, as shown in FIG. 6(b), opposing portions of each of the adjacent outer shell tunnel bodies 5, 5' are cut out to provide communication spaces 12 that communicate with each other. As shown in FIG. 1, this cutting is performed in the range of section A set in the tunnel axis direction of the outer shell tunnel 4, and the communication space 12 is made continuous in the tunnel axis direction. The communication space 12 is provided with a water stop plate 14 that connects the adjacent outer shell tunnel bodies 5, 5' to prevent water from leaking from the ground to the communication space 12.

〈第2の工程〉
図6(c)で示すように、一方の外殻トンネル躯体5に配備した荷役搬送装置100を利用して、鋼殻分割体7の設置開始位置であって連通空間12と対向する位置の支保工11を撤去し、鋼殻分割体設置領域Wを確保する。具体的には、一方の外殻トンネル躯体5内で荷役搬送装置100をトンネル軸線方向に前進移動させ、鋼殻分割体7の設置開始位置近傍で停止させたのち、アウトリガー120を展開して位置決めする。
<Second process>
As shown in FIG. 6(c), the cargo handling and conveying device 100 installed in one of the outer shell tunnel bodies 5 is used to support the installation start position of the steel shell segment 7 and the position facing the communication space 12. Remove the construction 11 and secure the steel shell split body installation area W. Specifically, the cargo handling and conveyance device 100 is moved forward in the tunnel axis direction within one of the outer shell tunnel bodies 5, stopped near the installation start position of the steel shell split body 7, and then the outriggers 120 are deployed and positioned. do.

次に、荷役装置本体130を稼働させて、把持部135にて支保工11を把持しつつ撤去し、把持したままの状態でアウトリガー120を収納し、荷役搬送装置100を後進させる。撤去した支保工11は、図7(a)で示すように、一方の外殻トンネル4のトンネル軸線方向における区画A内で、支保工11を未だ設置していない位置に盛替える。 Next, the cargo handling device main body 130 is operated, the support 11 is gripped and removed by the gripping portion 135, the outriggers 120 are stored while being gripped, and the cargo handling and conveyance device 100 is moved backward. The removed shoring 11 is replaced at a position where no shoring 11 has been installed yet, within section A of one of the outer shell tunnels 4 in the tunnel axis direction, as shown in FIG. 7(a).

こののち、同じく荷役搬送装置100を利用して、鋼殻分割体7を鋼殻分割体設置領域Wに搬送するが、鋼殻分割体7は、図7(a)で示すように、一方の外殻トンネル4の後方に仮置きされている。このため、支保工11を盛替えた後の荷役搬送装置100をさらに後進させ、図7(b)で示すように、仮置き場近傍で停止させたのちアウトリガー120を展開して荷役搬送装置100を位置決めする。 Thereafter, the steel shell divided bodies 7 are transported to the steel shell divided body installation area W using the same cargo handling and conveyance device 100, but the steel shell divided bodies 7 are separated from one side as shown in FIG. 7(a). It is temporarily placed behind the outer shell tunnel 4. Therefore, after the shoring 11 has been replaced, the cargo handling and transporting device 100 is further moved backwards and stopped near the temporary storage area, as shown in FIG. Position.

図7(c)で示すように、荷役装置本体130にて鋼殻分割体7を把持しつつ上昇させ、アウトリガー120を収納して荷役搬送装置100を鋼殻分割体設置領域Wに向けて前進させる。なお、荷役装置本体130の把持部135は、鋼殻分割体7に設けた連結材74を把持すればよく、鋼殻分割体7を容易に搬送することができる。 As shown in FIG. 7(c), the cargo handling device main body 130 lifts the steel shell segment 7 while holding it, stores the outriggers 120, and moves the cargo handling and transport device 100 forward toward the steel shell segment installation area W. let Note that the grip portion 135 of the cargo handling device main body 130 only has to grip the connecting member 74 provided on the steel shell segment 7, and the steel shell segment 7 can be easily transported.

また、鋼殻分割体7の建て込み作業は、図8(a)で示すように、鋼殻分割体設置領域Wの近傍で位置決めした荷役搬送装置100の荷役装置本体130を稼働させて一方の外殻トンネル躯体5の鋼殻分割体設置領域Wから連通空間12に向けて鋼殻分割体7を送り出す。そして、図8(b)で示すように、他方の外殻トンネル躯体5’に先行し設置されている鋼殻分割体7’と当接させ、これらを接続する。 In addition, as shown in FIG. 8(a), the installation work of the steel shell segment 7 is carried out by operating the cargo handling device main body 130 of the cargo handling and transporting device 100 positioned near the steel shell segment installation area W. The steel shell segments 7 are sent out from the steel shell segment installation area W of the outer shell tunnel frame 5 toward the communication space 12 . Then, as shown in FIG. 8(b), it is brought into contact with the steel shell segment 7' installed prior to the other outer shell tunnel frame 5' to connect them.

上記のような、支保工11の撤去跡に形成された鋼殻分割体設置領域Wから連通空間12に向けて鋼殻分割体7を送り出し建て込む作業を、図8(c)で示すように、区画A内における一方の外殻トンネル躯体5のトンネル軸線方向に順次繰り返し、鋼殻分割体7を連接させる。 The work of sending and erecting the steel shell segments 7 from the steel shell segment installation area W formed at the removal site of the shoring 11 toward the communication space 12 as described above is performed as shown in FIG. 8(c). , are repeated in sequence in the tunnel axis direction of one of the outer shell tunnel bodies 5 in section A, and the steel shell divided bodies 7 are connected.

図6~図8で示すように、荷役搬送装置100は、連通空間12に対応して配置された長尺架台10の位置に応じて、外殻トンネル躯体のトンネル軸線方向からみて傾けても走行でき、また、アウトリガー120により確実に停止させ位置決めできる。したがって、重量物である鋼殻分割体7を外殻トンネル躯体5の斜め下方に位置する連通空間12に向けて送り出す際にも、安定して資材の荷役搬送作業を行うことが可能となる。 As shown in FIGS. 6 to 8, the cargo handling and conveying device 100 can run even if it is tilted when viewed from the tunnel axis direction of the outer shell tunnel body, depending on the position of the long frame 10 arranged corresponding to the communication space 12. In addition, the outrigger 120 allows reliable stopping and positioning. Therefore, even when sending out the heavy steel shell divided body 7 toward the communication space 12 located diagonally below the outer shell tunnel body 5, it is possible to carry out the material handling and transportation work stably.

〈第3の工程〉
こののち、図9(a)で示すように、連結した鋼殻分割体7、7’各々にコンクリート8を充填打設して、躯体分割体6を構築する。本実施の形態では、図8(b)で示すように鋼殻分割体7、7’を、大断面トンネル構築予定領域3の周方向に2体連結するとともに、図8(c)で示すように大断面トンネル構築予定領域3の軸線方向(外殻トンネル躯体5のトンネル軸線方向)に5体連結するごとに、コンクリート8の充填打設作業を行っているが、その数量はなんら限定されるものではない。
<Third process>
Thereafter, as shown in FIG. 9(a), each of the connected steel shell segments 7 and 7' is filled with concrete 8 and poured to construct the frame segment 6. In this embodiment, as shown in FIG. 8(b), two steel shell segments 7, 7' are connected in the circumferential direction of the large-section tunnel construction area 3, and as shown in FIG. 8(c). Filling and pouring of concrete 8 is performed every time five bodies are connected in the axial direction of the large-section tunnel construction area 3 (tunnel axial direction of the outer tunnel body 5), but the quantity is not limited in any way. It's not a thing.

〈第4の工程〉
図9(b)(c)で示すように、一方の外殻トンネル躯体5内で荷役搬送装置100を用いて、上記と同様の要領で新たな鋼殻分割体7’’を所定位置に送り出して建て込み、これを連通空間12に位置する第3の工程で構築した躯体分割体6と連結する。また、適宜のタイミングで図9(b)で示すように、連通空間12と躯体分割体6との間、及び外殻トンネル4と鋼殻分割体7との間に生じた空隙部に、充填材16を充填する。
<Fourth step>
As shown in FIGS. 9(b) and 9(c), a new steel shell segment 7'' is sent to a predetermined position in the same manner as described above using the cargo handling and transporting device 100 within one of the outer shell tunnel bodies 5. This is then connected to the divided frame body 6 constructed in the third step located in the communication space 12. In addition, at an appropriate timing, as shown in FIG. Fill with material 16.

これらの工程を、図1で示すような、大断面トンネル構築予定領域3を囲繞する複数の外殻トンネル躯体5各々で繰り返し実施することにより、区画A内に複数の躯体分割体6よりなる筒状構造物が構築される。また、大断面トンネル構築予定領域3の軸線方向(区画A、区画B・・・)に繰り返すことにより、大断面トンネルの構築予定領域を囲繞する大断面トンネル躯体9を構築することができる。 By repeating these steps for each of the plurality of outer shell tunnel bodies 5 surrounding the large cross-section tunnel construction planned area 3 as shown in FIG. A shaped structure is constructed. Further, by repeating the process in the axial direction of the large-section tunnel construction area 3 (section A, section B, etc.), it is possible to construct a large-section tunnel frame 9 that surrounds the large-section tunnel construction area.

なお、荷役搬送装置100は、1つの外殻トンネル躯体5での作業が終了次第、他の外殻トンネル躯体5に移動させて再利用することが可能となる。 In addition, as soon as the work on one outer shell tunnel body 5 is completed, the cargo handling and conveying apparatus 100 can be moved to another outer shell tunnel body 5 and reused.

上記のとおり、荷役搬送装置100を用いた大断面トンネル躯体の構築方法によれば、大断面トンネル躯体9を構築する際に必要となる鋼殻分割体7や支保工11等、資材の荷役搬送作業を迅速化することができ、大断面トンネル躯体9の構築作業全体の作業効率の向上、及び工期短縮に寄与することが可能となる。 As described above, according to the method for constructing a large cross-section tunnel skeleton using the cargo handling and transporting device 100, materials such as the steel shell splits 7 and the shoring 11 necessary for constructing the large cross-section tunnel skeleton 9 can be handled and transported. The work can be speeded up, and it is possible to contribute to improving the work efficiency of the entire construction work of the large cross-section tunnel frame 9 and shortening the construction period.

また、連結材74を介して内側鋼殻板71と外側鋼殻板72とを一体に固定した鋼殻分割体7を製作しておくことで、連結材74を利用して鋼殻分割体7を荷役搬送装置100で荷役搬送できる。これにより、外側鋼殻板72と内側鋼殻板71の組立て設置作業を省略でき、また、鋼殻分割体7荷役搬送作業も容易となるため、大断面トンネル躯体9の構築に係る作業の省力化を図ることが可能となる。 Furthermore, by manufacturing the steel shell divided body 7 in which the inner steel shell plate 71 and the outer steel shell plate 72 are integrally fixed via the connecting member 74, the steel shell divided body 7 can be made by using the connecting member 74. can be handled and transported by the cargo handling and transporting device 100. As a result, the assembly and installation work of the outer steel shell plate 72 and the inner steel shell plate 71 can be omitted, and the cargo handling and transportation work of the steel shell split body 7 is also facilitated, which saves labor related to the construction of the large cross-section tunnel frame 9. This makes it possible to achieve

さらに、外側鋼殻板72と内側鋼殻板71の組立て設置作業を省略できることにより、建込み時の位置ズレ等が生じないため、大断面トンネル躯体9を精度よく構築することができ、大断面トンネルに所望の出来形を確保することが可能となる。 Furthermore, since the assembly and installation work of the outer steel shell plate 72 and the inner steel shell plate 71 can be omitted, positional deviations etc. do not occur during erection, so the large cross-section tunnel frame 9 can be constructed with precision, and the large cross-section It becomes possible to ensure the desired finished shape of the tunnel.

本発明の荷役搬送装置100、及び大断面トンネル躯体9の施工方法は、上記実施形態に限定されるものではなく、本発明の趣旨を逸脱しない範囲で種々の変更が可能である。 The cargo handling and conveyance apparatus 100 and the construction method of the large cross-section tunnel frame 9 of the present invention are not limited to the above embodiments, and various changes can be made without departing from the spirit of the present invention.

例えば、本実施の形態では、荷役搬送装置100において、荷役装置本体130に、ブーム133とアーム134を備えた資材把持機構132を採用し、動作方向(資材の送り方向)を柱部材114と平行な方向に設定した。また、アウトリガー120を、油圧ジャッキ121が荷役装置本体130の動作方向と平行な方向に伸長するよう、走行体110に設置した。このような構造は、図6~図9で示すように、地盤の深さ方向に鋼殻分割体7を送り出し建込む際に好適である。 For example, in the present embodiment, the material handling device 100 employs a material gripping mechanism 132 including a boom 133 and an arm 134 in the material handling device main body 130, and the operating direction (material feeding direction) is parallel to the column member 114. It was set in the direction. Further, the outrigger 120 was installed on the traveling body 110 so that the hydraulic jack 121 extends in a direction parallel to the operating direction of the cargo handling device main body 130. Such a structure is suitable for sending out and erecting the steel shell segments 7 in the depth direction of the ground, as shown in FIGS. 6 to 9.

しかし、図1で示す領域Xのように、外殻トンネル躯体5が略水平方向に隣り合う場合、両者の連通空間12は水平方向となるから、上述する荷役搬送装置100は、必ずしも、合理的な構造とはえいない。そこで、荷役搬送装置100の他の事例を、図10~図14を参照しつつ説明する。 However, when the outer shell tunnel bodies 5 are adjacent to each other in a substantially horizontal direction as in the region X shown in FIG. It doesn't look like a good structure. Therefore, other examples of the cargo handling and transporting apparatus 100 will be explained with reference to FIGS. 10 to 14.

荷役搬送装置100は、図10で示すように、走行体110と、アウトリガー120と、荷役装置本体130とを備えるが、図4で示した荷役搬送装置100とは、走行体110に設備移動装置160が設けられている点、荷役装置本体130が、送出し機構140と押込み機構150とを備える構造である点、アウトリガー120が押込み機構150とともに設備移動装置160に設けられている点で、その構造が異なっている。 As shown in FIG. 10, the cargo handling and transporting device 100 includes a running body 110, an outrigger 120, and a cargo handling device main body 130. However, the cargo handling and transporting device 100 shown in FIG. 160 is provided, the cargo handling device main body 130 has a structure including a sending mechanism 140 and a pushing mechanism 150, and the outriggers 120 are provided in the equipment moving device 160 together with the pushing mechanism 150. The structure is different.

走行体110は、フレーム111、主車輪116及び副車輪117を備え、フレーム111は、2体の下桁部材112、2体の上桁部材113、複数の柱部材114、及び複数の梁部材115とにより構成され、外殻トンネル躯体5のトンネル軸線方向に中空部を有する立方体状もしくは直方体状の外形を有する車体である。また、フレーム111の外隅を形成する下桁部材112及び上桁部材113各々に、主車輪116及び副車輪117が設置されている。 The traveling body 110 includes a frame 111, a main wheel 116, and a subwheel 117. The vehicle body has a cubic or rectangular parallelepiped outer shape with a hollow portion in the tunnel axis direction of the outer tunnel skeleton 5. Further, a main wheel 116 and a subwheel 117 are installed on each of the lower spar member 112 and the upper spar member 113 that form the outer corners of the frame 111.

上記の構成は、図4で示した前述の荷役搬送装置100の走行体110と同様であるが、図10では、走行体110を構成するフレーム111の中空部であって一方の側面に、設備移動装置160が設けられている。 The above configuration is the same as that of the traveling body 110 of the above-described cargo handling and conveying apparatus 100 shown in FIG. 4, but in FIG. A mobile device 160 is provided.

設備移動装置160は、図11で示すように、フレーム111の後方から前方に向かうレール状の案内部材161と、図12で示すように、案内部材161上を移動する架台162とを備え、架台162は、柱部材114と平行な平面を有し、この平面にターンテーブル163が回転可能に設置されている。そして、このターンテーブル163に、アウトリガー120と押込み機構150が設置されている。 The equipment moving device 160 includes a rail-shaped guide member 161 extending from the rear to the front of the frame 111, as shown in FIG. 11, and a pedestal 162 that moves on the guide member 161, as shown in FIG. 162 has a plane parallel to the column member 114, and the turntable 163 is rotatably installed on this plane. An outrigger 120 and a pushing mechanism 150 are installed on this turntable 163.

アウトリガー120と押込み機構150は、図11で示すように、架台162がフレーム111の後方に位置する状態で、フレーム111内に収納されている。また、図12で示すように、架台162を案内部材161上でフレーム111の前方まで移動させたのち、ターンテーブル163を回転すると、アウトリガー120及び押込み機構150がともに、フレーム111の前方(荷役搬送装置100の後進方向)に配置される。 The outriggers 120 and the pushing mechanism 150 are housed within the frame 111, with the pedestal 162 positioned at the rear of the frame 111, as shown in FIG. Further, as shown in FIG. 12, when the turntable 163 is rotated after moving the pedestal 162 to the front of the frame 111 on the guide member 161, both the outrigger 120 and the pushing mechanism 150 are moved to the front of the frame 111 (loading/transporting (in the backward direction of the device 100).

アウトリガー120は、図10で示すように、2体の油圧ジャッキ121とこれらをターンテーブル163に設置する取付部材(後述する押圧装置151がこれを兼用)とを備え、架台162をフレーム111の前方まで移動させターンテーブル163を回転すると、2体の油圧ジャッキ121がフレーム111の前方であって上桁部材113より上方に配置される。この状態で2体の油圧ジャッキ121各々は、ロッド121bが、外殻トンネル躯体5のトンネル軸線方向と直交しつつ、梁部材115と平行な互いに相反する方向に伸長する。 As shown in FIG. 10, the outrigger 120 includes two hydraulic jacks 121 and a mounting member for installing them on a turntable 163 (also used by a pressing device 151 to be described later), and a mount 162 is mounted in front of the frame 111. When the turntable 163 is rotated, the two hydraulic jacks 121 are placed in front of the frame 111 and above the upper beam member 113. In this state, the rods 121b of each of the two hydraulic jacks 121 extend in opposite directions parallel to the beam member 115 and perpendicular to the tunnel axis direction of the outer shell tunnel body 5.

また、押込み機構150は、柱状の伸縮自在な押圧装置151とその先端に設けられ、資材に当接して押圧力を作用する押圧部152と、押圧装置151をターンテーブル163に設置する取付部材153とを備える。そして、架台162をフレーム111の前方まで移動させターンテーブル163を回転すると、フレーム111の前方で押圧装置151が柱部材114と平行となるように配置される。この状態で、押圧装置151を伸張させると、押圧部152は、柱部材114と平行な方向に移動し、下桁部材112より下方に到達する。 Further, the pushing mechanism 150 includes a column-shaped extensible pushing device 151, a pushing section 152 provided at the tip thereof that contacts the material and applies a pushing force, and a mounting member 153 that installs the pushing device 151 on the turntable 163. Equipped with. Then, when the pedestal 162 is moved to the front of the frame 111 and the turntable 163 is rotated, the pressing device 151 is arranged in front of the frame 111 so as to be parallel to the column member 114. When the pressing device 151 is expanded in this state, the pressing portion 152 moves in a direction parallel to the column member 114 and reaches below the lower girder member 112.

送出し機構140は、図12で示すように、把持機構141とスライド機構142と、案内板143を備え、フレーム111の前面に設置されるが、アウトリガー120及び押込み機構150が、図10で示すように、フレーム111の前方に配置された際にこれらと干渉することのない位置に配置されている。 The delivery mechanism 140 includes a gripping mechanism 141, a slide mechanism 142, and a guide plate 143, as shown in FIG. Thus, when placed in front of the frame 111, it is placed in a position that will not interfere with these.

把持機構141は、チャック式もしくは電磁石式等いずれでもよく、また、アタッチメント式に構成され、把持しようとする資材の形状に応じた部材を取り替え自在な構成となっていてもよい。 The gripping mechanism 141 may be of either a chuck type or an electromagnetic type, or may be configured as an attachment type in which members can be replaced depending on the shape of the material to be gripped.

スライド機構142は、下桁部材112近傍と上桁部材113近傍の各々に設けた対をなすスプロケット142aと、スプロケット142aに掛け回される無端のローラーチェーン142bとにより構成されている。そして、このローラーチェーン142bの一部分に把持機構141が設けられることにより、スプロケット142aを回転させることで、図11及び図12で示すように、把持機構141を下桁部材112と上桁部材113との間(柱部材114と平行な方向)で往復移動させることができる。 The slide mechanism 142 is composed of a pair of sprockets 142a provided near the lower spar member 112 and near the upper spar member 113, and an endless roller chain 142b wound around the sprocket 142a. Since the gripping mechanism 141 is provided in a part of the roller chain 142b, by rotating the sprocket 142a, the gripping mechanism 141 can be attached to the lower spar member 112 and the upper spar member 113 as shown in FIGS. 11 and 12. (in a direction parallel to the column member 114).

案内板143は、把持機構141の背面であって、ローラーチェーン142bと平行に配置され、把持機構141が柱部材114と平行な方向に移動する挙動を補助している。 The guide plate 143 is arranged on the back side of the gripping mechanism 141 and parallel to the roller chain 142b, and assists the movement of the gripping mechanism 141 in a direction parallel to the column member 114.

このような構成の荷役搬送装置100は、図13(a)(b)で示すように、鋼殻分割体7の送り出し方向となる連通空間12が略水平方向であった場合に、外殻トンネル躯体5内で、トンネル軸線方向からみて倒伏姿勢となって、送出し機構140の動作方向(送り方向)と、押込み機構150の動作方向(押し込み方向)を略水平方向に向ける。 As shown in FIGS. 13(a) and 13(b), the cargo handling and conveying apparatus 100 having such a configuration is capable of moving the outer shell tunnel Inside the frame 5, it assumes a lying position when viewed from the tunnel axis direction, and the operating direction (feeding direction) of the delivery mechanism 140 and the operating direction (pushing direction) of the pushing mechanism 150 are directed approximately horizontally.

この姿勢であっても、フレーム111の外隅各々に主車輪116及び副車輪117が設置されていることから、送出し機構140の把持機構141で、鋼殻分割体7を把持することにより、外殻トンネル躯体5内で鋼殻分割体7を搬送することができる。 Even in this position, since the main wheels 116 and the sub wheels 117 are installed at each outer corner of the frame 111, by gripping the steel shell segment 7 with the gripping mechanism 141 of the delivery mechanism 140, The steel shell segments 7 can be transported within the outer shell tunnel body 5.

そして、図13(b)で示すように、隣り合う外殻トンネル躯体5、5’の連通空間12に向けて鋼殻分割体7を送り出す際には、送出し機構140のスライド機構142を稼働させ、スプロケット142aを駆動してローラーチェーン142bを回動する。すると、鋼殻分割体7は、連通空間12に向けて送り出される。このとき、把持機構141は、案内板143に移動を補助されているため、鋼殻分割体7を水平方向に安定して送り出すことができる。 Then, as shown in FIG. 13(b), when sending out the steel shell segment 7 toward the communication space 12 between the adjacent outer shell tunnel bodies 5 and 5', the slide mechanism 142 of the sending mechanism 140 is operated. and drives the sprocket 142a to rotate the roller chain 142b. Then, the steel shell segment 7 is sent out toward the communication space 12. At this time, since the gripping mechanism 141 is assisted in movement by the guide plate 143, the steel shell segment 7 can be stably fed out in the horizontal direction.

こののち、鋼殻分割体7を建込む際には、図14で示すように、架台162を案内部材161上でフレーム111の前方まで移動させ、また、ターンテーブル163を回転し、アウトリガー120と押込み機構150をフレーム111の前方に配置する。そして、アウトリガー120を展開し、2体の油圧ジャッキ121で略鉛直方向に位置する長尺架台10を押圧するようにして、荷役搬送装置100を外殻トンネル4の内周面に固定する。これにより、張出し方向が略鉛直方向となるアウトリガー120を介して、荷役搬送装置100の荷重を外殻トンネル躯体5に伝達できる After this, when erecting the steel shell divided body 7, as shown in FIG. A pushing mechanism 150 is arranged in front of the frame 111. Then, the outriggers 120 are deployed, and the two hydraulic jacks 121 press the elongated pedestal 10 located substantially vertically, thereby fixing the cargo handling and transporting device 100 to the inner circumferential surface of the outer shell tunnel 4. As a result, the load of the cargo handling and transporting device 100 can be transmitted to the outer shell tunnel frame 5 via the outrigger 120 whose extending direction is substantially vertical.

この状態で、押圧装置151を伸張させて押圧部152を鋼殻分割体7に把持させる一方で、送出し機構140の把持機構141による把持を開放する。そのうえで、押圧装置151をさらに伸張させて、鋼殻分割体7を押し込んで所定の位置に建て込む。これにより、鋼殻分割体7の送り出し方向が略水平方向であっても、効率よく鋼殻分割体7を建て込むことができる。 In this state, the pressing device 151 is extended to grip the pressing portion 152 on the steel shell segment 7, while the gripping mechanism 141 of the delivery mechanism 140 is released. Then, the pressing device 151 is further extended to push the steel shell segment 7 into a predetermined position. Thereby, even if the steel shell segment 7 is sent out in a substantially horizontal direction, the steel shell segment 7 can be efficiently built.

なお、図13(a)では既に撤去しているが、鋼殻分割体7を搬入する前に長尺架台10を利用し連通空間12と対向する位置に設けられていた支保工11も、送出し機構140の把持機構141を利用して撤去している。 Although it has already been removed in Fig. 13(a), the shoring 11 that was installed at a position facing the communication space 12 using the long frame 10 before the steel shell segment 7 was brought in was also removed. It is removed using the gripping mechanism 141 of the holding mechanism 140.

また、荷役装置本体130をなす送出し機構140と押込み機構150は、走行体110を構成するフレーム111の後方(荷役搬送装置100の後進方向)に配置されるようにしてもよい。 Furthermore, the delivery mechanism 140 and the pushing mechanism 150 that constitute the cargo handling device main body 130 may be arranged behind the frame 111 that constitutes the traveling body 110 (in the backward movement direction of the cargo handling and conveyance device 100).

1 本線トンネル
2 支線トンネル
3 大断面トンネル構築予定領域
4 外殻トンネル
5 外殻トンネル躯体
51 セグメント
6 躯体分割体
7 鋼殻分割体
71 内側鋼殻板
72 外側鋼殻板
73 せん断補強筋
74 連結材
8 コンクリート
9 大断面トンネル躯体
10 長尺架台
11 支保工
12 連通空間
13 レール
14 止水板
15 地盤改良部
16 充填材

100 荷役搬送装置
110 走行体
111 フレーム
112 下桁部材
113 上桁部材
114 柱部材
115 梁部材
116 主車輪
117 副車輪
120 アウトリガー
121 油圧ジャッキ
121a ピストン
121b ロッド
122 取付部材
130 荷役装置本体
131 軸部材
132 資材把持機構
133 ブーム
134 アーム
135 把持部
140 送出し機構
141 把持機構
142 スライド機構
142a スプロケット
142b ローラーチェーン
143 案内板
150 押込み機構
151 押圧装置
152 押圧部
153 取付部材
160 設備移動装置
161 案内部材
162 架台
163 ターンテーブル
1 Main line tunnel 2 Branch tunnel 3 Large cross-section tunnel construction area 4 Outer shell tunnel 5 Outer shell tunnel body 51 Segment 6 Structure divided body 7 Steel shell divided body 71 Inner steel shell plate 72 Outer steel shell plate 73 Shear reinforcing bar 74 Connecting material 8 Concrete 9 Large cross-section tunnel frame 10 Long frame 11 Shoring 12 Communication space 13 Rail 14 Water stop plate 15 Ground improvement section 16 Filling material

100 Cargo handling and conveyance device 110 Traveling body 111 Frame 112 Lower girder member 113 Upper girder member 114 Pillar member 115 Beam member 116 Main wheel 117 Subwheel 120 Outrigger 121 Hydraulic jack 121a Piston 121b Rod 122 Mounting member 130 Cargo handling device main body 131 Shaft member 132 Materials Gripping mechanism 133 Boom 134 Arm 135 Gripping part 140 Sending mechanism 141 Gripping mechanism 142 Slide mechanism 142a Sprocket 142b Roller chain 143 Guide plate 150 Pushing mechanism 151 Pressing device 152 Pressing part 153 Mounting member 160 Equipment moving device 161 Guide member 162 Frame 163 Turn table

Claims (3)

荷役搬送装置を用いた大断面トンネル躯体の構築方法であって、
前記荷役搬送装置は、
トンネル躯体内をトンネル軸線方向に移動可能な走行体と、
該走行体からトンネル軸線に直交する方向に相反して張出し、前記走行体を前記トンネル躯体に固定する一対のアウトリガーと、
前記走行体に設置され、該走行体の進行方向前方もしくは後方で資材の荷役作業を行う荷役装置本体と、を備え、
前記走行体は、
前記トンネル軸線方向からみた断面が矩形状のフレームと、
該フレームの前記トンネル軸線方向に延在する外隅各々の近傍に設けられ、前記トンネル躯体に当接する車輪と、を備えるものであり、
小断面の外殻トンネル躯体を並列に複数配置して、大断面トンネルの構築予定領域を囲繞し、
前記外殻トンネル躯体内で前記荷役搬送装置を走行させて資材の荷役搬送を行って、前記大断面トンネルの構築予定領域を取り囲む大断面トンネル躯体を構築することを特徴とする大断面トンネル躯体の構築方法。
A method for constructing a large cross-section tunnel frame using a cargo handling and conveying device, the method comprising:
The cargo handling and conveyance device is
a traveling body movable in the tunnel axis direction within the tunnel frame;
a pair of outriggers extending oppositely from the traveling body in a direction perpendicular to the tunnel axis and fixing the traveling body to the tunnel frame;
a cargo handling device main body that is installed on the traveling body and performs material handling work in front or rear of the traveling body;
The running body is
a frame having a rectangular cross section when viewed from the tunnel axis direction;
wheels provided near each outer corner of the frame extending in the tunnel axis direction and abutting against the tunnel skeleton;
Multiple small-section outer shell tunnel structures are arranged in parallel to surround the area where the large-section tunnel is planned to be constructed.
A large cross-section tunnel skeleton, characterized in that the cargo handling and conveying device runs within the outer shell tunnel skeleton to handle and convey materials, thereby constructing a large cross-section tunnel skeleton that surrounds an area where the large cross-section tunnel is planned to be constructed. Construction method.
荷役搬送装置を用いた大断面トンネル躯体の構築方法であって、
前記荷役搬送装置は、
トンネル躯体内をトンネル軸線方向に移動可能な走行体と、
該走行体からトンネル軸線に直交する方向に相反して張出し、前記走行体を前記トンネル躯体に固定する一対のアウトリガーと、
前記走行体に設置され、該走行体の進行方向前方もしくは後方で資材の荷役作業を行う荷役装置本体と、を備え、
前記走行体は、
前記トンネル軸線方向からみた断面が矩形状のフレームと、
該フレームの前記トンネル軸線方向に延在する外隅各々の近傍に設けられ、前記トンネル躯体に当接する車輪と、を備えるとともに、
前記荷役装置本体が、前記資材を所定位置に向けて送り出す送出し機構と、送り出した前記資材を所定位置に押し込む押込み機構と、を備え、
前記送出し機構による前記資材の送り方向は、前記アウトリガーの張出し方向に直交するものであり、
小断面の外殻トンネル躯体を並列に複数配置して、大断面トンネルの構築予定領域を囲繞し、
前記外殻トンネル躯体内で前記荷役搬送装置を走行させて資材の荷役搬送を行って、前記大断面トンネルの構築予定領域を取り囲む大断面トンネル躯体を構築することを特徴とする大断面トンネル躯体の構築方法。
A method for constructing a large cross-section tunnel frame using a cargo handling and conveying device, the method comprising:
The cargo handling and conveyance device is
a traveling body movable in the tunnel axis direction within the tunnel frame;
a pair of outriggers extending oppositely from the traveling body in a direction perpendicular to the tunnel axis and fixing the traveling body to the tunnel frame;
A cargo handling device main body that is installed on the traveling body and performs material handling work in the front or rear of the traveling body,
The running body is
a frame having a rectangular cross section when viewed from the tunnel axis direction;
wheels provided near each of the outer corners of the frame extending in the tunnel axis direction and abutting against the tunnel skeleton;
The material handling device main body includes a delivery mechanism that sends out the material toward a predetermined position, and a pushing mechanism that pushes the delivered material into a predetermined position,
The feeding direction of the material by the feeding mechanism is perpendicular to the extending direction of the outrigger,
Multiple small-section outer shell tunnel structures are arranged in parallel to surround the area where the large-section tunnel is planned to be constructed.
A large cross-section tunnel skeleton, characterized in that the cargo handling and conveying device runs within the outer shell tunnel skeleton to handle and convey materials, thereby constructing a large cross-section tunnel skeleton that surrounds an area where the large cross-section tunnel is planned to be constructed. Construction method.
請求項1または2に記載の大断面トンネル躯体の構築方法において、
前記大断面トンネル躯体が、該大断面トンネルの周方向及び軸線方向に接続される複数
の鋼殻分割体を備え、
該鋼殻分割体が、前記大断面トンネル躯体の外周面を形成する外側鋼殻板と、内周面を
形成する内側鋼殻板と、該内側鋼殻板と前記外側鋼殻板とを連結する連結材と、を有し、
該連結材を前記荷役搬送装置の前記荷役装置本体で把持しつつ、前記鋼殻分割体を前記
荷役搬送装置で荷役搬送することを特徴とする大断面トンネル躯体の構築方法。
The method for constructing a large cross-section tunnel frame according to claim 1 or 2 ,
The large-section tunnel body includes a plurality of steel shell segments connected in the circumferential direction and the axial direction of the large-section tunnel,
The steel shell division body connects an outer steel shell plate forming an outer circumferential surface of the large cross-section tunnel frame, an inner steel shell plate forming an inner circumferential surface, and the inner steel shell plate and the outer steel shell plate. a connecting member,
A method for constructing a large cross-section tunnel frame, characterized in that the steel shell segments are handled and transported by the cargo handling and transportation device while the connecting members are held by the cargo handling device main body of the cargo handling and transportation device.
JP2019215252A 2019-11-28 2019-11-28 Construction method of large cross-section tunnel structure Active JP7375501B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2019215252A JP7375501B2 (en) 2019-11-28 2019-11-28 Construction method of large cross-section tunnel structure
JP2023137242A JP2023156523A (en) 2019-11-28 2023-08-25 Cargo handling and conveyance device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019215252A JP7375501B2 (en) 2019-11-28 2019-11-28 Construction method of large cross-section tunnel structure

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2023137242A Division JP2023156523A (en) 2019-11-28 2023-08-25 Cargo handling and conveyance device

Publications (2)

Publication Number Publication Date
JP2021085237A JP2021085237A (en) 2021-06-03
JP7375501B2 true JP7375501B2 (en) 2023-11-08

Family

ID=76087069

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2019215252A Active JP7375501B2 (en) 2019-11-28 2019-11-28 Construction method of large cross-section tunnel structure
JP2023137242A Pending JP2023156523A (en) 2019-11-28 2023-08-25 Cargo handling and conveyance device

Family Applications After (1)

Application Number Title Priority Date Filing Date
JP2023137242A Pending JP2023156523A (en) 2019-11-28 2023-08-25 Cargo handling and conveyance device

Country Status (1)

Country Link
JP (2) JP7375501B2 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232426A (en) 2003-02-03 2004-08-19 Kawada Construction Co Ltd Floor panel laying apparatus
JP2004300688A (en) 2003-03-28 2004-10-28 Pc Bridge Co Ltd Mobile pre-cast floor slab erection machine
JP2011179305A (en) 2010-02-03 2011-09-15 Ohbayashi Corp Large cross section tunnel and construction method of the same
JP2014211054A (en) 2013-04-19 2014-11-13 株式会社安藤・間 Erector device and segment assembling device using the same
JP2018087437A (en) 2016-11-29 2018-06-07 吉永機械株式会社 Traveling truck
JP2018150752A (en) 2017-03-14 2018-09-27 株式会社大林組 Method for constructing tunnel skeleton

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004232426A (en) 2003-02-03 2004-08-19 Kawada Construction Co Ltd Floor panel laying apparatus
JP2004300688A (en) 2003-03-28 2004-10-28 Pc Bridge Co Ltd Mobile pre-cast floor slab erection machine
JP2011179305A (en) 2010-02-03 2011-09-15 Ohbayashi Corp Large cross section tunnel and construction method of the same
JP2014211054A (en) 2013-04-19 2014-11-13 株式会社安藤・間 Erector device and segment assembling device using the same
JP2018087437A (en) 2016-11-29 2018-06-07 吉永機械株式会社 Traveling truck
JP2018150752A (en) 2017-03-14 2018-09-27 株式会社大林組 Method for constructing tunnel skeleton

Also Published As

Publication number Publication date
JP2023156523A (en) 2023-10-24
JP2021085237A (en) 2021-06-03

Similar Documents

Publication Publication Date Title
JP5671373B2 (en) Bridge removal method and new construction method
JP5485076B2 (en) Tunnel construction equipment and construction method
JP6433855B2 (en) Tunnel lining device and tunnel lining method
JP4318042B2 (en) Tunnel construction method
JP6605944B2 (en) How to build a shield tunnel
JP2020002563A (en) Deck slab construction method
JP7375501B2 (en) Construction method of large cross-section tunnel structure
JP5793062B2 (en) Tunnel construction apparatus and tunnel construction method
US11480054B2 (en) Rapid construction method for secondary lining of small-section tunnel
JP2017125334A (en) Lining assembling apparatus
JP6550942B2 (en) Segment unloading method and segment unloading device
JP6549411B2 (en) Floor construction method of shield tunnel
JP3831900B2 (en) Tunnel construction method
JPH03241200A (en) Method and device for setting precast board for tunnel
JP5528049B2 (en) Tunnel drilling equipment
JP4118420B2 (en) Tunnel excavation and lining method and its equipment
JPH03129099A (en) Lining construction for tunnel in shield method and equipment thereof
JP2000130099A (en) Erector interlocking type segment built-up scaffolding
JP4392609B2 (en) Tunnel material transport equipment
JP2018131846A (en) Assembling method of transport device and rotational structure
JP2878254B1 (en) Open shield method
JP4316115B2 (en) Tunnel lining equipment
JP3153852B2 (en) Tunnel lining equipment
JP2012052376A (en) Segment shape retention device for shield tunnel
JP3249390B2 (en) Tunnel opening method and dismantling device used in the method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20221017

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230620

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230704

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230825

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230926

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231009

R150 Certificate of patent or registration of utility model

Ref document number: 7375501

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150