JP6501535B2 - Method and apparatus for diagnosing power generation status of photovoltaic system - Google Patents

Method and apparatus for diagnosing power generation status of photovoltaic system Download PDF

Info

Publication number
JP6501535B2
JP6501535B2 JP2015016461A JP2015016461A JP6501535B2 JP 6501535 B2 JP6501535 B2 JP 6501535B2 JP 2015016461 A JP2015016461 A JP 2015016461A JP 2015016461 A JP2015016461 A JP 2015016461A JP 6501535 B2 JP6501535 B2 JP 6501535B2
Authority
JP
Japan
Prior art keywords
string
time zone
value
current value
power generation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015016461A
Other languages
Japanese (ja)
Other versions
JP2016144244A (en
Inventor
純弥 菅野
純弥 菅野
佐藤 信之
信之 佐藤
真理 長坂
真理 長坂
佐藤 誠
佐藤  誠
中村 浩
浩 中村
中島 栄一
栄一 中島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Inc
Toshiba Energy Systems and Solutions Corp
Original Assignee
Tokyo Electric Power Co Inc
Toshiba Energy Systems and Solutions Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc, Toshiba Energy Systems and Solutions Corp filed Critical Tokyo Electric Power Co Inc
Priority to JP2015016461A priority Critical patent/JP6501535B2/en
Publication of JP2016144244A publication Critical patent/JP2016144244A/en
Application granted granted Critical
Publication of JP6501535B2 publication Critical patent/JP6501535B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Photovoltaic Devices (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Description

この発明は、太陽光発電システムの分岐計測を用いた発電状況診断方法及びその装置に関するもので、ストリング単位で太陽電池パネルの故障による性能劣化をできるだけ早く且つ確実に検出できる診断方法及びその装置を提供するものである。 The present invention relates to a method and apparatus for diagnosing a power generation state using branch measurement of a photovoltaic system, and a diagnostic method and apparatus capable of reliably detecting performance deterioration due to a failure of a solar cell panel in string units as quickly as possible. It is provided.

当該太陽光発電システムの構成は、図4に示すように、太陽電池パネル1を十数枚〜20枚程度(但し、図では概略枚数を表す)を直列に接続した1個の分岐回路を1つのストリング2としてこれを複数個用意し、当該複数個のストリング2をそれぞれ接続箱3を介して集電箱4に集約し、パワーコンディショナ5でDC/AC変換等を行い、連系変圧器6を介して発電電力を電力系統に供給している。 The configuration of the solar power generation system is, as shown in FIG. 4, one branch circuit in which about ten to twenty solar cell panels 1 (however, in the figure, the approximate number is shown) are connected in series. A plurality of strings 2 are prepared as one string 2, and the plurality of strings 2 are respectively integrated into a current collection box 4 via a junction box 3, and a power conditioner 5 performs DC / AC conversion etc. The generated power is supplied to the power system through 6.

前記太陽光発電システムの発電電力は、日射量と太陽電池温度から推定可能であるが、例えば、メガワットクラスの太陽光発電所で、1枚の太陽電池パネル1が故障した場合の発電電力の低下は単純計算でも約0.025%となり、発電所全体の発電電力からの検出はほぼ不可能に近い。これは、1枚の太陽電池パネル1につき250W程度の発電能力のため上記メガワットクラスの太陽光発電所となると、最低4000枚の太陽電池パネル1が使用される。このように1枚の太陽電池パネル1の発電電圧が低いことから、当該1枚の太陽電池パネル1の故障による発電所全体の発電電力の低下は極めて低く、検出できない。 The power generated by the solar power generation system can be estimated from the amount of solar radiation and the temperature of the solar cell, but, for example, a decrease in the generated power when one solar cell panel 1 breaks down in a megawatt class solar power plant Is about 0.025% even in simple calculations, and detection from the power generated by the entire power plant is nearly impossible. In the case of the above-mentioned megawatt class solar power plant because of the power generation capacity of about 250 W per one solar cell panel, at least 4,000 solar cell panels 1 are used. As described above, since the generated voltage of one solar cell panel 1 is low, the decrease in the generated power of the entire power plant due to the failure of the one solar cell panel 1 is extremely low and can not be detected.

そこで、昨今では、上記複数枚の太陽電池パネル1を直列接続したストリング2毎に計測を行うシステム(ストリングモニタ)を設置し、部分的な故障によるわずかな発電量の低下の検出が試みられている。このストリングモニタでは、各ストリング2を流れる電流は、同一時刻、同一気象条件であればほぼ同じ値になるため、他のストリング2と比較して電流値の少ないストリング2があれば、そのストリング2を構成する太陽電池パネル1が故障している可能性があると判断できる。 Therefore, in recent years, a system (string monitor) that measures each string 2 in which the plurality of solar cell panels 1 are connected in series is installed, and detection of a slight decrease in power generation due to a partial failure is attempted. There is. In this string monitor, the current flowing through each string 2 has almost the same value at the same time and under the same weather conditions. Therefore, if there is a string 2 whose current value is smaller than that of the other strings 2, that string 2 It can be determined that there is a possibility that the solar cell panel 1 that constitutes the

図5に、接続箱3内のストリング2を流れる電流及び分岐計測のイメージを示す。接続箱3に内蔵された計測システム(図示省略)により、各ストリング2の電流が計測される。 FIG. 5 shows an image of the current flowing through the string 2 in the junction box 3 and the measurement of the bifurcation. The current of each string 2 is measured by a measurement system (not shown) built in the connection box 3.

そして、太陽電池パネル1の一つが故障すると、その分だけ発電量が低下し、ストリング2の発電量が小さくなる。ところが、太陽光発電システムにおける発電量は、日射量によっても大きく変化するため、発電量が低下したとしても、太陽電池の故障による発電量の低下なのか、日射量の低下による発電量の低下なのか、判断は容易ではない。 Then, when one of the solar cell panels 1 fails, the amount of power generation decreases by that amount, and the amount of power generation of the string 2 decreases. However, since the amount of power generation in the solar power generation system largely changes depending on the amount of solar radiation, even if the amount of power generation is reduced, the amount of power generation is reduced due to the decrease in solar radiation Judgment is not easy.

これを解決するための技術として、特許文献1に示すように、太陽電池パネルの設置角度、設置場所の緯度、経度、設置方位、設置された地域における季節的な要因による平均の日射量などをパラメータとして予め設定することによって予測発電量を求め、この予測発電量を基準として故障を警報するシステムが開発されている。 As a technique for solving this, as shown in Patent Document 1, the installation angle of the solar cell panel, the latitude and longitude of the installation place, the installation direction, the average amount of solar radiation due to seasonal factors in the installed area, etc. A system has been developed which determines a predicted power generation amount by setting in advance as a parameter, and warns of failure based on this predicted power generation amount.

特開2006−67738号公報Unexamined-Japanese-Patent No. 2006-67738

しかしながら、特許文献1に記載されているように平均の日射量などを固定的なパラメータとして与える方法では、現実問題として、予測発電量を求めることは不可能に近い。日射量が比較的大きくなる晴天時においては良いが、日射量が比較的小さな曇天時には、発電量の予測は困難となる。結果として、例えば梅雨時など長期間にわたって曇天が続くような場合は、その期間に積算される予測発電量は、実際の発電量から大きく外れてしまうおそれがある。また、特許文献1に記載の技術では、定性的な警告表示を行うにとどまり、故障診断としては不十分である。 However, as described in Patent Document 1, it is almost impossible to determine the predicted power generation amount as a practical matter by the method of giving the average amount of solar radiation or the like as a fixed parameter. Although it is good in fine weather where the amount of solar radiation is relatively large, it is difficult to predict the amount of power generation in cloudy weather where the amount of solar radiation is relatively small. As a result, when cloudy weather continues for a long period of time, for example, during the rainy season, the predicted power generation amount integrated in that period may be greatly deviated from the actual power generation amount. Further, the technique described in Patent Document 1 only performs qualitative warning display, and is insufficient for failure diagnosis.

また一方、前記図5に示すように、各ストリング2の電流計測による電力量の低下を観察し、低下が検出された場合に当該ストリング2の太陽電池パネル1の故障と判断する際、直流電流の測定には以下の問題があり、計測誤差が発生し易い。まず、直流電流は変化がない(0Hz)ため、電流値のゼロ調整をしないと、計測誤差が発生し易い。また、分岐数が多く、電流値のゼロ調整など、オフセット調整機能を具備した計測システムは通常導入していないのが現状である。 On the other hand, as shown in FIG. 5, when a drop in the amount of power due to current measurement of each string 2 is observed, and a drop is detected, it is determined that the solar cell panel 1 of the string 2 is defective. There are the following problems in the measurement of, and measurement errors are likely to occur. First, since the direct current does not change (0 Hz), a measurement error is likely to occur unless the current value is adjusted to zero. Also, at present, a measurement system having an offset adjustment function such as a large number of branches and zero adjustment of current values is not usually introduced.

また、各ストリング2を構成する太陽電池1パネルには個々に性能差があるため、気象条件が同じであっても電流値が等しいとは限らない。図6は、8個のストリング2ごとの計測誤差及び性能差による電流差の例をしめす。同時刻であっても、あるストリング2では8.3A、最低値のストリングでは7.8Aと約0.5Aも異なり、測定値は各ストリングによってバラバラである。 In addition, since the solar cell 1 panels constituting each string 2 have individual performance differences, the current values are not necessarily equal even if the weather conditions are the same. FIG. 6 shows an example of current difference due to measurement error and performance difference for eight strings 2. Even at the same time, there is also a difference of 8.3 A for a certain string 2 and 7.8 A and about 0.5 A for the lowest value string, and the measured values are different for each string.

また、面的な広がりの大きいメガソーラでは、一部のパネルに影がかかるようなレイアウトになっているケースもあり、故障が無くても一時的に発電量が低下することがある。また、点検等のため一部のストリング2の運転を停止した、いわゆる作業停止(以下、単に「作業停止」という)の場合も故障が無いにも関わらず発電量が低下することとなる。この部分影、作業停止による発電量の低下は誤検出の原因となる。 In addition, in the case of a megasolar having a large surface area, there is a case where the layout is such that some panels are shaded, and even if there is no failure, the amount of power generation may be temporarily reduced. Further, in the case of so-called operation stop (hereinafter simply referred to as “operation stop”) in which the operation of a part of the strings 2 is stopped for inspection or the like, the power generation amount is reduced even though there is no failure. The partial shadow and the decrease in the amount of power generation due to the stop of work cause an erroneous detection.

そこで、この発明は、ストリング単位での太陽電池パネルの故障による性能劣化をできるだけ早く且つ確実に検出できる発電状況診断方法及びその装置を提供することを目的としたものである。 Then, this invention aims at providing the power generation condition diagnostic method and its device which can detect performance degradation by failure of a solar cell panel in a string unit promptly and certainly.

請求項1の発明は、太陽光発電システムにおいて、一定個数のストリングの同じ時刻の瞬時電流を全ストリングにわたり、一定周期で各時間帯ごとに一定期間測定して、全ストリングの第1の測定電流値の中央値を算出し、当該中央値から一定値以上乖離している第1の測定電流値を含む時間帯のデータを除外し、残った各ストリングの各時間帯ごとの第1の測定電流値を一定期間積算し、各ストリングの各時間帯における積算電流値の平均値を算出し、各ストリングの各時間帯の積算電流値の前記平均積算電流値に対する割合を算出してこれを補正係数とし、その後、各ストリングの各時間帯ごとに第2の電流値を測定し、当該各第2の測定電流値を相応する時間帯の補正係数で割ることにより、各ストリングの各時間帯ごとの補正電流値を算出し、前記ストリングの各時間帯ごとの補正電流値から中央値を算出し、前記第2の測定電流値が前記各ストリングの各時間帯の補正電流値の中央値より一定幅以上低い状態が一定期間連続した場合に、当該ストリングの性能低下と判定し、ストリングの性能低下と判断したものが、実際、当該ストリングに属する太陽電池パネルの故障であったかどうかを判定してその結果をフィードバックし、前記補正電流値の中央値からの一定幅の増減又は前記中央値より一定幅以下低い状態の連続している期間の増減を調整する、太陽光発電システムの発電状況診断方法とした。 The invention according to claim 1 is that, in the photovoltaic power generation system, instantaneous current of a fixed number of strings at the same time is measured over all strings for a fixed period for each time zone in a fixed cycle, and the first measured current of all strings Calculate the median of the values, exclude the time zone data including the first measured current value that deviates from the median by more than a fixed value, and measure the first measured current for each time zone of each remaining string The values are integrated for a fixed period, an average value of integrated current values in each time zone of each string is calculated, and a ratio of integrated current value in each time zone of each string to the average integrated current value is calculated as a correction coefficient and then, subsequently, the second current value is measured for each time zone of each string is divided by the correction factor of the time zone corresponding to the respective second measured current value, for each time zone of each string Correction current value Calculated, the calculated central value from the correction current value for each time zone of each string, the second lower state over a certain width from the center value of the correction current value of each time zone of measurement current value each string If it continues for a fixed period, it is judged that the performance of the string is degraded, and it is judged whether the performance degradation of the string is actually a failure of the solar panel belonging to the string, and the result is fed back. The method for diagnosing the power generation state of a photovoltaic power generation system adjusts the increase or decrease of a constant width from the median value of the correction current value or the increase and decrease of a continuous period of a state lower than the median value by a predetermined width or less.

請求項1の発明によれば、太陽光発電の発電診断において、各ストリングの電流の初期計測データを用いて測定電流値を補正することで、計測誤差及び性能差による電流差の影響を除去し、精度の高い診断が可能となる。また、各ストリングの各時間帯の補正係数を出して、当該補正係数により実際の同ストリングの測定電流値を補正して電流値の低下による太陽電池パネルの故障を判定するため、常に機器自体の性能に基づいて補正するため、場所や環境を問わず迅速に且つ正確な判定ができる。 According to the invention of claim 1, in the power generation diagnosis of solar power generation, the influence of the current difference due to the measurement error and the performance difference is eliminated by correcting the measured current value using the initial measurement data of the current of each string This enables accurate diagnosis. In addition, the correction factor of each time zone of each string is output, and the measured current value of the actual same string is corrected by the correction factor to determine the failure of the solar cell panel due to the reduction of the current value. Correction based on performance enables quick and accurate determination regardless of location or environment.

また、この発明によれば、各ストリングの発電量の低下を一定の時間の経過をもって判定するため、部分影や作業停止の影響を除去し、一時的な発電量低下と故障による永続的な発電量低下を正確に判別することが可能である。 Further, according to the present invention , since the decrease in the power generation amount of each string is determined with the elapse of a predetermined time, the influence of the partial shadow and the operation stop is eliminated, and the permanent power generation due to the temporary power generation amount decrease and failure. It is possible to determine the quantity drop correctly.

また、この発明によれば、ストリングの性能低下と判断したものが、実際、当該ストリングに属する太陽電池パネルの故障であったかどうかを判定した結果をフィードバックして判定条件を調整することにより、さらにより正確な判定が可能となる。 Further, according to the present invention , it is possible to further adjust the determination condition by feeding back the result of determining whether the performance degradation of the string is actually a failure of the solar cell panel belonging to the string. Accurate determination is possible.

この発明の実施の形態例1の発電状況診断方法の概略構成図である。It is a schematic block diagram of the electric power generation condition diagnostic method of Embodiment 1 of this invention. この発明の実施の形態例1の発電状況診断方法の各ストリングのある時間帯における補正係数を表したグラフ図である。It is a graph showing the correction coefficient in a certain time zone of each string of the power generation status diagnosis method of the embodiment 1 of the present invention. この発明の実施の形態例1の発電状況診断方法の各ストリングの補正前の電流値と補正電流値を表すそれぞれのグラフ図である。It is each graph showing the electric current value before correction | amendment of each string of the electric power generation condition diagnostic method of Embodiment 1 of this invention, and a correction current value. 太陽光発電システムの概略構成図である。It is a schematic block diagram of a solar energy power generation system. 太陽光発電システムの分岐計測を示す概略図である。It is the schematic which shows branch measurement of a solar energy power generation system. 太陽光発電システムの分岐計測における各ストリングごとの測定電流値を示すグラフ図である。It is a graph which shows the measurement electric current value for every string in branch measurement of a solar energy power generation system.

(実施の形態例1)
以下、この発明の実施の形態例1の太陽光発電システムの発電状況診断方法を図1〜図3に基づいて説明する。
(Embodiment 1 of the embodiment)
Hereinafter, the power generation state diagnosis method of the solar power generation system of Embodiment 1 of this invention is demonstrated based on FIGS. 1-3.

まず、運転開始後、最初の1ヶ月で取得したデータを用いて加工を行い、以下の様に、計測誤差および電流差に起因する電流値を補正し、補正電流値を各ストリング、各時間帯ごとに求める。 First, after the start of operation, processing is performed using data acquired in the first month, and the current value caused by the measurement error and the current difference is corrected as follows, and the corrected current value is for each string, each time zone Ask for each.

瞬間電流を全ストリング分集約する。具体的には、例えば8個の全ストリングについて、同じ時刻の電流値を平均値で1分間周期で計測し、これを1時間の時間帯ごとに5時間にわたり電流計測手段10で測定する。これによって得た全ストリングの第1の測定電流値から中央値を中央値算出手段11により算出する。次に、当該中央値から±6%以上乖離しているかどうかをチェックする。±6%以上乖離している電流値を一つでも含んでいる時間帯のデータは異常があるものと推定して、データ除外手段12で除外する。そして、全てのストリングの電流値が中央値から±6%以内に収まっていれば、その時間帯は特に異常がなかったと判定し、各ストリングごとにその時刻(時間帯)の第1の測定電流値を積算する。これは1日に例えば5時間行う。これらの第1の測定電流値を積算手段13により積算する。 Sum up the instantaneous current for all strings. Specifically, for example, current values at the same time are measured at an average value in a one-minute cycle for all eight strings, and this is measured by the current measurement means 10 for five hours every one hour. A median is calculated by the median calculation means 11 from the first measured current values of all the strings thus obtained. Next, it is checked whether or not it deviates by ± 6% or more from the median value. Data in a time zone including at least one current value that deviates by ± 6% or more is assumed to be abnormal and is excluded by the data exclusion means 12. Then, if the current values of all the strings fall within ± 6% from the median value, it is determined that there is no abnormality in that time zone, and for each string, the first measured current at that time (time zone) Accumulate values. This is done, for example, 5 hours a day. These first measured current values are integrated by the integrating means 13.

この様にして、この処理を1ヶ月行うと、各ストリングの各時間帯の電流の積算電流値が出る。これらの積算電流値から下記の式1によって電流差を補正する補正係数を、補正係数算出手段14で算出する。これは1ヶ月間の全ストリングの積算電流値の合計をストリングの数nで割って平均積算電流値を出し、この平均積算電流値に対するn番目のストリングの1ヶ月間の積算電流値の割合を出すことによりn番目のストリングの各時間帯の補正係数を出すものである。 In this way, when this process is performed for one month, an integrated current value of current in each time zone of each string is output. A correction coefficient calculation unit 14 calculates a correction coefficient for correcting the current difference from the integrated current value according to the following equation 1. This is obtained by dividing the sum of the integrated current values of all strings for one month by the number n of strings to obtain an average integrated current value, and the ratio of the integrated current value of one month of the nth string to the average integrated current value. The correction factor of each time zone of the n-th string is outputted by taking it out.

Figure 0006501535
Figure 0006501535

なお、上記式1において、
Kn:n番目のストリングの補正係数(n=1〜n)
Ahn:n番目のストリングの1ヶ月間積算電流値
N:全ストリング数
In the above equation 1,
K n: correction coefficient of n th string (n = 1 to n)
Ahn: 1-month accumulated current value of n-th string N: total number of strings

この補正係数は各ストリングについて、各時間帯の補正係数を算出する。従って、各ストリングにつき、1日5時間の計測であれば5個の時間帯の補正係数を算出する。図2はある時間帯の各ストリングの補正係数を表したグラフ図である。 This correction factor calculates the correction factor of each time zone for each string. Therefore, for each string, if it is measured 5 hours a day, correction factors of 5 time zones are calculated. FIG. 2 is a graph showing the correction coefficient of each string in a certain time zone.

次に、2ヶ月以降、上記と同様に各ストリングの電流値を測定する。そして、日中、例えば、9時〜14時の1時間毎に、発電量の低下を判定し、全ての時間帯で発電量の低下が発生していた時のみ故障による発電量の低下とみなすことで、部分影や作業停止の影響を除去する。 Next, after 2 months, the current value of each string is measured in the same manner as described above. Then, for example, during the daytime, for example, every hour from 9 o'clock to 14 o'clock, the decrease in the amount of power generation is judged, and it is regarded as the decrease in the amount of power generation due to failure only when the decrease in the amount of power generation occurs in all time zones. To eliminate the effects of partial shadows and work stoppages.

具体的には2ヶ月以降、上記と同様に各ストリングの電流値を前記電流計測手段10で測定し、各ストリングの各時間帯ごとの第2の測定電流値を各ストリングの各時間帯ごとの補正係数で割り、各ストリングの各時間帯ごとの補正電流値を、補正電流値算出手段15により算出する。図3の(a)図は各ストリングの補正前の電流値、(b)図は各ストリングの補正後の補正電流値を示すグラフ図である。この様に、補正をかけると各ストリングの電流値のばらつきが無くなり、略1本の太い線となる。 Specifically, after 2 months, the current measuring means 10 measures the current value of each string in the same manner as described above, and the second measured current value for each time zone of each string is measured for each time zone of each string. The correction current value calculation means 15 calculates the correction current value for each time zone of each string by dividing by the correction coefficient. FIG. 3A is a graph showing the current value before correction of each string, and FIG. 3B is a graph showing the correction current value after correction of each string. As described above, when the correction is performed, the variation in the current value of each string disappears, and it becomes approximately one thick line.

さらに、各ストリングの全時間帯の補正電流値の中央値を前記中央値算出手段11で算出し、各ストリングの各時間帯の第2の測定電流値が中央値から−3%以上乖離しているかどうかを第1判定手段16でチェックする。1時間の内で、全体の半分(30分)以上−3%以上乖離していた場合、当該ストリングの当該時間帯で発電量の低下が発生したとみなす。 Further, the median value of the correction current values of all time zones of each string is calculated by the median value calculating means 11, and the second measured current values of each time zone of each string deviate from the median by -3% or more The first determination means 16 checks whether or not there is an error. If one half (30 minutes) or more of the whole deviates by more than -3% within one hour, it is considered that a decrease in the power generation amount has occurred in the relevant time zone of the relevant string.

日中、9時〜14時の1時間毎に上記処理を行い、全ての時間帯で発電量の低下が発生していた時のみ、第2判定手段17で異常と認定し、表示手段18で表示又は警報を発する。これにより部分影や作業停止等の一時的な発電電力低下と故障による永続的な発電電力低下を判別する。 During the daytime, the above process is performed every hour from 9 o'clock to 14 o'clock, and the second judging means 17 recognizes as abnormal only when the decrease of the power generation amount occurs in all time zones, and the display means 18 Issue a display or alarm. As a result, it is possible to determine a temporary decrease in generated power such as a partial shadow or a work stop and a permanent decrease in generated power due to a failure.

なお、上記実施の形態例1においては、各測定電流値等を記憶する記憶手段19、各手段を制御する、CPU等から成る制御手段20等を備えている。前記記憶手段19は、大容量メモリとして機能する、ハードディスクドライブを有しており、アプリケーションプログラム、OS、制御プログラム、関連プログラム等が記憶される。前記式(1)や前記各手段の演算式等は、アプリケーションプログラムとして当該記憶手段19のハードディスクドライブに記憶されている。 In the first embodiment, the memory means 19 for storing the measured current values and the like, and the control means 20 for controlling the means, such as a CPU, are provided. The storage unit 19 has a hard disk drive that functions as a large capacity memory, and stores an application program, an OS, a control program, a related program, and the like. The equation (1) and the arithmetic equations of the respective means are stored in the hard disk drive of the storage means 19 as an application program.

その他、内部に基本I/Oプログラム、基本処理において使用する各種データを記憶するROM(=Read Only Memory)を有し、また、各種データを一時記憶するための制御手段20の主メモリ、ワークエリア等として機能する、RAM(Random AccessMemory)を有する。前記表示手段18は液晶ディスプレイ、有機ELディスプレイ、CRT等である。また、図示は省略したが、入力手段を有している。当該入力手段は、キーボード、タッチパネル、マウス等から構成されている。また、本件装置内の前記各手段は相互に信号線で接続されている。 In addition, a basic I / O program and ROM (= Read Only Memory) for storing various data used in basic processing are provided internally, and a main memory and a work area of control means 20 for temporarily storing various data. Etc., has a RAM (Random Access Memory). The display means 18 is a liquid crystal display, an organic EL display, a CRT or the like. Moreover, although illustration is abbreviate | omitted, it has an input means. The said input means is comprised from the keyboard, the touch panel, the mouse etc. Further, the respective means in the present apparatus are connected to each other by signal lines.

また、上記実施の形態例1の各ストリングの電流測定周期、1日の測定時間帯、1ヶ月の測定積算期間等の数値は限定的なものではなく、任意に設定できるものである。 In addition, numerical values such as the current measurement period of each string, the measurement time zone for one day, and the measurement integration period for one month in Embodiment 1 are not limited, and can be set arbitrarily.

また、前記補正電流値の算出は判定精度を向上させるための処理であり、部分影や作業停止の影響を除去した発電量低下の検出自体は、1ヶ月目からでも可能である。 The calculation of the correction current value is a process for improving the determination accuracy, and the detection itself of the reduction in the amount of generated power from which the influence of the partial shadow and the work stop has been removed can be performed even from the first month.

また、上記実施の形態例1に代えて、第1判定手段において、補正電流値の中央値を算出せず、前記第2の測定電流値が前記各補正電流値に対して一定幅以上低い場合に、当該ストリングの性能低下と判定し、これを表示手段18で表示又は警報しても良い。 Further, in place of the first embodiment, the first determination means does not calculate the median value of the correction current values, and the second measured current value is lower than each correction current value by a predetermined width or more. It may be determined that the performance of the string is degraded, and this may be displayed or warned by the display means 18.

なお、上記実施の形態例では最初の1ヶ月間モニタリングして、各ストリングの各時間帯の電流値の補正係数を求め、2ヶ月後からの各ストリングの電流値を計測して前記補補正係数から補正電流値を求めているが、上記期間に限定されるものではない。 In the above embodiment, the correction coefficient of the current value of each time zone of each string is determined by monitoring for the first one month, and the current value of each string after two months is measured to obtain the complementary correction coefficient. The correction current value is obtained from the above, but the present invention is not limited to the above period.

また、前記補正係数の算出のモニタリングを、一年後の相応する月の発電診断に使用しても良く、また、直近の1ヶ月前のモニタリングを発電診断に使用しても良い。さらには、当該モニタリングを順次更新して、使用することができる。 Further, the monitoring of the calculation of the correction coefficient may be used for the power generation diagnosis of the corresponding month after one year, and the monitoring of the latest one month ago may be used for the power generation diagnosis. Furthermore, the monitoring can be updated sequentially and used.

また、第2判定手段17でストリングの性能低下と判断したものが、実際、当該ストリングに属する太陽電池パネルの故障であったかどうかを判定してその結果をフィードバックし、前記補正電流値の中央値からの一定幅の増減又は前記中央値より一定幅以下低い状態の連続している期間の増減を調整することもできる。 Further, it is determined whether or not the performance deterioration of the string is judged by the second judging means 17 to be actually a failure of the solar cell panel belonging to the string, and the result is fed back, from the median value of the correction current values. It is also possible to adjust the increase or decrease of the constant width or the increase or decrease of the continuous period which is lower than the central value by a predetermined width or less.

実施例では、ストリング単位の部分故障の検出を示したが、パネル単位、接続箱単位、集電箱単位、PCS単位で電流値を測定し、ストリング単位と同様な処理をすることにより、それぞれの単位での部分故障を検出できる。 In the embodiment, detection of a partial failure in a string unit is shown, but the current value is measured in panel unit, junction box unit, current collection box unit, PCS unit, and processing is performed in the same manner as in string unit. It can detect partial failures in units.

1 太陽電池パネル 2 ストリング
3 接続箱 4 集電箱
5 パワーコンディショナ 6 連系変圧器
10 電流計測手段 11 中央値算出手段
12 データ除外手段 13 積算手段
14 補正係数算出手段 15 補正電流値算出手段
16 第1判定手段 17 第2判定手段
18 表示手段 19 記憶手段
20 制御手段
DESCRIPTION OF SYMBOLS 1 solar cell panel 2 string 3 connection box 4 current collection box 5 power conditioner 6 interconnection transformer 10 current measurement means 11 median value calculation means 12 data exclusion means 13 integration means 14 correction coefficient calculation means 15 correction current value calculation means 16 First determination means 17 second determination means 18 display means 19 storage means 20 control means

Claims (1)

太陽光発電システムにおいて、
一定個数のストリングの同じ時刻の瞬時電流を全ストリングにわたり、一定周期で各時間帯ごとに一定期間測定して、全ストリングの第1の測定電流値の中央値を算出し、当該中央値から一定値以上乖離している第1の測定電流値を含む時間帯のデータを除外し、
残った各ストリングの各時間帯ごとの第1の測定電流値を一定期間積算し、各ストリングの各時間帯における積算電流値の平均値を算出し、各ストリングの各時間帯の積算電流値の前記平均積算電流値に対する割合を算出してこれを補正係数とし、
その後、各ストリングの各時間帯ごとに第2の電流値を測定し、当該各第2の測定電流値を相応する時間帯の補正係数で割ることにより、各ストリングの各時間帯ごとの補正電流値を算出し、
前記ストリングの各時間帯ごとの補正電流値から中央値を算出し、前記第2の測定電流値が前記各ストリングの各時間帯の補正電流値の中央値より一定幅以上低い状態が一定期間連続した場合に、当該ストリングの性能低下と判定し、
ストリングの性能低下と判断したものが、実際、当該ストリングに属する太陽電池パネルの故障であったかどうかを判定してその結果をフィードバックし、前記補正電流値の中央値からの一定幅の増減又は前記中央値より一定幅以下低い状態の連続している期間の増減を調整することを特徴とする、太陽光発電システムの発電状況診断方法。
In a photovoltaic system,
The instantaneous current at the same time of a fixed number of strings is measured over the entire string for a fixed period for each time zone in a fixed cycle to calculate the median value of the first measured current values of all strings, and constant from the median value Exclude time zone data including the first measured current value that deviates by more than the value,
The first measured current value for each time zone of each remaining string is integrated for a fixed period, an average value of integrated current values in each time zone of each string is calculated, and integrated current values of each time zone of each string are calculated. Calculate the ratio to the average integrated current value and use this as the correction coefficient,
Thereafter, the second current value is measured for each time zone of each string, and the correction current for each time zone of each string is determined by dividing each second measured current value by the correction factor of the corresponding time zone. Calculate the value,
A median value is calculated from the correction current value for each time zone of each string, and a state in which the second measured current value is lower than the median value of the correction current values for each time zone of each string by a predetermined width or more is constant time If continuous, it is determined that the performance of the string is degraded,
It is determined whether the performance degradation of the string is actually a failure of the solar cell panel belonging to the string, and the result is fed back, and the increase or decrease of the fixed width from the median value of the correction current value or the center A method for diagnosing a power generation state of a photovoltaic power generation system, comprising adjusting an increase and a decrease in a continuous period of a state lower than a predetermined value by a certain range or less.
JP2015016461A 2015-01-30 2015-01-30 Method and apparatus for diagnosing power generation status of photovoltaic system Active JP6501535B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015016461A JP6501535B2 (en) 2015-01-30 2015-01-30 Method and apparatus for diagnosing power generation status of photovoltaic system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015016461A JP6501535B2 (en) 2015-01-30 2015-01-30 Method and apparatus for diagnosing power generation status of photovoltaic system

Publications (2)

Publication Number Publication Date
JP2016144244A JP2016144244A (en) 2016-08-08
JP6501535B2 true JP6501535B2 (en) 2019-04-17

Family

ID=56570994

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015016461A Active JP6501535B2 (en) 2015-01-30 2015-01-30 Method and apparatus for diagnosing power generation status of photovoltaic system

Country Status (1)

Country Link
JP (1) JP6501535B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019163413A1 (en) * 2018-02-20 2019-08-29 太陽誘電株式会社 Photovoltaic power generation failure diagnosis device, photovoltaic power generation failure diagnosis method, and program
KR102431426B1 (en) * 2020-09-04 2022-08-10 동명대학교산학협력단 Sunlight generation of electricity system and the diagnosis method
KR102431446B1 (en) * 2020-09-04 2022-08-10 동명대학교산학협력단 Sun light electric generator for detecting malfunction panel
CN113541600B (en) * 2021-05-25 2022-09-06 特变电工新疆新能源股份有限公司 Method, system, equipment and storage medium for judging branch fault of photovoltaic power station

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0511835A (en) * 1991-07-08 1993-01-22 Omron Corp Fault diagnostic device
JP2874156B2 (en) * 1994-04-13 1999-03-24 キヤノン株式会社 Power generation system
JPH11175177A (en) * 1997-12-17 1999-07-02 Meidensha Corp Solar battery monitoring device
EP2293089A1 (en) * 2009-09-02 2011-03-09 SMA Solar Technology AG String malfunction monitoring
JP2011077477A (en) * 2009-10-02 2011-04-14 Sansha Electric Mfg Co Ltd Monitor
EP2538450A4 (en) * 2010-02-19 2015-06-17 Onamba Co Ltd Method for detecting failure of photovoltaic power system
JP5671488B2 (en) * 2012-03-14 2015-02-18 東京エレクトロン株式会社 Solar cell module effectiveness monitoring system and monitoring method thereof
JP6037762B2 (en) * 2012-10-18 2016-12-07 三菱電機株式会社 Wind measuring device
JP2015099858A (en) * 2013-11-19 2015-05-28 タケモトデンキ株式会社 Abnormality detection device

Also Published As

Publication number Publication date
JP2016144244A (en) 2016-08-08

Similar Documents

Publication Publication Date Title
JP6501535B2 (en) Method and apparatus for diagnosing power generation status of photovoltaic system
ES2800773T3 (en) Procedure and device for detecting an equivalent load of a wind turbine generator system
KR100195686B1 (en) Abnormality detection method, abnormality detection apparatus & power generating system using the same
EP3940352B1 (en) Weighing scale diagnostics method
US10340849B2 (en) Diagnosis system and diagnosis method for photovoltaic power generation system
US9086442B2 (en) Methods and apparatus to detect leakage current in a resistance temperature detector
JP6813291B2 (en) Performance evaluation method for photovoltaic power generation
US8635035B2 (en) Systems and methods for monitoring operation of an LED string
US10648605B2 (en) Water hammer prevention system using operation state analysis algorithm
US20160356859A1 (en) Fault detection in energy generation arrangements
JP6608619B2 (en) Method and apparatus for diagnosing power generation status of solar power generation system
JP2013073414A (en) Sensor diagnostic device and sensor diagnostic method for plant
KR101532163B1 (en) Evaluation and condition diagnosis system for photovoltaic power generator
WO2015152205A1 (en) Power generation system analysis device and method
JP2015103699A (en) Abnormality detection method of solar cell string, abnormality detection device and photovoltaic power generation device
JP2004156616A (en) Method of diagnosing prognosis of turbine blade (bucket) by monitoring health condition thereof by using neural network utilizing diagnosing method in relation to pyrometer signals
KR20170126623A (en) photovoltaic power generation equipment efficiency detection system based on multi variables
JP2011181614A (en) Device and method for fault diagnosis
JP2013239686A (en) Failure detection method and monitoring system for solar power generation
KR101861838B1 (en) Actual effect precipitaion calculation apparatus and method for weighting precipitation-gauge
JP6548955B2 (en) Support system for power generation estimation learning in photovoltaic power generation
JP2003271231A (en) Estimation device of detector drift and monitor system of detector
JP7452119B2 (en) Diagnostic equipment, diagnostic methods and programs
JP2015099858A (en) Abnormality detection device
US20210305936A1 (en) Method, computer-implemented tool and power plant control device for detecting power production degradation of solar power plants and solar power plant system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180110

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20180131

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20180131

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20181024

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20181204

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190131

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190305

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190319

R150 Certificate of patent or registration of utility model

Ref document number: 6501535

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350