JP7248528B2 - Concrete filling jig, concrete filling method - Google Patents

Concrete filling jig, concrete filling method Download PDF

Info

Publication number
JP7248528B2
JP7248528B2 JP2019129206A JP2019129206A JP7248528B2 JP 7248528 B2 JP7248528 B2 JP 7248528B2 JP 2019129206 A JP2019129206 A JP 2019129206A JP 2019129206 A JP2019129206 A JP 2019129206A JP 7248528 B2 JP7248528 B2 JP 7248528B2
Authority
JP
Japan
Prior art keywords
concrete
filling
tubular body
partition wall
jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019129206A
Other languages
Japanese (ja)
Other versions
JP2021014710A (en
Inventor
振煥 全
和久 依田
茂 淺岡
信之 林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2019129206A priority Critical patent/JP7248528B2/en
Publication of JP2021014710A publication Critical patent/JP2021014710A/en
Application granted granted Critical
Publication of JP7248528B2 publication Critical patent/JP7248528B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

本発明は、コンクリートの落し込み充填に用いるコンクリート充填用治具およびこれを用いたコンクリート充填方法に関する。 TECHNICAL FIELD The present invention relates to a concrete filling jig used for dropping concrete and a concrete filling method using the same.

CFT(Concrete-Filled Steel Tube:コンクリート充填鋼管)造は、図5(a)に示すように、円形または角形の鋼管11にコンクリート12を充填して形成した柱1に、床スラブ(不図示)等を支持する鉄骨造の梁2などを組み合わせた構造をいう。CFT造では、鋼管11とコンクリート12の相互拘束効果(コンファインド効果)により、鋼構造とコンクリート造の両素材が有する特性以上の相乗効果を発揮する。 CFT (Concrete-Filled Steel Tube) construction, as shown in FIG. It refers to a structure that combines steel frame beams 2 and the like that support etc. In the CFT structure, due to the mutual restraint effect (confined effect) between the steel pipes 11 and the concrete 12, a synergistic effect exceeding the properties of both the steel structure and the concrete structure is exhibited.

柱1と梁2の接合部はパネルゾーン3と呼ばれ、パネルゾーン3では鋼管11内にダイアフラム13(内ダイアフラム)が設けられることが多い。ダイアフラム13は梁2から鋼管11に応力を伝達するための部材であり、図5(b)に示すようにダイアフラム13の中央部にはコンクリート12の充填時にコンクリート12を流通させるためのコンクリート打設孔131が設けられる。一方、ダイアフラム13の四隅付近には空気抜き孔132が設けられる。空気抜き孔132は、パネルゾーン3へのコンクリート12の充填時に空気抜きとして機能し、図5(c)の矢印bに示すように、コンクリート12の充填に伴ってコンクリート12の天端が上昇する際にパネルゾーン3の空気を上に逃がすことで、パネルゾーン3へのコンクリート12の充填性を向上させる。なお図5(c)のパネルゾーン3のダイアフラム13は図5(b)の線a-aによる断面を示したものであり、図5(a)および以下で参照する各図においても、ダイアフラム13については同様の断面が示されている。 A joint portion between the column 1 and the beam 2 is called a panel zone 3, and in the panel zone 3, a diaphragm 13 (inner diaphragm) is often provided inside the steel pipe 11. The diaphragm 13 is a member for transmitting stress from the beam 2 to the steel pipe 11, and as shown in FIG. A hole 131 is provided. On the other hand, air vent holes 132 are provided near the four corners of the diaphragm 13 . The air vent hole 132 functions as an air vent when the concrete 12 is filled into the panel zone 3, and as shown by the arrow b in FIG. By releasing the air in the panel zone 3 upward, the filling property of the concrete 12 into the panel zone 3 is improved. The diaphragm 13 in the panel zone 3 in FIG. 5(c) is a cross section taken along line aa in FIG. 5(b). A similar section is shown for .

CFT造において、鋼管11内にコンクリート12を充填する方法には、圧入工法と落し込み充填工法の2つがある。圧入工法は、コンクリートポンプから延びる配管を鋼管11の下部に設けた圧入口に接続し、この配管を介して鋼管11内にコンクリート12を圧入して充填することで、コンクリート12を上方へと打ち上げてゆくものである。 In CFT construction, there are two methods for filling concrete 12 into steel pipes 11: a press-fitting method and a drop-filling method. In the press-fitting method, a pipe extending from a concrete pump is connected to a pressure port provided at the bottom of the steel pipe 11, and the concrete 12 is pressed into the steel pipe 11 through this pipe to fill the steel pipe 11, thereby pushing the concrete 12 upward. It will continue.

落し込み充填工法は、トレミー管などの充填管を鋼管11の上方から鋼管11内に挿入し、この充填管を用いてコンクリート12を鋼管11内に落し込む方法である。例えばコンクリートホッパーをクレーンから吊り下げて鋼管11の上方に配置し、当該コンクリートホッパーから垂下した充填管を鋼管11内に挿入して、その筒先からコンクリート12を自由落下させる。 The drop filling method is a method in which a filling pipe such as a tremie pipe is inserted into the steel pipe 11 from above and the concrete 12 is dropped into the steel pipe 11 using this filling pipe. For example, a concrete hopper is suspended from a crane and placed above the steel pipe 11, a filling pipe suspended from the concrete hopper is inserted into the steel pipe 11, and the concrete 12 is allowed to fall freely from the pipe tip.

コンクリート12の自由落下高さが大きいと、骨材分離やエア(空気)の巻き込みによる充填不良を引き起こす恐れがあるため、落し込み充填工法ではコンクリート12の自由落下高さを1.0m以内にするよう定められている(新都市ハウジング協会「コンクリート充填鋼管(CFT)造技術基準・同解説」、平成24年8月発行)。この基準を満たすため、充填管の筒先は、コンクリート12の充填開始時には低い位置とし、コンクリート12の充填中はコンクリート12の天端の上昇に応じて引き上げる。 If the free fall height of the concrete 12 is large, there is a risk of insufficient filling due to separation of aggregates and entrainment of air (air). (Shintoshi Housing Association, Concrete Filled Steel Pipe (CFT) Construction Technical Standards and Commentary, published in August 2012). In order to satisfy this standard, the tip of the filling pipe is set at a low position when the filling of the concrete 12 is started, and is lifted as the top of the concrete 12 rises during the filling of the concrete 12 .

コンクリート12の自由落下高さが大きいことは、パネルゾーン3の充填不良を引き起こす原因にもなる。すなわち、コンクリート12の自由落下高さが大きいと、高速で落下したコンクリート12がダイアフラム13に当たって飛び散り、図5(d)に示すようにダイアフラム13の空気抜き孔132を塞いでしまう恐れがある。空気抜き孔132がコンクリート12によって塞がれると、空気抜き孔132が空気抜きとして機能せず、パネルゾーン3の充填不良が生じる恐れがある。 The high free fall height of the concrete 12 also causes poor filling of the panel zone 3 . That is, if the free fall height of the concrete 12 is large, the concrete 12 falling at high speed may scatter against the diaphragm 13 and block the air vent hole 132 of the diaphragm 13 as shown in FIG. 5(d). If the air vent hole 132 is blocked by the concrete 12, the air vent hole 132 will not function as an air vent, and there is a risk that the panel zone 3 will be incompletely filled.

落し込み充填工法には、特許文献1のように、鋼管の側面に設けた開口からフレキシブルホースを鋼管内に挿入し、当該フレキシブルホースの筒先からコンクリートを落し込むものもある。特許文献1では、パネルゾーンの充填不良を防止するため、鋼管内で下方に折れ曲がってダイアフラムの中央部のコンクリート打設孔に連通するエルボ管を用い、このエルボ管にフレキシブルホースを挿入してその筒先からコンクリートを落し込んでいる。 As for the drop filling method, as in Patent Document 1, there is a method in which a flexible hose is inserted into the steel pipe through an opening provided on the side of the steel pipe, and concrete is dropped from the tip of the flexible hose. In Patent Document 1, in order to prevent inadequate filling of the panel zone, an elbow pipe is used that bends downward inside the steel pipe and communicates with the concrete placement hole in the center of the diaphragm. Concrete is dropped from the tip of the pipe.

特開平11-100994号公報JP-A-11-100994

落し込み充填工法において、前記のように鋼管11の上方のコンクリートホッパーからコンクリート12を落し込む場合、コンクリートホッパーを吊り下げるためにクレーンが占有され、コンクリート12の充填中に他のクレーン揚重作業がストップする。また、鋼管11の上方にコンクリートホッパーが配置されるので、コンクリート12の充填中に鋼管11の上方で建方が出来なくなり、工程遅延の原因となる。 In the drop filling method, when the concrete 12 is dropped from the concrete hopper above the steel pipe 11 as described above, the crane is occupied to suspend the concrete hopper, and other crane lifting work is performed while the concrete 12 is being filled. stop. In addition, since the concrete hopper is arranged above the steel pipe 11, construction cannot be performed above the steel pipe 11 while the concrete 12 is being filled, which causes a delay in the process.

特許文献1のように鋼管の側面に形成した開口からフレキシブルホースを挿入してコンクリートの落し込みを行う場合、上記のような工程遅延の問題は無いが、フレキシブルホースの筒先がダイアフラムに引っ掛ったり、フレキシブルホースの引き上げ速度の制御に失敗して筒先がコンクリートの天端に埋もれて引き抜けなくなったり等、各種の不具合が生じ易い。またフレキシブルホースの準備も大変で、その取り扱いも重労働を伴う。 When pouring concrete by inserting a flexible hose from an opening formed on the side of a steel pipe as in Patent Document 1, there is no problem of process delay as described above, but the tip of the flexible hose may get caught on the diaphragm. Also, various troubles such as failure to control the lifting speed of the flexible hose and the tube tip being buried in the top of the concrete and unable to be pulled out are likely to occur. In addition, preparation of the flexible hose is difficult, and its handling is accompanied by heavy labor.

これに対し、フレキシブルホースを使用せずに鋼管の側面の開口から直接コンクリートを落し込むことも考えられるが、この場合、前記した自由落下の問題が生じる。つまり、コンクリートの圧送にはコンクリートポンプが使用されるところ、通常のコンクリートポンプは、2本のシリンダにコンクリートが供給され、これを各々のシリンダが交互に加圧する方法を取る。このため、コンクリートの圧送圧力には脈動が生じ、図5(e)に示すように圧送圧力が高いときにはコンクリート12が鋼管11の内面に当たり、内面伝いに流れ落ちるので自由落下は起きないが、圧送圧力が低いときにはコンクリート12が鋼管11の内面に当たらず、鋼管11内を自由落下する。結果、前記した自由落下高さの基準を守れず、骨材分離やエアの巻き込みによる充填不良の問題が生じる。また前記したように自由落下したコンクリート12がダイアフラム13に当たって飛び散り、空気抜き孔132を塞ぐことによってパネルゾーン3の充填不良が生じる恐れもある。 On the other hand, it is conceivable to drop the concrete directly from the opening in the side of the steel pipe without using the flexible hose, but in this case, the above-mentioned problem of free fall occurs. In other words, while a concrete pump is used for pumping concrete, a conventional concrete pump adopts a method in which concrete is supplied to two cylinders and each cylinder alternately pressurizes the concrete. For this reason, pulsation occurs in the pumping pressure of the concrete, and as shown in FIG. is low, the concrete 12 does not hit the inner surface of the steel pipe 11 and falls freely inside the steel pipe 11. - 特許庁As a result, the above-mentioned free fall height standard cannot be observed, and the problems of aggregate separation and filling failure due to entrainment of air arise. Moreover, as described above, the free-falling concrete 12 hits the diaphragm 13 and scatters, blocking the air vent hole 132 , thereby causing a filling failure in the panel zone 3 .

本発明は上記の問題に鑑みてなされたものであり、コンクリートの落し込み充填を好適に行うことのできるコンクリート充填用治具等を提供することを目的とする。 SUMMARY OF THE INVENTION It is an object of the present invention to provide a concrete filling jig and the like that can suitably drop-fill concrete.

前述した課題を解決するための第1の発明は、隔壁内でコンクリートの落し込み充填を行う際に用いられるコンクリート充填用治具であって、隔壁の開口を通り隔壁内で下方に折れ曲がる、コンクリートを隔壁の開口側の内面に向けて吐出するための管体を有し、前記管体は略円形の径方向断面を有し、前記管体は、隔壁内で略円弧状に下方に折れ曲がってその先端面が前記内面に対向し、前記先端面は、前記管体を径方向に対し傾斜した方向に切取った形となっており、鉛直方向の断面を見た時に、前記管体の折れ曲がり部分の外周側の先端は、前記折れ曲がり部分の内周側の先端よりも前記内面に近い位置にあることを特徴とするコンクリート充填用治具である。 A first invention for solving the above-mentioned problems is a concrete filling jig used when concrete is drop-filled inside a partition wall, the concrete filling jig passing through an opening of the partition wall and bending downward inside the partition wall. toward the inner surface of the opening side of the partition, the tubular body has a substantially circular cross section in the radial direction, and the tubular body is bent downward in a substantially circular arc within the partition The tip surface faces the inner surface, and the tip surface has a shape obtained by cutting the tubular body in a direction inclined with respect to the radial direction. The concrete filling jig is characterized in that the tip of the portion on the outer peripheral side is positioned closer to the inner surface than the tip of the bent portion on the inner peripheral side .

第1の発明のコンクリート充填用治具を用いてコンクリートを鋼管等の隔壁内に落し込むことにより、コンクリートが隔壁の開口に通した管体から隔壁の開口側の内面に向けて吐出され、コンクリートを当該内面に当てて内面伝いに流れ落ちるようにすることが可能になる。これにより、コンクリートの自由落下を防いで落し込み速度を抑えることができ、骨材分離やエアの巻き込みを抑えることができる。また前記のようなパネルゾーンが存在する場合も、コンクリートを内面伝いに低速で落し込むことでパネルゾーンおよびダイアフラムの下面にも密実にコンクリートを充填できる。さらに、コンクリートの充填にあたって鋼管等の上方で行う作業が無いので、他の工程を阻害せず工程遅延を防止でき、フレキシブルホースを用いる必要もないので作業効率の向上に繋がる。これらの効果により、コンクリートの落し込み充填を好適に実施できる。 By dropping concrete into the partition wall such as a steel pipe using the concrete filling jig of the first invention, the concrete is discharged from the tubular body passed through the opening of the partition wall toward the inner surface of the opening side of the partition wall, and the concrete is discharged. can be applied to the inner surface and flow down along the inner surface. As a result, free fall of concrete can be prevented and the drop speed can be suppressed, and separation of aggregates and entrainment of air can be suppressed. Even when such a panel zone exists, the panel zone and the lower surface of the diaphragm can be densely filled with concrete by dropping the concrete along the inner surface at a low speed. Furthermore, since there is no work performed above the steel pipe or the like when filling concrete, it is possible to prevent process delays without interfering with other processes. Due to these effects, drop-filling of concrete can be carried out favorably.

また第1の発明では、前記した管体の詳細形状により、管体から吐出されるコンクリートが、スムーズ且つ確実に隔壁の内面伝いに流れ落ちる。 In the first invention, the detailed shape of the tubular body allows the concrete discharged from the tubular body to smoothly and reliably flow down along the inner surface of the partition wall.

第2の発明は、隔壁内でコンクリートの落し込み充填を行うコンクリート充填方法であって、隔壁の開口を通り隔壁内で下方に折れ曲がる、コンクリートを隔壁の開口側の内面に向けて吐出するための管体を有するコンクリート充填用治具を用い、コンクリートを前記コンクリート充填用治具の管体から隔壁の開口側の内面に向かって吐出させることで、コンクリートが前記内面を伝って流れ落ちることを特徴とするコンクリート充填方法である。 The second invention is a concrete filling method for drop -filling concrete within a partition wall, in which the concrete is bent downward in the partition wall through the opening of the partition wall and is discharged toward the inner surface of the opening side of the partition wall. A concrete filling jig having a tubular body is used, and concrete is discharged from the tubular body of the concrete filling jig toward the inner surface on the opening side of the partition wall, so that the concrete flows down along the inner surface. It is a concrete filling method that

本発明により、コンクリートの落し込み充填を好適に行うことのできるコンクリート充填用治具等を提供することができる。 INDUSTRIAL APPLICABILITY According to the present invention, it is possible to provide a concrete filling jig and the like that can suitably drop-fill concrete.

治具4を用いたコンクリート充填方法について示す図。4A and 4B are diagrams showing a concrete filling method using a jig 4; FIG. 治具4を用いたコンクリート充填方法について示す図。4A and 4B are diagrams showing a concrete filling method using a jig 4; FIG. コンクリート充填試験について説明する図。The figure explaining a concrete filling test. 型枠11a内にコンクリートを充填する例。The example which fills concrete in the formwork 11a. CFT造およびコンクリート12の充填について示す図。The figure which shows CFT structure and filling of the concrete 12. FIG.

以下、図面に基づいて本発明の好適な実施形態について詳細に説明する。 Preferred embodiments of the present invention will be described in detail below with reference to the drawings.

(1.コンクリート充填方法)
図1等を参照し、本発明の実施形態に係るコンクリート充填方法について説明する。なお前記の図5で説明した構成と同様の構成については図等で同じ符号を付し、説明を省略する。
(1. Concrete filling method)
A concrete filling method according to an embodiment of the present invention will be described with reference to FIG. 1 and the like. In the drawings, etc., the same reference numerals are given to the same configurations as those described with reference to FIG. 5, and the description thereof is omitted.

本実施形態のコンクリート充填方法では、CFT造における柱1(図5(a)参照)の形成時に、図1(a)に示す鋼管11内にコンクリートを落し込んで充填する。 In the concrete filling method of the present embodiment, concrete is dropped and filled into the steel pipe 11 shown in FIG.

図1(a)は、鋼管11の下部の圧入口111(111a)から所定のパネルゾーン3(3b)まで圧入工法によってコンクリートを充填する予定であったが、当該パネルゾーン3(3b)の下階のパネルゾーン3(3a)の下方までコンクリート12を充填した時点でトラブルにより圧入を一旦中止し、後日、充填を再開等する際の状態を示している。本実施形態では、充填を再開する際に、コンクリートの落し込み充填を行う。上記のトラブルとしては、例えば圧入用のコンクリートを搬送するアジテータ車の到着遅れ等がある。 In FIG. 1(a), concrete was planned to be filled by the press-in method from the press-fitting hole 111 (111a) at the bottom of the steel pipe 11 to the predetermined panel zone 3 (3b), but below the panel zone 3 (3b) It shows a state when the press-in is temporarily stopped due to trouble when the concrete 12 is filled up to the lower part of the panel zone 3 (3a) of the floor, and the filling is resumed at a later date. In this embodiment, when resuming filling, drop filling of concrete is performed. The above-mentioned troubles include, for example, a delay in the arrival of an agitator vehicle for conveying concrete for press-fitting.

本実施形態では、コンクリートの落し込み充填を行う際に、上下のパネルゾーン3(3a、3b)の間且つ上階のパネルゾーン3bにより近い高さで、鉛直方向の鋼管11(隔壁)の側面に新たに開口112を形成し、この開口112にコンクリート充填用治具4(以下「治具4」という)を取付け、当該治具4を用いてコンクリートの落し込みを行う。 In this embodiment, when performing drop-filling of concrete, at a height between the upper and lower panel zones 3 (3a, 3b) and closer to the upper panel zone 3b, the side of the vertical steel pipe 11 (partition wall) A new opening 112 is formed in the opening 112, a concrete filling jig 4 (hereinafter referred to as "jig 4") is attached to the opening 112, and the jig 4 is used to pour concrete.

図1(a)の例では、上階のパネルゾーン3(3b)の若干上方に、上階でコンクリートの圧入工法を実施するための圧入口111(111b)が設けられており、この圧入口111を利用してコンクリートの落し込みを行うことも考えられる。しかしながら本実施形態では、当該圧入口111の位置が一旦打ち止めたコンクリート天端から高すぎるため、上記のように鋼管11の側面に別途形成した開口112を利用してコンクリートの落し込みを行うものとする。 In the example of FIG. 1(a), a press hole 111 (111b) is provided slightly above the panel zone 3 (3b) on the upper floor for carrying out the concrete press-in method on the upper floor. It is also conceivable to use 111 to drop the concrete. However, in this embodiment, since the position of the injection hole 111 is too high from the top of the concrete once cast, the opening 112 separately formed in the side surface of the steel pipe 11 is used to drop the concrete as described above. do.

図1(b)は治具4の鉛直方向の断面を示す図である。図に示すように、治具4は管体41、取付板42、締結具43等を有する。 FIG. 1(b) is a view showing a cross section of the jig 4 in the vertical direction. As shown in the figure, the jig 4 has a tubular body 41, a mounting plate 42, fasteners 43, and the like.

管体41は、鋼管11の開口112を通って鋼管11内に延びる。管体41は略円形の径方向断面を有し、鋼管11内で下方へと略円弧状に折れ曲がる。ここでの略円形とは、円形に近似した正多角形(例えば正24角形、正48角形など)も含むものとする。管体41の折れ曲がり部分410の先端面411は、鋼管11の開口112側の内面110に対向する。管体41は例えば金属製であるが、これに限らず、樹脂製など、強度や耐久性のある材質ならば何でもよい。 The tubular body 41 extends into the steel pipe 11 through the opening 112 of the steel pipe 11 . The tubular body 41 has a substantially circular cross section in the radial direction and bends downward in a substantially circular arc within the steel pipe 11 . The term “substantially circular” as used herein includes a regular polygon that approximates a circular shape (for example, a regular 24-sided polygon, a regular 48-sided polygon, etc.). A tip surface 411 of the bent portion 410 of the tubular body 41 faces the inner surface 110 of the steel pipe 11 on the opening 112 side. The tubular body 41 is made of metal, for example, but is not limited to this, and may be made of any material having strength and durability, such as resin.

本実施形態のコンクリート充填方法は、後述するように、コンクリートが鋼管11の開口112側の内面110を伝って流れ落ちるようにする、というものである。そのため、管体41はその内部を通るコンクリートを内面110に向けて吐出する。 As will be described later, the concrete filling method of this embodiment is to allow the concrete to flow down along the inner surface 110 of the steel pipe 11 on the side of the opening 112 . Therefore, the tubular body 41 discharges the concrete passing through its interior toward the inner surface 110 .

コンクリートを内面110に向けて吐出するための管体41の形状的特徴としては、管体41の折れ曲がり部分410の外周側の先端414が、折れ曲がり部分410において内面110から最も離れた位置Aよりも内面110側にあるという点、および、折れ曲がり部分410の外周側の先端414が折れ曲がり部分410の内周側の先端413よりも下に位置しているという点がある。これにより管体41の内部を通るコンクリート12を内面110に向けて吐出できる。 As a shape feature of the tubular body 41 for discharging concrete toward the inner surface 110, the tip 414 on the outer peripheral side of the bent portion 410 of the tubular body 41 is positioned farther from the inner surface 110 than the position A in the bent portion 410. There is a point that it is on the inner surface 110 side, and a point that the tip 414 on the outer peripheral side of the bent portion 410 is positioned below the tip 413 on the inner peripheral side of the bent portion 410 . Thereby, the concrete 12 passing through the inside of the tubular body 41 can be discharged toward the inner surface 110 .

このうち後者の点は、言い換えると、折れ曲がり部分410の内周側の先端413から折れ曲がり部分410の外周側の先端414へと延びる線分aと、折れ曲がり部分410の内周側の先端413から内面110の反対側へと水平方向に延びる水平線Hとが、水平線Hの下方において0°を超える180°未満の角度θをなす、ということもできる。なお実際には、上記の角度θは折れ曲がり部分410の外周側の先端414が内面110に当たらないように定められる。 The latter point is, in other words, the line segment a extending from the tip 413 on the inner peripheral side of the bent portion 410 to the tip 414 on the outer peripheral side of the bent portion 410 and the inner surface from the tip 413 on the inner peripheral side of the bent portion 410 . It can also be said that a horizontal line H extending horizontally to the opposite side of 110 forms an angle θ below the horizontal line H that is greater than 0° and less than 180°. Actually, the angle θ is determined so that the tip 414 on the outer peripheral side of the bent portion 410 does not hit the inner surface 110 .

特に図1(b)の例では、角度θを90°を超える値としており、折れ曲がり部分410の外周側の先端414を内周側の先端413よりも内面110に近い位置としている。また、折れ曲がり部分410の先端面411は管体41を径方向Bに対し傾斜した方向に切取った形となっており、先端面411の面積は、管体41の径方向Bの断面の面積よりも大きい。これらの形状的特徴は、コンクリート12がスムーズ且つ確実に内面110を伝って流れ落ちるように定められたものであるが、その詳細については後述する。 In particular, in the example of FIG. 1B, the angle θ exceeds 90°, and the tip 414 on the outer peripheral side of the bent portion 410 is positioned closer to the inner surface 110 than the tip 413 on the inner peripheral side. In addition, the tip surface 411 of the bent portion 410 has a shape obtained by cutting the tubular body 41 in a direction inclined with respect to the radial direction B, and the area of the tip surface 411 is the area of the cross section of the tubular body 41 in the radial direction B. bigger than These geometric features are determined so that the concrete 12 smoothly and reliably flows down along the inner surface 110, the details of which will be described later.

管体41の軸方向の途中には、管体41から外側に張り出すように取付板42が設けられる。鋼管11の開口112の周囲では、鋼管11の外面に補強板113が溶接等により取付けられており、取付板42はボルト等の締結具43により補強板113に締結される。これにより治具4が鋼管11の開口112に着脱可能に取付けられ、その着脱も容易である。 A mounting plate 42 is provided midway in the axial direction of the tubular body 41 so as to protrude outward from the tubular body 41 . Around the opening 112 of the steel pipe 11, a reinforcing plate 113 is attached to the outer surface of the steel pipe 11 by welding or the like, and the mounting plate 42 is fastened to the reinforcing plate 113 with fasteners 43 such as bolts. As a result, the jig 4 is detachably attached to the opening 112 of the steel pipe 11 and can be easily attached and detached.

管体41の折れ曲がり部分410と反対側の端部412にはコンクリートポンプのホース等が接続される。コンクリート12は図示しないポンプにより圧送され、図2(a)、(b)に示すように管体41を通って鋼管11内に吐出される。 A hose of a concrete pump or the like is connected to the end portion 412 of the tubular body 41 opposite to the bent portion 410 . The concrete 12 is pumped by a pump (not shown) and discharged into the steel pipe 11 through the tubular body 41 as shown in FIGS. 2(a) and 2(b).

図2(a)、(b)は、治具4を用いてコンクリート12の落し込みを行っている状態を図1(a)、(b)と同様に示す図である。本実施形態では、治具4を用いてコンクリート12の落し込みを行うことにより、コンクリート12が鋼管11の開口112側の内面110に向かって管体41から吐出され、当該内面110に当たり、当該内面110を伝って流れ落ちる。これによりコンクリート12の自由落下を防ぎ、落し込み速度を抑えて骨材分離やエアの巻き込みによる充填不良を避けることができる。コンクリート12の落し込み速度は、例えば、新都市ハウジング協会「コンクリート充填鋼管(CFT)造技術基準・同解説の運用及び計算例等」(平成29年12月発行)に基づき1.0m/分以下とするが、0.5m/分以下の低速とするとより望ましい。 FIGS. 2(a) and 2(b) are diagrams similar to FIGS. 1(a) and 1(b) showing a state in which the jig 4 is used to drop the concrete 12. FIG. In this embodiment, by dropping the concrete 12 using the jig 4, the concrete 12 is discharged from the tubular body 41 toward the inner surface 110 on the opening 112 side of the steel pipe 11, hits the inner surface 110, and the inner surface It flows down along 110. As a result, the concrete 12 can be prevented from free falling, and the drop speed can be suppressed to avoid aggregate separation and poor filling due to entrainment of air. For example, the drop speed of concrete 12 is 1.0 m/min or less based on the New City Housing Association "Technical Standards for Concrete Filled Steel Pipe (CFT) Construction, Operation and Calculation Examples of the Commentary" (published in December 2017). However, a low speed of 0.5m/min or less is more desirable.

上記のようなコンクリート12の落し込み充填は、前記した管体41の形状的特徴により実現されている。すなわち、前記したように、管体41の折れ曲がり部分410の外周側の先端414が、折れ曲がり部分410において内面110から最も離れた位置Aよりも内面110側にあり、且つ折れ曲がり部分410の外周側の先端414が内周側の先端413よりも下に位置していることで、管体41から内面110に向けてコンクリート12を吐出させることができる。 Drop-filling of the concrete 12 as described above is realized by the shape characteristics of the tubular body 41 described above. That is, as described above, the tip 414 on the outer peripheral side of the bent portion 410 of the tubular body 41 is closer to the inner surface 110 than the position A farthest from the inner surface 110 in the bent portion 410, and is located on the outer peripheral side of the bent portion 410. Since the tip 414 is positioned below the tip 413 on the inner peripheral side, the concrete 12 can be discharged from the tubular body 41 toward the inner surface 110 .

これに対し、例えば折れ曲がり部分410の先端面が図2(b)の仮想線Cに示すように形成され、折れ曲がり部分410の外周側の先端が折れ曲がり部分410において内面110から最も離れた位置Aとなっていると、コンクリート12が内面110に向けて吐出されず自由落下してしまう。また、折れ曲がり部分410の先端面が図2(b)の仮想線Dに示すように水平方向に形成され、折れ曲がり部分410の内周側と外周側の先端の高さが同じである場合も、コンクリート12が真下に自由落下し、内面110に向けて吐出できない。 On the other hand, for example, the tip surface of the bent portion 410 is formed as indicated by the imaginary line C in FIG. If this is the case, the concrete 12 will not be discharged toward the inner surface 110 and will fall freely. Also, when the tip surface of the bent portion 410 is formed in the horizontal direction as indicated by the virtual line D in FIG. Concrete 12 freely falls directly below and cannot be discharged toward inner surface 110 .

さらに本実施形態では、管体41の折れ曲がり部分410の外周側の先端414を前記したように内面110に近付けて配置することで、管体41から吐出されたコンクリート12が確実に内面110に当たり、内面伝いに流れ落ちる。これに対し、先端414の位置が内面110から遠すぎると、管体41から吐出されたコンクリート12が内面110に当たらず、自由落下になってしまう。 Furthermore, in the present embodiment, by arranging the tip 414 on the outer peripheral side of the bent portion 410 of the tubular body 41 close to the inner surface 110 as described above, the concrete 12 discharged from the tubular body 41 reliably hits the inner surface 110, It flows down along the inside. On the other hand, if the position of the tip 414 is too far from the inner surface 110, the concrete 12 discharged from the tubular body 41 does not hit the inner surface 110 and falls freely.

また本実施形態では、管体41の折れ曲がり部分410の先端面411が、前記したように管体41を径方向に対し傾斜した方向に切取った形となっており、先端面411の面積は管体41の径方向断面の面積より大きい。そのためコンクリート12の圧送圧力を先端面411付近で弱めることができる。また、折れ曲がり部分410の内周側の先端413の位置が内面110から一定距離離れているので、先端413付近を出たコンクリート12の圧送圧力は、コンクリート12が内面110に当たるまでの間に開放される。結果、コンクリート12は内面110に向かって斜め下方に吐出されスムーズに流れ落ちる(図2(b)の矢印E参照)。 Further, in this embodiment, the tip surface 411 of the bent portion 410 of the tubular body 41 has a shape obtained by cutting the tubular body 41 in a direction inclined with respect to the radial direction as described above, and the area of the tip surface 411 is It is larger than the area of the radial cross section of the tubular body 41 . As a result, the pressure for pumping the concrete 12 can be weakened in the vicinity of the tip surface 411 . In addition, since the tip 413 on the inner peripheral side of the bent portion 410 is separated from the inner surface 110 by a certain distance, the pumping pressure of the concrete 12 coming out near the tip 413 is released until the concrete 12 hits the inner surface 110 . be. As a result, the concrete 12 is discharged obliquely downward toward the inner surface 110 and smoothly flows down (see arrow E in FIG. 2(b)).

このように、本実施形態では管体41の形状的工夫によりコンクリート12が鋼管11の開口112側の内面110に向かって吐出され、内面伝いにスムーズ且つ確実に流れ落ちる。なお本実施形態では管体41の折れ曲がり部分410の曲げ径も適切に定められており、これにより開口112に通しての挿入を容易に行えるようにしている。 Thus, in the present embodiment, the concrete 12 is discharged toward the inner surface 110 on the opening 112 side of the steel pipe 11 by devising the shape of the tubular body 41, and smoothly and reliably flows down along the inner surface. In this embodiment, the bending diameter of the bent portion 410 of the tubular body 41 is also appropriately determined so that insertion through the opening 112 can be easily performed.

図2(c)は、パネルゾーン3aにおけるコンクリート12の落下状況を示す図である。本実施形態では、前記のようにコンクリート12が鋼管11の内面伝いに低速で流れ落ちることで、パネルゾーン3の充填不良も防止できる。 FIG. 2(c) is a diagram showing how the concrete 12 falls in the panel zone 3a. In the present embodiment, as described above, the concrete 12 flows down along the inner surface of the steel pipe 11 at a low speed, thereby preventing insufficient filling of the panel zone 3 .

すなわち、コンクリート12の落し込み速度を緩やかにすることで、図2(c)に示すように、コンクリート12がダイアフラム13の治具4側(図の左側に対応する)の空気抜き孔132をスムーズに落下し、コンクリート打設孔131と空気抜き孔132を落下するコンクリート12により、ダイアフラム13の下ではコンクリート12の天端に治具4の反対側(図の右側に対応する)に向かって下降する勾配がつく。 That is, by slowing down the dropping speed of the concrete 12, as shown in FIG. Due to the falling concrete 12 falling through the concrete placing hole 131 and the air vent hole 132, the top edge of the concrete 12 under the diaphragm 13 has a downward gradient toward the opposite side of the jig 4 (corresponding to the right side in the figure). comes.

コンクリート12の充填により、コンクリート12の天端は上記勾配を保ったまま上昇し、天端の上昇に伴ってダイアフラム13の下方の治具4側の空気は矢印Fに示すように治具4の反対側へと逃げ、治具4の反対側の空気抜き孔132等から上方へとスムーズに抜ける。またコンクリート12は鋼管11の内面を低速で伝い落ちるので、コンクリート12がダイアフラム13に当たって飛散し治具4の反対側の空気抜き孔132を塞ぐこともない。そのため、パネルゾーン3に密実にコンクリート12が充填される。 As the concrete 12 is filled, the top of the concrete 12 rises while maintaining the above gradient. It escapes to the opposite side and smoothly escapes upward from the air vent hole 132 or the like on the opposite side of the jig 4.例文帳に追加Further, since the concrete 12 runs down the inner surface of the steel pipe 11 at a low speed, the concrete 12 does not hit the diaphragm 13 and scatter to block the air vent hole 132 on the opposite side of the jig 4.例文帳に追加Therefore, the panel zone 3 is densely filled with the concrete 12 .

なお、スランプフローの大きな流動性の高いコンクリートの場合、図2(d)に示すように充填されたコンクリート12の天端がほぼ水平のまま上昇してダイアフラム13を通過することも考えられる。この場合、コンクリート12は十分軟かく、ダイアフラム13の治具4側の空気抜き孔132を淀みなく流れ落ち、治具4の反対側の空気抜き孔132だけでなく治具4側の空気抜き孔132も空気抜きとして機能する(図の矢印F参照)。従ってこの場合もパネルゾーン3でコンクリート12の充填が不十分になることはない。 In the case of concrete with a large slump flow and high fluidity, it is conceivable that the top of the filled concrete 12 rises almost horizontally and passes through the diaphragm 13 as shown in FIG. 2(d). In this case, the concrete 12 is sufficiently soft and flows smoothly down the air vent hole 132 on the jig 4 side of the diaphragm 13, and the air vent hole 132 on the jig 4 side as well as the air vent hole 132 on the opposite side of the jig 4 serves as an air vent. It works (see arrow F in the figure). Therefore, in this case as well, the filling of the concrete 12 in the panel zone 3 is not insufficient.

(2.治具4の効果)
本発明者は、以上のような治具4の効果について確認するためコンクリート充填試験を行ったので、以下その説明を行う。
(2. Effect of Jig 4)
The present inventor conducted a concrete filling test in order to confirm the effect of the jig 4 as described above, which will be described below.

図3(a)は試験対象のコンクリート充填方法を示す図である。図3(a)の(イ)(ロ)は比較例であり、(イ)はフレキシブルホース5を鋼管11の上方から鋼管11内に挿入し、コンクリートの自由落下高さを1mに維持しつつコンクリートを落し込む例、(ロ)はポンプ圧送したコンクリートを鋼管11の側面の開口112から治具4を使用せずに落し込む例である。(ハ)は本発明の治具4を用いた実施例であり、ポンプ圧送したコンクリートを治具4を用いて鋼管11の内面伝いに落し込む。ただし、治具4については、前記した角度θ(図1(b)参照)が若干小さく、45°程度である。 FIG. 3(a) is a diagram showing a concrete filling method to be tested. (A) and (B) of FIG. 3(a) are comparative examples. In (a), the flexible hose 5 is inserted into the steel pipe 11 from above, and the free fall height of the concrete is maintained at 1 m. An example of dropping concrete, (b) is an example of dropping the pumped concrete from the opening 112 on the side of the steel pipe 11 without using the jig 4 . (C) is an embodiment using the jig 4 of the present invention, in which the pumped concrete is dropped along the inner surface of the steel pipe 11 using the jig 4 . However, the jig 4 has a slightly smaller angle .theta. (see FIG. 1(b)), which is about 45 degrees.

鋼管11は1辺600mmの角形鋼管であり、落し込むコンクリートの水セメント比は30.0重量%、細骨材率は48.0体積%、呼び強度は67N/mm2とした。なお、呼び強度とは、設計基準強度Fcに耐久設計基準強度Fdや構造体強度補正値mSnを考慮して、調合管理強度Fmを定め、JIS規格を考慮して決定した発注強度のことである。コンクリートのフレッシュ性状は、スランプフローが66.5~68.0cmで、材料分離がなく良好であった。 The steel pipe 11 is a rectangular steel pipe of 600 mm on a side, and the water-cement ratio of the dropped concrete is 30.0% by weight, the fine aggregate ratio is 48.0% by volume, and the nominal strength is 67 N/mm 2 . In addition, the nominal strength is the ordered strength determined by considering the durability design strength Fd and the structure strength correction value mSn in the design strength Fc, determining the mixing control strength Fm, and considering the JIS standard. . The freshness of the concrete was good with a slump flow of 66.5-68.0 cm and no material separation.

図3(b)は、(イ)(ハ)の方法でコンクリートの充填を行った際のパネルゾーン3のコンクリート充填状況を示す図であり、ダイアフラム13の下面とコンクリート表面との間に気泡等により距離が生じている部分の分布をグレーで示したものである。なお図中の点線はコンクリート打設孔131の位置を示したものである。 FIG. 3(b) is a diagram showing the state of concrete filling in the panel zone 3 when the concrete is filled by the methods (a) and (c). The distribution of the part where the distance is generated by is shown in gray. A dotted line in the drawing indicates the position of the concrete placement hole 131 .

図3(b)に示すように、治具4を用いて鋼管11の内面伝いに落し込みを行う(ハ)の場合、上記部分の面積がかなり少なく、(イ)のフレキシブルホース5を用いて充填を行う場合よりもコンクリートを密実に充填できていることがわかる。なお(ロ)の場合、ダイアフラム13の下面における上記部分の面積は(イ)と同程度であった。 As shown in FIG. 3(b), in the case of (c) in which the jig 4 is used to drop along the inner surface of the steel pipe 11, the area of the above portion is considerably small, and the flexible hose 5 of (a) is used. It can be seen that the concrete can be filled more densely than in the case of filling. In the case of (b), the area of the above portion on the lower surface of the diaphragm 13 was approximately the same as in the case of (a).

図3(c)は、(イ)(ロ)(ハ)の方法で充填したコンクリート(材齢91日)をダイアフラム13の下で採取し、その圧縮強度を比較したものである。コンクリートは、ダイアフラム13の中央部のコンクリート打設孔131の近傍(図3(c)において「中央部」と表記)と、ダイアフラム13の四隅付近の空気抜き孔132の近傍(図3(c)において「四隅付近」と表記)で各複数個採取し、圧縮強度はそれらの平均値とした。 FIG. 3(c) compares the compressive strengths of the concrete (91 days old) filled by the methods (a), (b) and (c), sampled under the diaphragm 13 . Concrete is placed near the concrete placement hole 131 in the central portion of the diaphragm 13 (denoted as “central portion” in FIG. 3(c)) and near the air vent holes 132 near the four corners of the diaphragm 13 (in FIG. 3(c) A plurality of specimens were sampled at each of the four corners (denoted as "near the four corners"), and the compressive strength was taken as the average value thereof.

図3(c)に示すように、(イ)(ロ)(ハ)の各ケースにおいて、ダイアフラム13の中央部および四隅付近のコンクリートの圧縮強度は85~95N/mm2となっており、呼び強度67N/mm2を上回ったが、特に治具4を用いて鋼管11の内面伝いに落し込みを行う(ハ)のケースでは、骨材分離の防止やエアの巻き込み防止が高いレベルで実現されたことにより、(イ)や(ロ)のケースよりも良好な強度発現を示していた。 As shown in FIG. 3(c), in each of cases (a), (b), and (c), the compressive strength of the concrete near the center and four corners of the diaphragm 13 is 85 to 95 N/mm 2 , and the nominal Although the strength exceeded 67 N/mm 2 , especially in the case of (C) in which jig 4 is used to drop along the inner surface of steel pipe 11, prevention of aggregate separation and prevention of entrainment of air was achieved at a high level. Therefore, better strength development was shown than in the cases (a) and (b).

以上説明したように、本実施形態では、治具4を用いてコンクリート12を鋼管11内に落し込むことにより、コンクリート12が鋼管11の開口112に通した管体41から鋼管11の開口112側の内面110に向けて吐出され、コンクリート12を内面110に当てて内面伝いに流れ落ちるようにすることが可能になる。これにより、コンクリート12の自由落下を防いで落し込み速度を抑えることができ、骨材分離やエアの巻き込みを抑えることができる。またコンクリート12を内面伝いに低速で落し込むことで、前記したパネルゾーン3およびダイアフラム13の下面にもコンクリート12を密実に充填できる。さらに、コンクリート12の充填にあたって鋼管11の上方で行う作業が無いので、他の工程を阻害せず工程遅延を防止でき、フレキシブルホースを用いる必要もないので作業効率の向上に繋がる。これらの効果により、コンクリート12の落し込み充填を好適に実施できる。 As described above, in the present embodiment, by dropping the concrete 12 into the steel pipe 11 using the jig 4, the concrete 12 moves from the tubular body 41 passed through the opening 112 of the steel pipe 11 to the opening 112 side of the steel pipe 11. It is possible for the concrete 12 to hit the inner surface 110 and run down along the inner surface. As a result, free fall of the concrete 12 can be prevented, and the falling speed can be suppressed, and aggregate separation and entrainment of air can be suppressed. Further, by dropping the concrete 12 along the inner surface at a low speed, the panel zone 3 and the lower surface of the diaphragm 13 can also be densely filled with the concrete 12 . Furthermore, since there is no work performed above the steel pipe 11 when filling the concrete 12, it is possible to prevent delays in the process without interfering with other processes. Due to these effects, drop-filling of the concrete 12 can be carried out favorably.

さらに、図1(b)等で説明した治具4では、管体41の折れ曲がり部分410の先端面411を、管体41を径方向に対し傾斜した方向に切取った形とし、折れ曲がり部分410の外周側の先端414を内面110に近付け、内周側の先端413を内面110から遠ざけて配置している。これにより、管体41から吐出されるコンクリート12が、前記したようにスムーズ且つ確実に鋼管11の内面伝いに流れ落ちる。 Furthermore, in the jig 4 described with reference to FIG. The tip 414 on the outer peripheral side of is arranged close to the inner surface 110 , and the tip 413 on the inner peripheral side is arranged away from the inner surface 110 . As a result, the concrete 12 discharged from the tubular body 41 smoothly and reliably flows down along the inner surface of the steel pipe 11 as described above.

しかしながら、本発明は上記の実施形態に限らない。例えば本実施形態ではコンクリート12の圧入の中止後にコンクリート12の落し込み充填を行う例を説明したが、コンクリート12の落し込み充填を行う状況はこれに限らず、最初から落し込みによるコンクリート12の充填を行う場合もある。 However, the invention is not limited to the above embodiments. For example, in the present embodiment, an example in which drop-filling of the concrete 12 is performed after stopping the press-fitting of the concrete 12 has been described. may be performed.

また管体41の形状も、当該管体41から鋼管11の開口112側の内面110に向けてコンクリート12を吐出できれば良く、上記の実施形態に特に限定されるものではない。 Also, the shape of the tubular body 41 is not particularly limited to the above embodiment as long as the concrete 12 can be discharged from the tubular body 41 toward the inner surface 110 of the steel pipe 11 on the opening 112 side.

さらに、本実施形態では、鋼管11に取付けた治具4を用いて鋼管11内にコンクリート12を落し込み、CFT造における柱1を形成する例を説明したが、治具4はコンクリート12の充填空間を区画する隔壁に取付けられればよく、本実施形態の鋼管11の他、図4に示すように鉛直方向の型枠11a(隔壁)に取付けて型枠11a内のコンクリート12の充填に用いることも可能である。また治具4は柱だけでなく壁等の形成時にも利用可能である。 Furthermore, in the present embodiment, the concrete 12 is dropped into the steel pipe 11 using the jig 4 attached to the steel pipe 11 to form the column 1 in the CFT structure. It may be attached to the partition wall that divides the space, and in addition to the steel pipe 11 of this embodiment, it may be attached to the vertical formwork 11a (partition wall) as shown in FIG. 4 and used to fill the concrete 12 in the formwork 11a. is also possible. Moreover, the jig 4 can be used not only for forming pillars but also for forming walls and the like.

以上、添付図面を参照して、本発明の好適な実施形態について説明したが、本発明は係る例に限定されない。当業者であれば、本願で開示した技術的思想の範疇内において、各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。 Although the preferred embodiments of the present invention have been described above with reference to the accompanying drawings, the present invention is not limited to such examples. It is obvious that a person skilled in the art can conceive of various modifications or modifications within the scope of the technical ideas disclosed in the present application, and these also belong to the technical scope of the present invention. Understood.

1:柱
2:梁
3、3a、3b:パネルゾーン
4:コンクリート充填用治具
5:フレキシブルホース
11:鋼管
11a:型枠
12:コンクリート
13:ダイアフラム
41:管体
42:取付板
43:締結具
1: Column 2: Beams 3, 3a, 3b: Panel zone 4: Concrete filling jig 5: Flexible hose 11: Steel pipe 11a: Formwork 12: Concrete 13: Diaphragm 41: Pipe body 42: Mounting plate 43: Fastener

Claims (2)

隔壁内でコンクリートの落し込み充填を行う際に用いられるコンクリート充填用治具であって、
隔壁の開口を通り隔壁内で下方に折れ曲がる、コンクリートを隔壁の開口側の内面に向けて吐出するための管体を有し、
前記管体は略円形の径方向断面を有し、
前記管体は、隔壁内で略円弧状に下方に折れ曲がってその先端面が前記内面に対向し、
前記先端面は、前記管体を径方向に対し傾斜した方向に切取った形となっており、
鉛直方向の断面を見た時に、前記管体の折れ曲がり部分の外周側の先端は、前記折れ曲がり部分の内周側の先端よりも前記内面に近い位置にあることを特徴とするコンクリート充填用治具。
A concrete filling jig used for drop-filling concrete in a partition wall,
having a tubular body that passes through the opening of the partition wall and bends downward within the partition wall for discharging concrete toward the inner surface of the opening side of the partition wall;
the tubular body has a substantially circular radial cross-section,
the tubular body is bent downward in a substantially circular arc within the partition wall, and the tip surface thereof faces the inner surface;
The tip surface has a shape obtained by cutting the tubular body in a direction inclined with respect to the radial direction,
A jig for concrete filling, characterized in that, when viewed in a vertical cross-section, the tip of the bent portion on the outer peripheral side of the tubular body is positioned closer to the inner surface than the tip of the bent portion on the inner peripheral side. .
隔壁内でコンクリートの落し込み充填を行うコンクリート充填方法であって、
隔壁の開口を通り隔壁内で下方に折れ曲がる、コンクリートを隔壁の開口側の内面に向けて吐出するための管体を有するコンクリート充填用治具を用い、コンクリートを前記コンクリート充填用治具の管体から隔壁の開口側の内面に向かって吐出させることで、コンクリートが前記内面を伝って流れ落ちることを特徴とするコンクリート充填方法。
A concrete filling method for drop-filling concrete in a partition wall,
A concrete filling jig having a tubular body that passes through the opening of the partition wall and bends downward within the partition wall for discharging concrete toward the inner surface of the opening side of the partition wall is used, and the concrete is poured into the tubular body of the concrete filling jig . 1. A concrete filling method, characterized in that the concrete flows down along the inner surface of the partition wall by discharging the concrete toward the inner surface on the opening side of the partition wall.
JP2019129206A 2019-07-11 2019-07-11 Concrete filling jig, concrete filling method Active JP7248528B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019129206A JP7248528B2 (en) 2019-07-11 2019-07-11 Concrete filling jig, concrete filling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019129206A JP7248528B2 (en) 2019-07-11 2019-07-11 Concrete filling jig, concrete filling method

Publications (2)

Publication Number Publication Date
JP2021014710A JP2021014710A (en) 2021-02-12
JP7248528B2 true JP7248528B2 (en) 2023-03-29

Family

ID=74530358

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019129206A Active JP7248528B2 (en) 2019-07-11 2019-07-11 Concrete filling jig, concrete filling method

Country Status (1)

Country Link
JP (1) JP7248528B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114233002A (en) * 2021-12-09 2022-03-25 北京城建集团有限责任公司 High-throwing method for steel pipe column concrete

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3011241U (en) 1994-11-17 1995-05-23 ▲高▼松建設株式会社 Tip nozzle of concrete pumping hose

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6278359A (en) * 1985-09-30 1987-04-10 清水建設株式会社 Method and apparatus for vertically casting concrete
JPS6466367A (en) * 1987-09-04 1989-03-13 Fujita Corp Method of placing concrete
JPH07150764A (en) * 1993-11-30 1995-06-13 Maeda Corp Tube for placing concrete

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3011241U (en) 1994-11-17 1995-05-23 ▲高▼松建設株式会社 Tip nozzle of concrete pumping hose

Also Published As

Publication number Publication date
JP2021014710A (en) 2021-02-12

Similar Documents

Publication Publication Date Title
JP7248528B2 (en) Concrete filling jig, concrete filling method
CN108149709A (en) Underground pipe gallery precast assembly construction method
CN106382009A (en) Fixing device for fixing pump pipes during downward ultra-deep composite pumping of concrete
JP5806161B2 (en) How to place concrete
US9233795B2 (en) Concrete wall chute
JP2008088691A (en) Tunnel lining form and tunnel lining construction method
CN109854285A (en) A kind of depth vertical supporting construction and construction method
JP5334548B2 (en) Filling method for the base plate of the base isolation device
KR20210016759A (en) Embedded pipes for columns
CN112854764A (en) Concrete pouring construction structure in steel pipe column and construction method
JPH11100994A (en) Concrete casting induction pipe for steel pipe concrete column
CN114227900A (en) Prefabricating method of reinforcement cage for long spiral drilling pressure-grouting pile
CN208039845U (en) A kind of vertical blanking device of new concrete
JP2724329B2 (en) Deck plate for slab formwork
JP7153587B2 (en) Concrete Filled Steel Pipe Column Construction Method
JP2016169486A (en) Bucket for stiff-consistency concrete, and concrete casting method
JP2002220924A (en) Head nozzle for concrete transport pipe
JP2010127035A (en) Method and device for infilling filler into lower portion of base plate of base-isolating device
JP5462540B2 (en) Filling equipment
CN217734030U (en) Grouting device for PHC pipe pile
CN105178510B (en) Huge combination column with section steel and concrete structure and its construction method
CN216740733U (en) High-low combined concrete pouring device for square tube with super-large long and large cross section
KR200187717Y1 (en) Supporting roller for feeding pipe of concrete
CN211923554U (en) Pouring structure of steel reinforced concrete column
CN213204993U (en) Divide material system suitable for concrete unloading

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220228

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20221226

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230104

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230207

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230314

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230316

R150 Certificate of patent or registration of utility model

Ref document number: 7248528

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150