CN105735137B - A kind of bridge pier column reinforcement installation crosshead - Google Patents

A kind of bridge pier column reinforcement installation crosshead Download PDF

Info

Publication number
CN105735137B
CN105735137B CN201610182786.2A CN201610182786A CN105735137B CN 105735137 B CN105735137 B CN 105735137B CN 201610182786 A CN201610182786 A CN 201610182786A CN 105735137 B CN105735137 B CN 105735137B
Authority
CN
China
Prior art keywords
steel pipe
bridge pier
frame
pier column
reinforcement installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610182786.2A
Other languages
Chinese (zh)
Other versions
CN105735137A (en
Inventor
钟长海
段建军
罗万里
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
Original Assignee
Sinohydro Bureau 5 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN201610182786.2A priority Critical patent/CN105735137B/en
Publication of CN105735137A publication Critical patent/CN105735137A/en
Application granted granted Critical
Publication of CN105735137B publication Critical patent/CN105735137B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of bridge pier column reinforcement installation crosshead, including two steel pipe frames, the steel pipe frame cross section is U-shaped, and the free end face of two steel pipe frames is corresponding to be surrounded on bridge pier column periphery, and two corresponding free end faces are fixedly connected by assembly buckle.The assembly buckle includes fastener body, and fastener body left and right ends respectively set a combination neck;Two connection cross bars being provided with the steel pipe frame free end face on connection cross bar, corresponding free end face are fastened in the combination neck of same fastener body left and right ends respectively.The crosshead portable construction of the present invention, makes simple, is not limited by construction site, easy to operate in work progress, safe and reliable, and mobile flexible, repeats and utilizes, accelerates bridge construction progress, reduce engineering cost.

Description

A kind of bridge pier column reinforcement installation crosshead
Technical field
The present invention relates to bridge pier column reinforcement installation facility technology field, specially a kind of bridge pier column reinforcement installation operation Frame.
Background technology
At present, using method constructing and overhanging model is turned over more than bridge pier column reinforcement installation, in work progress, scaffold is essential Equipment, generally uses common fastener type steel pipe scaffold or disk buckle type scaffold, such scaffold is in build process now In hound, bridging and necessary ruggedized construction need to be set in time, it is to avoid scaffold glanced off during setting up and Tilt, while needing to fix using sleeve couple at fastener for connection, construction requirement is high, complex procedures, the work installed and removed Journey amount is also very big, and the variable cross-section rectangular pier columns especially for reinforcing bar peace amount than larger superelevation, and bridge site are in mountain Pier stud among paddy river course, adds and is limited by landform place, scaffolding height, efficiency of construction is very low.
The content of the invention
In view of the above-mentioned problems, it is an object of the invention to provide a kind of portable construction, making is simple, movement is flexible, peace is torn open Convenient bridge pier column reinforcement installation crosshead, technical scheme is as follows:
A kind of bridge pier column reinforcement installation crosshead, including two steel pipe frames, the steel pipe frame cross section is U-shaped, two The free end face of steel pipe frame is corresponding to be surrounded on bridge pier column periphery, and two corresponding free end faces are solid by assembly buckle Fixed connection.
Further, the assembly buckle includes fastener body, and fastener body left and right ends respectively set a combination neck;Institute State and connection cross bar is provided with steel pipe frame free end face, two connection cross bars on corresponding free end face are fastened in same respectively In the combination neck of fastener body left and right ends.
Further, the steel pipe frame includes a long frame side and two sides for being vertically fixed on long frame side two ends Frame.
Further, the long frame side includes outrigger and internal frame, and outrigger is multiple column steel pipes and multiple cross bar steel pipes Intersect and be fixedly connected with the gratings of composition, internal frame is identical with outrigger structure, and it is solid by support rail between internal frame and outrigger Fixed connection;The side rack is identical with long frame side structure.
Further, the intersection of the column steel pipe and cross bar steel pipe is provided with the welding groove being mutually twisted.
Further, the steel pipe frame bottom is fixedly connected with angle cleat.
Further, suspension ring are also fixedly connected with the steel pipe frame.
The beneficial effects of the invention are as follows:The crosshead portable construction of the present invention, makes simple, is not limited by construction site, It is easy to operate in work progress, safe and reliable and mobile flexible, repeat and utilize, effectively reduce rectangular pier columns special Be high pier merogenesis reinforcement installation in very complicated operational procedure, accelerate bridge construction progress, reduce engineering cost.
Brief description of the drawings
Fig. 1 is the top view of reinforcement installation crosshead of the present invention.
Fig. 2 is the diagrammatic cross-section of assembly buckle at A-A in this Fig. 1.
Fig. 3 is the structural representation of steel pipe frame in reinforcement installation crosshead of the present invention.
In figure:1- bridge pier columns;2- steel pipe frames;21- connection cross bars;The long frame side of 22-;23- side racks;24- cross bar steel pipes; 25 column steel pipes;26- angle cleats;27- support rails;4- assembly buckles;41- reinforcing bar diagonal braces;42- fastener bodies;43- is combined Neck;5- suspension ring.
Embodiment
The present invention is described in further details with specific embodiment below in conjunction with the accompanying drawings.As shown in figure 1, a kind of bridge pier Post reinforcement installation crosshead, including two independent steel pipe frames 2, the cross section of steel pipe frame 2 are U-shaped, during combination, two steel pipes The free end face of the U-shaped of frame 2 is corresponding to be surrounded on the periphery of bridge pier column 1, and two corresponding free end faces are detained by combining Part 4 is fixedly connected.Steel pipe frame is welded using 57 × 3mm of φ steel pipe combinations.
The combination of two steel pipe frame preferences is as shown in Fig. 2 assembly buckle 4 includes fastener body 42, fastener body 42 left and right ends respectively set a combination neck 43;Connection cross bar 21, corresponding freedom are provided with the free end face of steel pipe frame 2 Two connection cross bars 21 on end face are fastened in the combination neck 43 of the same left and right ends of fastener body 42 respectively.Assembly buckle 4 are formed using Φ 28 reinforcement welding, and fastener body 42 is welded with the rectangular frame of reinforcing bar diagonal brace 41, wherein fastener sheet for centre Using patch angle full weld between body 42 and the combination neck 43 of projection.Can be with according to the height of steel pipe frame, on corresponding free end face Multigroup connection cross bar 21 and assembly buckle 4 are set, to ensure the firm of connection.The combination, is not only simple in structure, and connection is steady Gu, installing/dismounting is also more convenient.
The structure and size of steel pipe frame 2 can be set according to the shape and size of the cross section of bridge pier column 1 in construction.If beam The cross section of pier stud 1 is circle, then steel pipe frame 2 need to be set to the semicircle arcuation of corresponding size, if the cross section of beam pier stud 1 is rectangle, Then steel pipe frame 2, which should be set to structure, includes one long frame side 22 and two side racks 23 for being vertically fixed on the long two ends of frame side 22.
Exemplified by reinforcement installation crosshead for cross section for the bridge pier column of rectangle, the concrete structure of above-mentioned steel pipe frame As shown in figure 3, long frame side 22 includes outrigger and internal frame, outrigger is that multiple column steel pipes 25 and multiple cross bar steel pipes 24 intersect The gratings of composition is fixedly connected with, internal frame is identical with outrigger structure, and is fixedly connected between internal frame and outrigger by support rail 27; The side rack 23 is identical with the long structure of frame side 22.
Wherein, the intersection of column steel pipe 25 and cross bar steel pipe 24 is provided with the welding groove being mutually twisted.In steel during welding Pipe junction eliminates 1/3 as welding groove, is allowed to be close to firm welding.
For convenience of lift, can on steel pipe frame 2 welding hanging ring 5, suspension ring use the reinforcing bars of Q235 φ 16, per single steel pipe frame use 4 suspension ring, are allowed to lifting and are steadily easily installed in place, suspension ring weld answers two-sided firm welding.
The bottom of steel pipe frame 2 is fixedly connected with angle cleat 26, can be using the welding of the angle steel of L100 × 10.It is welded on internal frame φ 20 bolt hole is opened up on angle cleat, so that steel pipe frame is bolted to connection with template.
Welding anti-slip steel thickness of slab 2.5mm is set up on every layer operation platform of crosshead, berm width is not less than 60cm, inner side Steel cat ladder is hung to be easy to pass through above and below workmen.
In use, can in advance on construction ground outside steel pipe frame is welded, can not so be limited by construction site, operate It is more convenient and simple.During construction, it is fixedly connected after two steel pipe frames are lifted in place with tower crane or automobile first with assembly buckle, It need to only be placed on one side on reserved section template operation platform, another side and reserved section template bolt connection.After steel pipe frame is installed Close mesh protection network is completely hung in surrounding, protection network should be close to surrounding.Dismantling operation frame after the completion of the construction of this section reinforcement installation is treated, then is pacified Fill combined steel formwork casting concrete.The steel pipe frame disassembled can also repeat recycle, greatly reduce operational procedure and Construction cost.

Claims (6)

1. a kind of bridge pier column reinforcement installation crosshead, it is characterised in that including two steel pipe frames(2), the steel pipe frame(2)It is horizontal Section is U-shaped, two steel pipe frames(2)Free end face it is corresponding to be surrounded on bridge pier column(1)Periphery, corresponding two are certainly Assembly buckle is passed through by end face(4)It is fixedly connected;
The assembly buckle(4)Including fastener body(42), fastener body(42)Left and right ends respectively set a combination neck(43); The steel pipe frame(2)Connection cross bar is provided with free end face(21), two connection cross bars on corresponding free end face(21) Same fastener body is fastened in respectively(42)The combination neck of left and right ends(43)In.
2. bridge pier column reinforcement installation crosshead according to claim 1, it is characterised in that the steel pipe frame(2)Including One long frame side(22)Long frame side is vertically fixed on two(22)The side rack at two ends(23).
3. bridge pier column reinforcement installation crosshead according to claim 2, it is characterised in that the long frame side(22)Including Outrigger and internal frame, outrigger are multiple column steel pipes(25)With multiple cross bar steel pipes(24)Intersect and be fixedly connected with the grid of composition Frame, internal frame is identical with outrigger structure, and passes through support rail between internal frame and outrigger(27)It is fixedly connected;The side rack(23) With long frame side(22)Structure is identical.
4. bridge pier column reinforcement installation crosshead according to claim 3, it is characterised in that the column steel pipe(25)With Cross bar steel pipe(24)Intersection be provided with the welding groove that is mutually twisted.
5. bridge pier column reinforcement installation crosshead according to claim 1, it is characterised in that the steel pipe frame(2)It is upper to go back It is fixedly connected with suspension ring(5).
6. bridge pier column reinforcement installation crosshead according to claim 1, it is characterised in that the steel pipe frame(2)Bottom It is fixedly connected with angle cleat(26).
CN201610182786.2A 2016-03-28 2016-03-28 A kind of bridge pier column reinforcement installation crosshead Active CN105735137B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610182786.2A CN105735137B (en) 2016-03-28 2016-03-28 A kind of bridge pier column reinforcement installation crosshead

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610182786.2A CN105735137B (en) 2016-03-28 2016-03-28 A kind of bridge pier column reinforcement installation crosshead

Publications (2)

Publication Number Publication Date
CN105735137A CN105735137A (en) 2016-07-06
CN105735137B true CN105735137B (en) 2017-08-29

Family

ID=56252118

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610182786.2A Active CN105735137B (en) 2016-03-28 2016-03-28 A kind of bridge pier column reinforcement installation crosshead

Country Status (1)

Country Link
CN (1) CN105735137B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178037A (en) * 2017-05-31 2017-09-19 中交二公局第工程有限公司 The outer frame connecting structure of trestle vase-shaped column-type pier pier shaft and its construction technology

Also Published As

Publication number Publication date
CN105735137A (en) 2016-07-06

Similar Documents

Publication Publication Date Title
JP3177157U (en) A simple tower instrument in a high-rise bridge.
CN105113388B (en) Formwork and bracket combining structure of vase pier of viaduct and application method
CN105350454B (en) Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge
CN102493360A (en) Reinforced concrete arch bridge construction method
CN107419824A (en) The full precast shear wall structural system of regenerative steel skeleton and construction method
CN107989447A (en) A kind of large-scale earthing concrete tank dome steel support structure and installation method
US20130298496A1 (en) Method for assembling shell segments for forming tower sections of a hybrid wind turbine tower
CN102535845A (en) Construction method of bearing frame of corridor structure
AU2013212529A1 (en) Automated formwork climbing system
CN106351445A (en) Bracing reinforcement system and installation construction method of steel reinforced concrete inclined shear wall form assembly
CN102277835A (en) Method for constructing single-column bent cap by adopting hoop and A-frame composite system
CN114059758A (en) Assembled double-layer integral elevator shaft platform
CN109469083B (en) Foundation beam reinforcement cage assembling system and construction method thereof
CN106320183A (en) Assembly type bent cap formwork system
CN106758839A (en) A kind of strutting system and its installation method of the cast-in-place segmental construction of pier top
CN105735137B (en) A kind of bridge pier column reinforcement installation crosshead
CN113833263A (en) Integral lantern type support circulating hoisting construction method for frame column
CN211006341U (en) Assembled strength nature skeleton suitable for mound tower reinforcing bar location
CN106592436A (en) Manufacturing method of tool mold plate for city bridges
CN102619335A (en) Construction method of large-height small-sized cast-in-place concrete beam slab
CN203129581U (en) Slip form system
CN106168036B (en) A kind of contrary sequence method drop modular system and drop mould method
CN206052780U (en) Modular system drops in a kind of contrary sequence method
CN105544402B (en) A kind of hanging gang form support frame and construction method for pier capping beam high
CN204225503U (en) Large span steel truss high altitude bulk conversion beam moulding bed

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant