JP5638228B2 - Metering device - Google Patents

Metering device Download PDF

Info

Publication number
JP5638228B2
JP5638228B2 JP2009266947A JP2009266947A JP5638228B2 JP 5638228 B2 JP5638228 B2 JP 5638228B2 JP 2009266947 A JP2009266947 A JP 2009266947A JP 2009266947 A JP2009266947 A JP 2009266947A JP 5638228 B2 JP5638228 B2 JP 5638228B2
Authority
JP
Japan
Prior art keywords
supply
stage
time
value
gate opening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2009266947A
Other languages
Japanese (ja)
Other versions
JP2011112412A (en
Inventor
孝橋 徹
孝橋  徹
恭将 佐藤
恭将 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yamato Scale Co Ltd
Original Assignee
Yamato Scale Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yamato Scale Co Ltd filed Critical Yamato Scale Co Ltd
Priority to JP2009266947A priority Critical patent/JP5638228B2/en
Publication of JP2011112412A publication Critical patent/JP2011112412A/en
Application granted granted Critical
Publication of JP5638228B2 publication Critical patent/JP5638228B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Weight Measurement For Supplying Or Discharging Of Specified Amounts Of Material (AREA)

Description

本発明は、定量供給装置に関し、特に、予め設定された目標重量値分の被計量物を供給する定量供給装置に関する。   The present invention relates to a quantitative supply device, and more particularly to a quantitative supply device that supplies an object to be weighed for a preset target weight value.

この種の定量供給装置、とりわけ樹脂ペレットやグラニュー糖のように流動性の高い粉粒状(バラ状)の被計量物を取り扱う定量供給装置、として、例えば、被計量物が収容された溜めホッパと、この溜めホッパの下方に配置されると共に当該溜めホッパから被計量物の供給を受ける計量ホッパと、を備えたものがある。計量ホッパには、ロードセル等の荷重センサが付属されており、この荷重センサから出力される計量信号に基づいて、当該計量ホッパに供給された被計量物の重量が求められる。そして、求められた重量測定値が目標重量値よりも小さい所定の供給停止重量値と一致したときに、溜めホッパから計量ホッパへの被計量物の供給が停止される。これにより、目標重量値分の被計量物を供給する、という定量供給が実現される。さらに、この定量供給を高速かつ高精度に実現するために、被計量物の単位時間当たりの供給量が段階的に変えられることがある。   As this type of quantitative supply device, in particular, a quantitative supply device that handles highly fluid powdery (rose-like) objects such as resin pellets and granulated sugar, for example, a reservoir hopper containing the objects to be weighed And a weighing hopper that is disposed below the reservoir hopper and receives a supply of an object to be weighed from the reservoir hopper. A load sensor such as a load cell is attached to the weighing hopper, and the weight of an object to be weighed supplied to the weighing hopper is obtained based on a weighing signal output from the load sensor. Then, when the obtained weight measurement value coincides with a predetermined supply stop weight value smaller than the target weight value, the supply of the object to be weighed from the reservoir hopper to the weighing hopper is stopped. Thereby, the quantitative supply of supplying the objects to be weighed for the target weight value is realized. Furthermore, in order to realize this constant supply with high speed and high accuracy, the supply amount of the object to be weighed per unit time may be changed stepwise.

具体的には、溜めホッパから計量ホッパへの被計量物の供給が開始された直後の初期の段階においては、比較的に大きな供給量で当該被計量物の供給が行われる。これにより、被計量物の供給開始から供給停止までに要する時間、言わば供給時間、の短縮化が図られる。そして、被計量物の供給開始から或る程度の時間が経過し、例えば上述した重量測定値が供給停止重量値よりも小さい所定の切換重量値に達した時点で、比較的に小さな供給量に切り換えられる。このように小さな供給量に切り換えられることで、時間の経過と共に増大する重量測定値の増大速度が低下し、当該重量測定値が供給停止重量値と一致するタイミング、つまり被計量物の供給を停止させるタイミング、の取得が容易になる。また、このタイミングに多少のズレが生じたとしても、被計量物の供給量が小さいので、当該ズレによる影響(誤差)が軽減される。この結果、目標重量値に対する実際の供給重量値の精度、言わば供給精度、が向上する。   Specifically, in the initial stage immediately after the supply of the weighing object from the reservoir hopper to the weighing hopper is started, the weighing object is supplied with a relatively large supply amount. This shortens the time required from the start of supply of the object to be weighed to the stop of supply, in other words, the supply time. Then, when a certain amount of time has elapsed from the start of supply of the object to be weighed, for example, when the above-described weight measurement value reaches a predetermined switching weight value that is smaller than the supply stop weight value, the supply amount becomes relatively small. Can be switched. By switching to such a small supply amount, the rate of increase of the weight measurement value that increases with time decreases, and the timing at which the weight measurement value matches the supply stop weight value, that is, the supply of the object to be measured is stopped. This makes it easier to obtain the timing. Even if some deviation occurs at this timing, the supply amount of the object to be weighed is small, so that the influence (error) due to the deviation is reduced. As a result, the accuracy of the actual supply weight value with respect to the target weight value, that is, the supply accuracy is improved.

なお、被計量物の単位時間当たりの供給量は、例えば、溜めホッパの底部にある排出口に設けられた開閉ゲートの開度によって制御される。即ち、このゲート開度が大きいほど、被計量物の単位時間当たりの供給量は大きくなり、当該ゲート開度が小さいほど、被計量物の単位時間当たりの供給量は小さくなる。そして、開閉ゲートが閉鎖されることで、溜めホッパから計量ホッパへの被計量物の供給が停止される。ただし、開閉ゲートが閉鎖されても、その後、暫くの間は、被計量物が計量ホッパに供給され続ける。これは、主に、開閉ゲートと計量ホッパとの間に距離があること、いわゆる落差量、に起因する。また、開閉ゲートを閉鎖させるタイミングが到来してから、つまり重量測定値が供給停止重量値と一致するタイミングが到来してから、実際に当該開閉ゲートが閉鎖されるまでに多少の時間遅れが生じることにも、起因する。これらを考慮して、供給停止重量値は目標重量値よりも小さく設定されている。   Note that the supply amount of the object to be weighed per unit time is controlled by, for example, the opening degree of the open / close gate provided at the discharge port at the bottom of the reservoir hopper. That is, the larger the gate opening, the larger the supply amount of the object to be weighed per unit time, and the smaller the gate opening, the smaller the supply amount of the object to be weighed per unit time. Then, by closing the open / close gate, the supply of the objects to be weighed from the reservoir hopper to the weighing hopper is stopped. However, even if the open / close gate is closed, the object to be weighed continues to be supplied to the weighing hopper for a while after that. This is mainly due to a distance between the open / close gate and the weighing hopper, that is, a so-called drop amount. In addition, after the timing for closing the open / close gate arrives, that is, after the timing when the weight measurement value coincides with the supply stop weight value, there is a slight time delay until the open / close gate is actually closed. It also comes from that. Considering these, the supply stop weight value is set smaller than the target weight value.

ところで、このようにゲート開度によって被計量物の単位時間当たりの供給量が制御されるゲート開度制御方式においては、当該ゲート開度が段階的に切り換えられると、その切り換わり前後の供給量差によって、荷重センサを含む計量ホッパへの衝撃荷重が変化する。この結果、荷重センサから出力される計量信号に振動成分が発生し、当該計量信号に基づいて求められる重量測定値に誤差が生じる。従って、特に被計量物の供給量が小さく設定される最終の段階、言わば小供給段階、において、被計量物の供給停止タイミングを正確に取得するには、この振動成分が十分に減衰するのを待つ必要がある。すると、この待ち時間を含む小供給段階に掛かる時間が長くなり、ひいては供給時間全体が長くなる。この不都合に対処するべく、従来、例えば特許文献1に開示されたものがある。   By the way, in the gate opening control method in which the supply amount per unit time of the object to be weighed is controlled by the gate opening in this way, when the gate opening is switched stepwise, the supply amount before and after the switching Due to the difference, the impact load on the weighing hopper including the load sensor changes. As a result, a vibration component is generated in the weighing signal output from the load sensor, and an error occurs in the weight measurement value obtained based on the weighing signal. Therefore, especially in the final stage where the supply amount of the object to be weighed is set to be small, that is, in the small supply stage, in order to accurately obtain the supply stop timing of the object to be weighed, this vibration component must be sufficiently attenuated. I need to wait. Then, the time required for the small supply stage including this waiting time becomes longer, and the entire supply time becomes longer. In order to cope with this inconvenience, there is a conventional one disclosed in Patent Document 1, for example.

この従来技術によれば、図11(a)に示すように、時間tがt=0という時点を基点として、開閉ゲートが開かれ、被計量物の供給が開始される。この被計量物の供給開始直後のゲート開度Gは、G11という比較的に大きな値に設定される。これにより、当該ゲート開度G11に応じた比較的に大きな供給量で溜めホッパから計量ホッパへ被計量物が供給される。この言わば大供給(大投入)段階においては、図11(b)に太実線A1で示すように、重量測定値Wxが当該ゲート開度G11に応じた比較的に高い一定の速度(dWx/dt)で増大する。そして、この重量測定値Wxが予め設定された供給停止重量値Wcよりも小さい第1の切換重量値W11に到達すると(Wx=W11)、その時点t11で、大供給段階から中供給(中投入)段階としての漸減段階に切り換わる。この漸減段階においては、ゲート開度Gが、時間tの経過と共に、厳密には重量測定値Wxが増大するに連れて、漸減され、詳しくは、次の式1に基づいて、制御される。   According to this prior art, as shown in FIG. 11 (a), the opening / closing gate is opened and the supply of the object to be weighed is started from the time point when the time t is t = 0. The gate opening G immediately after the start of supply of the object to be weighed is set to a relatively large value of G11. As a result, the object to be weighed is supplied from the reservoir hopper to the weighing hopper with a relatively large supply amount corresponding to the gate opening G11. In this large supply (large input) stage, as shown by a thick solid line A1 in FIG. 11B, the weight measurement value Wx is a relatively high constant speed (dWx / dt) corresponding to the gate opening G11. ) To increase. When the weight measurement value Wx reaches the first switching weight value W11 that is smaller than the preset supply stop weight value Wc (Wx = W11), at the time t11, the medium supply from the large supply stage (medium input) ) Switch to the gradual reduction step. In this gradual decrease step, the gate opening G is gradually decreased as the weight measurement value Wx increases as the time t elapses. Specifically, the gate opening G is controlled based on the following equation (1).

《式1》
G=(G11−G12)・{(W12−Wx)/(W12−W11)}α+G12
<< Formula 1 >>
G = (G11−G12) · {(W12−Wx) / (W12−W11)} α + G12

なお、この式1において、W12は、予め設定された第2の切換重量値であり、この第2切換重量値W12は、上述の第1切換重量値W11よりも大きく、かつ、供給停止重量値Wcよりも小さい(W11<W12<Wc)。また、冪指数αは、0.3≦α≦0.7を満足する任意の値である。さらに、G12は、後述する小供給(小投入)段階におけるゲート開度Gであり、この小供給段階におけるゲート開度G12は、大供給段階におけるゲート開度G11よりも小さい(G12<G11)。   In Equation 1, W12 is a preset second switching weight value, and this second switching weight value W12 is larger than the first switching weight value W11 described above, and the supply stop weight value. It is smaller than Wc (W11 <W12 <Wc). Further, the power index α is an arbitrary value satisfying 0.3 ≦ α ≦ 0.7. Further, G12 is a gate opening degree G in a small supply (small input) stage described later, and the gate opening degree G12 in the small supply stage is smaller than the gate opening degree G11 in the large supply stage (G12 <G11).

この漸減段階においては、時間tの経過と共に漸減するゲート開度Gに伴って、被計量物の供給量が徐々に低減されるので、重量測定値Wxの増大速度もまた徐々に低下する。そして、重量測定値Wxが第2切換重量値W12に到達すると(Wx=W12)、その時点t12で、漸減段階から小供給段階に切り換わる。なお、この漸減段階から小供給段階に切り換わる時点t12でのゲート開度Gは、数1からも分かるように、G12となる。そして、小供給段階においては、このG12という一定のゲート開度Gとされ、これに伴い、被計量物の供給量は、当該ゲート開度G12に応じた比較的に小さな一定値となり、重量測定値Wxの増大速度は、さらに低下する。   In this gradual decrease stage, the supply amount of the object to be weighed is gradually reduced with the gate opening G gradually decreasing with the lapse of time t, so that the increasing speed of the weight measurement value Wx also gradually decreases. When the weight measurement value Wx reaches the second switching weight value W12 (Wx = W12), the gradual decrease stage is switched to the small supply stage at the time t12. Note that the gate opening G at time t12 when the gradual reduction stage is switched to the small supply stage is G12, as can be seen from equation (1). In the small supply stage, a constant gate opening G called G12 is set, and accordingly, the supply amount of the object to be weighed becomes a relatively small constant value corresponding to the gate opening G12, and the weight measurement is performed. The increasing speed of the value Wx further decreases.

この小供給段階において、重量測定値Wxが目標重量値Wpよりも小さい供給停止重量値Wcと一致すると(Wx=Wc)、その時点t13で、ゲート開度Gがゼロ(G=0)とされる。つまり、開閉ゲートが閉鎖される。ただし、上述したように、開閉ゲートが閉鎖されても、その後、暫くの間は被計量物が計量ホッパに供給され続ける。これに伴い、重量測定値Wxは、増大し続け、詳しくは落差量d分だけ増大する。そして、最終的に、重量測定値Wxは、目標重量値Wpに近い値Ws(≒Wp)に収束する。この最終重量値Wsが得られると、計量ホッパに供給された被計量物は、当該計量ホッパから排出される。これをもって、一連(1回)の定量供給が終了する。   In this small supply stage, when the weight measurement value Wx matches the supply stop weight value Wc smaller than the target weight value Wp (Wx = Wc), the gate opening G is set to zero (G = 0) at the time t13. The That is, the open / close gate is closed. However, as described above, even if the open / close gate is closed, the object to be weighed continues to be supplied to the weighing hopper for a while after that. Accordingly, the weight measurement value Wx continues to increase, and specifically increases by the head d. Finally, the weight measurement value Wx converges to a value Ws (≈Wp) close to the target weight value Wp. When this final weight value Ws is obtained, the object to be weighed supplied to the weighing hopper is discharged from the weighing hopper. This completes a series (one time) of quantitative supply.

このように、特許文献1に開示された従来技術では、大供給段階と小供給段階との間に、中供給段階としての漸減段階が設けられる。そして、この漸減段階において、ゲート開度Gが、大供給段階におけるのと同じ開度G11から小供給段階におけるのと同じ開度G12まで連続的に漸減される。これにより、各段階の切り換わり前後の被計量物の供給量差が低減され、当該切り換わり時の振動成分の発生が抑制される。この結果、特に、小供給段階に掛かる時間T1(=t13−t12)が短縮され、ひいては供給時間全体が短縮される。   As described above, in the conventional technique disclosed in Patent Document 1, a gradual reduction stage as the middle supply stage is provided between the large supply stage and the small supply stage. In this gradual reduction stage, the gate opening G is gradually reduced from the same opening G11 as in the large supply stage to the same opening G12 as in the small supply stage. Thereby, the difference in supply amount of the object to be weighed before and after switching at each stage is reduced, and the generation of vibration components at the time of switching is suppressed. As a result, in particular, the time T1 (= t13−t12) required for the small supply stage is shortened, and as a result, the entire supply time is shortened.

ところが、上述の如く各段階の切り換わり時における振動成分の発生が抑制されるとしても、被計量物の供給開始直後における当該被処理物の落下衝撃力による振動成分の発生は抑制されない。そして、この落下衝撃力が大き過ぎると、要するに大供給段階のゲート開度G11が大き過ぎると、図11(b)に太破線B1で示すように、当該落下衝撃力による振動成分が過大となり、極端には、この振動成分を含む重量測定値Wxが上述した第1切換重量値W11を超えてしまう。すると、重量測定値Wxが第1切換重量値W11を超えた時点t11’で大供給段階から漸減段階に切り換わる。つまり、大供給段階から漸減段階に切り換わる所期(本来)の時点t11よりも早く当該大供給段階から漸減段階に切り換わり、言い換えれば大供給段階において未だ十分な重量の被計量物が供給されていないにも拘らず当該大供給段階から漸減段階に切り換わる。この結果、漸減段階に掛かる時間が長くなり、却って供給時間全体が長引く。これを回避するには、大供給段階のゲート開度G11を小さめに設定すればよいが、そうすると、当該大供給段階の重量測定値Wxの増大速度が低下し、やはり供給時間全体が長引く。   However, even if the generation of the vibration component at the time of switching at each stage is suppressed as described above, the generation of the vibration component due to the drop impact force of the object to be processed immediately after the start of the supply of the object to be measured is not suppressed. And if this drop impact force is too large, in short, if the gate opening G11 in the large supply stage is too large, the vibration component due to the drop impact force becomes excessive as shown by the thick broken line B1 in FIG. Extremely, the weight measurement value Wx including this vibration component exceeds the first switching weight value W11 described above. Then, at the time t11 'when the weight measurement value Wx exceeds the first switching weight value W11, the large supply stage is switched to the gradual reduction stage. That is, the large supply stage is switched to the gradual decrease stage earlier than the intended (original) time t11 when the large supply stage is switched to the gradual reduction stage. In other words, an object having a sufficient weight is still supplied in the large supply stage. In spite of this, the large supply stage is gradually switched to the gradual reduction stage. As a result, the time required for the gradual reduction stage becomes longer, and on the contrary, the entire supply time is prolonged. In order to avoid this, the gate opening G11 in the large supply stage may be set to a small value. However, in this case, the increase rate of the weight measurement value Wx in the large supply stage is reduced, and the entire supply time is also prolonged.

そこで、さらなる別の従来技術として、例えば特許文献2に開示されたものがある。この特許文献2に開示された第2の従来技術によれば、特許文献1に開示された第1の従来技術とは異なり、重量測定値Wxに基づく(言わば重量測定値Wxを変数とする)のではなく、被計量物の供給開始時点を基点(t=0)とする経過時間tに基づいて(言わば経過時間tを変数として)、各段階の切り換えが行われる。即ち、図12(a)に示すように、当該経過時間t(軸上)において、大供給段階から漸減段階に切り換わる第1切換時点t21と、漸減段階から小供給段階に切り換わる第2切換時点t22とが、予め設定される。そして、被計量物の供給開始と共に経過時間tが測定され、この経過時間tが第1切換時点t21に到達するまでが、大供給段階とされる。この大供給段階においては、ゲート開度GがG21という比較的に大きな一定値とされる。これにより、図12(b)に太実線A2で示すように、重量測定値Wxが、当該ゲート開度G21に応じた比較的に高い一定の速度(dWx/dt)で増大する。そして、経過時間tが第1切換時点t21に到達すると、大供給段階から漸減段階に切り換わる。この漸減段階においては、次の式2に基づいて、ゲート開度Gが制御される。   Thus, as another conventional technique, for example, there is one disclosed in Patent Document 2. According to the second prior art disclosed in Patent Document 2, unlike the first prior art disclosed in Patent Document 1, it is based on the weight measurement value Wx (in other words, the weight measurement value Wx is a variable). Instead, each stage is switched based on the elapsed time t with the starting point of supply of the object to be weighed as the base point (t = 0) (in other words, the elapsed time t is a variable). That is, as shown in FIG. 12 (a), at the elapsed time t (on the axis), the first switching time t21 when the large supply stage is switched to the gradual reduction stage and the second switching when the gradual reduction stage is switched to the small supply stage. Time t22 is set in advance. Then, the elapsed time t is measured with the start of the supply of the object to be weighed, and the time until the elapsed time t reaches the first switching time t21 is set as the large supply stage. In this large supply stage, the gate opening G is a relatively large constant value G21. As a result, as indicated by a thick solid line A2 in FIG. 12B, the weight measurement value Wx increases at a relatively high constant speed (dWx / dt) corresponding to the gate opening G21. When the elapsed time t reaches the first switching time t21, the large supply stage is switched to the gradual reduction stage. In this gradual reduction step, the gate opening degree G is controlled based on the following equation 2.

《式2》
G=(G21−G22)・{(t22−t)/(t22−t21)}α+G22
<< Formula 2 >>
G = (G21−G22) · {(t22−t) / (t22−t21)} α + G22

なお、この式2において、G22は、次に説明する小供給段階のゲート開度Gであり、例えば第1従来技術における小供給段階のゲート開度G12と略等価(G22≒G12)である。そして、冪指数αは、0<α≦1を満足する任意の値である。   In Equation 2, G22 is a gate opening degree G in the small supply stage described next, and is substantially equivalent to the gate opening degree G12 in the small supply stage in the first conventional technique (G22≈G12). The power index α is an arbitrary value satisfying 0 <α ≦ 1.

この漸減段階は、経過時間tが第2切換時点t21に到達するまで継続され、この間、当該経過時間tに伴って漸減するゲート開度Gに応じて、重量測定値Wxの増大速度もまた漸減する。そして、経過時間tが第2切換時点t21に到達すると、漸減段階から小供給段階に切り換わる。   This gradual decrease step is continued until the elapsed time t reaches the second switching time t21. During this time, the rate of increase of the weight measurement value Wx is also gradually decreased according to the gate opening G that gradually decreases with the elapsed time t. To do. When the elapsed time t reaches the second switching time t21, the gradual decrease stage is switched to the small supply stage.

小供給段階においては、上述したG22という一定のゲート開度Gとされ、これに伴い、重量測定値Wxが一定の低速度で増大する。そして、重量測定値Wxが供給停止重量値Wcと一致(Wx=Wc)した時点t23で、ゲート開度Gがゼロとされ、開閉ゲートが閉鎖される。これにより、重量測定値Wxは、当該時点t23から落差量d分だけ増大し、目標重量値Wpに近い最終重量値Wsに収束する。   In the small supply stage, the above-described constant gate opening G of G22 is set, and accordingly, the weight measurement value Wx increases at a constant low speed. At time t23 when the weight measurement value Wx coincides with the supply stop weight value Wc (Wx = Wc), the gate opening G is set to zero and the open / close gate is closed. As a result, the weight measurement value Wx increases by the drop amount d from the time point t23 and converges to the final weight value Ws close to the target weight value Wp.

このように、第2従来技術では、経過時間tに基づいて各段階の切り換えが行われるので、たとえ図12(b)に太破線B2で示すような振動成分が重量測定値Wxに含まれるとしても、この振動成分の影響を受けることなく、所期の通りに当該各段階の切り換えが行われる。従って、例えば、第1切換時点t21よりも前の或る時点t21’において、振動成分を含む重量測定値Wxが、当該第1切換時点t21における本来の(理想的な)値W21を超えたとしても、不本意に大供給段階から漸減段階に切り換わることはない。   As described above, in the second prior art, each stage is switched based on the elapsed time t. Therefore, it is assumed that a vibration component as indicated by a thick broken line B2 in FIG. 12B is included in the weight measurement value Wx. However, the respective stages are switched as expected without being affected by the vibration component. Therefore, for example, at a certain time t21 ′ before the first switching time t21, the weight measurement value Wx including the vibration component exceeds the original (ideal) value W21 at the first switching time t21. However, there is no inadvertent switch from the large supply stage to the gradual reduction stage.

しかしながら、この第2従来技術をもってしても、次のような問題がある。即ち、この第2従来技術における漸減段階においては、上述の如く式2に基づいてゲート開度Gが制御されるが、この式2における冪指数αは、0<α≦1を満足する任意の値である。例えば、この冪指数αがα=1である、と仮定すると、漸減段階におけるゲート開度Gは、図12(a)に太実線P2で示すように、直線的に推移する。一方、冪指数αが0<α<1である場合には、ゲート開度Gは、図12(a)に太破線P2’で示すように、上方に向かって凸状に膨らむように曲線的に推移する。そして、この曲線P2’の膨らみは、冪指数αの値が小さいほど、大きくなる。なお、常套的には、当該冪指数αは(1よりも)小さく設定され、つまり曲線P2’の膨らみが大きくなるように設定される。これは、ゲート開度Gが当該曲線P2’の如く推移することによって、漸減段階においても出来る限り大きな供給量で被計量物が供給されるようにし、ひいては供給時間全体のさらなる短縮化が図られるようにするためである。   However, even with the second prior art, there are the following problems. That is, in the gradual decrease step in the second prior art, the gate opening degree G is controlled based on the equation 2 as described above. The power index α in the equation 2 is an arbitrary value satisfying 0 <α ≦ 1. Value. For example, assuming that the power index α is α = 1, the gate opening degree G in the gradual decrease stage changes linearly as shown by a thick solid line P2 in FIG. On the other hand, when the power index α is 0 <α <1, the gate opening degree G is curved so as to bulge upward as shown by a thick broken line P2 ′ in FIG. Transition. The bulge of the curve P2 'increases as the value of the power index α decreases. Normally, the power index α is set to be smaller (less than 1), that is, set so as to increase the bulge of the curve P2 '. This is because the gate opening G changes as shown by the curve P2 ′ so that the object to be weighed is supplied with as large a supply amount as possible even in the gradual reduction stage, and the entire supply time is further shortened. It is for doing so.

ここで、漸減段階と小供給段階との境界である第2切換時点t22に注目すると、この第2切換時点t22においては、それまで式2に基づいて漸減(特に第2切換時点t22の直前には急減)していたゲート開度Gが、これ以降、突然G22という一定値になる。つまり、第2切換時点t22の前後の短い期間中に、ゲート開度Gが急変する。従って、この第2切換時点t22においても、図12(b)に太破線B2で示したように、(漸減段階がない場合に比べて振幅は小さいものの)多少の振動成分が発生する。その一方で、第2従来技術においては、上述の如く小供給段階に掛かる時間T2(=t23−t22)の短縮化が図られるが、この小供給時間T2が短すぎると、その始点である第2切換時点t22で発生する当該振動成分の振幅が小さくても、この振動成分の影響によって、小供給時間T2の終点である供給停止時点t23を正確に捉えることができず、ひいては供給精度が低下する。これを回避するには、やはり小供給時間T2を相応に長くする必要があり、詳しくは第2切換時点t22で見込まれる重量値W22をさらに低めに設定する、言い換えれば当該重量値W22と供給停止重量値Wcとの間隔(=Wc−W22)をさらに広げる、必要がある。しかし、これでは漸減段階を設ける意味が半減し、小供給時間T2を含む供給時間全体の短縮化が不十分となる。このことは、第1従来技術についても、同様である。即ち、上述の図11(a)における第2切換時点t12に注目すると、この第2切換時点t12においては、それまで式1に基づいて漸減(特に第2切換時点t12の直前には急減)していたゲート開度Gが、これ以降、突然G12という一定値になる。つまり、第2切換時点t12の前後の短い期間中に、ゲート開度Gが急変する。これによって、図11(b)に太破線B1で示したように、第2切換時点t12においても振動成分が発生し、この振動成分が十分に減衰するのを待つための時間を含む小供給時間T1を長くする必要があり、詳しくは第2切換重量値W12をさらに低めに設定する、言い換えれば第2切換重量値W12と供給停止重量値Wcとの間隔(=Wc−W12)をさらに広げる、必要がある。   Here, paying attention to the second switching time t22 that is the boundary between the gradual reduction stage and the small supply stage, at this second switching time t22, the gradual reduction has been made based on Formula 2 until then (particularly immediately before the second switching time t22). The gate opening G that has been suddenly decreased) suddenly becomes a constant value of G22 thereafter. That is, the gate opening G changes suddenly during a short period before and after the second switching time t22. Accordingly, even at the second switching time t22, as shown by a thick broken line B2 in FIG. 12B, some vibration components are generated (although the amplitude is smaller than that when there is no gradual decrease step). On the other hand, in the second prior art, the time T2 (= t23−t22) required for the small supply stage can be shortened as described above. If the small supply time T2 is too short, the first point is the first point. 2 Even if the amplitude of the vibration component generated at the switching time t22 is small, the supply stop time t23 that is the end point of the small supply time T2 cannot be accurately captured due to the influence of the vibration component, and the supply accuracy is lowered. To do. In order to avoid this, it is necessary to lengthen the small supply time T2 accordingly. Specifically, the weight value W22 expected at the second switching time t22 is set to be lower, in other words, the weight value W22 and the supply stop. It is necessary to further widen the distance (= Wc−W22) from the weight value Wc. However, in this case, the meaning of providing the gradual decrease step is halved, and the entire supply time including the small supply time T2 is not sufficiently shortened. The same applies to the first prior art. That is, paying attention to the second switching time t12 in FIG. 11A, at this second switching time t12, it gradually decreases based on the formula 1 until then (especially immediately before the second switching time t12). The gate opening G that has been set suddenly becomes a constant value of G12. That is, the gate opening G changes suddenly during a short period before and after the second switching time t12. As a result, as indicated by a thick broken line B1 in FIG. 11B, a vibration component is generated even at the second switching time t12, and a small supply time including a time for waiting for this vibration component to sufficiently attenuate is supplied. T1 needs to be lengthened. Specifically, the second switching weight value W12 is set to be lower, in other words, the interval (= Wc−W12) between the second switching weight value W12 and the supply stop weight value Wc is further increased. There is a need.

また、第2切換時点t22におけるゲート開度Gの急変度合いは、大供給段階におけるゲート開度G21が大きいほど、顕著になる。従って、第2従来技術においても、第1従来技術と同様、大供給段階におけるゲート開度G21が(理由は異なるものの)制限される。このこともまた、供給時間全体の短縮化が不十分となる一要因である。   Moreover, the sudden change degree of the gate opening degree G at the second switching time point t22 becomes more remarkable as the gate opening degree G21 in the large supply stage is larger. Accordingly, in the second conventional technique, as in the first conventional technique, the gate opening G21 in the large supply stage is limited (although the reason is different). This is also a factor that makes it difficult to shorten the entire supply time.

特開昭62−230527号公報JP-A-62-230527 実開平2−99324号公報Japanese Utility Model Publication No. 2-99324

即ち、本発明が解決しようとする課題は、第1従来技術および第2従来技術のいずれにおいても、供給時間の短縮化が不十分である、ということである。   That is, the problem to be solved by the present invention is that the supply time is not sufficiently shortened in both the first and second prior arts.

それゆえに、本発明は、従来よりも供給時間全体のさらなる短縮化を図ることができる定量供給装置を提供することを、目的とする。   Therefore, an object of the present invention is to provide a quantitative supply device capable of further shortening the entire supply time as compared with the prior art.

この目的を達成するために、本発明は、予め設定された目標重量値分の被計量物を供給する定量供給装置において、供給制御信号に従って被計量物の供給を行う供給手段と、当該供給制御信号を生成する供給制御手段と、供給手段による供給済みの被計量物の重量を測定する重量測定手段と、を具備する。ここで、供給制御手段は、被計量物の単位時間当たりの供給量が漸減する漸減段階と、この漸減段階の後に続く最終の段階であって当該供給量が一定である小供給段階と、を含む複数の段階に分けて、供給手段による被計量物の供給が行われるように、供給制御信号を生成する。また、供給制御手段は、漸減段階において、小供給段階に切り換わる時点が近づくに連れて時間の経過に対する供給量の変化率を漸減させると共に、当該切り換わり時点での供給量が小供給段階におけるのと略同じレベルになるように、供給制御信号を生成する。さらに、供給制御手段は、小供給段階において、重量測定手段による重量測定値が目標重量値よりも小さい所定の供給停止重量値と一致したときに、供給手段による被計量物の供給が停止されるように、供給制御信号を生成する。加えて、漸減段階における供給制御信号は、供給手段による被計量物の供給開始時点を基点とする経過時間の関数に基づく。そして、漸減段階を含む全ての段階における供給手段による被計量物の単位時間当たりの供給量は、供給制御信号に対して線形の関係にある、というものである。 In order to achieve this object, the present invention provides, in a quantitative supply device that supplies an object to be weighed for a preset target weight value, a supply means for supplying the object to be weighed according to a supply control signal, and the supply control Supply control means for generating a signal, and weight measurement means for measuring the weight of an object to be weighed that has been supplied by the supply means. Here, the supply control means includes a gradual decrease stage in which the supply amount per unit time of the object to be weighed is gradually decreased, and a small supply stage in which the supply amount is constant at the final stage following the gradual decrease stage. The supply control signal is generated so as to supply the object to be weighed by the supply means in a plurality of stages. Further, the supply control means gradually decreases the rate of change of the supply amount over time as the time of switching to the small supply stage approaches in the gradual decrease stage, and the supply amount at the time of the change is reduced in the small supply stage. The supply control signal is generated so that the level is substantially the same as the above. Further, the supply control means stops supplying the object to be weighed by the supply means when the weight measurement value by the weight measurement means coincides with a predetermined supply stop weight value smaller than the target weight value in the small supply stage. Thus, a supply control signal is generated . In addition, the supply control signal in the gradual reduction stage is based on a function of the elapsed time from the supply start time of the object to be weighed by the supply means. And the supply amount per unit time of the to-be-measured object by the supply means in all the stages including the gradual reduction stage has a linear relationship with the supply control signal .

即ち、本発明によれば、供給手段によって供給される被計量物は、その単位時間当たりの供給量が漸減される漸減段階と、これに続く最終の段階であって当該供給量が一定である小供給段階と、を含む複数の段階に分けて、供給される。より具体的には、被計量物は、漸減段階において、小供給段階に切り換わる時点が近づくに連れて時間の経過に対する供給量の変化率(漸減速度)を漸減させると共に、当該切り換わり時点での供給量が小供給段階におけるのと略同じレベルになるように、供給される。これにより、漸減段階から小供給段階に切り換わる時点での供給量の変動が抑えられ、当該切り換わり時点での振動成分の発生が確実に抑制される。また、供給手段による供給済みの被計量物の重量が、重量測定手段によって測定される。この重量測定手段による重量測定値は、小供給段階において、目標重量値よりも小さい所定の供給停止重量値と比較され、当該重量測定値が供給停止重量値と一致したときに、供給手段による被計量物の供給が停止される。これにより、目標重量値分の被計量物を供給する、という定量供給が実現される。この定量供給を実現するための供給手段の動作は、供給制御手段から与えられる供給制御信号に従う。ここで、漸減段階における供給制御信号は、供給手段による被計量物の供給開始時点を基点とする経過時間の関数に基づいて生成される。そして、漸減段階を含む全ての段階における供給手段による被計量物の単位時間当たりの供給量は、供給制御信号に対して線形の関係にある。 That is, according to the present invention, the object to be weighed supplied by the supply means is a gradual decrease stage in which the supply amount per unit time is gradually decreased, and the final stage subsequent thereto, and the supply amount is constant. The supply is divided into a plurality of stages including a small supply stage. More specifically, the object to be weighed gradually decreases the rate of change (gradual decrease rate) of the supply amount over time as the time of switching to the small supply stage approaches in the gradual decrease stage. Is supplied so that the supply amount is approximately the same level as in the small supply stage. Thereby, fluctuations in the supply amount at the time of switching from the gradual reduction stage to the small supply stage are suppressed, and generation of vibration components at the time of switching is reliably suppressed. Further, the weight of the object to be weighed that has been supplied by the supplying means is measured by the weight measuring means. The weight measurement value by the weight measurement means is compared with a predetermined supply stop weight value smaller than the target weight value in the small supply stage, and when the weight measurement value matches the supply stop weight value, The supply of the sample is stopped. Thereby, the quantitative supply of supplying the objects to be weighed for the target weight value is realized. The operation of the supply means for realizing this quantitative supply follows a supply control signal given from the supply control means. Here, the supply control signal in the gradual decrease step is generated based on a function of elapsed time with the supply start time of the object to be weighed by the supply means as a base point. And the supply amount per unit time of the to-be-measured object by the supply means in all the stages including the gradual decrease stage has a linear relationship with the supply control signal.

なお、供給制御手段は、漸減段階の前に、大供給段階を設け、この大供給段階において、被計量物の単位時間当たりの供給量が一定であり、かつ、当該供給量が小供給段階におけるのよりも大きくなるように、供給制御手段を生成してもよい。このような大供給段階が設けられることによって、供給時間全体の短縮化が図られる。この場合、漸減段階における供給量が、大供給段階におけるのと略同じレベルから小供給段階におけるのと略同じレベルまで漸減すると共に、当該漸減段階における供給量の時間に対する変化率が、まず漸増した後に上述の如く漸減するのが、好ましい。これにより、漸減段階における被計量物の総供給量が増大し、ひいては供給時間全体のさらなる短縮化が図られる。ここで、大供給段階においては、供給手段による被計量物の供給開始時点を基点とする上述の経過時間が予め設定された第1切換時点に到達したときに、当該大供給段階から漸減段階に切り換わる。そして、漸減段階においては、当該経過時間が第1切換時点よりも後の予め設定された第2切換時点に到達したときに、漸減段階から小供給段階に切り換わる。併せて、漸減段階においては、当該経過時間が第1切換時点と第2切換時点との間に予め設定された第3切換時点に到達したときに、供給量の時間に対する変化率が漸増する状態から漸減する状態に切り換わる。厳密に言えば、このような要領でそれぞれの切り換えが行われるように供給制御手段が供給制御信号を生成する。また、上述の関数は、第3切換時点における被計量物の単位時間当たりの供給量が所定値であることを条件として定められてもよい。 The supply control means is provided with a large supply stage before the gradual reduction stage. In this large supply stage, the supply amount per unit time of the object to be weighed is constant, and the supply amount is in the small supply stage. The supply control means may be generated so as to be larger than. By providing such a large supply stage, the entire supply time can be shortened. In this case, the supply amount in the gradual reduction stage gradually decreases from approximately the same level as in the large supply stage to approximately the same level as in the small supply stage, and the rate of change of the supply amount in the gradual decrease stage with respect to time first increases gradually. It is preferable to reduce gradually as described above. As a result, the total supply amount of the objects to be weighed in the gradual reduction stage is increased, thereby further shortening the entire supply time. Here, in the large supply stage, when the above-mentioned elapsed time from the supply start time of the object to be weighed by the supply means reaches the preset first switching time, the large supply stage gradually decreases. Switch. In the gradual reduction stage, when the elapsed time reaches a preset second switching time after the first switching time, the gradual reduction stage is switched to the small supply stage. At the same time, in the gradual decrease stage, when the elapsed time reaches a third switching time set in advance between the first switching time and the second switching time, the rate of change of the supply amount with respect to time gradually increases. Switches to a gradually decreasing state. Strictly speaking, the supply control means generates the supply control signal so that each switching is performed in such a manner. Further, the above function may be determined on condition that the supply amount per unit time of the object to be weighed at the third switching time is a predetermined value.

上述したように、本発明によれば、漸減段階から小供給段階に切り換わる時点での振動成分の発生が確実に抑制される。従って、小供給段階において当該振動成分が減衰するのを待つ必要がない。ゆえに、当該振動成分が減衰するのを待つ必要がある第1従来技術および第2従来技術に比べて、小供給段階に掛かる時間を短縮化することができ、ひいては供給時間全体のさらなる短縮化を図ることができる。   As described above, according to the present invention, generation of vibration components at the time of switching from the gradual reduction stage to the small supply stage is reliably suppressed. Therefore, it is not necessary to wait for the vibration component to attenuate in the small supply stage. Therefore, the time required for the small supply stage can be shortened as compared with the first and second prior arts in which it is necessary to wait for the vibration component to be attenuated, thereby further reducing the entire supply time. Can be planned.

本発明の一実施形態の全体構成を示す概略図である。It is the schematic which shows the whole structure of one Embodiment of this invention. 同実施形態における制御装置の内部の電気的構成を示すブロック図である。It is a block diagram which shows the electrical structure inside the control apparatus in the embodiment. 同実施形態における時間の経過に対するゲート開度および重量測定値の推移を特に第2の従来技術のものと比較して示す図解図である。It is an illustration figure which shows especially transition of the gate opening degree and the weight measurement value with respect to passage of time in the same embodiment compared with the thing of the 2nd prior art. 図3の一部を拡大して示す図解図である。It is an illustration figure which expands and shows a part of FIG. 同実施形態におけるCPUによって実行される自動運転タスクの内容を示すフローチャートである。It is a flowchart which shows the content of the automatic driving task performed by CPU in the same embodiment. 図5における供給処理の詳細を示すフローチャートである。It is a flowchart which shows the detail of the supply process in FIG. 図6に続くフローチャートである。It is a flowchart following FIG. 図5における計量処理の詳細を示すフローチャートである。It is a flowchart which shows the detail of the measurement process in FIG. 図5における排出処理の詳細を示すフローチャートである。It is a flowchart which shows the detail of the discharge process in FIG. 同実施形態の別の例を示す概略図である。It is the schematic which shows another example of the embodiment. 第1の従来技術における時間の経過に対するゲート開度および重量測定値の推移を示す図解図である。It is an illustration figure which shows transition of the gate opening degree and weight measurement value with respect to passage of time in 1st prior art. 第2の従来技術における時間の経過に対するゲート開度および重量測定値の推移を示す図解図である。It is an illustration figure which shows transition of the gate opening degree and weight measurement value with respect to passage of time in 2nd prior art.

本発明の一実施形態について、図1〜図10を参照して説明する。   An embodiment of the present invention will be described with reference to FIGS.

本実施形態に係る定量計量装置10は、樹脂ペレットやグラニュー糖のように流動性の高い粉粒状の被計量物100を取り扱うものであり、図1に示すように、当該被計量物100が収容された溜めホッパ12と、この溜めホッパ12の下方に配置されると共に当該溜めホッパ12から被計量物100の供給を受ける計量ホッパ14と、を備えている。溜めホッパ12の底部にある排出口には、開閉ゲート16が設けられており、この開閉ゲート16の開度Gによって、当該溜めホッパ12から計量ホッパ14への被計量物100の単位時間当たりの供給量(流量)Qが制御される。なお、ゲート開度Gと供給量Qとは、(被計量物100の性状(粒度,見かけ比重,粘度等)が一定であることを前提として)互いに相関関係にあり、例えば比例関係にある。従って、供給量Qは、被計量物100の単位時間当りの質量流量と考えてもよい。そして、この関係が維持されるように、溜めホッパ12は計量ホッパ14よりも十分に大きい容積を持ち、かつ、当該溜めホッパ12内に被計量物100が適宜に補充されることによって溜めホッパ12内の被計量物100の収容高さHは常に一定の範囲に保たれている。   The quantitative weighing device 10 according to the present embodiment handles a powder-like weighing object 100 with high fluidity such as resin pellets and granulated sugar, and the weighing object 100 is accommodated as shown in FIG. The reservoir hopper 12 is provided, and a weighing hopper 14 that is disposed below the reservoir hopper 12 and receives the supply of the object 100 from the reservoir hopper 12. An opening / closing gate 16 is provided at the discharge port at the bottom of the reservoir hopper 12, and the opening G of the opening / closing gate 16 causes the object 100 to be weighed from the reservoir hopper 12 to the weighing hopper 14 per unit time. The supply amount (flow rate) Q is controlled. Note that the gate opening degree G and the supply amount Q are correlated with each other (assuming that the properties (particle size, apparent specific gravity, viscosity, etc.) of the object 100 are constant), for example, in a proportional relationship. Therefore, the supply amount Q may be considered as a mass flow rate per unit time of the object 100 to be weighed. In order to maintain this relationship, the reservoir hopper 12 has a sufficiently larger volume than the weighing hopper 14, and the reservoir hopper 12 is appropriately filled with the object 100 to be weighed in the reservoir hopper 12. The accommodation height H of the to-be-measured object 100 is always kept within a certain range.

計量ホッパ14は、荷重センサとしてのロードセル18を備えており、このロードセル18は、自身への印加荷重に応じた電圧値を有するアナログ荷重検出信号Wyを生成する。このアナログ荷重検出信号Wyは、情報出力手段としての液晶型のディスプレイ20を備えた制御装置22に入力される。なお、ロードセル18としては、例えば歪ゲージ式のものが適当であるが、これ以外にも、磁歪式のものや静電容量式,ジャイロ式のもの等が採用可能である。また、ロードセル18以外の荷重センサが採用されてもよい。   The weighing hopper 14 includes a load cell 18 as a load sensor, and the load cell 18 generates an analog load detection signal Wy having a voltage value corresponding to a load applied to itself. The analog load detection signal Wy is input to a control device 22 having a liquid crystal display 20 as information output means. As the load cell 18, for example, a strain gauge type is suitable, but other than this, a magnetostrictive type, a capacitance type, a gyro type type, or the like can be adopted. A load sensor other than the load cell 18 may be employed.

制御装置22は、図2に示すように、増幅回路24を有しており、この増幅回路24に、アナログ荷重検出信号Wyが入力される。この増幅回路24に入力されたアナログ荷重検出信号Wyは、ここで増幅された後、A/D変換回路26に入力される。なお、図には示さないが、増幅回路24の前段または後段には、アナログ荷重検出信号W(t)に含まれる比較的に高い周波数帯域のノイズ成分、主に電気的な要因によるノイズ成分、を除去するためのローパスフィルタ回路が設けられている。   As shown in FIG. 2, the control device 22 includes an amplifier circuit 24, and the analog load detection signal Wy is input to the amplifier circuit 24. The analog load detection signal Wy input to the amplifier circuit 24 is amplified here and then input to the A / D conversion circuit 26. Although not shown in the figure, a noise component of a relatively high frequency band included in the analog load detection signal W (t), a noise component mainly due to electrical factors, is provided at the front stage or the rear stage of the amplifier circuit 24. Is provided with a low-pass filter circuit.

A/D変換回路26は、増幅回路24経由で入力されたアナログ荷重検出信号Wyを、パルス生成手段としてのクロックパルス生成回路28から与えられるクロックパルスCLKの立ち上がり(または立ち下がり)に合わせてサンプリングする。これによって、アナログ荷重検出信号Wyは、デジタル態様の信号に変換される。なお、A/D変換回路26によるサンプリング周期、つまりクロックパルスCLKの周期ΔTは、例えば1[ms]である。   The A / D conversion circuit 26 samples the analog load detection signal Wy input via the amplifier circuit 24 in accordance with the rising edge (or falling edge) of the clock pulse CLK supplied from the clock pulse generation circuit 28 as the pulse generation means. To do. Thereby, the analog load detection signal Wy is converted into a digital signal. The sampling period by the A / D conversion circuit 26, that is, the period ΔT of the clock pulse CLK is, for example, 1 [ms].

A/D変換回路26による変換後のデジタル荷重検出信号Wyは、入出力インタフェース回路30を介して、制御手段としてのCPU(Central
Processing Unit)32に入力され、厳密には、上述のクロックパルスCLKの立ち上がり(または立ち下がり)に合わせて、当該CPU32に取り込まれる。このため、CPU32にも、入出力インタフェース回路30を介して、クロックパルスCLKが与えられる。CPU32は、このデジタル荷重検出信号Wyに基づいて、計量ホッパ14に供給された被計量物100の重量値Wxを求め、さらに、この重量測定値Wxに基づいて、ゲート制御信号Sgを生成する。そして、ゲート制御信号Sgは、入出力インタフェース回路30を介して、D/A変換回路34に入力され、ここでアナログ態様の信号に変換された後、上述した開閉ゲート16を駆動するための後述するサーボアンプ回路36に入力される。また、ゲート制御信号Sgとは別に、CPU32は、排出制御信号Scを生成する。この排出制御信号Scは、入出力インタフェース回路30を介して、後述するシリンダ38に与えられる。
A digital load detection signal Wy after conversion by the A / D conversion circuit 26 is sent to a CPU (Central
Strictly speaking, the data is taken into the CPU 32 in accordance with the rise (or fall) of the clock pulse CLK described above. Therefore, the clock pulse CLK is also given to the CPU 32 via the input / output interface circuit 30. The CPU 32 obtains the weight value Wx of the workpiece 100 supplied to the weighing hopper 14 based on the digital load detection signal Wy, and further generates the gate control signal Sg based on the weight measurement value Wx. The gate control signal Sg is input to the D / A conversion circuit 34 via the input / output interface circuit 30 and is converted into an analog signal here, and then described later for driving the open / close gate 16 described above. To the servo amplifier circuit 36. In addition to the gate control signal Sg, the CPU 32 generates a discharge control signal Sc. The discharge control signal Sc is given to a cylinder 38 to be described later via the input / output interface circuit 30.

CPU32の動作は、当該CPU32に接続された記憶手段としてのメモリ回路40に記憶されている制御プログラムに従う。また、CPU32には、入出力インタフェース回路30を介して、上述したディスプレイ20と、当該CPU32に各種命令を入力するための命令入力手段としての操作キー42と、が接続されている。なお、ディスプレイ20および操作キー42は、互いに一体化されたものでもよく、例えばタッチスクリーンによって構成されてもよい。   The operation of the CPU 32 follows a control program stored in a memory circuit 40 serving as a storage unit connected to the CPU 32. Further, the display 20 described above and an operation key 42 as command input means for inputting various commands to the CPU 32 are connected to the CPU 32 via the input / output interface circuit 30. The display 20 and the operation keys 42 may be integrated with each other, and may be configured by a touch screen, for example.

図1に戻って、サーボアンプ回路36は、制御装置22から入力されたゲート制御信号Sgに基づいて、サーボモータ44を駆動するための駆動信号Sdを生成する。サーボモータ44は、この駆動信号Sdに従って駆動され、その駆動力は、駆動ギア46と従動ギア48とを有する駆動力伝達手段としてのギア機構50を介して、開閉ゲート16に与えられる。これにより、開閉ゲート16が開閉し、つまりゲート開度Gが制御される。さらに、サーボモータ44(回転軸)には、その回転角度を検出するための回転角度検出手段としてのロータリ型のポテンショメータ52が結合されており、このポテンショメータ52から出力される回転角度検出信号Spは、サーボアンプ回路36にフィードバックされる。サーボアンプ回路36は、このフィードバックされた回転角度検出信号Spと、上述のゲート制御信号Sgと、を比較し、さらに、この比較結果に基づいて、希望通りのゲート開度Gとなるように、駆動信号Sdを補正する。   Returning to FIG. 1, the servo amplifier circuit 36 generates a drive signal Sd for driving the servo motor 44 based on the gate control signal Sg input from the control device 22. The servo motor 44 is driven in accordance with the drive signal Sd, and the driving force is given to the open / close gate 16 via a gear mechanism 50 as a driving force transmitting means having a driving gear 46 and a driven gear 48. Thereby, the open / close gate 16 is opened and closed, that is, the gate opening degree G is controlled. Further, a rotary type potentiometer 52 as a rotation angle detection means for detecting the rotation angle is coupled to the servo motor 44 (rotation shaft), and the rotation angle detection signal Sp output from the potentiometer 52 is The feedback is sent to the servo amplifier circuit 36. The servo amplifier circuit 36 compares the feedback rotation angle detection signal Sp with the above-described gate control signal Sg, and further, based on the comparison result, the desired gate opening G is obtained. The drive signal Sd is corrected.

また、計量ホッパ14の底部は、当該計量ホッパ14に供給された被計量物100を排出するための排出口を形成しており、この排出口には、開閉ゲート16とは別のゲート、言わば排出ゲート54、が設けられている。そして、この排出ゲート54を駆動するための駆動手段として、上述したシリンダ38が設けられている。なお、シリンダ38としては、例えば空気圧式のものが適当であるが、油圧式等の当該空気圧式以外のものも採用可能である。また、シリンダ38に代えて、電磁ソレノイドやモータ等の他の駆動手段が採用されてもよい。   The bottom of the weighing hopper 14 forms a discharge port for discharging the object to be weighed 100 supplied to the weighing hopper 14, and this discharge port has a gate different from the open / close gate 16, so to speak. A discharge gate 54 is provided. The cylinder 38 described above is provided as a driving means for driving the discharge gate 54. As the cylinder 38, for example, a pneumatic type is suitable, but a cylinder other than the pneumatic type such as a hydraulic type can also be used. Further, instead of the cylinder 38, other drive means such as an electromagnetic solenoid or a motor may be employed.

このように構成された本実施形態に係る定量供給装置10によれば、次の要領により、被計量物100の定量供給が実現される。   According to the quantitative supply device 10 according to the present embodiment configured as described above, the quantitative supply of the workpiece 100 is realized by the following procedure.

即ち、本実施形態に係る定量供給装置10においても、上述の第1従来技術および第2従来技術と同様、大供給段階,中供給段階としての漸減段階,ならびに小供給段階という3つの段階に分けて、溜めホッパ12から計量ホッパ14へ被計量物100が供給される。そして、小供給段階では、重量測定値Wxが目標重量値Wpよりも落差量d分だけ小さい供給停止重量値Wcと一致したときに、当該被計量物100の供給が停止される。さらに、大供給段階から漸減段階への切り換え、および、漸減段階から小供給段階への切り換え、については、第2従来技術と同様、被計量物100の供給開始時点を基点(t=0)とする経過時間tに基づいて行われる。ただし、漸減段階では、図3(a)に太実線P0で示すように、経過時間tに対するゲート開度Gの関係が概略S字状に推移するように、具体的には、当該経過時間tに対するゲート開度Gの変化率、つまり漸減速度dG/dt、が前半部分で漸増し、後半部分で漸減するように、制御される。なお、図3(a)の太破線P2’は、比較参照用としての第2従来技術における経過時間tとゲート開度Gとの関係を示す(図12(a)に示したのと同じである)。   That is, the quantitative supply device 10 according to the present embodiment is also divided into three stages: a large supply stage, a gradual reduction stage as a middle supply stage, and a small supply stage, as in the first and second conventional techniques described above. Thus, the object to be weighed 100 is supplied from the reservoir hopper 12 to the weighing hopper 14. In the small supply stage, when the weight measurement value Wx matches the supply stop weight value Wc that is smaller than the target weight value Wp by the head d, the supply of the object 100 is stopped. Further, as for the switching from the large supply stage to the gradual reduction stage and the switching from the gradual reduction stage to the small supply stage, as in the second prior art, the supply start time of the object to be weighed 100 is set as the base point (t = 0) This is performed based on the elapsed time t. However, in the gradual decrease stage, as shown by the thick solid line P0 in FIG. 3A, specifically, the elapsed time t is set so that the relationship of the gate opening G with respect to the elapsed time t changes in a substantially S shape. The rate of change of the gate opening G with respect to, that is, the gradually decreasing speed dG / dt, is controlled so as to gradually increase in the first half and gradually decrease in the second half. A thick broken line P2 ′ in FIG. 3A shows the relationship between the elapsed time t and the gate opening G in the second prior art for comparison and reference (the same as shown in FIG. 12A). is there).

より具体的に説明すると、本実施形態においても、経過時間tに基づいて、大供給段階から漸減段階に切り換わる第1切換時点t01と、漸減段階から小供給段階に切り換わる第2切換時点t02とが、予め設定される。そして、被計量物100の供給開始と共に経過時間tが測定され、この経過時間tが第1切換時点t01に到達するまでが、大供給段階とされる。この大供給段階においては、ゲート開度GがG01という比較的に大きな一定値とされ、詳しくは第2従来技術におけるゲート開度G21よりも大きく設定される。これにより、図3(b)に太実線A0で示すように、重量測定値Wxが、当該ゲート開度G01に応じた比較的に高い一定の速度(dWx/dt)で増大する。なお、図3(b)の太破線A2は、第2従来技術における重量測定値Wxの推移を示す(図12(b)において太実線A2で示したのと同じである)。この第2従来技術における重量測定値Wxの推移と比較して分かるように、本実施形態における重量測定値Wxの方が、当該第2従来技術における重量測定値Wxよりも、高い速度で増大する。   More specifically, also in the present embodiment, based on the elapsed time t, the first switching time t01 when the large supply stage switches to the gradual reduction stage and the second switching time t02 when the gradual reduction stage switches to the small supply stage. Are preset. Then, the elapsed time t is measured with the start of the supply of the object to be weighed 100, and the time until the elapsed time t reaches the first switching time t01 is set to the large supply stage. In this large supply stage, the gate opening G is set to a relatively large constant value G01, and more specifically, is set to be larger than the gate opening G21 in the second prior art. As a result, as indicated by the thick solid line A0 in FIG. 3B, the weight measurement value Wx increases at a relatively high constant speed (dWx / dt) corresponding to the gate opening degree G01. In addition, the thick broken line A2 of FIG.3 (b) shows transition of the weight measurement value Wx in 2nd prior art (it is the same as having shown with the thick continuous line A2 in FIG.12 (b)). As can be seen from the transition of the weight measurement value Wx in the second prior art, the weight measurement value Wx in the present embodiment increases at a higher speed than the weight measurement value Wx in the second prior art. .

大供給段階において、経過時間tが第1切換時点t01に到達すると、当該大供給段階から漸減段階に切り換わる。そして、漸減段階においては、次の式3に基づいて、ゲート開度Gが制御される。   In the large supply stage, when the elapsed time t reaches the first switching time t01, the large supply stage is switched to the gradual decrease stage. In the gradual decrease stage, the gate opening degree G is controlled based on the following equation (3).

《式3》
G=k1・t+k2・t+k3・t+k4
<< Formula 3 >>
G = k1 · t 3 + k2 · t 2 + k3 · t + k4

この式3において、k1,k2,k3およびk4は、いずれも定数であり、次の4つの条件が満足されるように決定される。即ち、第1の条件として、経過時間tがt=t01であるときに、ゲート開度GがG=G01であることが、要求される。そして、第2の条件として、経過時間tがt=t02であるときに、ゲート開度GがG=G02であることが、要求される。さらに、第3の条件として、経過時間tがt=t01’であるときに、ゲート開度GがG=G01’であることが、要求される。そして、第4の条件として、経過時間tがt=t02であるときのゲート開度G02が、当該ゲート開度Gの最小値であることが、要求される。なお、G02は、小供給段階のゲート開度Gであり、例えば第2従来技術におけるゲート開度G22と略等価(G02≒G22)であり、言い換えれば、第1従来技術におけるゲート開度G12と略等価(G02≒G12)である。また、t01’は、第1切換時点t01と第2切換時点t02との間の任意の時点(t01<t01’<t02)であり、例えば基点から第2切換時点t02までの期間の約2/3に相当する時点に設定される。さらに、G01’は、大供給段階(第1切換時点t01)のゲート開度G01よりも小さく、かつ、小供給段階(第2切換時点t02)のゲート開度G02よりも大きい、任意のゲート開度G(G02<G01’<G01)であり、例えば大供給段階のゲート開度G01の約1/3の大きさに設定される。そして、第1切換時点t01は、例えば第2従来技術における第1切換時点t21と略同等であり、第2切換時点t02もまた、当該第2従来技術における第2切換時点t22と略同等である。   In Equation 3, k1, k2, k3, and k4 are all constants, and are determined so that the following four conditions are satisfied. That is, as the first condition, when the elapsed time t is t = t01, the gate opening degree G is required to be G = G01. As a second condition, when the elapsed time t is t = t02, the gate opening degree G is required to be G = G02. Further, as a third condition, when the elapsed time t is t = t01 ′, the gate opening degree G is required to be G = G01 ′. As a fourth condition, the gate opening degree G02 when the elapsed time t is t = t02 is required to be the minimum value of the gate opening degree G. Note that G02 is the gate opening degree G in the small supply stage, and is substantially equivalent to the gate opening degree G22 in the second prior art (G02≈G22), in other words, the gate opening degree G12 in the first conventional technique. It is substantially equivalent (G02≈G12). T01 ′ is an arbitrary time point (t01 <t01 ′ <t02) between the first switching time point t01 and the second switching time point t02, and is, for example, about 2 / of the period from the base point to the second switching time point t02. It is set at a time corresponding to 3. Furthermore, G01 ′ is smaller than the gate opening G01 in the large supply stage (first switching time t01) and larger than the gate opening G02 in the small supply stage (second switching time t02). Degree G (G02 <G01 ′ <G01), for example, set to about 1 / of the gate opening degree G01 in the large supply stage. The first switching time t01 is, for example, substantially equivalent to the first switching time t21 in the second prior art, and the second switching time t02 is also substantially equivalent to the second switching time t22 in the second prior art. .

この式3によれば、図3(a)に示した太実線P0からも分かるように、漸減段階におけるゲート開度Gは、時点t01’のゲート開度G01’を変曲点として、経過時間tに対して概略S字状に推移し、いわゆる3次曲線を描くように推移する。より詳しくは、第1切換時点t01から変曲時点t01’までの前半部分は、当該ゲート開度Gの漸減速度dG/dtが漸増するように推移し、変曲時点t01’から第2切換時点t02までの後半部分は、漸減速度dG/dtが漸減するように推移する。そして、最終的に、ゲート開度Gは、小供給段階におけるゲート開度G02と等価になる。このような制御によって、時点t01’を境にして、これよりも前の前半部分で第1実施形態および第2実施形態に比べてより多くの被計量物100の供給が行われ、後半部分で当該被計量物100の供給量Qがより緩やかに減ぜられる。これに伴い、重量測定値Wxは、相応の速度で増大する。なお、上述の第3の条件として、変曲点(t01’,G01’)を明確化するべく、経過時間tがt=t01’であるときの漸減速度dG/dtの変化率dG/dtがdG/dt=0であることが、要求されてもよい。 According to Equation 3, as can be seen from the thick solid line P0 shown in FIG. 3 (a), the gate opening G in the gradual reduction stage is an elapsed time with the gate opening G01 ′ at the time t01 ′ as the inflection point. It changes in a generally S shape with respect to t and changes so as to draw a so-called cubic curve. More specifically, in the first half from the first switching time t01 to the inflection time t01 ′ , the gradual decrease rate dG / dt of the gate opening G changes gradually, and from the inflection time t01 ′ to the second switching time. In the latter half of the period up to t02, the gradual decrease rate dG / dt is gradually decreased. And finally, the gate opening degree G becomes equivalent to the gate opening degree G02 in the small supply stage. By such control, more objects to be weighed 100 are supplied compared to the first embodiment and the second embodiment in the first half before the time t01 ′, and in the second half. The supply amount Q of the object to be weighed 100 is more gradually reduced. Along with this, the weight measurement value Wx increases at a corresponding speed. As the third condition described above, the rate of change d 2 G / decreasing rate dG / dt when the elapsed time t is t = t01 ′ in order to clarify the inflection point (t01 ′, G01 ′). It may be required that dt 2 is d 2 G / dt 2 = 0.

経過時間tが第2切換時点t02に到達すると、漸減段階から小供給段階に切り換わる。小供給段階においては、上述したG02という一定のゲート開度Gとされ、これに伴い、重量測定値Wxが当該ゲート開度G02に応じた一定の低速度で増大する。そして、重量測定値Wxが供給停止重量値Wcと一致(Wx=Wc)した時点t03で、ゲート開度Gがゼロとされ、開閉ゲート16が閉鎖される。これにより、重量測定値Wxは、当該時点t03から落差量d分だけ増大し、目標重量値Wpに近い最終重量値Wsに収束する。   When the elapsed time t reaches the second switching time t02, the gradual reduction stage is switched to the small supply stage. In the small supply stage, the above-described constant gate opening G called G02 is set, and accordingly, the weight measurement value Wx increases at a constant low speed corresponding to the gate opening G02. Then, at the time t03 when the weight measurement value Wx coincides with the supply stop weight value Wc (Wx = Wc), the gate opening G is made zero, and the open / close gate 16 is closed. As a result, the weight measurement value Wx increases by the drop amount d from the time point t03 and converges to the final weight value Ws close to the target weight value Wp.

最終重量値Wsが得られると、当該最終重量値Wsは、上述したディスプレイ20に表示される。そして、排出ゲート54が開かれる。これにより、計量ホッパ14に供給された被計量物100は、当該排出ゲート54を介して排出され、例えば図示しない包装袋に収容される。これをもって、一連の定量供給が終了する。なお、厳密には、最終重量値Wsは、次の式4に基づく移動平均処理によって求められる。この式4において、nは、任意のサンプリング番号である。そして、Mは、タップ数であり、詳しくは1以上の任意の整数である。   When the final weight value Ws is obtained, the final weight value Ws is displayed on the display 20 described above. Then, the discharge gate 54 is opened. As a result, the object to be weighed 100 supplied to the weighing hopper 14 is discharged through the discharge gate 54 and stored in a packaging bag (not shown), for example. This completes a series of quantitative supply. Strictly speaking, the final weight value Ws is obtained by a moving average process based on the following equation 4. In Equation 4, n is an arbitrary sampling number. M is the number of taps, and more specifically an arbitrary integer of 1 or more.

《式4》
Ws={ΣWx[n−m]/M} where m=0〜M−1
<< Formula 4 >>
Ws = {ΣWx [n−m] / M} where m = 0 to M−1

このように、本実施形態によれば、漸減段階におけるゲート開度Gが、その前段の大供給段階におけるゲート開度G01から後段の小供給段階におけるゲート開度G02まで連続的に漸減される。しかも、その漸減速度dG/dtが、当該漸減段階の前半部分で漸増され、後半部分で漸減される。これにより、大供給段階と漸減段階との境界である第1切換時点t01において、ゲート開度Gの変動、つまり被計量物100の供給量Qの変動、が抑えられ、この変動に起因する振動成分の発生が確実に抑制される。これと同様に、漸減段階と小供給段階との境界である第2切換時点t02においても、ゲート開度Gの変動、つまり供給量Qの変動、が抑えられ、この変動に起因する振動成分の発生が確実に抑制される。   Thus, according to this embodiment, the gate opening G in the gradual reduction stage is gradually reduced from the gate opening G01 in the preceding large supply stage to the gate opening G02 in the subsequent small supply stage. In addition, the gradually decreasing speed dG / dt is gradually increased in the first half of the gradually decreasing stage and gradually decreased in the latter half. As a result, at the first switching time t01, which is the boundary between the large supply stage and the gradual reduction stage, fluctuations in the gate opening G, that is, fluctuations in the supply amount Q of the object 100 to be measured, are suppressed. Generation of components is reliably suppressed. Similarly, at the second switching time t02, which is the boundary between the gradual reduction stage and the small supply stage, the fluctuation of the gate opening G, that is, the fluctuation of the supply amount Q is suppressed, and the vibration component caused by this fluctuation is reduced. Generation is reliably suppressed.

従って、特に、小供給段階において当該振動成分が減衰するのを待つ必要がないので、小供給段階に掛かる時間T0(=t03−t02)を短縮化することができ、ひいては供給時間全体の短縮化を図ることができる。なお、小供給時間T0を短縮するとは、第2切換時点t02での被計量物100の供給重量値W02を供給停止重量値Wcに近づけることを意味し、つまりこれら両者の間隔(=Wc−W02)を狭めることを意味する。因みに、第2従来技術において、第2切換時点t22での被計量物の供給重量値W22が供給停止重量値Wcに近づけられると、当該第2切換時点t22で発生する振動成分の影響によって、この振動成分を含む重量測定値Wxが本来の供給停止時点t23よりも早い時点で供給停止重量値Wcを超えてしまい、その時点で被計量物の供給が停止される、という不都合が生じる恐れがある。このことは、第1従来技術についても、同様である。即ち、第1従来技術において、第2切換重量値W12が供給停止重量値Wcに近づけられると、重量測定値Wxが当該第2切換重量値W12に到達した時点t12で発生する振動成分の影響によって、この振動成分を含む当該重量測定値Wxが本来の供給停止時点t13よりも早い時点で供給停止重量値Wcを超えてしまい、その時点で被計量物の供給が停止される。本実施形態によれば、このような不都合が生じないので、この点でも、本実施形態は有益である。   Therefore, it is not particularly necessary to wait for the vibration component to be attenuated in the small supply stage, so that the time T0 (= t03−t02) required for the small supply stage can be shortened, and thus the entire supply time can be shortened. Can be achieved. Note that shortening the small supply time T0 means that the supply weight value W02 of the workpiece 100 at the second switching time t02 is brought close to the supply stop weight value Wc, that is, an interval between them (= Wc−W02). ) Means narrowing. Incidentally, in the second prior art, when the supply weight value W22 of the object to be weighed at the second switching time t22 approaches the supply stop weight value Wc, this is caused by the influence of the vibration component generated at the second switching time t22. There is a concern that the weight measurement value Wx including the vibration component exceeds the supply stop weight value Wc at a time earlier than the original supply stop time t23, and the supply of the object to be measured is stopped at that time. . The same applies to the first prior art. That is, in the first prior art, when the second switching weight value W12 is brought close to the supply stop weight value Wc, the influence of the vibration component generated at the time t12 when the weight measurement value Wx reaches the second switching weight value W12. The weight measurement value Wx including the vibration component exceeds the supply stop weight value Wc at an earlier time than the original supply stop time t13, and supply of the object to be measured is stopped at that time. According to the present embodiment, such inconvenience does not occur, and this embodiment is advantageous also in this respect.

また、本実施形態においては、第2従来技術と同様に、被計量物100の供給開始時点からの経過時間tに基づいて各段階の切り換えが行われるが、例えば小供給段階に注目すると、当該第2従来技術に比べて、次のような利点がある。   In the present embodiment, as in the second prior art, each stage is switched based on the elapsed time t from the supply start time of the object to be weighed 100. For example, when focusing on the small supply stage, Compared to the second prior art, there are the following advantages.

即ち、本実施形態において、稼働中に被計量物100の性状を含む諸状況が変化すると、同じゲート開度Gであっても、当該被計量物100の供給量Qが変わることがある。特に、この供給量Qが増えると、図3の一部拡大図である図4の(b)に1点鎖線A0’で示すように、第2切換時点t02よりも前の或る時点t02’で、重量測定値Wxが当該第2切換時点t02における本来の(理想的な)値W02を超える。ただし、この時点t02’では、まだ、漸減段階から小供給段階へは切り換わらない。従って、同時点t02’におけるゲート開度G02’は、図4(a)に太実線P0で示すように、小供給段階における開度G02よりも少し大きい(>G02)。そして、同時点t02’から第2切換時点t02に掛けて、ゲート開度Gは漸減し、併せて、当該ゲート開度Gの漸減速度dG/dtもまた漸減する。そして、第2切換時点t02において、ゲート開度GはG=G02となり、当該ゲート開度Gの漸減速度dG/dtはdG/dt=0となる。これにより、ゲート開度Gが漸減する漸減段階から当該ゲート開度Gが一定とされる小供給段階へと緩やかに切り換わる。小供給段階においては、G=G02というゲート開度Gが維持され、重量測定値Wxが供給停止重量値Wcに到達した時点t03’で、当該ゲート開度Gはゼロとされる。この結果、このゲート開度Gがゼロとされる実際の供給停止時点t03’は、本来の供給停止時点t03よりも前に到来し、その分、実際の小供給時間T0’(=t03’−t02)は、本来の小供給時間T0よりも短くなる(T0’<T0)。このように実際の小供給時間T0’が短くなることによって、上述した振動成分による影響が懸念されるが、本実施形態によれは、当該振動成分の発生が確実に抑制されるので、そのような懸念はない。つまり、実際の供給停止時点t03’が正確に捉えられる。ゆえに、被計量物100の供給量Qが変わっても、供給精度が低下することはない。しかも、小供給時間T0’が短くなることによって、その分、供給時間全体がさらに短縮され、より好ましい状態となる。   That is, in the present embodiment, when various conditions including the properties of the object to be weighed 100 change during operation, the supply amount Q of the object to be weighed 100 may change even at the same gate opening G. In particular, when the supply amount Q increases, as shown by a one-dot chain line A0 ′ in FIG. 4B which is a partially enlarged view of FIG. 3, a certain time t02 ′ before the second switching time t02. Thus, the weight measurement value Wx exceeds the original (ideal) value W02 at the second switching time t02. However, at this time t02 ', the gradual reduction stage has not yet switched to the small supply stage. Therefore, the gate opening degree G02 'at the simultaneous point t02' is slightly larger than the opening degree G02 in the small supply stage (> G02) as shown by the thick solid line P0 in FIG. Then, from the simultaneous point t02 'to the second switching time point t02, the gate opening degree G gradually decreases, and at the same time, the gradually decreasing speed dG / dt of the gate opening degree G also gradually decreases. At the second switching time t02, the gate opening degree G becomes G = G02, and the gradual decrease speed dG / dt of the gate opening degree G becomes dG / dt = 0. As a result, a gradual switching from the gradually decreasing stage in which the gate opening G gradually decreases to the small supply stage in which the gate opening G is constant is performed. In the small supply stage, the gate opening G of G = G02 is maintained, and the gate opening G is made zero at time t03 'when the weight measurement value Wx reaches the supply stop weight value Wc. As a result, the actual supply stop time t03 ′ at which the gate opening G is zero arrives before the original supply stop time t03, and the actual small supply time T0 ′ (= t03′− t02) is shorter than the original small supply time T0 (T0 ′ <T0). Although the actual small supply time T0 ′ is shortened in this way, there is a concern about the influence of the vibration component described above. However, according to the present embodiment, the generation of the vibration component is surely suppressed. There is no serious concern. That is, the actual supply stop time t03 'can be accurately captured. Therefore, even if the supply amount Q of the weighing object 100 changes, the supply accuracy does not decrease. In addition, since the small supply time T0 'is shortened, the entire supply time is further shortened accordingly, and a more preferable state is obtained.

これに対して、第2従来技術では、稼働中に被計量物の単位時間当りの供給量が増えると、図4(b)に2点鎖線A2’で示すように、第2切換時点t22よりも前の或る時点t22’で、重量測定値Wxが当該第2切換時点t22における本来の値W22を超える。その一方で、同時点t22’におけるゲート開度G22’は、図4(a)に太破線P2’で示すように、小供給段階における開度G22よりもかなり大きい(G22’>G22)。従って、実際の供給停止時点t23’は、本来の供給停止時点t23よりもかなり前に到来し、その分、実際の小供給時間T2’(=t23’−t22)は、本来の小供給時間T2よりもかなり短くなる(T2’<T2)。そうすると、第2従来技術では、本実施形態とは異なり、小供給段階の始期である第2切換時点t22において上述の如く(当該第2切換時点t22の前後の短い期間中にゲート開度Gが急変することによる)振動成分が発生するため、この振動成分が減衰するのを待つ必要があるが、このように小供給時間T2’が短くなることによって、その待ち時間を確保することができなくなる。この結果、振動成分が減衰しないうちに供給停止時点t23’が捉えられることになり、ひいては供給精度が低下する。これを回避するには、元々の小供給時間T2を長めに設定する、つまり第2切換時点t22における重量値W22をより小さめに設定すればよいが、これでは、小供給時間T2を含む供給時間全体が長くなり、やはり不都合である。この点を比較しても、本実施形態は極めて有益である。   On the other hand, in the second prior art, when the supply amount of the object to be weighed increases during operation, as indicated by a two-dot chain line A2 ′ in FIG. 4B, from the second switching time t22. At a certain previous time point t22 ′, the weight measurement value Wx exceeds the original value W22 at the second switching time point t22. On the other hand, the gate opening G22 'at the simultaneous point t22' is considerably larger than the opening G22 in the small supply stage (G22 '> G22) as shown by the thick broken line P2' in FIG. Accordingly, the actual supply stop time t23 ′ arrives much before the original supply stop time t23, and the actual small supply time T2 ′ (= t23′−t22) is equivalent to the original small supply time T2. (T2 ′ <T2). Then, in the second prior art, unlike the present embodiment, at the second switching time t22, which is the beginning of the small supply stage, as described above (the gate opening G is set during the short period before and after the second switching time t22). Since a vibration component is generated (due to a sudden change), it is necessary to wait for the vibration component to attenuate. However, since the small supply time T2 ′ is shortened in this way, the waiting time cannot be secured. . As a result, the supply stop time t23 'is captured before the vibration component is attenuated, and the supply accuracy is lowered. In order to avoid this, the original small supply time T2 may be set longer, that is, the weight value W22 at the second switching time t22 may be set smaller, but in this case, the supply time including the small supply time T2 The whole becomes long and is also inconvenient. Even if this point is compared, this embodiment is very useful.

さらに、図3に戻って、大供給段階に注目すると、この図3の(a)に示すように、本実施形態における当該大供給段階のゲート開度G01は、第2従来技術における大供給段階のゲート開度G21よりも大きい。従って、この大供給段階における被計量物100の総供給量は、本実施形態の方が、第2従来技術よりも多い。このこともまた、本実施形態による供給時間全体の短縮化に大きく貢献する。これは、第1従来技術との比較においても、同様である。   Further, returning to FIG. 3 and paying attention to the large supply stage, as shown in FIG. 3A, the gate opening G01 of the large supply stage in the present embodiment is the large supply stage in the second prior art. Is larger than the gate opening G21. Therefore, the total supply amount of the objects to be weighed 100 in this large supply stage is larger in the present embodiment than in the second prior art. This also greatly contributes to shortening of the entire supply time according to the present embodiment. This is the same in the comparison with the first prior art.

このような有益な効果が得られるようにするためには、上述したt01,t01’およびt02という経過時間tに係るパラメータと、G01,G01’およびG02というゲート開度Gに係るパラメータと、が適切に設定される必要がある。そのために、本実施形態では、調整モードによる事前の調整作業が行われる。   In order to obtain such a beneficial effect, the above-described parameters related to the elapsed time t such as t01, t01 ′ and t02 and the parameters related to the gate opening degree G such as G01, G01 ′ and G02 are: It needs to be set appropriately. For this purpose, in the present embodiment, a pre-adjustment operation in the adjustment mode is performed.

具体的には、まず、図2に示した操作キー42の操作によって、調整モードが選択される。続いて、当該操作キー42の操作によって、希望の目標重量値Wpと、これに見合う供給停止重量値Wcとが、設定される。併せて、大供給段階のゲート開度G01と、小供給段階のゲート開度G02とが、適当に仮設定され、例えば第1従来技術におけるのと同程度のG01=G11およびG02=G12とされる。さらに、第1従来技術に倣って、第1切換重量値W01と、第2切換重量値W02とが、適当に仮設定され、例えばW01=W11およびW02=W12とされる。その上で、第1従来技術と同様の要領で仮の定量供給が実行される。なお、この仮の定量供給の実行においては、後述するように、重量測定値WxがW01,W02およびWcという各重量値に到達した時点t01,t02およびt03が捉えられ、これらの時点(厳密には基点(t=0)から各時点までの時間)t01,t02およびt03はディスプレイ20に表示される。   Specifically, first, the adjustment mode is selected by operating the operation key 42 shown in FIG. Subsequently, by operating the operation key 42, a desired target weight value Wp and a supply stop weight value Wc corresponding to the target weight value Wp are set. In addition, the gate opening G01 in the large supply stage and the gate opening G02 in the small supply stage are appropriately provisionally set, for example, G01 = G11 and G02 = G12, which are the same as those in the first prior art. The Further, following the first prior art, the first switching weight value W01 and the second switching weight value W02 are appropriately provisionally set, for example, W01 = W11 and W02 = W12. After that, provisional quantitative supply is executed in the same manner as in the first prior art. In the execution of this provisional quantitative supply, as will be described later, the time points t01, t02 and t03 when the weight measurement values Wx reach the respective weight values W01, W02 and Wc are captured. (Base time (time from t = 0) to each time point) t01, t02 and t03 are displayed on the display 20.

即ち、被計量物100の供給開始時点(t=0)から重量測定値Wxが仮設定された第1切換重量値W01に到達するまでが、G01というゲート開度Gによる大供給段階とされる。そして、重量測定値Wxが第1切換重量値W01に到達した時点で、大供給段階から漸減段階に切り換わり、その時点が、第1切換時点t01として仮設定される。この仮設定された第1切換時点t01は、仮設定された大供給段階のゲート開度G01および仮設定された第1切換重量値t01と共に、ディスプレイ20に表示される。   That is, a large supply stage with a gate opening G of G01 is set from the supply start time (t = 0) of the object to be weighed 100 until the weight measurement value Wx reaches the temporarily set first switching weight value W01. . Then, when the weight measurement value Wx reaches the first switching weight value W01, the large supply stage is switched to the gradual reduction stage, and that point is temporarily set as the first switching time t01. The temporarily set first switching time t01 is displayed on the display 20 together with the temporarily set large opening stage gate opening G01 and the temporarily set first switching weight value t01.

漸減段階においては、上述した式1に準拠する次の式5に基づいて、ゲート開度Gが制御される。なお、この式5における冪定数αについては、0<α≦1の範囲で適当に設定される。   In the gradual reduction stage, the gate opening degree G is controlled based on the following formula 5 based on the formula 1 described above. Note that the power constant α in Equation 5 is appropriately set in the range of 0 <α ≦ 1.

《式5》
G=(G01−G02)・{(W02−Wx)/(W02−W01)}α+G02
<< Formula 5 >>
G = (G01−G02) · {(W02−Wx) / (W02−W01)} α + G02

この漸減段階は、重量測定値Wxが仮設定された第2切換重量値W02に到達するまで継続され、その時点が到来すると、小供給段階に切り換わる。併せて、当該時点が、第2切換時点t02として仮設定される。なお、この仮設定された第2切換時点t02におけるゲート開度Gは、G=G02となる。そして、この仮設定された第2切換時点t02もまた、当該G02というゲート開度Gおよび仮設定された第2切換時点t02と共に、ディスプレイ20に表示される。   This gradual reduction stage is continued until the weight measurement value Wx reaches the temporarily set second switching weight value W02, and when that time comes, the small supply stage is switched. In addition, this time point is temporarily set as the second switching time point t02. Note that the gate opening degree G at the temporarily set second switching time point t02 is G = G02. The temporarily set second switching time t02 is also displayed on the display 20 together with the gate opening G of G02 and the temporarily set second switching time t02.

小供給段階においては、G02という一定のゲート開度Gで被計量物100が供給され、重量測定値Wxが供給停止重量値Wcに到達すると、その時点で、当該ゲート開度Gがゼロとされる。そして、このゲート開度Gがゼロとされた時点は、仮の供給停止時点t03として特定され、この特定された仮の供給停止時点t03は、供給停止重量値Wcと共に、ディスプレイ20に表示される。   In the small supply stage, the workpiece 100 is supplied at a constant gate opening G of G02, and when the weight measurement value Wx reaches the supply stop weight value Wc, the gate opening G is set to zero at that time. The The time point when the gate opening degree G is zero is specified as a temporary supply stop time point t03, and the specified temporary supply stop time point t03 is displayed on the display 20 together with the supply stop weight value Wc. .

このように仮の定量供給が実行されることによって、第1切換時点t01と第2切換時点t02とが仮設定され、併せて、仮の供給停止時点t03が一種の目安(指標)として特定される。そして、これらは(t01,G01,W01),(t02,G02,W02)および(t03,Wc)という関係で表示される。従って、オペレータは、この表示を参照することで、経過時間tに対するゲート開度Gおよび重量測定値Wxそれぞれの推移を認識することができる。なお、仮の定量供給が複数回実行されることによって、これらの関係が平均化されたものが表示されてもよい。   By executing the provisional quantitative supply in this manner, the first switching time t01 and the second switching time t02 are provisionally set, and the provisional supply stop time t03 is specified as a kind of guide (index). The These are displayed in a relationship of (t01, G01, W01), (t02, G02, W02) and (t03, Wc). Therefore, the operator can recognize the transition of the gate opening degree G and the weight measurement value Wx with respect to the elapsed time t by referring to this display. In addition, the provisional quantitative supply may be executed a plurality of times, and an average of these relationships may be displayed.

続いて、上述した変曲時点t01’と、これに対応するゲート開度G01’とが、適当に仮設定される。この条件の下、上述した式3が組み立てられ、つまり当該式3における各定数k1,k2,k3およびk4が求められる。その上で、今度は、本実施形態で説明した要領による定量供給が仮実行される。   Subsequently, the above-described inflection time t01 'and the corresponding gate opening G01' are provisionally set appropriately. Under this condition, the above-described expression 3 is assembled, that is, the constants k1, k2, k3, and k4 in the expression 3 are obtained. In addition, this time, the quantitative supply according to the procedure described in the present embodiment is provisionally executed.

即ち、被計量物100の供給開始時点(t=0)からの経過時間tが測定され、この経過時間tが仮設定された第1切換時点t01に到達するまでが、G01というゲート開度Gによる大供給段階とされる。そして、経過時間tが第1切換時点t01に到達すると、大供給段階から漸減段階に切り換わる。なお、第1切換時点t01における重量測定値Wxが、当該第1切換時点t01における目安的な重量値W01として改めて特定され、この特定された重量値W01は、第1切換時点t01および大供給段階のゲート開度G01と共に、ディスプレイ20に表示される。   That is, the elapsed time t from the supply start time (t = 0) of the object to be weighed 100 is measured, and until the elapsed time t reaches the temporarily set first switching time t01, the gate opening G called G01. According to the large supply stage. When the elapsed time t reaches the first switching time t01, the large supply stage is switched to the gradual reduction stage. It should be noted that the weight measurement value Wx at the first switching time point t01 is specified again as a reference weight value W01 at the first switching time point t01, and the specified weight value W01 is determined based on the first switching time point t01 and the large supply stage. Are displayed on the display 20 together with the gate opening G01.

漸減段階においては、上述した式3に基づいて、ゲート開度Gが制御される。そして、ゲート開度Gの漸減速度dG/dtの変化率dG/dtが逐次求められ、この変化率dG/dtがdG/dt=0となる時点が、変曲時点t01’として改めて設定される。併せて、この変曲時点t01’におけるゲート開度Gが、G01’として改めて設定される。そして、これら変曲時点t01’およびゲート開度G01’は、当該変曲時点t01’における重量測定値W01’と共に、ディスプレイ20に表示される。 In the gradual reduction stage, the gate opening degree G is controlled based on the above-described Expression 3. Then, the rate of change d 2 G / dt 2 of the gradual decrease rate dG / dt of the gate opening degree G is sequentially obtained, and the time when the rate of change d 2 G / dt 2 becomes d 2 G / dt 2 = 0 is changed. It is set anew as the music time t01 '. At the same time, the gate opening G at the inflection time t01 ′ is newly set as G01 ′. The inflection time t01 ′ and the gate opening G01 ′ are displayed on the display 20 together with the weight measurement value W01 ′ at the inflection time t01 ′.

経過時間tが仮設定された第2切換時点t02に到達すると、ゲート開度GがG=G02となり、漸減段階から小供給段階に切り換わる。そして、この第2切換時点t02における重量測定値Wxが、当該第2切換時点t02における目安的な重量値W02として改めて特定され、この特定された重量値W02は、第2切換時点t02およびG02というゲート開度Gと共に、ディスプレイ20に表示される。   When the elapsed time t reaches the temporarily set second switching time t02, the gate opening G becomes G = G02, and the gradual decrease stage is switched to the small supply stage. Then, the weight measurement value Wx at the second switching time t02 is specified again as a reference weight value W02 at the second switching time t02, and the specified weight value W02 is referred to as second switching times t02 and G02. It is displayed on the display 20 together with the gate opening degree G.

小供給段階においては、G02という一定のゲート開度Gで被計量物100が供給され、重量測定値Wxが供給停止重量値Wcに到達すると、その時点で、当該ゲート開度Gがゼロとされる。そして、このゲート開度Gがゼロとされた時点は、供給停止時点t03として改めて特定され、この特定された供給停止時点t03は、供給停止重量値Wcと共に、ディスプレイ20に表示される。   In the small supply stage, the workpiece 100 is supplied at a constant gate opening G of G02, and when the weight measurement value Wx reaches the supply stop weight value Wc, the gate opening G is set to zero at that time. The Then, the time when the gate opening degree G is zero is specified again as the supply stop time t03, and the specified supply stop time t03 is displayed on the display 20 together with the supply stop weight value Wc.

このように仮実行された定量供給によって、経過時間tに対するゲート開度Gおよび重量測定値Wxの推移が、(t01,G01,W01),(t01’,G01’,W01’),(t02,G02,W02)および(t03,Wc)という関係を含めて、認識される。ここで、大供給段階のゲート開度G01は、基本的にG01=G11であるが、これがG01>G11となるように設定し直される。併せて、第2切換時点t02における重量値W02は、基本的にW02=W12であるが、これがW02<Wcという条件を満足しつつW02>W12となるように設定し直される。さらに、第2切換時点t02が早められる。このように設定し直された上で、改めて式3が組み立てられ、本実施形態で説明した要領による定量供給が再度仮実行される。   The transition of the gate opening G and the weight measurement value Wx with respect to the elapsed time t is (t01, G01, W01), (t01 ′, G01 ′, W01 ′), (t02, G02, W02) and (t03, Wc) are recognized. Here, the gate opening G01 in the large supply stage is basically G01 = G11, but is reset so that G01> G11. At the same time, the weight value W02 at the second switching time t02 is basically W02 = W12, but is reset so that W02> W12 while satisfying the condition of W02 <Wc. Further, the second switching time t02 is advanced. After resetting in this way, Equation 3 is reassembled, and the quantitative supply according to the procedure described in this embodiment is temporarily executed again.

この結果、少なくとも供給停止時点t03が早まり、供給時間全体が短縮化される。一方、供給精度については、所期の精度(つまり第1従来技術および第2従来技術よりも高い精度)が得られることが必須であり、そうでない場合には、上述の大供給段階のゲート開度G01,第2切換時点t02における重量値W02および第2切換時点t02が設定し直される。なお、第1切換時点t01や変曲時点t01’、或いは当該変曲時点t01’におけるゲート開度G01’等の他のパラメータが適宜設定し直されてもよい。いずれにしても、所期の供給精度が得られると共に、供給時間全体の短縮化が図られるように、各パラメータが設定される。また、この作業が複数回にわたって繰り返されれば、確実性が向上する。   As a result, at least the supply stop time t03 is advanced, and the entire supply time is shortened. On the other hand, regarding the supply accuracy, it is essential to obtain the desired accuracy (that is, higher accuracy than the first conventional technology and the second conventional technology). Otherwise, the gate opening at the large supply stage described above is required. The degree G01, the weight value W02 at the second switching time t02, and the second switching time t02 are reset. Note that other parameters such as the first opening time t01, the inflection time t01 ', or the gate opening G01' at the inflection time t01 'may be reset as appropriate. In any case, each parameter is set so that the desired supply accuracy can be obtained and the entire supply time can be shortened. Further, if this operation is repeated a plurality of times, the reliability is improved.

この調整作業の後、稼働モードによる実際の稼働運転が上述した要領で成されるが、当該稼働運転時においては、CPU32は、上述した制御プログラムに従って、次のように動作する。   After this adjustment work, the actual operation operation in the operation mode is performed as described above. During the operation operation, the CPU 32 operates as follows according to the control program described above.

即ち、CPU32は、クロックパルスCLKの立ち上がりが到来すると、図5に示す自動運転タスクのステップS1に進む。そして、このステップS1において、所定のフラグFsに“1”が設定されているか否かを判定する。このフラグFsは、後述するステップS3の供給処理,ステップS5の計量処理,およびステップS7の排出処理のいずれかが実行されている途中であるか否かを表す指標であり、当該フラグFsが“1”であれば、いずれかの処理が実行されている途中であることを表し、当該フラグFsが“0”であれば、いずれの処理も実行されていないことを表す。なお、稼働運転の開始直後は、このフラグFsには“0”が設定されており、この場合、CPU32は、ステップS9に進む。   That is, when the rising edge of the clock pulse CLK arrives, the CPU 32 proceeds to step S1 of the automatic operation task shown in FIG. In step S1, it is determined whether or not “1” is set in the predetermined flag Fs. The flag Fs is an index indicating whether or not any of a supply process in step S3, a metering process in step S5, and a discharge process in step S7, which will be described later, is being executed. “1” indicates that any process is being executed, and if the flag Fs is “0”, it indicates that any process is not being executed. Note that “0” is set in the flag Fs immediately after the start of the operation operation. In this case, the CPU 32 proceeds to step S9.

ステップS9において、CPU32は、定量供給を開始する準備が整っているか否か、詳しくは、計量ホッパ14が空の状態であり、かつ、排出ゲート54が閉じられた状態にあるか否か、を判定する。この判定は、他のタスクでの結果に基づいて成され、当該準備が整っていない場合には、一旦、この自動運転タスクを終了する。一方、準備が整っている場合には、CPU32は、ステップS11に進む。   In step S9, the CPU 32 determines whether or not preparation for starting the quantitative supply is complete, specifically, whether or not the weighing hopper 14 is empty and the discharge gate 54 is closed. judge. This determination is made based on the results of other tasks, and when the preparation is not complete, the automatic operation task is temporarily terminated. On the other hand, if the preparation is complete, the CPU 32 proceeds to step S11.

ステップS11において、CPU32は、上述とは別のフラグFaに“1”を設定する。このフラグFaは、上述したステップS3の供給処理が実行中であるか否かを表す指標であり、当該フラグFaが“1”であれば、ステップS3の供給処理が実行中であることを表し、当該フラグFaが“0”であれば、ステップS4の供給処理が実行されていないことを表す。つまり、このステップS11では、当該フラグFaに“1”を設定することによって、CPU32は、これからステップS3の供給処理を実行することを宣言する。なお、稼働運転の開始直後は、フラグFaには“0”が設定されている。そして、CPU32は、次のステップS13に進み、上述したフラグFsに“1”を設定した後、ステップS3に進む。   In step S11, the CPU 32 sets “1” to a flag Fa different from that described above. This flag Fa is an index indicating whether or not the supply process in step S3 described above is being executed. If the flag Fa is “1”, it indicates that the supply process in step S3 is being executed. If the flag Fa is “0”, it indicates that the supply process of step S4 is not executed. That is, in this step S11, by setting “1” in the flag Fa, the CPU 32 declares that the supply process of step S3 will be executed from now on. Note that “0” is set in the flag Fa immediately after the start of the operation operation. Then, the CPU 32 proceeds to the next step S13, sets “1” to the flag Fs described above, and then proceeds to step S3.

このステップS3の詳細については、後で説明するが、このステップS3においては、上述したゲート開度制御方式による被計量物100の供給が行われる。そして、このステップS3の実行後、CPU32は、ステップS5の計量処理に進み、ここで、最終重量値Wsを求める。このステップS5の詳細についても、後で説明する。さらに、CPU32は、ステップS5の実行後、ステップS7の排出処理に進む。このステップS7の詳細についても、後述するが、このステップS7おいては、計量ホッパ14に供給された被処理物100が当該計量ホッパ14から排出される。そして、このステップS7の実行を終えることで、一連の定量供給が終了する。   Although details of this step S3 will be described later, in this step S3, the object to be weighed 100 is supplied by the above-described gate opening control method. And after execution of this step S3, CPU32 progresses to the measurement process of step S5, and calculates | requires final weight value Ws here. Details of step S5 will also be described later. Furthermore, after executing step S5, the CPU 32 proceeds to the discharging process of step S7. Although details of step S7 will also be described later, in this step S7, the workpiece 100 supplied to the weighing hopper 14 is discharged from the weighing hopper 14. And a series of fixed supply is complete | finished by finishing execution of this step S7.

さて、ステップS3の供給処理においては、CPU32は、図6に示すサブルーチンに入る。即ち、CPU32は、まず、ステップS101に進み、上述したフラグFaに“1”が設定されているか否かを判定する。ここで、例えば、このフラグFaに“1”が設定されていない場合、CPU32は、そのまま当該供給処理を終えて、次のステップS5の計量処理に進む。一方、フラグFaに“1”が設定されている場合には、CPU32は、ステップS103に進む。   In the supply process of step S3, the CPU 32 enters a subroutine shown in FIG. That is, the CPU 32 first proceeds to step S101 and determines whether or not “1” is set in the above-described flag Fa. Here, for example, when “1” is not set in the flag Fa, the CPU 32 ends the supply process as it is, and proceeds to the weighing process in the next step S5. On the other hand, when “1” is set in the flag Fa, the CPU 32 proceeds to step S103.

ステップS103において、CPU32は、上述したデジタル荷重検出信号Wyに基づいて重量測定値Wxを求める。そして、CPU32は、ステップS105に進み、経過時間tをカウントするためのカウンタのカウント値Ctを“1”だけインクリメントする。なお、稼働運転の開始直後は、この時間カウント値Ctは“0”とされており、つまりリセットされている。   In step S103, the CPU 32 obtains the weight measurement value Wx based on the digital load detection signal Wy described above. Then, the CPU 32 proceeds to step S105 and increments the count value Ct of the counter for counting the elapsed time t by “1”. Note that immediately after the start of the operation operation, the time count value Ct is set to “0”, that is, reset.

ステップS105の実行後、CPU32は、ステップS107に進み、ここで、ゲート開度Gを管理するためのカウンタのカウント値Cgが“0”であるか否かを判定する。なお、このゲート開度カウント値Cgもまた、稼働運転の開始直後にリセットされる。従って、当該稼働運転開始直後は、このゲート開度カウント値Cgは“0”であり、この場合、CPU32は、大供給段階を実行するべく、ステップS109に進む。   After executing step S105, the CPU 32 proceeds to step S107, and determines whether or not the count value Cg of the counter for managing the gate opening degree G is “0”. The gate opening count value Cg is also reset immediately after the start of the operation operation. Therefore, immediately after the start of the operation, the gate opening count value Cg is “0”. In this case, the CPU 32 proceeds to step S109 to execute the large supply stage.

ステップS109において、CPU32は、ゲート開度GをG01とするための準備をする。そして、ステップS111において、当該ゲート開度Gを実際にG01とするよう開閉ゲート16を制御し、詳しくはゲート制御信号Sgを生成する。これによって、大供給段階が実行される。   In step S109, the CPU 32 makes preparations for setting the gate opening degree G to G01. In step S111, the open / close gate 16 is controlled so that the gate opening G is actually set to G01. Specifically, a gate control signal Sg is generated. As a result, the large supply phase is executed.

そして、CPU32は、ステップS113に進み、上述した時間カウント値Ctと、調整作業で得られた第1の閾値Ct01と、を比較する。この第1閾値Ct01は、第1切換時点t01に対応し、具体的には当該第1切換時点t01を時間カウント値Ctに換算したものである。このステップS113において、例えば当該時間カウント値Ctが第1閾値Ct01未満(Ct<Ct01)である場合、つまり経過時間tが第1切換時点t01に到達していない場合、CPU32は、一旦、このステップS5の供給処理を終了する。一方、時間カウント値Ctが第1閾値Ct01以上(Ct≧Ct01)である場合、つまり経過時間tが第1切換時点t01に到達した場合は、ステップS115に進む。   Then, the CPU 32 proceeds to step S113, and compares the above-described time count value Ct with the first threshold value Ct01 obtained by the adjustment work. The first threshold value Ct01 corresponds to the first switching time point t01. Specifically, the first switching time point t01 is converted into a time count value Ct. In this step S113, for example, when the time count value Ct is less than the first threshold value Ct01 (Ct <Ct01), that is, when the elapsed time t has not reached the first switching time t01, the CPU 32 temporarily performs this step. The supply process of S5 is terminated. On the other hand, if the time count value Ct is greater than or equal to the first threshold Ct01 (Ct ≧ Ct01), that is, if the elapsed time t has reached the first switching time t01, the process proceeds to step S115.

ステップS115において、CPU32は、今現在の重量測定値Wxを予め用意された重量値レジスタRwに記憶させる。さらに、CPU32は、ステップS117に進み、今現在の時間カウント値Ctを予め用意された時間レジスタRtに記憶させる。そして、ステップS119に進み、これら重量値レジスタRwに記憶された重量測定値Wxと時間レジスタRtに記憶された時間カウント値Ctとをディスプレイ20に表示させる。なお、このステップS119で表示される重量測定値Wxは、第1切換時点t01における被計量物100の供給済み重量値W01(Wx=W01)である。また、当該ステップS119で表示される時間カウント値Ctに代えて、今現在の経過時間tが表示されてもよい。   In step S115, the CPU 32 stores the current weight measurement value Wx in a weight value register Rw prepared in advance. Further, the CPU 32 proceeds to step S117 and stores the current time count value Ct in a time register Rt prepared in advance. In step S119, the weight measurement value Wx stored in the weight value register Rw and the time count value Ct stored in the time register Rt are displayed on the display 20. The weight measurement value Wx displayed in step S119 is the supplied weight value W01 (Wx = W01) of the workpiece 100 at the first switching time t01. Further, the current elapsed time t may be displayed instead of the time count value Ct displayed in the step S119.

このステップS119の実行後、CPU32は、ステップS121に進み、ゲート開度カウント値Cgを“1”だけインクリメントする。そして、一旦、このステップS5の供給処理を終了する。   After execution of step S119, the CPU 32 proceeds to step S121 and increments the gate opening count value Cg by “1”. And the supply process of this step S5 is once complete | finished.

なお、上述のステップS107においてゲート開度カウント値Cgが“0”でない場合、CPU32は、図7のステップS123に進む。   If the gate opening count value Cg is not “0” in step S107, the CPU 32 proceeds to step S123 in FIG.

ステップS123において、CPU32は、ゲート開度カウント値Cgが“1”であるか否かを判定する。ここで、例えば、当該ゲート開度カウント値Cgが“1”である場合、CPU32は、漸減段階を実行するべく、ステップS125に進む。   In step S123, the CPU 32 determines whether or not the gate opening count value Cg is “1”. Here, for example, when the gate opening count value Cg is “1”, the CPU 32 proceeds to step S125 to execute the gradual decrease step.

ステップS125において、CPU32は、上述の式3に基づいて、ゲート開度Gを算出する。そして、ステップS127に進み、当該ステップS125における算出結果Gに基づいて、開閉ゲート16を制御する。これらステップS125およびステップS127が繰り返されることで、ゲート開度Gは漸減する。   In step S125, the CPU 32 calculates the gate opening degree G based on the above-described Expression 3. Then, the process proceeds to step S127, and the open / close gate 16 is controlled based on the calculation result G in step S125. By repeating these steps S125 and S127, the gate opening G gradually decreases.

そして、CPU32は、ステップS129に進み、時間カウント値Ctと、調整作業で得られた変曲点閾値Ct01’と、を比較する。この変曲点閾値Ct01’は、編曲時点t01’に対応し、詳しくは当該変曲時点t01’を時間カウント値Ctに換算したものである。このステップS129において、例えば当該時間カウント値Ctが変曲点閾値Ct01’と等価(Ct=Ct01’)である場合、つまり経過時間tが変曲時点t01’に到達した場合、CPU32は、ステップS131に進む。   Then, the CPU 32 proceeds to step S129, and compares the time count value Ct with the inflection point threshold value Ct01 'obtained by the adjustment work. This inflection point threshold value Ct01 'corresponds to the arrangement time point t01', and more specifically, the inflection time point t01 'is converted into a time count value Ct. In this step S129, for example, when the time count value Ct is equivalent to the inflection point threshold Ct01 ′ (Ct = Ct01 ′), that is, when the elapsed time t has reached the inflection time t01 ′, the CPU 32 proceeds to step S131. Proceed to

ステップS131において、CPU32は、今現在の重量測定値Wxを上述した重量値レジスタRwに記憶させる。さらに、CPU32は、ステップS133に進み、今現在の時間カウント値Ctを上述した時間レジスタRtに記憶させる。そして、CPU32は、ステップS135に進み、これら重量値レジスタRwに記憶された重量測定値Wxと時間レジスタRtに記憶された時間カウント値Ctとをディスプレイ20に表示させる。なお、このステップS135で表示される重量測定値Wxは、変曲時点t01’における被計量物100の供給済み重量値W01’(Wx=W01’)である。また、当該ステップS135においても、上述のステップS119と同様、時間カウント値Ctに代えて、今現在の経過時間tが表示されてもよい。   In step S131, the CPU 32 stores the current weight measurement value Wx in the above-described weight value register Rw. Further, the CPU 32 proceeds to step S133 to store the current time count value Ct in the time register Rt described above. Then, the CPU 32 proceeds to step S135, and displays the weight measurement value Wx stored in the weight value register Rw and the time count value Ct stored in the time register Rt on the display 20. The weight measurement value Wx displayed in step S135 is the supplied weight value W01 '(Wx = W01') of the object 100 to be measured at the inflection time t01 '. Also in step S135, as in step S119 described above, the current elapsed time t may be displayed instead of the time count value Ct.

ステップS135の実行後、CPU32は、ステップS137に進む。なお、上述のステップS129において、時間カウント値Ctが変曲点閾値Ct01’と等価でない(Ct≠Ct01’)場合も、つまり経過時間tが未だ変曲時点t01’に到達していないか、若しくは当該経過時間tが既に変曲時点t01’に到達した後である場合も、CPU32は、ステップS129からステップS137に進む。   After execution of step S135, the CPU 32 proceeds to step S137. In step S129 described above, when the time count value Ct is not equivalent to the inflection point threshold value Ct01 ′ (Ct ≠ Ct01 ′), that is, the elapsed time t has not yet reached the inflection point t01 ′, or Even when the elapsed time t has already reached the inflection time t01 ′, the CPU 32 proceeds from step S129 to step S137.

ステップS137において、CPU32は、時間カウント値Ctと、調整作業で得られた第2の閾値Ct02と、を比較する。この第2閾値Ct02は、第2切換時点t02に対応し、詳しくは当該第2切換時点t02を時間カウント値Ctに換算したものである。ここで、例えば当該時間カウント値Ctが第2閾値Ct02未満(Ct<Ct02)である場合、つまり経過時間tが第2切換時点t02に到達していない場合、CPU32は、一旦、このステップS5の供給処理を終了する。一方、時間カウント値Ctが第2閾値Ct02以上(Ct≧Ct02)である場合、つまり経過時間tが第2切換時点t02に到達した場合は、ステップS139に進む。なお、このステップS139に進むとき、ゲート開度Gは、基本的には小供給段階のゲート開度G02と等価(G=G02)である。   In step S137, the CPU 32 compares the time count value Ct with the second threshold value Ct02 obtained by the adjustment work. The second threshold value Ct02 corresponds to the second switching time point t02. Specifically, the second switching time point t02 is converted into a time count value Ct. Here, for example, when the time count value Ct is less than the second threshold value Ct02 (Ct <Ct02), that is, when the elapsed time t has not reached the second switching time t02, the CPU 32 temporarily executes step S5. The supply process ends. On the other hand, when the time count value Ct is equal to or greater than the second threshold value Ct02 (Ct ≧ Ct02), that is, when the elapsed time t has reached the second switching time t02, the process proceeds to step S139. When proceeding to step S139, the gate opening G is basically equivalent to the gate opening G02 in the small supply stage (G = G02).

ステップS139において、CPU32は、今現在の重量測定値Wxを重量値レジスタRwに記憶させる。さらに、CPU32は、ステップS141に進み、今現在の時間カウント値Ctを時間レジスタRtに記憶させる。そして、CPU32は、ステップS143に進み、これら重量値レジスタRwに記憶された重量測定値Wxと時間レジスタRtに記憶された時間カウント値Ctとをディスプレイ20に表示させる。なお、このステップS143で表示される重量測定値Wxは、第2切換時点t02における被計量物100の供給済み重量値W02(Wx=W02)である。また、当該ステップS139においても、上述のステップS119およびステップS135と同様、時間カウント値Ctに代えて、今現在の経過時間tが表示されてもよい。   In step S139, the CPU 32 stores the current weight measurement value Wx in the weight value register Rw. Further, the CPU 32 proceeds to step S141, and stores the current time count value Ct in the time register Rt. Then, the CPU 32 proceeds to step S143 to display the weight measurement value Wx stored in the weight value register Rw and the time count value Ct stored in the time register Rt on the display 20. The weight measurement value Wx displayed in step S143 is the supplied weight value W02 (Wx = W02) of the workpiece 100 at the second switching time t02. Also in step S139, the current elapsed time t may be displayed instead of the time count value Ct, as in steps S119 and S135 described above.

ステップS143の実行後、CPU32は、ステップS145に進み、ここで、ゲート開度カウント値Cgを“1”だけインクリメントする。そして、一旦、このステップS5の供給処理を終了する。   After executing step S143, the CPU 32 proceeds to step S145, where the gate opening count value Cg is incremented by “1”. And the supply process of this step S5 is once complete | finished.

なお、上述のステップS123において、ゲート開度カウント値Cgが“1”でない場合、CPU32は、小供給段階を実行するべく、当該ステップS123からステップS147に進む。そして、このステップS147において、ゲート開度GをG02とするための準備をした後、続くステップS149において、当該ゲート開度Gを実際にG02とするよう開閉ゲート16を制御し、詳しくはゲート制御信号Sgを生成する。これによって、小供給段階が実行される。   If the gate opening count value Cg is not “1” in step S123 described above, the CPU 32 proceeds from step S123 to step S147 to execute the small supply stage. In step S147, after making preparations for setting the gate opening G to G02, in the subsequent step S149, the gate 16 is controlled to actually set the gate opening G to G02. A signal Sg is generated. Thereby, the small supply stage is executed.

ステップS149の実行後、CPU32は、ステップS151に進む。そして、このステップS151において、今現在の重量測定値Wxと、上述した供給停止重量値Wcと、を比較する。ここで、例えば重量測定値Wxが供給停止重量値Wcに達していない(Wx<Wc)場合、CPU32は、一旦、このステップS5の供給処理を終了する。一方、重量測定値Wxが供給停止重量値Wcに達した(Wx≧Wc)場合は、ステップS153に進む。   After executing step S149, the CPU 32 proceeds to step S151. In step S151, the current weight measurement value Wx is compared with the supply stop weight value Wc described above. Here, for example, when the weight measurement value Wx does not reach the supply stop weight value Wc (Wx <Wc), the CPU 32 once ends the supply process of step S5. On the other hand, when the weight measurement value Wx reaches the supply stop weight value Wc (Wx ≧ Wc), the process proceeds to step S153.

ステップS153において、CPU32は、ゲート開度Gを0とするための、つまり開閉ゲート16を閉鎖させるための、準備をする。そして、ステップS155において、実際に開閉ゲート16を閉鎖させる。なお、上述したように、開閉ゲート16が閉鎖された後も、計量ホッパ14には落差量d分の被計量物100が供給される。   In step S153, the CPU 32 makes preparations for setting the gate opening degree G to 0, that is, for closing the open / close gate 16. In step S155, the open / close gate 16 is actually closed. As described above, even after the open / close gate 16 is closed, the weighing object 100 is supplied with the drop 100 for the drop amount d.

そして、CPU32は、ステップS157に進み、今現在の時間カウント値Ctを時間レジスタRtに記憶させ、さらに、ステップS159に進み、当該時間レジスタRtに記憶された時間カウント値Ctをディスプレイ20に表示させる。なお、このステップS159でディスプレイ20に表示される時間カウント値Ctは、供給停止時点t03(t03’を含む)に対応する。また、当該時間カウント値Ctに代えて、供給停止時点t03が表示されてもよい。   Then, the CPU 32 proceeds to step S157 to store the current time count value Ct in the time register Rt, and further proceeds to step S159 to display the time count value Ct stored in the time register Rt on the display 20. . Note that the time count value Ct displayed on the display 20 in step S159 corresponds to the supply stop time t03 (including t03 '). Further, the supply stop time t03 may be displayed instead of the time count value Ct.

このステップS159の実行後、CPU32は、ステップS161に進む。そして、このステップS161において、供給処理中であるか否かの判定フラグFaに“0”を設定した後、ステップS163に進み、後述する別のフラグFbに“1”を設定する。そして、このステップS163の実行をもって、CPU32は、供給処理を終了する。   After executing step S159, the CPU 32 proceeds to step S161. In step S161, “0” is set to the determination flag Fa as to whether or not the supply process is in progress. Then, the process proceeds to step S163, and “1” is set to another flag Fb described later. Then, with the execution of step S163, the CPU 32 ends the supply process.

この供給処理の後、ステップS5の計量処理が行われるが、この計量処理において、CPU32は、図8に示すサブルーチンに入る。即ち、CPU32は、まず、ステップS201に進み、フラグFbに“1”が設定されているか否かを判定する。このフラグFbは、当該計量処理が実行中であるか否かを表す指標であり、当該フラグFbが“1”であれば、計量処理が実行中であることを表し、当該フラグFbが“0”であれば、計量処理が実行されていないことを表す。なお、稼働運転の開始直後は、このフラグFbには“0”が設定されている。そして、このステップS201において、例えばフラグFbに“1”が設定されていない場合、CPU32は、そのまま当該計量処理を終えて、次のステップS7の計量処理に進む。一方、フラグFbに“1”が設定されている場合には、CPU32は、ステップS203に進む。   After this supply process, the weighing process in step S5 is performed. In this weighing process, the CPU 32 enters a subroutine shown in FIG. That is, the CPU 32 first proceeds to step S201, and determines whether or not “1” is set in the flag Fb. The flag Fb is an index indicating whether or not the weighing process is being executed. If the flag Fb is “1”, it indicates that the weighing process is being executed and the flag Fb is “0”. "" Indicates that the weighing process is not executed. Note that “0” is set in the flag Fb immediately after the start of the operation operation. In step S201, for example, when “1” is not set in the flag Fb, the CPU 32 ends the measurement process as it is, and proceeds to the measurement process in the next step S7. On the other hand, if “1” is set in the flag Fb, the CPU 32 proceeds to step S203.

ステップS203において、CPU32は、デジタル荷重検出信号Wyに基づいて重量測定値Wxを求める。そして、ステップS205に進み、時間カウント値Ctを“1”だけインクリメントした後、ステップS207に進む。   In step S203, the CPU 32 obtains the weight measurement value Wx based on the digital load detection signal Wy. Then, the process proceeds to step S205, the time count value Ct is incremented by “1”, and then the process proceeds to step S207.

ステップS207において、CPU32は、いわゆる安定待ちをする。即ち、今現在の時間カウント値Ctが、今現在の時間レジスタRtの記憶値と所定の安定待ち時間Tsに対応するカウント換算値Ctsとの総和(=Rt+Cts)に達したか否かを判定する。なお、今現在の時間レジスタRtの記憶値は、供給停止時点t03に対応する。ここで、例えば今現在の時間カウント値Ctが当該総和に達していない(Ct<Rt+Cts)場合、つまり供給停止時点t03から所定の安定待ち時間Tsが経過していない場合、CPU32は、一旦、このステップS5の計量処理を終了する。一方、今現在の時間カウント値Ctが当該総和に達した(Ct<Rt+Cts)場合、つまり供給停止時点t03から所定の安定待ち時間Tsが経過した場合は、ステップS209に進む。   In step S207, the CPU 32 waits for so-called stability. That is, it is determined whether or not the current time count value Ct has reached the sum (= Rt + Cts) of the stored value of the current time register Rt and the count conversion value Cts corresponding to the predetermined stable waiting time Ts. . Note that the current stored value of the time register Rt corresponds to the supply stop time t03. Here, for example, when the current time count value Ct does not reach the sum (Ct <Rt + Cts), that is, when a predetermined stabilization waiting time Ts has not elapsed since the supply stop time t03, the CPU 32 temporarily The weighing process in step S5 is terminated. On the other hand, when the current time count value Ct reaches the sum (Ct <Rt + Cts), that is, when a predetermined stabilization waiting time Ts has elapsed from the supply stop time t03, the process proceeds to step S209.

ステップS209において、CPU32は、上述の式4に基づいて、最終重量値Wsを求める。そして、ステップS211に進み、当該ステップS209で求められた最終重量値Wsを重量値レジスタRwに記憶させる。さらに、ステップS213に進み、当該重量値レジスタRwに記憶された最終重量値Wsをディスプレイ20に表示させる。   In step S209, the CPU 32 obtains a final weight value Ws based on the above-described equation 4. In step S211, the final weight value Ws obtained in step S209 is stored in the weight value register Rw. In step S213, the final weight value Ws stored in the weight value register Rw is displayed on the display 20.

このステップS213の実行後、CPU32は、ステップS215に進み、時間カウント値Ctをリセットする。さらに、CPU32は、ステップS217に進み、ゲート開度カウント値Cgをリセットした後、ステップS219に進み、計量処理中であるか否かの判定フラグFbに“0”を設定する。そして、続くステップS221において、後述する別のフラグに“1”を設定して、このステップS5の計量処理を終了する。   After execution of step S213, the CPU 32 proceeds to step S215 and resets the time count value Ct. Further, the CPU 32 proceeds to step S217 to reset the gate opening count value Cg, and then proceeds to step S219 to set “0” to the determination flag Fb as to whether or not the weighing process is being performed. In subsequent step S221, another flag to be described later is set to “1”, and the weighing process in step S5 is terminated.

この計量処理の後、ステップS7の排出処理が行われるが、この排出処理において、CPU32は、図9に示すサブルーチンに入る。即ち、CPU32は、まず、ステップS301に進み、フラグFcに“1”が設定されているか否かを判定する。このフラグFcは、当該排出処理が実行中であるか否かを表す指標であり、当該フラグFcが“1”であれば、排出処理が実行中であることを表し、当該フラグFcが“0”であれば、排出処理が実行されていないことを表す。なお、稼働運転の開始直後は、このフラグFcには“0”が設定されている。そして、このステップS301において、例えばフラグFcに“1”が設定されていない場合、CPU32は、そのまま当該排出処理を終える。一方、フラグFcに“1”が設定されている場合には、CPU32は、ステップS303に進む。   After this weighing process, the discharging process in step S7 is performed. In this discharging process, the CPU 32 enters a subroutine shown in FIG. That is, the CPU 32 first proceeds to step S301, and determines whether or not “1” is set in the flag Fc. The flag Fc is an index indicating whether or not the discharge process is being executed. If the flag Fc is “1”, the discharge process is being executed and the flag Fc is “0”. "" Indicates that the discharge process is not executed. Note that “0” is set in the flag Fc immediately after the start of the operation operation. In step S301, for example, when “1” is not set in the flag Fc, the CPU 32 ends the discharge process as it is. On the other hand, if “1” is set in the flag Fc, the CPU 32 proceeds to step S303.

ステップS303において、CPU32は、排出ゲート54を開放させる。これにより、計量ホッパ14に供給されている被計量物100が、当該計量ホッパ14から排出される。そして、CPU32は、ステップS305に進み、時間カウント値Ctを“1”だけインクリメントする。なお、このインクリメント後の時間カウント値Ctは、供給停止時点t03からの時間に対応する。   In step S303, the CPU 32 opens the discharge gate 54. Thereby, the object 100 to be weighed supplied to the weighing hopper 14 is discharged from the weighing hopper 14. Then, the CPU 32 proceeds to step S305 and increments the time count value Ct by “1”. The incremented time count value Ct corresponds to the time from the supply stop time t03.

ステップS305の実行後、CPU32は、ステップS307に進む。そして、このステップS307において、所定の排出時間Thが過ぎるのを待つ。即ち、今現在の時間カウント値Ctが、当該排出時間Thに対応するカウント換算値Cthに達したか否かを判定する。ここで、例えば今現在の時間カウント値Ctが当該排出時間Thに対応するカウント換算値Cthに達していない(Ct<Cth)場合、CPU32は、一旦、このステップS7の排出処理を終了する。一方、今現在の時間カウント値Ctが当該排出時間Thに対応するカウント換算値Cthに達した(Ct≧Cth)場合、つまり供給停止時点t03から排出時間Thが経過した場合は、ステップS309に進む。   After executing step S305, the CPU 32 proceeds to step S307. In step S307, the process waits for a predetermined discharge time Th. That is, it is determined whether or not the current time count value Ct has reached the count conversion value Cth corresponding to the discharge time Th. Here, for example, when the current time count value Ct does not reach the count conversion value Cth corresponding to the discharge time Th (Ct <Cth), the CPU 32 once ends the discharge process of step S7. On the other hand, if the current time count value Ct reaches the count conversion value Cth corresponding to the discharge time Th (Ct ≧ Cth), that is, if the discharge time Th has elapsed from the supply stop time t03, the process proceeds to step S309. .

ステップS309において、CPU32は、時間カウント値Ctをリセットする。そして、ステップS311に進み、排出ゲート54を閉鎖する。さらに、ステップS313に進み、排出処理中であるか否かの判定フラグFcに“0”を設定した後、ステップS315に進み、当該排出処理を含むいずれかの処理が実行中であるか否かの判定フラグFsに
“1”を設定して、このステップS7の排出処理を終了する。
In step S309, the CPU 32 resets the time count value Ct. In step S311, the discharge gate 54 is closed. Further, the process proceeds to step S313, and “0” is set to the determination flag Fc for determining whether or not the discharge process is being performed. Then, the process proceeds to step S315 and whether or not any process including the discharge process is being performed. The determination flag Fs is set to “1”, and the discharging process in step S7 is terminated.

なお、本実施形態で説明した内容は、飽くまでも本発明を実現するための一例であり、本発明の範囲を限定するものではない。   Note that the content described in the present embodiment is merely an example for realizing the present invention, and does not limit the scope of the present invention.

例えば、本実施形態においては、樹脂ペレットやグラニュー糖のように流動性の高い粉粒状の被計量物100を取り扱う定量計量装置10を例に挙げたが、これに限らない。例えば、当該樹脂ペレットやグラニュー糖よりも流動性の低い被計量物や、粘性のある被計量物等を取り扱う装置にも、本発明を適用することができる。特に、粘性のある被計量物を取り扱う場合には、当該被計量物がスクリューフィーダによって溜めホッパから計量ホッパへ供給される構成であってもよい。   For example, in the present embodiment, the quantitative weighing device 10 that handles the powder-like object 100 with high fluidity such as resin pellets and granulated sugar has been described as an example, but the present invention is not limited thereto. For example, the present invention can be applied to an apparatus that handles an object to be weighed having a lower fluidity than the resin pellet or granulated sugar, an object to be weighed having viscosity, and the like. In particular, when handling a viscous object to be weighed, a configuration may be adopted in which the object to be weighed is stored by a screw feeder and supplied from a reservoir hopper to the weighing hopper.

また、溜めホッパ12の下方に計量ホッパ14が配置され、この計量ホッパ14に付属されたロードセル18等の荷重センサによる荷重検出値に基づいて、当該計量ホッパ14に供給された被計量物100の重量値Wxが求められる構成を例に挙げたが、これに限らない。例えば、溜めホッパ12側にロードセル18等の荷重センサが設けられ、この荷重センサによる荷重検出値に基づいて、当該溜めホッパ12から排出された被計量物100の重量値Wxが求められる構成に、本発明を適用してもよい。   In addition, a weighing hopper 14 is disposed below the reservoir hopper 12, and based on a load detection value by a load sensor such as a load cell 18 attached to the weighing hopper 14, the weighing object 100 supplied to the weighing hopper 14 is measured. The configuration in which the weight value Wx is obtained has been described as an example, but is not limited thereto. For example, a load sensor such as a load cell 18 is provided on the reservoir hopper 12 side, and the weight value Wx of the object to be weighed 100 discharged from the reservoir hopper 12 is obtained based on the load detection value by the load sensor. The present invention may be applied.

さらに、開閉ゲート16を駆動する手段として、サーボモータ44を採用したが、これに限らない。例えば、当該サーボモータ44に代えて、図10に示すように、ステッピングモータ60を採用してもよい。この場合、ステッピングモータ60は、モータドライブ回路62から与えられる駆動信号Sd基づいて回転駆動する。また、図1に示した構成とは異なり、回転角度検出手段としてのポテンショメータ52が不要となり、併せて、当該ポテンショメータ52からモータドライブ回路62へのフィードバックも不要となる。従って、図1に示した構成に比べて、定量供給装置10全体の構成が簡素化される。ただし、ステッピングモータ60の脱調を防ぐために、特に、当該ステッピングモータ60の駆動時に、その回転速度(ステップ数)を徐々に変化させる等の適宜の工夫が必要になる。勿論、これらのモータ44または60以外にも、上述したシリンダ38のような他の駆動手段を採用してもよい。   Further, although the servo motor 44 is employed as means for driving the open / close gate 16, it is not limited thereto. For example, instead of the servo motor 44, a stepping motor 60 may be employed as shown in FIG. In this case, the stepping motor 60 is rotationally driven based on the drive signal Sd provided from the motor drive circuit 62. In addition, unlike the configuration shown in FIG. 1, the potentiometer 52 as a rotation angle detection unit is not necessary, and feedback from the potentiometer 52 to the motor drive circuit 62 is also unnecessary. Accordingly, the entire configuration of the quantitative supply device 10 is simplified as compared with the configuration shown in FIG. However, in order to prevent the stepping motor 60 from stepping out, it is necessary to take appropriate measures such as gradually changing the rotational speed (number of steps), particularly when the stepping motor 60 is driven. Of course, in addition to these motors 44 and 60, other driving means such as the cylinder 38 described above may be employed.

そして、漸減段階においては、上述の式3で表される3次式に基づいて、ゲート開度Gが制御されることとしたが、これに限らない。例えば、第1切換時点t01から変曲時点t01’までは、上述の式2に準拠する次の式6に基づいて、ゲート開度Gが制御されてもよい。   In the gradual decrease stage, the gate opening degree G is controlled based on the cubic expression expressed by the above-described expression 3, but the present invention is not limited to this. For example, from the first switching time t01 to the inflection time t01 ', the gate opening degree G may be controlled based on the following formula 6 based on the above formula 2.

《式6》
G=(G01−G01’)・{(t01’−t)/(t01’−t01)}α+G01’
<< Formula 6 >>
G = (G01−G01 ′) · {(t01′−t) / (t01′−t01)} α + G01 ′

そして、変曲時点t01’から第2切換時点t02までは、次の式7で表される2次式に基づいて、ゲート開度Gが制御されてもよい。なお、この式7において、s1,s2およびs3は、いずれも定数であり、ゲート開度Gの漸減速度dG/dtが漸減するように求められる。具体的には、経過時間tがt=t01’であるときに、ゲート開度GがG=G01’である、という第1条件と、経過時間tがt=t02であるときに、ゲート開度GがG=G02である、という第2条件と、経過時間tがt=t02であるときのゲート開度G02が、当該ゲート開度Gの最小値である、という第3条件と、の全てが満足されるように、各s1,s2およびs3が求められる。   Then, from the inflection time t01 'to the second switching time t02, the gate opening degree G may be controlled based on the secondary expression expressed by the following expression 7. In Equation 7, s1, s2, and s3 are all constants, and are determined so that the gradual decrease rate dG / dt of the gate opening G gradually decreases. Specifically, when the elapsed time t is t = t01 ′, the first condition that the gate opening degree G is G = G01 ′, and when the elapsed time t is t = t02, the gate opening is performed. A second condition that the degree G is G = G02 and a third condition that the gate opening G02 when the elapsed time t is t = t02 is the minimum value of the gate opening G. Each s1, s2, and s3 is determined so that everything is satisfied.

《式7》
G=s1・t+s2・t+s3
<< Formula 7 >>
G = s1 · t 2 + s2 · t + s3

さらに、大供給段階から漸減段階への切り換え、および、漸減段階から小供給段階への切り換え、については、第2従来技術と同様、経過時間tに基づいて行われることとしたが、これに限らない。例えば、第1従来技術と同様、重量測定値Wxに基づいて、当該各段落の切り換えが行われるようにしてもよい。ただし、この場合は、第1従来技術におけるのと同様の不都合が生じないように、第1切換重量値W01や第2切換重量値W02,大供給段階におけるゲート開度G01等を含む各条件を設定することが、肝要である。   Further, the switching from the large supply stage to the gradual reduction stage and the switching from the gradual reduction stage to the small supply stage are performed based on the elapsed time t as in the second prior art, but this is not limitative. Absent. For example, as in the first conventional technique, the paragraphs may be switched based on the weight measurement value Wx. However, in this case, the conditions including the first switching weight value W01, the second switching weight value W02, the gate opening degree G01 in the large supply stage, etc. are set so that the same inconvenience as in the first prior art does not occur. Setting is essential.

また、大供給段階、漸減段階および小供給段階という3つの段階に分けて被計量物100が供給される場合について説明したが、これに限らない。例えば、漸減段階および小供給段階の2段階で被計量物100が供給されてもよいし、4段階以上のより多くの段階に分けて被計量物100が供給されてもよい。いずれにしても、漸減段階の後に最終の段階である小供給段階が設けられればよい。   Moreover, although the case where the to-be-measured object 100 was supplied divided into three steps called a large supply stage, a gradual reduction stage, and a small supply stage was demonstrated, it is not restricted to this. For example, the object to be weighed 100 may be supplied in two stages of a gradual reduction stage and a small supply stage, or the object to be weighed 100 may be supplied in four or more stages. In any case, a small supply stage, which is the final stage, may be provided after the gradual reduction stage.

10 定量供給装置
12 溜めホッパ
14 計量ホッパ
16 開閉ゲート
18 ロードセル
22 制御装置
32 CPU
44 サーボモータ
DESCRIPTION OF SYMBOLS 10 Fixed supply apparatus 12 Reservoir hopper 14 Weighing hopper 16 Opening / closing gate 18 Load cell 22 Control apparatus 32 CPU
44 Servo motor

Claims (2)

予め設定された目標重量値分の被計量物を供給する定量供給装置において、
供給制御信号に従って上記被計量物の供給を行う供給手段と、
上記供給制御信号を生成する供給制御手段と、
上記供給手段による供給済みの上記被計量物の重量を測定する重量測定手段と、
を具備し、
上記供給制御手段は、上記被計量物の単位時間当たりの供給量が一定の大供給段階と、該大供給段階の後に続く段階であって該供給量が該大供給段階におけるのと略同じレベルから漸減する漸減段階と、該漸減段階の後に続く最終の段階であって該供給量が該大供給段階におけるそれよりも小さい一定の小供給段階と、を含む複数の段階に分けて上記供給手段による該被計量物の供給が行われ、かつ、該漸減段階において時間の経過に対する該供給量の変化率が漸増した後に漸減すると共に該漸減段階から該小供給段階に切り換わるときの該供給量が該小供給段階におけるのと略同じレベルになり、さらに、該小供給段階において上記重量測定手段による重量測定値が上記目標重量値よりも小さい所定の供給停止重量値と一致したときに該供給手段による該被計量物の供給が停止されるように、上記供給制御信号を生成し、
上記漸減段階における上記供給制御信号は上記供給手段による上記被計量物の供給開始時点を基点とする経過時間の関数に基づき、
上記大供給段階と上記漸減段階と上記小供給段階とを含む全ての段階における上記供給量は上記供給制御信号に対して線形の関係にあり、
加えて、上記供給制御手段は、上記大供給段階において上記経過時間が予め設定された第1切換時点に到達したときに該大供給段階から上記漸減段階に切り換わり、該漸減段階において該経過時間が該第1切換時点よりも後の予め設定された第2切換時点に到達したときに該漸減段階から上記小供給段階に切り換わり、併せて、該漸減段階において該経過時間が該第1切換時点と該第2切換時点との間に予め設定された第3切換時点に到達したときに上記変化率が漸増する状態から漸減する状態に切り換わるように、上記供給制御信号を生成すること、
を特徴とする、定量供給装置。
In a quantitative supply device that supplies an object to be weighed for a preset target weight value,
Supply means for supplying the object to be weighed according to a supply control signal;
Supply control means for generating the supply control signal;
A weight measuring means for measuring the weight of the object to be weighed supplied by the supplying means;
Comprising
The supply control means includes a large supply stage where the supply amount per unit time of the object to be weighed is constant, and a stage following the large supply stage, the supply amount being substantially the same level as in the large supply stage. The supply means is divided into a plurality of stages including a gradual reduction stage gradually decreasing from a gradual reduction stage, and a final small stage following the gradual reduction stage, the supply amount being a constant small supply stage smaller than that in the large supply stage. The supply amount when the object to be weighed is supplied, and gradually decreases after the rate of change of the supply amount with time in the gradual decrease stage gradually increases and switches from the gradual decrease stage to the small supply stage Is approximately the same level as in the small supply stage, and when the weight measurement value by the weight measuring means coincides with a predetermined supply stop weight value smaller than the target weight value in the small supply stage. As the supply of 該被 weighed are stopped by means generates the supply control signal,
The supply control signal in the gradual reduction step is based on a function of an elapsed time from the supply start time of the measurement object by the supply means,
The supply amount in all stages including the large supply stage, the gradual reduction stage, and the small supply stage is linearly related to the supply control signal,
In addition, the supply control means switches from the large supply stage to the gradually decreasing stage when the elapsed time reaches a preset first switching time in the large supply stage, and the elapsed time in the gradually decreasing stage. There switched from the tapering stage when it reaches the second switching time point set in advance later than the first switching point to the small feed stage, together, the elapsed time is first switched in the tapering step Generating the supply control signal so as to switch from a state in which the rate of change gradually increases to a state in which the rate of change gradually decreases when a preset third switching time is reached between the time point and the second switching time point;
A quantitative supply device characterized by
上記関数は上記第3切換時点における上記供給量が所定値であることを条件として定められる、
請求項1に記載の定量供給装置。
The function is determined on condition that the supply amount at the third switching time point is a predetermined value.
The quantitative supply device according to claim 1.
JP2009266947A 2009-11-25 2009-11-25 Metering device Active JP5638228B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009266947A JP5638228B2 (en) 2009-11-25 2009-11-25 Metering device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009266947A JP5638228B2 (en) 2009-11-25 2009-11-25 Metering device

Publications (2)

Publication Number Publication Date
JP2011112412A JP2011112412A (en) 2011-06-09
JP5638228B2 true JP5638228B2 (en) 2014-12-10

Family

ID=44234865

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009266947A Active JP5638228B2 (en) 2009-11-25 2009-11-25 Metering device

Country Status (1)

Country Link
JP (1) JP5638228B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5839476B2 (en) * 2012-03-19 2016-01-06 大和製衡株式会社 Weighing device
JP6143442B2 (en) * 2012-11-28 2017-06-07 ミネベアミツミ株式会社 Control device and filling device provided with the same
JP6255466B2 (en) * 2016-11-25 2017-12-27 ミネベアミツミ株式会社 Control device and filling device provided with the same
JP6255465B2 (en) * 2016-11-25 2017-12-27 ミネベアミツミ株式会社 Control device and filling device provided with the same

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0299324U (en) * 1989-01-24 1990-08-08
JPH0539497A (en) * 1991-01-23 1993-02-19 Tsukishima Shokuhin Kogyo Kk Cold-resistant vegetable oil
JPH08292084A (en) * 1995-04-24 1996-11-05 Nisshin Flour Milling Co Ltd Control method of feeder to weighing device and fixed quantity bagging machine therewith
JP2004198225A (en) * 2002-12-18 2004-07-15 Yamato Scale Co Ltd Weighting type filling machine
JP4764672B2 (en) * 2005-08-09 2011-09-07 株式会社松井製作所 Method for measuring powder material

Also Published As

Publication number Publication date
JP2011112412A (en) 2011-06-09

Similar Documents

Publication Publication Date Title
JP5638228B2 (en) Metering device
AU2013233497B2 (en) Combination weighing device
JP4109991B2 (en) A system for supplying divided materials to injection molding machines
JP5562778B2 (en) Metering device
US20230201819A1 (en) Automatic Liquid Transfer Optimization Pipetting Apparatus and Method
JP5410855B2 (en) Hopper gate opening / closing device and weighing device having the same
JP4744978B2 (en) Heavy-weight filling device
JP7140033B2 (en) Material testing machine and control method for material testing machine
JP6433727B2 (en) Loss-in-weight type quantitative feeder
US11137280B2 (en) Weighing apparatus including rough-charge weigher and combination weigher
JP2007047000A (en) Method for weighing powdery and granular substance
JP5523855B2 (en) Metering device
JP2002303275A (en) Discharging amount correcting method for quantitative discharger
JP5523888B2 (en) Metering device
EP1905822A2 (en) Discharge volume control method and injecting apparatus
JP5680332B2 (en) Metering device
JP2004198225A (en) Weighting type filling machine
JP6143442B2 (en) Control device and filling device provided with the same
US8735746B2 (en) Weighing apparatus and method
JP7228327B2 (en) Quantitative dispensing system
JP2005327118A (en) Multivariable control optimization program and volumetric feeder
JP4623601B2 (en) Combination scale
JP7207104B2 (en) CONTROL DEVICE, MATERIAL TESTING MACHINE, CONTROL METHOD AND PROGRAM OF MATERIAL TESTING MACHINE
JP2019043631A (en) Filling device
JP6255466B2 (en) Control device and filling device provided with the same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20121101

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130625

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130821

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140128

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140328

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140916

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140930

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20141021

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20141022

R150 Certificate of patent or registration of utility model

Ref document number: 5638228

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250