JP4381631B2 - Unit building shed structure - Google Patents

Unit building shed structure Download PDF

Info

Publication number
JP4381631B2
JP4381631B2 JP2001185188A JP2001185188A JP4381631B2 JP 4381631 B2 JP4381631 B2 JP 4381631B2 JP 2001185188 A JP2001185188 A JP 2001185188A JP 2001185188 A JP2001185188 A JP 2001185188A JP 4381631 B2 JP4381631 B2 JP 4381631B2
Authority
JP
Japan
Prior art keywords
shed
roof
building
unit
ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001185188A
Other languages
Japanese (ja)
Other versions
JP2003003570A (en
Inventor
淳 堀内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP2001185188A priority Critical patent/JP4381631B2/en
Publication of JP2003003570A publication Critical patent/JP2003003570A/en
Application granted granted Critical
Publication of JP4381631B2 publication Critical patent/JP4381631B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、例えば、箱状のユニットで形成されたユニット式建物の小屋組構造に関する。
【0002】
【背景技術】
従来、住宅等の建物の工法として、ユニット工法がある。ユニット工法とは、工場において、箱状の骨組みに、天井面材、床面材、外壁材、間仕切壁等を取り付けて形成した建物ユニットを製造し、これら箱状の建物ユニットを建築現場で複数組み合わせて建築するものである。
ユニット工法は、予め工場でできるだけ部材の加工・組立を行い、これらを運搬して現場で組み上げる施工方法であるため、従来建築現場で行っていた作業がほとんど工場で行われることとなり、建築現場での作業が著しく軽減され、高品質の建物を短期間で建築できるという利点がある。
【0003】
ところで、ユニット式建物における屋根部分の構造としては、各建物ユニット上に束やブレースによる軸組を形成し、この軸組で屋根を支持する構造が知られている(特願2000−41042号参照)。
【0004】
【発明が解決しようとする課題】
しかし、上述したユニット式建物では、例えば、屋根を特殊な形状とする場合や、屋根を複数種類の材料で形成する場合には、屋根の各建物ユニットへの荷重分布が屋根全体に均等にならないため、天井梁に過大な荷重がかかる可能性があった。そのため、大きな屋根荷重に耐えうる天井梁を備えた特殊な建物ユニットを用いる必要があり、製造コストの増大となっていた。
【0005】
本発明の目的は、大きな屋根荷重がかかる場合でも、経済的かつ確実に屋根を支持できるユニット式建物の小屋組構造を提供することにある。
【0006】
【課題を解決するための手段】
上記目的を達成するため、本発明のユニット式建物の小屋組構造は、次の構成を採用する。
本発明を図面を参照して説明すると、請求項1に記載のユニット式建物10の小屋組構造は、四隅の柱41の上下端を天井梁42および床梁43で連結して箱状に形成されたフレーム40を有する建物ユニット17をその角隅部Dを寄せ合わせて複数配置した屋根下建物ユニット16と、これら屋根下建物ユニット上に設けられた支持構造13と、この支持構造に支持された屋根14とを備えたユニット式建物の小屋組構造であって、屋根下建物ユニットを構成する建物ユニットの柱のうち、寄せ合わされた4つの角隅部の柱が省略されて大空間が形成され、支持構造は、小屋梁20と、2つの小屋フレーム30とを備え、小屋梁は、2本の長尺材21が抱き合わされて形成され、省略された4つの柱の両側に位置する4つの柱の間に架け渡された4つの天井梁上に配置され、各長尺材は、天井梁の長手方向に直交する方向に隣接する各天井梁上にそれぞれ配置され、各小屋フレームは、小屋梁を構成する部材と同一断面を有する部材により枠状に形成されるとともに、互いに隣接して配置されるように、かつ、角部が長尺材の一端にそれぞれ隣接して配置されるように、屋根下建物ユニットの各天井梁に積層されることを特徴とする。
【0007】
この発明によれば、屋根下建物ユニットの少なくとも1本の天井梁に沿って小屋梁を配置したので、この小屋梁によって天井梁が補強され、大きな屋根荷重がかかった場合でも、屋根を確実に支持できる。
また、天井梁に沿って小屋梁を配置するだけで、屋根下建物ユニット自体に何ら手を加えることなく、大きな屋根荷重がかかる天井梁だけを部分的に補強できるから、経済的である。
【0009】
この発明によれば、2本の長尺材を抱き合わせて小屋梁を形成したので、小屋梁を1本の長尺材で形成した場合に比べ剛性を向上できるから、小屋梁の構造耐力を向上できる。
【0011】
この発明によれば、屋根下建物ユニットのうち少なくとも1つの建物ユニットの各天井梁上に枠状の小屋フレームを積層したので、支持構造で受ける屋根荷重を1つの屋根下建物ユニット全体で支持することができ、屋根下建物ユニット全体の屋根荷重に対する構造耐力をさらに向上できる。
また、小屋梁と小屋フレームとを混用することによって、屋根下建物ユニットの所望の天井梁を安価かつ自在に補強することができ、屋根の意匠設計、構造設計の自由度を向上できる。
【0013】
この発明によれば、小屋フレームを構成する枠材を小屋梁を構成する部材と同一断面を有する部材で形成したので、小屋梁および小屋フレームの部品を共通化でき、支持構造の製造コストを低減できる。
また、小屋梁および小屋フレームの断面係数が同一となるから、小屋梁および小屋フレームの構造計算を容易に行うことができる。
【0015】
この発明によれば、建物ユニットの柱のうち寄せ合わされた1組の角隅部の柱を省略して大空間を形成したので、ユニット式建物内部の設計の自由度を向上できる。
この時、省略された柱の両側に位置する柱の間に小屋梁を架け渡したので、つまり、大空間の両端に位置する柱に小屋梁を設けたので、柱を省略したことによる屋根下建物ユニットの天井梁の構造耐力の低下を補うことができる。
【0016】
請求項1に記載のユニット式建物の小屋組構造は、請求項1から5のいずれかに記載のユニット式建物の小屋組構造において、前記支持構造は、小屋梁の上に立設された束を含んで構成されていることを特徴とする。
この発明によれば、小屋梁の上に立設された束を含んで支持構造を構成したので、屋根下建物ユニットの上に直接束を立設する場合に比べ、束の長さを短くするだけでよいから、支持構造の製造コストを低減できる。
【0017】
【発明の実施の形態】
以下、本発明の実施形態を図面に基づいて説明する。
図1には、本実施形態に係るユニット式建物10の全体斜視図が示されている。
ユニット式建物10は、基礎11と、この基礎11の上に設けられた建物本体12と、この建物本体12の上に設けられた支持構造13と、この支持構造13に支持された屋根14とを備えている。
このうち、建物本体12は、1階建物ユニット15と、この1階建物ユニット15の上に配置されかつ屋根14の下に位置する屋根下建物ユニットとしての2階建物ユニット16とを備え、これら1階建物ユニット15および2階建物ユニット16は、箱状に形成された建物ユニット17が複数組合わせて形成されている。
【0018】
建物ユニット17は、図2に示すように、四隅の柱41の上下端を連結する天井梁42および床梁43を有する箱状のフレーム40を備えている。このうち、柱41と天井梁42とは、柱41の柱頭側に配置される柱頭接合部材45を介して連結され、柱41と床梁43とは、柱41の柱脚側に配置される柱脚接合部材46を介して連結されている。
天井梁42としては、長さの異なる短辺天井梁42Aおよび長辺天井梁42Bの二種類が設けられ、床梁43としては、長さの異なる短辺床梁43Aおよび長辺床梁43Bの二種類が設けられている。また、対向する長辺天井梁42Bの間には、天井面材を支持するための天井小梁が架け渡され(図示省略)、また、対向する長辺床梁43Bの間には、床を形成するパーチクルボード等の床面材を支持するための複数の根太が架け渡されている(図示省略)。
【0019】
図3には、2階建物ユニット16の平面図が示されている。
1階建物ユニット15および2階建物ユニット16は、建物ユニット17をその角隅部Dを寄せ合わせて、梁間方向に3個、桁行方向に2個の計6個配置することにより形成されている。
したがって、2階建物ユニット16において、外周側では、2つの建物ユニット17の2つの角隅部Dが寄せ合わされて1組となっており、内部側では、4つの建物ユニット17の4つの角隅部Dが寄せ合わされて1組となっている。
【0020】
ここで、図3中右側を南側とすると、2階建物ユニット16を構成する建物ユニット17の柱41のうち寄せ合わされた1組の角隅部Dの柱41、ここでは、内部南側に位置する1組の角隅部Dの4本の柱41が省略されており(図3中点線で示す)、これによって、2階建物ユニット16の南側に大空間が形成されている。
【0021】
図4には、支持構造13の平面図が示され、図5には、図4のV−V断面図が示されている。
支持構造13は、省略された柱41の梁間方向両側に位置する柱41の間に短辺天井梁42Aに沿って架け渡された小屋梁20と、この小屋梁20の北側に隣接しかつ2階建物ユニット16の建物ユニット17の各天井梁42に積層された2つの小屋フレーム30と、これら小屋梁20、小屋フレーム30および2階建物ユニット16上に設けられた束50,51,52とを備えている。
【0022】
図6(A)には、小屋梁20の全体斜視図が示されている。
小屋梁20は、短辺天井梁2本分の長さを有する長尺材21が2本抱き合わされて形成されている。
図6(B)には、小屋フレーム30の全体斜視図が示されている。
小屋フレーム30は、小屋梁20を構成する部材と同一断面を有する部材、ここでは長尺材21が柱脚接合部材46を介して枠状に連結されて形成されている。
【0023】
図4および図5に戻って、束50〜52は、2階建物ユニット16の内部側に立設され、屋根14の棟部と軒先部の中間を支持するようになっている。
【0024】
次に、ユニット式建物10を組み立てる手順を説明する。
まず、建物ユニット17、小屋梁20、小屋フレーム30、束50〜52を工場で製作した後、建築現場に運搬する。運搬の際、柱41が省略された建物ユニット17の変形を防止するために、省略された柱41の代わりに図示しない仮柱を設けておく。
現場では、基礎11を施工した後、各建物ユニット17をその角隅部Dを寄せ合わせて隣接配置し、1階建物ユニット15および2階建物ユニット16を形成する。
【0025】
次に、省略された柱41の梁間方向両側に位置する柱41の間に小屋梁20を架け渡すとともに、2階建物ユニット16の建物ユニット17の各天井梁42に小屋フレーム30を積層する。その後、小屋梁20および小屋フレーム30を2階建物ユニット16の柱頭接合部材45にボルト等で連結した後、2階建物ユニット16内の仮柱を撤去する。
【0026】
次に、束50〜52を、小屋梁20、小屋フレーム30および2階建物ユニット16上にボルト等で固定し、これら束50〜52上に屋根14を設置する。
なお、本実施形態では、現場において束50〜52を取り付けたが、これに限らず、工場で予め取り付けておいてもよい。
【0027】
したがって、本実施形態によれば以下の効果がある。
(1)2階建物ユニット16の短辺天井梁42Aに沿って小屋梁20を配置したので、この小屋梁20によって短辺天井梁42Aが補強され、大きな屋根荷重がかかった場合でも、屋根14を確実に支持できる。
また、天井梁42に沿って小屋梁20を配置するだけで、2階建物ユニット16自体に何ら手を加えることなく、大きな屋根荷重がかかる天井梁42だけを部分的に補強できるから、経済的である。
【0028】
(2)2本の長尺材21を抱き合わせて小屋梁20を形成したので、小屋梁20を1本の長尺材21で形成した場合に比べ剛性を向上できるから、小屋梁20の構造耐力を向上できる。
【0029】
(3)2階建物ユニット16のうち2つの建物ユニット17の各天井梁42上に枠状の小屋フレーム30を積層したので、支持構造13で受ける屋根荷重を1つの2階建物ユニット16全体で支持することができ、2階建物ユニット16全体の屋根荷重に対する構造耐力をさらに向上できる。
また、小屋梁20と小屋フレーム30とを混用することによって、2階建物ユニット16の所望の天井梁42を安価かつ自在に補強することができ、屋根の意匠設計、構造設計の自由度を向上できる。
【0030】
(4)小屋フレーム30を構成する枠材を小屋梁20を構成する部材と同一断面を有する長尺材21で形成したので、小屋梁20および小屋フレーム30の部品を共通化でき、支持構造13の製造コストを低減できる。
また、小屋梁20および小屋フレーム30の断面係数が同一となるから、小屋梁20および小屋フレーム30の構造計算を容易に行うことができる。
【0031】
(5)建物ユニット17の柱41のうち寄せ合わされた1組の角隅部Dの柱41を省略して大空間を形成したので、ユニット式建物10内部の設計の自由度を向上できる。
この時、省略された柱41の両側に位置する柱41の間に小屋梁20を架け渡したので、つまり、大空間の両端に位置する柱41に小屋梁20を設けたので、柱41を省略したことによる2階建物ユニット16の天井梁42の構造耐力の低下を補うことができる。
【0032】
(6)小屋梁20の上に立設された束50Bを含んで支持構造13を構成したので、2階建物ユニット16の上に直接束52を立設する場合に比べ、束の長さを短くするだけでよいから、支持構造13の製造コストを低減できる。
【0033】
なお、本発明は前記実施形態に限定されるものではなく、本発明の目的を達成できる範囲での変形、改良等は本発明に含まれるものである
【0034】
【発明の効果】
本発明のユニット式建物の小屋組構造によれば、次のような効果が得られる。
請求項1に記載のユニット式建物の小屋組構造によれば、屋根下建物ユニットの少なくとも1本の天井梁に沿って小屋梁を配置したので、この小屋梁によって天井梁が補強され、大きな屋根荷重がかかった場合でも、屋根を確実に支持できる。
また、天井梁に沿って小屋梁を配置するだけで、屋根下建物ユニット自体に何ら手を加えることなく、大きな屋根荷重がかかる天井梁だけを部分的に補強できるから、経済的である。
【0035】
また、2本の長尺材を抱き合わせて小屋梁を形成したので、小屋梁を1本の長尺材で形成した場合に比べ剛性を向上できるから、小屋梁の構造耐力を向上できる。
【0036】
さらに、屋根下建物ユニットのうち少なくとも1つの建物ユニットの各天井梁上に枠状の小屋フレームを積層したので、支持構造で受ける屋根荷重を1つの屋根下建物ユニット全体で支持することができ、屋根下建物ユニット全体の屋根荷重に対する構造耐力をさらに向上できる。
また、小屋梁と小屋フレームとを混用することによって、屋根下建物ユニットの所望の天井梁を安価かつ自在に補強することができ、屋根の意匠設計、構造設計の自由度を向上できる。
【0037】
加えて、小屋フレームを構成する枠材を小屋梁を構成する部材と同一断面を有する部材で形成したので、小屋梁および小屋フレームの部品を共通化でき、支持構造の製造コストを低減できる。
また、小屋梁および小屋フレームの断面係数が同一となるから、小屋梁および小屋フレームの構造計算を容易に行うことができる。
【0038】
また、建物ユニットの柱のうち寄せ合わされた1組の角隅部の柱を省略して大空間を形成したので、ユニット式建物内部の設計の自由度を向上できる。
この時、省略された柱の両側に位置する柱の間に小屋梁を架け渡したので、つまり、大空間の両端に位置する柱に小屋梁を設けたので、柱を省略したことによる屋根下建物ユニットの天井梁の構造耐力の低下を補うことができる。
【0039】
請求項2に記載のユニット式建物の小屋組構造によれば、小屋梁の上に立設された束を含んで支持構造を構成したので、屋根下建物ユニットの上に直接束を立設する場合に比べ、束の長さを短くするだけでよいから、支持構造の製造コストを低減できる。
【図面の簡単な説明】
【図1】本発明の一実施形態に係るユニット式建物を示す全体斜視図である。
【図2】前記実施形態に係る建物ユニットのフレームの斜視図である。
【図3】前記実施形態に係る屋根下建物ユニットの平面図である。
【図4】前記実施形態に係る支持構造の平面図である。
【図5】図4のV−V断面図である。
【図6】前記実施形態に係る小屋梁および小屋フレームの斜視図である。
【符号の説明】
10 ユニット式建物
13 支持構造
14 屋根
16 屋根下建物ユニットとしての2階建物ユニット
17 建物ユニット
20 小屋梁
21 長尺材
30 小屋フレーム
40 建物ユニットのフレーム
41 柱
42 天井梁
43 床梁
D 角隅部
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a shed structure of a unit type building formed of, for example, box-shaped units.
[0002]
[Background]
Conventionally, there is a unit construction method as a construction method for a building such as a house. The unit construction method is to manufacture building units formed by attaching ceiling surface materials, floor surface materials, outer wall materials, partition walls, etc. to a box-shaped framework in a factory, and multiple such box-shaped building units are built at the construction site. It is constructed by combining.
The unit method is a construction method in which parts are processed and assembled in advance at the factory as much as possible, and these are transported and assembled at the work site. This has the advantage that the high-quality building can be built in a short period of time.
[0003]
By the way, as a structure of the roof part in a unit type building, the structure which forms the axis | shaft by a bundle | bundle or a brace on each building unit, and supports a roof by this axis | shaft is known (refer Japanese Patent Application No. 2000-41042). ).
[0004]
[Problems to be solved by the invention]
However, in the unit type building described above, for example, when the roof has a special shape, or when the roof is formed of a plurality of types of materials, the load distribution on each building unit of the roof is not uniform over the entire roof. Therefore, an excessive load may be applied to the ceiling beam. Therefore, it is necessary to use a special building unit having a ceiling beam that can withstand a large roof load, which increases the manufacturing cost.
[0005]
An object of the present invention is to provide a roof structure of a unit type building that can support a roof economically and reliably even when a large roof load is applied.
[0006]
[Means for Solving the Problems]
In order to achieve the above object, the unit building building structure according to the present invention employs the following configuration.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Referring to the drawings, the present invention will be described with reference to the drawings. The unit building structure of a unit building 10 according to claim 1 is formed in a box shape by connecting the upper and lower ends of pillars 41 at four corners with ceiling beams 42 and floor beams 43. A plurality of building units 17 each having a frame 40 arranged with their corners D aligned, a support structure 13 provided on these roof building units, and a support structure supported by the support structure. A unit-type building shed structure with an open roof 14, and a large space is formed by omitting the four corner corner pillars of the building unit constituting the under-floor building unit. The support structure includes a shed beam 20 and two shed frames 30, and the shed beam is formed by tying two long members 21 and is positioned on both sides of four omitted columns 4. Bridge between two pillars Each of the long members is arranged on each of the ceiling beams adjacent to each other in a direction perpendicular to the longitudinal direction of the ceiling beam, and each shed frame is a member constituting the shed beam It is formed in a frame shape by members having the same cross section, and is arranged adjacent to each other, and the corner portion is arranged adjacent to one end of the long material. It is characterized by being stacked on each ceiling beam .
[0007]
According to the present invention, the roof beams are arranged along at least one ceiling beam of the building unit under the roof, so that the ceiling beams are reinforced by the roof beams, and even when a large roof load is applied, the roof is surely secured. I can support it.
In addition, it is economical because only the roof beams that are subjected to a large roof load can be partially reinforced by simply arranging the roof beams along the ceiling beams without any modification to the under-floor building unit itself.
[0009]
According to the present invention, since the shed beam is formed by tying two long materials, the rigidity can be improved compared to the case where the shed beam is formed by one long material, so that the structural strength of the shed beam is improved. it can.
[0011]
According to the present invention, since the frame-shaped shed frame is laminated on each ceiling beam of at least one building unit among the roof building units, the roof load received by the support structure is supported by the whole roof building unit. It is possible to further improve the structural strength against the roof load of the entire building unit under the roof.
Further, by mixing the shed beam and the shed frame, the desired ceiling beam of the building unit under the roof can be reinforced at a low cost and the degree of freedom in the design and structural design of the roof can be improved.
[0013]
According to this invention, since the frame material constituting the shed frame is formed of a member having the same cross section as the member constituting the shed beam, the shed beam and the shed frame parts can be shared, and the manufacturing cost of the support structure is reduced. it can.
Further, since the cross section coefficients of the shed beam and the shed frame are the same, the structural calculation of the shed beam and the shed frame can be easily performed.
[0015]
According to the present invention, since a large space is formed by omitting a pair of corner corner pillars brought together among the pillars of the building unit, the degree of freedom in designing the interior of the unit type building can be improved.
At this time, because the shed beams were bridged between the columns located on both sides of the omitted columns, that is, the shed beams were provided on the columns located at both ends of the large space, so the roof under the column was omitted. It can compensate for the decrease in structural strength of the ceiling beam of the building unit.
[0016]
Roof structure construction of unitary building according to claim 1, in roof truss structures unitary building according to any one of claims 1 to 5, wherein the support structure beams erected on the tie beam It is characterized by including.
According to the present invention, since the support structure is configured including the bundle standing up on the roof beam, the length of the bundle is shortened compared to the case where the bundle is directly installed on the building unit under the roof. Therefore, the manufacturing cost of the support structure can be reduced.
[0017]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 is an overall perspective view of a unit building 10 according to the present embodiment.
The unit building 10 includes a foundation 11, a building body 12 provided on the foundation 11, a support structure 13 provided on the building body 12, and a roof 14 supported by the support structure 13. It has.
Among these, the building body 12 includes a first-floor building unit 15 and a second-floor building unit 16 that is disposed on the first-floor building unit 15 and is located under the roof 14 and is a lower-floor building unit 16. The first-floor building unit 15 and the second-floor building unit 16 are formed by combining a plurality of building units 17 formed in a box shape.
[0018]
As shown in FIG. 2, the building unit 17 includes a box-shaped frame 40 having a ceiling beam 42 and a floor beam 43 connecting the upper and lower ends of the pillars 41 at the four corners. Among these, the column 41 and the ceiling beam 42 are connected via a column head joint member 45 disposed on the column head side of the column 41, and the column 41 and the floor beam 43 are disposed on the column leg side of the column 41. The column base joint members 46 are connected to each other.
There are two types of ceiling beams 42, short-side ceiling beams 42A and long-side ceiling beams 42B having different lengths, and floor beams 43 are short-side floor beams 43A and long-side floor beams 43B having different lengths. Two types are provided. Further, a ceiling beam for supporting the ceiling surface material is bridged between the opposing long side ceiling beams 42B (not shown), and a floor is provided between the opposing long side floor beams 43B. A plurality of joists for supporting a floor material such as a particle board to be formed are bridged (not shown).
[0019]
FIG. 3 shows a plan view of the second-floor building unit 16.
The first-floor building unit 15 and the second-floor building unit 16 are formed by arranging a total of six building units 17 with the corners D thereof being brought close together, three in the beam-to-beam direction and two in the column direction. .
Accordingly, in the second-floor building unit 16, the two corners D of the two building units 17 are brought together in the outer peripheral side to form one set, and the four corners of the four building units 17 are arranged on the inner side. Part D is brought together to form one set.
[0020]
Here, assuming that the right side in FIG. 3 is the south side, one set of the pillars 41 of the corner corner D, which are brought together among the pillars 41 of the building unit 17 constituting the second-floor building unit 16, here, located on the south side inside The four columns 41 at one set of corner corners D are omitted (indicated by dotted lines in FIG. 3), thereby forming a large space on the south side of the second-floor building unit 16.
[0021]
FIG. 4 shows a plan view of the support structure 13, and FIG. 5 shows a VV cross-sectional view of FIG. 4.
The support structure 13 includes a shed beam 20 spanned along the short-side ceiling beam 42A between the columns 41 located on both sides of the omitted column 41 in the inter-beam direction, and adjacent to the north side of the shed beam 20 and 2 Two shed frames 30 stacked on each ceiling beam 42 of the building unit 17 of the floor building unit 16, and bundles 50, 51, 52 provided on the shed beam 20, the shed frame 30 and the second floor building unit 16, It has.
[0022]
FIG. 6A shows an overall perspective view of the roof beam 20.
The hut beam 20 is formed by tying two long materials 21 having a length corresponding to two short side ceiling beams.
FIG. 6B shows an overall perspective view of the cabin frame 30.
The shed frame 30 is formed by connecting members having the same cross section as the members constituting the shed beam 20, in this case, the long material 21 in a frame shape via a column base joint member 46.
[0023]
Returning to FIGS. 4 and 5, the bundles 50 to 52 are erected on the inner side of the second-floor building unit 16 and support the middle of the ridge portion and the eaves portion of the roof 14.
[0024]
Next, a procedure for assembling the unit building 10 will be described.
First, the building unit 17, the shed beam 20, the shed frame 30, and the bundles 50 to 52 are manufactured at the factory and then transported to the construction site. In order to prevent deformation of the building unit 17 from which the column 41 is omitted during transportation, a temporary column (not shown) is provided instead of the omitted column 41.
At the site, after the foundation 11 is constructed, the building units 17 are arranged adjacent to each other with their corners D aligned to form the first floor building unit 15 and the second floor building unit 16.
[0025]
Next, the shed beam 20 is bridged between the columns 41 located on both sides of the omitted column 41 in the beam direction, and the shed frame 30 is laminated on each ceiling beam 42 of the building unit 17 of the second-floor building unit 16. Then, after connecting the shed beam 20 and the shed frame 30 to the stigma joining member 45 of the second floor building unit 16 with a bolt or the like, the temporary pillar in the second floor building unit 16 is removed.
[0026]
Next, the bundles 50 to 52 are fixed on the roof beams 20, the cabin frame 30, and the second floor building unit 16 with bolts or the like, and the roof 14 is installed on these bundles 50 to 52.
In the present embodiment, the bundles 50 to 52 are attached at the site. However, the present invention is not limited to this, and the bundles 50 to 52 may be attached in advance at the factory.
[0027]
Therefore, according to this embodiment, there are the following effects.
(1) Since the roof beams 20 are arranged along the short-side ceiling beams 42A of the second-floor building unit 16, the roof beams 14A are reinforced by the roof beams 20 even when a large roof load is applied. Can be reliably supported.
Moreover, since only the roof beam 20 along the ceiling beam 42 is disposed and only the ceiling beam 42 to which a large roof load is applied can be partially reinforced without any modification to the second-floor building unit 16 itself. It is.
[0028]
(2) Since the shed beam 20 is formed by tying two elongate members 21 together, the rigidity can be improved compared to the case where the shed beam 20 is formed by one elongate member 21, and thus the structural strength of the shed beam 20 Can be improved.
[0029]
(3) Since the frame-like shed frame 30 is laminated on the ceiling beams 42 of the two building units 17 out of the two-floor building units 16, the roof load received by the support structure 13 is spread across the entire two-floor building unit 16. The structural strength against the roof load of the entire second-floor building unit 16 can be further improved.
In addition, by combining the shed beam 20 and the shed frame 30, the desired ceiling beam 42 of the second-floor building unit 16 can be reinforced at low cost and the degree of freedom in design and structural design of the roof is improved. it can.
[0030]
(4) Since the frame material constituting the shed frame 30 is formed of the long material 21 having the same cross section as the members constituting the shed beam 20, the parts of the shed beam 20 and the shed frame 30 can be shared, and the support structure 13 The manufacturing cost can be reduced.
Moreover, since the section modulus of the shed beam 20 and the shed frame 30 is the same, the structural calculation of the shed beam 20 and the shed frame 30 can be easily performed.
[0031]
(5) Since the large space is formed by omitting the set of corners D of the corners D of the columns 41 of the building unit 17, the degree of freedom in designing the unit building 10 can be improved.
At this time, since the shed beam 20 was bridged between the columns 41 located on both sides of the omitted column 41, that is, the shed beam 20 was provided on the columns 41 located at both ends of the large space. The reduction in the structural strength of the ceiling beam 42 of the second-floor building unit 16 due to the omission can be compensated.
[0032]
(6) Since the support structure 13 is configured to include the bundle 50B standing on the shed beam 20, the length of the bundle is set as compared with the case where the bundle 52 is erected directly on the second-floor building unit 16. Since it is only necessary to shorten the length, the manufacturing cost of the support structure 13 can be reduced.
[0033]
It should be noted that the present invention is not limited to the above-described embodiment, and modifications, improvements, etc. within a scope that can achieve the object of the present invention are included in the present invention .
[0034]
【The invention's effect】
According to the roof structure of the unit type building of the present invention, the following effects can be obtained.
According to the roof structure of the unit type building according to claim 1, since the roof beam is arranged along at least one ceiling beam of the under-floor building unit, the ceiling beam is reinforced by the roof beam, and the large roof Even when a load is applied, the roof can be reliably supported.
In addition, it is economical because only the roof beams that are subjected to a large roof load can be partially reinforced by simply arranging the roof beams along the ceiling beams without any modification to the under-floor building unit itself.
[0035]
In addition, since the shed beam is formed by tying two long materials, the rigidity can be improved as compared with the case where the shed beam is formed by one long material, and thus the structural strength of the shed beam can be improved.
[0036]
Furthermore, since the frame-shaped shed frame is laminated on each ceiling beam of at least one building unit among the roof building units, the roof load received by the support structure can be supported by one whole roof building unit, The structural strength against the roof load of the entire building unit under the roof can be further improved.
Further, by mixing the shed beam and the shed frame, the desired ceiling beam of the building unit under the roof can be reinforced at a low cost and the degree of freedom in the design and structural design of the roof can be improved.
[0037]
In addition, since the frame material constituting the shed frame is formed of a member having the same cross section as the member constituting the shed beam, the parts of the shed beam and the shed frame can be shared, and the manufacturing cost of the support structure can be reduced.
Further, since the cross section coefficients of the shed beam and the shed frame are the same, the structural calculation of the shed beam and the shed frame can be easily performed.
[0038]
In addition, since a large space is formed by omitting one set of corner corner pillars brought together among the pillars of the building unit, the degree of freedom of design inside the unit type building can be improved.
At this time, because the shed beams were bridged between the columns located on both sides of the omitted columns, that is, the shed beams were provided on the columns located at both ends of the large space, so the roof under the column was omitted. It can compensate for the decrease in structural strength of the ceiling beam of the building unit.
[0039]
According to the roof structure of the unit type building according to claim 2 , since the support structure is configured including the bundle standing on the roof beam, the bundle is directly set on the roof building unit. Compared to the case, it is only necessary to shorten the length of the bundle, so that the manufacturing cost of the support structure can be reduced.
[Brief description of the drawings]
FIG. 1 is an overall perspective view showing a unit building according to an embodiment of the present invention.
FIG. 2 is a perspective view of a frame of the building unit according to the embodiment.
FIG. 3 is a plan view of the under-floor building unit according to the embodiment.
FIG. 4 is a plan view of a support structure according to the embodiment.
5 is a cross-sectional view taken along line VV in FIG.
FIG. 6 is a perspective view of a shed beam and a shed frame according to the embodiment.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 10 Unit type building 13 Support structure 14 Roof 16 Second-floor building unit 17 as under-floor building unit Building unit 20 Shed beam 21 Long material 30 Shed frame 40 Building unit frame 41 Column 42 Ceiling beam 43 Floor beam D Corner corner

Claims (2)

四隅の柱の上下端を天井梁および床梁で連結して箱状に形成されたフレームを有する建物ユニットをその角隅部を寄せ合わせて複数配置した屋根下建物ユニットと、これら屋根下建物ユニット上に設けられた支持構造と、この支持構造に支持された屋根とを備えたユニット式建物の小屋組構造であって、
前記屋根下建物ユニットを構成する建物ユニットの柱のうち寄せ合わされた4つの角隅部の柱が省略されて大空間が形成され、
前記支持構造は、小屋梁と、2つの小屋フレームとを備え、
前記小屋梁は、2本の長尺材が抱き合わされて形成され、前記省略された4つの柱の両側に位置する4つの柱の間に架け渡された4つの天井梁上に配置され、
前記各長尺材は、前記天井梁の長手方向に直交する方向に隣接する前記各天井梁上にそれぞれ配置され、
前記小屋フレームは、前記小屋梁を構成する部材と同一断面を有する部材により枠状に形成されるとともに、互いに隣接して配置されるように、かつ、角部が前記長尺材の一端にそれぞれ隣接して配置されるように、前記屋根下建物ユニットの各天井梁に積層されることを特徴とするユニット式建物の小屋組構造。
A roof building unit in which a plurality of building units having frames formed in a box shape by connecting the upper and lower ends of pillars at the four corners with a ceiling beam and a floor beam are arranged by bringing the corners thereof together, and these building units under the roof A unit building shed structure comprising a support structure provided above and a roof supported by the support structure,
Among the pillars of the building units constituting the roof under the building unit, it is submitted together four corners pillars were the omitted large space is formed,
The support structure includes a shed beam and two shed frames,
The shed beam is formed by tying two long members, and is disposed on four ceiling beams spanned between four columns located on both sides of the omitted four columns,
Each of the long members is disposed on each of the ceiling beams adjacent to each other in a direction orthogonal to the longitudinal direction of the ceiling beam,
Each shed frame is formed in a frame shape by a member having the same cross section as a member constituting the shed beam , and is arranged adjacent to each other, and a corner portion is at one end of the long material. A roof structure of a unit type building, which is laminated on each ceiling beam of the under-roof building unit so as to be arranged adjacent to each other.
請求項1に記載のユニット式建物の小屋組構造において、
前記支持構造は、小屋梁の上に立設された束を含んで構成されていることを特徴とするユニット式建物の小屋組構造。
In the unit building shed structure according to claim 1 ,
The unit structure building shed structure is characterized in that the support structure includes a bundle standing on the shed beam.
JP2001185188A 2001-06-19 2001-06-19 Unit building shed structure Expired - Fee Related JP4381631B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001185188A JP4381631B2 (en) 2001-06-19 2001-06-19 Unit building shed structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001185188A JP4381631B2 (en) 2001-06-19 2001-06-19 Unit building shed structure

Publications (2)

Publication Number Publication Date
JP2003003570A JP2003003570A (en) 2003-01-08
JP4381631B2 true JP4381631B2 (en) 2009-12-09

Family

ID=19024814

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001185188A Expired - Fee Related JP4381631B2 (en) 2001-06-19 2001-06-19 Unit building shed structure

Country Status (1)

Country Link
JP (1) JP4381631B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6411811B2 (en) * 2014-08-07 2018-10-24 ミサワホーム株式会社 Roof support structure

Also Published As

Publication number Publication date
JP2003003570A (en) 2003-01-08

Similar Documents

Publication Publication Date Title
JP2010084465A (en) Connecting structure, unit building, and method for constructing the unit building
JP2005240358A (en) Unit building
JP5362333B2 (en) Unit building
JP3831545B2 (en) Unit building
JP4381631B2 (en) Unit building shed structure
JP2002081140A (en) Unit-type building
JP4328455B2 (en) Unit building
JP4163329B2 (en) Building units and unit buildings
JP4989286B2 (en) Unit building
JP4157238B2 (en) Unit building shed structure
JP4700178B2 (en) Unit building
JP4717245B2 (en) Unit buildings and corner reinforcements for unit buildings
JP4749611B2 (en) Unit type building and its construction method
JP4318408B2 (en) Roof structure
JPH11172770A (en) Building unit without column and beam, its building method, and unit building
JP3311323B2 (en) Pillarless building units and unit buildings
JP4585675B2 (en) Support structure for sloped roof
JP4248349B2 (en) Unit building
JP4801856B2 (en) Unit building
JP4676609B2 (en) Unit building
JP3766775B2 (en) Reinforced beams and unit buildings
JP4340402B2 (en) Building roof structure and roof construction method
JP3887233B2 (en) Unit building
JP4516200B2 (en) Unit building
JP4585676B2 (en) Roof support structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070427

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20070704

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20070827

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20080108

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20080131

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090528

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090602

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090724

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090901

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090916

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121002

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4381631

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131002

Year of fee payment: 4

LAPS Cancellation because of no payment of annual fees