JP3952843B2 - Construction method of tower structure - Google Patents

Construction method of tower structure Download PDF

Info

Publication number
JP3952843B2
JP3952843B2 JP2002139853A JP2002139853A JP3952843B2 JP 3952843 B2 JP3952843 B2 JP 3952843B2 JP 2002139853 A JP2002139853 A JP 2002139853A JP 2002139853 A JP2002139853 A JP 2002139853A JP 3952843 B2 JP3952843 B2 JP 3952843B2
Authority
JP
Japan
Prior art keywords
tower
climbing
construction method
push
gantry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002139853A
Other languages
Japanese (ja)
Other versions
JP2003328323A (en
Inventor
淳 高橋
大輔 石松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2002139853A priority Critical patent/JP3952843B2/en
Publication of JP2003328323A publication Critical patent/JP2003328323A/en
Application granted granted Critical
Publication of JP3952843B2 publication Critical patent/JP3952843B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、斜張橋の主塔などの逆Y字型の塔状構造物の施工方法に関するものである。
【0002】
【従来の技術】
斜張橋の逆Y字型の主塔を施工する場合、従来は、図6に示すように、主として所謂クライミングフォーム50とタワークレーン51を使用していた。逆Y字型の主塔1は、主桁を挟んで左右一対の主塔基部2,2と、この主塔基部2,2から互いに接近するように傾斜して立設される2本の柱部3a,3aからなる主塔中央部3と、2本の柱部3a,3aが合体する主塔結合部4と、この主塔結合部4から上方に突出する主塔頂部5等から構成され、次に示す手順で施工されていた。
【0003】
(1) 主塔基部2を地上のクレーンと総足場工法で施工する。
(2) クライミングフォーム50とタワークレーン51を組立て、クライミングフォーム50をクライミング装置により順次上昇させ、柱部3aの各ロットを順次施工していく。タワークレーン51は、クライミング装置(センターホールジャッキや高強度ねじ鉄筋など)を取付けるための先行埋め込み鉄骨や主筋などを搬入するためのものであり、柱部3aの伸長に伴い、下部に単位マストを順次継ぎ足して伸長させる。このマスト部分51aは、既設の柱部3aにステー(壁繋ぎ)52で支持させる。また、既設の柱部3a,3aを水平のストラット53で繋いでいる。
(3) 主塔中央部3の施工が完了すると、クライミングフォーム50を解体し、ブラケット54を中央部3の上部に取付け、総足場工法で主塔結合部4を施工し、続いて総足場工法で主塔頂部5の各ロットを順次施工していく。
【0004】
【発明が解決しようとする課題】
しかし、前述のような従来の施工方法では、タワークレーンを主塔に沿って伸長させていくため、ステーが上方にいくに従って長大なものとなり、主塔構築に伴う設備費が増大するなどの問題点があった。
【0005】
本発明は、このような問題点を解消すべくなされたもので、その目的は、逆Y字型の塔状構造物の施工に際し、塔の中間部でタワークレーンのステーを無くすことができ、塔構築に伴う設備費の低減を図れる塔状構造物の施工方法を提供することにある。
【0006】
【課題を解決するための手段】
本発明の請求項1は、基部から2本の柱部が互いに接近するように傾斜して立設され、この2本の柱部の結合部から頂部が突設されている塔状構造物の施工方法であり、2本の柱部の型枠を備え2本の柱部に掛け渡されるクライミング構台の両端部にタワークレーンをマストを継ぎ足していない最小の状態で設置し、このタワークレーンによる資材の搬入とクライミング構台による型枠の上昇を順次繰り返して2本の柱部を施工し、2本の柱部の合体後は、タワークレーンにマストを継ぎ足しながら、総足場工法あるいは型枠により頂部を施工することを特徴とする塔状構造物の施工方法である。
【0007】
本発明の請求項2は、請求項1に記載の施工方法において、クライミング構台の両端部における下面には既設の塔体に反力をとってクライミング構台を押し上げる押し上げ式クライミング装置が設けられ、このクライミング構台の上に型枠と足場が横移動可能に設けられていることを特徴とする塔状構造物の施工方法である。
【0008】
本発明は、例えば斜張橋の逆Y字型の主塔の施工に有効に適用されるものである。クライミング構台は、上に向かって狭まる2本の柱部の最大幅すなわち基部を取り囲むことのできる大きさで平面視で長方形のトラス桁などから構成され、クライミング装置を介して2本の柱部に取付けられ、クライミング装置により上昇する。
【0009】
クライミング装置は、例えば押し上げビーム等の押し上げ部材と押し上げジャッキ等の押し上げ装置などからなる押し上げ式クライミング装置であり、既設の2本の柱部等の塔体に反力をとってクライミング構台を押し上げる。また、2本の柱部の傾斜に対応できるように、押し上げ部材が横押しジャッキ等の横押し装置を介して塔幅方向に横移動可能にクライミング構台の下面に接続されている。型枠と足場は、例えばクライミング構台の上面を塔幅方向に移動可能な台車などに載置され、横押しジャッキ等の横押し装置により横移動し、2本の柱部の傾斜に対応できるようにされている。
【0010】
基部を総足場工法で施工した後、クライミング構台を基部の上に組み付け、クライミング構台の両端部のマストを継ぎ足していない最小状態のタワークレーンで資材の搬入を行い、コンクリートの打設を行い、1ロットの施工が完了するとクライミング構台を1ロット分上昇させ、以上の工程を順次繰り返すことにより、2本の柱部を施工する。
【0011】
柱部の結合部の手前で2本の柱部の施工が終了すると、総足場工法で結合部を施工し、続いてクライミング構台の両端部のクレーンを単位マストを継ぎ足すことで上方に伸長させつつ総足場工法で頂部を施工する。この総足場工法では、クライミング構台を撤去し、代わりにブラケットをタワークレーンのベースとしてもよい。さらに、総足場工法に限らず、クライミング構台と型枠をそのまま利用して結合部および頂部の施工を行うこともできる。
【0012】
本発明の施工方法によれば、逆Y字型の塔状構造物の施工に際し、塔の中間部の施工ではクライミング構台にタワークレーンを最小状態で載せてクライミングフォーム工法を実施するため、タワークレーンのステーを無くすことができ、塔上部に総足場工法を用いた場合には、塔の頂部の施工においてステーの長さを短くすることができ、主塔構築に伴う設備費の低減を図れる。また、押し上げビーム等の押し上げ部材と押し上げジャッキ等の押し上げ装置などからなる押し上げ式クライミング装置をクライミング構台の下面に設け、上部に型枠と足場を横移動可能に設けているため、スライド作業を容易かつ迅速に行うことができる。
【0013】
【発明の実施の形態】
以下、本発明を図示する一実施形態に基づいて説明する。この実施形態は、斜張橋の逆Y字型の主塔に適用した例である。図1、図2、図3は、本発明の施工方法の主塔中間部の開始状態を示す正面図、平面図、側面図である。図4は、主塔中間部の開始状態から終了状態までを示す正面図である。図5は、主塔結合部から主塔頂部までの施工状態を示す正面図である。
【0014】
図1に示すように、逆Y字型の主塔1は、主桁を挟んで左右一対の主塔基部2,2と、この主塔基部2,2から互いに接近するように傾斜して立設される2本の柱部3a,3aからなる主塔中央部3と、2本の柱部3a,3aが合体する主塔結合部4と、この主塔結合部4から上方に突出する主塔頂部5から構成され、本発明では、概略、クライミング構台10とその両端部のタワークレーン11を使用して2本の柱部3a,3aを施工し(クライミングフォーム施工範囲A:図1,図4参照)、2本の柱部の合体後は、タワークレーン11を伸長させて主塔頂部5を施工する(上部施工範囲:図5参照)。
【0015】
図1〜図3に示すように、クライミング構台10は、左右一対の主塔基部2,2を取り囲むことができる大きさの平面視で長方形のトラス桁12と、押し上げ式クライミング装置13などからなる。押し上げ式クライミング装置13は、例えば押し上げビーム13aと押し上げジャッキ13bなどからなり、既設の主塔基部や柱部の外側面に反力をとってトラス桁12を上昇させる。なお、押し上げビーム13aと押し上げジャッキ13bは横押しジャッキ等で主塔幅方向に横移動可能にトラス桁12の下面に取付けられており、柱部3aの傾斜に対応できるようにされている。
【0016】
トラス桁12の両端部における上面には、型枠20と足場21が設置され、クライミング構台10と共に型枠20が1ロット分順次上昇し、2本の柱部3a,3aが1ロット分順次施工される。これら型枠20と足場21は、例えば台車に載せられ、横押しジャッキ等により主塔幅方向に横移動可能とされ、柱部3aの傾斜に対応できるようにされている。
【0017】
タワークレーン11は、トラス桁12の両端部における型枠20・足場21の外側に設置され、型枠20に先行する鉄筋などの資材の搬入を行う。このタワークレーン11は、マストを継ぎ足していない最小の状態で据え付け、図4に示すように、クライミング構台10と共に上昇し、クレーン作業を行う。また、タワークレーン11は、傾斜する柱部3aに対応させて主塔側に移動させて固定する。
【0018】
図5に示すように、クライミング構台10が主塔結合部4の手前まで上昇すると、トラス桁12上に足場を組み、総足場工法で主塔結合部4を施工する。続いて、タワークレーン11の下部に単位マストを継ぎ足し、マスト11aを上方に伸長させながら足場を組上げ、総足場工法で主塔頂部5を施工する。
【0019】
なお、この主塔結合部4と主塔頂部5の施工では、クライミング構台10を撤去し、代わりにブラケット(図示省略)を柱部の上部外面に設置し、タワークレーン11のベースとすることもできる。
【0020】
また、クライミング構台10と型枠20と足場21をそのまま利用し、主塔結合部4と主塔頂部5を施工することも可能である。
【0021】
なお、以上は斜張橋の逆Y字型の主塔の施工に適用した場合を例示したが、これに限らず、その他の逆Y字型の塔状構造物の施工にも本発明を適用できる。
【0022】
【発明の効果】
(1) 本発明の施工方法によれば、逆Y字型の塔状構造物の施工に際し、塔の中間部の施工ではクライミング構台にタワークレーンを最小状態で載せてクライミングフォーム工法を実施するため、タワークレーンのステーを無くすことができ、塔上部に総足場工法を用いた場合には、塔の頂部の施工においてステーの長さを短くすることができ、主塔構築に伴う設備費の低減を図れる。
(2) 押し上げビーム等の押し上げ部材と押し上げジャッキ等の押し上げ装置などからなる押し上げ式クライミング装置をクライミング構台の下面に設け、上部に型枠と足場を横移動可能に設けることにより、スライド作業を容易かつ迅速に行うことができ、施工時間の短縮と施工コストの低減を図れる。
【図面の簡単な説明】
【図1】本発明の施工方法の主塔中間部の開始状態を示す正面図である。
【図2】図1の平面図である。
【図3】図1の側面図である。
【図4】本発明の施工方法の主塔中間部の開始状態から終了状態までを示す正面図である。
【図5】本発明の施工方法の主塔結合部から主塔頂部までの施工状態を示す正面図である。
【図6】従来の斜張橋の逆Y字型の主塔を施工する方法を示す正面図である。
【符号の説明】
1……逆Y字型の主塔
2……主塔基部
3……主塔中央部
3a…柱部
4……主塔結合部
5……主塔頂部
10……クライミング構台
11……タワークレーン
12……トラス桁
13……押し上げ式クライミング装置
13a…押し上げビーム
13b…押し上げジャッキ
20……型枠
21……足場
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing an inverted Y-shaped tower structure such as a main tower of a cable-stayed bridge.
[0002]
[Prior art]
When constructing an inverted Y-shaped main tower of a cable-stayed bridge, conventionally, a so-called climbing form 50 and a tower crane 51 have been mainly used as shown in FIG. The inverted Y-shaped main tower 1 has a pair of left and right main tower bases 2 and 2 across the main girder, and two pillars that stand upright so as to approach each other from the main tower bases 2 and 2 The main tower central part 3 composed of the parts 3a and 3a, the main tower coupling part 4 where the two column parts 3a and 3a are combined, the main tower top part 5 projecting upward from the main tower coupling part 4 and the like. It was constructed according to the following procedure.
[0003]
(1) The main tower base 2 will be constructed with a ground crane and a total scaffold construction method.
(2) The climbing form 50 and the tower crane 51 are assembled, the climbing form 50 is sequentially raised by the climbing device, and each lot of the pillar portion 3a is sequentially constructed. The tower crane 51 is for carrying in a pre-embedded steel frame or main bar for attaching a climbing device (center hole jack, high-strength screw rebar, etc.). Sequentially add and extend. The mast portion 51a is supported by a stay (wall connection) 52 on the existing column portion 3a. Further, the existing pillar portions 3 a and 3 a are connected by a horizontal strut 53.
(3) When the construction of the central part 3 of the main tower is completed, the climbing form 50 is dismantled, the bracket 54 is attached to the upper part of the central part 3, and the main tower connection part 4 is constructed by the total scaffold method, followed by the total scaffold method. Then, each lot of the main tower top 5 is constructed in sequence.
[0004]
[Problems to be solved by the invention]
However, in the conventional construction method as described above, the tower crane is extended along the main tower, so that the stay becomes longer as the stay moves upward, and the cost of equipment accompanying the construction of the main tower increases. There was a point.
[0005]
The present invention has been made to solve such problems, and the purpose thereof is to eliminate the stay of the tower crane in the middle of the tower when constructing the inverted Y-shaped tower structure, An object of the present invention is to provide a method for constructing a tower-like structure capable of reducing the equipment cost associated with tower construction.
[0006]
[Means for Solving the Problems]
Claim 1 of the present invention is a tower-like structure in which the two column portions are inclined and arranged so as to approach each other from the base portion, and the top portion protrudes from the joint portion of the two column portions. This is a construction method, and a tower crane is installed at the both ends of the climbing gantry that has a formwork of two pillars and is stretched over the two pillars in a minimum state where no mast is added. The construction of the two pillars is carried out sequentially by carrying in and the climbing of the climbing gantry, and after the two pillars are joined, the mast is added to the tower crane and the top part is attached by the total scaffolding method or the formwork. It is the construction method of the tower-like structure characterized by constructing.
[0007]
According to claim 2 of the present invention, in the construction method according to claim 1, a push-up type climbing device is provided on the lower surfaces of both ends of the climbing gantry to push up the climbing gantry by taking a reaction force against the existing tower body. A tower-like structure construction method characterized in that a formwork and a scaffold are provided on a climbing gantry so as to be laterally movable.
[0008]
The present invention is effectively applied to the construction of an inverted Y-shaped main tower of a cable-stayed bridge, for example. The climbing gantry consists of a truss girder that is rectangular in plan view with a maximum width of two pillars that narrows upward, that is, a size that can surround the base, and is connected to the two pillars via a climbing device. Mounted and raised by climbing device.
[0009]
The climbing device is a push-up type climbing device including a push-up member such as a push-up beam and a push-up device such as a push-up jack. The climbing device pushes up the climbing gantry by taking a reaction force on the existing towers such as two pillars. Further, the push-up member is connected to the lower surface of the climbing gantry so as to be laterally movable in the tower width direction via a lateral pushing device such as a lateral pushing jack so as to correspond to the inclination of the two column portions. The formwork and scaffolding are placed on a carriage that can move in the tower width direction, for example, on the upper surface of the climbing gantry, and can be moved laterally by a lateral pushing device such as a lateral pushing jack to cope with the inclination of the two pillars. Has been.
[0010]
After constructing the base with the total scaffold construction method, assemble the climbing gantry on the base, carry in the material with the tower crane in the minimum state where the masts at both ends of the climbing gantry are not added, place the concrete, 1 When the construction of the lot is completed, the climbing gantry is raised by one lot, and the two steps are constructed by sequentially repeating the above steps.
[0011]
When the construction of the two pillars is completed before the joint part of the pillar part, the joint part is constructed by the total scaffold construction method, and then the cranes at both ends of the climbing gantry are extended upward by adding unit masts. While constructing the top with the total scaffold construction method. In this total scaffold construction method, the climbing gantry may be removed, and the bracket may be used as the base of the tower crane instead. Further, not only the total scaffold construction method, but also the construction of the connecting portion and the top portion can be performed using the climbing gantry and the formwork as they are.
[0012]
According to the construction method of the present invention, when the inverted Y-shaped tower structure is constructed, the tower crane is mounted on the climbing gantry in the minimum state in the construction of the intermediate portion of the tower. When the total scaffolding method is used for the upper part of the tower, the length of the stay can be shortened in the construction of the top of the tower, and the equipment cost associated with the construction of the main tower can be reduced. In addition, a push-up type climbing device consisting of a push-up member such as a push-up beam and a push-up device such as a push-up jack is provided on the lower surface of the climbing gantry, and the formwork and scaffolding are provided on the upper part so that it can be moved laterally. And can be done quickly.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described based on an embodiment shown in the drawings. This embodiment is an example applied to an inverted Y-shaped main tower of a cable-stayed bridge. 1, 2, and 3 are a front view, a plan view, and a side view showing a starting state of a middle portion of the main tower of the construction method of the present invention. FIG. 4 is a front view showing from the start state to the end state of the middle part of the main tower. FIG. 5 is a front view showing a construction state from the main tower coupling part to the main tower top part.
[0014]
As shown in FIG. 1, the inverted Y-shaped main tower 1 has a pair of left and right main tower bases 2 and 2 sandwiching the main girder and is inclined so as to approach each other from the main tower base parts 2 and 2. A main tower central portion 3 composed of two pillar portions 3a, 3a provided, a main tower coupling portion 4 where the two pillar portions 3a, 3a are united, and a main projecting upward from the main tower coupling portion 4 Consists of a tower top 5, and in the present invention, two pillars 3a and 3a are constructed using a climbing gantry 10 and tower cranes 11 at both ends thereof (climbing foam construction range A: FIG. 1 and FIG. 1). 4) After joining the two pillars, the tower crane 11 is extended to construct the main tower top 5 (upper construction range: see FIG. 5).
[0015]
As shown in FIGS. 1 to 3, the climbing gantry 10 includes a rectangular truss girder 12 and a push-up type climbing device 13 in a plan view having a size capable of surrounding a pair of left and right main tower bases 2 and 2. . The push-up climbing device 13 includes, for example, a push-up beam 13a and a push-up jack 13b. The push-up climbing device 13 raises the truss girder 12 by taking a reaction force on the outer surface of the existing main tower base or column. The push-up beam 13a and the push-up jack 13b are attached to the lower surface of the truss girder 12 so as to be laterally movable in the main tower width direction by a lateral push jack or the like, so as to cope with the inclination of the column portion 3a.
[0016]
Forms 20 and scaffolds 21 are installed on the upper surfaces of both ends of the truss girder 12, the formwork 20 rises one lot at a time together with the climbing gantry 10, and the two pillar portions 3a and 3a are sequentially constructed for one lot. Is done. These molds 20 and scaffolds 21 are mounted on, for example, a carriage and can be moved laterally in the width direction of the main tower by a lateral push jack or the like so as to cope with the inclination of the column part 3a.
[0017]
The tower crane 11 is installed outside the formwork 20 and the scaffolding 21 at both ends of the truss girder 12 and carries in materials such as reinforcing bars that precede the formwork 20. The tower crane 11 is installed in a minimum state where no mast is added, and as shown in FIG. 4, the tower crane 11 is lifted together with the climbing gantry 10 to perform crane work. Moreover, the tower crane 11 is moved and fixed to the main tower side corresponding to the column part 3a which inclines.
[0018]
As shown in FIG. 5, when the climbing gantry 10 rises to the front of the main tower coupling portion 4, a scaffold is assembled on the truss girder 12, and the main tower coupling portion 4 is constructed by a total scaffold construction method. Subsequently, a unit mast is added to the lower part of the tower crane 11, and a scaffold is assembled while the mast 11a is extended upward, and the main tower top 5 is constructed by a total scaffold construction method.
[0019]
In the construction of the main tower coupling part 4 and the main tower top part 5, the climbing gantry 10 may be removed, and a bracket (not shown) may be installed on the upper outer surface of the column part instead to serve as the base of the tower crane 11. it can.
[0020]
It is also possible to construct the main tower coupling part 4 and the main tower top part 5 by using the climbing gantry 10, the formwork 20, and the scaffold 21 as they are.
[0021]
In addition, although the above has illustrated the case where it applies to the construction of the inverted Y-shaped main tower of the cable-stayed bridge, the present invention is not limited to this, and the present invention is also applied to the construction of other inverted Y-shaped tower structures. it can.
[0022]
【The invention's effect】
(1) According to the construction method of the present invention, when constructing an inverted Y-shaped tower structure, the construction of the intermediate part of the tower is to carry the climbing form method by placing the tower crane on the climbing gantry in the minimum state. The tower crane stay can be eliminated, and if the total scaffold construction method is used at the top of the tower, the length of the stay can be shortened in the construction of the top of the tower, reducing the equipment costs associated with the construction of the main tower Can be planned.
(2) A push-up type climbing device consisting of a push-up member such as a push-up beam and a push-up device such as a push-up jack is provided on the lower surface of the climbing gantry, and the formwork and scaffolding are provided on the upper part so as to be able to move laterally. Moreover, it can be performed quickly, and the construction time can be shortened and the construction cost can be reduced.
[Brief description of the drawings]
FIG. 1 is a front view showing a starting state of a middle part of a main tower in a construction method of the present invention.
2 is a plan view of FIG. 1. FIG.
FIG. 3 is a side view of FIG. 1;
FIG. 4 is a front view showing from the start state to the end state of the middle part of the main tower of the construction method of the present invention.
FIG. 5 is a front view showing a construction state from the main tower coupling part to the main tower top part of the construction method of the present invention.
FIG. 6 is a front view showing a method of constructing an inverted Y-shaped main tower of a conventional cable-stayed bridge.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Reverse Y-shaped main tower 2 ... Main tower base part 3 ... Main tower center part 3a ... Column part 4 ... Main tower connection part 5 ... Main tower top part 10 ... Climbing gantry 11 ... Tower crane 12 ... Truss girder 13 ... Push-up type climbing device 13a ... Push-up beam 13b ... Push-up jack 20 ... Formwork 21 ... Scaffolding

Claims (2)

基部から2本の柱部が互いに接近するように傾斜して立設され、この2本の柱部の結合部から頂部が突設されている塔状構造物の施工方法であり、2本の柱部の型枠を備え2本の柱部に掛け渡されるクライミング構台の両端部にタワークレーンをマストを継ぎ足していない状態で設置し、このタワークレーンによる資材の搬入とクライミング構台による型枠の上昇を順次繰り返して2本の柱部を施工し、2本の柱部の合体後は、タワークレーンにマストを継ぎ足しながら総足場工法で頂部を施工し、あるいは前記クライミング構台と型枠を利用して頂部を施工することを特徴とする塔状構造物の施工方法。It is a construction method of a tower-like structure in which two pillars are inclined and arranged so as to approach each other from the base, and the top part protrudes from the joint part of the two pillars. Install tower cranes at both ends of the climbing gantry spanned by the two pillars with the column formwork, with no mast added, and carry the material with the tower crane and raise the formwork with the climbing gantry The two pillar parts are constructed by repeating the above, and after the two pillar parts are combined, the top part is constructed by the total scaffold construction method while adding the mast to the tower crane, or by using the climbing gantry and the formwork. A construction method of a tower-like structure characterized by constructing the top. 請求項1に記載の施工方法において、クライミング構台の両端部における下面には既設の塔体に反力をとってクライミング構台を押し上げる押し上げ式クライミング装置が設けられ、このクライミング構台の上に型枠と足場が横移動可能に設けられていることを特徴とする塔状構造物の施工方法。In the construction method according to claim 1, a push-up type climbing device is provided on the lower surface of both ends of the climbing gantry to take up a reaction force on the existing tower body and push up the climbing gantry. A construction method of a tower-like structure, wherein the scaffold is provided so as to be laterally movable.
JP2002139853A 2002-05-15 2002-05-15 Construction method of tower structure Expired - Fee Related JP3952843B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002139853A JP3952843B2 (en) 2002-05-15 2002-05-15 Construction method of tower structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002139853A JP3952843B2 (en) 2002-05-15 2002-05-15 Construction method of tower structure

Publications (2)

Publication Number Publication Date
JP2003328323A JP2003328323A (en) 2003-11-19
JP3952843B2 true JP3952843B2 (en) 2007-08-01

Family

ID=29700874

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002139853A Expired - Fee Related JP3952843B2 (en) 2002-05-15 2002-05-15 Construction method of tower structure

Country Status (1)

Country Link
JP (1) JP3952843B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032678A (en) * 2014-05-06 2014-09-10 中铁港航局集团有限公司 H-shaped tower column inner force adjustable temporary cross supporting structure and construction method thereof
CN104499432A (en) * 2014-10-14 2015-04-08 中铁四局集团钢结构有限公司 Construction method of in-air connection universal mobile platform of curved surface leaning tower
CN110184927A (en) * 2019-05-14 2019-08-30 宁波市政工程建设集团股份有限公司 A kind of Y type pier stud construction method using Bailey bracket
CN110387824A (en) * 2019-07-12 2019-10-29 中交第二航务工程局有限公司 A kind of Sarasota creeping formwork becomes rail construction method in the air
CN111188268A (en) * 2019-12-31 2020-05-22 湖北省路桥集团有限公司 Super-large cast-in-situ gravity type anchorage and construction method

Families Citing this family (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010048060A (en) * 2008-08-25 2010-03-04 Shimizu Corp Construction method of structure
KR101118526B1 (en) 2011-09-08 2012-03-12 주식회사 한진중공업 Construction method of steel tower of bridge and dismantling method of lifting frame
CN102900022B (en) * 2012-10-22 2015-09-30 中铁十局集团有限公司 Cable stayed bridge leaning tower hydraulic climbing mould construction method
CN103243654B (en) * 2013-05-16 2015-01-21 中交路桥华南工程有限公司 Mounting method for steel anchor beam of cable-stayed bridge and assembly jig and cable bent tower mounting platform used in method
CN103410082B (en) * 2013-07-18 2015-06-17 广州市市政工程设计研究院 Double-layer bridge floor cable-stayed bridge
CN103835238B (en) * 2014-02-21 2015-11-18 中铁大桥局集团有限公司 A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
CN104109999B (en) * 2014-06-26 2016-08-24 中铁大桥局集团有限公司 The construction method of bridge tower thwart beam
CN104532743B (en) * 2014-12-29 2016-09-28 中交公路规划设计院有限公司 Tower beam consolidation mechanism and corresponding cable-stayed bridge and method of construction thereof
CN104532753B (en) * 2014-12-31 2017-01-11 中交二公局第二工程有限公司 Lifting device suitable for lifting and installing suspension bridge stiffening girders
CN104775362B (en) * 2015-04-16 2016-07-13 西南交通大学 Bluff body cross section bridge tower wind-induced vibration suppresses structure
CN105297613B (en) * 2015-10-27 2017-01-25 中交第二公路勘察设计研究院有限公司 Compact stay cable steel anchor beam and construction method thereof
CN105507147A (en) * 2016-02-29 2016-04-20 中铁大桥勘测设计院集团有限公司 Bridge main tower with built-in stairway
CN105755959B (en) * 2016-03-11 2017-07-28 广东省长大公路工程有限公司 Suitable for the Sarasota construction auxiliary stand system and building method of different cross section
CN105926457A (en) * 2016-05-30 2016-09-07 中国铁建大桥工程局集团有限公司 Method for mounting steel box girders in main tower area of cable-stayed bridge and auxiliary girder erection crane base
CN106522094B (en) * 2016-11-22 2018-10-16 中交第二航务工程局有限公司 A kind of Sarasota crosses segment structure and construction method
CN106758833B (en) * 2016-12-16 2018-07-13 四川公路桥梁建设集团有限公司 A kind of hydraulic climbing die block system for the construction of small-sized variable cross-section pier
CN109290739B (en) * 2018-08-15 2021-02-02 中铁宝桥集团有限公司 Manufacturing process of space curve steel tower segment
CN110184941B (en) * 2019-06-24 2020-11-06 安徽省公路桥梁工程有限公司 Bridge main tower construction method
CN110886227B (en) * 2019-12-03 2021-09-14 湖北省路桥集团有限公司 Main tower cast-in-place lower cross beam support system and construction method
CN111945573A (en) * 2020-08-18 2020-11-17 中铁八局集团第二工程有限公司 Double-limb thin-wall high-pier tie beam support-free construction method
CN112342928A (en) * 2020-11-20 2021-02-09 中铁九桥工程有限公司 Method for installing cable-stayed bridge of ultrahigh main tower in mountainous area
CN112853981A (en) * 2021-01-07 2021-05-28 中铁大桥局集团有限公司 Hoisting system and hoisting method for steel tower segment
CN113718625B (en) * 2021-09-29 2022-11-29 中国水利水电第三工程局有限公司 Construction method for cable-free beam section of tower area of composite beam cable-stayed bridge
CN113802468A (en) * 2021-11-01 2021-12-17 中天交通建设投资集团有限公司 Asymmetric cable-stayed bridge special-shaped concrete tower column construction process
CN114250712A (en) * 2021-12-31 2022-03-29 中建桥梁有限公司 Method for erecting cable-stayed bridge steel truss beam by asymmetric bracket
CN114790690A (en) * 2022-04-13 2022-07-26 中铁二十三局集团第三工程有限公司 Synchronous construction method for tie beam and pier body in hydraulic creeping formwork high pier
CN114837071A (en) * 2022-05-16 2022-08-02 中国十九冶集团有限公司 Construction method for pouring concrete high pier
CN115584687B (en) * 2022-10-17 2023-08-29 安徽省交通建设股份有限公司 Assembled truss template for crescent-shaped tower column and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104032678A (en) * 2014-05-06 2014-09-10 中铁港航局集团有限公司 H-shaped tower column inner force adjustable temporary cross supporting structure and construction method thereof
CN104032678B (en) * 2014-05-06 2016-08-24 中铁港航局集团有限公司 H type king-post internal force adjustable false stull structure and construction method thereof
CN104499432A (en) * 2014-10-14 2015-04-08 中铁四局集团钢结构有限公司 Construction method of in-air connection universal mobile platform of curved surface leaning tower
CN110184927A (en) * 2019-05-14 2019-08-30 宁波市政工程建设集团股份有限公司 A kind of Y type pier stud construction method using Bailey bracket
CN110387824A (en) * 2019-07-12 2019-10-29 中交第二航务工程局有限公司 A kind of Sarasota creeping formwork becomes rail construction method in the air
CN111188268A (en) * 2019-12-31 2020-05-22 湖北省路桥集团有限公司 Super-large cast-in-situ gravity type anchorage and construction method

Also Published As

Publication number Publication date
JP2003328323A (en) 2003-11-19

Similar Documents

Publication Publication Date Title
JP3952843B2 (en) Construction method of tower structure
JP4542048B2 (en) How to build an arch bridge
JP2008038463A (en) Bridge girder erection method
CN107989447A (en) A kind of large-scale earthing concrete tank dome steel support structure and installation method
CN107227814B (en) A kind of large cantilever concrete structure section construction method
JP3026161B2 (en) Self-elevating formwork apparatus and method of lifting the apparatus
JP3804883B2 (en) Concrete high structure construction apparatus and concrete oblique column construction method
CN210140771U (en) Construction work platform hoisting frame of high mound of bridge
JPH0959932A (en) Construction method of column head of overhanging erection girder bridge
CN109826232A (en) The construction method of subway station
JP3038154B2 (en) Overhang work equipment
JP3425352B2 (en) Self-elevating formwork device
CN107558607B (en) Tower crane system arranged on existing concrete structure and construction method thereof
CN105735137B (en) A kind of bridge pier column reinforcement installation crosshead
JP2004250144A (en) Supporting method of climbing tower crane
CN218951983U (en) Bridge pier shaft reinforcing bar installation bench device
KR200256837Y1 (en) Pier sheeting support structure using an assembly band and support
JP3326724B2 (en) Construction method of concrete cable-stayed bridge and form support trolley used for it
JPH0681314A (en) Construction method for concrete main tower
CN115162697B (en) Special-shaped column construction work I-shaped steel cantilever platform and construction method
JP3368483B2 (en) Bridge pier construction method
CN210552078U (en) Temporary construction platform for side form of ultrahigh-strength concrete precast beam
CN216974185U (en) Template bent frame composite structure
CN214362935U (en) High mound rollover construction reinforcement ligature protection frame
CN109056532B (en) I-beam construction platform

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050107

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070402

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070410

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070423

R150 Certificate of patent or registration of utility model

Ref document number: 3952843

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100511

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130511

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160511

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees