JP5558888B2 - Rehabilitation of existing pipes - Google Patents

Rehabilitation of existing pipes Download PDF

Info

Publication number
JP5558888B2
JP5558888B2 JP2010077990A JP2010077990A JP5558888B2 JP 5558888 B2 JP5558888 B2 JP 5558888B2 JP 2010077990 A JP2010077990 A JP 2010077990A JP 2010077990 A JP2010077990 A JP 2010077990A JP 5558888 B2 JP5558888 B2 JP 5558888B2
Authority
JP
Japan
Prior art keywords
pipe
floating
existing
floating body
existing pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010077990A
Other languages
Japanese (ja)
Other versions
JP2011208746A (en
Inventor
臨 中村
優秀 村上
和成 鎌込
秀雄 郡司
隆司 松本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Aqua Systems Co Ltd
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Aqua Systems Co Ltd
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Aqua Systems Co Ltd, Sekisui Chemical Co Ltd filed Critical Sekisui Aqua Systems Co Ltd
Priority to JP2010077990A priority Critical patent/JP5558888B2/en
Publication of JP2011208746A publication Critical patent/JP2011208746A/en
Application granted granted Critical
Publication of JP5558888B2 publication Critical patent/JP5558888B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)
  • Protection Of Pipes Against Damage, Friction, And Corrosion (AREA)
  • Pipe Accessories (AREA)

Description

本発明は、流水が存在する既設管内において、複数の管体を順次運搬し、連結することにより、既設管内に複数の管体が連結された更生管を構築する既設管の更生方法に関する。 The present invention, in existing pipe running water is present, sequentially transported a plurality of tubes, by linking relates to rehabilitation how the existing pipe to build rehabilitating pipe having a plurality of tubes in existing pipe is connected .

従来、老朽化した下水路、農業用水路、及び電力水路などの管路内に水が存在する既設管を更生する方法として、既設管内に存在する水に浮かせながら、管路に沿って順次運搬し、運搬先において管体を順次連結することによって、複数の管体が連結された更生管を既設管内に構築する方法が提案されている(例えば、下記特許文献1〜3参照。)。   Conventionally, as a method of rehabilitating existing pipes where water is present in pipes such as aging sewers, agricultural waterways, and electric power channels, they are sequentially transported along the pipes while floating on the existing pipes. There has been proposed a method of constructing a rehabilitation pipe in which a plurality of pipe bodies are connected in an existing pipe by sequentially connecting the pipe bodies at a transport destination (for example, see Patent Documents 1 to 3 below).

特開平6‐81980号公報JP-A-6-81980 特開2007‐285317号公報JP 2007-285317 A 特開2009‐281567号公報JP 2009-281567 A

前記特許文献1に記載の発明は、既設管路の下流側を堰き止めて満管(満水)状態とした上で、運搬する管体内部に浮袋状の浮体を挿入し、該浮体の有する浮力で管体内上部の内壁を下支えするようにして、既設管内の水に管体を浮かせるものである。しかしながら、前記特許文献1に記載の発明を実施するためには、既設管を満管状態とする必要があり、管体の運搬時に、作業員が既設管内に入ることができないという問題があった。   The invention described in Patent Document 1 dams the downstream side of an existing pipe line so as to be in a full pipe (full water) state, and then inserts a floating bag-like floating body inside the pipe to be transported, and the buoyancy of the floating body Thus, the pipe body is floated on the water in the existing pipe so as to support the inner wall of the upper part of the pipe body. However, in order to carry out the invention described in Patent Document 1, it is necessary to make the existing pipe full, and there is a problem that an operator cannot enter the existing pipe during transportation of the pipe body. .

前記特許文献2に記載の発明は、管体外周に発泡スチロール材を巻き付け、更に管体の両端部にそれぞれ仮蓋を配設することによって浮力を確保するものであり、既設管を満管状態とする必要はない。しかしながら、管体の運搬時、仮蓋に水が衝突することによって管体のバランスが崩れ易く、又、仮蓋に衝突した水が仮蓋を越えて管体内に浸入すると、管体の浮力が著しく減じられて運搬作業が困難になるという問題があった。   The invention described in Patent Document 2 secures buoyancy by wrapping a foamed polystyrene material around the outer periphery of the tube, and further disposing temporary lids at both ends of the tube, respectively. do not have to. However, when transporting the tube, the balance of the tube tends to be lost due to the collision of water with the temporary lid, and if the water that has collided with the temporary lid enters the tube beyond the temporary lid, the buoyancy of the tube will be reduced. There has been a problem that transportation work becomes difficult due to a significant reduction.

前記特許文献3に記載の発明は、管体の両端部に前後一対の止水板を固定すると共に、該前後一対の止水板を貫通するバイパス管を配設したものであり、止水板に衝突する流水の一部をバイパス管で逃がすことにより、水の衝突による衝撃を緩和することができ、又、水が止水板を越えて管体内に浸入することを可及的に抑制することができる。しかしながら、止水板にバイパス管を配設する構造が複雑で、部品点数も多くなるため、運搬前の管体への取り付け作業及び運搬先での管体からの取り外し作業が煩雑となる。   The invention described in Patent Document 3 is such that a pair of front and rear water stop plates are fixed to both ends of a pipe body, and a bypass pipe penetrating the pair of front and rear water stop plates is provided. By letting a part of the flowing water that collides with the water flow through the bypass pipe, the impact caused by the water collision can be mitigated, and water can be prevented from entering the pipe body beyond the water stop plate. be able to. However, since the structure for disposing the bypass pipe on the water stop plate is complicated and the number of parts increases, the attaching work to the pipe body before transportation and the detaching work from the tubular body at the transportation destination become complicated.

本発明は、前記技術的課題を解決するために開発されたもので、運搬時に作業員が既設管内に入ることができ、又、運搬時の管体の浮力を維持することができ、更に、運搬前における管体への浮体の取り付け作業及び運搬先での管体からの浮体の取り外し作業が容易となる新規な既設管の更生方法を提供することを目的とする。 The present invention was developed to solve the above technical problem, and an operator can enter the existing pipe during transportation, and can maintain the buoyancy of the tubular body during transportation. an object to provide a rehabilitation how the new existing pipe which floating body detaching from tube with floating mounting work and transport destination to the tube before the delivery is facilitated.

本発明における第一の既設管の更生方法(以下、「本発明第一方法」と称する。)は、 流水が存在する既設管内において、複数の管体を順次運搬し、連結することにより、既設管内に複数の管体が連結された更生管を構築する既設管の更生方法において、運搬される管体における管体内下部に、管体の内部空間を上下に分ける比重が1未満の浮体を、固定治具を介して着脱自在に固定することによって、前記運搬される管体に対し、既設管内の流水に浮かび得る浮力を付与し、前記浮力が付与された管体を既設管内の流水に浮かせながら上流から下流に向かって順次運搬し、運搬先において、前記固定治具による浮体の固定位置を管体内の上方向に移動させて、管体の喫水を深くすることにより管体の高さ調整を行うことを特徴とする。   The first existing pipe rehabilitation method in the present invention (hereinafter referred to as “the first method of the present invention”) is a method of transporting and connecting a plurality of pipes in an existing pipe where flowing water is present. In the rehabilitation method of an existing pipe for constructing a rehabilitation pipe in which a plurality of pipes are connected in the pipe, a floating body having a specific gravity of less than 1 that divides the internal space of the pipe up and down at the lower part of the pipe in the pipe to be transported By detachably fixing through a fixing jig, buoyancy that can float on the flowing water in the existing pipe is given to the transported pipe body, and the pipe body to which the buoyancy is applied is floated on the flowing water in the existing pipe. While transporting from upstream to downstream sequentially, the height of the tubular body is adjusted by moving the fixed position of the floating body by the fixing jig upward in the transportation destination and deepening the draft of the tubular body. It is characterized by performing.

一方、本発明における第二の既設管の更生方法(以下、「本発明第二方法」と称する。)は、流水が存在する既設管内において、複数の管体を順次運搬し、連結することにより、既設管内に複数の管体が連結された更生管を構築する既設管の更生方法において、運搬される管体における管体内下部に、管体の運搬方向に沿って管体内を水が通過できる貫通孔が設けられた比重が1未満の浮体を、固定治具を介して着脱自在に固定することによって、前記運搬される管体に対し、既設管内の流水に浮かび得る浮力を付与し、前記浮力が付与された管体を既設管内の流水に浮かせながら上流から下流に向かって順次運搬し、運搬先において、前記固定治具による浮体の固定位置を管体内の上方向に移動させて、管体の喫水を深くすることにより管体の高さ調整を行うことを特徴とする。   On the other hand, the second existing pipe rehabilitation method in the present invention (hereinafter referred to as “the second method of the present invention”) is carried by sequentially transporting and connecting a plurality of pipe bodies in an existing pipe where running water exists. In a rehabilitation method for an existing pipe that constructs a rehabilitation pipe in which a plurality of pipes are connected within the existing pipe, water can pass through the pipe body along the conveyance direction of the pipe body to the lower part of the pipe body in the pipe to be transported A floating body having a through hole provided with a specific gravity of less than 1 is detachably fixed via a fixing jig, thereby imparting a buoyancy capable of floating in flowing water in an existing pipe to the transported pipe body, The pipe body with buoyancy is sequentially transported from upstream to downstream while floating in the running water in the existing pipe, and at the transport destination, the fixing position of the floating body by the fixing jig is moved upward in the pipe body, Tubes by deepening body draft And wherein the adjusting the height of the.

即ち、本発明第一方法及び本発明第二方法は、いずれも老朽化した下水路、農業用水路、及び電力水路などの管路内に流水が存在する既設管内において、複数の管体が連結された更生管を構築することによって既設管を更生する方法であり、複数の管体を既設管内に存在する流水に浮かせながら既設管の管路に沿って順次運搬し、運搬先において順次連結することにより複数の管体が連結された更生管を既設管内に構築する方法である。   That is, in the first method of the present invention and the second method of the present invention, a plurality of pipes are connected in an existing pipe in which running water exists in pipes such as aged sewers, agricultural waterways, and power waterways. This is a method of rehabilitating existing pipes by constructing rehabilitation pipes, and transporting multiple pipes sequentially along the pipelines of existing pipes while floating in running water existing in the existing pipes, and sequentially connecting them at the destination This is a method of constructing a rehabilitation pipe in which a plurality of pipe bodies are connected in an existing pipe.

本発明第一方法及び本発明第二方法においては、いずれも運搬される管体における管体内下部に、比重が1未満の浮体を、固定治具を介して着脱自在に固定することによって、前記運搬される管体に対し、既設管内の流水に浮かび得る浮力を付与する。   In the first method of the present invention and the second method of the present invention, the floating body having a specific gravity of less than 1 is detachably fixed to the lower part of the tubular body in the transported tubular body through a fixing jig, thereby The buoyancy that can float on the flowing water in the existing pipe is given to the transported pipe.

即ち、本発明第一方法及び本発明第二方法においては、運搬される管体における管体内下部に、比重が1未満の浮体を固定することにより管体に浮力を付与することから、既設管を満管状態とする必要がなくなり、管体の運搬時に作業員が既設管内に入ることが可能となる。   That is, in the first method of the present invention and the second method of the present invention, buoyancy is imparted to the tubular body by fixing the floating body having a specific gravity of less than 1 to the lower part of the tubular body to be transported. Is not required to be in a full pipe state, and an operator can enter the existing pipe when transporting the pipe body.

又、浮体自身の有する浮力によって、管体に対し既設管内に存在する水に浮かし得る浮力を付与することから、管体の運搬時において管体の浮力が極端に変化することが無くなる。   Further, the buoyancy of the floating body itself gives the tubular body a buoyancy that can float in the water existing in the existing pipe, so that the buoyancy of the tubular body does not change extremely during transportation of the tubular body.

更に、管体に対する浮体の固定は、固定治具を介して着脱自在に行われることから、管体への浮体の取り付け作業及び管体からの浮体の取り外し作業が非常に容易になる。   Furthermore, since the floating body is fixed to the tubular body in a detachable manner via a fixing jig, the attaching work of the floating body to the tubular body and the removing work of the floating body from the tubular body become very easy.

なお、本発明方法において、「管体内下部」とは、管体を横向きに開口する状態に配置した場合における管体の高さの半分の位置に水平面を想定し、該水平面と該水平面より下側にある管体の内壁面とに囲まれる範囲に含まれる部分を指す。   In the method of the present invention, the “lower part of the tubular body” means a horizontal plane at a position half the height of the tubular body when the tubular body is arranged to open sideways, and the horizontal plane and the lower horizontal plane are assumed. The part contained in the range enclosed by the inner wall surface of the pipe body in the side is pointed out.

ところで、管体を既設管内に存する流水に浮かせながら流下運搬すると、流水が、管体に固定された浮体の運搬方向反対側の端部(以下、これを浮体の後端部と称する。)に衝突し、その衝撃によって管体のバランスが不安定となる場合がある。   By the way, when the pipe is transported down while floating in the flowing water existing in the existing pipe, the flowing water is at the end of the floating body opposite to the transport direction fixed to the pipe (hereinafter referred to as the rear end of the floating body). There is a case where the balance of the tubular body becomes unstable due to the impact.

この点につき、本発明第一方法においては、前記浮体として、特に、管体内下部に固定された際に、管体の内部空間を上下に分けるものが用いられる。なお、管体の内部空間を上下に分けるとは、浮体を管体内の長さ方向に沿って固定することによって、この浮体が管体の内部空間を上下に分ける間仕切りとなることを意味する。   In this regard, in the first method of the present invention, the floating body that divides the internal space of the tubular body into upper and lower parts, particularly when fixed to the lower part of the tubular body, is used. In addition, dividing the internal space of the tubular body vertically means that the floating body serves as a partition dividing the internal space of the tubular body vertically by fixing the floating body along the length direction in the tubular body.

一方、本発明第二方法においては、前記浮体として、特に、管体の運搬方向に沿って管体内を水が通過できる貫通孔が設けられたものが用いられる。   On the other hand, in the second method of the present invention, as the floating body, a floating body provided with a through hole through which water can pass through the pipe body is used.

即ち、本発明第一方法においては、前記浮体として、管体内下部に固定された際に、管体の内部空間を上下に分けるものを用いているから、管体に固定された浮体によって仕切られた管体内下部空間(間隙)に沿って、浮体の後端部に衝突する水の一部を管体内に通過させて、衝突する水の衝撃を緩和することができ、もって管体のバランスを安定させることができるのである。   That is, in the first method of the present invention, when the floating body is fixed to the lower part of the tubular body, the internal space of the tubular body is divided into upper and lower parts, so that the floating body is partitioned by the floating body fixed to the tubular body. Along the lower space (gap) in the tubular body, a part of the water that collides with the rear end of the floating body can be passed through the tubular body, so that the impact of the colliding water can be mitigated. It can be stabilized.

一方、本発明第二方法においては、前記浮体として、管体の運搬方向に沿って管体内を水が通過できる貫通孔が設けられたものを用いているから、この貫通孔に沿って、浮体の後端部に衝突する水の一部を管体内に通過させて、衝突する水の衝撃を緩和することができ、もって管体のバランスを安定させることができるのである。   On the other hand, in the second method of the present invention, since the floating body is provided with a through hole through which water can pass through the tubular body along the transport direction of the tubular body, the floating body is formed along the through hole. By passing a part of the water colliding with the rear end of the tube into the pipe body, the impact of the colliding water can be alleviated, so that the balance of the pipe body can be stabilized.

管体に浮力を付与した後、本発明第一方法及び本発明第二方法においては、管体を既設管内の流水に浮かせながら上流から下流に向かって運搬する。   After imparting buoyancy to the tube body, in the first method and the second method of the present invention, the tube body is transported from upstream to downstream while floating in running water in the existing pipe.

しかしながら、流水の流下速度が比較的大きい場合、管体の流下速度が増すため安全に運搬することが困難になるといった問題が生じることがある。   However, when the flow rate of the flowing water is relatively large, there may be a problem that it is difficult to transport safely because the flow rate of the tube increases.

そのため、本発明第一方法及び本発明第二方法においては、管体に索体の一端を固定し、上流側から該索体を繰り出すことにより管体の流下速度をコントロールしながら流下運搬することが好ましい。   Therefore, in the first method of the present invention and the second method of the present invention, one end of the cable body is fixed to the pipe body, and the cable body is fed out from the upstream side while controlling the flow speed of the pipe body to carry it down. Is preferred.

即ち、管体に索体の一端を固定し、上流側から該索体を繰り出しながら、管体の流下速度を流水の流下速度よりも遅くなるようにコントロールすれば、流水の流下速度が比較的大きい場合にあっても安全に管体を運搬することができる。   That is, if one end of the cable body is fixed to the pipe body and the cable body is fed out from the upstream side, the flow speed of the water flow is controlled to be slower than the flow speed of the running water. Even if it is large, the tube can be safely transported.

管体に固定される索体としては、特に限定されるものではなく、例えば、ロープ、ワイヤ、或いはチェーン等を挙げることができる。又、索体を繰り出す手段としては、人力を用いても良いのであるが、安定した駆動力及び安全性を鑑みて、ウインチなどの巻き揚げ機を用いることが好ましい。更に、前記索体は複数本用いても良い。   The cable body fixed to the pipe body is not particularly limited, and examples thereof include a rope, a wire, and a chain. In addition, human power may be used as a means for feeding out the rope body, but it is preferable to use a hoist such as a winch in view of stable driving force and safety. Further, a plurality of the cords may be used.

管体を運搬先に運搬した後、本発明第一方法及び本発明第二方法においては、運搬先において管体を連結する。この管体の連結にあたり、本発明第一方法及び本発明第二方法においては、固定治具による浮体の固定位置を管体内の上方向に移動させて、管体の喫水を深くすることにより管体の高さ調整を行う。   In the first method and the second method of the present invention, after the pipe body is transported to the transport destination, the pipe bodies are connected at the transport destination. In connection with this pipe body, in the first method of the present invention and the second method of the present invention, the fixing position of the floating body by the fixing jig is moved upward to increase the draft of the pipe body. Adjust body height.

即ち、運搬先に運搬された管体は、後述する裏込め材によって管体が浮上することを防止するために、通常、既設管内の所定高さに固定配置される。又、運搬先において管体同士を連結するにあたっては、連結する管体同士の高さ調整(レベル調整)が行われる。この際、水に浮かせながら運搬先に運搬されてきた管体は、運搬時に水に浮いていた位置よりも低い位置に下げて固定配置されることが多い。従って、連結する管体同士の高さ調整は、運搬してきた後続の管体の高さを、既に既設管内の所定高さに固定配置されている管体の位置まで下げる作業となる場合が殆どである。   In other words, the pipe body transported to the transport destination is usually fixedly arranged at a predetermined height in the existing pipe in order to prevent the pipe body from rising due to the backfill material described later. Moreover, when connecting pipe bodies in a conveyance destination, height adjustment (level adjustment) of the pipe bodies to connect is performed. At this time, the tubular body that has been transported to the transport destination while being floated on water is often fixedly disposed at a lower position than the position that has floated on the water during transport. Therefore, the adjustment of the heights of the pipes to be connected is almost always an operation for lowering the height of the subsequent pipes that have been transported to the position of the pipes that are already fixedly arranged at a predetermined height in the existing pipes. It is.

この点につき、本発明第一方法及び本発明第二方法においては、運搬先において、固定治具による浮体の固定位置を管体内の上方向に移動させるといった比較的簡単な作業で高さ調整が行われる。即ち、固定治具によって管体内下部に固定されている浮体の固定位置を上方向に徐々に移動させると、管体内下部に固定されていた浮体が内壁面から離れ、固定治具に支えられながら徐々に浮き上がり、これに応じて管体の喫水が徐々に深くなる。これより、運搬してきた管体の高さを既に既設管内の所定高さに固定配置されている管体の位置まで下げることができる。   In this regard, in the first method of the present invention and the second method of the present invention, the height can be adjusted by a relatively simple operation such as moving the fixing position of the floating body by the fixing jig upward in the transport destination. Done. That is, when the fixing position of the floating body fixed to the lower part of the tubular body is gradually moved upward by the fixing jig, the floating body fixed to the lower part of the tubular body is separated from the inner wall surface and supported by the fixing jig. The pipe gradually rises and the draft of the pipe gradually deepens accordingly. Accordingly, the height of the pipe body that has been transported can be lowered to the position of the pipe body that is already fixedly arranged at a predetermined height in the existing pipe.

なお、固定治具による浮体の固定位置を管体内の上方向に移動させると、浮体の自由度が高くなり、浮体が前後左右に動くことが可能になる。浮体が動いて固定治具の支えから離脱すると、浮力を失った管体が急落する場合がある。   In addition, when the fixing position of the floating body by the fixing jig is moved upward in the tubular body, the degree of freedom of the floating body is increased, and the floating body can move back and forth and right and left. When the floating body moves and leaves the support of the fixing jig, the pipe body that has lost its buoyancy may drop suddenly.

このため、本発明第一方法及び本発明第二方法において、固定治具による浮体の固定位置を管体内の上方向に移動させることによって高さ調整を行う際には、管体内下部の内壁面から浮上することによって自由度が高くなった浮体の動きを抑制するために、支持部材を介して浮体を管体に支持することが好ましい。   Therefore, in the first method of the present invention and the second method of the present invention, when the height adjustment is performed by moving the fixing position of the floating body by the fixing jig upward in the tubular body, the inner wall surface of the lower portion of the tubular body In order to suppress the movement of the floating body whose degree of freedom is increased by rising from the top, it is preferable to support the floating body on the tubular body via a support member.

前記支持部材による浮体の支持については、自由度が高くなった浮体の動きを抑制し得るものであれば特に限定されるものではない。具体的に例えば、棒状の支持部材を心張り棒(つっかい棒)のように用いて、浮体と管体内壁との間に斜めに立て掛けた状態で浮体を管体に支持したり、管体の外径より長い棒状の支持部材を浮体の幅方向に沿って固定配置すると共に、該支持部材における浮体からはみ出た両端部分を管体開口端に当接させて、浮体を管体に支持したりする手段等を挙げることができる。   The support of the floating body by the support member is not particularly limited as long as the movement of the floating body having a high degree of freedom can be suppressed. Specifically, for example, a rod-shaped support member is used as a centering rod (supporting rod), and the floating body is supported on the tubular body in a state where it is leaned diagonally between the floating body and the tubular body wall. A rod-shaped support member longer than the outer diameter of the floating body is fixedly disposed along the width direction of the floating body, and both ends of the supporting member that protrude from the floating body are brought into contact with the opening end of the tubular body to support the floating body on the tubular body. And the like.

続いて、前記既設管の更生方法に適用される管体構造について説明する。 Next, a pipe structure applied to the existing pipe rehabilitation method will be described.

一の管体構造(以下、「第一管体構造」と称する。)は、管体と、前記管体の内部空間を上下に分ける浮体であって、前記管体に対して水に浮かび得る浮力を付与する比重が1未満の浮体と、この浮体を管体内下部に着脱自在に取り付ける固定治具とを具備することを特徴とする。 The first tubular structure (hereinafter referred to as first tubular structure”) is a floating body that divides a tubular body and the internal space of the tubular body into upper and lower parts, and floats in water with respect to the tubular body. A floating body having a specific gravity of less than 1 for providing buoyancy to be obtained, and a fixing jig for detachably attaching the floating body to the lower part of the tubular body are provided.

一方、第二の管体構造(以下、「第二管体構造」と称する。)は、 管体と、前記管体の運搬方向に沿って管体内を水が通過できる貫通孔が設けられた浮体であって、この管体に対して水に浮かび得る浮力を付与する比重が1未満の浮体と、この浮体を管体内下部に着脱自在に取り付ける固定治具とを具備することを特徴とする。 On the other hand , the second tubular structure (hereinafter referred to as second tubular structure”) is provided with a tubular body and a through-hole through which water can pass through the tubular body along the transport direction of the tubular body. A floating body having a specific gravity of less than 1 for imparting buoyancy capable of floating in water to the tubular body, and a fixing jig for detachably attaching the floating body to a lower portion of the tubular body. .

即ち、第一管体構造は、前記本発明第一方法を実施するためのものであり、一方、第二管体構造は、前記本発明第二方法を実施するためのものであり、いずれも既設管内に存在する流水に浮かせながら順次運搬され、運搬先において順次連結されることにより、既設管内に複数の管体が連結された更生管を構築するための管体構造である。 That is , the first tubular structure is for carrying out the first method of the present invention, while the second tubular structure is for carrying out the second method of the present invention. It is a tubular structure for constructing a rehabilitation pipe in which a plurality of tubular bodies are connected in an existing pipe by being sequentially transported while floating in running water existing in the existing pipe and sequentially connected at the destination.

前記管体としては、複数連結されることにより更生管を構築し得るものであれば、特に限定されるものではない。又、管体を連結する手段としても、特に限定されるものではなく、ボルトやバイスなどの締結治具や適当な連結治具を用いて管体同士を連結しても良い。特に、本発明においては、連結作業を容易にするために、管体として受け口及び差し口が前後両端部にそれぞれ形成された構造のものを用い、一の管体の受け口に対し他の管体の差し口を挿入することにより管体同士が連結され得るようにすることが好ましい。   The pipe body is not particularly limited as long as a plurality of pipe bodies can be connected to construct a rehabilitation pipe. The means for connecting the tube bodies is not particularly limited, and the tube bodies may be connected using a fastening jig such as a bolt or a vise or an appropriate connection jig. In particular, in the present invention, in order to facilitate the connecting work, a tube having a structure in which a receiving port and an insertion port are formed at both front and rear ends, respectively, and another tube body with respect to the receiving port of one tube body. It is preferable that the tubular bodies can be connected to each other by inserting the insertion opening.

前記浮体としては、比重が1未満で浮体自身が浮力を有し、管体内下部に固定されることにより、管体に対し水に浮かび得る浮力を付与するものであれば、特に限定されるものではない。具体的に例えば、気体を密封することができる袋状の浮体や中空容器状の浮体、発泡スチロールなどの比重が低い素材で形成された浮体、或いはボート状に形成された浮体などを挙げることができる。但し、ボート状に形成された浮体を用いる場合には、ボート内の凹部に水が浸入しないように、該凹部を覆う蓋を設けることが好ましい。   The floating body is not particularly limited as long as it has a specific gravity of less than 1 and the floating body itself has buoyancy and is fixed to the lower part of the tube to give the tube a buoyancy that can float in water. is not. Specifically, for example, a bag-like floating body capable of sealing a gas, a hollow container-like floating body, a floating body formed of a material having a low specific gravity such as foamed polystyrene, or a floating body formed in a boat shape can be exemplified. . However, when using a floating body formed in a boat shape, it is preferable to provide a lid that covers the recess so that water does not enter the recess in the boat.

そして、第一管体構造においては、管体内下部に固定された際に、管体の内部空間を上下に分けるものが用いられる。 And in the 1st pipe structure, when fixing to the lower part of a pipe body, what divides the internal space of a pipe body up and down is used.

一方、第二管体構造においては、前記浮体として、特に、管体の運搬方向に沿って管体内を水が通過できる貫通孔が設けられたものが用いられる。 On the other hand , in the second tubular structure, in particular, the floating body is provided with a through hole through which water can pass through the tubular body along the transport direction of the tubular body.

即ち、管体を既設管内に存する流水に浮かせて運搬すると、流水が、浮体の後端部に常時衝突することになり、やはり管体のバランスが不安定となる場合がある。   That is, when the pipe is floated and transported in the running water existing in the existing pipe, the running water always collides with the rear end of the floating body, and the balance of the pipe may be unstable.

この点につき、第一管体構造においては、前記浮体として、管体内下部に固定された際に、管体の内部空間を上下に分けるものを用いているから、管体に固定された浮体によって仕切られた管体内下部空間(間隙)に沿って、浮体の後端部に衝突する水の一部を管体内に通過させて、衝突する水の衝撃を緩和することができ、管体のバランスを安定させることができる。 In this regard , in the first tubular structure, when the floating body is fixed to the lower part of the tubular body, the one that divides the internal space of the tubular body into upper and lower parts is used. A portion of the water that collides with the rear end of the floating body is allowed to pass through the tubular body along the partitioned lower space (gap), and the impact of the colliding water can be mitigated. Can be stabilized.

一方、第二管体構造においては、前記浮体として、管体の運搬方向に沿って管体内を水が通過できる貫通孔が設けられたものを用いているから、この貫通孔に沿って、浮体の後端部に衝突する水の一部を管体内に通過させて、衝突する水の衝撃を緩和することができ、管体のバランスを安定させることができる。 On the other hand , in the second tubular structure, since the floating body is provided with a through-hole through which water can pass through the tubular body along the transport direction of the tubular body, the floating body is formed along the through-hole. A part of the water that collides with the rear end portion is allowed to pass through the pipe body, so that the impact of the colliding water can be alleviated and the balance of the pipe body can be stabilized.

、第一管体構造及び第二管体構造においては、いずれも浮体の後端部に、水の衝突を、水の衝突方向に対して傾いた衝突面で受けることにより、衝突した水を衝突面に沿った方向に案内する緩衝部を設けることが好ましい。 Further, the water in the first Ichikan structure及beauty second tubular structure, the rear end portion of any floating body, the collision of water, by receiving the collision surface inclined with respect to the collision direction of the water, which collided It is preferable to provide a buffer portion that guides the guide in a direction along the collision surface.

即ち、浮体の後端部に、水の衝突方向に対して傾いた衝突面を有する緩衝部を設ければ、前記浮体の後端部に衝突する水を衝突面に沿った方向に案内することができ、もって、衝突する水の衝撃を緩和することができる。この緩衝部における衝突面を構成する具体的な形状としては、テーパー形状、曲面形状及び先鋭形状等を挙げることができる。   That is, if a buffer portion having a collision surface inclined with respect to the collision direction of water is provided at the rear end portion of the floating body, the water colliding with the rear end portion of the floating body is guided in a direction along the collision surface. Therefore, the impact of the impinging water can be reduced. Specific shapes constituting the collision surface in the buffer portion include a tapered shape, a curved surface shape, a sharp shape, and the like.

更に、第一管体構造及び第二管体構造においては、いずれも浮体の後端部両端に、上流側から衝突した水を下流側に案内する湾曲部が設けることが好ましい。 Further, in the first Ichikan structure及beauty second tubular structure, the rear end opposite ends of any floating body, it is preferable that the curved portion for guiding the water impinging from the upstream side to the downstream side provided.

即ち、浮体の後端部両端に湾曲部を設ければ、前記浮体の後端部に衝突する水を湾曲部に沿って下流側に案内することができ、もって、衝突する水の衝撃を緩和することができる。   That is, if the bent portions are provided at both ends of the rear end portion of the floating body, the water colliding with the rear end portion of the floating body can be guided downstream along the curved portion, thereby reducing the impact of the colliding water. can do.

一管体構造及び第二管体構造において、浮体を管体に固定する固定治具としては、浮体を着脱自在に固定することができ、浮体の固定位置を管体内の上下方向に移動させることができ、管体の運搬時に浮体が簡単に外れない程度の固定強度を付与し得るものであれば特に限定されるものではない。 Moving the first Ichikan structure及beauty second tubular structure, as the fixing jig for fixing a floating body to the tube, the floating body to be able freely to fix releasably the fixing position of the floating body in the vertical direction of the tube body There is no particular limitation as long as it can provide a fixing strength that does not allow the floating body to be easily detached during transportation of the tubular body.

このような固定治具の好適な例としては、ジャッキや突っ張り棒などの、浮体と管体内上部の内壁との間で突っ張り支持されることによって、前記浮体を管体内下部の内壁面に押し付けて固定する伸縮式の固定治具を挙げることができる。   As a suitable example of such a fixing jig, the floating body is pressed against the inner wall surface of the lower part of the tubular body by being supported by being stretched between the floating body and the inner wall of the upper part of the tubular body, such as a jack or a stick. A telescopic fixing jig to be fixed can be mentioned.

本発明は、運搬される管体における管体内下部に浮体を固定することにより該管体に浮力を付与することから、既設管を満管状態とする必要がなくなり、管体の運搬時に作業員が既設管内に入ることが可能になる。   The present invention provides buoyancy to the tubular body by fixing the floating body to the lower part of the tubular body to be transported, so that it is not necessary to make the existing pipe full. Can enter the existing pipe.

又、本発明においては、浮体自身の有する浮力によって、管体に対し既設管内に存在する水に浮かし得る浮力を付与することから、管体の運搬時に管体の浮力が極端に変化することが無くなる。   Further, in the present invention, the buoyancy of the floating body itself gives the tubular body a buoyancy that can float in the water existing in the existing pipe, so that the buoyancy of the tubular body may change extremely during transportation of the tubular body. Disappear.

更に、本発明において、管体に対する浮体の固定は、固定治具を介して着脱自在に行われることから、浮体の取り付け作業及び取り外し作業が非常に容易になる。   Furthermore, in the present invention, the floating body is fixed to the tube body in a detachable manner via a fixing jig, so that the mounting work and the removing work of the floating body are very easy.

加えて、本発明によれば、浮体の後端部に衝突する水の一部を管体内に通過させて、衝突する水の衝撃を緩和することができ、もって管体のバランスを安定させることができるのである。   In addition, according to the present invention, a part of the water that collides with the rear end of the floating body can be passed through the pipe body, and the impact of the colliding water can be reduced, thereby stabilizing the balance of the pipe body. Can do it.

又、本発明によれば、運搬先において、固定治具による浮体の固定位置を管体内の上方向に移動させるといった比較的簡単な作業で高さ調整を行うことができる。   Further, according to the present invention, the height can be adjusted by a relatively simple operation such as moving the fixed position of the floating body by the fixing jig upward in the transport destination at the transport destination.

図1は、管体に浮体を固定治具を介して着脱自在に固定した管体構造を、一部切り欠いて示す斜視図である。FIG. 1 is a perspective view showing a tubular body structure in which a floating body is detachably fixed to a tubular body via a fixing jig. 図2は、管体に浮体を固定治具を介して着脱自在に固定した管体構造に対し、更に衝撃緩衝治具及び補助輪を取り付けた状態を示す側面図(a)、及び正面図(b)である。FIG. 2 is a side view (a) and a front view showing a state in which an impact buffering jig and an auxiliary wheel are further attached to a tubular structure in which a floating body is detachably fixed to a tubular body via a fixing jig. b). 図3は、本発明方法の一実施形態の実施状態を説明する説明図である。FIG. 3 is an explanatory diagram for explaining an implementation state of an embodiment of the method of the present invention. 図4は、浮体に衝突した流水の状態を説明する説明図である。FIG. 4 is an explanatory diagram for explaining the state of running water that has collided with the floating body. 図5は、管体に別の浮体を固定した管体構造を示す側面図(a)、及び正面図(b)である。FIG. 5 is a side view (a) and a front view (b) showing a tubular structure in which another floating body is fixed to the tubular body. 図6は、芯出し治具を管体と共に示す側面図(a)、及び正面図(b)である。FIG. 6 is a side view (a) and a front view (b) showing the centering jig together with the tubular body. 図7は、支持部材を用いて、浮体を管体に支持した状態を示す正面図である。FIG. 7 is a front view showing a state in which the floating body is supported by the tubular body using the support member. 図8は、別の支持部材を併用して、浮体を管体に支持した状態を示す側面図(a)、及び正面図(b)である。FIG. 8 is a side view (a) and a front view (b) showing a state where the floating body is supported by the tubular body using another support member in combination. 図9は、接合治具を用いた管体の接合要領を説明する説明図である。FIG. 9 is an explanatory view for explaining the joining procedure of the tubular body using the joining jig. 図10は、既設管内に構築された更生管を示す側面図である。FIG. 10 is a side view showing a rehabilitation pipe constructed in an existing pipe. 図11は、本発明の一実施形態における排水作業、及び裏込め材充填作業を(a)〜(d)の順に経時的に説明する説明図である。FIG. 11 is an explanatory diagram for explaining the drainage operation and the backfilling material filling operation in one embodiment of the present invention over time in the order of (a) to (d).

以下、本発明の実施形態を図面に基づいて説明するが、本発明はこの実施形態に限定されるものではない。   Hereinafter, although an embodiment of the present invention is described based on a drawing, the present invention is not limited to this embodiment.

図1及び図2に、管体1に浮体2を固定治具としてのジャッキ3を介して着脱自在に固定した管体構造を示す。管体1はガラス繊維強化プラスチック(FRP)と樹脂モルタルとの積層構成からなるプラスチック複合管である。この管体1における一定の内外径を有する直管状の管本体部1cの一方の端部には、該管本体部1cよりも大径の短筒状の受け口1aが備えられており、管本体部1cの他方の端部には、先端に向かって先細の外周面形状を有する差し口1bが形成されている。   1 and 2 show a tubular structure in which a floating body 2 is detachably fixed to a tubular body 1 via a jack 3 as a fixing jig. The tube 1 is a plastic composite tube having a laminated structure of glass fiber reinforced plastic (FRP) and resin mortar. One end of a straight tubular tube body 1c having a constant inner and outer diameter in the tube body 1 is provided with a short cylindrical receptacle 1a having a diameter larger than that of the tube body 1c. At the other end of the portion 1c, an insertion port 1b having a tapered outer peripheral surface shape toward the tip is formed.

管体1同士の連結は、先行する管体1の受け口1aに後続する管体1の差し口1bを挿入することにより行われる。管体1の受け口1aの内周面(或いは、差し口1bの外周面)には、図示しない止水ゴムが設けられており、一の管体1の受け口1aに他の管体1の差し口1bを挿入して連結すると、受け口1aと差し口1bとが止水ゴムを介して水密状態で連結される。   The connection between the tube bodies 1 is performed by inserting the insertion port 1b of the tube body 1 following the receiving port 1a of the preceding tube body 1. A water blocking rubber (not shown) is provided on the inner peripheral surface of the receiving port 1a of the tube body 1 (or the outer peripheral surface of the insertion port 1b), and another tube body 1 is inserted into the receiving port 1a of the one tube body 1. When the port 1b is inserted and connected, the receiving port 1a and the insertion port 1b are connected in a watertight state via a water blocking rubber.

浮体2は、発泡スチロール製のブロックからなり、その長さ方向の長さが前記管体1の長さ方向の長さより幾分長く、その幅方向の長さが前記管体1における管本体部1cの内径より幾分短い。   The floating body 2 is made of a block made of polystyrene foam, and its length in the length direction is somewhat longer than the length in the length direction of the tube 1, and the length in the width direction is the tube main body 1 c in the tube 1. It is somewhat shorter than the inner diameter.

以下、この浮体2の各部の形状及び構成を説明するが、説明の便宜上、この浮体2の形状を四角柱に類似するものとみなし、管体1に固定された状態における浮体2の上面を甲板部、浮体2の下面を底部、浮体2の両側面をそれぞれ右側部及び左側部、浮体2の運搬方向側の端面を前端部、浮体2の運搬方向反対側の端面を後端部とする。   Hereinafter, the shape and configuration of each part of the floating body 2 will be described. For convenience of explanation, the shape of the floating body 2 is considered to be similar to a quadrangular prism, and the upper surface of the floating body 2 in a state of being fixed to the tubular body 1 is The bottom surface of the floating body 2 is the bottom, the right and left sides of the floating body 2 are the front end, the end surface of the floating body 2 on the transport direction side is the front end, and the end surface of the floating body 2 opposite to the transport direction is the rear end.

浮体2の甲板部には、後端部側の両角を丸めることによって湾曲部25が形成されている。又、甲板部上には、該甲板部全面を覆う合板21が固定されており、当該合板21上には、その幅方向に沿って複数の角材22を並べて固定している。更に、甲板部上の後端部寄りの所定位置には、アームの先端に車輪を設けた一対の支持部材8が、浮体2の幅方向に沿って起伏可能となるよう取り付けられている。該支持部材8は、浮体2の外側に向けて倒れた際に、少なくともアームの先端に設けた車輪が浮体2からはみ出す長さを有する。   A curved portion 25 is formed on the deck portion of the floating body 2 by rounding both corners on the rear end side. A plywood 21 covering the entire surface of the deck is fixed on the deck, and a plurality of square members 22 are arranged and fixed on the plywood 21 along the width direction. Further, a pair of support members 8 provided with wheels at the front ends of the arms are attached at predetermined positions near the rear end on the deck so as to be able to undulate along the width direction of the floating body 2. The support member 8 has such a length that at least the wheel provided at the tip of the arm protrudes from the floating body 2 when the support member 8 falls toward the outside of the floating body 2.

浮体2の右側部及び左側部には、その長さ方向にわたって、管体1における管体内下部の内壁面二箇所に当接し得る曲面形状を有する当接部23がそれぞれ形成されている。   On the right side and the left side of the floating body 2, a contact portion 23 having a curved shape capable of coming into contact with two inner wall surfaces of the lower portion of the tubular body 1 is formed in the length direction.

浮体2の後端部には、甲板部の後端辺から底部内側に向かって斜めに角を切り落とした如きのテーパー形状の衝突面を有する緩衝部24が形成されている。   At the rear end portion of the floating body 2, a buffer portion 24 having a tapered collision surface such that the corner is obliquely cut from the rear end side of the deck portion toward the inside of the bottom portion is formed.

固定治具としてのジャッキ3は、ボルトの螺合に応じてシャフトが伸縮するジャッキ構造を有する。   The jack 3 as a fixing jig has a jack structure in which a shaft expands and contracts according to screwing of a bolt.

前記浮体2は、両当接部23がそれぞれ管体1(管本体部1c)における管体内下部の内壁面二箇所に当接した状態で、ジャッキ3を介して着脱自在に固定される。   The floating body 2 is detachably fixed via a jack 3 in a state where both contact portions 23 are in contact with two inner wall surfaces of the lower portion of the tubular body 1 (tube main body portion 1c).

更に詳しく説明すると、管体1に浮体2を固定するにあたっては、まず管体1内の所定位置に浮体2を配置する。なお、管体1における差し口1b側より受け口1a側の重量が大きいことから、バランス配分を考慮して、浮体2は、後端部が管体1の受け口1aから突出するように、受け口1a側に片寄って配置される。   More specifically, when the floating body 2 is fixed to the tubular body 1, the floating body 2 is first arranged at a predetermined position in the tubular body 1. Since the weight on the receiving port 1a side is larger than that on the insertion port 1b side in the tubular body 1, considering the balance distribution, the floating body 2 has the receiving port 1a so that the rear end portion protrudes from the receiving port 1a of the tubular body 1. Arranged side by side.

次いで、浮体2の甲板部上を覆う合板21上の所定箇所(二箇所)に当て板4を置き、置かれた二つの当て板4の上にジャッキ3をそれぞれ配置する。この状態でジャッキ3を伸ばす方向に操作すると、該ジャッキ3が浮体2と管体内上部の内壁との間で突っ張り支持されると共に前記浮体2の両当接部23が管体1における管体内下部の内壁面二箇所に押し付けられる。これにより浮体2は、管体1の管体内下部に着脱自在に固定される。   Next, the backing plate 4 is placed at predetermined locations (two locations) on the plywood 21 covering the deck portion of the floating body 2, and the jacks 3 are respectively placed on the two placed backing plates 4. When the jack 3 is operated in the extending direction in this state, the jack 3 is stretched and supported between the floating body 2 and the inner wall of the upper part of the tubular body, and both contact portions 23 of the floating body 2 are lower in the tubular body 1. It is pressed against two inner wall surfaces. Accordingly, the floating body 2 is detachably fixed to the lower part of the tubular body 1.

なお、浮体2の底部は平坦面であることから、該底部は、管体1における管体内下部の内壁面には接触せず、結果、浮体2が間仕切りとなって管体1の内部空間を上下に分けることになり、浮体2の底部と管体内下部の内壁面との間には管体1の運搬方向に沿って貫通する間隙5が形成される。   In addition, since the bottom part of the floating body 2 is a flat surface, the bottom part does not contact the inner wall surface of the lower part of the tubular body 1 in the tubular body 1. A gap 5 penetrating along the conveying direction of the tube 1 is formed between the bottom of the floating body 2 and the inner wall surface of the lower portion of the tube.

図2に示すように、管体1の受け口1a側及び差し口1b側の両管側部の位置には、管体1の運搬時、管体1が既設管Sの内壁に接触することを避けるためのローラ部材からなる衝撃緩衝治具6がボルトを介して備えられる。又、管体1の受け口1a側の下方部の位置には、補助輪7がバイスを介して備えられる。なお、管体1が安定した状態で浮かんでいるときは、前記衝撃緩衝治具6及び補助輪7は既設管Sの内壁から離れた状態となる。   As shown in FIG. 2, the pipe body 1 is in contact with the inner wall of the existing pipe S when the pipe body 1 is transported at the positions of both pipe side portions of the pipe body 1 on the receiving port 1 a side and the insertion port 1 b side. An impact buffering jig 6 made of a roller member for avoiding is provided via a bolt. In addition, an auxiliary wheel 7 is provided via a vise at a position of a lower portion of the tube body 1 on the receiving port 1a side. When the tube body 1 is floating in a stable state, the shock buffering jig 6 and the auxiliary wheel 7 are separated from the inner wall of the existing tube S.

このように構成された管体1を利用して、農業用水路に使用されている既設管Sを更生する方法について説明する。   A method for rehabilitating the existing pipe S used in the agricultural waterway by using the pipe body 1 configured as described above will be described.

図3に示すように、この既設管Sには、発進側縦抗M1から到達側縦抗M2に到る施工区間にわたって、管体1を浮かせることができる水位の流水が図中矢印で示す方向に流れている。なお、流水の水位が管体1を浮かせるに十分な水位に満たない場合は、施工区間の下流側に堰を設けて流水を堰止めるなど、何らかの手段を講じて施工区間に必要とする水位を確保すればよい。   As shown in FIG. 3, in this existing pipe S, the flowing water at the water level that can float the pipe body 1 over the construction section from the starting side longitudinal resistance M1 to the reaching side longitudinal resistance M2 is indicated by an arrow in the figure. Is flowing. In addition, when the water level of the running water is not sufficient to float the pipe body 1, the water level necessary for the construction section is taken by taking some means such as installing a weir on the downstream side of the construction section to stop the running water. What is necessary is just to secure.

本実施形態においては、まず、流水の上流側に設けた発進側縦坑M1に、管体1を、その受け口1aが上流側を向くようにして吊り下ろす。なお、衝撃緩衝治具6及び補助輪7は、管体1を吊り降ろす前に取り付けるのが好ましい。   In the present embodiment, first, the pipe body 1 is suspended from the start side shaft M1 provided on the upstream side of running water so that the receiving port 1a faces the upstream side. The impact buffering jig 6 and the auxiliary wheel 7 are preferably attached before the tube body 1 is suspended.

吊り下ろされた管体1には、浮体2が固定治具3を介して着脱自在に固定される。又、管本体部1cにおける受け口1a側には、ナイロンスリング93が2本巻きつけられ、巻きつけたナイロンスリング93の端部に索体としてのワイヤ91の一端部に設けたフック92が接続される。一方、前記ワイヤ91の他端はウインチ9に巻き回されている。   A floating body 2 is detachably fixed to the suspended pipe body 1 via a fixing jig 3. Also, two nylon slings 93 are wound around the receptacle 1a side of the tube main body 1c, and a hook 92 provided at one end of a wire 91 as a rope is connected to the end of the wound nylon sling 93. The Meanwhile, the other end of the wire 91 is wound around the winch 9.

前記ウインチ9は、発進側縦抗M1近辺の所定位置に設置されており、流水に管体1を浮かせた後、当該ウインチ9によってワイヤ91を徐々に繰り出し、管体1の流下速度をコントロールしながら、既設管S内を下流側に向けて運搬する。即ち、本実施形態においては、ワイヤ91を繰り出すことにより該管体1の流下速度をコントロールして運搬しているため、流水の速度にかかわらず安全に管体1を運搬することができる。   The winch 9 is installed at a predetermined position in the vicinity of the start side longitudinal resistance M1, and after the pipe body 1 is floated on running water, the wire 91 is gradually fed out by the winch 9 to control the flow speed of the pipe body 1. However, the existing pipe S is transported toward the downstream side. That is, in the present embodiment, since the wire 91 is fed out while controlling the flow speed of the pipe body 1, the pipe body 1 can be safely transported regardless of the flowing water speed.

この際、流水の流下速度(本実施形態においては、約1.0m/s)が、引張による速度コントロールを受けながら運搬される管体1の流下速度(本実施形態においては、約0.5m/s)より大きいため、流水は浮体2の後端部に常時衝突する。   At this time, the flowing speed of the pipe body 1 (about 1.0 m / s in the present embodiment) is conveyed while receiving speed control by tension (about 0.5 m in the present embodiment). / S), the flowing water always collides with the rear end of the floating body 2.

この点につき本実施形態においては、浮体2の後端部に湾曲部25を設けているから、前記浮体2の後端部に衝突する流水を湾曲部25に沿って下流側に案内することができ、もって、衝突する流水の衝撃を緩和することができる。   In this embodiment, since the curved portion 25 is provided at the rear end portion of the floating body 2, the flowing water that collides with the rear end portion of the floating body 2 can be guided downstream along the curved portion 25. It is possible to alleviate the impact of the impinging running water.

又、本実施形態においては、甲板部の後端辺から底部内側に向かって斜めに角を切り落とした如きのテーパー形状の衝突面を有する緩衝部24が形成されているから、図4に示すように、緩衝部24に衝突する流水を衝突面に沿って下方向に案内することができ、もって、衝突する流水の衝撃を緩和することができる。   Further, in the present embodiment, since the buffer portion 24 having a tapered collision surface with a corner cut off obliquely from the rear end side of the deck portion toward the inside of the bottom portion is formed, as shown in FIG. Moreover, the running water that collides with the buffer portion 24 can be guided downward along the collision surface, so that the impact of the running water that collides can be reduced.

更に、浮体2の底部と管体内下部の内壁面との間には管体1の運搬方向沿って貫通する間隙5が設けられていることから、衝突面に沿って下方向に案内された流水は、間隙5内を通過して下流側に流出する。これにより、運搬時における管体1のバランスが非常に安定する。   Furthermore, since a gap 5 is provided between the bottom of the floating body 2 and the inner wall surface of the lower part of the tubular body so as to penetrate along the conveying direction of the tubular body 1, the running water guided downward along the collision surface. Passes through the gap 5 and flows out downstream. Thereby, the balance of the pipe body 1 at the time of conveyance becomes very stable.

加えて、管体1における管体内下部を通過する流水が、管体1の重心を下げるため、管体1が周方向へ回転すること(ローリング)が抑制される。   In addition, since the flowing water passing through the lower part of the tubular body 1 lowers the center of gravity of the tubular body 1, the tubular body 1 is prevented from rotating (rolling) in the circumferential direction.

なお付言するに、本実施形態においては、浮体2の底部22を平坦面とすることにより、浮体2の底部と管体内下部の内壁面との間に管体1の運搬方向沿って貫通する間隙5を形成し、運搬時に流水が当該間隙5を通過できるようにしているが、図5に示す別の管体構造のように、浮体2として、管体1の運搬方向に沿う貫通孔18を形成したものを用いても同様の効果が得られる。   In addition, in this embodiment, by making the bottom portion 22 of the floating body 2 a flat surface, a gap penetrating along the conveying direction of the tubular body 1 between the bottom portion of the floating body 2 and the inner wall surface of the lower portion of the tubular body. 5 is formed so that flowing water can pass through the gap 5 during transportation. However, as in the case of another tubular structure shown in FIG. 5, the floating body 2 has a through hole 18 along the transportation direction of the tubular body 1. The same effect can be obtained by using the formed one.

先頭の管体1が運搬先(この場合、施工区間の始端)に到達したならば、既設管Sの底部に、管体1を下支えする支持材10を配置し、管体1から衝撃緩衝治具6及び補助輪7を外す。次いで、管体1に浮体2を固定しているジャッキ3を縮め、浮体2を管体内下部の内壁面から浮上させて管体1の喫水を深くすることにより、管体1を沈めながら該管体1を前記支持材10上に載せる。更に、管体1の上部に浮上防止材11を配置し、管体1を既設管Sの所定位置に支持固定する。   When the first pipe body 1 reaches the transport destination (in this case, the start end of the construction section), a support member 10 that supports the pipe body 1 is arranged at the bottom of the existing pipe S, and the shock absorbing treatment is performed from the pipe body 1. Remove tool 6 and auxiliary wheel 7. Next, the jack 3 that fixes the floating body 2 to the tubular body 1 is shrunk, and the floating body 2 is lifted from the inner wall surface at the lower part of the tubular body to deepen the draft of the tubular body 1. The body 1 is placed on the support material 10. Further, the anti-floating material 11 is disposed on the upper portion of the tube body 1, and the tube body 1 is supported and fixed at a predetermined position of the existing tube S.

管体1を支持固定した後、既設管S内に固定された管体1から浮体2、ジャッキ3及びナイロンスリング93を外す。空になった管体内には、図3及び図6に示すように芯出し治具としてのキリンジャッキ12が取り付けられる。   After the tube body 1 is supported and fixed, the floating body 2, the jack 3 and the nylon sling 93 are removed from the tube body 1 fixed in the existing pipe S. As shown in FIGS. 3 and 6, a giraffe jack 12 as a centering jig is attached to the emptied tube.

先頭の管体1を施工区間の始端に支持固定したならば、同様にして後続する管体1を運搬し、その差し口1bを先頭の管体1の受け口1aに挿入し、先頭の管体1と後続の管体1とを連結する。   If the top tube 1 is supported and fixed at the start end of the construction section, the subsequent tube 1 is transported in the same manner, and the insertion port 1b is inserted into the receiving port 1a of the top tube 1 so that the top tube 1 and the succeeding tube body 1 are connected.

この際、既設管Sに支持固定された先行する管体1の高さ(固定位置)は、流水に浮いた状態の後続する管体1の高さ(浮上位置)より低い位置にある。そのため各管体1同士を連結するには、後続する管体1を先行する管体1の高さまで下げる高さ調整を行う必要がある。本実施形態においてこの高さ調整は、図7に示すように、後続する管体1において浮体2を固定しているジャッキ3を徐々に縮めてその固定位置を上方向に移動させ、浮体2を管体内下部の内壁面から浮上させて、管体1の喫水を徐々に深くすることによりことにより行う。   At this time, the height (fixed position) of the preceding pipe body 1 that is supported and fixed to the existing pipe S is at a position lower than the height (floating position) of the subsequent pipe body 1 that is floating in flowing water. Therefore, in order to connect the tubular bodies 1 to each other, it is necessary to perform height adjustment for lowering the succeeding tubular body 1 to the height of the preceding tubular body 1. In this embodiment, as shown in FIG. 7, this height adjustment is performed by gradually contracting the jack 3 that fixes the floating body 2 in the succeeding tube body 1 and moving the fixing position upward. This is done by rising from the inner wall surface of the lower part of the pipe body and gradually deepening the draft of the pipe body 1.

なお、ジャッキ3を緩めると浮体2の自由度が増し、該浮体2が動き易くなる。特に、自由度が増した浮体2は、流水に押されるようにして下流側に動き易くなる。   When the jack 3 is loosened, the degree of freedom of the floating body 2 increases and the floating body 2 becomes easy to move. In particular, the floating body 2 having an increased degree of freedom is easy to move downstream as it is pushed by running water.

この点につき、本実施形態においては、図7に示すように、浮体2の甲板部を覆う合板21に配した一対の支持部材8を浮体2の外側に向けてそれぞれ倒し、アームの先端に設けた車輪を管体1の受け口1a内壁に当接させて、支持部材8を心張り棒のようにして浮体2を管体1に支持することにより、浮体2が動くことを抑制している。   In this embodiment, as shown in FIG. 7, the pair of supporting members 8 arranged on the plywood 21 covering the deck portion of the floating body 2 are respectively brought down toward the outside of the floating body 2 and provided at the end of the arm. The floating body 2 is restrained from moving by making the wheel contact the inner wall of the receiving port 1a of the tubular body 1 and supporting the floating body 2 on the tubular body 1 like the support member 8 as a centering rod.

又、図8に示すように、別の支持部材19として管体1の外径より長い棒状部材を併用し、浮体2に設けた角材22に沿って配置すると共に該支持部材19の浮体2からはみ出した両端部を管体1の受け口1aの端部と当接させることにより、浮体2が流水に押されるようにして下流側に動くことを抑制しても良い。   Further, as shown in FIG. 8, a rod-like member longer than the outer diameter of the tubular body 1 is used in combination as another support member 19, arranged along the square member 22 provided on the floating body 2, and from the floating body 2 of the support member 19. The protruding both ends may be brought into contact with the end of the receiving port 1a of the tubular body 1 so that the floating body 2 is prevented from moving downstream by being pushed by running water.

管体1の高さ調整を終えると、管体1に取り付けられた衝撃緩衝治具6を外す。次いで、既設管Sに支持固定された先行する管体1に接近するように後続する管体1を移動させて、後続する管体1の差し口1bを先行する管体1に設置されたキリンジャッキ12の支持キャスター121に対向させる。この状態で、キリンジャッキ12のジャッキ122を伸ばし、起伏アーム123を介して支持キャスター121を上昇させることにより後続する管体1の差し口1bを持ち上げ、その軸心が先行する管体1の軸心と一致するように高さを微調整する。   When the height adjustment of the tube body 1 is completed, the shock absorbing jig 6 attached to the tube body 1 is removed. Next, the succeeding tube body 1 is moved so as to approach the preceding tube body 1 supported and fixed to the existing tube S, and the insertion port 1b of the succeeding tube body 1 is installed in the preceding tube body 1 It is made to oppose the support caster 121 of the jack 12. In this state, the jack 122 of the giraffe jack 12 is extended, and the support caster 121 is lifted through the hoisting arm 123 to lift the insertion port 1b of the succeeding tube body 1 so that the axis of the tube body 1 precedes the axis. Fine-tune the height to match your heart.

本実施形態においては、先行する管体1の受け口1aに後続する管体1の差し口1bを挿入するために、接続治具13が用いられる。この接続治具13は、図9に示すように、一対の接合板131、131を一対のレバーホイスト132を介して連結して構成される。各接合板131は、管体1の管本体部1cの端面に係合できるように、長さを調整できるようになっている。そして、接続治具13は、一方の接合板131を後続する管体1における受け口1aに係合させるとともに、他方の接合板131を先行する管体1における差し口1bに係合させた後、レバーホイスト132のワイヤーロープ133の先端に設けたシャックル134を各接合板131にそれぞれ係止する。その後、レバーホイスト132を操作して、後続する管体1側のワイヤーロープ133を引き取ることにより、先行する管体1に対して後続する管体1を強制的に引き寄せ、先行する管体1の受け口1aに後続する管体1の差し口1bを挿入する。   In the present embodiment, the connecting jig 13 is used to insert the insertion port 1b of the tube body 1 following the receiving port 1a of the preceding tube body 1. As shown in FIG. 9, the connecting jig 13 is configured by connecting a pair of joining plates 131 and 131 via a pair of lever hoists 132. Each joining plate 131 can be adjusted in length so that it can be engaged with the end surface of the tube main body 1c of the tube 1. Then, the connecting jig 13 engages one joining plate 131 with the receiving port 1a in the succeeding tubular body 1, and after engaging the other joining plate 131 with the insertion port 1b in the preceding tubular body 1, A shackle 134 provided at the tip of the wire rope 133 of the lever hoist 132 is engaged with each joining plate 131. Thereafter, by operating the lever hoist 132 and pulling the wire rope 133 on the succeeding tube body 1 side, the succeeding tube body 1 is forcibly pulled toward the preceding tube body 1, and the preceding tube body 1 The insertion port 1b of the tube body 1 following the receiving port 1a is inserted.

後続する管体1を先頭の管体1に接続したならば、管体1から浮体2、ジャッキ3及びナイロンスリング93を外す。次いで、後続する管体1の受け口1aを図示しない別のジャッキで持ち上げながら後続の管体1に取り付けられた補助輪7を取り外し、支持材10及び浮上防止材11を用いて支持固定する。   When the succeeding tubular body 1 is connected to the leading tubular body 1, the floating body 2, the jack 3 and the nylon sling 93 are removed from the tubular body 1. Next, the auxiliary wheel 7 attached to the succeeding tube body 1 is removed while lifting the receiving port 1a of the succeeding tube body 1 with another jack (not shown), and is supported and fixed using the support material 10 and the anti-floating material 11.

以下同様にして、複数個の管体1を施工区間にわたって連結し、支持固定して更生管Lを構築したならば(図10参照)、上流側末端の管体1の受け口1a側端部外周面に、既設管Sと管体1との間隙を閉塞する間仕切壁14を形成する(図11(a)参照)。前記間仕切壁14は、モルタルバッグからなり、該バッグを管体1に巻き付けた後、該バッグ内にモルタルを満たすことにより所定形状に膨張させ、既設管Sと管体1との間隙全面を閉塞する。この間仕切壁14の上方部には隙間が設けられており、この隙間から、裏込め材としてのエアーモルタルFを注入する注入パイプ15が長さを変えて複数本挿入される。   In the same manner, if a plurality of pipes 1 are connected over the construction section and supported and fixed to construct the rehabilitated pipe L (see FIG. 10), the outer periphery of the receiving end 1a side end of the upstream pipe 1 A partition wall 14 that closes a gap between the existing pipe S and the pipe body 1 is formed on the surface (see FIG. 11A). The partition wall 14 is composed of a mortar bag. After the bag is wound around the tube body 1, the bag is filled with the mortar to expand the bag into a predetermined shape, thereby closing the entire gap between the existing tube S and the tube body 1. To do. A gap is provided in an upper portion of the partition wall 14, and a plurality of injection pipes 15 for injecting air mortar F as a backfilling material are inserted through the gap with different lengths.

次いで、更生管Lにおける下流側末端の管体1の差し口1b側端部に、少なくとも既設管Sと管体1との間隙下半部を閉塞する間仕切壁14を形成する(図11(b)参照)。この間仕切壁14は、前述の上流側に形成した間仕切壁14と同形状のモルタルバッグからなり、ここでは、該バッグを管体1に巻き付けた後、該バッグ内にモルタルを半分程度満たしている。   Next, a partition wall 14 that closes at least the lower half of the gap between the existing pipe S and the pipe body 1 is formed at the end of the rehabilitating pipe L at the downstream end of the pipe body 1 of the pipe body 1 (FIG. 11B). )reference). The partition wall 14 is composed of a mortar bag having the same shape as the partition wall 14 formed on the upstream side. Here, after the bag is wound around the tube body 1, the bag is filled with about half of the mortar. .

そして本実施形態においては、下流側に形成した間仕切壁14の上方の開放部からポンプ16を差し入れ、既設管Sと更生管Lとの間隙に滞留する残水を揚水する。又、この残水の揚水作業と並行して、既設管Sと更生管Lとの間隙にエアーモルタルFを注入する。このエアーモルタルFの注入は、複数本ある注入パイプ15を短いものから長いものに順次替えながら行う(図11(b)〜(d)参照)。   And in this embodiment, the pump 16 is inserted from the open part above the partition wall 14 formed in the downstream, and the residual water which stays in the clearance gap between the existing pipe S and the renovated pipe L is pumped up. In parallel with this residual water pumping operation, air mortar F is injected into the gap between the existing pipe S and the renovated pipe L. The injection of the air mortar F is performed while sequentially changing the plurality of injection pipes 15 from a short one to a long one (see FIGS. 11B to 11D).

本実施形態において、エアーモルタルFの比重は1.16に調整されているため、既設管Sと更生管Lとの間隙に滞留する残水は、水よりも比重が大きなエアーモルタルFによって下流側に押し出される。押し出された残水は、順次ポンプ16によって揚水される。   In this embodiment, since the specific gravity of the air mortar F is adjusted to 1.16, the residual water staying in the gap between the existing pipe S and the renovated pipe L is downstream by the air mortar F having a specific gravity larger than that of water. Extruded. The extruded residual water is pumped up sequentially by the pump 16.

残水の揚水後、排水ポンプ16を取り出し、下流側の間仕切壁14を形成するモルタルバッグ内をモルタルで満たし、既設管Sと管体1との間隙全面を閉塞する。なお、この下流側の間仕切壁14の上方部の隙間には、空気抜き兼充填確認パイプ17が挿入される(図11(d)参照)。   After pumping up the remaining water, the drainage pump 16 is taken out, the inside of the mortar bag forming the downstream partition wall 14 is filled with mortar, and the entire gap between the existing pipe S and the pipe body 1 is closed. In addition, an air venting and filling confirmation pipe 17 is inserted into the gap above the partition wall 14 on the downstream side (see FIG. 11D).

裏込め材としてのエアーモルタルFが充填され、空気抜き兼充填確認パイプ17からエアーモルタルFが押し出されたことを確認したならば、既設管Sの内周面および更生管Lの外周面間の間隙にエアーモルタルFが充填されたものと判断する。   If it is confirmed that the air mortar F as the backfilling material is filled and the air mortar F is pushed out from the air venting / filling confirmation pipe 17, the gap between the inner peripheral surface of the existing pipe S and the outer peripheral surface of the renovated pipe L To be filled with air mortar F.

1 管体
2 浮体
3 ジャッキ(固定治具)
4 当て板
5 間隙
6 衝撃緩衝治具
7 補助輪
8 支持部材
9 ウインチ
10 支持材
11 浮上防止材
12 キリンジャッキ(芯出し治具)
13 接続治具
14 間仕切壁
15 注入パイプ
16 ポンプ
17 空気抜き兼充填確認パイプ
18 貫通孔
19 支持部材
L 更生管
S 既設管
F エアーモルタル(裏込め材)
1 Tube 2 Floating body 3 Jack (fixing jig)
4 Abutting plate 5 Gap 6 Impact buffer jig 7 Auxiliary wheel 8 Support member 9 Winch 10 Support material 11 Lifting prevention material 12 Kirin jack (centering jig)
13 Connecting jig 14 Partition wall 15 Injection pipe 16 Pump 17 Air venting and filling confirmation pipe 18 Through hole 19 Support member L Rehabilitation pipe S Existing pipe F Air mortar (back filling material)

Claims (4)

流水が存在する既設管内において、複数の管体を順次運搬し、連結することにより、既設管内に複数の管体が連結された更生管を構築する既設管の更生方法において、
運搬される管体における管体内下部に、管体の内部空間を上下に分ける比重が1未満の浮体を、固定治具を介して着脱自在に固定することによって、前記運搬される管体に対し、既設管内の流水に浮かび得る浮力を付与し、
前記浮力が付与された管体を既設管内の流水に浮かせながら上流から下流に向かって順次運搬し、
運搬先において、前記固定治具による浮体の固定位置を管体内の上方向に移動させて、管体の喫水を深くすることにより管体の高さ調整を行うことを特徴とする既設管の更生方法。
In an existing pipe rehabilitation method for constructing a rehabilitation pipe in which a plurality of pipes are connected in an existing pipe by sequentially transporting and connecting a plurality of pipes in the existing pipe where flowing water exists.
A floating body having a specific gravity of less than 1 that divides the internal space of the pipe body in the vertical direction is detachably fixed to the lower part of the pipe body to be transported with respect to the transported pipe body. , Giving buoyancy that can float in running water in existing pipes,
Carrying the pipe body to which the buoyancy is imparted in order from the upstream to the downstream while floating in the running water in the existing pipe,
Rehabilitation of an existing pipe, wherein the height of the pipe body is adjusted by moving the fixing position of the floating body by the fixing jig upward in the transport destination and deepening the draft of the pipe body Method.
流水が存在する既設管内において、複数の管体を順次運搬し、連結することにより、既設管内に複数の管体が連結された更生管を構築する既設管の更生方法において、
運搬される管体における管体内下部に、管体の運搬方向に沿って管体内を水が通過できる貫通孔が設けられた比重が1未満の浮体を、固定治具を介して着脱自在に固定することによって、前記運搬される管体に対し、既設管内の流水に浮かび得る浮力を付与し、
前記浮力が付与された管体を既設管内の流水に浮かせながら上流から下流に向かって順次運搬し、
運搬先において、前記固定治具による浮体の固定位置を管体内の上方向に移動させて、管体の喫水を深くすることにより管体の高さ調整を行うことを特徴とする既設管の更生方法。
In an existing pipe rehabilitation method for constructing a rehabilitation pipe in which a plurality of pipes are connected in an existing pipe by sequentially transporting and connecting a plurality of pipes in the existing pipe where flowing water exists.
A floating body having a specific gravity of less than 1 provided with a through-hole through which water can pass through the pipe body along the carrying direction of the pipe body is detachably fixed via a fixing jig. By giving the buoyant force that can float on the flowing water in the existing pipe,
Carrying the pipe body to which the buoyancy is imparted in order from the upstream to the downstream while floating in the running water in the existing pipe,
Rehabilitation of an existing pipe, wherein the height of the pipe body is adjusted by moving the fixing position of the floating body by the fixing jig upward in the transport destination and deepening the draft of the pipe body Method.
請求項1又は2に記載の既設管の更生方法において、管体に索体の一端を固定し、上流側から索体を繰り出すことにより管体の流下速度をコントロールしながら既設管内を流れる流水に乗せて管体を運搬する既設管の更生方法。   The rehabilitation method for an existing pipe according to claim 1 or 2, wherein one end of the cable body is fixed to the pipe body, and the flowing water flowing in the existing pipe is controlled by controlling the flow speed of the pipe body by extending the cable body from the upstream side. Rehabilitation method for existing pipes that carry pipes on board. 請求項1ないし3のいずれか1項に記載の既設管の更生方法において、固定治具による浮体の固定位置を管体内の上方向に移動することによって自由度が高くなった浮体の動きを抑制するために、支持部材を介して浮体を管体に支持する既設管の更生方法。   The rehabilitation method for an existing pipe according to any one of claims 1 to 3, wherein the movement of the floating body having a high degree of freedom is suppressed by moving the fixing position of the floating body by the fixing jig upward. In order to do so, a method for rehabilitating an existing pipe that supports the floating body on the pipe body via a support member.
JP2010077990A 2010-03-30 2010-03-30 Rehabilitation of existing pipes Active JP5558888B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010077990A JP5558888B2 (en) 2010-03-30 2010-03-30 Rehabilitation of existing pipes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010077990A JP5558888B2 (en) 2010-03-30 2010-03-30 Rehabilitation of existing pipes

Publications (2)

Publication Number Publication Date
JP2011208746A JP2011208746A (en) 2011-10-20
JP5558888B2 true JP5558888B2 (en) 2014-07-23

Family

ID=44940015

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010077990A Active JP5558888B2 (en) 2010-03-30 2010-03-30 Rehabilitation of existing pipes

Country Status (1)

Country Link
JP (1) JP5558888B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7128033B2 (en) 2018-06-04 2022-08-30 積水化学工業株式会社 Jigs, tubes with jigs, how to use jigs and how to transport tubes

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6483739A (en) * 1987-09-28 1989-03-29 Sekisui Chemical Co Ltd Method of fixing inserting pipe to sheath pipe
JPH09100947A (en) * 1995-10-09 1997-04-15 Sekisui Chem Co Ltd Piping method in existing pipeline
JP5060392B2 (en) * 2008-05-26 2012-10-31 積水化学工業株式会社 Rehabilitation method for pipes and existing pipes

Also Published As

Publication number Publication date
JP2011208746A (en) 2011-10-20

Similar Documents

Publication Publication Date Title
CN105102317B (en) Floatability transport and mounting structure, correlation technique and floatation type wind turbine
EP2428616A2 (en) Method and apparatus for installing marine equipment, especially offshore wind turbines
KR102248621B1 (en) Floating transfer ocean structure and construction method thereof
CN111692426B (en) Offshore welded junction loosening treatment method for large-diameter HDPE pipeline
KR100940795B1 (en) Method for launching and transporting heavy weight structures using air bags
JP5558888B2 (en) Rehabilitation of existing pipes
CN110130342B (en) Piling equipment and piling method for underwater reinforced concrete prefabricated sheet pile construction
JP5485660B2 (en) Rehabilitation of existing pipes
US9909274B2 (en) Wind turbine parts handling method and device
CN104649039A (en) Concrete transfer device
JP5060392B2 (en) Rehabilitation method for pipes and existing pipes
KR20070104066A (en) Floating building berth for small vessel
CN110053720A (en) Immersed tube combination transport installs equipment and transportation installation method
AU2012201899B2 (en) Boat Lifting Apparatus and Method
CN201786634U (en) Submersible pump rack
JP6496507B2 (en) Buoyancy body and method of adjusting desiccation
KR101124101B1 (en) Floating dock for ship building
CN213625682U (en) Long structure ballast type suction pile
JP2017044064A (en) Underwater arrangement structure and underwater conveyance method for structure for underwater structure
CN213773445U (en) Short structure ballast type suction pile
CN211141314U (en) Submerged pipe fishing platform
CN210126614U (en) Immersed tube combined type transportation and installation equipment
CN112227413A (en) Short structure ballast type suction pile
CN219974837U (en) Suspension pumping device
US20220356978A1 (en) Decommissioning Subsea Infrastructure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130219

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131227

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140225

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140404

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140507

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140605

R150 Certificate of patent or registration of utility model

Ref document number: 5558888

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250